2024-04-18 FCO Daily Report - Day 16 WS

The document provides a progress report for dry-dock work being done on the vessel FORTE DE COPACABANA. It details repairs underway across various areas of the ship including the deck, engine room, electrical systems, and navigation. The main tasks include an engine overhaul, tank repairs, and installation of new equipment. Photos document some of the repair work.

Uploaded by

Anggelo P.D.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views7 pages

2024-04-18 FCO Daily Report - Day 16 WS

The document provides a progress report for dry-dock work being done on the vessel FORTE DE COPACABANA. It details repairs underway across various areas of the ship including the deck, engine room, electrical systems, and navigation. The main tasks include an engine overhaul, tank repairs, and installation of new equipment. Photos document some of the repair work.

Uploaded by

Anggelo P.D.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Página 1 de 7

DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Annex 9: Dry-dock work progress report

Vessel : FORTE DE COPACABANA Superintendent : Darwin More


Date of report: 18/04/2024 ETA / ATA : 02/04/2024
Time : 19:00 ETDK / ATDK : 04/04/204
Repair Day : 16 ETUDK / ATUDK : 21/05/2024
Dock Day : 16 ETRC / ATRC : 23/05/2024
Dockyard : Wilson Sons- SHIPYARD ETD / ATD : 30 /05/2024

WORK PROGRESS REPORT:


Weather:
18/04/2024Temp 23º C - humidity 75% - predominantly clean / wind - 8 Km/h

General Info

Vessel programed dry docked on April 3rd at Estaleiro Wilson Sons – Guaruja – Santos –
Brazil.

Main Scope:
 4th Special Survey & Drydocking;
 65 000 Hr main Engine overhaul;
 Ballast Tanks hydraulic actuators “remote control” for all valves;
 A/E 03 overhaul 8000 Hrs
 Structural repairs on the in WBT No 1 PS/SB & 7 PS / SB and re-coating in the rest
 CAP Survey commencement.
 Cargo pump 3 overhaul
 Installation of FWG
 Installation of ORCA II -Sanitary black water plant

General Progress
 Repairs on ventilation ducts
 Repairs on empty spaces (tanks)

Deck
Job Code Work progress
18/04/2024 Repairs on the PS firefighting line near TK 3
18/04/2024 Welding on the N2 plant ventilation duct
18/04/2024 Repairs on empty space
Página 2 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

18/04/2024 Cleaning service in an empty space


18/04/2024 Cleaning TK 3
18/04/2024 Welding in empty space
18/04/2024 Changes to the forward ladder.

Engine Room
Job Code Work progress
18/04/2024 Removal of the remaining Main Engine cylinders.
18/04/2024 Removal of the Main Engine’s pump injector Springs.

Electrical
Date Work progress
18/04/2024 Checked GMDSS failure on the bridge.
18/04/2024 Changing the GMDSS battery cable terminals.
18/04/2024 Identifying buttons of emergency stop for their removal.
18/04/2024 Removed from on board 2 electric ventilation motors.
18/04/2024 Verifying the functionality of the Diesel Generator’s Batteries

Navigation & Communication


Job Code Work progress
18/04/2024 Treatment on the external walkway of the bridge PS
18/04/2024 NAVTEX antenna base treatment
18/04/2024 Start of diamond welding work on the bridge’s portholes

Safety/SOLAS
Job Code Work progress
18/04/2024 -

Additional Work
Job Code Work progress
18/04/2024 Removal of the cracked cabin porthole of the ‘condutor’s’ cabin

Vessel Staff
• Master: Castro

• C/E : Cabral
• Chief officer: Renzo

Classification
 BV veritas
Página 3 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

 All Certifies renew by BV


 CAP

Docking Repairs

Subcontractors
 Finanzauto: ME overhaul
 BV – CAP Survey
 END SAIA – Thickness Measurements;
 METALOCK – ME overhaul

Safety Officers Comments


Spares / Stores

ANNEX 1 – PHOTOS
Página 4 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Repairs on the PS firefighting line near Welding on the N2 plant ventilation duct
TK 3

Repairs on empty space Cleaning service in an empty space


Página 5 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Cleaning service in an empty space Welding in empty space

Treatment on the external walkway of the NAVTEX antenna base treatment


bridge PS
Página 6 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

Start of diamond welding work on the Removal of the cracked cabin porthole of the
bridge’s portholes ‘condutor’s’ cabin

Changes to the forward ladder. ME’s Pump injector springs


Página 7 de 7
DRY-DOCKING MANUAL
Version.Rev 1.02
FLO.DOC.03
Valid From 10/08/2020

remaining Main Engine cylinders.