0% found this document useful (0 votes)
25 views89 pages

Patu PDF

Uploaded by

Ashutosh Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views89 pages

Patu PDF

Uploaded by

Ashutosh Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 89

Govt.

of India, New Delhi

Electrification of Remote Hilly Area


Village : Tally Valley (Patu), 16 HH
Distt. : Lower Subansiri, Arunachal Pradesh
Micro Hydro Electric Based Electrical Power Plant (1 X 10 kW)

Prepared by:
Alternate Hydro Energy Centre
Indian Institute of Technology
Roorkee-247 667

January 2007
Govt. of India, New Delhi

Electrification of Remote Hilly Area


Village : Tally Valley (Patu), 16 HH
Distt. : Lower Subansiri, Arunachal Pradesh
Micro Hydro Electric Based Electrical Power Plant (1 X 10 kW)

Prepared by:
Alternate Hydro Energy Centre
Indian Institute of Technology
Roorkee-247 667

January 2007
TABLE OF CONTENT
Sl. No. Items Page. No.
i. FOREWORD
ii. EXECUTIVE SUMMARY i-ii
iii. SALIENT FEATURES S-1 to S-3
iv. PHOTOGRAPHS P1 – P6

CHAPTER – 1 BACK GROUND AND BASIC DATA

1.1 INTRODUCTION 1
1.2 PROJECT SPONSOR 1
1.3 NODAL AGENCY AND ASSOCIATED ORGANIZATIONS 2
1.4 SELECTION OF VILLAGE FOR MODEL DPR 2
1.5 GENERAL INFORMATION-VILLAGE PARO 3

CHAPTER – 2 LOAD ASSESSMENT/ENERGY REQUIREMENT AND


INSTALLATION CAPACITY

2.1 LOAD ASSESSMENT/ ENERGY REQUIREMENT 6


2.2 POWER HOUSE INSTALLATION CAPACITY 8

CHAPTER –3 SURVEYS AND INVESTIGATIONS


3.1 RECONNAISSANCE SURVEY 9
3.2 TOPOGRAPHICAL SURVEYS 9
3.3 REGIONAL GEOLOGY 9
3.4 GEOLOGY AT THE LOCATION OF CIVIL STRUCTURE 9
3.5 SEDIMENT (SUSPENDED & BED LOAD) INFLOW & 9
GRAIN SIZE COMPOSITION
3.6 DISTRIBUTION SYSTEM & RURAL ELECTRIFICATION 10
3.7 WATER QUALITY 10
3.8 CONSTRUCTION MATERIAL SOURCES 10

CHAPTER – 4 TECHNO-ECONOMIC STUDIES

4.1 PRESENT DEVELOPMENT AND EXISTING POWER FACILITIES 11


4.2 AVAILABILITY OF DISCHARGE 11
4.3 LOAD FORECAST 12
4.4 POWER POTENTIAL 12
4.5 DETAILS OF VILLAGE COVERED BY THIS SCHEME 12
4.6 INSTALLED CAPACITY AND NO. OF UNITS 12
4.7 ENERGY GENERATION 12

CHAPTER – 5 CIVIL WORKS

5.1 GENERAL 13
5.2 DIVERSION WEIR & INTAKE 13
5.3 FEEDER CUM POWER CHANNEL 14
5.4 DESILTING CUM FOREBAY TANK 14
5.5 FOREBAY 15

AHEC/MNES/C-347/AAS/Model DPR/MHP i
5.6 PENSTOCK 16
5.7 SPILLWAY & SPILLWAY CHANNEL 16
5.8 POWER HOUSE BUILDING 17
5.9 TAIL RACE CHANNEL 18
5.10 APPROACH ROAD 18

CHAPTER –6 ELECTRO MECHANICAL WORKS

6.1 GENERAL 19
6.2 CHOICE TURBINE 19
6.3 SYNCHRONOUS GENERATOR 25
6.4 GOVERNOR 26
6.5 MAIN INLET VALVE 26
6.6 ELECTRICAL CONTROL, PROTECTION AND METERING SYSTEM 27
6.7 STATION AUXILIARIES 29
6.8 EARTHING 32
6.9 POWER AND CONTROL CABLES 32
6.10 POWER EVACUATION 32

CHAPTER –7 COST ESTIMATES


7.1 GENERAL 33
7.2 ABSTRACT OF COST 33

CHAPTER -8 FINANCIAL AND ECONOMIC STUDIES

8.1 ESTIMATES OF COST AND PHASING 38


8.2 GENERATION COST 38

CHAPTER –9 CONSTRUCTION PLANNING


9.1 PRE-CONSTRUCTION ACTIVITIES 43
9.2 CONSTRUCTION ACTIVITIES/PERIOD 43
9.3 CONSTRUCTION MATERIAL 44
9.4 MANUFACTURED ITEMS 44
9.5 CONSTRUCTION OF CIVIL WORKS 45
9.6 CONTRACTUAL PERIOD OF O & M 45

CHAPTER-10 OPERATION AND MAINTENANCE OF PLANT & SYSTEM

10.1 GENERAL 47
10.2 FORMATION OF COMMITTEE FOR SUPERVISION OF O & M 47

CHAPTER-11 ENVIRONMENTAL IMPACT AND BENEFITS

11.1 ENVIRONMENTAL IMPACTS 49


11.2 BENEFITS 49

ANNEXURE – I
ANNEXURE – II
ANNEXURE – III

AHEC/MNES/C-347/AAS/Model DPR/MHP ii
LIST OF DRAWINGS

SL. NO. DRAWINGS NO. TITLE

1 C-341-1 LOCATION OF MAP OF VILLAGE


2 C-341-2 GENERAL LAYOUT OF WORKS
3 C-341-3 L- SECTION OF WATER CONDUCTOR SYSTEM
4 C-341-4(i) FEEDER CHANNEL
C-341-4 (ii) DIVERSION
5 C-341-5 DESILTING CUM FOREBAY TANK
6 C-341-6 DETAILS OF PENSTOCK PIPE
7 C-341-7 DETAILS OF POWER HOUSE
8 E-341-1 SINGLE LINE DIAGRAM

AHEC/MNES/C-347/AAS/Model DPR/MHP iii


FOREWORD
(This Foreword is not part of the Model DPR)

The Ministry of Non-Conventional Energy Sources, Government of India (MNES) have


identified over 24,000 remote villages which are proposed to be electrified through small
renewable energy sources e.g. Small Hydro Power, Biomass Gasification and Solar
Photovoltaic Technology, so as to improve the well being of population living in the far flung
isolated areas.

To make the Remote Village Electrification (RVE) programme successful, it is necessary that
the planning, design, execution and operation and maintenance of RVE projects is efficient
and reliable and also economical in the long run. MNES, vide letters number 13/5/2005 – 06
RVE dated 23.12.2005 and even number dated 09.03.2006 has asked the alternate Hydro
Energy Centre, IIT, Roorkee (AHEC) to prepare model detailed project reports (DPRs) for the
following four categories:

1. Category “A – 1” Village with 40 households in the hilly area.


2. Category “A – 2” Village with 40 households in the plain area.
3. Category “B – 1” Village with 200 households in the hilly area.
4. Category “B – 2” Village with 200 households in the plain area.

The villages are to be selected from the States of Uttarakhand and Arunachal Pradesh to make
the DPRs more versatile and practical so that these model DPRs can be used with slight site
specific changes by even those users who may not have much technical expertise.

This Document has been prepared for RVE through Hydro Electric Power Plant for the
Category “A-1” village: Tally Valley (Patu) (Circle-zero, District – Lower Subansiri, State –
Arunachal Pradesh) and also to serve as a Model Document recommended for use as a guide
for RVE of similar category villages (including those ones having some variation in number
of house holds) with plant and site specific modification. Any suggestions from institutions,
organizations, users and interested individuals are welcome. Suggestions should be addressed
to:
Head,
Alternate Hydro Energy Centre,
Indian Institute of Technology,
Roorkee – 247667, Uttaranchal, India.

E-mail: [email protected]
Fax: +91 – 1332 – 273517.

AHEC/MNES/C-347/AAS/Model DPR/MHP
EXECUTIVE SUMMARY

With the rapid changing scenario of fast depleting conventional energy sources, the future of
conventional electric power system is getting uncertain. This has led to worldwide thrust on
development and use of non-conventional energy sources for electric power generation and
use. This coupled with almost no chances of extending the electric power grids to the remote
hilly villages and particularly these located in the deep in the forest due to problems
associated with drawing power lines though it and their O&M, use of non–conventional
energy sources remains the only alternative for providing reliable electricity to such remote
villages.

Patu (Distt. Lower Subansiri, Arunachal Pradesh) is a human settlement set deep in the forest
having thickly vegetated mixed forest.

Most of the village people have low income. Micro hydro based electric power plant
proposed for this village will be helpful for

i. Improving the living conditions of the village people.


ii. Generating new opportunities for over all upliftment
iii. Providing light for study and promote education amongst children promising them
better future.
iv. Creating awareness about the renewable sources of energy and using them for enter
premiership like micro cottage industries etc. thereby improving economic conditions.
v. Saving kerosene and forest wood presently being used for lighting.
vi. Creating environmental awareness amongst the people and help control available
destruction of the forest.

The project is envisaged to be constructed in a period of 12 months from the date of singing
the contract agreement. The proposed period takes core of the adverse conditions of monsoon
season, transport problems and afford required time for better construction management and
quality of works etc.

AHEC/MNES/C-347/AAS/Model DPR/MHP i
The economic condition of most of the villagers being low, one time contribution of Rs. 1000
per house hold has been proposed towards initial construction of the plant (which, through,
insignificant, will create a sense of belongingness thereby help make the scheme successful
and send good message to other to follow suit) and a monthly payment of Rs. 60/- per month
towards O&M (which they will be able to pay as they will have a monthly saving on cost of
Kerosene). The balance cost of the O&M will have to be managed by the nodal agency.
Source of funding for construction of plant and the system is proposed to be as:

i. Incentive subsidy by MNES Rs. 11.61 Lacs


ii. Balance Project Cost Rs. 37.89 Lacs
iii. Total Cost of the Project Rs. 49.50 Lacs

The cost of generation works out to Rs 10.97 per kWh and Rs. 16.45 per kWh without
subsidy and Rs. 9.10 per kWh and Rs. 13.64 per kWh with subsidy at 90% and 60% load
factor respectively

AHEC/MNES/C-347/AAS/Model DPR/MHP ii
SALIENT FEATURES

I NAME OF PROJECT : Patu Micro Hydel Project,


Talley Valley

1 LOCATION

i. State : Arunachal Pradesh


ii. District : Lower Subansiri
iii. Circle : Zero
iv. Village : Talley Valley
v. Village census code : 00102800
Latitude : 27.546320
Longitude : 93.900960
vi. Access : The site can be approached from the Ziro
Town. Through all weather metalled road
upto Monopoliyang (8 km) from
Monopoliyang the Patu (Talley Valley)
Village is 8.0 km (Foot Track)

2 HYDROLOGY

i. Name of River/Nallah : Patu


ii. Dependable flow as adopted in
design for power generation : 0.133 cumec
iii. Type of Nallah : Perennial
iv. Minimum flow : 0.116 cumec
v. Maximum flow (Flood) : 1.464 cumecs

3 DIVERSION WEIR

i. Type : Bush & Boulder


ii. Shape : Trapezoidal
iii. Length : 5.0 m
iv. Design discharge 1.464 cumecs

4 INTAKE CUM POWER CHANNEL

i. Length : 200 m
ii. Shape/Material : Rectangular/ Stone masonry
iii. Size : 0.60 m
a. Width : 0.30 m
b. Depth : 1 in 400
iv. Bed slope : 0.30 m
v. Full supply depth : 0.15 m
vi. Free board : 0.130 cumec
vii. Design discharge

AHEC/MNES/C-347/AAS/Model DPR/MHP S-1


5 DESILTING CUM FOREBAYTANK

(i) Forebay Tank


a. Length : 4.0 m
b. Width : 1.8 m
: 0.40 m
c. Full supply depth :
d. Free board :
0.30 m
e. Type/material : R.C.C.
f. Design discharge : 0.130 cumec

(ii) Spillway

a. Size : 5.10 m x 1.8 m


b. Width : 1.5 m
c. Depth : Total 1.5 m
d. Free Board : 0.3 m
e. Type / Material : RCC.
f. Design Discharge : 0.130 cumec

6 PENSTOCK

i. Number : 1 No.
ii. Diameter : 250(ID), 262 mm (O.D.)
iii. Thickness : 6 mm
iv. Length : 150 m
v. Design discharge : 0.130 cumec
vi. Material : Steel

7 POWER HOUSE
i. Type : Stone Masonry with intermediate
: RCC. Pillars and C.G.l. sheet
ii. Size : Roofing.
iii. Capacity : 7.0 m x 5.0 m x 4.0 m
iv. Gross head 1 x 10 kW
v. Net head : 18 m
16 m (Approx)
8 ELECTROMECHANICAL EQUIPMENT

i. Turbine
a. Type Cross flow
b. Number 1 No.
c. Capacity of each turbine
d. Speed 10 kW
750 rpm
ii. Generator
a. Type of generator Synchronous
b. Number 1
c. Capacity 10 kW 0.85 PF, 50 Hz,3 Phase

AHEC/MNES/C-347/AAS/Model DPR/MHP S-2


9 TAIL RACE CHANNEL

i. Shape : Rectangular
ii. Size : 1.1 m x 0.7 m
iii. Length : 25 m (Approx)

10 POWER

i. Installed capacity : 1 x 10 kW
ii. No. of Units generated

a. At 90% load factor : 0.079 Million Units


b. At 60% load factor : 0.053 Million Units

11 TRANSMISSION AND DISTRIBUTION

415kV, 3 phase : 1.0 km

12 ESTIMATES OF COSTS

i. Civil Works : Rs. 36.05 lacs


ii. Electro mechanical works : Rs. 6.95 lacs
iii. Transmission and Distribution Line : Rs. 3.00 lacs
iv. Other expenses : Rs. 3.50 lacs
a. Total Cost of project : Rs. 49.50 lacs
b. Cost per kW : Rs. 4.95 lacs

13. COST OF GENERATION PER kWh

i. At 90% load factor:


a. Without subsidy : Rs. 10.97
b. With subsidy : Rs. 9.10

ii. At 60% load factor:


a. Without subsidy : Rs. 16.45
b. With subsidy : Rs. 13.64

AHEC/MNES/C-347/AAS/Model DPR/MHP S-3


Photo -1 : Approach Road to the Village Talley Valley (Patu) Village.

Photo-2 : Different View of the Houses Located in Talley Valley (Patu) Village.
Photo-3 : Different View of the Houses Located in Talley Valley (Patu) Village.

Photo-4 : View of Isolated House in the Talley Valley (Patu) Village.


Photo-5 : A View of the Patu Nala.

Photo-6 : Different View of the Patu Nala.


Photo-7: Different View of the Patu Nala

Photo-8: A View of Diversion Site. Stream is Having Normal Gradient.


Photo-9: A Close View of Diversion Site.

Photo10: Marking at the Power House Site.


Photo-11: Flat Terrace for Power House Site.

Photo-12: Approach Road to Power House Site


CHAPTER –1

BACK GROUND AND BASIC DATA

1.1 INTRODUCTION

There is acute shortage of electric power generation in the country so much so that the
areas already connected to the power grids are subjected to frequent power cuts. The
available fuel resources being used for electricity generation are getting fast depleted.
This problem and sensitivity coupled with drawing the electric power lines through
deep forest, the cost involved in extending the power grids and cost and problems in
O & M of the line of isolated remote villages make it almost impossible to make grid
the electricity reach the remote villages.

The economic and social conditions of the inhabitants of un-electrified remote


villages in the Arunachal Pradesh State are poor. Electricity being one of the basic
infrastructural requirements for development and progress, the only hope in the above
scenario is the use of renewable energy sources to generate and supply electricity to
the remote villages. In an effort towards this end, this project has been conceived for
immediate electrification of village Talley Valley (Patu) in the Lower Subansiri
district of Arunachal Pradesh. Talley Valley falls within the famous Birds Sanctuary
located at higher elevation of Arunachal Pradesh Pradesh.

1.2 PROJECT SPONSOR

MNES, vide Letters number 13/5/2005 -06 RVE dated 23.12.2005 and even number
dated 09.03.2006 has asked the alternate Hydro energy Centre, IIT, Roorkee (AHEC)
to prepare model detailed project reports (DPRs) for the following four categories:

1. Category “A-1” village with 40 households in the hilly area.


2. Category “A-2” village with 40 households in the plain area.
3. Category “B-1” village with 200 households in the hilly area.
4. Category “B-2” village with 200 households in the plain area.

The villages are to be selected from the States of Arunachal Pradesh and Uttarakhand
to make DPRs more versatile and practical so that these model DPRs can be used with

AHEC/MNES/C-347/AAS/Model DPR/MHP 1
slight site specific changes by even those users who may not have much technical
expertise.
MNES, GOI, is subsidizing the cost of RVE projects to large extent. The balance
project cost is generally met by the Nodal Agency and the people of the villages.

1.3 NODAL AGENCY & ASSOCIATED ORGANIZATIONS

Arunachal Renewable Energy Development Agency, Itanagar (APEDA) has been


assigned to carry out development work through non-conventional sources by the
Government of Arunachal Pradesh. For the present DPR works APEDA has been
nominated as Nodal Agency by MNES.

In identification and selection of the village to be electrified the cooperation was


sought from department of APEDA.

1.4 SELECTION OF VILLAGE FOR MODEL DPR

Reconnaissance survey was undertaken to various remote villages located in the


Lower Subansri District for selection of village(s) as per suggestion by APEDA. After
gathering information and data, interacting with the local people and the village level
organizations e.g Gram Panchayat, survey and assessment of various aspects related
to the generation of power through MHP and electrification of remote village, Talley
Valley was selected for preparation of Model Detailed Project Report.

Here it is intended to electrify the remote village of Talley Valley (Patu) located deep
within the forest. The villagers are subjected to isolated life, having limited resources
and access. Their income is also restricted to marginal cultivation, occasional labour
and through seasonal tourism trade. Due to complete absence of sources of
entertainment, people have adopted to drinking habits (local wine) which has further
detoriated their economic status.

To uplift the life of this village dominated by, backward community, it is essential to
provide electricity so as their living standard can be raised and they can augment their
income through tourist industry which is likely to grow rapidly after availability of
power in the area.

AHEC/MNES/C-347/AAS/Model DPR/MHP 2
It is difficult to link the village through State/National grid as it will be next to
impossible to draw the HT line through the forest area. Therefore it has become
imperative to provide the power to this remote village through a non conventional
source of energy. Due to availability of a stream in the surroundings of the village, the
electrification through micro hydroelectric power has been selected for the village.

1.5 GENERAL INFORMATION – VILLAGE TALLEY VALLEY


1.5.1 Location And Access

Talley Valley village in the Lower Subansri District of Arunachal Pradesh is a human
settlement set deep in broad valley within thickly vegetated mixed forest. It is linked
with Zero Town through highway up to Monipoliyang (8km) and from their through
all weather umetalled nonmotorable forest road (8km).

The nearest Railway Station North is situated at about 170 km from the village. From
Zero Town Jeep can be hired upto monipoliyang which is the only source of
communication in the area. The nearest block office is at a distance of 20 km. The
nearest 11 kV substation is around 11 km from the village.

1.5.2 Socio Economic Status

Talley Valley village is dominated by backward community having 16 households


with a population of 29. Each family consists of 2 to 3 members. These villagers are
having a second house also at lower altitude.

Most of the villagers are laborers having limited resources. Main crops of the area are
paddy and millet.

Nearly all the inhabitants are engaged in the casual labour and to cultivation on a
minor scale. People also have second place to live to which they move in the winters.
With the provision of power in the area it is expected that the in the area tourism will
get a boost and people will stay in the village only. Wood is used for cooking and
warming proposes. The forest department is the sole employee in the area. In general
the income of a family varies between Rs.1500.00 to Rs 2000.00 pm.

1.5.3 Additional Sources Of Income

To augment their income most of the families keep poneys. Nearly a family keeps 3 to 4 poneys.

AHEC/MNES/C-347/AAS/Model DPR/MHP 3
1.5.4 Education

Talley Valley village does not have any primary school. Overall education level of the
village as revealed by mukhia is as follows:

12th standard - 1
th
10 standard - 2
th
8 standard - 4
5th standard - 6
1.5.5 Health

People are in general having good health. In case of illness people have to travel for
preliminary treatment at PHC at Monipoliyang. For hospital facilities they have to go
to Hapoli.

1.5.6 Roads And Transport


Village is connected with Zero town through all weather unmettaled forest road (8km)
up to Monipoliyang, and then through 8km metalled road. Jeep plies on the roads
between Zero and Monipoliyang once a day to ferry the people. Public transport is not
available on this route.

1.5.7 Electricity availability

Village is located deep in the forest, where transmission lines cannot be drawn
through thick forests. The village is un-electrified and the possibility of getting power
from the grids is also insignificant. Villagers do not have any solar home modules.
Kerosene is being used for illuminating the houses.

1.5.8 Water availability


Drinking and irrigation water is drawn from the rivers and nallas encircling the
village.

1.5.9 Communication

The village is totally isolated and is not having any mode of communication with the
rest of the world.

1.5.10 Haat/Market

Market facilities are available at Monipoliyang.

AHEC/MNES/C-347/AAS/Model DPR/MHP 4
1.5.11 Grazing ground and fodder

Open grazing ground is found by the sides of the village in the valley.. Fodder in the
form of leaves and grass is also collected from the forest.

1.5.12 Wood as Fuel

Villagers are collecting wood from the forest and use it for cooking and warming in
the winters. Wood logs are also collected from the forest for construction and repair
of the houses. Villagers collect the wood in their compounds for monsoon and winter
seasons. Cow dung from domestic cattle is used for preparation of organic manure.

AHEC/MNES/C-347/AAS/Model DPR/MHP 5
CHAPTER – 2
ASSESMENT/ENERGY REQUIREMENT AND
INSTALLATION CAPACITY
2.1 GENERAL
2.1.1 Village Lay Out and Type Of Houses

Village Patu is situated in the foothills of Arunachal Pradesh along the border with
Assam close to North Lakhimpur. The houses are spread over a large area on various
terraces of river Dulang.

The houses are mostly pakka with tin roofs. Few thatched roof houses also exist.
5 houses are having 5 to 6 rooms and the remaining 11 houses 3 to 4 rooms.

2.1.2 Use of Electricity


The use of electricity power is proposed as below:
i. Domestic Use
ii. Public Lighting
iii. Power Supply to Government Offices
iv. Multipurpose Uses
v. Future Expansion
2.1.3 Use Requirement
i. Domestic Use
a. On detailed enquiry from the local people and the officials, it was gathered that out of 16
houses, 5 houses will opt for higher load and the remaining 11 houses some what lower
loads. The domestic load is expected to comprise 2 Nos. 11 W CFLs, 1 Nos. 60 W bulb
and loads comprising radio/T.V., Fan, heating etc. The domestic load is assessed to be of
the order of 750 W in case of 5 households and 500 W in case of 11 houses holds.

b. The diversity factor is assessed to be as:


• CFLs : 100%
• Other Loads : 200%

AHEC/MNES/C-347/AAS/Model DPR/MHP 6
c. Assed load
• CFLs : 2 x 11 x 16
= 352 W or 0.352 kW
• Other Loads : ½ [5x (750 – 22) + 11 (500-22)]W
4.449 kW
Total = 0.352 + 4.449
= 4.801 kW
= Say, 10 kW
d. Supply Hours
The sum sets early and the village life settles down around 19 P.M. the supply hours
are assessed as:
• For Lighting : 6 hours (2 hours in the morning, say : 5 to
7 A. M. & 4 hours in the evening, say: 17.30 to
21.30 P.M.)
• Other Loads : 10 hours
e. Energy consumption per day works out as:
• CFLs : 0.352 x 6 kWh = 2.112 kWh
• Other Loads : 4.449 x 10 kWh = 44.490 kWh
Total = 46.602 kWh
ii. Public Lighting

The public lighting may be used for 4 hours (1 hour in the morning and 3 hours in the
evening). The requirement is assessed below:
a. No. of light points : Upto 10
b. Type of load : 18 Watts CFL
c. Lighting hours : 4
d. Power required : Upto 18 x 10 W = 0.18 kW
e. Energy Consumption : Upto 0.18 x 4 kWh = 0.72 kWh
per day
iii. Multipurpose Use
The power may be restricted to about 4 kW for about 6 hours during period of
morning and evening hours and supply about 6 kW for 6 hours during the period
beyond supply hours of above loads. Assuming a diversity factor of 300%, the energy
consumption works out to:
1/3 x 6 x (4+6) = 20 kWh

AHEC/MNES/C-347/AAS/Model DPR/MHP 7
2.2 P. H. INSTALLATION CAPACITY
2.2.1 Installed Capacity
Assuming the P.H. consumption and line losses as 10% and the future growth as 20%
in the next 10 years, the P.H. installation capacity is worked out below:

i. Domestic Load : 4.801 kW


ii. Public Lighting : 0.180 kW
iii. Future load growth : 0.2 x 4.981 = 0.9962 kW
Sub Total : 5.9772 kW
iv. P. H. Consumption & : 0.59772 kW
System Losses
Total : 6.57492 kW
Say, : 10 kW
2.2.2 Energy Consumption/Day
i. Domestic Load : 46.602 kWh
ii. Public Lighting : 0.720 kWh
iii. P.H. consumption/Losses : 0.1 x 10 = 1.00 kWh
Total : 48.322 kWh
The proposed daily use requirement of Electrical Power and Energy consumption is
tabulated below:
Table – 2.1 : Assessed Daily Use Requirement
Sl. No. Use Daily Use of
Power (kW) Energy (kWh)
1. 2. 3. 4.
1. Domestic Use 4.801 46.60
2. Public Lighting 0.18 0.72
Sub –Total 4.981 47.32
4. Further Growth 0.996 Not Added
5. P. H. Consumption, Losses 0.598 1.00
Total 6.575 48.32
Say 10 48

AHEC/MNES/C-347/AAS/Model DPR/MHP 8
CHAPTER –3

SURVEYS AND INVESTIGATIONS

3.1 RECONNAISSANCE SURVEY

Identification of the scheme was undertaken after Reconnaissance Survey of the entire
area. During reconnaissance survey approximate location for diversion site, Desilting
tank, forebay tank & powerhouse were identified.

3.2 TOPOGRAPHICAL SURVEYS

Patu Micro Hydro Electric Project is a run off- river scheme on. The water will be
diverted from the river near village Talley Valley camp site and conveyed to
powerhouse through a 200 m long feeder–cum-power channel, and about 150 m long
penstock. Preliminary survey has been carried out by the staff of AHEC,IIT Roorkee
and APEDA Itanagar.

3.3 REGIONAL GEOLOGY

The Granitic rocks of the Crystallines consisting of granites, granitic gneisses,


migmatites and pegmatites are found in a vast expanse in the regional area.

3.4 GEOLOGY AT THE LOCATION OF CIVIL STRUCTURE

Geological investigation of the proposed scheme indicates that the rocks are not
exposed in the area. Thick soil cover is obtained in the entire area over which thick
vegetation is existing.

The geo-morphological setup of the area and the pattern of vegetation indicates that
the area is stable and project can be executed safely.

3.5 SEDIMENT (SUSPENDED & BED LOAD) INFLOW & GRAIN SIZE
COMPOSITION

The water is clear in being mostly spring water from October to April. During rains
between May to September water contains sufficient amount of fine silt.

AHEC/MNES/C-347/AAS/Model DPR/MHP 9
3.6 DISTRIBUTION SYSTEM & RURAL ELECTRIFICATION

Proper distribution line network as per rural electrification code and electric
connection to individual beneficiary/consumer will be provided as per norms.

3.7 WATER QUALITY

The quality of water in the stream is good in which no organic compound mixtures or
harmful minerals are observed for construction purposes, penstock pipe and turbine.

3.7.1 Dissolved & Suspended Materials


The water of Patu Nala is slightly hard. It contains lot of suspended silt during the
monsoon for which suitable desilting arrangement has been proposed.

3.7.2 Suitability of Water


Being a Hydro Project the quality of water is not so important. However, since the
water of Patu Nala is spring water, it dose not contains organic compounds in it.
Whereas during rainy season a fair amount of suspended material is observed which is
found to settle down rapidly. No corrosion is expected in the penstock or turbine due
to quality of water after removal of silt particles up to 0.25mm size and above.

3.8 CONSTRUCTION MATERIAL SOURCES

Cement, reinforcement steel, structural steel, C.G.I. sheets and trusses for roof, doors
and windows of powerhouse can be purchased from Itanagar or North
Lakhimpur/Guwahati. Sand, Grit, Stone and stone ballast are available in the stream.

Adequate manpower will be arranged for collection of sand, stone, stone ballast from
the nearby area and buffer stock will be maintained at suitable level near the
construction location of the various project components. The material stock site will
be so selected that the site is well above and away from the estimated and observed
high flood level of the river. The site should also be safe from natural drains, safe
from scouring/flushing due to rains. Adequate buffer stock of cement and steel will be
maintained in the site store to safe guard the supply against blockage of roads due to
rains etc. The supply of cement and steel will be staggered as per bar chart.

AHEC/MNES/C-347/AAS/Model DPR/MHP 10
CHAPTER-4
TECHNO-ECONOMIC STUDIES
4.1 PRESENT DEVELOPMENT AND EXISTING POWER FACILITIES

The area is deprived of all modern development and is amongst most backward area.
There is no existing power facility as electricity is not available near the proposed
scheme. Presently firewood and kerosene is used for cooking and lighting while
traditional watermills are used for grains grinding. The area has fertile terraced fields
but with little irrigation facilities. The agricultural production is low. Each village in
Arunachal Pradesh has a stream near by, which feed them for centuries. These
streams are perennial, clean and silt free and almost flood free due to strong
vegetation in catchment area. Arunachal Pradesh is bestowed with hydro energy
abundantly by nature and is a boon for the people. Harnessing of hydro energy will
uplift the life of the remote villages.
4.2 FLOW DURATION
Based on the discharge data for the period of Jan. 2003 to Dec. 2005 of Patu stream,
which is perennial tributary of Pangih River, the flow duration analysis has been
carried out.
100% = 0.116 cumecs
75% = 0.133 cumecs
50% = 0.150 cumecs
The water available for power generation with percentage of time equaled or
exceeded is shown in Table –1.
Table –1: Flow Duration Data
Sl. % of Time Equaled or Discharge in Cumecs Average Discharge
No. Exceeded (Descending Order) (Cumecs)
2003 2004 2005
1 2 3 4 5 6
1. 8.33 0.210 0.213 0.216 0.213
2. 16.67 0.206 0.211 0.216 0.211
3. 25.00 0.202 0.207 0.212 0.207
4. 33.33 0.186 0.184 0.182 0.184
5. 41.67 0.186 0.181 0.176 0.181
6. 50.00 0.148 0.150 0.152 0.150
7. 58.33 0.139 0.138 0.136 0.138
8. 66.67 0.138 0.135 0.132 0.135
9. 75.00 0.136 0.133 0.130 0.133
10. 83.33 0.128 0.125 0.124 0.126
11. 91.67 0.118 0.121 0.124 0.121
12. 100.00 0.116 0.116 0.115 0.116
Note: The discharge was measured as 0.376 m3/s on 2.6.06 by AHEC Team.

AHEC/MNES/C-347/AAS/Model DPR/MHP 11
4.3 LOAD FORECAST

As discussed earlier, the load has been assessed as 10 kW.

4.4 POWER POTENTIAL

The power generation may vary depending open the actual equipment purchased and
their efficiency. For calculating flow available for power generation the discharge is
reduced to 90% to account for seepage, evaporation and other losses.

Sl. % of the Average Flow Gross Net Head Power


No. time Discharge in Available Head (m) Potential
equaled Cumecs for power (m)
or exceed Generation
1 2 3 4 5 6 7
1. 8.33 0.213 0.191 18.00 16.00 16.78
2. 16.67 0.211 0.189 18.00 16.00 16.61
3. 25.00 0.207 0.186 18.00 16.00 16.35
4. 33.33 0.184 0.165 18.00 16.00 14.50
5. 41.67 0.181 0.162 18.00 16.00 14.24
6. 50.00 0.150 0.135 18.00 16.00 11.87
7. 58.33 0.138 0.124 18.00 16.00 10.89
8. 66.67 0.135 0.121 18.00 16.00 10.63
9. 75.00 0.133 0.119 18.00 16.00 10.46
10. 83.33 0.126 0.113 18.00 16.00 9.94
11. 91.67 0.121 0.108 18.00 16.00 9.50
12. 100.00 0.116 0.104 18.00 16.00 9.20
Note: kW = 9.81 x discharge x head x η g × ηT
ηg = Efficiency of generator = 0.8
ηT = Efficiency of cross flow turbine = 0.7

4.5 DETAILS OF VILLAGES COVERED BY THIS SCHEME

Name of village = Tally Valley


Distance from Power House = 1.50 km
No. of house hold = 16 Nos.
Population = 29 Nos.

4.6 INSTALLED CAPACITY AND NO. OF UNITS

It is evident from the power potential calculations that power potential at 75%
dependability is 10.46 kW. As per load forecast, 1 Unit of 10 kW is proposed.

4.7 ENERGY GENERATION

90% Plant Load Factor = 0.79 Lacs Unit


60% Plant Load Factor = 0.53 Lacs Unit

AHEC/MNES/C-347/AAS/Model DPR/MHP 12
CHAPTER - 5
CIVIL WORKS

5.1 GENERAL

Simple and cost effective type of civil works has been planned for the scheme. The
location of the scheme is shown in Drg. No. C-343-1. General layout of works of the
scheme is shown in Drg. 343-2. The L-Section of water conductor system is shown in
Drg. No. C -343-3.

5.2 DIVERSION WEIR AND INTAKE

A diversion structure is required across the nallah for diverting its water for power
generation. The nallah bed consists of pebbles, gravels and boulders. The site is also
remotely located. Keeping in view the availability of boulders etc. in abundance
locally, the Bush & Boulder type weir is proposed to be provided to divert the water
from nallah to intake channel. Such weirs are also suited for mountainous streams as
they do not much interfere with the regime of the stream. It is proposed that the weir
shall be constructed in full width of stream to avoid any restriction to flow that could
cause an afflux. The design features of weir are as follows.

i. A Bush & boulder type weir (with height from river bed as 800 mm & apron length
4000 mm) is provided across the stream for a width of 5.00 m. The top level of the
weir is kept at EL 1883.92 m. This shall ensure that the stream regime is not changed.
This will be a overflow weir.
ii. The intake structure shall be provided on right side of the stream. This shall ensure
passage of water (0.140 cumecs) to the intake channel (200m long).
iii. The weir has been designed for a design flood of 3.95 m3/sec with constant c = 1.7,
length of weir = 5.0 m and head over crest 0.60 m.
iv. A vertical trash rack consisting of 12 mm x 50 mm mild steel flats at 30 mm clear
spacing in full depth of intake channel is provided so that the entry of stones,
boulders etc. into the weir is checked. The clogging of the trash rack is not envisaged
for more than 50-60 percent.

AHEC/MNES/C-347/AAS/Model DPR/MHP 13
5.3 FEEDER CUM POWER CHANNEL

The water fed from diversion weir is lead to desilting tank through a rectangular
stone masonry channel (bed width 0.60 m x depth 0.30 mm) with free board of 0.15
m. The channel will be lined by 13 mm thick plastering of cement mortar.

The channel is designed on the following criteria:

i. To keep incoming upto 25 mm sediment moving in the supply channel upto desilting
tank, (at RD 200 m) the slope of channel is provided as 1 in 400.
ii. Design discharge of the intake channel is 0.140 m3/s.

5.4 DESILTING CUM FOREBAY TANK

As per site condition & requirement desilting tank and forebay is constructed
combinally here desilting tank and forebay detail is given separately.

Desilting tank Patu Nallah carries not much appreciable quantities of coarse silt
during rainy season. However for precaution and safe operation a desilting chamber is
considered necessary to minimize the abrasion effect on the turbine runners.
Consequently a desilting chamber has been proposed in order to remove sediment
particles above 0.25 mm size. The design has been made according to CBIP
publication No. 175, entitled “Small Hydro Stations - Standardisation”. The design
was also checked through computer programme. Wherever required the tank may be
covered by a slab on which proper earth cover be provided to provide insulating layer
for avoiding any chances of water freezing etc. The design features of desilting tank
are as follows.

i. The discharge outgoing from desilting tank for power generation is 0.119 cumec. To
provide for continuous flushing of silt during monsoon periods, a provision of 15%
of design discharge has been provided.
ii. Particles coarser than 0.25 mm size have been proposed to be trapped in the tank,
keeping in view the turbine type proposed.
iii. The flow velocity has been taken 0.22 m/s. The size of tank is fixed as 4.0 m x 1.8m
x 0.40 m (depth).
iv. A longitudinal slope of 1:4.45 is provided in the bed of the tank accompanied with
suitable transverse slope for smooth travel of settled sediment towards depressions.

AHEC/MNES/C-347/AAS/Model DPR/MHP 14
v. Suitable channel transitions of 1.8 m length in upstream are provided.
vi. One valve has been provided at outlet for silt flushing from the desilting tank. The
silt-ridden water is discharged back into the nallah.
vii. Suitable protection works are proposed at the junction of channel to the river for
disposing the silt ridden water.
viii. Free board in desilting tank is 0.30 m is provided.
5.5 FOREBAY
The forebay, penstock and powerhouse are treated as an integrated unit so far as their
location is concerned. The desilting forebay has been located on a rather flat area
followed by the penstock provided along moderately sloping hill side leading to the
power house on a flat terrace. The geology and terrain is favourable. The layout will
not involve any significant excavation for the forebay. The forebay is provided to
ensure supply of immediate water demand on starting the generating units. The
design features of forebay tank are as follows.

i. Storage time has been kept 2 minutes as per guide lines issued by Central Electricity
Authority-1982. Thus a storage capacity of 15.03 m3 (12.15+2.88 the capacity of
desilting tank) has been provided for a design discharge of 0.119 m3/s. Accordingly,
the size of tank is kept as 4.5 m x 1.80 m x 1.50 m. Suitable provisions are made for
free board allowance of 0.30 m, silt storage allowance of 0.20 m and allowance for
water head of 0.10 m required above spillway for passing the discharge.
ii. A minimum water cover of 1660 mm is provided over the crown of penstock intake
from the full supply level in the forebay tank to prevent any possible air entry into the
penstock.
iii. A locally depressed pocket of 1.80 m x 1.80 m x 2.28 m (depth) is provided at the
penstock intake in the forebay to reduce the structure height/its cost.
iv. A storage of 0.20 m (depth) is provided below the penstock invert for possible silt
deposition which would be removed manually once a while, through a silt flushing
pipe.
v. A mild slope for the silt movement is provided in the floor towards the silt flushing outlet.
vi. The penstock intake is provided with bell mouthing to have smooth entry of water to
reduce the entry losses.
vii. A mild steel trash rack with racks at 30 mm clear spacing is provided at penstock
intake to check the entry of trash into penstock.

AHEC/MNES/C-347/AAS/Model DPR/MHP 15
5.6 PENSTOCK

Water from forebay is being taken to the powerhouse to run hydraulic turbine through
pressurized penstock pipe running from forebay tank. The penstock pipe of mild steel
is proposed to be erected as penstock made of other material such as R.C.C., are not
economical for such sizes & site conditions in comparison to steel pipes. Various
criterion adopted for penstock design are as follows

i. A steel penstock of 0.292 mm outer dia is proposed from economical point of view.
The penstock thickness is kept as 6.0 mm.
ii. The optimum diameter is determined by minimizing the sum of annual loss of
generation due to friction and annual working cost including interest on capital loan,
depreciation, O&M charges. This diameter will develop maximum velocity in the
penstock.
iii. The design head for the penstock pipe is about 18 m plus 50% for water hammer
pressure.
iv. The penstock is proposed to be partially buried in the ground for about 1.0 m with
earth / muck cover over it.
v. The penstock intake is provided with bell mouthing to have smooth entry of water.
vi. A gate valve of 280 NB is proposed near the penstock intake to control the flow in
penstock.
vii. A trash rack before the bell mouthing is provided for preventing entry of trash in the
penstock.
viii. An air vent tube of 50 mm dia is provided just downstream of penstock intake to
release the air if entered into penstock.
5.7 SPILLWAY AND SPILLWAY CHANNEL
To allow the water to escape from forebay tank in case of emergency shut down of
the machines, spillway is provided in the upstream of forebay tank to divert the water
into the nallah through a channel. The area has exposed rocks and energy dissipation
would be easily done. The design details of spillway are as follows.
i. The spillway is designed for the flow of 0.119 cumecs discharge i.e. discharge
coming from the power channel.

ii. The length of spillway is kept as 2.0 m. The depth of water (head over spill way crest)
required to pass the discharge is determined as 0.10 m.

AHEC/MNES/C-347/AAS/Model DPR/MHP 16
iii The spill channel will be in a slope of 1:200 (or as per terrain available) the total
length of channel has been taken 150 m and the size of channel shall be 0.55 m x 0.25
m with a free board of 0.150 m.

5.8 POWER HOUSE BUILDING

Powerhouse building is a simple structure housing the generating units, auxiliary


equipment, control panels and suitable outlet for tail water discharge. The main
features of the powerhouse building are as follows.

i. The building of size 6.0 m x 6.0 x 4.0 m in plan is provided to accommodate 1 No.
turbine of 10 kW control panels, auxiliary equipments etc. (with out office & toilet)
ii. The height of the building is kept 4.00 m including the provision of crane to facilitate
handling of equipment during erection and maintenance. The power house building
may be partly below the ground level in order to provide proper insulation from
ground.
iii. Walls of the building are made of stone masonry with R.C.C. columns running in
between the walls as shown in the drawing.
iv. A H.O.T. Crane of 5 ton capacity is provided to facilitate the handling of equipment
over rails supported on R.C.C. columns.
v. Stop logs are provided at the tail race channel outside power house building.
vi. A trench of 0.3 m x 0.3 m with slope I in 100 for drainage may be provided around
the power house building discharging into tail race channel.
vii. Machine foundation has been provided as block foundation of reinforced cement
concrete of M 20 for these reciprocating machines.
viii. The floor of power house building is provided at an elevation of 1864.774 m which is
well above the highest flood level of Pongte River.
ix. Thermocol false ceiling in roof and wooden floor shall be provided in order to
provide thermal insulation to the power house building.
x. All the windows and ventilators be provided on southern side in order to arrest
maximum sun rays.

AHEC/MNES/C-347/AAS/Model DPR/MHP 17
5.9 TAIL RACE CHANNEL

Turbine discharge shall be disposed off to river through the tail race channel. The
width of channel is 0.50 meter with a depth of water as 0.25 m with a free board of
0.15m. The length of tailrace channel is approximately 25 meter and channel is
provided with the slope suitable to the terrain. The channel is proposed to be
constructed in stone masonry. At the end of channel, where it joins with river
protection works have been provided consisting of boulders in crates.

5.10 APPROACH ROAD

A suitable approach road (2 km) is envisaged to reach powerhouse area and for
transportation of equipment to the powerhouse.

AHEC/MNES/C-347/AAS/Model DPR/MHP 18
CHAPTER –6
ELECTRO MECHANICAL WORKS
6.1 GENERAL

Based on the Techno-Economic studies and choice of the scheme, selection of


electromechanical equipment, has been worked out as discussed here.

6.2 TURBINE
6.2.1 Applicable Range for Various Types of Turbines
The various types of turbines available for the available head (16 m) and their
specified speeds are given in Table 6.1 below:
Table 6.1: parameters Applicable for Various Hydro Turbines

S. Type of Turbine Specific Speed Head Application


No. (m)
Min. Max.
1 2 3 4 5

1. Reaction (Axial flow) 340-1000

i. Vertical fixed blade Propeller 2 25


ii. Vertical adjustable blade propeller 16 40
(Kaplan)
iii. Tubular with adjustable blades and 2 25
adjustable gates (Horizontal
Kaplan)
iv. 2 25
Bulb (Horizontal Propeller)
2 25
Rim (Horizontal Propeller)

2. Reaction (Francis, Mixed Flow) 80-400


10
i. Francis horizontal, vertical 250
2
ii. Francis open flume 25

3. Impulse

i. Pelton wheel 12-30 100 500

ii. Turgo Impulse (inclined pelton) 20-70 40 200

iii. Cross flow 20-100 1 200

AHEC/MNES/C-347/AAS/Model DPR/MHP 19
6.2.2 Choice
i. Reaction (Axial Flow)
ii. Francis Turbine
n P
ns =
H5/4
10kW
Where P = Turbine out put in metric H.P. =
0.736 × 0.80
H = Net Head = 16 metres
n = Speed of turbine
ng = efficiency of generator = 0.80

10
n
0.80 × 0.736
ns =
(16)5 / 4
= n x 0.128
1553 2334
Trial Specific Speed = to
16 16
= 388.20 to 583.5
388.20 583.5
Trial Speed = to
0.128 0.128
= 3032.8 rpm 4558.59 rpm
The trial speed is very high, hence Francis turbine is not suitable. The choice therefore goes
to Turgo Impulse or Cross Flow Type turbine.

iii. Turgo Impulse Turbine


10kW
Discharge = = 0.0971 m3/s
9.81 × 16 × 0.80 × 0.82
Absolute velocity of water C1 = Kc 2 gH

= 0.98 2 × 9.81 × 16
= 17.36 m/s
4Q
Optimal Jet diameter, d =
π C1

4 × 0.0971
=
π × 17.36
= 0.084 m
= 84 mm

AHEC/MNES/C-347/AAS/Model DPR/MHP 20
Optimal peripheral velocity µ 1 = Kµ 2 gH

Where K µ is a coefficient = (K µ = 0.46, 0.46 ------0.49)

µ1 = 0.49 2 × 9.81 × 16
= 8.68 m/s
60 × µ1 × T
Pitch Circle Diameter D =
π ng

T = Transmission Ratio
Speed of Generator
=
Speed of Turbine

ng = Speed of Generator

60 × 8.68 × 1 165.74
D = =
π ng ng

ng = 1500 D = 110.49 mm

ng = 1000 D = 165.74 mm

ng = 750 D = 221.00 mm

ng = 600 D = 276.23 mm

Table 6.2: Parameters of turbine corresponding to jet diameter of 84 mm.


Sl. Speed (ng) Jet Diameter (d) Pitch Circle No of Buckets
No. (mm) Diameter (mm) πD
2d
1 2 3 4 5
1. 1500 84 110.49 2.066
2. 1000 84 165.74 3.099
3. 750 84 221.00 4.13
4. 600 84 276.23 5.16

Since the minimum number of buckets should be at least 16, the turbine should have even
number of jet i.e. 2, 4 and 6 jets (Maximum).

AHEC/MNES/C-347/AAS/Model DPR/MHP 21
4Q
Jet diameter, d =
π C1
4 × 0.0971
=
6 × π × 17.36
= 0.0344 m
= 34.4 mm
Considering Jet dia of 30 mm, various Parameters are worked out and placed in Table – 6.3
below:

Table – 6.3 : Parameters of turbine for Jet diameter of 30 mm.

Sl. Speed (ng) Jet Diameter (d) Pitch Circle Diameter No of Buckets
No. (mm) (mm) πD
2d
1 2 3 4 5
1. 1500 30 110.49 5.78
2. 1000 30 165.74 8.68
3. 750 30 221.00 11.56
4. 600 30 276.23 14.46

Again number of buckets available are less than 16, therefore, Turgo Impulse Turbine is not
suitable for this head and discharge.

iv. Cross Flow Turbine


Velocity of water before entering runner
V = 0.98 2 gH

= 0.98 2 × 9.81 × 16
= 17.36 m/s
Periferal velocity of wheel µ = 0.50 x V Cos α
α = Angle between V with the tangent to periphery = 160
= 0.50 x 17.36 cos 160
= 8.345 m/s
π Dn
Periferal Velocity µ =
60
Where, D = Diameter of runner
n = Speed in rpm
π Dn
= 8.345
60
60 × 8.345
D =
π ×n

AHEC/MNES/C-347/AAS/Model DPR/MHP 22
159.32
=
n
When Speed, n = 750 rpm
D = 212 mm

A simple formula for calculating diameter directly is also given below.

39.819 H
Diameter of runner (D) =
n
39.819 16
=
750
= 212 mm
Width of Rotor B0 is given by Equation
B0 D π φ 2 gh Sin α
0
Q =
3600
φ0 = Admission arc angle = 900-1200
H = Net head
10 kW
Q = Discharge =
9.81 × 16 × 0.80 × 0.70
= 0.113 m3/s
α = Angle between absolute velocity water before
entering runner with the tangent to the periphery
of runner
= 160
Adopting φ 0 = 1200
Q = 1.2787 b0 D H
0.113 = 1.2787 b0 0.212 16
B0 = 104 mm
= 110 mm (Adopt.)

a. Parameters of Cross Flow Turbine

Diameter of runner = 212 mm


Width of runner = 110 mm
Speed = 750 rpm
Specific speed = 96 rpm

The speed of turbines have been selected 750 rpm because a 750 rpm generator
coupled with turbine will have 8 poles resulting more uniform distribution of
magnetic flux and hence less distortion of sinusoidal wave form. Further the vibration,
wear and tear in bearings and other moving parts will be less in comparison to 1000

AHEC/MNES/C-347/AAS/Model DPR/MHP 23
rpm or 1500 rpm turbine-generator set. The speed of turbine-generator set have
therefore been selected as 750 rpm.

From the above discussion, it is apparent that Francis Turbine and Turgo Impluse
Turbine are not suitable to deliver 10kW at 16 meter head. Cross Flow Turbine is
suitable for this scheme. The design of cross flow turbine is very simple and is
manufactured in India by several manufacturer but its efficiency is very low. The
maintenance of cross flow turbine is less complex and cheap than for other type of
turbine. A less complex civil structure is required in cross flow turbine and saving in
cost may be realized. In view of above, cross flow turbine is preferred for this scheme.
The turbine shall be capable to supply 10% continuous over load. The salient features
of Cross Flow Turbine is discussed below.

A cross flow turbine may best be described as an impulse type turbine with partial air
admission. This type of turbine is offered by Ossgerger Turbine Fabrick Co of
Wessenburg, Germany and has the name “Ossberger Turbine.

Performance characteristics of this turbine are similar to an impulse turbine, and


consist of a flat efficiency curve over a wide range of flow and head conditions. The
wide range is accomplished by use of a guide vane at the entrance which directs the
flow to a limited portion of the runner depending on the flow. This operation is
similar to operation of multi-jet impulse turbine.

Peak efficiency of the Cross Flow turbine is less than that of other turbine types.

At the present time the largest size runner produced by cross flow is 4 feet in
diameter. This limits the unit capacity but multi-unit installation are often used.
Allowable heads range from 20 to 600 feet.

Cross flow turbines are equipped with a conical draft tube creating a pressure below
atmosphere in the turbine chamber. Therefore the difference between the turbine
centerline elevation and the tail water is not lost to an cross flow turbines as is the
case for an impulse turbine. Air is admitted into the chamber through an adjustable air
inlet valve used to control the pressure.

AHEC/MNES/C-347/AAS/Model DPR/MHP 24
Cross Flow turbines are free from cavitation, but are susceptible to wear when
excessive silt or sand particles are in the water. Runners are self-cleaning and, in
general, maintenance is less complex than of the other types of turbine.

Floor space requirements are more than for the other turbine types, but a less complex
structure is required and a savings in cost might be realized.

The turbine shall be capable to with stand runway speed continuously without any
detrimental effect.

The most suitable type of turbine and layout, to the site, however shall depend upon
the actual tendering of the equipment. The selection for the turbine is recommended
on the basis of cost of turbine and associated civil structure and over all efficient and
operating range.

6.2.3 Conclusion

In view of foregoing, 1 Unit of Cross Flow Turbine of 10 kW capacity with


synchronous generator, electrical control protection and metering equipment is
recommended for this project.

6.3 SYNCHRONOUS GENERATOR

Horizontal synchronous generator of 10 kW at 415 V, 0.80 PF, 3 Phase A.C., 50 Hz,


750 rpm, natural air-cooled self ventilated with brush less excitation will be used. The
generator shall be capable of delivering 10% continuous over load. The generator
shall be star connected complete with stator, rotor, bearings, stator temperature
detector, oil coolers for bearings, brush less excitation system comprising high
frequency generator, diode wheel, AVR and protection equipment.

The generator shall be designed to with stand the runway speed of the turbine
continuously without any detrimental effect. The generator shall be able to operate in
parallel with other generator and with grid also. The generator stator and rotor shall
have class F insulation and designed for continuous operation at 10% over load with
screen-protected enclosure. The generators are designed to conform to IS
4722/2001/IEC-34/BS 4999.

AHEC/MNES/C-347/AAS/Model DPR/MHP 25
The six terminals from three main windings shall be brought out to the terminal box.
The generator neutral shall be directly connected to earth through earthing link. The
generator shall be capable to operate with either leading or lagging power factor by
control of excitation. The power factor commonly ranges between 0.85 and 0.95.
The synchronous generator will be capable to establish its own operating voltage and
maintain frequency while operated isolated. Thus if interconnection to the power
system is severed, the generator may continue supplying the station and local load.

6.4 GOVERNOR

Each Turbine shall be equipped with suitable non-flow control digital shunt load
governor (electronic load controller), which switches/adjust load so as to match
available generation.

Digital shunt load governor shall be digitally controlled (Miniprocessor based


controlled) electronic governor for following control.

i. Speed Control
ii. Unit Control
iii. Suitability for Isolated Operation
iv. Suitability for Parallel operation
v. Suitability for Grid Operation

The governor controls the out put load only. Standard controllable load (like Water
Heater) shall be provided along with governing system. The load on the machine will
be maintained constant using these loads in such a way, so that user gets stable
voltage and frequency. The governor shall be of proven design, capable of
maintaining control of speed under all conditions of head, discharge and load.
Parallel operation with grid is achieved by dead band in ELC operation between 48.5
Hz & 51.5 Hz frequency. Time delayed over speed protection is provided for inlet
valve closing.

6.5 MAIN INLET VALVE

The main inlet valve of the turbine shall be butterfly/other type for connecting to
penstock. The valve shall be suitable for slow opening and closing so as to avoid
water hammer pressure rise/drop in the penstock and control of unit by electronic load

AHEC/MNES/C-347/AAS/Model DPR/MHP 26
controller. The valve shall be manually/geared motor opened and closed if required by
counter weight, so that it is capable of being closed under all emergencies. The valve
shall close automatically under normal and emergency shut down conditions. The
valve shall be complete with inlet pipe, outlet pipe with dismantling joint, by pass
arrangement if required for equalization of pressure on either side of the valve etc.

The valve shall meet all requirements specified in IS 7326-1902. The main inlet
valve for each unit shall be suitable for penstock outer diameter.

6.6 ELECTRICAL CONTROL, PROTECTION AND METERING SYSTEM


6.6.1 Control System

Manual control system is recommended for use here.

6.2.2 Protection System

i. Over Current Protection


Moulded case circuit breaker equipped with static trip release which provides
protection against over load, short circuit, over voltage and under voltage with
adjustable plug setting will be used. The MCCB will have shunt release for
interlocking and remote tripping and confer to the latest edition of IS – 2516 –
1977 and IEC – 157 –1-1973. The rating of MCCB will be as below:
a. Thermal Rating - 25 Amps
b. Voltage - 415 V 3 Phase, 4 wire
c. Continuous current setting - 90% of Thermal Rating
d. Breaking capacity - 10 kA at 415 V 0.25 PF
e. Short circuit trip setting - 8 times of thermal rating
adjustable from 50% to 100% by
appropriate setting plug
f. Auxiliary Contact - Change over contacts for MCCB
‘ON, ‘OFF’ and Trip
The MCCB shall be placed as closed to generator terminal as possible.

ii. Earth Fault Protection - An earth leakage circuit breaker


(ELCB) also known as Residual
current device of 30 mA 415 V
rating will be provided as closed to
the generator terminals as possible.
AHEC/MNES/C-347/AAS/Model DPR/MHP 27
The over current and earth fault protection can be placed in the same box but
mounting should not be on the generator body so as to avoid vibration damage.

iii. Over Voltage, Under Voltage, Over Frequency and Under Frequency
Protection

These shall be provided to protect consumer load from un-acceptable voltages


and frequency.

Over Voltage - 250 V Trip


Under Voltage - 200 V Trip
Over Frequency - 51.5 Hz
Under Frequency - 48.5 Hz
iv. Over Speed Electrical/Mechanical (12)
v. Lightning Protection
a. Lightning Protection for Power House Building
b. Lightning Protection on Transmission Line
• One arrestor on each phase on the first pole outside the power house.
• One arrestor on each phase per km of Transmission Line.
• One additional arrestor on each phase if a consumer is more than 500
away from the arrestor.
vi. Following Mechanical Protections is recommended for providing on
Generator

1. RTD (PT – 100) in stator core and in bearing for indication, alarm, recording and
shutdown of the unit, for stator and bearing temperature control.
2. Governor oil pressure low.
3. Over speed for normal and emergency shutdown.

6.6.3 Metering System

The power generated shall be metered at generator terminal through metering CT and
PT. Following metering instruments shall be provided on relevant panels.

i. kW Meter
ii. kWh Meter
iii. kV Meter
iv. Ampere Meter

AHEC/MNES/C-347/AAS/Model DPR/MHP 28
v. PF Meter
vi. Frequency/Speed Meter
vii. Temperature Meter (only on generator panel)

6.6.4 CT for Generator (3 Nos.)


25/5 class ‘0.5’, 15 VA, 1.1 kV for metering

6.6.5 PT for Generator (3 Nos.)

415 V 110 V
/ class ‘0.5’, 15 VA 1.1 kV for metering and protection.
3 3

6.6.6 Generator Breaker (1 No.)

1.1 kV 25 Amps, 10 kA for one second, Moulded case circuit breaker with static trip
release which provides protection against over load, shor circuit, over voltage and under
voltage with adjustable plug setting confer to IS –2516 – 1977 and IEC –157 –1 – 1973.

6.6.7 Isolating Transformer (1 No.)

15 kVA, 415V/415 kV, Yn d 11, 50 Hz, three phase, oil immersed, off load tap
changer on H V side (+ 2.5% to 7.5 % in step of 2.5%), ONAN cooling suitable for
out door mounting.
6.6.8 Consumer Isolation Switch

415 V 32 Amps, 10 kA short circuit withstand current for one second, utilization
category AC – 22A, Confer to IS 13947 (Part –3) 1993 will be used.

6.7 STATION AUXILIARIES


6.7.1 Mechanical Auxiliaries
i. Cooling Water System
ii. Fire Fighting System
iii. Ventilation system
6.7.2 Electrical Auxiliaries

i. 24 V Batteries /Charger/DB.
ii. Switchyard
iii. Earthing System
iv. Power and Control Cables
v. Station service board
vi. Lighting System
vii. Chain pulley block/Turfer
AHEC/MNES/C-347/AAS/Model DPR/MHP 29
6.7.3 Cooling Water System

Suitable provision for providing cooling water for the bearings of turbine shall be
made. The water should be free from silt and other suspended particles. If quality of
water is not proper, a separate water storage tank may be provided. The tank be filled
with forebay water through motor pump. A suitable control system is to be developed
so that motor is operated on predetermined water level for filling the tank. Suitable
strainers may also be provided for removing suspended particles. Alternatively,
desilting arrangement may be provided in this tank.

6.7.4 Fire Protection System

Portable fire extinguishers are used for protection against fire in Micro Hydro Power
Station. The portable fire extinguishers are of following types.

i. Soda Acid Type


ii. Foam Type
iii. Dry Powder Type
iv. Carbon Tetrachloride (CTC) Type
v. Carbon Dioxide Type

Soda Acid Type extinguishers is suitable only for Class ‘A’ fire i.e. fire in ordinary
combustible material such as wood, paper etc. It is used in office areas.

Foam Type is suitable for oil fires (Class ‘B’ Fires). Soda Acid and foam type are not
suitable for electrical fire.

Dry powder type, CTC and CO2 type extinguishers are suitable for class ‘A’ and ‘B’
as well as class ‘C’ (Electrical Apparatus) fire and should be provided in adequate
quantities in areas housing electrical apparatus.

Portable CO2 fire extinguishers will be put up for general use. Portable foam type for
oil fire. Dry powder type will also be provided for electrical equipment. The fire
extinguishers of appropriate capacity will be provided. This system of fire protection
is proposed since the power station is small. Elaborate CO2 protection has not been
considered necessary as these generators being of open ventilation and the ventilating
air being drawn from both the ends of the generators and is discharged at the top of

AHEC/MNES/C-347/AAS/Model DPR/MHP 30
the machine. Two Nos. portable CO2, two Nos. portable foam type, 2 Nos. dry power
type each of 9/10 kg capacity will be sufficient for the power house. One set of six
buckets filled with clean dry sand and water will also be kept in erection bay.

6.7.5 Ventilation System

Natural ventilation system will be used for this powerhouse. Natural ventilation
means ventilation by providing adequate size of windows and ventilators. The object
of providing windows and ventilators is two fold i.e. to get fresh air and light. The
area of windows and ventilators to be provided in powerhouse shall be one-fifth of the
floor area. Efforts should be made to develop cross ventilation. The air intake should
be at least 1.25 m above ground or deck level to reduce dust intake. The ventilators
should be fixed as high as possible for proper expulsion of warm air.

6.7.6 Station Battery, Charger and DC Distribution Board

24 Volt 45 AH, nickel cadmium batteries high discharge type complete with stands,
insulator, inter cell connector with float and boost charger and D.C. distribution board
shall be required for control and protection system, D.C. emergency lighting of power
house and tripping and closing coils of MCCB, field circuit breaker of generator etc.
The charger will be automatic voltage regulated, static type full wave complete with
filters, rectifier, AVR, Voltmeter, moulded case circuit breaker, miniature circuit
breaker, fuses etc. The battery shall be open type single cell construction. The
capacity will however be designed taking into consideration of various load of
powerhouse.
6.7.7 415 Volt Station Service Board (1 No.)

The 415 Volts station service board is required for distribution of power at 415/240
Volts, 3 Phase, 4 wire 50 c/s to various auxiliaries of generating unit and station
auxiliaries of powerhouse. The source of power supply to station service board is
from 15 kVA 415V/415V Isolating transformer. MCB used in station service board
will be rated for 10 kA short-circuit with stand capacity for one second.

6.7.8 Lighting System

The complete powerhouse, appurtenant works and switchyard shall be adequately


illuminated as per relevant norms. The system shall include lighting fixtures,
AHEC/MNES/C-347/AAS/Model DPR/MHP 31
distribution boards, lighting board, junction boxes, switchboard, cable wire conduits,
poles etc. Following illumination levels are to be observed.
Machine Hall 200 Lux
Control pANEL 300 Lux
Switchyard AND outside area 50 Lux
6.7.9 Chain Pulley block (Tripod) (1 No.)

For erection and subsequent maintenance of the turbine/ generating units as well as
for handling other equipment, Chain Pulley Block of one Tonnes capacity shall be
required. This will handle all the equipment inside and outside powerhouse machine
hall. The cost has been included with the cost of main plant.

6.8 EARTHING

Suitable provision has been made for Earthing all the electrical equipment,
powerhouse and switchyard etc. as per I.E rules. A proper Earthing network will be
designed to provide full protection to equipment and working persons against step
potential and touch potential due to short-circuiting and other faults. The resistance of
Earthing network shall be less than 1 Ohm for the switchyard and for the powerhouse.

6.9 POWER AND CONTROL CABLES

i. 1.1 kV x 10 Sq. mm single core Alluminium conductor HRPVC insulated


armoured FRLS cable to connect generator terminals to 15kVA 415 V/415V
Isolating transformer.
ii. 1.1 kV x 16 sq. mm four core aluminum conductor HRPVC insulated
armoured FRLS cable to connect Isolating transformer to the MCCB.
iii. 1.1 kV 16 sq mm 4 cores aluminum conductor HR PVC insulated armoured
FRLS cable to connect switch fuse unit to LT Line.
iv. Multi core 2.5/4.0 mm aluminum conductor PVC insulated FRLS armoured
control cable will be used for CT, control and protection circuit.

6.10 POWER EVACUATION


The power generated shall be delivered at 415 V to Tally Valley (Patu) village
through 415 V lines. The 415 V line will be constructed on steel tubular pole (410 –
SP – 21) by AAAC 7/3.15 mm conductor (revised Rabbit equivalent). A provisions of
1.0 km 415 V line have been made in the project report.

AHEC/MNES/C-347/AAS/Model DPR/MHP 32
CHAPTER -7
COST ESTIMATES
7.1 GENERAL

Cost of the scheme is worked out in sufficient details so as to arrive at realistic cost
estimate. The estimates for Civil Works have been prepared in Annexure-III. The basis of
working out cost as below:

i. Rates for various components of civil structures have been adopted as given in the
schedule of current rates published by Department of Power Govt. of Arunachal
Pradesh and price obtained from manufactures for the items which are not
included in the schedule.
ii. Provisions made for
a. Establishment charges at the rate of 2% of the cost of works.
b. Audit and accounts charges at the rate of 1% of the cost of works.
c. Losses on stock at the rate of 0.25% of the cost of works.
iii. Cost of electromechanical units including generators, control panels etc. is based
on budgetary price quoted by several manufacturers in the country. Cost of other
equipment such as switchyard equipment, chain pulley block, ventilation system
equipment etc. are based on local inquiry from equipment manufactures.
iv. Duties, taxes, freight and insurance charges have been included in the cost of
electro-mechanical equipment. The estimates include inspection, erection and
commissioning charges, losses on stock and maintenance during construction.

7.2 ABSTRACT OF COST


Abstract of item wise cost of civil and electromechanical work is available in Table - 7.1.
The estimated total cost of the project is Rs. 49.50 lacs with transmission line. The cost of
installation works out to be Rs. 4.95 Lacs per kW.

AHEC/MNES/C-347/AAS/Model DPR/MHP 33
Table - 7.1 : COST ESTIMATE

Sl. NO. ITEM COST


(Rs. Lacs)
1 2 3
I A Preliminary 0.15
B Land 0.20
C Civil Works (as per Table - 7.2) 36.05
J Power Plant (as perTable -7.3) 6.95
K Buildings 0.00
M Plantation 0.10
O Miscellaneous 0.50
P Maintenance (1% of I works less A, B & Q) 0.44
Q Special T & P 0.15
R Communication including access to site 0.25
Y Losses on stock (0.25% of I-Work) 0.11
Total -Work 44.90
II Establishment (2% of I works excluding Buildings) 0.90
III Oridinary T & P (1% of I – Works) 0.45
IV Suspense Nil
V Receipts and recoveries (-) 0.20
VI Indirect Charges (1% of I – Works for Audits Accounts) 0.45
VII Transmission and Distribution (as per Table - 7.7) 3.00

Total Project Cost 49.50

AHEC/MNES/C-347/AAS/Model DPR/MHP 34
Table - 7.2 : ABSTRACT OF COST OF CIVIL WORKS

Sl. NO. ITEM COST


(Rs. Lacs)
1 2 3
1 Diversion Weir & Intake 4.39

2 Fedder Cum Head Race Channel 5.63

3 Desilting Cum Forebay Tank 8.39

4 Penstock, Anchor and Saddle Block 9.25

5 Power House and Tailrace Channel 8.39


Total 36.05

AHEC/MNES/C-347/AAS/Model DPR/MHP 35
TABLE - 7.3 ELECTRICAL & MECHANICAL WORKS

Sl. No. ITEM QUANTITY AMOUNT


(Rs Lacs)
1 2 3 4

1 GENERATING PLANT AND EQUIPMENT


1.1 Cross flow Turbine to deliver 10 kW at Generator terminals with shaft, runner, casing, 1 Nos. 0.85
bearings, oil pressure units etc. and all other auxiliaries with 10% continuous over
rating
1.2 Synchronous Generator 10 kW, 0.415 kV, 3 Phase, 0.85 Pf, 50 Hz+ 3%, 750 rpm, 1 Nos. 0.50
class 'F' insulation, terminal equipment like neutral grounding system, CTs, PTs,
LA/SC and other auxiliary system with 10% continuous over rating
1.3 PLC based Generator/Turbine control panels including Protection, metering systems 1 Set 1.00
all indicating instruments and switches etc .
1.4 Electronic load Controller including electronic panels complete in all respect and 1Set. 1.00
suitable for above system with ballast load
1.5 Main inlet valves suitable for fixing on penstocks for emergency closing 1 Nos. 1.00
1.6 Spares for 5 years operation 1 Set 0.25
Sub Total 4.60
2 STATION AUXILIARIES
2.1 Mechanical Auxiliaries
2.1.1 1 Tonne chain pulley block 1 No. 0.10
2.1.2 Fire Protection system 1 Set 0.15
2.2 Electrical Auxiliaries
2.2.1 Power and Control PVC cables 0.10
2.2.2 Lighting in the power house and appurtent works 0.20
2.2.3 24 Volts 45 AH D.C. battery, charger and Distribution Board. 0.15
2.2.4 L.T. Distribution Board including busbar & MCCBs of adequate capacity. 0.10
2.2.5 Earthing of power house equipment including earthmat. 0.10
2.2.6 25 A 10 KA 1.1 KV Generator breaker ( MCCB) 1 Nos. 0.10
2.2.7 Earth leakage circuit breaker 30mA 415V 1 No. 0.03

Sub Total 1.03


3 Switch Yard
3.1 Step up Transformer 15 kVA, 0.415/.415 kV ONAN cooling complete with all 1 No. 0.15
accessories, oil, spares for 5 years
3.2 32A and 16A,415V Switch Fuse Unit 1 Sets 0.01
Sub Total 0.16
Total 5.79
4 Freight, insurance and octroi of (1) to (3) charges @ 10% (Material is to be transported 0.58
on head load for a distance of 8 Km)
5 Erection & commissioning of (1) to (3) @ 10% 0.58
Total E&M Works 6.95

AHEC/MNES/C-347/AAS/Model DPR/MHP 36
Table - 7.4 : O-MISCELLANEOUS

Sl. No. ITEM AMOUNT


(Rs. lacs)

1 Photography and Publication 0.05


2 Medical aid and health sanitation 0.05
3 Printing technical material 0.05
4 Foundation stone laying ceremonies and Project 0.15
Inauguration
5 Entertaining guests & invitees 0.10
6 Miscellaneous 0.10

Total 0.50

Table - 7.5: SPECIAL T & P (Q)


Sl. Item of work Qty Rate (Rs.) Amount
No. (Rs. lacs)
1 2 3 4 5
1 Workshop Machine and Tools L.S L.S 0.15

Total 0.15

Table - 7.6: COMMUNICATION

Sl. Item of work Qty Rate Rs. Amount


No. (Rs. lacs)
1 2 3 4 5
Construcion of approach road to site L.S 0.25

Total 0.25

Table - 7.7 TRANSMISSION & DISTRIBUTION LINES

Sl. No ITEM QTY. RATE AMOUNT


( Rs. lacs ) (Rs lacs)

1 3 Phase L.T. Line on AAAC 7/3.15 mm 1 km 2.90 2.90


conductor and steel tubalar poles (410-SP-21) 8.5
m long.
2 Miscellaneous L.S. 0.10

Total 3.00

AHEC/MNES/C-347/AAS/Model DPR/MHP 37
CHAPTER -8

FINANCIAL AND ECONOMIC STUDIES

8.1 ESTIMATES OF COST AND PHASING

The total project cost is estimated as Rs. 49.50 lacs comprising of Rs. 36.05 lacs for
Civil Works, Rs. 6.95 lacs for Electro-Mechanical Works, Rs. 3.00 lacs Transmission
and Distribution and Rs. 3.50 lacs for other expenses. The installation cost worked out
to be Rs. 4,95,000.00 per kW.

The total fund required is Rs. 49.50.00 lacs without MNES subsidy.

8.2 GENERATION COST

i. Cost of generation per kWh of power depends on total annual generation and
annual working expenditure.
ii. The annual expenditure will consist of

a. Operation cost @ 1% of works cost


b. Maintenance cost - @ 1% of cost of civil works less cost
@ 2% of cost of electro-mechanical works
c. Depreciation charges- considering life of civil works and electro-
mechanical works as per standard norm given in the Gazette of India
Extraordinary Part-II, Section -3 Subsection ii Published by Ministry
of Power and Non-Conventional Energy Sources, Deptt. of Power
Govt. of India, vide notification No. 82, Jan 31, 1992 with assumption
10% as scrap value.
d. Interest @ 12% per annum on capital invested.

iii. The annual cost has been worked out and given in Table - 8.2.
iv. Annual units generated are computed as 0.079 MU at 90% load factor & 0.053
MU at 60% load factor. The generation cost per kWh has been worked out and
given in Table - 8.1 (a) Table - 8.1 (b).

AHEC/MNES/C-347/AAS/Model DPR/MHP 38
Table - 8.1(a): COST OF GENERATION (WITHOUT SUBSIDY)
Sl. No. ITEM AMOUNT
(Rs. Lacs)
1 2 3

1 Project Cost 49.50

2 Annual Interest during Construction 2.97

3 Total Project Cost 52.47

4 Annual working expenses as per Table - 8.2 2.35

5 Interest @ 12 % on total project cost 6.30

6 Total annual expenses 8.65

7 Annual generation at power house (Million Units)

(i) at 90% load factor 0.079

(ii) at 60% load factor 0.053

8 Cost of generation per kWh (in Rs.)

i. at 90 % load factor 10.97

ii. at 60% load factor 16.45

AHEC/MNES/C-347/AAS/Model DPR/MHP 39
Table - 8.1(b): COST OF GENERATION (WITHOUT SUBSIDY)

Sl. No. ITEM AMOUNT


(Rs. Lacs)
1 2 3

1 Project Cost 49.50

2 Capital Subsidy As per MNES 11.61

3 Balance Project Cost 37.89

4 Annual Interest during Construction 2.27

5 Total Project Cost 40.16

6 Interest @ 12 % on total project cost 4.82

7 Annual working expenses as per table 8.2 2.35

8 Total annual expenses 7.17

9 Annual generation at power house (Million Units)

(a) at 90% load factor 0.079

(b) at 60% load factor 0.053

10 Cost of generation per kWh (in Rs.)

(i) at 90 % load factor 9.10

(ii) at 60% load factor 13.64

AHEC/MNES/C-347/AAS/Model DPR/MHP 40
TABLE - 8.2: STATEMENT OF YEARLY WORKING EXPENSES

Sl. ITEM Cost


No. (Rs. Lacs)
1 2 3

1 Operation cost @ 1% of works cost 0.49


2 Maintenance cost of C-works @ 1% 0.36
3 Maintenance of E&M works @ 2% 0.14
4 Annual depreciation charges (as per Table 8.3) 1.36

Total 2.35

AHEC/MNES/C-347/AAS/Model DPR/MHP 41
TABLE - 8.3 : ANNUAL DEPRECIATION OF ASSETS

Sl. No. Item Life in Cost Rate of Depreciation


years Rs. Lacs Depreciation in % Rs. Lacs
1 2 3 4 5 6
1 Land Infinity 0.20 NIL NIL
2 Diversion Structure, Intake 50 18.41 1.95 0.36
channel,Desilting Chamber,
Forebay, tail race approach
road and other misc. works
3 Power house building, Penstock 35 17.64 3.40 0.60
pipe, valves etc
4 Turbines, generators, cables and 35 4.80 3.40 0.16
other E&M works
5 Transformers, switchgears, LT 25 3.39 5.06 0.17
distribution board ,
transmission line, Isolators
6 Fire Fighting Equipment, 15 0.15 8.24 0.01
Ventilation equipment
7 Batteries with charger 5 0.15 21.55 0.03
8 Lighting System including 15 0.20 8.24 0.02
wiring and fittings
9 Earthing of Power House and 50 0.10 1.95 0.002
Switch Yard
Total 1.36

AHEC/MNES/C-347/AAS/Model DPR/MHP 42
CHAPTER – 9
CONSTRUCTION PROGRAMME
9.1 PRE-CONSTRUCTION ACTIVITIES

Pre-construction activities, viz: preparation of bid-document, purchase of bid-


document by prospective bidders, study and submission of bid will take some time. It
will be followed by opening of bid, its finalization, and placement of order and
signing of contract. A period of 3 months is considered sufficient for these activities.

9.2 CONSTRUCTION ACTIVITIES/PERIOD

Construction activities have been shown in the Bar Chart (Fig. 9.1). The period for
various construction activities have been taken as below:
Days
9.2.1 Pre-Construction activities
i. Preparation of bid document 30
ii. Notice Inviting Bid and Receipt 60
iii. Bid finalization, Planning of order and singing of contract 30

9.2.2 Construction of Civil Works


i. Diversion Structure & Intake 120
ii. Feeder Cum Head Race Channel 90
iii. Desilting Cum forebay Tank 60
iv. Installation of Penstock 120
v. Power House and Tail Race Channel 120
9.2.3 Electro-Mechanical Works
i. Receipt of Electro-Mechanical Equipment at site 150
ii. Erection of Electro-Mechanical Equipment 120
iii. Erection of Control Panels & other Auxiliaries 60
iv. Installation of Station Auxiliaries 60
v. Construction of Distributing Line 30
vi. Testing and Commissioning 30
vii Trial Run 15
The construction of total civil works will be completed in 180 days and of Electro
Mechanical works will be completed in 150 days as shown in the bar chart. The
testing and commissioning will be completed in 60 days.

AHEC/MNES/C-347/AAS/Model DPR/MHP 43
Trial run period of 30 days has been considered to ensure safe and reliable operation
of the plant.

The place being remote, located deep in the forest and connected through kachcha
forest road which becomes problematic during monsoons and rainy days, some period
is likely to be lost causing delays. Some time margin has been considered for the
same. However, the contractor may finish the whole work in lesser period if possible.
The O & M will start after successful commissioning and operational trial of the plant
and the system.

9.3 CONSTRUCTION MATERIAL

The natural material like stones required for either stone masonry and for
manufacturing of aggregate and sand, screened gravel and grit are available in the
nearby area. However, their sources have to be finalized after carrying out necessary
test for their acceptance.

Planning and procurement of item like cement steel and timber has to be initiated well
in time.

9.4 MANUFACTURING ITEM

The manufactured or bought out items include:-

i. Fabricated structure like trash rack, gate, roof trusses, chain pulley block (if
required) and their fittings
ii. Generating equipment –turbine, governor generator, control panels, switchgear
and other auxiliary equipment.
iii. The other bought out items like pipes, valves, ventilation, equipment, fire
fighting equipments, lighting fitting/accessories and their building accessories.

AHEC/MNES/C-347/AAS/Model DPR/MHP 44
9.5 CONSTRUCTION OF CIVIL WORKS

9.5.1 In the civil construction of various structure, the following are the major items of
works:-

i. Excavation in soil
ii. Plain cement concrete
iii. Reinforcement cement concrete
iv. Stone masonry in cement sand mortar
v. Installation of penstock
vi. Foundation of hydro mechanical equipments and structural steel works

9.5.2 The Main Civil Works are listed below:

i. Diversion Weir and Feeder Channel


ii. Desilting Tank cum Forebay Tank
iii. Spillway
iv. Penstock Layout Anchor & Saddle Block etc.
v. Power House Building
vi. Tail Race Channel

9.6 CONTRACTUAL PERIOD OF O & M

The initial O & M is proposed to be carried out by the contractor for initial 5 years
and thereafter the plant will be run by the villagers.

AHEC/MNES/C-347/AAS/Model DPR/MHP 45
AHEC/MNRE/C-347/AAS/ Model DPR/MHP

Pre-
Construction Construction Period O&M Period
Sl. Period
ACTIVITIES
No. Months Months Years

1 2 3 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
I PRE-CONTRACT ACTIVITIES
1 Preparation of bid document
2 NIT & bid Receipt
3 Bid Finalization, placing order and signing of contract
IICONTRACTUAL ACTIVITIES
1 Contractor mobilization
2 Survey & investigation
3 Preparation of Drawings , Documents & Submission
4 Checking of Drawings & approval by Purchaser
5 Construction of Civil Works
5.1
Diversion Structure & Intake
5.2
Feeder cum Head Race Channel
46

5.3
Desilting cum Forebay Tank
5.4
Installation of Penstock
5.5
Construction of Power House & Tail Race Channel
6 Manufacture & supply of Equipment, Material F.O.R. Site
7 Construction of E&M works
7.1Receipt of E&M equipment at site
7.2Erection of E&M equipment
7.3Installation of Control, Protection & Metering System
7.4Installation of Station Auxiliaries
7.5Installation of Distribution line, House wiring & Meters
(Where necessary)
8 Testing & Commissioning
9 Trial Run
10 O & M of plants for 5 years
FIG. 9.1- BAR CHART : MICRO HYDRO BASED ELECTRIC POWER PROJECT : PATU (DISTT. LOWER SUBANSIRI, ARUNACHAL PRADESH)
CHAPTER –10

OPERATION AND MAINTENANCE OF PLANT & SYSTEM

10.1 GENERAL
After the plant and system is tested commissioned and the trial period is over, the
operation and maintenance for 5 years period will be the responsibility of the
contractor who has supplied, erected tested and commissioned the plant and the
system. The contractor may not use100% of his own staff and requires certain number
of additional persons for managing O&M under the guidance of his limited staff. The
Nodal Agency (APEDA) is proposed to from village energy committee (VEC) from
amongst the villagers to take care of the plant and the system and O&M of the plant.
The Village Energy Committee may arrange for the same from amongst the people of
the village, depending on the age, physical and mental health, willingness and the
educational qualifications.

10.2 FORMATION OF COMMITTEE FOR SUPERVISION OF O & M


i. Executive Committee

The VEC will make an Executive Committee of 5 persons, which will supervise
and monitor:
a. Day to day functioning of the plant & system
b. Monitor day to collection of revenue & Expenditure
ii. Staff

Following Staff is proposed to be appointed by VEC from amongst the villagers:


a. Manager : 1 No.
b. Operational Staff : 6 Nos.

iii. Record Keeping

Following record is suggested to be kept and maintained by the VEC.


a. Stock Register recording : Sl. No., Date, Quantity Received
b. Issue Register: Recording Sl. No., Date, Quantity issued and signatures of the
receiver
c. Cash receipt register

AHEC/MNES/C-347/AAS/Model DPR/MHP 47
d. Cash book
e. Ledger
f. Bank Pass Book & Cheque Book
g. General Stock & Issue Register
h. Register for Consumables

iv. Supervision & Maintenance of Record

a. The manager will keep maintain the record, write cash book & maintain the
account
b. VEC executive will check the accounts monthly
c. General Meeting of VEC will be held every quarter in which manager will
place before it the records, accounts and status of the plant.
d. An annual audit of accounts assets and liabilities will be got carried out by a
competent chartered Account appointed for the purpose by the Nodal Agency
Appropriate action will be taken by the Nodal Agency after careful
examination.

AHEC/MNES/C-347/AAS/Model DPR/MHP 48
CHAPTER – 11

ENVIRONMENTAL IMPACT AND BENEFITS

11.1 ENVIRONMENTAL IMPACTS

The Micro Hydro Power Plant will utilize the potential energy of the water of the stream
which is being lost at the present in friction etc. The civil & other construction work being
of very low order, there will hardly be any adverse impact on the nature. It will help to
conserve the other natural resources e.g. the forest and, therefore, will improve the
environment.

11.2 BENEFITS
i. With the provision of electricity in the village, the life of SC/ST and Backward
Community constituting the population of the village will be uplifted.
ii. Provision of electricity will provide opportunities to the villagers to have cottage
industries. This will enhance their economic status.
iii. School going children will have better studying conditions in the homes.
iv. With the provision of power in the area, the pressure on wood will reduce considerably.
v. With the betterment of lining conditions due to co-operation from the forest department,
the people will have a different attitude towards the forest resources, which will
ultimately result in saving the forest.

AHEC/MNES/C-347/AAS/Model DPR/MHP 49
LIST OF PERSONNEL INVOLVEMENT

I. AHEC, IIT, ROORKEE

1. Sri Arun Kumar, Head, AHEC


2. Sri M. K. Singhal, SSO, AHEC
3. Sri Ashutosh Agrawal, JRF, AHEC

II. CONSULTANTS

1. Dr. G.C.S. Gaur, Former Faculty Member UOR Roorkee


2. Sri Y. S. Jadaun, Former Chief Engineer (UPSEB)
3. Shri S. C. Jain, Former, General Manager and Chief Engineer, UPPCL
4. Shri R. D. Goel, Former Executive Engineer, U. P. Irrigation Department

III. ASSISTANTS

1. Sri R. K. Singhal, Technical Assistant


2. Sri Chandarpal Singh, Senior Attendant

AHEC/MNES/C-347/AAS/Model DPR/MHP 50
Annexure-I
Sheet 1 of 5

DESIGN CALCULATIONS OF MAJOR CIVIL WORKS

1.0 GENERAL

The Patu Micro Hydro Project comprises of the following Civil Works.

i. Diversion Weir
ii. Intake Channel cum Power Channel
iii. Forebay cum Desilting Tank
iv. Penstock
v. Power House
vi. Tail Race Channel

Levels of structures, rated head and discharge based on the preliminary survey
conducted by a joint team of AHEC and APEDA, the parameters have been fixed as
given below.

a. Bed Level of Patu Nalla at diversion site = 1883.120m


b. Bed Level of Intake channel at head = 1883.62 m
c. Approximate bed Slope of Stream = 1 in 20
d. F.S.L of Intake /Feeder Channel at Head = 1883.62 + 0.30
= 1883.92 m
e. F.S.L in Desilting Tank = 1883.92 -0.50
= 1883.42 m
(i) Length of Feeder cum Power Channel = 200 m
(ii) Slope of Feeder cum Power Channel = 1 in 400
f. F.S.L in Forebay = 1883.40 m
g. Centre line of penstock in P.H keeping
500 mm above floor level = 1865.40 m
h. Gross Head = F.S.L in Forebay - Centre line of penstock
= 1883.40 – 1865.40 m
= 18 m
i. Head loss in Penstock = 2.0 m
j. Neat Head = 18 – 2.0
= 16.0 m

AHEC/MNES/C-347/AAS/Model DPR/MHP A-1


Sheet 2 of 5

2.0 POWER POTENTIAL AVAILABLE

The discharge was measured by AHEC team on May 02, 2006 and found 376 litres
per second. This is the peak period discharge.
The power potential available kW = 9.81 x Q x H x η g x η t
= 9.81 x .376 x 16 x 0.80 x 0.70
= 33 kW
But as per site requirement only 10 kW is needed to be generated
10
So discharge required for 10 kW =
9.81 × 16 × 0.80 × 0.70
= 0.113 m3/s

3.0 FIXING OF DISCHARGING CAPACITY FOR VARIOUS CIVIL


STRUCTURES
(i) Design discharge for Penstock and tail race channel
= 0.113 cumecs
(ii) Design discharge of Feeder cum head race channel upto desilting cum forebay tank
(Add 15% discharge for silt flushing) = 0.113/0.15
= 0.12995 cumecs (Say 0.130 m3/s)
4.0 DIVERSION WEIR

Bush & boulder type weir shall be constructed.


Length of weir = 5.50m
River bed level = 1883.12 m
Height above bed level = 0.80 m

5.0 FEEDER CUM POWER CHANNEL

Length of channel = 200 m


Q = 0.130 m3/s
S = 1 in 400
n = 0.018
Bed Width = 0.60 m
Water depth = 0.30 m
Velocity = 0.768 m/s
Free Board = 0.15 m

AHEC/MNES/C-347/AAS/Model DPR/MHP A-2


Sheet 3 of 5

6.0 DESILTING CUM FOREBAY TANK

6.1 Design Calculation Of Desilting Tank


The recommend particle size to be removed upto 0.25 mm.

Design discharge = 0.130 m3/s


Flow Velocity (Vf) = 0.22 m/s
Particle size to be removed = 0.25 mm & above
Settling velocity (Vs) = 2.75 cm/sec
Width proposed (W) = 1.80 m
Q 0.130
Depth required h = =
W ×Vf 1.80 × 0.22

= 0.328 m
Depth provided = 0.400 m
0.132
Moderate settling velocity = Vs − × Vs
D
0.132
= 2.75 − × 2.75
0.40
= 2.75 – 0.574
= 2.176 cm/s
= 0.022 m/sec
Vf
Settling length = × Depth
Vs
0.22
= × 0.40
0.022
= 4.0 m
Length = 4.0 m
Depth = 0.40 m
Width = 1.80 m
⎛ 1.80 − 0.60 ⎞
Provide U/s transition length = 3x ⎜ ⎟
⎝ 2 ⎠
= 1.8 m

AHEC/MNES/C-347/AAS/Model DPR/MHP A-3


Sheet 4 of 5
6.2 Design Calculation of Forebay Tank

Design discharge = 0.113 m3/s


Storage required = 2 minute
Capacity of tank = 0.113 x 2 x 60
= 13.56 m3
Taking water depth = 1.50 m
Area required = 9.04 m2
Provide width = 1.80 m
13.56
Length =
1.50 × 1.80
= 5.02 m
Provide Length = 5.10 m
Free Board = 0.30 m
Total depth = 1.50 + 0.30 m
= 1.80 m
Depth at reparation (adding extra 0.70 m) = 2.50 m

6.3 Design Calculation of Spillway

Discharge Capacity Q = 0.113 m3/s


Q = CLH3/2
C = 2.0
Length of spillway assume = 2.0m
2/3
⎛ 0.113 ⎞
H = ⎜ ⎟
⎝ 2.0 × 2.0 ⎠
= 0.0911 m Say 0.10 m (Assured)
Provide free board = 300 mm above F.S.L.

Design of Spillway Pipe

Length of channel = 150 m


Q = 0.113 m3/s
Velocity = 2.50 m/s
Area required = 0.0452 m2
Dia of pipe = 0.239 m
Provided dia of pipe = 250 m2

AHEC/MNES/C-347/AAS/Model DPR/MHP A-4


Sheet 5 of 5
7.0 PENSTOCK

Design Discharge Q = 0.113 m3/s


Length of Penstock = 150 m
Considering Velocity of Penstock = 2.50 m/s
Area of pipe required = 0.0452 m
Dia of pipe = 0.240 m
Provide = 250 mm
Gross head = 18.0 m
2.70 × 24.0
Thickness (PD/2 σ ) =
2.0 × 1050
= 0.030 cm
1.80
Water pressure including hammer (P) = 1.80 + kg / cm 2
2.0
= 2.70 kg/cm2
Diameter of penstock (D) = 24.0 cm
Permissible stress in steel (σ ) = 1050 kg/cm2
Add 1.50 mm for corrosion allowance + = 3.30 mm
1.50 mm abrasion allowance
Assume thickness = 6.00 mm
Outer dia of penstock = 262 mm

8.0 POWER HOUSE BUILDING

The layout of the powerhouse building has been worked out on the basis of IS code
and size of powerhouse building shall accommodate control panel, erection or service
bay, operators space and other auxiliaries. The size has been fixed as 8.10 m x 4.10 m
x 3.20 m.

9.0 TAIL RACE CHANNEL

Each unit will have its own Tailrace. Tailrace channel is designed as rectangular section
to cater design discharge 0.113 m3/s. Rectangular section with bed slope as per the
terrain is proposed for tailrace channel. The tailrace channel length is about 15.0 m.

Bed Slope = 1 in 200


n = 0.018
Water Depth = 0.235 m
Bed Width = 0.50 m
Area = 0.1175 m2
Perimeter = 0.970 m
Hydraulic Radius = 0.12113 m
Velocity = 0.962 m/s
Q (Discharging capacity) = 0.113 m3/s
Free Board = 0.15 m

AHEC/MNES/C-347/AAS/Model DPR/MHP A-5


ANNEXURE -II
SCHEDULE OF RATES

Sl.No. Items Unit Rate in Rs.

1 Excavation
(I) In ordinary soil m3 101.00
(II) In soft rock and dense hard soil excluding Blasting 3 244.00
m
(III) In Hard Rock including blasting 3 407.00
m
2 Earth filling m3 46.00
3 Providing and laying PCC conforming to Grade M-10 including all materials, 3 4127.00
m
labour, T & P etc.
4 Plain cement concrete M15 (1:2:4) in foundation, flooring slabs m3 4807.00
5 25 mm thick damp proof course with PCC. (1:2:4) m3 198.00
6 Reinforced cement concrete M15 (1:2:4) excluding cost of reinforcement in 3 5257.00
m
foundation, slabs, anchor blocks etc.
7 Providing and laying RCC conforming to Grade M-20 including all materials, 3 6758.00
m
labour, T & P excluding steel reinforcement including formwork.
8 Stone masonry in cement mortar 1 : 6 including supply of all materials, labour, T&P 3 3344.00
m
etc. Complete.
9 Boulders in wire crates m3 1466.00
10 Steel reinforcement including supply, bending, binding and placing in position with M.T 37100.00
all labour T&P complete.
11 Pointing in 1:3 cement sand mortar on stone masonry m2 111.00
12 12 mm thick cement plaster
(a) 1:4 C.M. on stone masonry m2 133.00
(b) 1:6 C.M. on stone masonry 2 111.00
m
13 Providing distemper/colour wash in 3 coats including supply of all materials, 2 36.00
m
labour etc.
14 White washing in 2 coats m2 12.00
15 Supply and fixing of G.I. Sheets roofing complete with all materials, labour, T&P m 2 780.00
etc.
16 Supply and erection in position the mild steel Gate including fabrication, painting L.S. 50000.00
transport, erection etc. as per drawings and specifications complete.

17 Supply and erection in position the mild steel trash rack at intake including M.T 74200.00
fabrication, painting transport, erection etc. as per drawings and specifications
complete.
18 Penstock pipe including supplying, fabrication, transportation, and painting etc M.T 84800.00
complete.
19 Supply and laying of well graded filter including labour, T&P complete. 3 1657.00
m
20 Structural steel like channels, angles etc. including fabrication and erection. M.T 74200.00
21 Water proofing and guick setting compound Kg 276.00
22 Centering and shuttering including strutting propping and removal of prop Sqm 175.00
23 Supply, providing and fixing 5 mm thick glass with aluminium beading frame on L.S. 35000.00
shutters including Labour, T & P complete
24 Suppling and fixing 38mm thick shisham/teak/deodar wooden doors and windows Sqm 1358.00
including Labour, T & P complete as per drawing & direction of E/I.
25 Masonry with pre-cast cement concrete 1:3:6(1 cement: 3 coarse sand:6 graded m3 6784.00
stone aggregate 20 mm nominal size) blocks in cement mortar 1:4 in
foundations,plinth and superstructure

AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 1 of 6
DIVERSION WEIR AND INTAKE

S. NO. ITEM UNIT QTY. RATE (RS.) AMOUNT (RS.)

1 2 3 4 5 6
1 Earth work in excavation in foundation trenches in ordinary
soil and softrock and disposal of excavated earth as
obtalined to a distance upto 1 km inlcuding all leads and
lifts, travelling, ramming the foundation trenches, removing
roots of trees, shurbs all comptete as per approved design,
specification and direction of E/I.

(i) In soft rock and dense hard soil excluding blasting Cum 20.70 244 5051
(ii) In Hard Rock including Blasting Cum 31.00 407 12617
2 Earth work in filling in layers not exceeding 150 mm thick Cum 15.50 46 713
well watered, rammed, fully compacted and fine dresseed
with earth obtained after cutting within a lead of 1 km and
all lift compelte as per specification and direction of E/I.
(Mode of measurement compacted volume).

3 Providing P.C.C. M-15 with nominal mix of (1:2:4) with 4 Cum 11.60 4807.00 55761
cm down graded coarse aggregate, approved coarse sand
and cement including scaffolding, vibrating, providing
construction joints, finishing, curing , T&P etc. complete as
per direction of E/I.
4 Providing PCC. M-10 with nominal mix of 1:3:6 with 4 cm Cum 4.72 4127 19479
down graded coarse aggregate, approved coarse sand and
cement including vibrating finishing, curing, T&P etc. as per
E/I.
5 Providing R.C.C. M-20 with nominal mix of (1:1.5:3) with 2 m3 2.40 6758.00 16219
cm down graded coarse aggregate, approved coarse sand
and cement including scaffolding, vibrating, providing
construction joints, finishing, curring (but excluding the cost
of reinforcement) T&P etc. complete as per direction of E/I.
6 Supply and laying of well graded filter including labour, T&P 3 2.80 1657.00 4640
m
complete.

7 providing and placing boulders in wire crates dule packed at L.S. 50000.00 50000
the toe of wing wall with all lifts as per specifications and
direction of E/I.
8 supply of fixing gate at intake channel & under sluice gate in L.S. 75000.00 75000
weir with all cost as per drawing & direction of E/I.
9 Providing TOR steel reinforcement as per approved design MT 0.20 37100.00 7420
and drawing including cartage to work site bending and
binding with annealed wire with cost of wire removal of rust
placing in position all complete as per specification and
direction of E/I.
10 Providing stone masonry in cement mortar in 1:6 cement m3 53.70 3344.00 179573
coarse sand of 2 to 2.5 F.M. including cost of screening,
carriage of materials, curing, taxes and royalty all complete
as per specifications and direction of E/1.

Total Rs. 426473


Add Contigency 3% 12794
Total Rs. 439267

AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 2 of 6

FEEDER CUM POWER CHANNEL


S. NO. ITEM UNIT QTY. RATE (RS.) AMOUNT (RS.)

1 2 3 4 5 6
1 Earthwork in excavation in ordinary soil and soft rock and
disposal of excavated earth as obtained to a distance upto 1
km. Including all leads and lifts, levelling, ramming the
foundation trenches, removing of roofs of trees, shurbs all
complete as per approved design, specification and
direction of E/I.
(i) In soft rock and dense hard soil excluding blasting Cum 70.40 244 17178
(ii) In Hard Rock including Blasting Cum 105.60 407 42979
2 Earth work in filling in layers not exceeding 150 mm thick Cum 52.80 46 2429
well watered, rammed, fully compacted and fine dresseed
with earth obtained after cutting within a lead of 1 km and
all lifts compelte as per specification and direction of E/I.
(Mode of measurement compacted volume).

3 Providing PCC. M 10 With nominal mix of (1:3:6) in Cum 32.00 4127 132064
foundation with approved quality of stone chips 40 mm
down grated and clean coarse sand of F.M.2.5 to 3
including screening, shuttering, mixing cement cuncrete in
mixer and placing in position, vibrating, striking, curing taxes
and royalty all complete as per specification and direction of
E/I.
4 providing and fixing trash rack & PVC water stop at intake L.S. 50000 50000
and water stop at junction of desilting tank.
5 Providing 13mm thick cement plaster (1:4) with clean Sqm 460.00 133.00 61180
coarse sand of 1.5 F.M. including cost of carriage screening
curing, with all leads & lifts of water scaffolding, taxes and
royalty all complete as per building specifications and
directions of E\I.
6 Providing stone masonry in cement mortar in 1:6 cement Cum 72.00 3344.00 240768
coarse sand of 2 to 2.5 F.M. including cost of screening,
carriage of materials, curing, taxes and royalty all complete
as per specifications and direction of E/1.

Sub Tatol Rs. 546598


Contigency @ 3% 16398
Total Rs. 562996

AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 3 of 6

DESILTING CUM FOREBAY TANK & SPILLWAY CHANNEL

S. NO. ITEM UNIT QTY. RATE (RS.) AMOUNT (RS.)

1 2 3 4 5 6
1 Earth work in excavation in foundation trenches in ordinary
soil and softrock and disposal of excavated earth as
obtalined to a distance upto 1 km inlcuding all leascs and
lifts, travelling, ramming the foundation trenches, removing
roots of trees, shurbs all comptete as per approved design,
specification and direction of E/1.
(i) In soft rock and dense hard soil excluding blasting Cum 43.80 244.00 10687
(ii) In Hard Rock including Blasting Cum 65.70 407.00 26740
2 Earth work in filling in layers not exceeding 150 mm thick Cum 15.93 46.00 733
well watered, rammed, fully compacted and fine dresseed
with earth obtained after cutting within a lead of 1 km and
all lift compelte as per specification and direction of E/1.
(Mode of measurement compacted volume).

3 Providing P.C.C. M-10 with nominal mix of (1:3:6) in Cum 25.69 4127.00 106023
foundation with approved quality of stone chips 40 mm
down graded and clean coarse sand of F.N. 2.5 to 3
shuttering, mixing cement concrete in mixer and placing in
position, vibrating, striking, curing taxes and royality all
complete as per specification and direction of E/I.

4 Providing RCC. M-20 with nominal mix of (1:1.5:3) with 4 Cum 24.41 6758.00 164963
cm down graded,stone gravel approved coarse sand and
excluding cost of reinforcement and including shuttering,
scaffolding vibrating, providing construction joints, finishing,
curings, T&P etc. complete as per E/I.
5 Providing stone masonry in cement mortar in 1:6 cement m3 48.00 3344.00 160512
coarse sand of 2 to 2.5 F.M. including cost of screening,
carriage of materials, curing, taxes and royalty all complete
as per specifications and direction of E/I.
6 Providing 13mm thick cement plaster (1:4) with clean Sqm 322.50 133.00 42893
coarse sand of 1.5 F.M. including cost of carriage screening
curing, with all leads & lifts,scaffolding, taxes and royalty all
complete as per specifications and directions of E\I.

7 Providing TOR steel reiforcement as per approved design MT 1.92 37100.00 71232
and drawings including cartage to work site, bending and
binding with annealed wire with cost of wire removal of rust,
placing in position all complete as per specifications and
directions of E/1.
8 Providing and placing in position gates to control water into L.S. 50000 50000
tank and silt ridden water flow pipe including sluice valve
from the tank as per drawings specifications and direction of
E/I
9 Providing mild steel railing including painting etc. complete L.S 50000 50000
as per drawings and direction of E/I.
10 Providing and placing boulders for portection works where L.S 30000 30000
silt ridden water joins nallah.
11 Supply and erection in position the mild steel trash rack at MT 0.67 74200.00 49714
intake including fabrication, painting transport, erection etc.
as per drawings and specifications complete.

12 Providing and fixing silt flushing 150 mm pipe including No 2 30000 60000
sluice valve as per direction of E/I.
Total Rs. 823496
Add Contigency 3% 24705
AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 4 of 6
Total Rs. 848201

AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 5 of 6

PENSTOCK

S. NO. ITEM UNIT QTY. RATE (RS.) AMOUNT (RS.)

1 2 3 4 5 6
1 Earth work in excavation in foundation trenches in ordinary
soil and softrock and disposal of excavated earth as
obtalined to a distance upto 1 km inlcuding all leascs and
lifts, travelling, ramming the foundation trenches, removing
roots of trees, shurbs all comptete as per approved design,
specification and direction of E/1.

(i) In soft rock and dense hard soil excluding blasting Cum 5.00 244.00 1220
(ii) In Hard Rock including Blasting Cum 7.50 407.00 3053
2 Earth work in filling in layers not exceeding 150 mm thick Cum 1.40 46.00 64
well watered, rammed, fully compacted and fine dresseed
with earth obtained after cutting within a lead of 1 km and
all lift compelte as per specification and direction of E/1.
(Mode of measurement compacted volume).

3 Providing P.C.C. M-10 with nominal mix of (1:3:6) in Cum 2.14 4127.00 8831.78
foundation with approved quality of stone chips 40 mm
down graded and clean coarse sand of F.N. 2.5 to 3
shuttering, mixing cement concrete in mixer and placing in
position, vibrating, striking, curing taxes adn royality all
complete as per specification and direction of E/I.
4 Plain cement concrete M15 (1:2:4) in foundation, flooring Cum 8.40 4807.00 31726.2
slabs
5 Reinforced cement concrete M15 (1:2:4) excluding cost of Cum 7.35 5257.00 38639
reinforcement in foundation, slabs, anchor blocks etc.
6 Providing TOR steel reinforcement as per approved design MT 0.58 37100.00 21407
and drawings including cartage to work site, cutting bending
and binding with annealed wire with cost of wire, removal of
rust, placing in position all complete as per specifications
and directions of E/I.
7 Supplying at site steel pipe with bends for penstock MT 6.20 84800.00 525760
including cutting welding, testing, painting etc. as per
drawings, specification and direction of E/I.
8 Installation and erection of penstock pipe @ 30% of the cost MT 6.20 25440.00 157728
as per S. No. 5.
9 Supply steel bends for penstock including cutting welding all No. 3 20000 60000
complete as per direction of E/I.
10 Providing and Laying butterfly valve 280 mm dia as per No. 1 50000 50000
direction of E/I.
Total Rs. 898429
Contigency 3% 26953
Total Rs. 925381

AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 6 of 6

POWER HOUSE & TAIL RACE


S. NO. ITEM UNIT QTY. RATE (RS.) AMOUNT (RS.)

1 2 3 4 5 6
1 Earth work in excavation in foundation trenches in ordinary
soil and softrock and disposal of excavated earth as
obtalined to a distance upto 1 km inlcuding all leascs and
lifts, travelling, ramming the foundation trenches, removing
roots of trees, shurbs all comptete as per approved design,
specification and direction of E/1.
(i) In soft rock and dense hard soil excluding blasting Cum 14.1 244.00 3450
(ii) In Hard Rock including Blasting Cum 21.220 407.00 8637
2 Earth work in filling in layers not exceeding 150 mm thick Cum 7.92 46.00 364
well watered, rammed, fully compacted and fine dresseed
with earth obtained after cutting within a lead of 1 km and
all lift compelte as per specification and direction of E/1.
(Mode of measurement compacted volume).

3 Providing P.C.C. M-10 with nominal mix of (1:3:6) in Cum 11.160 4127.00 46057
foundation with approved quality of stone chips 40 mm
down graded and clean coarse sand of F.N. 2.5 to 3
shuttering, mixing cement concrete in mixer and placing in
position, vibrating, striking, curing taxes adn royality all
complete as per specification and direction of E/I.
4 Providing RCC. M-20 with nominal mix of (1:1.5:3) with 2 cm Cum 4.74 6758.00 32033
down graded, coarse aggregate approved coarse sand and
excluding cost of reinforcement and including shuttering,
scaffolding vibrating, providing construction joints, finishing,
curings, T&P etc. complete as per E/I.
5 Masonry with pre-cast cement concrete 1:3:6(1 cement: 3 Cum 37.2 6784.00 252365
coarse sand:6 graded stone aggregate 20 mm nominal size)
blocks in cement mortar 1:4 in foundations,plinth and
superstructureas per direction of E/I.
6 Providing TOR steel reinforcement as per approved design MT 0.37 37100.00 13727
and drawings including cartage to work site, cutting bending
and binding with annealed wire with cost of wire, removal of
rust, placing in position all complete as per specifications
and directions of E/I.
7 Stone masonry in cement mortar 1 : 6 including supply of all Cum 8.0 3344.00 26752
materials, labour, T&P etc. Complete.
8 25 mm thick damp proof course with PCC. (1:2:4) m3 1.679 198.00 332

9 Supplying and fixing in position roof truss including MT 1.5 74200.00 111300
fabrication, erection, Painting etc. complete as per drawings
and specifications.
10 Providing and fixing good quality well dressed and well Sqm 25.74 1358.00 34955
seasoned sal/shisham wood work in dcors and windows/sky
lights unlcuding application of two cats of wood preservative
on the surface butting walls and clean coarse sand of F.M.
2.5 to 3 including screening, shuttering, mixing cement
concerte in mixer with 5% profing compound & pacing in
pisition, striking curing, taxes and royalty all complete as per
building specifications and directions of E/I.

11 Providing 12mm thick cement plaster (1:4) on stone Sqm 331.56 133.00 44097
masonry with clean coarse sand of 1.5 F.M. including cost
of carriage screening curing, with all leads & lifts of water
scaffolding, taxes and royalty all complete as per building
specifications and directions of E\I.

AHEC/MNES/C-347/AAS/Model DPR/MHP
Annexure -III
Sheet 7 of 6
12 Providing two coats of painting with ready mixed paint over L.S 35000.00 35000
a coat of primer of approved shade and make over new
wooden and steel surface including preparing the surface
after cleaning, removing dirt, scales, smokes, greas and
sand papering including cost of scaffolding adn taxes all
complete as per building specifications adn directions of E/I.

13 White washing and distemper in three coats over new sqm 279.06 36.00 10046
surface with approved quality of lime including cost of
cleaning surface throughly and removing the scales of
smoke and mesh mark with rubbing, scaffolding, washing of
Jhoma floors and taxes all complete as per building
specifications and directions of E/I.
14 Providing and placing boulders duly packed in slope for L.S 75000.00 75000
protection works at the place of joining of tail race channel
with nallah as per specification and direction of E/I.

15 Providing fencing and gate around power house area L.S 50000.00 50000
16 Supplying and Fixing CGI roof sheet Sqm 39.82 780.00 31060
17 Thermocool false ceiling L.S 50000.00 50000
Sub Total Rs. 825176
Add 3% Contingency 24755
Total Rs. 849931

AHEC/MNES/C-347/AAS/Model DPR/MHP
Project Site

Project Site

Project Site

Drg. No. C-343-1


Location Map of Patu Micro Hydro Power Project, Distt. Lower Subansiri, Arunachal Pradesh
1900
1895
1890
1885
1880
1875
1870 EL.1883.1 DIVERSION WEIR
1865 EL.1864.12
1860 FOREBAY CUM
DESILTING TANK

EL
1855 200M. CHANN

1850 PENSTOCK LENGTH


150 M.

1845
POWER
HOUSE

1840 EL.1864.2
A
AL

1880
N
TU
PA

MINISTRY OF NON CONVENTIONAL ENERGY SOURCES,G.O.I

Consultant
ALTERNATE HYDRO ENERGY CENTER
INDIAN INSTITUTE OF TECHNOLOGY, ROORKEE
I
AD

1860 PATU MICRO HYDRO PROJECT


NN

1840
GENERAL LAYOUT OF WORKS
GI

Pa
N

ng
PA

in DRAWN CHKD. INSP.


Na
di SUBT. APPD.
DSGN.

DRG.NO.C-343-2 ROORKEE JAN.2007 FILE C-347

You might also like