ADP-221100-018 R5 Domestic Water Pumps (A)
ADP-221100-018 R5 Domestic Water Pumps (A)
Method Statement for Testing & Commissioning of Domestic Water Pump Page 2 of 24 Rev. 005
Hold
Para. Description of Hold
No.
004 Terminated
Page 2 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 3 of 24 Rev. 005
Ite
m Comments On Rev.003 Contractor’s Response
No.
1 Comply
7.3 Pre-commissioning
was added in this narrative
Mechanical Checks
because it was missed and it
1. Ensure signed off Installation RFIT
5 was originally written in
Electrical Checks
checklist FM-MS-ADP-221100-
1. Ensure Electrical Power Supply RFIC is signed off
018-001
END OF COMMENTS
Page 3 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 4 of 24 Rev. 005
Table of Contents
1.0 Purpose
3.0 References
4.0 Definitions
5.1 Competency
5.2 Roles & Responsibilities of Commissioning Engineer
5.3 Roles & Responsibilities of QC Engineer
5.4 Roles & Responsibilities of Foreman
5.5 Roles & Responsibilities of HSE Supervisor
5.6 Roles & Responsibilities Faisal Jassim’s Representative
7.1 General
7.2 Safety Precautions
7.3 Pre-Commissioning
7.4 Commissioning
9.1 Induction
9.2 PPE
9.3 Hazard Identification, Risk Assessment & Control
9.4 Toolbox Talks
9.5 Permit to Work
9.6 Training of Personnel
10.0 Attachments
Page 4 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 5 of 24 Rev. 005
1.0 PURPOSE
The main purpose of this method statement is to ensure that all the Domestic Pumps are executed in
accordance with the project specifications and implemented with the highest level of conformance.
This method statement covers the Start-up & Commissioning of the Domestic Pumps as per project
specification, approved method statement and approved shop drawings.
3.0 REFERENCES
4.0 DEFINITIONS
Page 5 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 6 of 24 Rev. 005
The Commissioning Manager has the overall responsibility for the implementation of this Method
Statement, also will individually assess the manpower required for Testing & Commissioning of Domestic
Water Pump to meet the schedule. Typically, these will include:
Commissioning Engineer
QC Engineer
Foreman
HSE Supervisor
Faisal Jassim’s Representative
5.1 Competency
The competency of all construction personnel shall be controlled in accordance with the
Competent Persons Designation Procedure Ref: ADP-013529-066.
Commissioning Engineer will be in charge of all operations during Testing & Commissioning
following Project HSE requirements and Project Quality Plans.
Maintains work permits with coordination of the HSE Supervisor.
Coordinates with QC Engineer for inspections and raise RFIC with complete attachments such
as approved (ITP, shop drawing, check list etc.).
Ensures that only trained and competent personnel are involved for Final Testing of the Domestic
Pumps.
Ensures that tools & equipment are certified, maintained and used correctly.
Ensure that all testing tools are calibrated, and calibration is up to date.
Ensures that all required documents and related drawings to execute the works are up to date.
Shall prepare open front for his crew and liaise with planning department for progress reporting
and schedule monitoring.
Shall coordinate with Faisal Jassim’s Representative on his supervision during commissioning of
the equipment.
Ensure that all inspection and test reports pertaining to everyday work activities are submitted to
the QC inspection.
Prevent the use of equipment that could cause improper test relative to Project Specification.
Stop test activity that is not being done in accordance with the specified requirements and
approvals.
Ensure that test have been done in accordance with approved method statement and Project
specification to offer for CSC and CxA’s inspection.
The foreman will carry out his duties by maintaining continuous coordination with the
Commissioning Engineer on daily basis, and ensure proper distribution of the workforce in the
required and planned locations.
Page 6 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 7 of 24 Rev. 005
To ensure that his assistant foreman/charge hand are aware of the job requirements and they
have enough information to carry out their duties properly.
To ensure in consultation with the site engineer that the manpower involved in the works are
moving as agreed and planned for the work.
To ensure that the daily work is progressing as planned and advice the Commissioning Engineer
of any requirement for additional resources.
To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure that all his
working team are aware of the same to prevent accident and losses.
To inform the Commissioning Engineer and of the areas ready for inspection.
Assist the Site Engineer in conducting Tool box talks prior to starting the activity.
Ensure PPE shall be worn as appropriate according to the nature of job.
Ensure safety precautions shall be followed as per established project HSE requirements and
Project Quality Plans safety plan.
Faisal Jassim’s Representative shall conduct the testing & commissioning of the Domestic Pump
System.
Faisal Jassim’s Representative shall sign off the pre-commissioning check list and
commissioning test sheets when the requirements stated in this Method Statement are satisfied.
4 Faisal Jassim will do pre-commissioning, alignment and start-up of the pump and certify the
alignment of the base mounted pump prior to start-up.
The following tools & equipment will be used during the Testing and Commissioning of Domestic
Water Pump.
Note: All tools and equipment’s will be inspected, and colour coded before use at site
Page 7 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 8 of 24 Rev. 005
7.1 General
Make available at site, an approved copy of shop drawing for the intended commissioning.
4 Pre-Commissioning, Alignment and pump start-up of the Domestic Pumps shall be done by an
authorized representative from Faisal Jassim.
All safety precaution shall be followed as per established project safety plan.
Only experienced and skilled technician shall be engaged for carrying out the commissioning of
Domestic Pumps.
Appropriate warning signs and tapes shall be placed during testing and commissioning as
required.
All PPE shall be worn as appropriate according to the nature of job.
Lock Out & Tag Out procedure (Ref. ADP-013529-026) shall be followed during entire activity
related to Testing and Commissioning as applicable.
Work area shall be maintained neat and clean.
Page 8 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 9 of 24 Rev. 005
Check all control devices and wiring with labels are complete.
Check the size and type of the cable as per approved shop drawing and manufacturer
recommendation.
Ensure cables are tested for continuity and insulation resistance with signed-off document.
Check the terminal details of the motor is attached inside the terminal box.
Check the cabling and termination to the motor are completed.
Open the door of the box of the enclosure and inspect the internal components and wiring for
any visible damage.
Check motor nameplate for Voltage and FLC, then check electrical protection if they are sized
correctly.
Bump start the motor and check for correct rotation. If rotation is incorrect, change any two-phase
connections on the motor terminal plate, if there is a VFD associated with the motor, change the
rotation setting on the VFD to reverse the rotation.
Avoid dry running of the pump. Either fill the pump with liquid or uncouple the motor when
checking direction of rotation.
Ensure that the coupling is aligned correctly and that the coupling guards are in place.
7.6 Priming
Close the discharge isolating valve and loosen the air vent screw in the motor stool. Pay attention
to the direction of the vent hole and take care to ensure that the escaping water does not cause
injury to persons or damage to the motor or other components.
Slowly open the isolating valve in the suction pipe until a steady stream of liquid runs out of the
vent hole.
Tighten the air vent screw and completely open the isolating valve(s).
Close the discharge valve and then crack open to assure minimal flow.
Ensure that the pump recirculation line is free from obstructions.
Start the motor and bring to full speed as quickly as possible.
As soon as the pump is at full speed, slowly open the discharge valve. (This will prevent sudden
changes in velocity and surging in the discharge line)
Record the voltage and running current, using the clamp meter and check if is within the
acceptable limits of the motor.
7.9 Commissioning
Page 9 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 10 of 24 Rev. 005
(Notes: Extra caution and care must be observed when working with hot Surface. This hot surface
temperature may rises up to 70°C. Temperature resistant gloves must be worn when working
with hot surface.)
Page 10 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 11 of 24 Rev. 005
MEP RFIC should be issued for QC Inspectors verification before submission to CSC & CxA.
Refer to ITP No. ADP-221429-002 and strictly follow inspections steps.
Refer to QMP-ADP-014000-625 for RFIC submission process.
Work should be approved by consultant CSC & CxA (submitting RFIC).
9.1 Induction
Prior to commencing work all personnel shall have attended the HSE induction course conducted by the
JV HSE department. No work shall be undertaken by personnel who have not attended the Project HSE
induction. In all aspects, work is to be carried out in a safe manner and in accordance JV approved Health
and Safety Plan and in accordance with HSE requirements
All personnel involved in the Testing and Commissioning will comply with the Project requirements for
PPE:
Work Boots with toe protectors
Safety Helmet
Eye Protection with side shields
HV Gloves
Dust masks (as required)
Rubber Mat
Additional PPE identified by the task risk assessment shall also be provided. Personnel shall sign and be
responsible for their own items of PPE issued to them and the Engineer shall ensure that his team is
complying with the minimum required PPE and that damaged or defective PPE is replaced or repaired
immediately.
Hazard identification, risk assessment and control are detailed in the appropriate risk assessment and
Job Safety Task Instruction (JSTI) attached herewith. Hazards may vary as the works progress and shall
be re-evaluated. All personnel undertaking testing and commissioning activities shall be aware of
particular location hazards. The Project Risk Assessment Procedure ADP-013529-028 is to be referred
to during the planning stages. Should changes occur during the course of commissioning which alters
the associated risks then the risk register shall be updated to reflect any additional risk and mitigation
measure.
The attached JSTI is provided to cover the initial work tasks relating to Testing and Commissioning of
Domestic Pumps - JSTI (attached). This JSTI is prepared based on theoretical information interpreted
from the project documents. A further assessment will be required at the actual work site to verify the
control measures and address any additional hazards. Reference is to be made to the relative Health,
Safety, Environmental & Security procedures to control the risks associated with activities where they
occur.
Page 11 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018
Method Statement for Testing & Commissioning of Domestic Water Pump Page 12 of 24 Rev. 005
Prior to the commencement of site activities, the Engineer, with support from the HSE Officer, shall
conduct a pre-start toolbox talk with all the crew present. The MEP Supervisor shall explain the testing
and commissioning of Domestic Pumps activities, focusing on the hazards and risks involved in the
activity and the mitigation measures that shall be taken as detailed in the Risk Assessment. Regular
Toolbox talks shall be conducted in order to prevent complacency within the crew. The Engineer shall
conduct a Pre-start toolbox talk for the new person/s prior to starting work.
A Permit shall be obtained when and where applicable in accordance with the requirements of Permit to
Work Procedure (ADP-013529-034) prior to performing the Installation, Testing and commissioning of
Domestic Pumps. The supervisor will ensure that all relevant risk assessments, method statements and
permit to work control measures are in place and that all relevant procedures contained within
these documents are fully understood by the operative personnel.
All personnel involved in Testing and Commissioning Domestic Pumps works shall be trained in
accordance with the requirements of the Project HSE Program. No personnel shall be assigned
tasks that they have not received appropriate training in or have been assessed for competency.
Further training shall be given as required and when additional training is identified during the
risk assessment process.
All personnel involved in Testing and Commissioning of Domestic Pumps activities shall be
assessed for qualifications, competency and if they have the required trade skills and experience,
or trained in accordance with the requirements of the project standards.
10.0 ATTACHMENTS
10.1 ADP-221100-018-ITP
10.2 Form No: FM-MS-ADP-221100-018-001
10.3 Form No: FM-MS-ADP-221100-018-002
10.4 Schedule (To be supplied during RFIC submission)
10.5 JSTI
10.6 Risk Assessment
Page 12 of 24
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-221100-018-ITP
Document Title:
Inspection & Test Plan (ITP) – Domestic Water Pumps Page 1 of 1 Rev.005
(JV REF. ITP-1122-311 T&C)
Specification 221100
Start Up
Approved MS
Start-up & Commissioning Test All relevant
221100-018 RFIC & FM-MS-
Commissioning Domestic Pump document must be
2. Approved Installation H W W ADP- 221100-018-
Checklist for Domestic Transfer Pump approved by
RFIT 002
Water Pumps Booster Pump Consultant.
Approved Drawings
Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R – Record Review
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
Pre-Commissioning Checks List for Domestic Pump/
Booster Pump/Transfer Pump
FM-MS-ADP-221100-018-001 Revision:005 Date: 16-Nov-17 Page 1 of 1
QC Acceptance Status
ACTIVITIES /ITEMS TO BE INSPECTED
Yes No Remarks
Electrical
1. Ensure electrical Power Supply RFIC is signed off
2. Ensure RFIT for electrical pump installation is signed off
3. Check that Power to the electric motor of the pump is available
Mechanical
1. Ensure Signed off Installation RFIT.
2. Ensure Pump detail correct against the approved drawings.
5. Ensure bearing housing fill with the appropriate oil or grease to the correct level.
6. Ensure Shaft seal is leak free & Drive guard or shield is properly installed.
8. Check, align and certify alignment of base mounted pumps prior to start-up with sign off documents
9. The initial start-up and setting to work shall be carried out by the pump manufacturer/supplier
10. Check that all valves, pressure gauge and other accessories are installed as per approved shop
drawing.
Cx JV Acceptance Status
ACTIVITIES /ITEMS TO BE INSPECTED
Yes No Remarks
1. Pump Rotation is correct
3. Booster Pump set-check the sequence of operation (start-stop pressure and sequence) and “dry run”
protection check
4. Ensure the Transfer Pump set sequence of operation works as per design requirement.
5. Ensure the Domestic Pump set sequence of operation works as per design requirement.
COMMENTS / DISCREPANCIES:
JV Commissioning Engineer
JV QA/QC Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-221100-018-001
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
Manufacturer Model
Comments
INSTRUMENT USED
Equipment Name Model No. Serial No. Calibration due date
1.
2.
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-221100-018-002
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 1: Task Planning (task identification and details)/ Шаг 1: Планирование задания (выявление задачи и деталей)
Step 3: Risk Management (list any nearby activities that may impact the work) Шаг 3: Управление Рисками (перечень деятельности которые могут повлиять на работу)
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 4: Job Safety/Hazard Analysis/ Шаг 4: Анализ/Оценки Рисков
Activity
(What must be done? i.e. tools, Hazards Risks
equipment, and material used) (How could an injury occur?) What Can Happen Recommendations
Item
(Can hazards be eliminated or modified?)
Планирование работы. Опасность Риски Меры контроля
Номер (Что надо для работы. Например: (Как может произойти (Что может произойти) (Как опасность может быть устранена)
инструменты, оборудование и травма)
материалы)
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Ensure that personnel engaged of working at
Serious injury to personnel height are trained and competent to the given
or even fatality due to fall task.
Fall of material from height. Supervisor must provide full body harness for
Fall from height Injury to personnel due to personnel engaged of working at height.
Working at heights Collapse of scaffold falling debris. Workplace place must be barricaded underneath
3
Cold weather Injury to personnel or even prior to start the work.
fatality due to collapse of A proper work platform should be provided
scaffolds. Monitor the temperature, and wind chill index.
Hypothermia Work rest period implemented.
Wear Winter PPE. (as per weather condition)
Provide hot beverage for employees.
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Wear all required PPE’s.
Slips, trips and fall due to work boots/ rubber boots with toe
Slips scattered materials or protector
Trips rubbish. hard hat
Fall Foot injuries visibility vest / jacket
7 Housekeeping safety glass
Hand injuries
Dust Mask ( as required )
Personnel injury due
Gloves
slippery surface
Supervisor must ensure that used materials
must be stored in designated, to prevent
scattered at work area
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 5: Unplanned Events (if any of the following occurs, stop work and talk to your supervisor)/ Шаг 5: Незапланированные мероприятия: если следующие случаи имеют
место, то остановите работу и известите супервайзера
Nearby work hazards Chemical spills or release
Excessive noise Fires and explosions Unusual odours Heat stress
Опасности на рабочем Утечки химических
Черезмерный шум Пожар и взрывы Странный запах Тепловой удар
месте веществ
Extreme weather/high
winds
Significant near miss Change in the following work conditions:
Evacuation alarm Экстримальные
Существенное, возможное Изменение в процессе работы:
Эвакуация/тревога погодные условия и
происшествия
сильный ветер
Step 6: Unplanned Events (if any of the following occurs, stop work and talk to your supervisor) Шаг 6: Незапланированные мероприятия: если следующие случаи имеют
место, то остановите работу и известите супервайзера
Emergency telephone number: Alarm Code (for commission period)
Телефон экстренной связи: +77015301064 Код сигнализации (при пусконаладке)
Nearest Muster Point/Safety Shelter location: Nearest First Aid Station location:
Ближайший пункт Место Сбора: Ближайший пункт Первой Помощи:
Evacuation Route (Supervisor to explain to workers): Safety shower / eye washer location:
Пути эвакуации(Супервайзер должен объяснить работникам): Пункт промывки глаз:
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
11 36
12 37
13 38
14 39
15 40
16 41
17 42
18 43
19 44
20 45
21 46
22 47
23 48
24 49
25 50
Supervisor Name:
Ф.И.О Супервайзера: ________________________________________ Signature/ Подпись: __________________ Date/Дата: ____________________________ /______/________
This JSTI is prepared based on theoretical information interpreted from the project documents. A further assessment will be required
at the actual work site to verify the control measures and address any additional hazards. Reference is to be made to the relative
Health, Safety, Environmental & Security procedures to control the risks associated with activities where they occur.