139Q - MS - 32 Dismantle & Re-Erect Palisade Fencing - Rev1

This document provides a method statement for dismantling and re-erecting palisade fencing as well as installing electric fencing above the new palisade fence. It describes pre-start activities, execution including clearing, civil works, foundations, and installation. It also lists resources, quality control, and health and safety requirements.

Uploaded by

Olona Lona
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
165 views5 pages

139Q - MS - 32 Dismantle & Re-Erect Palisade Fencing - Rev1

This document provides a method statement for dismantling and re-erecting palisade fencing as well as installing electric fencing above the new palisade fence. It describes pre-start activities, execution including clearing, civil works, foundations, and installation. It also lists resources, quality control, and health and safety requirements.

Uploaded by

Olona Lona
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

CONSTRUCTION METHOD PROJECT: PHASE 2A IRT: E1 HEINZ TO NY72

STATEMENT C / N. 139Q/2022/23
JOB CODE: DUI365
PALISADE FENCING
MS No. 139Q-MS-32 PAGE: 1 of 5

Revision Date Prepared Checked Approved


1 28/11/2023 P Kayingana A, Theron GIBB

SIGNATURES

1. TASK DESCRIPTION
This method statement describes the procedures that will be followed for the safe and effective dismantling
and re-erection of palisade fencing as well as the installation of electric fence above the new palisade fence in
accordance to COLTO B5500

2. PRE-START ACTIVITIES
• Ensure all workers are medically fit for duty (verify medicals with safety officer)
• Ensure all workers have the required PPE (Safety officer)
• Ensure risk assessment is on site and communicated daily before start of shift
• Verify existing services in the works area, both overhead and underground
• Clearly mark out positions of existing services showing depths of underground services
• Product certificates/conformance documentation to specifications submitted to the Engineer for
approval – 2 weeks prior to commencement of works (If applicable).
• Test results and material samples submitted to the Engineer for approval – 2 weeks prior to commencement
of works (if applicable)
• All required wayleaves to be in place where applicable
• Install ready fence panels as per the attached marked up layout

3. EXECUTION
Clearing the alignment

• Strip the topsoil and stockpile in approved location.


• Clearing areas of all grass, weeds, shrubs, debris, including grubbing roots and cart away all
vegetation and debris with a girth less than 1m.
• Once the clearing is completed the setting out will be carried out by the Surveyor giving the
new positions as agreed with the EA and Property owner.
• Excavation of concrete footings to specified depth by hand.
• The excavation material will be stockpiled at the designed areas.
• Tipper trucks or Wheel barrows will be used to transport the topsoil to the area of the
stockpile.
• Compaction and backfill to be carried out to the specifics according to the inspection test
method.
• Compaction will be applicable on the backfill around fence mesh trench, fence post and
material

Civil works

• A storm water pipe will be laid at the mouth of the pond as indicated in the layout

139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1


Page 1 of 5
CONSTRUCTION METHOD PROJECT: PHASE 2A IRT: E1 HEINZ TO NY72
STATEMENT C / N. 139Q/2022/23
JOB CODE: DUI365
PALISADE FENCING
MS No. 139Q-MS-32 PAGE: 2 of 5

• Approved backfill material will be used to backfill over the pipe and will be compacted to
achieve driveability over the pond
• Care will be taken to ensure that the pipe ends are protected using a wire net or other
suitable material to ensure that no material clogs the pipe and caused blockages
• The area will be well barricaded to ensure that the pond stays protected and no foreign
materials encroach into the pond as a consequence of the contractor working in the vicinity

Civils 2000. (2023) barricading. Govan Mbeki Rd


• Excavation will be carried out using a TLB or hand excavation for the retaining wall base
• The insitu material will be levelled & compacted to the required MDD
• Reinforcement steel will be fixed to detail as specified by the EA
• The subsoil drain will be placed as per the drainage detail
• An inspection will be placed ensuring that the AREs are satisfied with the drainage
installation prior to placement of terra-force blocks
• Terra-force blocks will be placed ensuring that the steel cover is maintained
• Concrete will be cast inside the terra-force blocks and mildly vibrated to eliminate any air
bubbles that may occur
• The back of the wall will be backfilled and compacted to the required MDD
• Inspections will be continuously placed as we go ensuring that spec are met and quality of
works is acceptable

139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1


Page 2 of 5
CONSTRUCTION METHOD PROJECT: PHASE 2A IRT: E1 HEINZ TO NY72
STATEMENT C / N. 139Q/2022/23
JOB CODE: DUI365
PALISADE FENCING
MS No. 139Q-MS-32 PAGE: 3 of 5

GIBB. (2023) typical retaining wall detail. Govan Mbeki Rd

Foundations and post holes

• Once the earthwork is completed, inspected, and approved the preparation of the fence will
commence.
• The surveyor will stake the footprint area of the fence line to be erected.
• Before the work starts the foreman must make sure that the workers are wearing the correct
PPE.
• The tools to be used to erect the fence must be in a good working order.
• Workers will then start with the excavations of the corner posts. Digging holes of 600 mm x
500 mm²
• Posts will be placed into the holes and secured with concrete 20MPa.
• Posts will be planted at intervals of 2m
• The surveyor will check that the position of the middle posts are in a straight line and will mark
the position of each hole with a stake.
• Horizontal rails will be bolted to the posts at a clearance of 100mm top and bottom.
• Pales shall have pale heads and will be welded between the posts at intervals of 150mm.
• Pales will be welded to the horizontal rails, welding screen to be used and all safety measures
in place.
• Straining and or corner posts shall be erected at terminal points, gates, low points, corners,
bends or junctions.
• All earthing will be installed/executed in compliance with specifications and drawings. earthing
will be done with solid copper rod connected to earth spikes at intervals, if required.

139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1


Page 3 of 5
CONSTRUCTION METHOD PROJECT: PHASE 2A IRT: E1 HEINZ TO NY72
STATEMENT C / N. 139Q/2022/23
JOB CODE: DUI365
PALISADE FENCING
MS No. 139Q-MS-32 PAGE: 4 of 5

• Gates to suit the width of access as required, and posts installed in the same manner as
mentioned above
• Once the erection of the fence is complete a gate will be installed as per the property owner’s
requirements
• After work for the day is completed all machinery that will be kept on site or open excavations
that will be open over-night will be barricaded with temporary fencing.

Installation of electric fence

• Install the metal stakes


• Thread the wire
• Set up connection
• Inspection and test

Dismantling of existing palisade fence

• Undo the bolts and remove the whole 2m length of pales welded to the 2 horizontal rails
• Load and cart to designated storage area
• Break the concrete for the posts using a concrete breaker and cart to storage area
• Backfill all the holes and mildy compact with a rammer

4. RESOURCES REQUIRED
Plant and equipment
• TLB, Concrete breaker, Compactor (rammer), Sit on roller

• Hand tools (spade, wire cutters, utility knife, tape measure, ratchet, claw hammer)

• Electrical tape, Electric drill and screws

5. QUALITY CONTROL
• Refer to inspection & test plan (QCP)

6. HEALTH, SAFETY & ENVIRONMENTAL


• Refer to risk assessment
• Wear your PPE at all times
• Keep a tidy site
• Do not put yourself or others at risk
• Follow safety signs and procedures
• Never work in unsafe areas
• Report defects and near misses
• Never tamper with equipment
• Use the right equipment

139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1


Page 4 of 5
CONSTRUCTION METHOD PROJECT: PHASE 2A IRT: E1 HEINZ TO NY72
STATEMENT C / N. 139Q/2022/23
JOB CODE: DUI365
PALISADE FENCING
MS No. 139Q-MS-32 PAGE: 5 of 5

I acknowledge I have received clear and detailed instructions of the requirements, including health &
safety hazards and requirements for the completion of this task:
Name & Surname ID Number Date Signature

139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1


Page 5 of 5