0% found this document useful (0 votes)
53 views6 pages

Dry-Docking Progress Report for Forte

The document provides a progress report for dry-dock work being done on the vessel FORTE DE COPACABANA. The main tasks include a main engine overhaul, ballast tank repairs and coating, and installing new equipment. Work is underway on deck repairs, main engine removal, and electrical system checks.

Uploaded by

Anggelo P.D.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views6 pages

Dry-Docking Progress Report for Forte

The document provides a progress report for dry-dock work being done on the vessel FORTE DE COPACABANA. The main tasks include a main engine overhaul, ballast tank repairs and coating, and installing new equipment. Work is underway on deck repairs, main engine removal, and electrical system checks.

Uploaded by

Anggelo P.D.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Página 1 de 6

DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Annex 9: Dry-dock work progress report

Vessel : FORTE DE COPACABANA Superintendent : Darwin More


Date of report: 16/04/2024 ETA / ATA : 02/04/2024
Time : 19:00 ETDK / ATDK : 04/04/204
Repair Day : 14 ETUDK / ATUDK : 21/05/2024
Dock Day : 14 ETRC / ATRC : 23/05/2024
Dockyard : Wilson Sons- SHIPYARD ETD / ATD : 30 /05/2024

WORK PROGRESS REPORT:


Weather:
15/04/2024Temp 23º C - humidity 75% - predominantly clean / wind - 8 Km/h

General Info

Vessel programed dry docked on April 3rd at Estaleiro Wilson Sons – Guaruja – Santos –
Brazil.

Main Scope:
 4th Special Survey & Drydocking;
 65 000 Hr main Engine overhaul;
 Ballast Tanks hydraulic actuators “remote control” for all valves;
 A/E 03 overhaul 8000 Hrs
 Structural repairs on the in WBT No 1 PS/SB & 7 PS / SB and re-coating in the rest
 CAP Survey commencement.
 Cargo pump 3 overhaul
 Installation of FWG
 Installation of ORCA II -Sanitary black water plant

General Progress
 Repairs and maintenance of tanks and accessories of the main deck.

Deck
Job Code Work progress
16/04/2024 Forward master scaffolding
16/04/2024 Replacement of main deck structural plates
16/04/2024 Scaffolding of structural plate at bulbous
Página 2 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

16/04/2024 Repair of bites at stern STB


16/04/2024 Scaffolding in firefighting Dry powder system line

Engine Room
Job Code Work progress
16/04/2024 METALOCK removes from the Main Engine:
- Air distributor
- Valve actuators.
- Water lines.

Electrical
Date Work progress
16/04/2024 Checked GMDSS failure on the bridge.
16/04/2024 Changing the GMDSS battery cable terminals.
16/04/2024 Removed from onboard emergency fire pump electric motor.
16/04/2024 Removed from on board 2 electric ventilation motors.

Navigation & Communication


Job Code Work progress
16/04/2024

Safety/SOLAS
Job Code Work progress
16/04/2024 Scaffolding in firefighting lines PS

Additional Work
Job Code Work progress
16/04/2024

Vessel Staff
• Master: Castro

• C/E : Cabral
• Chief officer: Renzo

Classification
 BV veritas
 All Certifies renew by BV
 CAP
Página 3 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Docking Repairs

Subcontractors
 Finanzauto: ME overhaul
 BV – CAP Survey
 END SAIA – Thickness Measurements;
 METALOCK – ME overhaul

Safety Officers Comments


Spares / Stores

ANNEX 1 – PHOTOS
Página 4 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Main Engine Air distributor


Main Engine Valve actuators

Main Engine Water lines Scaffolding in firefighting lines PS


Página 5 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Forward master scaffolding Replacement of main deck structural plates

Scaffolding of structural plate at bulbous Repair of bites at stern STB


Página 6 de 6
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Scaffolding in firefighting Dry powder


system line