G.R. No. 199851, November 07, 2018
G.R. No. 199851, November 07, 2018
DECISION
LEONEN, J.:
The contractor may be solidarily liable with the owner and the subcontractor for any unpaid
obligations to the subcontractor's supplier despite the absence of a contract between the
contractor and supplier. Full payment to the subcontractor, however, serves as a valid defense
against this liability.
This resolves a Petition for Review on Certiorari[2] assailing the Court of Appeals April 28,
2011 Decision[3] and December 7, 2011 Resolution[4] in CA-G.R. CV No. 89300, which affirmed
the Regional Trial Court's finding that Noell Whessoe, Inc. (Noell Whessoe) was solidarily
liable with Liquigaz Philippines Corporation (Liquigaz) and Petrotech Systems, Inc. (Petrotech)
to Independent Testing Consultants, Inc. (Independent Testing Consultants) for unpaid fees of
P1,063,465.70.
Independent Testing Consultants is engaged in the business of conducting non-destructive
testing on the gas pipes and vessels of its industrial customers.[5]
Sometime in June 1998, Petrotech, a subcontractor of Liquigaz, engaged the services of
Independent Testing Consultants to conduct non-destructive testing on Liquigaz's piping
systems and liquefied petroleum gas storage tanks located in Barangay Alas-Asin, Mariveles,
Bataan.[6]
Independent Testing Consultants conducted the agreed tests. It later billed Petrotech, on
separate invoices, the amounts of P474,617.22 and P588,848.48 for its services. However,
despite demand, Petrotech refused to pay.[7]
Independent Testing Consultants filed a Complaint[8] for collection of sum of money with
damages against Petrotech, Liquigaz, and Noell Whessoe for P1,063,465.70 plus legal interest.
It joined Noell Whessoe as a defendant, alleging that it was Liquigaz's contractor that
subcontracted Petrotech.[9]
In its Answer,[10] Liquigaz argued that Independent Testing Consultants had no cause of action
against it since there were no contractual relations between them and that any contract that
Independent Testing Consultants had was with its subcontractors. [11]
Noell Whessoe, on the other hand, denied that it was Liquigaz's contractor and that its basic
role was merely to supervise the construction of its gas plants.[12] It argued that any privity of
contract was only with Petrotech. Thus, it asserted that Petrotech alone should be liable to
Independent Testing Consultants.[13] Noell Whessoe later submitted a Formal Offer of
Documentary Exhibits[14] showing that Liquigaz engaged Whessoe Projects Limited (Whessoe
UK), a limited company organized under the laws of the United Kingdom, for the construction
of its storage facilities.[15] Whessoe UK, in turn, engaged Noell Whessoe, a separate and
distinct entity, to be the construction manager for the Mariveles Terminal Expansion Project.
[16]
The documents further stated that Whessoe UK had already paid in full its contractual
obligations to Petrotech.[17]
For its part, Petrotech alleged that upon Noell Whessoe's approval, Independent Testing
Consultants was chosen to conduct the non-destructive testing on Liquigaz's liquefied
petroleum gas storage vessel under the supervision of OIS, an inspection firm from the United
Kingdom, and of Nick Stephenson (Stephenson).[18] However, it averred that it later received a
letter from Noell Whessoe withdrawing its approval for Independent Testing Consultants'
continued services. Independent Testing Consultants' services allegedly failed to satisfy the
standards set by the OIS and Stephenson.[19] Petrotech further claimed that due to
Independent Testing Consultants' poor performance, it incurred additional costs. Thus, it
prayed that Independent Testing Consultants be ordered to pay the additional costs as actual
damages.[20]
The Regional Trial Court later declared Petrotech in default for failure to appear during the
pre-trial conference.[21]
In its March 7, 2005 Decision,[22] the Regional Trial Court found Liquigaz, Noell Whessoe, and
Petrotech solidarity liable to Independent Testing Consultants. It ruled that Liquigaz was
liable considering that it was the entity which directly benefited from Independent Testing
Consultants' services. It likewise held that Noell Whessoe, as the main contractor of the
project, could not escape liability. Petrotech, as the subcontractor of the project, was also
held liable.[23] The dispositive portion of the Regional Trial Court March 7, 2005 Decision read:
WHEREFORE, premises considered, judgment is hereby rendered in favor of the plaintiff and
against the defendants Liquigaz Philippine Corp., Noell Whessoe, Inc. and Petrotech Systems,
Inc.
1) Ordering all defendants to pay plaintiff jointly and severally the amount of Php 1,063,465.70
plus legal rate of interest from December 1, 1998 until it is fully paid;
2) Ordering the defendants to pay attorney's fees equivalent to 25% of the principal amount of
claim; and, the costs of suit.
SO ORDERED.[24]
Only Noell Whessoe and Liquigaz appealed to the Court of Appeals. [25] Thus, the Regional Trial
Court March 7, 2005 Decision became final as to Petrotech. [26]
In its April 28, 2011 Decision,[27] the Court of Appeals affirmed the Regional Trial Court March
7, 2005 Decision and found that Noell Whessoe, Petrotech, and Liquigaz were liable to
Independent Testing Consultants. It found that Whessoe UK, as contractor, assigned
construction management to Noell Whessoe, effectively stepping into the shoes of Whessoe
UK. Hence, Noell Whessoe could not disclaim knowledge that Petrotech engaged the services
of Independent Testing Consultants, considering its admission that it later sent a letter to
Petrotech withdrawing its approval of the engagement.[28] The Court of Appeals, however, held
that Noell Whessoe's liability did not preclude it from demanding reimbursement from
Petrotech for any amount paid.[29]
The Court of Appeals likewise found that Liquigaz had knowledge, as early as January 1999,
that one of its subcontractors, Petrotech, failed to fulfill its contractual obligations in the
amount of P1,063,465.70 to another subcontractor, Independent Testing Consultants. [30] It
likewise found that Liquigaz still owed Noell Whessoe the amount of US$9,000.00, which it
could have withheld subject to Petrotech's fulfillment of its contractual obligations. Thus,
Liquigaz was liable to Independent Testing Consultants, but only up to the amount of
US$9,000.00, which it could also demand from Petrotech.[31] The dispositive portion of the
Court of Appeals April 28, 2011 Decision read:
WHEREFORE, the instant appeals are PARTLY GRANTED. The Decision of the RTC, Branch
161, Pasig City, dated March 7, 2005, is hereby AFFIRMED with MODIFICATIONS.
1. Defendants WHESSOE and PETROTECH are ordered to pay plaintiff-appellee jointly and
severally the total claim of P1,063,465.70 plus legal rate of interest from December 1, 1998
until it is fully paid. On the other hand, the liability of defendant-appellant LIQUIGAZ, in case it
is required to satisfy the judgment herein, is limited only to the amount of US$9,000.00, or its
peso equivalent at the time of payment, with right of reimbursement from PETROTECH.
SO ORDERED.[32]
Noell Whessoe filed a Motion for Reconsideration, which was denied by the Court of Appeals in
its December 7, 2011 Resolution.[33] Hence, it filed this Petition[34] before this Court.
Petitioner asserts that it should not have been made solidarity liable to respondent
Independent Testing Consultants since it had no privity of contract with the latter. It
maintains that the Contract Agreement for the Mariveles Terminal Expansion Project [35] was
between Liquigaz and Whessoe UK, an entity separate and distinct from petitioner. It likewise
asserts that the Pipework and Mechanical Equipment Installation Subcontract [36] for the
testing and delivery of subcontracting works was between Whessoe UK and Petrotech. It
explained that the Conditions of Contract for Supply of Professional, Technical and
Management Services[37] between Whessoe UK and petitioner was not intended to be a deed
of assignment where petitioner would step into Whessoe UK's shoes as contractor but was
rather merely an undertaking to supply professional, technical, and management services. [38]
Petitioner maintains that it cannot be bound by the contract between Whessoe UK and
Petrotech simply because it sent a letter to Petrotech expressing dissatisfaction or
disapproval of respondent Independent Testing Consultants' services. [39] It likewise points out
that even assuming that there was privity of contract, Whessoe UK had already paid in full its
contractual obligations to Petrotech.[40] Thus, it asserts that it was entitled to moral damages
of P1,000,000.00 since "the filing of this baseless and unfounded case . . . has tarnished its
good business name and standing by giving the erroneous and false impression to the public
that it is a company that reneges on its obligations."[41]
Respondent Independent Testing Consultants, on the other hand, counters that petitioner
directly approved and commissioned its services, as admitted by Petrotech in its Answer
before the Regional Trial Court.[42] It claims that petitioner never introduced evidence that it
had already paid Petrotech, and that its allegation that it was not the same entity being sued
was negated by its Answer before the Regional Trial Court.[43] Thus, respondent argues that
petitioner was not entitled to any of its counterclaims.[44]
From the arguments of the parties, this Court is asked to resolve the issue of whether or not
petitioner Noell Whessoe, Inc. can be held solidarily liable with respondents Liquigaz
Philippines Corporation and Petrotech Systems, Inc. for unpaid fees to respondent
Independent Testing Consultants, Inc. Assuming that petitioner Noell Whessoe, Inc. was not
liable, this Court is further asked to resolve the issue of whether or not it was entitled to moral
damages.
I
To resolve the issue of whether petitioner is solidarily liable with Liquigaz and Petrotech, this
Court must first pass upon petitioner's argument that it is a separate and distinct entity from
Whessoe UK, the signatory of the contracts with them. This, however, is a question of fact.
As a general rule, only questions of law can be raised in a petition for review on certiorari
under Rule 45 of the Rules of Court.[45] The distinction between a question of fact and a
question of law is settled. There is a question of law if the issue can be determined without
reviewing or evaluating the evidence on record. Otherwise, the issue raised is a question of
fact.[46]
Petitioner raises an issue that has already been factually determined by both the Regional
Trial Court and the Court of Appeals. For this Court to pass upon the same issue, it would have
to review and evaluate the evidence presented before the lower courts. Clearly then,
petitioner raises a question of fact.
Appeal is not a matter of right but of sound judicial discretion. [47] This Court may, in its
discretion, entertain questions of fact if they fall under certain exceptions, summarized
in Medina v. Mayor Asistio, Jr. :[48]
(1) When the conclusion is a finding grounded entirely on speculation, surmises or
conjectures; (2) When the inference made is manifestly mistaken, absurd or impossible; (3)
Where there is a grave abuse of discretion; (4) When the judgment is based on a
misapprehension of facts; (5) When the findings of fact are conflicting; (6) When the Court of
Appeals, in making its findings, went beyond the issues of the case and the same is contrary
to the admissions of both appellant and appellee; (7) The findings of the Court of Appeals are
contrary to those of the trial court; (8) When the findings of fact are conclusions without
citation of specific evidence on which they are based; (9) When the facts set forth in the
petition as well as in the petitioners' main and reply briefs are not disputed by the
respondents; and (10) The finding of fact of the Court of Appeals is premised on the supposed
absence of evidence and is contradicted by the evidence on record. [49] (Citations omitted)
Petitioner's assignment of the Court of Appeals' alleged errors centers on the Court of
Appeals' interpretation of the provisions of the Conditions of Contract for Supply of
Professional, Technical and Management Services,[50] and the Letter[51] dated June 29, 1998.
Therefore, it alleges that the Court of Appeals' judgment was based on a misapprehension of
facts. Any review requires a reevaluation of these two (2) documents mentioned.
The presence of any of the exceptions to the general rule, however, does not automatically
place the case under this Court's review. This Court explained in Pascual v. Burgos[52] that
the party claiming an exception "must demonstrate and prove"[53] that a review of the factual
findings is necessary.
Petitioner has not alleged that it raised a question of fact, much less allege that this case falls
under any of the exceptions. This would have merited the denial of the Petition since this
Court is not a trier of facts. Petitioner, however, argues that this case falls under the
considerations stated in Rule 45, Section 6 of the Rules of Court:
Section 6. Review discretionary. — A review is not a matter of right, but of sound judicial
discretion, and will be granted only when there are special and important reasons therefor.
The following, while neither controlling nor fully measuring the court's discretion, indicate the
character of the reasons which will be considered:
(a) When the court a quo has decided a question of substance, not theretofore determined by
the Supreme Court, or has decided it in a way probably not in accord with law or with the
applicable decisions of the Supreme Court; or
(b) When the court a quo has so far departed from the accepted and usual course of judicial
proceedings, or so far sanctioned such departure by a lower court, as to call for an exercise of
the power of supervision.
In particular, petitioner alleges that:
a. The Court of Appeals has so far departed from the accepted and usual course of judicial
proceedings and/or has decided a question of substance in a way not in accord with law or
with the applicable decisions of the Honorable Court when it held that petitioner Noell
Whessoe is solidarity liable with respondent Petrotech for the claims for respondent ITCI.
b. The Court of Appeals has so far departed from the accepted and usual course of judicial
proceedings and/or has decided a question of substance in a way not in accord with law or
with the applicable decisions of the Honorable Court when it denied petitioner Noell
Whessoe's counterclaims.[54]
A quick perusal of the parties' evidence reveals that the Regional Trial Court and the Court of
Appeals may have erred in finding that petitioner was still liable to respondent Independent
Testing Consultants for its unpaid fees. If not corrected, the assailed judgments may result in
grave injustice to petitioner.
II
"[A] contract is law between the parties[.]"[55] Generally, contracts only take effect between
the parties, and their assigns and heirs.[56] Thus, subject to certain exceptions,[57] those not
privy to the contract would not be bound by any of its provisions.
Petitioner contends that all contracts between the parties were undertaken by Whessoe UK,
an entity that it alleges is separate and distinct from itself.
Both the Regional Trial Court and the Court of Appeals rejected this argument on the ground
that petitioner's co-defendants, Liquigaz and Petrotech, alleged that petitioner was the
contracting party. Liquigaz's Answer read, in part:
5. On November 7, 1996, defendant Liquigaz and defendant Whessoe entered into a Design and
Construction Contract ("contract") for the construction of a storage facility for liqu[e]fied
petroleum gas located in Mariveles, Bataan. Under the contract, defendant Whessoe
undertook to complete the design and execute and complete the construction of the storage
facility.
6. Under the contract, defendant Whessoe could subcontract the performance of any of its
obligation as it deemed expedient. Thus, it subcontracted majority of the project work to
several local subcontractors. One such subcontractor was defendant Petrotech. Defendant
Petrotech was responsible for the fabrication of vessels and piping. Its work included
conducting various non-destructive testing ("NDT"), which in turn defendant Petrotech
subcontracted to several NDT firms. Apparently, plaintiff was one such NDT firm. [58]
Petrotech, on the other hand, alleged:
4. From December 5, 1997 to February 24, 1999, herein defendant Petrotech Systems
Corporation (hereinafter Petrotech) became a sub-contractor of defendant Noell Whessoe
(hereinafter Whessoe) in the latter's project for defendant Liquigaz Philippines Corporation
(hereinafter Liquigaz); part of the conditions of the contract that Petrotech has is that all
works must pass Non-destructive Testing (hereinafter NDT) by an independent third party
before said works can be accepted by Whessoe[.][59]
To determine whether the Regional Trial Court and the Court of Appeals correctly held that
petitioner is the same entity as Whessoe UK, further examination of the evidence is
necessary.
The Contract Agreement for the Mariveles Terminal Expansion Project [60] dated November 7,
1996 was between Liquigaz and Whessoe UK, thus:
THIS AGREEMENT is made [on] the 7th day of November, 1996
Between LIQUIGAZ PHILIPPINES CORPORATION
a) Divulge to any other party any matter or thing arising from the performance of the
SUBCONTRACT at any time except as may be necessary to assist either CONTRACTOR or
SUBCONTRACTOR in their assessment, and then only in the event that the third party
enters into a similar Confidentiality Agreement or
....
In witness hereof the parties have caused this Confidentiality Agreement to be signed by the
parties['] behalf.[64]
As of April 12, 1997, petitioner referred to itself as a "wholly owned subsidiary" of Whessoe
UK. It alleged, however, that on June 5, 1997, it was registered with the Securities and
Exchange Commission as a domestic corporation engaged in general construction and other
allied businesses.[65] Unfortunately, no evidence was presented to prove that it was
incorporated as a separate corporation by June 5, 1997. It instead filed on August 24, 1998 its
Amendment of Articles of Incorporation.[66]
Petitioner contends that it was already a separate and distinct entity since it had to execute a
Conditions of Contract for Supply of Professional, Technical and Management Services [67] on
November 29, 1997 with Whessoe UK for the Mariveles Terminal Expansion Project. Pertinent
portions of this contract provided:
THIS AGREEMENT is made on the 29 day of November 1997 between WHESSOE PROJECTS
LIMITED whose registered office is at Brinkburn Road, Darlington, Durham, England,
hereinafter called the "Employer" of the one part and Noell Whessoe Philippines Construction
Incorporated whose registered office is at Unit 2409, Herrera Tower, 98 Herrera corner Valero
St., North Salcedo Village[,] Makati City, Philippines, hereinafter called the "Contractor" of the
other part.
WHEREAS, the Employer assign to the Contractor the construction management of the
Mariveles Terminal Expansion Project located at Barangay Alas-asin, Mariveles, Bataan.
Article The Contractor will, subject to the conditions of the Contract, perform and complete the
1 Works.
Article The Employer will pay the Contractor such cost or costs expended in relation to the
2 Works on a cost reimbursable basis plus a ten (10) percent mark-up.
....
1.2 The "Work" means any and all services rendered by the Contractor in relation to the
construction and successful completion of the Mariveles Terminal Expansion Project.
Such services shall include but not be limited to the:
....
2.3 The Contractor shall be responsible for the timely and successful completion of the
Project.[68]
Petitioner argues that the execution of this contract did not make it the contractor for the
Mariveles Terminal Expansion Project. It asserts that it was merely a subcontractor hired by
Whessoe UK to oversee the management of the site and the other subcontractors' activities.
Records, however, show that during the negotiations for the Pipework and Mechanical
Equipment Installation Subcontract with Petrotech, Petrotech made no distinction between
petitioner and Whessoe UK.
On April 24, 1997, Whessoe UK sent a Facsimile Message[69] to Petrotech on its Tender.
Petrotech replied on April 28, 1997 to petitioner with its comments. [70] On April 30, 1997,
Whessoe UK sent another message discussing the terms of the Quotation. [71] Petrotech
replied on May 13, 1997 to petitioner, negotiating the subcontract price. [72] Whessoe UK
replied on July 1, 1997 with a counter-offer.[73] Petrotech again addressed its reply to
petitioner on July 2, 1997, submitting its Tender Form.[74]
In the letter[75] dated June 27, 1998, petitioner informed Petrotech that it was withdrawing its
approval of the subcontract. This letter stated, in part:
We confirm our withdrawal of approval to your employment of Intec as your MPI-NDT Sub-
contractor with effect from today, 27th June, 1998, for which we served warnings to Mr.
McGrane over seven (7) days ago.
We additionally confirm having received Mr. McGrane's concurrence with this measure, and
your undertaking to employ a new service subcontractor for the remaining work still to be
performed, with effect from Monday, 29th June, 1998.
We also wish to confirm to you that since our engagement of the U.K. inspection firm, O.I.S., to
supervise and manage your NDT obligations, such of Mr. Mick Stephenson's time has been
rendered abortive by Intec's ap[p]arent inability to react qualifiedly to his instructions, which
have not in any manner been onerous, resulting in an unacceptably high level of reboots and
poor quality Radiographs that have been impossible to interpret and rejected because of
density, limits, film marks, debris etc.
Whilst it was at our own cost, and of necessity to the project that we arranged for O.I.S.'s
services, these costs have escalated unreasonably due to Intec's intransigence.
We therefore feel compelled to onpass (sic) to your account our assessment of the abortive
costs based upon a Re-shoot factor of 32.6% of the total of 414 radiographs inspected.
To date this amounts to 52.6% of 720 hours @ $ 72.50/Hours = $17,017.20 and continuing,
dependent upon the degree of improvement that you are able to motivate from Intec's
replacement. Otherwise, it is indicated that your responsibility] for continuing extra costs will
increase by a further $ 8,200.00 for O.I.S. charges to us.[76]
This letter did not state that Whessoe UK, through petitioner, was withdrawing approval. It
states that petitioner was withdrawing approval. Petrotech was not privy to the Contract for
Supply of Professional, Technical and Management Services between Whessoe UK and
petitioner. It was only bound by its contract with Whessoe UK. Petitioner's withdrawal of
approval would not have bound Petrotech.
Considering that Petrotech abided by petitioner's instructions, it did not consider petitioner
and Whessoe UK as two (2) separate and distinct entities.
This Court made the same conclusion in Pioneer International v. Hon. Guadiz.[77] Although the
issue in that case was on jurisdiction, this Court made a similar examination of the
communications between the parties to determine whether several corporations were
separate and distinct entities:
PIL's alleged acts in actively negotiating to employ Todaro to run its pre-mixed concrete
operations in the Philippines, which acts are hypothetically admitted in PIL's motion to
dismiss, are not mere acts of a passive investor in a domestic corporation. Such are
managerial and operational acts in directing and establishing commercial operations in the
Philippines. The annexes that Todaro attached to his complaint give us an idea on the extent
of PIL's involvement in the negotiations regarding Todaro's employment. In Annex "E,"
McDonald of Pioneer Concrete Group HK confirmed his offer to engage Todaro as a consultant
of PIL. In Annex "F," Todaro accepted the consultancy. In Annex "H," Klepzig of PPHI stated
that PIL authorized him to tell Todaro about the cessation of his consultancy. Finally, in Annex
"I," Folwell of PIL wrote to Todaro to confirm that "Pioneer" no longer wishes to be associated
with Todaro and that Klepzig is authorized to terminate this association. Folwell further
referred to a Dr. Schubert and to Pioneer Hong Kong. These confirmations and references tell
us that, in this instance, the various officers and companies under the Pioneer brand name do
not work independently of each other. It cannot be denied that PIL had knowledge of and even
authorized the non-implementation of Todaro's alleged permanent employment. In fact, in the
letters to Todaro, the word "Pioneer" was used to refer not just to PIL alone but also to all
corporations negotiating with Todaro under the Pioneer name.
As further proof of the interconnection of the various Pioneer corporations with regard to their
negotiations with Todaro, McDonald of Pioneer Concrete Group HK confirmed Todaro's
engagement as consultant of PIL (Annex "E") while Folwell of PIL stated that Todaro rendered
consultancy services to Pioneer HK (Annex "I"). In this sense, the various Pioneer
corporations were not acting as separate corporations. The behavior of the various Pioneer
corporations shoots down their defense that the corporations have separate and distinct
personalities, managements, and operations. The various Pioneer corporations were all
working in concert to negotiate an employment contract between Todaro and PPHI, a
domestic corporation.[78] (Emphasis supplied)
In their respective Answers, Liquigaz and Petrotech referred to both Whessoe UK and
petitioner when they used "Whessoe." Neither party was aware that Whessoe UK and
petitioner held themselves as separate and distinct entities.
Petitioner cannot also be considered as a mere subcontractor of Whessoe UK. The Contract
Agreement for the Mariveles Terminal Expansion Project between Liquigaz and Whessoe UK
provided:
10.1 Neither the Purchaser nor the Contractor shall without the previous consent of the other
transfer any benefit or obligation under the Contract to any other person in whole or in part,
save that the Contractor may without such consent assign absolutely or by way of charge
any money which is or may become due to him under the Contract.
10.2 Subject to the provisions of Clause 11 (Nominated Subcontractors) the Contractor may
subcontract the performance of any of his obligations under the Contract as the Contractor
considers expedient with the exception of any limitations on subcontracting as defined in
Schedule 12 (Limitations on Subcontracting).
10.4 The Contractor shall not subcontract the whole of the Works.[79] (Emphasis supplied)
Under this Contract, Whessoe UK may subcontract the performance of some obligations but
was prohibited from subcontracting "the whole of the Works." On the other hand, the Contract
for Supply of Professional, Technical and Management Services between petitioner and
Whessoe UK stated that petitioner would provide the following services:
1.2 The "Work" means any and all services rendered by the Contractor in relation to the
construction and successful completion of the Mariveles Terminal Expansion Project. Such
services shall include but not be limited to the:
2.3 The Contractor shall be responsible for the timely and successful completion of the Project.
[80]
All of Whessoe UK's responsibilities as contractor for Liquigaz were passed on to petitioner,
despite Liquigaz's stipulation that Whessoe UK could not subcontract all of its work to a
subcontractor. Considering this stipulation, petitioner cannot be considered as a mere
subcontractor of Whessoe UK. Otherwise, Whessoe UK would be in breach of its Contract with
Liquigaz.
There was insufficient evidence proving that Whessoe UK and petitioner were two (2)
separate and distinct entities. As with Pioneer International, prior acts by Liquigaz and
Petrotech indicate that they were contracting with the same entity, albeit with different
names. Thus, petitioner failed to prove that for the Mariveles Terminal Expansion Project, it
was a separate and distinct entity from Whessoe UK. Therefore, it cannot set up the defense
of privity of contract to escape liability.
Article 1729 of the Civil Code provides:
Article 1729. Those who put their labor upon or furnish materials for a piece of work
undertaken by the contractor have an action against the owner up to the amount owing from
the latter to the contractor at the time the claim is made. However, the following shall not
prejudice the laborers, employees and furnishers of materials:
1. Payments made by the owner to the contractor before they are due;
2. Renunciation by the contractor of any amount due him from the owner.
In JL Investment and Development, Inc. v. Tendon Philippines, Inc .,[81] this Court explained
that Article 1729 of the Civil Code is an exception to the general rule on the privity of
contracts:[82]
This provision imposes a direct liability on an owner of a piece of work in favor of suppliers of
materials (and laborers) hired by the contractor "up to the amount owing from the [owner] to
the contractor at the time the claim is made." Thus, to this extent, the owner's liability is
solidary with the contractor, if both are sued together. By creating a constructive vinculum
between suppliers of materials (and laborers), on the one hand, and the owner of a piece of
work, on the other hand, as an exception to the rule on privity of contracts, Article 1729
protects suppliers of materials (and laborers) from unscrupulous contractors and possible
connivance between owners and contractors. As the Court of Appeals correctly ruled, the
supplier's cause of action under this provision, reckoned from the time of judicial or extra-
judicial demand, subsists so long as any amount remains owing from the owner to the
contractor. Only full payment of the agreed contract price serves as a defense against the
supplier's claim.[83] (Emphasis supplied)
Article 1729 talks of three (3) different parties: the owner, the contractor, and the supplier. In
certain situations, the supplier may also be referred to as a subcontractor to provide materials
or services. There are also situations where, as in this case, the subcontractor further
subcontracts some materials and services to another subcontractor. This sub-subcontractor
would be considered the supplier of materials and services. In this case, the owner is
Liquigaz, the contractor is petitioner, the subcontractor is Petrotech, and the supplier/sub-
subcontractor is respondent Independent Testing Consultants.
Considering that the rationale behind the provision is to protect suppliers from possible
connivance between the owners and the contractors, there would be no reason to apply the
same rationale when it was the subcontractor that hired the supplier. The liability will extend
from the owner to the contractor to the subcontractor.
Under Article 1729, respondent Independent Testing Consultants had a cause of action
against Liquigaz and petitioner, even if its contract was only with Petrotech. The Regional
Trial Court and the Court of Appeals, therefore, did not err in concluding that petitioner was
solidarily liable with Liquigaz and Petrotech for unpaid fees to respondent Independent
Testing Consultants.
Article 1729 creates a solidary liability between the owner, the contractor, and the
subcontractor. A solidary obligation is "one in which each debtor is liable for the entire
obligation, and each creditor is entitled to demand the whole obligation." [84] Respondent
Independent Testing Consultants may demand payment for all of its unpaid fees from Liquigaz,
petitioner, or Petrotech, even if its contract was only with the latter.
However, Article 1729, while serving as an exception to the general rule on the privity of
contracts, likewise provides for an exception to this exception. The contractor is solidarily
liable with the owner and subcontractor for any liabilities against a supplier despite the
absence of contract between the contractor and the supplier, except when the subcontractor
has already been fully paid for its services.
Here, the Court of Appeals found that there was "uncontroverted evidence that PETROTECH
had already been paid for its services:"[85]
MR. JOHN TATE, President of [petitioner] and former Managing Director of WHESSOE-UK,
testified in open court affirming the existence of the Agreement (Exhibit "7" - Whessoe)
between PETROTECH and WHESSOE-UK indicating the schedule of payment of the remaining
balance in the amount of US$283,436.42, as well as two (2) Barclays International Payments
Service Customer Order Forms (Exhibits "8" and "9" - Whessoe) evidencing payment in the
amounts of US$125,000.00 and US$158,436.42, respectively, that was coursed through the
account of PETROTECH with China Banking Corporation in the Philippines. [86]
Since Whessoe UK and petitioner should be considered the same entity for the purposes of the
Mariveles Terminal Expansion Project, Whessoe UK's full payment to Petrotech would serve as
a valid defense against petitioner's solidary liability. Thus, petitioner still cannot be held
solidarily liable with Liquigaz and Petrotech for any remaining receivables from respondent
Independent Testing Consultants. Any remaining obligations to it should be solidarily borne by
the owner, Liquigaz, and the subcontractor, Petrotech.
III
While petitioner is absolved from its solidary liability, it is not, however, entitled to any moral
damages.
Petitioner asserts that it was entitled to moral damages of P1,000,000.00 on the basis that
respondent Independent Testing Consultants' collection suit "has tarnished its good business
name and standing[.]"[87]
Moral damages are awarded when the claimant suffers "physical suffering, mental anguish,
fright, serious anxiety, besmirched reputation, wounded feelings, moral shock, social
humiliation, and similar injury."[88] "These damages must be understood to be in the concept of
grants, not punitive or corrective in nature, calculated to compensate the claimant for the
injury suffered."[89] Its award is "aimed at a restoration, within the limits possible, of the
spiritual status quo ante; and therefore, it must be proportionate to the suffering inflicted." [90]
A corporation is not a natural person. It is a creation of legal fiction and "has no feelings[,] no
emotions, no senses[.]"[91] A corporation is incapable of fright, anxiety, shock, humiliation, and
physical or mental suffering. "Mental suffering can be experienced only by one having a
nervous system and it flows from real ills, sorrows, and griefs of life[.]" [92] A corporation, not
having a nervous system or a human body, does not experience physical suffering, mental
anguish, embarrassment, or wounded feelings. Thus, a corporation cannot be awarded moral
damages.
In the 1968 case of Mambulao Lumber v. Philippine National Bank,[93] this Court stated, in
passing, "[a] corporation may have a good reputation which, if besmirched, may also be a
ground for the award of moral damages."[94]
This same statement has appeared in People v. Manero.[95] Mambulao Lumber and Manero,
however, were not meant to be used as basis to carve an exception to the rule. There is still
no definitive pronouncement by this Court of any existing exceptions to the rule. In ABS-CBN
Broadcasting Corporation v. Court of Appeals,[96] this Court even clarified that the statement
in Mambulao Lumber and Manero was mere obiter dictum.
There is no standing doctrine that corporations are, as a matter of right, entitled to moral
damages. The existing rule is that moral damages are not awarded to a corporation since it is
incapable of feelings or mental anguish. Exceptions, if any, only apply pro hac vice.
Even assuming that moral damages may be granted, no moral damages can be awarded in this
case. Claims for moral damages must have sufficient factual basis, either in the evidence
presented or in the factual findings of the lower courts.[97] Petitioner has not presented any
evidence, other than its bare allegations, that it was entitled to its award.
WHEREFORE, the Petition is PARTIALLY GRANTED. The Court of Appeals April 28, 2011
Decision and December 7, 2011 Resolution in CA-G.R. CV No. 89300 are AFFIRMED WITH
MODIFICATION.
Petitioner Noell Whessoe, Inc. is ABSOLVED from solidary liability with respondents
Petrotech Systems, Inc. and Liquigaz Philippines Corporation to respondent Independent
Testing Consultants, Inc. in view of its full payment to Petrotech Systems, Inc. Petitioner Noell
Whessoe, Inc.'s claim for moral damages is DENIED for lack of factual basis.
All other previous dispositions by the Court of Appeals STAND.
SO ORDERED.
Peralta (Chairperson) and Hernando, JJ., concur.
Gesmundo and J. Reyes, Jr., JJ., on wellness leave.
January 4, 2019
NOTICE OF JUDGMENT
Sirs / Mesdames:
Please take notice that on November 7, 2018 a Decision, copy attached hereto, was rendered
by the Supreme Court in the above-entitled case, the original of which was received by this
Office on January 4, 2019 at 2:05 p.m.
Very truly yours,
(SGD.) WILFREDO V.
LAPITAN
Division Clerk of Court