J-WP-2365-06 1/12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
WRIT PETITION NO.2365 OF 2006
Abhijeet Ashoka Infra Structure Pvt. Limited
A Company duly incorporated under the
provisions of the Companies Act, 1956 and
having its registered office at F-8 M.I.D.C.
Industrial Area Hingna, Nagpur,
Through its Director … Petitioner
-vs-
1. The Joint District Registrar (Class-I)
and The Collector of Stamps, Bhandara
2. The Chief Controlling Revenue Authority
(Appellate Authority), Maharashtra State,
Pune … Respondents
Shri D. V. Chauhan, Advocate for petitioner.
Ms Tajwar Khan, Assistant Government Pleader for respondents.
CORAM : A. S. CHANDURKAR AND VINAY JOSHI, JJ.
Arguments were heard on : 27/02/2020
Judgment is pronounced on : 06/03/2020
Judgment : (Per : A. S. Chandurkar, J)
The challenge raised in this writ petition is to the order dated
28/02/2006 passed by the Chief Controlling Revenue Authority,
Maharashtra State, Pune thereby confirming the order dated 11/11/2005
passed by the Collector of Stamps in proceedings under the Maharashtra
Stamps Act, 1958 (for short, the said Act). By the said order, the
agreement between the parties has been adjudicated as a “lease” falling
under Article 36(b) of Schedule-I to the said Act.
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 2/12
2. The facts in brief are that an advertisement was issued by the
State of Maharashtra for constructing a bridge across Vainganga river. That
work was to be done on “ Build, Operate and Transfer” (BOT) basis. The
offer made by the petitioner came to be accepted. A Concession Agreement
was accordingly entered into between the petitioner and the State of
Maharashtra through the Secretary, Public Works Department on
16/11/1998. The Collector of Stamps initiated proceedings for adjudication
of proper stamp duty payable on the said agreement. After considering the
agreement entered into by the petitioner on 05/07/2005 a communication
was issued to the petitioner in which it was stated that the agreement was in
the nature of lease as per provisions of Section 2(n)(iii) of the said Act. The
petitioner was called upon to show cause as to why stamp duty should not be
recovered in terms of Section 39(1)(b) of the said Act. According to the
petitioner the Concession Agreement could not be treated as “lease” as
defined by Section 2(n) of the said Act. The petitioner submitted its
explanation on 19/07/2005 and after exchange of communications, the
Joint District Registrar and Collector of Stamps called upon the petitioner to
pay deficit stamp duty of Rs.7,84,76,540/-. However on 11/11/2005 an
order came to be passed by the Joint District Registrar and Collector of
Stamps under Section 39(1)(b) of the said Act and the petitioner was called
upon to pay the deficit stamp duty within a period of thirty days. Being
aggrieved by that order the petitioner filed an appeal under Section 53(1A)
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 3/12
of the said Act. Though the petitioner filed an application under Section 54
of the said Act seeking a reference of the question of law to this Court no
orders were passed on that application. Ultimately by the impugned order
the appeal preferred by the petitioner came to be rejected by the respondent
No.2. Being aggrieved the said order has been challenged in this writ
petition.
3. After the writ petition was entertained and admitted by the
learned Single Judge, by virtue of administrative directions issued, the writ
petition was directed to be placed before the Division Bench. Accordingly we
have heard the learned counsel for the parties.
4. In support of the challenges raised to the impugned order Shri D.
V. Chauvan, learned counsel for the petitioner submitted that on complete
reading of the Concession Agreement which was not a registered document
it was clear that the same could not be termed to be a “lease” as defined by
Section 2(n) of the said act. The subject matter of the Concession
Agreement was the construction of a bridge over Vainganga river and the
agreement was to be executed on “BOT” basis. With a view to enable the
petitioner to recover the cost of construction it was permitted to collected
toll for a period of eighteen years and nine months which included the
construction period of two years and six months. Referring to Clause-1.13 of
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 4/12
the Concession Agreement it was submitted that the petitioner was entitled
to collect fees as notified by the Government of India under the National
Highways Act and the fees were to be retained by the petitioner collected
from the vehicles using the facility. Referring to Clause 3.14 it was
submitted that exclusive possession of any immovable property was never
handed over to the petitioner and it was merely required to undertake the
construction of the bridge. The overall control was retained by the
respondent No.1 and therefore by no stretch of imagination the Concession
Agreement could be treated as a ‘lease’. There was no relationship of lessor
and lessee between the parties nor was any land described to constitute a
lease. Referring to the judgment of the Honourable Supreme Court in
ICICI vs. State of Maharashtra and ors. (1999) 5 SCC 708 it was submitted
that as possession of the immovable property in the form of land remained
with the owners thereof and the Concession Agreement merely gave a right
to the Company to construct the bridge, the document in question could not
be treated as a lease. He also referred to the judgment of learned Single
Judge in Larsen and Toubro Ltd. and ors. vs. The State of Maharashtra and
ors. 2012(7) ALL MR 460 to substantiate his contention. He sought to
distinguish the decision of Honourable Supreme Court in State of
Uttarakhand and ors. vs. Harpal Singh Rawat (2011) 4 SCC 575 by
submitting that in that case the agreement in question specifically permitted
collection of toll which clarified the intention of the parties. He also
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 5/12
submitted that the decisions of the Allahabad and Andhra Pradesh High
Courts referred to in the impugned orders had no application to the facts of
the present case. It was therefore submitted that by incorrectly construing
the provisions of the said Act, the impugned order came to be passed. The
same was thus liable to be set aside.
5. On the other hand Ms Tajwar Khan, learned Assistant
Government Pleader for the respondents submitted that the Concession
Agreement permitted the petitioner to collect toll from the vehicles using the
bridge. The definition of the expression “lease” as per Section 2(n) of the
said Act being inclusive in nature, it was rightly treated as “lease” for the
purposes of the said Act. The petitioner was permitted to retain control of
the bridge in question for the period as provided in the Concession
Agreement. Reference was also made to Articles 25 and 36 of Schedule-I to
the said Act and it was submitted that since the intention of the parties was
clear in permitting the petitioner to collect toll, the impugned adjudication
did not call for any interference. She also referred to the provisions of
Section 6 of the said Act to justify the demand as made. Placing reliance on
the decisions in State of Uttarakhand and ors. (supra) it was submitted that
the order passed by the respondent No.2 did not call for any interference. It
was also urged that there was a distinction between a “lease” as
contemplated by Transfer of Property Act, 1882 and “lease” as defined under
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 6/12
Section 2(n) of the said Act. It was therefore submitted that since all
relevant provisions of the said Act had been taken into consideration while
passing the impugned order, there was no reason to interfere with the same.
6. We have heard the learned counsel for the parties at length and
we have given due consideration to their respective contentions.
The question to be considered is with regard to the stamp duty
that is liable to be paid on the execution of the Concession Agreement dated
16/11/1998. For that purpose the nature of the Concession Agreement
would be required to be seen. Under Section 3 of the said Act the stamp
duty is liable to be paid on the instrument as executed and not on the
transaction. An instrument as defined by Section 2(l) of the said Act
includes a document by which any right or liability is created or extended.
Perusal of the Concession Agreement indicates that the State Government
had invited bids for constructing a bridge across Vaingananga river under
Build, Operate and Transfer scheme. Private investment in the said project
was permitted and with a view to enable the party constructing the bridge to
recover the project cost, a concession period was fixed during which period
the said party was entitled to collect fees for the purposes of reimbursement
of the total project cost. The concession period fixed was eighteen years and
nine months which included the construction period of two years and six
months from the date of signing of the agreement. The fees to be collected
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 7/12
from vehicles using the bridge were the fees as fixed by the Government
under National Highways Act, 1956 and the fees so collected during the
concession period were to be retained by the party constructing the bridge.
Thereafter at the end of the concession period the project, namely the bridge
was to be handed over to the Government. It was clarified that the
possession of the land on which the proposed project was to be constructed
was with the Public Works Department and the same was to be handed over
to the party making the construction but the same would not amount to
transfer of ownership.
7. It would be necessary to refer to relevant provisions of the said
Act. Section 2 defines various expressions which expressions would get
their meaning as defined unless there was anything repugnant in the subject
or context. Section 2(l) defines an ‘instrument’ to include every document
by which any right or liability is either created or purported to be created.
Section 2(n) defines a lease of immovable or movable property. The said
definition is inclusive in nature. Section 2(n)(iii) is relevant for the present
purpose and it reads thus :
2(n) “lease” mean a lease of immovable property and includes
also :
(i) …., (ii)….
(iii) any instrument by which tolls of any description are let;
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 8/12
Section 3 mandates every instrument as mentioned in Schedule-I
to be chargeable with stamp duty. Section 6 specifies that if any instrument
comes within two or more descriptions in Schedule-I and the duties payable
therein are different, such document would be chargeable only with the
highest of such duty.
Article 36(b) reads thus :
36. LEASE, including an under-lease
or sub-lease and any agreement to let
or sub-let or any renewal of lease :
(a) …
(b) where the lease is granted for The same duty as is leviable on a
fine or premium or money advanced conveyance under clause (a), (b)
or to be advanced and where no rent [(c) or (d)], as the case may be,
is fixed; of Article 25, on the amount of
such fine or premium or money
advanced or to be advanced.
8. From a complete reading of the entire agreement it becomes clear
that by virtue of execution of said document the party constructing the
bridge was entitled to recover the cost of the project through collection of
toll from the vehicles using the said bridge during the period of 18 years 9
months. The amount of premium was also fixed at Rs.261.88 crores. Even
if the entire cost of the project was recovered prior to that period the party
constructing the bridge was entitled to retain such fees till the completion of
the concession period. The said document therefore creates a right in
favour of the petitioner to recover fees from vehicles using the bridge. The
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 9/12
Concession Agreement is thus an “instrument” as defined by Section 2(l) of
the said Act.
9. The definition of the term “lease” under Section 2(n) of the said
Act is distinct from the definition of the term “lease” under Section 105 of
the Transfer of Property Act, 1882. Under Section 2(n) of the said Act the
term is not restrictive. Besides a lease of immovable or movable property or
both, any instrument by which tolls of any description are let is also included
in the said definition. The term “let” in the context of rent legislation has a
different connotation and the same would not be relevant in the present
context. In Black’s Law Dictionary, the word ‘let’ also means to allow or to
permit. A lease therefore would also include any instrument by which tolls
of any description are let.
10. In State of Uttarakhand and ors. (supra) the provisions of Section
2(16)(c) of the Stamp Act, 1899 as applicable to the State of Uttarakhand fell
for consideration. Those provisions are in pari materia to the provisions of
Section (2)(n) of the said Act. The question that was considered in the said
decision was with regard to the stamp duty payable on a lease agreement
executed between the State Government and the contractor entitling the
latter to collect toll tax. After noticing that the said definition was inclusive
in nature it was held that since the contractor was permitted to collect toll
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 10/12
tax for use of a particular road, the agreement in question fell within the
ambit of the term “lease” as defined by Section 2(16)(c) of the Stamp Act,
1899.
We find that the ratio of the aforesaid decision interpreting pari
materia provisions would squarely apply to the case in hand. Merely
because there was a specific auction held for grant of lease and to collect toll
tax would not make much difference in view of the fact that in the present
case under Concession Agreement the petitioner was permitted to collect toll
with a view to recover the project cost.
11. It may also be noted that the Honourable Supreme Court in the
aforesaid decision has referred to the judgment of Allahabad High Court in
Banney Khan vs. Chief Inspector Stamp AIR 1976 All 475 as well as the
judgment of the Andhra Pradesh High Court in Uppalapati Durga Prasad vs.
Executive Engineer (R & B) (2001) 4 Andh LT 228 and has thereafter
affirmed those decisions by observing that when toll is collected for using a
road or bridge then in such cases neither the road nor the bridge is leased
out. It is only the right to collect toll that is leased out and thus right of
leasing out the collection of toll would be a “lease” for the purposes of the
Stamp Act, 1899. In the impugned order the appellate Authority has
referred to the aforesaid two decisions while dismissing the appeal. We
find that the appellate Authority has rightly adjudicated the appeal by
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 11/12
applying the correct legal provisions.
11. Heavy reliance was placed by the learned counsel for the
petitioner on the judgment of the Honourable Supreme Court in ICICI
(supra). Its perusal would indicate that the document in question was an
agreement to create a lease in future. It was thus held in the said facts that
the intention of the parties was to execute a document of lease in future and
till such document was executed, the status of the appellant therein was that
of a licensee. In the light of these facts the ratio thereof is clearly
distinguishable and is thus not applicable to the case in hand. Similarly the
ratio of the decision in Larsen and Toubro Ltd and ors . (supra) would also
not be applicable to the case in hand inasmuch as in said case also there was
no lease created in favour of the parties and such lease was to be created
after the construction was to be completed.
12. It is thus found that the Concession Agreement has been rightly
found to be chargeable as a lease as defined by Section 2(n) of the said Act.
Article 36 (b) of Schedule-I has rightly been made applicable rather than
Article 5(h) of the said Act in view of the fact that Section 6 mandates a
document to be charged with the higher duty prescribed when it comes
under two or more descriptions in Section Schedule-I. It is found that the
appellate Authority has applied the correct legal principles while passing the
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::
J-WP-2365-06 12/12
impugned order. There is no reason to interfere with that adjudication.
Consequently the impugned order is liable to be upheld.
13. In the result the challenge to the impugned order fails. The writ
petition is dismissed. Rule stands discharged with no order as to costs.
In terms of order dated 07/12/2007 the petitioner shall abide by
the undertaking given with regard of payment of balance amount of stamp
duty.
JUDGE JUDGE
Asmita
::: Uploaded on - 11/03/2020 ::: Downloaded on - 04/02/2024 21:38:13 :::