Wa0000.
Wa0000.
Advantages of Tunneling
1. Freedom from snow and iceberg hazards.
2. Reduction in overall cost by reducing the distance.
3. Reduction in maintenance cost and provision of easier gradients.
4. Avoids interference with surface and air rights.
DESIGN FACTORS
1. Options for Tunneling:
For each type of tunnel there are certain geometrical constrains and other
specific factors affecting cost.
For a road tunnel, acceptable gradients and curves will be related to the
design speed and hence to traffic costs.
For a pressure tunnel, there is little direct geometrical constraint and the
differential cost of construction in relation to the ground would need to be
considered again the capitalized head losses.
A general knowledge of the geological structure will indicate whether or not
the most direct route conform to a favourable geological horizon or whether
on the contrary it may encounter unstable ground such as squeezing rock,
running sand, major fault zones, decomposed rock, or similar hazards which
may only be penetrated at great expense.
Where there is a possibility of adopting an economic method of tunneling,
related specifically to a type of ground with limited variation, there may be a
considerable benefit from diverging from the most direct route, in order to
situate the tunnel throughout in such ground.
At the earliest stage in planning, such factors should be considered so that the
options may be described, systematically tested and reduced as information
arises from the first stage of site investigation.
2. Design shapes:
The shape of a tunnel is dependent upon the nature and type of ground
where it is to be constructed.
Tunnels in solid rocks are self-supporting and are gene4rally designed with
semi-circular arch with vertical side walls.
Tunnels in soft ground are generally made circular which can resist the
pressure on exposed surfaces.
A circular tunnel is best suited to resist external and internal stresses. But for
laying railways or highways, the bottom curvature haws to be filled up.
(continue 2b H)
In soft soils and rocks, a horse shoe shaped tunnel is provided which is a
compromise between the above two types.
A circular x-section is ideal for full-flowing water tunnels because it provides
the greatest area for flow, and permits use of a high strength tubular steel
liner.
An elliptical or egg-shaped x-section works well for servers and storm water
drainage tunnels. The small-radius invert acts as a narrow self-scouring
channel during periods of low flow and the upper and larger parts of the
cross section provide a high flow capacity for surge discharge during storms
and floods.
A transportation tunnel requires a more or less rectangular area for traffic.
Tunnel start and end in portals if they penetrate horizontally through a hill or
mountain, or in shafts if they go deep below water or relatively flat terrain.
At portals adverse factors can combine to give the worst conditions for both
excavation and support.
The portal is the location of least cover, where any loss of ground quickly migrates
upwards to cause settlements at the surface, where the rock is most weathered and
the joints most open, and where problems of slope instability combine with those of
tunneling alone.
It is also the place where the con tractor starts, and therefore has the least experience
of the ground conditions, and where blasting and support are still being adjusted
and may not yet be adequate.
Pre-reinforcement of the portal area, intensive monitoring of ground movements,
and careful blasting of the initial sections are needed in most cases.
The ideal portal location, other factors being equal, is at an outcrop where the
quality of rock can be confirmed as sound, and where the rock above the tunnel
crown is at least several metres thick.
Shafts are acceptable when a tunnel is to carry water, oil or gas, but not usually for
entering or leaving a road or rail tunnel.
Shafts tend to be more stable than portals and tunnels because gravity acts in a
favourable direction, along the shaft axis, and because horizontal stress components
are often similar in magnitude.
The worst problems of shaft sinking usually coincide with the soil-rock interface,
where the soils are often boulder and the rock loose, weathered, and permeable.
Pregrouting or even freezing may be needed at this level to contain water inflows
and to stabilize the ground.
CONSTRUCTION OF TUNNELS
Tunneling in form ground depends upon the shape, size and available equipment.
Depending upon the type of strata, size of the tunnel and the method adopted,
excavation is supported by temporary wooden supports or permanent steel
supports.
METHODS OF TUNNELING
II
III
Drill Holes
Heading
Benching
Mucking
In case the rock is badly broken, the top heading is driven well ahead of the
bench and the bench is employed in installing timbers to support the roof.
With the development of jumbo this method is rarely used.
3. Drift Method
In case of large size tunnels a pilot tunnel or drift is sometimes driven
through full length or a portion of tunnel length before excavating the full
cross-section of the tunnel.
The drift is then widened by drilling holes on its faces.
Method 1:
A crown drift is made first
It is supported by two vertical posts which are removed later and a
segment of steel ribs is provided which forms part of the ultimate ribs.
Drifts on either side of the central drift are then made. These drifts are
supported by steel rib segments in such a way that along with the segment
over the central top drift a complete semicircle above the springing is
formed. This is followed by bending.
Method 2:
A side drift is driven through the zone at subgrade on each side.
A support in steel or concrete is construed in each drift with suitable
provision for drainage.
If the height of side walls be too great to build the concrete wall in a single
lift, another side drift may be driven immediately above the concrete side
wall carried on up to springline.
DRILLING ROCK
Drilling through rock is essential for keeping explosives that loosen the rock.
A drifter is commonly used for this purpose. It is equipped with steel drill and
detachable bits.
Various types of drills and bits are employed under different circumstances
Water is used to remove the cuttings from the holes.
For a particular project the depth and spacing of holes over the tunnel face are
determined experimentally.
The depth of holes varies with
the size and shape of the tunnel
The type of rock and
The drilling equipment likely to be employed.
The depth advanced during one drilling and shooting operation is known as a
round and it varies from 1.3 to 6 metres.
DRILL JUMBOS
A drill jumbo is a portable carriage with one or more working platforms.
It is equipped with beams, columns and booms support the drills. These are
designed to allow the drills to be spaced to any desired pattern.
A number of holes can be drilled simultaneously with jumbos.
A jumbo may be mounted on wheels for travelling on rails or on pneumatic
tyres.
Tyre mounting provides a jumbo freedom of movement and thus facilitates
spotting the positions of the holes to be drilled.
DRILLING PATTERN
May be defined as the position of the holes drilled into the face of a tunnel in
advancing on road.
The best drilling pattern under a given circumstance will break the greatest
volume of rock with the least total length of holes and quantity of explosives.
To obtain this result, a number of factors such as size of tunnel, depth of holes
drilled, the type of rock and the method of mounting drills needed proper
consideration.
It should be determined experimentally for each project.
BORING
Is less disruptive than blasting and produces a more stable tunnel requiring less
support.
Full-face boring machines nowadays can cut economically through most types of
grand.
Their disadvantages include:
(i) they are expensive to by and transport
(ii) they are expensive to assemble on site.
DUCTS
LIGHTING
Adequate lighting should be provided at
The face and at any other point where work is in progress at equipment
installation, such as pumps, fans and transformers. Along the length of
the tunnel also adequate lighting should be provided.
Any obstructions such as formwork, etc inside the tunnel should be well lighted
to avoid accidents when hauling units are moving.
Lighting at working face should be profuse. No single light however, should be
so powerful as to cause temporary blinding effect when looked at.
Incandescent lamps should be fixed in the centre of the roof of tunnel. In case
the lamps are to be fixed on sides of the tunnel, they should be so high as
possible and well above ventilation ducts, so that the shadow of the duct is not
formed on the road surface.
The electric circuit of the lighting in tunnel should be divided into a number of
independent circuits with their insulators and fuse boxes separate. With the
separation of the circuits, the repair work in the electric lighting system can be
easily done by switching of the desired circuits while the other circuits are still in
operation.
In addition to the fixed lighting system, all hauling equipment should have their
own lighting system. These lights not only give indication to the personnel in
the tunnel of the approach of the hauling equipment but also permit them to
negotiate the tunnel without any danger in case of emergencies when the fixed
light system are turned out.
In addition to the normal lighting, provision of flood lights should be made at
suitable intervals for detailed inspection for any particular length of spot.
In the case of soft soil requiring instantaneous support, drilling and blasting is not
done.
Continuous support has to be provided to the periphery of the excavated section.
The type and method of support depends on the nature of ground.
In extremely running materials like dry or quick sand, the soil is first supported and
then excavation of the tunnel is taken up.
In moderately firm materials, like dry earth, cemented sands and gravels, the roof
and side walls of the tunnel may be left unsupported for a short period.
In self-supporting materials like sandstones and cemented sands and gravels, the
roof side walls can remain unsupported till the full cross-section is excavated.
The hydraulic rams are fixed against the complete primary lining.
The whole procedure is repeated as the excavation proceeds.
TUNNEL LINING
Tunnel lining is provided to take the following loadings:
(i) Weight of lining
(ii) Weight of internal structure (if any)
(iii) Weight and presence of surrounding ground along with water and
superimposed loading.
(iv) Loadings related to the use of tunnel such as weight and impact of traffic, or
internal pressure.
Note:
If the strata of the tunnel, is such that the excavated portion is able to support itself,
the lining would only serve as a veneer.
If also provides a smooth friction reducing surface and a protective cover against
spalling or deterioration of the rock due to chemical and physical changes that occur
due to weathering.
1. Brick Lining:
Used in many old tunnels constructed before concrete technology was
evolved.
Not popular for the following reasons.
(i) Requires a heavy and large entering.
(ii) The ground has to stand for a comparatively long time with
permanent support.
(iii) Unsuitable in shield tunneling.
2. Stone Masonry Lining:
Stone and timber were only materials available before bricks were
introduced.
Limitation of use of stones similar to those of thick lining.
3. Timber Lining:
Due to cheapness and availability, it is often used in the earlier stages of
tunneling as temporary lining or support in other types of lining.
Unsuitable in shield tunneling and also in water proof lining.
(i) Bulkhead:
These are provided at the end of each pour and therefore its length depends
on the length of the formwork.
(ii) Longitudinal
These have to be provided at the junction of the sides and the invert and at
haunches of arches when the sides and arches are placed separately for
various considerations.
Compaction:
It is advisable to vibrate conc. through the window by immersion type vibrators
and also by fixing vibratos to the formwork.
Curing:
May be generally done by spraying water.
Pack Grouting:
Conc. and steel lining for underground works should be grouted to pack
the spaces between rock and conc. lining and between the steel lining and
conc. lining.
It should be done not earlier than 21 days after placement of conc. lining.
The pressure of grouting should not exceed 5Kg/cm2.
Pressure Grouting:
When it is found that the rock strata is highly fissured or poor or there is
seepage of water, it would be necessary to do high pressure grouting with deep
holes either before the lining is placed or after the lining is placed according to
the circumstances.
The numbers 1, 2 and 3 show the sequence of conc. placing in the tunnel lining.
Reinforcing steel:
Steel ribs, bars, etc. are used as reinforcement in conc. lining when and
where required.
In design of a thick conc. lining, two layers of reinforcing bars, one near
the inner and the other near the outer surface of the lining, are provided.
The gap between two layers, specially near the roof, should be large
enough to allow the insertion of a pipe through which the conc. will be
placed.
6. Structural steel
For the same strength requirements, it is lighter than cast iron lining and
hence the number of segments can be reduced.
TUNNEL VENTILATION
The purpose of ventilation in tunnel is to make the working space safe for workers
by providing fresh air which is free from harmful obnoxious gases and dust.
The diesel engines working inside the tunnel cause rise in temperature. Ventilation
helps to bring down this temperature.
1. Natural Ventilation
Applicable to tunnel with straight alignment and uniform gradient, up to
100m length.
Natural drafts are depended on to renew the air inside the tunnel.
If the tunnel dips under an obstruction, or the grades are changing or the
alignment contains curves, the quantity of natural air expected to provide
natural ventilation is considerably reduced and the length of the tunnel upon
which natural draft can be expected to take care of ventilations drastically
reduced.
Another factor that restricts the length upon which natural ventilation would
suffice is whether the traffic in the tunnel is one directional or it is either
direction of the tunnel.
In the case of one directional traffic, comparatively longer length of tunnel
(>100m) may not need mechanical ventilation.
FANS
Types of ventilation fans include:
Reversible or Non-reversible
Externally driven or Internally driven.
For ventilation of tunnels the reversible type axial blowers with fan fitted directly on
totally enclosed electric motor is recommended. It is a normal practice to fit two
such units in one shell to increase the total output.
In the use of ventilation system the pressure under which the air is to be pumped
into other tunnel may be mentioned. The diameter of the pipe should be fixed after
taking into account the pipes and other relevant factors.
Some length of the air duct near the working face should be kept flexible. For long
length of tunnel, addition of boosters at suitable place may be necessary.
For some length from the portal, no elaborate ventilation system is necessary for
excavation of tunnels.
VENTILATION BUILDINGS
Usually located near the portals of the tunnels or at intermediate shaft or both as
considered necessary from the overall economy of the arrangement in each case.
Generally arrangement of ventilation equipment is to locate the blower fans on
floors with large openings to the outside atmosphere with louvers in the openings to
protect against rain and snow. The exhaust fans are situated in airtight chambers
with expanding exhaust stacks to the outside atmosphere.
Floor heights of the buildings are based on the considerations of the longest
equipment/machinery to be installed. Additional space should be available for air
ducts without having to bend the duct to provide elbows in the line.
Ventilation equipment and lighting of tunnel are controlled from a central control
station which is located either in one of the ventilation buildings or in a separate
service building.
DUST CONTROL
Dust in the tunnel is formed due to the various operations connected with tunneling:
Drilling
Blasting
Loading and
Hauling of muck