Página 1 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Annex 9: Dry-dock work progress report
Vessel : FORTE DE COPACABANA Superintendent : Darwin More
Date of report: 18/04/2024 ETA / ATA : 02/04/2024
Time : 19:00 ETDK / ATDK : 04/04/204
Repair Day : 16 ETUDK / ATUDK : 21/05/2024
Dock Day : 16 ETRC / ATRC : 23/05/2024
Dockyard : Wilson Sons- SHIPYARD ETD / ATD : 30 /05/2024
WORK PROGRESS REPORT:
Weather:
18/04/2024Temp 23º C - humidity 75% - predominantly clean / wind - 8 Km/h
General Info
Vessel programed dry docked on April 3rd at Estaleiro Wilson Sons – Guaruja – Santos –
Brazil.
Main Scope:
4th Special Survey & Drydocking;
65 000 Hr main Engine overhaul;
Ballast Tanks hydraulic actuators “remote control” for all valves;
A/E 03 overhaul 8000 Hrs
Structural repairs on the in WBT No 1 PS/SB & 7 PS / SB and re-coating in the rest
CAP Survey commencement.
Cargo pump 3 overhaul
Installation of FWG
Installation of ORCA II -Sanitary black water plant
General Progress
Repairs on ventilation ducts
Repairs on empty spaces (tanks)
Deck
Job Code Work progress
18/04/2024 Repairs on the PS firefighting line near TK 3
18/04/2024 Welding on the N2 plant ventilation duct
18/04/2024 Repairs on empty space
Página 2 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
18/04/2024 Cleaning service in an empty space
18/04/2024 Cleaning TK 3
18/04/2024 Welding in empty space
18/04/2024 Changes to the forward ladder.
Engine Room
Job Code Work progress
18/04/2024 Removal of the remaining Main Engine cylinders.
18/04/2024 Removal of the Main Engine’s pump injector Springs.
Electrical
Date Work progress
18/04/2024 Checked GMDSS failure on the bridge.
18/04/2024 Changing the GMDSS battery cable terminals.
18/04/2024 Identifying buttons of emergency stop for their removal.
18/04/2024 Removed from on board 2 electric ventilation motors.
18/04/2024 Verifying the functionality of the Diesel Generator’s Batteries
Navigation & Communication
Job Code Work progress
18/04/2024 Treatment on the external walkway of the bridge PS
18/04/2024 NAVTEX antenna base treatment
18/04/2024 Start of diamond welding work on the bridge’s portholes
Safety/SOLAS
Job Code Work progress
18/04/2024 -
Additional Work
Job Code Work progress
18/04/2024 Removal of the cracked cabin porthole of the ‘condutor’s’ cabin
Vessel Staff
• Master: Castro
• C/E : Cabral
• Chief officer: Renzo
Classification
BV veritas
Página 3 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
All Certifies renew by BV
CAP
Docking Repairs
Subcontractors
Finanzauto: ME overhaul
BV – CAP Survey
END SAIA – Thickness Measurements;
METALOCK – ME overhaul
Safety Officers Comments
Spares / Stores
ANNEX 1 – PHOTOS
Página 4 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Repairs on the PS firefighting line near Welding on the N2 plant ventilation duct
TK 3
Repairs on empty space Cleaning service in an empty space
Página 5 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Cleaning service in an empty space Welding in empty space
Treatment on the external walkway of the NAVTEX antenna base treatment
bridge PS
Página 6 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
Start of diamond welding work on the Removal of the cracked cabin porthole of the
bridge’s portholes ‘condutor’s’ cabin
Changes to the forward ladder. ME’s Pump injector springs
Página 7 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020
remaining Main Engine cylinders.