List of Checking - Test of HydroGenerator Set-1
List of Checking - Test of HydroGenerator Set-1
(i) Stator dielectric tests. These tests consist of: Insulation resistance and polarization
index, Corona probe test, Corona visibility test, Final AC high potential test, Partial
discharge analysis (PDA) test, and Ozone detection (optional).
(ii) Rotor dielectric tests.
(iii) Stator and rotor resistance tests.
(iv) Noise and vibration measurements.
1.2 Special field test (one unit of series). These tests consist of:
NOTE: 1. Guide lines indicated here under are general and may vary from manufacturer
to manufacturer.
2. Items not applicable for particular turbine can be indicated as NA.
11 Checking & ensuring Line -Line & Line -Earth clearances for
all bus wires & equipments at ODY
12 Checking & ensuring grounding of all equipment
13 Measuring earth-mat resistance for proper value. Checking its
value with the design calculations
14 Protection relays- soft-ware loading, Checking for proper
operation of all protections, adopt recommended settings
15 Extending power supply to various auxiliary systems like OPU
sets, Lube-oil systems, cooling water system, etc; adjust for
required flow at recommended pressures, ensuring proper
change-overs, alarm/trip settings of various associated limit/
pressure/ level/flow switches & commissioning each as per
schemes.
16 Checking all individual CTs, PTs (415V/1 1kV/220kV) for
proper PI -P2 positioning, ratio & polarity; IR values.
17 Checking the synchronising scheme
18 Dry stroking of MIV/butterfly valve/pen stock gate as the case
may be; adjust for proper opening/closing times, adjust correct
settings of limit & pressure settings, Checking for proper
indications, alarms, trips etc. as per scheme.
19 Dry stroking of turbine, ensure proper beddings, achieve
L Taking over:
After the successful completion of the "Reliability test" the
unit will be taken over by the 'Owner' for 'commercial
operation'. In case the rated head or discharge is not available
to operate the unit at full capacity, the unit shall be
provisionally taken over after completion of Reliability tests at
available head or discharge. The Contractor shall prove the
unit at full capacity immediately when the rated head and /or
the discharge is available after which the unit will be 'Taken
over' by the 'Owner'
M Protocol on Tests
A protocol on tests carried out at site including acceptance tests
shall be prepared and supplied.