28asce 29GM.1943-5622.0001574
28asce 29GM.1943-5622.0001574
Abstract: Rockbursts are a common form of disaster that occur during the construction of deep tunnels in hard rock. This is especially the
case in the breakthrough stage of excavation, when even more attention should be paid to the risk of rockburst in order to ensure construction
safety. This work studied the characteristics of the microseismicity associated with 10 breakthrough cases in the deep tunnels (maximal depth
2,525 m) of the Jinping-II Hydropower Station in China. The results showed that the microseismicity was relatively more active in the
breakthrough period (compared with that in adjacent sections) due to the effect of working two faces in tandem and was concentrated
in the breakthrough section. Furthermore, the characteristic c-value associated with the seismic energy–potency relationship was larger,
indicating that the apparent stress was greater in the breakthrough section. Spatiotemporal changes in microseismicity that are associated
with rockburst development were found in the breakthrough section which can be used to qualitatively warn of the risk of rockburst.
Rockburst risk can be quantitatively assessed during tunnel breakthrough based on the monitored microseismicity and a quantitative method
of rockburst warning. Based on results thus obtained, the rockburst risk in the breakthrough section was found to increase continuously as the
distance between the two working faces decreased. When both working faces are excavated in the breakthrough section, the quantitative risk
of rockburst increases significantly. However, when only one working face is in action, the quantitative risk of rockburst increases only
slightly. The results of this work will be helpful in warning of impending rockbursts, and thus improving the safety of the construction
process, when breakthrough is carried out in deep tunnels excavated in hard rock. DOI: 10.1061/(ASCE)GM.1943-5622.0001574.
© 2019 American Society of Civil Engineers.
Author keywords: Tunnel; Breakthrough; Rockburst; Microseismicity; Jinping-II Hydropower Station.
Introduction
1
Associate Professor, State Key Laboratory of Geomechanics and
Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese
To speed the construction process, a multiface construction strategy
Academy of Sciences, Wuhan 430071, PR China (corresponding author). often is adopted in the excavation of long tunnels. Therefore, sit-
ORCID: https://orcid.org/0000-0001-9231-0732. Email: glfeng@whrsm uations will be encountered in which two opposing working faces
.ac.cn are simultaneously excavated to the point at which breakthrough is
2
Professor, State Key Laboratory of Geomechanics and Geotechnical achieved. When this happens in deep tunnels that pass through hard
Engineering, Institute of Rock and Soil Mechanics, Chinese Academy rock, the potential risk of a rockburst occurring is particularly sig-
of Sciences, Wuhan 430071, PR China; Professor, Key Laboratory of nificant. A rockburst is a sudden, and usually violent, collapse of
Ministry of Education on Safe Mining of Deep Metal Mines, Northeastern
rock under stress, and such events also lead to the occurrence of
Univ., Shenyang, Liaoning 110819, PR China. Email: fengxiating@
mail.neu.edu.cn accompanying seismic events (Hedley 1992; Kaiser et al. 1996).
3
Professor, State Key Laboratory of Geomechanics and Geotechnical Close to the point of breakthrough in deep, hard tunnels, the rock
Engineering, Institute of Rock and Soil Mechanics, Chinese Academy between the two working faces is simultaneously affected by the
of Sciences, Wuhan 430071, PR China. Email: [email protected] work being carried out on the two opposing working faces. Energy
4
Associate Professor, State Key Laboratory of Geomechanics and changes in the rockmass of the breakthrough section therefore is
Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese more intense. In addition, because there are two free surfaces
Academy of Sciences, Wuhan 430071, PR China. Email: yxxiao@ (i.e., the two working faces) to contend with in the breakthrough
whrsm.ac.cn
5
Lecturer, School of Highway, Chang’an Univ., Xi’an, Shanxi 710064,
section, energy release and deformation can occur in more direc-
PR China. Email: [email protected] tions than when a single working face is involved. As a result, the
6
Ph.D. Student, Key Laboratory of Ministry of Education on Safe stability of the rockmass can be expected to be poorer and the risk
Mining of Deep Metal Mines, Northeastern Univ., Shenyang, Liaoning of rockburst higher. Therefore, even more attention should be paid
110819, PR China. Email: [email protected] to the risk of a rockburst occurring during the breakthrough period
7
Ph.D. Student, Key Laboratory of Ministry of Education on Safe in deep tunnels passing through hard rock.
Mining of Deep Metal Mines, Northeastern Univ., Shenyang, Liaoning Microseismic (MS) monitoring techniques involving the three-
110819, PR China. Email: [email protected]
dimensional monitoring of MS events produced by the microcrack-
Note. This manuscript was submitted on March 16, 2019; approved
on July 11, 2019; published online on December 6, 2019. Discussion ing of rocks have been widely used around the world for many
period open until May 6, 2020; separate discussions must be submitted years to monitor and investigate rockbursts, with different degrees
for individual papers. This paper is part of the International Journal of of success (Mendecki 1993, 1997; Poplawski 1997; Becka and
Geomechanics, © ASCE, ISSN 1532-3641. Brady 2002; Li et al. 2007; Kaiser 2009; Trifu and Suorineni 2009;
and fracture states of the rock masses present. Using this informa- helpful in warning of impending rockbursts in future deep, hard
tion, a warning can be issued if the risk of an impending rockburst rock excavations, and in improving construction safety during
is high. A good example of the application of this technique is breakthrough.
the deep tunnels of the Jinping-II Hydropower Station in China
(Feng et al. 2015c). The excavations required to construct this
particular hydropower station involved seven parallel tunnels with Engineering and MS Monitoring Tests: Overview
a mean length of 16.7 km. They lie at great depth and pass through
hard rockmasses, so rockbursts of varying intensity were frequent The Jinping-II Hydropower Station is located on the Yalong River,
during the construction work. Therefore, MS activity was moni- Sichuan Province, in southwestern China. The project was
tored continuously during a part of the Jinping-II excavation project described in detail by Shan and Yan (2010) and Zhang et al.
and warnings were issued about impending rockbursts, which (2012). The geological cross section of the MS-monitored tunnels
significantly reduced the number of casualties suffered. The con- is illustrated in Fig. 1. There are many branch tunnels, some of
struction schedules of the tunnels thus were ensured and the safety which were excavated collaboratively to accelerate the construc-
of the workers somewhat improved. The technique thus proved tion process. Therefore, there were many situations in which
Fig. 1. Geological cross section along the monitored tunnels and distribution of the 10 breakthrough points (1-1, 2-1, 3-1, 3-2, 3-3, 4-1, 4-2, 4-3, P-1,
and P-2). A-#1, A-#2, and A-#3 are branches that were used to accelerate the construction of the headrace and drainage tunnels.
Microseismicity Characteristics
Table 2. Basic mechanical parameters of rockmass
Downloaded from ascelibrary.org by University of Western Ontario on 12/11/19. Copyright ASCE. For personal use only; all rights reserved.
(a) (b)
Fig. 3. Simulation results showing the elastic energy distribution after excavation for (a) Headrace tunnel 1; and (b) the drainage tunnel.
-4.00 -4.00
-3.56 -3.56
-3.11 -3.11
-2.67 -2.67
-2.22 -2.22
-1.78 -1.78
-1.33 -1.33
-0.89 -0.89
-0.44 -0.44
0.00 0.00
Downloaded from ascelibrary.org by University of Western Ontario on 12/11/19. Copyright ASCE. For personal use only; all rights reserved.
(a) (b)
Fig. 4. Spatial distribution of the MS activity in the breakthrough and adjacent sections for (a) the headrace tunnels; and (b) the drainage tunnel.
A sphere’s size represents the energy of the MS event (the larger the sphere, the greater was the energy released).
(a) (b)
Fig. 5. Cloud diagrams (nephograms) showing the spatial distribution density of the MS events in the breakthrough and adjacent sections for (a) the
headrace tunnels; and (b) the drainage tunnel.
respectively. In Fig. 7, most of the curves are higher in the middle However, although the microseismicity in the breakthrough
and lower at both ends. This is a clear indication of the greater level section tends to be more active than in the adjacent sections, it does
of MS activity in the section influenced by breakthrough (compared not always have to be a highly active MS section. For example,
with those that were not). in breakthrough Cases 1-1, 3-4, and 4-3, the microseismicity (num-
ber of MS events, MS energy, and MS apparent volume) was
smaller than that corresponding to the mean levels. At the same
time, there was some variation between cases, so some difference
in the microseismicity occurred in the various cases. This is illus-
trated by the cumulative number of events, energy, and apparent
volume, which ranged from 1 to 31, from 102.6 to 105.9 J, and from
1.1 to 61,660 m3 , respectively. Because microseismicity is related
to rockburst risk, this means that the rockburst risk in different
breakthrough sections is different, and thus these sections are not
always high rockburst risk regions.
(a) (b)
(c)
Fig. 7. Microseismicity in the different sections of the 10 breakthrough cases showing: (a) the number of MS events; (b) MS energy; and
(c) MS apparent volume.
can be made by determining the correlation between energy (E) case (4-2), there was no rockburst occurrence in the breakthrough
and potency (P). This so-called E–P correlation was investigated section.
and described by Mendecki (1993) and Amidzic (2005). Normally, Fig. 9 illustrates the spatiotemporal evolution of the microseis-
for a specific temporal and spatial domain, E and P are correlated in micity associated with the intense rockburst that occurred in
a way best revealed via a log–log plot [i.e., they obey the relation- Case P-1. On this occasion (1) a large number of MS events oc-
ship in Eq. (4) in section “Engineering and MS Monitoring Tests: curred that were spatially clustered together in the breakthrough
Overview”]. The fitting constants derived from such correlation section [Fig. 9(b)]; (2) before the rockburst occurred, the cumula-
plots [specifically, the value of c in Eq. (4)] yield a useful parameter tive number of MS events and amount of MS energy released in-
that can be used to analyze the apparent stress level. That is, a large creased heavily [Fig. 9(c)]; and (3) the Schmidt number decreased
c-value corresponds to a high apparent stress. sharply prior to rockburst and the cumulative apparent volume in-
Fig. 8 presents log–log plots of energy versus potency for the creased abruptly at the same time [Fig. 9(d)]. The Schmidt number
MS events recorded in the different sections studied. There were measures the spatiotemporal complexity of the seismic flow of the
good linear correlations between log E and log P in each section. rock—the lower the Schmidt number, the less stable is the flow and
The equations representing the linear fits to the data also are given the stronger is the microseismicity (Mendecki 1997). This case
in Fig. 8, which therefore specify the corresponding c-values. should be compared with Case 4-2, wherein breakthrough occurred
Clearly, the c-values for the left and right sections both were without rockburst and the microseismicity was relatively much qui-
smaller than that for the breakthrough section. This implies that eter. Fig. 10 presents a similar set of figures to those shown in Fig. 9.
when the two working faces interact (in the breakthrough section), Because no rockburst occurred during breakthrough in Case 4-2,
the apparent stress and stress decrease are enhanced. This variation the resulting tunnel had good integrity and shape [Fig. 10(a)]. Only
is why the microseismicity is more active in the breakthrough a few MS events occurred in the breakthrough section, so the spatial
section. distribution was relatively sparse [Fig. 10(b)]. The cumulative num-
ber of MS events and cumulative MS energy released increased
gently with time and there was only a small jump in these quantities
Microseismicity Changes during Rockburst just before breakthrough [Fig. 10(c)]. The Schmidt number de-
Development in Breakthrough Section creased sharply but the cumulative apparent volume increased only
slightly [Fig. 10(d)].
This section concentrates on two cases. In one case (P-1), there The preceding comparison shows that the microseismicity is
was an intense rockburst in the breakthrough section; in the other correlated with the region in which the rockburst occurs; rockbursts
(c)
Fig. 8. Log–log plots of energy (E) versus potency (P) for the MS events occurring in three different regions: (a) left sections; (b) breakthrough
sections; and (c) right sections.
Local Magnitude
-4.00
-3.56
-3.11
-2.67
-2.22
-1.78
-1.33
-0.89
-0.44
0.00
(a) (b)
(c) (d)
Fig. 9. Data relating to the intense rockburst that occurred during breakthrough Case P-1: (a) photograph of rockburst area; (b) spatial distribution of
microseismicity in the rockburst area, in which a sphere’s size represents the energy of the MS event (the larger the sphere, the was greater the energy
released); (c) temporal variation in the number of MS events and energy released; and (d) the temporal change in Schmidt number and apparent
volume.
(a) (b)
Downloaded from ascelibrary.org by University of Western Ontario on 12/11/19. Copyright ASCE. For personal use only; all rights reserved.
(c) (d)
Fig. 10. Comparable diagrams to those in Fig. 9 for breakthrough Case 4-2 (no rockburst): (a) photograph of the tunnel highlighting its good physical
condition; (b) spatial distribution of the microseismicity, showing its quiet nature, in which a sphere’s size represents the energy of the MS event
(the larger the sphere, the greater was the energy released); (c) temporal variation in the number of MS events and energy released; and
(d) corresponding change in Schmidt number and apparent volume.
are more likely to occur in regions of high microseismicity. More- the jth MS parameter. The probability value for each rockburst in-
over, the way the microseismicity changes in breakthrough sections tensity type ranges from 0% to 100% (naturally, the greater the
with and without rockbursts is quite different. Therefore, we can probability, the greater is the rockburst risk). The sum of the
qualitatively warn of the potential risk of rockburst based on the probabilities of rockbursts of all intensity types is 100%.
different microseismicity changes outlined previously. During the breakthrough periods, the method was used to quan-
titatively and dynamically warn of the potential occurrence of rock-
burst in the breakthrough sections. Daily risk assessments were made
Quantitative and Dynamic Rockburst Warning in and released to support the safety of the construction process. Figs. 11
Breakthrough Section and 12 present the results obtained for the two breakthrough cases
discussed previously (P-1 and 4-2). The results showed that
Feng et al. (2015c) devised a method to quantitatively and dynami- 1. The calculated rockburst risks changed continually as excava-
cally warn of the risk of a rockburst occurring in deep tunnels tion proceeded in both cases. As the distance between the
based on microseismicity. The method established a quantitative two working faces became smaller, the potential risk of rock-
relationship between rockburst risk and microseismicity, and it burst increased continuously. The risk changes were significant
was eventually used to form a quantitative formula for rockburst and rockburst risk increased rapidly when the two working faces
warning in the deep tunnels of Jinping-II were very close or about to break through.
2. In Case P-1, the rockburst risk in the breakthrough section was
X
n
Pi ¼ wj Pji ð5Þ high when the distance between the two working faces was less
j¼1 than 44 m [Fig. 11(a)]. On January 22, when the distance be-
tween the two faces was 44 m, there was a 54.3% probability of
where i = intensity of rockburst (i.e., extremely intense, intense, a moderate rockburst risk. As the two working faces continued
moderate, slight, or none); and Pi = probability that rockburst to move forward, the rockburst risk increased to an intense level
occurs with intensity i. The summation extends over n MS on January 24 (with 23 m between the two working faces).
parameters which are labeled with the index j. The functional cor- The risk of an intense (moderate) rockburst occurring on that
relation between the occurrence of a rockburst of intensity i and day was 66.2% (33.5%). Two days later, on January 26, the risk
MS parameter j is Pji , and wj is a weighting coefficient for of an intense rockburst occurring increased to 71.2%, and an
(a) (b)
Fig. 11. Variation in the probability that a rockburst of given intensity will occur in the days leading up to breakthrough for (a) Case P-1
(intense rockburst); and (b) Case 4-2 (no rockburst).
intense rockburst occurred on that day. The quantitative rock- was halted (so the chainages of the working faces were the same
burst warning result therefore was in good agreement with the on the next day). As a result, on the following day (January 25), the
actual situation in the tunnel. risk of an intense rockburst increased only slightly, to 69.5%. On
3. In Case 4-2, the rockburst risk in the breakthrough section January 25, excavation was resumed on one face only (the left).
remained low throughout the overall construction period That is, the workers changed from two-directional to single-
[Fig. 11(b)]. This reflected well the actual situation in the tunnel, directional excavation in an attempt to reduce the disturbance to
because no rockburst occurred at this site. From September 19 to the surrounding rockmass. Once again, no rockburst occurred. On
25, the warning results suggested a low risk of rockburst (on January 26, the distance between the two working faces was only
these days, the no-rockburst probability ranged from 68.7% to 18 m and the intense rockburst risk had reached 71.2%. The micro-
100%). When the distance between the two working faces was seismicity was abnormally active and concentrated in the left work-
less than 13 m, the rockburst risk increased somewhat. From ing face (Fig. 13). Under such circumstances, single-directional
September 24 to 26, the risks associated with slight and mod- excavation should have been continued to reduce the intense mu-
erate rockbursts increased as excavation continued (and the tual effect of simultaneously excavating and unloading two work-
working faces moved from 13 m apart to 0 m). On September ing faces. Unfortunately, this strategy was not implemented on this
26, the risk of slight rockburst rose to 44.0% and breakthrough occasion (Fig. 12). Instead, both working faces were excavated
was achieved in the tunnel. This probability (that a slight rock- simultaneously. The left and right working faces advanced by ap-
burst might occur) should not be viewed as particularly high, proximately 2 and 4 m on that day, respectively. This resulted in the
because there also was a 30.5% chance that no rockburst would occurrence of an intense rockburst. After that rockburst, measures
happen at all at this time. were again taken to improve the situation. From January 27 on-
The excavation progress and intense rockburst warning results ward, single-directional excavation was again employed. This time,
in Case P-1 are shown in Fig. 12 in greater detail. From January 21 excavation was resumed at the right working face (where the micro-
to 24, the risk of an intense rockburst occurring increased heavily seismicity was relativity low) which continued to advance until the
(from 0% to 66.2%) as both working faces were excavated. On tunnel broke through safely.
January 24 (66.2% chance of intense rockburst) work on both faces The preceding discussion shows that rockburst risk can be
quantitatively assessed, and warnings issued dynamically, based
on microseismicity recorded during breakthrough. Based on such
Local Magnitude
-4.00
-3.56
-3.11
-2.67
-2.22
-1.78
-1.33
-0.89
-0.44
0.00
Feng, G. L., X. T. Feng, B. R. Chen, Y. X. Xiao, and Q. Jiang. 2015b. Mendecki, A. J. 1997. Seismic monitoring in mines. London: Chapman &
“Sectional velocity model for microseismic source location in tunnels.” Hall.
Tunnelling Underground Space Technol. 45 (Jan): 73–83. https://doi Poplawski, R. F. 1997. “Seismic parameters and rockburst hazard at
.org/10.1016/j.tust.2014.09.007. Mt Charlotte mine.” Int. J. Rock Mech. Min. Sci. 34 (8): 1213–1228.
Feng, G. L., X. T. Feng, B. R. Chen, Y. X. Xiao, and Y. Yu. 2015c. https://doi.org/10.1016/S1365-1609(97)80072-X.
“A microseismic method for dynamic warning of rockburst Salvoni, M., and P. M. Dight. 2016. “Rock damage assessment in a large
development processes in tunnels.” Rock Mech. Rock. Eng. 48 (5): unstable slope from microseismic monitoring—MMG Century mine
2061–2076. https://doi.org/10.1007/s00603-014-0689-3. (Queensland, Australia) case study.” Eng. Geol. 210 (Aug): 45–56.
Feng, G. L., X. T. Feng, B. R. Chen, Y. X. Xiao, and Z. N. Zhao. 2019. https://doi.org/10.1016/j.enggeo.2016.06.002.
“Effects of structural planes on the microseismicity associated with Shan, Z., and P. Yan. 2010. “Management of rock bursts during excavation
rockburst development processes in deep tunnels of the Jinping-II of the deep tunnels in Jinping II Hydropower Station.” Bull. Eng. Geol.
Hydropower Station, China.” Tunnelling Underground Space Technol. Environ. 69 (3): 353–363. https://doi.org/10.1007/s10064-010-0266-2.
84 (Feb): 273–280. https://doi.org/10.1016/j.tust.2018.11.008.
Trifu, C. I., and F. T. Suorineni. 2009. “Use of MS monitoring for rockburst
Feng, X. T., et al. 2012. “Study on the evolution process of rockbursts in
management at VALE INCO mines.” In Proc., 7th Int. Symp. on Rock
deep tunnels.” J. Rock. Mech. Geo. Eng. 4 (4): 289–295. https://doi.org
burst and Seismicity in Mines, edited by C. A. Tang, 1105–1114.
/10.3724/SP.J.1235.2012.00289.
New York: Renton.
Feng, X. T. 2017. Rockburst: Mechanism, monitoring, warning and
Wang, P., L. S. Jiang, J. Q. Jiang, and P. Q. Zheng. 2018. “Strata behaviors
mitigation Elsevier-Health Sciences.
and rock burst–inducing mechanism under the coupling effect of a
Feng, X. T., B. R. Chen, C. Q. Zhang, S. J. Li, and S. Y. Wu. 2013. Mecha-
hard, thick stratum and a normal fault.” Int. J. Geomech. 18 (2):
nism, warning, and dynamic control of rockburst development proc-
04017135. https://doi.org/10.1061/(ASCE)GM.1943-5622.0001044.
esses. [In Chinese.] Beijing: Science.
Xu, N. W., T. B. Li, F. Dai, B. Li, Y. G. Zhu, and D. S. Yang. 2015.
Feng, X. T., Z. B. Yao, S. J. Li, S. Y. Wu, C. X. Yang, H. S. Guo, and
“Microseismic monitoring and stability evaluation for the large scale
S. Zhong. 2018. “In situ observation of hard surrounding rock displace-
underground caverns at the Houziyan hydropower station in Southwest
ment at 2400-m-deep tunnels.” Rock Mech. Rock. Eng. 51 (3): 873–892.
https://doi.org/10.1007/s00603-017-1371-3. China.” Eng. Geol. 188 (Apr): 48–67. https://doi.org/10.1016/j.enggeo
Hedley, D. G. F. 1992. Rockburst handbook for Ontario hardrock .2015.01.020.
mines: CANMET SP92-1E. Ottawa: Energy, Mines and Resources Canada. Xu, N. W., T. B. Li, F. Dai, R. Zhang, C. A. Tang, and L. X. Tang. 2016.
Kaiser, P. K. 2009. “Seismic hazard evaluation in underground construc- “Microseismic monitoring of strainburst activities in deep tunnels at the
tion.” In Proc., 7th Int. Symp. on Rock Burst and Seismicity in Mines, Jinping II hydropower station, China.” Rock Mech. Rock Eng. 49 (3):
1–26. New York: Renton. 981–1000. https://doi.org/10.1007/s00603-015-0784-0.
Kaiser, P. K., D. D. Tannant, and D. R. McCreath. 1996. Canadian rock- Yu, Y., B. R. Chen, C. J. Xu, X. H. Diao, L. H. Tong, and Y. F. Shi. 2017.
burst support handbook. Sudbury, Canada: Geomechanics Research “Analysis for microseismic energy of immediate rockbursts in deep
Centre, Laurentian Univ. tunnels with different excavation methods.” Int. J. Geomech. 17 (5):
Li, A., F. Dai, N. V. Xu, G. K. Gu, and Z. H. Hu. 2019. “Analysis of a 04016119. https://doi.org/10.1061/(ASCE)GM.1943-5622.0000805.
complex flexural toppling failure of large underground caverns in lay- Yu, Y., D. X. Geng, L. H. Tong, X. S. Zhao, X. H. Diao, and L. H. Huang.
ered rock masses.” Rock Mech. Rock. Eng. 52 (9): 3157–3181. https:// 2018. “Time fractal behavior of microseismic events for different inten-
doi.org/10.1007/s00603-019-01760-5. sities of immediate rock bursts.” Int. J. Geomech. 18 (7): 06018016.
Li, T., M. F. Cai, and M. Cai. 2007. “A review of mining-induced seismicity https://doi.org/10.1061/(ASCE)GM.1943-5622.0001221.
in China.” Int. J. Rock. Mech. Min. Sci. 44 (8): 1149–1171. https://doi Zhang, C. Q., X. T. Feng, and H. Zhou. 2012. “Estimation of in situ stress
.org/10.1016/j.ijrmms.2007.06.002. along deep tunnels buried in complex geological conditions.” Int. J.
Li, X. B., F. Q. Gong, M. Tao, L. J. Dong, K. Du, C. D. Ma, Z. L. Zhou, Rock. Mech. Min. Sci. 52 (Jun): 139–162. https://doi.org/10.1016/j
andT.B.Yin.2017.“Failuremechanismandcoupledstatic-dynamicloading .ijrmms.2012.03.016.
theory in deep hard rock mining: A review.” J. Rock Mech. Geotech. Eng. Zhang, J. F., F. X. Jiang, S. T. Zhu, and L. Zhang. 2016. “Width design
9 (4): 767–782. https://doi.org/10.1016/j.jrmge.2017.04.004. for gobs and isolated coal pillars based on overall burst-instability
Liu, J. P., Y. H. Li, and S. D. Xu. 2018. “Relationship between microseis- prevention in coal mines.” J. Rock Mech. Geotech. Eng. 8 (4):
mic activities and mining parameters during deep mining process.” 551–558. https://doi.org/10.1016/j.jrmge.2015.12.006.
J. Appl. Geophys. 159 (Dec): 814–823. https://doi.org/10.1016/j Zhang, K., T. H. Yang, H. B. Bai, and R. P. Gamage. 2018. “Longwall
.jappgeo.2018.10.018. mining–induced damage and fractures: Field measurements and
Lu, C. P., L. M. Dou, N. Zhang, J. H. Xue, X. N. Wang, H. Liu, and J. W. simulation using FDM and DEM coupled method.” Int. J. Geomech.
Zhang. 2013. “Microseismic frequency-spectrum evolutionary rule of 18 (1): 04017127. https://doi.org/10.1061/(ASCE)GM.1943-5622
rockburst triggered by roof fall.” Int. J. Rock. Mech. Min. Sci. 64 (6): .0001040.
6–16. https://doi.org/10.1016/j.ijrmms.2013.08.022. Zhao, Z. N., X. T. Feng, B. R. Chen, G. L. Feng, and T. Y. Chen. 2013.
Lu, C. P., G. J. Liu, Y. Liu, N. Zhang, J. H. Xue, and L. Zhang. 2015. “Study of relativity between rockburst and MS activity zone in deep
“Microseismic multi-parameter characteristics of rockburst hazard in- tunnel.” [In Chinese.] Rock Soil. Mech. 34 (2): 491–497. https://doi
duced by hard roof fall and high stress concentration.” Int. J. Rock. .org/10.16285/j.rsm.2013.02.037.