W N 05 Bangur Power New

The document provides test results for Portland pozzolana cement from Shree Cement Ltd. showing compliance with IS 1489 (Part-1): 2015 standards on chemical and physical requirements such as insoluble residue, magnesia, strength, and fineness.

Uploaded by

cricketsanju1811
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
324 views1 page

W N 05 Bangur Power New

The document provides test results for Portland pozzolana cement from Shree Cement Ltd. showing compliance with IS 1489 (Part-1): 2015 standards on chemical and physical requirements such as insoluble residue, magnesia, strength, and fineness.

Uploaded by

cricketsanju1811
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

IS 1489 (PART-1) : 2015

SHREE CEMENT LTD

SHREE GRINDING UNIT- SURATGARH

Near N.H.No.15 Village:-Udaipur Udasar Tehsil-


Suratgarh Ganganagar 335804 RAJASTHAN
PORTLAND POZZOLANA CEMENT

PPC Premium

Test & Compliance

SL No. Particulars REQUIREMENT OF IS 1489 (PART-1) : 2015 Test Result

CHEMICAL REQUIREMENTS

1 INSOLUBLE RESIDUE(% BY MASS) (X=%OF POZZOLANA USED) 30.92

2 MAGNESIA (% BY MASS) 6.0 % MAX 1.74

3 SULPHURIC ANHYDRITE (% BY MASS) 3.5 % MAX 2.69

4 TOTAL LOSS ON IGNITION(%) 5.0 % MAX 2.51

5 TOTAL CHLORIDE (%) 0.10 % MAX 0.010

PHYSICAL REQUIREMENTS

1 FINENESS (M2/KG) NOT LESS THAN 300 M2/KG 368

2 SOUNDNESS: LECHATLIER EXPANSION(MM) 10.0 MAX 0.50

3 AUTO-CLAVE(%) 0.8 MAX 0.043

4 SETTING TIME(MINUTES):INITIAL 30 MIN 130

5 FINAL 600 MAX 180

6 COMPRESSIVE STRENGTH (MPA):3 DAYS 16 MIN. 26.8

7 7 DAYS 22 MIN. 33.4

8 28 DAYS 33 MIN. 47.3

9 TEMP. DURING TESTING 27 +/- 2 DEG 0C 27

The cement complies with IS 1489 (PART-1) : 2015 for Despatched on 04.02.2024

Week no. : 5
Date : 08.03.2024

This is the computer generated output hence no signature is required.