CONFIDENTIAL, BAJJUL 2023/MGT345/375
UNIVERSITI TEKNOLOGI MARA
FINAL EXAMINATION
COURSE OPERATIONS MANAGEMENT
COURSE CODE MGT345/375
EXAMINATION JULY 2023
TIME 3 HOURS
INSTRUCTIONS TO CANDIDATES
1. This question paper consists of two (2) parts: PART A (5 Questions)
PART B (5 Questions)
‘Answer ALL questions in the Answer Booklet. Start each arswer on a new page.
e
Do not bring any material into the examination room unless permission is given by the invigitator.
B
Please check to make sure that this examination pack consists of:
i) the Question Paper
il) an Answer Booklet — provided by the Faculty
il) a graph paper — provided by the Faculty
5. Answer ALL questions in English
DO NOT TURN THIS PAGE UNTIL YOU ARE TOLD TO DO SO
This examination paper consists of 7 printed pages
© Hak Cipta Universit Teknologi MARA CONFIDENTIALCONFIDENTIAL,
PARTA
QUESTION 1
BA/JUL 2023/MGT345/375
Nazril Enterprise is considering locating its existing obsolete plant. The company had done a
study on three locations; Shah Alam, Seremban and Puchong. The cost details for the
locations are:
Location Fixed Cost (RM) Variable Cost per unit (RM)
‘Shah Alam) 50,000 50
‘Seremban 60,000 30
Puchong 75,500 20
Construct the total cost curves for all locations and identify which location to choose for each
relevant range of production.
(© Hak Cipta Universiti Teknologi MARA
(12 marks)
CONFIDENTIALCONFIDENTIAL
QUESTION 2
BAWJUL 2
1023/MGT345/375,
Permada Manufacturing Sdn Bhd produces high-quality shoes. Manufacturing these shoes
requires 10 separate tasks. There are 7 hours available for manufacturing the shoes in the
plant each day and the daily demand is 60 shoes. Tre information for the tasks is as follows:
TASK TASK TIME (MINUTES) PREDECESSOR
A 7 =
B 3 A
c 2 5
D a B
E 7 CD
F 3 a
c 2 F
H 5 c
T i EH
J 3 T |
a) Draw the precedence diagram of the operation.
b) Assuming 5 days of work a week, calculate the cycle time of the line.
¢) Determine the theoretical minimum number of workstations.
4) Construct the line layout of
the operation.
2) Compute the resulting efficiency and balance of delay percentages.
(© Hak Cipta Universiti Teknologi MARA,
(4 marks)
(1 mark)
(1 mark)
(4 marks)
(2 marks)
CONFIDENTIAL,CONFIDENTIAL 4
QUESTION 3
BA/JUL 2023/MGT345/375
New Resources Sdn Bhd has contracted Bumi Mekar Construction to start building a new
factory. The table below provides the following information regarding the preject.
‘Activity Preceding Activity | Duration (months)
A - 8
B A 7
c A 3
D B 5
— B 4
F D 2
G BC 7
4 EG 2
1 F 3
J G 8
K Hid 6
Based on the information given above,
a) Construct the network diagram for the project
b) Compute the Earliest Event Time and Latest Event Time for each event
¢) Identity the critical activities.
4) Determine the project completion time.
e) Determine the Free Float and Independent Float for activity F.
(3 marks)
(3 marks)
(2 marks)
(1 mark)
(2 marks)
)_ Ifthe duration of activity D were to change from 5 months to 7 months, what would
happen to the project's completion time?
(© Hak Cipta Universiti Teknologi MARA
(2 marks)
CONFIDENTIAL,CONFIDENTIAL 5 BAJJUL 2023/MGT345/375
QUESTION 4
Muhibah Manufacturing plan to produce a new portable vacuum cleaner this year. The
company has developed an aggregate capacity plan for January to June 2023 as below:
Months Forecasted Demand (units)
January 7300
February 7700
March 7400
April 6400
May 6500
June 7500
The company also plans to produce additional 3000 units each month to cover any uncertainty
in demand.
Additional information:
Current workforce: 20 workers
Standard output: 30 minutes/unit
Regular working hours: 8 hoursiday
Regular labor cost: RM5.00!hour
Overtime rate: RM8.00/hour
Overtime constraint: 1000 units/month
Inventory carrying cost: RM2.00lunit
Subcontract cost: RM9.00/unit
Working days: 26 days/month
a) Prepare an aggregate production plan for Jenuary to June 2023 using a constant
workforce strategy by varying overtime and subcontract requirements to meet the demand.
(6 marks)
b) Calculate the total costs for the plan.
(7 marks)
© Hak Cipta Universiti Teknologi MARA, CONFIDENTIALCONFIDENTIAL 6 BAWJUL 2023/MGT345/375
QUESTION 5
Robert Manufacturing is a company that produces modular parts. The company has been
successful in automating much of its work. However, there are issues with the computerized
method. Over the past 20 months, the machines have broken down at the rate indicated in the
following table:
numer, | ‘areakoouns
(MONTHS)
0 5
4 4
2 2
3 5
: ;
‘The company estimates that each breakdown cost RM400 in time and service expenses. To
solve the issue, a scheduled preventive maintenance contract was recently offered by an
outside maintenance company. Even if Robert Manufacturing contracts for preventive
maintenance, there will still be breakdowns, averaging one breakdown per month. The price
for service is RM500 per month.
Determine whether Robert Manufacturing should contract for preventive maintenance or
continue the current maintenance. Justify your answer.
(10 marks)
@ Hak Cipta Universiti Teknologi MARA CONFIDENTIAL,CONFIDENTIAL T BANJUL 2023/MGT345/375
PARTB
QUESTION 4
Explain four (4) characteristics of services
(8 marks)
QUESTION 2
Explain four (4) objectives of Research and Development.
(8 marks)
QUESTION 3
List any four (4) goals of sustainability.
(8 marks)
QUESTION 4
Discuss the four (4) types of allowances with examples.
(8 marks)
QUESTION 5
Discuss any four (4) objectives of quality control.
(8 marks)
END OF QUESTION PAPER