CONSTRUCTION METHOD                      PROJECT:          PHASE 2A IRT: E1 HEINZ TO NY72
STATEMENT                           C / N.            139Q/2022/23
                                                                          JOB CODE:         DUI365
                                       PALISADE FENCING
                                                                          MS No.            139Q-MS-32       PAGE:     1 of 5
 Revision            Date                     Prepared                          Checked                     Approved
     1            28/11/2023                 P Kayingana                        A, Theron                     GIBB
         SIGNATURES
1.   TASK DESCRIPTION
     This method statement describes the procedures that will be followed for the safe and effective dismantling
     and re-erection of palisade fencing as well as the installation of electric fence above the new palisade fence in
     accordance to COLTO B5500
2.   PRE-START ACTIVITIES
     •      Ensure all workers are medically fit for duty (verify medicals with safety officer)
     •      Ensure all workers have the required PPE (Safety officer)
     •      Ensure risk assessment is on site and communicated daily before start of shift
     •      Verify existing services in the works area, both overhead and underground
     •      Clearly mark out positions of existing services showing depths of underground services
     •      Product certificates/conformance documentation to specifications submitted to the Engineer for
            approval – 2 weeks prior to commencement of works (If applicable).
     •      Test results and material samples submitted to the Engineer for approval – 2 weeks prior to commencement
            of works (if applicable)
     •      All required wayleaves to be in place where applicable
     •      Install ready fence panels as per the attached marked up layout
3.   EXECUTION
     Clearing the alignment
            •   Strip the topsoil and stockpile in approved location.
            •   Clearing areas of all grass, weeds, shrubs, debris, including grubbing roots and cart away all
                vegetation and debris with a girth less than 1m.
            •   Once the clearing is completed the setting out will be carried out by the Surveyor giving the
                new positions as agreed with the EA and Property owner.
            •   Excavation of concrete footings to specified depth by hand.
            •   The excavation material will be stockpiled at the designed areas.
            •   Tipper trucks or Wheel barrows will be used to transport the topsoil to the area of the
                stockpile.
            •   Compaction and backfill to be carried out to the specifics according to the inspection test
                method.
            •   Compaction will be applicable on the backfill around fence mesh trench, fence post and
                material
     Civil works
            •   A storm water pipe will be laid at the mouth of the pond as indicated in the layout
                                       139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1
                                                              Page 1 of 5
                  CONSTRUCTION METHOD                     PROJECT:         PHASE 2A IRT: E1 HEINZ TO NY72
                       STATEMENT                          C / N.           139Q/2022/23
                                                          JOB CODE:        DUI365
                        PALISADE FENCING
                                                          MS No.           139Q-MS-32       PAGE:    2 of 5
•   Approved backfill material will be used to backfill over the pipe and will be compacted to
    achieve driveability over the pond
•   Care will be taken to ensure that the pipe ends are protected using a wire net or other
    suitable material to ensure that no material clogs the pipe and caused blockages
•   The area will be well barricaded to ensure that the pond stays protected and no foreign
    materials encroach into the pond as a consequence of the contractor working in the vicinity
    Civils 2000. (2023) barricading. Govan Mbeki Rd
•   Excavation will be carried out using a TLB or hand excavation for the retaining wall base
•   The insitu material will be levelled & compacted to the required MDD
•   Reinforcement steel will be fixed to detail as specified by the EA
•   The subsoil drain will be placed as per the drainage detail
•   An inspection will be placed ensuring that the AREs are satisfied with the drainage
    installation prior to placement of terra-force blocks
•   Terra-force blocks will be placed ensuring that the steel cover is maintained
•   Concrete will be cast inside the terra-force blocks and mildly vibrated to eliminate any air
    bubbles that may occur
•   The back of the wall will be backfilled and compacted to the required MDD
•   Inspections will be continuously placed as we go ensuring that spec are met and quality of
    works is acceptable
                       139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1
                                              Page 2 of 5
                     CONSTRUCTION METHOD                     PROJECT:         PHASE 2A IRT: E1 HEINZ TO NY72
                          STATEMENT                          C / N.           139Q/2022/23
                                                             JOB CODE:        DUI365
                          PALISADE FENCING
                                                             MS No.           139Q-MS-32       PAGE:    3 of 5
                    GIBB. (2023) typical retaining wall detail. Govan Mbeki Rd
Foundations and post holes
   •   Once the earthwork is completed, inspected, and approved the preparation of the fence will
       commence.
   •   The surveyor will stake the footprint area of the fence line to be erected.
   •   Before the work starts the foreman must make sure that the workers are wearing the correct
       PPE.
   •   The tools to be used to erect the fence must be in a good working order.
   •   Workers will then start with the excavations of the corner posts. Digging holes of 600 mm x
       500 mm²
   •   Posts will be placed into the holes and secured with concrete 20MPa.
   •   Posts will be planted at intervals of 2m
   •   The surveyor will check that the position of the middle posts are in a straight line and will mark
       the position of each hole with a stake.
   •   Horizontal rails will be bolted to the posts at a clearance of 100mm top and bottom.
   •   Pales shall have pale heads and will be welded between the posts at intervals of 150mm.
   •   Pales will be welded to the horizontal rails, welding screen to be used and all safety measures
       in place.
   •   Straining and or corner posts shall be erected at terminal points, gates, low points, corners,
       bends or junctions.
   •   All earthing will be installed/executed in compliance with specifications and drawings. earthing
       will be done with solid copper rod connected to earth spikes at intervals, if required.
                          139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1
                                                 Page 3 of 5
                            CONSTRUCTION METHOD                    PROJECT:         PHASE 2A IRT: E1 HEINZ TO NY72
                                 STATEMENT                         C / N.           139Q/2022/23
                                                                   JOB CODE:        DUI365
                                 PALISADE FENCING
                                                                   MS No.           139Q-MS-32       PAGE:    4 of 5
         •   Gates to suit the width of access as required, and posts installed in the same manner as
             mentioned above
         •   Once the erection of the fence is complete a gate will be installed as per the property owner’s
             requirements
         •   After work for the day is completed all machinery that will be kept on site or open excavations
             that will be open over-night will be barricaded with temporary fencing.
     Installation of electric fence
         •   Install the metal stakes
         •   Thread the wire
         •   Set up connection
         •   Inspection and test
     Dismantling of existing palisade fence
         •   Undo the bolts and remove the whole 2m length of pales welded to the 2 horizontal rails
         •   Load and cart to designated storage area
         •   Break the concrete for the posts using a concrete breaker and cart to storage area
         •   Backfill all the holes and mildy compact with a rammer
4.   RESOURCES REQUIRED
     Plant and equipment
         •   TLB, Concrete breaker, Compactor (rammer), Sit on roller
         •   Hand tools (spade, wire cutters, utility knife, tape measure, ratchet, claw hammer)
         •   Electrical tape, Electric drill and screws
5.   QUALITY CONTROL
         •   Refer to inspection & test plan (QCP)
6.   HEALTH, SAFETY & ENVIRONMENTAL
         •   Refer to risk assessment
         •   Wear your PPE at all times
         •   Keep a tidy site
         •   Do not put yourself or others at risk
         •   Follow safety signs and procedures
         •   Never work in unsafe areas
         •   Report defects and near misses
         •   Never tamper with equipment
         •   Use the right equipment
                                139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1
                                                       Page 4 of 5
                        CONSTRUCTION METHOD                     PROJECT:         PHASE 2A IRT: E1 HEINZ TO NY72
                             STATEMENT                          C / N.           139Q/2022/23
                                                                JOB CODE:        DUI365
                             PALISADE FENCING
                                                                MS No.           139Q-MS-32       PAGE:    5 of 5
 I acknowledge I have received clear and detailed instructions of the requirements, including health &
 safety hazards and requirements for the completion of this task:
Name & Surname                       ID Number                    Date                   Signature
                             139Q - MS - 32 Dismantle & Re-erect palisade fencing_Rev1
                                                    Page 5 of 5