TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : May 19th, 2023
DAILY PROGRESS REPORT
0. DAILY PROGRESS & MANPOWER Construction Phase
MANPOWER WORK HOURS RAINFALL RECORD
PLAN ACTUAL ACTUAL ACTUAL
DISCIPLINE/ACTIVITY
Night Day Overtim Night Overtim Night
Day Shift Overtime Day Shift Start End Total Hours Remarks
Shift Shift e Shift e Shift
Direct Labor * 144 69 759
Skilled Worker (Source : Jakarta) 110 69 759
Rebarman 25 22 242
Mason 20 14 154
Carpenter 25 16 176
Fitter 12 5 55
Boilermaker 8 4 44
Pipe Fitter 6 2 22
HDPE Piping 4 4 44 OTHER CONDITION
Welder Steel (SMAW+GTAW) 8 2 22
Total
Start End Remarks
Hours
Painter 2
Unskilled Worker (Source : Local) 34
34
Indirect * 65 49 509
Construction Manager 1 1 11 Total Hours :
Site Manager 1 1 11 Note :
Planner 1 1 11 Blasting at purnama Pit, all worker evacuate from
Surveyor 2 2 22 TMF area
Field Engineer/Project Engineer 1 1 11
HR Staff 3 2 22 EQUIPMENT ON SITE QTY
Civil Foreman 2 2 22
Civil Supervisor 1 1 11 Roughter Crane 50 Ton 1
Civil QC Engineer 2 1 11 Roughter Crane 90 Ton 1
Civil Superintendent 1 1 11 Boomtruck 15 Ton 1
QC Staff 2 1 11 Concrete Pump 1
Mechanical 6 1 8 Mixer Truck 01 1
SMP Foreman 2 2 22 Mixer Truck 02 1
SMP Supervisor 1 1 11 Mixer Truck 03 1
SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 04 1
Scaffolding Inspector 1 Telehandler 1
Scaffolder 7 7 77 Tractor Head 6X6 1
HSE Supervisor 1 1 11 LV 01 (Pajero) 1
Safety Officer 3 2 22 LV 02 Double Cabin 1
Logistic and Warehouse 2 1 11 LV 03 Double Cabin 1
Rigger 3 2 22 Generator 45 kVA 4
Driver 3 2 19 Generator 165 kVA 1
Electrician 2 2 22 Compressor 2
Operator Crane 2 2 22 Total Equipment 20
Operator Telehandler 1 1 11
Operator Manlift 1
Operator Boom Truck 1 1 11
Operator Trailer 1 1 11
Operator Concrete Pump 3 3 24
Operator Mixer Truck 4 4 32
PERI UP Supervisor 2 1 8
TOTAL 209 118 1268
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : May 19th, 2023
DAILY PROGRESS REPORT
2. MAJOR HIGHLIGHT
Friday, 19 May 2023 Saturday, 20 May 2023
ACTIVITY UNIT QTY ACTIVITY UNIT QTY
A. Civil A. Civil
Assembly foundation rebar GL -05-06-07 Continue Assembly foundation rebar GL -05-06-07
Start Install formwork GL 13-11 Continue joint survey GL 1,2,3,4,5
Curing concrete GL 15-13 Continue curing concrete GL 15-13
Start bottom rebar GL 4,3 & Column P3A Continue start bottom rebar GL 4,3 & Column P3A
Joint survey column GL 1,2,3,4,5 Continue joint survey column GL 1,2,3,4,5
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Mobilize HDPE piping material Continue Mobilize HDPE piping material
Joint pipe HDPE filtration feed reach 8 joint 8 Continue Joint pipe HDPE filtration feed
E. Logistic : E. Logistic :
Unloading tools & equipment to TMF area Continue Unloading tools & equipment to TMF area
F. Scaffold : F. Scaffold :
Manpower complete 7
G. Others G. Others
Online & offline Training Online & offline Training
Produce office furniture & site facilities Continue produce office furniture & site facilities
Concern :
Cast In plate, Embeded plate, not yet arrive at TMF
PERI UP material not yet complete
Concreting water stop material for Filtration building not enough (25 meter more)
Local hire need to joint
Potential night shift to catch up schedule
Prepared by : Checked By : Acknowledged By :
Project Control Site Manager
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Date : May 19th, 2023
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
General Pre-start meeting Internal EMK TBM
CIVIL
Remove formwork GL 15-13 Remove formwork GL 15-13
Install bowplank SF-02 Continue install rebar bottom GL 4 & 3 & Column P3A GL9
Install column axis C GL 9 & Chipping joint construction Install scaffolding GL 13-11
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Date : May 19th, 2023
DAILY PHOTOGRAPH
PHOTOGRAPH
Marking pedestal column GL 15 Start assembly PERI UP
Piping
Welding joint no.6 HDPE pipe Welding joint no.7 HDPE pipe
Welding joint no.7 HDPE pipe Continue fit up HDPE pipe Filtration Feed
Prepared by : Approved by :
Project Control