4th Ra Bill For Sirsala 12.1.2023 (Revised)
4th Ra Bill For Sirsala 12.1.2023 (Revised)
1 2 nd R.A. Bill
2 Recvory Statement
3 Steel Consumption
4 Cement Consumption
5 Work-Order
6 Third Party Inspection Report
4
1 2 3 4 5 6 7 8 9 10
JAL JEEVAN MISSION
NAME OF WORK : SIRSALA AND 4 VILLAGES R.W.S.SCHEME TQ: SILLID
Sub Work No.3:Approach Bridge
Item No.3:Providing & laying In situ M150 for PCC M.B. N0/P.No.
3.81 PCC M-15 5854.36 cum 22305 22305 2469/926
Total of Sub-Work No.3 :- 22305 22305
Advance Payment for works done of Qty. Items Work (Grouped under sub heads) or sub works of estimate Rate Unit Payment on the basis actual Remarks
yet measured executed up measurement
to date as
Total as per Since Total per Uptodate Amount Since Previous
Previous Bill previous upto measure- Amount
Bill Date ment book
1 2 3 4 5 6 7 8 9 10
149.00
Item No.7:Reffing the trenches ……Complete. 71.40 Cum 76,890 0 2119/412
1076.89 Reffing . 84.00
Total of Sub-Work No.7 :- 4,486,046 0
6339.00 8309.00 b)150 mm dia, DI K-9 1163.20 Rmt 9665029 6213815 2119/405
(Note: 80 % Payments Prop. As per Work-order ) 1454.00
Advance Payment for works done of Qty. Items Work (Grouped under sub heads) or sub works of estimate Rate Unit Payment on the basis actual Remarks
yet measured executed up measurement
to date as
Total as per Since Total per Uptodate Amount Since Previous
Previous Bill previous upto measure- Amount
Bill Date ment book
1 2 3 4 5 6 7 8 9 10
Item No.8:Lowering , Laying & Jointing D.I.Pipes
2103 2103.00 etc………Complete.
200 mm diaD.I.K-9 Pipe. 96.05 Rmt 201,993 0 2469/916
(Note: 85% Payments Prop. ) 113.00
Item No.12:Reffing the trenches ……Complete. 71.40 Cum 222,363 29,811 2469/919
3114.33 Reffing . 84.00
(Note: 85% Payments Prop. )
Total of Sub-Work No.11 :- 17,703,751 7,667,881
Advance Payment for works done of Qty. Items Work (Grouped under sub heads) or sub works of estimate Rate Unit Payment on the basis actual Remarks
yet measured executed up measurement
to date as
Total as per Since Total per Uptodate Amount Since Previous
Previous Bill previous upto measure- Amount
Bill Date ment book
1 2 3 4 5 6 7 8 9 10
709.62 Murm bedding 75.60 Cum 53,647 29,502 2469/925
84.00
Item No.8:Lowering , Laying & Jointing D.I.Pipes
2839.00 etc………Complete.
a) 100 mm diaD.I.K-7 Pipe. 54.40 Rmt 154,442 0 2469/912
64.00
Item No.12:Refilling the trenches ……Complete. 71.40 Cum 338,470 195,080 2469/926
4740.48 Refilling . 84.00
757271967.xlsx3rd RA BILL 7
8
Advance Payment for works done of Qty. Items Work (Grouped under sub heads) or sub works of estimate Rate Unit Payment on the basis actual Remarks
yet measured executed up measurement
to date as
Total as per Since Total per Uptodate Amount Since Previous
Previous Bill previous upto measure- Amount
Bill Date ment book
1 2 3 4 5 6 7 8 9 10
Item No.1 Designing ( aesthctilly) and constructing
RCC GSR ….........etc complete.
1 a) RCC Sump Cap.0.75 L.L. 264776.00 No 264,776 241,413 2470/970
778753.00
Total of Sub-Work No:14:- 264,776 241,413
Total of All Sub-Work 42586574 17319821
As per A/C tender 19.55% above 8325675 3386025
Total 50912249 20705846
Add 18% GST 9164205 3727052
Grand Total 60076454 24432898
Deduction Last RA BILL 35643558 0.00
Net 4 th R.A. BILL 24432896 24432898 -2
Say Rs 24432896
Total Value of work done to date (A)
Figure (D) in words Deduct Value or works shown on previous bill
Net value of work since previous bill (E) Figure
in words
757271967.xlsx3rd RA BILL 8
Part-II Account of Second Advance allowed on the Security of materials brought to site
Quantity Deduct Quantity Full rate as Description of Material Unit Reduced upto date Reference to Reason or nonclearance of
out quantity outstandin assessed rate at amount of divisional Officers advance when outstanding
standing utilitized in g including by the which advance written orders for more than three month
from work quantity Divisional advance authorising the
previous bill measured brought to officer is made advance
since site since
previous previous
bill bill
No. Date
1 2 3 4 5 6 7 8 9 10 11
1. Certified (i) that addition to and quite from the quantities of the work actually executed as shown in column in 4 of part-I some work has been actually done in connection with
serveral items and the value of such work apart afer (deducting) the reform the proportinate amount of secured advance if ultimately recorable on account of the quantities
of materials used thein) is in no case less than the advance payments asper columns 3 of part-I made or purposed to be made for the convenince of the contractor of in
annotification and subject to the result of depad m,easurement which will be made as soon as possible.
2. Certificate (i) that the plus quantities of material shown in column 3 of part-II above have been actually brought the contractor to the work and the contractor has nor
previous any advance on their security (ii) that the materials are of on imperisheble nature and all are required by the contractor for use in the work in connection with
items for which the for finished work have arranged upon and (iii) that formal agreements in form 50 signed and executed by the contractor in accordance with paragraph
10-2-19 of the M.P.
Sub Divisional Engineer
Maharashtra Jeevan Pradhikaran,
Sub-Dn no 2 Aurangabad
Dated Signature of the Contractor Dated Signature of Officer Preparing the bill
* The signature is necessary only when the officer preparing the bill is not the officer authorising payment Dated Signatur of Officer authorising payment
Outer P.W. 410 c.
FORM 47
RUNNING ACCOUNT BILL
Referred to in Paragraph 10-2-11 of M.P.W.A.Code
For
Extension granted up to :
Gazetted Officer
Payment-IV Memorandum of Payments
1) Total Value actually measured asper part-1 Column B, Entry (A) Rs. Ps.
2) Total up-to-date Advance payment for work not yet measured asper part-1
Column 3 Entry (b)
c) by cheque
* Here specify the net amount payable, vide item 8 (e) dated initials of Disbursing Officer
Stamp
Dated
Witness : (Full Signature of Contractor)
Dated
Paid by me vide Cheque Dated initian of the person actually making the payment
Part-V R E M A R K S
(This space is reserved for any remarks the disbursing officer or the Executive Engineer may wish the record in respect of the
NIL
Sub-Work No: 13
RCC ESR @ Pangri 0.00 0.00 0.879 0.435 0.257 0.701 2.27 M.T.
1 2 3 4 5 6 7
Sub-Work No: 13 RCC Elevated Service Reservoirs
Item No: 3:- Providing , & Laying in situ M-15. Cement brought by
PCC M-15 62 contractor
9.87 6.27 61.88
Item No: 4:- Providing , & Casting in situ M-30.
RCC M-30 61.96 9.2 570.03 571
Sub-Work No: 03 RCC Approach Bridge
Item No: 3:- Providing , & Laying in situ M-15.
PCC M-15 3.81 6.27 23.89 24
Total Qty 657
i.e. 32.84 M.T.
Page 14 of 19
Bottom Mesh raft slab without bentup bar @12mm 150mm c/c x and Y
spacing
SR no dia of slab in radius of slab spacing from h total no of bar total length
centre
1 13.6 6.8 0 0 0.1 1 6.80
2 13.6 6.8 0.15 0.15 0.1 47 6.80
3 13.6 6.8 0.15 0.3 0.1 47 6.79
4 13.6 6.8 0.15 0.45 0.1 47 6.79
5 13.6 6.8 0.15 0.6 0.1 47 6.77
6 13.6 6.8 0.15 0.75 0.1 47 6.76
7 13.6 6.8 0.15 0.9 0.1 47 6.74
8 13.6 6.8 0.15 1.05 0.1 47 6.72
9 13.6 6.8 0.15 1.2 0.1 47 6.69
10 13.6 6.8 0.15 1.35 0.1 47 6.66
11 13.6 6.8 0.15 1.5 0.1 47 6.63
12 13.6 6.8 0.15 1.65 0.1 47 6.60
13 13.6 6.8 0.15 1.8 0.1 47 6.56
14 13.6 6.8 0.15 1.95 0.1 47 6.51
15 13.6 6.8 0.15 2.1 0.1 47 6.47
16 13.6 6.8 0.15 2.25 0.1 47 6.42
17 13.6 6.8 0.15 2.4 0.1 47 6.36
18 13.6 6.8 0.15 2.55 0.1 47 6.30
19 13.6 6.8 0.15 2.7 0.1 47 6.24
20 13.6 6.8 0.15 2.85 0.1 47 6.17
21 13.6 6.8 0.15 3 0.1 47 6.10
22 13.6 6.8 0.15 3.15 0.1 47 6.03
23 13.6 6.8 0.15 3.3 0.1 47 5.95
24 13.6 6.8 0.15 3.45 0.1 47 5.86
25 13.6 6.8 0.15 3.6 0.1 47 5.77
26 13.6 6.8 0.15 3.75 0.1 47 5.67
27 13.6 6.8 0.15 3.9 0.1 47 5.57
28 13.6 6.8 0.15 4.05 0.1 47 5.46
29 13.6 6.8 0.15 4.2 0.1 47 5.35
30 13.6 6.8 0.15 4.35 0.1 47 5.23
31 13.6 6.8 0.15 4.5 0.1 47 5.10
32 13.6 6.8 0.15 4.65 0.1 47 4.96
33 13.6 6.8 0.15 4.8 0.1 47 4.82
34 13.6 6.8 0.15 4.95 0.1 47 4.66
35 13.6 6.8 0.15 5.1 0.1 47 4.50
36 13.6 6.8 0.15 5.25 0.1 47 4.32
37 13.6 6.8 0.15 5.4 0.1 47 4.13
38 13.6 6.8 0.15 5.55 0.1 47 3.93
39 13.6 6.8 0.15 5.7 0.1 47 3.71
40 13.6 6.8 0.15 5.85 0.1 47 3.47
41 13.6 6.8 0.15 6 0.1 47 3.20
42 13.6 6.8 0.15 6.15 0.1 47 2.90
43 13.6 6.8 0.15 6.3 0.1 47 2.56
44 13.6 6.8 0.15 6.45 0.1 47 2.15
45 13.6 6.8 0.15 6.6 0.1 47 1.64
46 13.6 6.8 0.15 6.75 0.1 47 0.82
r @12mm 150mm c/c x and Y direction
no of bend total
no of Gross
mat L covr 90 degree cutting lapping wt in kg
sides length
2nos length
0.1 0.05 0.048 6.80 0.6 4 27.81 24.75
0.1 0.05 0.048 6.80 0.6 8 55.00 48.95
0.1 0.05 0.048 6.80 0.6 8 54.96 48.92
0.1 0.05 0.048 6.79 0.6 8 54.90 48.86
0.1 0.05 0.048 6.78 0.6 8 54.80 48.78
0.1 0.05 0.048 6.76 0.6 8 54.68 48.67
0.1 0.05 0.048 6.74 0.6 8 54.54 48.54
0.1 0.05 0.048 6.72 0.6 8 54.36 48.38
0.1 0.05 0.048 6.70 0.6 8 54.16 48.20
0.1 0.05 0.048 6.67 0.6 8 53.93 48.00
0.1 0.05 0.048 6.63 0.6 8 53.68 47.77
0.1 0.05 0.048 6.60 0.6 8 53.39 47.52
0.1 0.05 0.048 6.56 0.6 8 53.08 47.24
0.1 0.05 0.048 6.52 0.6 8 52.73 46.93
0.1 0.05 0.048 6.47 0.6 8 52.36 46.60
0.1 0.05 0.048 6.42 0.6 8 51.95 46.24
0.1 0.05 0.048 6.36 0.6 8 51.52 45.85
0.1 0.05 0.048 6.31 0.6 8 51.05 45.43
0.1 0.05 0.048 6.24 0.6 8 50.54 44.98
0.1 0.05 0.048 6.18 0.6 8 50.01 44.51
0.1 0.05 0.048 6.10 0.6 8 49.44 44.00
0.1 0.05 0.048 6.03 0.6 8 48.83 43.46
0.1 0.05 0.048 5.95 0.6 8 48.18 42.88
0.1 0.05 0.048 5.86 0.6 8 47.49 42.27
0.1 0.05 0.048 5.77 0.6 8 46.77 41.62
0.1 0.05 0.048 5.67 0.6 8 46.00 40.94
0.1 0.05 0.048 5.57 0.6 8 45.18 40.21
0.1 0.05 0.048 5.46 0.6 8 44.31 39.44
0.1 0.05 0.048 5.35 0.6 8 43.40 38.63
0.1 0.05 0.048 5.23 0.6 8 42.43 37.76
0.1 0.05 0.048 5.10 0.6 8 41.40 36.85
0.1 0.05 0.048 4.96 0.6 8 40.31 35.87
0.1 0.05 0.048 4.82 0.6 8 39.15 34.84
0.1 0.05 0.048 4.66 0.6 8 37.91 33.74
0.1 0.05 0.048 4.50 0.6 8 36.60 32.57
0.1 0.05 0.048 4.32 0.6 8 35.19 31.32
0.1 0.05 0.048 4.13 0.6 8 33.68 29.97
0.1 0.05 0.048 3.93 0.6 8 32.05 28.52
0.1 0.05 0.048 3.71 0.6 8 30.28 26.95
0.1 0.05 0.048 3.47 0.6 8 28.35 25.23
0.1 0.05 0.048 3.20 0.6 8 26.22 23.33
0.1 0.05 0.048 2.90 0.6 8 23.83 21.21
0.1 0.05 0.048 2.56 0.6 8 21.09 18.77
0.1 0.05 0.048 2.16 0.6 8 17.84 15.88
0.1 0.05 0.048 1.64 0.6 8 13.71 12.20
0.1 0.05 0.048 0.83 0.6 8 7.20 6.41
Total length and weight of bar 1966.28 1749.99
MAHARASHTRA JEEVAN PRADHIKARAN DIVISION AURANGABAD
MAHARASHTRA JEEVAN PRADHIKARAN SUB- DIVISION VAIJAPUR
::- MUKKHYMANTRI RURAL DRINKING WATER SUPPLY PROGRAMME -::
NAME OF WORK :- Chapaner & 2 Villages Water supply scheme Tq.Kannad , Dist.Aurangabad Bill No: vth
NAME OF AGENCY :-M/S G.S.R. Construction @ Aurangabad
Agreement No: B-1/12 for the Year 2017-18
::- STATEMENT SHOWING THE ROYALITY CHARGES FOR SAND, MURUM, STONE ETC. -::
Sr. Item Particulars of Item Qty Unit Metal Royality Amount of Sand Royality Amount Murum / Stone Royality Amount of Total Remarks
No. No. Charges metal (7x8) Charges of sand Charges of Murum Amount
for metal of sand Murum (15x16) (9+13+17)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19