Página 1 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Annex 9: Dry-dock work progress report
Vessel : FORTE DE COPACABANA Superintendent : Darwin More
Date of report: 16/04/2024 ETA / ATA : 02/04/2024
Time : 19:00 ETDK / ATDK : 04/04/204
Repair Day : 14 ETUDK / ATUDK : 21/05/2024
Dock Day : 14 ETRC / ATRC : 23/05/2024
Dockyard : Wilson Sons- SHIPYARD ETD / ATD : 30 /05/2024
WORK PROGRESS REPORT:
Weather:
15/04/2024Temp 23º C - humidity 75% - predominantly clean / wind - 8 Km/h
General Info
Vessel programed dry docked on April 3rd at Estaleiro Wilson Sons – Guaruja – Santos –
Brazil.
Main Scope:
4th Special Survey & Drydocking;
65 000 Hr main Engine overhaul;
Ballast Tanks hydraulic actuators “remote control” for all valves;
A/E 03 overhaul 8000 Hrs
Structural repairs on the in WBT No 1 PS/SB & 7 PS / SB and re-coating in the rest
CAP Survey commencement.
Cargo pump 3 overhaul
Installation of FWG
Installation of ORCA II -Sanitary black water plant
General Progress
Repairs and maintenance of tanks and accessories of the main deck.
Deck
Job Code Work progress
16/04/2024 Forward master scaffolding
16/04/2024 Replacement of main deck structural plates
16/04/2024 Scaffolding of structural plate at bulbous
Página 2 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
16/04/2024 Repair of bites at stern STB
16/04/2024 Scaffolding in firefighting Dry powder system line
Engine Room
Job Code Work progress
16/04/2024 METALOCK removes from the Main Engine:
- Air distributor
- Valve actuators.
- Water lines.
Electrical
Date Work progress
16/04/2024 Checked GMDSS failure on the bridge.
16/04/2024 Changing the GMDSS battery cable terminals.
16/04/2024 Removed from onboard emergency fire pump electric motor.
16/04/2024 Removed from on board 2 electric ventilation motors.
Navigation & Communication
Job Code Work progress
16/04/2024
Safety/SOLAS
Job Code Work progress
16/04/2024 Scaffolding in firefighting lines PS
Additional Work
Job Code Work progress
16/04/2024
Vessel Staff
• Master: Castro
• C/E : Cabral
• Chief officer: Renzo
Classification
BV veritas
All Certifies renew by BV
CAP
Página 3 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Docking Repairs
Subcontractors
Finanzauto: ME overhaul
BV – CAP Survey
END SAIA – Thickness Measurements;
METALOCK – ME overhaul
Safety Officers Comments
Spares / Stores
ANNEX 1 – PHOTOS
Página 4 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Main Engine Air distributor
Main Engine Valve actuators
Main Engine Water lines Scaffolding in firefighting lines PS
Página 5 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Forward master scaffolding Replacement of main deck structural plates
Scaffolding of structural plate at bulbous Repair of bites at stern STB
Página 6 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Scaffolding in firefighting Dry powder
system line