Installation of Wall-Split Units
Installation of Wall-Split Units
August 21
Installation of Indoor Unit and
>> Outdoor Unit 01
Copper pipe
Expander
cutter
Copper pipe
Pressure gauge
bender
Infrared
thermometer
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Accessories
No. Name of Accessories Q’ty
1 Installation Plate 1
2 Clip Anchor (expansible hook) 8
3 Self-tapping Screw ST3.9x25 (Type “A”) 8
4 Seal 1
5 Drain Joint 1
6 Remote controller 1
Parts you must purchase (a
7 Connecting pipe Assembly minimum pipe wall-thickness of
0.7mm is required.)
8 Wrapping Tape
9 Connecting Cable
Parts
10 Additional Drain Pipe (Outer Diameter 15.5mm)
Purchased separately
11 Insulation Materials
12 Cable Tie (5~10 pcs)
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Typical installation
Typical installation
Select Location
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
① Fit the installation plate horizontally on the wall with level gauge around the installation plate.
② If the wall is made of brick, concrete or the like, drill eight (8) 5mm diameter holes in the wall.
Insert clip anchor for appropriate mounting screws.
③ Fit the installation plate on the wall with eight (8) type “A” screws.
Correct orientation (should be level to prevent water drop from indoor unit)
of Installation Plate
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
① Bend the connective pipe to be laid at 43mm height or less from the wall.
② Fix the end of the connective pipe. (Refer to Tightening Connection in REFRIGERANT PIPING
CONNECTION)
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Drainage Installation
① Run the drain hose downward slantly. Do not install the drain hose as illustrated below.
② When connecting extension drain hose, insulate the connecting part of extension drain hose
with a shield pipe.
NOTE: Before performing any electrical work, turn off the main power to the system.
① The inside and outside connecting cable can be connected without removing the front grille.
② Connecting cable between indoor unit and outdoor unit shall be approved polychloroprene sheathed
flexible cord, type designation H07RN-F or heavier cord.
③ Lift the indoor unit panel up, remove the electrical box cover by loosening the screw.
④ Ensure the color of wires of outdoor unit and the terminal Nos. are the same to the indoor’s
respectively.
⑤ Wrap those cables with insulation tapes, so that they will not touch any electrical components.
Secure the cable onto the control board with the wire clamp.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Wrapping
① Bundle the tubing, connecting cable, and drain hose with tape securely, evenly as shown below.
② Because the condensed water from rear of the indoor unit is gathered in ponding box and is piped out
of room. Do not put anything else in the box.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Caution
If you have to install the outdoor unit in above locations, please ask for customization of special treatment.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Rooftop installation
If the outdoor unit is installed on a roof structure, be sure to level the unit.
Ensure the roof structure and anchoring method are adequate for the unit location.
Consult local codes regarding rooftop mounting.
If the outdoor unit is installed on roof structures or external walls, this may result in excessive
noise and vibration, and may also be classed as a non serviceable installation.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Necessary Protections
Built a shell where always Built a wall where is Make a simple shell Take good care of the
heavily rains and snows always strong wind where is direct sunshine exhausted air if it stand
toward the street
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Outdoor installation
Install the outdoor unit on a rigid base to prevent increasing noise level and
vibration.
Determine the air outlet direction where the discharged air is not blocked.
In the case that the installation place is exposed to strong wind such as a
seaside, make sure the fan operating properly by putting the unit lengthwise
along the wall or using a dust or shield plates.
Specially in windy area, install the unit to prevent the admission of wind.
If need suspending installation, the installation bracket should accord
with technique requirement in the installation bracket diagram. The
installation wall should be solid brick, concrete or the same intensity
construction, or actions to reinforce, damping supporting should be taken.
The connection between bracket and wall, bracket and the air conditioner
should be firm, stable and reliable.
Be sure there is no obstacle which block radiating air.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
If a drain elbow (block drainage, only used on cooling only AC) is used,
the unit should be placed on a bracket which is taller than 3cm.
If the unit (cooling and heating AC) is used in an area where
temperature falls below 0OC for 2 or 3 days in succession, it is
recommended not to use a drain elbow, for the drain water freezes and
the fan will be broken down.
Fit the seal into the drain hole, then insert the drain joint into the
base pan hole of outdoor unit, rotate 90o to securely assemble them.
Connecting the drain joint with an extension drain hose (Locally
purchased),
In case of the water draining off the outdoor unit during the heating
mode.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
R22 Units
<18K φ6.35 5 10 5 30
18≤ C <21K φ6.35 5 15 8 30
21≤ C <35K φ9.52 5 20 10 60
35≤ C <41K φ9.52 5 25 10 60
41≤ C <60K φ9.52 5 30 15 60
60K φ9.52 5 30 20 60
Caution: Capacity is base on standard length and maximum allowance length is base of reliability;
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
<18K φ6.35 5 20 8 20
18≤ C <36K φ9.52 5 25 10 40
36≤ C <60K φ9.52 5 30 15 40
60K φ9.52 5 30 20 40
Caution: Capacity is base on standard length and maximum allowance length is base of reliability;
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
≤15K φ6.35 5 15 8 15
15< C ≤24K φ9.52 5 25 15 30
24< C ≤36K φ9.52 5 30 20 30
36< C ≤60K φ9.52 5 50 30 30
Caution: Capacity is base on standard length and maximum allowance length is base of reliability;
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
<15K φ6.35 5 25 10 15
15≤ C <24K φ9.52 5 30 20 30
24≤ C <36K φ9.52 5 50 25 30
36≤ C <60K φ9.52 5 65 30 30
Caution: Capacity is base on standard length and maximum allowance length is base of reliability;
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
<18K φ6.35 5 20 8 12
18≤ C <36K φ9.52 5 25 10 24
36≤ C <60K φ9.52 5 30 15 24
60K φ9.52 5 30 20 24
Caution: Capacity is base on standard length and maximum allowance length is base of reliability;
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
<15K φ6.35 5 25 10 12
15≤ C <24K φ9.52 5 30 20 24
24≤ C <36K φ9.52 5 50 25 24
36≤ C <60K φ9.52 5 65 30 24
Caution: Capacity is base on standard length and maximum allowance length is base of reliability;
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Oil Trap
Flaring work
Flaring work
B、Burr removal.
① Completely remove all burrs from the cut cross section of
pipe/tube.
② Put the end of the copper tube/pipe in a downward
direction as you remove burrs in order to avoid dropping
burrs into the tubing.
Flare nut
C、 Putting flare nut on.
Remove flare nuts installed on indoor and outdoor unit, then
Copper tube
put them on pipe/tube having completed burr removal. (not
possible to put them on after flaring work)
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Flaring work
D、 Flaring
Firmly hold copper pipe in a die in the dimension shown in the table below.
Flaring work
E、 Check.
Compare the flared work with the below diagram.
If flare is found to be defective, cut off the flared section and do flaring work
again.
Show movie
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Pipe work
Following the Three Basic Rules of Refrigerant Piping.
(2) Cleaning (free of
(1) Drying (no moisture) (3) Tightening (air-tightness)
contamination)
There shall be no moisture in the There shall be no dust in the pipe. There shall be no refrigerant leak.
pipe.
Item
• Water entering from outside, • Oxidized film generated during • Insufficient brazing Inadequate
such as rain. brazing. flaring or insufficient tightening
Cause • Moisture due to dew • Entering of foreign items such as torque.
condensation occurring inside the dust, particles and oil from • Inadequate tightening of flange
pipe. outside. connection.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Pipe work
(2) Cleaning (free of
(1) Drying (no moisture) (3) Tightening (air-tightness)
contamination)
• Clogging of expansion valve, capillary • Clogging of expansion valve, capillary • Gas shortage
tube, etc. tube, etc. • Insufficient cooling or heating.
• Insufficient cooling or heating. • Insufficient cooling or heating. • Temperature increasing of discharge gas.
• Degradation of refrigerant oil. • Degradation of refrigerant oil. • Degradation of refrigerant oil.
• Malfunction of compressor. • Malfunction of compressor. • Malfunction of compressor.
Tightening Connection
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Electric safety
Electric safety
An individual branch circuit and single receptacle used only for this air conditioner must be available. See
the following table for suggested wire sizes and fuse specifications:
Model Power supply Input Rated Amp(Switch/Fuse)
12K 16A
18K 20A
220-240V~, 50/60Hz
24K 30A
30k 30A
NOTE: The supply voltage must be consistent with the rate voltage of the air conditioner.
NOTE: Before performing any electrical work, turn off the main power to the system.
① Remove the electrical control board cover from the outdoor unit by loosening the screw.
② Connect the connective cables to the terminals as identified with their respective matched numbers
on the terminal block of indoor and outdoor units.
③ Secure the cable onto the control board with the cord clamp.
④ To prevent the ingress of water, from a loop of the connective cable as illustrated in the installation
diagram of indoor and outdoor units.
⑤ Insulate unused cords (conductors) with PVC-tape. Process them so they do not touch any electrical
or metal parts.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Or Or
Wire-holding bo ard
( 1)
Or
Wire-holding
bo ard
( 2)
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Caution
After the confirmation of the above conditions, prepare the wiring as follows:
Never fail to have an individual power circuit specifically for the air conditioner. As for the method of wiring,
be guided by the wiring diagram posted on the inside of control cover.
The screw which fasten the wiring in the casing of electrical fittings are liable to come loose from vibrations
to which the unit is subjected during the course of transportation. Check them and make sure that they are all
tightly fastened. (If they are loose, it could cause burn-out of the wires.)
Specification of power source.
Confirm that electrical capacity is sufficient.
See to that the starting voltage is maintained at more than 90 percent of the rated voltage marked on the
name plate.
Confirm that the cable thickness is as specified in the power source specification.
Always install an earth leakage circuit breaker in a wet or moist area.
The following would be caused by voltage drop. Vibration of a magnetic switch, which will damage the
contact point, fuse breaking, disturbance of the normal function of the overload.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Reason: If the compressor run with air inside for a long time and the discharge pipe is blocked, it
may cause explosive.
Therefore, the indoor unit and tubing between the indoor and outdoor unit must be do leakage test
and evacuated to remove any non-condensable air and moisture from the system.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
Note: For the R32 refrigerant model, make sure the conditions within the area have been made the safe by control of
flammable material when the refrigerant added into air conditioner.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Necessary Tools IDU Installation ODU Installation Pipe Work Wiring Air Purging
2. Leak detector
Use the leak detector to check for leakage.
CAUTION:
A: Lo packed valve
B: Hi packed valve
C and D are ends of indoor unit connection.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Gas Leakage Check Drainage Check Test Running
Drainage check
Perform test operation after completing gas leak check at the flare nut connections and electrical safety
check.
Check that all tubing and wiring have been properly connected.
Check that the gas and liquid side service valves are fully open.
1. Connect the power, press the ON/OFF button on the remote controller to turn the unit on.
2. Use the MODE button to select COOL, HEAT, AUTO and FAN to check if all the functions works well.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Gas Leakage Check Drainage Check Test Running
3. When the ambient temperature is too low (lower than 17OC), the unit cannot be controlled by the remote
controller to run at cooling mode, manual operation can be taken. Manual operation is used only when the remote
controller is disable or maintenance necessary.
Hold the panel sides and lift the panel up to an angle until it remains fixed with a clicking sound.
Press the Manual control button to select the AUTO or COOL, the unit will operate under Forced AUTO or COOL
mode.
4. The test operation should last about 30 minutes.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Gas Leakage Check Drainage Check Test Running
To judge whether the system is operating well, we normally test the low pressure of the system and
the current of the compressor. When the following phenomena happen, we can fix the most possible
reasons.
Phenomena
The most possible reason
Low pressure Compressor current
The gas in the compressor or 4-way valve is leaked
Higher Lower
from high pressure side to low pressure side.
The refrigerant is over charge. The ambient
Higher Higher
temperature is too high.
The refrigerant is not enough. The ambient
Lower Lower
temperature is too low.
Lower Higher The refrigeration system is blocked.
Normal Higher Low voltage
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
Install the indoor units level is quite important, which will help to facilitate drainage.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips: Basic requirements of location and spaces for outdoor installation: to ensure the outdoor unit
Smooth in/out the wind, the left side should ≥ 30cm, to the right ≥ 60cm, to the up ≥ 30cm, above ≥ 30cm, in front
≥ 200cm
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips: Basic requirements of location and spaces for outdoor installation: to ensure the outdoor unit
Smooth in/out the wind, the left side should ≥ 30cm, to the right ≥ 60cm, to the up ≥ 30cm, above ≥ 30cm, in front
≥ 200cm
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips: The air-conditioner piping and wiring connections should be correct, solid, and to a
reasonable degree of bending
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
Wall-off hole should be neat, installed after the sealed-off block wall of mud hole to prevent foreign
matter into the indoor air.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
For the connection of pipes and wire, make sure to wrap the connecting wire, connection pipe and drain
pipe together with wrapping belt, taking the direction from outdoor side to indoor side while wrapping,
which will prevent the system from rain. In order to not affect the air-in of indoor piping, also make sure the
right distances between indoor and outdoor connection.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Messy wires
Installation Tips:
The connection wires have to be wrapped with piping together, they are not allowed to be exposed
outside, in case of any danger that may be caused.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
No drainage
bending.
Installation Tips:
When the wrapped piping and wires have been put into the room through the wall hole, you have to bend
the part of piping and wires near the wall hole, preventing rains from coming into the indoor units.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
No heat preservation
on the piping.
Installation Tips:
The connecting parts of the outdoor units and piping have to be protected with the black insulation foam,
then using the wrap belt to wrap together with wire. The exposed parts of piping without black insulation
foam can’t be more than 10CM, or the cooling/heating performance of the unit may be reduced.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
The connection pipe need to be vertically or horizontally organized, when bending the pipe, make sure
bending radius is no bigger than 10CM, and when bending, the pipes must not be flattened.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
Indoor unit installation plate have to be evenly attached to the unit and leaned to the wall closely.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
When outdoor unit is installed on a platform, the drainage of outdoor unit have to be more care-taken, and the unit
need to be fixed to avoid moving when units vibrate.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
When installing the first bracket (outdoor), at least 6 screws need to be used, and the diameter for each
one shall not be less than φ10mm. And
the bracket need to be horizontally installed.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
4 bolts (diameter bigger than Φ10mm) on the bottom bracket need to be well fastened.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
The long power cord should be well arranged, and put into the vacant spaces in the indoor unit or fix it
beside the unit; it is not allowed to wind the wire to little circles which may cause heat.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Using nonstandard
connection wire
Installation Tips:
The indoor-outdoor connection wire must be neoprene wire, PVC wire can’t be used.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
Usually, only single phase air conditioner with rated current which isn’t bigger than 16A is suggest to use
power plug, while other A/C is usually connected to the wire connector. If use power plug on these units, it
has big potential to cause heat or even fire.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Grounding is not
well fixed.
Installation Tips:
Grounding wire or grounding end must be well connected or fastened. If you want to loosen it, you have
to use tools to do that. And the green-yellow wire can only be used for grounding.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Installation Tips:
If the unit don’t have grounding wire or leakage protection switch, when the unit work abnormally or
short circuit or leakage happen, the unit can’t be grounded, thus it may cause fire or casualties.
Installation of Indoor & Outdoor Unit Checking and Test Running Failure Cases
Nonstandard connection