Project Management Course Guide
Project Management Course Guide
Kundan K. Gautam
MBA (HR), B.E. (Electronics).
n
ME128A Price? 190/·
TechKna11ledgi
~r PubI i c a t i o n s 11111111111
(Book Code :ME128A)
.
l
\
INDEX
MCKlute•l
: Definitiono1 a project. Project Vs Operations.Necessity of project management. Triple constraints. Project life cydes (type.al
I and atypical)Project pt,ases and stage gate process. Role of project manager. Negotiation9a.nd resolving conflicts. Project menagement
in various organizationstructures.PM knowledgeareas as per ProjectManagementInstitute (PMI).
1.1 Introduction................................... ..........................................................................................................................- ...........- ...- ... 1. 1
1.2 Project ........................................................................................
...............................................................
......·-·-······..-·-···· 1 • 1
1.2.1 Projec1 Management.................................
............................. .-.-· .. ···.....1. ,
...............................................................
• 1.3 Operations ................
....................................................................: ... .........................................................................
·--······ ..··- 1 • 1
1.3.1 The Differencebetween Projects and Operations.................................................................._ ......................_ ..._ ... , • 2
1.4 Objectives/Necess
ity of Project Management................................................................................................_ ............................. 1 • 3
1.5 Importanceof Project Management............. .. .... ..................................................................·-·· ···..·••••......................._._ ...........1 . 3
1.6 ProjectScope··· ············· .. ···· .....................................................................................................................
...................- ................ 1 • 4
1.7 Project Environment............................................................................................................................... . •-····-····· ······-·······-- ' • "
1.a Triple Constraint ...........................................................................................................................................·-···-· ···-····-·--··--· .. 1 - 5
1.8.1 Importanceof Triple Constralnl.......................................................................
..................._ ...........- ....................1 - 5
1.9 Project ManagementUfa Cycle ...............................
...................................
......................
............·--· -·····-· ····-·· ..-·-·······-· ·' - 7
1.9.1 Typical Project ManagementPhases.......................................
...............................
..- .............·-- ·······..-··· ·····"· 1 • 7
1.9.2 Atypical(Adaptive)Project Life Cycle................................
......................................
·-······- ···-..- ········- ..········ ... 1 • 9
1.9.2.1 The Core Values of Atypical ProjectLife Cycle .....................:.......................•..•.....·-········ ·-·-- ···..···-·-·······1 - 10
1.10 Stage Gate Process .............................................................................................................................
---···-·---···.. ... 1 -10
1.10.1 Gates.....................................................
.................................................................................
- · ---··-· ........1 - 10
1.10.2 Stages..........................
·.....................
...............................................................- ...····-·······....·---·-·-•-· ..···-· 1 -11
. .
1.11 Role and Responsibilitiesof the ProjectManager...................................
........................
................·-·-····---··--··-· ....1 - 13
1.12 Negotiation.....................................
...................................
..............................
- ..........................- .......·--···--·· ..····•...- .....1 - 13
1.12.1 . NegotiationFalls Within Two Categories...............................................................- - ·· ..- ·...- ..-- .. --···· .. ···' -14
1.12.2 Processof Negotiation...............................................................
..........................- .......-·-······· ·-········- ........._ 1 -14
1.13 Conflicts ...............................
................................
....................................................................................
· ·········-·········..- ...1 • 15
1.13.1 Causes of Conflict..........................................................
.........................................
......................
.............................1 - 15
1.13.2 Ways to ResolveConflicts .....................................................................
- ..........................
.......................·-·-..·····-· 1 -1 6
1.14 Organization Structure.........................................................................................................
..................................
....- ............... 1 • 17
1.14.1 Roles of OrganizationStructure...................................................
.........................................................
.....................1 • 17
1.14.2 Importanceof OrganizationalStructure.........................................................
........................ ........- .........................1 -18
1.14.3 Some of the Most Common Organization Structuresare ..........................................................................................
1 - 18
1.15 Project ManagementInstitute(PMl).............................................
........................................
..........................
..............................1 • 22
1.16 PM KnowledgeAreas...............................................................................................................
....................................................1 • 23 •
1.17 CertifiedProject ManagementProfessional (PMP)................................
......................................................................................
1 • 23
1.17.1 .................1 - 24
The Demand for Project ManagementProfessionals...............................................................................
1.1o/.2 Careers in ProjectManagement............................................................ ............,........: 1 - 24
..............................................
1.18 Project Management Book of Knowledge (PMBOK)...............................
...........................................................
.........................
. 1 • 24
1.18.1 PMBOK Structure...........................................
...................................................................
........................................
1-25
...........
1" ,,,u,111,11,
2.S Strategic Project Selection ......................................... ....................... .................................................. ........ ......... ................. ......... 2 ·9
2.3. 1 Techn ique s used for Strateg ic Project Selection ..................................................................... ..................... ............... 2- 8
I, Module3 .J
l£hapter 3 : Pro)ect Plennlng and Schedullng 3-1 to 3-41
I Syllabu• : Work Breakdown structure(WBS) end linear reaponslbllltychart, Interface Co-ordinationand concurrentengineering, Protect
cost estimationand budgeting, Top down and bottomsup budgeting, Networl<Jngand Schtdullng technlque1. PERT, CPM, GANTTchatt,
Introduction10 Pro 8C1 Mana ement Information stem PMIS .
~. ProjectPlanning .........................................................
................................
.........................................................
........................... 3 • 1
1
3. .1 Purposeol the Projec1 Plsmlng.......................................................................................
- ...............- ......._ .........- 3- 1
1
3.1.2 Basic Processesol ProjectPlanning..............................................
.............................................................................
3• t
3.1.3 Important Areas ol Project Planning...............................................................................
...................- .........·-···.........3- 2
3.2 Projec1 Scheduling.....................................
............................
...............................................................,........- .............................3. 2
3.2.1 ProjectSchedulingProcess......................................
....................................
..............................................
- ...............3 - 2
3.2.2 SctiedulingTechniques..............................
:..........................................................
.....................-••- .........-·-· ··- ····.. 3 • 3
3.3 Work BreakdownStructure(WBS) .......................
.........................................................................................
- .............- ...........- 3 • 4
3.3.1 Characteristicsof a Work BreakdownStructures................................
................................................
.........................3 - 4
3.32 Advantagesof WBS ..................................................... ....- · .........·--··-·--·····- 3 • 5
...........................................
3.3.3 ·-··· ..................-- ..·······3- S
Work BreakdownStructureRules................................................:......................................
3.3.4 Work BreakdownStructureDiagram........................................................... - ....'.......- ....·····--·····•···3 - 8
.......................
3.3.5 DifferentForms of Work BreakdownStructure.............................
.........................................
·--·-·---- ....3- 7
3.3.6 Processto Create a Work BreakdownStruciure.. ...................... :..............:.........-·-·--- ........3-8
...........................
3.4 Linear Responsibi!ily Chart ..................................................................................
........................................ ·-·-·----- 3· 11
3.4.1 Preparationof LAC..................................·................................................................
......-....... .... · - . --· 3 • 11
3.4.2 AdVantagesol LinearResponsibilityChart......................................................................
......- .................
-- ......3 • 12
3.4.3 Disadvantagesof LinearResponsibilityChart .........................
: .........................- ............................- ....___ 3 • 12
3.5 InterfaceCoordination..................................................
.......................
..................·........................................- ...···---·· ..···3 • 13
3.5.1 Objectives.............................
................................................................
........................................- ...······-···· ........ 3 • 13
3.5.2 Process................................
.........................................·....................
........................................---· ....·--· ...- 3 • 14
3.5.3 Functionsof lnter1aceCoordination....................
.................................................................................
....- ...........3 - 14
3.5.4 ....................................................................3 • 14
Roles and Responsibilitiesof lnter1aceCoordinator$.............................
3.6 ConcurrentEngineering .................................................................
........................ ................._ ..............3 - 14
....................................
3.6.1 Benefitsof Concurrent Engineering...................................................................;.....................................- - ..........3. 16
3.6.2 Advantages ol ConcurrentEngineering.............................................
...............................................
.......·-· ·····.....3 - 16,.
3.6.3 ·-·······- - ····.....s - 16
Disadvantagesof ConcurrentEnglneerfng......................................................................................
3.7 ProjectCost Estimationand Budgetlng...............................................
.........................
................................................................3. 16
3.7.1 Characteristics................................
...................................................
....................................
.......................... 3. 17
3.7.2 Key Componentsof a Cost Estimate................................................... ........ .......3. 17
.....................................................
3.7.3 ProjectCost Estimation Techniques........:·········.................... .............. 3 . 18
......................................................................
3.7.4 Cost EswnatingProcess·...........................................
.'................................
.............................................
_ ....- ... 3 - 19
............
3.7.5 Advantages ol Cost Management.. ..........................................................................................................,. ,.............3. 20
3.8 Bottom•UpEstimating............................................................................................................................
·.............·....., .•. •·.........S. 20
3.10
~~;:.:~:=::::-- --- - - - -._- _ _ .----__ _ _ _ _ - - - - -_.-_• •-_. . - - : ::::::··: ::-~:::;
3.1 o.1 S1eps used In Network Planning........................... · ...................................................................
3. 23.
Netwonl Olagram............................
....................m are ..... :::::::::::::::::::::::·· ................ ................................. ............... : ....... : .. :....... 3-23 •
3.11 .1 Main Functions of a Network Dlagra ................................................. 3 • 24
3.12
3.12. 1 Basic eoncepts ol Network An Y5I • ..............................3. 29
3.13
:::
40
3.14
:,:~""":::-.;:~~~:;;:.;;;::;•: ::::•••::: •----------•---------- - ---------- ------ ---. ···::
3.15
3.15.1
3.15.2
3 .15.3
3.15.4
Project ManagementInformation System . (PM IS) ....: ............................. ................... ............. ............. .... .................... ... .............. 3 • 46
3 .16
3.16 .1 Functions ......................................................... ...................................... .................. .............. ................. .................... 3 • 47
3.16.2 Advantages................................................................... 3 • 48
...........................................:····..•·•·····.. ················•·••·••···•··••••
Syllabue : Crashing project time, Resource loading and levelling, Goldratt's critical chain, Project Stakeholders and Communication pl_an.
Risk Management in projects : Risk management planning, Risk Identification and risk raglster, Qualitative and quantitative riskl
assessment,Probability and impactmatrix. Risk responsestrategiesfor positiveand negative risks.
4.1 ...............................................·••...•4 •
Introduction................•••....••.. ••••.. ••••••••••••·..•·••..•••••..•...•••••.....••··................................................
4.2 Project Resou rce Allocation .. ........................................................... ...................................................· .................................. ........ 4.
4.2.1 Benefits of Resource Allocation..............:.......................................................
........... • •
4
4.3
6.10
5.10.1
5.10.2
5.10.2 (a)
5.10.2 (b)
Project Management(MU)
7 Table of Contents
.
6.2.3 Ethical DIiemma......................................
......................................................
...............................................................
6-4
6.2.4 Traits of Ethical Professlonala...........................
: ...........................................
..........................:.........................
.:.........6 - 5
............
,,1 1tc ath•1
Definition of a project, Project Vs Operations, Necessity of project management, Triple constraints, Prnject fife cycles
(typical & atypical) Project phases and stage gate process. Role of project manager, Negotiations and resolving
conflicts, Project management in various orgahization structures, PM knowledge areas as per Project Management
Institute (PMI).
1.1 Introduction
Project Management for long has been an Important functional area of large no. of organizations. Today, large no. of
organizations execute 50% of their work activities in the form of projects. There are large no. of project organizations
whose main activity is to undertake and develop projects for. other organizations. The projects executed are of all kinds be
ft infrastructure, IT, industrial setup or services. The successful execution of a project requires an effective use of
management tools & te(:hniques in order to achieve the objectives. Thus, Project management as a subject of study has
become important for management personnel and students ..
1.2 Project
- A project is a temporary work done with a definite start and end. It is generally unique in nature unlike a regular
operation . It is planned and executed keeping a specific problem or opportunity in mind. The aim is always to achieve a
specific goal that helps solve the problem or avail the opportunity present.
For example : Building a bridge or a building, Developing a software, Launch.Inga p~duct, Conducting an event, Doing
a market survey etc. Almost everyday around the w9rld large no. of projects are initiated.
The success of any project is measured by the objectives achieved at the end. Some of the important objectives to be
achieved are the set standard of the output, its timely compietion and meeting budget limits. In order to achieve the
objectives, the role of management becomes very Important. Project Management is the application of management
knowledge, skills, tools and techniques to project activities In order to meet the project requirements.
Operations
Operation Is a vital organizational function. It Includes production of goods as well as services. The process of
operations turns raw materials Into goods. The quality of products to a great extent depends on the operational
efficiency and effectiveness.
- Operations include a three step process- Input, Process and Output. It is a routine function within an organization and
is performed as long as the business of the organization exists.
... For effective and efficient operations Its proper management Is of utmost Importance. Operation management is the
administration of business practices to create ~he highest level of efficiency possible within an organization.
There are many differences between projects and operation s. Some differences are as follows :
(i) Projects are unique and temporary , while operation s are ongoing and permanent with a repetitive output.
(ii) Projects have a fixed budget, while operations have to earn a profit to run the business .
{ill) Projects are executed to start a new business objective and terminated when It is achieved, while operational worfr
does not produce anything new and is ongoing.
(Iv) Projects aeate a unique product , serv ice, or result, while operations produce the same product , aim to earn a p
and keep the system running.
(v) There are more risks in projects as they are usually done for the first time, while in operations there are fewer risks
they are repeated many times.
(vi) Projects are performance Intensive while operations are efficiency intensive.
(vii) Projects are managed through project management and operations require business proces ~ rr,anagement.
Understand this difference through an example : Assume you were given a _project to build a car manufactu
facility. You build the facility and deliver ft to the client. Your Job is completed , and the client has started manufacturt
cars. In th is example, building the facility is an example of a project , because here you
. con st ru ct e d a car manu fa ctu
.
facility and handed It over to the dlent and signed off.
However , once the faclllty ~tarts working and the car manufacturing process begins this Is
operations , because here the facility is producing a repetitive o~tput, cars. Therefore, t~is Is an
operation .
~. development and Implementation of project's phases : A project generally Involves different phases such
_ succesSTu1
as Initiation, Planning and Design, Construction and Execution, Monitoring and Contr ol, Completion. The smooth and
uninterrupted development and execution of all the phases ensures the success of a project .
productive guidance, efficient communication and supervision:The successor failure of a project Is highly dependent
on teamwork which requires collaboration among Its members. Proper guidance, Good communication and r~lar
supervision are of major Importance as Information needs to be articulated In a dear , unambiguous and complete way
so everything is comprehended fully
_ Achievement of the project's main goal : Project management has the responslblllty of achieving the set goals of a
project even with the presence of all constrains. ·
_ Optimization of the allocated resources : The success of the project also depends on the optimum utilizat ion of all the
resources. This is a major objective of Project management. The Identification and proper utilizat ion of the resources
are to be done to achieve the goals.
_ completion of project as per the client's exduslve needs and objectives : This might n;,ean that you need to shape
and reform the client's vision or to negotiate with them as regards the project's objectives, to modify them into
feasible goals. Once the client's aims are clearly defined they usually Impact on all decisions made by the project's
stakeholders.
1
.5 Importance of Project Management
l aearfy defines the plan of the project before It begins : The importance of planning in project management cannot be
I ignored. The more complex· project , the more scope there is for chaos. One of project management's primary
functions is to tame the chaos by mapping out a clear plan of the project from beginning to end.
• Establishes an agreed schedule and plan : Schedules help to elimln·ate delays or overruns and provide a plan to be
followed for all those involve~ with the project.
. .
Create a base for teamwork : People are required to work In a team on a project. This Is due to team synergy benefits
t hrough the sharing and support of knowledge and skills. Bringing people together in this way inspires team members
to collaborate on a successful project .
Maximization of Resources : Both human and financial resources tend to be expensive. Project tracking and project
risk management ensure that all resources are used efficientlv and are accounted for economically.
Facilitates Integration : Projects that are completed w ithin an organisation are generally integrated with wider
business processesand systems. Integration forms the value aspect of proje cts and their management.
Keeps control of the cost : Depending on the scope of the project , some projects can Incur organisations significant
costs. It is important therefore to keep on budget and to control spending. Project management greatly reduces the
risk of budget overruns.
Manages O,ange : Today, more than ever, change Is something which all organisations face. Projects, during their
running, also face changes and must be prepared to face such deviations from the orig inal plan. Project management
allows for effective change management and makes It less of a complex ta sk.
Ensures Quallty : More so than ever, it Is important to produce quality results. Project management helps to Identify,
manage and control quality . Quality results ~ake clients happv, which Is a w in-win situation for all Involved •
no.....,.
• •••••cat&
••'
Business functions or projects are not performed In closed environment. There are a lot of uncertainties that surround
a project. These are called environmental factors and they play a vital role in the success or failure of a project . They m
be interna l as well as external to the organization and often many of them are beyond the control . Therefore it beco
apparent to Identify all of them in time so that pro-active measures can be planned to minimize the damage
interferen ce In case such a situatio n arises.
1. Internal Environment : It comprises all those factors that are present with in the organization and that may impact t
success of the project. They are g_enerally within organization's control. Some of them are
L -
Scanned with CamScanne r
. .
Project·Management(M~) 1-5 Project ManagementFoundation
Triple Constraint
It is a model of the constraints Inherent in managing a project. Those constraints are threefold. They an~
0 Cost: It is the financial constraints of a project also known as the project budget.
o Scope : It is the tasks required to fulfil the project's goals
0
Time : It is the schedule for the project to reach completion
The Triple Constraint states that the success of the project is impacted by its cost, scope and time. As a manager of the
project, you can trade between these three constraints. However, changing the constraints of one means that the
other two will suffer· to some extent which should give you an idea of ho~ important the Triple eo·nstraint is when
managing a project.
If you are managing a project you are working with the Triple Constraint too . Therefore, it can·be easily argued that
the Triple Constraint becomes a vital concept in project management.
- While it's true th at' the Triple Constraint is an important part of any succes~ful project, it doesn't determine success.
Projects are made from many parts, more than the three that. make up the Triple Constraint but these factors are
always at play in the project .
1. Cost
- Cost is the first financial constraint that affects a project . It is the flnanclal commitment that Is made to the
project. Cost of a project Is dependent on several components ranging from the materials to people. Apart from
that there are outside forces also that Impact a project and therefore they too are considered as the cost of the
work .
- Costs are divided Into fixed and variable cost. Both of them are associated with a project. Costs vary depending
on various factors such as the use of contract workers or outsourcing .
The scope of a project Is the second constraint . It outllnes the specific requirements or tasks which a~e "'"'°'sa,w
t 0 compete
I
the project . Managing the scope Is vital In any project, whether they are a811e software ProJectsar
·
well-planned waterfall projects. Failingto control the scope of the project will not help in delivering it on·-ar
within budget .
Managing scope is critical. It Is Important to prioritize the tasks so that resources are planned and assisn.c1
effectively .
Project management has a specific feature called task management that help ' a project easily assign, sort and
prioritize the tasks . This way all ttie critical project tasks can be delegated to the right people. It prevents the
scope to be compromised . Additionally, by offeri_ng file sharing and task co~ments, collaboration on the tast
level is encouraged .
Manilging and establishing scope a lso requires effective handling of stakeholder expectations. Stakeholders often
o I have new demands that keep coming up during the progress of a project and that need to be fulfilled. This can
especially be the case in long term projects whe re new stakeholders might be Introduced in the middle of the
project.
In order to fulfill the requests and new demands of stakeholders that come with the progress of the projects, it is
important to manage change. At the same time care should be taken to ~ccommodate only those change
requests that are necessary to achieve project goals and deliverab les.
The steps used under scope management are essential as the amount -of time each task required 1.s critical
a
assure the quality .of the project. This can have great impact on schedule and cost particularly for a proj
/' which is large.
3. Time
nme is a very important project constraint. The amount of t ime required to complete a project or produce
deliverables must be estimated well for a good schedule . Usually, this .ls done by flrst identifying all the tasks
are going to be performed during the entire life cycle of the project.
For estimating time , first of all a Work Breakdown Structure (WBS) Is used generally to convertthe large p
goal into a series of manageable tasks . These tasks ~re then prioritized and placed on a tlmeline .
A useful tool In the form of Gantt Charts can also be used to prepare the project schedule, .with each task
place on that timeline , with task dependencies linked, and durations determined. Data from previous pro
can also help make more accurate estimates .
For estimat ing time, various project management software features such as an online Gantt chart are aval ·
Here , time gets updated automatically as your team completes their projeot tasks, so data is always accur~te. ·
Accord ing to the Project Management Body of Knowledge (PMBOK), the schedule can be managed through a p
of time management . Those steps are as follows.
(IJ Planning schedule : Before beginning with a project, necessary policies, procedures and documentation with regard
to planning, executing and monitor ing of the project schedule should be prepared .
(Ii) oeflnlng Activities : It is very Important to Ident ify and reco rd all the actions that can be taken to produce the project
deliverables.
(Ill) sequencing Activities: Next step Is to Identify and record the order of the work activities In the right logical way.
(Iv) Estimating Resources Required : A project requ ires various resources In various quant ities. Therefore , It Is Important
to estimate What type of and how many material s, p~ople, equipment , supplies, etc . will be required to perform each
activity.
(v) Estimating Activity Durations : In this step , you calculate the time required to complete each activity with the
required resources .
(vi) Developing Schedule : In this step , you Analyze activity, duration , resources and timellne to develop a proper
schedule.
(vii) Controlling Schedule : This Is done by comparing the planned schedule to the actual progress . It tells whether the
project is on track or not. Necessary actions can be taken based on the ana_lysls.
Thus, as we can see, the triple constraint should be balanced to reach a successful conclusion.
The project management life cycle is a process that is followed by nearly all the project managers . It provided a
~a mework within which any project can be well managed . Leaders around the world have found that following a project
e cycle is critical for the success of a project . . ·
A project cycle can be of two types
Typical : It is also called a standard Project life cycle becau se It follows a set of steps that are predictable and prove
successful in most of the cases. '
• Atypical : It is also called Adaptive Project life cycle. It deviates from the set steps and is used mostly for projects
where rapid changes are expected and scope is not possible to define upfront .
In project m~nagement there are five pha ses: initiatin& planning, execut un& contr olling and closing. The five phases of
.I
project const itute the project management life cycle.
. Initiation .
. .
This Is the pha se where all projects begin. In this phase, t~e value as well as the feasibility of the project is
determined . The project is approved or rejected on the basis of these two documents . They are created to convince
the stakeholders or sponsors: •
(I) Business Case : A business case Is a document prepared t~ justify t·he need ·of the project . It anal;,,ies the benefits
to be offered by the project both in ter'!ls of financial gain and problem solving.
(IIJ FeasibilityStudy : This is an important report . It analyze whether it Is feasib le to start the project and complete
on the given time. You need to evaluate the project's goals, the timellne to comp.letion a·nd the total cost to be
Incurred. You also requ ire to identify the resources to be requlr~d to complete the project .
Once tha project Is approved, the next step Is to build a project team and start working on .project planning. Pl
helps to achle th
ve e goals within budget and allotted time. .· .
The project plan Identifies the resources, financing and materials needs . The plan also gives your team directton
the following : · ·
(I) Scope : A Scope statement reiterates the need for the project and lde~tifles its deliverables and objectives. . .
(II)
Definition : It is a process used to break down the larger deliverables into smaller ones th at help manage:
better .
{Ill) Tasks : Tasks are performed to produce the deliYerables. Thus thel~ identification and dependence on
tasks must be figured out . .
(Iv) Schedule : This refers to the duration of the tasks and their completion date and time.
(v) Cost: Costs are the financial commitments involved·across the 'project and it helps formulate a budget.
(vi) Quality : Quality objectives are important to be defined and 'met throughout the project.
(vii) Organization : Project organization must be clea.rly described with a good structure including (eporting
progress.
(viii) Staff : Determining roles and responsibilities of the project team is another vital aspect of project planning .
(ix) Communications : Decide how information wiPI be disseminated, to whom and with what frequency .
(x) Risk : Project plan also includes asse ssment of possible risks that are likely, and their impact on the project and
how to resolve them. ·
(xi) Procurement : Decide what work or materials will be contracted. Define those contracts and who they'll go to
3. Execution
·After planning is done , it's time to start the project execution. This phase is made up · of the following detail
processes:
(i) Executing the Plan : You begin by following the plan you crea~ed . Assign the tasks to team mem~ers and mana
and monitor t~eir progres s with project management t~ols
(ii) Admlnlstrat _e : This is done by manag ing the _contracts secured Ion the project.
I. Close
1
This Is the last phase of the cycle. A project Isn't over tlll the project goals and objectives have been met. The last
phase of the project Is all about meeting the goals. This Involves the following set of processes:
(I) scope: Make sure the project deliverables have been comp leted as planned.
, (II) Administration : Close out all outstanding contracts and administrative matters, archive. the paperwork and
disseminate to proper parties.
_ • The life cycle of a particular project Is composed of different phases, around which the project management scheme is
organized. There are different types of project life cycle depending on the organizations involved as well as the phases.
one of the project fife cycles important In project management is the adaptiveor atypical project flfe·cyde.
An atypical project life cycle is change-driven. It Is an agile way of doing things as it is intended to the high level of
changes. It needs on-going stakeholders involvement. In this life cycle, the overall scope of a project is broken down
, into different sets of requirements or sub-projects that wiil be undertaken individually. During the iteration, the
functionalities of the cycle is discussed, imp lemented and, finally, reviewed by the client.
Here iteration s are very rapid usually with a duration of 2 to 4 weeks and are fixed .In time and cost. This life cycle is
· used for projects where rapid changes are expected and scope is not possible to define upfront . So, a change during
the proj ect is naturally handled in rapid iterations.
Also, the end result is delivered at the end of 2 to 4 week iteration. Like, a yearlong project_will have multiple 2-4 we~k
ite ration and each iteration will execute Planning, Analysis, Design, Code, testing phases and deliver the result at the
end of the iteration.
The advantage of atypical life cycle is that it is appropriate for projects that involve higher levels of complexity and
uncertainties such that each ite ration of. this particular project life cycle should address issues for every task and each
task should be completed before another task is undertak~n. The risk _is minimized for this particular project life cycle.
Constant Change
2. Urgency
f
Need to Learn
Small Team Ability
Deliver in Small Increments
When we work in adaptive, there's a sense of urgency, we've to move quickly. We also recognize before we get
underway that there will be constant change. There will always be change on projects. It's constant change after
change and de~ision after decision. You need a different framework for an adaptive project then you do for predictive,
incremental or iterative projects .
Unlike a predictive lifecycle or incremental iterative where you could have one factor suggest that t~is is a predicted,
or thi s is incremental becau~e we can do phases or stages. In an Adaptive project you need constant change as a .
definition. There will be a sense of urgency to learn because you don't know the goal because it's unclear.
For this methodology, or sometimes referred to as the Agile Manifesto, It Is a small team ability.Small teams set out
to work to figure out where to go.
wTedl....._.
..... , w1t1 ,at101s
' -
Scanned with CamScanner
project Management Fo
1-10 ,
. Project Management (MU) 5 exploring but unsure wttictl Pro
. Th~ State Gate pro:ess is ·a patented tradema~k of Dr. Robert ·co~per. The center of this model ~s on dev~~
innovative
. . processes
. . . Waterfall process.
. , It 1s also called the . This model offers a pr OJe · ct management technique• •:
whk:h
proJect 1s d1V1ded into severa l stages. The stages are sepa rated by 'gates' wh ere d ec Is1ons
· are taken to decide whether'
not to proceed to the next stage. This mode l Is generally useful while d I · . . ·
improvements in a. · eve oping new products or bringing change'
1.10.1 Gates
Gates in state
, gate process are decision points In a pro ject. They help take a d l . · · ,
, ·: "'
~tage or not. The decision is based on the availablllty of Information ec sion whether to continue then
O th
1s taken by a manager: or a committee . n e project progress till that moment. Th~ de . •
At each gate, the quality and repercus sions of Id . . ' '. •,
. b . an ea are asses d Th
execution, usmess motivation to continue flnanciall se . e areas of assess . . . ., . .'
the project successful. After each gate one of th Yand the action plan showing the th' ment are the ~uality.
' e ,ollowing deci I mgs that need t b -:.i -- · t "'
- Go: This decision consid th s ons Is to be taken ; o e uone ,. o
ers e project-good enough to . , , . :..:, .
. . . move on to the next stage. .i
1.10.2 Stages
The Stage Gate process has five stages. They are connected to each other by gates. Each stage is designedto collect
specific information :
stage O: Discovery
Stage 1 : Scoping
Stage 2 : Business Plan Concept
Stage 3 : Development
Stage 4: Testing and Validation
Stage O : Discovery
I . .
This is the initl.11 preparatory stage. It identifies the project ·a company wants to undertake. For that, Ideas are
generated in brainstorming sessions. ~veryone from Employees, Customers to the suppliers are involved in the session.
~ey provide useful Info rmation for idea generation . An Idea is first selected and then proposed. If the idea is not is not
. found good enough the gate closes here.
Stage 1 : Scoping
In thi s stage, the product and the existing market for It are assessed. Product's strengths and weaknessesand the
benefit s it brings to the user/consumer are evaluated . All the possible threat s from competitors are also taken into
account. The assessment of the threats helps decide whether project will not continue .. If the threats .are big the chances
are that the gate will be closed.
Stage 2 : Business Plan Development
This is the last stage of concept development . Here; business plan is developed considering all kinds of opportunities,
~re ats, competit ions, et c. It is crucial before starting th e actual project lmple~entat ion. Thl.s stage indudes the following
sob-stages: .
Here, a document of the project Is prepared to describe and define the project requirements Including the legal health
and safety requirements .
This plan contains a list of all tasks that are to be executed during the ent ire project development cycle. It also o
the roles and responslbllltles of the people Involved In the execution. The expected launch date can also be me
In this plan.
(Iv) Feaslblllty review
Here, a fea slblllty study Is done In which different departments assess the plarf s chances of succeeding . Even at
st age If it appear s that the business concept Is not having sufficient potential the gate Is closed.
Stage 3 : Development
- At th is stage, the plans are executed and simple tests are conducted. For example, at this stage c~st omers can
asked for their feedback of the product . A timellne with specific milestones that have to be achieved are created
the development team.
- This tlmellne can be revised and updated regularly. It also takes help of multi-functional teamwork . Different
departments provide input with expert advice. This stage results into a product prototype , which is then extensively
tested during the next stage. The gate remains closed if the prototype of the product has not been sufficiently
developed .
This test is done to identify all possible production errors or any other problem area'. At this stage, the product isi
almost ready to be sold. The groups that carry out this test include staff, regular customers and suppliers and are
closely tied to the organization.
In this part, the product is tested in the field by various participants who can make a valuable contribution. This
usually done with the help of specific customers. Whether this target group is interested in the product is evalua
The characteristi cs they consider important and the context in which the product will be used are also assessed .
This is an optional test as the product is offered in the market only when it has passed through the previous t
stages. This ~est is just to assess to see whether the product sufficiently matches the needs and wishes of
consumer after a period. The product is usually pretty much in Its final form after testing . However, a good marketln
plan Is equally important at the time of launching the product . If not, the gate to the next stage will remain closed.
. 1n· this stage , the marketing strategy comes into play. The product is ready to be launch d d h . ,
. . · e an t at requires atten
by means of an advertising ca mpa ign, free publicity and Interviews or other promot · . .. .
. . 1ona 1 act1v1t1es. An estimate ls m
a~out the quantity that will be sold. Policies regarding production inventory and d' t' 'b . . ·.
, 1s n ution are prepared In this st3
the sales team is predominantly respons ible for ensuring a smooth process . · ·
relative impact
He identifies and obtains support and advice required _for the management, planning and control of the project,
managing project a~ministration
_ , He has to regularly conducting a project evaluation review to assess how well the project is being managed and then
. he prepares any follow-on action on the received recommendations . ·
1.12 Negotiation
Negotiation is a process used to resolve disputes of different kinds_between different people or group . It is done by
conducting consultations between the involved parties to reach a consensus.
. .
Negotiation involves a discussion between two -or more parties involved: It aims at reaching an agreement or
settlement. It can take place at any time in a project, program or portfolio and it may be formal or informal in nature .
- Formal negotiations are held on issues such as contract agreements while Informal negotiations include discussions to
resolve conflict, or discussions to obtain internal resources.
The skill of negotiation is used in many areas of Project Management : They could be managing conflict, contract,
requirements management and stakeholder management. Negotiations can take place at any time within the project
management life cycle. Depending on the issues, It can be either formal or non-formal . Negotiations· are generally
initiated by the project manager and therefore he should have excellent negotiation skills.
Negotiation is done through a process whlc~ can be categorized Into phases. These include planning. discussing.
proposing and reviewing.
Planning is the first phase. It helps a manager in preparing all the relevant Information needed for the discussion. The
' second phase is discussing. It refers to setting up the scene for discussion. In this phase, the conflicting Issues are
e><plor@d and discussed.
The proposing stage Involves creating the solution to solve the problem. ,This may also Include bargaining before
arriving at ari agreement. Once the agreement Is done, the Information In this regard Is disseminated all throu,hout
the organization. Finally, the last phase reviewing Is carried ol)t to see whether it resulted Into a win-win sltua.tion for
both the parties or not .
Planning : This is the first step where the focus of the negotiating party is to gather as much Information as possib
That helps in preparing better plans. A plan is prepared by setting goals that' could be agree d upon .
Discussing : Project managers are often required to open the negotiations by giving the details of the conflict~
they explore and discuss the key issues. The involved parties must listen to, probe and question and regularly ch
the ir understanding of the discussion.
Proposing : At this step , the discussion Is over and based on that a proposal is made and communicated clearly
openly to all.
Bargaining : In this step , the negotiation begins for trade-offs . The parties involve try to accommodate each oth
demands.
Agreement : At this step , an agreement is reached and based on that an agreement is done , prepared on paper
signed as there is no substitute for a written record;
Review : Here, the outcome is communicated to all parties and the consequences Incorporated within the p
management plan .
Project managers often face a situation where negot iation becomes necessary. Therefore they need to be prepared
and apply negotiation skills throughout the project life cycle. Early on In a project, as requirements are being assessed
Initial plans produced, the project manager needs to balance the time , cost, quality and scope requlrffllents of the
and
project and negotiate with stakeholders.
_ AS resources are mobilized and procured , Internal negotiation with line managers who 'own' the rHOUrces and
conduct more formal contract negotiations with potentlal prov iders become necessary.
A.s the project progresses, conflicts may arise. Therefore the project manager wlll be required to negotiate the issues
of conflicts.
_ In some environments, there may be specialist support available. It Is Important for project managers to know when to
ask for help from , for example, the HR or legal departments within the host organization .
1.13 Conflicts
Conflicts are nothing new. We all experience it in our dally lives. It ranges from minor disagreement to a major
problem. But they have the potential to d!srupt organizational activities and progress. Being a project manager or a
team leader, these conflicts are especially rampant and thus damaging in project environment.
Since project activities are executed by human resources ·there Is a possibllity of conflict. Everyone tries to
execute activities in order to achieve project objectives as per the expectations of ·the stakeholders.- While
managing human resources, conflicts are natural but they become serious when they lead to quarrels, fights
and even a breakup of the project .team . According to the PMBOK Guide, "conflict is inevitable in a project
environment. #
o Inevitable
o Must be managed
Cultural differences
Poor Planning
After defl~ing the problem, the PMBOI< Guide suggests five techniques for project management. let's revi~
techniques and id .
. cons er when to use them In managing conflicts.
1
· With draw/Avofd Conflict
This Is a good technique where people involved retreat from an actual or potential conflict situation.
po st pone the issue to be better prepared or to be better resolved by others. Suppose you are short-tern ·
With drawing can be an excellent technique. By withdrawing, you have the opportunity to come up With
Ideas to address the conflict.
Temporar ily avoiding the conflict allows you to take time and rethink over the issues It also means you have
chance to think through the other person's perspective. While ~ithdrawing and avoiding is valuable in the
term, it can be over used. If you retreat · from a conflict situation and fail to follow up, the conflict is likely
. '
become worse over t ime.
2. Smooth/Accommodate Conflict
In this technique, emphasis is given on areas of agreement rather than .areas of difference. One concedes h'
position to accommodate the n·eeds of ~thers in order to maintain harmony in relationships. This approa
maintains professional relationships which are critical to project success. On long tenn projects, anything over:
few weeks, persevering and strengthening the project team becomes very important. Project tea m mem
constantly emphasize differences making progress on the project becomes very difficult.
Areas of agreement to emphasize may vary depending on the context. You can look at how disagree
impacts other s on the team.
3. Compromise/Reconcile Conflict
In this technique , the focus is on searching for solutions that bring at least some degree of satisfaction to·
parties and the conflicts is resolved either temporarily or partially. This technique recognizes that some
cannot be fully solved.
But, this technique has some drawbacks too. The project manager needs to understand the needs of the
,or stakeholder for successful negotiation. The project manager also has to be willing to make changes
project . For compromise to be successful, each party needs to benefit and sacrifice party of their objectives.
Project ~anager s can also compromise across time. For example, you m~y respond to a stakeholder's reqtt
additional functionality by deferring their request to phase two of a multi-phase proje~ . Though, this.
change Is best handled through a change request.
4. Force Conflict
· This technique creates more problems thari solutions. Here, the focus is on pushing one's viewpoi~t
expense of others thus offer ing only win-lose solutions It Is usually enforced through •. t
. · a power pos1t1on o
an emergency. From time to time, project managers have to take a stand and I th •
app y eir power .
As the PMBOK definition suggests , applying force to resolve fl'
con lets comes at a cost The P
manager is likely to harm relationships with the project team b · h" ·
. Y using t rs method. Abuse or overuse
technique tends to cause more conflict in the long term o h . .
. d · ne s ou 1d use thrs technique only when ab
require . . . ,,,,
5, Collaborate Conflict
_ Th6S techniquefocuses on Incorporatingmultiple viewpointsand Insights from differing perspectives. It require, a
cooperative attitude and open dialoguethat typlcally leads to consensusand commitment.
_ This technique Is the most productive technique. It has two major benefits; one, the conflict Itself Is solved and
second, the project team Is strengthenedas a by-product of working to solve the problem. This techniqueIs most
likely to be successfulIn situations where the project team already has a high level of trust.
The functions of Organizing and organization are Important In the following ways :
- Sp I II t
° ·
ec a zat on : In the process of creating a suitable structure, care Is ta ken t see that the activities are divided•
subdivided Into compact and convenient jobs. An organizational structur~ thus promotes specialization, s
. performance of tasks and efficiency.
- Well-Defined Jobs : The organization structure clearly defines and differentiates the jobs of managers an~
th
managers. This helps the process of looking for and selecting the employees and fitting the right person to e
job.
- Clarifies authority a.nd Power : A clear-cut definition of authority enjoyed by each manager and his jurisdiction
activity minimizes conflict and c~nfuslon about the respectivepowers and privileges of managers. A good organizatl
structure clarifies authority and power.
- Avoids Duplication of Work : The organization structure helps In avoiding duplication of work and over1apping i
responsibilities among various employees and work unit s. This is because specific jobs are assigned to individuals a
work groups.
- Coordlnatl(?n: The organization structure serves as a mechanism for coordination and unification of efforts of peo
Harmony of work is brought about by higher levei managesexercising their authority over interconnected ·activities
lower-level managers.
Line organization is the simplest form of organization and ls most common among small companies. H
authority is embedded in the hierarchical structure and it flows from the top of the managerial hierarchy d
different levels of managers and subordinates. and further down to the operative levels of workers. It
identifies authority, responsibility and accountability at each level. · ·
These relationships in the hierarchy connect the position and tasks of e~ch level with those above and be
There is clear unity of command so that the person at each level Is reasonably independent of any other
at the same level and is responsible only to the person above h·1m The Ii I
• ne personne are directly invol
achieving the objectives of the company.
Because of the small size of the company the llne structure is sim I d h ·
' P e an t e authority a d lb"
clear-cut, easily assignable and traceable. It Is easy to de I n respons 1
ve op a sense of belo • h .
communication Is fast and easy and feedbackfrom the empl ngmg to _t e organ
. oyees can be acted upon faster . .
(b) Line and Staff Organization ·
taff • This group has a general background usually similar to e,cecutlves and serves as assistants to top
GeneraI S ·
em ent They are not spec.lallstsand generally have no authority or responslblllty of their own Th.., may be
manag · · -,
known as special assistants,assistantmanagersor In a college setting as deputy chairpersons.
spedallzedstaff : Unlike the general staffs who generally assist only one llne e,cecutlve, the spedallzedstaffs provide
expert advice and service to all employeeson a company wide basis. This group has a specfalizedbackgroundIn some
functionalarea and it could serve In any of the following capacities:
(I) Advisory capacity : The primary purpose of this group Is to render specialized advice and assistance to
management when needed. Some typical areas covered by advisorystaff are legal, public relations and economic
development.
(ii) service capacity : This group provides a service that Is useful to the organlz~tlonas a whole and not just to any
I specific divi.sion or function. An example would be the personneldepartment serving the enterprise by procuring
the needed personnel for all departments. Other areas of service Include research and development, purchasing,
statistical analysis, insuranceproblemsand so on.
(iii) Control capacity : This group includes quallty control staffs who may have the authority to control the quality
and enforcestandards.
The line and staff type of organization uses the expertise of specialistswithout diluting the unity of command.
With the advice of these specialists,the line managers also become more effective and develop a sense of
objective analysisof business problems.
The line and staff type of organizationis widely used and is advantageousas the specializedadvice improves the
quality of decisions resulting In operational effectiveness. Staff specialists are conceptually oriented towards
looking ahead a~d have. the time to do strategic planning and analyze the possible effects of expected future
events.
Its main. disadvantagesare the confusion and conflict that arises between line and staff, the high cost that is
associated with hiring specialists and the tendency of staff personnel to build their own image that is sometimes
at the cost of undermining the authority and responsibilityof line executives.
Functional Organization
- One of the disadvantagesof the line organizationIs that the line executl ve.s lack specialization. Additionally, a line
managercannot be a specialistin all areas. In the line and staff type of organization, the staff specialist does not
have the authority to enforce his recommendations. The functional organizationalconcept, originated with F W
Taylorperm~s a specialistin a given area to enforce his directive within the dearly defined scope of his authority.
The following Fig. 1.14.1 is an exampleof functional organization :
'Vice President. .
~' Engineemg-
.. , rt ,,,...
:,°"FunctJon: .
..,.,Manager-~:J.- ____ .. .____ ...... ..... ___ .... .,______ .....,.a.;.;....._;._ ...
Tldi.......
.. ,,a 11c, uo as
Matrix,Organizatlon
- A matrix structure can be said to be a combination of project and functional structures and is created to
overcomethe problemsassociated~ Ith project and functionalstructures. The key features of a matrix structure
are that the functionaland project lines of authority are super-Imposedwith each other and are shared by both
functional and project managers.
Chief
Executive
Project Manager
ProjectManager
- Matrl,c organizational design Is most useful when there Is pressure for shared resources. For example, a compa
may need eight product groups, yet have the resources only to hire four marketing specialists. The m ·
provides a convenient way for the eight groups to share the skills of the four specialists.
Each matrix contains three unique sets of role relati onships :
0 The top mal')ager or Chief Executive Officer who Is the head and balances the dual chains of command
o The managers of functional and project (or product) departments who share subordinates
o The specialists who report to both the respective functional manager and ·project manager.
- PMI stands for the Project Management Institute . It is a not-for-profit volunteer professional membership association
for project managers and program managers. It supports and drives our Industry forward.
- PMI was started in 1969, and with over 250 project chapters and a membership of more than 2.9 million professionals
around the globe, PMI today is the largest project management membership ·group.
- The Project Management Instit ute is the organization that gives out the PMP (Project Management Professional)
credential, a globally recognized certificate that assures employers that a person is trained and qualified to manage
projects.
- PMI, in conjunction with its volunteer membership, developed A Guide to the Project Management Body of Knowledge
(PM BOK• Guide), which is the agreed upon book of standard language, terminology and principles governing project
management. In the past, there was no formal degree in project management for project · managers. PMI has been
instrumental in creating the Project Management Professional (PMP) certification, which professionalize~ the career of
project management. Now, project managers worldwide have been studying the agreed upon principles and passi
the PMP exam. The PMP certification is formalizing and validating the profession.
Project Management Institute, Inc. (PMI) found that 52% of all project teams are a mix of professional proj
managers and non-project managers. In the past, experienced project managers had a couple ·ot choices. Invest in
high end software solution that takes a lot of training to Implement, or purchase a low end tool that lacks featu
Now, Project Insight bridges the gap.
Project Insight is the only mid-range project software that respects and conforms to PMl's PMBOK Guide or standa
body . This is important for teams that are of mixed levels of expertise.
- Most experienced project managers have been using Microsoft Project desktop to manage projects. More and more
these savvy project managers find that they need to collaborate on projects with dispersed project teams. Vet,
still need robust scheduling functionality. On the other end of the spectrum, the team members , vendors, con .
and other third parties they collaborate with want something that Is simple to use.
Project Managers
Functional Managers
Team Leads
Project Executives
Tedll 111 Ip
• Pv\1 Jc it t1 •s
- Offers good career - As Project Management Professionals are In huge demand across industries, the opportuniti
never cease and good decisions provide a soaring career .
- Constant learning- Project managers are always learning and enhancing their skills. This is a great career move
individuals who wish to regularly update and refresh their knowledge.
PMBOK has been used as the standard by which Project management Professional Certification is obtained.
Certification is based upon a survey of many companies' best practices . The advantages of using PMP Certified p·
Managers and Team members are that resources have already been trained . PMBOK Is valuable for both companies
employee s. PMBOK Is valuable for many reasons . Here are three :
- The first reason PMBOK Is valuable Is that It allows companies to standardize p ctl
ra ces across departments. Thls
that the people In development manage projects In the same manner a th d . .
s ose In \stnbut1on.
- Second, PMBOK can help project managers to work with a stand di d ·
ar ze system across com I So
for company x who then moves onto company y can use t.he sa pan es. meone
me pract Ices .
- Third, PMBOK discusses what works. The methods documented Ith\ h
those who are uncertain of how to undertake k w n t e project management community can
rI5 management PMBOK 1 •
prevents failure of projects. · a so discusses what doesn't wortc.
1· th camscanner
scanned W
Pro'ect Management MU .
1-25 Pro ect ManagementFoundation
- Finally, project managers who are famlllar with PM BOK standardscan custom tailor their proJect management process
to best fit their company's needs. There's an old saying, "To break the rules, first you have to know the rules." When
project managers Invest time Into learnlns the rules, they also are Investing time In !earning how and where rules can
be broken.
Project management as a practice Is rapldly growing and spreading worldwide, and is now seen globally as a
recognized and strategic competency, a career path a.nd a subject for training and education. The PMBOK framework
-consists of five process groups and ten domain areas.
Initiating
The initiating process group involves the processes, activities, and skills needed to effectively define the beginning of a
project. Setting all permits, authorizations and lnlt lal work orders in place to secure an effective and logical
progression of initlal project activities sets ~he stage for subsequent success throughout all _project phases. Setting
dear phases for work to be completed, initializing teams, and having the budget in place before work begins are vital
for a strong start to any project across industry.
Planning
The Planning Process Group sets forth the processesneeded to define the scope of the project, set strategic plans in
place to maximize worlcflow, and begin to assemble priority lists and plan team needs. This process group also
addresses a more narrow clarification of all proj ect goals and expectations and puts in place the project infrastructure
necessary to achieve tho se goals according to the timellne and budgetary constraints .
3. Executing
The executing process group Involves managing teams effectively while orchestrating timeline expectations and
reaching benchmark goals. Project managers utilizing this set of skills will demonstrate a high degree of organization
and communication skills while addressing team concerns or other complex situations associated with getting the
work done on t ime and within budget.
Monitoringand Controlling
Processing change orders, addressing on-going budget considerations, and mit igating unforeseen circumstances that
may affect a team's ability to meet lnltlal project expectations are all part of the core skills and competencies involved
in the Monitoring Process Group. Seasoned managers keep the momentum moving forward and guard the project
against stalling by actively monitoring progress and using foresight and quick response to address project challenges.
Monitoring and Controlling hover over the whole project. According to PMBOK GUIDE these are" • d
. , processes require
to track, review~nd regulatethe progress and performance of the project .
Closing
. The biggest challenge of this process group Is to bring the project to a successf I h
u cIose w lch means completing it on
time and within the budget allotted . The bottom line Is that while th
. ese process groups are not necessarily easy to
. implement , not doing so means the team may never realize the full be flt f h
ne so t elr highly strateg ic projects.
I· RevltiW'~ 1
2 nd 1 5
What is Project management?State Its importance. (Refer Sections1, • • )
Q. 1
· . (Refer Sections1.3 and 1.3.1)
Q. 2 What do you mean by Operations? DifferentiatePro}ect& Operations.
Q. 7 Oescn'be the atypical project life cycle along with its phases. (Refer Section 1.9.2}
Q. 8 What is Stage Gate Process? Describe its stages. {Refer Sections 1.10 and 1.10.2)
Q. 9 Desaibe the role and responsibility of a project manager. (Refer Section 1.11)
Q.10 What is Negotiations? What is its importance in rroject Management?How should a project manager prepare for·
{Refer Section 1.12)
Q.11 Describe Conflict and its causes. Explain ways to handle conflict. (Refer Sections 1.13 and 1.13.2)
Q.12 What is OrganizationalStructure? Describe its importancefor a proiect. (Refer Sections 1.14 and 1.14.2)
Q.13 Explain Functional & Project Structure. (Refer Sections 1.14.3 (c) and 1.14.3 (e))
Q.16 Describe the knowledge areas as recommendedby PMI. (Refer Section 1.16)
.,
2.1 Introduction
A project work demands a lot of plannlng and effort from all those who are involved in it . The basic understanding of
the project life cycle Is vital for every project manager speclally. As it Is said, well begun Is half done, the successful
Initiation of a project plays a very Important role in Its ultimate success. If you begin ·by putting the right foot forward you
are in a good chance of making it to the end as desirable. Thus project Initiation becomes a very important part of a project
work. This chapter deals with everything that helps you d~velop a good understanding of project initiation.
2.2.1(a) · People
'
Following are _the people generally associated with a project. Let us understand ~elr roles .
1. Team
(I) Describeyour Team
In the Project Initiation phase, It Is Important to define and form a team on the basis of the project requirements
and deliverables. You have to plan on what shape ~our team must be given. The following points help when you
form your core team :
2. Stakeholders
2.2.1{b) Process
Following are the elements of a project process to explore before Initiating a project .
1. Methodology
For your process to be effective you must begin by outlining your project act lv\tl d . b
es, e11vera les and the team.
process often comprises a blended mix of different methodologies Eff rt h .
1
methodologies that are suitable to give the desired outcome You sh Id. . f o I sf s ou d be. made to Identify
· ou re ra n rom forcing a certa in metho
Followingare useful when considering the methodology :
- Size of your project .
- Scope, timellne and budget.
- Right team (Dedicated or shared).
- Stakeholders collaborations
Always get your internal team and stakeholders agreement whlle selecting the right too ls. It Is also Important to know
how to use them effectively. later changes can· always be made depending on the requirements .
Managing Risks
There is no project that is without any risk. Risk Is an Integral part of a project. Thinking and planning all the possible
risks ahead ls vital in the proj @
ct Initiation phase. To do this, highlight all possible Risks and then Identify ways to
reduce their impacts incase that happens. You should also involve your team hold a pre-mortem session with your
team members where you discuss areas of risk, as they are often unexpected.
1. Requirement Analysis
Right product s the outcome of a project work . Therefore, you should try to understand the requirements of your
· project as clearly as possible In the initial phase. It's important to begin by outlining things that you know already such
'as the needs of the business, dient and users. This helps you to have a clear understanding of the background and
context for the project.
During the project · initiation phase, you must have a clear idea of the scope and deliverables that are required . You
must write them in details so that every aspect of them Is Included and agreed upon . This will avoid any confusion at
later stages. Needless to say, the Involvement of your team members and the stakeholders Is of utmost Importance .
3. . Setting Deliverables
on the basis of the Informat ion you collect, the dellverables must be flnallzed In order to avoid later confusions .
Therefore you must organize an Internal meeting with your team members and stakeholders to go through the
deliverables. Make sure to get the feedback and suggestions from everyone . During the meeting while reviewing the
deliverables with your team, keep these ateas In mind :
- The deliverables
Their format , shape, size and specifications
1. Business Case
The first step is establishing a busln_ess case in which focus is given on explai ning the reasons for _starting
project. The business case describes the availability of financia l a!"'d other resources to support the busi
need. A business case considers the requirements of the project and justifies how it fits the site and risk of
proposal. The stru~ure cif a business case re111ains the same irrespective of the project types. A business ·
basically outlines the project relevance comprehensively describing Its need and the likely impact . It does
reveal the technical aspect of the proposed project .
While describ ing the business case care should be taken to make It easy to understand , clear, logical
relevant . The key aspects need to be Identifie d, measured and ju stified . There also must be accountability
comm itment for the delivery of the· project outcomes and costs involved in the project '
Follow ing should be the contents of a business case :
o Preface
o Table of contents
o Executive contents of the project
o Business drivers , scope of the project and financials aspect
o Business analysis such as the costs and benefits , risk
0 Conclusion f ' .J
sf Project Management(MU)
2-5 InitiatingProject
2. Feaslblllty Study
- The next step is to prepare a project charter. It describesthe purpose for the project and its proposed structures
and execution. A project charter also sets the vision, objectives, scope and deliverablesof the project In details. It
identifiesand describesthe responsibilitiesof the project teamand the stakeholders.
- At this stage, the project charter Is able to present the project In structurallyorganized,well documented form
which mentlo~sthe project plan and list all risks, Issues and assumptions.
Building Team
- The next step is buildingof a team as a projectcannot be Initiated without an effectiveteam. Therefore, th is step
first prepares job descriptionsfor the people who will play their role in Implementing the project plan. This
includestheir role and responsibilities.
- A project team is built by first by defining the roles for each member as dearly as possible to keep the work
flowing smoothly. Next comes the responsibilitiesthat come with the role. Authorityassociated with each role is
also clearlydescribed.
- Sometimesa detailed organizationalchart Is built by listingthe skills and experience needed for each position. It
is also helpful In defining· different qualifications r_equired for each position. The chart also indudes the
performance criteria,salaryand'worklng conditions.
Project Office
- A project office is a place In the office·or work site where the project man~ger and support staff sit and woric
together during the project. It Is generally equipped with the communications infrastructure and other
technologyneeded for the project.
- The location of the project office must be near to the actual project work site. It should be large enough to house
all the people associatedwith the project.
Periodical review
- Periodicalreview of each step that was Identifiedduringthe Initiationphase must be done to ensure that there is
nothing that goes against the project as It Is always possibleto make mistakes and this Is especially true with the
project Initiationphase as it Is so criticalto the success of the project. Project periodic review is an essential part
of the project management.
- Periodicalreview also looks at the risks that were earlier Identifiedand see if any have occurred, and if so how
. .......
they were controlledand resolved. At times, changes are made to a project. A review evaluates if these changes
were done correctlyand whether they have kept the project on track.
,..
.... 11, -1 0 111
There are lots of ways to decide on which projects to select. Following are some basic techniques used for pick
projects to undertake . All of the methods listed here can be used alone, or In combination with other techniques .
·ng the project selection care should be taken to see how well a project can support organizational strategy. For
ouri
exarnple, if a service based organization sets Its mission to provide superior customer service, then the projects
ed should be such that It enhances customer service. For an organization that focuses solely on Innovation to
I ct
see
. competitive advantage, projects that support research and development should be picked as a better option
gain
Businessenvironment, today, is ever changing. lndustrlal, regulatory, and market conditions keep changing resulting
In the creation of new requirements. Organizations must keep a close eye on the changing requirements and fulfill them
with the right projects. People should be assigned with the specific job of tracking all the changes and looking for an
opportunity for t he organization to come up with a ~lutlon .
While selecting a project we must look at the time frame as it is an important point of consideration In the selection of
a project. It is done in two ways; analyzing the time of implementation and t ota l project life cycle time.
Time required in the Implementatio n of the proj ect compon ents is important to analyze part icularty when significant
portions of the project are to be implemented in a time bound manner. Analysis should be done to find out whether
the organizational resources required for a project are available at the time of project planning. Project life cycle time
is the total time involved in the completion of the project starting from selection and initiation to final dosing and
shut-down. Time frame becomes more important if there Is a limited period of time available for the undertaking of a
project.
Weighted scoring models are project selection analysis tools . They are useful when the decision on project selection Is
taken on the basis of not one, but several factors . In such a case, a weighted scoring model (Also called Decision
Matrix) is considered one of the best tools to examine, rate, and select a project among multiple available options.
- A weighted scoring model Is developed by determ ining the factor s which are considered Important to an organ~atlon
in project selection. Those factors are the n assigned a relative level of Importance or value (weight) . The factors are
then examined and rated for each available project opt ion under consideration with the rating multiplied by the
relative weight of the factor. The proj ect with the highest total score Is the one that should be selected
Project selection Is an Important function of businessorganizations. A wrong selection of project may ge~erat~·
which Is undesirable. Therefore, having a thorough understanding of project selectlon models becomes very Import~
Following are the two Important types of project selectlon models.
1. Non-Numeric
This is a commonly used method in which the senior members of the organization suggest a project out of their o
I
I understanding and expertise. Most' of the projects using this method are those that ar~ initiated out of an appare
opportunity available or taking chance of an un~established idea for a new product . The project is created as
immediate result of this approach in which about whatever the boss proposes becomes the project.
The sacrednessof such project reflects the fact that it generally c;ntlnues till It fin•is~es or until the senior declares
failure of the idea & ends it.
Sometimes, the necessity of a project arises simply because it i~ capab!~ of either ·enha,:icing the operating effid
of the organization or solving a serious problem that's troubling the organization . For example, if a plant is threat
by the flood then it is not much complex and effortful to start a project for developing a protective des~ M
potential projects are evaluated for sele~ion using this criterion of project selection. Questions such as t~e esti
cost and its comparative effectiveness come In· for analysis In front of the organization. The project cost Is gene
analyzed to find out whether these ~ould be maintained as minimum and compatible with the success of the proj
• I , •
Organization always like to stay ahead In competition and this desire becomes the basis for making decision to
out a project. Although, preference Is generally given to the project whose needs Is felt b th .
. • V
e operating nee
competitive necessity with regard to Investment. Generally both types of project I ctl . -
, se e on models are con
quite useful & effective as compared to others. ·
In this selection model called the product fine extension a project I iti d ·
.
' s In ate for the d · I & di~n
· 'b
new products and Is evaluated on the basis of how much It It th eve opment
5 u s e company's cu t d .. h . ,
fortifies a weak tine, fills a gap, or enhance the fine.. rren pro uct lines, ow
On many occasions, evaluatlon of profltablllty Is not done as the decision makers take decisions on the basis of their
belief about the probable Influence of the addition of the new product to the llne over the entire performance of
system-
Q-Sort Model
_ This is the one of the most simple and straightforward techniques used for selecting projects. In this model, the
available project for undertaking are first divided into three groups according to their relatfve merits. They are
Good, Fair and Poor.
- The main group is further subdivi~ed into the two types · fair-minus and fair-plus. The projects within each type
are ranked from best to worst. Again relat ive merit of the respective projects provides the basis for determining
thi s order. Specific criterio n is used by the rater to rank each project . Sometimes, he just uses his general entire
judgment.
- At times, one person holds the responsibil ity for carrying out the evaluation & selection process of the project.
Sometimes, a selection committee is formed to perform the selection process. The ranking of the projects differ
only to some degree from rater to. rater. Finally the projects are selected on the order of preference, though
financial basis becomes the most important aiterion before final selection .
These,.. models use profitability as the sole measurement criterion for selection of a project . Majority of the
arpnizations use different numerk types of project selection models. Following are some of numeric models for project
selection.
1. Payback Period
2. Accounting Rate of Return
3. Break Even Analysis
• 4. Cost benefit Analysls
5. Net Present Value (NPV)
6. Internal Rate of Return (IRR) • l
- This method Is a simple non-discounted factor method. It calculates the time period that will be requl,:ed for the
project to generate enough returns to recov~r the Initial Investment. It focuses on measuring the cash Inflows,
3. Break-Even Analysis
- Break-even analysis is another numeric financial tool used frequently for project selection. It is used to deter
the stage at which your project, a new service or a product, will be profitable .
- In other word s, it's a financial calculation done to determine the number of products or services a comp
should sell to cover its costs. Break-even is defined as a situation where your income and expenses match
thus you are neither making money nor losing money. You have enough income to recover all your costs.
- This method is useful in understanding the relationshlp between the variable cost, fixed cost and revenue . As
this analysis it has been observed that an organization with low fixed costs will have a low break-even po
sale. For an example, a company has a fixed cost of Rs.O (zero) will automatically have brok en even upon the
sale of its product. · ·
Usage of Break-evenAnalysls
(I) Startinga new project : For selecting every new project It is advisable to conduct a break-even analysis. Not
it helps you in deciding, whether the project idea Is viable, but It will force you to be realistic about the
will also guide you on the pricing strategy.
(ii) Laun~lng a_new p~oduct : An existing business planning to launch a new product should do a break
analysis particularly 1f such a product is going to add a significant expenditure.
subtracting the costs from benefits. When completed, a cost benefit analysis gives concrete results that can be
used to develop reasonableconclusions around the feaslblllty and/or advlsabllltyof a decisionor situation.
_ cost benefit analysis In project management Is one more tool In your toolbox. This has been devised to evaluate
the cost versus the beneflts In your project proposal. It beginswith a 11st.
_ The list of project expense Is prepared on one side and the benefits to be received after successfullyexecuting
the project is listed on the other side. Based on this you can calculatethe returns on Investment (ROI), Internal
rate of return (IRR), net present·value (NPV) and the payback period.
_ The difference between the cost and the benefits determineswhether action ls required to be taken or not. In
most cases, if the cost is SO percent of the benefits and the payback period is not more than a year the action is
worth taking.
uses of Cost-BenefitAnalysis
(i) To determine the feasibility of a project : This analysis helps the managementof an organization in determining
whether undertakingthe project will give benefits or not as nobody wants to incur losses In business. When a
huge sum of money is invested in a project or initiative, It should at least break even or recover the cost. The
costs and benefits are identified and discounted to present value to ascertainthe viability.
(ii) To help compare projects : As you have today so many choices for Investment there must be a basis for selecting
the best alternative. Cost-benefit analysis Is quite useful to pick through the available options. This model helps
businesses to rank the projects accordingto their order of merit and choose the one that Is the most profitable.
(iii) EvaluatingOpportunity Cost : Cost-benefit analysis is a useful tool for comparing and selecting the projects and
selecti ng best option particularly when the resources are finite but investment opportunities are many. However,
while choosingthe most viable project, it is also important to know the Opportunity Cost which is the cost of the
·next best alternative foregone. It helps businesses to identify the benefits that could have arisen if the other
option was chosen.
(iv) Sensit.lvityAnalysis : Sensitivity analysis is a useful tool for improving the results of Cost-benefit analysis and is
mainly used when there ls no clarity over the discount rate. In thi s condition, the discount rate and the horizon
value are changedto test the sensitivity of the Cost-BenefitAnalysismodel.
- This is another widely used method for evaluating the returns t hat you can get out of an Investment in a project.
In this technique the cash inflow that is expected at different periods of tim e ·is discounted at a particular rate.
The present values of the cash Inflow are compared to the original Investment. If the difference between them Is
positive then it is accepted or otherwise rejected. This method considers the time value of mon~ and is
consistent with the objective of maximizing profits for the owners. .
- Net PresentValue is calculatedby subtracting the present value of cash outflows from the present value of cash
inflows.The present value defineswhat wlll be the worth of the future sum of money as of today.
- While Investingin certain Investments or projects If It producespositive NPV then you can accept the project as
this will show the additional value to your wealth.
- And in case of negative NPVyou should not accept the project,
Where·
Cash Flows = Cash flows In the time period
r = Discount rate
impact,time_frames, and achievementof specitib"g~ali: ... " -· .. ..... ... .. . . --- ... .. .. .. - -- . -- . .. - . . I •• • -- ---
- - . . .
- Proj~ctpo~olio ~rocessha_s becom.~ ak,ey c.o_m'p~~ent_in_o,rg~_ni~.!tio'h_s, a¥ th~v
lo~k) c( etj_t-~!'C~-~h~l{ a~ilityjct:'
multiplepro1ectsm _an efficrentand .effect,ive\vay;_ Project p'ortfcilio'managerne"nf
it d fi h . . . ,.. . •· .,. ... . . . . . . .. .
process-'is'lffe
.
icf'y (o ·,,, <._'.\• ,~-, -~-.::~
success .
_e nes. ow.an ~rga~ization approaches projec;tP,i'iorit'!zaticl'n,/ ~.s~~rce''al!o1:ation{budget1ng;;sch,e~ulln . :i 'i,,;-;":.;;
ma1orproJectcomponents: · .. .. · ·· & ".~· --
- The goal of ProjectPortfolioProcessis to find the best possible comb· ti f ·
. b' . · ma on o resources to help an ent •
its o Ject,ves, and it takes into account such factors as exter I k erpnse
environment,and government regulations. na mar et conditions, customer demands ; ·comp .
- The·· need for Project Portfolio Process 15· driven' by the 't ct h . , ... , . _ . '(. . - ·•
completed successfully. But often the ·resources , d d t aU proje~s /re~u!re 'fund,ng ~ti_~~f ~ri'd_l't ": -
. , .f nee e are In limited suppl At h " - · · · ·· · ..., ' · "
proJects are o equal value to an organization,As a I· . y. t e same .~im'e/it'ftl~a1i'tlit! '
to ensure th at t he most strategicallyImport t resu t, stakeholder$
.
need a • .., · --··--'
·
way to ·manage p •;;.~~ ·'-"1~;.i"~,,-. "'~'"
an projects will receive t~ ,. ·· · . . roJ~~ ~~!ll:f...,..
- To ensure success with a Project Portfoliop . e attentionand resourcestcf e·'f{~;;f " .,.
rocess, organizations can follow th f . . ,.Jl~,~~ -~...,
1. IdentifyBusinessGoals and Strategy e allowing steps :
_ A common pltf.lll occurs when organizationsldl!ntlfy their buslnes1 str:itl!ttos but lo, ., 1tp,ht of the lndlvfdu:il
projects. To avoid this, organizations should tAkfl tho time to Identify the business drategy 11i well a, evaluate
where projects stand In relatlon to buslnl!SSobjective~.
_ This involves taking an Inventoryof all current projects and resources, lncludlnflevalu.ttlngthtt current proJeruIn
the plpellne for redundancies, stalled projects and other potential aren~ for co1t siivlngs, and Identifying skllll!d
employeesand their current and future avallnbllltyto find out who' s av11llableto wor~ on hl,tl,-,valueprojects.
- Finally, companies need to deploy a Project Portfolio Process solution that can lncre~se cohesion and vlslblllty
·into their processes.
- These tools can help create' a hlstorlcal project archive, which business leaders can draw upon wh~ they make
future Investment decisions. Organizationsshould thoroughly evaluate products before buying them, lndudlng
readingreviews of Project Portfolio Process platforms and schedulingproduct demonstrations. ·
"' Project Portfolio Process platforms can Identify projects that do not warrant Investmentand provide clarity Into
projects at everv level, from objectivesto cost. They can provide strategic Insight and visibility Into the most
important projects that make sense for an organization,prioritize the most valuable work, and hef deliver p
P<0jectInitiatives on time and on budget.
Ensure separation of decision-making responslbllltles between project manager and projects sponsor
Ensure accountability for the realization of project benefits
Ensure oversight of the project management function
Carry out senior stakeholder management
Project promotion : One of the foremo st function s of a project sponsor Is to support and promote the importance of
the project t o relevant stakeholders. This Is necessary to 81Ve the project visibility at higher levels and to provide a
hurnan face to answer questions about why the project needs to happen.
putting forward the business case : Someone who is a project sponsor needs to be a believer In the necessity of the
project t o sincerely make the case for It. They will assist the PM and team leaders In forming the business case so that
it makes a powerful argument for why It should go ahead.
Ensuring funding and resources : The project sponsor also assists In making sure that the project has everyth ing it
needs
Determining project scope : During the Initial exploration and project planning stage, the project sponsor Is often
. called upon to contribute the ir experience of the possibilities and limitat ions for previous projects they have worked
on.
Approval and authorization for project steps : In order to streamline the reporting structures for a project, the
project sponso r will often be handed responsibility for revlewiing and approving project activities , which means that a
PM can get a quicker response than having to address executives or stakeholders.
Overseei ng project health : Although they may not have .dally interactions with the project, project sponsors receive
regular project reports so that they have an understand ing of the overall level of project health . They assist the PM in
following up on budget proposal s and maintaining the fund ing of the project . They also assist with the hiring of human
r esources and implementat ion of new techn ologies.
Informing stakeholders of progress: A very important function of the ~roject sponsor is to receive information about
the project and then transfer this to rele_
vant stakeholders. This is done to ensure continued support for the project
and to make sure all stakeholders are kept in the information loop .
Assessingfinal dellverables : At the final stage of the project th!! person who is a proj ect sponsor should review the
.fin al deliverables to sign off on them before being handed over to the client. This is a final checking process perfonned
by someone who has enough distance from the project to be able to judge it fairly .
Project Charter
Project Charter is a statement that describes the objectives ot'a project . This statement also sets out detailed project
goals, roles and responsibilities , identifies the main stakeholders, and the level of authority of a project manager . It
also acts as a guideline for future projects.
,t defines the roles and re.sponsibllities of the participants and outlines the objectives and goals of the project. The
.charter also identifies the main stakeholders and defines the authority of the project manager.
2. It serves as a primary sales document. When you present this to the stakeholders they now have a
dist.ribute or present when approached about other projects, so they can focus their resources where they're
3. This is a document that stays with you throughout the life cycle of the project . You refer to it through~ut,
meetings or to assist with scope management. The charter acts llke a roadmap.
Writing a project charter Is a process which also requires good experience and
expert 1se. Here are some
may help you In preparing a good project charter. .
Vision
ou have the vision clear, then you can break It down Into more practlcal blU. It must be supported by the
once Y
following :
Objective: List three to five objectivesof the project - specific,measurable, achievable, reallstlc and time bound:
_ scope : Outllne the formal boundaries of the project by describing how the buslnes, may change or alter by
-I
delivery of your project, also note what's relevant to the project and what Is not. This Is how you m1lntaln bftter
control of the project.
oe11verables : Describe each of the dellverables the project Is tasked to produce. Once yotlve got all of them
down, you've got a foothold on your charter and are ready to move on.
Organize
When you're building a structure for your charter there are four subsets you need to Identify. This Is done by listing
the following :
_ customers/End Users : To complete this 11st, ask yourself: Who is a customer and/or end user In the context of
this project? Is there a specific individual or entity responsiblefor acceptingthe deliverablesof the project?
_ stakeholders : As noted earlier, identifying the stakeholders of the project is crucial. They are the person or
entity within or outside of the project with a specifickey Interest in that project. It might be a financial controller
overseeing costs or the CEO, but whoever it Is they'll have a slightly different focus depending on their role.
_ Roles : You n·eed to assign the key roles and responsibilities to those involved in delivering the project, from the
project sponsor, project board and project manager. After each entry write a short summary defining their role
and what their responsibilitiesare In the project.
- Structure : Now you need to defi'ne the lines of reporting between these various roles In the project. Use a
project organization chart to do this. It diagrams the structure of an organization and the relationships and roles
of those involved in the project.
Implementation
You have a vision and have organizedthe various parts of your project. Now you have to develop a plan to implement
them. There are four parts to this :
- Plan : To implement your project as stated you need an Implementation plan. This is a way to develop an
atmosphereof confidencefor your customersand stakeholdersby fisting the phases, activities and timeframes of
the project's life cycle. Gantt charts are the traditional planning tool for projects. They tum your tasks and
deadlinesInto visual timelines.
- Milestones : Milestones mark major phases In the project and collect smaller tasks Into bigger chunks of wort.
The project should only have a few of them, that's why they're milestones, but they are an Important way to
acknowledgethe completion of a key dellverable.
- Dependencies: List all key dependenciesand what their Importance Is to the project. These are tasks or activities
that are linked to one another, as they wlll Impact the project during Its life cycle.
- Resource Plan : What resources are Involved In the project? Break down this fist into labor, equipment and
materials. This is how you will know what you need before you need It, and you wlll be able to estimate your
budget more accurately. As the project progresses, and changes are Introduced, you will need to adapt your
resource plan. ProJectManager.com features workload and resource management tools that let you qulddy see
everyon~'s workload, so you can reassign tasks as necessary. This keeps everyone from being over or under
worked.
• TtdllaNIWei
" ••11c 1 t1t 1t
- Title page : Use the title page to introduce yourself and your project Be sure to II d
· nc u e your name your c:o
name, the date you submitted the proposal, and the name of the sponso • d. Id , .' .
r or m IV ua 1you re subm1ttmg the p
to.
Table of contents: A table of contents will let your sponsor kn ·
ow exact 1y what w\11 be c d. h
If you're sending your proposal electronically Include a
11 k bl overe in t e proiectp
. , c c a e table of content th .
sections of your proposal for easy reading and navigation. s at will iump .to the d
- Executivesummary : The executive summary details exact! h .
th b f 'fi
e est or a spec, 1c problem or situation. Slmlla t
Yw Yyou're sending th
e proposal and why your sol
r o a value propositl l
products or services, and how they can solve the spe lfl on, t outlines the benefits of your p
c t problems
After readl,:igyour executive summary, even. If they don' . .
of how you can help them. t read the full proposal th
' e prospect should have a
There'sa lot to keep in mind when writ ing a project proposal. Here are a few tips to help you out:
Keep it simple : While there's no ideal project propos~I length, focus on quality over quantity . Keep sentences short
and simple, and avoid the use of businessjargon.
- , Stay on brand : Don't be afraid to let your comp~ny'~personality to shine through in your proposal. Stay true to your
brand and show the sponsor what sets you apart from your competitors.
- Include data and visuals : Don't forget to include compelling, quantitative data. When applicable, use visuals such as
· chartsand graphsto enhance the proposal.
- Quality control : Before you send the proposal out, make sure to read and re~read it for any typos or grammatlcal ·
A Project Team is an organized group of people who are Involved In performing shared/individual tasks of the project
as well as achievingshared/individual goals and objectives for the purpose of accomplishingthe project and producing
its results.
- The team consists of the full-time and part-time human resources supposed to collaboratively work on producing the
deliverables and moving the project towards successfulcompletion.
, Successful projects are ~sually the result of careful plannlng and the talent and collaboration of a project's team
members. Projectscan't move forward without each of Its key team members.
The project team is a group of people who have a role In the project. Team members· can be grouped but each
individual has a certain role and function and thus can be assignedcertain tasks. ·
The project team fulfills these roles and functions within the time frame of the project and Is usually dismantled after
the project completion. During that time, the project team works towards the common goal of delivering ~he project's
scope within time and budget/cost.s.Each team member has certain responslbllltles based on thelr •role, functions and
assigned t~sks. , ... ·
WT1eH111111eqi
P"ill t. tU Onl
- Project teams are multl-dlsclpllnary . Team members are bought together from different departments and may
experts from external companies or suppliers.For an effective team, project team organization structure Is '1tal
the Project Manager must have sufficient seniority and author ity to lead the project tea~ .
- For the duration of the project the team should report to the project manager and the organization structure of
project team should reflect the ownership of the project mana~er.
- An example project organization structure Is shown Fig. 2.9.1. The Project Manager heads th e team wlt_h a dlr
reporting line to senior management.
'" Customer
Customer~
" Project :
' Manager
'Construction
..;: manager '
t ~:
,ConstrtJCOO!l :.
: _ site ;
- Successful implementation of this task requires the manager to acquire, develop and lead a group of peopla who
supposedto do the project. A group of_peop~e turns into a team when every person of the group is capable of m
the following conditions :
o Understandingthe work to be done within the endeavor
o Planningfor completing the assignedactivities
Every team, regardlessof the project type, size and nature has three I d fl
' ro es e ned as conventional. These roles are:
1. Leader : A project team leader ls a person who provides leadershl d Id ·
P an gu ance to the t d k 'b
for the results of teamwork. The team leader role Involvesthe d eam an ta es respons1
eveIopment and en .
training, leading, motivation, recognition, rewarding and oth couragement of the team thro
er actIvltles that stl I .
the required tasks. · mu ate or force team members to
Member : A project team member Is a person who Is InvolvedIn doln1 assigned taiks. Team membersdirectly access
2
' roJect and activelyevolve Its processes. They're subordinatedto the team leader.
the P
S. contributor : A project team contributor Is a person or an organization that partldpa1esIn teamworic but Is not
actually Involved In performing tasks and carryln1 out prcSJect team responslbllltles. Contributors help Improve the
project through giving valued suggestions, expert Judgmentand consultation. They have an Interest In the protect, so
they facilitate Its successfulcompletion.
A team can be responsiblefor a variety of duties and responslbllltles, depending on the project they're Involved In.
Here're several common responsibilities and duties of a project team :
_ Gainingthe right understandingof the amount and scope of assignedwork
Roles, responsibilities,approachesand practices significantly depend on the partiaJlar project. its goals, envtronment,
and requirements. While this is true, there are several typical roles that wori< for literally any project t~am.
Sponso ·r
Sponsor is the most senior member of a project team who has crucial responsibilities and ls aa:ountable for the
project performance. He is the key person In communication of the team with the company's management and key
stakeholders. This is also the person who provides necessary resources for project performance and approves «
rejectsthe outc~me.
Key responsibilities of a sponsorare :
· Defining project's goals and expectedoutcome;
- Providing necessary resources;
- Managingcommunication between project team and key stakeholders;
- Translatingcompany'sstrategy and vision to the team;
- Approvingor rejecting the outcome.
- Some project teams have a project steering committee that consists of the sponsor and key stakeholders. tt
representsthe Interests of parties Involved In project lmplementatlon, provides leadership In the work process,
and resolves issues escalatedby project manaaersand team leads. ·
Project Manager
Project manager Is the team member who deflnes the framework and course of the project, sets dinlltes and
......,.
milestones, defines required resources, and manages project activities. The responslbllltles of a projea 'man1geran
include a wide range of activities that depend on specificproject. In seneral, the key activities are :
,
•• U1t a t1, a1
A ·team member is the heart of any project. By partk:ipating in project activities and performing their
assignmen~,regular team me~bers contributeto the ~xpected outcome of the project. Alongside with that,
projectresponsibilitiesinclude :
An effectiveprojectteam is one which possessesboth professionaland soft skills. They ensure better communl
ateamwork, and outcomeof the projectwork. followingare the key parametersto pay attention to when hiring and bu
projectteam.
PJ Skills and e,perlence: This is a very Importantcriterionfor most poslti6ns.Relevantprevious e,perience and
skills are criticalfor a smoothstart of a projectwork.
(II) Wllllnrnessto learn new skills:Some hiring e<pert advice that It might be useful to look beyond the skills need
the role. Employeesneed to be wllling to get out of their comfortzone to help the team a d I h'i
(1111 Per,onal traits : Personal traits are often a reason why a team of professionalstu · b somet ng· new.
n earn ·
are nearly as important as professional skills, e><perlence and expertise u . rns out to e dysfunctional.
.
• nw,111 ngness to help' arrogance
other types of toxic behaviourimpair teamwork. So It's better to Prevent thl . ·
team. s on the first step of building a P,
(Iv) Cultural'flt: It's a matter of fact that professionalculturesare very diff · ·
other factors. Making sure all your employeesflt In your off! erent aod depend on Industry, region a,nd
• • ce cu1ture not only • l'fl
but also preventswork environmentIssues In the future. · simp es their on-boar~lng pr
I
Establishthe Team
_ The first step is to establish the project management team. The best project teams include stakeholdersat all
levels, from executives to those Individuals at the front line. These Individuals have the Inside knowledgethat will
be critical to the success of the project.
_ The most important element about team composition Is having a team that Is effective working together.
collaboration and communication skills are two of the most critical personal skills demanded of all members
Encourage Collaboration
. .
- Groupsthat plan togetherare typically more successful,therefore project leaders must reanze the importanceof
collaborative planning and goal setting. This collaborativegoal setting allowsteam membersto achieveindividual
succes.ses, while contributing to the overall project goals. Collaboration is the vehiclewhich:
o Generates the most creative solutions
o Gets the greatestmembership support
o Produces the greatest amount of personal growth
- By matchingeach team member's incentive to the overall goals, the entire team Is motivated further to achieve
success. It is also the project manager's responsibilityto manage the team's developmentto ensure a cohesive
integratedteam is founded.
- Bringing a group of people together does not necessarily constitute a team, especiallynot an effective working
team. One of the biggest mistakes made by project managersis not recognizing this as a fact and then expecting
their project team to do well from day ~me. ·....,
- Project leaders facilitate relationships among people of very different backgrounds. However, they all share the
common goal of the project. Conflict within projectscan manifestitself in many different ways but a good project
managerwill interceptand take action when confWctoccurs.
- A recognitionand reward scheme will help reinforcethe Importanceof the key project deliverablesand focus the
team on the Important aspects of the project. Completionof a project and the steps along the way can be very
rewardingfor team members.
1. Be a decisiveleader
,.... h-
If you are the project leader you be a decisiveleader. Make declslons on the basis of the informatJon"""'
nd
....,: at .._ u•
time and make sure to involveyour team. Team members, being a part of th at process a seefngyouas a leaderwt'I
is focused on the success of the project, will be motivated to focus on the ir work, identify and point out pos.si
issues,suggestimprovements,and perform better.
Being a project leader, you should get productivityfrom everyone. Assign tough tasks to all project team me
·and expect weekly accountabilityfrom each team member for their respective tasks. One of the best practices
monitoringteam membersinput Into the projectIs to use_some project management software.
- Teamwork and communication are the keys to productivity of the team. That's why just finding
professionalsfor your team Is not enough: it's not uncommonthat the best ones come with big egos. _..,.__
and unwillingnessto communicateare extremelydetrimental for productivityof an otherwise great team_
for overall results too. It's not always easy to Identifythat during hiring processes or tearn selection p,roc:essie11
be carefulto ask tough questions and not Just take the best talent with blinders on.
- The project managementteam needs to clearly understand the requirements and deliverables of the.
well as being aware of the organlzatlonal overall strategy objectives ·and d · •
. ' nvers. It 1s also essential for
proJect managementteam to understand the organization's professionala d th" •
n e •ca1requirements and su
to them and ensure that the projectcomplieswith them.
iQ)
Adjourning
'ij
Forming
w
;
Storming
Time
Fig. 2.10.1 : Stages ofTeam Progress
Fonning Stage
The forming stage involves a period of orientation and acquaintance. There Is a high level of uncertainty during thls
stage, and people look for leadershipand authority. A member who asserts authority or Is knowledgeablemay be
looked to take control. In this stage team members ask for their role and benefits. Most Interactions are social as
members get to know each other.
Stonning Stage
_ The storming stage Is the most difficultand criticalstage to pass through. It Is a period marked by conflictand
competitionas Individual personalitiesemerge; Team performance may actuallydecrease in this stage because
energy Is put into unproductiveactivities.
- Members may disagree on tea·m goals, and subgroupsand cliques may form around strong personalitiesor areas
of agreement. To get through this stage, members must work to overcome obstacles, to accept individual
differences, and ~o work through conflictingideas on team tasks and goals.
- Teamscan get bogged down in this stage. Failureto address conflictsmay result in long-termproblems.
- By getting through the storming stage, conflict is resolved and some degree of unity emerges. In the norming
stage, consensus develops around who the leader or leaders are, and individual member's roles. Interpersonal
differences begin to resolve and a sense of cohesionand unity emerges.
- Team performanceincreases during this stage as members learn to cooperate and begin to focus on team goals.
However, the harmony is precarious, and if disagreements re-emerge the team can slide back into ~orming.
Performing Stage
In this stage, consensus and cooperation are well-established and the team ls mature, organized,and well-functioning.
There is a clear and stable structure, and members are committed to the team's mission. Problems and conflictsstill
emerge, but they are dealt with constructively. The team is focused on problem solving and meeting team goals.
Adjourning Stage
- In the adjourningstage, most of the team's goals have been accomplished. The emphasis Is on wrapping up final
tasks and documenting the effort and results. As the work load Is diminished, Individual members may be
reassigned to other teams, and the team disbands.
- There may be regret as the team ends, so a ceremonlal'acknowledgementof the work and success of the team
can be helpful. If the team ls a standing committee with ongoing responslblllty, members may be replaced by
new people and the team can go back to a forming or stormingstage and repeat the developmentprocess.
1. Open Communication
- Consider this scenario: A young manager-to-be accompanied his mentor , an experienced manager, to observe
high-perform ing t eam in operation at a manufacturing company. When he first walked Into the room, he said
his mentor, "Oh boy, t his Is a dysfunctional team ! Listen to the way they're arguing with each other ." The
man replied, "Pay attention , you're witne ssing a great team ." ·
- It took the younger man several minutes to understand what the manager meant. This team was in conflict.
members were strongly disagreeing with one another on the best way to Improve their _product. It is ~ften a
sign when this kind of friction ~xists. A team that cares passionately about Its task is very positive. It has
honest communication. That Is a team dynamic!
2. Empowerment
- You get a strong team dynamic when you empower your team members by giving them the right to
decisions concerning the work they are doing. Of course, you set boundaries of tinie, money, choices,
fu~ . '
- But once you give the team the final power of decision making, you will noti ce a confidence and a J
strength.
- Whatever you do, make sure you do not empower .teams that are not ready for it. That can be disastro~
many new managers make thi s big mistake. They probably do It because.they want to get into the good
the team. Make sure the team is ready for empowerment or you and the organization will suffer from
consequencesof its poor decisions.
- Can yo~ -~alk up to any one of your team members and have this person clearly define his role
respons1b1lrtle s on the team? Can you walk up to any one of your team m ·b d h . ·
em ers an ave this person
define the roles and responsibilitie s of every other team member lncludl h ··
, ng you as t e leader?
When team members can do this, they know what Is expected of the d h • •
b m an w at 1s expected of every other
mem er. They also know on whom they can count for helpln th · h • ·
effective team dynamic. g em wt 1 th e1r work . All of this lead$
4. Goal Clarity
5. Effective Leadership
When you are able to check off all the neces.sary items, you are doing your part in buildingan effective team dynamic.
·As leader, you should do the following:
_ set dear goals for each team member and the team. Give clear directions for those who need it
_ Share examples and experiences.of your personal successes and mistakes in order to relate to the team.
Emphasizethe positive rather than the negative in your talks with your team
- Give continualfeedback to each team member and to the team-b oth positive and constructive and express your
and the organization'sappreciation thr~ugh rewards, if available
Use small successes to build team cohesiveness. Develop a constructive relationship.
- Make change happen for the better by encouraging creativi_ty and innovation. Encourageself-reliance and self-
development
- Encourageteam members to express their views during conflict and share yours with them
- Help your team see Its connection to the larger organization, customers, and the community
I Review Qua•ttom• :J
Q. 1
State the importance of Project Initiation phase. (Refer Section 2.2)
Q, 2
Describe Project Initiation Process. (Refer Section 2.2.2)
Q. 3 Describe some of the techniques used for strategicselectionof project. (Refer Section 2.3.1)
Q. 4 Describe any four non-numericalProjectSelectionModels. (Refer Section 2.4.1)
Q. 6 Write notes on (i) Payback period (ii) Break even analysis. (Refer Section 2.4.2)
Q.6 What is cost benefit analysis?What is its usage? (Refer Section 2.4.2)
Q. 7 Describe Project Portfolio Process. (Refer Section 2.5)
Q. 8 What is a project sponsor?Describeits functions. (ReferSections 2.6 and 2.6.2)
Q.9 What is Project Charter? Describeits benefits and use. (ReferSections2.7, 2.7.2 and 2.7.4)
Q.10 What is Project Proposal?How do we write a Project Proposal?(Refer Sections 2.8 and 2.8.1(a))
Q. 11 What is a project team? State its key members and their roles. (Refer Sections 2.9 and 2.9.3)
Q.12 Describe the role and responsibilities of a project team. (ReferSections2.9, 2.9.1 and 2.9.2)
1
Q.13 Describe the technique of building an effectiveprojectteam. (Refer Section 2.9.5)
Q.14 Desaibe the stages of Project team development.(Refer Section 2.10)
Q.15 Describe ttie importance of team dynamics. What are its importantdimensions?(Refer Sections 2.11 and 2.~1
Project Planning
Project planning is the most important part of the project life cycle. It tells what is to be achieved and how. The
planning phase is when the project plans are documented,the project objectives and requirements are defined, and
the project scheduleis created.
It involves creatinga set of plans to help guide you through the implementation and closure phases of the project. The
plans created during this phase helps manage time, cost, quality,. changes, risk, and related issues. They also help
axrtrol staff and externalsuppliersto ensure that the project Is deliveredon time, within budget,and within schedule.
The project planning phase is often the most challengingphase of project managementas you need to plan the staff,
resources, and equipment needed to complete your project. You may also need to plan your communications and
procurementactivities.
Scope planning: It specifiesthe scope requirementsfor the project to help in creatingthe work breakdownstructure
Preparation of the work breakdownstructure : Here, the entire project is divided into tasks and sub-tasksfor better
handling and execution.
Project schedule development: Here, the entire schedule of the activities of the project Is prepared detailing their
sequence of implementation.
-.SOurce planning: This process Identifiesand then plans the effective utilization of the all the resources required
Wiring the project implementation.
llidget planning: it specifies the budgetedcost to be Incurred at the completlonof the project
ocurementplanning : It plans to Identify the right vendors outside the company for procurementof materials and
Scope, schedule and cost : Project Planning needs to outline the scope and size of th e project, the scheduling of:
tasks and activities, which means planning them out along a tlmeline. The plan also needs to iociude how the costs
going to be spread out and covered.
Quality, human resources, communications and risk : The quality of the outcomes needs to be established In the
so that they can be measured throughout the project progress. Team members need to be allocate«:ftasks before t
project begins so that they are aware of what is expected of them. The way in which communications Wil_l be held a
' . needs to be outlined along with the potential risks and bottlenecks of the project.
Requirements plan : In the project plan format, a project may have several requ irements such as.Imr::1et"....._
location, space etc. It Is important to plan and organise for the availability of these requirements before the
begins
- Change management plan : Any proyect can face changes and uncerta inty. Planning for these changes and ae ·
way in which they will be dealt with reduces their negative impact on the project . So it is important to manage
correctly and establish a plan for its management.
Process Improvement plan : Improvement and learning is essential in p~oject management . It is important to stri~
quality results. Lessons can be learned from previous projects and applied to future ones, heightening the potential
increased success.
Project scheduling is a mechanism to communicate what tasks are to be done and which organizational resources
be allocated to complete those tasks. Th us project scheduling fs a document collecting all the work needed to be
to deliver the project on time.
. .
- A project is made up of many tasks, and eac~ task has a start and end time to ensure timely finish . People in the
had printed calendars on a shared wall in the water-cooler room, or shared spreadsheets via email, today most
use online project scheduling to ols.
Typi cally, project scheduling Is Just one feature within a larger project management software solution, and
many different places In the.software where scheduling takes place.
Before going deeper into project scheduling, let's review the fundamentals to proJ·ect h d . · . ·
· sc e u1mg. ProJect
occurs during the planning phase of the proj ect. You have to ask yourself three questions to start :
What needs to be done?
When will it be done?
Who will do It?
Once yo~ have got answers to these questions you can begin to plan d · t ti k . . . ,. · · •
_and resources. The followln~ are the steps needed to schedule a project : a es, n activ,t,es, set the duration, mil
Defining Activities
Identify and define the activ ities that you have to do In the project. By using a Work Breakdown Structure (WBS) and a
deliverablesdiagram, you can begin to take these activities and organize them by mapping out the tasks necessary to
cornplete them in an order than makes sense.
Preparing Estimates
After you have the activiti es defined and broken down Into tasks, the next step is to determine the t ime and effort It
will take to complete them. This Is an essential p'.ece of the equat ion In order to calculate the correct schedule.
Determining Dependencies
Tasks are not an island, and often one cannot be started until the other is completed. That's called a task dependency,
and your schedule is going to have to refle ct the se linked tasks. One way to do this is by putting a bit of slack _in your
schedule to accommodate these related tasks. ·
Assigning Resources
The last step to finalizing your planned schedule is to decide what resources are going to be required to get those
tasks done on time. For example assembling a team and scheduling the ir time just like the tasks .
2 Scheduling Techniques
Tl)e first two techn iques used by project managers are Critical Pat h Method (CPM) and Program Evaluation and
r!W Technique (PERTI. You can use these methods to calculate the assumed start and fin ish dates, based on the known
pe of the project.
• Critical Path Method (CPM)
- The Critical Path Met hod helps you uncover the longest possible t imeline for the project, as well as the short~
one. With the CPM you will also be able to mark critical tasks and the ones that may float. Changes in the latter's
delivery won't affect the schedule.
- To use th e CPM, you need to know your proje ct's scope and list all of the tasks necessary for its completion . Next,
estimate how long each task may take. After that, you shou ld also note all dependencies between the tasks. This
way you know whi ch ones can be done separately, and which ones require previous tasks to be comp leted .
Lastly, add milestone s and deliverables to your project.
A critical path help s to visualize the project flow and calculate its duration when all dependencies and
deliverables are known . This technique may notbe so handy lfthere are many uncertainties in the project .
- Similar to a critical path , PERT is a way to visualize tasks' flow iri the project and estimate the timeline based on
their assumed duration. This techn ique also illustrates dependen cies between tasks.
To schedule a project using PERT, just like in CPM you will need to define tasks and the ir order first, based on
your proj ect's mile.stones. Oslng a network framework slmllar to CPM, consisting of these tasks, you can estimate
different time lines for a project depending on t he level of confidence :
• MS--..
, 11 11 1r 1 t U•1
-
• •
The WBS 1s a method for getting a comp1ex, mu
ltl -step project done In an easy and effective way by divldins it,
nd more efficiently. -
smaller units so that you can get things done f ast er a
l tree structure that outlines your project and breaks it down·
- Work breakdown structure (or WBS) Is a hierarchica b
d
smaller and more manageable units. Today, software Is also available which you can use to ull a WBS by er
folders and subfolders, and can even go further to divide Individual tasks Into subtasks.
- The goal of a WBS is to make a large project more manageable by breaking it down into smaller chunks ~o
separate but interconnected units can be done simultaneous¼yby different team members leading to better
productivity and easier project management overall.
Following are a few reasonsfor creating a WBS in a project :
o It aeates an accurate and readable project organization.
o It creates accurate assignment of responsibilities to the project team.
A well-designed WBS facilitates planned outcomes instead of planned actions. Outcomes are the desired ends of
project, such 'as a product, result, or service, and should be predicted accurately. Actions, on the other hand,
diffi cult to predict accurately. A well-designed WBS makes it easy to assign elements of the WBS to any project a
good WBS should exhibit the following characteristics :
1. Definable : It is easily described and well understood by project participants.
2. Manageable : It is a meaningful project planning method wllere specific responsibility and authority are as~g
responsible individuals.
3. Estimated : Using WBS, duration of the whole project and separate units can be estimated in terms of the
required to complete, and the cost likely to be Incurred in resources required to complete the project .
4. Independent : It allows minimum Interface with or dependence on other ongoln I (' . · ·
g e ements t.e., assignable to a
control account, and clearly dlstingulshable from other work packages).
s. Integration : It facilitates integration with other project work eleme t d
I
h -
schedules t o Include the entire project. n s an w t higher level cost estima.
6. Measurable : WBS can be used to measure progress· has start d
milestones. ' an completion dates and
Advantages of WBS
3.2
Now that you have the complete work breakdown structure, It's time to review why you should use this approach to
management. Using a work breakdown structure delivers numerous beneflt 5 Including :
improved planning : Large, complex projects can be difficul t to wrap to execute let alone plan from start to finish.
Using work breakdown structure helps Improve planning by making It easy to visualize the sc.ope of the project and
break lt down Into more manageable milestones. As a result, work breakdown structure allows you to set clear
tlmelines earlier on. It makes sure no work gets dupli cated or overlooked and It understands the level of output at any
i,oint In the project timeline .
smarter budget and resource allocatlon : By Improving project planning, work breakdown structure allows for smarter
budget and resource allocatio n. Speclflcally, It ensures that all _budget and time requirement s get accounted for at the
very beginning of a project. Addltlonally, the mutually exclusive rule guarantees that no duplicate work wlll take place,
which eliminates wasted budget and tim e.
Simplifi ed risk Identification : The visual nature of work breakdown structure makes it easier to identify areas of risk
50 that you can get ahead of problems and remedy them faster .
Improved accountability: The clear work assignments, timellnes, and budgets identified by work breakdown structure
Improve accountability among team members . That' s because eve&')'oneInvolved should have a dear understand ing of
what they are responsible for and the time they have to complete that work .
Enhanced vlslbillty : Finally, work breakdown structure provides a high level of visibility into · f!Very project. Thi s
visibility makes it easy to communicate expectations to stakeholders and team members and track progress
throughout the project.
A work breakdown stru_cture is a helpfu l method for managing the challenges that accompany large:-scale enterprise
There are several ways you can create a work breakdown structure. The low est tech options are a whiteboard or a
waD with sticky notes, but that clearly won't work for a geographically dispersed team . Go digital with project management
are that drives agility across teams, whethe r in the same room or distributed across the globe .
As you get started with work breakdown structu re, there are several rules to keep in mind, many of which are covered
the work breakdown structure definition . These rules Include :
• 100% Rule
- Both the work and budget allotment for all deliverables must always add up to 100% and they must do so In a
hierarchical manner. For example, at all _level two deliverables must add up to 100% of work and budget for the
entire project as outlined at level one of the hierarchy.
- Below that, at all level three deliverables must add up to 100% of their parent deliverable . So, If the parent
deliverable Is 40% of wo~k for the project and Rs. 60,000, the sum of all its sub-deliverables must equal 40% of
work and Rs. 60,000.
Mutually Exclusive
Every deliverable and sub-deliverable must be mutua lly exclusive, which means that no milestone can appear with in
the work breakdown structure twice . This mutual exclusivity helps ellmlnate duplicate work , excessive costs, and
communication issues since It means that only one team or person Is responslble for each deliverable.
3. Focus on Outcomes
. d ut in the work breakdown structure defines an
O
Once again, it's important that every deliverable mappe . • o
not an action. This rule makes it easier to manage project scope and gives team members working on the
Initiation
Library Management
System
ProjectPhases
~ ------------------ ------------------------------- ----------------------------------- -------------:
: Planning Executionand Control · Closeout :
~-_,__~.~---
-~----~---
----~----~
-- ----~----~-- •--.-..- .-..-.-•.•.-. -..-..-.-.-..-.•
..-.-
..-.8
..M
. ~..•. ..~P_-__~_w__~-~----~•.-.-.•-.-••- .- ..•.J
.••.8_.~.~
••~.-
.~upportAndroid _Integration
·.improve
. .. .
,Site Performance.:·,..
-· .
' DAT-3300Insurance
' rabies
- --- ------ - - --- ------ - ------ -- - ------- --- ---- - .. --· --·--- .. -- .. ----- - ----- - - -------------,
t. ~-- ----- - ----- -----..
•j r-------lt,.._---- ,-_____ .,,_______ ,------...&..------- I
l
l
'
.UnifiedCAM -
•
"'P'----------~·
----------------------------------....
-- ---------------------------------
Perform·cRM System
Back:OfficeSuite ' . '
+
----------...1, ••
User Manual
-----------------------------------·'
• '
3. Responslblllty-basedstructure
r anlzatlon units that will work on the project.
It defi nes and structures project activities based on~t:_::h:e.:.o~g
:------i
Online Shop
Teams
:(.______-_-_--_--_-_-_--_--..,_-_-_- _-_--_-_-·_·.·,·_··::·.:.:·:.:··.·:.·:.:: ·.·:.·:.:.:.:=~----
: - - - - - - - - - - - - - esting Te~~ - - -- ---i
-_-_-71
i Profect Manag~mentTeom 1_......,,..c...o_re_P.,.r.;.oj_ec_t..,.T-:e":"
~ am
:'::":':':~ - l..-_-__ - _-_-__-_...
__-_-__
- _.,.,.
__,.._,..
_...
__..._...
__~_..
___:
\- ~ ---------·---------------------- ------- --------- Test Shopping Sile
DevelopProject Plan Design Team
Test Admin Panel
Report Status Design New Web UI
Develop Testing Report
Report Risks DesignAdmln UI
.Library Managemen,System
Projectorx 2
0
Sitemap
o Wireframes
0
page designs
0
Front-end code
0 Back-end code
Be sure to include all tasks and that you are not leavlng anything out. For Instance, if you are working on a website
redesign project, have you accounted for content? If you miss a deliverable now, you will regret it later.
That's why listing things out as a team is so helpful. A team conversation not only ensures all your bases are covered. It
also helps you set expectations for who will be responsible for deliverables and tasks, all while engaging the team on
the overall process of the project.
Therefore, as you dig into each high-level deliverable, ask your team :
Annotate sections
0 Oeliverv2
th
0 conductmeetingwi clients der to get to a finalizedsitem
. be done In or
0 Finalize s,temap k that will need to h ur team to discussth
t for all of the wor ·t down wit yo · · •
- This list of tasks Is an estlma e d h t's 1·ust fine. When you SI d ne Listing out every single
This might not be the way you'd do ·t, , an t a derstandlng of how th'ings are . o ·
Ith a common un
Just be sure you are operatingw I te the deliverable.
help you spell out the effort it will take to comp e
a to do that is to exarriJ
Step 3 : PrepareMinuteDetails detailedas possible.The only w y . . the work that
You should make your work breakdown structure , asII about elaboratinge ff ort and determining . ,
.
task you have identifiedand list out subtasks.It s a
to be done to successfullycompletethe deliverable. d this you will find less room for
'f ake an investmentto o , . . ch
It's a processthat takes time and thought, but ' you m k the next step and detail out what will go into ea ..
. the long term So, ta e ct
expectationsand budgetoveragesin · , k d wn the "Test the current stru ure
h , how you might brea o
Using the website redesign as an example, ere 5 .
site users" deliverableeven further:
o Recruit users
o Schedulesessions
o Write test script
o Conduct5 sessions
Compensateusersfor time
o . .
_ Write up fi~dlngsand recommendations.This one task is proofthat any•single line item in a scope can be an exp~ns
one! Not only did this example includesubtasksit also included a line ite~ that requires payment to a party outsid~
the project.
You are going to ~ant to know about any expensesbeforescoping your project, and your clients will too. Be ~u
accountfor them early on so nothingcomes as a surprise·when you are knee-deep In your project.
Step 4 : Formatand Estimate
- Traditionally,you will find work breakdownstructures presented in flowchartsthat resemble ·website sitemaps-.
format works well becauseit show's a hierarchyof tasks and is easily numbered and referred back to.
- But, some people like to list them out on whiteboardsor put them in spreadsheets. The format isn't what matters
it's the completenessand accuracyof the tasks Included.You can create your work breakdown structure in any
that makes you comfortable.
- When you have listed all of your tasks and subtasks in a format that makes se s · 'II . ·
make sure you have Includedall of the possibletasks and subtasks. . n e, you w1 want to review it a
- Once that's confirmed, go through the list and discuss each task · t f .-
O
hours, days, weeks. It really depends on how granularyo d in erms level of effort ..This could be In mf
u nee to get and how y . .
Assigningan incrementof time to each task will help y dd our organization estimates.
ou a up a total estim t f • ·
you up to createa projectplan when you are ready fo .th . a e o time (and possible cost) a
r at step in your project . .
When you are done, you will know if you are in ·
• 1
art,cu ated too much time or effort to d scope, out of scope· you might run this · ·. • i·
o everythingwithin th exerc 1se and find
the baselinefor what's needed and as a e Scop~ of the project Th ,
. ' group, you can scale back on t k · e good thing.is,you
as s to fit the .
. · scope or the timellne.
- As a contribution to Building Practice Guidelines, these Linear ResponsibilityChart templates list the typical tasks
involved in a building project accordingto its phase or stage. Each entry recommendswho should take the lead and
who else should be providing significant support for each task. The tasks should be modified or augmented to suit the
particularconstructionproiect and the needs of its participants.
In a_well developed team, all will participate to some degree. Nevertheless,on a project it ls essential for the project
managerto identify who will be accountablefor initiating, conductin·g and concludingeach and every task.
Preparation of LRC
- LRC is prepared to find out responsibility centre of all key activities In the project and for that purpose, LRC is divided
into rows and columns and numbers. The rows of LRC Indicate activities, responslblllty and authorities. Th~ columns
identify the position of the project participants and numbers Indicate the degree of authority and responslbillty existed
between rows and columns of LRC, the n~mberscan.be symbol. .
'- The Linear Responsibilitychart Is divided Into :
o Rows : They indicate activities, responslbllltles,authority.
o Columns: They Identify position of project participants.
o Numbers : They indicate th~ degree of authority-responsibility existing between the rows. and columns. They can
be symbols. ·
' ,. ,. ,.,, ·- .
,, General.M•n•i~er Ma~ager~f-ProJ - p i' . rt . • " •
,: Acttvlty/R11ponitblllty . 3
3
Establish Objectives & Policies 1
3 3
1
Integration of Projects 2
1 3
4
2
Project D&rectlon
1 3
4 2
Project Planning
5 1
2 4
Functional planning
1 3
4 6
Project Budget
1 3
4 2
Project Control
Symbols
1 = Actual Responsibility
2 = General Responsibili ty
3 = Most be consulted
4 = May be consulted
5 = Must be notified
6 = Must Approve
- It describes the role of project participants in project matters. Authority, responsibility and accountability for
. '
activities are delineated among various project participa nts. Problem-solving becomes easier .
- Communication is facilitated. It cuts red tape. It is a us_efu l tool for superv ising of authority and responsibilities.
is delegation of aut hority .
- ft postures coordinatio~ because it clarifies ru!es and responsibility, authority and r espon sibility relationsh
project activities among the partic ipants.
- ft reduces confusion and conflict between project manager and functional ma nager s which
responsibility of project part icipants.
- ft combines organizatio nal structure with work breakdown structure which makes easy t fi lb 'I'
. .
part1c1pants. . .
o ,x. re spon s .
1 1ty to
- It does not describe the people Intera ctio ns In the project. It Is a mechanical aid.
All relationships may be difficult to dellneate .
An interface is definedas a point of connect between entitie.sworkingon a common project. This point can be :
o Physical: Physical interactionbetween components
o Functional: FunctionalRequirementsbetween systems
o Contractual: Interactionsbetween subcontractors/suppliers
o Organii.ational: Informationexchangedbetween disdplin~s
o Knowfedge:Generalinformationexchangedbetween parties
o Resource: Pointsof dependenciesbetween equipment, material;and labour suppliers
Internal Interface : An internal interface Is one where the complete responsibilitylies within contractor's scope of
worit.
External Interfaces: These are part of the Soope of Work under the responsibilityof contractor which may influence,
or be influenredby, the scopeof wortccovered by any other contractrelated to the project. ·
1 Objectives
Identify the appropriate personnel who wi!I be responsibl~ for each Interface request and for resolution of
nterfacerequest.
Provide a system which will facilitate the ldentiflcatfonof Interfaces, and address the specific in_terface request
Establisha procedure that promotes efficientmanagementof Interface issues from Initiationto close out.·
Definemethods for communicationand coordinationof Interfacerequests betweenvarious parties.
Facilitatedear and frequent communicationsamon~t parties.
Facilitatethe agreement of ii' schedule for Interfacerequest resolutionand.close-out;
Definea means for the control,~itln& and reporttna of pr01res.son the transfer of Interface requests.
Define processes assurancethat Interfacerequests are effectivelyIdentifiedand man~ged.
.. ProjectMa
Providecollaborativeinterfaceresolutionsupport
- Serve as PMT liaison betweencontractorand operatingpiant point of conta~
- Inform InterfaceManagerof potentialImpactsdue to unsatfsfact . I ••
ory reso ut1on response.
3.6 Concurrent Englneerfng
- As time has become a compe+:..:
. uuve weapon time
The pressurehas made , pressures have becom
businessperformance. project_managersunderstand that time compress: ce_ntral ~o the project-basedo
·- on is a driver of r . .
As a consequence,methods t h P OJect and its
, ec nlques and or: .
way that time compressionneeds be ha;dled In :anlzatJonalapproaches have bee . . '
------------~====n~tlv.
- All these approaches have proper manner. n designed and developed
d I one common · •
eve opmenttasks that can be Pnnclple Is that· th
performedconcurre . . try to ma)(im• . ev
This has given the co IZe the number of maj~r
ncept of con · .:
current eng1neering.
Activityflow chart methodssuch as I0EF3 allow for detailed planning and monitoring of the different parallel
-
0
v«Japping activities Involved In project execution. Failure Mode and Effects Analysis (FMEA) allows fi
systematicInvestigationof the occurrenceand Impact of poss ible flaws In the new product design.
_ The use of Design of Experiments (DOE) enables the systematic ldentlflc.atlon of aftJcal product/pr
parametersthat Influenceperformance. .
- These are just a few of the many supportive methods that can be used In a concurrent englneertng environ
- Enhanced Productfvtty : Quick discovery of design problems helps In correcting the potential problems early than
laterstage in the development process.
- Oem!ased Design and Development Tlme : It makes products which match the ir customer's needs In less ti~e a·
a reduced cost ·
Unbiased
- At times not sa>ping th e project thoroughly enough, not.understanding technical d'lfficulties a nd making changes
are the most common reasons why projects do not adhere to cost estimates and budgets. Cost estimates can
never be too detailed .
An effective and simple way to estimate costs and prepare a project budget is to use project management ~-
Most software has features that identify the types, quantities, and phasing of different twes of labour. It also has
capabilities for ~mating the costs for individual project pieces and adding them togethe .r to reach a project total
The pieces can differ . In size and number from a few large phases of a project with known costs to hundreds or
thousands of small tasks . 'I
A cost estimate is the . sum of all th~ costs involved In successfully finishing a project from initiation to completion.
project costs can categorized In a number of ways but the simplest classification divides costs into two main
• Direct costs
They are broadly dassifled as the costs that are dlrectly associated with a single area such as a department or a
project . In project management, direct costs are expenses billed exduslvely to a specific project. They can indude
project t~am wages, the costs of resources to produce physical products, fuel for equipment. and money spent to
address any,project-spedffc risks. ·
They are not associated wtth a spedflc cost and are Instead Incurred by a nuniber ~f projects sfmultaneousl
IOmetlmes in varying amounts. In project management, quality control security costs d .•. y
. • . . , an uti 1ities are ~ally
dassin
oct Ma
na
ed a~ lndl
80lon1 Ml/ 3· 1B
Project Planning &
Here, experts Who have experienc e in similar projects are approached for he(p. They use your own historical
you have access to relevant historical data, tty analogous estimating, which can show precedents that help
what your future costs will be in the early stages of the project.
2. Statistfcal Modeling
Statistical modeling, or param e tric estimating also uses historical data of key cost drivers and then calcu
what those cost would be if the duration or another aspect of the project is changed .
Three Point Estimate : Another approach is the thre!?"point estimate , which comes up with three scenarios:
likely, optimistic and pessimistic ranges. These are then put into an equation to develop cost estima tion . .
3. Reserve analysis
This technique determine s how much contingency reserve must be allocated. This approach tries
uncertainty .
4. Cost of quallty
This techniques uses money s pent du ring the project to avoid failures and. money
-
applied after the project
failures . This can help fine-tune your o verall project cost estimat ion. And comparing bids from vendors can also
figure out costs.
5. Bottom-up Analysis
This technique supports the Idea that the individual cost of ea ch activity or entire work package is of
importance. By using the method , ind ividual scheduled activities or a work package can be estimated to the
detail . All estimates are grouped and sorted by categories and then gathered into a summaiy table that is
tracking, control and reporting purposes . ·
- This ~ep_focuses on obtaining project information Including all previously developed protect scope and schedule
details and data from which a project cost estimate can be prepared .
- The level of scope detail varies depending on the project phase, project type, and project complexitybut womd
include the design matrix and criteria, all assumptions and pertinent sc.ope details.
- The estimate basis should be clearly. documented and forms the beginning of the estimate file that be
prepared for each estimate. Each of the following steps will add informationto this file with thl! end resultbeir,g
a complete traceable history for each estimate .
Prepare Base Estimate
- This step dev elop s the estimated costs for all components of a project. exduding future escalatfon. These
components may be estimated using different techniques depending on the level of scope definitianand the size
and complexity of the project.
The number and detail of components estimated may vary depending on the project daelopment phase.
inputs to this ste.p include pro ject scope details, Historical Databases and other cost da•abasu. llt.uwledge of
Mat1tet Conditions, and use of Inflation Rates.
A required component of the base estimate step is the preparation of a Basis of Estimate. document ttgt
describes the pr~ject in words and indudes underlying assumptions, cautionary notes.and
........
Scanned with CamScanner
3-21
_ Bottom-up estimating Is a way to estl p Pia &
mate an overallvalue by ·
the sum total of these values as th approxtmatlngvalues for srnan
e overall value In p J tt componemsand ustng
schedule or budget. · ro ect management, this type of estlmatfna ,_ ,_....,
· ·n. 0 U><:U to create a
- Another disadvantage of bottom-up estimating Is that It can be costJy.The time spent dtt.ompost"I project work Is not
---1&..1.-
m..duaIs r"'->t"""Qf"""for mnpedt• the
free. Additionally,the estimation done for each component. Is given by the lnd:.
components .
In ~eneral, bottom -up estimating is not the best choice for projects that do not allow for long periods cA ptar,nh• or
proJects that have contracted resources that typicallydo not start on the project much earfier than when the wc,r1r is
going to be completed.
Top-Down Estimating
Top Down estimating is a project estimating technique .in which the overall project is estimated first, and indMdual
tasks are apportioned from it. You start from the top of the pyramidand work downwards..
' '
- This type of project budgeting usually occurs when there Is a fixed budget and/or the scope of the proiect must flt
within a predetermined funding level, particularfywhen.projects aren't blessed with rich resources.
Top Down is the opposite of Bottom Up Estimating,whereby individualtasks are estimatedmt and 9raled up~ Into
the overall project estimate .
- In top down estimating, individual task estimates are only as accurate as the overall project esti~ they are demed
from. If the overall estima~ is incorrect, nothing will make the Individualtask estimates accurate.
- And because projects are normallytracked via lndlvldual tasks, this could lead to Issues duri• the project when
individualtasks are fncorrectJyapportioned, even though the overall estimate Is correct.
- Top-down estimating can be very useful when cost ~mates are needed In the very early phases of a project. This Is
typicallywhen not much Is known about the project and very llttle Information,If any, ls available.
- Since this technique Is based ~n high level Information, the estimated cost can be calctllated faster and wilh fewer
resources and effort. Therefore, It's a less expensive quick method for establlshlngthe project budpt than ocher cost
estimating technfques that require.more detailed Information.lnvoMnamore time and resources.
Another good advantag~ Is that top-doWn est1matln1gets greater commitment for the project from upper~!
management, while relaying to the 'tower management staff expectations for the budseL
Network Planning is a technique used in Project Management. It is used to plan, schedule and control the projects
consist of many interrelated activities. There are many techniques used in Network Planning. The techniques sepa
planning and scheduling functions .
Network Planning uses a network diagram to show various activities of a project. The diagram shows vari
sequences of the activities to be done using different techniques .
In other wo~s, we can say that the network planning is the categorisation of the activities involved in proj
implementation in a sequential order followed by a schematic presentation of the activities ne~essary for the
project.
A- Identify and list the category of activities involved from the start to the completion of the project. The activities
grouped in categories which are different from each other.
B. Arrange the list of activities in sequential order of their performance. There may be a0:ivity which can be started
after the completion of some other activity, whereas there may also be some o~her independent activity which
started simultaneously.
In network planning, such independent and inter-dependent activities a;e laid do • •
. · wn a 1ong with their estimated
schedule, i.e. the duration estimated from the start to the completion of the activity.
,. With the details of following A and B , draw the diagram of the netwo .rk 0 f th . •.
- - . . . e act1v1t1es so that the opera
planning of the execut.Jon of the entire proJect can be visualised. ,
. This whole procedure is the network planning of the project schedule which ma . - .
- ct easier than to look around the list of activities and locate 1 • kes the monitoring and controlll
the proJe apses, 1f any .
Network Diagram
A network diagram is a graphical representation of all the tasks, responsibilities and work -flow for a pn>fect . It often
looks like a chart with a series of boxes and arrows. It Is used to map out the schedule and work sequence ro, the
project and track its progress through each stage, up to and lndudlng completion. Since It encompasses t!YefY single
action and outcome associated with the project, a network diagram also illustrates the scope of the pn,fect.
_ A network diagram not only allows a project manager to track each element of a project and quickly share its status
with others, but also improves comprehension and enhances retention . As research shows depicting data In a visual
way can also boost performance and productivity while reducing stress among your t.eam members.
_ The project network diagram displays the duration of activities In the project , their chronological orde.r and logical
~ependencies between the activities graphically or In tabular form.Unlike the work breakdown structure (WBS), a
network diagram also takes into account the chronological order of activities according to their dependencies, and not
just the logical order of the project activities. Bar charts su~ as Gantt Charts are a special form of the networ1c
diagram.
ldentify ing Risk by identifying the critical path and the potential bottlenecks in the project process
Tasks
- · Prior to the construction of the network diagram, the project needs to have been broken down into its constituent
tasks. Tasks should not be too 'small or they become prone to micromanagement. Neither should they be too large to
lose the benefit of project control. So, a large task Is ~o different than a whole project .
For an example, a simple task list for a small convention could be:
o Finalize Attendees
o BookVenue
o Order Catering
o Write Speech
o Travel&Setup
- Interestingly, several of these tasks can be done In parallel. If you force yourself to perfonn Heh tJlsk one after the
other, you might be taking too long. That's where task dependencies come In.
(li) Rnlst\tD Rnlst\ (FF) : Task B cannot finish unti1 Task A comp letes .
(Iii) S'tartto Slalt (SS) : Task B cann ot start until Task A starts.
(hr) Sta rt (this one is rare) .
rt tD Rnlsh (SF) : Task B cannot start until Task Asta ·1 nod of ttm.
. T k B doesn't start unti a pe
Also. the tasks do not have to line up exactly . A lead time means that as . nagement software,
elapsed, and a lag time means that Task B starts before Task A finishes . In proJect ma
usually only a lag time specified , and a lead time is simply entered as negative lag.
•onsh' is by far the most common and if
It SOUnds oomplicated, but suffice it to say that Finish to Start (FS) relati •P
Stick to that. you won't get into much trouble . .
1 • de • •
n Pf'OJeCt man.-gem~t. the network diagram is a graph ical p1ctton
of a project schedule which uses
.
bous1
represent each task. It is used to determine the aitical path, as well as the float of each task.
(i) Critical hth : These are the tasks which define the completion date of the project. They cannot finish late, or
moved. or the overall project completion date will change by the same amount.
(i) Roat : It is the amount by which a task can move without affecting the completion date of the project.
path tasks have a float of zero . It is also called Slack.
Creating a n etworic dJagram can be an Involved process that begins after you have determined predecessors
activity. Here's a simple example that can help you learn how networit diagrams can be useful in any project
manage.
You find out how to draw the network diagram for a sample project from the information in the table shown he.re :
Paede(essor Rmtionships for YOUT Picnic
~----~ .;_. ....- -·. ---'
.. , - -- .:>·
r~~~!, ..
• ;
1·!": '--~ "'- . .. ,,.. ,,. ...t
lI
:, 'I.· ,.J... ,a
,, ,-~~- .-"
-.;:~ -,
Rg. 3.11.1
. . 4. Find all activities that have your first activity as an Immediate predecessor. Activities 2 and 7 have Activity 5 as at
immediate predecessor. Draw boxes to represent these two activities, and draw arrows from Activity 5 to AdMties 2
and 7.
s. Continue in the same way with the remaining ~cthrities.
Rg.3.11.2
Draw a box.to rep~ Activity6 and draw an arrow from Activity2 to that box. Only ActMty 3 has ActMty 7 as
an Immediate predecessor. So draw a box to represent Activity3, and draw an arrow from Activity 7 to ActMty 3.
Now realize that Activity·1 has both Activities 3 and 6 as Immediate predecessors. ~. draw a boll
representing Activity1 and draw arrows from Activities3 and 6 to this boll.
The rest is pretty straightforward. Because only Activity4 has Activity1 as Its lmmedl~te predecessor. draw a box
representing Activity4 and draw an arrow from Activity 1 to Activity4.
6. After adding all the activities to the diagram, draw a box to represent End, and draw an arrow from ActMty 4 (the last
r
activityyou have to complete) to that t?ox.
suvassolJne
• rs-10 _, .,
,._. Make ,
• sandwiche9 ,
ti= 10 ·
Ag. 3.11.3
. .· ur friend take to get to the lake far
Now for an 1mpartant timing-related question. How long will you a nd yo d th
. S2 I utes to complete, an e 1owe,
prcnlc? The upper path (Start , Activities 5, 2, 6, 1, 4, and End) takes mn .. th .
(St.art, Activities 5, 7, 3, 1, 4, and End) takes 57 minutes to complete. Thus, 1•t wr·11 take 57 minutes from e
start until you arrive at the lake fur your picnic, and th!? lower path is ~e critical pat.h.
.n
etWork diagrams . An ADM chart also does not have a way to encapsulate lead and I ti.
.
•h .
ag mes wit out intro u
d
nodes and activities, and it's Important to note ADM Is not widely used anymore d t 'ts . ·•
ue o I representational lim
2 • p,ecedence Diagram Method (PDM)
In the precedence diagramming method for creating network diagra h . .
- · I • hi . ms, eac box, or node represents an
the arrows representing re at1ons ps between the different cti . . .
a Vlties. The arrows th '
possible relationshlps : . . can ere,ore rep
(Iv) •start to Finish• (SF) : This Is an unoommon dependency and only used when one activity cannot finish until
another activity starts .
In PDM, lead times and lag times can be written In alongside the arrows. If a partlwlar actMty Is golng to require 10
days to elapse until the next activity can occur, for example, you can simply write "10 days" over the arrow
representing the relationship between the connected nodes.
PDM network diagrams are frequently used in project management today.
- Network analysis has played an importan~role in field of engineering. Applicationof networtcanalysis has been made
In information theory, study of transportation problem and planning and control of research and dewelopment
projects.
- In transportation problem, there are member of routes to reach a terminal,
. but we liketo choose
. a route far which the
cost or time is minimum. Th~re is a problem to select the shortest route through a netwult. Thus the problem of
network analysis is to find a course of action, which minimizessome measure of perfonnance.
- A project consists of no. of interrelated activities which must be executed in specificorder to complete the project. The
activities are interrelated In a logical sequence in such a way that some activities cannot start until some othersare
completed.
- These activities require time and consumption of resoun:es like labor, money, material and machine ett. The main
· objective before starting any project l.s to schedule the required activitiesIs an efficient manner so as to completeit-on
or before a specified time limit at minimum cost of its completion.
- The techniques which are used for planning, scheduling and controlling large and complex projects are termed as
network analysis or network techniques. These techniques are based on the representation of the projectas a network
of activities.
- · A network is essentially a araphlcal plan consistingof a certain conflsuratlon of arrows and nodes for showi,. the
logical sequence of various activities to be performed to complete the project.
Fig. 3.12.1
2. Event
An event In a networ1c diagram Is a specific lnmnt of time which mar1ts the start, or the end of an activtty.E
consumes neither time nor resources . It Is represented by a circle and the event number is written within the d ·
The event drdes are called nodes. Therefore, the major difference between actM\ies and events is that 'rtNma
31
represent the passage of tJme whereas events are points In Ume.
All actMty arrowsmust besln and end with event nodesas shown as follows
@~(§
Fig. 3.12.3
Rg.3.12A
(i) Merge Event : An event which represents the joint completion of more than one activity is known as merge
event.
(ii) Burst Event : An event which represents the beginningof more than one activityIs known as burst evt!nt.
(ffi) Merge and Burst event : An event may be merged for som·e act.ivities and burst for some other activities
simultaneously.
• ...... ,.,...
1\:::1 •
- CPM me th od developed was by E.I. du Pont de Nemours Company (USA) In 1958 and named as critlcal path
(CPM) to schedule and control the project. CPM Is applicable to both large and small projects, taking from
Program,. tn ~ddlng or horse shows .
- It Is Widely recognlted and Is the most versatile and potent manasement planning techniques. The objective of crltl
th
pa analysts Is to estimate the total project duration and to assign starting and nnlshlng times to all activitiesI
In the project.
1. Break down the project Into various activities systematlcally . Label all actMttes. Arrange all the activities in I
sequence . Construct the network diagram .
2. Number all the nodes (events) and activities. Find the time for each activity considering It to be deterministic. lndi
the activity times on the arrow diagram .
3. Calculate earliest start time, earliest finish time, latest start time and ,atest finish time. Tabulate activity normal ti
earliest times and latest times .
4. Determine the total float for each activity by taking difference between the earliest time and latest time for
node .
5. Identify the aitical activities (the activities with zero float) and connect them with the beginning node and the end '
node in the network diagram by double line arrow . This gives the critical path .
6. Calrulate the total project duration.
7. It is intended to reduce the total project duration , crash the critical activities of the network.
8. Optimize the cost.
The ba.sic objective of the time analysis l.s to get a planned schedule of the project for which the following fa
should be known :
- Total completion time of the project.
Earliest time when each activity can begin.
Latest time when each activity can be started without delaying the total project .
- Float for each activity I.e., amount of time by which the completion of an activity can be delayed without delaying
total project completion time.
Identification of critical activities and altlcal path .
The basic scheduling computations can be grouped Into the following heads :
EF11 =ESq+tq
=.E1+ tq
(iv) calculate earliest occurrence ti
.., d' me for event J (J > I) which Is the maximum of the eartlest finish times of all
act1V1ties en mg Into that event, I.e.
E1 = Maximum (£Sq+ liil .
= Max (E1+ tq)
The computed values are Put Into the lower left portion of each event. ·
2. BackWard Pass Method (For latest allowable time)
In this method calculation begin from last event L
The various steps are as follows :
(i) Set the latest occurrence time of last event L which is equal to the earliest occurrence time of that event
obtained from forward pass method. ·
i.e., Assume L = Efor endingevent.
(ii) Latest finish time for activity(ij) equal to the latest event time of event j, i.e., lfq =
(iii) Latest starting time of activity(l,j) ls the latest completion time of (l,j) minus the activitytime Le.
LSiJ :s lfiJ - liJ
= t.-t u
.
(iv) Latest event time for event i is the minimumof the latest start time of all activities origlnatina from that event.
'·
Thus
L; = Minimum (L.Sii)
= Min (LFIJ-l;j)
= Min (~-Lt;)
The computed values are put Into the lower right portion of each event.
..........
,
• • , , • •• , 1 •• •
2. Acttv1ty-On-Mode(AON) Network
In AON networks, activities are represented by drdes or nodes and arrows are used only to
dependency relationship between the activity nodes. Generally these diagrams have no partiaJlar starti
ending node for the whole pro}ect. The ladt of dummy activities in diagrams makes them easier to draw
understand.
(i) ActivityA
pt events cannot occur until all the Incoming activities Into It have bttn completed .
pt activitY cannot start until all the Preceding actMtJ~ have bttn compf~ed .
t40 set of activities cannot form a drcular loop.
,Jtt r the networic is drawn In a loglcal sequence, every event Is assllned a number . The number sequence must be
so as to reflect th e flow of the netwonc - A number Is placed Inside the drde . The rule deYtsed by D.R. Fufltttson Is
used for numbering .
The procedure for applying this rule conslsts of Identifying the Initial event and then gradually mmoertfnl the
succeed ing event by deleting the arrows from the previous preced ing events . A number is assigned only when by such
deletions a node is converted Into fnltfal event. ft Jnvofvesthe foflowfng steps :
0
Event numbers should be unique .
0 Event numbering should be carried out on a sequentlal basis from left to right,
0 The initial event which has all _outgoing arrows with no Incoming arrow fs membered as.
0 Dele te all arrows etnerBing from all the numbered events . This will aeate at least one new start eveYt out of the
proceeding events.
0 Number all new start events 2. 3 and so on. Repeat this process until all terminal event without any s-JC • essor
activity is reached, Number the tennlnaf node suitably .
EJarnple : Construd a netwonc for the project whose adMfies and their precedence raationship 818 as giYer1 as fellows :
ABC DEF · G HI
A A D 8,C,E F D G,H
olution :
From the gjyen constraint, it is dear that A, D are the starting activity and I the terminal activity. B and Care staa tile
ith the same event and are both the pred~rs t;;f the activity F. AJso E _has to be the .,redec:essor of both F and H.
!IICe, we have to introduce a dummy activity.
(•) (b)
(c) (d)
Ag. 3.13.1
1 is the dummy activity.
• ....., ...,...
a,;c r•
H
Rg. 3.13 .1 (e)
The constructionof C.P.M. diagram can be explainedby the followingex~mples:
. lhe .........i-. op818fiocl8 -
Example 3.13.1 : Fof the constructionof wall the complete processcan be broken intO IUOIU'l"f" "II •
Solutlon:
These following operation have not been written In a logical sequence. These operations can be denoted by
symbolsABCD.
The C.P.M. diagramcan be drawn as shown In Fig. P.3.13.l(a}.
D C B A
Ag. P.3.13.1(a)
The operations D, C, 8 and A have now been shown in the logical sequence. From the study of these operations, it ·
found that preparingmortar is independent of diggingfoundation and planning operations. Therefore a mocfifiedU.
diagramis drawn in Fig. P.3.13.l(b).
Dig
Foundation Planning
•, t ·----f
Prepare
Mortar
Rg. P.3.13.1(b)
In this Fig. P.3.13.l(b} numerals (1, 2, 3, etc.) are used commencing from the first column on the left and then
proceedingtowards right.
The operations are not given In logicalorder. There loglcalorder will be accordingto Fig. p3 .l3.l{a)
E
Rg. P.3.13.2(a)
·1>--~ ·---~
Rg. P.3.13.2(b)
- 'fhe cutti ng and drilling of the bamboos and wrings are different operations, and these are Independent of each other .
Therefore cutting two ~mboos and cutting wrings can be started concurrently . Thus after the end of operation E,
0 peratio n D can begin and similarly after the end of operation e, operation C can start.
_ After the end of operation C and D, the last operation of fixing nails can begin _. Thus the network is drawn from left to
right and each drc:fe representing an operation Is numbered from left to right . All the drdes in the ~me left are
first numbered and so on.
_ It is clear fro m the Fig. P.3.13.~(b) that operation 5 can only begin when the operation 3 and 4 are over. Thus we can
say t hat operation 1 immediately preceding operation 3, and operation 2 immediately precedesoperation 4. Also the
operation 3 and 4 must Immediately precede the operation s.
_ In the language of C.P.M., the operations 1 and 2.are called the pre-operations (or PRE- OPR) of 3 and 4 respectively.
Similarly 3 and 4 both are the PRE-OPR of operation s. Also 3 and 4 will be called post operations (POST-OPR) of
operatio ns 1 and 2 respectively, 5 is the POST-OPR of operation 3 and 4.
EJample3.13.3 : Suppose we want to start a small scale factory in a shed aVBJlable in an Industrialarea in which wakshap
is to be prepared . First step is then to <frvidethe project into operations.
The 6st of operations is given as follows.which is not in a logical order :
A = Machine foundation
B = Electric fitting
C = Repair of floor
D = Installation of machines
E Procure workshop bui~
F = Whitewash
G =Clean up
Its logical order of operations should be E, A. D, B, F, C and G. (Refe.r Fig. P.3.13 ..3(a)).
Rg.
- If each operation is represented by a drde then this worlt can be executed In a better way as follows :
- Sketch shown in Ag P. 3.13.3(b) is drawn as per drde and line method in which drdes ~presents the operation or
activity and the line shows the relationship between the two activities. The operation on the left of each line should be
completed before the starting of the operations on the right of the line .
Flg. P.3.13.3(b)
- ·
Network shows that operation 3 and 4 are not affected by operations 2, s and 6• Hence the operations 3 and 4 can
conducted at the same time , when 2, 5 and 6 operat ions are being conducted .
- This reduces the tlme to complete the project because after operation 1, oper:ation 2 and 3 can be started
simultaneously. Operations 6 and 4 should be completed before the beginning of the operation7. In the final nf!twodr.
diagram operations should be represented by the numerals Instead of alphabets .
1 2.3
2 4
3 4.5
4 6
5 6
Solution :
As no operation precedes operation 1, hence we s_hall start network from operation 1, keeping it in first vertical
rolumn. Operations 2 and 3 are ~st-operations of operation 1; hence these are kept in second vertical column as shown in
Fig. P. 3.13.4(a)
•t------1 ~ ,
Flg. P.3.13.4(a)
As operation 4 can be started when operation 2 is C?mpleted therefore, it will be kept in third vertical column.
Operations 4 and Sare the post-operat ions of operation 3 and can be started simultaneously after completion of operation
3, henceoperations 4 and 5 both can be kept _in the same third column. As operation 6 is the post-operation of operations
4 and 5, hence will be connected by both 4 and 5 an~ will be placed in the next column, I.e•• in the fourth column as shown
in Ag. P. 3.13A(b)
Flg. P.3.13.4(b)
In Fig P3.13 .4(b) , line connecting operations 3 and 5 crosses another line; hence It may be arranged In a better and
dear form as shown in Rg. P.3.13.4(c). ·
. ' .
5
Fig. P.3.13.4(c)
sometim~,. it is not possible to avoid ft then the llnes may cross each other but care shoufd be taken that such lines
shOUld be as minimum a.s possible and dear to understand.
2 1
3 1 and2
Solution:
- As the operation 1 is the first operation, hence networtc wilf be started by operation 1 denoted by the drde in first
column. Operation 2 is the post-operation of 1 and therefore will be kept in second column.
- Operati on 3 has pre-operations 1 and 2; therefore opera tion 3 cannot be started unless operations 1 and 2 are
complete. Hence operation 3 can be kept in th ird column , I.e. after operation 2, and not in second column immediately
after operation 1. It is shown in fig. P.3.13.S(aJ.
Rg. P.3.13.S(a)
>lutlon :
After dividing the project into some operations, networtc can be drawn as per Fig. P.3.13.6(aJ,
Fig. P.3.13.l(a)
•
If suffioent ·
men, nt'
equlpme s an
d materials are avaflabfethe netwoncwoufd be better to draw In the form as shown
- the tf fn,o ..-.ufred for selecting colors, ordering and testing pafnts and wfthout waltl,. for
·•g. P. 3.13.6{b) to reduce m D • - ...
• be done on ground floor and In the mean-time plaster wort on first floor w,11 be
plasteron first floor, painting can
can be done Thereforenetwork shown In fll. P. 3.13.6(bJ Is a better dla,ram
.
1pleted and the painting on the same ·
n the paint of vfew that it will savethe time. '
..,., '-.-
..__-_______
Example 3.13.7 : Draw the network diagrams for the project in which PRE-OPR or POST-OPR are given as :
-- .'PRS:.OPR' _,,
A None
B A
C B
0 B
E B
.F C,D , E
Solution:
Fig. P.3.13.7(a)
Example3.13.8: The example 3.13.7 for the above networ1< diagram can also be framed in terms o1 POST-OPR as given
under: =~~~.,,,...,..,=:-::r.-:,,,,....,,.,,,..--::-,,,-,,-, .
·;J:•~· fPO
~;,,.
'' ...
n .iina
...-.~~l;'"'p t
A Precedes B
B • C,D,E
C Precedes F
D .. F
n
E F
Solution: Refer example3.13.7
Example 3.13.9 : Draw the networ1<for the followingIn which POST-OPRsare given :
,.
;_ J'.!_1.~ ._.;j, .. ,,
.,
I
•:!
.,,...... , v·
.. ·-r ,
•
f,· ~'
••I
i"°8T~Pit
A Precedes B
B " C, [?
C " E,F
0 "
.. E
I
E G
F "" G
(a) (b)
Fig. P.3.13.9
As tar as possible, the crossing of lines should be avoided . This makes the diagram less confusing and easier to
understand. However, sometimes it m'ay_not be possible or desirable to eliminate the occurrence of such crossing
lines. The numbering should be done starting from left and moving towards right, the first vertical sequence of
operation being numbered first and then the second and so on.
(c) (d)
Fig. P.3.13.9
A MacgubeFoundation 10
B Bedric Fitting 15
C Repairfloor 20
D lns1alla~n 12
E ProcureWortcshopBuilding 15
F 5
WhitewaSh
G 2
Can
lution:
The following activities are drawn in the network as shown ls Ag. P.3.13.l0(a}. Each activity Is represented by the
lJ meraI ·in the arde.
. b
Num ers o
f days are mentioned on the left comer of circle representing the operation.
3-40
Fig. P.3.13.10(b)
- PERT (Program Evaluationand Review Technique)was developed by a navy sponsored resource team composed of
Messrs. DG. Malcolm,J.R. Roseboom, C.E. dark and W. Fazor in about 1950.
This Is essentiallya management technique used with advantage for responsibility accounting in addition to attaining
other well defined objectives . It is a method In which we try to exercise logical discipline in planning and controlling
projects.
- PERT Is designed for scheduling complex projects that klvolves many Inter-related tasks. It improves the planning
process because:
0 It forms the planner to define the projectsvariouscomponent activitiesand events logically.
0 It provides a basis for normal time estimates and yet allow for some measure of .; . . ·
• comp ....
estimating d tes 0pumum or pessimasm In ,
1c:uOn a . .
0 It showsthe effects of changes to the overall plan as they contemplated.
0 It providesa built In means for on-goingevaluation of the plan.
0 It facilitates the process of communication betweenplannersm ,
anagement by either adh . . . .
or aosslng over them. In essence, PERT makes the clear cut a . enng organisationallines
ss1gnmentof feSPonsib"t•ty
11 .
P0s-s1ble.
The main objective in the analysis through PERT is to find out the completion for a partkulMevent within specified
date. If yes, what are the chances of completingthe job? The PERT approach takes Into account the uncertainties. In this
approach,three time values are assoeiated with each activityof the optimisticvalue, the pessimistic value. and the most
likelyvalue.These three tim_e valuesprovide a measure of uncertainty associated with that activity • .
This is the shortest possible time in which the activitycan be finished. It assumes that everythinggoes very well. This is
denoted by tO or a.
2. Most likely Time (Im)
This ls the most likely time as probablythe actual time required to complete an activity . In this case it assumes that
thingsgo in the normal way, with a few delaysor breakdownetc. this is denoted by tm or m.
3. Pessimistic Time ·(tp)
This time is based on the assumption that everythingwill go badly. Thus, it is the maximumpossaaletime requiredto
perform an activity. However,this does not indudemajor catastrophes like labour strikes.acts of God. and unrest. It ls
denoted by tp orb.
t-
i:::,
I
u.
Moetllely Pemnlstic
.'MF 5 %"
th~
I distribution where 99% of e area
- Variance for an activity is estimated on the basis of analogy to th e norma . ately 6a in length therefore, the
the normal curve lies with in the ± 3a from the mean or fall wi th in lhe rang~ adp.pr~XJbutim_ Thus if denote the standard
. 6<J fa cvmmetrtc istri on. •
interval (to, t) or range (lc,-tp) is assumed to enclose a bo. ut o .. , ...
deviation, then
6cr ==
OT CJ =
Variance of activity tim e,
er = C¥Y
6CJ = lp-to
(J = (¥)
Variance of activity time,
er= (¥Y
3.14.2 PERT Algorithm
The various steps involved in devel oping PERT-network for analyzing any project are summarized as follows :
Step 1:
1. Developa list of activitiesthat made up the projectIncluding immediate predecessors.
2_ A rough PERT network is drawn on the basisof the three questions for each activity.
{i) Which activities precede this one?
(ii} Which activitiesfollow this one?
(iii) Which activitiesare concurrentwith this one?
ObviousJv, the first activity woutd be preceded by none and the last r-tkm-.. ·
. a~....,.., would .be followed by none. During
...... ._._
Using the expected activitv time estimates, determine the earliest start time and the earliest finish time for each
7.
actMtv, the earliest finish time for the complete project correspondsto the earliestfinish timefor the lastactMty.
After determining the latest start time and the latest finish time for each activity, a,mpute the float assoaatl!dwith
8.
each activity, the critical path activities are the activitieswith zero float. Detenninenow the aitical path ttwuuBttthe
given network.
cf = .[¼(b-a)]l
10. Use the variabilitV in the ·activity times to estimate the ~riability of the project completion ~. then using
this estimate compute the probability of meeting a specified a,mpletion date by usi11l the standard normal
equation.
Due date Expecteddate of completion
z =
_ Where z= no of standard deviations the d~e date or target date liesfrom the mean or eapected date.
. · th criti I th durationis not acceptable to the
- Crashing or compressing the project may have to be undertaken tf e ca pa
· . h · to be performedif resourcesare limited.
management or resou~ allocation may ave
~-... .,.
Scann.edwith CamScanner
p
3-44
rt Dlrt8
Rep0I ,i/12 31/12
2
... 3112 10/12 11112
Preliminary .
:
lnY11Sllgatton '
WriteRepon
rw
Interviews
.b
I
I
:
Training :
I
Evaluation J
Final Report
[ 1
0
construction
0
consultingAgencies
0 Marketingteams
0 Manufacturing
0
Human Resources
0 SoftwareDevelopment
0 Event Planning
Difficult to see on one sheet of paper : The software products that produce these charts need to be viewed on
computer saeen, usually in segments , to be able to see the whole project. It then becomes difficultto show the d
of the plan to an audience . Further, you can print out the chart, but this will normally entail quite a large •cut
paste• exercise . If you are going to do this frequently, it can be very time-consuming.
I _ ::::: ::ke:::: -:=:.-. acxess to data from ~fferem proje<ts for nwh>jnje<t •~
integrating with other systems,such as payroll, inventory, etc. The easier a PMIS is to use, the less time and money
required to train. ·
3.16.1 Functions
3.16 .2 Advantages
benefits of using an onllne or d
-
Wh·1 1 e th ere are manual project manogemcnt informat Ion systems, the ·ty effide nCV, eco nomy, accuracy
noed c.ipact , l
system are numerous . With an online Information system Sr , fits the most practlca Is speed.
ab 1Tty
1 h fall these bene I ,
to and le complex projects can all be approved . But O r needs with great
Its a project manage
- Once the data ls collected , It can then be adjusted to reflect the resu d evise plans, schedules or
accu N c.in it create an r
racy . A manual program Is never going to match that . or
qu, 'ckly · What once took days or longer Is now completed ·'" secon
· ds · Is lso
- . . ts of data wtth a PMIS. That data a
ProJect mana gers and their organ izations can store large amoun which is large and requires
accessed, Prioritized and summarized as needed . And unlike a man~al system,
support P~nel, an online PMI.S needs far le.ss support and space .
With these factors there is also a cost benefit. The cost advantage of a digIta
I over a manual PMIS isfusually sign
Is
. . . correct. the chance o errors
especially when c:on.sidering storage and proces sing. And ,f inputs are
diminished with a doud-based PMIS.
I·ReviewQuestions \
Q.1 Explain Project Planning & its purpose. (Refer Sections 3.1 and 3.1.1)
Q.2 Desaibe the important areas of Project Planning. (Refer Section 3.1.3)
Q.3 Expmin Project Scheduling. Describethe process of Scheduling: (Refer Sections 3.2 and 3.2.1)
Q.4 Explain wor1c breakdownstructure.What are its advantages?(Refer Sections 3.3 and 3.3.2)
Q.S Describe the process of creatinga work breakdoWnstructure.(Refer Section 3.3.3)
Q.6 Explain Linear Responstbi lity Chart. List its advantages & cisadvantages.(Refer Sections 3A, 3.4.2 and 3.4.3)
Q. 7 Describe Interlace Coordination . What are its functions?(Refer Sections 3.5 and 3.5.3)
Q.8 Desaibe oonc:unent engineering. List its advanlages& disadvantages.(Refer Sections 3.6, 3.6.2 and 3.6.3)
Q.9 Explain Project cost estimating.What are its key components?(Refer Sections 3.7 and 3.7.2)
Q.10 Desaibe any four cost estimationtechniques. (Refer Section 3.7.3)
Q.11 Desaibe and dttferentiateBottom-opand Top-down Estimatingtechniques. (Refer Sedlons 3.8 and 3.9)
· 0.12 Oescti>e netwoncPlann ing and the steps used in it (Refer Sections 3.10 and 3.10.1)
o. ·13 What is a Networ1cDiagram?How we constructit? Explain(Refer Sections 3.11 and 3.11 .2)
Q.14 Explain different methods of constructing network diagram. (Refer SecUon 3.11.3)
Q.15 . What is Networ1cAnalysis?List i1s advantages. (Refer Sections 3.12 and 3.12.2)
Q.16 Describe Critical Path Methodwith its steps. (Refer Section 3.13)
0.17 Desaibe and cflfferentiateAOA & AON (Refer Section 3.13.3)
0.18 Describe PERT. Explain~e three time estimatessystem. (ReferSections 3.14 and _ _ )
3 14 1
Q.19 Explain PERT algorithm.(Refer Section 3.14.2)
Q.20 Explain Gantt Charts. Describeits advantagesand Limitations (R8 fa
• . • r Sections3.1S. 3.15.4 and 3.15.5)
0.21 Explain Project ManagementInformation System. List ils advanta.
ges. (ReferSections3.16 and 3.1U)
crashing project time, Resource loading and levelling, Goldratt's critical chain , Project Sia~ end
communicationplan.
Risk Management in projects : Risk management planning, Risk identifica1ionand "*
register. Ouailahe and
quantitativerisk assessment.Probabilityand Impactmatrix. Risk responsestrategiesfor posffiw and negatNerisks.
4,1 Introduction
_ project planning is the most important part of the project life cycle. It tells what is to be achined and how. The
planning phase is when the project plans are documented, the project objectivesand requirementsare defined,and
the projectschedule is created..
_ It involves creating a set of plans to help guide youthroughthe implementationand dosure phases of the The
plans created during this phase helps manage time, cost, quality, changes, risk, and related is.sues.They also help
control staff and external suppliers to ensure that the project is delivered_on time, withinbudget.and within schedule.
_ Project schedulingis a mechanismto communicatewhat tasks are to be done and which cwga11iutio11alresourceswil
· be allocatedto complete those tasks. Thus project schedulingis a documentcollectingall the work neededto be
to deliver the project on time.
- Project risk management is the area of project managementthat deals with the identification,analysis and mitiptian
of risks that can occur on projects. A p~oject is· t~porary endeavour undertakento produce a unique product.
service or result. This definition shows it is a risky endeavour.Since every project is unique, there are often ""'1Y
uncertaintiessurroundingit. ~e limitedtime and cost for each projectalso inaeases its risk.
- can have a positiveor negativeimpacton the scope, cost. time and qualityof the project.
A projectrisk is an event that
Risks usually have causes and if they occur,they _can have multipleImpacts.
- Therefore it is important to plan for these .risks, Identifyand prioritizethem, and ensure that adequate responses are
provided.'The goal here is to minimizethe effects of these risks so .they do not negatwelyaffect the time, cmt
and performanceof the project.
financial) with the needs of the organization in order to achieve the established goals. Optimization brings the d
results within a set timeframe and budget with minimum usage of the resources .. The need to optimize ~nrnrr.
particular1y evident when the organization's demands tend to saturate and/or exceed the resources
available .
In Project Management, Resource Optimization Techniques are utilized to make adjustments in the impi
and completion dates of the projects, modify the organized resourceused and resource aa:essibllity. Used a as
the Schedule Network Analysis to calculate the schedule compression of the ro ·ect Resou .: - ·- -·
Techniques indudes the scheduling of activities and the resources required by thos:
a~ wh" rce : ; ·
accessibmtv of resources and the task time. es lie-
4.3.1 Benefits
Find the normal aitlcal path and Identify the critical actiVltY•
2. c.alailate Cost slope
- Calculate the cost slope for the different actMtie.s by using the formula .
Cost slope = Crash cost-Normal cost/Crasht11M-Nonnaltime
- The cost slope indicates the extra cost required to expedite an activity per unit time.
3. Rankins
Rank the activities in the ascending order of cost slope. The activity havingthe minimum cost slope have to be
first. crash the selected activity to its minimum dura tion.
4. Ctashir'C
Crash the activities in the ait:ic:al path as per the ranking i.e., activity having lower cost slope would be er.ashed~
the maximum extent possible. Calculate the new direct cost by cumulative ad~ing the cost or crashing to the n
cost.
5. Parallel aashlnc
As the critical path duration is reduced by the crashing in step 3, other paths also become critical, le .• we
critical path . This means that project duration can be reduced duty by simultaneous aashing or~ on the ·
aiticaJ path . -~ ........,,
6. Totalcmt
Crashing as per steps 3 and 4, one reaches a point when further crashingis either not •
reduction
.
°'
aash lng or project duration For the d"1ff
. ·
P0SSlble or does
erent project durations total cost ls fou
not result
by adding corresponding fixed cost to the direct cost
commutativeto the norma l cost. ' an
d th nd up to total cost
e d irect cost Is got by adding the expedmna crash-.
4.5 Resource Loading In Project Management
- In project management, the constraintIs the Ion est .
pr-oject. Most projects involve ma 8 chain of activities from the sta
definesthe effectivenessof th j ny different resources at different tim Thrt of the project until the end
e pro ect. es. e effective f
- A good project management organlza"'' use o these
uon must make ff ·
managers to maxJmlze the use of the reso e ectiveuse of Its limited
urces so that key resou resources.This often puts
rces can be kept .._,__ _
~,. But, the aim of good
~p~:::::=::::::;::::::::~::~~===-=========~~~~
,_
lflanag
ernent is to complete the projects as early
0 when key resources are overloaded or dist
5
as Possible without •
Plan . .
eds
compromisingon the deliverables.This can't
t,aPPe . . ratted . Manageme t oft:
rces. Often 1t results mto delayed projects With 1 . h n en commits errors of overloading
resou . . ess t an high qualitycontent.
fact is neither too httle nor too much utlllzati of ·
The our key resources will be used. Schedulln kon resourcesIs deslrable. It 1s ~--- ·f
~m:r r we can somehowpredict
wtten B ey resourcesto completetasks I adva
owever, key resources are often used many times in n nee soundslike a good Idea.
H I in a task can cause chaos In sudl a co . II a projectand frequentlyshared betweenprojects. Even a small
de av , mp cated and Interrelatedschedule.
While it may be possible to estimate the current w kl d
or oa on hand for a spedficresource at any moment In time it is
d·fficult to be accurate. Examining the world d of k
1 oa ey resources In advance in a general way can yteld leading
indicatorsfor managers to effectivelyuse these resources.
source loading is basicallyallocati 8 .
_ Re . n resourcesto the activitiesat the right time. Project managerswith the help of
resource loading can calculate the employees working hours and do the allocation of various tasks. Based on the
th
prediction, e manager can also Predictif he needs to add any empl~ees to the projectto complete It on time.
_ The Resource Loadingtechnique looks forwardIn time for a finite periodand estimatesthe workloadof key resources
during that period. It does n?t look at exact work schedules but the general badJoad of work released for the ·
resources.
_ It also assumes there is adequate work in the system to allow the resourcesto have work most of the time. It does not
look at unique timing situations which may overioadeven the best plannedschedule.
_ some projects are long and some are short. The ResourceLoadingexaminesall the active projects of an orpuization
and takes a simple average of the planned length of the projects. The averageis simply the sum tat.al of the planned
length of each project ~i~ded .by the number of•projects. _The Look_Ahead Peri~ will change each time a projectends
or another project starts.
_ The Resource load ing examinesthe all uncompletedtasks remainingin _each activeprojectfor look Ahead Period. The
technique looks at .each resource type involved in the active projects and adds the ·estimared ~pleted task
durations required during the Look,. Ahead Period.
- This total task load time for each resource type is.divided by the number of resourcesof that type and again by the
Look Ahead Period. Th~ key resourcesare those that have more than a 50% workload.
_ The Resource Loadingcan quicklyidentifythe Key Resourcesof the organization.Th~ resourcesdeterminethe rate
at which projects can be completed. If these resourcesare more than 100% loaded, the project organizationhas
overloaded the resources and project p~ is almostat a standstill.
· loading·at about 75% generates.fast, quality projects and optimizesthe: projectresoun:es..
- Keeping the key resource
. . . .falls.be1o~-75%, the key-resources can
When key resource ut1hzation a,TI:1.1 an -•c,--
be st __ _. d the nnr.:anir.atlon 1s not befntt
''I:>
PlanningProjects
- If the feeder chains are scheduled to their early schedule dates, early starts, and early finishes, there is a disadva
The disadvantage is that if changes in requ irements, risks, or other problems OCOJr in the project. much of the work
the feeder chains will already be done and will have to be ripped out.
- This problem can be at least partially avoided by scheduling the feeder chains more toward their late schedule.
Delaying the schedule of the feeder chains will also let us take advantage of lessons learned on the aitical chain
activities. These can be app.lied to the feeder chain activities. ·
10 85
Stan~devltlon 3 3 4 2 6.2
Fig. 4.7.1 : FeederChainsand CriticalChains
4.7.2 Constraints In Critical Chain
1r~~::=~:::::::;:;=:::::-;:=::;::~::=::::=-~------~==~~~
u
. heir scheduledtime. In other words the sav d ti
11t1I t ' e me cannot be
'f there are delays over and above the estlrnat....a
PIA,.,.....,. .
pa~ed on to nntsh the project~ On th other
h3r,d, I schedules thes d I e
irt rflO
• . •
st cases, will exponentiallyincrease the pro)- l" ...L
..... .JU1edule.
'
--.au
~a .. ,.
e e ays Will most definitelyget -......a d
on, an ,
critical Chain Pro)ect Management Proces
4.1.3 s
f:"plolt the Constraint
1
· i·ect management activities earlier were based ·
pro on constraintsthat sometl del d
·rfle is added to a project Just to get It finished on ti mes aye the Pfolett.So extra ree,-ye
ti u are trying to achieve. Of course you want th me even after delays. So the first step is to let people know wh.lt
yo ' e average time In which an activity be ..a
everythinggoes well. After you have got all the lnformati can_ com.,,etedto_make 5Urf!
average time, plus a buffer that's between the best and w ont, you can st~rt constructingyour aitltal ~ -using the
. ors -case scenarios.
Eliminate Multitasking
z.
Multitaskingis th e process of dropping a task before It Is finished to start another and begin vet other It •
removed because you probably cannot do several things at once. Your projects expect 100 percent foe: on~~
iri hand.
' ',.
1_ Top Management
- Top management may include the president of the company, vice-presidents,directors, division managers. the
corporate operating committee, and others. These people direct the strategy and development of the
organization.
- The support of the top management makes It easier to recruit the best staff to carry out the project. and acquire
needed material and resources; also visibility can enhance a project manager's professionalstanding in the
company.
Some Sugestions in dealingwith top managementare :
0 Develop In-depth plans and major milestones that must be approved· by top management dwing the
planningand design phases of the project.
0 Ask top management associated with your projectfor their lnfonnationreporting needs and frequency.
0 Developastatus reporting methodologyto be distributedon a scheduledbasis.
0 Keep them informed of project risks and potentialimpactsat all times.
_
- Workingdosely with the team to sond i P:ch memberwill help you get their support and _cooperation.
your support for the project team a or ··rte 7 \ -
•••,u.,,•••
.
d who can won< with the project
- Normally, the top management decides what the assignment Is an t the neces.sarvresources to
on projects . Keepingyour manager Informed will help ensure th at you ge
your project.
d. and supportive boss to go to bat for
- If thing-s go wrong on a project, it Is nice to have an understan mg ft,
O
necessary. Bv supporting your manager, you will find your manager will support you more en .
Suggestions
6. Internal Customers
Internal customers are individuals within the orga · t·
niza 10n who are t. ·
- . •
Internal demands . The customer holds the pow t cus omers f9r projects that meet the
. er o accept or re·ect .
1 your Work. After the pro · ect begins
manager must stay tuned in to the Internal cust .., 1 the
ome, s concerns and issues . ,
a nd keep the customerInformed.
- When project stakeholders do not share·a common culture, project manacement must adapt its organizations and
work processesto cope with culturaldifferenc;es.
The followingare three major aspects of culturaldifferencethat can affecta project:
1. Communications
2. Negotiations
3. Decisionmaking
- Communicationis ~aps the most vfsible mantfestatJonof culture. Project managersencounter cultural diffbences
in communicationin langua,e, a,ntext, and candour.LanguaaeIs dearly the 1reatestbarrierto communication.When
project stakeholders do not share the same languag~,communicationslows down and Is often filtered to share only
informationthat ls deemed attical. The barrier to communicationcan Influenceproject executionwhere quick and
accurate exchangeof ideas and informationIs critical. .
- The interpretationof Informationreflectsthe extent that contextand candour Influenceculturalexpressionsof Ideas
and d . . rmatf I e cultures an affirmativeanswer to a questiondoes not always mean yes.
un erstanding of info on. n som ,
The cultural .influencecan aeate a>mu;,,On
-1.. ,_, n a pro·'ectwhere projectstakeholdersrepresentmore than one rulture.
o ·
_________ _:______ __,;._ __,,.-----------:---------.~Te+l~~·~b~· ,,.11 c a1 1eas
.
0 Communicationtools and th .
: . me 0 ds, and
o High level project communfear .
10n messages
0
.setting d ear ~ectations for h~ and when updates will be shared
increasing visibilityof the project and status
0
providingopportunities for feedback to be shared
0
0
aoosting the productivity~ team meetings
0
Ensuring the project continues to align with goals
A communication plan must be aeated for the project. To do this, it's important to spend time plhefnc input from
all stakeholder groups to ensurethe plan is comprehensive. It's also Important to note that changes may need to~ made
10 the plan as the pro!ect movesforward. Here's the general framework. ·
2. CommunicationRoles
Communicationwon't comefrom j~ one person ~'!ri"i your project. Oearly define all roles and their CDih?5PCJ!Cii•
communication responsibilities. He,:e are a few roles to consider :
- Project Sponsor
• '1 ;·,
Project Manager
Leadership/ Management Team ·
- Steering Team
Project Lead
3. CommunicationTools
·
Selection ·· and how a message Is deliveredwm vary from projectto project. Y0411 peferred
of the tools t use . ·
tha
.
th
tools should be those which can easilybe comprehendedby e receivinggroup. _
-..a....1nsthe contentof the communication.-.d the methodIn which It wdl
Alwayskeep your receiverIn min~ when d · · uestl rovldefeedbactcan provide beneftcfal
be delivered Methods . that offeropportunitiesfor'peopleto ask q ons or P ·
· · Just a few•
Brainstorming a list of possible tools can get you started.Here_are ..
., 35 2 ,-
- Meetlngsummaries
- Status reports
- Newsletters
Formal presentations
- Surveys
- Internet/ Intranet Web Page
- Informalsmallgroup meetings
- Brown bag lunch workshops
- CUstom project dashboards
4. Communication Methods · · nd h Id 1
munication plan can a s ou
There's no single right way to communicateon a project. In fact, your com
variety of communicationmethods. Here are a few to consider:
- Email
- Meetings(in-person,phone,or video chat)
- Discussionboards
- Collaborationapps
To-do lists
Surveys
~--~-::=~~==~------=--------
RtS
~isk Management In Project
. k is inevitable in a business organlz ti
condition that has ·a positive
fo
or negative eff
can affectyour proJect r better or for worse.
•
a ·on when
ct
und kl
erta ng
·
projects . PMI defines risk as an unoertait
e on a proiect' b,1
.! s o 1ectfves. Basically,risk 1s any unexpected
" evewt ot
that
-----------------------------.;~.;;.~
management activities required for the project.
•
T 17 I -C•
The major inputs of the qualitative risk analysis process are the identified risks, the project ~nagement
and the scope baseline. Other inputs can indude industry studies and prior information from previous ·~
0 process : A process is adopted Jn order to Jdentify, analyze, evaluate,and mitigaterisks thfOUlhoutthe project
life cycle. ·
0 Budget : ~ere Is alwaysrisk on costingof the projectas when the projectstarts there are bound to be dal9!$ as
the project's proceeds. The method of dealing with such a change neeas to be elaboratl!d in the project risk
management plan. . •
0 Work Breakdown Structure : The strategies involvedin the project risk managementare to be to
the WBS such ashow and.when needs to be IncludedIn the projectrisk managementplan.
• 1, •
0 . Risk Register:· The frequency of reviewingthe·risk ;egister is an Importantpart in the project risk Miliacem,ent
plan.
0 Roles and Respousibllltles:When the project runs into an Issue with risk attached to it. the plan will let the
project member knowabout the in-chargeof differentscenarios.
0 ReportingStructure:'This is the same as with the roles and responslbil~lesbut briefly elaborateson the repo,tlnc
structure in the situation of encounteringa risk and In whose hands ~o the decisionsneed to lie. ·
-
4-20
All th e Identified risks are detailed down Into the Risk Register a nd a level Is attached to each·risl{
These levels are based on the likely occurrence of the risk In the due c.ourse of lhe Project life CYtfe
seriousness .
2.
Analyzing and Evaluating Riska
Once the risks associated to the project are Identified, the next step Is to analyze and evaluab!
determine their effect on the successful completion of the project. Risks should be analyzed and
con sidering the following two criteria : ·
(i) Likelihood
(ii) level of Impact
Project managers are urged to rate each risk listed Into the risk register on the scale of low, moderate; a
likely occurrence rate and low, moderate, and highseriousness of Impact rate. They can create a matrtx
out thl:?se evaluations so as to gain a wholesome idea about the risks and their influence on the project.
a Identifying Risk Trtggers
At this stage, the project manager can determine the roles and responsibilities that each team and the
members take up when faced with a risk scenario. Authoritative power is given to individuals to manage,
settle the budg ~ts for ·each risk and they are responsible for coming up with ideas and a plan for those ideas,,
the project manager in tow .
Roles and responsibilities can be distributed based on ·the department , working title, or expertise of
individual or team.
Each team now takes up their risks and brainstorms Into ideas that subdue the threats. These should
preventive rrieasures or continge _ncy plans taken by the team at the start of the project to deaease or ellm
the effects these risks have on the completion of the project.
Opportunities are most often the positive risks in the project and, more so often, these opportunities can in
neutralize the negative risks that we focus on. Project managers should urge the project risk management
through ways of the project risk management pliin to pay dose attention to even the opportunities to
risks.
5. Creating a Plan
The risks are identified, ~e possible solutions or measures are taken into account, what is left to cream
action plan for these. This action plan is the fundamental unit of the project risk management and
project manager owning this plan, they will need to document all the possible solutions to all the di~
identified aaoss the project. These plans are basically risk mitigation strategies in ploy to keep the risks at
These risk mitigation strategies will either reduce the chances of the risk being accomplished or wi~I
Impact of the risk at hand . These risk mitigation strategies are born out of the ideas belted out the brai
. session held. There are two types of mitigation strategies. They are as follows :
(i) Preventative : This strategy Is designed In a manner so as to reduce the likelihood of the risk or seri
of the risk way before the risk Is even realized.
(If) Contingency : These are planned actions In the event of the risk being realized . The risks that·are
high~ priority will need to be attended to first by the project manager and their mitigadon plans
be realized before the project starts or as per the action plan. The ris~ with a lower p(iority ~n bl
care of later, but cannot be Ignored or neglected.
Risk Identification
4,11
AS a projectmanager worldngon a new.projectIt's necessaryfor you to carry out a thorough r1sk management anatysfs
to ensure that the project is deliveredby an agreed deadllne and at an agreed cost. Risk management wffl ensure that
the core functionalitiesof the project will be deliveredand that the design standards will not be compromised.
The risk management processon a projectconsistsof four steps :
1. Risk identification
2. Risk assessment
3. Risk response development, and
4. Risk response control
_ Risk identificationis the pro~s of listing potential project risks and their characteristics.The results of riSk
identificationare normally documented in a risk register, which includes a list of identified risks along with their
sources, potential risk responses, and risk categories.
_ This information used for risk analysis,which in tum will suppc;rtcreating risk responses. Identifiedrisks can also be
representedin a risk breakdown.~cture, a hierarchicalstructure used to categorizepotential project risks by source~
_ Though the -major wortc on risk identi~cationis usuallydone in the beginningof a project. it's important to remember
that risk identificationis an iterative process;new risks can be identifiedthroughout the project life cyde as the.result
of internalor external changesto a project.
- This process involves preparing checkli~ of. potential risks and evaluatingthe likelihood that those ewerwt:s miaht
happen on the project. Some companies ind~~ develop risk checkJistsbased on experiencefrom past projects.
- The checklistscan be helpfulto th~ project managerand projectteam in identifyingboth specificrisks on the cheddist
and expanding the thinking of the team. The past experience of the project team. project experiencewithin the
company,.and experts in the Industrycan be valuableresourcesfor Identifyingpotentialrisk on a project..
Identifyingthe sources of risk by categoryis another m~thod for explo~~ potential risk o1 project. Son:'eexamples
of categoriesfor potential risks Include~e following:_ .
'" I •... I• • •· '
o Technical
0 Cost
o Schedule •• I
o Qient
° Contractual
o Political
o Environmental
o People
- The result Is a clearer understanding of where risks are most concentrated . This approach helps the P,ofect
Identify known risks, but can be restrictive and less creative In Identifying unknown risks and risks not easily
inside the WBS.
Face-to-face interactions between project managers and the team promise better and
communication . The must feel comfortable to share and find hidden or elusive risks.
2. Repetition
Information changes and appears as the risk management process proceeds . Keeping Identified risks rurrent a
updated means the system is focused on mitigating the ~ost prevalent Issues.
3. Approach
Certain objectives require distinct approaches to best combat Identification failure. One method is to Identify all
causes, undesirable events , and map the ir potential impacts. Another is to identify ~ntial performance fund!
the project must enact to be successfu l then find possible issues with each function or goal.
4. Documentation
Consistent and exhaustive docum entation leads to compre hensive and reliable solutions for a specific project
future risk management team' s analysis. Most communication is recorded by a project manager and data is
stored, and updated for continued risk prevent ion.
s. Roots and Symptoms
It is essential in the risk identification phase to find the root causes of a risk instead of mistaking them with
symptoms. A symptom can be confused with the root cause, making· it critical to discoYer the origin of risks
denote what their symptoms are.
6. Project Definition Rating Index (PDRI)
PDRI is a risk assessment tool that helps develop mltfgatlon programs for high-risk areas. It facilitates the ~•s
assessment within the defined project scope, budget, and deadlines . It also provides further detail of lndivid~I
and their magnitude , represented by a score .
7. Event Trees
Comm.only used In reliability studies and probablllstlc risk assessments, event trees represent an event folloWed
factors and faults related to It. The top of the tree Is the event and It Is supported by any condition that ffril'f
that event, helping with likelihood visibility.
Af1Sk r g u track details of the risks portant component of the risk management systffll. A rtsk register Is a
that helps yo f a project. A risk regt t . ~ssoclated with a project and address them u they arise. It rs created during
1001
earlY stages s er s used to Identify,assess, and manage rtsb to acuptable le'fflS through a
1.~e d updating process. ·
·e'llan
,evl
purpose of a Risk Register
4J2,1 .
" k......i
Of .
Tlle purpose a ns '""l!>'sterIn project management Is to record the details of all risks that have been identffiedafonf
, with their analysis and plans fur how those risks will be addressed.
Risk register identifies risks along With their severtty.'ft also outJlnes the actions and steps to be taken to mltfpte tht!
, risk. The risk regisler da ta base can be viewed by project managers as a management toot for monitoring the rfslc
,nanagement processes within the project. It Is the responsibility of the project manager to ensun! that the risk
register is updated ~enever necessary. The task of updating the risk register Is usually delept.ed to the project
control function.
The list of risks that are identified and recorded in the risk register drives the followingrisk man~ processes.
perform Qualitative Risk Analysls .
1. • I
1n the Perform Qualitative Analysis process, deta iils are added to the existing list of risks in the risk registe indudfnt
the priority, urgency, categorization of risks, and any other trends that were noticed while perfonnfng this process.
Risks that have been ·managed, avoided, or are no longer relevant can be. removed from the risk register. The-
associated risk actioo plans can also be deleted from the risk register.
In the Perform Quantitative Risk Analysis process, the risk register is updat.ed with t:fle probabifdies assodab!d with
each identified risk and the probability of meeting the cost and time projections. Additionally, risk. priorities are
updated and trends that have been observed are also noted.
.. ....
Qualitative risk analysis is the process of evaluating the potential losses to .a project from a particular risk. It is
using a combination of known information about _the situation, knowledge about the underlying process,
judgment about the information that is not known or well understood . . · .
- A qual~tive ris~-analysis prio~tizes the i~entlfied project ~sks using a pre-defined rating scale. Risks are scored
on their probabrhty or like.lihoodof occurnng and the likely impact on project objectives. . . .
- Probability/likelihood is commonly ranked on a zero to one scale (for exam 1 · •· . :.6
.k t rl ) P e, •3 equating to a 30% probal:MlitY111
ns even occur ng . . . .. .
1. Delphi Technique
This is a form of risk brainstorming. Delphi Technique makes use of expert opinion to identify. analyse and evaluate
risks on an individual and anonymous basis. Each eXi,ert then reviews other expert's risb. and a risk resister Is
produced through continuous review and consensus between the experts. ·
2. SWIFT Analysis
Standing for •structured What-IfTechnique•, this Is a simplifiedversion of a HAZOP. SWIFTapplies a~ tNm-
based approach In a ~p environment, where the team Investigates how cha~ from an approveddeslan. or
plan, may affect a project through a series of "What If" considerations. This technique is particularly useful In
evaluatingthe viabilityof Opportunity Risks.
3· DecisionTree Analysis
Similar to Event Tree Analysis,but without providinga fully quan,ttattve output, DecisionTree ~s is most often
used to help determine the best course of action wherever there Is uncertainty In the outcome of possibleevents or
Proposed plans. This Is done by.starting with the Initial proposed dedslon and mapping the different pathways and
outcomes as a result of events occurring from the Initial decision. Once all pathways and outa>mes have been
established, and their respective probabiiltfesevaluated, a course of action may be selected on a combi~tion
~e most desirable outcomes, associated events and probabllttyof success. · .
• 'hen s ,-
•••nc•• ••••
4. Bow-tie Analysts
. •d itifv riskmltigations . Bow•tie Analvsls
This Is one of the most practical techniques available In helpmg I en .
the left all the potentia 1 causes of the
looking at a risk event and then projects this In two directions . T0 ' 'bl · Id
e listed It is then poss, e to enttty
listed and, to the right, al\ the potential consequences of the even t ar · .
mitigations \or bamers) to each of the causes and consequences separately, effectively mitigating both \he
of risk occurrence and the subsequent Impacts, should the risk stlll occur.
L Better overall Project Risk Analysis : Individual risks are evaluated in the qualitative risk ~nalysis. But the qua
analysis allows us to evaluate the overall project risk from the individual risks.
2. Better Buslness Dedsions : Business decisions are rarely made with all the information or da~ we desire. For
aitical decisions, quantitative risk analysis provides more objective information and data than the qualitative a
While the quantitative analysis is more objective, it is still an estimate .
3. Better Estimates : It helps in preparing accurate estim.ates. For example,a project manager estima~ a
duration at eight months with a cost of Rs. 3 million. The project actually took twelve months and cost Rs.
million.The reason for this variation is the fact that the project manager did a Work Breakdown SuuctUre ~)
estimated the work. However, the project ·manager failed to consider the potential impact of the risks lgood and
on the schedule and budget.
Large, complex projects that require Go/No/Go decisions which may occur multiple times in a project.
Projects where upper management wants more detail about the probability of completing the pro,iect on schedule
within budget.
r.1onte carto Analysis : This technique uses ~ptlmlstlc,.most likely, and pesslml.sticestimates to determine the tDbl
'- projectcost a nd project compl~on dates. For example, we could estimate the probability of completjn1a pn,tect at a
cost of RS. 20M. Or what is a tomPi!ny wanted to have an 80% probability of achieving Its cost obtectiws.What is the
cost to achieve80%?
sensitiVitYAnalysis: This technique ls used to determ ine which r,sks have the greatest Impact on a protect.
s.
fault Tree Analysis(FMEA) : This technlq~e uses the analysis of a structured diagram which Identifies elements ttat
6,
can causesystem failure. . ·
---(With Very Low, Low, Medium, High and Very Hlih radnp for probability and. Impact}. A Simple ProbabiUty-fr,,pact
Matril(is given Here for your reference.
.
Impact
Trivial Minor
•II , ' ! '•i.
Very llkely
-
· d· ct f this risk is major, then you look
If a particular risk has a moderate probability and the estimate 1mpa 0
into
respective row and column to identify the risk rating. For a ~oderate probability and major impact, th e rfsk ·
the matrix is "Medium". The col~urs are visual indications of the seriousness of the risks.
- Risks can be prioritized for further quantitative analysis and planning risk responses based on their risk rating.
are ·assigned to risks based on their assessed probability and impact. Evaluation of each risk's importance and ·
for attention is typically conducted using a look-up table or a probability and impact matrix.
- Such a matrix specifies combinations of probability and impact that lead to rating the risks as low, moderate,or h
priority. Descriptive t~rms o.r numeric values can be used depending on organizational preference.
- Each risk is rated on its probability of occurrence and impact on an objective if it does occur. The organization sh.
determine which combinations of probability and impact result in a classification.of high risk, moderate risk, and
risk. In a blade-and-white matrix, these conditions are denoted using different shades of ~ray.
These risk-rating rules are specified by the organization in advance of the project and included in organ· •
process assets. Risk rating rules can betailored in the Plan Risk Management process to the specific proJect.
The Risk Impact/Probability Chart is based on the principle that a risk has two primary dimensions :
1. Probability
A risk is an event that "may" occur. The probability of it occurring can range anywhere from just above o
just below 100 percent. (Note: It can't be exactly 100 percent, because then it would be a certainty, not·a rblc.
can't be exactly O percent , or it w_ouldn'tbe a risk.) · · · · ·
2. Impact
A risk, by its very nature, always has a negative impact. However the · f th • . .. •
. . , s11e o e impact vanes·m.tenns of
and impact on health, human hfe, or some other critical factor . ,
The chart allows you to rate potential risks on these two di · · ·
mensions. The probability ·that a risk will
represented on one axis of the chart- and the Impact of the risk, If it
•.· . ,._ . •• • •t • • ,, .. _ • • . • ,· ' • I, , .. , a. •
0 ccurs, on the other .
- ;The basic form·of the Risk Impact/Probability' c'ha·rt':Is·sho· ·.,: · ··F,: ·,<. ··..
. · ·· . · . wn 1n 1g:-.~1~:2.
I
Low
low -------+High
Impact of Rlak
Ag. 4.15.2 : RWt lmpacttProbabllltyawt
1')1e comers of the chart have these characteristics :
(ii L0'1f impact/lowproblblfty: Risks In the bottom left comer are low level, and you can often ignore them-
Risks in the top left comer are of moderate importance - if these things ~""'.appet_,,.
(ii) L0'1f impact/hf&h.probablllty: ...,
you can cope with them and move on. However,yo~ should try to reduce the likelihood that they'll ocxur.
(iii) High Impact/low probablUty: Risks In the bottom right comer are of high Importance tf they do oca,r, but
they're very unllkeJyto happen. For these , however, you should do what you can to reduce the impact they'll
have if they do occur, and you should contingency plans in place just in case they do.
(iv) High Impact/hip probabllty: Risks towards the top right comer are ot critical importance. These are your top
priorities, and are risksthat you must pay dose attention to.
Strategies can be made to deal with negative risks. Ideally, you would like to avoid the risk. but in most cases. it is
possibleto do that all the time. Thus, you will utilize strategie.s. Some of them are
1. Escalate
- You use the escalate risk response strategy when yo~ identify risk·and find that you cannot manage it on
own because you lack the authority, resources or knowledge required for
. . a response.
- You will contact your project manager or the top management to Inform them about it and ask them to take
responsibilityof managing the risk when this kind of situation happens. You won't take any further action
to note it down in the risk register once the top management or PMO accepts your request to take NMl:nniMtll.-
for the risk.
- For example, you know that the government is planning to announce a regulation and it could impact
project negatively if approved. You have no legal advisor and other resources to manage this risk. so you
approach your superiors to handle the risk.
2. Mitigate
- You will try to lesser the impact of the risk In this risk response strategy. You can do so by either trylrW
deaease the probability of the risk happening or the effect of the risk. Th"IS st t d rttyof
.k ra egy ecreases the seve
ns .
-For example, you find that a team member may leave for a specific duratl d ri h ..-i..rt . -ar
. . on u ngt epeakofyour..,.,".-•nu
1s a negative risk; therefore to minimize the impact of his b • ,.-t1..,
. . a sence, you find another employee with Slrm-
quahfications from your organization and Inform his bo th
ti Thi ss at you may need him for your project .for some
me. s employee may not be as capable as the old employee b t h
--~-------------:------~~=•-=u::e~ca:n:co=ve=r~fo:r~th:e~o:ld~em~p:lovee::·~~
a11tC =;;;
1IIIP" ,11 11eot1t••
,,ster
~- 1"' yot.J use this strategy when you lack skllls or resources to manage the risk, or you are too busy to m-anageIt.In the
,, t(clnsfer risk respo~ strategy, you transfer the rtsk to a thltd party t.o managf! it. Though tran1ferrtng not
eliminatethe risk; tt only shifts th e respooslbilltyof managingthe risk to the third party.
for e,iarnple, in ~ur project, there Is a task to Install some equipment, and you have litde e,rperfentt wtth this
,, task- The task is complex, and few contractors have successfullyInstalled It. Therl!fore, you find a con.tractor and
ask them to Install It and sign a fixed prfce contact.
In this way, you have transferred the responsibility of the whole task to a third party, and now it. is their
- resPonsibilityto complete the task within the agreed time and cost.
,woid
4. Here, you trY to eliminate the risk or its Impact. You do this by changing your project management plan-, by
changingthe project scope, or by changingthe schedule.
This is a desired risk response strategy mainly used for critical risks. This is the best technique for at1 risks;
hOwever, it cannot be used most of the time.It is easy to use this strategy if you identify the risk in a W!fY
stage; otherwise, it is difficult to adopt this strategy because in a later st.age changing scope or schedule is a
costlY affair.
_ You will have to convince the client or your management to change the scope or schedule to use this stratelY-
You can only utilize the avoid risk response strategy after their approval.
_ for example, you observe ~at during certain periods of your project there is a chance of rain and_you have wortE
plannedoutdoors at that time. Therefore, to avoid this risk, you move these activities to a few days later to avoid
the impact of rain.
5. Accept
- This risk response strategy can be used with both kinds of risks, i.e., positive risks or negative risks. Here you take
no actionto manage the risk except acknowledgingit.
- You use this strategy when the risk is not critical,if it is not possible or practical to respond to the risk throuahthe
other strategies, or if the importance of the risk does not warrant a response.
- You can accept the risk either by actively acknowledgingit or passivelyacknowledging it. In the active .acceptana!
you keep a separate contingency reserveto manage·the risk, and In passive acceptance, you do nothing except
note down the risk in the risk register.
- For example, you are diging to construct a building, and there Is a risk that you may find artifacts. though the
chancesare low. So you note it d~wn and take no action as a response plan may cost you a lot with no guarantee
of findingan object of interest.
4,16 2 Pasitl •
· ve Risk ResponseStrategies
P<>siti • • •
ha ve nsk ts also known as an opportunity, whldfhas a positive Impact on yourproJect. so you Will always wantitto
PPen Th
not ·. e most desired strategy for opportunity Is •exptolt9which ensuresthat the opportunityls realized, though it ls
Possibleto
lisJt is r .
~nitsown. _____ __ .
__;_
.
______________~---
use ttus strategy all the time. Accept Is the least desire~ stratecv where you take no action .and hope the
___;_,____..:.:..
• et:•
T I\•
1llf' •••llc•tt••s
.
2. Enhance ,
50
- In the enhance risk response strategy you tJy to Increase the chance of a risk happening you can realize
• · y
benefits of this risk. In this case, you try to realize the opportunity . ou ca n say that the enhance risk resi:Mlli• I
- For example, let us say your project will be co~pleted in three months . You find out that the government
about to float a similar type of project in two months . Therefore, you can bid for a new project if you
complete your project in two months. This is an opportunity for you.
- Therefore, you tJy to compress the schedule with fast-tracking so that the project can be completed ahead
time and you can have a chance to bid for the new project.In the our following example, you are using
enhance risk response strategy because here; you are trying to realize the opportunity.
3. Exploit
- In the 9plo it risk response strategy, you ensure that the opportunity is realized. Here, you do not try to
the opportunity; you make sure that the opportunity is rea.Jized.
- · For example, let us consider that your project will be completed in three months. You learn that the -,-n•
is about to float a similar type of project in two months . Therefore, you can bid for the. new project if yau
complete your project in two months.
- You have an opportunity here if you complete the project ahead of time, you will get a chance to bid for
. next project.Now you have to ensure -that you realize ttiis opportunity . You take every possible measun
ensure that th e project is completed ahead of time so you can bid for the new project. You brins new
oompress·the schedule , do overtime, etc.
4. Accept
- This risk response strategy is common for both type -of risks; I.e., pos itive risks and negative risks.In the
risk response strategy, you take no action to realize the opportunity . You leave the opportunity as is, and
happens on its own, you will benefit from It. This risk response strategy is used when the cost of the ·. ·
high, and there Is less of a chance of It occurring or the benefit does not ou~ igh the effort Involved.
- For exam~le, suppose there Is a chance you may g~t some skilled workers from anoth~r ~ject at a lower
you convince them to join you. However, you do not pursue this matter and instead let them decide lllhl!IIIU •
they are intere$led in your pro ect or not. '
0,1
DescribeResourceOptimization What ·
-l
oescribeR~rce Allocation.What are Its h-......_
ua, IUlll3? {R9fw Section. 4.2 8f'ld 4.2.1)
0.8 What is a Pro;ectBuffer? What ara ils types? (Refer section 4.7 A)
Q.9 Describethe aiticaJ chain schedulingmethod. (Refer Section 4.7.7)
'
a. 10 Write a note on the slakehold8fsin Project.(Refer Secdon 4.8)
a.14 Describein brief the processes of Risk management(ReferSections 4.10 and 4.10.1)
Q, 19 Describeprobability and Impact Matrix. How'dowe use It? Describe. (fWw Secdol•4.15 and4.15.1)
----
a·22
.
.
IC!,----n4.11.2)
Explainthe positiverisk responsestrategies. (Rel9rSecdol
000
s.1 Introduction
- The project management monitoring and controlling starts as soon as a ~ro}ect begins. Monitoring and
project work is the process of tracking, reviewing, and regulating the progress in order to meet the pen
objectives. It is a very important part of ProjectManagement.
- Project Work in~olvestrackingthe actual project performancewith the planned projectmanagementactivities.It
mainly be looked as a Control ~nction that takes place at all stages?fa project i.e. from Initiation through dosing.
- This process of monitoring and controlling project work is extremely important as it can happen that you are
completethe project on-time, however,have not been able to meet the desired quality levels.
- Similar1y, your project has increasedscope, however,have exceededlimits of time and cost. The project manager
balance the requirements of different knowledge areas to control the project through Monitor and Control
wor\. ProjectManagerscreate performancemeasuresor use existing organizationalperformance measures to ·
project performance at regular intervals during the course of the project. Monitoring and controllingproject
involve monitoring any other performancemeasurethat the project managerhas .createdor used for this project.
. Project monitoring is an integral part of the project management.It providesunderstanding of the pn)iTeSS
prothJect so that appropriatecorrective_actionscan be taken when the performance de'liatessignificantlyfrom the
pa .
5.2.1 Characteristics
_ II
helps the management for the fine-tuning of the implementation activities, reorientatbi of the project
implementation by making appropriate changes in future planning .
_ without effective monitoring it is normally Impossible to judge if work is going in the right direction, whdher p,ucaess
and successcan be claimed and how further efforts can be Improved.
. .
5.2.3 ProjectMonitoring Activities
o The reporting of project status, costs and outputs and other relevant Information, at a summary level, to the
management.
• The format and tim ing of project monitoring and reporting varies ln each organization and also depends upon such
items as the size, duration, risk and complexity of the project .
• Measuring progress of project a~tles against established schedules and Indicators of~
• Id ·ty
enti ing factors affecting the progress of project actMtles
• .Measunng· th e response of the decision taken on ~he project activities and Its effect on the prc,cress of project.
irnplernentation
' Minimizi •
~g the nsks of project failure.
Inputs
The inputs to the process of project monitoring and controlling are :
1. Project Management Plan
2. Schedule Forecasts
3. Cost Forecasts
4. Validated Changes
5. Wortc Performance Information
6. Enterprise Environmental Factors (EEF)
7 Organizational Process Assets (OPA)
•• nnorl119and ControllfngProjectWortc
1. "'o
Tlle Monitoring and Controlling Project Wortt process collects,measuresand er~ pefonnatee lnfamatlon
and assesses
measures and trends to forecast potential items requiring a>rredM acdon. This includes rrolllfo,lt•
project risks and ensuring that they are beingmanasecfaccordir11 to the project's risk plans.
3. 5c0pe Verification
The scope verificationprocess ensures that project deliverables are formallyaa::epted.
4. Scope Control
The Scope Controlprocess ensures that changes to project sa,pe are controlled.
I
5. Schedule Control
The Schedule Control process monitors and controls changes to the project schedule.
6. Cost Control
The Cost Control process monitors and controls msts and changes to the project budiJet.
7. Perlonnlng Qualfty Control
The quality control ·performance process measures spedffc results to detennlne whether the prqJec:t is
I
meeting q~lity standards. 1
8· Managingthe Profed Teem i
This process trades team member performance, provides feedbadt, rescwes Jssues and coo.cllutes to
maintain and improve project performance.
9. PerronnanceReporting
The Performance Reporting process coUects and ~lstributes penonnanceInformation - lndudlrw status ,eports,
reports and forecasts.
...,....,......
*P Pl 7 Ts
Maf1891ngStakeholdere
10. rks with stakeholders to ensure that requl
This process manages stakeholder communicationsand wo
satisfiedand Issues are proactivelyresolved.
Purpose
The purpose of information needs analysis technique is to identify and set priorities for the information ~--
support businessactivitiesIn order to reach established business goals.
5.4.1 Objectives
- To identifyand set prioritiesfor the information needed to support business activities and to reach the business
- To gain further insight into the business structure for subsequent improvement of the information architecture.
- To understand the implicationsof these priorities for current and planned systems, technicalfacilities, etc., as
an enterprise engineering project.
To facilitate commitment to the strategy developed to meet re_engineering or other enterprise goals and objectives.
5.4.2 Benefits
There are several benefits to utilizing the information needs analysis technique.
- It enables us to gain further insight into the business structure to support subsequent improvement of the i
architecture.
- It enables an understanding of the implications of established priorities for current and plannedsystems and t
facilities.
- It fac1itates commitment to the strategies developed to meet enterprise-wide goals and objectiYes.
5A.3 Procedures
- Identifysource material and source interviews, focus groups, or questionnaires.
- Reviewmaterials and itemize a list of information needs.
- Consolidate needs and develop an Information needs summary diagram.
- Collectadditional data, as required, to complete the Information needs summary diagram.
Determine the relative importance of each Information need .
- Confirmresults.
- Use as Input Into information architecture development or !~pact assessment.
- -'---------:--""'."'"":
Scanned with--=:----=-·
CamScanner
5-7 projectExecuting,Monttortng& bi.__.
Prt)jeCIPAanllgement(MU)
j5 ream ava .
liability report example
ed to knoW
what resources you have available to 8tt ......
a&. I It ......
• build an accurate project plan, you ne h team member has on u,e r p a e so YOU ca,, ,,r
If you want to ·t b'llty report shows you how much work eac -'!'II
done, A team ava, a ,
--"'•rdng decisionsfor your project.
sr,,art,o;--
n 'a
rtdrr,s
I
alreadyoverdue.
L Set a cadence: A reportingschedule establishesregular touch points so everyone knows when to expect and perhlps
even providesimportant project updates. Just be sure you keep the lines of communication open between schedad
reports.
2. Mind your : A report is only as good as the Information111 It. Check that project details current and a,rred
beforesharingreports with dlents and stakeholders.
3. Write to your audience : Olents and executive stakeholders don't need to be bogged down by nitty-grittYprajtd
details.Keep it succinctwith bullet points and avoid technical Jargon so It's a friendly read for everyone.
4. Add visuals: A pictureis worth a thousand words. Use charts and graphs when possible to make your report easvto
digest.
5. Be honest : If the project is behind schedule or over budget, don't shy away from mentioning It In your report.n,e
sooneran Issuecomes to light, the sooner It can be resolved and the more llkelyyou are to win your dlent's trUSt -.
• ..... ...
u ,.,,..
- AProjectTea~ i~ an organi~edgroup of people who are involvedin performing shared/individual tasks of the projed
as well as achievingshared/individual goals and objectivesfor the purpo ·f • • ___,,,nnr
its results. se O accomplishing the project and J"""..- ..
,,ess
ful projects are usually the result of
. , taref ul pf
P Ex .
'
& r.,,,.....,....,.
Sil bers. pro1ectscan t move forward Without ch annlna and the taltnt and colla._~, .
, er11 ea of Its k l UUl".-t on of :, pr01ed's tl!.lm
111 anagement Is an Integral part ·f f!V earn members.
0
rf'I "' a Project rn
,, fe:ermines the project roles required to execute the anager's role. The p,ofttt manacer ldentlfles thf? and
d~oire team members. tasks and the ~Ifs requfred to Pl!ffowm the tast, . H'! to
a • •5 not enough. to plan resources A
aiJI it , • cqu1re thern and d ..._
" ct manager needs to manage the tea e~ate tasks to them to have a sucassful pn,fect. The
" ,oje rn such that he/sh I bl ·
P ..,ember and at the same tlrne th t e s a e to extract optimumperformance from each
1ear11 '"d e earn Is motivated t o work on the project and the project obfectf¥es are
achieve .
,-ocess of managing project team d
11ie p . t· n recognlti d a dresses specific team management challenges associated wfth
" ,onir,1un1ca 10 ,d ri on an assessment of °
t earn b·'1ectlves. The project manager takes responsibilityof manap11
projectteam an ensu ng success of team management activities.
e projectmanager should use the followingInterpersonalskllls for managingproject team :
111
(ii Leadershipis a aitical skill for teambuilding and teamwork management. A high level of leadershipallows the
project manager to communicate the project vision a·nd organizethe project team to achieve high perfc:,nmnce_
Iii) 1nfluendngis aitical for- bearing Influence on project stakeholders and their decisions. The project rna11a1er
needs to develop this interpersonal skill to reach mutual ~greements with project team members and addless
critical issues.
pii) effective decision making is an ability to undertake the decision-makingprocess which entails conduaing
negotiations with stakeholders and project team for ihe purpose of studying environment factDrs, dewiopil,g
personal quality of team members, stimulating team aeativity, and managingrisb and opportunities.
'!he process of Team Management involves the use of specific project team management methods and techniques
which are listed are as follows :
L Method of communication and supervi.sionis used to track current wortc and attitudes of proiect t2am members. By
means of live conversation and observation, the project manager communicateswith team members and rftiews
their achievements in the mntext of delivefc!bles
, accomp.fishmentsand interpenonal issues.
2. Method of performance appraisals allows measuring performance of project team members to darify project team
roles and responsibilities, ~eview corutructive feedback, discover unresolved issues. ~op individual traini,w
I programs,and outline specific goals for future project activities.
3. Method of conflict management allows handling conflicts in a team environment to achieYe higher productMtyand
positive working relationships among team members. The method Is used within·the conflict managementprocess
and managed by the project manager. The followingcharacteristicsof conflictshould be consideredwhl1e perfannirc
the conflictmanagement process :
(ii Nature of mnflict : A conflict may be a team Issue or an IndividualIssue.
Iii) Opennessto conflicts.
(iii) Time : A resolution of conflict should focus on the present not the past.
The followingoutputs can be obtained from the successfulproject team manacement Pf oc:ess Implementation:
l Change requests are generated during the course of the process and submitted to the project ~t team.
Change requests allow reducing the probability or Issue occurrence and mltlpte a ~alive Impact on project
activities.The major purpose of change requests Is to ensure development of prevenuve actions to reduce team
absence, achieve appropriate role dariflcatJon,and avoid gaps In project schedulesand timellnes. , , s : : -
• a
2. Perfc,nnanceTracking .
ber He should be aware of which tasq
The project manager needs to track performance of each team mem · ._
f rf nee The team member should be ...._
done by which team member, the status and level o pe orma · '""' ·
appropriate feedback. If the resou rce Is doing well, appreclatin~ _In front of other team members boastsa,.
morale an~ inspires others to do well.
- If the team member has achieved a major breakthrough, an award or and an appreciat ion mail keepingSeita,
management informed.will also motivate the team member . Performance reports that measure the Pl'08n!lrd
team members using time, cost and quality parameters should. ~e generated regularly. This will help
performance over the course of the project.
3. Handling lncompeter_,tPerfonnance
- If any team member is not doing well, concrete details with examples should be given to him as to whJle
manager thinks he is not doing well. Other team members can be asked to assist/guide him in some tasks.•
team member can be given other tasks which he may perform properly .
- If the resource is not performing well for a long time, it may be best to release him from the project. A
meeting with project team members on their performance can be used to share co~structive feedbact.'Ille
.organization's performance appraisal process should indude the feedback from the project.
. .
4. Training
- Trainingis a useful motivational tool. Appropriate training needs must be identified for resources and ~•
per organization's criteria. Training in new skill sets, new technologies act as a canot to motivate e~ployeestD
give their best performance.
- It helps in talent management. Team members · ~ho show potertial leadership skills can be given-trainlllkl
leadership courses. Employees with high techn ical skills can be sent to technical trainings and wortcsh,opsGIi
architecture and design so that they can groomed to take on the next level challenges. ·
5. ConflictResolution
- Each individual is d!fferent and there can be issues and conflicts between team members. It~ not "~fc,
team members to be the best of frien~s but they should work towards achieving project objectives . and act as..
part of one team. Project managers should anticipate conflicts ·and disagreements beforehand and take·stePSto
avoid issues.
proJect Communication
8
,, ~munication is a aitlcal com ·
1/,euent comr ponent of project success. In fact. according to th~ Project Man~
, £~ ·cute (PMI), most project failures are due to c:ommunlcatfon problem,. Profttt c:ommunlcatlon
1nstt that does not happen. •
ensures . .
nsistS of three processes th at help make sure the right messages are sent, re~d, and understood by the "8ht
11 cO • d d d
ople. lhe processes '" u e In this area have changed over the years, but In the current venlon , there are three
r'.rnarYproject communicationmanagement processes.
pfl
'(llese are: .
plan communications Management
1,
Manage Commu~ications
2-
Monitor Communications
3.
p1an Project Comm~nicatlons Management
5t1
llle first step is to plan how you will manage communicationson your project and acrossall of ygur stakeholders.
• . done by creating a project communicationsmanagement plan.
5 .
it's important to ensure the followingfactors are addressed in your plan :
(i) Audience : This is a list of all stakeholders affected by the project. It should indude team membe s, spoc
customers, and ·other interested parties. Consider ~ryone impacted by the project or who inffuences its
success.
(ii) Objective : Identifythe objectives of your communications. You may use some communkations far awaa e,ess.
like a status report, and others that require action, such as requiring a sponsor to aulharizespending. or a
customer to approve project testing.
(iii) Message : Decide and create message for each type of communication. This is the act1Jal content that will be
shared. Key components to be communicated indude scope, schedule, budget. objectives. risks. and deliverables..
(iv) Channel : Choose the right channel through which the message will be delivered.• WiU it be. a formal report .
emailed out? An informalverbal debrief duringa team meeting ?
- Your communicationplan should be detailed enough to lay out exactly what will be to whom, how, when. and
who is responsible. Involvingyour stakeholders in the aeation of this plan is.important. You need to their
communication preferences and expectatl<>!15•
Once the plan has beena~ted and approved, It's the project manager's Job to ensure It's rnanaiged well. This means
th .
t e plan needs to be reviewed and updated on a regular basis to reflect any cha~es to the project or its mbhokle,s.
Theprojectmanager also has to managethe executionof the communicationmanagementplan. .
This indudes :·
1. Strongactive listeningskills
2. Proficientwritingskills
3. Excellentspeakingability
4. Askingquestions and probing for more information
5. Settingand managing expectations
6. Motivatingpeople to become and stay engaged
7. Conflictresolution skills
8. The abilityto summarize and recap what you have heard
...,..,,,....,
team member should know what needs to be done before they get started on their task. __.-:-
"",,_,
.._,
·1th camScanner
scanne d W
,cal s J you say you
i,c nicat1on In pro ect management-don'tov are going to deliver. And remember th
r11rfltl erprom1se1 • e cardinal rute of
, ,o hef1 r,eeded : Just like most things I llf
,Adl"st : ith your team to adjust on the fly ....Ln e, a project ProbablyWon't go like you pla
,,est ... ""'" needed .
11_
n. DIC
n-,
c,uu e enough and
..,rflunlcallon Methoc:ta
CO••·
9.6
~- he organlzatlonaland geosraphlcal div
Given 1' 10n Today's enhanced technoloav all erslty of project teams - It Is Importantto consfder all methods of
1111
jc,J • DF OWs us to co I
r11 • ation strategy should be con~lved at th mmun cate easily whereverthe team members may •e. A
1,o111r1111ri 1
' e project plannlnsstages, so key Is Its Influenceon the sucuss or the
·&·
f' ,,1cat1onmethods can either be active or n.••tv .
~u
Co Ecommunicationmethodsbeing th ·
~CflV ose used to communicateIn the here and now, fOf examplethe use of:
face to Face meetings
_ Video conference, meeting - one on one, or group
Telephone conference, or voice only web conference
_ Webinars, becominglnaeaslngty popularfor the deliveryof presentation based activities
Telephone-good old fashioned call
stand up presentations In person
i pASSIVE communicationmethodswould be those which recipientscan adopt in their own time, for example:
Pod cast
_ Web cast
_ fmail
Intranet bulletinboards
Biogs
Website
- Project newsletter-paper based
- Table top presentation
Always ensure that a ml~ of actJve and passive methods of communicatio~Is used to complimenteach other. This
should be considered as part of the overallproject managementcommunicationstrategy.
ProjectMeeting
· Project meetings refer to an effective method to distribute information and communicate wi~ the team and
stakeholders.
• AProject Meetingis a resular event that Involves everyone, who shares or Is interested in the project. in
communicating with other participantsand stakeholdersby discussingIssues, makingproposals.approvingor rejecting
offers, for the purpose of generating group dedslons that contribute to quicker project delivery, accordinato the
Planned goalsand expected results.
~
~rse of the project implementation process. Regular(dally, weekly, monthly) meetingsare scheduled and itemized
therr......
~m unfcation management plan. •
·
' . .w, • -
7 0
r•••tc•lf••s
L ~dcoff: It presents the project goals, Introduce the participants, and decide ~n certain logistical uestior the-ti
time a team gets together, the project spansor usuallyspeaks to them and generates e~th • . q 1S;
2. Pia ni It d • us1asm.
n ng : evelopsthe project plan; assign rol d . .
carriedout. es an responslb1llties;~ake decisions about how the projectwl be
7_ Start and end on time : If someone is fate for a meetin& begin without him or her. Don't punish the wfto mme
on time.
l Record brainstorming Items or other Important information on a flip mart to keep ideas In front of peopie and ID
stimulate discussion. Transaibe these notes as part o! the minutes ~s necessary.
.
. tum : This helps keep the disaJssions orderfy and ensures that weryooe•s Ideas ill'e
!. Ask each person to speak fn
heard.
lO. Keep the gr~up focused on the purpose, objectives,and agenda.
IL Recap the meeting : At the end of the meetin& review the decisions,accomplishments.and action plan ID make s..-e
every decisionwill be carried out by a particularperson within a particulartlmeframe.
l2. Provide meetingdocumentation to participantsas soon as possibleafter the meettn,.
Meeung Documentation
d Taking the minutes at the meetings of the project team often falls to the administrativepn,fesskJnal
R~nta tion should-be brief and to the point. In most cases there Is no need to keep details of all of the d1samions..
tord the d ..
actM . eos,ons that the group makes and an action plan of what will be done by whom, aod when and how these
tieswin b ,
in111 d. e measured. If the group generates a 11st of Ideas, record them for future reference. Om.date the document
e lately Ad . .
new tasks to_t~e master plan.
. . .,. in t I~
,011011.!.
- Providesan 'Ear1y Warning'signalfor prompt corrective action. The types of signalscan be the following:
(i) Bad news : Holding on to the bad news does not help. The project manager needs to take an immediate acliil.
(ii) Still time to recover : In case, the project is not going as per schedule and may get delayed, the situadala
needed to be taken care of by finding out _the reason.sthat are causing delay and taking the requiredcomdllt
action.
(iii) Providestimely request for additional funds. Whilethere is time to recover, the need for additional rm,rG!Sci
funds can be escalated with an early warning.
o It allows'rolling up' the progress of many tasks Into an overall project status.
o It provideswith a uniform unit of measure (dollarsor work-hours}for the progress.
There are three inputs to the Earned Value method. Each of these variables must be obtained from each task's_
progress:
1. Planned Value (PV) is the planned expenditure of funds to the date of analysis, taken from the project $chedUle-
example,if a task is antldpated to last from January 1 to January 10 and today is January s, PV = SQ% of taSkt,udglt
5_10.2(c) Analysis
calculations give the followingmeaning ·
_ Apositive CV means theproject is under budget (positive= good). Negative means averbudget. The CPf Ids JOU how
much above or below the budget -it is, in percentage terms, for example, CPI = US the project is 255 below
budget.
• Apositive SV means the project is ahead of schedule (again, positive = good) . Negative means behind schedule. The
SPI tells you how much ahead or behind schedule t!Je project is, in percentage teffl1S, for~ 5PI = 0.9 meansthe
projectis 10% behind schedule.
The variables tell you where the project Is right now or at the point of analysis. This Is~ useful for decision
ling. The following three metrics tell where the project was trending.
1 .
Estimate at Completfon (EAC) : This fs the estimated final cost of the project. There are~ ways to calculatetNs.
based on the assumptions that are made.
- If Past project performance is expected to continue :
RAC = BAC/CPI
- If
Past project performance is consldered one-ti~, and future performance will to the~ rate :
= AC+BAC-EV
ETC = EAC-AC
3. To Complete PerformanceIndex {TCPI) : This value tells you how efficient you need to be to complete the
according to the original plan. For example, If you were inefficient at. CPI = 0.9 thro~g~out the first ~rter
project. a TCPI = 1.03 means you have to pick it up and be 3% more effiae~t than the onginal plan to _finish on~
TCPI = (BAC-EV)/(EAC-AC)
- These forecasts could be used to update financial metrics such as Net Present Value (NPV), paybackPl!l1lit."°
Return on Investment (ROI) whi ch were used to justify the project .
- A project lasts for a fixed period of time which could be a few weeks to several years. In some cases, for~
construction projects or publi c works, they are run for decades. To track progress along the way and e~1helly
deliverables are being achieved according to the timeline, project managers use Milestones :
- A Milestone in a project signifies a change or stage in development. Milestones are powerful components in .._
management because they show key events and map forward movement as per your project plan .
- M ilestones act a.s signposts throughout the proj ect life cycle ensuring that the project stay on track. Withoutpnta
milestone tradting, you are just monitoring tasks and not necessarily following the right path in your project:
- Milestones can do more than just showing progress. They can help you communicate about what's happenlnc11111
your project.
(v) Other fixed points in time that need calling out specifically
2. Timing : While it Is Important not to present milestones too frequently, It Is also Important not tu SPiCe them too ~r
apart• Th"rs will cause your staff 'to lose momentum and motivation. Ideally, try to space milestones so they l.iind
approximatelytwo weeks from each other.
l, Virs,"bility. p
d . sure that their team Is aware of each milestone by dlstributfns the necess.1,y
• roJect mana1ers should be
etarls to h ·
~ac team member and keep them displayedprominentlyIn the workplace.
• ,-=er : .-
.... , •...1.
Key delivertes
- Qient and stakeholderapprovals
t meetingsand presentations
- lmportan timeline
Kev dates or outagesthat may impactyour
2. SpotlightImportantdates .
It's importantto keep all of the importantevents in mind when you are planning a proj~ because they a>Uld AGlffr
- ·A change request is a proposalto alter a product or system, often brought up by the dlent or another team ,nembef.
Duringa project,this can happen when a client wants to change or alter the agreed upon deliverables.
- Duringa project,a change request can often be met with dread. But the fact Is, they are a reality in the businesswortcf
and often, change requests are submitted for legitimate reasons. In our constantly changing business envm,nrnent.ll
Is impossiblefor anyoneto reallyknow exactfywhat they will need to achieve their objectives at the ~rt of a proJed,
- So the best way to handle change Is by managingit rather than avoiding it. Although teams should resistun~ecessaiY
..... ...
chang_es,_It is important to stay open to new opportunities that could bring more value to the projed and
organization.
,...........
1. Requestfor supportingmaterials
_ The person who is making the change must be as specificas possible.Ask that pe,scn to put bis~ in wrftin1
and provide any supporting materials that might be helpful. ·
l
I
•
I
- Have that person articulate his request for the change and the antidpated benefit of the m..,.erequest is. This
will help your team determine whether or not the changerequestis worth the t!ffort..
!
2. Determinewhether the change requestIs In Insideor outsidethe scope
t
Il
- chooses tD implement this
It is a good idea to consider what the scope of the change request Is. ff your tNffl I
change, what new requirements will thl.s put on the project? You should consider~ aspecU of the pn:Jjectthat
will be impacted by implemenUngthis change request.
,J
- If the reque~t is outside of the scope, a lot of problemsmight end up popping up such as acing CM!f'-budpt«
I
having to waste too much time on the project.
l
3· Assessthe priority of the changerequest
I
- Before your team Implements any changes to the project you should considerMY pcmlbie risks. What Is the
expected benefit of the charigebeingproposed?Is this change requestthe result of an Ktua1 need to respondto
a change in the martcetplaceor would It simplybe nice to have1
- You can consid~r the opinion of the person who proposed the change request. but at the same time, use
common sense. The dient might not know what's In their own best Interests.Have dNlfy defined auidelmesfor
~ uating the urgency as there may be varyingopinionsamongstteam members.
T ti S V
• ,,auc•tt•••
P _._. the change ~uest d understand the impact it will have on the~
4.
1'1'P'°"9Of •~·knoW hoW Importantthe change request Is an
_ NO'# that you . rejectthe request. oval process• General\v,a~
am can e,thef awrove or bout the appr l'tai...
the te will have differentways of going a within the team. Whereas a change r~
Differentorganizations be apPfOVed I ~'tt
·11 .....,ulre minima\ additional worlt can \re eiecutiVeapprova .
that "" •~-. 1work mav requ
would req1.11rea month's worth of addiUona
Decideon a course of action goingforward ·11 need to be updated. Th\s can lnductt._
5. ro}ect deliverablesw1
th . --
If the change request is approvedthen e p ·rements documents.
d nts and the requ, .
and schedules,businessprocess ocume ' can communicate the new course of 111
theSe updates have been made, the project managerh cessarv tasks to the people in C-.
- Once delegate t e ne · CII
everyone who will be impacted. Now you can .
implementingthese new changes.
0
Does this changerequire an inaease in funding?
0
Even though this changemay have a negativeImpact on this pro~ect,does it result in significantbusiness·upsides
that make itwonhwhile?
0
Does enacting this change now make more sense than delaying it? Will the delay end up costing the. CDffllalt
more money In the end?
o Have all the affectedstakeholders been considered, and do they endorse the change?
o Are there contractual ramificationsto consider? For example, will commitments with outside be
unfutfilled becauseof this change?
- The answerto these questionswill hetp approveor rejectthe change request with complete certainty.
- Scope aeep Is a situatlonwhen a project stretches far beyond iu originalvision and deadline. Scope ~p is one ti
the biggest causes of project failure. It usually starts with a small change request, iust a minor readjust;mentof die
projectscopewhich ls followedby one more request then another and another.
- Beforeyou know the small change turns the prolect into a different shape altogether. Instead of five delivefableS.you
now have 15. But the budget and the deadline are the same.
- So, SC0pe creep refersto small, continuousrequests that stretch the project beyond its originallydefined scape.Sint!
these change requestsare often small, they tend to "aeep• up on the scope. Hence the term usedis •scopetree(_:-.
..
•wJd - ·., ....
• ••'"'
·th CamScanner
scanne d w,
r
·eC! M80898 ment (MU)
5-24
. 5
~es of Scope Creep
surface.
Not agreeingon how to handiechange : If you haven't agreed on how to handle change at the tJea1minfof~ profect.
J. it only makes sense that it's going to be difficultto work through changes in scope at a later date.
s. poor Estimation: Estimationis very difficultto get right. It's a challengeto be actUrate at the beginninaof a proied.
when there are many unknowns.Certain things may not get accounted for, and you end up tied to this ema·sr:ope to
be able to deliveryour overall project.
. '
9. Not evaluatingnew requests: It's easy to take on new requests or ideas from clientsor team members.befieW11that
they are the right path forward. If you don't evaluate these requests propertyyou could end up ~tir• new sms-.
duplicating work or buildingunnecessary features without noticing.
10. Not involvingusers early enough : Many projects go to the final stages before actuallyputting it in front of r&I users.
It's tempting to fool ou~elves thinking~at we know the users well enough to avoid interacting with them. If you are
not incorporatinguser feedback early on, you can go far down a route that doesn't test well with users. At that pctnt.
your scope can suddenly spiral.
s. Ernbrace it Work out what's necessary for a testable, usable product-If that muns chanalncscope. look.atways to
incor
Poratethe changes.
I •
. .
Scanned with CamScanner
projec! Executing, Monilortno&
5-25
!. pro~ Management (MU)
parts of work is crucial for delivering a quality producton time. Make sure you have a justificationfor sayingno.
- Project Audit is a project evaluationtechnique designedto determine ,he true status of work performed on a proied
and its conformancewith the projectstatement of work, includihgschedule and budget constraints.
- It is an Independent and structured assessment of the state of affairs conducted by a competent examiner.8f
inference or extrapolation,it providesinsightinto the work needed to meet project objectives and the adequacyofthe
scheduleand budgetto do so. In addition,it can illuminatemistakes that can cause project failure and thus can trfaer
timely correctiveaction.
- A project audit is a project of its own, and as such, no one ·site fits all. It takes an experienced and knowl~
projectmanagerto conductan audit from beginning to end, and to adapt it accordingto the environment.
Project audits can help identifywhen a project is about to go off-course.In addition, a ~roject audit can providethe
followingbenefits:
1· Improveproject performance.
2· Increasecustomerand stakeholder sati~actlon.
audit team ~ives full and uninterrupted accessto all required information,~ and
. duringtheir audit. This indudes emails,and documents developed by the project team. Having everythingat your
makes it easy to answer questions whenthey arise.
#1pS .
When you conduct an audit, determine whether the PM has addressed the key items in each phase M the project
_1 This includes : ·
~1'\ve· I'
Initiation Phase tt
1.
l
_ identifythe main objectiveof the project.
Write the project charter.
_ Get sign-off on the project charter.
2, Planning Phase
After you complete reviewingthe InitiationPhase, review the actual project plan or Wort BrealcdownStructure(WBS).
You should focus on how well defined the WBS is and how well and dependencieshave been scheduied.Make,
sure the planning is sound. Failingto plan is planning.to fail.
- Createa Project ManagementPlan.
- Establish project deliverables.
- Write a scope statement.
- Determine a project budget.
- Distinguish project activities:
- Work out a schedule.
- Determine specialskills needed to complete plannedtasks.
t ExecutionPhase
Once the planning phase has been reviewed,the executionphase reviewtakes place. Many projects suffer from sa,pe
~eePdunng
·
this phase. Has the project team stuck· to their scope? Poor communication,misunderstandingsand lade
Ofinforrn . •
~ •on may have caused issues.
MS I Py
•
pu
t together the projectteam.
Administer and guide the pro e
I ct team
.
status review meetings.
conduct
lcate project Information.
--~Id
- t qualityassurancemeasures. - roc;e<turesare wo escn -
- lmplemen nd the correctionP
Make sure the control measuresare sound a
4. controlllng Pha58
Measureperformanceagainst the plan.
Evaluatethe correctivemeasures.
_ Manage change requests.
0
Document lessonslearnedduringthe project.
0 Archive projectrecords.
0
Formalize the dosing of the project.
o Release project resources.
-
o Write final Statu s Report.
In general,you must try to understandall the processes.How well suited is the methodologyto this particularIRIIIU
Are all the processesrequired in place? Did they miss anythingfrom the methodology that should be there 1
I
5.14.3 Phases of Project Audit
~~velop the questionsso that they help to lde11tlfv the major project su~s; the major project issUes, concerns
d challenges'. how the team worked together; how vendors were managed; how reporting and meetin&S -
handled; how nsk and changewas managed,etc.
0
Risk Logs
0
Issue Logs
0
change Logs
• Review the Project Plan to determine how the Vendor Plan has be.en inc~rporatedinto the overarlproject plan.
• Interview selected Stakeholdersto Identify and determine what their expectationsof the project had been and to
identify to what extent their expectations have been met.
_ Review the Project Quality Management and the Product Quality Managementto identify the issues, concerns and
challenges in the overall managementof the project and to identify the opportunities that can be, realized through
improvements to the attention of project and product quality.
- Identify the Lessons Learnedthat can improve the performance of other future projectswithin the organization.
0
PrimaryProcurement
o SecondaryProcurement
-' .
electroniclra"5ml
'f!r.'M~ ~ purctiaslngdepartment
r6 needeci!or a butlneti
..,
: liafIs' received,
.. ,are -ierffied.The I
:received from vendor.·
,._-,;,., ' . 'I.'·:.... <-, -: ..... ,
. .. .' ....
atloflof the invoi'ce ·
~i~tled: The ven.dor i
~-1.....~~.. • . 7 .. ..
- ~ -~r .. .,~~ ;_,,.,. ,.
1
5.31
I5 for dire .
be,:s
ct consumption , i.e., it 'Will
.
_, projectMsna~m en
(MU
-ptlon : When the pro sumptlon purpose. To order a material
curement . for c, Ill...
d consu..,
"I/"_
rement for D1re houfd speclfy the con '
procu d the user s ystem,
as It Is receive ' d within the s
as soon h ea master recor
the material mav av .
al Procurement I Procurement . .
fdernal and Intern f E ternal vs rnterna . from external vendors. There art"'
2. the difference o x d or services ...,et
followlng points show f rocurlng goo s . g component of the TT system.
The t . It Is the process o P b the purchastn
Erternal procoremen . t generallysupported y e ordered irregularly. . .
of externalprocuremen Ices that ar
basic forms lfy used for materialand serv d . For materials that are being-Oht..... ..
time ordersare genera f lease or ers . . -l!f
(I) one· . with the subsequent Issue o re . h the vendor (seller) for pricing or~,
(fl) Longer-termcontracts negotiate deaf wit
regularly and In large quantities,we can J pecify the validitydate.
rd then In a contract.In a contractyou a sos J • If a material is ordered on an everydayt....
reco I
schedu es . 9lllll
Internal Procurementis process o ge . em with separate Balance, Profit & Loss Stat1!fnents1o,
these companies maintains a complete bookkeepingsyst .
that when trade occurs between them it wiff be recorded.
secondary Procurementis the stocks that are managed differently as these stocks ~o not bel~ng .to the tontpaay.
They are kept at some particularlocation.Secondaryprocurement is divided into the following categories ·
1. Consignmentstocks : Consignmentstocks are those materials that •are available at the store premjses but it.SIi
belongs to the vendor. ff you utilizethe material from consignment stocks you have to pay to the vendor.
2. Third-party processing: In third-party processing,a company passes on a sales order to the associate external VeTICb
who sends the goods directly to the customer. The sales order is not processed by the company, but by the,vendo,,
Third-party items can be entered in purchase requisitions, purchase orders, and sales orders.
3. Pipeline handling : In pipelinehandling, the company need not order or store the material involved. It is obtaioable1S.
and when required via a pipeline (for example, oil or water), or another style of cable (such as electricity~ 1he
material that is consumedIs settled with the vendor on a regular basis.
4
• ReturnableTransportGoods: The Company orders goods from a vendor. The goods are delivered with red
~ansportpackaging(pa/lets,containers)that belongs
return ,t to the company. .
to the vendor and Is stored at the customer premisesuntil tho!
s. ::b;t•ctln1: The vendor or the subcontractorreceives components from the ordering party with the help Ii
'' t produces a product. The product Is ordered b
required by the vendor to m 8 t h y your company th rough a purchase order. The components
anu,ac ure t e ordered product are 11st d I h . .....
subcontractor. n t e purchase order and provided to u~
.e
6. Stock t sfi . .
ran er usingstock transportorder : Goods are ro . .
good~ Internallyfrom another I t ( . p cured and supplied Within a company. One plant orders the
P h . - Pa.I) receiving plant/Issuingplant) Th . ,• f
urc5 ase
0
order1 the stock transport d Y • e goods are proc~red With a.special typ~. o.
tran or er. ou WIii be able to requ t d . ck'
· P rt 9rder, es an monitor the transfer of goods .with a sto
~ I
nv projects and lnfrastruct
E11erY a from software c ure Works are 1Jndtttaken
,,. es ranging , onstructlon, telecom a<rcns the world. These pr-oJt!(.t! are of dlffl!T~
rYPd vendor/seller/s upplier In common. , to scientific, and oll & 9a~. Every proJl!d ha, ,;ta~ hold'!O/dl~ts
an
t,er words, every project Is lnltfated b
111 ot J Yan organization with th h
,,. rement. In pro ect procurement mana e elp of suppllersfor the various Me~ of thl!
,ocu sement, these twO 1
P h agreement between the two Is c II d h part es are senerallytermed as 'boyer.' a"d the ' ~le,'
a11d t e · a e t e #contract."
cts are an essential part of procure
contra ment management It t I
,,. contracts are necessary for project . crea es a egal binding betwttn the buyt!f and the
5eUer. ,:nanagementas they providereliefon either side
. rTlanaging the risks Involved In procur ·
,,. 11 is "bilities in completion of the j ements. A contract Is required to share and bear the individuar"s
,esponsr pro ect. This Is more so In larger and complexprofects.
contract Manager
5,16,1
The contract Project Manager plays a very criticalrole Project Contracting. He/she manages contracts throughout the
·ects and their life cycle. On ~any occasions, he also plays the role of a llaonlng person between t'-- eotrrpa.•
. . . I~ I~
ernplovees, venddorsT , hcustomers. He creates the contract's repository and is solely responsible for maintaining all the
cot1tractual recor, s. e company uses these records for their projects, whichfinallybecomepart of Record ~agement.
5
p0nsibilitles
.
oraft, develop, negotiate and execute the contract.
_ Create policies and procedures to the contract and ensure the effectiveness.
o t /on of procurement
o Loca . I ontractors t .
0
AVallablllty o f suppllers c J ct undertaken . The fo lowtng•re~
.
Local govemrne reg
ulatfons f ntract sulta ble for the pro e .
'"'-
'I'\
o di the type o co
These guidelines assist in decl ngp o}ect Management.
of contracts generallyfollowed In r
The prices of the gdbdS and services a~e set and are never subjected to change unless the scope is~
and agreed mutually. This type is favorable mostly to the buying organizations . Because theextentof~
the goods remains vnchanged .and r.ecurri'ngbuying happens.
{ii) Find Ji.riceJncentrveFee .(.FPJF)
The price ceiling is set, and the .seller needs to perform and fulfill the contract requirements ~ithtn thatpricz.
Art the costs above the price-ceiling are the respons ibinty of the seller . This type gives both the
buyerandtht
seller some flexibility for performance with technical incentives'. The incentives are tied to achleving_
agrttd
upon metrics such as cost, schedule and technical expertise of the seller.
(iii) FfxedPrice with EconomicPriceAdjustments (FPEPA)
It is suitable when the contracts are executed In differentcountriesand payments are made in a diffett?t
currency. Also, if the seller's work lasts for a few years (3-5 years eneraliy) this contract Is fitting.Thls
8
contractgives an option to make adjustmentsIn the predefinedfinal payment as agreed to in the contract
due to changedconditions·such as Inflation rates . ·
2
· Cost ReimbursableContracts
' . '
atlhis
ongtype
withofacontract
pre-defiinvolves
d f cost reimbursementfor lhe costs Incurred during
· ~ompletlonof the contractual·Jof1, ItIS
-- cha~ge d~ . me ee
. . the. co'!tr~ct representingseller proflt. It Is recomtnended If the scope·of ·1h1> work Is·
Period. .
3· flliS a hybrid type of contra~ combining the features of Fixed as well as Cost Reim~ contracts. This is ofte-n
used when contractual requirements (scope) is not known/ prescribed. Also, this type of contract is suitabte for
,quisition/hiring of experts, project staffrequired (or a parti cular period .
a •
I
• project at hand requires skills that are beyond the capabilities of a business's_current employee,.
_ project outsourcing has been proven to improve core· business competency·and helps compa11ies.artbad: on c:apitaf
expenditures, since the too ls needed to accomplish the proj ect are already provided as oppose to porchasingnew
ones.
_ Hence, if you are a business owner and you would like to optimize the productivity of your enterprise without f
expending too much, the project outsourcing servicescan definitely help you occ.ompfishsum goal. t
A
- Process outsourcing by lrnfustries around the world has seen considerable growth from duriRg wt few decades. It
started with busine_
ss process outsourcing and now has reached to knowledgeprocessoutsourcing.
- Surprisingly, outsoorclng of project management sefVices is still in its Infancy. Judgins from the- growth in outsourcing
of other business processesthere seems to be very good opportunity for project managementoutsourcing.
• Some organizations have successfully outsourced their project control functi~s to outside vendors. The main
challenge in the growth of project management outsourcing is In acceptingproject control as a separate function and
indelegating this to other departments or vendors.
• In the past most outsourcing that has been donehas been In the IT sector and a large ~rt has been for project-based
assignments. For theser project management was an lntesral part and was. lnduded as part of the scope of. the vendor
or service provider. Considerableimportance is-given by clients and the serviceproviders for project management.
Many clients view project man~gement skills of the vendors as criteria before they are awardedcontracts. So when an
outsourcing a . . _ dor &or examplesoftware development,project manasementrs considered a
Part ss,gnment ts grven to
. a ven
. • . 1
0 A service provider outsources a part of Its project management functions to anol h er vendor or ser,,ice
o Project management functions are considered separately and award ed as a separate asslgnrnt~
organization. , ._
I,. Cllent
Within an organization
Pros
- Clients can focus on core competencies
- Vendor can ensure that best practices are followed and can provide latest trends in specific sectors
Cons
- Commitment and resources requ_
lred internally, even though external resources are used
- Because ownersh ip of resources does not exist with client, vendor can discont inue the relationship
0_1 Explain the characteristicsand advantagesof Proie<?t Monitorfng. (Refer Sections5.2. 5.2.1 and 5.2.2)
o.2 Describe Project monitoring& controlling process. (Refer Sections 5.3 and 5.3.1)
o.3 What is Information need of a project? Describeits objectives.(Rifir Sections5.4 and 5.4.1)
o.4 Explain the reporting of information. Describeany four types of report. {ReferSecttons5.5 and 5.5.1)
a.9 What is project meeting? Explain Its planning steps. {ReferSectlo~• 5.9 and 5.9.1)
a. 20 What is Project Cont~cting?Describe the types of Contracts.(Refer Sections 5.16 and 5.18.3)
.sy}~~11us,
1ntrv<'
•
,r::::~=-:------------~=--------
_,111c1ion to ~rojectleadership, ethics1
n Prolecta, Multlcuttu 1
, acceptance; Reasons of pro),.,.. ra and \llr1ual proj9Cta.
c11$101118 • ""'' termination VarlO
rntion, Starvation), Process of project ' ua types of projee11ermiMllons(Eldlnclon Addle>
1te9 termination compl81ln fl ' '·
11~001"1edging successesand failures· Project ' g a nal report; doing a lessons teemed .,,.,_ ,
:i _ f further study. ' managementtemplates and o1her r8SOUIC8I: M8MglngwlholJt _ __: '
Are~~ o _..,. ,., .
project Leadership
~~~~~--=----:----------------
, !ea3ership is ~lie ~bility to establish vision and direction, Influence and align others towards '6mmon
"'""' ' and inspire people to achievesuccess. · - ...,
_ project leadership Is the.act of leading a team towards the successfulcompletionof a project.Projectleadership_ .
,,ms in both managementand leader>hlp.It Is a soft sk111. _.,
_ teadership for long has been growing in relevance and importanceas more
and more projects are betns delhered '"
more complex and uncertain environment. The role of leadership In a ·project is to promote me ·ect 0 •
encourage pos1·t·1ve reIatIonsh'1ps, support effectiveteamwork,raise morale,and empowerand,lnspireindMduals.
PfOJ b;ecriYes.
An effective leadership: ·
o Set standards of behaviorand performance
o Motivate the team members to high performanc-eand
o Rally the team memberswhen the project has,problef!lSto overcome.
111!"'_
•
.lJI proiec1
Mana ement MU)
Ject planning : The crux of advance
d project managem
fit the frequency of scope chan.ge can eithe,
--.-i"
ent and strategic leadership lies in !I"_,~
\
teslc pro J ct th t poses no bene , . redo~
3. stra II no one would take up a pro e a . ct leadership skill lies in striking a balance' ~Ot
•ect Wh e j t A popular proJe
pr<>J • h benefits or doing a particular pro ec · b efits. This is why seasoned leaders PQfl
I crease t e I th lines of long•terrn en • Pl'Olit...
n . fr sh challenges and thinking a ong e . fts . demand and acquiringa scalabte~f "'l
seeking e . ss InvolvesIdentifyingvolatileshl in . °'It.
portfolio strategically. The proce thods of managing projects are being swapped in favour 0f
..i.•ng MilestoneDelivery: These days traditional me s is Rather than having to wait till the.,,_, ..
4 rra~1 . . . h . 'ble a project's progres . . - , ••
. liverf·And the biggest advantage IS in ow v1s1 ro)ect leader has enabled them to actively ,o
de d fi rrors with a back track, the evolution ln the role of a P U..
spot an 1x e
h d againsteach release within a project.
milestones reac e h h Ith of a project is to record quality aucttts, ,_
H Ith • The reason to regularlycheck t e ea ..._.
5 Maintaining Project ea · d r1 elines targets and deliverables. Project health~~
· · ployee performances as well as recor m , -~
mistakes, review em . . pproval or rejection of scope changes and actionst::o&,~
•· ming the project's selection, business case, a ..._.'e
of decmons conce . t priorities and inject flexibilitywhere required so ,._ 11...
issues. It lets project leaders match resources agains ""
reso1ve d d t supply of resources
· ct stays the course and makes use of the right an a equa e ·
pro1e • t' h h I ·
Risk Mitigation : Project leaders know from experience that risks are inevita.ble. Tha s w V t ey re y on in~ illd
6· . . 'd •ty d b t Id new or common risks. As a pro1ectleader , you have to be better inf°'11ed
forecastinginsights to I ent1 an com a o , . . .
of the risks and the ways to counter them. You can work together to create a risk chart depicting the severtty,
and mitigation plan. .
ConflictResolution: Project leaders have to deal with people and the likelihood of asymmetries between expertidllais
7
· and reality.Simply put, once the resources are assigned to projects, competing interests arise despite ther~ beinga tat
priority log. Add to which, newer priorities override existing one and displace schedules, which can result in tan.i
becoming dysfunctionaland uncooperative.
.,
,·
------
- It promotesfair decision m~king.
.
. 4'
- .d s a greaterchance of success.
It provi e
- d an,riety and stress and ultimatelyturnover In projects.
11 re uce.s
2..2 PMI Code of Ethics means for PMPs
6
• table for their own successful or failed
~ns PMPs have a responsibilityto hold themselves accoun de6.....
- 1tmea • ....
actions, as well as any repercussions.
It means being respectfuland demonstratinga high regard for oneself,others, and any reSotJrcesentrusted~-
- ' fid nee cooperation and diversity.
It me-ans fosteringexcellencethrough mutual respect, trust, con I e , '
_ It means the views of others are encouragedand valued.
_ , m-=ans practicing fairness at all times, making decisions,and remaining Impartial a nd objective. Behavior_ITMlst be"'-
1
from self-interestand self-gain,prejudice,or favouritism.
It means demonstrating honesty through words and conduct at all times.
_ Indeed, being ethical and following ethical norms can be said to be prerequisites for project managers who'-'-
practice ethics and observe ethical rules. ·
- Let us take a look at some of the most common types of ethical dilemma in business, and how you can navigate~
through them.
1. Accountability: When things go wrong, it is·human nature to try to avoid the consequences and placethe tiaat
somewhere else. Not only ~n this damage careers and reputat ions, it creates additional project issues by cnr, :le
the real source of the problem. Project managers should understand the importance of owning their own mislats,
and of recognizing situations in which teani members or other stakeholders are attempting to shift 111t
responsibilitiesfor problems that arise.
2. Conflictsof Interest : At the enterprise level, when projects involve large numbers of people and sever-iiof Odidt
vendors, there are ample opportunities for stakeholders to give inappropriate preference to certain teams 11
companies. As a project manager, you should make sure that all parties involved In a project understandp
comparry'sstandards for bidding and vendor selection, and that the definition of a conflict of interest iS' cB ID
everyone.
3. Workplace Culture : While today's workplace environments are generally more respectful and inclusive than ltl!Y
were a few decades ago., no organization has perfected its company culture. Project managers should be very flflliar
with their company's code of conduct and should ensure that all employees, contractors and business~
understand what is expect.ed of them. This Is particularly Important with projects that Include team membenfro!_'
multiple countries as behavior that Is acceptable In one culture may be vie~ed as harassing or even threatenlrC-'
another.
Intesti nal fortitude: The fnner strength of mind anC, will that enable you to act In the race of advenity.
Courage to do what Is 'right : The ability to do ,somethingthat you know Is correct and appropriateregardlessof the risk to
yourself. .
Tools for commun ication need to be In place before the team beg ins work Technical t -h
. · ma er 1a 1s are fundamental to t e
team's ability to generate useful work products . The technical env iron ment should pr Id h .
. ov e t e mea ns for onhne document
review, Inte ractive meetings , traini ng, discussion threads, research and survey d t b ·
a a, enchmarklng quality revie w data
collectlon , and rewa rd systems for sustain ing team comm itment. ' . '
(v} Standards for project management and for work production. PMl's A Gulde to the Project Manag~nt Body of
Knowledge
(vi) Programmanagementfiles
_ Hthe organization'slarger infrastructure does not contain the tools to capture, share and refe'rence key documents.thf!n
the project team should develop them within the communicationsplan for Its own use. If the project cannot arrange the
proper technology,put it in the risk plan for managementslgnoff.
Scanned W
·1th camscanner
,!~ p,oLect Managemenl(MU) 6-9
Physfcal inspectionof the deliverable
(ii) Third party audit of the deliverable
(iii) Analysisof the processes used to create the dellverable
(iv) Review of Project Plan re: time spent creating the deliverable
(v) Review of FinancialPlan re: cost of creatingthe deliverable
(vi) Review against the Quallty Plan re: qualityof the deliverable
_ To increase your chances of gaining customer sign-off, you may wish to Involve the customer in the acceptance testing
process itself. This gives the customer additional confidence that the deflverablesmeet the acceptance afteria and that
the testing methods used to determine the completionof each dellverable are comprehensiveand effective.
_ After the acceptance test is complete, the Project Manager commissionsany additional work needed to meet specified
acceptance criteria. Upon completfon of that additional work, the dellverable Is re-tested to determine whether it h3S
achieved the required level of quality.This process continues until the deliverableis ready for customer sign-off.
_ once the testing is complete and the deliverableis ready for sign-off, the Project Manager completes an A«eptance Form
within their project management templates, which describes the acceptance criteria and the overall results of the
acceptance test. This should give customers confidence that delivera~lesmeet their requirements in full and should be
accepted as 100% complete.
Step 3 : Gain Customer Acceptance
The customer reviews the AcceptanceForm and decides to :
o Commissionits own acceptance test
o Request further informationabout the testing activities
o Not approve the deliverableand raise a formal issue
o Approve the deliverableas 100% complete
- Throughoutthe AcceptanceManagement Process,the QualityManager keeps an AcceptanceRegister up-te>-dateto allow
the Project Managerto monitor and controlaccepta.nce of project deliverables.
- To gain the full customer acceptance of aH deliverables in your project, consider using these acceptance project
management templates: AcceptanceManagementProcess, AcceptanceForm and AcceptanceRegister.
Project termination is one of ttie most seriousdecisionsa project managementteam and its control board have to take. It
causes frustration for those stakeholders who sincerelybelieved that the project could produce the results they expected, or
still expect. The project manager, his team members and very Important· stakeholders of the project will feel that they
personally failed. They als~ will be scared of negative consequences for their careers; their motivation and consequently,
productivity will decrease significantly._
Technical reasons
- Requirements or specifications of the project result are not clear or unrealiSt ic b h ged accordingly
. contract cannot e c an
- Requirements or specifications change fundamentally so that the underIying
- lack of project planning, especially risk management
The intended result or product of the project becomes obsolete, .1s no t any longer needed
Adequate human resources, tools, or material are not available
. h proj·ect cost or too low project revenue
- ,:he project profit become s significantlylower tha n expected, due to too h ig
The parent organization does not longer exist
- The parent organization changes its strategy, and the project do~s not support the new st rategy
- Force majeure (e.g. earthquake, flooding, etc.)
Necessary conditions disappear
lack of management support
lack of customer support
- o_n the other hand, involuntary failure of the project may _occur due to insufficient financial support, poor leadership, weak
front-end planning, and excessive negat ive Impacts of pro ject stakehold~rs.
-
6.9
processto Terminating a Project
. . .
The closing phase of project management involves several steps. Work through the following cheddist to ensure your
project is successfullycompleted. ·
1. Formallytransfer all deliverables
The first step to closing out your project is to finali~~ ~nd.1transfer the project deliverablesto the dient. Go through your
project plan to identify all deliverables and make sure they have been fuHy co'!'pleted and handed off.
6-12
if Project Management(MU
rn rnernbers and any other Pa ·
4. Release resources II rs contractors, tea d officially release them so rt""'.
5
Formally release resources from the project, lncludlng supp e ' or obligatlon , an thtv 1ft
1 ayrnents ·
Notify them of the end of the project.Confirm any flna P
tree to work on other projects.
5• Conduct a post-mortem of the pro J·ect closure process. This is• a t1..
"'Ill•to
1uable steps it nit ies for improvem
A post-mortem or project review Is one of the moSt va d Identify oppo u . ent ...
review the successes, failures, and challenges of the project an
forward. j ct In other words, calculate the pr~--
. . w of the pro e . -,,ai;{s
As you begin your post-mortem, conduct a performance revie ·
performance in terms of cost, schedule,and quality. to get feedback on how the DrftL...
. t managernent team r·~
Next, conduct a survey or hold a meeting with the proJeC ·ct re of the pro ject's performance.
prehensfve P1 u
went. These individual answers will help paint a more com
. .
. d and op'portuniti
. then identify lessons 1earne es fiort1it
With the project performance and feedback m mmd, you can
future.
6. Archivedocumentation
. 1· 11 documentation (contracts, project plans.-
Once you have completed your project post-mortem, you can f ma ize a
. h' f r later .reference .Be sure to keep clear notes-
--,,:.
outline, costs, schedule, etc.) and index them in the company arc 1ves o · . ..,
· · ·· easily reference and implement them on ..;-..
the proJect's performance and improvement opportunities so you can -•-
projects in the future.
7. Celebrate
- The end of a pr?ject is a big accomplishment and r~presents the culmination of many hours of hard ~and -
dedication from a team of contributors . An end-of-project party is a great way to acknowledge your team'~ hanhat
- The final report .is an internal project management tool which reviews th e imp
· Iementat,on
• process of the projed P~
:::~
presents the proJect's outcomes and results.
- It provides an opportunity for the project managers within the Imp! ement 1ng ent1t1. .es to summariz · d sure of the
_
project, the project's achievements, outl ine the problems encounte d
.
e, upon
re , as well as the good practices and lessons teamed-
°
The. final report should include a part icular focus on assessin g th e· extent to which th d • were
delivered, as illustrated by the indicators of achievement. . e expecte accomphsh"!'ents .
- In the final _report Implementing entit les are also requested t 0 eIab orate on the t · · the
presence of multiplier effects and supplementary funding. · sus amability of the projects' efforts,
Table 6.10.1 : Annual Progress Report, Final Report and Evaluation Report for the DevelopmentAccount
Summarytable
..
: fEva~~rt . .
nmefra Should oe submitted For 9th tranche projects that closed by For 9th tranche projects that closed by
me by January 31st for December 2017, the final report should December 2017, the evaluation report should
the preceding year. be submitted by 31st March 2018. be submitted by 31st March 2018.
For 9th tranche projects that received°an For 9th tran che projects that received an
exceptional extension, the firial report exceptional extension, the evaluation report ·
should be submitted within 3 months of should be submitted ~ ithin, 3 months of the
the proj ect's operational closure. project 's operation~l closure.
The evaluation report should ideally be .
submitted with the final report.
External consultant ·hired by implementing
Drafter Project manager in Project manager In Implementing entity.
entity .
implementing entity .
2% of the total budget of the project is
Budget No fi nancial. No financial resources require d.
Initially budgeted to fund the evaluation.
resources required.
Should there be savings and need for
additional funds for evaluation, the 2" figure
can be revised upwards. I( the proposed
evaluation budget exceeds 4% of the project
budget, prior _approval needs to be received
from the DA•PMT.
....__
--- •T_......_..
-1=-=-=-=-=--=--=-=1=-=-=-=-=----.:::-=-=~==-=-=-=-=--=--=--=-==~~-=-=-=-=-=-=7~~~;;; 1" ,. 1 1u al l t ttt
This section should be no longer than one page and ~hould provide a concise and effective narrative of the basic
accomplishments of the project. It should not repeat Information alr~ady provided (for instance, informatia"n presented In
the projectdocument) but should highlightresults, potential Impact and any relevant achievement related to the project's
implementation (including unexpected results, both positive and negative). If the project (or one If its parts) Is considered
!t
successstory should be dearly stated In this section. The Information repo rted In this section ~ight be used for the ~A
awebsite.
' , lcatrJr,of,
H~nt:
ci:1) Co.111••
. t_..,.
: •...4 --i # , •
·ther~
. . .
(P 'lfy
e, actMt,
p~Je_ct'sdts,!gn.Sls~t···-~
EAl
A.1.1
A.1.2
EA2
'.cf' It
Description of challenges ase indicate whet her and how it
1
(for each challenge, p e
(Please list all challengesfaced) was solved)
5. Good Pract ices and Key Lessons Learned · with respect to the desig n or exec ution of 1he
- In this section entities are requested to elaborate on good practices ,
project, which could be successfully replicated in future programm ing. nsidered important lesso ns for f. ... _
b
- The sect ion should also out line any releva nt finding that can e co "'wn!
programming.
6. Sustainability
This section should elabora te on the extent to which th e achievements of the projec t are likely to b e s usta ined beyond its
cornpleti~n, leading to durable , self-sustained results. It should alsc;> include reference to any follow-u p activity to the
project that was implemented or initiated by the entity or other partn ~rs following the completio n of th e project..
7. Multiplier Effects
This sect ion sho uld elabo rate on whether the project triggered processes for t h e replica tion of its activities, in other
participating countries, non-participating count ries, or, alternat ively, any plan to do so.
8. Supplementary Funding
- This section should elabo rate on whether add~tional fu nding (financial o r in-kin d) w as leveraged to further the
implementation of the project (e.g. secu ring additional part icipants at workshops, paying fo r ve nues/add itional
activities, etc.). In addre~s ing this section , implementing entities are asked to fill in t he table 6.10.5 .
- Ple~se note that supplementary funding does not refe r t o funds leveraged fo r projects ot her t h an the one being
rev1ew~d (fo)llow up activities to the p roject or spin-offs In other countries should b e reported in sect ions 6 and 7,
respective 1y .
. -~·, .
Co_!ltributlng-Entfty
f.Donor Purp_ose
sh USD) .· .'~
contractual sen.:ices
120 -;
Total
- The lessons learned analysis fs a technique through which we can learn from our mistakesand successes;and ~e
our performance over time. This Is also known as the post-mortem analysis. Generally, this process is held near the
completion of a project, but It's more beneficial to hold It during the courseof projects. For example, whffl a milestoneha5
been achieved, we can hold a lesson learned analysis and act based on the learnins. There's no need to wait until the end
to act, especially if the lesson Is somethingeveryone can benefitfrom.
- The objective of the lessons learned sessions ls to share and apply the knowledge derived from both posltive and negative
experiences. Positive experiences are all the things that we would like to continue doing in the future. Negative
experiencesI on the other handI are those things. that we should never repeat.
- During a lessons learned analysls, an honest, no-penalty discussion is held with a man;aatr and his/her team. It is
frequently used for project work at strategic points and at a project's conclusion. It can also used to improve change
initiatives and for new assignments given to team members.
The process of Lesson Learned Analysis comprises fiv~ main elements : defining the prolect, collectingi~
verifying applicability, storage, and disseminat ion.
1. Definethe Project
This Is the Initial step where in the need for lessons learned analysis Is Identified and the process and team to r4tf!J
lessons are estab lished . It Is Important to establish the specific need. and purpose for lessons, the audi~ +.
\
I
product , and Individuals that should comprise the prolect team . Initial engageme nt from all key players 1 ·
\
- ------- - --- - --- ------------------------;::::;------;:.
.....
I
. . ues, writ t en forms, and meetlnBs Th rue ure ~s well as unstruttt Jred proces~e,; sud, 1tt prr,ject
cnt1Q • e collettlon of le
. . g 10 solicit. l essons learned can b b ssons may come from a, many ~outc"s tJ., ttn orpnf t.tfton is
,v,11,n e ased both upon posit!
ative experiences that result In undeslta ve exper1ent es that .Jdileve orianl atioo 8¢111, .md· M
neS r more importa nt as docume ti ble outcomes. For some ptojecu, a colh,boratlve leiso ns colll!Ctfon pr~~ an t\
L,e as O n ng the lessons.
5, Disseminate
The final and the most importa nt eleme nt is the dissemination of lessons learned. Lessons are of little benefitunless they_
are distributed and used by people who will benefit from them . Dlssemlnat.lon can indude the revision of a wctil process.
training, and routine distributi on via a variety of communi cation media. lessons can ·be "pushed," or automatkally.
delivered t o a user, or "pulled " in situat ions wh ere a user must manually search for them
It is important t o know the sort of lessons do we need to capture and bulld in to planning future projects. FolJowtr.-.ar•
,ne common areas where lessons shou ld be learned :
1. Communications weaknesses
In gen~ral, lack of effe ctive communic atio n has always been an area of concerned In either proerammesor proje(ts.. It
includes managing key stakeholder expectat ions, managing third-party suppliers, etc. Having more. better and different
types of communication is vlta l and that might mean getting people together in the same room, face-to-face, to resoM
issues mor e effectively and devel op a clearer under standing of the brief and desired outcomes.
2- Management of risks and Issues
Risk and issues need to proact lvely addressed and owned by the project management team. Some peopfe's of
managing risk is a t ick-box act ivity rathe r than a necessltY to mitlaate project failure
3
· Obtaining the right resource• to get the Job done
Projectmanagers need to be aware of the resources hey require during the project. Very often., resource manacementls a
Problem. Therefore , It must be looked out for durlna the Lesson Learned Analysis.
• .... .....,
,-.,:;; ,. I\.
4 Clarity around roles and responslbllltles pMO takes over the running of the
· Project managers need to understand what's expected of t hem If thnager e Is not adhering
· t O PMO requirementsit
project/programme. There are differentskill-setsat work and If a project ma •
. .p. So, this is a kind of lesson we must look out for.
can affect the relat1onsh1
- It is said, failure Is the pillar to success. But this holds true only when you acknowledge failure. An attempt to recogn ize
and overcome failure In projects and succeedIn future Initiatives can be challenging.
- If your project has been launched befor~ but failed for some reasons, most likely your team and other stakeholders have a
negative mindset towards it. But the failure reasonscan be addressedand a new project will be successful.
- · o f f ailed
A t h oroug h anaIys1s ; project can greatly help understand what was done wrong. You can develop feasible
solutions, and remove any barrier for future success.
1. Wrong Team Organization : You need to explore the team organization chart to figure out whether wrong people
were Involved In the work, from leaders and sponsors to team members and personnel.
2. Poor Motivation : Try to find out whether the business organization provides the team with the right attitude and
motivation towards the work to be done.
3. Insufficient Technology capabllltles : Can you say that the project has been failed because of the wrong technology
selected and Insufficiency In the capabllltles to support what was needed?
4. Wrong Methodology: Analyze the methodology employed In the processes and explore wheth It .
. er was appropriate
to the project's procedure and change controls.
ever. h .. h . d d .
· e figure out whet e r 1t as increase or ea-..
You must explore every change in failed project· managemen t pract ,c , -::-:-~
• ct implementa t ion. ·
d &
the likelihoodof success, and document the current nee ,or proJe
ate the resu lts to assess whet her the IWIII,,,.
- combine all of your records on the changes in a single sheet an d t hen aggre g . ..."I'll
is worth a new try. Hold a meeting with the stakeholders to highlight the changes a nd th eir impact to success and~-
on whether the new project should be undertaken at this time.
Being optimistic means demonstrating certa in behavior that makes everyone around believe that everything wili be(i.
regardless of how bad the things were in the past. In order to fight project . f~ilure , you must show an opt imistic a~
towards the new initiative , telli ng key stake holders that the new project's outcome will be quite different than dit
previous failures.
Do ~our best to address the natura l tendency to be sceptical about resurrect ing a fa iled project . Be persuas ive
motivate everyonet owards succeeding at the new Initiative.
Communicate the adjust ed framework of your project and ensure t he stakeholders that this project Is reframed In
current context. Tell about the lessons learned from pr~vious ~nsuccessful attempts and point out all those adjustments
that have ~een made to turn the new pro ject into success • .
-
enthusiasm won't bed
I
epeted.
Closely collaborate with lead
changes that could
II
a stakeholder groups to ensure that the project won't lose its momentum and that the
d .
. ers an supervisors to keep track of any Issues In the team environment and detect and solve
l
negatiVely Impact Your project .
th
- Succeedk in PM rough Con~nuous Analysis. Even if your previous failures are considered, the lessons are learned. lhe
sta eholders ate committed d
' an Your new project is initiated, you must expect · for a more challenging process that
ultimately brings the job to a successful dose. .
- How often do you celebrate project ~uccess? Celebrating project completion and spedfically successful completion means
acknowledging successand mind yau, that's very important.
. .
- Most companies do n'ot celebrate ends . They think the completion· of a project is a reward in itself. But they are wrong.
Achievements . and outstanding effort deserve acknowledgement. Take a moment to reflect and feel proud of
accom~lishments. These moments are rare, and too often leaders fail to savour them but rather rush full..speeci ahead
into the next tunnel.
- Even when we do celebrate, perhaps too often the focus is on celebrating once the project is over. That can often be after
several years of hard constant work. No one feels like celebrating when this is the case. They are all just glad that the
project is over.
- Th~t' s wf:ly it is important for the moral of the team that you celebrate project success along the way.
Consider celebrating at the following point along the project journey :
1. . Project Kickoff : If you gather the team together and do a formal meet and greet, so that everyone gets to know
·who's on the 'Team' then there is an opportunity to have an afternoon tea, or pizza lunch to celebrate everyone
being on board fur the project. doing this, you will find that there is more team cohesion. It is simply because
people realize they are part of a team this way. They see the others who will be working beside them. This helps
then know who they can talk to about the project and any issues that arise, as they arise.So consider a small, kickoff
celebration
2. When key project · deliverables are completed : Sometimes it's great celebrating when the key deli~rables are
completed . There might be several phases within the project . And within those phases are key deliverables. Just
stop and celebrate the deliverables being finished. The teams will appreciate the break, even If it Is only for an hour.
What yo~ will notice by ha~ng such celebrations Is ~hat the1eam appreciates being acknowledged for the hard work
they have ju~ completed. It gives them the recognition they deserve, and In that, ~ou notice they are more willing to
• •••" .. ~•••••
. ~,.. , s ,,·
- Celebrating success is more than just a good or nice Idea, or even the right thing to do . It can provide meaning,
teamwork , and help achieve even greater success .
1. Coll~ on Projects: People frequently designate Individual tasks which are part of a bigger project the whole teanaIs
trying to complete. Project management software gives employees a method to collaborate on projects by dtscns•
documents, timelines, outstand ing work, etc. •
s. oocument Sharfn~: Documentsharing, whether Inside the tool 04' In a Integrated 3rd party system , enables to find
r,,ore comprehensrve documents, wlreframes,SpecificatJons, etc., which enabtes transparency and communic3tkJn •
. tio with OJ with di ts and
6. cornniunica n ents and Suppliers : Companies should be able to talk to and c.oflaborate ,en
~uppliers from the same place. Companiesusing project management software should offer ther dients the ability to log
in and view only th eir relevant project data. This way, d lents can provide direct feedbadc, matte edits and reviC!!'W prug, ess
in the same place.
i. optimized Decision Making: Project management software solutions assist In making the right deci:sionSas you h.rve aJI
the details in one designated place. Hence the decisionprocess is enhanced and much more accur.rte-
s. Enhanced Customer Satisfaction : When you get a project done promptJy and under budget. the die:nt walks 'JWiJY with a
smile on their face - and a satisfied customer is one you will see again. Smart project management softwa~ lhe
tools which allow this customer/supplier relationshipto carry on. By applying fundamental project management.software
strategies,you'll narrow your focus, achieve your goals and improveyour deliverabifrtyand rate of success..
_ Microsoft Project is a project management software program developed and sold by Miaosoft. It was designed to assist a
project manager in developing a schedule, assilr,ing resources to tasks, tracking prog,ess. managing the budget. and
analyzingworkloads.
- MS Project creates budgets based on assignment wort and resource rates. As resources are as.signed to tasks and
assignment wort f!St:imated,the program cal~lates the cost, equal to the wort times the rate, which rolls up to the task
level and then to any summary task, and finallyto the project level.
I
- Each resource can have its own calendar, which defines what days and·shifts a resource is available. Microsoft Project is
not suitable for solving problems of available materfals (resources) constrain~ production. Additional software ls
necessary to manage a complgxtacilitythat produces physical goods.
- Resource definitions (people, equipment and materials) can be shared between projects using a shared resource pool.
Each resource can have its own calendar which defines what days and shifts a resource Is a~ilable.
- Resource rates are used to calrulate resource assignment costs which are rolled up and summarized the resource level .
- Each resource can be assigned to multiple tasks. In multiple plans and each task can be assigned multiple re.sources.
MicrosoftProject schedules task wort based on the resource availabilityas defined in the resource calendars. All resources
can be defined in an enterprise resource pool.
..~-.... .....
, , ,-"
$
6.14 ProjectManagementTemplates
- ~reat ing all the documents related with a project from scratch waste a monumental amount of time. This is why f!!#ffV
project manager usually has a trusted arsenal of project management templates these days.
- Using templates not only improves your · efficiency, it also brings much-needed standardization to your proled
management process . Instead of creating documents on an ad-hoc basis, you can have a single template for e1ery f\indiOft
that can be used across the organization.
Borrowing pre-made templates ca~ also ensure that you use best practices in your planning and reporting. If a tefflPltll
has proven to be successful in one organization , there Is a good chance It will be useful in yours as well. .
There are ·a number of project m~nagement templates on line, but few centrally organized resources.
ith camScanner
Scanne d W
-!d project Management(MU)
• 6-29 P"°f:'9LG8dorShfp, EJt,Jca & CJoacJffl
~owto Use Project Management Templates ?
Most PM templates are made In Ms Ex • 1y downlOINf
' o· ct fil Ii ks eel. A few text-heavyones use MS Word. To use these templat~ , itmp
1hem. ,re , e n are markedspecifically.
, have to give up your email address In exchange for ttM! me Once downloaded,f!dit them wtth you,
In some ~ses, you WIii
wn details and export In your h f --sourer
0 c osen onnat. If you don't have Excel or W0td you can use ubre<>fflceas an open
alternative. Alternatively,upload the file to G '
your oogle MyDrlveaccount.
5t
6.14.1 Mo C~mmon Project ManagementTemplates
_ _1(a) Project Charter Template
6 14
, T}lis is an important document template that outlines the scope, objectives, and stakeho4dersinvotYed In the project. tt
documents everythingth e project needs and its expectedoutcomes.
- T}le project charter also doubles up as a business case document. In case· you need to convtnce stakeholders of the
importance of a project, or outline the goalsto your team, you will tum to the project charter.
_ Whether you are using one of the project charter templates or creating one from scratd'I, there are a few e-fementsyou
should always indude:
1. Project titl~ : 5tart with the title. Make sure it is specificenough to make identification easier. A good template to
follow is this - •[ProjectType) to [ProjectObjective]for (ProjectOient/Product
2. Executivesummary: In dude a high-levelsummaryof the project, its purpose, and its stakeholders.
¥
3. Project objectives : Explainthe •why" of the purpose In greater detail. Be very specificabout the outcomes you sttk.
It's a good idea to indude specific numbers or at least a _range. Don't say "increase traffic• ; say •j~ase websit~
traffic by 200% in 6 months". -
4. Business objectives : Use this section to describe how the project fits Into the business' broader sbategic goals. For
instance, if you are ruMing a campaignto increasetraffic to a website, describe how the highef"traffic would hetp the
business in achievingits goals.
s. Project requirements : Explainthe project's requirements in terms of resources - both tangible and intangible - at a
high-level.
6. Project scope : Use this section to answer the question: •what is the project meant to accomplish?" Focus on both
long and short-term goals and objectives,but briefly.
7. Key deliverables: Brieflylist the key deliverablesat different milestones.
s. Project schedule : Give a high-level overviewof the project's estimated schedule. You don't hiM! to be accurate
down to the day, but a broad explanationof key milestoneswill help.
9. Project budget : Give a high-level desaipti~n of the project's budget. You can break this down by resource
requirements if you want to go Into more detail.
6.14.1(b)ProjectPlan Template
There is no fixed •recipe" for making a project plan. You can be as detailed or superficial as you need to be. Unlike the
project charter, which is meant for stakeholders on both sides of the table, the project plan ls mostly to cue you and your team
into the project and its goals.
Here are some things you ~n Include In the project plan Templat e : description, 10, dlent. 1
I dud ing Its name, nd ....._
1. ProJect ldentfflcation : lndude deta lls about the prolcd , n ·
manager's name . vou can also Include a counter I~
2• th
Prolectdates : Ident ify the start and estlmate _d end date of e pro)ect . · '-
number of days lef\ until the end date . f llestones accompllst, ....
I ted so far In terms o m ~-
3. Progress : Mention how much of the project has been comp e . d r bl d
f k tasks, actlvitles or e ivera es, emn.t....
4.
.
Tasks/acthritlesfdeltverables: You can lnd ude a broad overview
O
ey fOcus on deliverables whll~ ;-.Ill\
the level of granularity . In comp lex projects, for Instance, you might want to ' ....
projects , vou can specify the exact tasks needed to produce said deliverables .
· h team or person responsible for It, and the....._
5. Task detans: lndude details about each task' s start and end dates, t e , -.
status.
n nd
6. Timellneor Gantt cmirt : You can also Include a tlmeline or Gantt chart showing depeode cies a progressfo,..
task.
'
1. Task progress : dearty identify all tasks that have been accomplished since the last reporting period,what you
on rurrently , and what's com ing up in the next reporting period .
,we..-..
l
\ 2. Issues, risks and change requests : Ust all current issues and their status (open, dosed, pending}. Also list changerequms,
and their history. Your goal should be to alert stakeholders about any Issues that need their immediate attention.
. 3. Milestones and deliverable: Identify all milestones completed since . the las~ reporting period. Also identify
milestones and deliverables as well as their start/finish dates.
As far as project management documents go, work schedules are fairly straightforward .
l
ll
- As project managers like to say, communication is about 90% of their job.From delegating tastes and solving issues to
keeping stakeholders ·updated on the what. why, and whe~ of the project, you'll spend most of your time communicating.A
solid communication plan will make your job infinitely easier.
- Communication plans help you communicate faster, anticipate client needs, alert your team about issues before they
happen, and standardize communlcatio~ aero~ your entire organization.Anywell-rounded communication plan template
should indude the following:
5. Help the team understand you support their Image and brand : Be transparen, . Let them know that you will foster,
networ1c and generally be supportive of them, so they know that they are not worldng In an Isolated bubble . Remind them
that just because they aren't report ing to their manager for this pro}ect doesn't mean there Isn't company •wlde vlslb\lltV,
and organizational visibility and the ir reputation at stake . Help them understand that the ir behavior and their
performance in this projea can and will impact them positively or negatively In the larger company setting .
2. Hybrid Approach
- The one-size-fits-all strategy is now facing extinctio~. The conventional waterfall methodologies are now being
twea ked with the modem strategies and adapted vividlyto help with the various processes of project management .
- The implementation of these hybrid methodologies is best suited for the scenarios where the projects are handed
over with an . exceptionally larger work base with an imperative .requirement of multiple project managers to be
'
involved in it.
- Hence, the present corporate world is demanding a considerably higher number of hybrid project managers. who are
not exclusively ~pert in one prescriptive methodology but are well-versed in several multiple methodologies.
5. Cyber Security
· . 't be wro ng to say that security over the I~
With all the advancements in inteme t techno logy arou nd us, tt won ed fi the concerns "'---
. • .:.1.. highly protect,rewa II, a..._, ._
is a myth . Until and unless you are securing your data w, u , a · .
. mised is ontv going to increase minute .
security of your project is highly valuable as ~e data getting comp~o
· · tad· 3 way by enhancing the cyber security m~
It has to be accepted that data breaches aren't completely mg .
· d stratooies from an onltne threat. vou stand a
But once you secure your project managem ent method ologies an ~ t>· •
• · f b
chance of not getting robbed on line. And with the nse o CV er-a c tta k at an alarming rate, the chances are morefara
fonnal regu lation to be created in order to set a standard of detection, prevention, a nd response from technolagy
and agencies alike.
6. Remote Teams
The sharing economy has proven the fact that more organizations are highly appreciative of the use of a distributed
· team structure. This is because remote teams are comparative ly cheaper ·and way more prod_uctive when managed
efficiently and effectively with the apt set of ~anagement t ools.
And needless to say, remote working teams are gradually beco ming standard practice in the wood of project
management. The prese.nt-day project managers are steadily proceeding ahead with the investment of this
technology to promote highly effective commun ication over a wide range of platforms.
The loT is basically a gtobal netwonc of devices that can use the Internet to communicate with one another as well as
with the end-users. And the interesting fact is that loT bisects with project management on all the aspects ranging
from data collection to team collaboration.
The advantage of loT In a project management strategy Is that the devices can sense and respond to the surrounding
happenings automat ically through the ir networ1<,thereby reducing the requirement of involving manual intervention. :
. loT has a significant role in t~e 2020 project management trends . It helps to lower the operating costs, minimizln&
errors and increasing the response tJ~e. You also get the leverage to provide the cust~mers with a comparativetv
raster and better service .
Q.1 4
How importantis it to acknowledgefailure and success of a project.(Refer Section 6.12)
a. 1s How can we find out the reasons for project .failure? (Refer Sections 6.12 and 6.12.1)
Q. 20 Describesome of the areas that ca~ be studied in project managementin future. (Ref91Section L 16)
aaa
I •
......t"!'.i'""'-
'" -""--"------------ -"--
Scanned with CamScanner