0% found this document useful (0 votes)
35 views12 pages

In The High Court of Judicature at Bombay Nagpur Bench, Nagpur. Writ Petition No.2365 of 2006

The document discusses a writ petition challenging an order that classified an agreement as a lease under the Maharashtra Stamps Act. It summarizes the facts of the case, arguments from both parties, and the court's consideration of whether the concession agreement constituted a lease for stamp duty purposes based on definitions in the Act.

Uploaded by

saransh yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views12 pages

In The High Court of Judicature at Bombay Nagpur Bench, Nagpur. Writ Petition No.2365 of 2006

The document discusses a writ petition challenging an order that classified an agreement as a lease under the Maharashtra Stamps Act. It summarizes the facts of the case, arguments from both parties, and the court's consideration of whether the concession agreement constituted a lease for stamp duty purposes based on definitions in the Act.

Uploaded by

saransh yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

J-WP-2365-06 1/12

IN THE HIGH COURT OF JUDICATURE AT BOMBAY


NAGPUR BENCH, NAGPUR.

WRIT PETITION NO.2365 OF 2006

Abhijeet Ashoka Infra Structure Pvt. Limited


A Company duly incorporated under the
provisions of the Companies Act, 1956 and
having its registered office at F-8 M.I.D.C.
Industrial Area Hingna, Nagpur,
Through its Director … Petitioner

-vs-

1. The Joint District Registrar (Class-I)


and The Collector of Stamps, Bhandara

2. The Chief Controlling Revenue Authority


(Appellate Authority), Maharashtra State,
Pune … Respondents

Shri D. V. Chauhan, Advocate for petitioner.


Ms Tajwar Khan, Assistant Government Pleader for respondents.

CORAM : A. S. CHANDURKAR AND VINAY JOSHI, JJ.


Arguments were heard on : 27/02/2020
Judgment is pronounced on : 06/03/2020

Judgment : (Per : A. S. Chandurkar, J)

The challenge raised in this writ petition is to the order dated

28/02/2006 passed by the Chief Controlling Revenue Authority,

Maharashtra State, Pune thereby confirming the order dated 11/11/2005

passed by the Collector of Stamps in proceedings under the Maharashtra

Stamps Act, 1958 (for short, the said Act). By the said order, the

agreement between the parties has been adjudicated as a “lease” falling

under Article 36(b) of Schedule-I to the said Act.

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 2/12

2. The facts in brief are that an advertisement was issued by the

State of Maharashtra for constructing a bridge across Vainganga river. That

work was to be done on “ Build, Operate and Transfer” (BOT) basis. The

offer made by the petitioner came to be accepted. A Concession Agreement

was accordingly entered into between the petitioner and the State of

Maharashtra through the Secretary, Public Works Department on

16/11/1998. The Collector of Stamps initiated proceedings for adjudication

of proper stamp duty payable on the said agreement. After considering the

agreement entered into by the petitioner on 05/07/2005 a communication

was issued to the petitioner in which it was stated that the agreement was in

the nature of lease as per provisions of Section 2(n)(iii) of the said Act. The

petitioner was called upon to show cause as to why stamp duty should not be

recovered in terms of Section 39(1)(b) of the said Act. According to the

petitioner the Concession Agreement could not be treated as “lease” as

defined by Section 2(n) of the said Act. The petitioner submitted its

explanation on 19/07/2005 and after exchange of communications, the

Joint District Registrar and Collector of Stamps called upon the petitioner to

pay deficit stamp duty of Rs.7,84,76,540/-. However on 11/11/2005 an

order came to be passed by the Joint District Registrar and Collector of

Stamps under Section 39(1)(b) of the said Act and the petitioner was called

upon to pay the deficit stamp duty within a period of thirty days. Being

aggrieved by that order the petitioner filed an appeal under Section 53(1A)

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 3/12

of the said Act. Though the petitioner filed an application under Section 54

of the said Act seeking a reference of the question of law to this Court no

orders were passed on that application. Ultimately by the impugned order

the appeal preferred by the petitioner came to be rejected by the respondent

No.2. Being aggrieved the said order has been challenged in this writ

petition.

3. After the writ petition was entertained and admitted by the

learned Single Judge, by virtue of administrative directions issued, the writ

petition was directed to be placed before the Division Bench. Accordingly we

have heard the learned counsel for the parties.

4. In support of the challenges raised to the impugned order Shri D.

V. Chauvan, learned counsel for the petitioner submitted that on complete

reading of the Concession Agreement which was not a registered document

it was clear that the same could not be termed to be a “lease” as defined by

Section 2(n) of the said act. The subject matter of the Concession

Agreement was the construction of a bridge over Vainganga river and the

agreement was to be executed on “BOT” basis. With a view to enable the

petitioner to recover the cost of construction it was permitted to collected

toll for a period of eighteen years and nine months which included the

construction period of two years and six months. Referring to Clause-1.13 of

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 4/12

the Concession Agreement it was submitted that the petitioner was entitled

to collect fees as notified by the Government of India under the National

Highways Act and the fees were to be retained by the petitioner collected

from the vehicles using the facility. Referring to Clause 3.14 it was

submitted that exclusive possession of any immovable property was never

handed over to the petitioner and it was merely required to undertake the

construction of the bridge. The overall control was retained by the

respondent No.1 and therefore by no stretch of imagination the Concession

Agreement could be treated as a ‘lease’. There was no relationship of lessor

and lessee between the parties nor was any land described to constitute a

lease. Referring to the judgment of the Honourable Supreme Court in

ICICI vs. State of Maharashtra and ors. (1999) 5 SCC 708 it was submitted

that as possession of the immovable property in the form of land remained

with the owners thereof and the Concession Agreement merely gave a right

to the Company to construct the bridge, the document in question could not

be treated as a lease. He also referred to the judgment of learned Single

Judge in Larsen and Toubro Ltd. and ors. vs. The State of Maharashtra and

ors. 2012(7) ALL MR 460 to substantiate his contention. He sought to

distinguish the decision of Honourable Supreme Court in State of

Uttarakhand and ors. vs. Harpal Singh Rawat (2011) 4 SCC 575 by

submitting that in that case the agreement in question specifically permitted

collection of toll which clarified the intention of the parties. He also

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 5/12

submitted that the decisions of the Allahabad and Andhra Pradesh High

Courts referred to in the impugned orders had no application to the facts of

the present case. It was therefore submitted that by incorrectly construing

the provisions of the said Act, the impugned order came to be passed. The

same was thus liable to be set aside.

5. On the other hand Ms Tajwar Khan, learned Assistant

Government Pleader for the respondents submitted that the Concession

Agreement permitted the petitioner to collect toll from the vehicles using the

bridge. The definition of the expression “lease” as per Section 2(n) of the

said Act being inclusive in nature, it was rightly treated as “lease” for the

purposes of the said Act. The petitioner was permitted to retain control of

the bridge in question for the period as provided in the Concession

Agreement. Reference was also made to Articles 25 and 36 of Schedule-I to

the said Act and it was submitted that since the intention of the parties was

clear in permitting the petitioner to collect toll, the impugned adjudication

did not call for any interference. She also referred to the provisions of

Section 6 of the said Act to justify the demand as made. Placing reliance on

the decisions in State of Uttarakhand and ors. (supra) it was submitted that

the order passed by the respondent No.2 did not call for any interference. It

was also urged that there was a distinction between a “lease” as

contemplated by Transfer of Property Act, 1882 and “lease” as defined under

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 6/12

Section 2(n) of the said Act. It was therefore submitted that since all

relevant provisions of the said Act had been taken into consideration while

passing the impugned order, there was no reason to interfere with the same.

6. We have heard the learned counsel for the parties at length and

we have given due consideration to their respective contentions.

The question to be considered is with regard to the stamp duty

that is liable to be paid on the execution of the Concession Agreement dated

16/11/1998. For that purpose the nature of the Concession Agreement

would be required to be seen. Under Section 3 of the said Act the stamp

duty is liable to be paid on the instrument as executed and not on the

transaction. An instrument as defined by Section 2(l) of the said Act

includes a document by which any right or liability is created or extended.

Perusal of the Concession Agreement indicates that the State Government

had invited bids for constructing a bridge across Vaingananga river under

Build, Operate and Transfer scheme. Private investment in the said project

was permitted and with a view to enable the party constructing the bridge to

recover the project cost, a concession period was fixed during which period

the said party was entitled to collect fees for the purposes of reimbursement

of the total project cost. The concession period fixed was eighteen years and

nine months which included the construction period of two years and six

months from the date of signing of the agreement. The fees to be collected

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 7/12

from vehicles using the bridge were the fees as fixed by the Government

under National Highways Act, 1956 and the fees so collected during the

concession period were to be retained by the party constructing the bridge.

Thereafter at the end of the concession period the project, namely the bridge

was to be handed over to the Government. It was clarified that the

possession of the land on which the proposed project was to be constructed

was with the Public Works Department and the same was to be handed over

to the party making the construction but the same would not amount to

transfer of ownership.

7. It would be necessary to refer to relevant provisions of the said

Act. Section 2 defines various expressions which expressions would get

their meaning as defined unless there was anything repugnant in the subject

or context. Section 2(l) defines an ‘instrument’ to include every document

by which any right or liability is either created or purported to be created.

Section 2(n) defines a lease of immovable or movable property. The said

definition is inclusive in nature. Section 2(n)(iii) is relevant for the present

purpose and it reads thus :

2(n) “lease” mean a lease of immovable property and includes

also :

(i) …., (ii)….

(iii) any instrument by which tolls of any description are let;

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 8/12

Section 3 mandates every instrument as mentioned in Schedule-I

to be chargeable with stamp duty. Section 6 specifies that if any instrument

comes within two or more descriptions in Schedule-I and the duties payable

therein are different, such document would be chargeable only with the

highest of such duty.

Article 36(b) reads thus :

36. LEASE, including an under-lease


or sub-lease and any agreement to let
or sub-let or any renewal of lease :

(a) …
(b) where the lease is granted for The same duty as is leviable on a
fine or premium or money advanced conveyance under clause (a), (b)
or to be advanced and where no rent [(c) or (d)], as the case may be,
is fixed; of Article 25, on the amount of
such fine or premium or money
advanced or to be advanced.

8. From a complete reading of the entire agreement it becomes clear

that by virtue of execution of said document the party constructing the

bridge was entitled to recover the cost of the project through collection of

toll from the vehicles using the said bridge during the period of 18 years 9

months. The amount of premium was also fixed at Rs.261.88 crores. Even

if the entire cost of the project was recovered prior to that period the party

constructing the bridge was entitled to retain such fees till the completion of

the concession period. The said document therefore creates a right in

favour of the petitioner to recover fees from vehicles using the bridge. The

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 9/12

Concession Agreement is thus an “instrument” as defined by Section 2(l) of

the said Act.

9. The definition of the term “lease” under Section 2(n) of the said

Act is distinct from the definition of the term “lease” under Section 105 of

the Transfer of Property Act, 1882. Under Section 2(n) of the said Act the

term is not restrictive. Besides a lease of immovable or movable property or

both, any instrument by which tolls of any description are let is also included

in the said definition. The term “let” in the context of rent legislation has a

different connotation and the same would not be relevant in the present

context. In Black’s Law Dictionary, the word ‘let’ also means to allow or to

permit. A lease therefore would also include any instrument by which tolls

of any description are let.

10. In State of Uttarakhand and ors. (supra) the provisions of Section

2(16)(c) of the Stamp Act, 1899 as applicable to the State of Uttarakhand fell

for consideration. Those provisions are in pari materia to the provisions of

Section (2)(n) of the said Act. The question that was considered in the said

decision was with regard to the stamp duty payable on a lease agreement

executed between the State Government and the contractor entitling the

latter to collect toll tax. After noticing that the said definition was inclusive

in nature it was held that since the contractor was permitted to collect toll

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 10/12

tax for use of a particular road, the agreement in question fell within the

ambit of the term “lease” as defined by Section 2(16)(c) of the Stamp Act,

1899.

We find that the ratio of the aforesaid decision interpreting pari

materia provisions would squarely apply to the case in hand. Merely

because there was a specific auction held for grant of lease and to collect toll

tax would not make much difference in view of the fact that in the present

case under Concession Agreement the petitioner was permitted to collect toll

with a view to recover the project cost.

11. It may also be noted that the Honourable Supreme Court in the

aforesaid decision has referred to the judgment of Allahabad High Court in

Banney Khan vs. Chief Inspector Stamp AIR 1976 All 475 as well as the

judgment of the Andhra Pradesh High Court in Uppalapati Durga Prasad vs.

Executive Engineer (R & B) (2001) 4 Andh LT 228 and has thereafter

affirmed those decisions by observing that when toll is collected for using a

road or bridge then in such cases neither the road nor the bridge is leased

out. It is only the right to collect toll that is leased out and thus right of

leasing out the collection of toll would be a “lease” for the purposes of the

Stamp Act, 1899. In the impugned order the appellate Authority has

referred to the aforesaid two decisions while dismissing the appeal. We

find that the appellate Authority has rightly adjudicated the appeal by

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 11/12

applying the correct legal provisions.

11. Heavy reliance was placed by the learned counsel for the

petitioner on the judgment of the Honourable Supreme Court in ICICI

(supra). Its perusal would indicate that the document in question was an

agreement to create a lease in future. It was thus held in the said facts that

the intention of the parties was to execute a document of lease in future and

till such document was executed, the status of the appellant therein was that

of a licensee. In the light of these facts the ratio thereof is clearly

distinguishable and is thus not applicable to the case in hand. Similarly the

ratio of the decision in Larsen and Toubro Ltd and ors . (supra) would also

not be applicable to the case in hand inasmuch as in said case also there was

no lease created in favour of the parties and such lease was to be created

after the construction was to be completed.

12. It is thus found that the Concession Agreement has been rightly

found to be chargeable as a lease as defined by Section 2(n) of the said Act.

Article 36 (b) of Schedule-I has rightly been made applicable rather than

Article 5(h) of the said Act in view of the fact that Section 6 mandates a

document to be charged with the higher duty prescribed when it comes

under two or more descriptions in Section Schedule-I. It is found that the

appellate Authority has applied the correct legal principles while passing the

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::


J-WP-2365-06 12/12

impugned order. There is no reason to interfere with that adjudication.

Consequently the impugned order is liable to be upheld.

13. In the result the challenge to the impugned order fails. The writ

petition is dismissed. Rule stands discharged with no order as to costs.

In terms of order dated 07/12/2007 the petitioner shall abide by

the undertaking given with regard of payment of balance amount of stamp

duty.

JUDGE JUDGE

Asmita

::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::

You might also like