Milas Oren Sewerage System and Wastewater Treatment PDF 1645788945
Milas Oren Sewerage System and Wastewater Treatment PDF 1645788945
TP                  Total Phosphorus
TSS                 Total Suspended Solids
TurkStat            Turkish Statistical Institute
UN                  United Nations
UNESCO              United Nations Educational, Scientific and Cultural Organization
UNFCCC              United Nations Framework Convention on Climate Change
WB                  World Bank
WBG                 World Bank Group
WWTP                Wastewater Treatment Plant
        This report has been prepared by Encon Çevre Danışmanlık Ltd. Şti. (ENCON) in the
scope of the Environmental and Social Impact Assessment (ESIA) study conducted for the Milas-
Oren Sewerage System and Wastewater Treatment Plant (WWTP) Project (the Project). The
Project has two components; one is the construction of a 74.5 km sewerage network in Oren
neighbourhood of Milas District with four buried pumping stations, and the other one is the
construction of Oren WWTP on one parcel located in the borders of Oren neighbourhood and
1,542 meter discharge line.
        The diameters of pipes to be used in Oren’s sewerage system vary between Ø200 mm and
Ø3000 mm. The pipes will be HDPE corrugated and Glass Reinforced Plastic (GRP). System’s
design is made according to 2054 population and flowrate. The 74.5 km sewerage network
construction consists of installation of 53 km sewerage network, 9.5 km household connection and
12 km force main. Within the sewerage network, four underground pumping stations will be
constructed. While two of the pumping pumping stations will be constructed as package pumping
stations, the others will be constructed as reinforced concrete pumping stations.
         The other component of the Project is Oren WWTP, which has a daily design capacity of
4,000 m3/day for the 1st Stage (until 2028), and total of 8,000 m3/day (4,000 m3/day + 4,000
m3/day) for the 2nd Stage (after 2028). The WWTP will be able to treat organic pollutants together
with nitrogen and phosphorus. After the treatment, treated effluent will meet the national legislative
quality criteria and necessary WBG EHS Guideline criteria and will be discharged to Hanay Creek
through 1,542 meter discharge line to be constructed. Milas – Oren WWTP consists of the following
units:
           Coarse Screen
           Pump Station
           Fine Screen
           Aerated Grit Chamber
           Rectangular Weir and Distribution Chamber
           Anaerobic BioP Tanks
           Aeration Tanks
           Final Sedimentation Distribution Chamber
           Final Sedimentation Tanks
           Treated Water Pit
           Disinfection Tank
           Sludge Pumping Station
         A map showing the location of the Project and the Project components is presented below
in
         Figure 0.1.
        The project will be in compliance with the good international practice, including World Bank
Policies, guides, standards and best practices documents alongside the national legislation.
Specific standards related to the project are as follows:
        According to the EU Environmental Impact Assessment (EIA) Directive the Oren WWTP is
subject to Annex II, as the capacity of the WWTP is below 150.000 PE. Similarly, sewerage
network is also subject to Annex II considering it within the scope of “Urban Development Projects”.
For the projects that are subject to Annex II, the member states determine the need of an
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                               Executive Summary - Pg. 2/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
Environmental Impact Assessment through a case-by-case basis examination or thresholds/criteria
set by the Member State. According to the Turkish EIA Regulation, the Project is not subject to the
mentioned legislation as the capacity of the WWTP is below both 150.000 PE for Annex I and
50.000 PE for Annex II requirement therein. Within this regard, EIA exempt decision is given for the
WWTP. However, considering the location and environmental and social aspects of the Project, the
Project has been proposed as a “Category A” Project by considering the OP 4.01 requirements.
For “Category A” projects, a comprehensive full-scale ESIA is required to be conducted.
       The Project is located at Oren neighbourhood of Milas district of Mugla. The Project design
was made according to the projected populations for 2054. In 2054, the population to be served
and wastewater generation rate will be 23,863 and 123 l/s, respectively.
          In the scope of the baseline studies for the Project and to determine the existing
contamination status of soils located in the site, two samples were taken from the site. Although
both samples were taken from the WWTP site, the concentrations of some parameters significantly
differ from each other, such as chromium, nickel and TPH. Chromium levels in uncontaminated soil
vary in between 2 and 60 mg/kg and soils with chromium levels up to 100 mg/kg are considered as
appropriate for agricultural activities (Seven v.d., 2018). Therefore, the chromium concentration
observed in the sampling location-1 which is 205.2 mg/kg, and its comparison with the
concentration observed in the second sampling location which is 57.17 mg/kg, indicate a possible
contamination in the location-1. Nickel levels in soils vary widely depending on local geology and
anthropogenic inputs, but concentrations typically range between 4 and 80 ppm (Seven v.d., 2018),
however in the sampling location-1 nickel concentration is measured as 223.1 mg/kg. On the other
hand in USA, the most commonly used soil cleanup standard for TPH is 100 mg/kg (Michelsen,
1993), in the current situation TPH levels in sampling location-2 is measured as 117.5 mg/kg.
Therefore, the assessment made by evaluating chromium levels is also valid when considering
TPH and nickel levels in the WWTP site.
        Although it is not decided yet, it is expected that around 100 workers at the peak period of
construction phase and 10 workers in the operation phase of the Project will be employed.
Regardless of the exact number of people to be employed, priority will be given to the local
community during recruitment process. The sewerage network and WWTP is planned to be
completed in 24 months and 18 months, respectively, following tendering processes.
          Within the scope of the Project, the excess sludge which will be generated during the
operation of WWTP, will be analysed to determine compliance with the Annex-2 of the Regulation
on Landfilling of Wastes and if it is deemed appropriate, the sludge will be collected by the licensed
disposal companies determined by MUSKI every year. After that, the sludge will be disposed at
landfill in accordance with the provisions of Urban Wastewater Treatment Regulation and other
relevant legislation. According to the information retrieved from MUSKI, the sludge will be
transported by competent and licensed firms to the landfill which has enough capacity. At the end,
the sludge will be stored in the landfill. On the other hand, incineration and other options will be
considered under the sludge management plan to be prepared prior to operational phase. Within
this regard, according to information obtained from MUSKI, EIA Positive decision for incineration
plant is obtained. However, whether the plant will be constructed or not is depends on the supply of
funding for this issue. Currently, waste to energy system is not considered because the plant
capacity is low, so the amount of sludge to be generated will be limited.
           Project would have environmental and social impacts during construction and
            operation phases. Potential impacts of the Project during the construction phase would
            be generally short term with low to medium magnitude that would be locally significant.
            These impacts can be initially summarized as follows:
                o Permanent change of land type at the WWTP site.
                o Air emissions and increased level of noise generated from the operation of the
                    construction machinery and equipment.
Construction Phase;
Operation Phase;
        MUSKI should manage an effective information disclosure system in line with the World
Bank Information Disclosure Policy, and should request from its possible contractors to do so. Also,
in order to collect the opinions of the community, MUSKI should operate an effective grievance
mechanism and stakeholder engagement.
        Overall, with the realization of the Project, the wastewaters will be treated, discharge of
untreated wastewaters into environment will be prevented and the Project will have positive impact
on both the environment and public health.
         The first public participation meeting (PPM-1) was held on July 7, 2020, at Oren with the
participation of 84 people. The discussions and Q&A sessions were fruitful and the community was
made aware of the Project and its possible environmental and social impacts. In general, the
community supports the Project since they have been awaiting this Project to start for many years.
Following the completion of the Draft ESIA Report, PPM-II was held at February 11th, 2022 with the
participation of 63 people. In this context, the findings of the ESIA studies were shared with the
public and stakeholders. Their opinions, concerns and suggestions were obtained and considered
and addressed in this Final ESIA as relevant.
        İller Bankası A.Ş. (ILBANK) and World Bank (WB) have developed the Sustainable Cities
Project (SCP) to establish a support mechanism for participating second level metropolitan
municipalities to plan and invest in a sustainable future. The investments to be made within the
scope of SCP will follow environmental legislation of Republic of Turkey as well as World Bank
safeguard policies and standards. Under SCP financed by WB, two sub-loan agreements were
signed between General Directorate of Water and Wastewater Utility of Mugla Metropolitan
Municipality (MUSKI) and ILBANK in the wastewater sector. The project with MUS2-W2 code,
which is subject to this study, is in the scope of SCP-II.
         This report has been prepared by Encon Çevre Danışmanlık Ltd. Şti. (ENCON) in the
scope of the Environmental and Social Impact Assessment (ESIA) study conducted for the Milas-
Oren Sewerage System and Wastewater Treatment Plant (WWTP) Project (the Project). Under the
scope of the Project, one component is the construction of sewerage networks in Oren
neighbourhood of Milas District. The other component is the construction of Oren WWTP on one
parcel located in the borders of Oren neighbourhood with additional discharge line.
        The diameters of pipes to be used in Oren’s sewerage system vary between Ø200 mm and
Ø3000 mm. The pipes will be HDPE corrugated and GRP. System’s design is made according to
2054 population and flowrate. The 74.5 km sewerage network construction consists of installation
of 53 km sewerage network, 9.5 km household connection and 12 km force main. The other
component of the Project is Oren WWTP, which has a daily design capacity of 4,000 m3/day for the
1st Stage (until 2028), and total of 8,000 m3/day (4,000 m3/day + 4,000 m3/day) for the 2nd Stage
(after 2028). The WWTP will be able to treat organic pollutants together with nitrogen and
phosphorus. After the treatment, treated effluent will meet the national legislative quality criteria
and necessary WBG EHS Guideline criteria and will be discharged to Hanay Creek through 1,542
meter discharge line to be constructed.
        This ESIA Report in hand is prepared for the Project in full compliance with the World Bank
Safeguards Policies, to ensure that the upcoming stages of the project will meet these standards.
The ESIA studies for the Project were carried out through utilization of resources including the
related literature, previously prepared reports, information provided by MUSKI and ILBANK, and
outcomes of the field studies that covers sampling and measurement campaigns to determine
baseline conditions and surveys, interviews, and discussions made with dwellers, muhtars and
municipality representatives.
        After gathering required data from the sources, the studies were carried out with impact
assessment using relevant impact assessment methodologies including mathematical calculations,
geographical information systems, sampling, analysis, face-to-face surveys, and interviews, and
experts’ opinions. The “List of Preparers and Contributors” who have contributed in the ESIA
studies is included in Annex 1 of this report.
        Various documents were consulted during the preparation of the ESIA Report, including
legal reports, laws and regulations, technical and economic reports regarding the project,
publications on land use, natural resources, geology, socio-economic features of the area/region,
maps, various data on water quality, hydrology, and climatology obtained from different agencies
(see References). The impacts were identified and evaluated in the light of all results gathered
together.
        Finally, the report was prepared by ENCON, covering baseline conditions of the physical,
biological, and socio-economic environments, assessments regarding the potential impact of the
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                        Chapter I - Pg. 9/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
project on the outlined baseline conditions, mitigation measures, environmental and social
management plans (ESMPs) that covers construction and operation phases, evaluation of project’s
site and technology alternatives, and public participation activities.
        The World Bank policies formed the basis of the development of environmental, social and
ESIA policies of the International Finance Institutions (IFIs). The general outline of this ESIA report
is guided by the requirements of the World Bank’s Operational Policy (OP) 4.01 Environmental
Assessment (EA) for Category A Projects 1, and includes the following major headings;
         Introduction
         Project description
         Policy, legal and administrative framework
         Baseline data
         Environmental and social impacts and risk and mitigation measures
         Analysis of alternatives
         Environmental and social management plan (ESMP)
         Public participation
         Annexes
        The Project was structured around the above-mentioned main headings. The information
provided in the report was detailed under these headings to the extent that the best available data
allowed. Accordingly, the chapters included in the ESIA Report can be briefly explained as the
following:
         Chapter I. Introduction; leads an introduction to the project and ESIA Report, providing
          project details and environmental and social impact studies.
         Chapter II. Project Purpose and Description; is a description of the project including its
          location, components, technical specifications, associated construction and operation
          activities, and a proposed schedule for implementation.
         Chapter III. Policy, Legal and Administrative Framework; explains national and
          international legal requirements, and also identified environmental agreements that are
          relevant to the project. It also gives an in-depth explanation on the EIA procedure in
          Turkey.
         Chapter IV. Environmental and Social Baseline Conditions; describes the baseline
          conditions in and around the proposed project area, including physical, biological and
          socio-economic conditions.
         Chapter V. Environmental and Social Impact Assessment and Mitigation Measures;
          assesses the potential positive and negative impacts of the project, identifying mitigation
          measures.
         Chapter VI. Project Alternatives; is an analysis of feasible alternatives to the proposed
          project site, technology, design and operation, including a “no project” alternative.
         Chapter VII. Environmental and Social Management Plan; describes the necessary
          management strategies, monitoring activities, and responsibilities for implementation of the
          identified mitigation measures.
1
 A proposed Project is classified as Category A if it is likely to have significant adverse environmental impacts that are
sensitive, diverse, or unprecedented. The impacts may affect an area broader than the sites or facilities subject to physical
works. EA for a Category A project examines the project’s potential negative and positive environmental impacts, compares
them with those of feasible alternatives, and recommends any measures needed to prevent, minimize and mitigate, or
compensate for adverse impacts and improve environmental performance (The World Bank, 2011).
       In line with the World Bank OP 4.01, supplementary information, such as list of preparers
and contributors, references, official letters, related reports, etc., which is relevant to the contents of
the chapters listed above, will be provided in the annexes of the ESIA Report.
        Mugla is a city in south-western Turkey and stretches along the Aegean coast. The city
center is located inland at an altitude of 660 m and lies at a distance of about 30 km from the
nearest coast. Districts of Mugla are Bodrum, Dalaman, Datça, Fethiye, Kavaklıdere, Köyceğiz,
Marmaris, Milas, Menteşe, Ortaca, Seydikemer, Ula and Yatağan. Mugla is surrounded by Aydın
Province on north, Denizli Province on east, Burdur Province on east-southeast and Antalya
Province on southeast. Major part of Mugla belongs to Aegean Region while the remaining small
portion belongs to Mediterranean Region.
       The Project Area is located in the Oren Neighborhood of Milas District. The districts of
Mugla are shown in Figure II.1. In Figure II.2, the site location map of the Project is presented.
        Air distances to the WWTP site are 33.5 km from Milas District Center and 44.5 km from
Mugla City Center. Oren WWTP site’s distances to nearest settlements are shown on a map given
in Figure II.3.
        The construction works of sewerage network will be conducted on existing zoning roads
and no land acquisition is required. On the other hand, pumping stations will be built on public
lands that are registered as park, therefore, no land acquisition is required for pumping stations
either.
        For the second component of the Project, which is Oren WWTP, parcel 407/1 will be used.
The parcel, previously owned by Mugla Metropolitan Municipality, currently belongs to MUSKI.
According to the information given by MUSKI, the parcel is currently in idle status and there is no
land use for any purpose. On the other hand, construction works of the discharge line will be
conducted on existing zoning roads and no land acquisition is required within this regard. Details
about the vicinity of the WWTP site are as follows:
         The construction works of sewerage network and discharge line will be conducted on
existing zoning roads and no land acquisition is required. On the other hand, pumping stations will
be built on public lands that are registered as park, therefore, no land acquisition is required for
pumping stations either. Photos taken from the areas where pumping stations will be built are
provided in Figure II.5.
        In terms of auxiliary facilities, the construction/camp site will be established at the WWTP
site which currently belongs to MUSKI. For the energy transmission lines cadastral roads will be
used.
         Although the energy transmission line has a linear route, only electric poles with a base
size of approximately 5m x 5m will be erected for the energy transmission line. For this reason, in
case of any expropriation process will be needed, the land acquisition area will be very limited as
the land acquisition will only be for the electric poles. Based on that, if energy transmission line will
pass on any private lands or private users on public parcels on the finalized design, then
expropriation and easement activities will be carried out based on the national Expropriation Law
(Official Gazette Date: 08.11.1983 Number of Official Gazette: 18215) and World Bank OP 4.12 -
Involuntary Resettlement. As per the Resettlement Policy Framework of Ilbank for the Project a
RAP (consistent with RPF) will be prepared by MUSKI, reviewed by Ilbank and submitted to WB for
review and approval. Expropriation activities and access to land will not take place without a World
Bank-approved RAP being in place and implemented. Meaning, for any loss of land or establishing
easement rights for the ETL components, compensations will be paid or deposited into escrow
accounts in accordance with the RAP before civil works start. After the expropriation activities,
ownership of the transmission line will be transferred to Turkish Electricity Transmission
Corporation (TEİAŞ). According to that, necessary procedures will be followed as well.
         According to the information given by MUSKI, the parcel is currently in idle status and there
is no land use for any purpose. Photographs taken from the WWTP site are provided in Figure II.6.
         However, no construction works should start in the parcels where public benefit decision is
taken for the ETL components and hence, expropriation or easement rights to be applied. In order
to enter the land, MUSKI has to prepare a RAP in line with the RPF and submit to ILBANK and WB
for review and approval. After RAP approved and implemented (meaning depositing compensation
to people’s accounts) then they can access lands.
        Population projection is an essential part in the design of a sewage network and WWTP
projects. In order to meet the future demand, the population projection of the settlements located in
the service area should be handled properly. When calculating the future population and
accordingly the wastewater generation in the sewage and wastewater treatment facility projects,
generally, 30 years for the service period and 5 years for the realization of the facility (construction)
are accepted and thus, the target year of the project is determined. In the case of the Project at
hand, the target year is determined as 2054 and the population calculations are done accordingly.
         The projections are conducted by using several calculation methods such as Ilbank
Population Calculation Method, Population Projection According to Zoning Plan. After the
calculations, the results are compared with each other and the most realistic one selected as a
design population.
         This method is developed and used frequently by Ilbank (former Bank of Provinces) and is
utilized prevalently during the design phase of infrastructure projects in Turkey. The calculation is
mainly based on geometric method.
        According to this method, the following formulae are used; the first one is used to calculate
population growth coefficient (P) and the second one is used to calculate future population (Ng):
                                               𝑎   𝑁𝑦
                                        𝑃=( √         − 1) 𝑥100
                                                   𝑁𝑒
                                                        𝑃 𝑛𝑔−𝑛𝑦
                                       𝑁𝑔 = 𝑁𝑦 (1 +        )
                                                       100
Where:
       In this method, in order to avoid unrealistically high and/or low population projections,
upper and lower limit values are defined for P. Therefore;
Total Housing Zone in the Zoning Plan = Housing + Developing Housing Zone (m2)
Total Housing Zone in the Zoning Plan = Housing + Developing Housing Zone (m2)
Total Housing Zone in the Zoning Plan = Housing + Developing Housing Zone (m2)
         The population increase rate (Pavg) is obtained as 1.82 by using the census results of the
previous years (1940-2018) for Oren Neighborhood. However, another calculation was made at the
request of the administration using Population Projection According to Zoning Plan and the
resulting population was calculated as N = 33,546. The value of P avg calculated by Ilbank
Population Calculation Method was then accepted as 3.00 and the difference between the two
projections was accepted as a result of Secondary Housings (Summerhouse, time-share etc.) and
calculations were made accordingly.
       According to the calculations, the projected populations are given in the Table II.1 and
Table II.2 in terms of summer and winter populations, respectively. Winter populations are
accepted as the resident population of Oren whereas; tourism contribution is also taken into
consideration during the summer period projection calculations.
                           Years                                                    Population
                           2018                                                        3.058
                           2019                                                        3.150
                           2024                                                        3.651
                           2029                                                        4.233
                           2034                                                        4.907
                           2039                                                        5.689
                           2044                                                        6.595
                           2049                                                        7.645
                           2054                                                        8.863
Source: Milas District Oren Neighbourhood Sewerage Network Project Identification Report
        The summer populations of the settlement areas of the Oren neighbourhood, which
constitute the subject of the project, in line with the projected design stages and considering that
the region is a touristic one are considered with the addition of; the residential population, tourism
population, secondary housings, excursionists and hotel population.
             Residential Population: Population residing in the region during both winter and
              summer seasons.
             Tourism Population: Population coming to the region as a result of tourism activities
              and staying in hotels, motels, hostels, resorts and similar touristic facilities.
             Secondary Housing: The periodic residents of the housing estates, timeshare and
              private summer houses.
             Excursionists: Population found in the region for tourism purposes for less than a day.
             Hotel Population: The working population of hotels in the region.
       For further information on the population projection calculations please see the document
named “Milas District Oren Neighbourhood Sewerage Network Project Identification Report”
prepared by IC Engineering, Architecture and Consulting Services Ltd. for this Project.
         In order to identify the required capacities of sewerage network and WWTPs, accurate
wastewater projections are as much important as population projections. The wastewater amount
calculations are performed based on the water consumption per capita values. Assumed water
consumption per capita data are provided in Table II.3. According to the accepted consumption
rates the wastewater amounts that is foreseen to be generated in the coming years are given in
Table II.4.
         The entire project area produces domestic wastewater. In the previous section, 24-hour
wastewater generation of the District was determined. It is foreseen that the wastewater generated
will reach the sewerage network in 12 hours. The total amount of wastewater generated according
to the years is given in Table II.5 below.
                          Years                                                          Flowrate
                             2019                                              30.00 * 2 = 60.00 l/sec
                             2024                                              33.50 * 2 = 67.00 l/sec
                             2029                                              37.50 * 2 = 75.00 l/sec
                             2034                                              41.50 * 2 = 82.00 l/sec
                             2039                                              45.50 * 2 = 91.00 l/sec
                             2044                                             50.50 * 2 = 101.00 l/sec
                             2049                                             55.50 * 2 = 111.00 l/sec
                            2054                                              61.50 * 2 = 123.00 l/sec
Source: Milas District Oren Neighbourhood Sewerage Network Project Identification Report
        In addition to the domestic wastewater generation rates of the area that the Project will
serve, the wastewater flow coming from Turkevleri and Bozalan Neighborhoods which are
generally consist of holiday camps and summer houses, located in the western part of Oren
neighborhood are also considered as downstream flow for the Project. Also, the wastewater from
the marina within the borders of the Oren neighborhood will also be given in the system as
downstream flow.
         Moreover, Kilic Fishery and Fish Farm located in Bozalan Neighborhood currently using a
sewage truck to collect its wastewaters and discharge it. The wastewater from this Fish Farm will
also be discharged into the new sewer system in the scope of the Project as downstream flow. The
total wastewater flowrates of the area that the project will serve at the target year (2054) is given in
Table II.6 below.
Design Flowrates
         The design flowrates of the Milas – Oren WWTP for 1st and 2nd stages are presented in
Table II.7. These flowrate determinations were conducted based on the approved feasibility reports
and the negotiations made with the related governmental authority.
         For the characterization of wastewater, pollution load per capita data found by conducted
literature research was used. This was found to be sufficient and accurate since the only
wastewater source will be domestic and it is easy to find literature values for the characterization of
domestic wastewater.
         During literature searches, different pollution load per capita values were found (Erdogan
et. al., 2005; WWTP Technical Specifications Communique, 2010; WWTP Design Guide, 2012;
ATV-A 281 E, 2001 etc.). The wastewater characterization calculations were performed by using
these entire different pollution load per capita values and ATV-DVWK standards. After the
calculations performed, the obtained wastewater characteristics and pollution load of Milas – Oren
WWTP are given in Table II.8.
         Discharge standards for Milas – Oren WWTP has been determined based on the Urban
Wastewater Treatment Regulation (Official Gazette date: January 8, 2006, number: 26047) which
was published to accomplish the harmonization of national regulations with Directive 91/271/EEC
on Urban Waste Water Treatment and Directive 98/15/EEC amending Directive 91/271/EEC.
Discharge standards to be complied with are given in Table II.9 and these standards are accepted
as maximum limits. As the Project also follows WB standards and guidelines, the effluent quality
will meet the limit values stipulated by these. WBG General EHS Guidelines refers to WBG EHS
Guidelines for Water and Sanitation for guideline values for effluent quality of centralized,
municipal, wastewater treatment systems. The WBG EHS Guidelines for Water and Sanitation
states that effluent water quality should be consistent with applicable national requirements or
internationally accepted standards such as Council Directive 91/71/EEC of 21 May 1991 on Urban
Wastewater Treatment, whose discharge criteria is in line with the Turkish Urban Wastewater
Treatment Regulation. Therefore, following Turkish Urban Wastewater Treatment Regulation will
also keep the Project in line with international standards in terms of effluent quality.
        The effluent of the WWTP will be discharged to the Hanay Creek through 1,542 meter
discharge line. Hanay Creek is not determined as a sensitive receiving body, thus the effluent of
the WWTP will be subjected to the limit values described in above paragraph. The Project will be
subjected to the limit values given for TN and TP as well.
 TSS                                                    mg/L                                       35
 BOD                                                   mg O2/L                                     25
 COD                                                   mg O2/L                                     125
                                                                                    15 (for population equivalent btw
 TN                                                    mg N/L
                                                                                          10,000 and 100,000)
                                                                                 2 (for population equivalent btw 10,000
 TP                                                    mg P/L
                                                                                              and 100,000)
Source: Milas District Oren Neighbourhood Sewerage Network Project Identification Report
        For the selected design of the WWTP, specific density and volume of the sludge that is
expected to be generated after the sludge dewatering process, are estimated as 1.05-1.1 ton/m3
and 0.13-0.21 L/capita.d, respectively2. For the calculation of sludge generation amount, below
given formula is used.
       Within the light of this information, estimated sludge generation amounts for the years and
seasons are given in Table II.10.
                                        Winter                                Summer
         Years
                                        ton/d                                  ton/d
         2019                            0.58                                   2.14
         2024                            0.67                                   2.40
         2029                            0.78                                   2.68
         2034                            0.90                                   2.97
         2039                            1.04                                   3.29
         2044                            1.21                                   3.62
         2049                            1.40                                   3.99
         2054                            1.63                                   4.38
        A new sewer system will be constructed to collect the wastewater of Oren Neighborhood of
Milas District. This new sewer system will be connected to the Milas – Oren WWTP.
        The wastewater system consists of manhole shafts, parcel connections, secondary and
main collector network lines, and force mains, starting from the point where wastewater is
generated. The network lines are designed such that the wastewater can be delivered to the main
collector and thus the WWTP in the fastest way, without entering the reverse slope as much as
possible. As for the collecting lines, wide roads were preferred as much as possible considering the
grading. The system is determined to be a separate system. In separate systems, storm waters
and wastewaters are collected with different networks.
         Within the hydraulic principles for determining the diameters of the channels in the sewage
system, the difference in water consumption at certain times of the day is the most important factor
affecting the results. The change in water consumption gives different flow rate on an hourly, daily
and weekly basis. The maximum flowrate during the day can be expressed as a function of the
average flowrate. For this reason, a peak flow factor will be used to stay safe in the design of sewer
channels, and the peak factor is determined as 2 for the project design of the channels.
2Andreoli, C., Sperling, M., & Fernandes, F. (2007). Sludge treatment and disposal. London: IWA
Publishing.
        The hydraulic calculations of the Oren sewerage system are made using the Kutter
formula;
                                                           𝑎√𝑅
                                                𝑄=𝐹∗              √𝐽𝑅
                                                         𝑏 + √𝑅
        According to the calculations made and conditions considered, the minimum, maximum
slope limits, fill rate, and maximum distance between the manhole shafts, are given in the Table
II.11.
       In order to prevent blockages and provide the best flow in sewer systems, the minimum
diameters of the parcel connection and network pipes will be 150 mm and 200 mm, respectively.
        Manhole Shafts will be installed in direction changing locations, slope changing locations,
and pipe connections. These manholes will be used for maintenance and cleaning of the channels.
These Manhole Shafts will be designed in compliance with the standards of the ILBANK
specifications, which are:
         In manholes with chute, minimum chute height is planned as 0.75 m and maximum chute
height is planned as 4.00 m. In the diameter change locations, the crown levels of the pipes will be
levelled and there will be no transitions from large diameter pipes to small diameter pipes. The
channels are designed telescopic both horizontally and vertically. The shortest possible vertical
crossings have been made where the system crosses roads, streams, and channels.
        The pipes that will be used in the sewer system will be HDPE corrugated pipes and GRP
pipes with SN8 rigidity. The exemplary manhole structures that will be used in the sewer systems
are given in the Figure II.8.
Pumping Stations
        Within the scope of the Project, four underground pumping stations will be constructed.
While two of the pumping stations will be constructed as package pumping stations, the others will
be constructed as reinforced concrete pumping stations.
         The pumps within the pumping stations are selected as submerged electromagnetic pulse
pumps. Within the pumping stations, sound insulation building materials will also be used, in order
to prevent generation of the excessive noise levels in the vicinity of the pumping stations.
According to the Design and Pre-evaluation Report of the Project, the final design of the pumps is
not decided yet apart from the numbers and locations. Thus, some changes may occur during the
upcoming period. An exemplary design of the envisaged system of pumping stations is given in
Figure II.9.
         During the site selection process for these pumping stations the sites were selected as
public lands that are registered as parks, therefore no land acquisition processes will be triggered.
If any changes occur on the site selected for pumping stations during subproject implementation,
MUSKI will share this change for the approval of Ilbank and WB, and make necessary
amendments in the site specific environmental and social safeguards instruments accordingly.
Within this respect, an ESIA Addendum needs to be prepared when site selections are finalized for
the pumping stations. When selected sites are known, eligibility evaluation should be done as a
priority within the scope of the Project. Then, the ESIA Addendum will be conducted in line with the
requirements of OP/BP 4.01 and will cover all the impacts covered in this ESIA, as minimum. The
ESMP of this ESIA will be updated with the findings of ESIA Addendum.
         Milas – Oren WWTP will be constructed as a part of this integrated Project. The Milas –
Oren WWTP is designed as an advanced biological wastewater treatment system to work with
Extended Aeration Activated Sludge Process. As mentioned before, the plant will have a daily
capacity of 4,000 m3/day for the 1st Stage, and total of 8,000 m3/day (4,000 m3/day + 4,000 m3/day)
for the 2nd Stage. The WWTP will be located on an area of 8278.11 m2. The 1st Stage of the plant
will be in operation until 2028. After 2028, the 2nd Stage of the plant will be realized. The area,
where the WWTP will be constructed, is given in Figure II.10. The layout of the WWTP is given in
Figure II.11.
        Coarse Screen
        Pump Station
        Fine Screen
        Aerated Grit Chamber
        Rectangular Weir and Distribution Chamber
        Anaerobic BioP Tanks
        Aeration Tanks
        Final Sedimentation Distribution Chamber
        Final Sedimentation Tanks
        Treated Water Pit
        Disinfection Tank
        Sludge Pumping Station
        Sludge Thickener
        Sludge Dewatering Building
        Blower Building
        Administrative Building
        Transformer and Generator Building
        Security Cabin/Guardhouse
        Preliminary treatment units of Milas - Oren WWTP consist of coarse and fine screens and
aerated grit chambers. Coarse and Fine screens are used for removing solid wastes such as
debris, found in the wastewater. Aerated Grit Chambers are used for removing grit from
wastewater streams.
Coarse Screens
       Coarse screens remove rags, sticks, large solids and other debris ranging from 5 to 15 cm.
They can be as simple as a trash rack or as complicated as a mechanically cleaned bar screen.
Generally speaking, larger treatment facilities will install a mechanically cleaned bar screen
whereas small, outdated facilities are likely to use a manually cleaned bar screen.
Fine Screens
        Where coarse screens use bars or rods to remove solids, fine screens employ wire cloth,
wedge wire elements or perforated plates. Fine screens are used to remove particles that may
cause maintenance issues for process equipment and/or operational problems to the treatment
process. Fine screen openings typically range from 1.5 mm to 5 cm. The smaller size openings
allow the fine screens to remove 20 to 35% of suspended solid and BOD.
         Removal of grit and oil-grease within the wastewater will be ensured through aerated grit
chambers. In aerated grit chamber, inorganics like sand, pebble, silt, glass, metal etc. will be
removed. Grit chambers are equipped with aeration systems to keep low density organics
suspended and separating oil and grease. Grit chambers are designed to remove at least 85% of
the solid particles with diameters greater than 0.2 mm and specific gravity greater than 2.65.
       The scraper/skimmer bridge moves back and forth regularly over the tank and collects and
sends the suspended grit to grit washer by its submersible pumps. The bridge also skims the oil
and grease and collects them in the hopper. Floating material such as oil and grease collected at
the hopper is transferred to the container for final disposal then.
        Removal of carbon-based pollutants as well as nitrogen and phosphorus are carried out
simultaneously at the bio-phosphorus tanks, aeration tanks and final sedimentation tanks. These
units are considered as the advanced biological treatment components of Milas – Oren WWTP.
The detailed information about these units is given in following subsections.
        Biological phosphorus removal consists of two stages. These stages are storage of
phosphorus release in anaerobic environment and the storage of the excess of the released
phosphorus in anoxic/oxic environment. To enable phosphorus release, readily degradable
dissolved organic carbon in the inlet water shall be stored within the cell. When there is an electron
Aeration Tanks
          In the anoxic and oxic sections of the aeration tanks, biological treatment continues with
nitrification and denitrification processes. The amount of air required for nitrification is supplied and
the ammonium nitrogen at the inlet is converted into nitrate nitrogen. Generated nitrate nitrogen
then is used as an electron acceptor for the removal of biochemical oxygen demand. Then the
wastewater is transferred to aeration tanks for its further treatment in bio-P tanks. Aeration tanks
are designed as pre-denitrification systems.
         The secondary (final) sedimentation tanks allow the microorganisms and other solids to
settle after secondary or biological treatment. This sludge is pumped back into the inlet end of the
primary sedimentation tanks and settles with the raw sludge. At this stage the BOD may be
reduced to approximately 75 - 80% of the influent level and suspended solids are removed.
Sludge Thickener
        Sludge thickening process involves the concentration of thin sludges to more dense sludge
in special circular tanks designed for this purpose. Its use is largely restricted to the watery excess
sludge from the activated sludge process. It may also be used to concentrate sludge to primary
tanks or a mixture of primary and excess activated sludge prior to high rate digestion.
         The thickening tank is equipped with slowly moving vertical paddles built like a picket
fence. Sludge is usually pumped continuously from the sedimentation tank to the thickener which
has a low overflow rate so that the excess water overflows and the sludge solids concentrate in the
bottom. A blanket of sludge is maintained by controlled removal which may be continuous at a low
rate. Sludge with a solids content of 8 -10% or more can be produced by this method. This means
that with an original sludge of 2%, about four-fifths of the water has been removed, and one of the
objectives in sludge treatment has been attained.
Sludge Dewatering
        Sludge dewatering will be performed by decanters. Biological sludge that will be collected
from the final sedimentation tanks and the sludge that will be collected from sludge thickening
tanks will be sent to the sludge dewatering system. Sludge dewatering units will increase the solid
content of the sludge from 1% to 25%.
Sludge Disposal
       After stabilization and dewatering, the excess sludge will be analysed to determine
compliance with the Annex-2 of the Regulation on Landfilling of Wastes and if it is deemed
appropriate, the sludge will be collected by the licensed disposal companies determined by MUSKI
every year. The sludge will be collected from the facility by transportation vehicles of licensed
companies and then will be stored in landfill.
         In Milas – Oren WWTP, the treated effluent will be discharged into the Hanay Creek and
hence, disinfection of the effluent is required. Disinfection is the process designed to kill or
inactivate most microorganisms in wastewater, including essentially all pathogenic organisms. In
this scope, the effluent of the Milas – Oren WWTP will be disinfected by using chlorination method.
        In the scope of the Project, several auxiliary facilities will be required. Related information
about these facilities is given below:
                In order to provide energy for the WWTP, energy transmission line will be needed.
                 According to the information given by MUSKI, the energy will be supplied from the
                 transformer no. 3 located 700 meters away from the WWTP. 35.4 kV (medium
                 voltage) of energy will be used from this transformer which has a capacity of 2
                 MVA. For the energy transmission line cadastral roads will be used. The
                 subcontractor will be responsible from the construction of energy transmission line.
                 Although the energy transmission line has a linear route, only electric poles with a
                 base size of approximately 5m x 5m will be erected for the energy transmission
                 line. For this reason, in case of any expropriation process will be needed, the land
                 acquisition area will be very limited as the land acquisition will only be for the
                 electric poles. Based on that, if energy transmission line will pass on any private
                 lands or private users on public parcels on the finalized design, then expropriation
                 and easement activities will be carried out based on the national Expropriation Law
                 (Official Gazette Date: 08.11.1983 Number of Official Gazette: 18215) and World
                 Bank OP 4.12 - Involuntary Resettlement, and a RAP (consistent with RPF) will be
                 prepared and implemented as needed. After the expropriation activities, ownership
                 of the transmission line will be transferred to Turkish Electricity Transmission
                 Corporation (TEİAŞ). According to that, necessary procedures will be followed as
                 well.
                The construction materials will be provided from close vicinity of the Project area.
                 There will be no need for borrow pits/quarries within the scope of the project since
                 the need will be met from the existing licensed quarries in the region.
                In terms of establishment of construction/camp site, the Contractor will be
                 responsible within the scope of Project.
                Regardless of the exact number of people to be employed, the priority will be given
                 to the local population. Therefore, there will be no accommodation at construction
                 site.
                Since the WWTP site is accessible through the existing road network and the
                 sewerage network and discharge line will be constructed on public roads,
                 construction of any access/service road is not required.
        However, no construction works should start in the parcels where public benefit decision is
taken and hence, expropriation or easement rights to be applied. In order to enter the land, MUSKI
has to prepare a RAP in line with the RPF and submit to ILBANK and WB for review and approval.
After RAP approved and implemented (meaning depositing compensation to people’s accounts)
then they can access lands.
         Although it is not decided yet, it is expected that around 100 workers at the peak period of
construction phase and 10 workers in the operation phase of the Project (WWTP and Sewerage
Network) will be employed. Regardless of the exact number of people to be employed, the priority
will be given to the local population. Therefore, there will be no accommodation on site.
        The tendering and contracting period of the Project is expected to take place in the Q1 of
2022, after the tendering period the construction works will start and last for 18 and 24 months for
the WWTP and sewerage network, respectively. The defect liability period (DLP) starts just after
that and lasts for 12 months. The anticipated schedule of the Project is provided in Table II.12.
Construction
DLP
Sewerage Network
Construction
DLP
         The key national laws and regulations presented in this section include the legal
requirements to reduce the potential environmental impacts that may arise from the construction
and operational activities of the Project. Turkish Legislation related to the Project is presented in
the following sections under relevant subtopics.
         Environmental Law, which is ratified in August 1983, is one of the principal legislation
related to the Project. Several by-laws and decrees are enforced under the Environmental Law.
        The Environmental Impact Assessment Regulation (Official Gazette date November 25,
2014, number 29186) defines the administrative and technical procedures and principles to be
followed throughout the EIA process. When an activity (a Project) is planned, the Project developer
is responsible for preparing an Environmental Impact Assessment (EIA) Report along with many
other permits required to realize the Project. However, facilities are subject to preparation of an EIA
Report depending on the type of the facility, its capacity, or the location of the activity. The activities
that are subject to the provisions of the Environmental Impact Assessment Regulation are listed in
Annex I and Annex II of the Regulation. For Annex I activities a full EIA report is required and those
Projects go through the full EIA process. For Annex II activities, a Project Presentation File (PPF) is
prepared in accordance with the outline given in the Regulation and the relevant process has to be
conducted. As a result of the submission of PPF, if “EIA is required” decision is given, a full EIA is
prepared.
         The EIA process starts with submitting a brief report (EIA Application File), summarizing
the characteristics of the Project and the impact area, and the potential environmental impacts and
mitigation measures, prepared according to the format provided in Annex III of the EIA Regulation
to the Ministry of Environment, Urbanisation and Climate Change. Then the MoEUCC, General
Directorate of EIA, Permit and Inspection forms a committee from related governmental and non-
governmental agencies, which also includes the Project Owner and the consultant that would
prepare the EIA report. With the formation of this committee the scoping phase starts.
        This committee aims to define the scope of the EIA report to be prepared for the Project.
The EIA scope is defined based on findings of the committee and the comments and suggestions
received from a public consultation meeting to be held at the Project site. The purpose of the
meeting is to give information regarding the Project and take the opinion of the public and answer
their questions regarding the Project.
         In addition, the Ministry shall announce that the EIA process regarding the Project has
been initiated and information regarding the EIA process may be obtained also via the internet. The
scoping phase is completed with a meeting of this committee during which the EIA scope is agreed
on. Based on the agreed scope, the EIA studies are conducted and the report is prepared. After the
submission of the EIA Report to the General Directorate of EIA, Permit and Inspection, it is
checked with regard to the contents to decide whether the report is suitable for starting the review
process. If the content of the report is found to be appropriate, the review period starts and ends
with either a positive or negative decision.
        Infrastructure projects such as sewerage networks, water supply networks and storm water
systems are out of the scope of the Environmental Impact Assessment Regulation. Therefore, no
EIA study is required for the sewerage network component of this Project. Wastewater treatment
plants are scoped-in according to their daily capacity or equivalent population. While the treatment
plants with an equivalent population higher than 150,000 and/or capacity higher than 30,000
m3/day require full EIA study, which means these projects are listed under Annex I of the
regulation; the ones with an equivalent population in between 50,000 and 150,000 and capacity in
between 10,000 m3/day and 30,000 m 3/day require PPF, which means these projects are listed
under Annex II of the regulation. Therefore, the wastewater treatment plant of this Project, which
has 8,000 m3/day design capacity, does not require either an EIA or PPF. EIA exempt decision is
given in Annex-9 of this report.
        Medium voltage overhead transmission lines are not subjected to the national EIA
Regulation. Energy transmission lines more than 15 km and higher than 154 kV are subjected to
EIA procedure, whereas the ones between 5 km and 15 km and higher than 154 kV are subjected
to Selection and Elimination criteria. By taking into consideration of the length and voltage of the
proposed energy transmission line, it is anticipated that the risks and impacts due to construction
and operation of the energy transmission line would be of a low magnitude.
      The Project with all its components is out of the scope of the Turkish Environmental Impact
Assessment Regulation.
         The rest of the Turkish EHS Legislation that the Project will comply with is presented in
Table III.1 below.
        MUSKI shall comply with the requirements of the current national legislations and codes of
practice, and fulfil all other legal requirements. Therefore, during each stage of the planned Project
and implementation of related management plans, all activities will be carried in accordance with
certain standards and limits set by the above-mentioned laws and regulations and any license
and/or permit required for the upcoming stages of the Project will be acquired accordingly.
Table III.2 Project related Turkish Legislation on the Conservation of Nature and Wildlife
          The Turkish Labor Law (Law No: 4857) was enacted on 22.05.2003 and published in
official gazette on 10.06.2003. The purpose of this law is to regulate the working conditions and
work-related rights and obligations of employers and employees working under an employment
contract. This Law applies to all the establishments and to their employers, employer’s
representatives and employees, irrespective of the subject matter of their activities with the
exception of the activities and employment relationships listed in Article 4 of this law, some
examples to these exceptions are; sea and air transport activities, any construction work related to
agriculture which falls within the scope of family economy, domestic services, sportsmen, etc. This
law regulates the labor related subjects such as; The principle of equal treatment which aims to
avert discrimination based on language, race, sex, political opinion, philosophical belief, religion or
similar reasons; The transfer of the establishment or one of its sections which defines the process
of the transfer paying attention to not to victimize anyone; Temporary employment relationships in
order to protect the rights of both parties. Also, labor law regulates the employment contracts, types
and terminations, wages, organization of work, employment service, supervision and inspection of
working conditions, administrative penal provisions and supplementary, transitional and concluding
provisions of labor related subjects.
         The Turkish Law on the Right to Information (Law No: 4982) was adopted in 09.10.2003
and published in the official gazette on 24.10.2003. The main objective of this law is to regulate the
procedure and the basis of the right to information according to the principles of equality,
impartiality, and openness that are the necessities of a democratic and transparent government.
This law is applied to the activities of the public institutions and the professional organizations
which qualify as public institutions. The Law which is formed of five parts in total explains the legal
obligations about information disclosure processes. The first part of the law defines the objective,
scope, and definitions of terms that are used in law. The second part of the Law makes statements
about the subjects of the Right to Information and the Obligation to Provide Information. According
to Articles 4 and 5 of this Law found in this part, everyone has the right to information and the
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                                    Chapter III - Pg. 46/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
responsible parties are obligated to provide information. The application process for accessing
information is explained in the third part of the law. In the fourth part of the Law the information that
is restricted is described some exemplary ones are; information and documents pertaining to the
state secrets, information, and documents pertaining to the economical interests of the state, etc.
Finally, the last part of the Law describes the miscellaneous aspects of this law such as entry into
force and execution.
III.1.5 Permits
             Project Approval
             Construction license
             Permit for zoning amendment
             Permits for pumping stations
The international agreements and conventions that Turkey had ratified are:
             Paris Convention on the Protection of the World Cultural and Natural Heritage (1975),
             Barcelona Convention on the Protection of the Mediterranean Sea Against Pollution
              (1976),
             Bern Convention on Protection of Europe's Wild Life and Living Environment (1982),
             The Convention for the Protection of Marine Environment and the Coastal Region of
              the Mediterranean (Barcelona Convention) (1981),
             Convention on Long Range Transboundary Air Pollution (CLRTAP) (1983)
       Since the main finance source of the Project is WB; the Project must be in compliance with
the good international practice, including WB Safeguard Policies, guides, performance standards
and best practices documents alongside the national legislation.
        WB governs projects and activities by the Safeguard Policies in order to assure that they
are conducted in an environmentally, financially and socially sound manner. Safeguard Policies
include Environmental Assessments and other policies that define environmental and social
adverse effects of the projects as well as their reduction and prevention. These policies are
enlarged upon in “The World Bank Operations Manual”, which also provides guidance on
compilation with the Operational Policies (OP), Bank Procedures (BP) and Good Practices (GP).
OPs are defined as statements of policy objectives and operational principles including the roles
and obligations of both the Borrower and the Bank, while BPs are compulsory procedures to be
followed by both the Borrower and the Bank and GP are non-compulsory advisory material.
Specific policies related and maybe related to the Project are listed below:
         The main objectives and tasks of the Project-related WB Safeguard Policies are explained
below:
          To notify the riparian countries in case of any activities implemented affecting the
           quality and quantity of water on international waterways. The waterways identified as
           NOT an international waterway (do not trigger OP 7.50) in Turkey are as follows:
           Susurluk, North Aegean, Gediz, Kuçuk Menderes, Buyuk Menderes, Western
           Mediterranean, Antalya, Sakarya, Western Black Sea, Yesilirmak, Kizilirmak, Konya
           Kapali, Eastern Mediterranean, Seyhan, Ceyhan, Eastern Black Sea, Burdur,
           Afyon,Orta Anadolu, and Van. There is no international waterway within the scope of
           the Project.
         Under the WB’s Operational Policy for Environmental Assessment (OP 4.01), projects are
classified as Category A, B and C, based on the level of their likely environmental and social
impacts. Brief definition of these categories is given as follows:
        Considering the location of the Project and the nature of its potential environmental and
social impacts, the Project would be categorized as Category A Project for which a full-scale
environmental and social impact assessment is required under WB screening criteria and OP 4.01.
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                      Chapter III - Pg. 50/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
        It should be noted that Turkish laws, notably Law No. 2863 dated 21.07.1983 on the
Protection of Cultural and Natural Assets (revised through the amendment issued on 27.07.2004
dated Official Gazette) and practices meet the World Bank requirements for physical cultural
resources (OP 4.11). The Regulation on Research, Drillings and Excavations in Relation to the
Cultural and Natural Assets, which was published in the Official Gazette No. 18485 dated
10.08.1994 define the procedures and obligations concerning the cultural and natural assets found
out during construction.
         The World Bank Group (WBG) Environmental, Health and Safety (EHS) Guidelines
constitutes technical reference resources that include general and sector specific examples of
international good sector practices. It includes the information on applicable environmental, health
and safety issues for all industrial sectors. WBG uses the EHS Guidelines as a technical source of
information during project appraisal. EHS Guidelines include performance levels and
measurements that can be achieved at newly installed facilities using WBG's available
technologies at reasonable cost.
General Health and Safety Guidelines include the following main items;
           Environmental
            o Air Emissions and Ambient Air Quality
            o Energy Conservation
            o Wastewater and Ambient Water Quality
            o Water Conservation
            o Hazardous Materials Management
            o Waste Management
            o Noise
            o Contaminated Land
           Occupational Health and Safety
            o General Facility Design and Operation
            o Communication and Training
            o Physical Hazards
            o Chemical Hazards
            o Biological Hazards
            o Radiological Hazards
            o Personal Protective Equipment
            o Special Hazard Environments
            o Monitoring
           Community Health and Safety
            o Water Quality and Availability
            o Structural Safety of Project Infrastructure
            o Life and Fire Safety
            o Traffic Safety
            o Transport of Hazardous Materials
            o Disease Prevention
            o Emergency Preparedness and Response
           Construction and Decommissioning
            o Environment
            o Occupational Health and Safety
            o Community Health and Safety
         In addition to the General EHS Guidelines, WBG EHS Guidelines for Water and Sanitation
is also applicable.
        According to national legislation, the areas, with significant biological diversity, with local
endemics of importance, with species that has a threat status of endangered, etc. are given
protection status. With this regard, sites can be put under protection and conservation as national
park, nature conservation area, wildlife protection and/or development area, specially protected
area, water products production area.
         Main issues between Turkish legislation and OP 4.04 are in fact related with Turkish
planning and environmental assessment requirements, but some other issues can be summarized
as follows:
             The process for identification of important natural habitats and lack of consultation with
              relevant stakeholders in this process.
             Requirements of baseline studies in important natural habitats
             Identification of the projects that would be allowed in such areas.
             Study requirements (such as EIA reports) for the projects to be realized in
              important/critical natural habitats.
         National regulatory process and procedures for the EIA reports are in general compatible
with the WB policies on environmental assessment (OP 4.01). EIA regulation requires the coverage
of all issues regarding biological diversity and terrestrial and aquatic flora and fauna in the EIA
reports. In these terms, they are compatible with WB policies on natural habitats (OP 4.04).
        The main issues rise in the scope and details of the EIA studies and reports can be listed
as given in the following paragraphs:
         National PPF process is basically a process for screening projects (which are listed in
Annex 2 of the EIA regulation) to decide if there is a need for a full EIA. In these terms, it does not
comply with the project classification of the WB for environmental assessments. That is to say WB
might require an ESMP based on a more simple impact assessment, when compared with EIA
assessments, for category B projects. However, in PDF reports in Turkey a simple impact
assessment is required, but it ends up generally with very limited environmental management and
monitoring measures and there is no requirement of monitoring. In fact, these differences are again
due to the scoping and review of these PPF reports and not due to the lack of relevant terms in the
legislation.
        In this regard, main conflict or gap with the WB policies in terms of environmental
assessment comes into picture for the Annex 2 projects (which are like Category B projects of WB)
in Turkey.
             For these projects impact assessment in the PPF is rather superficial and does not
              come up with relevant impact management and monitoring measures.
             These projects are accepted to be rather small scale and associated facilities for such
              projects are either all ignored or very slightly mentioned.
             The biodiversity issues and natural habitats evaluations in PPF reports are almost all
              depended on literature for many projects (if there is not international loan involvement
              or a well-known sensitive area).
             The social assessment is not included in the PPF reports. Therefore, during the PPF
              there aren’t any requirements for social studies, in terms of both desktop and field
              research.
III.3.4   Differences between Project-related National Legislation and WBG Guidelines’ Limit
          Values
         Among the legislation presented in Chapter III.1.1, the key Project-related national
regulations are Surface Water Quality Regulation and Urban Wastewater Treatment Regulation in
terms of thresholds and limit values. While Surface Water Quality Regulation determines water
quality of the receiving body in its Annex-5 Table 3, Urban Wastewater Treatment Regulation sets
limit values for effluent quality and treatment efficiencies as presented in Table III.3.
60 (EP 2,000-10,000) 70
                                            2 (EP 10,000-100,000)
 Total Phosphorus**                                                                       80
                                               1 (EP >100,000)
                                            15 (EP 10,000-100,000)
 Total Nitrogen**                                                                        70-80
                                               10 (EP >100,000)
* EP: Equivalent Population
** Requirements for discharges from urban waste water treatment plants to sensitive areas which are subject to
eutrophication
         The WBG’s Environmental, Health and Safety Guidelines for Water and Sanitation, which
is another key document, does not provide limit values for effluent water quality parameters as in
Turkish Urban Wastewater Treatment Regulation. However, the Article 65 of the Guideline refers to
the “applicable national requirements or international accepted standards” for the effluent water
quality. The Turkish Urban Wastewater Treatment Regulation has been constituted on the base
European Union: Council Directive 91/271/EEC of 21 May 1991 Concerning Urban Wastewater
Treatment, which is the footnote-referred legislation of the Guideline, thus; there are no gaps in
between.
          Descriptions and information provided in this chapter, regarding current conditions of the
Project area and its vicinity, are based on reports prepared by related public and private
institutions, field studies conducted for identification of physical environment, Geographical
Information Systems (GIS) studies and satellite imagery, data acquired from the Ministry of
Agriculture and Forest and data acquired from the meteorology stations of the General Directorate
of Meteorology.
        In this section detailed information on the land use and ownership status of the Project
area is given.
Land Use
         The site (8278.11 m 2) designated for Milas-Oren WWTP currently consists of an area that
is used as pasture but currently idle and it is not used for any purpose (See sections II.1 and II.2 for
the photographs taken from the site). The site is selected due to the closeness to the Hanay Creek.
The WWTP area previously owned by Mugla Metropolian Municipality, currently belongs to MUSKI.
In the close vicinity of the WWTP area, there are roads, belt conveyor of Kemerköy Thermal Power
Plant, Mugla Sitki Kocman University Fisheries Research and Development Centre, and privately-
owned plots where construction of yacht manufacturing repair and boatyard is currently
undergoing.
        The closest settlement to the WWTP site is located 50 meters at the northeast at Mugla
Sitki Kocman University Fisheries Research and Development Centre and the closest settlement
area is around 175 meters at the south-east. The WWTP area can be accessible with the current
roads; therefore, no access roads will be constructed.
        In the scope of the Project, the WWTP will be constructed within the area that belongs to
MUSKI and there will be no need for land acquisition. On the other hand, construction of the
discharge line will take place in existing roads and no land acquisition is required within this
respect.
        The new sewerage system will be constructed by following the same route of the existing
system and pumping stations will be built on public lands that are registered as park. Therefore,
there will be no resettlement and/or physical displacement of persons in and around the Project
Area.
        In terms of auxiliary facilities, the construction/camp site will be established at the WWTP
site which currently belongs to MUSKI. For the energy transmission lines cadastral roads will be
used, therefore, no land acquisition will be required.
        According to the 1/5000 and 1/1000 scale development/zoning plans, WWTP area has
been allocated as WWTP site and pumping station areas as park (public garden) sites. MUSKI
applied to Milas Municipality regarding the amendment of 1/5000 and 1/1000 scale
development/zoning plans for the allocation of related park sites to technical infrastructure (such as
pumping station) sites on July 06, 2020 (see Annex-8). As a result of this application respective
amendments are still under evaluation by the municipality.
Property
         The WWTP site is selected due to the closeness to the Hanay Creek. In the scope of the
Project, the WWTP will be constructed within the area belongs to MUSKI and there will be no land
acquisition. Currently, the area is idle and it is not used for any purpose (See sections II.1 and II.2
for the photographs taken from the site).
        The closest building to Oren WWTP is located 50 meters at the north-east, which is Mugla
Sitki Kocman University Fisheries Research and Development Centre, and the closest settlement
is around 175 meters at the south-east. The area can be accessible with the existing roads;
therefore, no access roads will be constructed.
         There are no land related issues expected for sewerage network and discharge line, as
they will be constructed on existing roads.
        On the other hand, pumping stations will be built on public lands that are registered as
park, therefore, no land acquisition is required for pumping stations either.
         In terms of auxiliary facilities, the construction/camp site will be established at the WWTP
site which currently belongs to MUSKI. For the energy transmission lines cadastral roads will be
used. Although the energy transmission line has a linear route, only electric poles with a base size
of approximately 5m x 5m will be erected for the energy transmission line. For this reason, in case
of any expropriation process will be needed, the land acquisition area will be very limited as the
land acquisition will only be for the electric poles. Based on that, if energy transmission line will
pass on any private lands or private users on public parcels on the finalized design, then
expropriation and easement activities will be carried out based on the national Expropriation Law
(Official Gazette Date: 08.11.1983 Number of Official Gazette: 18215) and World Bank OP 4.12 -
Involuntary Resettlement, and a RAP (consistent with RPF) will be prepared and implemented as
needed. After the expropriation activities, ownership of the transmission line will be transferred to
Turkish Electricity Transmission Corporation (TEİAŞ). According to that, necessary procedures will
be followed as well.
        However, no construction works should start in the parcels where public benefit decision is
taken and hence, expropriation or easement rights to be applied. In order to enter the land, MUSKI
has to prepare a RAP in line with the RPF and submit to ILBANK and WB for review and approval.
After RAP approved and implemented (meaning depositing compensation to people’s accounts)
then they can access lands.
       This chapter identifies existing topographical, soil and geological conditions along the
Milas-Oren Wastewater Treatment Plant, discharge line and sewerage network. As, the sewerage
system and discharge line will be constructed on the existing public roads and pumping stations will
Topography
        The project area is located in the Aegean region of Turkey, which is known with its tourism
potential. The Aegean Sea is located in the south of the Project area, the Milas district in the north,
the (Merkez) Mentese district in the east and the Bodrum Peninsula in the west.
         The only streams that flow inside the town are the Kemer and Koca Streams which are
also located in the vicinity of the WWTP site. In addition, Hanay Creek can be mentioned also, as
this stream is the closest stream to town apart from Koca and Kemer Streams. The highest
elevation is +60 meters and the lowest elevation is around +1 meter within the zoning plan in the
Project area. The regional center has a topographic structure that slopes from north to south.
Soil
        Turkish General Directorate for Rural Services database defines the land use capabilities
in 8 different classes as summarized in Table IV.1. These classes represent the agricultural
potential of the soils. In this classification system, soils are categorized between Class I, which
represent the arable lands on which agricultural activities can be conducted in the most efficient,
economic and simplest way without causing erosion, and Class VIII, which represent the lands that
are not arable, cannot even be used as grassland or forest areas but support only wildlife
development or can be used as resting area or national park by human. Characteristics of each
class are summarized in Table IV.1 (Former Ministry of Agricultural and Rural Services, July 2008).
        The Land Use Capabilities of the soils corresponding to the WWTP area is agricultural
lands not suitable for soil cultivation as Class V. Map of great soil groups and land use capability
classes for the project area is represented in Figure IV.1.
Table IV.1 Agricultural Potentials Represented by Different Land Use Capability Classes and Their Characteristics
                Agricultural
 Class                         Definition of Land Use Capability
                Potential
                               Class I lands are; flat or near flat, deep, fertile and easily cultivated so that the conventional
                               agricultural methods can be applied; potential for water and soil erosion are minimal; have
                               good drainage; are not prone to flood damage exposure; suitable for hoe plants and other
 Class I
                               intensively grown crops; Class I irrigated lands with low precipitation rates have slope values
                               less than 1% slope, loamy structure, good water holding capacity and medium level
                               permeability.
                               Class II lands are decent lands that can only be processed after taking some special
                               precautions. Their difference from Class I lands are one or more of the limiting factors such
 Class II
                Agricultural   as slight slope, moderate exposure to erosion, moderately thick soil, exposure to occasional
                lands          moderate floods and a moderate level of moisture that can easily be isolated.
                suitable for   Class III lands are moderately good lands for hoe plants which can generate solid income
                agricultural   provided they are utilized with a good cropping system and proper agricultural methods.
 Class III      soil           Moderate slope, increased erosion sensitivity, excessive moisture, exposed soil, presence of
                cultivation    stones, having a lot of sand and/or gravel, low water holding capacity and low yield are
                               properties of this type of land.
                               Class IV lands can be constantly utilized as meadows. Field crops can also be occasionally
                               grown. High levels of slope, bad soil characteristics, erosion and climate are the factors
                               limiting agricultural activities on these lands. Soils with low slopes and poor drainage are
 Class IV                      also classified as Class IV lands. These soils are not subject to erosion, but they are
                               unsuitable for growing many agricultural products as they have a low yield and a tendency to
                               suddenly dry up in the spring. In semi-arid regions, cropping systems incorporating legumes
                               are generally not possible due to climate.
                Agricultural   Class V lands are reserved for long-life plantations such as meadows and forests as they
 Class V        lands not      generally are unsuitable for cultivated plants. A few factors such as stony structure and
                suitable for   sogginess hinder cultivation here. The land is flat or near-flat. It is not subject to an
         In bad drainage areas, also Hydromorphic Alluvial Soils have been distinguished in
mapping studies of Turkey. These soils are not suitable for agriculture in their current form. Some
of these soils have surface or near surface, groundwater for most of the year. In some soils, in wet
cool seasons, the water is close to the surface, but in late summer, it drops below 1m for a short
time. Some of the soils are exposed to floods. Topography is flat or concave. Surface drainage and
internal drainage are very bad or there is no drainage. Therefore, especially the lower levers are
wet. The rising and lowering of the groundwater causes successive oxidation and reduction in the
part of the soil above it. The result is bluish-gray reduction and reddish oxidation (oxidation, rust)
spots. Although the depth is high in these soils, the reduced floors limit the root zone (Former
Ministry of Agricultural and Rural Services, July 2008).
        Erosion levels of the project area and its vicinity is given in Figure IV.2. According to the
erosion map, Project area which includes the WWTP, the sewerage network, discharge line and
pumping stations is affected with moderate to low level of erosion. Factors such as structure of soil,
bareness of its surface, slope of the land and wrong cultivation of the soil are causes that increase
erosion risk of the soil. Although at Mugla province forest areas are not confronted with destructive
erosion danger due to effects of geographic conditions, measures taken for erosion control are
continued.
Figure IV.3 Photos from the WWTP Site and Soil Sampling
         The soil sampling and analysis study provides insight on existing soil quality in the WWTP
site. Soil sample locations 1 and 2 correspond to expansion area and sludge treatment units,
respectively. These locations are selected in order to provide baseline conditions regarding to 1 st
and 2nd stage areas of WWTP. Addition to that, soil sample location 2 is also selected to observe
any possible sludge related contamination. Although both samples were taken from the WWTP
site, the concentrations of some parameters significantly differ from each other, such as chromium,
nickel and TPH.
        Chromium levels in uncontaminated soil vary in between 2 and 60 mg/kg and soils with
chromium levels up to 100 mg/kg are considered as appropriate for agricultural activities (Seven
v.d., 2018). Therefore, the chromium concentration observed in the sampling location-1 and its
comparison with the concentration observed in the second sampling location indicate a possible
contamination in the location-1. Nickel levels in soils vary widely depending on local geology and
anthropogenic inputs, but concentrations typically range between 4 and 80 ppm (Seven v.d., 2018).
In USA, the most commonly used soil cleanup standard for TPH is 100 mg/kg (Michelsen, 1993).
Therefore, the assessment made by evaluating chromium levels is also valid when considering
TPH and nickel levels in the WWTP site.
         In addition, during the soil sampling study carried out in the site, visually no pollution
source that could cause permanent soil pollution was observed. Therefore, possible soil pollution at
the site might have resulted from a one-time source.
Geology
        In Mugla Province, oldest lithologies are from the Precambrian time, which are gneiss,
micaschist, fine grained schist and quartzite, starting from the mountainous part north of Yatagan
and Milas Districts and spreading further north. Paleozoic age rocks; cemented sandstones,
marbles and schists cover these Precambrian units from the south. Marbles and crystalline
limestones, clayey schists, sandstones, conglomerates, siliceous schists and phyllites can be
observed in the Yatağan - Mugla trough are also Paleozoic aged.
      Main units that can be observed in Mugla and its vicinity are; Menderes Massif, Lycia
Nappes and Beydaglari autochthon. Menderes Massif starts with Precambrian gneiss, and covered
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                      Chapter IV - Pg. 65/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
with micaschits and followed by metamorphics such as metaquartzite, phyllite, recrystallized
limestones. Towards to top, molasses and flysch sedimentary rocks are deposited. The Lycian
Nappes include nappe slices sediments from various times, and ophiolite and ophiolitic melange
slices formed in the Late Cretaceous period. Beydaglari autochthon is made up of various
formations. Carbonate sequence of the autochthon starts with rudist reef deposits and semi-pelagic
massive limestones with planktonic foraminifera fossils deposited on top of it. Later under
transgressive conditions, units with abundant plantonic foraminifera deposited in the basin.
         The Mugla Region has undergone intense tectonic activites in Cenozoic and resulted with
uplift and subsidence which exposed Precambrian and Paleozoic units. Many lakes formed due to
this tectonism and some of them filled with Quaternary alluvium. General Geology Map of project
site that was studied is presented in Figure IV.5.
          Quaternary alluvium sediments cover the entire study area. The WWTP area was used as
the filling area of the excavation material that excavated during the construction of a thermal power
plant. It was determined that the filling thickness varies in the between 3.60 and 8.00 m, depending
on the previous topography of the site and time.
        Alluvium is made up of lenticular layers of clay, sand and small gravel materials in different
proportions. Silt and fine sand dominated lithologies are gray, dark gray due to organic residues,
and they are intercalated laterally and vertically. However, due to the precipitation conditions, silt
and sandy pebbly materials under the filling (excavation material) vary between 1.80 - 4.60 m
thicknesses.
Natural Hazards
        As a result, no risks related to natural disasters including landslide, rock fall, avalanche,
etc. are identified at the Project Area which covers both the WWTP and the sewerage network to
be considered as part of "Law on Aids Implemented with Mitigations taken for Natural Disasters on
Public Life" numbered 7269.
Seismicity
        According to Map of Earthquake Regions of Turkey issued by Official gazette No. 30364
dated 18.03.2018, ground acceleration of Mugla province, including Milas District is classified as
between 0.2-0.3 g. Therefore, earthquake risk has to be taken into consideration in the design of
the WWTP. Earthquake Regions Map is given in Figure IV.7 and Active Fault Map of Turkey is
given in Figure IV.8.
        Aegean Sea Region is tectonically active, earthquakes with various magnitudes can
happen Mugla Province, and its vicinity, thus, earthquake risk must be taken to consideration for
the design of the WWTP.
       Turkish Earthquake Zones Map was prepared by the T.R. Ministry of Public Works and
Settlement and came into effect with Council of Ministers’ Decision no 96/8109 dated 18.4.1986.
According to this map, Mugla region is in 1st degree earthquake region.
        According to Council of Ministers decision dated March 18, 2018, published in the Official
Gazette No. 30364 is, "Turkey Earthquake Building Regulation" which entered into force on
January 1, 2019, construction works are going to comply with the principles of the regulation
rigorously.
        Within scope of Wastewater Treatment Plant Project, GAB Engineering and Consultancy
Company (“GAB”) conducted field work, drilling and laboratory studies in order to collect
geological-geotechnical data and their evaluations.
                                                    Coordinates (ITRF-96)
 Drilling Well/Trial Pit No.      Depth (m)                                   Groundwater Depth (m)
                                                      X              Y
 DW-1                                30.45        581957,65      4100648,67           2.67
 DW-2                                15.00        581958,21      4100695,87           3.15
 DW-3                                15.00        581911,85      4100647,65           3.70
 DW-4                                15.00        581898,43      4100680,44           4.00
 DW-5                                15.00        581892,11      4100746,22           3.70
 DW-6                                15.00        581942,65      4100754,88           3.60
 TP-1                                 2.00        581941,88      4100721,95             -
 TP-2                                 3.00        581965,14      4100660,84             -
 TP-3                                 3.00        581904,86      4100711,96             -
        The drilling wells showed that groundwater levels are ranging from 2.67 to 4.00 m in the
WWTP area. Accordingly, the groundwater-related problems are expected in cases where the
foundation depth of the WWTP units to be built exceeds 2.60 m It should also be noted that
depending on seasonal conditions and precipitation, the groundwater level may change. The
locations of the boreholes are presented in Figure IV.9.
         In addition, during the soil sampling study carried out in the site, visually no pollution
source that could cause permanent soil pollution was observed. Therefore, possible soil pollution at
the site might have resulted from a one-time source. Within this context, no significant impact on
groundwater is foreseen due to a possible soil contamination.
        Project area is located in West Mediterranean Water Basin. West Mediterranean Water
Basin incudes Gokova Bay and Akdaglar mountains of Mugla province. The catchment area of the
basin is approximately 21,000 km 2. There are 322,000 hectares of plain in the basin. 211,500
hectares of the plains are irrigable. The waters of the Western Mediterranean Basin are discharged
to the Mediterranean with Dalaman and Esen Creek. These creeks are also two most important
streams of the province.
        Main water courses in the Mugla are Kargicik Creek Namnam Creek, Kargi Creek,
Karaculha Creek, Kocadere Creek, Saricay Creek. The water potentials of these water courses are
given in Table IV.4 and maps of the hydrology of the Project area and its vicinity is shown in Figure
IV.10.
       Natural lakes in Mugla Province can be listed as Bafa Lake, Koycegiz Lake, Sulungur
Lake, and Kocagol Lake. The areas of this main lakes located in the Mugla are given in Table IV.5.
                                                                                            Flow Rate
                                    Total Length          Length in Province
 Name                                                                                        (m3/sec)
                                        (km)                Borders (km)
                                                                               Min            Max        Average
 Dalaman Creek                            190                    65            9.51           1050          43
 Kargıcık Creek                            17                    17            0.35           22.8         1.33
 Esen Creek                               128                    80            1.65            271         14.9
 Namnam Creek                              33                    33            0.014           556         9.65
 Dipsiz Creek                               -                     -            0.114            -         4.707
 Sancay                                     -                     -              -             220         1.32
 Kartaculha River                           -                     -            0.001           2.2        0.071
 Batis River                                -                     -              -            35.4        0.189
Source: West Mediterranean Basin Protection Action Plan
        Information on ponds and dams of Mugla province are presented in Table IV.6 and
locations are shown in Figure IV.11.
         The Oren WWTP that will be constructed within the scope of the Project will discharge its
effluent through 1,542 meter discharge line to Hanay Creek which is located at the western part of
the WWTP and reaching directly to the sea. The creek bed is made of concrete. While the creek
current is approximately 5 meters wide at the upstream of the discharge point, at the downstream it
reaches up to 45 meters width due to cooling water that is being discharged from Kemerköy
Thermal Power Plant. The photos of Hanay Creek are provided in Figure IV.12Hata! Başvuru
kaynağı bulunamadı..
 Kemerköy Thermal Power Plant Cooling Water Discharge Located at the Downstream of the Planned Discharge
                                                Location
         To constitute a baseline inventory and to determine the existing quality of the receiving
environment a sampling study was conducted on December 14 th, 2021. In the scope of the study,
total of three surface water samples were taken from the upstream (upstream surface water
sampling location) and downstream (downstream surface water sampling location) of the planned
discharge location, and downstream of the Kemerköy Thermal Power Plant where cooling water is
being discharged (downstream surface water sampling location-2). Sampling locations are
presented on a map given in Figure IV.13. Laboratory reports are provided in Annex-2 of this
report.
        The measurement and analysis results of Hanay Creek are presented in Table IV.7
together with the water quality classification criteria stipulated in the Water Pollution Control
Regulation and Surface Water Quality Regulation (indicated with “*" sign).
        As seen from the Table IV.7, upstream and downstream of the planned discharge location
of the Hanay Creek is classified as Class IV in terms of total coliform. Class III due to pH and total
phosphorus parameters. Other measured parameters are mostly belongs to Class I and Class II.
Although total coliform levels are high, low E.coli and fecal coliform levels indicate that high total
coliform levels might be caused by entry of soil or organic matter into the water. Therefore, it can
be concluded that there is no reach or continuous direct discharge of sewerage to Hanay Creek.
        On the other hand, downstream of the Kemerköy Thermal Power Plant where cooling
water is being discharged is classified as Class IV in terms of TDS and conductivity. Other
measured parameters are belongs to Class I and Class II. Within this regard, high levels of TDS
and conductivity might resulted from wastewaters originated from fossil fuel extraction activities that
enter the surface water.
                                                     Upstream of the     Downstream of the      Downstream of the   Water Pollution Control Regulation and Surface Water Quality
                                                    Planned Discharge    Planned Discharge      Kemerköy Thermal                             Regulation
 Parameters                           Unit               Location             Location            Power Plant                          Water Quality Classes
                                                        (X: 580469,          (X: 580505,           (X: 580644,
                                                                                                                         I               II              III              IV
                                                       Y: 4099008)          Y: 4098924)           Y: 4098750)
 Temperature                           °C                 15.3                  15.0                  15.7               25             25              30               >30
 pH                                     -                 8.58                  8.55                  8.28            6.5-8.5         6.5-8.5         6.0-9.0         <6.0 - >9.0
 Dissolved Oxygen                     mg/L                9.29                  9.31                  9.16               8               6               3                <3
 Ammonium                        mg   NH4+-N   /L         <0.02                <0.02                  <0.02             0.2              1               2                >2
 Nitrite                         mg NO2--N /L             0.01                 0.0090                 0.004            0.002           0.01            0.05             >0.05
 Nitrate                         mg NO3--N /L             0.274                0.306                  <0.1               5              10              20               >20
 TP                                   mg/L                0.24                  0.18                  0.10              0.02           0.16            0.65             >0.65
 TDS                                  mg/L                 322                  601                  37859              500            1500            5000             >5000
 COD                                  mg/L                18.53                18.04                  10.61              25             50              70               >70
 BOD                                  mg/L                4.80                  6.00                  3.16               4               8              20               >20
 TKN                                  mg/L                0.92                  0.62                  0.76              0.5             1.5              5                >5
 Fecal Coliform                  CFU/100 mL                37                    52                    0                 10             200            2000             >2000
 Total Coliform                  CFU/100 mL              >100000              >100000                 210               100            20000          100000           >100000
 Escherichia coli                CFU/100 mL                 0                    0                     0                 -               -               -                 -
 TSS                                  mg/L                 613                  144                    42                -               -               -                 -
 Turbidity                            NTU                  249                 80.90                  4.11               -               -               -                 -
 Salinity                              ‰                   0.3                  0.54                   38                -               -               -                 -
 Conductivity*                        µS/cm                628                  1098                 56300             <400            1000            3000             >3000
         In order to identify and evaluate the protected areas within the Project Area and its
immediate vicinity, desktop studies and literature researches were carried out by using the
databases of the relevant institutions within the scope of the Project. For this purpose, sensitive
area list available in Annex 5 of the EIA Regulation was used as reference. This list covers areas
that need to be protected in accordance with international conventions that Turkey is contracting
party and nationally declared protected areas. As can be seen from the evaluations in the following
paragraphs, the nearest protected area is Gokova Special Protected Environmental Area, located
about 1.1 km away from the site.
         National Parks, Natural Parks, Natural Monuments, Nature Reserve Areas, Wildlife
Protection Areas, Wild Animal Raising Areas, Cultural Assets, Natural Assets, Protected Areas,
Areas under Protection in accordance with Bosporus Law, Biogenetic Reserve Sites, Biosphere
Reserves, Special Environmental Protection Areas and Protected Areas related to Drinking and
Utility Water Reserves are not located within Project Site.
         Utilized main data sources within the scope of the desktop studies, but not limited to, are
listed below:
           Database of Ministry of Agricultural and Forestry (former Ministry of Forestry and Water
            Affairs) (http://geodata.ormansu.gov.tr)
           Database of Ministry of Agricultural and Forestry, General Directorate of Nature
            Conservation and National Parks (http://www.milliparklar.gov.tr)
           Database of Ministry of Culture and Tourism, General Directorate of Cultural Heritage
            and Museums (http://kve.ulakbim.gov.tr)
           Map of Prohibited and Open Hunting Areas in Mugla Province for years 2018-2019
        Areas required to be protected in accordance with the legislation of the country defined
under Annex 5 (Sensitive Regions) of the EIA Regulation are listed in the following items and the
evaluations related to the indicated areas are presented therein.
         National Parks, Nature Parks, Nature Monuments and Nature Conservation Areas defined
in Article 2 and 3 of the National Parks Law
      There are 11 Natural Parks in Mugla Province. The closest one to the Project Area is
Cubucak Nature Park which is located 26.7 km southeast of the Project Area (covering both the
WWTP and the sewerage network).
      There are 2 National Parks in Mugla Province. The closest one to the Project Area is
Marmaris National Park and it is located 27.9 km southeast of the Project Area.
        Sirtlandagi Aleppo Pine Nature Conservation Area is located 27.0 km northwest of the
Project Area, at the Mugla-Milas Province Border.
     There are 5 nature monuments in Mugla Province and the closest one is Olive Tree Nature
Monument and it is located 41.5 kilometers west of the Project Area.
        The closest Biogenetic Reserve Area (Calabrian pine) is located 9.1 km away from the
Project area. The closest Seed Stand Type (Calabrian pine) is 9 km west of the Project area.
        Map of prohibited and open hunting areas for years 2019-2020, prepared by Ministry of
Agricultural and Forestry, General Directorate of Nature Conservation and National Parks, is
presented in Figure IV.16. As could be seen from the map given in Figure IV.14, the closets wildlife
development area is Mugla-Koycegiz WDA that is located about 39.3 km southeast of the Project
Area. There are various hunting areas in the Province as well as prohibited hunting areas (see
Figure IV.16).
         Areas defined as Cultural Property, Natural Property, Protected Site and Protected Area
according to 2863 numbered Law on Protection of Cultural and Natural Properties dated July 21
1983, Article 3, Paragraph 1, Clause (a) (Definitions); Sub-clauses 1, 2, 3 and 5; and areas
identified and registered in the same Law and amendments
Aquaculture Production and Breeding Sites within the scope of Aquaculture Law
        Dalyan channels which is in Koycegiz district is completely prohibited hunting inland waters
in Mugla province.
       Closest natural lake to the Project Area is Metruk Tuzlası Wetland, which is located
26.7 km northwest of the Project Area. The closest dam in operation to the Project Area is
Mumcular Dam, which is located about 17.9 km northwest of the Project Area.
         According to the 7th Article of Air Quality Assessment and Management Regulation, zones
and sub-zones for air quality identification are listed in Annex-1 of Memorandum 2013/37. With the
relevant circular, Turkey is divided into various regions and sub-regions. With this distinction, the
Ministry tried to determine the pollution profile of the provinces. The list in Annex-III of the circular is
divided into two groups according to the pollution profile of provinces substances: "high pollution
potential cities" and "low pollution potential cities". Pollution profiles of provinces were carried out
within the 2012-2013 winter season air quality data and air quality bulletins received from air quality
monitoring stations connected to the national air quality monitoring network. According to this, the
Mugla Province is in the list of "high pollution potential".
        Areas identified and declared as Special Environmental Protection Areas by the Cabinet of
Ministers in accordance with the 9th Article of Environment Law
        There are 5 special environmental protection areas in Mugla Province. Gokova Special
Environmental Protection Areas are the closest ones which are located about 1.1 km southeast of
the Project Area.
       The Project Area is not located in pasture land which is subjected to 4342 numbered
Pasture Law.
        There are 7 wetland areas in Mugla Province. These are; Koyceyiz Lake, Bafa Lake,
Dalyan Wetland, Dalyan Wetland Ecosystem, Girdev Lake, Golkoy Lake, Gulluk Delta. There are
not any RAMSAR areas in Mugla Province.
        In addition to presented information above, the areas listed below (also listed in Annex 5 of
the EIA Regulation) do not exist in the Project Area:
             Areas in accordance with the 17th, 18th, 19th and 20th Articles in the Water Pollution
              Control Regulation
             Protected areas within the scope of Bosporus Law
             Forest Areas within the scope of Forest Law
             Areas subject to construction ban in accordance with the Coastal Law
             Areas designated in accordance with the Law on the Vaccination of Pesticides and
              Improvement of Olive Cultivation
             Areas subjected to construction ban and areas of which their present characteristics
              should be protected according to Approved Environment Plans (areas of which their
              natural characteristics should be protected, biogenetic reserve areas, geothermal
              areas, etc.)
             Agricultural Areas: Agricultural development areas, irrigated areas, potentially irrigated
              areas, areas with land use capability class of I, II, III and IV, rainfed agricultural lands
              classified as I and II and specific product plantations areas
             Wetlands: Natural or artificial, permanently or temporarily, standing water or flowing,
              freshwater, hard or salt water, all the wetlands have importance for the organisms
              especially for aquatic birds, sea depth range below six meters during the low tide,
              swamp, reeds and turbaries and ecologically wetlands on their coastal sides
             Lakes, rivers, groundwater operation sites
             Areas important for endemic species that is endangered or potentially endangered or
              important for scientific researches, biosphere reserve, biotopes, biogenetic reserve
              areas, areas have unique characteristics for geologic and geomorphologic formations
        In order to identify the cultural assets and protection areas in the vicinity of the Project
Area, the database of cultural heritage of Turkey (http://kve.ulakbim.gov.tr) has been queried. As
the Project Area is located about 39.6 km southwest of Mugla city center, cultural assets have been
searched in district basis (i.e. by considering Milas district of Mugla Province). The identified
immovable cultural assets that are vicinity of the project area are listed in Table IV.8.
There are no areas within the context of below mentioned protected/restricted areas;
             Mediterranean Monk Seal Living and Reproduction Areas, I. and II. Conservation
              Zones defined in Important Sea Turtle Reproduction Areas from the protected areas in
              accordance with the Convention for the Protection of the Wildlife and Habitats of
              Europe (BERN Convention)
             Areas protected under the Convention on the Protection of the Mediterranean from
              Pollution (Barcelona Convention)
             Areas designated as Special Protection Area in Turkey in accordance with the Protocol
              on the Protection of Special Protection Areas in the Mediterranean
             Fields on the list of 100 Coastal Historic Sites with Joint Prevention in the
              Mediterranean published by the selected United Nations Environment Program in
              accordance with the Geneva Declaration
             The coastal areas that are the living and feeding environment of Native Species of
              Hazardous Dangers to the Mediterranean included in 17 th Article of the Geneva
              Declaration
             Cultural, historical and natural areas that are protected by the Ministry of Culture under
              Cultural Heritage and Natural Heritage status according to the 1st and 2nd articles of
              the Convention for the Protection of the World's Cultural and Natural Heritage
             Protected areas in accordance with the Convention for the Protection of Wetlands with
              International Importance as Particularly Water Birds Living Environment (RAMSAR
              Convention)
             European Landscape Contract
        The region has a climate characteristic composed of the synthesis of Aegean and
Mediterranean climates. It is warm and rainy in winter, and hot and dry in summer and has micro-
climate area features in peninsula, which is also valid for Oren. There is hardly any moisture in the
summer months. In the winter months, the humidity rate is quite low. It is hot and dry in the summer
months, quite warm and rainy in the winter months.
        The primary factors affecting the air quality are the natural factors such as topography,
meteorology, natural vegetation, and the human factors such as population increase, unplanned
urbanization and industrialization. Domestic heating and industry take place near the top in ranking
of the basic factors affecting the air quality in Mugla province.
        For the ESIA studies, comparing to the Milas meteorological observation station, which is
located inland and around 40 km away from the sea and consequently its direct effects, the
Marmaris meteorological observation station is considered to best represent the Project Area. The
data presented in the following subsections are retrieved from the State Meteorology Services
Marmaris Meteorological Observation Station.
Temperature Distribution
        Marmaris Meteorology Station records show that annual mean temperature is 19.1 °C. The
highest temperature is recorded as 45ºC in August. The lowest temperature is recorded as –4.5ºC
in February. The graphical and tabular representation of the average, maximum, minimum
temperature records measured in this station are given in Figure IV.17 and Table IV.9, respectively
Precipitation Distribution
        Marmaris Meteorology Station records show that annual average total precipitation is 59,8
mm. Total precipitation is maximum in September with 232 mm and minimum in July with 5 mm.
Average monthly precipitation and daily maximum precipitation amounts are given graphically in
Figure IV.18 and tabulated in Table IV.10.
Humidity Distribution
        Marmaris Meteorology Station records show that average annual humidity is 60.5%.
Minimum monthly relative humidity is recorded in July (49.8%) and maximum relative humidity is
recorded in December (67.6%). The monthly average and minimum relative humidity values are
given graphically in Figure IV.19 and in tabular format in Table IV.11.
Pressure Distribution
        Annual mean local pressure measured in Marmaris Meteorology Station is 1010.4 hPa.
During the whole observation period, minimum pressure is recorded as 979.10 hPa in January and
maximum pressure is recorded as 1028,90 hPa in February. Monthly average, maximum and
minimum pressure values recorded in the station are provided in Figure IV.20 and Table IV.12.
Months Average Temperature (hPa) Maximum Pressure (hPa) Minimum Pressure (hPa)
          Marmaris Meteorology Station records show that the number of annual average snowy
days is 2.8 and annual average number of days with snow blanket is 0.7. The snow cover depth is
recorded only on January as 3 cm. Monthly distribution of average foggy, snowy, snow covered,
hail, frosty and stormy days are given in Table IV.13.
Table IV.13 Monthly Average Foggy, Snowy, Snow Covered, Hail, Frosty and Stormy Days Distribution
         The annual and seasonal distribution of wind blow numbers and wind speeds recorded in
Marmaris Meteorological Station are graphically represented in Figure IV.21, Figure IV.22 and
Figure IV.23. According to annual wind blow numbers, 1st dominant wind direction is NNE (north-
northeast). 2nd dominant wind direction is N (north). 3rd dominant wind direction is NE (northeast)
and 4th dominant wind direction is SSE (south-southeast).
Figure IV.21 Annual Wind Diagram of Wind Blow Numbers and Average Wind Speeds
       The annual average wind speed is 3.2 m/sec and monthly average wind speeds are
presented for each month in Table IV.14.
Months                Jan.    Feb.     Mar.   Apr.        May    June    July     Aug.       Sept.    Oct.    Nov.    Dec.
Average Wind
                       3.6     3.8      3.4     3          2.7    3.1      3.6         3.2    2.8      2.6       3      3.6
Speed (m/sec)
        Marmaris Meteorology Stations records show that the direction of the highest wind speed is
south (S) with 41.7 m/sec. The number of annual average stormy days is 2.8 and number of annual
average strong windy days is 8. Maximum wind speeds, directions and average stormy and strong
windy day numbers are provided in Table IV.15.
Table IV.15 Maximum Wind Speeds and Directions, Average Numbers of Stormy and Windy Days (1960-2015)
        The operation noise limit values defined in the RAMEN Annex VII Table 4 are presented in
Table IV.16.
       For construction activities noise limit values are defined in Table 5 Appendix VII of RAMEN
and presented in Table IV.17.
WBG Standards
        Noise limit levels are described under, WBG Environmental, Health and Safety (EHS)
Guidelines, General EHS Guidelines: Environmental Noise. The noise limit values are based on
World Health Organization Guidelines for Community Noise. Noise levels defined by WBG EHS
Guidelines are presented in Table IV.18. WBG EHS Guidelines requires that noise impacts should
not exceed the levels presented in Table IV.21, or result in a maximum increase in background
noise levels of 3 dB at the nearest receptor location off-site.
         Noise during the construction phase will be mainly generated due to the activities of
construction machinery and equipment. To determine the impact significance, background noise
levels should be known. Therefore, a noise level measurement study was conducted to determine
background levels around the WWTP site. Since the sewerage system component of the Project
will be constructed in the city centre, where there are numerous noise sources, no measurement
was conducted.
        Two locations were selected as sensitive receptors and these are presented on Figure
IV.24 below. Noise Measurement Location-1 (NML-1) is the nearest sensitive receptor to the
WWTP site, which is Sitki Kocman University Fisheries Research and Development Centre. NML-2
represents background noise levels at summer housings located at 180 m east of the WWTP site.
The background noise measurements were carried out at these points on July 6th and 7th, 2020 by
ENCON Laboratory and the results are presented in Table IV.19. Assessment of noise impacts of
the Project is provided in Section V.4.5.
                                                                                Measurement Results
                                     Measurement
                                                                                    (Leq) (dBA)
                                      Coordinates
 Measurement       Type of the      (UTMED50-Z35)                                                     WBG General EHS
                                                                 RAMEN Periods
 Points             Receptor                                                                          Guideline Periods
                                                       Daytime       Evening         Night       Daytime       Nighttime
                                       X     Y
                                                     (07.00-19.00) (19.00-23.00) (23.00-07.00) (07.00-22.00) (22.00-07.00)
 NML-1*             Educational     581954 4099159       53.8            53.1          50.2           53.7        50.6
 NML-2              Residential     582120 4099020       54.0            47.7          47.6           53.1        47.6
         As it is seen from Table IV.19, background noise levels were very close to each other at
NML-1 and NML-2 during the periods determined by the Regulation on the Assessment and
Management of Environmental Noise (RAMEN) and WBG General EHS Guidelines: Environmental
Noise. However, nighttime measurements are already above the limits that are defined in WBG
General EHS Guidelines: Environmental Noise. The high measurement results might be related
with traffic. Based on these measurement results, background noise levels should not be exceeded
more than 3 dB at the nearest receptor location off-site during the construction and operation
phases of the Project.
        In Mugla, there are two air quality monitoring stations that belong to MoEUCC. One of
these stations is located at Yatagan, while the other one is located at the Mugla city centre. There
is no monitoring station in Oren and considering its population density and industries, it is
anticipated that there should not be much pollution stress on air environment in Oren. However, it
should be noted that SOx, NOx and CO2 emissions of Kemerköy Thermal Power Plant located in
Oren contributes to air pollution in the region.
        Mugla’s air pollution data taken from Musluhittin monitoring station, which only monitors
PM10 and SO2 parameters, is presented in the Table IV.20 below. The data belongs to period
between January 2019 and July 2020. As seen from the table, while daily average PM10
concentration is a little higher than the regulatory limit value, SO 2 concentration is in compliance
with the Regulation on the Assessment and Management of Air Quality limit value.
                                                          PM10                                      SO2
Measurement Location                          Daily Average      Limit Value       Hourly Average         Limit Value
                                                 (µg/m³)           (µg/m³)            (µg/m³)               (µg/m³)
         There is no active air quality monitoring stations in the local level. Therefore, to constitute a
baseline inventory and to determine air quality in the Project area; 24-hour PM10 and PM2.5
measurements were conducted at the nearest sensitive receptor, which is 50 m to the WWTP site.
The measurement location is same with the NML-1 presented in Figure IV.24. The measurement
results are presented in Table IV.21.
                                                                               Result (µg/Nm3)
 Coordinates of the              Type of the
 Measurement Location         Sensitive Receptor                 PM10                                 PM2.5
         According to the Industrial Air Pollution Control Regulation, PM10 values should not exceed
50 µg /Nm³ more than 35 times in a year. On the other hand, according to WBG General EHS
Guidelines: Air Emissions and Ambient Air Quality PM10 and PM2.5 values should not exceed 50 µg
/Nm³ and 25 µg /Nm³, respectively. Therefore, PM10 and PM2.5 baseline measurement results
satisfy both national and WBG General EHS Guidelines ambient air quality limit values.
          For this Report, biological environment was investigated which included habitat structures
of the Project area, protected areas and key biodiversity areas (KBA). For this purpose, both
desktop studies and field survey were carried out. The related literature and previous studies have
been reviewed and the general biological characteristics of the region have been revealed. Also a
field visit was conducted with an expert biologist on July 7th, 2020.
       The project area is located within the borders of Oren neighbourhood of Milas district in
Mugla Province. As mentioned in the previous sections, the project consists of two components,
the sewerage line and the WWTP. Both components have heights ranging from 0 to 10 m altitudes
above sea level.
        The Mediterranean climate is dominant in the project area which located in the Aegean
region. The average annual temperature is around 20°C. In July and August, this temperature
increases to 32 -44°C. Although the temperature does not fall below 10°C in winter, rainy and warm
weather is dominant in winter.
        Since the project area is located in the Aegean region, it is located entirely in the
Mediterranean Plant Geography region and it has the characteristics of the Mediterranean climate.
However, since the regions where the activities in the project area are located close to the
settlements, the anthropogenic effect is quite high.
         The sewerage network covers a very large area within the Oren neighbourhood. However,
due to the nature of the Project, the sewerage network will be constructed in residential areas while
sewerage network and discharge line will be installed mainly on roadsides. Therefore, the sewer
lines and discharge line will be built on areas that do not have high value in terms of biological
diversity.
         The WWTP part of the project covers an area of 8,278.11 m2. The area where WWTP will
be built is located 400 m from the sea. The closest settlement to the planned WWTP is 175 m
away. The WWTP is generally surrounded by distributed trees and scrubs, herbaceous species
and riparian vegetation. Also, there is a dry dock construction site on the west of the project area.
For this reason, rubbles of construction and uncontrolled site entry of work machines has been
partially destroyed the area. Some photographs of the WWTP area are given in Figure IV.25.
         Ecology and Biodiversity part of the Project is guided by the requirements of the World
Bank’s Operational Policy (OP) 4.04 in order to manage environmental risks and impacts on
ecology and biodiversity. (OP) 4.04 aims that the protection of critical natural habitats and to be
taken mitigation measure to minimizing habitat loss. According to the (OP) 4.04 this issue is
explained as “…If the environmental assessment indicates that a project would significantly convert
or degrade natural habitats, the project includes mitigation measures acceptable to the Bank. Such
mitigation measures include, as appropriate, minimizing habitat loss (e.g., strategic habitat
retention and post-development restoration) and establishing and maintaining an ecologically
similar protected area…”. As appropriate, the project will take the necessary measures and
         In the line with the (OP) 4.04, assessments of the baseline conditions and determined
significance criteria for impacts assessments were detailed according to IFC Performance
Standards 6 (PS6). IFC PS6 covers areas of biodiversity conservation, ecosystem services and
sustainable management of living resources, which are all fundamental to achieve sustainable
development. The objectives of PS6 are outlined as follows:
         The requirements of PS6 are applied to projects: (i) located in modified, natural, and critical
habitats; (ii) that potentially impact on or are dependent on ecosystem services over which the
client has direct management control or significant influence; or (iii) that include the production of
living natural resources (e.g. agriculture, animal husbandry, fisheries and forestry) based on the
risks and impacts identification process.
Bern Convention
        Bern Convention was put forward in 1982 in order to protect the European wildlife and
natural habitats. Species to be protected according to the Bern Convention are listed in four
appendices, which are presented in Table IV.22 with their explanations:
        Annex             Explanation
            I             Strictly protected flora species
            II            Strictly protected fauna species
            III           Protected fauna species
            IV            Prohibited means and methods of killing, capture and other forms of exploitation
         CITES stands for the Convention on International Trade in Endangered Species of Wild
Flora and Fauna. It is an international agreement that has been ratified by governments of 164
states (including Turkey), whose aim is to ensure that international trade in specimens of wild
animals and plants does not threaten their survival. The principles of CITES are based on
sustainability of the trade in order to safeguard ecological resources (live animals and plants, vast
array of wildlife products derived from them, including food products, exotic leather goods, etc.).
CITES was signed in 1973 and entered in force on July 1, 1975. Turkey ratified the Convention in
1996. Categories and species included in CITES are listed in three different appendices based on
their protection statuses. These appendices and their explanations are given in Table IV.23.
      Appendix          Explanation
                        covers the species, which are under the threat of extinction. Trade in the specimens of these
           I
                        species is not allowed except extraordinary circumstances
                        includes species, which are not threatened with extinction, but trade in specimens is restricted
          II
                        in order to prevent utilization incompatible with their survival
                        for which other parties of CITES is applied for assistance in controlling trade and which are
          III
                        conserved at least in one country.
         The International Union for Conservation of Nature (IUCN) publishes its Red List of
Threatened Species, which intends to draw attention to species whose populations are at risk or
under threat. The IUCN places a species on the Red List only after studying its population and the
reasons for its decline. Some countries pay greater attention to IUCN-listed species than Bern-
listed species, since the Red List relies on more research. The 1994 (ver.2.3) and 2001 (ver.3.1)
categories and criteria of the IUCN Red List are presented below in Table IV.24. The Red List
Categories and Criteria had been re-formed through evaluating more open and easier to use
systems. As a result the IUCN Commission made revisions in February 2000, and the new set of
categories and criteria were published in 2001.
 IUCN Red List Categories and Criteria                      IUCN Red List Categories and Criteria
 1994 (ver. 2.3)                                            2012 (ver. 4.0)
    EX       Extinct                                          EX        Extinct
   EW        Extinct in the Wild                              EW        Extinct in the Wild
   CR        Critically Endangered                            CR        Critically Endangered
    EN       Endangered                                       EN        Endangered
    VU       Vulnerable                                       VU        Vulnerable
    LR       Lower Risk
             cd : conservation dependent                       NT       Near Threatened
             nt : near threatened                              LC       Least Concern
             lc : least concern
   DD        Data Deficient                                    DD       Data Deficient
    NE       Not Evaluated                                     NE       Not Evaluated
       This reference prepared by Prof. Dr. Ali Demirsoy and published by the former Ministry of
Environment and Forestry lists the threat/conservation statuses for vertebrates in Turkey as
presented in Table IV.25.
 Category               Definition
 Ex                     Extinct
 E                      Endangered
 R                      Rare species
 V                      Vulnerable species
 I                      Status of taxon is unknown
 K                      The category of taxon is unknown due to data deficiency
 O                      Species that are not threatened
 nt                     Widespread, abundant species that are not threatened
Kiziroglu, I. (2009). The Pocket Book for Birds of Turkiye (RDB for Birds)
        Birds of the biodiversity study area were also assessed according to national threat
categories defined in The Pocket Book of Birds of Turkey (Kiziroglu, 2009) within the categories
defined in Table IV.26.
Category A
A.1.2    (CR)      Critically endangered and breeding species in Turkey
A.2       (EN)     Endangered and breeding species in Turkey
A.3       (VU)     Vulnerable and breeding species in Turkey
A.3.1       (D)    Declining, vulnerable and breeding species in Turkey
                   Near threatened, breeding species do not face to risk now but are likely to qualify for threatened
A.4       (NT)
                   category in the near future in Turkey
A.5       (LC)     Least concern, breeding species that are widespread in Turkey
A.6      (DD)      Data deficient, breeding species on which there is deficient information in Turkey
A.7       (NE)     Not evaluated, Breeding species which have not been evaluated in Turkey
Category B
B.1.2    (CR)      Critically endangered and non-breeding species in Turkey
B.2       (EN)     Endangered and non-breeding species in Turkey
B.3       (VU)     Vulnerable and non-breeding species in Turkey
B.3.1       (D)    Declining, vulnerable and non-breeding species in Turkey
                   Near threatened, non-breeding species do not face to risk now but are likely to qualify for threatened
B.4       (NT)
                   category in the near future in Turkey
B.5       (LC)     Least Concern, non-breeding species that are widespread in Turkey
B.6      (DD)      Data deficient, non-breeding species on which there is deficient information in Turkey
B.7       (NE)     Not Evaluated, non-breeding species which have not been evaluated in Turkey
        Protected Areas and Internationally Recognized Areas within the Region of the
Project Area
        The map showing the national protected areas and internationally recognized areas in the
project area or its immediate surroundings can be shown in
        Figure IV.28. International recognized areas investigated as KBA (Key Biodiversity Area),
IBA (Important Bird Area) and AZE (the Alliance for Zero Extinction).
        Turkey’s KBAs have been identified on a national scale by Doga Dernegi (the Nature
Society of Turkey) in collaboration with the Ministry of Agriculture and Forestry (former Ministry of
Environment and Forestry), Birdlife International and Royal Society for the Protection of Birds.
       Important Bird Areas were identified by a database prepared by Birdlife International and
Royal Society for the Protection of Birds.
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                                      Chapter IV - Pg. 104/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
         The Alliance for Zero Extinction (AZE), established in 2004 and comprising 88 biodiversity
conservation NGOs, is dedicated to the identification and safeguard of all KBAs holding effectively
the entire global population of at least one Critically Endangered or Endangered species. A total of
587 AZE sites have been identified. (Brooks T M., et al.,2016) AZE members work to rebuild
populations of endangered and critically endangered species through efforts to eliminate human
threats such as commercial exploitation, disease and the introduction of invasive species.
        Effective conservation of all AZEs is by definition essential to achieve the CBD target of
preventing extinctions of known threatened species (all such sites are under threat and the loss of
any one of them in the short- to medium-term would almost certainly result in global extinction of at
least one species)
        AZEs hold ≥95% of the global population of any Critically Endangered or Endangered
species, and hence are locations at which species extinctions are imminent unless appropriately
safeguarded (i.e. protected or managed sustainably in ways consistent with the persistence of
populations of target species); 588 such sites have been identified for 919 highly threatened
vertebrate and conifer species. Terrestrial AZE sites have been identified globally for all mammals,
birds, amphibians, selected reptile clades (Testudines, Crocodylia and Iguanidae) and conifers
(Butchart, S. H. M. et al., 2012)
        One suggestion for safeguarding AZE sites is to begin by considering two levels of
protection: any protection and “targeted” protection. A second and more long-term goal can be to
work towards “targeted” protection for all AZE sites, with “targeted” defined on a case-by-case
basis centered on the threats to and ownership of each site and the AZE species’ management
needs.
           Level 1: Any protection: Any level of official protection for unprotected or partially-
            protected AZE sites. All unprotected or partially-protected AZE sites receive a basic
            level of official protection
           Level 2: Targeted protection: Protection based on threats to the sites on a case-by-
            case basis centered on the threats to and ownership of each site. Some sites are at
            risk due to specific threats, such as invasive species, trafficking, or logging. Working to
            reduce or eliminate these threats will be key to the long-term persistence of such sites.
        As can be seen on the map, the nearest national protected area to the sewerage system
part of the Project Gokova Specieal Protected Area with a distance of 1.1 km. In addition, the
Datca and Bozburun Peninsula KBA and IBA border is 20 m away from the sewerage system part
of the Project.
       Gokova Special Environmental Protection Area covers a large area of 57,690 hectares.
The area is home to 34 species that are protected by national and international conventions.
However, it is seen that these species are distributed in the southern coasts of Gokova Bay,
especially in the region between “Yedi Islands and Tuzla Bay”, and they do not intensively use the
area where the Project Area is located. Akbuk Bay and around (black dot in Figure IV.26)
southeast of Hanay Creek, are inhabited by Epinephelus marginatus and Sciaena umbra species.
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                      Chapter IV - Pg. 105/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
Akbuk Bay is about 17 km away from Hanay Creek, and the fish species protected in the area are
mobile aquatic fauna species.
        Anadromous fish species are fish that complete their growth and development in the seas
and go to inland waters to spawn when they reach reproductive maturity. In other words, it defines
fish species that migrate from marine waters to inland waters. No fish species protected within the
scope of the Gökova Special Environmental Protection Area enter the Hanay Creek by
anadromous migration.
        The region has freshwater inlets due to its natural structure. This situation increases the
productivity of the coastal ecosystem and causes many species to prefer this area as a spawning
area. However, as shown from the map below, the region where the project area is located is not
among the dense areas used by the species for spawning.
        Hanay Creek is an anthropogenic creek, which currently has a concrete creek bed and
from which the cooling water of the thermal power plant is discharged. The water to be treated and
discharged at the wastewater treatment plant is not expected to adversely affect the aquatic
environment in the Gökova SEPA, where the creek flows.
        As a result, it has been determined that sensitive species in Gokova Special Environmental
Protection Area do not use the Hanay Creek for breeding or spawning purposes. According to that,
the Gokova Special Environmental Protected Area is not included in the Project’s Area of Influence.
         In Turkey, there are three AZE sites determined. The closest one to the Project area is
Gulluk Mountain with 210 km away. In addition, the other closest AZE site is Nissos Saria kai Voria
Karpathos where is a Greece Island located in 139 km southwest of the Project area. Both AZE
sites are quite far away from the Project area and these sites will not affected from the Project
activities.
        These areas are wild and natural areas with high biodiversity value. A large part of the
project area will be built in the city. The area to be WWTP is relatively poor in terms of biodiversity.
Therefore, the project area is not considered to reflect the characteristics of the protected areas in
the environment.
        Project area is located in C1 grid in grid square system of flora of Turkey and
phytogeographically speaking, is located in a transition zone of Mediterranean zone. Climate
feature of the region has the Mediterranean climate characteristic due to the project area is located
in the Aegean region (see Figure IV.29).
       The grid square system is a method used to understand spatial distributions of species.
According to the system, distributions of endemic species of Turkey are shown in Figure IV.30.
When the distribution of the endemics taxa in Turkey is analysed as the grid system, it was
determined that C1 square area where the project is located, below an average of Turkey with
0.9% (Turk Cografya Journey 69 (2017) 109-120).
        In addition, planned WWTP area covers 8278.11 m2. Settlements start about 175 m from
the project area and the anthropogenic effect is dominant therefore vegetation of close vicinity of
the area has poor vegetation. Randomly distributed trees and scrubs and ruderal areas are
dominant in the area. Also, there is riparian vegetation near the area. It is possible to examine the
planned WWTP area as two types of vegetation in general:
          a) Riparian vegetation: The dominant plants of this vegetation that grows in streams in the
research area are plants like Platanus orientalis, Ulmus minor, Nerium oleander, Vitex agnus-
castus, Rubus sanctus, Bolboschoenus maritimus, Juncus heldreichianus, Ononis spinosa, Melisa
officinalis. All of these plants have more or less water demand.
        b) Ruderal vegetation: This type of vegetation grows mostly on field edges and roadsides
in the study area. Dominant shrub species like Rosa canina, Prunus divaricata ssp. divaricata,
Quercus coccifera, Paliurus spina-christi, Crataegus monogyna ssp. azarella and Pyrus
amygdaliformis var. amygdaliformis. In addition, Hirschfeldia incana, Rapistrum rugosum,
Sisymbrium officinale, Hypericum triquetrifolium, Daucus carota, Notobasis syriaca, Carlina
corymbosa are widely available as herbaceous plants.
         All components of the Project cover poor vegetation features and modified. There are
seven habitat types in the sewerage line and WWTP area according to EUNIS Habitat
Classification. None of these habitats are critical or sensitive habitats. Flora species of these
habitats are widespread and adapted to human pressure. Habitat types of the Project area are
described as follow:
        G1.3: Mediterranean Stream Trees: This habitat is spread along stream near the project
area. The dominant plants of this habitat are Platanus orientalis, Nerium oleander, Vitex agnus-
castus and Ulmus minor.
        F5.5: Warm Mediterranean Shrubs: It represents maquis in the form of a green bush in the
project area. Its characteristic species are Quercus coccifera, Quercus infectoria, Olea europaea
and Phillyrea latifolia.
       I1.2: Agricultural areas and cultured areas: Represents olive groves and dry agricultural
areas within the project area.
        J4.2: Disused road, rail and other constructed hard-surfaced areas: Road surfaces and car
parks, together with the immediate highly-disturbed environment adjacent to roads, which may
consist of roadside banks or verges.
        J 2.1: Scattered residential buildings: Houses or flats in areas where buildings, roads and
other impermeable surfaces are at a low density.
Flora Species
        The flora vegetation of the project area is very weak. The planned sewerage line,
discharge line and wastewater treatment plant area consists of unnatural or semi-natural areas. For
this reason, possible flora species of the areas consist of herbaceous plants and widely distributed
species. According to field studies and literature reviews, the flora types of the Project area are
presented in the Table IV.27.
       According to Table IV.27 there are not any endemic and/or sensitive flora species are
expected within the sewerage line and WWTP areas.
                                                                                                                               BERN            CITES
                                                                                         Phytogeographical
            Family                                         Taxon                                             Endemism   IUCN                            App
                                                                                              Region
                                                                                                                               App1   App1     App2     3
 SPERMATOPHYTA
 GYMNOSPERMAE
 PINACEAE                      Pinus brutia Ten.                                           Mediterranean        -       LC      -        -        -        -
 ANGIOSPERMAE
 RANUNCULACEAE
                               Ranunculus ficaria L. subsp. ficariiformis Rouy & Fouc.      Widespread          -        -      -        -        -        -
                               Ranunculus arvensis L.                                       Widespread          -        -      -        -        -        -
 PAPAVERACEAE                  Papaver rhoeas L.                                            Widespread          -       LC      -        -        -        -
 CRUCIFERAE                    Hirschfeldia incana (L.) Lag.-Foss.                          Widespread          -        -      -        -        -        -
                               Biscutella didyma L.                                         Widespread          -        -      -        -        -        -
                                                                                            Widespread                          -
                               Thlaspi perfoliatum L.                                                           -
                                                                                                                         -               -        -        -
                               Capsella bursa-pastoris (L.) Medik                           Widespread          -       LC      -        -        -        -
                               Nasturtium officinale R. Br.                                 Widespread          -       LC      -        -        -        -
                               Sinapis arvensis L.                                          Widespread          -       LC      -        -        -        -
                               Sisymbrium officinale ( L.) Scop.                            Widespread          -       LC      -        -        -        -
                               Erysimum smyrnaeum Boiss. & Bal.                             Widespread          -        -      -        -        -        -
 CARYOPHYLLACEAE               Minuartia hybrida (Vill.) Schischk. subsp.hybrida            Widespread          -        -      -        -        -        -
                               Holosteum umbellatum L. var. umbellatum                      Widespread          -        -      -        -        -        -
                               Silene vulgaris (Moench) Garcke var. vulgaris                Widespread          -       LC      -        -        -        -
                               Silene behen L.                                              Widespread          -        -      -        -        -        -
 ILLECEBRACEAE                 Herniaria incana Lam.                                        Widespread          -        -      -        -        -        -
 GUTTIFERAE                    Hypericum perforatum L.                                      Widespread          -       LC      -        -        -        -
                               Hypericum triquetrifolium Turra                              Widespread          -        -      -        -        -        -
 MALVACEAE                     Malva sylvestris L.                                          Widespread          -       LC      -        -        -        -
 LINACEAE                      Linum bienne Miller                                         Mediterranean        -        -      -        -        -        -
 GERANIACEAE                   Geranium lucidum L.                                          Widespread          -        -      -        -        -        -
         Since the project will be constructed in the city center, it is not expected to have habitat
types that will inhabit wildlife. However, as a result of the studies conducted by examining the
literature and previous studies, it was possible to make an inventory for the fauna species. The
investigations were carried out as reptiles-amphibians, birds and mammals.
     Reptile and amphibian species are concentrated in riparian habitat beside the planned
WWTP area. Amphibian and reptile species likely to be found in the area are shown in Table IV.28.
         Among the detected species, only tortoise (Testudo graeca) is in the category “VU”
(Vulnerable: Sensitive) (Table IV.20) according to IUCN. However, tortoise is a widely spread
reptile species found in every region except the Eastern Black Sea region in Turkey. Other reptile
species are not in any threatened category. According to the IUCN species "LC: Least Concern"
category is located in this region, and Turkey in general are widespread species of Western
Palearctic zoogeographical.
Table IV.28 Possible Reptile and Amphibian Species in and around the Project Area
Threatened Status
                                                                                    International              National
Species Name            Turkish Name            English Name
                                                                                                                     Endemism
                                                                                                       CITES
                                                                                         BERN
                                                                            IUCN
                                                                                                               RDB
Bufo bufo               Siğilli Kurbağa         Common Toad                LC         Annex II         -       nt      -
Bufotes variabilis      Gece Kurbağası          Green Toad                 DD         Annex II         -       nt      -
Phelophylax
                        Ova Kurbağası           Marsh Fog                  LC         Annex II         -       nt      -
bedriagae
                        Balkan Çizgili
Mauremys rivulata                               Western Caspian Turtle     LC            -             -               -
                        Kaplumbağası
Testudo graeca          Tosbağa                 Spur-thighed Tortoise      VU         Annex II      Annex II   nt      -
Mediodactylus
                        İnceparmaklı keler      Kotschy's Gecko            LC         Annex II         -       nt      -
kotschyi
Hemidactylus turcicus Geniş parmaklı keler      Turkish Gecko              LC        Annex III         -        -      -
Laudakia stellio        Dikenli Keler           Hardim                     LC         Annex II         -       nt      -
Lacerta trilineata      İri Yeşil Kertenkele    Balkan green lizard        LC         Annex II         -       nt      -
Ophisops elegans        Tarla Kertenkelesi      Wester sanke-eyed lizard   LC         Annex II         -       nt      -
Ablepharus kitaibelii   İince kertenkele        European copper skink      LC         Annex II         -       nt      -
Trachylepis aurata      Tıknaz Kertenkele       Levant skink               LC        Annex III         -       nt      -
Blanus strauchi         Kör Kertenkele          Anatolian worm lizard      LC        Annex III         -       nt      -
Typlops vermicularis    Kör Yılan               Blind snake                LC        Annex III         -       nt      -
Platyceps najadum       İnce Yılan              Dahl's whip snake          LC         Annex II         -       nt      -
Platyceps collaris      Toros Yılanı            Taurus whip snake          LC         Annex II         -       nt      -
Eirenis modestus        Uysal Yılan             Ring-headed dwarf snake    LC        Annex III         -       nt      -
Natrix natrix           Yarısucul Yılan         Grass Snake                LR/       Annex III         -       nt      -
Natrix tasellata        Su Yılanı               Dice Snake                 LC         Annex II         -       nt      -
Telescopus fallax       Kedigözlü Yılan         Soosan Snake               LC         Annex II         -       nt      -
          In the Project area, it is possible that some of the bird species are found in a certain period
of the year (spring-breeding and / or autumn-migration) and are usually that leave the region in the
fall. It has been determined that the project site is not on the main migration route for large
migratory birds flying with long wings. It is not a preferred transition area for migratory birds due to
the lack of suitable wintering habitats (permanent) wetlands (such as river-lake) and nutrient-rich
steppe areas for the project site and its immediate surroundings. Flocks of birds using as
accommodation and wintering areas during migration were not observed.
        Since the Project area is located in the city center, there are mostly passeriform birds and
cosmopolitan species. Possible bird species expected to be seen in the project area are presented
in Table IV.29.
         According to Table IV.29 Streptopelia turtur categorized as VU according to the IUCN Red
List but this species is very common (widespread) in Mugla and in Turkey.
Table IV.29 Possible Bird Species in and around the Project Area
Threatened Status
International National
                                                                                                                 Endemism
                                                                                             CITES
                                                                                 BERN
                                                                      IUCN
                                                                                                         RDB
Buteo buteo              Şahin                   Common buzzard       LC     Annex III    Annex II   A.3         -
International National
                                                                                                                               Endemism
                                                                                                         CITES
                                                                                          BERN
                                                                             IUCN
                                                                                                                       RDB
Sitta neumayer              Kaya Sıvacısı              Rock nuthatch         LC       Annex II                       A.2       -
Lanius collurio Kızıl Sırtlı Örümcekkuşu Red-backed shrike LC Annex III A.2 -
Miliaria calandra Tarla Çintesi Corn bunting LC Annex III Annex II A.4 -
Mammals
         The project area is not expected to support the wildlife considering the location of the
project components. The mammalian species of the region, like other fauna groups, are widely
distributed species with high adaptation to the city. Sewerage lines, discharge line and WWTP will
be constructed within settlements and areas where human impact is intense. Therefore, the area is
not expected to accommodate mammalian species that will require protection. Possible mammal
species expected to be seen in the project area are presented in Table IV.30.
Table IV.30 Possible Mammal Species in and around the Project Area
Threatened Status
International National
                                                                                                                                 Endemism
                                                                                                             CITES
                                                                                              BERN
                                                                               IUCN
RDB
Martes foina Kaya Sansarı Stone Marten LC Annex III Annex III nt -
          The treated water of the WWTP project will be discharged to Hanay Creek and its
characteristics are provided in Chapter IV.1.6. It directly drains into the sea without connecting to
another stream. The creek bed is made of concrete, and the cooling water is being discharged from
Kemerköy Thermal Power Plant to the Hanay Creek. The creek is an anthropogenic creek that has
lost its natural characteristics.
        In the field studies, it was observed that there is flow in the creek (see Figure IV.31).
However, no fish were detected in the creek due to anthropogenic effects. The mouth of the sea is
located at a distance of about 1 km to the discharge point. Fish species can live in brackish waters
at the intersection of the creek and the sea. The most dominant species in the region is mullet
belonging to the Mugilidae family. Mullet is seen as a widespread species in Turkey and classified
as "LC: Least Concern" according to IUCN. However, it is known that the environment, whose
temperature increases due to cooling water discharge, creates a barrier for mullet species.
        In this section, information regarding the economic activities and demographic features of
Mugla province and Milas district on the regional scale and Oren, Bozalan, and Turkevleri regions
on the local scale are presented to the extent possible. The state data retrieved from TurkStat is
supported with the results of field studies and site surveys conducted at Oren.
Parameters                                                                                                       Value
Socio-economic development ranking (Ministry of Development, 2011)                                                 8th
GDP per capita (TurkStat, 2018)                                                                                 9.448 $
Number of Firms in Top 1000 (Istanbul Association of Manufacturers, 2018)                                          2
Number of Foreign Financed Firms (TOBB, 2019)                                                                      8
Total Exportation (TÜİK, 2019)                                                                                559 Million $
Primary school enrolment rate 2012 and after-net (%) (Turkey % 91.92) (TurkStat, 2018)                          %90.49
Secondary Education Schooling Rate (Turkey % 93,28) (TurkStat, 2018)                                            %92.01
Number of Students Per Classroom (Primary School-Secondary School) (Turkey 24) (TurkStat, 2018)                    18
Number of Hospital Bed per 100,000 Persons (Turkey 283) (TurkStat, 2018)                                          211
Forest Area / Total Area Ratio (General Directorate of Forestry )                                               %67.54
Tourism Facility Licensed Bed Numbers (MUTSO-TurkStat, 2018)                                                    197,054
Total number of overnights (TurkStat, 2019)                                                                   14,497,222
        Mugla located in a region that historical and cultural heritage traces are present. From the
scope of employment and income, the most important sector is tourism. 1,124 km coastal length,
Mugla pine honey, Milas carpet, Bodrum tangerine and natural beauties are the prominent values
of Mugla. While foreign tourists visit the province for summer vacation, winter season is not
evaluated enough from tourism scope. With advanced tourism opportunities such as airports,
seaports and marinas, hotels and beach facilities it is one of the most popular destinations of
Turkey.
        In Table IV.32 and Table IV.33, Mugla Chamber of Commerce and Industry’s latest
available data showing number of tourists entering to Mugla and tourism facility statistics are
presented, respectively. It should be noted that data presented in Table IV.32 does not contain
access by road, which is the primary choice for most of the local tourists.
Table IV.32 Number of Tourists Entering Mugla by Mode of Transportation between 2016 and 2018
Table IV.33 Tourism Facility Statistics Prepared by TurkStat for Mugla Chamber of Commerce and Industry.
         Important sectors other than tourism are seafood and animal products, mining and
quarrying, fresh fruit and vegetables, ship and yacht. For development of the economy of Mugla,
the province has potential future for medical tourism, renewable energy, organic agriculture,
agriculture based industry, ecology tourism and medicinal and aromatic plant production.
        Mugla’s exports mainly consists of four main sectors; manufacturing, mining and stone
quarry, agriculture, forestry and fishing. Their total contribution to expropriation of Turkey is around
559 Million $.
          The Southern Aegean Region, identified as TR32 Region, is composed of Aydin, Denizli
and Mugla provinces. Turkey’s 4.1% population lives in this region. TR32 Region constitutes 4.6%
of total labor force, 4.7% of total employment, and 3.2% of total unemployment of Turkey.
       In 2019, employment and unemployment rates of TR32 are 51.2% and 9.2%, respectively.
The employment rate in the region is higher than Turkey’s average, which is 45.7%, and
unemployment rate in the region is lower than Turkey’s average, which is 13.7%. The employment
and unemployment rates according to years are presented in Figure IV.32.
                          60
                                                                                       53
                                             50,3        50,3              51,5                      51,2
                                50
                          50
40 45,5 45,7
30
                          20                                                                         13,7
                                9,9          10,3        10,9              10,9        11
                          10
                                                                                                     9,2
                                7,2          6,9          6,7              7,1         6,9
                          0
                               2014         2015         2016             2017        2018          2019
                                                                 Years
                                      Employment Rate Turkey             Employment Rate TR32
                                      Unemployment Rate Turkey           Unemployment Rate TR32
Figure IV.32 Employment and Unemployment Rates According to Years, TR32 (TurkStat, 2019)
       The shares of service, agriculture and industry sectors within the region are 41.1%, 39.6%
and 19.1%, respectively (see Figure IV.33).
                                         19,1
                                                            41,1
                                                                          Service
                                                                          Agriculture
                                  39,6
                                                                          Industry
          In Milas District, where Oren neighborhood is located at, agriculture is the main sector that
contributes most to the district’s economy, but mining and industry have also great importance. The
district ranks first in the province in terms of the number of industrial workplaces registered to
Turkish Union of Chambers and Commodity Exchanges and employment. Milas Airport and Gulluk
Port strengthen the district’s transportation and storage infrastructure. The vast majority of fish
production, packaging and feed mills of the region are located in Milas and vicinity, and 68% of
Turkey's farmed fish production is met. There are many feldspar and marble quarries and marble
processing facilities in the district. Milas has the 2 nd place after Yatagan for the number of workers
in mining sector.
          While agricultural lands of Mugla’s districts are presented in Figure IV.34, the breakdown of
Milas’s agricultural land is provided in Table IV.34, and following that top ten agricultural products
of Milas and their amounts are presented in Table IV.35. As seen from Figure IV.34, Milas ranks
first in terms of agricultural land acreage among Mugla’s districts. Mugla’s 42.7% of agricultural
lands consist of olive groves (53080 ha, around 8 million trees). There are 16 businesses in Milas
that produce organic olive and olive oil.
       In addition to agriculture, Milas also ranks first in terms of stockbreeding among districts of
Mugla as it can be seen from Figure IV.35. Milas also ranks first in honey production with 2800 ton.
         The residents of Oren were making their living from agriculture (citrus, sesame, tobacco,
cotton, and cereals), husbandry, and waving until 1990. After 1990, growth in tourism has changed
the economy of Oren and its vicinity. Then hotel management, restaurant management, yachting,
and service jobs have become widespread and started to contribute to the economy of Oren (Milas
District Governorship Information Notice, 2018). TurkStat does not provide any economic data on
neighbourhood level; therefore, site surveys were used to gather as much data as possible on
socio-economics of Oren and its vicinity. Eighteen surveys were conducted in Oren during the first
public participation meeting held on July 7, 2020. The information gathered by these surveys are
presented in Table IV.36. As seen from below, mostly elderly people participated to the survey
studies and almost all of them are on retirement pension. Unemployment rate among the
participants is quite high (28.58%) comparing to Muğla’s data presented above. However, all
participants have social securities and 53% of them have savings.
Information on Participants
Number of surveys                                                                              18
Ratio of female participants                                                                   29.40%
Ratio of male participants                                                                     70.60%
Average age of the participants                                                                53
Percentage of participants between the ages of 20 and 30                                       12.50%
Percentage of participants between the ages of 30 and 40                                       6.25%
Percentage of participants between the ages of 40 and50                                        12.50%
Percentage of participants between the ages of 50 and 60                                       37.50%
Percentage of participants between the ages of 60 and 70                                       25%
Percentage of participants between the ages of 70 and 80                                       6.25%
Percentage of people living in Milas 12 months of a year                                       35.71%
Percentage of people living in Milas less than 6 months of a year                              42.85%
Percentage of residents who have been in Milas for more than 10 years                          33.30%
Percentage of residents who have been in Milas for less than 10 years                          66.70%
Sources of Income
Salary                                                                                         46.66%
Retirement pension                                                                             20.04%
Commercial income and retirement pension                                                       6.66%
Commercial income                                                                              6.66%
Rent and retirement pension                                                                    6.66%
Tourism income and rent                                                                        6.66%
Tourism income and retirement pension                                                          6.66%
Main Unemployment Reason
Retired                                                                                        57.13%
Unemployed                                                                                     28.58%
Seasonal unemployment                                                                          14.29%
Total Annual Income in 2019
Less than 100.000 TL                                                                           40%
More than 100.000 TL                                                                           60%
Savings
        The biggest industry in Oren is Kemerköy Thermal Power Plant and associated coal mines.
Other than the plant, there are no attraction centres in Oren for active population. In off-season,
Oren’s population decreases to 3000 from 30000 and mostly elderly residents stay in the village
according to the interviews made with the public.
        Oren has three schools; one primary school, one secondary school and one high school.
The total number of students in the neighbourhood is 450. There are 30 classrooms and 50
teachers in these schools (Milas District Directorate of National Education, 2020). It can be said
that education infrastructure in Oren is strong with sufficient number of schools, classrooms, and
teachers. For university-level education, nearest university is Mugla Sitki Kocman University.
       Despite strong education infrastructure, Oren has very limited health services. There is
only one primary care clinic in Oren. The clinic is occupied with three doctors. This indicates that
number of population per doctor is 1000 for winter period and this value is way beyond the Turkish
average (498.2) and OECD average (341.3). The ratio is much worse for summer season, where
the population reaches ten-fold. The nearest full-fledged hospital, which is 75. Yıl State Hospital, is
IV.3.2 Population
Provincial Level
        Mugla ranks twenty fourth province of Turkey in terms of total population, as of 2019, its
population is 983.142. Population density (number of people per square kilometer) is 76.5, it is
lower than Average of Turkey (108.05) when compared with. It is a famous settlement in the
Aegean Region, with a small part of its territory in the Mediterranean Region, where the holiday
resorts such as Ortaca, Dalaman, Fethiye, Marmaris, Milas, Datca and Bodrum are located. The
province has 13 districts (TurkStat,2019).
         Substantial part of the Mugla population consists of age group of 0-24 and this group
comprises 30.67 percent of total population. Age and gender distribution of Mugla is given in Table
IV.37 and it is shown that the age group of “35-39” (8.22%) and “40-44” (8.06%) has the highest
ratio within the total population.
Table IV.37: Age and Gender Distribution of Mugla Province (TurkStat, 2019)
        Population pyramid of Mugla province is presented in Figure below. When the population
pyramid examined, it can be said that Mugla has contracting population pyramid profile. By
considering these data, the dependency ratio (of Mugla is 43.9% and this ratio is slightly lower than
the average ratio of Turkey (47.46%).
80-84
70-74
60-64
         50-54
   Age                                                                                               Female
         40-44                                                                                       Male
         30-34
20-24
10-14
               0-4
                 10,00             5,00                0,00            5,00              10,00
         According to the data obtained from Address Based Population Registration System, 2019
results, population of the Milas district, where project area is located, is 141,107. With this
population, Milas has the 3rd highest population behind Bodrum and Fethiye respectively. The
population distribution of Mugla and the population of the districts are given in Table IV.38.
         Milas ranks third with its 141,107 population among districts of Mugla. The population
density is 68.7, which is lower than both Mugla average 76.5 and Turkey average 108.05. Age and
gender distribution of the population is presented in Table IV.39. The table shows that the age
distribution of Milas is balanced and the age group of “35-39” (7.68%) and “30-34” (7.26%) has the
highest ratio within the population. The average age in Milas is 38.7, which is 42 for Mugla and
32.7 for Turkey. The dependency ratio of Milas is calculated as 47.2 %, while it is 43.9% in Mugla
and 47.46% in Turkey.
Table IV.39 Age and Gender Distribution of Milas Province (TurkStat, 2019)
       Population pyramid of Milas is presented in Figure IV.37. When the population pyramid
examined, it can be said that Mugla has contracting population pyramid profile.
'80-84'
'70-74'
               '60-64'
   Age Group
               '50-54'
                                                                                                    Female
               '40-44'
                                                                                                    Male
               '30-34'
'20-24'
'10-14'
                 '0-4'
                         6    4            2            0             2       4         6
Neighbourhood Level
        Three neighbourhoods of Milas – Oren, Turkevleri, and Bozalan - are in the scope of the
Project. The demographic information of these neighbourhoods are retrieved from TurkStat and
presented in Table IV.40. It should be noted that during summer season, these numbers could go
up-to ten times.
        The ESIA scoping process for the Project considered relevant project activities and the
environmental and social aspects they would interact with in order to identify the issues to be
focused on in the ESIA studies. The analysis of these potential interactions has been done using a
color code (see Table V.1) in a modified Leopold matrix (see Table V.2). This approach provided
the means to identify the potential interactions each Project activity may have on a range of
resources/receptors within the Project Area of Influence (AoI).
        The Turkish EIA Regulation defines the area of influence as "the area affected by a
planned project before operation, during operation and after operation". The area of influence may
be different for different types of impacts and different environmental components (physical,
biological, social) (World Bank ESMAP, December 2012).
          The area likely to be affected by: (i) the Project (e.g. Project sites, immediate air shed
           and watershed, or transport corridors) and the Project Sponsors’ activities and facilities
           that are directly owned, operated or managed (including by contractors) and that are a
           component of the project (e.g. tunnels, access roads, borrow and disposal areas
           construction camps); (ii) impacts from unplanned but predictable developments caused
           by the project that may occur later or at a different location; or (iii) indirect project
           impacts on biodiversity or on ecosystem services upon which Affected Communities’
           livelihoods are dependent.
          Associated facilities, which are facilities that are not funded as part of the project and
           that would not have been constructed or expanded if the project did not exist and
           without which the project would not be viable.
          Cumulative impacts that result from the incremental impact, on areas or resources
           used or directly impacted by the project, from other existing, planned or reasonably
           defined developments at the time the risks and impacts identification process is
           conducted.
        In this respect, the Project together with all of its components and auxiliary facilities
(sewerage network including the pumping stations, Oren WWTP, energy transmission lines and
construction camp) has been considered in the ESIA to the extent the level of information allowed.
        Those interactions that are coloured white are scoped out of further consideration in the
impact assessment process and no discussion is warranted in the ESIA report. Those interactions
that are coloured grey are also scoped out, but during the impact assessment process these
potential interactions have been reviewed to confirm that resulted impacts are not significant and/or
are appropriately addressed through one or more embedded controls. Those interactions marked
with red and green are scoped in and subject to impact assessment as part of the ESIA process.
These impacts would be assessed for their significance and additional mitigation measures,
beyond the already planned embedded controls, would be proposed as necessary.
Environmental Resources
Biological Environment
                                                                                                                                                                                                                              Climate Change
                                                                                         Groundwater
                                                                                                                                                                                (Aesthetics)
                                                      Air Quality
Construction
Vegetation    clearance,      levelling works   and
construction activities at Oren WWTP site
Excavation of surface material for laying down of
sewerage system
Use of energy
Operation
                                                                                                                                                                                                                      Working Conditions)
                                                                                                                                                                       Ecosystem Services
                                                      Local Economics
                                                                                                                                                                                                         Livelihood
                                                                                                                                Cohesion
Land Use
                                                                                                                                                                                                                                                           Security
Construction
Employment of personnel and procurement of goods
and services (from local market)
Labor influx
Road closures
Operation
Employment of personnel and procurement of goods
and services (from local market)
Maintenance of sewerage system, discharge line,
pumping stations and WWTP
         The purpose of impact assessment and mitigation is to identify and evaluate the
significance of potential impacts (positive or negative) on identified receptors and resources
according to defined assessment criteria; to develop and describe the measures that will be taken
to avoid or minimize any potential adverse effects and enhance potential benefits; and to report the
significance of the residual impacts that remain following mitigation.
       The assessment of environmental and social impacts has been done based on the criteria
provided below using mainly expert judgement, relevant standards and guidelines:
        Project’s location is presented in Figure V.1. As described before, the Project will have
impacts especially on the vicinity of the Project sites. The potential area of influence for the Project
includes the neighbourhoods that are located in the sewerage network service area, discharge line,
pumping stations, WWTP, energy transmission line, construction camp and its close vicinity. In
short, the settlement areas located in the Oren, Turkevleri, and Bozalan Neighbourhoods are
considered as the potential area of influence, which is shown in Figure V.2. Project’s potential
social area of influence and the distances between WWTP and nearest settlements are show on a
map given in Figure V.3, which is similar with the potential area of influence. The identified
sensitive receptors are shown on a map presented in Figure V.4.
        Project would have environmental impacts during construction and operation phases.
Potential impacts of the Project during the construction phase would be generally short term with
low to medium magnitude that would be locally significant. These impacts can be initially
summarized as follows:
           Air emissions and increased level of noise generated from the operation of the
            construction machinery and equipment.
           Soil contamination as a result of inadequate management of waste generated on site,
            and possible leakage of hazardous materials (oil and lubricants from outdoor
            equipment).
           Wastes to be produced by workers.
         In terms of auxiliary facilities, impacts during the construction activities are expected to be
similar to the impacts regarding to main Project components, therefore, these impacts are
evaluated together for both main Project components and auxiliary facilities. Although the energy
transmission line has a linear route, only electric poles with a base size of approximately 5m x 5m
will be erected for the energy transmission line. For this reason, excavation works will be limited for
the electric pole and construction activities will be carried out in a short period of time. Therefore,
impacts related to energy transmission line during the construction phase will be low in significance
and short-term. On the other hand, for operation phase, impact regarding to electrocution from
energy transmission line could be considered as significant if not properly managed.
        During the operation phase significant adverse environmental impacts are not expected.
The operation of the WWTP might create noise, odour, and sludge related impacts on sensitive
receptors, which could be considered as significant if not properly managed. Maintenance and
repair works of the WWTP, discharge line, sewerage network, pumping stations and energy
transmission line might have minor environmental impacts such as generation of waste and
increased level of noise. These impacts will be local and short-term with low in significance.
         The following table provides a detailed overview of the identified impacts and their
assessment as a result of the execution of project activities in different project phases, types of
activities and baseline conditions on the Project area.
Impact
                                                                                                        On-site/project
                                                                                                                                                                                                                                                   Medium        Medium        Medium          Medium
Negative (-)
                                                                                           Cumulative
                                        Positive (+)
                                                                                                                                                                                            Permanent
                                                                                                                                                        Short term
                                                                                                                                                                                Long term
                                                                                                                                                                                                                                                   Low           Low           Low             Low
Regional
                                                                                                                                                                     Mid-term
                                                                                                        footprint
National
                                                                                                                                                                                                                                        Unlikely
                                                                                Indirect
                                                                                                                                                                                                                               Likely
                                                                      Direct
                                                                                                                          Local
                                                                                                                                                                                                                                                   Negligible/   Negligible/   Negligible/     Negligible/
                                                                                                                                                                                                                                                   None          None          None            None
A. CONSTRUCTION PHASE
1. Air Quality
4. Groundwater Resources
                                                                                                                                                                                                   Impact
                                                                                                                                                                                                                                                       Sensitivity   Magnitude     Impact         Impact
                                                                                                                                                                                                            Likelihood of                                                          Significance
                                            Nature                                 Type                                  Extent/area                                     Duration                                                                      of the        of the                       Significance
                                                                                                                                                                                                             Occurrence                                                            without
                                                                                                                                                                                                                                                       Receptor      Impact                       with ESMP
                                                                                                                                                                                                                                                                                   ESMP
                                                                                                                                                                                                                                                       High          High          High           High
                                                                                                            On-site/project
                                                                                                                                                                                                                                                       Medium        Medium        Medium         Medium
Negative (-)
                                                                                               Cumulative
                                            Positive (+)
                                                                                                                                                                                                Permanent
                                                                                                                                                            Short term
                                                                                                                                                                                    Long term
                                                                                                                                                                                                                                                       Low           Low           Low            Low
Regional
                                                                                                                                                                         Mid-term
                                                                                                            footprint
National
                                                                                                                                                                                                                                            Unlikely
                                                                                    Indirect
                                                                                                                                                                                                                                   Likely
                                                                          Direct
                                                                                                                              Local
                                                                                                                                                                                                                                                       Negligible/   Negligible/   Negligible/    Negligible/
                                                                                                                                                                                                                                                       None          None          None           None
6. Biological Environment
     No     significant    impacts    on
1    biological      environment     are                                                                                                                                                                                                               Low           Low           Low            Negligible
     expected
9. Climate Change
                                                                                                                                                                                                Impact
                                                                                                                                                                                                                                                    Sensitivity   Magnitude        Impact           Impact
                                                                                                                                                                                                         Likelihood of                                                             Significance
                                         Nature                                 Type                                  Extent/area                                     Duration                                                                      of the        of the                            Significance
                                                                                                                                                                                                          Occurrence                                                               without
                                                                                                                                                                                                                                                    Receptor      Impact                            with ESMP
                                                                                                                                                                                                                                                                                   ESMP
                                                                                                                                                                                                                                                    High          High             High             High
                                                                                                         On-site/project
                                                                                                                                                                                                                                                    Medium        Medium           Medium           Medium
Negative (-)
                                                                                            Cumulative
                                         Positive (+)
                                                                                                                                                                                             Permanent
                                                                                                                                                         Short term
                                                                                                                                                                                 Long term
                                                                                                                                                                                                                                                    Low           Low              Low              Low
Regional
                                                                                                                                                                      Mid-term
                                                                                                         footprint
National
                                                                                                                                                                                                                                         Unlikely
                                                                                 Indirect
                                                                                                                                                                                                                                Likely
                                                                       Direct
                                                                                                                           Local
                                                                                                                                                                                                                                                    Negligible/   Negligible/      Negligible/      Negligible/
                                                                                                                                                                                                                                                    None          None             None             None
                                                                                                                                                                                                                                                                                                    None/
2   Community encroachment                                                                                                                                                                                                             Low           Medium          Low
                                                                                                                                                                                                                                                                                                    Negligible
                                                                                                                                                                                                                                                                                                    Negligible/
1   Chance finds                                                                                                                                                                                                                       Low           Low             Low
                                                                                                                                                                                                                                                                                                    None
                                                                                                                                                                                               Impact
                                                                                                                                                                                                                                                   Sensitivity   Magnitude        Impact           Impact
                                                                                                                                                                                                        Likelihood of                                                             Significance
                                        Nature                                 Type                                  Extent/area                                     Duration                                                                      of the        of the                            Significance
                                                                                                                                                                                                         Occurrence                                                               without
                                                                                                                                                                                                                                                   Receptor      Impact                            with ESMP
                                                                                                                                                                                                                                                                                  ESMP
                                                                                                                                                                                                                                                   High          High             High             High
                                                                                                        On-site/project
                                                                                                                                                                                                                                                   Medium        Medium           Medium           Medium
Negative (-)
                                                                                           Cumulative
                                        Positive (+)
                                                                                                                                                                                            Permanent
                                                                                                                                                        Short term
                                                                                                                                                                                Long term
                                                                                                                                                                                                                                                   Low           Low              Low              Low
Regional
                                                                                                                                                                     Mid-term
                                                                                                        footprint
National
                                                                                                                                                                                                                                        Unlikely
                                                                                Indirect
                                                                                                                                                                                                                               Likely
                                                                      Direct
                                                                                                                          Local
                                                                                                                                                                                                                                                   Negligible/   Negligible/      Negligible/      Negligible/
                                                                                                                                                                                                                                                   None          None             None             None
B. OPERATION PHASE
1. Air Quality
    Air and odorous gas emissions
1                                                                                                                                                                                                                                             Medium        Medium          Medium            Low
    from Oren WWTP
2. Geology, Soils and Contaminated Land
4. Groundwater Resources
6. Biological Environment
                                                                                                                                                                                                Impact
                                                                                                                                                                                                                                                    Sensitivity   Magnitude        Impact           Impact
                                                                                                                                                                                                         Likelihood of                                                             Significance
                                         Nature                                 Type                                  Extent/area                                     Duration                                                                      of the        of the                            Significance
                                                                                                                                                                                                          Occurrence                                                               without
                                                                                                                                                                                                                                                    Receptor      Impact                            with ESMP
                                                                                                                                                                                                                                                                                   ESMP
                                                                                                                                                                                                                                                    High          High             High             High
                                                                                                         On-site/project
                                                                                                                                                                                                                                                    Medium        Medium           Medium           Medium
Negative (-)
                                                                                            Cumulative
                                         Positive (+)
                                                                                                                                                                                             Permanent
                                                                                                                                                         Short term
                                                                                                                                                                                 Long term
                                                                                                                                                                                                                                                    Low           Low              Low              Low
Regional
                                                                                                                                                                      Mid-term
                                                                                                         footprint
National
                                                                                                                                                                                                                                         Unlikely
                                                                                 Indirect
                                                                                                                                                                                                                                Likely
                                                                       Direct
                                                                                                                           Local
                                                                                                                                                                                                                                                    Negligible/   Negligible/      Negligible/      Negligible/
                                                                                                                                                                                                                                                    None          None             None             None
                                                                                                                                                                                                Impact
                                                                                                                                                                                                                                                    Sensitivity   Magnitude     Impact          Impact
                                                                                                                                                                                                         Likelihood of                                                          Significance
                                         Nature                                 Type                                  Extent/area                                     Duration                                                                      of the        of the                        Significance
                                                                                                                                                                                                          Occurrence                                                            without
                                                                                                                                                                                                                                                    Receptor      Impact                        with ESMP
                                                                                                                                                                                                                                                                                ESMP
                                                                                                                                                                                                                                                    High          High          High            High
                                                                                                         On-site/project
                                                                                                                                                                                                                                                    Medium        Medium        Medium          Medium
Negative (-)
                                                                                            Cumulative
                                         Positive (+)
                                                                                                                                                                                             Permanent
                                                                                                                                                         Short term
                                                                                                                                                                                 Long term
                                                                                                                                                                                                                                                    Low           Low           Low             Low
Regional
                                                                                                                                                                      Mid-term
                                                                                                         footprint
National
                                                                                                                                                                                                                                         Unlikely
                                                                                 Indirect
                                                                                                                                                                                                                                Likely
                                                                       Direct
                                                                                                                           Local
                                                                                                                                                                                                                                                    Negligible/   Negligible/   Negligible/     Negligible/
                                                                                                                                                                                                                                                    None          None          None            None
                                                                                                                                                                                                                                                                                                None/
4   Community encroachment                                                                                                                                                                                                        Low                   Medium        Low
                                                                                                                                                                                                                                                                                                Negligible
Construction Phase
         The major impacts on air quality during the construction phase of this project will be related
with the material handling, vehicle movement and emission from heavy construction machinery
(trucks, excavators, etc.). Air pollution will be mainly dust emissions and exhaust emissions as well
as GHG emissions. The sensitive receptors that will be exposed to these air emissions will be the
local population who lives near the construction sites.
         During construction phase of the project, there will be vehicle movement for transportation
of various construction materials to the project site. Impacts on air quality will be mainly due to dust
emissions caused by the vehicle movement on unpaved roads and earthworks to be performed
within the Project Area. In addition to the fugitive dust emissions, exhaust emissions will originate
from vehicles used in construction activities. In order to determine fugitive dust and exhaust
emissions during the construction phase, the number of machinery and equipment to be used for
the construction should be known. The machinery requirement of the Project is not determined by
MUSKI yet and therefore, the construction machineries and equipment to be used during the
construction phase is assumed and presented in Table V.6.
        The amount of fugitive dust emission generated during the construction phase of the
Project is calculated with the emission factors defined in IAPCR. The emission factors are
presented in Table V.7.
                                                                      Emission Factors
    Sources                                                                                                  Unit
                                                         Uncontrolled              Controlled
    Dismantling/Excavation                                   0.025                   0.0125
    Loading                                                  0.010                   0.0050                  kg/ton
    Unloading                                                0.010                   0.0050
    Storage                                                  5.800                   2.9000              kg dust/ha.day
   Transportation (total distance)                            0.700                  0.3500              kg/km- vehicle
Source: Industrial Air Pollution Control Regulation, Appendix 12.
        According to the project schedule, construction activities are planned to last for 18 months
(approximately 450 work days) and daily shifts will last for 8 hours. Construction works will start
with earthworks, which will last for 240 days. Earthworks consist of levelling, excavation, temporary
storage, loading and transportation of excavation material.
        The amount of dust emission expected as a result of the construction activities of the
Project have been calculated and presented in detail below.
       12,379.51 m3 of excavated soil will be stored for its reuse in the WWTP Area and sewerage
network. The storage height will be 3 m. Thus, required storage area is 4,126 m2, which is 0.41 ha.
        Dust will be generated mainly during the excavation works performed for the construction
of the sewerage network, discharge line, pumping stations and WWTP. The sewerage network and
discharge line will follow the cadastral roads and the construction will be performed gradually. For
the pumping stations, construction activities will take place on the route of sewerage network.
Therefore; the receptors will be limited to the vicinity of construction works and these receptors are
presented in Figure V.3. Their sensitivity is assessed as medium, especially the ones in populated
areas (i.e. city centre). The most sensitive receptor to dust is considered as Sitki Kocman
University Fisheries Research and Development Centre, which is located adjacent to the WWTP
site. Additionally, there is a hospital around TM-6 Pumping Station. Therefore, necessary mitigation
measures described in the further sections of this report should be taken to not to impact the
regular operation.
         Standards for PM10 (particles with aerodynamic diameter smaller than 10μm) are defined
for particles which are respirable by humans and therefore, PM10 is the accepted measure of
particles in atmosphere. In this context, the Regulation on Air Quality Assessment and
Management defines the standards in terms of PM10.
        Regulation on Assessment and Management of Air Quality was put into force in Official
Gazette dated June, 6 2008 and numbered 26898. With this regulation, the Regulation on
Protection of Air Quality was abolished. Long and short terms standards were specified for the
harmonization of environmental regulations in the process of accession to the European Union.
However, the regulation sets a transition period for the application of these limit values.
        Industrial Air Pollution Control Regulation (IAPCR) published in Official Gazette dated July
3, 2009 and numbered 27277 aims to control emissions in form of smoke, dust, gas, vapor and
aerosol which are released to the atmosphere as a result of activities of industrial plants and
energy generation facilities, to protect human beings and the environment from pollution, and to
manage and prevent negative impacts of air pollution which result in significant problems on public
health. With this regulation, the Regulation on Air Pollution Caused by Industry has been abolished.
         Ambient air quality limit values for various pollutants defined in above-mentioned
legislations are presented in Table V.9.
                                                                                                       Limit Value*
             Parameter                                          Duration
                                                                                                         (µg/m3)
                                      Hourly (cannot be exceeded more than 24 times a year)                 350
                                      24 hour                                                               125
 SO2
                                      Long term limit                                                       60
                                      Annual and winter season (October 1 - March 31)                       20
                                      Hourly (cannot be exceeded more than 18 times a year)                 250
 NO2
                                      Annual                                                                40
                                      24 hour (cannot be exceeded more than 35 times a year)                50
 Particulate Matter (PM 10)
                                      Annual                                                                40
  CO                                    8 hour daily maximum                                              10,000
* Regulation on Assessment and Management of Air Quality
** Industrial Air Pollution Control Regulation
WBG Standards
       In addition to the Turkish legislations, the ambient air quality limit values stipulated in the
WBG General EHS Guidelines shall be complied. The WBG General EHS Guidelines –
Environmental Air Emissions and Ambient Air Quality refers primarily to national legislated
standards or in their absence to WHO Air Quality Guidelines. Therefore, the national legislated
standards will be followed.
        During the construction phase of the project, the above-mentioned regulations and
standards will be complied with. As a result, when the works to be carried out within the scope of
construction activities and corresponding work load are taken into account, it can be concluded that
the impacts will be low in significance upon implementation of the mitigation measures and
adherence to good construction methods.
        The following techniques for the reduction and control of air emissions will be implemented
during the construction phase in accordance with relevant Turkish regulations and international
standards:
             Dust should be minimized from open area sources, including storage piles, by using
              control measures such as installing enclosures and covers, and increasing the
              moisture content.
             Daily backfilling, bedding and covering materials will be stored at temporary storage
              areas, the materials will be moisturized and compacted to prevent the materials moving
              with the help of wind.
             Continuous water spraying will be conducted at the WWTP site to minimize dust
              impacts on Mugla Sitki Kocman University Fisheries Research and Development,
              which is adjacent to the site, and during the works to be performed around TM-6,
              where there is a hospital nearby.
             Inner roads of the WWTP will be covered to prevent dust formation.
             Speed limitations will be defined and obeyed for construction vehicles.
             The drop height of potentially dust generating materials will be kept as low as possible.
             Trees will be planted to the borders of WWTP, especially at the east and south
              borders.
             When there is traffic flow on the existing roads, where the works performed at, dust
              suppression measures will be continuously applied to ensure traffic safety. If there is
              no traffic existing in the local roads, dust suppression measures will be applied only at
              local residential and business areas.
             Loading and unloading operations will be performed without throwing/scattering.
        In addition to the fugitive dust emissions, there will be exhaust emissions of heavy
construction machinery. Primary emissions from exhaust gases of vehicles are NO 2, CO, HC, SO2
and PM. Emission characteristics depend on parameters such as; age of the vehicle, engine
speed, working temperature, ambient temperature and pressure, type and quality of fuel. Emission
factors developed by USEPA for gasoline and diesel fuelled vehicles are presented in Table V.10.
                                                           EMISSIONS (g/km/vehicle)
 POLLUTANTS
                                                Gasoline                              Diesel Fuel
        The indicative list of construction machinery to be used for the construction activities were
previously presented in Table V.6. Exhaust emissions of the machinery are presented in Table
V.11.
                                            Emissions (kg/hour)
        NOX                    CO                   SO2                   HC                        PM
       0.153                  0.255                0.026                0.049                   0.014
       According to the calculations made, exhaust emissions are quite below the IAPCR limit
values for all parameters. Although no significant exhaust emission is expected during the
         In addition to that only electric poles with a base size of approximately 5m x 5m will be
erected for the energy transmission line. For this reason, excavation works will be limited for the
electric posts and construction activities will be carried out in a short period of time. Therefore,
impacts related to energy transmission line will be low in significance and short-term.
Operation Phase
        The operation phase of the Project is not expected to cause significant dust and exhaust
emissions. However, as stated in the IFC’s EHS Guidelines for Water and Sanitation, air emissions
from wastewater treatment operations may include hydrogen sulfide, methane, gaseous or volatile
chemicals used for disinfection processes, and bioaerosols. Hydrogen sulfide and methane are
known as odorous gases. Therefore, odor impacts will be observed during the operation phase of
the Project.
        During the operation phase, odor is generally generated in physical treatment and sludge
units of wastewater treatment plants. Screens, aeration tanks, sedimentation tanks, sludge
thickeners and dewatering units and operations performed within these units can result in
generation of odor which may result in disruptive impacts around the treatment plant. In addition,
pumping stations can also cause odor emissions even though they will be buried underground and
will have odor removal units with activated carbon filters.
        Wastewater influent contains high amounts of organic material. Organic materials are
decomposed into odorous compounds by bacteria in biological treatment process. Activated sludge
contains high amounts of bacteria and organic matter which can be decomposed by bacteria in
short amount of time. Odor is generated as a result of compounds generated during this process.
        Establishing a buffer zone between the treatment plant and residential areas and isolating
odor is the main method to prevent odor generated in the treatment plant to be dispersed to
settlements. Suggested buffer zone distances between treatment plants units and residential areas
are presented in Hata! Başvuru kaynağı bulunamadı.. Distance of the treatment units to the
nearest residential/commercial area is also presented in the table. As seen below, the nearest
Table V.12 Recommended Distances to Settlements for Odor Prevention and Nearest Receptors
        By good operation conditions and relevant measures taken for deodorization, disruptive
odors can be prevented. Below proposed mitigation measures will be implemented in three levels
for the WWTP. The first level measures are as follows:
       If odour nuisance prevails after the proper implementation of first level measures, the
second level measures will be taken. These are as follows:
               Plantation of trees in the WWTP site boundaries and the buffer zone around the
                treatment plant for the prevention of odor distribution.
               Addition of oxidizing material (such as hydrogen peroxide, sodium hypochloride)
                (oxidizing materials, prevent generation of especially hydrogen sulphide). Addition of
                sodium hydroxide can also be considered. Sodium hydroxide will dissolve hydrogen
                sulphur gas in water.
               Preventing anaerobic bacteria with control of pH levels or disinfection.
               Oxidizing odorous compounds by the help of chemicals.
      If nuisance still prevails after implementation of first and second measures, following final
measures will be implemented
           Apart from that, following mitigation measures will be implemented within the scope of
Project.
         Significant odor related nuisances are not expected to be observed as long as the
measures mentioned above are taken. In addition, in the operation phase of the Project, necessary
action shall be taken to comply with the provisions of Regulation on the Control of Odor-Causing
Emissions. There are no mandatory numerical standards set in Turkey for odor concentration in
ambient air at the site boundary or at receptor locations. If a new regulatory limit value will be set in
the future, the Project shall comply all the mandatory numerical standards.
       In conclusion, with the implementation of mentioned mitigation measures, the impact will
be medium, long-term, local and with low significance.
Construction Phase
        There are some geological risks in the construction phase of Oren WWTP as described in
the Soil Investigation Report prepared by GAB Mühendislik ve Danışmanlık Ltd. Şti. Therefore,
MUSKI shall take necessary mitigation measures to minimize risks and related impacts. The risks
are summarized below:
           The groundwater table levels observed in the boreholes drilled in the WWTP site vary
            between 2.67 and 4 m.
           The site has a liquefaction potential after 7.5 m depth.
       Another impact of the construction of the Project is loss of topsoil, which is mostly valid for
the WWTP site since the sewerage system and discharge line will follow cadastral roads and
pumping stations will be buried underground. Therefore, necessary mitigation measures to lower
the impact significance are developed and presented.
         In the construction phase of the project, soil contamination may be seen due to accidental
oil leakages in the areas where the works are carried out as well as improper disposal of wastes.
This may affect the soil quality in the project area, if necessary mitigation measures are not taken.
These impacts can be easily managed and mitigated to low in significance.
      Potential impacts and possible risks on the soil environment in case that necessary
measures will not be taken during land preparation and construction phase of the Project are
summarized below:
           Soil compaction as a result of soil stripping, levelling excavation and filling activities,
            work of construction machinery;
           Mixing of soil layers as a result of excavation and filling activities;
           Loss of topsoil at the WWTP site;
           Soil contamination as a result of oil or fuel leaks or spillage that may result from
            incidents and unexpected events; and
           Soil pollution which may occur in case of uncontrolled storage or disposal of solid
            and/or liquid wastes to be generated within the scope of the Project.
           Erosion potential due to earthworks
           In order to minimize the impacts on soil environment, the amount of soil that could be
            subject to compaction and contamination/pollution will be minimized by ensuring the
            use of only the designated work sites and routes for the construction machinery and
            equipment and field personnel.
           Wastes and wastewater to be generated during the construction phase of the Project
            will be stored and disposed in a controlled manner in accordance with the relevant
            regulations, WBG EHS Guidelines and in line with the management practices
            described in this report. Thus, it will not be possible for the wastes and wastewater to
            be generated in the Project Area interact with the soil environment and cause any
            impacts.
           The areas that the construction works take place will be reinstated after the completion
            of works.
           By establishing a suitable drainage system in the field, the potential impact of surface
            runoff will be minimized. In this context, drainage channels will be constructed in
            accordance with the topographical conditions of the site.
         Project’s anticipated impacts on geology, soils, and contaminated land are assessed as
low in significance.
Operation Phase
        In the operation phase of the Project, the activities will have a limited physical interaction
with the environment. In the operation phase of the Project, no additional significant direct impacts
on topography, soil and land use are anticipated under normal operating conditions. Impacts of
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                       Chapter V - Pg. 159/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
operation phase of the Project are related with the risks arise during repair and maintenance works,
such as spillage/leakage of wastewater, oil, and chemicals to soil and the permanent land use
change at the WWTP site, which is not used for any purpose before this Project. Therefore, the
impact significance is determined as negligible.
         During the construction phase, employees’ needs and dust suppression will create water
supply requirement. The drinking water needs of employees will be fulfilled by bottled water to be
purchased from the local market and the domestic water required will be met by water trucks until
the network connections are constructed. For dust suppression and tire cleaning, water will be
provided to site by water trucks with sprinkler system. The total amount of daily water requirement
is calculated based on the multiplication of number of employees that will be working at the peak
time of the phase and the daily water requirement for a person, which is 0.23 m3 (TurkStat, 2018).
Although the number of personnel required is not determined yet, it is assumed as 100. Therefore,
the daily water requirement of employees during the construction phase will be;
        Together with the amount of water required for dust suppression and tire cleaning, which
are predicted to be 10 m3/ day, the total water requirement during the construction phase will be 43
m3/day.
         The quality of drinking water that will be supplied to the Project shall be in compliance with
the Regulation Concerning the Water Intended for Human Consumption together with the
internationally accepted standards, such as WHO and WBG’s General EHS Guidelines.
        During the operation phase of the Project, the drinking water will be procured from the local
market, and for the other needs the tap water will be used as the connections to the water network
will be constructed. The total amount of water required by employees is calculated as in the
previous section. Although the number of personnel required is not determined yet, it is assumed
as 10. Therefore, the daily water requirement of employees during the operation phase will be;
        In addition to the daily needs of the personnel, there will be operational water
requirements, and these are presented together with the Project’s water requirement according to
its phases in Table V.13.
                                                                  Water Requirement
 Project Phase                 Intended Use
                                                       3
                                                     m /h              m3/day             m3/year
                          Drinking water / Tap
 Construction                                         0.96              23.00               8,395
                          water
 Construction             Dust Suppression            1.25              10.00               3,650
 Construction             Tire Cleaning               1.25              10.00               3,650
                          Drinking water / Tap
 Operation                                            0.10              2.30                840
                          water
        Domestic wastewater discharge criteria to the receiving bodies are regulated under Urban
Wastewater Treatment Regulation Annex-IV Table 1 and Table 2. The discharge limits given in the
regulation are presented below in Table V.14.
         Currently, there is no WWTP in Oren and the generated wastewater is either discharged
uncontrollably to receiving bodies or sent to the nearest WWTPs after pumped-out from septic
tanks by sewer trucks. The realization of the Project will enable MUSKI to manage the collection,
treatment and discharge of wastewater in Oren. The wastewater that is collected by sewerage
network and sent to Oren WWTP for treatment will be discharged to Hanay Creek after reaching
effluent concentrations and minimum treatment efficiencies given in Table V.14. Therefore, the
realization of the Project will positively affect the environment as well as public health.
Construction Phase
       In the construction phase of the Project, the water requirement will be very low. Since the
water demand/requirement within the scope of the Project will be provided/supplied by water
network which will be connected at the beginning of the construction period and by purchasing from
the market, a direct impact on surface water within the AoI of the Project is not expected.
       Also, during the construction phase of the WWTP tire cleaning ponds will be inserted to
both entrance and exits of the construction site. The water found in the cleaning ponds will never
be discharged into the environment under any circumstances; the water will be collected in
leakproof containers and will be disposed in a proper way.
        Construction activities may pose the potential for accidental release/leakages of petroleum-
based products, such as lubricants, hydraulic fluids, or fuels during their storage, transfer, or use in
equipment. All chemical storage containers, including diesel fuel, and hazardous liquid waste
drums/containers should be placed in secondary containment so as to minimize the risk of soil,
surface water and groundwater contamination during construction.
       In the construction phase of the project the impact will be direct and negative with short -
term duration, local and negligible significance.
Operation Phase
        During the operation phase of the Project, the regular maintenance works to be performed
on sewerage network, discharge line and pumping stations might create impacts similar to the ones
in construction phase. In Oren WWTP’s operation on the other hand, there will be storage of some
chemicals such as acids, bases, disinfectants, lubricants, etc. All storage tanks and drums will be
         In terms of flooding, there is no flood risk in Milas-Oren according to the models prepared
within the scope of the Western Mediterranean Basin Flood Management Plan studies (Ministry of
Agriculture and Forestry General Directorate of Water Management, 2019. Western Mediterranean
Basin Flood Management Plan). On the other hand, wastewater discharged into the creek might
change the hydrology of the stream. However, during the site visit the width of the creek bed which
is approximately 45 meters, was found to be sufficient for effluent discharge. Therefore, the creek
bed can handle the flow.
Mitigation Measures
         Water to be used in dust suppression during land preparation and construction phase of
the Project will be absorbed by soil or lost by evaporation. Therefore, there will not be any surface
runoff formation or wastewater generation due to watering for dust suppression.
        Within the scope of the measures to be taken in order to protect the water resources in the
region, the limited amount of domestic wastewater generated at site will be collected in the
container of toilet cabins to be established or leak-proof septic tanks to be constructed in the
Project Area during construction phase and will be sent to the nearest WWTPs after pumped-out
from septic tanks by sewer trucks. No discharge will be made to water resources in the land
preparation and construction within the scope of the Project.
In the operation phase of the Project, the following measures will be taken:
Construction Phase
         In construction phase, the major impact on groundwater may be seen due to accidental oil
leakages in the areas where the works with construction machinery are carried out as well as
improper disposal of wastes. This may affect the groundwater quality in the project area, if
necessary mitigation measures are not taken. However, it can be said that the impacts will not be
significant upon implementation of the mitigation measures and adherence to good engineering
methods.
        It is assessed that in the construction phase of the Project, the impact significance will be
negligible.
Operation Phase
         The impacts on groundwater resources in the operation phase will be similar to the ones of
the construction phase. The impacts will be mostly related with the accidental spills/leakages and
poor management of generated wastes and sludge. The impacts will be low and negligible in
significance upon adherence to good engineering methods.
Mitigation Measures
        Within the scope of the measures to be taken in order to protect the water resources in the
region, the limited amount of domestic wastewater generated at site will be collected in the
container of toilet cabins to be established or leak-proof septic tanks to be constructed in the
Project Area during construction phase and will be sent to the nearest WWTPs after pumped-out
from septic tanks by sewer trucks. No discharge will be made to water resources in the land
preparation and construction within the scope of the Project.
        The units of the Project that are in touch with water, wastewater and chemicals will be
constructed with using concrete with appropriate cement ratio and durability in order to provide
basement impermeability. Thus, no leakages to soil and groundwater will occur during the
operation phase of the Project.
     In all phases, the Project will follow the provisions of the national legislation together with
WBG EHS Guidelines and good international practices.
        A noise measurement study was conducted at the Project area in order to measure the
background noise level of the area. When the baseline study results are compared with the
standards given in national legislation and WBG EHS, it can be seen that the background noise
levels are generally in compliance. However, nighttime measurements are already above the limits
that are defined in WBG General EHS Guidelines: Environmental Noise. The high measurement
results might be related with traffic. Therefore, noise impacts should not result in a maximum
increase in background noise levels of 3 dB at the nearest receptor location off-site within the
scope of Project activities according to the WBG General EHS Guidelines and noise limit values of
RAMEN should also be complied with according to national legislation.
       The project activities within the construction phase are associated with a range of activities
that generate noise. The noise would be potentially generated by transportation vehicles,
machinery and outdoor equipment used for preparation of the terrain, trenching and drilling.
         The indicative list of machinery and equipment, which will be used during the land
preparation and construction phase and are likely to cause noise, and their number and noise
intensity levels are presented in Table V.15.
Table V.15. Machinery and Equipment and their Noise Intensity Levels (Lw)
        In order to assess the noise impacts of the activities that will be conducted during phase,
the total noise generations should be calculated for the worst-case scenario and should be
compared with the national legislative and WBG EHS Guidelines requirements. To satisfy this
need, noise generation calculation is performed below with the assumption of worst case scenario.
The worst case scenario assumes that all machines and equipment operates simultaneously at
maximum noise intensity levels at the same location in the Project Area.
        The formulas given below were used for the calculation of noise levels regarding land
preparation and construction phase of the Project. Formula (1) is used to calculate total noise level
at the source according to noise intensity level of each equipment, Formula (2) is used to calculate
the noise level that reaches a definite distance (Lpt), and Formula (3) used to include topographical
absorption effect into consideration.
                   C1        = 5xlog(do/d)
                   C1        =5xlog(1/50)
                   C1        =-8.49 dBA
        The distribution of noise generated with respect to distance from the source is presented in
tabular format in Table V.16 and graphically in Figure V.5. Environmental noise level decreases
below the regulatory limit value defined for construction activities (70 dBA) at a distance about 138
m from the source.
        As seen from the above, under the worst case conditions, noise level near the closest
building to the center of the WWTP Area caused by the construction phase of the Project is above
regulatory limit values. In addition, the noise that will be generated at the site will cause a
cumulative impact on the background noise level by reaching the nearest building at different
levels. In this context, the cumulative noise level expected at the settlement is calculated
numerically by logarithmically adding of the noise resulting from the construction activities to the
background noise level measured at the settlement. The cumulative noise at the receptor is given
in Table V.17.
Table V.17. Estimated Noise Level around the Nearest Residential Building
        As seen from the Table V.17, while the cumulative noise level of the nearest receptor is
above the limit values given in Turkish RAMEN. In addition to RAMEN, the calculated cumulative
noise levels exceed the limits defined by WBG General EHS Guidelines. In that case, necessary
measures defined below shall be taken to decrease the noise level at the nearest receptor.
       On the other hand, it is unlikely in reality that all construction machinery and equipment are
used at the same physical location and non-stop at maximum noise intensity levels (worst case
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                                  Chapter V - Pg. 166/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
scenario). In addition, as the construction activities will occur outdoors, it is expected that there will
be a decrease in noise level depending on the distance due to the atmospheric reduction in real
conditions. Similarly, vegetation cover is among the factors that could reduce the impact during the
spread of noise. However, since calculations are based on the worst case approach, factors such
as effect of location, atmospheric reduction, vegetation cover, etc. have not been taken into
consideration. According to all these evaluations, it is expected that in real terms the noise level at
the nearest building will be lower than the calculated value during construction activities of the
Project.
        As the noise to be generated at the Project Area during construction activities could have
an impact beyond the borders of the Project Area during certain times of the construction phase
and the background noise level at certain parts of the neighborhood could increase within the limit
values of RAMEN and WBG EHS Guidelines.
          In addition to that only electric poles with a base size of approximately 5m x 5m will be
erected for the energy transmission line. For this reason, excavation works will be limited for the
electric posts and construction activities will be carried out in a short period of time. Therefore,
impacts related to energy transmission line will be low in significance and short-term. As explained
above, if any of the electric poles or transmission lines hit or pass-through private parcels or private
users on public lands, a RAP, consistent with the Project RPF, will be prepared by MUSKI ahead of
the civil works and access to private lands.
            A Noise Management Plan that is in line with the OP/BP 4.01 Environmental
             Assessment and WBG EHS Guidelines (both general and sector specific) will be
             prepared by the construction contractor prior to the construction phase.
            Construction noise barriers will be used at north-eastern boundary of the WWTP site
             and around the TM-6 Pumping Station and by doing so, around 5 to 10 dBA noise
             reduction would be achieved at the receptor.
            Trees will be planted to the WWTP site, especially its north-eastern boundary, and
             around the pumping stations.
            It will be ensured that machinery and equipment will not be operated together in the
             close section of the WWTP Area to nearest building (north-eastern boundary) so that
             the noise level at the nearest buildings does not exceed the regulatory and WBG
             General EHS Guidelines limit values as it is calculated so.
            Attention will be given to the selection of equipment with low noise level.
            The maintenance of the construction machinery and equipment will be carried out
             regularly and regulatory speed limitations will be followed for construction vehicles and
             this should be included in the construction site transport and traffic management plan
             to be prepared by the contractor.
            The works will be performed day-time; no night work unless it is absolutely necessary.
            A grievance mechanism will be established to manage noise related grievances as
             well.
        Vibration that will affect humans or the structures in the vicinity is not expected to occur as
there will be no blasting activity within the project.
Operation Phase
        During the operation phase of the Project, noise will be generated from WWTP equipment
such as engines, compressors, pumps and blowers. The level of noise generated from the
equipment is expected to be constant as all equipment will be in operation during the plant
operation hours (24 hours). Equipment generating noise during the operation of the plant will be
        On the other hand, all pumping stations will be built underground and building materials
that provide sound insulation will be used. Also, machinery and equipment at the pumping stations
will be in enclosed structures. Therefore, no significant impact is expected from the pumping
stations regarding noise generation. However, regular maintenance activities will be carried in
order to ensure that.
         The impact is assessed as direct and negative with long term duration, local and low in
significance.
         In this section, potential impacts of the proposed construction activities for the Project on
the biological environment are considered. These impacts could be in effect during both the
construction and operation phases of the project. Potential impacts will affect terrestrial and aquatic
flora-fauna directly or indirectly. Therefore, impacts of project activities can be further divided into
the target group of biological elements as terrestrial.
         The following subsections define the potential impacts of the project considering the
foreseen project activities during construction and operation. The potential impacts are assessed
for terrestrial and aquatic flora and fauna. Mitigation measures to be taken in order minimize these
impacts are also included in the assessments.
         The impact of project activities on ecological components is related to the size of the
impact and the vulnerability of the recipient. For terrestrial flora-fauna species, size and
significance of the effects according to the matrices presented below have been determined in
accordance with the criteria determined according to the ecological sensitivities of the species. It is
known that the features of each step in the systematic classification of species are different from
each other and accordingly the shapes and dimensions of the influence from the Project will vary
within themselves. Sensitivities of terrestrial flora and fauna species determined within the Project
Area are explained in detail in the report. Criteria for significance for ecological components are
explained in following topic.
         The impact assessment criteria for the impacts on ecology and biodiversity were
determined, as high, moderate or low, based on the evaluation of magnitude of impact and
sensitivity/value of the receptors/resources. OP 4.04 definitions are used in habitat and species
assessments. These definitions are explained step-by-step.
        “Natural habitats are land and water areas where (i) the ecosystems' bio-logical
communities are formed largely by native plant and animal species, and (ii) human activity has not
essentially modified the area's primary ecological functions. All natural habitats have important
biological, social, economic, and existence value. Important natural habitats may occur in tropical
humid, dry, and cloud forests; temperate and boreal forests; Mediterranean-type shrub lands;
        “Critical Natural habitats: (i) existing protected areas and areas officially proposed by
governments as protected areas (e.g., reserves that meet the criteria of the World Conservation
Union [IUCN] classifications), areas initially recognized as protected by traditional local
communities (e.g., sacred groves), and sites that maintain conditions vital for the viability of these
protected areas (as determined by the environ-mental assessment process); or (ii) sites identified
on supplementary lists prepared by the Bank or an authoritative source determined by the Regional
environment sector unit (RESU). “
        Significance conversion: Such sites may include areas recognized by traditional local
communities (e.g., sacred groves); areas with known high suitability for bio-diversity conservation;
and sites that are critical for rare, vulnerable, migratory, or endangered species.
         Listings are based on systematic evaluations of such factors as species richness; the
degree of endemism, rarity, and vulnerability of component species; representativeness; and
integrity of ecosystem processes.
        Significant conversion may include, for example, land clearing; replacement of natural
vegetation (e.g., by crops or tree plantations); permanent flooding (e.g., by a reservoir); drainage,
dredging, filling, or channelization of wetlands; or surface mining. In both terrestrial and aquatic
ecosystems, conversion of natural habitats can occur as the result of severe pollution.
         Conversion can result directly from the action of a project or through an indirect mechanism
(e.g., through induced settlement along a road).
        Based on these criteria, sensitivity criteria for ecological components within the scope of
the project have been determined as given in Table V.18.
        In the construction phase of a project some direct or indirect impacts could be occurred.
The loss of habitat and biodiversity are the most important examples to direct impacts. However,
the planned Project will be realized in an already modified area. There is not any critical natural
vegetation which harbours wildlife, so there will not any sensitive habitat and vegetation loss during
the Project construction activities.
         Another direct impact of the construction phase will be the vehicle traffic for construction.
The fauna species which have limited mobility will be prone to fauna mortality. The risk of crushing
will increase as the animals cross the road.
         Indirect impacts of construction include disturbance in terms of noise and visual nuisance
and pollution. Some of the secondary impacts have been identified as changes in the composition
of soil and water quality, changes in air quality (dust generation, etc.), wastes to be generated due
to project activities and noise pollution that might impact species’ behaviour especially that of fauna
elements.
        IFC PS6 states that internationally and/or nationally recognized areas of high biodiversity
value are likely to be qualified as critical habitat. The closest natural protected area is Gokova
Special Protected Area and the closest KBA-IBA is Datca-Bozburun Peninsula KBA and IBA.
Although this seems to be ecologically important, it is obvious that the biological structure of the
project area and its immediate environment does not provide the characteristics of the protected
areas. In addition there are not any AZE sites within and around the Project Area. The impact of
construction activities on Internationally and National Recognized Areas is assessed as negligible.
Terrestrial Flora
        The most major impacts of this kind of projects on the terrestrial environment are generally
habitat and vegetation loss or damage. However Project will be built in semi-natural area with poor
vegetation. There are a lot of settlements in the vicinity of project area. Therefore, there are no
sensitive habitats or flora species and such an effect will not be the issue.
        The effects of the construction activities will include dust. These effects may soon lead to
effects on plant species within the vicinity of the project area, but none of these effects will have a
         According to the OP 4.04 “Natural habitat” definition, land part of the project area does not
have any natural habitat and wild life. To conclude, the impacts on the biological environment
during construction will be limited. It is considered that all the impacts will be minimized or
eliminated completely if necessary precautions are taken. The impact of construction activities on
terrestrial flora species is assessed as negligible.
Terrestrial Fauna
        There are poor vegetation and settlements in the immediate vicinity of the project area.
This makes mammals and bird species not preferring these areas. However, the effects of
construction activities on fauna species in the region can be seen. These effects will mostly consist
of secondary effects. Due to the construction activities, mortalities may be observed due to
disturbed fauna species and traffic congestion. At the same time, dust and noise formation due to
construction activities may also have a negative impact on fauna species. All these effects can be
eliminated by taking appropriate measures. The impact of construction activities on terrestrial fauna
species is assessed as negligible .
Aquatic Environment
        Hanay Creek, where the discharge will be made, is a creek that has lost its natural
characteristics due to anthropogenic effects. However, due to the construction activities, it is likely
that destruction in the physical and chemical properties of the species constituting the aquatic
biodiversity might occur. These impacts can be reduced to a low level with the relevant mitigation
measures. The impact mitigation measures to be taken on this issue are presented in the following
sections.
        The negative impact of the project's operational activities on terrestrial flora and fauna is
not expected. When necessary preventive measures are taken, natural life will continue in its
former state.
         In addition, during the operation, the receiving body will be free from intense pollution due
to the treated effluent discharge. This will be an important step towards conserving biodiversity and
protecting the water quality of the Hanay Creek. With the Project, the treated water will be
discharged to receiving body with nitrogen and phosphorus removal through the advanced
biological treatment process. Therefore, it is considered that the effect on the species in the
environment will be at the minimum level. This is considered as the most important positive impact
of the project on the biological environment.
Mitigation Measures
       The mitigation measures to be taken to the possible impacts on the terrestrial biologic
environment from the Project activities during the construction and operation phases are given
below.
          Prior to the land preparation phase, definite working areas will be set up where
           activities (e.g. vegetation clearing, vegetation removal, leveling and construction) and
           permanent structures (units and roads) will be established,
          Project construction sites and access roads will be separated from other areas with
           appropriate signboards, signs and fences. Therefore, staff and vehicle access to the
           area will be limited to the construction site,
          Avoid and/or minimize dust emissions by lightly watering the immediate surroundings
           of construction sites, and wetting the stored material,
          Construction waste generated due to project activities will first be stored at designated
           storage areas and then disposed,
          Construction work will be done gradually so that it will have enough time to escape for
           possible fauna species to be found,
          If there is a nest of birds species, the nest should be marked with a safety strip about 3
           meters in diameter and an expert ornithologist should be informed,
          If there is a species that has limited mobility, transfer to safer locations if encountered
           during construction,
          Measures to reduce noise are provide in Chapter V.4.5 Noise for details,
          Measures to reduce dust and air pollution are provide in Chapter V.4.1 Air Quality for
           details,
          Project workers will not be allowed to bring any live animals or plants into the
           construction site to avoid the risk of pest/invasive species establishing in the Project
           Area,
          Construction and operation sites will be fenced in order to prevent fauna species’
           entrance into these areas.
Aquatic Environment
       The following mitigation measures are recommended in order to minimize the potential
impacts of the Project on aquatic species:
          Mixing any chemical substances, that is used in the construction area, in waterbed
           and/or aquatic ecosystems will be prevented.
          Excavation materials will not be dumped onto riverbed.
          Especially during the breeding season of fish species (April-June), any intervention on
           riverbed will be prevented.
          The natural structure of the riparian vegetation will be preserved which forms the
           spawning and sheltering area for many aquatic organisms.
          Monitoring studies in Hanay Creek will be conducted in operational phase with aquatic
           biologist on appropriate seasons, as appropriate.
        In case any construction sources impact on rivers and/or streams within the scope of the
Project, following criteria of water quality should be taken into consideration and should be
monitored for the continuity of aquatic species.
          Water temperature is one of the most important factors impacting the life in aquatic
           ecosystems and it changes according to seasons, circulation of air and depth. Increase
           in temperature decrease the gas solubility (such as oxygen and corbondioxide) in
           water (Polat, 1997). In addition, increase in temperature can cause change in density
           and also viscosity of water. Beside, temperature affects species distribution, feeding,
           spawning and general behavior.
          Dissolved oxygen (DO) is another parameter that is recommended to be continuously
           monitored during the construction and operation phases of the Project. It is quite
Construction Phase
         During construction phase of the project, due to the nature and location of the works, there
will be impairment of quality of life. All the sewerage network and pumping station works will be
performed in the city centre and this will create nuisance for the people living or working nearby the
sites. However, the impacts will be short-term. In order to mitigate, which are assessed to have
medium significance, the sewerage network and discharge line construction works will be limited to
day-time only. Moreover, the construction plan will be disclosed to the public and this will also ease
the traffic planning. Therefore, the impact significance after implementation of mitigation measures
would be low.
        As for the construction of the WWTP, discharge line and energy transmission line, the
impacts of the works will again be short-term. In order to mitigate the impacts of the construction of
the WWTP the construction works will be limited to day time similar to the sewerage network. In
order to reduce the nuisance for the people residing in the area the construction plan of the WWTP
will be shared with public and the public will be informed about the issues regarding the traffic.
Since the pumping stations will be built underground, no impact on landscape and visual is
expected by them.
Operational Phase
         In operational phase, the aesthetics impacts will be mostly related with the WWTP and
energy transmission line, which will be a permanent impact. Pumping stations will be buried and
built on public lands registered as park. Landscaping of pumping stations will be conducted
compatible with the existing landscape of the park areas and trees will be planted, as appropriate.
In order to decrease the impacts of WWTP, it is recommended MUSKI to plant trees at the borders
of the plant and paint the visible buildings to colours suits to the background.
       All the wastes to be generated during the land preparation and construction and operation
phases of the Project are required to be properly managed in line with the requirements of national
The possible sources that will generate various type of waste are listed below:
         During construction phase of the Project, activities such as vegetation clearance, levelling,
construction and installation of main operation and auxiliary units, procurement, transportation and
assembly of units and equipment will be carried out. Solid waste types expected to be generated
within the scope of these activities are; municipal wastes, packaging wastes of system equipment
(e.g. wood, cardboard, plastic, etc.), hazardous wastes, special wastes, excavation and
construction wastes (e.g. scrap metal, wood, concrete waste, etc.), and waste system equipment
(panels, cables, electronic components). Hazardous and special wastes might contain chemical
substances (e.g. paint, solvent) or packaging materials and cloths contaminated with oils, waste
oils resulting from operation and maintenance of machinery and vehicles, solvents, accumulators,
batteries, filters, machine parts. These kinds of wastes will be stored in special compartments in
the Temporary Storage Area allocated for this purpose, in containers, separated from the non-
hazardous wastes. This area will have an impermeable base/ground and will be protected from the
surface flows and rain. Additionally, necessary drainage for the area will be provided. Hazardous
wastes will be collected and disposed of by companies licensed by the Ministry of Environment,
Urbanization and Climate Change.
        Table V.19 lists the types of wastes that can be generated during the construction phase of
the Project and their waste codes according to the waste lists given in the annexes of the Waste
Management Regulation
Table V.19. List of Possible Waste Types to be Generated during Land Preparation and Construction Phase of the
Project
         Solid waste management studies in Mugla province continue within the framework of
Waste Management Regulation. In the province, solid wastes collected by Bodrum, Dalaman,
Datça, Fethiye, Kavaklıdere, Köyceğiz, Marmaris, Menteşe, Milas, Ortaca, Seydikemer, Ula and
Yatağan Municipalities are stored by the Metropolitan Municipality in a total of six Solid Waste
Landfills in Datça, Fethiye, Milas, Marmaris, Menteşe and Ortaca in Muğla Province.
        Municipal wastes within the scope of the Waste Management Regulation are referred to
domestic wastes or commercial, industrial and institutional wastes similar to domestic wastes in
terms of its content or structure, which are defined with waste code of 20, in the Waste List given in
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                                  Chapter V - Pg. 175/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
Annex-4 of the Regulation and of whose management responsibility belongs to the municipality.
Therefore, these types of wastes will be stored separately from hazardous wastes and recyclable
wastes and will be collected regularly by Milas Municipality. Milas Solid Waste Landfill Facility of
Muğla Metropolitan Municipality is located in Milas district. The facility serves in Bodrum and Milas
districts and the wastes generated in these districts are stored. Milas Solid Waste Landfill Facility is
arranged in 2 lots and will be able to meet the 25-year need of the region. The facility has a storage
volume of 1 million 235 thousand 186 cubic meters and 250 tons of waste per day can be disposed
of at the facility. The infrastructure of the Milas Municipality is sufficient for managing the wastes
produced in the Project site.
        In addition, a pre-treatment facility will be established in the facility area, where waste with
economic value in mixed waste will be separated. In this way, it is aimed to use the facility for a
longer period by reducing the amount of stored waste.
        In order to determine the amount of municipal wastes to be generated at site, the average
daily municipal waste per person is taken as 1.08 kg according to the municipal waste statistics of
TURKSTAT in year 2014 (TURKSTAT, 2014). The estimated amount of municipal waste to be
generated during the construction phase of the Project, based on the number of people working, is
given below. This amount includes also separately collected fractions such as paper, cardboard,
glass, metal, plastic, etc. together with biodegradable wastes:
        There will be no cafeteria in the construction site. Thus, there will be no food preparation
related waste generation within the context of the Project. The food will be supplied through
catering services.
        The general composition of the municipal waste in Turkey is as demonstrated in Figure V.7
according to the results of the solid waste composition determination study made within the scope
of the Solid Waste Master Plan Project. 34% of municipal waste consists of kitchen wastes.
Separately collectable and recyclable fractions such as paper, cardboard, bulk cardboard, plastic,
glass and metal constitute 25% of municipal waste.
Figure V.7. Composition of Municipal Waste (former Ministry of Science, Industry and Technology, 2014)
           Food Waste                    : 5%
           Other Combustible             : 27%
           Other Non-combustible         : 31%
           Paper                         : 16%
           Cardboard                     : 2%
           Bulky Cardboard               : 6%
           Plastic                       : 3%
           Glass                         : 8%
           Metal                         : 2%
         Now, it can be said that approximately 5.4 kg of food wastes and 40 kg of separately
collectable and recyclable wastes will be generated daily during the construction phase of the
Project.
         Waste vegetable oil will not be generated at site during the construction activities as meals
for the staff will be provided by catering companies. Waste tire generation and storage will not take
place due to the fact that the tire changes of the construction machines and other vehicles to be
used at this stage will be carried out at the facilities in the region providing service for this purpose.
Besides, there will not be any significant amount of medical waste generation at site within the
scope of the Project, as there will no infirmary in the project site and Oren Primary Care Clinic will
be used for possible medical interventions in case of an incident during the activities. The negligible
amount of medical waste generation might happen as a result of the first-aid applications.
         Vegetation clearing and levelling works will be carried out at certain locations in order to
flatten the area during the construction phase of the Project. For all activities regarding excavation
storage, transport and reuse; provisions of Regulation on the Control of Excavation, Construction
and Demolition Wastes will be complied.
        The construction machinery will require oil changes during the land preparation and
construction phase of the Project, at least once in every two-month period of the phase. Oil
changes of the construction machinery will be carried out at services licensed for the maintenance
of the machinery. Thus, there will be no waste oil generation in the land preparation and
construction phase of the Project.
       The annual amount of waste battery per person in Turkey is six and this value corresponds
to 140 grams (Ministry of Environment and Forestry, General Directorate of Environmental
Management, 2009). According to this, the annual waste battery production of 100 people to be
employed during the construction phase of the Project is calculated as 14 kg.
        No significant impact resulting from waste generation is expected due to the nature and
scale of the Project, as explained above. Therefore, the impact is assessed as direct and negative
with short term duration, local and low significance. However, mitigation measures proposed in the
following sections in order to prevent and/or minimize likely impacts will be implemented such as:
           Wastes to be generated within the scope of the Project will be managed in accordance
            with the waste management hierarchy.
           Wastes will only be temporarily stored on site and final disposal will be carried out
            outside the facility
Operation Phase
         In the operation phase, there might be waste generation resulting from damaged,
malfunctioned or end-of-life equipment and material that could be replaced or controlled during
maintenance and repair activities to be performed periodically or in case of a breakdown. Also,
procurement of new equipment, pieces and others will also result generation of packaging waste.
Besides, personal protective equipment, clothes and rags used during maintenance and repair
activities might result a limited amount of waste generation. Milas Solid Waste Landfill Facility is
arranged in 2 lots and will be able to meet the 25-year need of the region. The facility has a storage
volume of 1 million 235 thousand 186 cubic meters and 250 tons of waste per day can be disposed
of at the facility. The infrastructures of the Milas Municipality is sufficient for managing the wastes
produced in the Project site.
        10 workers will be employed in the project's operation phase. Therefore, municipal waste
generation will be 13.5 kg/day and using the same approach as in land preparation and
construction, the recyclable portion of the municipal waste and the amount of food waste will be 10
kg/day and 1.35 kg/day, respectively. In addition, in addition to recycling municipal waste,
recyclable waste such as packaging waste, paper, cardboard, plastic and scrap metals are
expected to be taken into account.
       In the operation phase of the Project, due to the oil change needs of equipment such as
blowers, there will be limited amount of waste oil generation.
       Table IV.17 lists the waste types and waste codes that may occur during the operational
phase of the Project, according to the waste lists given in the Waste Management Regulation's
Annex.
        The most important waste that will be generated as a result of the activities of the WWTP is
sludge together with the screenings. The solid content of the sludge that will be generated will be
increased through sludge dewatering and drying units. The water that will be extracted from the
sludge cake will be sent back to the inlet of the WWTP. After dewatering, the sludge cake will be
transferred to a covered and appropriate container through the belt conveyor. After that, the excess
sludge will be analysed to determine compliance with the Annex-2 of the Regulation on Landfilling
of Wastes and if it is deemed appropriate, the sludge will be collected by the licensed disposal
companies determined by MUSKI every year. After that, the sludge will be disposed in accordance
with the provisions of Urban Wastewater Treatment Regulation and other relevant legislation.
According to the information retrieved from MUSKI, the sludge will be transported by competent
and licensed firms to the landfill which has enough capacity. Sludge will be stored in the landfill.
        If sludge would be determined as hazardous, the sludge will be sent to Anadolu Tehlikeli
Atik Depolama Sanayi ve Ticaret A.Ş. for disposal by competent and licensed firms.
         The impact is assessed as direct and negative with long-term duration, on-site and low in
significance. Mitigation measures proposed in the following sections in order to prevent and/or
minimize likely impacts will be implemented such as:
             Wastes to be generated within the scope of the Project will be managed in accordance
              with the waste management hierarchy.
             Wastes will only be temporarily stored on site and final disposal will be carried out
              outside the facility
             Waste recycling, transport and disposal will be carried out by means of licensed
              companies and/or related municipalities.
             Incineration or burying of wastes by any means at site and/or dumping of wastes to
              nearby roads or water resources will absolutely not be in question.
             All kinds of implementations that may threaten personnel or public health will be
              avoided in all activities involving collection, temporary storage, transport and disposal
              of wastes throughout the Project.
             Wastes to be temporarily stored on site will be delivered to licensed transport vehicles
              appropriate to the type of waste for disposal. Information related to the operations in
              this context will be recorded and the records will be kept in the administrative building.
        According to IPCC Guideline for National Greenhouse Gas Inventories, waste sector
includes the following components:
        In scope of this report, components 4A and 4B and partly components 4C, 4D and 4E are
investigated. According to 2007 data, waste sector is the second highest source of greenhouse gas
emissions in Turkey. However, there is no inventory on greenhouse gas emissions from generation
and disposal of WWTP sludge.
         In addition, activities which are subject to greenhouse gas monitoring, reporting and
verification are presented under heading “Activities subject to monitoring, reporting and verification
of greenhouse gas emissions” in Annex-1 of the Regulation on Tracking Greenhouse Gas
Emissions (dated May 17, 2014, Official Gazette No: 29003), and any of the components of this
Project are not listed in Annex-1 of the Regulation.
Construction Phase
        The Project’s contribution to the climate change during the construction phase will be due
to the emission of GHG. The majority of greenhouse gas emissions will be due to construction
machinery/equipment usage. The major greenhouse gas emission will be CO 2 emissions resulting
from the combustion of petroleum-based products, like gasoline, in internal combustion engines.
Relatively small amounts of methane and nitrous oxide will also be emitted during fuel combustion.
Therefore, these emissions will contribute to the climate change.
        The project’s contribution to the climate change through GHG emissions is assessed as a
negative and direct impact. The impact’s extent will be regional and duration will be short-term.
Although the sensitivity of the receptor is considered as medium, due to the usage of small number
of construction machinery/equipment, the significance of the impact is considered as low.
With the realization of proper mitigation measures, GHG emissions can be minimized.
         Within this regard, the following measures are suggested to mitigate the potential impacts
of the project on climate change through greenhouse gas emissions:
            Construction operations of the project will be in line with good industrial practices.
            Speed restrictions and equipment to optimize fuel efficiency will be adopted by
             construction vehicles.
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                      Chapter V - Pg. 180/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
           Regular maintenance of construction vehicles and equipment will be applied.
           Energy uses associated with construction vehicles and equipment will be monitored.
           Trainings will be performed on project personnel regarding energy efficiency
Operation Phase
        The project’s contribution to the climate change during the operation phase will be similar
to the one explained for the construction phase and the significance of the impact will be low. In the
operation phase, usage of fossil fuel burning equipment/machinery (including procurement of
materials) usage will be limited.
        GHG emissions generated operation phase of the project can be considered as relatively
short term emissions. With the realization of proper mitigation measures, GHG emissions can be
minimized.
         Within this regard, the following measures are suggested to mitigate the potential impacts
of the project on climate change through greenhouse gas emissions:
         Improvement of the existing roads or establishment of new access roads is not foreseen
within the scope of the Project as both components will use existing cadastral roads.
        The construction phase of the Project will last for 24 months (18 months for WWTP, 24
months for sewerage network) hence; vehicle load on existing traffic infrastructure will be
somewhat significant. However; as part of the Project, existing traffic volume will be affected only
during transportation of the excavation materials and receiving the relevant technical equipment.
During the construction phase of the Project, the traffic access will be interrupted. The major impact
of the works will be the ones related with the traffic.
       In the operation phase of the Project, main traffic load contributions will be observed due to
the sewage trucks of the close vicinity neighbourhoods, which have no connection to sewerage
network, and recycle and disposal companies’ trucks. It is anticipated that accumulation of sludge
cake and other disposable and/or recyclable wastes will be slow. Thus, the operation phase
impacts on transport network are considered as negligible.
         Moreover, since the Project is located in a touristic area, the impacts on the tourism should
also be assessed. The impact on tourism enterprises and local businesses during the construction
will only be temporary and anticipated to be insignificant. Roads might be closed for a short-time,
therefore, tourism enterprises and local businesses will not be significantly affected during the
construction phase.
         Within this regard, a project specific SEP will be prepared by MUSKI as well. The SEP will
include a robust stakeholder engagement and active management programme which enables
regular updates on construction progress and activities to all Project Affected Parties, including
reference to the Project Grievance mechanism to enable the prompt addressal of any issues which
may arise. Within this respect, any party who may potentially be significantly affected by temporary
economic displacement, will be identified within the SEP and regular engagement/communication
will be undertaken with these parties.
         Additionally, in case of an any unforeseen delays in the Project that could impact on the
project timeline and ultimately impede access to local businesses which may subsequently lead to
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                      Chapter V - Pg. 181/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
related potential livelihood impacts, a RAP (consistent with RPF) will be prepared and
implemented. The RAP will also consider an appropriate response to any potential temporary
economic displacement as a result of the construction programme.
         On the other hand, as stated before in the present case, there is no wastewater treatment
plant in the region. The hotels and other tourism complexes located in the region solve their
wastewater problems by their own means. For these facilities, the most common solution is to
install a package treatment plant followed by a septic tank. However, the summerhouses located in
the region are dealing with the problem in a primitive way, such as septic tanks. During the
withdrawal of these tanks by sewage trucks, odor and leakage of the wastewater occur quite
frequently. While this method is creating environmental nuisance among the residents of the
region, it also causes financial and managerial burden. It is envisaged that the realization of the
Project will positively contribute to the residents and investors of the region.
Mitigation Measures
        Within this regard, the following measures are suggested to mitigate the potential impacts
of the Project on socioeconomic environment:
           In case any road, facility, building etc. will be damaged due to the activities originating
            from the construction activities the necessary maintenance, improvement and
            compensation works will be done by the Contractor promptly in accordance with the
            responsible authority.
           Prior to construction activities, the Contractor will install all signs, barriers and control
            devices needed to ensure the safe use of the road by traffic and pedestrians, as
            required by the transport and traffic management plan to be prepared.
           The Contractor will take and ensure the implementation of necessary precautions in
            terms of road traffic safety along the road by cooperating with the relevant
            authority/administration. In addition, precautions will also be taken in the entry and exit
            of the treatment plant.
           Local authorities and residents in a working area will be consulted and informed before
            any detours for construction or diverted public traffic are established
           Trucks, trailers and other vehicles to be used to transport necessary equipment and
            materials will be provided to comply with the speed limits. MUSKI will ensure that the
            Contractor will comply with Highways Traffic Law, Road Transport Law and the
            regulations issued in compliance with these laws, as well as WB policies, standards,
            and guidelines.
           Signs, crossing guards and other appropriate safety features will be incorporated at
            grade level rail and road crossings.
           Disruptions to traffic and road transport will be minimized. The contractor shall ensure
            that the roads remain open to traffic during construction activities.
           Disposal sites and haul routes will be identified and coordinated with local officials.
           Construction vehicles will use temporary roads constructed for that purpose to
            minimize damage to agricultural land and local access roads. Where local roads are
            used, they will be maintained and reinstated to their original condition after the
            completion of work.
           MUSKI will ensure that the contractor will prepare and implement a Transport and
            Traffic Management Plan during the construction phase.
           MUSKI will ensure that a Waste Management Plan prepared and implemented during
            both construction and operation phases.
           MUSKI will disclose construction plan to the public. This will help people to know when
            there will be interruptions in traffic and on which roads the access will be limited.
           At the beginning of construction activities, a MUSKI Representative will conduct face to
            face meetings with the tourism enterprises and local businesses in order to inform
        Apart from that, the necessary measures regarding the COVID-19 Pandemic will be taken
during both construction and operation phases of the Project such as;
        This section presents application of WB OP/BP 4.01 and WBG General EHS Guidelines for
the Project.
        Although the number of personnel to be recruited is not yet decided it is estimated 100
workers will be employed during construction and 10 will be employed for operation. During
recruitment the priority will be given by MUSKI and contractors to local people during the
recruitment process.
        On the overall, labour and working conditions for the construction and operation phase
include the issues listed below:
      Commitments on labour and working conditions are concluded with a range of mitigation
measures for managing labour-related risks and impacts.
           The legal frame for the chapter can be drawn with two major national laws relevant to the
Project:
              The Labour Law (Act. No. 4857) which regulates the relations between an employer
               and an employee;
              Occupational Health and Safety Law (Law No: 6331) which regulates management of
               all occupational health and safety issues
        Turkish Labour Law and related regulations covers the basic principles of international
labor standards and the OP/BP 4.01 and WBG General EHS Guidelines in the issues of equal
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                     Chapter V - Pg. 183/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
treatment of employees, restrictions on the working age and employment of children, avoidance of
forced labour and ensuring occupational health and safety at the workplaces. Monitoring of the
implementation is essential to ensure full compliance of the activities with the relevant legislation.
        Turkey has ratified a broad range of International Labor Organization (ILO) Conventions
including the following:
       The requirements defined in the Turkish Occupational Health and Safety Law regarding the
HR Policy will be fulfilled in accordance with the ILO conventions.
        MUSKI will ensure that the contractors and sub-contractors provide workers with
documented information that is clear and understandable, regarding their rights under national
labor law; including collective agreements, their rights related to hours of work, wages, overtime,
compensation, and benefits as of start-up of working relationship and when any material changes
occur.
        MUSKI will ensure that the contractors and sub-contractors will not discourage workers
from electing worker representatives, forming or joining workers’ organizations of their choosing, or
from bargaining collectively, and will not discriminate or retaliate against workers who participate,
or seek to participate, in such organizations and collective bargaining.
        MUSKI will ensure measures to prevent child labour and forced labour. In this respect,
children under 18 years of age will not be employed during construction and operation stages.
Contractors will develop an age verification system to ensure no one under 18 years old are
involved in hazardous works.
         Construction stage of the Project includes assembling works for equipment and the use of
duty vehicles in this scope. As described in the WBG EHS Guidelines for Water and Sanitation;
work at sanitation facilities is often physically demanding and may involve hazards such as open
water, trenches, slippery walkways, working at heights, energized circuits, and heavy equipment.
The nature of the work may also involve entry into confined spaces, including manholes, sewers
pipelines, storage tanks, wet wells, digesters, and pump stations.
        Before the commencement of the construction works, contractor will prepare a site-specific
Emergency Preparedness and Response Plan and Occupational Health and Safety Management
Plan for the Project based on construction site OHS risk assessment in line with the Turkish
Legislation and international standards such as ILO standards inclusive of:
       In addition to preparing its own OHS management plan, the contractor will also ask the
subcontractor to prepare an OHS management plan in line with the Project’s OHS requirements.
These requirements will be added to the bid documents to be prepared for construction tenders.
        OHS Plan for the construction phase will include the measures listed below in order to
prevent accidents and risks but not limited to:
           All Project staff shall comply with the environmental, health and safety policies and
            guidelines.
           An OHS Management Plan will be prepared before the commencement of works that
            will also cover measures to address COVID-19 and/or any other
            pandemic/communicable disease risk.
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                   Chapter V - Pg. 185/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
        In order to minimize the risks and hazards that may arise (e.g. natural disasters,
         accidents, equipment malfunctions etc.) on human health and safety, safe working
         environments in the working sites will be established and physical hazards and risks
         will be prevented.
        The relevant plans and procedures of the relevant Turkish legislation and the MUSKI
         will be complied within the OHS measures and practices.
        Employees will be informed about the hazards that may cause from their work and thus
         a safer work environment will be created.
        Training will be given to employees according to the Regulation on the Procedures and
         Principles of Occupational Health and Safety Trainings. In this context, a training
         program will be prepared, training records will be kept and evaluation activities will be
         carried out after the trainings.
        Personal protective equipment will be provided to all employees and necessary training
         will be given for their use.
        Work areas will be equipped with warning signs (e.g. "Hazard", "Entry Prohibited", etc.)
         in accordance with the quality and potential risks of the work to be performed in that
         area.
        All necessary precautions will be taken in the Project Area to prevent possible fires
         from construction activities. Uncontrolled fires in and out of the field will be prevented.
        Smoking in areas where there is a risk of fire will be prohibited. All employees must
         have knowledge of what to do in the event of a fire.
        Project staff will include first aid trained personnel. In case of emergency where an
         intervention is required, personnel will be sent to the nearest health centre by
         appropriate means.
        The Contractor will apply the sufficiency of the technical requirement of the machinery,
         equipment, and tools to be used in the activities.
        Moving parts of machinery and equipment will be equipped with appropriate protective
         systems (e.g. metal shields etc.), minimizing the risk of injury or damage to the person
         using the machine or equipment.
        Personal factors that may create and control risks during activities (e.g. long hair,
         jewellery and accessory use, clothing etc.) will be removed from the site by the
         regulations brought by the field management. Project staff will be informed about the
         relevant regulations within the scope of the training program.
        Drivers and operators will be trained to comply with traffic rules and to control the
         vehicles and equipment they use against risks and hazards originating from vehicle
         traffic. Required traffic signs will be placed in the Project Site and its surroundings.
         Machine operators and other employees will be informed and alerted about the
         relevant signs. The wastes to be generated within the scope of the construction phase
         of the Project will be managed under the Waste Management Regulation and the
         negative impacts on public health will be minimized.
        Areas where excavation work is to be carried out will not be accessible other than the
         authorized personnel. The loading and unloading activities shall be carried out together
         with the persons to oversee the personnel to carry out the activity.
        Persons and/or organizations with the necessary permits will be assigned to ensure the
         security of the Project Area, especially the WWTP site. These persons and/or
         organizations shall regularly monitor the facility and its surroundings. The special
         security applications and officials’ authorities within the scope of the Project shall
         comply with the provisions of Regulation on the Implementation of the Law on Private
         Security Services and the Law on Private Security Services.
        In addition to safety personnel, monitoring of the WWTP site for security purposes will
         be provided by a closed circuit camera system that will be installed at appropriate
         distances on the site boundary (e.g. 30-40 m) to provide daytime and night-time
         monitoring of the whole area.
        Since the works will be performed at areas close to the public, the public access to
         these areas shall be restricted by any means. If a trench needed to be left open for
Mitigation measures that will be taken during the operation phase are listed below:
        The whole WWTP site will be fenced, the access of local people and wildlife will be
         controlled and encroachment will be prevented. The entry of personnel and third
         parties into the facility will be carried out in a controlled manner.
        Personal Protective Equipment will be provided for the workers according to the nature
         of work to be performed. The necessary trainings will be carried out for their use.
        Smoking will be prohibited where the risks of fire is high. All the workers will be
         informed about the action plan in a case of fire
        All equipment will be operated in proper working order.
        Procedures approved by the MUSKI in the maintenance and repair activities and the
         requirements of the technical specifications of the supplier companies will be complied
         with.
        The necessary health and safety signs and traffic signs will be placed around the
         project site. Employees will be informed and alerted about the subject matter markings.
        Trainings will be given to employees and operational and maintenance personnel
         within the scope of the Regulation on Procedures and Principles of Occupational
         Health and Safety Trainings and measurement and evaluation activities will be carried
         out after the trainings.
        Entrance of operation and maintenance personnel and third parties will be carried out
         in a controlled manner.
        Equipment that meets international standards in terms of electrical performance and
         safety will be used.
        MUSKI will ensure that subcontractors are reputable and legitimate enterprises and have
an appropriate ESMS that will allow them to operate in a manner consistent with the labor
conditions provided by MUSKI.
         MUSKI will monitor the performance of subcontractors such that human rights policy and
labor rights of all workers are exercised properly.
      MUSKI will ensure that workers of subcontractors have access to the overall grievance
mechanism to be established for the Project.
        MUSKI will monitor its primary supply chain for safety issues related to supply chain
workers, and where necessary MUSKI will introduce procedures and mitigation measures to
ensure that suppliers are taking steps to prevent or to correct life-threatening situations.
       In order to realize those, MUSKI will prepare a Contractor Management Plan and ensure its
implementation.
      MUSKI shall ensure that the impacts and measures defined by this ESIA and the relevant
ESMP are followed by the Contractor.
         In case when personnel or material or services required for the works to be carried out in a
construction project cannot be sourced from local sources; technical personnel with adequate
capacity or materials that meet international standards must be brought from outside the project
area. In such cases, suppliers, potential suppliers and potential jobseekers might move to the close
vicinity of the project area to provide goods and services to the Project and create an influx in the
region. In order to call this situation as workforce influx, which can be observed in any project,
people who will work on the project or provide goods and services to the project should be settled
quickly in the region. In such a case, people who settle in the area due the project may have a
negative impact on the local population (especially if the area is rural, remote and small).
        As mentioned earlier, 100 employees in the construction phase and 10 employees in the
operation phase is expected to be employed. In order to avoid the negative impacts of the
workforce influx, MUSKI will give priority to the local people in recruitment and this will be added to
the terms of the contracts of the Contractor and possible subcontractors in order to ensure this. In
contract process, MUSKI will request the contractor to plan the workforce and request from the
contractor to prepare a Workforce Management Plan if the requirement for a workforce other than
the one specified in this ESIA is seen. MUSKI will evaluate and submit this plan to ILBANK for
approval. In addition, there will be no accommodation within the scope of the Project. The Project is
not expected to cause workforce influx, if an unusual situation is not triggered. Therefore, it is
thought that the impacts of workforce influx will be insignificant.
         MUSKI and the Contractor shall ensure that code of conduct and public communication
trainings are given to all employees as an orientation training to prevent a possible future dispute.
       If it is possible and feasible to do so, local procurement options will be selected at all
phases of the Project and this will have a positive impact on the local economy of the region.
         The community health and safety impacts of the Project are mostly limited to the
construction phase. In the construction phase, emissions of gaseous pollutants and fugitive dust
from equipment and machinery used, noise generation, poor handling of wastes to be generated,
requirement to shut down the entire plant and/or specific units for construction works and risks
associated with community encroachment might create negative impacts on community health and
safety. Impacts associated with emissions, noise and waste generation will be managed with the
proper implementation of mitigation measures presented previously in the related sections of this
report.
        Construction works will involve increased traffic of heavy vehicles and equipment at local
level and traffic interruptions. Accidents and incidents leading to fatalities could result from traffic
operation while transporting equipment and materials to the construction sites as well as from truck
and vehicle movements. The significance of the impact is considered as medium and through the
implementation of mitigation measures; it could be reduced to low. Impacts associated with traffic
        Another risk would be community encroachment to the active worksites. The risks
associated with this issue would be easily mitigated to negligible significance through
implementation of mitigation measures presented at the end of this section.
        Similar to the impacts during the construction phase, improper handling of wastes would
create negative impacts on community health and safety. Differently from the construction phase,
sludge will be generated as a result of the operation of the WWTP. In case that the final sludge will
not be handled properly and/or disposed in an uncontrolled manner, magnitude of its impacts on
community health and safety would be somewhat significant.
         There will be an increase in the traffic load between the WWTP site and sludge disposal
sites in the operation phase. This increase will be lower than the one anticipated to happen during
construction phase since material transport during the operation phase will be limited with disposal
of wastes and sludge generated. The significance of the impact would be low. In the operation
phase of the WWTP, there would be times that the entire plant or specific units need shutdown due
to excessive precipitation, planned or unplanned maintenance requirements, or any other foreseen
or unforeseen challenges. A shutdown has major consequences for wastewater treatment,
especially biological wastewater treatment. Stopping a physical-chemical treatment generally does
not present many problems; however, turning down of aerobic and anaerobic treatment units has
major impact on the speed of the start-up process, which directly affects effluent quality. The
significance of the shutdown or failure related impacts on community health and safety would be
high without proper implementation of mitigation measures.
        Similar to the construction phase, community encroachment to the active worksites is also
a risk in operation phase. The risks associated with this issue would be easily mitigated to
negligible significance through implementation of mitigation measures presented at the end of this
section
Mitigation Measures
        In terms of community health and safety aspects, the generated wastes and sludge will be
disposed in accordance with the measures presented in Chapter V.4.8. In addition to that, MUSKI
will ensure that the Sludge Management Plan to be prepared before the commencement of the
operation phase covers community health and safety point of view. For the electrocution through
energy transmission line regular vegetation clearance and maintenance requirements of the energy
transmission line route will be carried out while communicating with the related authority.
      For the WWTP and/or unit shutdowns or failures during the operation phase, following
measures will be applied:
           All unit shutdown requirements will be scheduled at least one week beforehand and
            MUSKI will make necessary adjustments.
           In major shutdowns of the plant or biological treatment units that require longer times,
            nutrition levels will be maintained at the biological treatment units, aeration will be
            stopped after one day for aerobic processes.
        For the community encroachment that might happen during both construction and
operation phases of the Project, similar mitigation measures will be implemented. These measures
are as follows:
           Community Health, Safety, and Security Management Plan that is in line with OP 4.01
            and WBG EHS Guidelines (both general and sector specific) will be developed by
            MUSKI or security services provider before the construction phase. MUSKI and
            contractor will ensure that the plan is actively implemented.
           Persons and/or organizations with the necessary permits will be assigned to ensure the
            security of the Project Area (e.g. private security companies/officials). These persons
            and/or organizations shall regularly monitor the facility and its surroundings. The
            special security applications and officials' authorities within the scope of the project
            shall comply with the provisions of the Regulation on the Implementation of the Law on
            Private Security Services and the Law on Private Security Services.
           The entrance to the existing WWTP will continue to be restricted through strengthening
            security procedures such as repair of existing fences, installation of security cameras
            at key access points and use of a site visitor register.
           Sufficient lighting of the existing WWTP and active construction worksites will be
            ensured.
Construction phase
        During the construction phase (earth and construction works) of these type of projects it is
possible to discover unknown archaeological locations or findings. In this context, a potential
damage to archaeological or cultural heritage elements in the project area is possible. Uninformed
employees cannot identify and warn about possible chances for findings. Thus, it is possible to lose
or destroy important undiscovered archaeological locations, together with potentially valuable
evidence. With a properly managed chance finds procedure this impact can be mitigated.
        In a case of damage to and loss of assets during any phase of the Project, MUSKI will
compensate for the losses by swiftly identifying the damage on site or through its Grievance
Mechanism (building control team, written grievances, grievances collected from web site etc.).
MUSKI will make efforts to avoid any temporary and/or permanent damage or loss that may occur
during the construction. In addition, contracts made with contractor and sub-contractors will include
clauses to cover the damages given during the construction period stemming from civil works.
         The impact is assessed as direct and negative with short term duration, on-site and low
significance.
        In the light of the information given by MUSKI and the Ilbank the locations for the pumping
stations and WWTP is chosen as these lands were already categorized as public lands and owned
by Milas Municipality. The required permits regarding the transfer of these areas from Milas
Municipality to MUSKI were obtained.
       No project alternative concerns the scenario that the Project does not become operational
and negative or positive possible consequences of the scenario.
         As explained in the previous sections, the domestic wastewater generated in the service
area of the Project is currently being discharged to receiving environment without any treatment.
        In case of the project is not actualized, the situation will continue and the wastewater of the
region will be discharged uncontrollably without treatment. Therefore, its negative impacts will
continue and the discharge will create pollution stress on the environment. Furthermore, in order to
ensure that the settlements located in the service area of the Project will not be able to benefit from
wastewater services in a healthy and sustainable manner since necessary treatment is not applied.
Therefore, adverse impacts could continue to occur on public health, especially in terms of bathing
water.
       Since the WWTP site is already belongs to MUSKI, there will not be any new area use.
Therefore, the Project will not cause a significant change on land use.
        Construction phase short term impacts such as noise and dust generation will not occur if
the Project is not actualized. However, these impacts will be kept in regulation limits and will not
have significant impacts on local residents anyway.
Site selection criteria for the planned WWTP are listed below;
           Need of collection and treatment of wastewater at Oren and its close vicinity,
           The absence of residences in the immediate vicinity of the treatment plant,
           The absence of any rare and endangered flora and fauna species in the WWTP Area,
           The ownership of the area belongs to the General Directorate of Water and Sewerage
            Administration of Mugla,
           The facility should be easily accessible at all times during the year, energy,
            communication and drinking water connections should be made easily,
           The site should be close to a large body of water and/or a green field where the treated
            wastewater can be discharged or can be used for irrigation purposes,
           The wastewater treatment facility should have a low elevation area where the collected
            wastewater can be brought with gravity flow;
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                       Chapter VI - Pg. 193/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
           A moderately-slope site, if possible, should be preferred, especially as it would allow a
            suitable hydraulic profile.
        The area that meets the above criteria at the most appropriate level has been selected as
the Project Area which is also subject to this ESIA Report. The planned Milas – Oren Wastewater
Treatment Plant is at a point where most of the wastewater coming from the pump stations is
reached with gravity flow. Wastewater collected from TM 5 - 8, will be provided to the facility by
evaluating the most feasible condition of operating conditions. Also, as the site that the WWTP will
be constructed belongs to MUSKI, during the site selection this situation was considered.
         There are many criteria that should be taken into account in the construction of the
pumping station and should be examined by different engineering disciplines such as
infrastructure, hydraulic, electricity, machinery, ground engineering. The optimum solutions
regarding all these considerations are also made taking into account the possible environmental
and social impacts (noise, odor, etc.).
         The pumping stations that are planned under the scope of the Project will be constructed in
a manner that these stations will be completely closed to the outside and have no effect on human
health in terms of emissions of toxic gases or pest formation, etc. In addition, each pumping station
will also be equipped with an active carbon filtered odor removal unit and will be built using
advanced technology.
         During the site selection process for these pumping stations, the sites were selected
paying particular attention to that they are not categorized as agricultural lands but public lands
which are registered as parks. As it stated in the previous sections of the report, the sites that
chosen for constructing the pumping stations were originally belonged to Milas Municipality and the
required permits are obtained regarding the transfer of these sites to MUSKI. Also, the site
selection was made accordingly to the assessment and technical studies such as hydraulic
calculations and the selection of the optimum alternative was ensured. In addition, the areas where
the pumping stations are located are planned to be properly afforested and put into use as a park if
possible.
        Four underground pumping stations will be constructed within the scope of Project. It is
planned that two of the pumping stations will be constructed as package pumping stations whereas
the others will be buried reinforced concrete pumping stations. Advantages and disadvantages of
the buried pumping stations compared to above ground pumping stations are given below:
           Higher cost
           Difficult for maintenance activities
        Package pumping stations are also underground structures that can reach a depth of up to
5 m used for pumping wastewater at low flow rates. Its technical features are the same as semi
buried-aboveground reinforced concrete pumping stations and it does not differ except that it is
         In this section, the alternatives of the advanced biological treatment of the Milas – Oren
Wastewater Treatment Plant are examined. When BOD/COD concentrations and the discharge
criteria are taken into consideration within the scope of feasibility study, the necessity of the
advanced treatment for the removal of nitrogen and phosphorus is understood.
        In order to identify the process alternatives, working principle of the system is determined.
Sequencing batch or continuous treatment configurations can be applied. Sequencing batch
configuration is not recommended for touristic regions due to possible difficulties in operation and
high design flowrates. The big difference between summer and winter flowrates makes hard to
design and apply different operation alternatives (i.e. while operating whole lines during summer
and operating less lines during winter). Therefore, continuous configuration is recommended for the
plant.
The alternatives of the continuous advanced biological treatment for the plant are:
         When compared to conventional activated sludge, MBR systems requires %50 less area.
Also final sedimentation is not required in MBR systems, therefore filamentous growth and bulking
sludge problems occurring in sedimentation tanks are not possible. Separation of biomass is done
by filters. Moreover, MBR systems can be operated with high MLSS concentrations which cause
decrease in bioreactor volume and enable high organic loads. Also, toxic organics create less
operational problems and nitrification is not affected negatively as much in conventional activated
sludge. However, the configuration is more complex and control is harder than conventional
systems because treatment process takes place in single tank. Necessary engineering services for
operation and monitoring of development cost more than conventional systems. Moreover, initial
investment cost is higher than conventional systems because membranes are expensive and
delicate automation and control systems are necessary. For MBR to be able to operate properly in
long run, pre-treatment may be required; which requires additional costs. Furthermore, membranes
must be renewed within certain periods. Energy used during backwash and chemicals used in
backwash increases cost. Consequently, initial investment cost and operational cost are higher
than conventional systems, thus MBR systems are not utilized frequently.
        Other drawbacks of the MBR are the clogging of the membrane frequently during treatment
of industrial and domestic wastewater, absence of high flowrate system application examples, and
the need of field test during project design, which consumes time and cause additional cost. Figure
VI.2 presents overall flow diagram of MBR process.
        A2O (denitrification first or simultaneous systems), Step Feed, Bardenpho and UCT are the
conventional activated sludge systems. These systems can be converted to each other via placing
gates in transition points of tanks and inserting pipes. For the treatment plant, these systems are
recommended and explained below:
A2O Process
          A2O is a modification of the AO process which provides phosphorus removal via anaerobic
tank and nitrogen removal via anoxic tank. Hydraulic retention time of anoxic tank is about 1-1.5
hours. Denitrification takes place in anoxic reactor. In order to denitrify the nitrate produced via
nitrification in aerobic tank, recycling of some portion of the effluent of the aerobic tank to anoxic
tank entry and well mixing with the raw waste water is required. Necessary carbon source for
denitrification is contained in raw wastewater and conveyed to anoxic tank via activated sludge
recycle line. When it is not required anoxic and aerobic tanks to be separated, by providing recycle
in oxidation tanks and forming anoxic and aerobic parts in each tank, simultaneous nitrogen
removal can be achieved. Simultaneous systems are more suitable to treatment plants with low
flowrates.
        Entry of the dissolved oxygen to anoxic tank via nitrate recycle line must be minimized.
Nitrogen removal efficiency is directly proportional to internal recycle ratio. A 2O process is not
affected negatively by the changes in flowrate and pollution strength. Also, extended aeration
systems of the process provide sludge stabilization; thus there is no need to apply additional
sludge stabilization methods. Figure VI.3, A2O shows the flow diagram of the process.
        Step Feed configuration is capable of removing carbon and nitrogen and it is applied to
optimize the biological nitrogen removal. Raw wastewater is given to tanks at 2 or 3 points.
Therefore, second and the following anoxic tanks receive carbon source for denitrification from raw
wastewater. Increased denitrification efficiency and relatively constant MLSS concentration through
reactor can be counted as the advantages of this configuration. It is suitable for high nitrogen
concentrations. Figure VI.4 shows the flow diagram of the process.
UCT Process
        Activated sludge system configurations with the anaerobic, aerobic and anoxic tank are
needed to remove nitrogen and phosphor from wastewater. Nitrate and oxygen concentration
should be minimized in the recycle line from anoxic tank to improve phosphor removal and avoid
negative effects on treatment performance. That is why UCT process, which is a modification of
A2O process, is developed. Nitrate is recycled from aerobic to anoxic tank to reduce nitrate
concentration in the anaerobic tank and sludge is recycled from the final sedimentation tank to
anoxic tank and also from anoxic to anaerobic tank. UCT process is especially applicable for the
wastewater which has the low COD/TP to be able to increase phosphor removal.
         Hybrid system is obtained by the integration of the biofilm layers into the suspended
activated sludge system. As IFAS have more biomass, higher quality effluent standards and higher
influent loads are obtained. IFAS can be used in the domestic wastewater treatment plant, differs
from activated sludge process in that all biomass is not suspended, it will grow by holding onto a
media integrated in the aeration tank. Anaerobic and anoxic tanks are required for the nitrogen and
phosphorous removal as in the conventional activated sludge process.
            Non-widespread technology,
            High quality of staff needed for the maintenance and repair,
            Higher initial investment and operating costs than conventional activated sludge
             systems.
Figure VI.7 Flow Diagram of the Integrated Fixed Film Activated Sludge (IFAS) Process
         Sludge treatment is one of the most difficult processes in terms of operation and planning
in wastewater treatment plants. Although the amount of sludge produced corresponds to a low
percentage of 1% to 6% by volume of wastewater, the investment and operation costs of the
sludge treatment units are a higher in the total cost of the plant. In general waste management;
primarily strategy is to prevent waste generation or to minimize , then to recover it if possible, if it
cannot be recovered, it is essential to dispose of it in harmony with the environment. Sludge should
be reused on the soil, used as additional fuel in cement plants, anaerobic digestion and energy
recovery methods, and environmentally compatible and regularly stored and incinerated. In
general, the sludge from the system with the pumps is first condensed and then decomposed by
suitable sludge stabilization method selected under the sludge management, dewatered, dried and
removed using the final disposal methods.
        The concentration of the solid content of sludge coming from the wastewater treatment
units is increased by removing a portion of liquid fraction and volume is decreased in sludge
thickening.
Gravity Thickening
         Solid matter that has high density in the sludge and can precipitate spontaneously is
separated from water and becomes concentrated by gravity. It is applied to the preliminary settling
sludge which has the high inorganic and perceptible solid content. Sludge thickening is
accomplished in circular sedimentation basins. The solids concentration reached in the
gravitational sludge thickening is generally 5-10% solids content for preliminary settling sludge, 2-
3% solid content for waste activated sludge, 3-6% solid content for drip-filtered filter sludge and 4-
7% for mixed sludge.
Floatation Thickening
        It is primarily used to thicken the solids in biological process. The incoming solids is
concentrated as 2~8 times degree. Separation of solids is achieved by introducing fine air bubbles
created under pressure of several atmospheres into the liquid, attaching to solids to cause flotation
of solids. The condensed sludge that accumulates on the surface of the tank is stripped away.
Coagulant addition can also be performed to better perform solid/liquid separation in process.
Disadvantages of flotation thickening are equipment cost, maintenance-repair and high operating
cost depending on energy requirement.
        It is a common method for sludge thickening and dewatering. During the centrifugation
process, centrifugal force separates the solid substances and free water in the sludge. The most
advanced centrifuges are spinner type solids decanter type centrifuges. Entrance of the sludge is
continuous and the solid materials are gathered around the horizontal cylinder and paddled out of
the cradle. The water of the sludge is removed from the thickener by means of weirs.
 SUSTAINABLE CITIES PROJECT
 MILAS-OREN SEWERAGE SYSTEM AND WASTEWATER                                       Chapter VI - Pg. 200/259
 TREATMENT PLANT PROJECT FINAL ESIA REPORT
        Advantages of centrifugation;
Disadvantages of centrifugation;
        Gravity belt thickeners which are used in the waste activated sludge, aerobic and
anaerobic digestive sludge and some industrial sludge are applied in solids concentrations less
than 2%. Treatment sludge is distributed on the condensation band in the pore structure and the
water is directed by gravity effect after the addition of polymer. Through the use of a series of
scraper knives placed along the course of the band, the water is allowed to pass from the sludge to
the band.
        If sludge incineration applications are preferred as a final disposal, since the amount of
energy to be obtained as a result of the combustion process depends on the calorific value of the
sludge, it may be considered that not to conduct stabilization of the sludge since the stabilization of
the sludge will reduce calorific value of the sludge.
         In this case, however, the dewatered sludge must be transferred to the incineration
process without prolonged storage. The main technologies used for sludge stabilization are as
follows:
Aerobic Digestion
         Aerobic digestion can be applied to waste active sludge or mixed sludge (primary
sedimentation + waste active sludge or primary sedimentation + dripping filter sludge). Waste
activated sludge into a separate tank and aerated for a few days. Thus, the volatile solid materials
in the sludge are biologically stabilized.
Anaerobic Digestion
         Sludge in the anaerobic digestion, one of the most common processes used for sludge
stabilization, is heated at about 35°C to decompose organic and inorganic substances in the
mesophilic environment in the absence of molecular oxygen. Condensed primary sludge and
excess the biological sludge is pumped to the digesters where air intake is off and well mixing
conditions are provided. The organic substances in the waste sludge are biodegraded and
converted into various end products such as methane and carbon dioxide. The most important
parameter in reactor design is the waiting period, which can be accepted between 20-25 days. The
most important advantage of anaerobic digestion is that biogas can be obtained as a product and
heat and electricity can be supplied by the gas cogeneration system collected in the gas reservoirs.
        Electricity is generated by inserting the generator into the generator. The generator meets
some of the electricity needed by the treatment plant. The cooling water from the gas motor is used
as heat energy to protect the existing mesophilic temperature of the sludge digester.
         In chemical stabilization, the lime is added to the raw water to raise pH above 12. The
environment created by high pH is not suitable for the survival of microorganisms. Thus,
microorganism will not cause rot, bad smell and harmful health. Despite the low initial investment
cost, the operating cost is high due to the high amount of chemical addition and sludge formation.
         Extended aeration activated sludge systems have a high sludge age and therefore excess
biological sludge removed from the system is in a stabilized state. Larger tank volumes and more
oxygen supply are needed due high sludge age. It is stated that the process according to our
specification will be done according to ATV-DVWK-A131. Aerobic sludge stabilization in ATV-A131
is also recommended.
           Mechanical Thickener
           Aerobic Sludge Stabilization Pool
           Diffuser System
           Mixers, dosing pumps PE dosing unit
           Blower Unit
           Lime Unit is required.
           No energy recovery,
           More costly due to the energy costs which is spent for aeration,
           Weaker dewatering character of digested sludge,
           Process is affected by temperature, tank geometry, amount of solids in the input
            sludge, the quality of mixing / ventilation equipment and the type of tank building
            material.
        Also; in some facilities that are in MUSKI’s responsibility, for example existing Marmaris
Wastewater Treatment Plant; the aerobic sludge stabilization pool and lime unit were constructed.
It has been declared by the plant manager that the sludge stabilization pool has never been used
to date since these facilities were built. It is not possible to use the stabilization pool in all seasons
of the year since there are serious seasonal differences in the summer and winter pollution load of
the incoming wastewater. On the basis of all these evaluations, it was concluded that since it is not
economical and useful in the operation and it would be more appropriate to not construct aerobic
sludge stabilization due to insufficient land.
        To facilitate the final disposal of treatment sludge and to reduce the amount of sludge to be
removed, it is necessary to increase the content of solids and reduce the water content. The
reduction in the volume of sludge is of great importance for the capacity and investment of the final
disposal facilities. In addition, it reduces the cost of transporting and transporting sludge. Sludge
dewatering by mechanical methods, is the most preferred method for dewatering treatment sludge,
have low area requirement and higher dewatering efficiency. Decanter centrifuges, belt filter
presses and filter presses are most widely used dewatering equipment. Other mechanical sludge
dewaters are vacuum filters and drill presses which their usage rates are low.
         Today, centrifugation is one of the most common used methods. Centrifugation dewatering
is the treatment of sludge under the influence of centrifugal forces, making it more dense sludge.
The sludge, which usually contain chemicals such as polyelectrolyte, alum and limestone, are
given to centrifuges rotating about a horizontal axis at a speed of 1,600-2,000 rpm. The sludge
drained from the ditch is conveyed to the entrance to the wastewater treatment plant. The
dewatering yields are 90-95%, and the solids content of the outlet sludge can vary between 20-
25%.
         Dewatering with a belt filter is based on the principle that the squeezing of the sludge with
the pressure effect applied to the sludge will remove the water. Polymer addition is required to
purify the sludge quenching feature. Sludge is compressed between the two strips with a porous
surface, with the tension provided by the cylinders of different diameters. Belt filter designs have
basic features such as polymer conditioning, gravity drainage, under-compression and under-
compression. The filtration area provided by the belt filter, the use of additional rollers, and the belt
rotation speed are factors affecting the dewatering efficiency. Belt filter dewatering can be
dewatered to 18-20% solids in general, depending on the yield sludge characterization.
          Filter press dewatering is the method of dewatering mechanical sludge which provides the
oldest and highest output solid matter ratio. Higher pressures are applied in filter press dewatering.
It is a suitable method to be used in industrial sewage sludge which has discontinuous sludge feed
and low water supply ability. 28-30% solid matter ratios can be achieved.
         The water in the sludge has to be evaporated in order to dry the sludge. Since the water in
the sludge has different properties, it is generally considered in two main parts; free water not
bound to solid particles and part of the water that is difficult to evaporate. Both natural and
mechanical dewatering and drying methods have been developed for the sludge disposal with
different moisture contents according to the final sludge disposal method. The dried sludge is
biologically stable and has low water content as well as burning and storage, and so on. The
advantages of sludge drying are that the problem of odor is low, transport, handling and storage
costs are reduced considerably by reducing the volume of wet sludge in large volumes.
        The biggest advantages of dried the treatment sludge is the possibility of using the final
product as following areas;
Thermal Drying
        Thermal drying reduces the content of moisture in the sludge far below that obtained by
mechanical dehydration methods. Advantages of the dried sludge are lower transportation costs,
reduction of pathogens and better storage and marketing.
        In the contact drying process, heat is indirectly transferred to the sludge through the heated
surface while heat is directly supplied to the particles in the convection drying process. The most
common types of drying are tape, drum and fluid bed dryers.
        The sludge is poured onto the conveyor belt and the hot air is fed into the system. Since
the speeds of the driers are adjustable, it is possible to obtain between 65% and 90% solids. The
drying capacities of the dryers vary between 500 - 4000 kg H2O / hr. Mixing with dry matter (pre-
dried slurry) is required at the beginning of the system in order to pass the adhesive phase to
prevent plugging.
         Wet sludge is dried in specially prepared greenhouse areas where are extremely
transparent, with special coverings that prevent uncontrolled air change and therefore unnecessary
heat loss. With ventilators located in the unit, the drying air of the ambient air is introduced into the
circuit by the optimal air flow rate. Solar drying, climatic conditions and mud drying characteristics
are parameters that determine the design of the drying facility. Space required for drying depends
on sludge characteristics and atmospheric conditions such as precipitation, relative humidity and
temperature. The disadvantage of solar drying is that very high area is needed.
Lime Drying
        By the addition of slaked lime, to a hygienic and pathogen free product is obtained from the
waste sludge. This is achieved by reaction heat and alkalization. The obtained product has organic
content, can be used in agriculture and in soil lacking in lime.
         Land application, storage, incineration and composting alternatives can be applied for final
disposal. Information about the final disposal methods that can be applied to the treatment sludge
to be formed at the Milas – Oren Treatment Plant is as in the following.
Field Application
        The application of treatment sludge to agricultural areas aims to increase the use of
sludge, fertilizer as a source of nutrients or as soil conditioner and to increase agricultural
production. The pH of the soil to be applied to the treatment sludge must be 6.5. Thus, the
movement of heavy metals within the soil is limited.
         Regulation on the Use of Soil and Municipal Sewage Sludge, which was published in the
Official Gazette dated 03.08.2010 and numbered 27661, covers the technical and administrative
principles related to soil controlled use in such a way that treatment sludge does not harm soil,
plant, animal and human. It is strictly forbidden to use raw sludge to the soil according to the
Regulation. In treatment sludge, there are limit values for heavy metals, organic compounds and
dioxins. Heavy metal content limit values for soil and stabilized sludge to be used in soil are
presented in Table VI.1 and Table VI.2.
                                                     6≤ph<7                          pH≥7
 Heavy Metal (Total)
                                              mg. Kg-1 Oven Dry Soil        mg. Kg-1 Oven Dry Soil
 Lead                                                   70                            100
 Cadmium                                                1                             1,5
 Chromium                                               60                            100
 Copper                                                 50                            100
 Nickel                                                 50                             70
 Zinc                                                  150                            200
 Mercury                                               0,5                             1
       The maximum permissible values of stabilized sludge for organic compound are given in
Table VI.3 below. The limit value for the stabilized sludge content for the polychlorinated
dibenzodioxin / dibenzofurans is specified as 100 ng Toxic Equivalent kg-1 dry matter.
Table VI.3 Organic Compound Limit Values for Stabilized Sludge to be used in Soil
         There are important restrictions on the use of the sludge in the soil both in terms of soil
quality, and in the treatment sludge, heavy metals, organic compounds and dioxin content.
       There are significant restrictions on the soil quality of the treatment sludge in terms of
heavy metal, organic compound and dioxin content. Therefore, heavy metal content of the
treatment sludge within the limit values does not mean that the sludge can be used in the soil.
Composting
Disadvantages of composting;
            Operating costs are higher than laying out of the raw sludge.
            Ventilation causes energy consumption. In order to ensure an optimum C/N ratio, it
             may be advantageous to mix the treatment sludge with other wastes, and in the case
             where it is necessary to purchase these wastes, it can turn into a disadvantage.
Landfill
        Regulation on the Regular Storage of Wastes, which was published in the Official Gazette
dated 26.03.2010 and numbered 27533, covers the technical and administrative basis for the
prevention and management of environmental effects that may occur during the disposal process
of waste through the regular storage method.
Table VI.4 Waste Acceptance Limit Values for Class II Landfill Facilities
        The most important provisions in the Regulation on the Regular Storage of Wastes are
included in Temporary Article 4. Temporary Article 4 is stated below:
Incineration
         The disposal of sewage sludge directly for agricultural purposes or to the landfill site is
subject to increasingly stringent legal controls. Mixing domestic solid wastes and waste sludge
optimize the operation of the combustion plants. The volumetric reduction in very significant
quantities is the result of the burning.
         It is estimated that incineration will be increasingly used by burning sewage sludge, despite
the high investment costs in incineration systems, the incidence of incineration criteria, increased
costs associated with the processing of emission gases, and the difficulty of disposal of ash
resulting from combustion.
         The Regulation on the Waste Incineration, which was published in the Official Gazette
dated 06.10.2010 and numbered 27721, is designed to prevent the adverse impacts of the
incineration of wastes on the environment, in particular the risks that may arise for pollution
resulting from emissions in air, soil, surface waters and groundwater and human health.
           Some definitions related to sludge management within the scope of the Regulation are as
follows:
        Incineration plant: The units included in the facility for waste storage, preheating unit, waste
treatment and waste disposal systems, boiler, flue gas treatment systems, regular storage of
residues resulting from combustion and wastewater treatment, control and burning of flue, including
any other thermal disposal operations such as pyrolysis, gasification, or plasma processes,
including the combustion of waste by oxidation, which may or may not recover the resulting
combustion heat, including all the units involved in the process, including measurement devices
and systems used to monitor and record thermal disposal refers to any kind of system.
         The moisture content of the sludge is important for the incineration because dewatered
sludge with a moisture content of 70% or more cannot sustain the combustion process and require
additional fuel. For the sludge to be used as an alternative fuel, it must have a dry matter content of
at least 85%. Cement factories around the treatment plant accept dried sludge as fuel in calorific
value range 2,700-3,000 kcal.
           After burning, there is a significant reduction in the volume of the treated sludge (it is
            linked to the organic matter content of the sludge being burnt).
           Sewage sludge is used as energy.
           It is possible to use the by-products produced after the burning of the treatment sludge
            by recycling (asphalt road filler, concrete production and brick making).
           This process is not affected much by the sludge composition.
           They are reliable (known / implemented) systems.
           The smells are minimized due to the system being closed and high temperatures.
                                                                              Conventional
                                                Significance
 Concept                                                       MBR Process      Activated     IFAS Process
                                                   Level
                                                                             Sludge Systems
 Providing Discharge Standards                       15            5                4              5
 Ease of Operation and Maintenance                   10            2                5              3
 Land Requirements                                   10            5                3              4
 Electricity and Maintenance Costs                   20            2                4              3
 Resistance to flow and load changes                 10            3                5              4
 Investment Costs                                    20            2                4              2
 Aesthetic                                           5             4                3              4
 Sludge Disposal Costs                               10            4                2              3
 Total (weighted score)                             100           3.15            3.85            3.35
         Table VI.5 compares the advantages and disadvantages of three different biological
treatment processes capable of nitrogen and phosphorus removal. Conventional activated sludge
systems containing different configurations of classical activated sludge systems have been
evaluated together at this stage. All processes can provide discharge standards, but the highest
quality effluent is obtained by MBR and IFAS processes.
       Operating conventional activated sludge systems is easier than operating IFAS systems.
The fact that the application examples are not common in our country and that the application
examples for high wastewater treatment are limited is disadvantageous in terms of operation.
         The MBR process requires the least land due to the fact that the final settling tanks are not
needed. On the contrary, conventional activated sludge processes require higher space
requirements than other systems because of the higher pool volumes and the need for the final
settling tank. In IFAS systems too, low ventilation pool volumes arise due to the adherence of some
of the biomass to the media. Also the filtration unit instead of the last settling tank can also be
used.
        MBR systems have a disadvantage in terms of operating cost due to high electricity
consumption and frequent blockage of MBR units. In conventional activated sludge systems,
operating cost is much lower than other systems. In IFAS systems, low sludge production, high
energy consumption is the issue.
        The application example for resistance to flow and shock pollution loads are the most
common conventional activated sludge systems is more advantageous than other alternatives. In
the MBR process biological treatment performance against shock loads is significantly affected. In
case of shock loading in MBR application examples, the caps are automatically closed in biological
reactors and no water is taken into the system. This is a major drawback to the business. The IFAS
system has been evaluated as a process resistant to shock pollution loads and flow rates due to its
two types of microbial lifecycle.
        In the MBR system, the initial investment cost is higher than conventional systems due to
the high membrane cost and the need for precise measurement-automation. Similarly, the IFAS
process is often patented technology and has high initial investment costs.
        Since the most sludge production from the treatment alternatives under consideration is
related to the conventional systems, it has the highest score in terms of sludge disposal costs.
Since the least sludge production occurs in the MBR and IFAS processes, a lower rating is made.
        Sewage sludge that is generated after the treatment process in all wastewater treatment
plants operated by MUSKI is disposed of at Solid Waste Regular Storage Facilities operated by the
Environmental Protection and Control Department.
        Sludge treatment is one of the most difficult processes in terms of operation and planning
in wastewater treatment plants. Although the amount of the originating sludge corresponds to a low
percentage like 1% to 6% of wastewater in volume, the investment and operation costs of the
sludge treatment units have a higher share in the total cost of the plant. Therefore, it is of great
importance to select the most suitable sludge treatment system.
        When the sludge treatment and disposal alternatives, the project site, the location and
other related conditions of the wastewater treatment plants are taken into account, meeting legal
standards, operational and maintenance costs and ease of operation, initial investment costs and
land requirements of the place to be selected shall be considered.
         The assessment method for the sludge treatment system is the same as the one used for
wastewater treatment technologies. The criteria are weighted in percentiles according to the
significance level. The weighted scores have been achieved by multiplying the scores indicating
significance level with the technology scores (Table VI.6).
        It is required to select the most feasible disposal method for the sludge according to the
characteristics of the sludge generated from the treatment plant as a by-product and considering
the environmental conditions.
         Within the framework of the five basic criteria determined upon examination of Table VI.6,
the most appropriate method is the incineration system, as no sludge stabilization is required,
energy recovery is ensured, the products generated as a result of incineration are suitable for re-
use, and it decreases to a large extent in volume. The incineration operation is a system with a
high initial investment cost and operating cost, and which highly requires qualified personnel to
operate it.
         The other alternative is that the treatment sludge may be dried and stored by the licensed
companies. In this context, the analyses of the sludge shall be carried out in accordance with the
parameters specified in Appendix-2 of the “Regulation on Regular Storage of Wastes” entering into
force after publication in the Official Gazette dated 26.03.2010 and numbered 27533, and the final
disposal form shall be determined according to the results of the analyses. Albeit, while disposing
of the sludge, it is required to pay attention to the Provisional Article 4 of the “Regulation on the
Amendment of the Regulation on Regular Storage of Wastes” entering into force after publication in
the Official Gazette dated 11.03.2015 and numbered 29292.
        It is necessary that the society is firstly informed and its awareness on this issue is raised.
If the sludge cannot be used in the agricultural activities, energy recovery is provided by
transferring them to the cement plants as the final disposal method.
          Within this regard, final decision on sludge management is that the excess sludge which
will be generated during the operation of WWTP, will be analysed to determine compliance with the
Annex-2 of the Regulation on Landfilling of Wastes and if it is deemed appropriate, the sludge will
be collected by the licensed disposal companies determined by MUSKI every year. After that, the
sludge will be disposed in accordance with the provisions of Urban Wastewater Treatment
Regulation and other relevant legislation. According to the information retrieved from MUSKI, the
sludge will be transported by competent and licensed firms to the landfill which has enough
capacity. At the end, sludge will be stored in the landfill. Currently, the only option available is
landfilling, but incineration and other options will also be considered under the sludge management
plan to be prepared prior to operational phase. Within this regard, according to information
obtained from MUSKI, EIA Positive decision for incineration plant is obtained. However, whether
the plant will be constructed or not is depends on the supply of funding for this issue.
        During the operation period, documents related to the amount of sludge delivered to the
licensed disposal company shall be issued, and a record shall be kept within the scope of
monitoring.
Significance
Stabilization
Stabilization
                                                                                 Stabilization
 Concept
Lime Drying
                                                                                                                                                                                                                    Composting
                                                                                                            Centrifugal
                                                                                                                                                                                                     Application
                                                                                                                                                                          Sun Drying
                                                                                                            Dewatering
Dewatering
                                                                                                                                       Dewatering
                                                                                                                                       F i l t e r Press
                                                                                                                          Belt Press
                                                                 Anaerobic
                                                                                                                                                                                                                                              (Cement etc.
                                                                                                                                                                                                                                               Incineration
                                                                                                 Extended
                                                                                 Chemical
Aeration
                                                                                                                                                           Methods
                                                                                                                                                           Thermal
                                               Aerobic
                                                                                                                                                                                                                                              facilities)
                                                                                                 System
                                                                                 Sludge
                                                                                                                                                                                                                                   Landfill
                                                                                                                                                                                                     Land
 Land requirement*              20                 3                 4                4             3           5            4               4               4              1            3               1            3             2              4
Investment costs 20 3 3 4 3 3 4 4 3 4 4 3 3 4 1
Total (Weighted Score) 100 2.9 3.6 3.1 3.7 4.15 3.55 3.2 3.4 3.5 3 2.9 3.25 3.35 3.60
        The primary purpose of this ESMP is to ensure that the environmental requirements and
social commitments associated with the Project are carried forward into implementation and
operational phases of the Project and are effectively managed. The specific objectives are:
        1. Anticipating and avoiding, reducing, mitigating and if these are not achieved
           compensating any adverse environmental, social and health impacts resulting from the
           project activities;
        2. Prevent or compensate any loss of the affected person;
        3. Conducting all project activities in accordance with the applicable national legislation
           and in compliance with the World Bank’s Environmental and Social Framework (ESF)
        4. Prevent environmental degradation as a result of either individual subprojects or their
           cumulative effects;
        5. Enhance positive environmental and social outcomes;
        6. Ensure that the ESMP is feasible and cost-efficient;
        7. To act as an Action Plan in order to ensure that the project impact mitigation measures
           are properly implemented and monitored; and
        8. Ensure that all stakeholders concerns are addressed.
       This ESMP has been prepared consistent with the World Bank guidance specified in the
OP4.01.
         This ESMP was developed based on the findings of the impact assessment studies.
Identification of risks, mitigation and monitoring activities are considered for the two main phases of
the Project, which are “Construction” and “Operation”. In order to achieve environmental and social
outcomes consistent with the WB OP given in the Terms of Reference of the Project, potential
adverse environmental and social impacts anticipated in each phase of the project components will
be identified; requirements for effective and timely interventions will be defined; and means for
meeting these requirements will be described in the context of this ESMP.
       In order to reflect developments on detailed Project design, this ESMP will be improved
and evolved in the future. Hence, this ESMP is a living document that will be continuously reviewed
and updated by taking into account of these subjects:
           Monitoring results,
           Test and trial results performed during Project’s operation phase,
           Changes on national legislation and international standards, and
           Changes on Project parameters (if any).
        The following chapters were prepared to outline the legislative background for
management, organizations that will be responsible for the implementation of this ESMP,
specifications of the Project, mitigation plans for construction and operation phases of the Project,
monitoring plan, public participation, and inspection and reporting.
        The purpose of the Mitigation Management and Monitoring Plan presented under this
chapter is to apply mitigation measures to reduce the impacts of the Project, describe the roles of
the participating parties and key personnel responsible for the implementation of the mitigation
         Impact mitigation measures and activities are developed for all phases of the Project for
both project components and auxiliary facilities including energy transmission lines and working
camps in the scope of this ESMP and are in compliance with the national legislation as well as
international standards. Impact mitigation management plan is presented in Table VII.1 and Table
VII.2 for construction and operation phases, respectively.
                                                                         As required by Article 4 of Law on the Conservation of Cultural and Natural Properties (2863 Numbered Law),
                                                                          chance finds procedure will be implemented during land preparation and construction works. In this content:                                          Visual observation
      Archaeological                                                                                                                                                                           Contractor
                                                                          -    Construction works will be stopped immediately in case of finding any movable or immovable cultural                              No costs       Official notification to authorities
C13   and cultural     Chance finds         Adverse   Low                      asset by chance.                                                                                                Supervision      involved       Number of chance finds
      heritage                                                            -    Related Civilian Authority or Museum Directorate will be informed latest in three days.                         Consultant
                                                                                                                                                                                                                               Monitoring Report Findings
                                                                          - Works will not proceed until official notification is received
                                                                          Subcontractors will be reputable and legitimate enterprises and have an appropriate ESMS that will allow them
                      Workers Engaged                                      to operate in a manner consistent with the labor conditions requirements,                                             Contractor
                                                                                                                                                                                                                  Included in    Sub-contractor Agreements
                      by Third Parties                                    The performance of subcontractors will be monitored such that human rights policy and labor rights of all             MUSKI
C15   Labor Force                            Adverse   Low                                                                                                                                                        construction   Grievance Records
                      and the Supply                                       workers are exercised properly,                                                                                       Supervision      costs          Monitoring Report Findings
                      Chain                                               The workers of subcontractors will have access to the overall grievance mechanism to be established for the           Consultant
                                                                           Project.
      Landscape and                                                                                                                                                                              Contractor
                      Nuisance for the                                    The construction works will be limited to day time only.                                                                               No costs       Visual observation
C16   Visual                                 Adverse   Medium                                                                                                                                    Supervision
                      People                                              The construction plan will be disclosed to the public.                                                                                 involved       Monitoring Report Findings
      (Aesthetics)                                                                                                                                                                               Consultant
                      General
      Community
                      construction related                                A Community Health, Safety, and Security Management Plan that is in line with WBG OP/BP 4.01                          Contractor       Included in
                                                                                                                                                                                                                                 Incident records
C17   Health and                             Adverse   Low                 Environmental Assessment and WBG EHS Guidelines (both general and sector specific) will be developed by               Supervision      construction
                      impacts on                                                                                                                                                                                                 Grievance records
      Safety                                                               the construction contractor                                                                                           Consultant       costs
                      community
                                                                          Community Health, Safety, and Security Management Plan that is in line with WBG OP/BP 4.01 and WBG
                                                                           EHS Guidelines (both general and sector specific) will be developed by MUSKI or security services provider
                                                                           before the construction phase. MUSKI and contractor will ensure that the plan is actively implemented.
                                                                          Persons and/or organizations with the necessary permits will be assigned to ensure the security of the Project
                                                                           Area (e.g. private security companies/officials). These persons and/or organizations shall regularly monitor the      Contractor
      Community                                                            facility and its surroundings. The special security applications and officials' authorities within the scope of the                    Included in    Active CCTV system
C18   Health and      Encroachment           Adverse   Low                 project shall comply with the provisions of the Regulation on the Implementation of the Law on Private Security       MUSKI            construction   Security reports
      Safety                                                               Services and the Law on Private Security Services.                                                                    Supervision      costs          Visitor logs
                                                                                                                                                                                                 Consultant
                                                                          In addition to safety personnel, monitoring of the Project Site for security purposes will be provided by a closed
                                                                           circuit camera system which will be installed at appropriate distances on the site boundary (e.g. 30-40 meters)
                                                                           to provide daytime and night-time monitoring of the whole area.
                                                                          Entry of staff and third parties into the working site will be carried out in a controlled manner from the doors at
                                                                           which authorized security personnel will work.
                                                                               Apart from that, following mitigation measures will be implemented throughout the Project.
                                                                                   Establishment of an operating grievance mechanism to manage odor related grievances.
                                                                                   Maintaining pipelines and ensuring effective management and operation of the sewerage system including
                                                                                    effective maintenance of all elements of the sewerage system and rapid response to emergencies.
                                                                                   Regular maintenance and cleaning works shall be conducted on the machinery and equipment in order to
                                                                                    prevent occurrence of odor.
                                                                                   Regular and sufficient ventilation at the pumping stations will be provided.
                                                                                   Trees will be planted around the pumping station areas.
                                                                                  During the procurement of equipment and machinery, sound levels given in the technical
                                                                                   specifications/data sheet will be taken into consideration,
                                                                                  Relevant provisions and limit values of national legislations and World Bank Group’s General EHS
                                                                                   Guidelines and Sectorial Guidelines will be complied with during the operation phase.
                                                                                                                                                                                                                                                          Noise Measurement Results
                         Increase in noise                                        Equipment generating noise during the operation of the plant will be located in isolated closed buildings and
 O2        Noise                               Adverse   Low                                                                                                                                       MUSKI              Included in the operational costs   Grievance Records
                         levels                                                    some of them will be submerged in wastewater, if necessary.
                                                                                                                                                                                                                                                          Monitoring Report Findings
                                                                                  All pumping stations will be built underground and building materials that provide sound insulation will be
                                                                                   used.
                                                                                  Natural noise barriers such as trees will be planted particularly to the east and south borders of the WWTP
                                                                                   and around the pumping stations.
                      The existence of                                          It is recommended MUSKI to plant trees at the borders of the plant
       Landscape
                      the Treatment Plant                                       MUSKI should paint the visible buildings to colours suits to the background.
O9     and Visual                            Adverse   Low                                                                                                                                            MUSKI              Included in the operational costs   Monitoring Report Findings
                      and pumping                                               Landscaping of pumping stations will be conducted compatible with the existing landscape of the park
       (Aesthetics)
                      stations                                                   areas and trees will be planted, as appropriate.
                                                                                Generated wastes will be managed as described in the Waste Management Plan. Uncontrolled disposal of
                                                                                 wastes is forbidden and all wastes will be sent to final disposal and/or recycle by licensed companies.
                                                                                Generated sludge will be collected in impermeable containers and will be sent to final disposal based on
                                                                                 the characteristics of the sludge, in accordance with the Sludge Management Plan. Uncontrolled sludge
                      Community’s                                                disposal is forbidden.
                      exposure to
                      disease due to                                            All unit shutdown requirements will be scheduled at least one week beforehand and MUSKI will make                                                                           Monitoring Report Findings
       Community      improper handling                                          necessary adjustments.
                                                                                                                                                                                                                                                             Period of disease occurrence
O10    Health and     of wastes, including   Adverse   High                     In major shutdowns of the plant or biological treatment units that require longer times, nutrition levels will be    MUSKI              Included in the operational costs
       Safety                                                                                                                                                                                                                                                Training records
                      sludge                                                     maintained at the biological treatment units, aeration will be stopped after one day for aerobic processes.
                                                                                 Recirculation will be turned down for anaerobic processes, and pH regulation and nutrient dosing will be                                                                    Grievance records
                                                                                 conducted only when the gas production is less than 10% of the original gas production.
                      Failure of operation
                                                                                During the longer shutdowns or failures, MUSKI will inform Provincial Directorate of Environment,
                                                                                 Urbanisation and Climate Change regarding the situation.
                                                                                During excessive loads that the WWTP cannot handle, the bypass line of the existing plant will be used to
                                                                                 bypass the load.
                                                                                Community Health, Safety, and Security Management Plan that is in line with WBG OP/BP 4.01 and WBG
                                                                                 EHS Guidelines (both general and sector specific) will be developed by MUSKI or security services
                                                                                 provider before the commencement of operation phase. MUSKI will ensure that the plan is actively
                                                                                 implemented.
                                                                                Persons and/or organizations with the necessary permits will be assigned to ensure the security of the
       Community                                                                 Project Area (e.g. private security companies/officials). These persons and/or organizations shall regularly                                                                Active CCTV system
       Health,        Community                                                  monitor the facility and its surroundings. The special security applications and officials' authorities within the                                                          Security reports
O11                                          Adverse   Low                                                                                                                                            MUSKI              Included in the operational costs
       Safety and     encroachment                                               scope of the project shall comply with the provisions of the Regulation on the Implementation of the Law on                                                                 Visitor logs
       Security                                                                  Private Security Services and the Law on Private Security Services.
                                                                                The entrance to the existing WWTP will continue to be restricted through strengthening security procedures
                                                                                 such as repair of existing fences, installation of security cameras at key access points and use of a site
                                                                                 visitor register.
                                                                                Sufficient lighting of the WWTP will be ensured.
       Community      Electrocution from
                                                                                Regular vegetation clearance and maintenance requirements of the energy transmission line route will be                                                                     Incident Records
O12    Health and     Energy                 Adverse   Low                                                                                                                                            MUSKI              Included in the operational costs
                                                                                 carried out while communicating with the related authority.                                                                                                                 Monitoring Report Findings
       Safety         Transmission Lines
        Information collected with the monitoring can be used to improve management plans
during all phases of the Project. While impact assessment attempts to encompass all relevant
potential impacts to identify their significance and include appropriate responses for these impacts,
unanticipated impacts may still arise, which can be managed or mitigated before they become a
problem using the information obtained through monitoring. Therefore, monitoring will ensure the
successful implementation of the mitigation/management plans and optimize environmental
protection through good practice at each and every stage of the Project.
        Some of the monitoring parameters are determined in the scope of engineering design
studies. Monitoring studies will ensure the accordance with the relevant legislation, contract
necessities and implementation of impact mitigation measures.
Monitoring activities are submitted in tabular form in Table VII.3 and Table VII.4.
                                                                                                                                       When the
                                                                                      Where the
                                Which parameters           Why the parameters                                 How the parameters       parameters
 No.      Subject                                                                     parameters shall be                                                  Costs            Responsibility
                                shall be monitored?        shall be monitored?                                shall be monitored?      shall be
                                                                                      monitored?
                                                                                                                                       monitored?
                                Amount of refilled,
                                stored, and disposed
                                excavation materials
                                                                                                                                       Once in a week
                                Amount of stripped                                                                                     starting from the
                                and reused topsoil by      To assess the efficiency                           Visual observation                           Included in      Contractor
          Storage and usage                                                           Construction site and                            initialization of
 C1                             indicating reuse           of the waste                                                                                    construction
          of excavation waste                                                         storage areas           Records                  land preparation                     MUSKI
                                locations                  management                                                                                      cost
                                                                                                                                       and construction
                                Storage conditions of                                                                                  phase
                                topsoil (humidity and
                                pile height)
                                                                                                                                       Upon grievance
                                                                                                                                       and any
                                                                                                                                       contamination
                                                                                                                                       observed during
                                Soil quality, including,                                                                               spot checks
                                pH, heavy metals,
                                phosphorus,                                                                   Sampling and analysis    Once prior to
                                nitrogen, Na, Ca,          To assess if there are                             Spot checks              initialization of
                                                           any pollution/             Work sites and                                   land preparation    Included in      Contractor
                                salts, PAHs
 C3       Soil pollution                                   contamination in the       storage areas           Grievance registration   and construction    construction
                                hydrocarbons                                                                                                                                MUSKI
                                                           soils                                                                       phase               cost
                                Number of oil/fuel                                                            Environmental incident
                                and chemical                                                                  registry                 Once in a week
                                leakages/spills                                                                                        starting from the
                                                                                                                                       initialization of
                                                                                                                                       land preparation
                                                                                                                                       and construction
                                                                                                                                       phase
                                                                                                                                Quarterly starting
                        Settled dust and                                                                                        from the
                        PM10/2.5                                            Nearest sensitive                                   initialization of
                                                                                                    Sampling/analysis           construction         Included in      Contractor
                                                                            receptors for
C5    Air Quality                               To assess the air quality                                                       phase                construction
                        Maintenance records                                 measurements            Maintenance records                                               MUSKI
                                                                                                                                                     cost
                        of all machinery and                                (Nearest resident)                                  Upon grievance
                        equipment                                                                                               (for settled dust
                                                                                                                                and PM10/2.5)
                                                                                                                                                     Included in      Contractor
                                                To assess the noise         At the complainants     Noise level
                                                                                                                                Upon grievance       construction
                                                levels                      house/workplace         measurements                                                      MUSKI
                                                                                                                                                     cost
                                                                                                                             Daily basis
                                                                                                  Visual observation         starting from the
                                                                                                                                                  Included in      Contractor
                       Number of chance           To protect and conserve   On and around the                                initialization of
C9    Chance Finds                                                                                Official notification to                        construction
                       finds                      the cultural heritages    working location                                 land preparation                      MUSKI
                                                                                                  authorities                                     cost
                                                                                                                             and construction
                                                                                                                             phase
                            Number of received
                            grievances                                                                Grievance records
                            Number of open and                                                        (grievance log, received
                            closed grievances       To assess the success                             grievance forms, etc.)      Monthly during      Included in      Contractor
C10   Grievances            Average grievance       in responding the needs   Administration office                               the construction    construction
                            response and closure    of PAPs                                           Grievances related to the   phase               cost             MUSKI
                            time                                                                      GBV and SEA/SH
                            Variety of grievance                                                      allegation
                            channels
                            Number of
                            accidents/Injuries
                                                                                                      Visual observation
                            Number of                                                                                             Daily basis
                            nonconformities                                                           Site inspection             starting from the
                                                    To evaluate the project                                                                           Included in      Contractor
      Occupational Health                                                                                                         initialization of
C12                         Period of disease       in terms of OHS           Construction site       Incident Records                                construction
      and Safety                                                                                                                  land preparation                     MUSKI
                            occurrence              implementations                                                                                   cost
                                                                                                      Training Records            and construction
                                                                                                                                  phase
                            Number of personnel                                                       Work Permits
                            who are infected with
                            an infectious disease
                            Number of employed
                            person from the local
      Job creation and      community                                                                 Employment records          Prior to
                                                    To record the job                                                                                 Included in      Contractor
      impacts on local                                                                                                            construction and
C13                         Business                related effects of the    Oren and its vicinity   Procurement records                             construction
      businesses                                                                                                                  during                               MUSKI
                            growth/increase in      Project                                                                                           cost
                                                                                                      Inspection                  construction
                            income for local
                            communities
                                                       To monitor improper
                                                                                                                                        Quarterly starting
                                                       working conditions, child                            Employment records                               Included in      Contractor
                                                                                                                                        from the
C17   Labor Force             Local employment         labor, forced labor and     Administration office                                                     construction
                                                                                                                                        operation phase
                                                       unregistered                                         Grievance records                                cost             MUSKI
                                                                                                                                        of the Project
                                                       employment
                                                                                                                                      When the
                           Which
                                               Why the parameters        Where the parameters         How the parameters shall be     parameters
 No.       Subject         parameters shall                                                                                                               Cost          Responsibility
                                               shall be monitored?       shall be monitored?          monitored?                      shall be
                           be monitored?
                                                                                                                                      monitored?
                           Conditions of the
                           chemical and
                           disinfectant                                                                                               Daily basis
                           storage area                                                                                               starting from the
           Storage and                         To see if the chemicals                                Visual observation                                  Included in
                           Maintenance                                                                                                initialization of
 O1        usage of                            are handled in a proper   Storage areas                                                                    operation     MUSKI
                           records of                                                                 Chemical dosing system checks   the operation
           chemicals                           way                                                                                                        cost
                           chemical dosing                                                                                            phase of the
                           system                                                                                                     Project
                           Number of leaks,
                           spills, etc.
                                                                                                                                      Weekly basis
                           Type and amount                                                            Visual observation              starting from the
                                                                         Treatment plant site,                                                            Included in
                           of wastes           To record the waste                                                                    initialization of
 O2        Wastes                                                        storage areas and            Waste Records                                       operation     MUSKI
                           generated           categories and amounts                                                                 the operation
                                                                         administration office        Site inspections                                    cost
                           including sludge                                                                                           phase of the
                                                                                                                                      Project
                                                                         Nearest sensitive
                                                                         receptors
                                               To assess the impacts     At pumping stations          Grievance records                                   Included in
 O3        Odor            Odor level          of the odor on the        Manholes                     Site Inspection                 Upon grievance      operation     MUSKI
                                               vicinity                  Close vicinity of the WWTP   Sampling/analysis/measurement                       cost
                                                                         Close vicinity of the
                                                                         pumping stations
                                                                         Nearest sensitive
                                                                         receptors                                                                        Included in
                                               To assess the noise                                                                    Upon grievance
 O4        Noise           Noise level                                   or                           Noise measurement                                   operation     MUSKI
                                               levels                                                                                 Once in a year
                                                                         At the complainant's                                                             cost
                                                                         house/workplace
                                                                                                                                       Continuous
                        Legislation                                                                                                    monitoring for the
                        applicable                                                                                                     detectable by
                        parameters, and                                                            Automatic measurement for           automation           Included in
       Effluent water                        To assess the efficiency    Oren WWTP discharge                                           measurement
O6                      parameters to be                                                           relevant parameters, and                                 operation     MUSKI
       quality                               of the treatment            unit                                                          device
                        followed according                                                         laboratory analysis for others                           cost
                        to the WBG
                        guidelines                                                                                                     Weekly basis for
                                                                                                                                       others
                        Number of
                        received
                        grievances
                        Number of open                                                             Grievance records (grievance
                        and closed                                                                 log, received grievance forms,
                                             To assess the success                                 etc.)                               Quarterly during     Included in
                        grievances
O7     Grievances                            in responding the needs     Administration office                                         the operation        operation     MUSKI
                        Average grievance
                                             of PAPs                                                                                   phase                cost
                        response and                                                               Grievances related to the GBV
                        closure time                                                               and SEA/SH allegation
                        Variety of
                        grievance
                        channels
                       Number and
                       duration of                                                                                              Weekly during
                                                                                                  Shutdown/failure reports
                       unit/plant                                                                                               operation phase
                       shutdowns            To control if the                                                                                        Included in
       Failure of
O9                                          provisions given in ESIA   Administration office                                                         operation     MUSKI
       operation
                                            are managed properly                                                                                     cost
                       Amount of
                                                                                                                                During each
                       discharge during                                                           Measurements
                                                                                                                                shutdown/failure
                       shutdown/failure
                       Number of
                       accidents/Injuries
                       Number of                                                                  Visual observation            Daily basis
                       nonconformities                                                                                          starting from the
       Occupational                         To evaluate the project                               Site inspection                                    Included in
                       Period of disease                                                                                        initialization of
O10    Health and                           in terms of OHS            Worksites                  Incident Records                                   operation     MUSKI
                       occurrence                                                                                               the operation
       Safety                               implementations                                       Training Records                                   cost
                                                                                                                                phase of the
                       Number of                                                                  Work Permits                  Project
                       personnel who are
                       infected with an
                       infectious disease
                       Community
                       encroachment                                                               Security reports              Weekly during
                       cases                To control if community                                                             operation phase      Included in
       Community                                                                                  Visitor logs
O11                                         encroachment is            Administration office                                                         operation     MUSKI
       Encroachment
                       Condition of CCTV    prevented                                                                                                cost
                                                                                                                                Daily during
                       system                                                                     System checks
                                                                                                                                operation phase
       Electrocution                                                                              Visual observation
                       Number of            To control if the                                                                                        Included in
       from Energy                                                     Energy Transmission Line                                 Weekly during
O12                    accidents/Injuries   provisions given in ESIA                              Site inspection                                    operation     MUSKI
       Transmission                                                    Route                                                    operation phase
                                            are managed properly                                  Incident Records                                   cost
       Lines
                                                                                                                                Quarterly starting
                                                                                                  Employment records                                 Included in
                                            To keep the records of                                                              from the
O13    Labor Force     Employment data                                 Administration office                                                         operation     MUSKI
                                            employment                                            Grievance records             operation phase
                                                                                                                                                     cost
                                                                                                                                of the Project
        In that scope, it is suggested to add below mentioned liabilities to tender documents of any
possible contractor(s):
        As the possible impacts of the Project are varied according to the land preparation and
construction, and operation phases and/or impact levels are different, environmental and social
management is assessed separately. ESMP consists of three main components in that scope,
which are as follows:
         MUSKI holds ultimate responsibility for the environmental and social performance of the
overall Project, including the technical performance of its contractors and any other subcontractors.
Organizational structure of the MUSKI is provided in Figure VII.2. Within this regard, the
Wastewater Project Chiefship, which is under the Plan Project Investment and Construction
Department, Planning and Investment Branch Directorate, will be the responsible unit from the
implementation and monitoring of the Project. MUSKI’s environmental engineer who is under the
Wastewater Project Chiefship and currently responsible from conducting, managing and monitoring
environmental and social subjects within the projects funded by the World Bank, will act as the
Environmental Manager of this Project, will oversee the implementation of the ESMP and
monitoring progress. The environmental engineer will be supported by environmental and social
consultants, when necessary. Environmental engineer will appoint a representative in the treatment
plant to lead the development of this ESMP, and site implementation of it.
         In addition, MUSKI’s social expert who will be employed under Wastewater Project
Chiefship for this Project, will act as the Social Affairs Manager of this Project, and will manage the
social issues determined in the ESIA Report, this ESMP, and their monitoring progress. The social
expert will also manage the grievance mechanism and stakeholder engagement.
        Supervision consultant will include at least one Environmental Expert, one Social Expert
and one Occupational Health and Safety Expert. Within this context, obligation to employ an OHS
specialist/expert will be added to the contractual requirements of Supervision Consultant. Number
of experts will be increased if necessary. Supervision Consultant will provide supervision of
construction and/or rehabilitation works and installation of equipment. The expert will identify and
manage environmental, social and OHS related risks and initiate corrective actions where
necessary. The expert will also monitor and evaluate performance of services provided by the
contractor. In addition, regular monthly report regarding to environmental, social and OHS issues of
the Project during construction phase will be provided by Supervision Consultant.
        ILBANK, being the financial intermediary, is responsible for the satisfactory implementation
of the project including the environmental and social performance. The regional directorate of
ILBANK in Mugla will act as controller of the project compliance during construction period and will
work closely with the MUSKI for the successful accomplishment of the project.
        The World Bank and ILBANK will be promptly notified of any incident or accident related to
the Project which has, or is likely to have, a significant adverse effect on the environment, the
affected communities, the public or workers including but not limited to; incidents and accidents
encountered during construction works, environmental spills, etc.
         Sufficient detail will be provided regarding the incident or accident, findings of the Root
Cause Analysis (RCA), indicating immediate measures or corrective actions taken or that are
planned to be taken to address it, compensation paid, and any information provided by any
contractor and supervision consultant, as appropriate. It will be ensured that the incident report is in
line with the World Bank’s Environment and Social Incidence Response Toolkit. Subsequently, per
the Bank’s request, a report on the incident or accident and propose any measures to prevent its
recurrence will be prepared.
         Therefore, MUSKI will report details of any significant environmental or social incidents
(e.g. fatalities, lost time incidents, environmental spills etc.) within three business days and submit
an incident report, including RCA, precautions and compensation measures taken within 30
business days. ILBANK will forward the incident report to the World Bank immediately upon receipt
from MUSKI. Prompt notification of accident and incidents will remain inclusive under the
contractor’s ESMP.
         The contractor will develop monthly and quarterly Environmental and Social Monitoring
Reports in order to submit to the ILBANK though MUSKI and supervision consultant. During the
construction phase, the contractor firm will train its workers on environmental and social aspects
(including OHS) as per WB’s OPs and national regulations in order to raise environmental and
social awareness. During the defects liability period, the contractor will be responsible for any
repairs of the newly constructed facilities, in accordance with legal regulations as of provisional
acceptance. Within the liability period, the contractor will implement measures given in
Environmental and Social Mitigation Plan for operation.
       One of the main necessities of the ESMP is trainings for the MUSKI’s and contractor’s top
level management and employees. Table VII.5 provides examples of the basic trainings for the
ESMP implementation. The training programs will be developed and delivered by the MUSKI.
Module 1
                       Soon after the project effectiveness but at least 1 month before the construction of the first
 Time
                       contract. The follow-up training will be scheduled as needed.
Duration Four days of training twice a year to be repeated on a yearly basis until the end of the DLP.
Module 2
Duration Three days of training twice a year to be repeated on a yearly basis depending on needs.
       Environmental and Social Monitoring Report is one of the most important tools to record
the monitoring activities.
         In that scope, an Environmental and Social Monitoring Report will be prepared in quarterly
basis, in Turkish and English. Monitoring report will at least include all the issues defined in the
monitoring plan.
         Results of technical assessments of relevant issues given in Table VII.3 and Table VII.4
will be presented in the monitoring report. The results shall be compared with the national
legislative requirements and World Bank Group EHS Guidelines. The results of the visual
observations together with the key issues observed will be submitted in written form. The report
should focus on the negative findings as well as the good practices. The negative findings should
be supported with the photographical evidence. For each negative observation, a corrective action
should be suggested with a reasonable due date. Any analysis/sampling/measurement report
should be given as an annex of the report together with the relevant assessment and necessary
remediation activities. The findings of the Environmental and Social Monitoring Reports will keep
this ESMP as a living document; thus, the ESMP should be reviewed and revised by the
environmental and social unit of the Municipality according to these findings, if necessary to do so.
        The contractor will develop monthly and quarterly Environmental and Social Monitoring
Reports and submit these reports to MUSKI. MUSKI will produce and submit ILBANK quarterly
progress reports including the environmental and social performance of the Project. ILBANK will
prepare and submit to the World Bank regular monitoring reports on the environmental, social,
health and safety performance of the Project semi-annually (every 6 months).
        The reports will be prepared in both Turkish and English, and annual performance reports
will be disclosed through MUSKI’s website and at least Turkish versions will be made physically
available at Oren, Turkevleri, and Bozalan neighbourhoods’ muhtar offices.
          Currently, a Project specific Stakeholder Engagement Plan (SEP) is not developed for the
 Project. MUSKI aims to finalize the SEP, before the commence of the construction activities, after
 the draft SEP is disclosed for public consultations along with the ESIA and other relevant site
 specific instruments of the subproject. MUSKI is currently developing site specific SEPs for all of
 the sub-projects under their responsibility. Therefore, in this section the information on public
 consultation activities and the grievance mechanism for the Project are mentioned along with the
 purpose and scope of the SEP.
          The SEP will cover the measures to be adopted by MUSKI and the contractors to ensure
 effective and efficient community relations during all phases of the Milas-Oren Sewerage System
 and Wastewater Treatment Project.
                To involve and interact with the Project Affected Person, Stakeholders and other
                 institutions that may be affected by the project or that may affect the project during
                 the construction phases;
                To ensure continuous and good relations with the members of the local community
                 and affected parties.
                To minimise impacts and manage those that are unavoidable in order to maintain
                 good relations
                To increase pre-construction awareness in areas such as construction schedule,
                 impacts, mitigation measures and recruitment
                To enable pre-notification for any disturbance to infrastructure or utilities;
                 immediate action for unplanned disturbances
                To avoid impacts to access -- for education, health care, cultural heritage sites,
                 pasture access, etc.
                To prepare and implement a Grievance Management Procedure, and establishing
                 a project grievances mechanism that allows for taking, investigating, following up,
                 reporting and resolving grievances from all stakeholders
          Public Participation Meeting-I (PPM-I) was conducted on July 7, 2020 at Oren. Tools used
 during the planning stage for informing public are described below. Similar tools can be used for
 informing the public in the further stages of the Project. The aim of the public participation meeting
 is to inform people who may be potentially affected from the project and to understand their
 concerns, opinions and suggestions about the project.
         PPM-I was first announced on June 26, 2020 through MUSKI’s website with presentation
 to be made during the PPM attached to gather communities’ opinions prior to the meeting. The
 announcement is presented in Figure VIII.1. Following that national and local newspaper
 announcements were published on June 26 and June 29, 2020 as presented in Figure VIII.2 and
 Figure VIII.3, respectively. In addition to these, the correspondence letters were sent to muhtars of
 Oren, Turkevleri, and Bozalan neighbourhoods by MUSKI.
Figure VIII.2 PPM-1 National Newspaper Announcement (June 26, 2020, Birgun)
        The PPM-1 took place at Oren Labranda Cafeteria by taking necessary COVID-19
measures at 10:30 on July 7, 2020. Before the commencement of meeting, information brochures
regarding the Project were distributed to attendants and A0 maps of the Project made available for
them. The brochure is provided in Annex-3 of this document.
         The meeting was held with the participation of representatives from MUSKI, Mugla
Metropolitan Municipality, Milas Municipality, and ENCON. MUSKI performed the moderation of the
meeting. The meeting started with an introduction and explanation of the purpose and scope of the
meeting which is to inform the locals about the Project at hand and understand their concerns,
opinions and suggestions about the project, and followed by a presentation given by ENCON and a
final discussion session where questions, concerns and suggestions were received.
        Eighty-four people participated to the meeting including muhtars of Oren, Bozalan and
Turkevleri. The meeting lasted for 1.5 hours. Photographs taken during the meeting are presented
in Figure VIII.4.
         Q1: Will odor problems occur due to collectors to be built within the sewerage system?
(Resident of Oren)
         A1: When the wastewater velocity in the collectors is above a certain level, odors caused
by H2S can be prevented. This situation will also be taken into consideration in the system to be
built, so odors that may emanate from the collectors will be prevented.
           Q2: Where will the treatment plant effluent be discharged, will the wastewater mix with the
sea?
         A2: After the treatment, the effluent reaches the quality specified in the legal regulations
and it will be discharged to the Kemer stream 3 located near the facility. The water of Kemer stream
reaches the sea, but since the facility will be built with the principle of advanced biological
treatment, the treatment will be performed at high efficiency, so the effluent from the treatment
plant will not cause pollution in the sea.
         Q4: Will residents have to pay any fee while connecting to the channel?
         A4: Pipes to be made between households and sewer collectors will be made under the
responsibility of the residents, but these pipes will only be 1-2 m long. Also, the channel
participation fee will be charged from the households for the connection.
         Q5: Will this project prevent water problems frequently experienced in the region?
         A5: Within the scope of this project, only a sewerage system and wastewater treatment
plant will be built, the drinking water network is not included in this project.
          Q6: What are the exact start date and end date of the project? When will the project be
finalized?
          A6: The World Bank will provide the financing of the project. This meeting is held in
accordance with the World Bank procedures. Your opinions that are gathered with this meeting will
be taken into consideration in the ESIA report that is being prepared, and then the tender phase
will begin after the approval of the ESIA report by ILBANK and the World Bank. In the tender
phase, if the necessary approvals are obtained from the World Bank, the construction of the project
will start. If there is no setback during these processes, the project construction is expected to start
in 2021. The project will take approximately 18 to 24 months to complete.
         Following the Q&A session, 18 people were selected for socio-economic questionnaire.
Part of the questionnaire findings is previously presented in Chapter IV.3.1. The remaining relevant
information are presented in Table VIII.1 below.
3 After the PPM, the discharge location was changed to Hanay Creek.
MUSKI will prepare the mentioned SEP with regard to the information provided above.
        PPM-II was conducted on February 11th, 2022 at Oren. Tools used during the planning
stage for informing public are described below. The aim of the public participation meeting was to
inform people who may be potentially affected from the Project and to understand their concerns,
opinions and suggestions about the Project.
         PPM-II was firstly announced through national and local newspapers that were published
on February 2nd, 2022 as presented in Figure VIII.5 and Figure VIII.6, respectively. Following that,
PPM-II was announced on February 3rd, 2022 through MUSKI’s website as presented in Figure
VIII.7. In addition, official letters were written by MUSKI to the relevant public authorities, the
muhtars of the Project affected neighborhoods were invited through face-to-face meetings/phone
calls and announcements were made in the Oren neighborhood.
        The PPM-II took place at Oren Labranda Cafeteria, by taking necessary COVID-19
measures, at 10:30 on February 11th, 2022. Before the commencement of meeting, information
brochures regarding the Project were distributed to attendants and A0 maps of the Project made
available for them. The brochure is provided in Annex-5 of this document.
        The meeting was held with the participation of representatives from MUSKI, Mugla
Metropolitan Municipality, Milas Municipality, and ENCON. MUSKI performed the moderation of the
meeting. The meeting started with an introduction and explanation of the purpose and scope of the
meeting which is to inform the locals about the Project at hand and understand their concerns,
opinions and suggestions about the Project, and followed by a presentation given by ENCON and a
final discussion session where questions, concerns and suggestions were received. The
presentation is provided in Annex-6 of this document.
       Sixty-three people participated to the meeting and the meeting lasted for 1.5 hours.
Photographs taken during the meeting are presented in Figure VIII.8.
      Questions received during the Q&A session of the meeting and answers given to them are
summarized below:
       Q2: When will the construction phase of the Project be completed and the Project will be
implemented? (Resident of Oren)
       A2: The construction of the sewerage network and WWTP will take 24 months and 18
months, respectively.
        Q3: Will the treated effluent water from the WWTP be discharged directly to the sea? In
addition, will the treatment in the WWTP be carried out chemically or biologically? (Resident of
Oren)
        A3: Wastewater coming to the WWTP will be treated and then discharged to Hanay Creek
in accordance with the discharge standards specified in the Urban Wastewater Treatment
Regulation. Discharge permits were obtained from related authorities in this regard. In addition,
advanced biological treatment will be carried out at the WWTP and the treated wastewater will be
discharged after disinfection.
        Q5: Why are pumping stations foreseen in the project, can't the wastewater be conveyed
by gravity? (Resident of Oren)
        A5: Although the topography of the project area is relatively flat, deep excavations cannot
be made and elevation differences cannot be adjusted due to the groundwater levels.
         Q6: Does the project cover the 1st degree archaeological site? (Resident of Oren)
         A6: No, the project does not cover the 1st degree archaeological site.
         Q7: Will there be any expropriation within the scope of the Project? (Resident of Oren)
         A7: The WWTP area is currently owned by MUSKI. Construction of the sewerage network
and discharge line will take place in existing roads and no land acquisition is required within this
respect. Pumping stations will be built on public lands that are registered as park. Therefore, there
will be no resettlement and/or physical displacement of persons in and around the Project Area.
        In accordance with WB policies, a process will be established by which people who deem
that they have been adversely affected by the Project during planning, construction or operation
can bring grievances to the Project for consideration and, if required, resolution.
         Managing grievances, including avoiding and minimizing them as well as their timely and
effective resolution, is an integral part of a sound stakeholder engagement strategy. Experience
shows that significant numbers of grievances arise from misunderstandings, and that such
grievances can be avoided, or their numbers reduced, through proactive and consistent
engagement with communities. Engagement also helps anticipate and review community concerns
to prevent them from escalating into grievances. A project-specific Grievance Mechanism (GM) is
beneficial in addressing community and individual concerns and complaints before they escalate
beyond control.
        MUSKI has an already established GRM. Within that, MUSKI will be responsible for overall
implementation of the GM to ensure that all stakeholder comments, suggestions and objections are
addressed promptly and sensitively. Therefore, the GM will enable receiving comments/grievances
both in English and Turkish to be able to serve to all potential stakeholders of the Project. The
GRM will be in accordance with the provisions of the WB standards.
        The formal grievance mechanism procedures will be prepared by MUSKI. This internal and
external grievance mechanism will focus on both stakeholders and public. All complaints received
are collected in the PIU complaints mechanism section, which consists of the staff of MUSKI.
Afterwards, received complaints are recorded in the database and stored. Then, PUB GM Officer,
communicates with the person who made the complaint, in order to confirm that the complaint is
delivered in seven days by telephone or e-mail. After that, he/she prepares the draft response and
submits it to the Project Management approval. Following the response, the Complaint / Complaint
Form is updated according to the outcome of the process and the complainant gets the result
within 5 days Complaints follow-up process, recorded in the monitoring and evaluation system. At
the end, MUSKI should inform the statistics of the complaints to ILBANK. Complaints / feedback
received will be resolved within a certain time period as specified in the national law and the ”Beyaz
Masa” system of the MUSKI. Basic steps in a grievance mechanism are explained in the Figure
VIII.9.
       If complainant’s request that their names are not included on the registration form,
especially for GBV/SEA survivors, this request will be fulfilled.
       Direct and contracted workers also have the opportunity to benefit from other grievance
mechanisms such as CIMER that are used nation-wide and which is accessible for every
employee.
       Table VIII.2 presents the minimum key elements of a grievance mechanism that could be
used by Construction Contractor is presented below table:
                                                                     Parameters to be                                Durati
 Level        Relevant Authority         Means of Application                                    Activities
                                                                        identified                                    on
          MUSKI
        MUSKI and Construction Contractor should have separate free phone lines for receiving
the grievances.
           Tncl İnşaat Mühyendislik Proje Yönetim Danışmanlığı Tic. Ltd. Şti., 2016, Dünya
            Bankası Ek Kredi Teknik Fizibilite Raporu
           Bakanlar Kurulu, 16.06.1939 tarih ve 4234 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 3634 sayılı "Milli Müdafaa Mükellefiyeti Kanunu".
           Bakanlar Kurulu, 08.09.1956 tarih ve 9402 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 6831 sayılı "Orman Kanunu".
           Bakanlar Kurulu, 23.07.1983 tarih ve 18113 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 2863 sayılı "Kültür ve Tabiat Varlıklarını Koruma Kanunu".
           Bakanlar Kurulu, 11.08.1983 tarih ve 18132 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 2872 sayılı "Çevre Kanunu".
           Bakanlar Kurulu, 08.11.1983 tarih ve 18215 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 2942 sayılı "Kamulaştırma Kanunu".
           Bakanlar Kurulu, 09.07.1987 tarih ve 19512 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 3402 sayılı "Kadastro Kanunu".
           Bakanlar Kurulu, 29.02.1998 tarih ve 23272 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 4342 sayılı "Mera Kanunu".
           Bakanlar Kurulu, 08.12.2001 tarih ve 24607 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 4721 sayılı "Türk Medeni Kanunu".
           Bakanlar Kurulu, 22.05.2003 tarih ve 25134 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 4857 sayılı "İş Kanunu".
           Bakanlar Kurulu, 13.07.2005 tarih ve 25874 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 5393 sayılı "Belediye Kanunu".
           Bakanlar Kurulu, 19.09.2006 tarih ve 26301 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 5543 sayılı "İskan Kanunu".
           Bakanlar Kurulu, 21.06.2012 tarih ve 28489 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 6360 sayılı "On Dört İlde Büyükşehir Belediyesi ve Yirmi Yedi İlçe
            Kurulması ile Bazı Kanun ve Kanun Hükmünde Kararnamelerde Değişiklik
            Yapılmasına Dair Kanun".
           Bakanlar Kurulu, 30.06.2006 tarih ve 28339 sayılı Resmi Gazete 'de yayımlanarak
            yürürlüğe giren 6331 sayılı "İş Sağlığı ve Güvenliği Kanunu".
 Köy Hizmetleri Genel Müdürlüğü (KHGM), 1995, Muğla İl Arazi Varlıkları, Ankara.
          Ministry of Agriculture and Rural Services, July 2008. Technical Procedure on Soil
           and Land Classification Standards and Relevant Legislation.
          Mülga Çevre ve Orman Bakanlığı, 20.10.2010 tarih ve 27527 sayılı Resmi Gazete
           'de yayımlanarak yürürlüğe giren "Atıksu Arıtma Tesisleri Teknik Usuller Tebliği."
          T.C. Muğla Valiliği, Çevre ve Şehircilk İl Müdürlüğü, 2019, Muğla İli 2018 Çevre
           Durum Raporu, Muğla.
          The World Bank Group, 2011. Greenhouse Gas Emissions Mitigation in Road
           Construction and Rehabilitation: A Toolkit for Developing Countries. Asia
           Sustainable and Alternative Energy Program.
 https://avlakharitalari.ormansu.gov.tr/AvlakHaritalari/63.jpg
 http://www.deprem.gov.tr
 http://www.dogadernegi.org/onemli-doga-alanlari/
 http://www.geodata.ormansu.gov.tr
 http://www.kulturvarliklari.org/kve
 http://www.milliparklar.gov.tr
 http://www.ramsar.org
 http://www.tuik.gov.tr
 http://kve.ulakbim.gov.tr
 https://webdosya.csb.gov.tr/db/ced/editordosya/Mugla_icdr2014.pdf
 https://geka.gov.tr/uploads/pages_v/mugla-fethiye-afet-tehlike-analizi-2013.pdf
 https://sp.lyellcollection.org/content/291/1/1
          https://www.academia.edu/15447190/TÜRKİYE_DE_AFETLERİN_MEKANSAL_V
           E_İSTATİSTİKSEL_DAĞILIMI_AFET_BİLGİLERİ_ENVANTERİ
 http://www.maden.org.tr/resimler/ekler/a4410d4fb85f566_ek.pdf
          https://geka.gov.tr/uploads/pages_v/mugla-ili-sosyo-ekonomik-durum-raporu-
           2014.pdf
          https://www.ab.gov.tr/files/ardb/evt/2_turkiye_ab_iliskileri/2_2_adaylik_sureci/2_2_
           8_diger/tckb_sege_2013.pdf
 http://www.mutso.org.tr/wp-content/uploads/tr_322sunum_mutso_paylasim.pdf
 https://biruni.tuik.gov.tr/ilgosterge/?locale=tr
          http://www.mutso.org.tr/wp-content/uploads/muglada-is-ve-yatirim-ortami-
           raporu.pdf