The document describes a critical path analysis for wedding and apartment renovation project plans. It provides the activities, earliest and latest start and finish times, and identifies the critical paths and slack for each. The wedding critical path is A-D-F-H and the project requires 22 weeks. The apartment project will be completed by September 1 as the latest finish is week 16.

Uploaded by

h.123123 saleh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
157 views2 pages

Assignm

The document describes a critical path analysis for wedding and apartment renovation project plans. It provides the activities, earliest and latest start and finish times, and identifies the critical paths and slack for each. The wedding critical path is A-D-F-H and the project requires 22 weeks. The apartment project will be completed by September 1 as the latest finish is week 16.

Uploaded by

h.123123 saleh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Exercise 3:

Critical Path for Wedding Plans. To help with preparations, a couple has devised a project network to describe the
activities that must be completed by their wedding date. In addition, they have estimated the time of each activity
(in weeks).

a. Identify the critical path. A-D-F-H


b. How much time will be needed to complete this project? 22 weeks
c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?
No, Activity D cannot be delayed without delaying the entire project because it's on the critical path.
d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? Yes, Activity C can be
delayed without delaying the entire project. The maximum delay allowed for activity C is the amount of slack, which
is 2 weeks.
e. What is the schedule for activity E?
the schedule for Activity E is from week 3 to week 10
Activity Earliest Earliest Latest Latest Slack Critical
Start (ES) Finish (FS) Start (LS) Finish (LF) (LS–ES) Path?
E 3 10 4 11 1

Activity Earliest Earliest Latest Latest Slack Critical


Start (ES) Finish (FS) Start (LS) Finish (LF) (LS–ES) Path?
A 0 5 0 5 0 YES
B 0 3 1 4 1
C 5 12 7 14 2
D 5 11 5 11 0 YES
E 3 10 4 11 1
F 11 14 11 14 0 YES
G 11 21 12 22 1
H 14 22 14 22 0 YES
Exercise 4:
Apartment Building Renovation. Jefferson Park Apartments is undertaking a summer renovation of its main
building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The
manager identified the following renovation activities and their estimated times.

a. Draw a project network.


b. What are the critical activities? A,D,E,H are the critical activities.
c. What activity has the most slack time? activity F has the highest difference between LS and ES, which means it has
the most slack time.
d. Will the project be completed by September 1? Yes since the latest finish is 16 SO, the project will be completed by
September 1.

Activity Earliest Earliest Latest Start Latest Slack Critical


Start (ES) Finish (EF) (LS)) Finish (LF) (LS–ES) Path?
A 0 3 0 3 0 YES
B 0 1 2 3 2
C 0 2 1 3 1
D 3 7 3 7 0 YES
E 7 12 7 12 0 YES
F 3 6 7 10 4
G 7 13 10 16 3
H 12 16 12 16 0 YES