Chapter 2
Chapter 2
Power Potential
2.1. Estimation of Water Power Potential
Work done = Force * displacement
The potential energy of water is:
Work done =m * g * H, where H is the total head the water will fall.
= ρ * V * g * H, where: ρ *g=ү
= ү*V*H; V=Q*t
W= ү *Q*H/t→ W* t =ү *Q * H,
Hence, the theoretical electrical energy produced from a site is:
Power (Watt) = ү *Q * H (where Ƴ= unit weight of water, 9810N/m3)
If factor of efficiency (η) is introduced,
Then , Power = ү* Q * H * η = 9.81 * Q * H * η (KW)
2.2. Definitions(Terms)
Gross head = it is the difference in water level between the water level in the
fore-bay (or head water in the reservoir) and tail water level.
Net Head = gross head - all the hydraulic losses. It is the available head to do
work on the turbine
Design Head = the net head at which the turbine reach its peak efficiency.
Rated Head = it is the net head at which the turbine operating at full gate
opening.
Load factor = it is the ratio of the average load over a certain period of time to
the peak load during the same period.
Depending on the period chosen, there are different load factors as daily,
monthly or annual.
Load factor, LF = average load over a certain period
Peak load during that period
The maximum load determines the capacity of the units while the load
factor gives an idea of degree of utilization.
Example, an annual LF 0.6 indicate that the machines are producing 60% of
their yearly rated capacity (max. production capacity).
Definitions…
Capacity factor (plant use factor, plant factor) = defined as the ratio of average
output of the plant for a given period of time to the plant capacity.
Capacity factor, CF = average load (over a given period of time)
Plant capacity during that period
The capacity factor and load factor would become the same if the peak load
is equal to the plant capacity.
Utilization factor = Throughout the day or any given time period, a hydroelectric
plant power production goes on varying, depending upon the demand in the
power grid and the power necessary to be produced to balance it.
Utilization factor = Maximum power production over certain period
Installed capacity
Capacity:- is the maximum amount of power that a generating plant can deliver,
expressed in kilowatts.
Evaluation of site potential
The primary purpose of a preliminary investigation in hydropower
development is to determine how much power is available at the site and
how often it is available.
The power output of hydroelectric power plant is given by:
QgH
P ( KW ) 9.81QH
1000
shows the relation between flow and time during which the discharges are
available.
P
Power Demand Curve
It is defined as the total load, which consumers choose, at any instant of
time, to connect to the supplying power system.
Highest instantaneous value of demand is the peak load or peak
demand.
Base load is the total load continuously exists where as the average
load is the area under the curve divided by the time
If the demand is uniform, the demand curve is a horizontal line,
and the mass demand curve is a straight line having a slope
equal to the demand rate.
2.4. Load prediction and Demand Assessment
Load prediction
Prepare the mass demand curve corresponding to the given rate of demand
Draw lines AB, FG, etc such that, parallel to the mass demand curve and
tangential to the crests, A, F, etc of mass curve. Points A, F etc indicate the
beginning of the dry periods.
determine the vertical intercepts DC, HJ, etc b/n the tangential lines and the
mass inflow curve. These intercepts indicate the volumes by which the
inflow volumes fall short of demand.
Note: The capacity obtained is the net storage capacity which must be available
to meet the demand. The gross capacity should include the losses as
evaporation, seepage, etc.
Mass curve
Adjust inflow from the river (stream flow and rainfall over the reservoir);
Adjust the demand (total out flow from the dam), as evaporation loss, water
demand for power production, environmental losses and others;
Note: The storage would be required only in those months in which the demand
is greater than the adjusted inflow.
Determine the total storage capacity of the reservoir adding the storage
required found above.
Sequent peak Algorithm
Storage and Pondage
Storage: is the reservoir that accumulates water behind
the constructed dam, which sometimes grows to be some
of the largest lakes in the world.
Question:
1. Sketch the load curve
2. Determine the load factor, capacity factor and Utilization factor
Solution
Load curve
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Q(m3/s) 117 150 203 117 80 118 82 79 58 45 57 152
Question:
It is intended to design a hydroelectric power plant across the streams,
using the above data, net head at the plant site =20m, efficiency of the
turbine = 90%.
1. Plot the flow and power duration curves and calculate the firm
and secondary power available from this source if the maximum
usable flow is limited to 150m3/s.
2. It is intended to develop power at a firm rate of 15MW, either by
providing storage or by providing a standby diesel plant with no
storage, determine the minimum capacity of the reservoir and
of the diesel unit.
Solution: FDC and PDC
Power (MW)
Flow Cumulative Frequency Frequency equaled (=20*0.9*9.81/1000)=
(m3/s) (months) or exceeded (%) 0.176
[1] [2] [3]=([2]/[12])*100 0.176*[1]
203 1 8.33 35.728
152 2 16.67 26.752
150 3 25.00 26.4
118 4 33.33 20.768
117 5 41.67 20.592
117 5 41.67 20.592
82 7 58.33 14.432
80 8 66.67 14.08
79 9 75.00 13.904
58 10 83.33 10.208
57 11 91.67 10.032
45 12 100.00 7.95
Solution…
A. The flow duration curve (flow Vs frequency equaled or exceeded) will be
plotted.
The same plot can be used as a power duration curve by multiplying the
ordinates by a factor of η*p*g*H/10^6 =(0.9*9,810*20/10^6) = 0.176
to obtain the power in MW with η=90% and H=20m, (i.e. P=0.176*Q)
The firm power available (equal to the area of the power duration
curve) under the 45m3/s line is 7.95MW (=0.9*9.81*1000*20*45/10^6).
The secondary power (equal to the area under the power duration
curve between the 150 and 45m3/s lines) is 10MW.
B. The power to be supplemented by storage or standby unit to obtain a firm
power of 15MW is the area "abc” = 17.76MWmonth.
Therefore the storage required is: (17.76 * 10^6 *30*24*60)/ (1000
*9.81*20*0.90) = 2.6 *10^8m3.
The firm power available is 7.95MW. Therefore the capacity of the
standby unit is 15-7.95=7.05MW.
Solution: FDC and PDC…
Example-4
Compute the minimum reservoir storage required to maintain a demand of
50m3/s monthly river flows to the reservoir is available as follows:
Month Mean flow # of days Monthly flow (m3/s. Cumulative flow
(m3/s) day) (m3/s.day)
Jan 94 31 2914 2914
Feb 82 28 2296 5210
Mar 45 31 1395 6605
Apr 20 30 600 7205
May 26 31 806 8011
Jun 43 30 1290 9301
Jul 90 31 2790 12091
Aug 110 31 3410 15501
Sep 86 30 2580 18081
Oct 70 31 2170 20251
Nov 53 30 1590 21841
Dec 40 31 1240 23081
Example-4
The demand is 50m3/s=50m3/s*# of days in a months for each month. Then
draw a demand line having a slope of 50m3/s*# of days in a month on the
mass curve starting at the peak point. The vertical difference b/n these two
lines give reservoir storage.
As shown on the graph below, two vertical lines CD and EF are drawn. The
maximum of the two is the line EF having a value of 1,982m3/s-day.