100% found this document useful (1 vote)
389 views17 pages

Detailed Quantity Surveying With Earthworks

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
389 views17 pages

Detailed Quantity Surveying With Earthworks

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

DETAILED QUANTITY SURVEYING

TOPICS COVERED:
● BILL OF QUANTITY
● TAKING OFF
● EARTHWORKS
BILL OF QUANTITY VS BILL OF MATERIALS

Bill of Quantities (BOQ) includes an itemized list of all projects cost -


including labor and materials.

Bill of Materials (BOM) only includes materials.


BOQ FORM Measurement of dimensions

Expressed in m³, m², m


Measurement of Dimensions
Taking off (Quantity):
Volume = L x W x D
The process of preparing or
Area = L x W
defining a detailed list of all
labour and materials necessary for Linear Meter = L
the work and entering the items Where,
on properly dimensioned paper.
L - length
W - width/breadth
D - depth/height
3 Methods:
1. Out-to-out method
2. In-to-in method
3. Center Line method
EX 1. FIND THE VOLUME OF EXCAVATION OF TRENCH, BRICKWORK
IN CEMENT MORTAR, AND PCC.

SECTION
PLAN
BOQ FORM:
EARTHWORKS
Takes place after clearing all obstructions at natural grade in the
construction site and staking.

Covers the following items:


● EXCAVATION
● BACKFILLING
● EMBANKMENT
● SOIL COMPACTION
EXCAVATION
EXCAVATION COMPUTATION:
The process of moving soil, rocks,
existing subgrade structures or Volume = L x W x D
other materials in the purpose of
Where,
attaining a specific grade, as L - length
indicated on the Plans, for the W - width/breadth
construction of footings, at-grade D - depth/height
and subgrade beams, and laying of
plumbing lines and facilities
(septic tank, trench drains, etc.).
BACKFILLING BACKFILL COMPUTATION:
V = 1.25 (V - Vѕ)
Backfilled materials shall be
approved as non-swelling/ non- Where,
expansive materials such as clays. V - Volume of Backfill Materials
V - Volume of Excavated Materials
Excavated materials may be Vѕ - Volume of subgrade structural
considered as backfill materials if members
it passes the conditions
mentioned. 1.25 = Swell Factor
EMBANKMENT EMBANKMENT COMPUTATION:
V = 1.25V
Similar requirement for
backfilling materials. Where,
V - Volume of Embankment
The embankment/filling materials Materials
must be new for those to be V - Volume of Embankment
placed under unreinforced thin Materials in compacted state
concrete slabs and beneath
pipeline as supports against 1.25 = Swell Factor
cracking.
COMPACTION
● Prevents the likelihood of settlement of soil under concrete structures
which may cause potential cracking
● Usually done using a plate compactor
● Payable in terms of square meter (m²)
EX 2. Calculate the volume of excavation and backfill required
from the drawing shown: 200

3500

C1 C1
NGL
3000
1300

C1 C1 300 1500 x 1500

PLAN SECTION
EX 3. How much will it cost excavate 100 m³ using 10 men
at Php 327.00/day per man?
Given: 1 man can excavate 0.72 m³/day
EX 3. How much will it cost excavate 100 m³ using 10 men
at Php 327.00/day per man?
Given: 1 man can excavate 0.72 m³/day
Using 10 men:
Accomplishment/day = (Capability of 1 man per day) x (No. of men)
= (0.72 m³/day)(10 men)
= 7.20 m³/day
Number of days = Total volume of excavation / Accomplishment per day
= (100 m³) / (7.20 m³/day)
= 13.89 days = say 14 days
EX 3. How much will it cost excavate 100 m³ using 10 men
at Php 327.00/day per man?
Manpower cost:
Total Direct Cost = (Php 327/day/man)(10 men)(14 days)
= Php 45, 780.00
EX 4. How much will it cost backfill 85 m³ using 9 men
at Php 327.00/day per man?
Given: 1 man can compact 1.00 m³/day

You might also like