Unit 5
Unit 5
FINANCE MANAGEMENT
By
V. Kamala
Asst Prof
DOIE, Anna University
Capital Budgeting
FV = PV(1 + i)n
where: FV = Future Value of an investment (project)
PV = Present Value of that same investment
i = Interest rate, discount rate or cost of capital
n = Number of years
Example:
Invest $1000 today (PV)
for 1 year(n)
at an interest rate of 10% (i).
As a result, the investment is worth
$1000(1+.1)1 = $1,100 at the end of project year # 1,
$1000(1+.1)2 = $1210 at the end of project year # 2, etc.
What happens when you have two different investments (2 different projects)
with varying rates of return?
We need to adequately compare those 2 projects on equal terms (or, the same
basis) !
Time Value of Money Method:
Discount Rates
You put both on equal terms by changing the
formula slightly to evaluate all future cash flows at
time zero or today
PV = FV / (1+i) n
Example:
◼ You have a project that promises you $1000 of
profit at the end of the first year.
◼ Discount rate is 10%. So, Present Value (today)
of project is
◼ PV = $1,000/ = $909
(1+0.1)1
◼ The project is worth only $909 today
Net present value (NPV)
Net present value is the difference between the present value of cash
inflows and the present value of cash outflows that occur as a result of
undertaking an investment project. It may be positive, zero or negative.
These three possibilities of net present value are briefly explained below:
Positive NPV:
◼ If present value of cash inflows is greater than the present value of the
cash outflows, the net present value is said to be positive and the
investment proposal is considered to be acceptable.
Zero NPV:
◼ If present value of cash inflow is equal to present value of cash outflow,
the net present value is said to be zero and the investment proposal is
considered to be acceptable.
Negative NPV:
◼ If present value of cash inflow is less than present value of cash outflow,
the net present value is said to be negative and the investment proposal
is rejected.
◼ Projects with a positive NPV should be
considered if financial value is a key criterion
n
Ft
Σt=
(1 + t
k)
1
Determines the NPV of all cash flows by discounting them by
required rate of return.
Project A Project B
Initial value of investment Rs. 5,00,000 Rs.11,00,000
Present value of cash inflows Rs.6,00,000 Rs. 12,50,000
NPV Rs.1,00,000 Rs. 1, 50,000
n
CFt
IRR:
IO
(1 +
t= IRR)
Σ t =
1
◼ Step 1: Select 2 discount rates for the calculation of NPVs
You can start by selecting any 2 discount rates on a random
basis that will be used to calculate the net present values in
Step 2.
◼ Step 2: Calculate NPVs of the investment using the 2
discount rates
◼ Step 3: Calculate the IRR
Using the 2 discount rates from Step 1 and the 2 net
present values derived in Step 2, you shall calculate the IRR by
applying the IRR Formula stated below.
Internal Rate of Return
Where:
R1 = Lower discount rate
R2 = Higher discount rate
NPV1 = Higher Net Present Value (derived from R1)
NPV2 = Lower Net Present Value (derived from R2)
IRR