Weekly Environmental Inspection Report - ARCADIS

The document provides an environmental inspection report for a construction project. It identifies waste management, oil spills, and other issues as critical. It summarizes observations from the inspection and required follow up actions to address non-compliance.

Uploaded by

sana ullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views5 pages

Weekly Environmental Inspection Report - ARCADIS

The document provides an environmental inspection report for a construction project. It identifies waste management, oil spills, and other issues as critical. It summarizes observations from the inspection and required follow up actions to address non-compliance.

Uploaded by

sana ullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

CONSTRUCTION ENVIRONMENTAL INSPECTION REPORT

INSPECTION OVERVIEW
Report Number: CEIR-ARC-20220919-04 Date: 29 September 2022
PMC: ARCADIS Start Time: 2:00 pm
Project Title: • Cooling district Duration: 1:15 hours
• Almeshraq
Report by (name): Najoud Alsaiari Report by AESG
(company):
Comments Waste is critical issue in the project site -
Project Stakeholder Name & Company
Attendance0

Misk- Client Name: Shaker A Katu


AESG Name: Najoud Alsaiari
PMC Name: Absence
Contractor Env. Name: Absence

Site Observation Map (29 Sep ,AESG,2022)

Critical Issues Observed:

Critical
Summary of Critical Environmental Issues Observed
Issue #
1 Waste Management
Rank in order of
criticality

2 Oil spill
3

Summary of Inspection Observations &


Follow-up:

# Report Content / Summary # %


1 New observations identified during this inspection 13 N/A
2 Reported observations not inspected / verified during this inspection 0 N/A
3 Inspection Observations Closed during this inspection 0 N/A
4 Inspection Observations verified as not completed during this inspection 0 N/A
*Note – All open and current observations must be closed
within one week of the date of this report.

Page 1 of 11
Potential Potential Failure Consequence example Response
Description
High Immediate and/or Direct Environmental Impact; Potential for adverse environmental impact Immediate

Latent and/or Indirect Environmental Impact; Potential for adverse environmental impact and unwanted
Medium conditions exist which may affect projects reputation
1 working day

Low System improvement / Minor environmental impacts 5 working days

Observed Conditions and Required


Corrections
Action Required to
# Details of Observations Made Photo of Observation

Coordination

(Day. Month. Year)


Address Non-

Close out Photograph


Date Observed

(Current; Closed; Not Completed)


(High / Medium / Low)
compliance

Potential

Status
• Record all actual and potential environmental issues observed during the
inspection • Describe the action that is required to address the non-compliant condition • Insert a representative photo of the non-compliant condition observed.
Insert • Observations should appear on the report in the chronological order in which observed • In the photo, capture where environmental impact has occurred
sequentia they were observed on site • Actions should be specific – avoid inputting multiple actions against a single where applicable
lnumber • Observations may require multiple actions to address the non-compliant observation
condition. In such cases, repeat the observation, but with a different ‘Action • Where an action has been completed to the satisfaction of the inspection
Required’ to rectify the observed lead, strike-through to indicate that the action has been closed
condition

Inspection Observations
1. • Oil tank in observed in • Contractor to
laydown area and the relocate tank to

24.70550N 46.58206E
area is open appropriate area to
avoid any potential
• No signage board to

29 September 2022
risk. Clear signage

Current
show the use of this

High
to be added
tank and the period of
showing usage and
use
date and purpose
• Hydrocarbon Odour
detected

2 • Metal waste has been • Contractor to


observed on the rocky transfer waste to
hill . It appear to be the the waste
materials used on generation area to
excavation stage which avoid any soil

24.70031N 46.59048E
has not been removed contamination

29 September 2022

Current
correctly • Contractor shall
High

provide training to
their workforce
about waste
management and
how it is important
to protect
environment
3 • Topsoil covered with • Contractor to
cement waste remove topsoil
impacted by
24.70550N 46.58206E

cement waste to
29 September 2022

the waste
Medium

Current

generation area

4 • Raw materials • Cover sheet to be


identified in the put in place for the
24.70550N 46.58206E

laydown area without big equipment to


29 September 2022
Medium

Current

a cover sheet reduce any impact


to the
• An accumulation of
environment. In
metals identified on
particular - air
the topsoil which can
quality.
contribute on soil • Corrective action to
contamination be taken by
contractor to
remove the topsoil
that contains metal
and dispose of
correctly

5 • Storage area identified • Contractor to secure


with improper storage fencing and access
of equipment – area to the area. As well
contained pipes, wood as recording in an
, electrical equipment equipment register
mixed with vegetation. of items received,
stored or used.
Remove any waste

24.705664 46.582408
from the area.

29 September 2022

Current
High
6 • Oil spill • Contractor to
remove the topsoil
• Hydrocarbon Odour

29 September 2022
contaminated by oil

Current
and dispose of as High
46.588102
24.703283
per the waste
management plan.

7 • Remains of rubber tire • Contractor to


waste remove tire waste
and relocate to the
• Foam insulation which
appropriate
is combustible and not
recycling/waste
healthy appropriate to
management area
be used
• Contractor to be
aware about the
24.703244 46.587933

level of risk of foam


29 September 2022

Current

which is considered
High

environmentally
hazardous.
• Contractor to
provide evidence
that this has been
removed correctly
and in line with the
contractors
Hazardous Waste
Management Plan.
8. • General waste • Contractor to
identified in an provide sufficient
inappropriate location waste disposal
and on the bare units and remove
ground in L21-District 5 all waste. Any

24.70354N 46.58482E
area contaminated soil

19 September 2022
should be removed

Current
High
and disposed of
correctly in
accordance with
the waste
management plan.

9. • Contractor identified • Contractor to stop


using a non-approved using this access
access road that pass road and to submit
through a small Wadi environmental
observed in Buffer incident report.

24.70351N 46.58784E
Park area. This can

19 September 2022
cause contamination

Current
High
of the soil and water.

10. • Backfilling materials • Contractors to stop


are stored in non- using this area for
approved area. This is their materials.
impacting accessing Contractor is only
roads via the correct allowed to use 24.69323N 46.56955E
routes, dust emission. designated material
19 September 2022
Waste is also being storage areas.
Current
High

disposed of behind • Contractor to


District Cooling area. remove waste in the
area.

Najoud Als
Report Generated by: Najoud Alsaiari Signature Report Date: 29 September2022

Description:
Note:
• The ‘Closure Rate’ is a measure of Contractors ability to successfully address previously identified observations and conditions.
• The Closure Rate is calculated as follows:
o Total number of observations made during the previous inspection = A
o Total number of observations made during the previous inspection not observed during the current inspection = B
o Total number of observations successfully completed = C
o Total number of observations which have not being completed as observed during the current inspection = D
o (A - B) = E
• C / E x 100 = Closure Rate (Closed)
• D / E x 100 = Closure Rate (Not Completed)
Previous observations on the report which have been assigned a “Closed Status” are highlighted as such and will be deleted from the next report for the same
location. This allows for all location specific observations to be tracked to closure.