RUPTL 2013-2022 Sum
RUPTL 2013-2022 Sum
Electricity Supply
Business Plan
PT PLN (Persero) 2013 - 2022
CONTENTS
INVESTMENT NEEDS 9
31
2013 - 2022
DEVELOPMENT PLAN FOR ISOLATED POWER SYSTEMS 32
RISK ANALYSIS 32
CONCLUSION 33
e Electricity Supply Business Plan (RUPTL) by PT PLN (Persero) for the period 2013 - 2022 has been issued
to fulfill the mandate of the Government Regulation No.14/2012 on Power Supply Operations and to serve as
guidance for the development of power infrastructure to meet electricity demand within PLN business areas
in an efficient and well-planned manner, in order to prevent inefficiencies from starting at the planning stage.
RUPTL covers electricity demand load forecasts, generation capacity expansion plans and the development
plans related to transmission, substations and distribution. Projected electricity demand has been prepared
for each province and electricity system, including the electricity systems in remote islands across the region.
Development plans for generating capacity, transmission and substation are also for their respective projects.
Electricity demand forecasts are prepared to project the electricity needed to support economic growth tar-
geted by the government and to take into consideration population growth.
e development of generation capacity has been planned to meet the growing demand for electricity, reserve
margin and to the extent possible, based on the principle of lowest cost. Utilization of local energy sources is
also prioritized, especially renewable energy such as geothermal and hydropower. Several projects have been
confirmed as undertaken as a PLN project or independent power producer (IPP) project, whilst some projects
have not been designated as either a PLN or IPP project. is is intended for PLN to decide a later stage, with
the approval of the Government, whether a project is implemented as a PLN or IPP project.
e development of the transmission system is planned to strike a balance between generation capacity and
power requirements efficiently to meet certain reliability and quality criteria. In electricity systems as large as
Sumatera and Java, an extra high voltage transmission line has been planned for the transmission system, to
form the backbone of the electrical system.
In the last five years, between 2008 and 2012, PLN’s business has continued to grow. Electricity sales in-
creased from 128 TWh in 2008 to 172 TWh in 2012, the number of customers increased from 39 million in
2008 to 50 million in 2012 and the electrification ratio increased from 62.3% in 2008 to 75.9% in 2012.
e electricity landscape by September 2013 can be described as follows: As of September 2013 the installed
capacity of PLN power plants and IPPs in Indonesia was 40,533 MW, consisting of 31,815 MW in Java-Bali
and 8,718 MW in Sumatera and East Indonesia, excluding 2,933 MW of rental generating units. Generating
capacity in Sumatera and East Indonesia is barely sufficient to meet the electricity needs of the community,
but there can be a shortfall when there is disruption to the power supply or a plant needs to undergo routine
maintenance. For example, the electricity system of North Sumatera operates for almost the whole year
without backup operation and often faces shortfalls in electricity supply, resulting in the operation of many
2013 - 2022
liquid fuel generating plants. e South Sumatera system also experiences a similar issue, suffering from
shortfalls in electricity supply for most of the year. is situation also occurs in several other areas, such as
East Kalimantan, South Kalimantan, Southeast Sulawesi, Minahasa-Gorontalo, Palu, Lombok, Ambon, Ternate
and Jayapura. Smaller deficits are also observed in other smaller electricity systems. In Java and Bali, there is
enough generating capacity to meet the power requirements. However, certain operational issues were faced
in 2012, such as insufficient gas supply for PLN’s power plants, over-loading of many transformers, as well as
the increasing transfer of power from Central Java/East Java to West Java, which resulted in voltage in the
system transmission during peak-load periods.
e problems in electricity supply that need to be addressed are an urgent need to meet electricity demand in
areas that lack electricity supply, replacing oil-fired plants with a non-petroleum fuels and to electrify regions
where there is no supply of electricity.
Certain actions that have been taken in West and East Indonesia, including rental of generation capacity,
purchase of electricity from small-scale IPPs, partnership/co-operation with local governments, purchase of
excess power, acceleration of the development of coal-fired power plants as stipulated in PR71/2006, build-
ing of transmission lines, securing continuity of primary energy supply and installation of solar power plants.
Short-term measures in the Java - Bali system include acceleration of the procurement of 150/20 kV trans-
former and 500/150 kV interbus, adding generating capacity in Bali, accelerating the commissioning of subma-
rine cables in Java-Bali 150 kV circuits 3 and 4 and installing shunt capacitors in the Jakarta system to improve
voltage levels.
Coal resources of 120 billion tonnes and reserves of 28 billion tonnes in Indonesia are the basis for the plan-
ning of the development of coal power plants, both coastal power plants using coal at market prices, as well
as mine-mouth power plants using low-rank coal at cost price plus a margin.
For natural gas, although Indonesia has large reserves amounting to 165 TSCF, in reality there is insufficient
gas available for power generation. In fact, the supply of gas to the existing power plants has been and will
be declining such that a deficit in gas supply is expected if there is no new gas supply. In the year 2012, the
LNG FSRU plant in Jakarta commenced supply of LNG to power plants in Jakarta during peak load periods. e
price of gas in LNG form is relatively high and is only economically viable if used for generation at peak load.
Faced with such a gas supply situation, the RUPTL only plans for 2 units of 800 MW Combined cycle gas-fired
power plant classes, with the expectation that one unit will received gas supply from the Cepu block, while the
gas supply for the other unit is to be determined. LNG for power generation will also be developed in Arun,
which will supply peaking power plants in Arun and Pangkalan Brandan and existing power plants in Belawan.
Continuing on the topic of gas, the RUPTL plans a smaller number of peaking power plants that will utilize
LNG or CNG in East Indonesia. e base load requirements will be met by the planned development of coal
fired power plants, while gas supplies will be used for peaking power plants wherever possible, to avoid the
use of oil.
A large number of plants utilizing renewable energy on large scale, such geothermal and hydro powers, have
also been planned in the RUPTL.
Interconnection System
RUPTL
Power system planning is optimized from an economic perspective, with the objective of achieving a configu-
ration of the development of plants which provide the lowest total NPV of the electricity supply cost, while
still meeting certain reliability criteria. e cheapest configuration is obtained through an optimization process
or objective function that includes capital costs, fuel costs, operation and maintenance costs and the cost of
energy not served. Simulation and optimization is done by using a model called WASP (Wien Automatic Sys-
tem Planning).
e reliability criteria used in the planning process is a Loss of Load Probability (LOLP) which is less than 1
day per year. is means the probability of peak loads exceeding available generating capacity is less than
In the Java-Bali system, the LOLP of < 0.274% is equivalent to a reserve margin of ≥ 25 - 30% of net gen-
eration capacity. When expressed in terms of installed capacity, the reserve margin required is approximately
35%.
For East Indonesia and West Indonesia, the reserve margin is set at about 40%, in view of a smaller number
of generating units, a larger unit size relative to peak load, a higher level of de-rating and a higher growth rate
compared to Java Bali.
As part of the optimization process, renewable energy generation capacity, particularly geothermal and hydro-
power, is treated as a ‘fixed system’ (permitted to enter the grid with no economic optimization required) at
the time the project is put into commercial operation.
Power generation planning for isolated small systems do not apply probabilistic methods and the economic
optimization process, but use the deterministic method. In this method, the planning was based on a N-2 cri-
teria, i.e. the minimum reserve must be greater than the two largest generation units. e reserve is defined
as the difference between the total generation capacity of existing power plants and peak load.
e transmission planning is carried out using both a static and dynamic reliability criteria N-1. e static N-1
criteria requires that when there is an outage in a transmission circuit due to a disruption or maintenance, then
the remaining transmission circuits must be able to distribute the overall load, so the continuity of electrical
power supply is maintained. e dynamic N-1 criteria requires that in the event of a three-phase short-circuit,
followed by the loss of a transmission circuit, then there should not be a loss of synchronization between that
group of generators and other groups of generators.
Generally, the criteria applied in the RUPTL is that there is a need for additional transformer capacity when the
loading of the transformer reaches 70% - 80%.
Between 2013 and 2022, electricity consumption in Indonesia is expected to increase from 189 TWh to 386
TWh, with an average growth of 8.4% per year, as shown in Figure-1. e number of costumers is projected
to increase from 54 million to 77 million by 2022, an increase of 2.7 million per annum. e additional custom-
ers will increase the electrification ratio from 79.6% to 97.7%. Regionally, the electricity demand in Java-Bali
is expected to increase from 144 TWh to 275 TWh, growing at a rate of 7.6% per annum. Demand in East
2013 - 2022
Indonesia is expected to grow more rapidly, increasing from 18 TWh to 46 TWh, a growth rate of 11.2% per
annum, while demand in Sumatera is expected to grow from 26 TWh to 66 TWh, a growth rate of 10.6% per
annum.
Figure-2 shows that in the Java-Bali system, industrial customers account for the largest portion of total con-
sumption, an average of 38.5% of total sales. In East Indonesia and Sumatera, the proportion of consumption
by industrial customers is relatively smaller, at 11% and 15.8% respectively. By 2022, residential customers
would dominate sales, accounting for 62% of sales in East Indonesia and 55 % in Sumatera.
450,000 300,000
Indonesia Jawa-Bali
400,000
250,000
350,000
300,000 200,000
250,000 Industrial
Industrial 150,000
200,000
Public Public
150,000 100,000
Business Business
100,000
50,000
50,000 Residenal Residenal
- -
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Indonesia
70,000 50,000
Sumatera Eastern Indonesia
45,000
60,000
40,000
50,000 35,000
30,000
40,000 Industrial
Industrial 25,000 Public
30,000
Public
20,000 Business
Business
20,000 15,000
- -
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Figure-2. Power Demand Growth Composition by Customer Group in Indonesia Regions (GWh)
To meet the growing power demand, an additional generating capacity of 59.5 GW for the whole of Indonesia
is required, an average growth rate of 6 GW per annum, as shown in Figure-3. e RUPTL plans for PLN and
IPPs to develop 16.9 GW and 25.5 GW of capacity respectively, with the remaining 17.1 GW currently unal-
located, i.e. projects where developers and funding sources have not been established.
Unallocated
10.000 IPP
2.555
PLN
8.000 2.689
6.000
3.435
1.026
6.838
2.084 1.954 3.274
4.000 - 2.003
878 6.410
-
314 96 1.506 1.391
729
2.000 3.948 1.535
2.518 2.908 2.919
2.013 1.869 2.003
1.234 1.244
- 55 90
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Figure-4 shows the additional generation capacity required, by plant type. New coal-fired power plants will
dominate the additional generation capacity to be developed, accounting for 37.9 GW, or 63.8% of the planned
additional capacity. Planned combined cycle gas-fired power plants amount to 5 GW of capacity, or 8.4 %. For
renewable energy, the largest planned additional capacity relates to hydropower at 6.5 GW, or 11.0% of the
total additional capacity, followed by geothermal at 6.0 GW, or 10.2%. Of this planned additional capacity,
around 16.6 GW will be in West Indonesia and around 11.5 GW in East Indonesia. In West Indonesia, there is a
510 MW hydroelectric project Batang Toru to be developed by the private sector, and in East Indonesia there
is also a 450 MW hydropower project Karama which will be developed by the private sector. For the Java - Bali
system, additional power is about 31.5 GW, or an average of 3.2 GW per year, including 353 MW of mini-hydro
and 50 MW of wind turbine power plants.
12,000
10,627
10,000
9,154
8,000
7,473
6,053
2013 - 2022
5,948
6,000 5,449 5,348
4,000 3,786
2,831 2,838
2,000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
e energy mix for power generation in 2022 for Indonesia is projected to be 65.6% coal, 16.6% natural gas
(including LNG), 11.0% geothermal, 5.1% hydroelectric and 1.7% oil and other fuels as shown in Figure-5.
450,000
400,000
350,000
300,000
GWh
250,000
200,000
150,000
100,000
50,000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Import Biomass Solar/Wind/Hybrid HSD MFO LNG Gas Coal Geothermal Hydro
Table-1 shows the energy mix for Indonesia from 2013 to 2022.
No, Fuel Type 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
1 HSD ( x 10^3 kl ) 6,679 6,007 4,711 3,414 2,651 1,740 1,812 1,757 1,862 2,019
2 MFO ( x 10^3 kl ) 1,267 1,238 1,599 1,544 1,185 183 191 190 194 212
3 Gas (bcf) 387 396 412 447 448 400 366 357 354 375
4 LNG (bcf) 92 87 119 147 174 242 244 245 258 269
5 Batubara (10^6 ton) 59 71 83 94 106 114 120 131 143 151
6 Biomass (10^3 ton) 1 80 286 474 693 738 745 752 761 770
System planning process in RUPTL 2013 - 2022 doesn‘t take into account the CO2 emissions cost as one of
variable costs. However, this doesn’t mean that RUPTL ignoring the CO2 emissions reduction. It can be seen
from the number of geothermal and hydropower power plants candidate set into the electrical system even
though they are not the lowest cost solution. e use of supercritical boiler technology and ultra supercritical
in Java also prove that PLN concerned with the efforts to reduce CO2 emissions from power generation.
RUPTL
e amount of emissions is calculated from the amount of fuel used and converted into CO2 emissions (in
tonnes of CO2 ) by using a multiplier factor (emission factor) issued by the IPCC (Intergovernmental Panel on
Climate Change ).
Figure 6 shows the CO2 emissions that would be generated with electricity production and fuel mix as shown
in Figure 5. From Figure 6 it can be seen that CO2 emissions in Indonesia will increase from 165 million tons
in 2013 to 339 million tonnes by 2022. Of the 339 million tons of emissions, 294 million tons (87%) comes
from burning coal.
300
250
200
150
100
50
0
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Average grid emission factor for Indonesia in 2013 was 0.766 kgCO2/kWh, will increase to 0.846 kgCO2/kWh
in 2017 and will further decline due to the operation of geothermal and hydro projects so that the average grid
emission factor in 2022 became 0.773 kgCO2/kWh.
PLN will utilize carbon finance opportunities through the UNFCCC or outside the UNFCCC framework. Carbon
finance project implementation will be applied to all activities within the PLN, which has the potential to obtain
carbon finance.
Since the year 2002 PLN is aware of funding opportunities of carbon through the Clean Development Mecha-
nism (CDM) and do some assessment of potential CDM projects, and results to date PLN has signed several
ERPA (Emission Reduction Purchase Agreements). In addition PLN also develop projects through the VCM
(Voluntary Carbon Mechanism).
2013 - 2022
Since the expiration of the first commitment of the Kyoto Protocol by the end of 2012, the use of carbon
finance will be adjusted to the new carbon financing mechanisms, both within and outside the UNFCCC frame-
work of the UNFCCC.
e planned development of the transmission system for the period 2013 - 2022 includes the development
of the transmission system with a voltage of 500 kV and 150 kV in the Java-Bali system, and systems with
voltage of 500 kV, 275 kV, 150 kV and 70 kV in East Indonesia and West Indonesia. Generally, the construc-
tion of the transmission system looks to achieve compatibility between the upstream generation capacity and
the downstream portion of the power demand in an efficient manner. In addition, it also looks to overcome
bottlenecks and improve service voltage.
e development of 500 kV transmission lines in Java is generally intended to transmit power from new and
expansion plants and to maintain the N-1 reliability criterion, whether static or dynamic. On the other hand,
the development of 150 kV transmission lines is intended to maintain the N-1 reliability criterion and the as-
sociated transmission, in relation to the new 150 kV substations.
12.000
10.000
8.000
6.000
4.000
2.000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
25.000
20.000
15.000
10.000
5.000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
70/20 kV 150/20 kV 150/70 kV 250 kV DC
275/150 kV 500 kV DC 500/150 kV 500/275 kV
e development of 500 kV transmission line in Sumatera is intended to form the backbone of the transmis-
sion system, bringing together the interconnections in the eastern corridor of Sumatera. Large-scale power
plants and load centers in Sumatera will be connected to this 500 kV transmission system. is transmission
system also will transmit power from regions with rich and inexpensive primary energy sources (e.g. Sumbag-
seland Riau) to regions which lack an affordable primary energy source (e.g. Sumbagut). In addition, a 500 kV
transmission line will also be developed in South Sumatera as a feeder electricity supply from the mine mouth
power plants to the converter station for the HVDC transmission line, which will connect Sumatera and Java.
INVESTMENT NEEDS
20.0
PLN power plant : US$ 37,2 billion
18.0 IPP power plant : US$ 54,1 billion
Transmission : US$ 19,4 billion
16.0 Distribution : US$ 14,5 billion
14.0
Total PLN : US$ 71,1 billion
12.0 Total PLN+IPP : US$125,2 billion
10.0
8.0
6.0
4.0
2.0
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
To date, many PLN projects have been financed through loans obtained from overseas (two-step loan). How-
ever, since 2006 the role of this kind of financing has begun to decline and financing by issuing bonds (both
local and global) has been increasing. e 10,000 MW Fast Track project was fully financed by loans to PLN,
backed by a guarantee from the Government. Lately, PLN has once again tried to obtain loans from multilateral
and bilateral financial institutions to fund power projects, such as the Upper Cisokan pumped storage and the
Sumatera-Java HVDC transmission line.
2013 - 2022
JAVA - BALI SYSTEM DEVELOPMENT PLAN
e additional generation capacity to be developed over the period of 2013 - 2022 for the Java - Bali system is
31.5 GW, or an average increase in capacity of 3.2 GW per year, including small-scale mini-hydro power plants
of 353 MW and wind power plants of 50 MW. e capacity of PLN will increase by as many as 8.3 GW, or 26%
of the total planned additional capacity. Private sector participation represents a large proportion of the total
planned additional capacity, i.e. 15.6 GW, or 50%, while unallocated projects amount to 7.5 GW, or 24%. Of the
types of power generation, coal-fired power plants will represent the majority of additional capacity to be de-
veloped, at 22.6 GW, or 71.8%, followed by combined cycle gas-fired power plants with a total capacity of 3.2
GW, or 10.0% and gas-fired plants with total capacity of 0.2 GW, or 0.7 %. As for renewable energy, additional
capacity consists of geothermal at 2.8 GW, or 8.9%, hydro electric at 2.6 GW, or 8.4%, and other plants of 0.05
GW, or 0.2%. e breakdown of power generation development in the Java-Bali system is shown in Table-2.
PROJECTS 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Energy Sales GWh 144,010 157,183 170,232 183,486 197,293 211,527 226,314 241,805 257,968 274,850
Growth % 8.8 9.1 8.3 7.8 7.5 7.2 7.0 6.8 6.7 6.5
Energy Production GWh 163,501 178,009 192,714 207,605 223,336 239,235 255,816 273,475 292,238 312,111
Load Factor % 78.4 78.5 78.6 78.7 78.8 78.9 79.0 79.1 79.2 79.3
Gross Peak Load MW 23,801 25,880 27,982 30,106 32,346 34,605 36,957 39,458 42,112 44,919
GENERATION
CAPACITY
Net Capacity MW 29,053 29,028 29,028 29,028 29,028 29,028 27,997 27,997 27,997 27,997
Installed Capacity MW 30,285 30,261 30,261 30,261 30,261 30,261 29,229 29,229 29,229 29,229
PLN MW 24,625 24,601 24,601 24,601 24,601 24,601 23,569 23,569 23,569 23,569
Retired/Mothballed -200 -25 0 0 0 0 -1031 0 0 0
IPP MW 5,660 5,660 5,660 5,660 5,660 5,660 5,660 5,660 5,660 5,660
e breakdown of the planned development for Java - Bali power system above indicates that the net reserve
margin varies between 16 - 36%, with the lowest reserve margin occurring in 2015 (18%), 2016 (16%) and
2017 (16%), due to delays some IPP projects such as Sumsel 8 coal-fired power plant (2x600MW), Central Java
coal-fired power plant (2x950 MW), Madura coal-fired power plant (2x200 MW), Java-1 coal-fired power plant
(1x1,000 MW), Java-3 coal-fired power plant (2x660 MW) as well as some geothermal power plants amounting
to 400 MW. In anticipation of lower reserve margins in 2015 to 2017, steps have been taken to address the
2013 - 2022
issue.
e Muara Karang combined cycle gas-fired power plant (450 MW), Grati combined cycle gas-fired power plant
(450 MW), Pesanggaran gas engine power plant (200 MW) and Java-1combined cycle gas-fired power plant
(800 MW) and coal-fired IPPs such as Celukan Bawang power plant (380 MW), Banten power plant (625 MW)
and Cilacap expansion (600 MW) should be operational over the period 2014 - 2017, to ensure that the re-
serve margin is maintained and does not decline.
Plants that undergo changes are as follows: (i) Changes in plant type and unit size: Muara Karang open
cycle gas-fired power plant (400 MW) to Muara Karang combined cycle gas-fired power plant (450 MW) and
the Grati open cycle gas-fired power plant (300 MW) to Grati combined cycle gas-fired power plant (450 MW),
as combined cycle gas-fired power plants are more efficient and are able to operate on a daily start-stop basis
as a peaker plant, (ii) Capacity of Java-1 and Java-2 combined cycle gas-fired power plants to increase from
750 MW to 800 MW, to keep abreast of the latest technology that is more efficient, (iii) Changes in location:
e locations of coal-fired power plants and combined cycle gas-fired power plants are subject to change in
accordance with developments in project preparation, including the availability of gas supply.
BDSLN UNGAR
UJBRG TANDES
NGBNG
PMLNG
SBSLN
SBBRT
CGRLNG
TASIK
RWALO GRATI
SOLO
CLCAP IPP ADIPALA PITON
PEDAN
KDIRI
BANGIL
NEW ANTOSARI
Legend:
Existing Power Plant in 500 kV
~ Planned Power Plant in 500 kV
Existing 500 kV S/S
Planned 500 kV S/S
Existing 500 kV EHV
Planned 500 kV EHV
e development of the 500 kV transmission in Java is generally intended to evacuate power from new and
expansion power plants, to maintain both the static and dynamic N-1 security criterion,while the development
of the 150 kV transmission is intended to maintain the N-1 security criterion and the transmission associated
with the new 150 kV substation.
e plans for development of the 500 kV transmissions in Java-Bali are shown in Figure-10. Considering the
development of EHV transmission lines and HV transmission lines are often delayed due to licensing, ROW
and social issues, as well as the urgent need for additional power, there is a need for PLN to take steps to
increase transmission capacity soon. e development of EHV transmission line using the new route would
take a long time, while the reconductoring of several sections of the 500 kV and 150 kV transmissions would
take a shorter time.
Construction of the 500 kV transmission is intended to evacuate power from large-scale coal-fired power
plants such as Adipala, Indramayu 4 and 5, Central Java, Java-1, Java-3, Java-4, Java-5, Java-6, Java-7, Java-
Bali Crossing to transfer from Paiton to the load center in Bali, pumped storage hydropower Upper Cisokan
and Matenggeng, as well as several other new plants.
RUPTL
e 500 kV EHV transmission lines to undergo reconductoring are New Suralaya-Bojonegara-Balaraja (2018)
and Old Suralaya-Balaraja-Gandul (2019).
e new 500 kV transmission development plan for EHV transmission lines includes Tanjung Jati B-Pemalang-
Indramayu - Cibatu, Balaraja - Kembangan - Duri Kosambi and Duri Kosambi - Muara Karang - Muara Tawar for-
ming looping EHV transmission lines in North Jakarta, to strengthen and improve the reliability and flexibility of
the system operation in Jakarta. A 500 kV HVDC transmission interconnection between Sumatera-Java will also
be built, to distribute power from the mine mouth power plants in South Sumatera to the load centers in Java.
TELUK JAKARTA
TNAGA
MKRNG
TNAGA II KAPUK
PRIOK PLTU 4x1.000 MW
SPTAN PLNDOB MTWAR
PLNDOA
SPTAN III MKRNG ANCOL
MKRNG III
SPTAN II
TGBRU II GNSRI
SOETA KMYRN KDSPI II
ANGKE MGBSR II PLPNG JGC MRNDA
PSKMS TGBRU DMGOT HRPDH
GRGOL KTPNG MGBSR KMYRN II KLPGD
TGRNG III CKRNG
RWBUAYA TTNGI KDSPI
GBLMA
MAXIM DRKSB GMBRU PGLNG II CBTUBR
KBSRH PKRNG
New GPOLA
JTAKE Old BKASIUTRA
CKNDE CKUPA GRGOL II BDKMY
TGRNG PGSAN PGLNG
SMBRT II DKTAS
DKTASII GBLMA-2 BKASI II
SPINML CLDK PLMAS PGDNG SKTNI
KBJRK KARET MGRAICIPNG II BKASI
BLRJA LIPP NewOld
STBDI CIPNG KESA KSBRU
O
PGDGSTEEL
BNTEN LIPP ALMSTRA NSYAN II AGP IISMBRT
O II KMBNG
LAUTS SNYAN AGP PCRAN2 FAJAR
PNCOL II
MLNIUM NSYAN DNYSA II TMRSD PDKLP
Old
CITRA PNCOL
PWRSTEL MPANG
DNYSA CIKRNG
TGRSA BKSPWR
HVDC
CSW CSW II JTWRG
DRTGA
CWANG TMBUN II
JBEKA
LEGOKLKONG MRT TMBUN
CWANGBR TMBUN
PTKNG RJPKSI
TGRSA II PDNDH II
CSW III/ MNTUR
LKONG II BNTRO II Psmede GDMKR CBATU
CSENG KMANG
LKONG PDNDH
LKONG III/BSD
RGNAN
BNTRO
GNDUL
DPBRU
JTNGNII/
CBBUR
CBATU
LEGEND : CLGSI II/
DEPOK III
EXISTING 500 KV S/S CMGIS II JONGGOL
CLGSI
NEW 500 KV S/S CMGIS ASPEK
CIBNG
EXISTING 150 KV S/S
NEW 150 KV EXISTING BGORX
NEW 150 KV S/S FOR HV CUSTOMER CIBNG II SGLNG
SCBNG
EXISTING 70 KV S/S CLGON
SNTUL ITP
TSMYA BGBRU
KDBDK
To strengthen the system supply in Jakarta, construction has been planned for a EHV transmission line for the
Duri Kosambi - Muara Karang - Priok - Muara Tawar section (looping EHV transmission line for north Jakarta
route) as shown in Figure-11. e new EHV transmission line will also improve the reliability and flexibility of
operation of the power systems in Jakarta and Bekasi.
2013 - 2022
Table-3 shows the gas supply based on current contracts. From Table-3 it shows that the supply of gas for the
next 10 years is likely to decline, especially for Priok, Muara Karang, Muara Tawar, Gresik and Grati. Tambak
Lorok and Pesanggaran (Bali) have been using fuel oil to-date and they are expected to obtain gas supplies
from new sources. Demand for gas for power generation in Java-Bali is shown in Table-4. In the coming years,
there will be additional planned gas-fired generating capacity as follows: Pesanggaran gas engine power plant
200 MW (2015), Grati combined cycle gas-fired peaker plant 450 MW (2015/16), Muara Karang combined
cycle gas-fired peaker plant 450 MW (2016), Java-1 combined cycle gas-fired power plant (in Gresik) 800 MW
(2017), which is expected to receive gas supply from the Cepu block; as well as Java-2 combined cycle gas-
fired power plant (alternative in Grati) 800 MW (2018), which has yet to establish its gas supply.
No. Power Plant MW 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
1 Muara Karang 1) 2,077
Gas Demand 164 150 140 127 124 122 123 122 124 122
2 Tanjung Priok 1,923
Gas Demand 168 197 176 169 163 159 157 156 181 205
Gas Supply 140 140 140 140 110
LNG Supply 192 207 176 136 136 136 229 229 197 197
Surplus-Deficit 0 0 0 -20 -42 -145 -51 -49 -109 -131
3 Muara Tawar 2) 2,662
Gas Demand 179 182 179 201 201 202 160 162 164 159
Gas Supply 179 182 134 92 92 96 56 30 30 30
Surplus-Deficit 0 0 -45 -110 -109 -106 -104 -132 -134 -129
4 Gresik 3) 2,979
Gas Demand 301 290 284 269 242 236 236 237 240 245
Gas Supply 301 290 284 269 208 174 103 100 93 93
Surplus-Deficit 0 -34 -63 -134 -137 -147 -152
5 Tambak Lorok 1,234
Gas Demand 50 98 166 166 166 166 139 120 120
Gas Supply 50 98 166 166 166 166 139 120 120
Surplus-Deficit 0 0 0 0 0 0 0 0 0
4
6 Grati ) 2,014
Gas Demand 90 90 90 96 89 160 161 161 164 174
Gas Supply 90 90 90 40 34 21
Surplus-Deficit 0 -56 -55 -139 -161 -161 -164 -174
7 Cilegon 740
Gas Demand 110 110 110 110 110 110 110 110 110 110
Gas Supply 110 110 110 110 110 110 110 110 110 110
Surplus-Deficit
8 Pesanggaran 250
Gas Demand 30 30 20 20 20 20 20 20
Gas Supply 30 30 20 20
Surplus-Deficit -20 -20 -20 -20
9 Total Jawa-Bali
Gas Demand
Gas Supply
Surplus/Deficit -
1,012
- 1,012
0
1,069
1,069
0
1,108
1,063
-45
1,168
982
-186
1,116
876
-240
1,176
723
-453
1,133
663
-470
1,107
608
-499
1,123
549
-574
1,156
549
-607
2013 - 2022
Note:
1) Includes Muara Karang combined cycle gas-fired power plant 450 MW
2) Includes Muara Tawar Add-on Blocks 2,3,4 combined cycle gas-fired power plant 650 MW
3) Includes Java-1 combined cycle gas-fired power plant 800 MW
4) Includes Java-2 combined cycle gas-fired power plant 800 MW
Table-5 shows the power supply and demand balance of the Sumatera power system. e power system in
Sumatera is planned to achieve a reserve margin of 65% by 2022, which is lower than the reserve margin in
the RUPTL 2012 - 2021, which had planned to achieve a reserve margin of 70% in 2018. Potential burden on
Sumatera could be higher than planned. With reserve margins that are high enough, it is possible to accom-
modate such potential high loads. However, if the reserve margin is lower than 40 %, it would be necessary
to control the load.
Projects Unit 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Demand
Energy Production GWh 28,935 31,603 34,918 38,562 42,599 47,047 52,981 57,456 63,539 70,312
Load Factor % 70 69 69 69 70 70 71 72 72 73
Gross Peak Load MW 4,742 5,227 5,770 6,316 6,912 7,561 8,288 9,288 9,916 10,961
Supply
Installed Capacity MW 5,722 5,607 5,492 4,832 4,542 4,384 4,384 4,384 4,384 4,384
Net Capacity MW 4,711 4,672 4,542 4,019 3,849 3,742 3,742 3,742 3,742 3,742
PLN MW 3,126 3,093 3,093 2,960 2,795 2,773 2,773 2,773 2,773 2,773
Rental MW 728 728 688 298 293 208 208 208 208 208
IPP MW 857 851 761 761 761 761 761 761 761 761
Retired & Mothballed (PLN) MW 90 33 - 133 166 22 - - - -
Additional Capacity
PLN ON-GOING & COMMITTED
Tarahan (FTP1) CFPP 200
Meulaboh (Nagan Raya) #1,2 (FTP1) CFPP 110 110
Teluk Sirih #1,2 (FTP1) CFPP 112 112
Pangkalan Susu #1,2 (FTP1) CFPP 220 220
Riau (FTP1 Amandment) CFPP 220
Pangkalan Susu #3,4 (FTP2) CFPP 200 200
Sungai Gelam (CNG/Peaker) GEPP 92
Duri GEPP 112
Arun (Peaker) GT/GEPP 200
Batanghari CCPP 30
Keramasan CCPP 80
Hululais (FTP2) GeoPP 55 55
Sungai Penuh (FTP2) GeoPP
Peusangan 1-2 HEPP 88
Asahan III (FTP2) HEPP 174
Masang-2 (FTP2) HEPP 55
RENTAL
Dumai CFPP 240
Lampung (Sribawono + Sutami) GT/GEPP 200 -200
Payo Selincah GT/GEPP 50 -50
Tanjung Jabung Timur GT/GEPP 100 -100
ADDITIONAL RENTAL
(Diesel/GT/GEPP)
Sumbagut MW 165 265 -175 -255
Sumbagselteng MW 50 80 -130
e development of transmission lines in Sumatera will form the transmission backbone 500 kV interconnec-
tion system that unites the corridors of Sumatera in the east. e centers of large-scale generation and load
centers in Sumatera will be connected to this 500 kV transmission system. is transmission also will transfer
2013 - 2022
electricity from power plants in the areas with adequate cheap primary energy source (Sumbagsel and Riau) to
areas which lack a primary energy source (Sumbagut). e addition of 500 kV transmission is also developed
in South Sumatera as a feeder supplier of electricity from the mine mouth coal fired power plant to the HVDC
transmission converter station which will connect the islands of Sumatera and Java.
e development plan in RUPTL 2013 - 2022 for the transmission system will see significant change to the
network topology with the establishment of the 275 kV and 500 kV interconnection system in Sumatera. e
development is also done to meet the growing demand in the form of additional transformer capacity. Deve-
lopment to improve the reliability and debottlenecking which is also planned in some systems, such as the
plan to build a second circuit and reconductoring several sections in the Sumbagsel and Sumbagut transmis-
sion systems.e plan for a 275 kV interconnection in Sumatera is programmed to be implemented entirely in
2017. In addition some substations and 150 kV transmission are being constructed to take over the load of
diesel generators to interconnected systems.
22
21
2017 20
2017
1 24
2017 25
2 18
3
23
No GI 275 kV COD 17
2018 16
1 Sigli 2016 2014
19
2 Meulaboh 2016
2018 2020
3 Lhokseumawe 2016 15
4 Sarulla 2015
5 Payakumbuh 2015 4 2016 2015
6 Kiliranjao 2015 2016
14
7 Muara Bungo 2015
8 Bangko 2015 2015
2018
2016
9 Lubuk Linggau 2015 5 27
10 Lahat 2015 13
11 Gumawang 2014 2018
12 Muara Enim 2016
6
13 Betung 2015 2015
14 New Aur Duri 2015 7 2017
2016 12
16 New G. Sak2015 8
17 P. Sidempuan 2017
18 Simangkok 2014 2014 11
19 Galang 2013 No GI 500 kV COD 2014
20 Binjai 2013 12 Muara Enim 2016 9
21 Pangkalan Susu 2013 14 New Aur Duri 2016 10
2018 28
22 Ulee Kareeng 2016 15 Rengat 2016
23 Rantau Prapat 2018 26
16 New G. Sak2016
26 Lumut Balai 2014 23 Rantau Prapat 2018
27 Sungai Lilin 2015 24 Medan (S.Rotan) 2018
28 Lampung 2018 25 Kuala Tanjung 2018
e projected fuel mix for electricity production in Sumatera in 2022 would be 49% coal, 17% natural gas,
11% hydro, 1% oil and 22% geothermal as shown in Figure-14.
80,000
70,000
60,000
50,000
GWh
40,000
30,000
RUPTL
20,000
10,000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
No Power Plant Supplier 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
1 Aceh Timur Medco Blok A - - - - 5.0 5.0 5.0 5.0 5.0 5.0
Belawan, P. Pasir, Kambuna 5.0 - - - - - - - - -
2 Sumbagut-1 dan FSRU LNG Tangguh - - 47.5 92.1 92.1 92.1 92.1 92.1 92.1 92.1
Arun PEP Benggala 2.0 2.0 2.0 2.0 - - - - - -
3 Teluk Lembu Kalila Bentu 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0
PLTMG Rawa Min- Petroselat Rawa Minyak - 2.0 5.0 5.0 5.0 5.0 5.0
4
yak Bengkalis (Potensi)*
5 PLTG sewa Jabung Petro China (Potensi) - 5.0 5.0 5.0 5.0 5.0 5.0
PEP - TAC (Own Opera- 2.0 2.0 2.0 2.0 2.0 - - - - -
6 Sungai Gelam
tion)
Payo Selincah, PEP - TAC Sungai Gelam 2.5 2.5 2.5 2.5 2.5 - - - - -
7
Simpang Tuan Perusda Jambi 2.5 2.5 2.5 2.5 2.5 -
8 Payo Selincah, Energasindo 14.0 14.0 14.0 14.0 14.0 14.0 - - - -
Batanghari Jambi Merang 20.0 20.0 18.0 16.0 14.0 14.0 14.0 - - -
9
Jakabaring (CNG) PDPDE Sumsel 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 - -
10 Indralaya Medco E&P Indonesia 21.0 10.0 17.0 - - - - - - -
11 Talang Duku PGN 8.0 8.0 8.0 8.0 8.0 8.0 8.0 - - -
12 Borang Medco E&P Indonesia 18.0 18.0 - - - - - - - -
13 Keramasan Medco E&P Indonesia 15.0 - - - - - - - - -
Pertamina EP 15.0 15.0 15.0 - - - - - - -
14 Gunung Megang
Medco E & P Indonesia 15.0 15.0 15.0 15.0 15.0 15.0 - - - -
Borang Pertamina EP (Asri Gita) 31.0 31.0 31.0 31.0 31.0 - - - - -
-
16.0
3.0
-
16.0
3.0
12.5
16.0
3.0
12.5
16.0
3.0
12.5
16.0
3.0
12.5 12.5
-
-
12.5
-
-
12.5
2013 - 2022
-
-
e current installed capacity in West Kalimantan is 335 MW (including rental capacity) which all plants are
using fuel oil, so operating costs are very high. Additional generation capacity in West Kalimantan is still in the
planning stage, with the exception of Fast Track Phase 1 – Parit Baru (2x50 MW) and Kura-kura (2x25 MW)
coal-fired power plants are under construction and expected to be operational by 2015.
PLN and Sarawak Electricity Company (SESCO) have signed a Power Exchange agreement (PEA) which sets
out plans for PLN to purchase electricity to supply West Kalimantan from Sarawak for 50 MW flat (as base-
load) and at peak load PLN can purchase up to 230 MW, starting from early 2015 until 2019. In the long term
e power supply and demand balance of the West Kalimantan system (Table-8) indicates that the reserve
margin will reach 51% by 2020. is situation is still acceptable considering that coal-fired power plant pro-
jects in West Kalimantan are at a risk of delays for various reasons andthere is no take-or-pay clause at peak
periods in the Sarawak interconnection.
Projects 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Demand
Energy Production GWh 1,371 1,632 1,855 2,373 2,907 3,302 3,675 4,088 4,544 5,040
Load Factor % 67 67 66 66 66 66 66 66 67 67
Peak Load MW 234 280 319 413 506 575 636 703 776 856
Supply
Installed Capacity MW 335 434 136 79 131 139 139 139 139 139
Net Capacity MW 270 360 123 71 119 126 126 126 126 126
Interconnected isolated
MW - - - 41 89 96 96 96 96 96
system
Additional Capacity
PLANNED ADDITIONAL
CAPACITY
(Peaking)
(Baseload)
RUPTL
Total Additional Capacity MW 0 0 385 100 200 100 0 150 200 128
Total Installed Capacity MW 335 434 471 514 766 874 874 1,074 1,274 1,402
Total Net Capacity MW 270 360 508 556 804 911 911 1,061 1,261 1,389
Interconnection with Sesco can be extended, but only for peaking, after Kalbar-2 coal fired power plant in operation
SARAWAK
(MALAYSIA)
ARUK BIAWAK
SAMBAS SERIKIN
KUCHING
2013
Ke GITET
PLTU P. Baru (FTP2) JAGOI Matang
BABANG BATU KAYA
2x50 MW – 2016 KALIMANTAN
TIMUR
U TEBEDU
SINGKAWANG
BADAU PUTUSSIBAU
BENGKAYANG ENTIKONG 2020
PLTU P. Kura-Kura (FTP1) 2014
U PLTA Pade Kembayung PLTU Sintang
2x27,5 MW – 2015 3x10 MW – 2022 3x7 MW – 2015
A
MEMPAWAH NGABANG
2014
55 km SANGGAU
2016
PARIT BARU
PLTU P. Baru (FTP1) SIANTAN TAYAN U
2x50 MW – 2015 2013
U U SINTANG
2016 PLTA Nanga Pinoh
PLTG/MG Peaker G GB 2x49 MW – 2022
100 MW – 2017 U SEKADAU
KOTA BARU SEI RAYA 2016
2015
A
PLTU Sanggau
2x7 MW – 2013 /14 NANGA PINOH KALIMANTAN
2018 TENGAH
PLTU Kalbar -1
2x100 MW – 2018/19 GI. K0TA BARU
2019
PLTU Kalbar -2
2x200 MW – 2020/21
PERENCANAAN SISTEM
PLTU Ketapang PT PLN (Persero )
U KETAPANG PETA JARINGAN
2x10 MW – 2016 2017 PROPINSI KALIMANTAN BARAT
PLTU IPP Ketapang / GI 500 kV Existing / Rencana U / U PLTU Existing / Rencana
2x6 MW – 2016 GI 275 kV Existing / Rencana G / G PLTG Existing / Rencana
/
96 km
e fuel mix for electricity production in West Kalimantan is presented in Figure-16. e role of each primary
energy can be explained as follows: (i) in 2013, because of the lack of new power generation capacity besides
fuel oil, electricity production using fuel oil reached 1,498 GWh. In line with the operation of coal-fired power
plant and imports of electricity from Sarawak, the use of fuel oil as the primary fuel in the West Kalimantan
2013 - 2022
power system can be further reduced; (ii) Hydro power resources are found in the Nanga Pinoh area, so a 98
MW Nanga Pinoh hydropower plant has been planned, to be operational by 2022; (iii) ere are also plans
to ship LNG from Batam to West Kalimantan, which will be used to supply peaker plants 100 MW with gas
demands of 5 bbtud.
5.000
4.000
GWh
3.000
2.000
1.000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
e South-Central Kalimantan (Kalselteng) system and North - East Kalimantan (Kaltimra) system have suffered
power supply shortages for many years. To improve the power shortage situation, PLN has introduced both
short-term and long-term solutions. Short-term solutions involve rental of diesel engine generating units, while
long-term solutions involve the planning and development of a number of coal fired power plants, gas fired
power plants and hydroelectric power plants. In reality, however, many of these power generating projects have
faced problems and as such, project completions have been delayed from the initial schedule. As a result, the
additional power generated from the short-term solution (rental of diesel engine units) has not been able to suf-
ficiently improve the power shortage situation, due to the rapid growth of demand for power. In addition, main-
tenance of existing power plant machinery could not be carried out as planned because these plants have to be
operated continuously. Also, some potential customers with high power demand could not be served.
Currently, the power generation capacity of PLN and IPP power plants, including rental diesel engine units and
excess power, in the South, Central, North and East regions of Kalimantan (Kalseltengtimra) is 815 MW, with
peak load at 847 MW, excluding the Asam-asam coal fired power plant units 3 and 4, which are expected to be
operational in 2013. In addition, the portion of power generation plants operating on oil fuel in Kalseltengtimra
is still high, hence the power generation cost remains high.
A large number of additional power plants have been planned in anticipation of project delays. is is reflected
in the power balance of the Kalseltengtimra system, where the annual reserve margin is 33% to 53%, other
RUPTL
than in 2015, when the reserve margin is only 22% of the net available capacity. Reserve margins are esti-
mated to be highest in 2019 if all projects are completed on time. However, based on PLN’s experience to
date, the success rate of power generation projects is relatively low, particularly in Kalimantan. e steam
turbine IPP project, which had been planned to be operational by 2012 - 2014, has been delayed by one year.
PLN Muara Jawa/Teluk Balikpapan coal fired power plant (FTP1) is estimated to be delayed by one year, while
Pulang Pisau coal fired power plant is estimated to be delayed by two years.
From the above, it can be seen that the reserve margin is relatively high (up to 53%). is is intended to provide
greater certainty to the people South Kalimantan, Central Kalimantan, East Kalimantan and North Kalimantan
that the electricity supply in these regions will be adequate.
2013 - 2022
Kusan HEPP - - - - - - - - - 65
Kalsel (FTP2) CFPP - - - - 100 100 - - - -
Kalselteng 1 CFPP - - - - - 100 100 - - -
Kalselteng 2 CFPP - - - - 200 - - -
Kalselteng 3 CFPP - - - - 50 50 - - - -
Kaltim (FTP2) CFPP - - - - 100 100 - - - -
Kaltim (Mine Mouth) CFPP - - - - - 55 - - - -
Kaltim 3 CFPP - - - - - - - 150 150 -
Kaltim 4 CFPP - - - - - 100 - - - -
Total Additional Capacity MW 312 270 275 420 555 505 100 150 250 120
TOTAL INSTALLED CAPACITY MW 1,282 1,551 1,719 1,959 2,167 2,727 2,827 2,977 3,227 3,347
TOTAL NET CAPACITY MW 1,127 1,396 1,565 1,804 2,131 2,691 2,791 2,941 3,191 3,311
e development plan of the Kalseltengtimra 150 kV and 70 kV transmission system is intended to meet elec-
tricity demand growth and to connect isolated systems to the grid. e transmission system is also intended
to support regional development to ensure availability of power supply, given the establishment of the North
Kalimantan province, which will result in increasing electricity demand.
With the establishment of the North Kalimantan province, it is expected that the electricity demand in the next
few years will grow higher, especially in big cities: Tanjung Selor (the province’s capital) and Tana Tidung and
Malinau (regency capital cities). e North Kalimantan Interconnection System in Kalseltengtim is a 150 kV
transmission network connecting Muara Wahau – Tanjung Redep – Tanjung Selor and is expected to be ready
in 2018.
SYSTEM PLANNING
PT PLN (Persero)
SOUTH AND CENTRAL KALIMANTAN SYSTEM
/
SS 500 kV Existing / Plan
SS 275 kV Existing / Plan
CF
GT
/ CF
/ GT
CFPP Existing / Plan
GTPP Existing / Plan
2013
2013
/
/ SS 150 kV Existing / Plan GEO / GEO GEOPP Existing / Plan
/ SS 70 kV Existing / Plan H / H HEPP Existing / Plan Bangkanai GEPP 140 MW – 2015
/ SS 500/275 kV Existing / Plan CC CC
CCPP Existing / Plan Bangkanai GT/GE PP 2x70 MW – 2016/17
/
/
SS 500/275/150 kV Existing / Plan GE
/
/ GE GEPP Existing / Plan 2015
2015 to
/
SS 275/150 kV Existing / Plan MH / MH
MHPP Existing / Plan
SS 150/70 kV Existing / Plan D / D
Diesel PP Existing / Plan Melak SS
/ T/L 70 kV Existing / Plan PP Existing (East
/ T/L 150 kV Existing / Plan PP Plan Puruk Cahu Kalimantan)
/ T/L 275 kV Existing / Plan ACSR 2x240 mm2 GE
/ T/L 500 kV Existing / Plan Edit November 2013
ACSR 2x240 mm2
D 47 km - 2015
2xZebra
2013
2013
96 km - 2016 50 km - 2014
D Muara Teweh
Kuala Kurun
D
to
ACSR 2x240 mm2 Kuaro SS
110 km - 2014
ACSR 2x240 mm2
2012
2012 (East
Kalimantan)
Kalselteng 1 CFPP
120 km - 2016 2012
2012
2x100 MW – 2018/19
CF Buntok
2011
20
011 D
ACSR 2x240 mm2
130 km - 2014 2 ACSR 2x240 mm2
ACSR 2x240 mm2
65 km - 2013
2010
2010
142 km - 2013
Kasongan D
Parenggean Kalsel CFPP (FTP 2)
Palangkaraya
2x100 MW – 2017/18 Tanjung
CF
D New
Nangabulik
Pangkalan ACSR 1x240 mm2 ACSR 2x240 mm2 Palangkaraya
Banteng Sampit 80 km - 2013 Amuntai
172 km - 2014
CF D
D
CF
Muara Wahau
Embalut (Expansion) CFPP Maloi
1x50 MW – 2014 ACSR 2x240 mm2
80 km - 2017 Kaltim Peaker 3 GT/GE PP
Kaltim 4 CFPP Sepaso 50 MW – 2021
100 MW – 2018
Sangatta Kaltim CFPP (FTP2)
G 2x100 MW – 2017/18
CENTRAL Bontang CF
WEST GT
Kaltim Peaking GTPP
KALIMANTAN 2x50 MW – 2014
KALIMANTAN Melak Kota Bangun New Smd
to Bangkanai CF Sambera Kaltim (Mine Mouth) CFPP
GT/GE PP 2x27.5 MW – 2018
(Central Sambutan
SYSTEM PLANNING ACSR 2x240 mm2 Kaltim 3 CFPP
PT PLN (Persero) Kalimantan) 100 km - 2015
NORTH AND EAST KALIMANTAN SYSTEM 2x150 MW – 2020/21
Karangjoang CF
SS 500 kV Existing / Plan Sepaku Senipah GTPP
/
CF
/ CF CFPP Existing / Plan GT
SS 275 kV Existing / Plan 2x41 MW – 2014
GTPP Existing / Plan Kariangau CC
/
/ SS 150 kV Existing / Plan
GT
GEO
/ GT
/ GEO GEOPP Existing / Plan ACSR 2x240 mm2 CF G Manggarsari Senipah (ST) CCPP
CENTRAL
SS 70 kV Existing / Plan 155 km - 2015 New Balikpapan
/
/ SS 500/275 kV Existing / Plan
H / H HEPP Existing / Plan Industri 35 MW – 2017 SULAWESI
CC
/ CC
CCPP Existing / Plan
/ SS 500/275/150 kV Existing / Plan GE / GE GEPP Existing / Plan Petung Kaltim Peaker 2 GT/GE/CC PP
/ 100 MW – 2016
SS 275/150 kV Existing / Plan MH / MH
MHPP Existing / Plan Longikis
/
SS 150/70 kV Existing / Plan D / D
Diesel PP Existing / Plan Kuaro ACSR 2x240 mm2
Muara Jawa/Teluk Balikpapan CFPP (FTP1)
/ T/L 70 kV Existing / Plan PP Existing 47 km - 2015
2x110 MW – 2014
/ T/L 150 kV Existing / Plan PP Plan Komam
/ T/L 275 kV Existing / Plan To Tanjung SS Grogot SOUTH SOUTH
/ T/L 500 kV Existing / Plan Edit November 2013 (South Kalimantan)
KALIMANTAN SULAWESI
Demand for High Speed Diesel (HSD) and Marine Fuel Oil (MFO) in the Kalseltengtimra system is expected
to trend downwards, from 598,000 kiloliters in 2013 to 69,000 kiloliters in 2022, while the use of coal will
increase from 1.5 million tons in 2013 to 6.5 million tons in 2022. e volume of gas utilization in the form of
CNG and LNG will also increase from 3 bcf in 2013 to 22 bcf in 2022. Electricity production from hydro-power
will also increase from 106 GWh in 2013 to 580 GWh in 2022.
16,000
14,000
12,000
10,000
2013 - 2022
GWh
8,000
6,000
4,000
2,000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
e planned additional new generating capacity in North Sulawesi is relatively large, as can be seen from the
annual reserve margin, which lies between 34% and 58%. A high reserve margin of 58% has been planned
due to uncertainty of completion of the Kotamobagu I and II geothermal power plants. In 2013 and 2014, the
reserve margin is relatively low. is is mainly due to delays to several projects, namely the Sulut 1 coal-fired
power plant, Minahasa combined cycle gas turbine or gas turbine/engine peaker plant, Lahendong V and VI
geothermal plants, which are behind the original schedule. e power generation plan for North Sulawesi is
shown in Table-10.
New power generation capacity planned during the period 2013 - 2022 is 1,087 MW, consisting of coal fired
power plants (675 MW), geothermal power plant (120MW), gas fired turbine/engine peaker with gas storage
(250 MW) and hydro-electric plants (44 MW).
Projects 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Demand Sulut - Gorontalo - Tolitoli Interconnection
(2016)
Energy production GWh 1,777 2,000 2,182 2,536 2,787 3,075 3,391 3,740 4,119 4,539
Load Factor % 65 65 66 65 65 66 66 66 66 67
Peak Load MW 311 349 379 445 487 535 587 645 708 777
Supply
Installed Capacity MW 386 386 386 282 195 195 195 195 195 195
Net Capacity MW 336 336 336 232 168 168 168 168 168 168
PLN 22.6 MW 227 227 227 227 164 164 164 164 164 164
IPP 5.3 MW 4 4 4 4 4 4 4 4 4 4
Rental MW 104 104 104 - - - - - - -
Retired & Mothballed - - - - 63 - - - - -
Additional Capacity
Rental
Amurang (2x25) Rental CFPP CFPP 50
PLN On Going & Committed
Gorontalo (FTP1) CFPP 50
Sulut I (FTP1) CFPP 25 25
IPP On Going & Committed
Molotabu CFPP 20 -
Gorontalo (Terkendala) CFPP 12*)
PLANNED ADDITIONAL CAPACITY
Tolitoli CFPP 15 30
Sulut 3 CFPP 100
Sulbagut 1 CFPP 50 50
Sulbagut 2 CFPP - 100 100
Sulbagut 3 CFPP 60
Poigar 2 HEPP 30
Sawangan HEPP 12
Minahasa Peaker GT/GE/CCPP - 150
RUPTL
e use of coal is expected to increase from 172,000 tons in 2012 to 1.73 million tons in 2022, or an increase
of 10 times. LNG will be used from 2016 at 3 bcf and will increase to 4 bcf in 2022. LNG will be used to ope-
rate peaking power plants. e use of geothermal energy will continue to increase from 552 GWh in 2013 to
797 GWh in 2022. e increase in hydropower is relatively small since the potential is low - from 215 GWh in
2013 to 369 GWh in 2022.
5.000
4.500
4.000
3.500
3.000
GWh
2.500
2.000
1.500
1.000
500
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
e integration of the Sulbagsel system which comprises Central Sulawesi (Sulteng), West Sulawesi (Sulbar),
South East Sulawesi (Sultra) and South Sulawesi (Sulsel), is planned to be completed in 2014. Presently, the
Central Sulawesi system relies on supply from Tawaeli 2x15 MW coal-fired IPP, PLN and rental diesel engine
plants. In 2014, additional supply will be obtained from Poso hydro power plant after the 150 kV transmission
line between Poso hydro power and New Palu is in operation. e Sulteng and Sulbar systems will be intercon-
nected with the Sulsel system through the Poso – Palopo 275 kV transmission line and the Silae – Pasangkayu
150 kV transmission line. With this interconnection, the use of coal-fired power plants on a larger scale can be
implemented in Central Sulawesi.
e Sulsel system receives sufficient supply of power from the Jeneponto coal-fired IPP, Barru coal-fired plant
and Poso hydro power plant. In the Sultra system, the shortage of power has not been fully resolved due to
the lack of reliability of Kendari 2x10 MW coal-fired power plant (Fast Track 1 Project), which still requires im-
In order to meet long term electricity needs over the period of 2013 - 2022, non-oil power plant projects with
a total capacity of 3,639 MW in System Sulbagsel have been planned. ese projects consist of hydro power/
mini-hydro power plants (1,392 MW), coal-fired power plants (1,475 MW), combined cycle gas-fired turbine/
engine plants (600MW) and geothermal power plants (95 MW). Within the plan includes the Karama 450 MW
hydro power project in West Sulawesi. Karama is a hydro power project involving an unsolicited IPP procur
ement process which will be carried out by the PPP scheme. e power generation development plan for Sul-
bagsel is shown in Table-11.
e transmission system development plan in Sulbagsel system (Figure-21) is as follows: 275 kV transmission
line connecting Karama hydro power plant – Mamuju – Enrekang – Sidrap – Makassar (Daya Baru) – Bantaeng,
together with a 275/150 kV EHV substation, to evacuate 450 MW of power from the Karama plant; 275 kV
transmission line connecting Enrekang – Palopo, in anticipation of the Poso II hydro power, to be developed
simultaneously to improve system stability (especially Kendari), as well as gain operational flexibility; 275 kV
EHV substation at Enrekang to evacuate power from Bonto Batu, Poko, Malea, as well as Bakaru II hydro
power and channeled to the load center through the 275 kV Enrekang – Sidrap – Makassar – Bantaeng trans-
mission line.
Palu 3 CFPP
2x50 MW - 2018 Tawaeli Expansion CFPP
2x15 MW - 2016
Ampana CFPP
Marana/Masaingi (FTP2) GeoPP 2x3 MW–2016
CF 20 MW - 2022
CF
GEO
Palu GEO
Luwuk
Baru
Poso
Toili
CENTRAL GE
Luwuk Peaker GEPP
Pasangkayu SULAWESI 2x10 MW–2016/18
Poso HEPP
3x65 MW
H
WEST Poso 2 HEPP
H Tentena
2x66 MW – 2021/22
SULAWESI Kolonedale
Mamuju H
Baru
Malea HEPP Malili to to
CF
2x45 MW – 2017 Barru SS
Mamuju Wotu Sidrap SS
Pangkep
Bungku
Bakaru II HEPP
2x63 MW – 2020 Tonasa
Tello GTPP
123 MW
H
Palopo
SOUTH EAST
2013 - 2022
H Makassar Peaker GT/GE/CC PP
Bonto Batu HEPP 300 MW-2016 Maros
Makale 2x50 MW – 2017 SULAWESI 150 MW-2017
Bosowa
150 MW-2018 G Mandai
Polman HH H Wotunohu HEPP Tallo G Daya Kima
Majene Lasusua
15 MW – 2021 Lama
Bakaru Enrekang Bontoala Daya Baru
Kendari/Nii Tanasa CFPP Tello
H Konawe HEPP
2x10 MW Panakukang
Poko HEPP 2x25 MW – 2021
2x117 MW – 2020/21 Siwa Kendari (Expansion) CFPP Tanjung Sungguminasa
1x10 MW - 2014 Bunga
Bakaru 1 HEPP
Pinrang Sidrap SOUTH Kendari 3 CFPP
2x63 MW Pare
D SULAWESI H CF
CF
CF
2x50 MW – 2018 to
Takalar to
Sengkang GTPP (GT 22) Kolaka Laenia GeoPP Tallasa SS
Sengkang Kendari P 2x10 MW - 2022 CFPP
60 MW – 2013 Unaaha
GT
CC
Sulsel Barru CFPP GE Sengkang CCPP (ST 28)
2x50 MW 60 MW – 2013
CF Soppeng
Sulsel Barru 2 CFPP CF Wajo GEPP
2x50 MW - 2016 20 MW – 2015
Barru Raha (FTP2) CFPP
2x3 MW – 2016
Andolo
Bone
Raha 2 CFPP
2x3 MW – 2018
Pangkep
angkep
a Tonasa
T
Tona
ona
CF
Maros Kajuara Raha
Bosowa
Bos Kasipute
T oD
Tello Bau-Bau CFPP Wangi-Wangi CFPP
G 2x7 MW - 2014 2x3 MW – 2015/16
Daya Baru
Sungguminasa
asa
a Sinjai
Bau-Bau CFPP
CF
2x10 MW – 2014/15
CF
Bau-Bau 2 CFPP
CF CF
Bantaeng 2x10 MW – 2018/19 CF
Jeneponto Bulukumba Bau-Bau
Tallasa
Sulsel 2 CFPP Bantaeng
2x200 MW – 2018/19 Punagaya CF Smelter
Sulsel-3/Takalar CFPP CF CF
2x100 MW – 2022
Punagaya CFPP (FTP2)
2x100 MW – 2016
Jeneponto CFPP SYSTEM PLANNING
2x100 MW PT PLN (Persero)
SULAWESI SYSTEM
Jeneponto 2 CFPP
2x100 MW – 2016 SS 500 kV Existing / Plan
/
CF
/ CF CFPP Existing / Plan
/ SS 275 kV Existing / Plan GT / GT GTPP Existing / Plan
/ SS 150 kV Existing / Plan GEO / GEO GEOPP Existing / Plan
/ SS 70 kV Existing / Plan H / H HEPP Existing / Plan
/ SS 500/275 kV Existing / Plan CC CC
CCPP Existing / Plan
/
/ SS 500/275/150 kV Existing / Plan GE / GE GEPP Existing / Plan
/
/
SS 275/150 kV Existing / Plan MH / MH
MHPP Existing / Plan
SS 150/70 kV Existing / Plan D / D
Diesel PP Existing / Plan
/ T/L 70 kV Existing / Plan PP Existing
/ T/L 150 kV Existing / Plan PP Plan
/ T/L 275 kV Existing / Plan
/ T/L 500 kV Existing / Plan Edit December 2013
e development of the transmission grid throughout Sulawesi for the period 2013 - 2022 covers 7,751 kms
and requires investments of US$1.082 billion.
Projected power generation in Sulbagsel from 2013 to 2022 is shown in Figure-22. Power generation from
oil in 2013 is expected to remain high, at 1,250 GWh (22%). However, beginning from 2018, power gene-
rated from oil will be replaced by power generated from natural gas in the form of LNG when the Makassar
gas turbine/engine peaker plant and coal fired power plant become operational. Power generated from gas
fired power plants will increase nominally but decrease in terms of percentage, i.e. from 1,693 GWh (33%) in
2013 to 2,902 GWH (18%) in 2022. is is due to additional capacity from gas fired power plants (Sengkang
combined cycle gas-fired plant) owned by the private sector and peaker power plants running on LNG. Power
generated from coal fired power plants will increase from 1,706 GWh (30%) in 2013 to 9,160 GWh (57%) in
2022. Power generated by hydropower will increase from 1,127 GWh (20%) in 2013 to 3,650 GWh (23%) in
2022 when several hydropower projects become operational, namely Bonto Batu, Malea, Karama, Bakaru II,
Poko, Poso II, Konawe and Watunohu.
Oil consumption in the Sulbagsel system is expected to decrease from 297,000 kiloliters in 2013 to 57,000
kiloliters in 2022 after non-BBM plants become operational. e use of coal will continue to increase from
1.06 million tons in 2013 to 5.6 million tons in 2022, or an increase of 5 times. e volume of natural gas
usage, including LNG, will also continue to rise from 13 bcf in 2013 to 24 bcf in 2022. LNG will only be used
for operating peaking power plants. Production from geothermal plants amounting to 479 GWh will commence
in 2022. e use of hydropower will increase sharply given the construction of many new hydro power plants,
increasing from 1,127 GWh in 2013 to 3,650 GWh in 2022, or an increase of 3 times.
16,000
14,000
12,000
10,000
GWh
8,000
6,000
4,000
RUPTL
2,000
-
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Solar/Hybrid HSD MFO LNG Gas Coal Geothermal Hydro
PLN has prepared a development plan for New and Renewable Energy (EBT) as shown in Table -13. e deve-
lopment plan comprises of 1) Mini hydro power plants: PLN encourages the development of mini-hydro plants
by the private sector to meet the local demand and to be distributed to the PLN grid 2) Wind turbine generat-
ing plants: As the potential for wind power in Indonesia is limited, the development of wind turbine generating
2013 - 2022
plants will be limited to areas with wind power potential 3) Biomass: PLN intends to build biomass power
plants if PLN has control over the biomass supply. PLN cooperating with several local government for biomass
industry pioneer 4) Marine energy: While the potential of marine energy is estimated to be large, the techno-
logy and economics of marine power plant development are still unknown, hence PLN will conduct small scale
pilot tests as research and development projects 5) Biofuel: Depending on the readiness of the biofuel market,
PLN is prepared to utilize biofuel if it is available 6) Solar power plants: PLN will develop solar plants in 1,000
locations/islands, especially in outlying and isolated areas to improve the electrification ratios.
Taking into account the wide geographical distribution of the population and difficulties in reaching remote
areas, PLN plans to build solar power plants as follows: centralized/communal solar power plants (indepen-
dent or hybrid operating mode); small scale and dispersed solar home systems (solar panel + LED lamps with
battery), limited to provinces where application of renewable energy is still low and in areas where there will be
no conventional electricity available within 5 years. e development of these solar power plants is intended to
electrify remote areas as soon as possible, avoid utilization of oil if they are served by diesel engine generating
units, and to reduce the generation costs in certain areas where transportation of oil is very expensive, e.g.
around the mountain peaks of Jayawijaya Papua. e electrification program with solar home systems or “su-
per energy saving” lantern (SEHEN) is not a capacity development program for the power system. e SEHEN
electrification program is intended to be a temporary program and is limited to areas with low electrification
ratios, such as in West Nusa Tenggara, East Nusa Tenggara and Papua, after first conducting a feasibility
study. e SEHEN program can be substituted by centralized/communal solar power plants. e construction
of solar power plants and installation of solar home system will be preceded by a feasibility study.
New and
renewable
No Capacity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Total
energy power
plant
1 MHPP MW 33 42 96 149 237 192 186 156 190 200 1,481
2 Solar Power MWp 6 104 75 54 36 60 75 75 75 75 634
3 Wind Power MW - - 50 20 20 20 30 40 50 50 280
4 Biomas PP MW 48 10 15 20 30 40 50 50 50 50 363
5 Ocean PP MW - - 1 - 1 3 3 5 5 10 28
6 Biofuel PP ousand Kilo 15 400 400 500 500 600 600 600 600 600 4,815
Liter
Total MW 87 156 237 243 324 315 344 326 370 385 2,786
Besides the 6 interconnected power systems, there are more than 100 isolated systems spread throughout
the Eastern Indonesia region. e systems are spread over the provinces of Maluku, North Maluku, Papua,
West Papua, West Nusa Tenggara, East Nusa Tenggara and Riau Islands. Even in islands where the power sys-
tems are interconnected, there are isolated systems such as in Nias, Belitung, Buton, Selayar, Karimun Jawa,
Bawean and many other islands.
RISK ANALYSIS
Based on the probability and impact if the risks occur, the risks have been mapped as shown in Figure-23. e
assessment of the risks and impact have been conducted with qualitative method based on PLN’s experience
in carrying out similar programs in the past, and PLN’s experience in handling such risks in the past.
RUPTL
Determination of the risk impact is based on the impact to company cash flow and the impact on smooth
operation of the company.
Medium
Low
Very Low
IMPACT SCALE
Description :
EXTREME RISK : HIGH RISK :
3 Limited funding capability risk 1 Change in electricity sector order/policy risk
4 PLN and IPP project completion delay risk 2 Unrealized electricity tariff rationalization risk
5 Unconformity power plant and transmission line risk 6 Non-oil primary energy supply constrain risk
10 Increase of primary energy price risk 7 Electricity consumption higher than demand projection risk
8 Power plant and transmission performance degradation risk
9 Transmission line system bottlenecking risk
11 Environmental risk
12 Disaster risk
CONCLUSION
Assuming the economic growth during the next ten years average 6.9% and increasing from actual electricity
2013 - 2022
demand in 2012, projected electricity sales in 2022 are estimated to reach 387 TWh or a growth rate of 8.4%
over the next 10 years. Peak load in 2022 is projected to reach 64 GW. To meet electricity demand, the deve-
lopment of new power plants during the period 2013-2022 with total capacity of 60 GW has been planned.
In line with the development of aforementioned power plants, the development of 57,100 kms of transmis-
sion system will be required, consisting of 5,600 kms of 500 kV AC EHV transmission lines, 1,100 kms of 500
kV HVDC transmission lines, 462 kms of 250 kV HVDC transmission lines, 6,400 kms of 275 kV AC transmis-
sion lines, 39,600kms of 150 kV HV transmission lines and 3,900 kms of 70 kV HV transmission lines. Addi-
tional transformer capacity required include 134,000 MVA consisting of 72,900 MVA 150/20 kV transformers,
3,700 MVA 70/20 kV and 35,700 MVA 500/150 kV inter-bus transformers (IBT), 17,100 MVA 275/150 kV
IBT, 480 MVA 150/70 kVIBT, 4,000 MVA 500/275 kV IBT and 600 MVA 250 kV DC. In anticipation of electric-
ity sales growth during the period 2013 - 2022, it will require additional 224,800 kms of medium voltage grids,
217,200 kms of low voltage grid and 35,600 MVA of distribution transformer capacities.
e funds for PLN investment will be met by the State Budget (APBN) in the form of Government equity parti-
cipation, new loan, and internal funds. PLN’s internal funding capacity is limited and as such, all funds required
for investment will be obtained from debt. PLN’s investment needs to be supported by increasing capacity
for self-funding and maintaining the ratio of debt to PLN’s assets, so that it would continue to support the
development of electrical power supply. e role of APBN each year will be significant because it is politically
difficult to raise electricity tariff to a level higher than the basic generating cost (BPP) in the near term.
RUPTL