TEMPLATE FIVE (5)-YEAR WORK PROGRAM FOR WESC ANNEX - I.
6
WIND WORK PROGRAM
Wind Project Name: _________________________
Location: __________________________________
RE Developer: _____________________________
Year 1 Year 2 Year 3 Year 4 Year 5 Financial Commitment (PhP)
ACTIVITIES
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Year 1 Year 2 Year 3 Year 4 Year 5
A FEASIBILITY STUDY
1 Market Study (Identify potential market/off-
taker and rates
2 Technical Study
a. Installation of meteorological mast/
LIDAR/SODAR
b. Wind data gathering, processing,
analysis and interpretation
c. System/Distribution Impact Study (SIS
or DIS)
d. Identification of Production Area
e. Detailed Wind Farm Modeling
3 Management Study
a. Implementation strategy of
development and construction of the
project
b. Identification and short listing of
potential EPC Contractor, Owner's
Engineer and O & M
4 Social and Environmental Study (Applicable
permits, licenses and agreements for the
conduct of feasibility study)
5 Financial Study
a. Financial modelling
b. Financial Closing
B DECLARATION OF COMMERCIALITY/NON-COMMERCIALITY
C OTHERS
TOTAL COMMITMENT -
Prepared by: Approved by:
Signature over Printed Name Signature over Printed Name
Designation, Company Designation, Company
TEMPLATE FIVE (5)-YEAR WORK PLAN FOR CERTIFICATE OF AUTHORITY ANNEX ___
OFFSHORE WIND WORK PLAN
Wind Project Name: __________________________________
Location: ____________________________________________
RE Developer: __________________________________________
TIMELINE COST (PHP)
WORK COMMITMENT Year 1 Year 2 Year 3
Year 1 Year 2 Year 3
1 2 3 4 1 2 3 4 1 2 3 4
A. ACQUISITION OF PERMITS AND OTHER APPROVALS*
1 Stakeholder engagement and public consultations
2 Local Government Units
a. Barangay (if applicable)
b. Municipal (if applicable)
c. Provincial (if applicable)
3 Department of Environment and Natural Resources
a. Environmental Management Bureau
b. Biodiversity Management Bureau
c. Forest Management Bureau (if applicable)
d. Land Management Bureau (if applicable)
4 Department of Agriculture
a. Bureau of Fisheries and Aquatic Resources
5 Department of Transportation
a. Civil Aviation Authority of the Philippines
b. Maritime Industry Authority
c. Philippine Coast Guard
d Philippine Ports Authority
National Commission on Indigenous People (if applicable)
6
Other applicable agencies/authorities with jurisdiction over
7
the OSW operations
B. PRELIMINARY RESOURCE ASSESSMENT/PRE-
FEASIBILITY STUDY
1 Site Survey
2 Resource Assessment
3 Geophysical and Bathemetry Survey
4 Micro-Siting for the Installation/Deployment of
Meteorological Mast/Remote Sensing Device
5 Energy Yield Estimate
6 Wind Farm Modelling/Conceptual Design
7 Port and Supply Chain Assessment
8 Transmission and Interconnection Assessment
9 Market Study
10 Financial and Economic Study
C. INVESTMENT DECISION
1 Signing of OSWESC; or
2 Relinquishment of OSWEC Application
D. OTHERS
Note:
* Tentative list of agencies/bureaus/authorities, subject to change depending on the results of DOE's Study on Permitting and Consenting of Offshore Wind Projects
Prepared by: Approved by:
Signature Over Printed Name Signature Over Printed Name
Designation, Company Designation, Company
TEMPLATE FIVE (5)-YEAR WORK PLAN FOR WEOC ANNEX - __
WIND WORK PLAN
Wind Project Name: _________________________
Location: __________________________________
RE Developer: _____________________________
TIMELINE FINANCIAL COMMITMENT (PhP)
WORK COMMITMENT Year 1 Year 2 Year 3 Year 4 Year 5
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Year 1 Year 2 Year 3 Year 4 Year 5
A PRE-CONSTRUCTION
1 Identify and secure market/off-taker and
rates
2 System/Distribution Impact Study (SIS or
3 Identification of Production Area
4 Detailed Wind Farm Modeling
5 Implementation strategy of development
and construction of the project
6 Negotiation and Contract Signing with EPC
Contractor, Owner's Engineer and O & M
7 Application and acquisition of applicable
permits, licenses and agreements
8 Financial modelling
9 Financial Closing
10 Submission of EPC and Work Schedule to
DOE
4 Detailed Engineering Design
B CONSTRUCTION
1 Start of Construction
2 Electromechanical Completion
3 Full Completion of Construction
C POST CONSTRUCTION
1 Testing and Commissioning
D OPERATION AND MAINTENANCE
1 Commercial Operation
2 Repair and Maintenance
E OTHERS
TOTAL COMMITMENT -
Prepared by: Approved by:
Signature over Printed Name Signature over Printed Name
Designation, Company Designation, Company