BG 1 - 2007 Handover, O&M Manuals and Project Feedback
BG 1 - 2007 Handover, O&M Manuals and Project Feedback
southbank
On
20/02/2018
n es
d es e o gs, t u
u c
l n ti a n n iq
inc ida y ra cup echn
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
u
ow g rg oc t
N ate ene on, ack
d l ti
to iona ifica feed
b Handover, O&M Manuals,
up rat ert ct
e c je
op rgy pro
e
and Project Feedback
en , and
s
vey
r
su
Supported by
BG 1/2007
Preface
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
4HE PUBLICATION OF Handover, O&M Manuals and Project Feedback IS A WELCOME ADDITION TO THE
LIBRARY OF PRACTICAL "32)! GUIDES
(ISTORICALLY THE CONSTRUCTION AND MANAGEMENT PHASES OF A BUILDING HAVE BEEN FOUNDED ON
DISCRETE ACTIVITIES )NDIVIDUAL PIECES OF THE JIGSAW HAVE BEEN DELIVERED WITHOUT REFERENCE TO
THE COMPLETE PICTURE "32)! HAS BEEN A DRIVING FORCE IN ENCOURAGING THE INDUSTRY TO
ADOPT A MORE JOINED UP APPROACH FORGING STRONGER LINKS BETWEEN THE DIFFERENT DISCIPLINES
AND PROMOTING A WHOLE LIFE CYCLE APPROACH TO BUILDING 2ELIANCE &ACILITIES -ANAGEMENT
3ERVICES IS PLEASED TO OFFER ITS FULL SUPPORT TO THIS INITIATIVE
&OCUS ON THE PERFORMANCE OF BUILDINGS IS GATHERING MOMENTUM NOT JUST IN TERMS OF USE
BUT ALSO OF A REDUCED IMPACT ON THE ENVIRONMENT 2ELIANCE &ACILITIES -ANAGEMENT 3ERVICES
HAS TAKEN A LEADING ROLE WORKING WITH OUR FELLOW PROFESSIONALS IN THE PROPERTY INDUSTRY TO
HELP OCCUPIERS REDUCE THEIR USE OF ENERGY AND IMPROVE THEIR TOTAL CARBON FOOTPRINT 7E
NEED TO ASSESS THE IMPACT OF OUR ACTIVITIES NOT ONLY IN THE CONTEXT OF OUR
INDIVIDUAL DISCIPLINES BUT ALSO IN TERMS OF THE TOTAL UTILISATION AND LIFE
EXPECTANCY OF BUILDINGS AND SYSTEMS 5NDERSTANDING THE BUILDING LIFE CYCLE IS CRITICAL
TO THE CREATION OF SAFER MORE PRODUCTIVE AND ENERGY EFFICIENT BUILDINGS
4HIS "32)! GUIDE PROVIDES AN ESSENTIAL BASIS FOR COMMON UNDERSTANDING WHICH AS
PRACTITIONERS WE MUST ALL EMBRACE IF WE ARE TO MAKE A DIFFERENCE
"ARRY .EALON
#HAIRMAN
2ELIANCE &ACILITIES -ANAGEMENT 3ERVICES
© BSRIA BG 1/2007
Part 1
Acknowledgements
"32)! ACKNOWLEDGES THE HELP OF THE FOLLOWING PEOPLE AND ORGANISATIONS WHO
HELPED IN THE REVISION OF THIS GUIDE
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
"32)! WOULD ALSO LIKE TO THANK *O (ARRIS OF "32)! FOR FACILITIES MANAGEMENT AND
MAINTENANCE INFORMATION AND *OHN !RMSTRONG AUTHOR OF THE FORTHCOMING REVISED
PUBLICATION CIBSE Guide M: Ownership, Operation and Maintenance of Building Services
FOR HIS ASSISTANCE IN ENSURING THAT THE "32)! AND #)"3% GUIDES ARE COMPLEMENTARY
4HE AUTHORS HAVE SOUGHT TO ENSURE THAT THE CONTENTS OF THIS GUIDE WERE RELEVANT
AND UP TO DATE AT THE TIME OF PUBLICATION (OWEVER READERS SHOULD BE AWARE THAT
LEGISLATION STANDARDS AND CODES OF PRACTICE CHANGE REGULARLY 2EADERS SHOULD SATISFY
THEMSELVES THAT THEIR ACTIONS INFORMED BY THIS GUIDE CONFORM TO ALL RELEVANT
LEGISLATION PREVAILING AT THE TIME OF USE
%DITABLE FILES
%DITABLE 7ORD VERSIONS OF THE TABLES PRO FORMAS AND OTHER SUPPORTING
DOCUMENTATION ARE ATTACHED TO THE PDF OF THIS PUBLICATION AND ARE ALSO
AVAILABLE AT WWWBSRIACOUKGOTOHOMPF
%65,$-XO\,6%1
© BSRIA BG 1/2007
Contents
Introduction 5
1 Building handover information 9
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
© BSRIA BG 1/2007
Part 1
2.13 Copyright 62
2.14 Manual costs 63
3.1 Scope 67
3.2 Definitions 67
3.3 General requirements 68
3.4 Checking and approval 70
3.5 Content and layout of a manual 70
3.6 Updating procedures for operating and maintenance manuals 72
3.7 Procedures for updating manuals 72
6 Appendices 105
A Maintenance labour resource 105
B Checklist of engineering services 107
C Extract From BS 8210:1986 Section 5 108
D Extract from the Building Regulations 111
E Draft display energy certificate 112
F Principles of percentiles 113
G Components of benchmarking 114
© BSRIA BG 1/2007
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Õfn
With over 40 years experience in building, maintenance
All around you there are amazing people, and facilities services, PME is one of the UK’s leading
breathing life into the environments in companies in its field. As part of Carillion plc, we are
setting standards in sustainability, Health and Safety
which we live, work and play. They keep
and corporate social responsibility. We use the latest
essential services flowing and enable all technology to deliver bespoke solutions, from routine
kinds of organisations to operate safely, office maintenance to the critical asset management
effortlessly and effectively. of financial data centres.
Introduction
4HE CONSTRUCTION INDUSTRY IS UNIQUE IN THE WAY THAT MILLION POUND PRODUCTS
CAN CHANGE HANDS WITH VERY LITTLE IN THE WAY OF FORMAL HANDOVER AND CUSTOMER
CARE %VEN THE HUMBLE a HATCHBACK IS SUBJECT TO A STRINGENT PRE DELIVERY
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
4HE UNFLATTERING COMPARISON BETWEEN BUILDINGS AND CARS IS NOT ONE IN WHICH
THE CONSTRUCTION INDUSTRY CAN TAKE MUCH PRIDE PARTICULARLY CONSIDERING THAT
BUILDINGS ARE MORE LIKE SHIPS THAN CARS ,IKE BUILDINGS SHIPS ARE RARELY IDENTICAL
USUALLY CUSTOMISED MADE ON SITE AND OFTEN SUBJECT TO CHANGES DURING THEIR
ASSEMBLY !S A RESULT THEY NEED ONEROUS SEA TRIALS BEFORE THEY CAN BE CONSIDERED
SEAWORTHY )N STARK CONTRAST BUILDINGS ARE OFTEN PRESSED INTO USE DURING THE FINAL
STAGES OF THEIR FIT OUT
%VEN WHEN A BUILDING HAS BEEN ACCEPTED AS COMPLETED AND THE CERTIFICATES
SIGNED IT IS ESSENTIAL THAT PROJECT TEAMS DO NOT DISAPPEAR 5NDERSTANDABLY CLIENTS
ANDOR OCCUPIERS WANT TO GET THEIR BUSINESSES UP AND RUNNING AS QUICKLY AS
POSSIBLE BUT THIS SHOULD NOT BE A SIGNAL FOR A DESIGN AND CONSTRUCTION TEAM TO
DISBAND )T IS ESSENTIAL n TO MEET THE REQUIREMENTS OF ENVIRONMENTAL LEGISLATION IF
NOTHING ELSE n FOR DESIGNERS TO HOLD THEIR CLIENTS HANDS DURING THE CRITICAL FIRST
FEW MONTHS OF OCCUPATION
"32)!S +EY 0ERFORMANCE )NDICATORS REVEALED THAT THE POOR QUALITY OF
/- MANUALS REMAINED A MAJOR PROBLEM FOR CLIENTS "32)! HAS COLLECTED DATA
ON THE QUALITY AND TIMELINESS OF DELIVERY OF /- MANUALS SINCE $URING
THAT TIME THE QUALITY OF /- MANUALS HAS DECLINED RATHER THAN IMPROVED4HERE
IS CLEARLY HUGE ROOM FOR IMPROVEMENT
4HE NEW GUIDE ALSO REFLECTS THE SIGNIFICANT SHIFT TOWARDS IMPROVING THE
OPERATIONAL PERFORMANCE OF BUILDINGS4HE UPDATE TO Part L2A OF THE
Building Regulations NOW DEMANDS THAT BUILDINGS HAVE A LOGBOOK4HE %5S
Energy Performance of Buildings Directive HAS ALSO PUSHED BUILDING LEGISLATION
TOWARDS ENERGY EFFICIENCY CERTIFICATION AND THE REGULAR INSPECTION OF BOILERS AND
AIR CONDITIONING SYSTEMS &ROM !PRIL PUBLIC SECTOR OCCUPIERS OF
BUILDINGS WITH A TREATED FLOOR AREA GREATER THAN M WILL NEED TO DISPLAY A
$ISPLAY %NERGY #ERTIFICATE $%# BASED ON ACTUAL MEASURED ENERGY
CONSUMPTION 3KILLED ASSESSORS WILL BE NEEDED FOR THIS TO HAPPEN
&OR THESE REASONS THIS GUIDE INCLUDES GUIDANCE ON CARRYING OUT ENERGY
PERFORMANCE ANALYSIS AND WAYS TO BENCHMARK THE RESULTS 2EFLECTING THE
INCREASING USE OF POST OCCUPANCY SURVEYS THIS GUIDE ALSO INCLUDES A NEW SECTION
ON MEASURING OCCUPANT SATISFACTION USING THE RESULTS TO INFORM DESIGN DECISIONS
7HEN USED IN CONJUNCTION WITH ENERGY ANALYSIS OCCUPANT SATISFACTION SURVEYS
© BSRIA BG 1/2007
CAN BE VERY POWERFUL TOOLS FOR UNDERSTANDING HOW A BUILDING IS WORKING
'IVEN THE EXPANDED CONTENT OF THE COMBINED GUIDANCE THE PUBLICATION HAS
BEEN SUB DIVIDED INTO FIVE DISTINCT PARTS4HESE PARTS PRESERVE THE LAYOUT OF THE
TWO SUPERSEDED GUIDES WITH THE ADDITION OF TWO NEW SECTIONS ON ENERGY
CERTIFICATION AND FEEDBACK TOOLS
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
3INCE 4. Handover Information for Building Services WAS LAST UPDATED THE
Building Regulations INTRODUCED THE REQUIREMENT FOR BUILDING LOGBOOKS
4HE LOGBOOK MUST PROVIDE ENOUGH DETAILS OF INSTALLED BUILDING SERVICES PLANT
AND CONTROLS THEIR METHOD OF OPERATION AND MAINTENANCE AND OTHER DETAILS
THAT ENABLE ENERGY CONSUMPTION TO BE MONITORED AND CONTROLLED /WNERS AND
OCCUPIERS ARE OBLIGED TO KEEP CONTROL OF THE CONTENT AND QUALITY OF THEIR
LOGBOOK
%DITABLE 7ORD VERSIONS OF THE TABLES PRO FORMAS AND OTHER SUPPORTING
DOCUMENTATION ARE ATTACHED TO THE PDF OF THIS PUBLICATION AND ARE ALSO
AVAILABLE AT WWWBSRIACOUKGOTOHOMPF
© BSRIA BG 1/2007
Part 1
ATTEMPTS TO OPTIMISE ENERGY EFFICIENCY THE GREATER THE RISK THAT THE ENERGY
TARGETS WONT BE MET 0OST OCCUPANCY STUDIES FROM THE 02/"% STUDIES
ONWARDS REGULARLY REPORT DISCREPANCIES BETWEEN EXPECTATION AND OUTCOMES
.OTE THAT THE TERM POST OCCUPANCY EVALUATION 0/% HAS BECOME A
EUPHEMISM FOR A WIDE RANGE OF ANALYTICAL TOOLS )N ITS STRICT SENSE 0/% IS
CERTAINLY USEFUL FOR RESEARCHERS WHO WANT TO FIND OUT WHAT WORKED AND WHAT
WENT WRONG IN A BUILDING &OR BUILDING DESIGNERS A POST OCCUPANCY EVALUATION
IS MORE A CASE OF SHUTTING THE STABLE DOOR AFTER THE HORSE HAS BOLTED 3OME
IMPROVEMENTS AND FINE TUNING MIGHT BE POSSIBLE BUT IT MAY BE TOO LATE FOR
MAJOR CHANGES
4HIS GUIDE PREFERS THE TERM FEEDBACK TOOLS WHICH DESCRIBES THOSE METHODS
SUITABLE FOR USE AT ANY STAGE IN A PROJECT BUT MOST USEFULLY AT THE PRE DESIGN
STAGE4HEIR USE CAN PROVIDE VALUABLE INSIGHT INTO WHAT CLIENTS AND BUILDING
USERS WANT FROM THEIR BUILDINGS AND IDENTIFY THE ASPECTS OF DESIGN MOST
IMPORTANT TO THEM 2ESULTS OF OCCUPANT SURVEYS MIGHT SHOW FOR EXAMPLE THAT
THE USERS OF A PARTICULAR BUILDING MAY BE WILLING TO PUT UP WITH TRAFFIC NOISE IN
ORDER TO HAVE OPENABLE WINDOWS WHEN ESTABLISHED DESIGN GUIDANCE MIGHT
SUGGEST OTHERWISE
4HE SAME TOOLS CAN BE USED FOR REALITY CHECKING DURING DESIGN ITERATIONS AND
TO CLOSE THE LOOP BETWEEN CLIENT END USER AND DESIGNER EXPECTATION AND THE
© BSRIA BG 1/2007
PERFORMANCE OF THE FINISHED BUILDING )N GENERAL THE MORE EMPIRICAL THE
FEEDBACK METHOD THE MORE LIKELY THAT ALL STAKEHOLDERS WILL FIND IT ADDS VALUE
TO THE PROCESS OF DESIGNING BUILDING AND RUNNING A BUILDING
4HIS GUIDE DOES NOT INSTRUCT READERS IN HOW TO USE FEEDBACK TOOLS )NSTEAD IT
DESCRIBES THE MORE ESTABLISHED METHODOLOGIES AND GIVES GUIDANCE ON SELECTION
CRITERIA 2ATHER THAN ATTEMPT TO UNDERSTAND THEIR INNER WORKINGS IT IS MORE
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
IMPORTANT FOR DESIGNERS TO APPRECIATE THE VALUE THAT FEEDBACK TOOLS CAN BRING
TO A DESIGN PROCESS AND THEIR USEFULNESS FOR FINE TUNING BUILDINGS4HE MOST
IMPORTANT MESSAGE FOR THE CONSTRUCTION INDUSTRY IS THAT FEEDBACK STUDIES NEED
TO BECOME ROUTINE RATHER THAN THE EXCEPTION
4HE FACT THAT YOU READING THIS GUIDE IS EVIDENCE THAT YOU AND YOUR COMPANY
UNDERSTAND THE INDUSTRYS SHORTCOMINGS IN ITS APPROACH TO HANDOVER AND
OPERATION AND MAINTENANCE AND ARE KEEN TO DO BETTER )F YOU FOLLOW THE
GUIDANCE AND USE THE TOOLS DESCRIBED IN THIS GUIDE YOU SHOULD BE ABLE TO
DELIVER BETTER PERFORMING BUILDINGS SIGNIFICANTLY MORE USABLE /- MANUALS
LESS ENERGY HUNGRY BUILDING SERVICES AND HAPPIER OCCUPANTS )F NOTHING ELSE
THATS A GOOD RECIPE FOR REPEAT BUSINESS
Roderic Bunn
September 2007
%ACH 0ART HAS A COLOUR CODED FLAG IN THE TOP CORNER OF EVERY PAGE TO
MAKE IT EASY TO FIND
Go to 12 O&M manual and record !NY SUPPORTING GUIDANCE WEBLINKS AND QUOTES FROM STANDARDS AND
drawing specification REGULATIONS WILL BE SHOWN SEPARATELY IN THE OUTER COLUMN WITH PAGE LINKS
SHOWN IN THE OUTER COLUMN THUS 12
© BSRIA BG 1/2007
Part 1
● 2ECORD DRAWINGS
● #OMMISSIONING INFORMATION
7HEREVER POSSIBLE THE SPACE PLANING SHOULD ENSURE THAT DEPARTMENTS WITH A
BUSINESS SYNERGY BE LOCATED IN CLOSE PROXIMITY FOR EASE OF COMMUNICATION4HE
USER GUIDE SHOULD INCLUDE FLOOR PLATE LAYOUTS COLOUR CODED TO INDICATE EACH
GROUP LOCATION
4HE HELPDESK NUMBER AND DETAILS OF HOURS OF OPERATION FOR NON CORE SERVICE
SUPPORT DEPARTMENTS SHOULD BE INCLUDED SUCH AS FACILITIES INFORMATION AND
COMMUNICATION TECHNOLOGY AND HUMAN RESOURCES
! VIRTUAL REALITY TOUR OF A NEW BUILDING IS FEASIBLE AS THE COST OF HAVING THESE
PRODUCED IS BECOMING MORE COMPETITIVE! VIRTUAL REALITY TOUR CAN SHOW HEALTH
AND SAFETY INFORMATION IN $ WHICH BUILDING OCCUPIERS MAY FIND MORE
ACCESSIBLE AND COMPREHENSIBLE THAN THE WRITTEN WORD
)T IS NOT UNUSUAL FOR CONTRACTS TO ONLY COVER THE COST OF RUDIMENTARY /-
INFORMATION AND RECORD DRAWINGS AS REQUIRED BY THE Health and Safety at Work
etc Act )NFORMATION PRODUCED TO MEET THE REQUIREMENTS OF THE Act WILL
NORMALLY BE SUFFICIENT FOR RELATIVELY SMALL PROJECTS INCORPORATING BASIC SERVICES
(OWEVER FOR LARGER MORE COMPLEX INSTALLATIONS IT IS LIKELY TO PROVE INADEQUATE
AS A BASIS FOR THE EFFICIENT AND COST EFFECTIVE OPERATION OF BUILDING SERVICES
© BSRIA BG 1/2007
4O COMPENSATE CLIENTS NEED TO WORK CLOSELY WITH THEIR DESIGN TEAMS TO
ESTABLISH A MAINTENANCE BRIEF4HIS WILL ENABLE SPECIFIC INFORMATION
REQUIREMENTS TO BE IDENTIFIED ALONG WITH ADEQUATE PROVISIONS IN THE CONTRACT
Part 1, Section 1.17 provides 7HEN THE SCOPE AND CONTENT OF /- INFORMATION IS BEING PLANNED
Go to 24 an outline of the primary Acts CONSIDERATION SHOULD BE GIVEN TO THE LEGAL OBLIGATIONS FOR OPERATING AND
and regulations that should
be considered. MAINTAINING THE BUILDING SERVICES #OMPREHENSIVE /- INFORMATION CAN HELP
SIGNIFICANTLY IN FULFILLING THESE OBLIGATIONS
4RADITIONAL HARD COPY /- MANUALS HAVE LARGELY FAILED TO KEEP UP WITH THE
INCREASING COMPLEXITY OF BUILDING SERVICES 0APER BASED RECORDS AND
DOCUMENTATION OFTEN PROVE TO BE AN INADEQUATE MEDIUM WHEN USED FOR
MANAGING PRESENTING AND UPDATING LARGE AMOUNTS OF /- RELATED
INFORMATION (ARD COPY MANUALS ALSO CANNOT BENEFIT FROM USEFUL COMPUTER
BASED INFORMATION CREATED DURING THE DESIGN AND CONSTRUCTION PHASES
BG2/2004 Computer-based "Y CONTRAST COMPUTER BASED SYSTEMS CAN OFFER IMPROVED ACCESSIBILITY AND EASE
Operating and Maintenance OF UPDATING4HEY CAN ALSO LINK TO OTHER ELECTRONIC SYSTEMS WHOCH ENHANCES
Manuals, BSRIA 2004 is
available via www.bsria.co.uk/
THEIR OVERALL EFFECTIVENESS "32)! PUBLICATION BG2/2004 Computer-based O&M
bookshop Manuals GIVES DETAILS ON VARIOUS TYPES OF COMPUTER BASED /- SYSTEMS AND
THE ORGANISATIONS THAT DELIVER THEM AS BESPOKE PACKAGES
© BSRIA BG 1/2007
Part 1
● 4HEY ENABLE THE VIEWING OF SCHEMATICS AND DRAWINGS THROUGH DIRECT LINKS
WITH #!$ SYSTEMS
#OMPUTER AIDED FACILITIES MANAGEMENT SYSTEMS ARE ALSO USEFUL FOR HOLDING
RECORDS AND DOCUMENTS THAT WOULD OTHERWISE BE STORED IN A REMOTE LOCATION
4ABLE
Advantages Disadvantages
● Selected data can be carried around site ● Manuals cannot be easily up-dated (unless
● Tried and tested approach with low risk copies of the original word-processed
factor documents have been kept on disk)
● For small projects, hard-copy ● Working copies of manuals and drawings
documentation and drawings are likely to be become tatty
the cheapest and most practical option ● Documents and drawings can be misplaced
● Limited flexibility in use
Advantages Disadvantages
● Text-based information and CAD drawings ● Initial expense of hardware, software and
can be easily accessed and up-dated training
● Well suited for recording breakdowns and ● System management
scheduling maintenance work ● Scanning of drawings and manufacturers’
● A multi-user network can be set up, with literature can incur significant cost
the option to interface with a building ● Scanned drawings will be read only unless
management system they are converted into a vector-based
format suitable for CAD systems
● The cost of updating CAD drawings can be
high, especially when only minor works have
been carried out
© BSRIA BG 1/2007
1.6 Record drawings
#LIENTS SHOULD WORK WITH THEIR DESIGN TEAMS AT THE DESIGN BRIEFING STAGE TO
ESTABLISH THE SCOPE AND FORMAT FOR RECORD DRAWINGS APPROPRIATE TO THE
MAINTENANCE BRIEF AND THE REQUIREMENTS FOR THE /- MANUAL
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
4HE CLIENT SHOULD ASCERTAIN WHETHER DRAWINGS ARE NEEDED TO ASSIST WITH
FACILITIES PLANNING DURING OCCUPATION )F DRAWINGS ARE REQUIRED IT IS ADVISABLE
THAT THE CLIENT SETS UP A SYSTEM FOR IDENTIFYING ROOMS SUCH AS A NUMBERING
SYSTEM
,AYOUT PLANS ARE NECESSARY FOR THE FUTURE SPACE PLANNING AND FOR DIVISION OF THE
BUILDINGS INTO SUB LET OR INTERNAL DEPARTMENTAL AREAS #OMMUNAL AREAS SUCH AS
LIFT LOBBIES AND STAIRCASES MAY BE IDENTIFIED AS A SEPARATE COST CHARGE DIVIDED
EQUALLY AMONG ALL THE TENANTS ANDOR COMPANY DEPARTMENTS!N OWNER
OCCUPIER MAY REQUEST THAT DRAWINGS ARE PROVIDED IN PRE SET LAYERS SO THAT
FURNITURE LAYOUTS CAN BE OVERLAIN WITH THE CEILING GRID LIGHTING SYSTEMS AND
MECHANICAL AND ELECTRICAL SERVICES IN ORDER TO HELP THE SPACE PLANNING
7HILE ESTABLISHING THE SCOPE AND CONTENT OF THE /- MANUAL AND RECORD
DRAWINGS THE FOLLOWING POINTS WILL NEED TO BE CONSIDERED
! TIMESCALE FOR PRODUCTION WILL BE NEEDED INCLUDING DATES FOR THE START OF THE
SERVICES INSTALLATION COMMENCEMENT OF COMMISSIONING AND THE ISSUING OF DRAFT
MANUALS AND DRAWINGS4HIS COULD BE EXPRESSED AS A SET NUMBER OF WEEKS
BEFORE THE ANTICIPATED DATE OF PRACTICAL COMPLETION
! SYSTEM FOR CHANGE CONTROL WILL BE NEEDED TO HELP ENSURE THAT THE INDIVIDUALS
APPOINTED TO PRODUCE THE /- MANUAL AND RECORD DRAWINGS WILL TAKE
ACCOUNT OF ANY CHANGES TO SERVICES THAT TEND TO OCCUR DURING INSTALLATION
Detailed guidance for the )T WILL ALSO BE IMPORTANT TO CREATE A PROCEDURE FOR CHECKING THE PRODUCTION OF
specifying and procuring or THE /- MANUALS AT SPECIFIC POINTS DURING THE PROJECT )T MIGHT ALSO BE USEFUL
O&M manuals is provided in
Parts 2 and 3. TO DEFINE THE DEGREE OF DEFICIENCY IN /- CONTENT THAT WOULD BE CONSIDERED
SERIOUS ENOUGH TO DELAY COMPLETION4HIS WOULD BE ACCOMPANIED BY A
© BSRIA BG 1/2007
Part 1
PROVISION MAKING THE PRODUCERS OF THE /- MANUAL AND RECORD DRAWINGS
RESPONSIBLE FOR THE COST OF MAINTENANCE DURING THE PERIOD BETWEEN PRACTICAL
COMPLETION AND APPROVAL OF THE COMPLETED MANUALS AND RECORD DRAWINGS
/NCE ALL THE REQUIREMENTS FOR THE /- MANUAL AND RECORD DRAWINGS HAVE
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Electrical installations
,AYOUT DRAWINGS SHOULD INDICATE
● #ABLE ORIGIN PATH DESTINATION LOADING CONDUCTOR METAL AND SIZE INSULATION
TYPE AND COLOUR IF REQUIRED FOR IDENTIFICATION NUMBER OF CORES IN CABLE
NUMBER OF CABLES IN TRUNKING
● 7HETHER CABLES CONDUIT AND TRUNKING ARE CONCEALED IN WALL CHASES SCREED
CAST in-situ OR RUN ON THE SURFACE
● $ISTRIBUTION SWITCHGEAR
● $ISTRIBUTION BOARDS
● 3INGLE AND THREE PHASE WIRING AND CABLE ROUTES INCLUDING SUB CIRCUITS
● %ARTH TAPES
© BSRIA BG 1/2007
● #ABLES PROVIDING SPECIALIST EARTH CIRCUITS
● %MERGENCY LIGHTING
Mechanical installations
,AYOUT DRAWINGS SHOULD SHOW
● 4HE INSTALLATION OF MECHANICAL SERVICES INCLUDING THE SIZE AND ROUTE OF DUCT
WORK AND PIPEWORK
● 4HE ARRANGEMENT OF PLANT IN PLANT ROOMS INCLUDING THE IDENTITY SIZE AND
RATING OF PLANT
$ETAILED WIRING AND CONTROLS DRAWINGS SHOULD BE PROVIDED FOR ALL EQUIPMENT
SUPPLIED UNDER THE MECHANICAL CONTRACT WHICH SHOULD INDICATE
© BSRIA BG 1/2007
Part 1
● 4HE ORIGIN ROUTE AND DESTINATION OF EACH CABLE
● 4HE CONDUCTOR SIZE AND NUMBER OF CORES INCLUDING SPARE CORES INSULATION
TYPE AND RATING NAME AND NUMBER OF RELEVANT British Standards OR INDUSTRY
CODES WITH WHICH THE CABLE COMPLIES
© BSRIA BG 1/2007
4HE EXTENT OF THE COMMISSIONING PROCEDURES SHOULD BE IDENTIFIED WITHIN A
METHOD STATEMENT DRAWN UP BY THE DESIGNER INSTALLER OR COMMISSIONING
SPECIALIST AND AGREED BY ALL THREE4HIS WILL ENABLE THE APPROPRIATE ALLOWANCE TO
BE INCLUDED IN THE BUILDING CONTRACTORS PROGRAMME 0ROVISION SHOULD BE MADE
IN THE METHOD STATEMENT FOR WITNESSING RESULTS AND FOR PRODUCING
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
/N MANY PROJECTS THE TIME SPAN BETWEEN PURCHASING BUILDING SERVICES PLANT
AND THE HANDOVER OF A BUILDING CAN RUN INTO MANY MONTHS OR EVEN YEARS )N
THESE CASES MANUFACTURERS WARRANTIES MAY EXPIRE BEFORE THEIR EQUIPMENT IS
BROUGHT INTO OPERATION )F THIS CAN BE ANTICIPATED AN EXTENDED WARRANTY MAY
BE AVAILABLE THROUGH PAYMENT OF AN ADDITIONAL PREMIUM TO THE SUPPLIER
! FAILURE ON A CLIENTS PART TO ENSURE THAT BUILDING SERVICES ARE OPERATED AND
MAINTAINED IN AN EFFECTIVE MANNER DURING THE DEFECTS LIABILITY PERIOD MAY
DIMINISH THE RESPONSIBILITY OF BOTH THE MAIN CONTRACTOR AND INSTALLATION
CONTRACTORS TO MAKE GOOD ANY LATENT DEFECTS4O AVOID THIS SITUATION
ARRANGEMENTS FOR MAINTENANCE SHOULD BE IN PLACE WELL IN ADVANCE OF PRACTICAL
COMPLETION
© BSRIA BG 1/2007
Part 1
!N EDITABLE
Checklist for information planning VERSION OF Form
is ATTACHED
Action
Suggested
Actioned or submitted by Comments TO THIS PDF
responsibility
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Go to page 1
Have the required scope and content
Design team and
for the O&M manual and record
client
drawings been established?
© BSRIA BG 1/2007
1.11 Pre-handover duties
$URING THE RUN UP TO PRACTICAL COMPLETION AND DURING THE PERIOD FOLLOWING
HANDOVER THE CLIENT OR CLIENT REPRESENTATIVE WILL NEED TO CONSIDER A NUMBER OF
ISSUES
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● 4HE CLIENT IS ADVISED OF THE ANTICIPATED HANDOVER DATE AND MAY BE INVITED TO
INSPECT THE SITE WITH THE DESIGN TEAM ANDOR THE DESIGN TEAM LEADER
● $RAFT /- MANUALS AND RECORD DRAWINGS ARE CHECKED AND APPROVED
● !LL COMMISSIONING WORK AND REQUIRED TESTS AND EXAMINATIONS ARE COMPLETED
INCLUDING DOCUMENTATION
● 4HE HEALTH AND SAFETY FILE AND OTHER DOCUMENTATION IS PASSED TO THE CLIENT
● !RRANGEMENTS ARE AGREED BETWEEN THE CLIENT AND CONTRACTOR FOR DEALING WITH
FAULTS DURING THE DEFECTS LIABILITY PERIOD WHICH REQUIRE IMMEDIATE ATTENTION
● 4OWARDS THE END OF THE DEFECTS LIABILITY PERIOD A LIST OF OUTSTANDING DEFECTS IS
COMPILED BY THE CLIENTS REPRESENTATIVE AND ISSUED AS AN INSTRUCTION TO THE
CONTRACTOR
● 4HE REMAINDER OF THE RETENTION FUND IS RELEASED WHEN ALL LISTED OUTSTANDING
DEFECTS HAVE BEEN MADE GOOD
● 4HE FINAL ACCOUNT DETAILS THE ADJUSTMENT OF ALL THE PRIME COSTS AND
PROVISIONAL SUMS PLUS ALL THE VARIATIONS
© BSRIA BG 1/2007
Part 1
● ! FINAL CERTIFICATE IS ISSUED BY ARCHITECT OR PROJECT MANAGER WHEN ALL THE LISTED
OUTSTANDING DEFECTS HAVE MADE GOOD AND THE ACCOUNT AGREED
4HE EXAMINATION OF LIFTS AND PRESSURE SYSTEMS CANNOT TAKE PLACE UNTIL THEY ARE
FULLY COMMISSIONED BY THE INSTALLATION CONTRACTOR OR COMMISSIONING ENGINEER
&URTHER LIFT EXAMINATIONS ARE REQUIRED AT SIX MONTHLY INTERVALS WHILE THE
FREQUENCY OF PRESSURE SYSTEM EXAMINATIONS WILL DEPEND ON A 7RITTEN 3CHEME
OF %XAMINATION
4HE RESPONSIBILITY FOR INSURING BUILDING SERVICES SYSTEMS PASSES TO THE CLIENT
WHEN THE POINT OF PRACTICAL COMPLETION IS REACHED )F A CLIENT WISHES TO TAKE
UP INSURANCE FOR PARTICULAR SYSTEMS OR EQUIPMENT ARRANGEMENTS SHOULD BE
MADE WELL IN ADVANCE OF THE ANTICIPATED DATE OF PRACTICAL COMPLETION4HIS WILL
ALLOW TIME FOR THE DESIGNATED INSURANCE COMPANY TO CARRY OUT ANY NECESSARY
SURVEYS AND EXAMINATIONS
7HERE APPLICABLE THE CLIENT WILL NEED TO ENSURE THAT THE ORGANISATIONS
DESIGNATED PERSONNEL ATTEND ANY TRAINING SESSIONS )T IS ADVISABLE THAT A RECORD IS
KEPT OF ALL PERSONNEL WHO ATTEND INCLUDING ANY DETAILS OF ANY CERTIFICATES OF
COMPETENCE THAT MAY BE ISSUED
3UFFICIENT TIME SHOULD BE ALLOWED PRIOR TO HANDOVER FOR CHECKING THE DRAFT
/- MANUAL AND RECORD DRAWINGS4HIS TASK IS NORMALLY CARRIED OUT BY THE
CONSULTING ENGINEER IN THE CAPACITY OF THE CLIENTS PROFESSIONAL ADVISOR
© BSRIA BG 1/2007
1.14 Commissioning information
)T IS IMPORTANT THAT THE CLIENT KEEPS A DETAILED RECORD OF ANY WORK CARRIED OUT
BY CONTRACTORS DURING THE DEFECTS LIABILITY PERIOD IN CASE OF SUBSEQUENT
DISPUTES4HIS RECORD SHOULD INCLUDE
● !NY SUBSEQUENT DAMAGE TO OTHER PLANT AND SYSTEMS CAUSED AS A RESULT OF THE
DEFECTS
Go to 27 The Construction (Design and 4HE MAJORITY OF THE INFORMATION PASSED TO THE CLIENT AT HANDOVER WILL FORM A
Management) Regulations 2007 PART OF THE HEALTH AND SAFETY FILE AS REQUIRED BY THE Construction (Design and
are covered in Part 2
Management) Regulations 2007 AND WILL CONSIST OF A WIDE VARIETY OF DOCUMENTS
AND DRAWINGS 3PECIFIC ELEMENTS MAY INCLUDE THE FOLLOWING
● %XAMINATION REPORTS
© BSRIA BG 1/2007
Part 1
● #OMMISSIONING INFORMATION
● #ONTRACTUAL DOCUMENTATION
5NDER THE Construction (Design and Management) Regulations , CLIENTS ARE
REQUIRED BY LAW TO ENSURE THAT THE HEALTH AND SAFETY FILES ARE KEPT SECURELY AND
ARE AVAILABLE FOR INSPECTION BY ANY PERSON WHO MAY NEED ACCESS TO THEM )T IS
IMPORTANT THAT CLIENTS CONSIDER HOW INFORMATION WILL BE INDEXED OR FILED AND
THAT SOMEONE IS GIVEN THE RESPONSIBILITY FOR IMPLEMENTING REVISIONS
© BSRIA BG 1/2007
Form 2: Sample checklist for planning information required at practical completion.
!N EDITABLE
VERSION OF Form Checklist for practical completion
is ATTACHED
TO THIS PDF Action Actioned or
(The order and need for the actions Suggested responsibility submitted by, Comments
Go to page 1 listed below will var y between projects) and date
Has the health and safety authority Design team and client
been approached to determine any
required inspections?
Have licences been obtained for the Design team and client
storage of hazardous chemicals?
Has all the commissioning work been Design team, client, installation contractor
completed, and has an appropriately and commissioning engineer
signed witnessing document been
provided?
Have all the required test certificates Design team, client, installation contractor
been issued? and commissioning engineer
Have operator training sessions taken Design team, client, installation contractor
place and details of attendance and and commissioning engineer
certificates of competence awarded
been recorded?
Have the fire systems and means of Installation contractor, equipment supplier,
escape been inspected and approved? and designated fire authority
A fire risk assessment must be
undertaken
Have the listed outstanding defects Design team and installation contractor
been rectified to acceptable
standards?
Have all the meter readings and fuel Installation contractor and client
stocks been recorded?
Have all the required tools, spares, Design team and installation contractor
and consumables been issued, and an
inventor y provided?
Have the completed and semi- Design team and client and installation
complete record drawings been contractor
issued and checked?
Has the Health and Safety File been Planning super visor
compiled, checked and issued?
© BSRIA BG 1/2007
Part 1
Form 3: Checklist of building services certificates for mechanical systems.
!N EDITABLE
Checklist of building services certificates VERSION OF Form
is ATTACHED
Mechanical systems Suggested format of the Submitted by Received by Comments TO THIS PDF
cer tificate and guidance and date and date Go to page 1
Escalator test certificate Format suggested in HSE
Guidance Note PM45
examination
© BSRIA BG 1/2007
Form 4: Checklist of building services certificates for electrical systems.
!N EDITABLE Checklist of building services certificates
VERSION OF Form
is ATTACHED Electrical systems Suggested format of the Submitted by Received by
TO THIS PDF cer tificate and guidance and date and date
Comments
Go to page 1
IEE electrical systems test certificates Forms of completion and
inspection certificate to
IEE Regulations (BS 7671)
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● 2ECORD OR AS BUILT DRAWINGS AND PLANS USED AND PRODUCED THROUGHOUT THE
CONSTRUCTION PROCESS ALONG WITH DESIGN CRITERIA
© BSRIA BG 1/2007
Part 1
Form 5: Documentation to be held by the building owner or occupier.
A log detailing smoke extract tests Fire Safety Order 2005; BS 5588
A log detailing fire hose reels and the test for portable fire In accordance with BS 5306 to meet the requirements of the Fire Safety Order
extinguishers 2005
A log detailing escape-route pressurisation tests Fire Safety Order 2005; BS 5577-4
Examination certificates and reports for lifts and lifting equipment, and Lifting Operations Lifting Equipment Regulations 1998; Pressure Safety Systems
pressure systems and vessels Regulations 2000
Management of Health and Safety at Work Regulations 1999 (if not already
Risk assessment records for plant and systems
covered by COSHH Regulations)
Building ser vices operating and maintenance information including Section 2 and 6 of the Health and Safety at Work Act 1974; Construction
emergency procedures (Design and Management) Regulations 2007, Building Regulations Par t L2 2006
Record drawings for building ser vices installation Section 2 and 6 of the Health and Safety at Work Act 1974
Record of insulation and earthing tests Institute of Electrical Engineers Wiring Regulations 16th Edition 1991; BS 7671
Water authority discharge of waste certificate Water Authority and National Rivers Authority
© BSRIA BG 1/2007
Design Build
Concept Technical Services
Specifications Project Management
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Operation elementa
consulting
Handover
Facilities Management Compliance
Carbon Footprinting Validation
Feedback Log Books
Energy Reduction Programs O & MS
Post Occupancy Evaluations
&HUWLfiFDWH1R)6
www.elementaconsulting.com
Part 2
5NDER 3ECTIONS AND OF THIS Act AS AMENDED BY THE Consumer Protection Act
1987 DESIGNERS MANUFACTURERS AND IMPORTERS OR SUPPLIERS OF PLANT AND SYSTEMS
HAVE A DUTY TO PROVIDE ADEQUATE OPERATING INFORMATION FOR THE USER TO ENSURE
THAT THE PLANT OR SYSTEM WILL BE SAFE AND WITHOUT RISK TO HEALTH WHEN IN USE
4HIS SHOULD INCLUDE DETAILS OF ANY MAINTENANCE REQUIRED FOR CONTINUED SAFE
OPERATION
3ECTIONS AND OF THE Health and Safety at Work Act IMPLY THAT BUILDING OWNERS
MUST POSSESS ADEQUATE OPERATING INFORMATION FOR THE OPERATION AND
MAINTENANCE OF BUILDING SERVICES4HE PRIMARY ITEMS OF LEGISLATION THAT APPLY
ARE
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
CO ORDINATOR AND A COMPETENT CONTRACTOR TO BE THE PRINCIPAL CONTRACTOR
4HE #$- CO ORDINATOR ACTS AS THE HEALTH AND SAFETY CO ORDINATOR DURING THE
PLANNING STAGE WHILE THE PRINCIPAL CONTRACTOR IS RESPONSIBLE FOR CO ORDINATING
HEALTH AND SAFETY DURING CONSTRUCTION4HIS DIVISION IS REFLECTED IN THE
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
$URING THE PLANNING STAGE THE CLIENT MUST ENSURE THAT THE #$- CO ORDINATOR
ALLOCATES SUFFICIENT TIME AND RESOURCES TO ENSURE THAT THE DUTIES IMPOSED BY THE
Regulations CAN BE ACHIEVED4HE CLIENT ALSO HAS A DUTY TO PROVIDE KNOWN
INFORMATION REGARDING THE CONDITION OF ANY PREMISES WHERE THE CONSTRUCTION
WORK WILL TAKE PLACE
!S PART OF DESIGN CONSIDERATIONS DESIGNERS MUST ENSURE THAT THEIR DESIGN WORK
INCLUDES ADEQUATE REGARD FOR SAFETY OF ALL PERSONS INVOLVED IN THE CONSTRUCTION
AND SUBSEQUENT CLEANING AND MAINTENANCE OF A STRUCTURE AND ITS SERVICES
4HE #$- CO ORDINATOR MUST ENSURE THAT THE OTHER PARTIES ARE AWARE OF THEIR
OBLIGATIONS AND MUST ALSO PROVIDE THEM WITH ADEQUATE ADVICE4HE #$- CO
ORDINATOR MUST ALSO ENSURE THAT ANY DESIGN WORK INCLUDES ADEQUATE
CONSIDERATION TO THE REQUIREMENTS DETAILED ABOVE &INALLY THE #$- CO
ORDINATOR MUST ENSURE THAT A (EALTH AND 3AFETY &ILE IS PREPARED IN RESPECT OF
EACH STRUCTURE AND PASSED TO THE CLIENT UPON COMPLETION OF THE WORK
4HE PRINCIPAL CONTRACTOR MUST ENSURE THAT EVERY CONTRACTOR AND EVERY
EMPLOYEE AT WORK ON THE PROJECT CO OPERATES WITH EACH OTHER AND COMPLIES
WITH THE HEALTH AND SAFETY PLAN4HE PRINCIPAL CONTRACTOR IS REQUIRED TO PROVIDE
THE #$- CO ORDINATOR WITH ALL RELEVANT INFORMATION WHICH MAY BE REQUIRED
BY THE PLANNING SUPERVISOR FOR THE PURPOSES OF THE HEALTH AND SAFETY FILE
4HE Approved Code of Practice FOR THE Construction (Design and Management)
Regulations STATES THAT THE HEALTH AND SAFETY FILE PROVIDES INFORMATION NEEDED
DURING FUTURE CONSTRUCTION WORK4HIS INCLUDES CLEANING MAINTENANCE
ALTERATIONS REFURBISHMENT AND DEMOLITION
4HE Approved Code of Practice STATES THAT THE HEALTH AND SAFETY FILE SHOULD INCLUDE
INFORMATION RELEVANT TO THE HEALTH AND SAFETY OF FUTURE CONSTRUCTION WORK4HE
LEVEL OF DETAIL SHOULD BE PROPORTIONATE TO THE RISKS4HE INFORMATION SHOULD COVER
● 2ESIDUAL HAZARDS AND HOW THEY HAVE BEEN DEALT WITH FOR EXAMPLE SURVEYS OR
OTHER INFORMATION CONCERNING ASBESTOS CONTAMINATED LAND WATER BEARING
STRATA AND BURIED SERVICES
● !NY HAZARDS ASSOCIATED WITH THE MATERIALS USED FOR EXAMPLE HAZARDOUS
SUBSTANCES LEAD PAINT OR SPECIAL COATINGS WHICH SHOULD NOT BE BURNT OFF
© BSRIA BG 1/2007
Part 2
● )NFORMATION AND AS BUILT DRAWINGS OF THE STRUCTURE ITS PLANT AND EQUIPMENT
SUCH AS THE MEANS OF SAFE ACCESS TO AND FROM SERVICE VOIDS FIRE DOORS AND
COMPARTMENTATION
! KEY AREA IN WHICH THE COSHH Regulations AFFECT BUILDING SERVICES IS IN THE
PREVENTION OR CONTROL OF legionella BACTERIA WHICH CAN CAUSE LEGIONNAIRES
DISEASE4HE SERVICES THAT PRESENT A RISK ARE
● %VAPORATIVE CONDENSERS
● #OOLING TOWERS
● 3PRAY HUMIDIFIERS
● 3PRINKLER SYSTEMS
4HE /- INFORMATION SUPPLIED WITH NEWLY INSTALLED WATER SYSTEMS WILL ASSIST
THE TASK OF CARRYING OUT A RISK ASSESSMENT! WRITTEN SCHEME FOR MINIMISING THE
RISK WILL NEED TO BE PRODUCED4HE SCHEME SHOULD INCLUDE
● 4HE STORAGE CAPACITIES AND DESIGN TURNOVER RATE FOR COLD WATER CISTERNS AND
HOT WATER STORAGE AND SEMI STORAGE PLANT
● 4HE HEAT RECOVERY TIME FOR HOT WATER STORAGE AND SEMI STORAGE PLANT
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
SHOULD DETAIL IN EASILY UNDERSTOOD TERMS OPERATION AND MAINTENANCE
PROCEDURES THAT ENABLE PLANT OPERATORS TO CARRY OUT THEIR DUTIES SAFELY AND
EFFECTIVELY
● 4HE MANUALS SHOULD INCLUDE EQUIPMENT AS FITTED AND REPRESENT THE SYSTEM AS
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
2ISKS TO HEALTH ASSOCIATED WITH A BUILDING ARE WIDER THAN legionella4HE (3%
Approved Code of Practice L5 FOR THE COSHH Regulations PROVIDES GUIDANCE
CONCERNING THE DOCUMENTATION REQUIREMENTS RELATING TO RISK ASSESSMENTS4HE
AMOUNT OF INFORMATION THAT EMPLOYERS SHOULD RECORD WILL BE PROPORTIONATE TO
THE RISKS POSED BY THE WORK7HERE A WORK ACTIVITY INVOLVING EXPOSURE TO A
HAZARDOUS SUBSTANCE POSES LITTLE OR NO RISK THE EMPLOYER NEED ONLY RECORD THAT
● 4HE SUBSTANCES TO WHICH THE EMPLOYEES ARE OR ARE LIKELY TO BE EXPOSED AND
THE FORM IN WHICH THEY OCCUR
© BSRIA BG 1/2007
Part 2
7HERE THE WORK CONCERNED PRESENTS MORE OF A RISK TO HEALTH THE SIGNIFICANT
FINDINGS OF THE ASSESSMENT SHOULD COMPRISE A MORE COMPREHENSIVE RECORD )T
SHOULD INCLUDE THE ITEMS FROM THE FOLLOWING LIST
● (AZARDS AND RISKS THE SUBSTANCES PRESENT UNDER NORMAL CONDITIONS OF USE AND
IN CIRCUMSTANCES OF AN UNFORESEEN INCIDENT ACCIDENT OR EMERGENCY WHICH
COULD RESULT IN AN UNCONTROLLED RELEASE OF THE SUBSTANCE
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Environmental Protection Act 1990
4HE Environmental Protection Act PLACES OBLIGATIONS ON ALL WHO PRODUCE CARRY
KEEP TREAT OR DISPOSE OF CONTROLLED WASTE ! KEY REQUIREMENT IS THAT ALL PERSONS
TO WHICH THE Act APPLIES MUST
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● 0REVENT ANOTHER WHOM THEY MAY KNOW OR NOT KNOW FROM ILLEGALLY KEEPING
TREATING OR DISPOSING OF THEIR WASTE
"UILDING OWNERS AND OCCUPIERS MUST HAVE A PROCEDURE FOR THE HANDLING AND
DISPOSAL OF WASTE WHICH THEY GENERATE4HIS INCLUDES WASTE FROM BUILDING
SERVICES SYSTEMS SUCH AS REFRIGERANTS WASTE OIL AND CHEMICALS AND FLUORESCENT
TUBES !S PART OF THIS PROCEDURE A RECORD OF THE WASTE THAT HAS BEEN TRANSFERRED
MUST BE KEPT INCLUDING DETAILS OF THE AUTHORISED WASTE HANDLER OR TRANSPORTER
! SEASON TICKET MIGHT BE USED FOR EXAMPLE FOR THE WEEKLY OR DAILY COLLECTIONS
OF WASTE FROM SHOPS OR COMMERCIAL PREMISES OR THE REMOVAL OF A LARGE HEAP OF
WASTE BY MULTIPLE LORRY TRIPS (OWEVER A SEASON TICKET SHOULD NOT EXTEND FOR A
PERIOD OF MORE THAN MONTHS FROM THE DATE ON WHICH THE FIRST OF THE
TRANSFERS SUBJECT TO THE ARRANGEMENTS TAKES PLACE
Factories Act 1961, and the Offices, Shops and Railway Premises
Act 1963
4HESE TWO Acts HAVE LARGELY BEEN SUPERSEDED BY THE Health and Safety at Work
Act AND ITS ASSOCIATED REGULATIONS IN PARTICULAR THE Workplace (Health, Safety and
Welfare) Regulations
4HE Order FIRMLY PLACES THE RESPONSIBILITY FOR FIRE SAFETY MEASURES ON A
RESPONSIBLE PERSON AND OUTLINES ALL THE MEASURES THAT MUST BE TAKEN TO ENSURE
THE SAFETY OF ALL PEOPLE UNDER THE DUTY OF CARE OF THE RESPONSIBLE PERSON EITHER
DIRECTLY OR INDIRECTLY!T THE SAME TIME IT ALLOWS THE ENFORCING AUTHORITY USUALLY
THE FIRE AUTHORITY TO MAKE SURE THE Order IS ENACTED WHICH MAY INCLUDE LEGAL
ENFORCEMENT MEASURES AND TO SET PENALTIES IF IT IS NOT
© BSRIA BG 1/2007
Part 2
&OR ORGANISATIONS THAT EMPLOY FIVE OR MORE PEOPLE THE SIGNIFICANT FINDINGS
OF A FIRE RISK ASSESSMENT MUST BE RECORDED )N LARGER AND MORE COMPLEX
PREMISES IT IS BEST TO KEEP A DEDICATED RECORD OF ALL MAINTENANCE OF FIRE
PROTECTION EQUIPMENT AND TRAINING
3ECTION OF Fire Safety Assessment for Offices and Shops GIVES THE FOLLOWING
GUIDANCE ON RECORDING PLANNING INFORMING INSTRUCTING AND TRAINING
Your records should be kept in a specified place on the premises (for example, in the
management’s office), and should include:
● Details of any significant findings from the fire risk assessment and any action
taken (see part 1, section 4.1)
● Testing and checking of escape routes, including final exit locking mechanisms such
as panic devices, emergency exit devices and any electromagnetic devices
● Testing and maintenance of fire extinguishers, hose reels, and fire blankets etc
● If appropriate, testing and maintenance of other fire safety equipment such as fire-
suppression systems and smoke control systems
● Maintenance and audit of any systems that are provided to help the fire and
rescue service
● All alterations, tests, repairs and maintenance of fire safety systems, including
passive systems such as fire doors.
● The competence, qualifications and status of the persons responsible for carrying
out inspections and tests
● The results of periodic safety audits, reviews, inspections and tests, and any
remedial action taken
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
● All incidents and circumstances which had the potential to cause accidents and monitor
subsequent remedial actions; and
● A record of the building use, the fire prevention and protection measures in place and
high-risk areas.
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
…fire safety means information relating to the design and construction...and the services,
fittings and equipment provided in or in connection with the building, or extension, which
will assist the responsible person to operate and maintain the facility with reasonable fire
safety.
&OR CLARITY THE GUIDANCE IS GIVEN IN TERMS OF SIMPLE AND COMPLEX BUILDINGS BUT
THE LEVEL OF DETAIL REQUIRED WILL VARY FROM BUILDING TO BUILDING AND SHOULD BE
CONSIDERED ON A CASE BY CASE BASIS &OR COMPLEX BUILDINGS FURTHER GUIDANCE IS
AVAILABLE IN BS 5588-12:2004 Fire precautions in the design, construction and use of
buildings: Managing fire safety Annex A Fire Safety Manual
!SSESSMENTS MADE FOR THE PURPOSES OF THE COSHH Regulations WILL NOT NEED
TO BE REPEATED UNDER The Management of Health and Safety at Work Regulations.
3AFETY INFORMATION RELATING TO BUILDING SERVICES IS AN IMPORTANT ELEMENT OF
COMPREHENSIVE /- MANUALS AND WILL ASSIST IN THE TASK OF CARRYING OUT RISK
ASSESSMENTS FOR BUILDING SERVICES INSTALLATIONS
© BSRIA BG 1/2007
Part 2
)N MANY CASES EMPLOYERS AND THE SELF EMPLOYED WILL ALSO NEED TO RECORD
SUFFICIENT DETAIL OF THE ASSESSMENT ITSELF SO THAT THEY CAN DEMONSTRATE THAT THEY
HAVE CARRIED OUT A SUITABLE AND SUFFICIENT ASSESSMENT4HIS RECORD OF THE
SIGNIFICANT FINDINGS WILL ALSO FORM A BASIS FOR A REVISION OF THE ASSESSMENT
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
4HE EMPLOYER OR SELF EMPLOYED PERSON NEEDS TO REVIEW THE RISK ASSESSMENT IF
DEVELOPMENTS SUGGEST THAT IT MAY NO LONGER BE VALID OR CAN BE IMPROVED )N
MOST CASES IT IS PRUDENT TO REVIEW RISK ASSESSMENTS AT REGULAR INTERVALS4HE TIME
BETWEEN REVIEWS IS DEPENDENT ON THE NATURE OF THE RISKS AND THE DEGREE OF
CHANGE LIKELY IN THE WORK ACTIVITY4HESE REVIEWS SHOULD FORM PART OF THE
STANDARD MANAGEMENT PROCESS
● 0RESSURISED GASES AND FLUIDS WHICH ARE KEPT UNDER A PRESSURE GREATER THAN
BAR GAUGE AND WILL FLASH TO GAS IF RELEASED TO THE ATMOSPHERE
O
● 0RESSURISED HOT WATER ABOVE #
4HE Pressure Systems Safety Regulations 2000 CONTAIN SPECIFIC REQUIREMENTS FOR
MANUFACTURERS AND DESIGNERS OF PRESSURE SYSTEMS AS DEFINED ABOVE TO PROVIDE
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
● 4EST CERTIFICATES AND CERTIFICATES OF CONFORMITY FROM MANUFACTURERS AND
EXAMINATION BODIES
4HE INTERVALS MUST REFLECT A DEGREE OF RISK ASSOCIATED WITH EACH PART AND ENSURE
THAT SUFFICIENT EXAMINATIONS ARE CARRIED OUT TO IDENTIFY AT AN EARLY STAGE ANY
DETERIORATION OR MALFUNCTION WHICH IS LIKELY TO ADVERSELY AFFECT THE SAFETY OF
THE SYSTEM
)T IS THE RESPONSIBILITY OF THE OWNER OR USER TO DEFINE THE SCOPE OF THIS SCHEME
SUCH AS THE PARTS OF THE PRESSURE SYSTEM THAT SHOULD BE INCLUDED4HE SCHEME
MUST BE PRODUCED OR APPROVED BY SOMEONE DEEMED TO BE A COMPETENT PERSON
● 4HE NATURE OF THE EXAMINATION REQUIRED INCLUDING THE INSPECTION AND TESTING
TO BE CARRIED OUT ON ANY PROTECTIVE DEVICES
● 7HERE APPROPRIATE THE NATURE OF ANY EXAMINATION NEEDED BEFORE THE SYSTEM
IS FIRST USED
© BSRIA BG 1/2007
Part 2
4O ENSURE THAT THESE REQUIREMENTS ARE MET THE Provision and Use of Work
Equipment Regulations 1998 REQUIRES EMPLOYERS TO
"Y WAY OF EXAMPLE THE Approved Code of Practice AND GUIDANCE ON THE
Regulations CONTAINS A NON DEFINITIVE LIST OF EQUIPMENT THAT IS SUBJECT TO THE
Regulations )NCLUDED IN THIS LIST ARE COOLING TOWERS AND PRESSURE VESSELS FROM
WHICH IT CAN BE INTERPRETED THAT BUILDING SERVICES EQUIPMENT CAN GENERALLY BE
CLASSED AS WORK EQUIPMENT
4HE Code STATES THAT WRITTEN INSTRUCTIONS CAN INCLUDE THE INFORMATION PROVIDED
BY MANUFACTURERS OR SUPPLIERS OF WORK EQUIPMENT IN THE FORM OF INSTRUCTION
SHEETS OR MANUALS AND TRAINING MANUALS -ANUFACTURERS AND SUPPLIERS HAVE A
DUTY TO PROVIDE SUFFICIENT INFORMATION INCLUDING DRAWINGS TO ENABLE THE
CORRECT INSTALLATION SAFE OPERATION AND MAINTENANCE OF THE WORK EQUIPMENT
)NFORMATION AND WRITTEN INSTRUCTIONS SHOULD COVER
● !LL HEALTH AND SAFETY ASPECTS ARISING FROM THE USE OF THE WORK EQUIPMENT
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
AMENDED AND EXTENDED EXISTING PROVISIONS IN THE ORIGINAL Act INCLUDING
● -AKING IT EASIER FOR DISABLED PEOPLE TO RENT PROPERTY AND FOR TENANTS TO
MAKE DISABILITY RELATED ADAPTATIONS
● -AKING SURE THAT PRIVATE CLUBS WITH OR MORE MEMBERS CANNOT KEEP
DISABLED PEOPLE OUT JUST BECAUSE THEY HAVE A DISABILITY
● %XTENDING PROTECTION TO COVER PEOPLE WHO HAVE ()6 CANCER AND MULTIPLE
SCLEROSIS FROM THE MOMENT THEY ARE DIAGNOSED
● %NSURING THAT DISCRIMINATION LAW COVERS ALL THE ACTIVITIES OF THE PUBLIC SECTOR
"USINESSES AND ORGANISATIONS ARE CALLED SERVICE PROVIDERS AND INCLUDE SHOPS
RESTAURANTS LEISURE CENTRES AND PLACES OF WORSHIP
4HE REASON FOR THE NEED OF NOTIFICATION IS THE POTENTIAL FOR THE Legionella
Pneumophila BACTERIUM TO GROW IN RECIRCULATORS AND WATER SUPPLY SYSTEMS4HE
MAIN PURPOSE OF THE REQUIREMENT IS TO ASSIST INSPECTORS IN INVESTIGATING Legionella
OUTBREAKS THOUGHT LIKELY TO HAVE ARISEN FROM WET COOLING TOWERS OR EVAPORATIVE
CONDENSERS
You should record the major findings of your risk assessment, and your action plan.The
major findings are your estimates of daily personal noise exposure and peak noise
© BSRIA BG 1/2007
Part 2
exposure, your analysis of the risks and whether they are as low as reasonably practicable,
any other information on which you based the evaluation of risks and the decisions on
actions required under the Noise Regulations.The record will provide some evidence for the
decisions that you made to comply with the law. A minimum adequate record will include
details of:
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● The workplaces, areas, jobs or people included in the assessment, including a description
of the work going on
● The daily personal noise exposures of the employees or groups of employees concerned
● If noise measurements have been made, relevant details of the measurements, including the
person(s) responsible for carrying them out
● The name of the person(s) responsible for making the risk assessment
4HE Approved Code of Practice L108 ALSO STATES THAT YOU SHOULD KEEP AN UP TO
DATE HEALTH RECORD FOR EACH INDIVIDUAL AS LONG AS THEY ARE UNDER HEALTH
SURVEILLANCE4HESE RECORDS SHOULD INCLUDE
7HERE A VISITING SERVICE CONDUCTS THE TESTING THE RESULTS SHOULD BE MAINTAINED
BY THE EMPLOYER SEPARATE FROM PERSONNEL RECORDS
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
2.2 The content of operating and maintenance manuals
Go to page 91 Part 5 includes advice on system 4HE SPECIFICATION SHOULD BE DRAFTED TO ENSURE THAT THE MANUAL MEETS THE NEEDS
fine-tuning, and describes a range OF THE END USER )T SHOULD INCLUDE GUIDANCE ON THE LIKELY COMPETENCE OF
of empirical feedback techniques
that can be used to identify POTENTIAL USERS WITH DETAILS OF TRAINING AND QUALIFICATIONS WHERE APPROPRIATE
problem areas and any occupant
dissatisfaction. ! BUILDING /- MANUAL SHOULD BE A COMBINATION OF FUNCTION AND SYSTEM
BASED STRUCTURED INFORMATION ARRANGED IN A LOGICAL AND HIERARCHICAL STRUCTURE AS
LAID DOWN IN BS 4884:Part 1:1992 Specification for Presentation of Essential
Information PARTICULARLY Part 2:1993 Guide to Content AND Part 3:1993 Guide to
Presentation.
7ITH THE INCREASING DEMAND FOR LOW ENERGY BUILDINGS AND TECHNOLOGIES LIKE
PASSIVE ENERGY RECOVERY IT IS INCREASINGLY IMPORTANT THAT THIS INFORMATION IS
INCLUDED7HERE A BUILDING IS LET TO TENANTS RESPONSIBLE FOR OPERATING AND
MAINTAINING THE SERVICES THE CLIENT MUST ENSURE THAT DESIGN INTENT AND
INFORMATION ON THE BUILDINGS INTENDED USE IS MADE AVAILABLE
&UNCTION BASED MANUALS SHOULD AIM TO DESCRIBE THE USER OPERATION OF LOCAL
SYSTEMS SUCH AS OVERHEAD PROJECTORS ROOM LIGHTING AND LOCAL ENVIRONMENTAL
CONTROLS
Copies of Controls for End Users – 4HE "UILDING #ONTROLS )NDUSTRY !SSOCIATION "#)! IS A GOOD SOURCE OF
a Guide for Good Design and INFORMATION ON WHAT CONSTITUTES USABLE CONTROLS4HE "#)! "32)! AND THE
Implementation are available from
www.bsria.co.uk/bookshop. A PDF 5SABLE "UILDINGS 4RUST 5"4 HAVE COLLABORATED ON PRODUCING NEW GUIDANCE
version is available to BSRIA FOR DESIGNERS MANUFACTURERS AND INSTALLERS OF USER CONTROLS4HIS GUIDANCE IS
Members as a free download AIMED AT DESIGNERS CLIENTS INSTALLERS AND CONTROLS COMPANIES
System-based manuals
3YSTEM BASED MANUALS SHOULD OUTLINE THE OPERATION OF EACH BUILDING SERVICES
SYSTEM INSTALLED TOGETHER WITH MANUFACTURERS DATA AND COMMISSIONING
INFORMATION 3YSTEM BASED MANUALS ARE USUALLY DELIVERED AS PART OF PROJECT
HANDOVER DOCUMENTATION
© BSRIA BG 1/2007
Part 2
-ANUALS PREPARED TO #LASSES ! AND " WILL ONLY COVER RUDIMENTARY /-
INFORMATION AND RECORD DRAWINGS AS REQUIRED BY THE Health and Safety at Work
Act etc 1974 AND WOULD ONLY PROVIDE INFORMATION ADEQUATE FOR RELATIVELY SMALL
OR SIMPLE INSTALLATIONS -ANY RECOMMENDATIONS GIVEN IN THIS GUIDE WOULD ALSO
NOT GENERALLY APPLY TO #LASS ! AND " MANUALS 0REPARATION OF MANUALS TO THIS
LEVEL CAN REASONABLY UNDERTAKEN BY THE INSTALLATION CONTRACTOR WITH NO OTHER
SUPPORT
#LIENT ORGANISATIONS THAT HAVE IN HOUSE OPERATION AND MAINTENANCE EXPERTISE Part 5 includes advice on system Go to page 91
SHOULD ENSURE THAT THIS EXPERTISE HAS AN INPUT DURING THE BRIEFING PROCESS4HIS fine-tuning, and describes a range
of empirical feedback techniques
WILL ALLOW A VALUABLE INTERCHANGE OF IDEAS AND WILL ESTABLISH SPECIFIC NEEDS4HE that can be used to identify
FEEDBACK METHODS DESCRIBED IN 0ART CAN BE VERY USEFUL IN IDENTIFYING THE problem areas and any occupant
NEEDS OF BUILDING USERS dissatisfaction
4HE OPERATING AND MAINTENANCE STRATEGY DEVELOPED ON THE BASIS OF THESE BROAD
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
OBJECTIVES SHOULD IDENTIFY AIMS AND RESPONSIBILITIES AND PERHAPS MOST IMPORTANT
IN THIS CONTEXT THE AMOUNT OF INFORMATION NEEDED AND BY WHOM AND IN WHAT
DETAIL IT IS REQUIRED 3UCH PLANNING IS CRUCIAL WHEN DETERMINING THE CONTENT
AND PRESENTATION OF MANUALS
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Go to page 105 Labour resources for maintenance ! MORE DETAILED MAINTENANCE PLAN DESCRIBING HOW THE OBJECTIVES WILL BE
are shown in Appendix A ACHIEVED NEEDS TO TAKE ACCOUNT OF COST LIMITATIONS THE PLANNED LIFE OF THE
VARIOUS SERVICES RISK ANALYSIS PLANT BREAKDOWN POLICY THE AVAILABILITY OF PLANT
FOR MAINTENANCE SPECIALIST SUPPORT AND ISSUES TO DO WITH CLIENT IMAGE SUCH AS
EXTERNAL FLOODLIGHTING AND WATER FEATURES
4HE USERS OF /- MANUALS CAN BE DIVIDED INTO THREE BROAD CATEGORIES
PEOPLE WHO OCCUPY A BUILDING PEOPLE RESPONSIBLE FOR MANAGING THE OPERATION
AND MAINTENANCE OF A BUILDING AND PEOPLE WHO MAINTAIN A BUILDING %ACH OF
THESE GROUPS OF PEOPLE WILL HAVE SPECIFIC INTERESTS ABILITIES AND EXPERTISE AND
EACH WILL REQUIRE SOMETHING DIFFERENT OF THE /- MANUAL
4HESE VARYING REQUIREMENTS HAVE IMPLICATIONS FOR BOTH THE CONTENT AND THE
PRESENTATION OF AN /- MANUAL4HE NEEDS OF THE DIFFERENT USER GROUPS MUST
ALWAYS BE MET )NFORMATION SHOULD BE AVAILABLE TO EACH GROUP IN THE
APPROPRIATE DETAIL AND PRESENTATION SHOULD ENSURE THAT THIS INFORMATION CAN
READILY BE FOUND AND EXTRACTED )N SOME INSTANCES IT MAY BE SUFFICIENT FOR A
SINGLE DOCUMENT TO BE DIVIDED SO THAT THE RELEVANT PORTIONS CAN BE ISSUED
SEPARATELY IN OTHERS IT MAY BE NECESSARY TO PRODUCE A SEPARATE DOCUMENT FOR
EACH USER GROUP
4HERE ARE THREE MAIN SOURCES OF INFORMATION FOR /- MANUALS DESIGN
ENGINEERS EQUIPMENT MANUFACTURERS AND SUPPLIERS AND INSTALLATION CONTRACTORS
© BSRIA BG 1/2007
Part 2
4HE AMOUNT OF INFORMATION IN ANY /- MANUAL WILL VARY MORE WITH THE
NATURE AND COMPLEXITY OF A PROJECT RATHER THAN ITS SIZE4WO PROJECTS OF GREATLY
DIFFERING SIZE BUT WITH THE SAME RANGE OF ENGINEERING SERVICES MAY BE SIMILAR IN
TERMS OF THE VARIETY OF COMPONENTS AND MATERIALS4HE MANUAL FOR EACH PROJECT
WOULD THEREFORE BE OF SIMILAR CONTENT DIFFERING ONLY IN THE QUANTITIES OF
MATERIALS AND SYSTEM COMPONENTS
!LTHOUGH THE DEGREE OF DETAIL WILL VARY ALL /- MANUALS FOR BUILDING SERVICES For heating systems BSEN 12170
INSTALLATIONS NEED TO CONTAIN CERTAIN TYPES OF INFORMATION BS 4884 LISTS NINE and BSEN 12171 provide a
CATEGORIES OF INFORMATION TO BE INCLUDED 4HOSE THAT APPLY TO BUILDING SERVICES recommended content
depending on whether the
/- MANUALS INCLUDE system requires a trained
operator or not.
● 4HE PURPOSE OF THE INSTALLATION
● )NSTALLATION RECORDS
● -AINTENANCE SCHEDULES
4HE FOLLOWING SECTIONS SET OUT A PRESENTATIONAL SEQUENCE FOR AN /- MANUAL
DESCRIBING WHAT IS REQUIRED UNDER EACH HEADING
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
2.8 Contents, structure and layout
4HIS SECTION IS A GUIDE TO THE CONTENTS STRUCTURE AND LAYOUT OF THE MANUAL )T
ENABLES THE READER TO COMPREHEND THE SCOPE AND PURPOSE OF THE DOCUMENT
AND HELPS TO IDENTIFY WHERE SPECIFIC INFORMATION CAN BE OBTAINED
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● $ATES FOR THE START OF THE INSTALLATION FOR HANDOVER PRACTICAL COMPLETION AND
FOR THE EXPIRY OF THE DEFECTS LIABILITY PERIOD
&OR EACH ITEM OF PLANT AND EQUIPMENT INSTALLED WITHIN THE BUILDING AND
CONTAINED IN THE LIST OF SERVICES COVERED BY THE /- MANUAL COPIES OF THE
FOLLOWING DOCUMENTS SHOULD ALSO BE PROVIDED WHERE APPLICABLE
● 4EST CERTIFICATES
Overall purpose
4HIS SECTION SHOULD PROVIDE A GENERAL OVERVIEW OF THE ORIGINAL DESIGN INTENT
AVAILABLE IN OUTLINE FROM THE DESIGN BRIEF AND IN DETAIL FROM THE SPECIFICATION
© BSRIA BG 1/2007
Part 2
● 4HE PARAMETERS AND CONDITIONS WITHIN WHICH IT HAS BEEN DESIGNED TO OPERATE
A SYSTEM
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● 4HE TYPE OF EACH SERVICE GAS ELECTRICITY AND WATER REQUIRED TO OPERATE A
SYSTEM
Description
4HIS SECTION SHOULD PROVIDE A DETAILED DESCRIPTION OF EACH ENGINEERING SYSTEM
INSTALLED )T SHOULD INCLUDE
● $ESIGN DATA BASIC DESIGN PARAMETERS BASIC ASSUMPTIONS MADE DURING DESIGN
Equipment schedule
4HE TYPE MODEL NUMBER AND SERIAL NUMBER OF ALL COMPONENT ITEMS WITHIN THE Appendix B provides a simple Go to page 107
SYSTEM SHOULD BE LISTED TOGETHER WITH THE NAMES OF THEIR RESPECTIVE checklist of engineering services in a
building
MANUFACTURERS OR SUPPLIERS
Spares policy
4HIS SECTION SHOULD OFFER A GUIDE TO THE SETTING UP OF A SPARES FACILITY INCLUDING
RECOMMENDED STOCK LEVELS )T SHOULD BE PREPARED AFTER CONSULTATION WITH THE
OCCUPIER REGARDING THE CONSEQUENCES OF FAILURE RISK TO CORE BUSINESS AND THE
PERIOD OF ACCEPTABLE DOWNTIME )T SHOULD ALSO TAKE INTO ACCOUNT SUPPLIERS
RECOMMENDATIONS AS GIVEN ABOVE!GAIN THOSE ITEMS NORMALLY HELD IN STOCK BY
A SUPPLIER OR FOR WHICH A REFURBISHMENT SERVICE IS AVAILABLE SHOULD BE CLEARLY
IDENTIFIED
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Commissioning data
4HE RESULTS OF ALL COMMISSIONING WORK AND ASSOCIATED TESTS SHOULD BE GIVEN
4HIS SHOULD INCLUDE
● -EASURED DATA
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● -EASUREMENT POINTS
Operation
)NSTRUCTIONS MUST BE GIVEN FOR THE SAFE AND EFFICIENT OPERATION OF EACH
ENGINEERING SYSTEM UNDER NORMAL AND EMERGENCY CONDITIONS4HESE WILL BE IN
ADDITION TO MANUFACTURERS LITERATURE FOR PLANT ITEMS AND SHOULD INCLUDE
● 4HE MEANS BY WHICH ANY POTENTIALLY HAZARDOUS PLANT CAN BE MADE SAFE
● &ORMS FOR RECORDING PLANT RUNNING HOURS ENERGY CONSUMPTION AND ENERGY
COSTS
Maintenance instructions
4HE MANUFACTURERS RECOMMENDATIONS AND INSTRUCTIONS FOR MAINTENANCE MUST
BE DETAILED FOR EACH ITEM OF PLANT AND EQUIPMENT INSTALLED #LEAR DISTINCTION
SHOULD BE MADE BETWEEN PLANNED TASKS PREVENTATIVE MAINTENANCE AND WORK
DONE ON A CORRECTIVE BASIS )NSTRUCTIONS SHOULD BE GIVEN ON EACH OF THE
FOLLOWING
© BSRIA BG 1/2007
Part 2
Maintenance schedules
-AINTENANCE SCHEDULES SHOULD BE PROVIDED FOR ALL PREVENTIVE MAINTENANCE
TASKS4HESE SHOULD BE BASED ON BOTH MANUFACTURERS RECOMMENDATIONS AND
OTHER AUTHORITATIVE SOURCES SUCH AS STATUTORY OR MANDATORY REQUIREMENTS 4HE
SCHEDULES SHOULD INCLUDE
● )NSPECTIONS
● %XAMINATIONS
● 4ESTS
● !DJUSTMENTS
● #ALIBRATION
● ,UBRICATION
● 0ERIODIC OVERHAUL
Modification information
-ODIFICATIONS ARE AUTHORISED CHANGES WHICH AFFECT SAFETY RELIABILITY OPERATION
OR MAINTENANCE OF A SYSTEM OR ANY OF ITS COMPONENTS
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Fault finding
0ROCEDURES FOR THE LOGICAL DIAGNOSIS AND CORRECTION OF FAULTS SHOULD BE
PROVIDED
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Lubrication
! SCHEDULE OF ALL PLANT REQUIRING LUBRICATION SHOULD BE PROVIDED TOGETHER WITH
MANUFACTURERS RECOMMENDATIONS ON THE TYPE OF LUBRICANTS AND THE METHOD
AND FREQUENCY OF APPLICATION7HERE A TYPE OF LUBRICANT IS IDENTIFIED BY
PRODUCT NAME A GENERIC REFERENCE SUCH AS A British Standard SHOULD ALSO BE
GIVEN )NFORMATION MUST ALSO BE PROVIDED ON SPECIAL REQUIREMENTS FOR THE
HANDLING AND STORAGE OF LUBRICANTS
Disposal instructions
7HERE RELEVANT INFORMATION SHOULD BE PROVIDED ON THE FOLLOWING DETAILS
● !NY KNOWN DANGERS LIKELY TO ARISE DURING THE DISPOSAL OF SPECIFIC ITEMS OF
PLANT OR EQUIPMENT TOGETHER WITH THE NECESSARY PRECAUTIONS AND SAFETY
MEASURES
Emergency information
!N IMPORTANT FEATURE OF ANY MANUAL IS THE EMERGENCY INFORMATION4HIS
INFORMATION SHOULD BE LOCATED AT THE END OF THE DOCUMENT FOR EASE OF
REFERENCE AND SHOULD INCLUDE NAME ADDRESS TELEPHONE AND FAX NUMBER AND
E MAIL ADDRESSES OF THE APPROPRIATE CONTRACTS IN THE EVENT OF FIRE THEFT OR
BURGLARY AND GAS ELECTRICITY OR WATER FAILURES AND LEAKS )T SHOULD ALSO LIST FIRMS
OR STAFF TO CONTACT IN THE EVENT OF THE FAILURE OR BREAKDOWN OF PLANT SUCH AS
© BSRIA BG 1/2007
Part 2
LIFTS BOILERS OR PUMPS7HERE APPLICABLE THE LOCATION OF FIRE FIGHTING A suggested format for this Go to page 55
EQUIPMENT HYDRANTS AND RISING MAINS SHOULD BE DESCRIBED 3PECIAL ATTENTION information is given in Figure 1
SHOULD ALSO BE GIVEN TO HAZARDS PARTICULAR TO THE BUILDING $EPENDING ON CLIENT
POLICY A NOTE OF SECURITY INSTALLATIONS MAY ALSO BE INCLUDED
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Manufacturers’ literature
! COMPLETE SET OF ALL MANUFACTURERS LITERATURE SHOULD BE PROVIDED FOR THE PLANT
AND EQUIPMENT INSTALLED AND ASSEMBLED FOR EACH BUILDING SERVICES SYSTEM
● 0ROTECTIVE MEASURES
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Form 6: BSRIA’s proposed format for recording contractual and legal details.
!N EDITABLE
VERSION OF Form Site and ownership details
is ATTACHED
TO THIS PDF
Name of building
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Go to page 1
Address
Freeholder name
Address
Contact name
Telephone numbers
Contact e-mail
Leaseholder details
Leaseholder name
Address
Details of lease
Date signed
Duration of lease
Period of notice
Name
Address
Telephone numbers
Contact
Consent obtained
Date of consent
Contract number
© BSRIA BG 1/2007
Part 2
Form 6: Continued.
!N EDITABLE
Gas supply authority VERSION OF Form
is ATTACHED
Name TO THIS PDF
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Go to page 1
Address
Telephone numbers
Contact
Consent obtained
Date of consent
Contract number
Name
Address
Telephone numbers
Contact
Consent obtained
Date of consent
Contract number
Design team
Name
Address
Telephone number
Contact name
e-mail address
Design consultants
Name
Address
Telephone number
Contact name
e-mail address
Continued overleaf
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Form 6: Continued.
!N EDITABLE
VERSION OF Form Main installation contractor
is ATTACHED
TO THIS PDF Name
1
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Go to page
Address
Telephone number
Contact name
e-mail address
Name
Address
Telephone number
Contact name
e-mail address
Name
Address
Telephone number
Contact name
e-mail address
Name
Address
Telephone number
Contact name
e-mail address
Name
Address
Telephone number
Contact name
e-mail address
© BSRIA BG 1/2007
Part 2
Form 6: Continued.
!N EDITABLE
Relevant dates VERSION OF Form
is ATTACHED
Date contract signed with main contractor TO THIS PDF
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Go to page 1
Date work commenced on site
e-mail address
Item
Guarantee
Expiry date
Contact
Name
Address
Telephone numbers
e-mail address
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Form 7: BSRIA’s proposed format for recording emergency information.
!N EDITABLE
VERSION OF Form Contacts in case of emergency
is ATTACHED
TO THIS PDF Fire
Go to page 1 Contact name
Address
Contact name
Address
Lifts
Contact name
Address
Contact name
Address
Generators
Contact name
Address
Name
Address
© BSRIA BG 1/2007
Part 2
P
10
4HE MANUAL FORMAT WILL BE INFLUENCED BY THE SPECIFIC INSTALLATION AND THE See BS EN 12171:2002 Procedure
INTENDED USERS OF THE MANUALS SUCH AS THE BUILDINGS OWNER THE OCCUPIERS for the Preparation of Documents for
Operation, Maintenance and Use -
THOSE RESPONSIBLE FOR MANAGING OPERATIONS AND MAINTENANCE OR THE MAINTAINERS Heating Systems Requiring a Trained
THEMSELVES !S DIFFERENT PARTS OF THE MANUAL ARE LIKELY TO APPLY TO DIFFERENT Operator.
CATEGORIES OF USER THE DOCUMENTATION SHOULD BE APPROPRIATELY SUBDIVIDED AND
ASSEMBLED TO MEET THEIR NEEDS
4HE MAINTENANCE MANAGER WILL REQUIRE A MUCH MORE DETAILED BRIEF INCLUDING
● %QUIPMENT SCHEDULES
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
● 3PARES POLICY
● -AINTENANCE GENERAL
● #OMMISSIONING DATA
● -ANUFACTURERS LITERATURE
4HE CONTENTS OF THE MANUAL CAN EITHER BE ASSEMBLED TO TAKE INTO ACCOUNT THE
REQUIREMENTS OUTLINED ABOVE OR CAN BE ORGANISED INTO A SERIES OF MANUALS &OR
LARGE AND COMPLEX INSTALLATIONS THERE WILL BE A NEED TO CREATE SEPARATE
DOCUMENTS FOR THE FOLLOWING
● %QUIPMENT SCHEDULES
● /PERATION
● -AINTENANCE
● -ANUFACTURERS LITERATURE
)N EVERY CASE THE TYPES OF MANUAL REQUIRED AND THE MOST APPROPRIATE LAYOUT
SHOULD BE IDENTIFIED EARLY IN THE PLANNING PROCEDURES4HE DETAILS SHOULD BE
COVERED IN THE SPECIFICATION
© BSRIA BG 1/2007
Part 2
Figure 2: Contractual
relationships and information
Fee agreement flows in the installation process.
Employer
Contract Brief
Design team
Main
contractor Specification
Specification Contract
Commissioning data Commissioning data
Services
installation Equipment
Contract subcontractor suppliers
Contract data
of order
or order
Vendor
data Purchase Specialist
Commissioning orders author
specialist
! DESIGN TEAM WILL NOT ONLY PREPARE A DESIGN AND A SPECIFICATION BUT MAY ALSO
BE INVOLVED IN SELECTING CONTRACTORS AND IN MONITORING THE CONSTRUCTION
PROCESS THIS MAY INCLUDE ADVISING THE CLIENT WHEN MONEY SHOULD BE RELEASED
TO CONTRACTORS /THER CONTRACTUAL RELATIONSHIPS ARE POSSIBLE &OR EXAMPLE A
BUILDING SERVICES INSTALLATION SUBCONTRACTOR MAY HAVE DESIGN RESPONSIBILITIES AND
BECOME A MEMBER OF A DESIGN TEAM
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
WHO IN TURN ESTABLISHES CONTRACTS AND PLACES ORDERS WITH MANUFACTURERS AND
SUPPLIERS TO OBTAIN MATERIALS AND EQUIPMENT 5NDER THE TERMS OF THE CONTRACT
LAID DOWN IN THE SPECIFICATION AN INSTALLATION SUBCONTRACTOR MAY ALSO BE
EXPECTED TO SUBCONTRACT CERTAIN TASKS FOR EXAMPLE THE COMMISSIONING OF THE
INSTALLED EQUIPMENT AND THE PREPARATION OF /- MANUALS4HIS WILL INVOLVE
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
© BSRIA BG 1/2007
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Table 2: The division of responsibilities for the procurement of O&M manuals, within the design, construct and handover processes.
Activity Client Employer/occupier Design team Main contractor Services installation Specialist author
contractor
Brief Use occupant surveys and Provision of information Set energy targets based
design quality tools to and agreement with the on installed loads and
identify user needs, such design team expected hours of
as space, comfort, storage, occupation.
and controls usability
Production Consider occupant Specify information for Agree subcontractor Issue copy orders and Progress information from
information guidance, training, helpdesk construction, and provide programme for the release manufacturers' details to designers, installers,
services, and labelling for to specialist author of information to specialist the specialist author manufacturers
user controls such as author
lighting and blinds
© BSRIA BG 1/2007
develops, and match based on altered acquisition of information
against the original design specifications and/or
intent expected hours of use
Setting to work Receive and comment on Receive and distribute Operate and maintain Make draft manuals
draft manuals draft manuals for use and plant and equipment in available to main
approval accordance with draft contractor, Continue
manuals familiarisation to conform
draft procedures
59
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
60
Table 2: Continued.
Activity Client Employer Design team Main contractor Services installation Specialist author
contractor
Handover Extract system concepts Receive final manuals, issue Handover installation to Issue final manuals,
from the manuals and re- to relevant staff client and/or maintenance Confirm date for issue of
package information in organisation plans, drawings
formats that occupants
can understand (such as
mouse mats, and desk
blotters)
© BSRIA BG 1/2007
Fine-tuning through Use empirical feedback Monitor building Modify O&M manuals to
post-handover methods to refine building performance for the good reflect results of fine
suppor t systems and controls and of the client, and for tuning and record results
solve user problems. Avoid design team education of surveys
dysfunction, waste and
user alienation
Part 2
Content
4HE SPECIFICATION MUST GIVE ADEQUATE DETAIL OF THE CONTENT REQUIRED FOR THE
MANUAL4ABLE OUTLINES A SUITABLE PRO FORMA WHICH COULD BE COMPLETED BY A
CONSULTING ENGINEER AND INCLUDED AS PART OF A SPECIFICATION )T PROVIDES DETAILS
FOR THE ORGANISATIONS NORMALLY THE INSTALLATION CONTRACTOR AND THE SPECIALIST
AUTHOR RESPONSIBLE FOR PREPARING THE MANUAL4HE SPECIFICATION SHOULD COVER
● 4HE EXTENT OF THE INFORMATION REQUIRED IN THE MANUAL IN TERMS OF BOTH THE
SYSTEMS INSTALLED AND THE INFORMATION REQUIRED FOR EACH SYSTEM
● 7HERE THE RESPONSIBILITY LIES FOR PREPARING AND COLLECTING THE VARIOUS ITEMS OF
INFORMATION THIS MAY BE THE CONSULTING ENGINEER AND THE DESIGN TEAM THE
INSTALLATION SUBCONTRACTORS OR THE EQUIPMENT MANUFACTURER )TEMS NOT REQUIRED
CAN BE DELETED
Timescales
4IMESCALES FOR PREPARING MANUALS SHOULD BE SET AT THE START OF THE PROJECT4HE
KEY DATES IN THE PROJECT PROGRAMME SHOULD BE INCLUDED IN THE SPECIFICATION
AND COMMUNICATED TO THOSE TENDERING FOR PREPARATION OF THE MANUALS4HE
SPECIALIST AUTHOR WILL NEED TO KNOW
● 4HE INSTALLATION START DATE4HIS DETERMINES THE EARLIEST TIME AT WHICH THE
AUTHOR CAN MAKE SITE INSPECTIONS AND BECOME FAMILIAR WITH THE INSTALLATION
● 4HE START DATES FOR INSPECTING AND COMMISSIONING $RAFT DOCUMENTATION MAY
BE REQUIRED AT THIS STAGE ALTHOUGH THIS MAY BE PHASED IF COMMISSIONING IS
PHASED
● 4HE SETTING TO WORK DATE4HIS IS THE DATE AT WHICH THE FULL DRAFT
DOCUMENTATION SHOULD BE AVAILABLE
4HE PROCESS REQUIRES THE ALLOCATION OF ADEQUATE TIME AND RESOURCES FOR
CHECKING AND APPROVING THE DRAFT DOCUMENTATION )F THE HANDOVER DATE IS ALSO
THE FINAL DATE FOR COMPLETION OF THE MANUAL A LEAD IN PERIOD SHOULD BE
ALLOWED FOR CHECKING AND APPROVAL $EPENDING ON THE SIZE AND COMPLEXITY OF
THE PROJECT AND THE TIME OF YEAR THIS PROCESS COULD TYPICALLY TAKE EIGHT WEEKS
)T SHOULD BE TREATED AS A PROJECT MILESTONE IN ITSELF
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
&OR PHASED COMPLETION AND HANDOVER OF SYSTEMS OR AREAS IN A BUILDING IT WILL
BE NECESSARY TO SPECIFY THOSE PARTS OF THE MANUAL THAT ARE TO BE AVAILABLE IN
EITHER DRAFT OR FINAL FORM AND BY WHAT DATES
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
2.12 Confidentiality
2.13 Copyright
4HE ORIGINATOR OF A MANUAL NEEDS TO BE SURE THAT ONLY MATERIAL IS USED WHERE
COPYRIGHT HAS EITHER BEEN ASSIGNED OR WHICH DOES NOT APPLY )T IS NOT
APPROPRIATE TO CUT AND PASTE MATERIAL FROM ANY SOURCE WITHOUT FIRST SEEKING
REPRODUCTION RIGHTS
© BSRIA BG 1/2007
Part 2
!S A VERY GENERAL GUIDE COSTS FOR THE PREPARATION OF /- MANUALS AMOUNT TO
BETWEEN AND PERCENT OF THE TOTAL CONTRACT VALUE4HE ACTUAL PROPORTION
WILL VARY BOTH WITH THE EXTENT AND COMPLEXITY OF THE SERVICES TO BE INCLUDED
IN THE MANUAL AND INVERSELY WITH THE SIZE OF THE INSTALLATION %CONOMIES OF SCALE
ENCOUNTERED IN LARGER INSTALLATIONS CAN REDUCE THE FIGURE BELOW PERCENT
WHILE FOR SMALL INSTALLATIONS COSTS MAY BE AS HIGH AS ONE TO TWO PERCENT !
SURVEY CONDUCTED BY "32)! DURING THE PREPARATION OF THE GUIDE FOUND BROAD
ACCEPTANCE OF THESE FIGURES
! MORE ACCURATE ESTIMATE OF COSTS CAN BE OBTAINED WHEN GOING OUT TO TENDER
)T IS RECOMMENDED THAT A MINIMUM OF THREE /- MANUAL PREPARERS SHOULD BE
INVITED TO TENDER ! COMPREHENSIVE SPECIFICATION SHOULD BE PREPARED AND
SUBMITTED TO EACH TENDERER TO ENSURE THAT ALL ESTIMATES ARE BASED ON THE
STANDARDS SET BY INDIVIDUAL AUTHORS THESE CAN VARY CONSIDERABLY
4HE ROUTE FOR OBTAINING MANUALS MAY BE A SEPARATE PRIME COST SUM ! PRIME
COST SUM CAN BE DEFINED AS A SUM ENTERED IN A BILL OF QUANTITIES BY THE
CONSULTANT BEING PROVIDED TO PAY FOR THE COST TO A CONTRACTOR OF A SPECIFIC
ARTICLE AFTER DEDUCTING ALL DISCOUNTS EXCEPT THE PERCENT DISCOUNT FOR
MONTHLY SETTLEMENT OF ACCOUNTS
4HE AGREEMENT MUST ALSO TAKE INTO ACCOUNT THE LIKELY DURATION OF THE
INSTALLATION PROGRAMME )F A SIGNIFICANT PERIOD MORE THAN TWELVE MONTHS IS
LIKELY TO ELAPSE BETWEEN THE ESTIMATES BEING OBTAINED AND THE PREPARATION OF
THE MANUAL THEN SOME MEANS OF INCREASING THE ESTIMATE TO TAKE ACCOUNT OF
INFLATION WILL NEED TO BE INCORPORATED IN THE CONTRACT
© BSRIA BG 1/2007
HANDOVER, O&M MANUALS, AND PROJECT FEEDBACK
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
64
!N EDITABLE
VERSION OF Form
is ATTACHED
TO THIS PDF
Go to page 1
Form 8: A BSRIA-developed checklist of information sources, based on the National Engineering Specification.
Identify which member of the project team is responsible for procuring the information (Examples in italics) Project details
Code: CE: Consulting engineer IC: Installation contractor EM: Equipment manufacturer
System Equipment Parts identification Commissioning Operation Maintenance Maintenance Fault Lubrication Modification Disposal
schedule and recommended data schedules finding information
spares
Air conditioning
© BSRIA BG 1/2007
Automatic controls
Boilers
Catering
Clocks
Cold water
Communications
Cooling distribution
Dr y/wet risers
Emergency lighting
Form 8: Continued.
System Equipment Parts identification Commissioning Operation Maintenance Maintenance Fault Lubrication Modification Disposal
schedule and recommended data schedules finding information
spares
General lighting
Hot water
Lighting protection
Local controls
LV distribution
LV supply
Mechanical handling
Pressurised water
Solar control
Sprinklers
Steam generators
© BSRIA BG 1/2007
Thermal insulation
Toilet extraction
Transport
Waste disposal
Other systems For guidance on other systems, refer to the suite of design checks for building services, published by BSRIA. Search on www.bsria.co.uk/bookshop
Source code CE: Consultant engineer IC: Installation contractor EM: Equipment manufacturer
65
The Granary, Brockhill Court
MultiLink Solutions Ltd specialise in providing Authoring, Hardcopy and Software Solutions to
the Construction Industry.
Our Authoring and Hardcopy services include the production of Health and Safety Files, Operation
and Maintenance Manuals, Record Drawings and Building Log Books with documents provided in both
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
O&M manuals
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
3.1 Scope
4HIS SPECIFICATION DETAILS THE TYPE AND CONTENT OF TECHNICAL DOCUMENTATION
REQUIRED TO PROVIDE FOR THE SAFE AND EFFICIENT OPERATION AND MAINTENANCE OF
ENGINEERING SERVICES INCLUDING AS FITTED AND OTHER DRAWINGS
-ECHANICAL
%LECTRICAL
0UBLIC HEALTH
&IRE PROTECTION
3ECURITY
#ONTROL
#OMMUNICATION
4RANSPORTATION
0ROCESS
3.2 Definitions
&OR THE PURPOSE OF THIS SPECIFICATION MAINTENANCE TERMS DEFINED IN
BS 3811:1993 HAVE BEEN USED AS FAR AS PRACTICABLE The British Standard Glossary
of Refrigeration, Heating,Ventilation and Air Conditioning Terms BS 5643:1984 SHALL
BE USED AS GUIDANCE FOR DEFINING TERMS IN THE TECHNICAL DOCUMENTATION
© BSRIA BG 1/2007
● 3UPPLIER OF TECHNICAL MANUALS CALLED THE SUPPLIER 4HE ORGANISATION MADE
RESPONSIBLE FOR PROVIDING THE CORRECT DOCUMENTATION EVEN THOUGH THE
ORGANISATION EMPLOYS A SPECIALIST AUTHOR TO SUPPLY THIS OR TO CARRY OUT
ASSOCIATED WORK
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
!BBREVIATIONS SHALL ONLY BE USED ONCE THEIR MEANING HAS BEEN MADE
UNAMBIGUOUS )MPERATIVES SHALL BE USED FOR INSTRUCTIONS REGARDING THE OPERATION
MAINTENANCE AND DISASSEMBLY OF ENGINEERING SERVICES
7HERE POSSIBLE ORIGINAL ARTWORK SHALL BE USED RATHER THAN SECOND OR THIRD
GENERATION SCANS )F ORIGINAL ARTWORK CANNOT BE OBTAINED CONSIDERATION SHALL BE
GIVEN TO REDRAWING DIAGRAMS AND ILLUSTRATIONS
7HERE DIAGRAMS ARE PROVIDED IN ELECTRONIC FORMAT THE RESOLUTION AND FILE
FORMAT OF THE IMAGERY SHALL BE CHECKED FOR SUITABILITY #OMPRESSED FILE FORMATS
SUCH AS *0%' ARE DESIRABLE IN TERMS OF THEIR SMALL FILE SIZE BUT THE IMAGES MAY
© BSRIA BG 1/2007
Part 3
REASONABLE FILE SIZE WITH NO LOSS OF DETAIL AND ENABLE LAYERING )F %03 FILES ARE
PROVIDED THE NAME AND VERSION OF THE ORIGINAL SOFTWARE THAT CREATED THEM SHALL
BE SUPPLIED AND THE /- MANUALS SHALL INCLUDE A FREEWARE %03 VIEWER
3OFTWARE PACKAGE
6ERSION NUMBER
4HE INDEXING AND CROSS REFERENCING INCLUDED IN OTHER PARTS OF THE MANUAL SHALL
BE ARRANGED TO PROVIDE EASY ACCESS TO ANY REQUIRED INFORMATION
Programme
4O ENSURE THAT THE OPERATING AND MAINTENANCE MANUAL IS AVAILABLE WHEN Form 9 shows key dates and Go to page 71
REQUIRED THE PROGRAMME IN &ORM SHOULD BE FOLLOWED &ORM SHOULD BE restraints in the project
programme
PROVIDED IN AN ACCOMPANYING LETTER UNDER )NFORMATION TO 4ENDERERS
Collection of information
4HREE PRINCIPLE SOURCES OF INFORMATION WILL BE USED BY THE SPECIALIST AUTHOR
4HE SPECIALIST AUTHOR WILL BE RESPONSIBLE FOR ENSURING THAT CLOSE LIAISON IS
MAINTAINED WITH EACH OF THESE SOURCES AND THAT THEY ARE AWARE OF THE
INFORMATION REQUIRED BY THE SPECIALIST AUTHOR 3UCH LIAISON WILL BE ARRANGED TO
GIVE ALL PARTIES ADEQUATE TIME TO COLLATE THE NECESSARY INFORMATION
4HE INSTALLATION CONTRACTORS WILL PROVIDE COPIES OF ALL ORDERS FOR PLANT
EQUIPMENT AND SUBLETS DUCTING AND CONTROLLERS TO THE SPECIALIST AUTHOR4HE
SPECIALIST AUTHOR WILL ENSURE THAT THE PERFORMANCE AND TECHNICAL DATA INCLUDED
WITHIN THE MANUAL IS FOR THE ACTUAL EQUIPMENT INSTALLED4HIS IS BEST UNDERTAKEN
BY A SITE INSPECTION
© BSRIA BG 1/2007
THE SPECIALIST AUTHOR
4HE SPECIALIST AUTHOR SHALL USE ALL THE INFORMATION PROVIDED AND SUCH OTHER
INFORMATION BELIEVED TO BE NECESSARY TO PRODUCE A SATISFACTORY OPERATING
MAINTENANCE MANUAL7HERE APPROPRIATE INFORMATION SHALL BE MODIFIED TO
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Reader ability
5PON APPOINTMENT THE SPECIALIST AUTHOR SHALL IDENTIFY FROM THE CLIENTS
PROFESSIONAL ADVISER THE INTENDED MAINTENANCE STRATEGY FOR THE INSTALLATION AND
THE LEVEL OF TECHNICAL COMPETENCE AND COMPREHENSION OF THE PERSONNEL LIKELY
TO BE EMPLOYED4HE SPECIALIST AUTHOR SHALL PREPARE THE MANUAL TO SUIT THIS LEVEL
OF READER 4HE SPECIALIST AUTHOR SHALL ENSURE THAT THE MANUAL STATES THE READERS
ASSUMED LEVEL OF TECHNICAL COMPREHENSION AND COMPETENCE
4HE SPECIALIST AUTHOR WILL PROVIDE TRAINING IN THE USE OF THE MANUAL FOR
SEARCHING FOR SPECIFIC ITEMS SO THAT THE BUILDING OPERATORS WILL BE ABLE TO USE
THEM AFTER THE BUILDING IS HANDED OVER
4HE PERSONNEL EXPECTED TO USE THE MANUAL WILL BE TICK THOSE THAT APPLY
4HE SPECIALIST AUTHOR SHALL SUPPLY THE FIRST DRAFT OF THE MANUAL IMMEDIATELY
PRIOR TO THE COMMISSIONING OF THE INSTALLATION4HE FIRST DRAFT SHALL CONTAIN ALL
THE INFORMATION IDENTIFIED IN THIS SPECIFICATION EXCEPT THAT UNAVAILABLE AT THE
TIME SUCH AS COMMISSIONING TEST RESULTS
4HE NUMBER OF COPIES SUPPLIED OF THE FIRST DRAFT SHALL BE ??????? THREE IF NO
OTHER NUMBER IS ENTERED
4HE FIRST DRAFT SHALL BE SUPPLIED TO THE PROFESSIONAL ADVISER OF THE CLIENT WHO IS
???????????????????????????????????????????????????????????????????????????
4HE PROFESSIONAL ADVISER WILL CHECK THE DRAFT AND RETURN IT TO THE SPECIALIST
AUTHOR WITHIN A PERIOD OF WEEKS STATE EIGHT WEEKS IF NO OTHER TIME
IS STIPULATED FROM THE DATE OF DESPATCH BY THE SPECIALIST AUTHOR TOGETHER WITH
ALL COMMENTS NECESSARY TO OBTAIN A FINAL APPROVED DOCUMENT
4HE MANUAL SHALL FOLLOW THE GUIDANCE AND PRO FORMAS SET OUT IN 0ART OF THE
Go to page 64 See Form 8 checklist "32)! 'UIDE "' Handover, O&M Guides, and Project Feedback
© BSRIA BG 1/2007
Part 3
Presentation
-ANUALS SHALL COMPRISE LOOSE LEAF ! PAGES ON GOOD QUALITY PAPER THAT IS
STRONG ENOUGH TO STAND UP TO HEAVY USE AND SUFFICIENTLY OPAQUE TO AVOID
SHOW THROUGH4HE PAPER WEIGHT SHALL BE AT LEAST GSM
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
,OOSE LEAF FOUR RING BINDERS SHALL BE USED FOR THE BINDING4HESE SHALL BE
CONSTRUCTED FROM PVC COVERED HEAVYWEIGHT CARD $IVIDERS BETWEEN SECTIONS
AND PARTS SHALL USE STEPPED OVERLAPPING PRINTED CARD
Copyright
4HE CLIENT PURCHASING THIS OPERATING AND MAINTENANCE MANUAL SHALL HAVE SOLE
COPYRIGHT TO THE DOCUMENT AND SHALL BE ABLE TO REPRODUCE ANY PART FOR ITS OWN
USE
Form 9: BSRIA model form for information to tenderers. !N EDITABLE 7ORD VERSION Go to page 1
OF &ORM IS ATTACHED
Project programme key dates TO THIS PDF
From To
From To
From To
From To
© BSRIA BG 1/2007
3.6 Updating procedures for operating and maintenance manuals
The value of maintenance guides depends on the degree to which they are kept up to date.
When changes occur to the building concerned or when new information becomes available,
all copies of the maintenance guides should be amended, and they should be reviewed
annually.
&URTHERMORE PARAGRAPH C OF THE Health and Safety at Work etc Act REFERS TO
THE DUTY OF VERY EMPLOYER
● RESPONSIBILITY FOR REGULAR UPDATING LIES WITH THE BUILDING OWNEROPERATOR AND
NOT WITH THE CONSULTING ENGINEER OR INSTALLATION CONTRACTOR RESPONSIBLE FOR
INITIAL PREPARATION OF MANUALS
● BY THE TIME MANUAL UPDATING BECOMES NECESSARY THERE ARE NO LONGER ANY
FORMAL OR SPECIFIC LINKS BETWEEN THE BUILDING OPERATOR THE ORGANISATION THAT
PREPARED THE ORIGINAL MANUAL AND THE ORGANISATIONS THE DESIGN ENGINEER THE
INSTALLATION CONTRACTOR AND THE EQUIPMENT SUPPLIERS THAT PROVIDED THE ORIGINAL
INFORMATION
7HILE UPDATING OF THIS NATURE CAN BE CARRIED OUT AS AND WHEN REQUIRED
BS 8210:1986 Guide to Building Maintenance Management RECOMMENDS AN ANNUAL
REVIEW OF DOCUMENTATION )N THE ABSENCE OF ALTERNATIVE ADVICE THIS
RECOMMENDATION SHOULD BE FOLLOWED AS A FORMAL PROCEDURE TO IDENTIFY
WHETHER MAJOR CHANGES TO AN INSTALLATION HAVE TAKEN PLACE AND WHICH REQUIRES
© BSRIA BG 1/2007
Part 3
/NCE THE NEED FOR UPDATING HAS BEEN ESTABLISHED THERE ARE SEVERAL MEANS BY
WHICH THIS CAN BE DONE
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● UPDATING THE MANUALS CAN BE MADE PART OF THE SPECIFICATION TO THE INSTALLATION
CONTRACTOR WHO MAKES THE ALTERATIONS
!LL THESE OPTIONS WILL INVOLVE A SEPARATE COST TO THE BUILDING OR OPERATOR
© BSRIA BG 1/2007
RYB:KONSULT
ENERGY
ENVIRONMENT
ENGINEERING
RYB Konsult is an international consulting engineering business
specialising in engineering, energy and environmental design.
We are experts in both the design of new energy efficient buildings
and the design of energy efficient improvements to existing
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
buildings.
5<%.RQVXOW
/LQGVH\6WUHHW/RQGRQ(&$+3
7(LQIR#U\ENRQVXOWFRP:ZZZU\ENRQVXOWFRP
Part 4
4HE PROVISION OF A BUILDING LOGBOOK FOR NEW NON DOMESTIC BUILDINGS IS A See Appendix D for the Go to page 111
REQUIREMENT OF Approved Document L2A AND L2B OF THE Building requirements of the 2006 Building
Regulations as they apply to O&M
Regulations4HESE DOCUMENTS PROVIDE GUIDANCE ON MEETING THE LEGISLATIVE manuals and building logbooks
REQUIREMENTS FOR NEW AND EXISTING NON DOMESTIC BUILDINGS4HE FUNDAMENTAL
REQUIREMENTS ARE EXPRESSED IN Approved Document L2B AS
Providing to the owner sufficient information about the building, the fixed building services
and their maintenance requirements so that the building can be operated in such a manner
as to use no more fuel and power than is reasonable in the circumstances.
)N THE CONTEXT OF THE Approved Documents, THERMAL ELEMENTS COVER WALLS FLOORS
AND ROOFS
&OR A NEW BUILDING THE Building Regulations STATE THAT A BUILDINGS LOGBOOK
SHOULD ALSO RECORD THE TARGET EMISSION RATE 4%2 AND BUILDING EMISSION RATE
"%2 ENERGY CALCULATIONS USED DURING THE DESIGN AND CONSTRUCTION OF THE
BUILDING )T RECOMMENDS THAT ELECTRONIC COPIES OF THE INFORMATION BE HELD BY
THE BUILDING OWNER FOR FUTURE USE
4HE LOGBOOK IS INTENDED TO ENABLE THE BUILDING OWNER TO OPERATE THE BUILDING
IN AN ENERGY EFFICIENT MANNER AND IN ACCORDANCE WITH THE DESIGN INTENT )T IS
NOT DESIGNED TO DUPLICATE THE INFORMATION IN THE /- MANUALS4HE /-
MANUALS ARE AIMED AT THE MAINTENANCE PERSONNEL AND ARE NOT DESIGNED FOR THE
OWNERS AND OPERATORS OF THE BUILDING4HEY ARE GENERALLY WRITTEN IN TECHNICAL
TERMS AND MUCH OF THE DETAIL IS REPEATED WITHIN THE HEALTH AND SAFETY FILE AS
The Construction (Design and Go to page 27
Management) Regulations 2007
REQUIRED BY THE Construction (Design and Management) Regulations 2007 #$- are covered in Part 2
"32)! HAS PRODUCED A GENERIC LOGBOOK TEMPLATE4HIS CAN BE SPECIFIED BY !N EDITABLE VERSION OF THE "SRIA Go to page 1
PROPERTY OWNERS TO ENSURE THE STANDARD OF INFORMATION THEY RECEIVE FROM THEIR LOGBOOK TEMPLATE IS ATTACHED TO
THIS PDF.
CONTRACTORS ENABLES THEM TO OPERATE THEIR PROPERTIES EFFICIENTLY
/NLY WHEN OWNERS CAN MONITOR BENCHMARK AND CONTROL ENERGY CAN THEY
EFFECTIVELY MANAGE IT "UILDINGS IN WHICH THE BUILDING SERVICES SYSTEMS ARE WELL
MANAGED ARE MORE LIKELY TO ACCOMMODATE PRODUCTIVE AND SATISFIED OCCUPANTS
© BSRIA BG 1/2007
Go to page 1 !N EDITABLE VERSION OF THE 4HE BUILDING LOGBOOK TEMPLATE AIMS TO PROVIDE THE RIGHT BALANCE BETWEEN
"32)! LOGBOOK TEMPLATE SATISFYING THE Building Regulations AND MAKING THE DOCUMENT USABLE FOR FACILITIES
IS ATTACHED TO THIS PDF
MANAGERS OR MAINTENANCE SERVICE PROVIDERS2EALISTICALLY LARGER BUILDINGS WITH
ON SITE MAINTENANCE STAFF WILL TEND TO STORE MAINTENANCE RELATED DETAILS
SEPARATELY BUT SUCH SITES WOULD STILL BENEFIT FROM A BUILDING LOGBOOK THAT
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
CAPTURES THE DESIGN INTENT AND OUTLINES THE OPERATION OF THE BUILDING ALONG
WITH THE BUILDINGS TARGET ENERGY CONSUMPTION
Boiler plant
● #OMBUSTION EFFICIENCY TESTS
© BSRIA BG 1/2007
Part 4
Space heating
● #OMPARISON OF HEATING PERIODS WITH OCCUPANCY PATTERNS
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● #ALORIFIER INSULATION
© BSRIA BG 1/2007
● 0OTENTIAL FOR HEAT RECOVERY
● %NERGY CONSUMPTION OF FANS AND PUMPS AND POTENTIAL FOR LOWER CONSUMPTION
Controls
Controls for End Users – a Guide for ● /CCUPANT CONTROLS THAT ARE INTUITIVE TO USE
Good Design and Implementation is
available as a free PDF download
to BSRIA Members from ● !PPROPRIATE LEVEL OF TRAINING FOR FACILITIES STAFF IN THE USE OF THE CONTROLS
www.bsria.co.uk/bookshop
● 3YSTEM DEFAULT TO OFF IF SAFE TO DO SO AFTER A DEFINED TIME PERIOD
Building fabric
● )NSULATION STANDARDS OF ROOFS WALLS AND FLOORS
● 'LAZING STANDARDS
● !IR INFILTRATION
General points
2ECOMMENDATIONS FOR ENERGY SAVING MEASURES SHOULD BE SPLIT BETWEEN NO
COSTLOW COST MEASURES MEDIUM COST MEASURE AND HIGH COST MEASURES7HERE
RELEVANT THE FOLLOWING INFORMATION SHOULD BE GIVEN FOR EACH RECOMMENDATION
● $ESCRIPTION OF RECOMMENDATION
● ,OCATION OF RECOMMENDATION
● &UEL TYPE
● !NNUAL SAVINGS
● )MPLEMENTATION COST
© BSRIA BG 1/2007
Part 4
#)"3% TM22 Energy Assessment and Reporting Method PROVIDES PROCEDURES TO TM22 can also be used as a Go to page 98
ALLOW THE ASSESSMENT OF THE ENERGY PERFORMANCE OF A BUILDING TO BE project feedback tool, as
DETERMINED BASED ON METERED ENERGY USE4HE PROVIDED CALCULATION PROCEDURES described in Part 5
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
MAY BE USED AS THE BASIS FOR DETERMINING THE EMISSIONS FOR A BUILDING IN
ACCORDANCE WITH Statutory Instrument 2007/991 SI 2007/991 .
SI 2007/991 CONTAINS REQUIREMENTS FOR LABELLING OF ALL BUILDINGS AT THE TIME OF The requirements of the Energy
CONSTRUCTION SALE OR RENT AND IN SOME CASES FOR LABELS TO BE DISPLAYED4HE Performance of Buildings Directive are
now embodied in Statutory
GUIDANCE THAT FOLLOWS APPLIES MOSTLY TO BUILDINGS REQUIRED TO DISPLAY SUCH Instrument 2007 No 991.
ENERGY LABELS
● !PRIL %NERGY PERFORMANCE CERTIFICATES REQUIRED FOR THE SALE OR RENT OF
BUILDINGS OTHER THAN DWELLINGS WITH A FLOOR AREA OVER M!LSO ENERGY
PERFORMANCE CERTIFICATES REQUIRED ON CONSTRUCTION FOR ALL NON DWELLINGS AND
DISPLAY CERTIFICATES REQUIRED FOR ALL PUBLIC BUILDINGS OVER M
● *ANUARY &IRST INSPECTION OF ALL EXISTING AIR CONDITIONING SYSTEMS OVER
K7 BY THIS DATE
● *ANUARY &IRST INSPECTION OF ALL REMAINING AIR CONDITIONING SYSTEMS OVER
K7 BY THIS DATE
● /PTION " 'ENERAL BUILDING ASSESSMENT OF THE ACTUAL CARBON DIOXIDE EMISSIONS Energy Services Directive 2006/32/
PER UNIT FLOOR AREA BASED ON THE METERED ENERGY USE OF A BUILDING OR SITE EC of the European Parliament
and of the Council of 5 April
WHICH CAN HAVE ZONES OF DIFFERENT TYPES AND NON STANDARD OCCUPANCY AND 2006 on energy efficiency and
ENERGY USES energy services, Official Journal of
the European Union, L 114/64-84
"UILDINGS WILL BE ASSESSED AGAINST BENCHMARKS4HERE MAY BE TWO BENCHMARKS (27 April 2006).
QUOTED ON THE DISPLAY CERTIFICATES &OR AIR CONDITIONED OFFICE BUILDINGS FOR
EXAMPLE A BENCHMARK WILL BE SHOWN FOR NON AIR CONDITIONED BUILDINGS AS WELL
AS A SUB TYPE BENCHMARK FOR AIR CONDITIONED BUILDINGS4HE LATTER WILL ENABLE
THE PERFORMANCE OF AN AIR CONDITIONED BUILDING NOTABLY WHERE AIR
CONDITIONING IS UNAVOIDABLE TO BE COMPARED AGAINST ITS PEER GROUP
© BSRIA BG 1/2007
4HE METHOD CAN MAKE USE OF DATA AVAILABLE FROM A BUILDING LOG BOOK
PRODUCED IN ACCORDANCE WITH #)"3% TM314HE DOCUMENTATION GENERATED BY
THE %XCEL WORKBOOK CAN BE REFERRED TO IN THE BUILDING LOGBOOK ALONG WITH
THE INCLUSION OF SUMMARY DATA
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
The CLG will publish guidance SI 2007/991 REQUIRES AN DISPLAY ENERGY CERTIFICATE TO BE DISPLAYED PROMINENTLY
later in 2007 to enable building IN CERTAIN PUBLIC BUILDINGS4HE DEPARTMENT FOR #OMMUNITIES AND ,OCAL
occupiers to determine their
liabilities and responsibilities for 'OVERNMENT #,' WILL PUBLISH GUIDANCE ENABLING BUILDING OCCUPIERS TO
reporting building energy DETERMINE THEIR LIABILITY UNDER THE LEGISLATION
performance
$ISPLAY ENERGY CERTIFICATES ARE REQUIRED TO INCLUDE
Go to page 112 A draft design of the display ● ! STATEMENT OF THE BUILDINGS ENERGY PERFORMANCE INCLUDING UP TO THREE
energy certificate is shown in YEARS HISTORICAL PERFORMANCE FOR COMPARATIVE PURPOSES
Appendix E
● AN ASSESSMENT OF THIS PERFORMANCE AGAINST APPROPRIATE BENCHMARKS
2) Except where regulation 18(3) applies, on and after 6 April 2008 every occupier of
any building to which this regulation applies must:
(a) have in its possession or control at all times a valid advisory report; and
(b) display at all times a valid display energy certificate in a prominent place clearly visible
to the public.
3) A display energy certificate is valid for a period of 12 months beginning with the
nominated date.
(4) An advisory report is valid for a period of seven years beginning with the date it is
issued.
4HE OPERATIONAL RATING PROCESS MUST BE CARRIED OUT AND ISSUED BY AN ENERGY
ASSESSOR WHO IS ACCREDITED TO PRODUCE ENERGY PERFORMANCE
© BSRIA BG 1/2007
Part 4
● %NERGY AND #/ BENCHMARKS RELATING TO THE STOCK BENCHMARK FOR THE TYPE
OF BUILDING
● "ACKGROUND INFORMATION ON THE METHOD ADOPTED WHO DID IT AND THE INPUT
DATA AND ASSUMPTIONS
● 3TEP #ALCULATE THE OPERATIONAL RATING NO LATER THAN THREE MONTHS AFTER THE
END OF THE PERIOD OVER WHICH THE OPERATIONAL RATING IS CALCULATED
● 3TEP #OMPARE THE INDICATORS WITH THE BENCHMARKS TO GRADE THE BUILDINGS
ENERGY EFFICIENCY
● 3TEP "RING TOGETHER ALL THE RELEVANT DATA ONTO AN ENERGY PERFORMANCE Demonstration versions of an
CERTIFICATE building energy performance
certificate suitable for display are
available at http://online.eplabel.org
4HESE STEPS WILL BE COMBINED IN AN INTEGRATED SYSTEM THAT SATISFIES THE
REQUIREMENTS OF Building Regulations AS THEY APPLY TO %NGLAND AND 7ALES
© BSRIA BG 1/2007
SUCH AS GEOTHERMAL DISTRICT HEATING AND COOLING
RARELY METERED SEPARATELY OR ANY CARBON OFFSETS SUCH AS TREE PLANTING AS THIS
WILL NOT PROVIDE THE INCENTIVE TO SAVE ENERGY AT THE POINT OF USE (OWEVER THE
CERTIFICATION PROCESS WILL CREDIT THE USE OF LOW CARBON ENERGY SOURCES ONSITE
SUCH AS PHOTOVOLTAICS OR BIO FUELS WITH THE CONTRIBUTION CLEARLY IDENTIFIED
4HIS ENSURES THAT THE TOTAL BUILDING ENERGY REQUIREMENT IS DECLARED WHILE THE
USE OF RENEWABLES IS CELEBRATED AS A PERCENTAGE OF THE TOTAL n A VALUABLE
COMPONENT FOR THE REPORTING OF CORPORATE AND SOCIAL RESPONSIBILITY
4HIS APPROACH ALSO INTRODUCES A DYNAMIC TENSION BETWEEN THE USE OF FOSSIL
FUELS AND RENEWABLES )F A BUILDING USES A RELATIVELY HIGH AMOUNT OF RENEWABLE
ENERGY THE TOTAL ENERGY CONSUMPTION MAY INDICATE THAT THE BUILDING IS
INTRINSCALLY INEFFICIENT WHICH WOULD PLACE THE ONUS ON THE BUILDINGS OPERATOR
TO REDUCE ENERGY CONSUMPTION
4HESE LARGER BUILDINGS ALSO INCLUDE MANY OF THE MORE INTENSIVELY USED AND
ENERGY INTENSIVE ONES AND HENCE ACCOUNT FOR MORE THAN HALF OF NON DOMESTIC
ENERGY USE ,ARGER BUILDINGS ALSO TEND TO HAVE DEDICATED MANAGEMENT WHICH
COULD IMPROVE ENERGY PERFORMANCE SUBSTANTIALLY
! HIGH LEVEL OF ANALYSIS MAY ALSO APPLY TO ORGANISATIONS WHO USE THEIR BUILDINGS
INTENSIVELY SUCH AS HIGHER LEVELS OF OCCUPANCY AND USE OF EQUIPMENT OR FOR
LONGER HOURS OF USE SUCH AS THE COMMUNITY USE OF SCHOOLS IN EVENINGS AND AT
WEEKENDS 3OME BUILDINGS ALSO CONTAIN ENERGY INTENSIVE FACILITIES LIKE
RESTAURANTS AND SERVER ROOMS4HESE FACILITIES MAY NOT BE PRESENT IN TYPICAL
BUILDINGS OF THE SAME TYPE OR THEY MAY BE MORE MODEST SO ONLY A MINIMUM
ALLOWANCE MAY BE MADE FOR THEM IN THE BASIC BENCHMARKS ,ARGER FACILITIES WILL
TEND TO LEAD TO A POOR BENCHMARK COMPARISON UNLESS THEY ARE ASSESSED SEPARATELY
Section 18 of SI 2007/991 $ATA GATHERING NEEDS TO BE COMMENSURATE WITH THE REQUIREMENTS OF THE
explains in detail the CERTIFICATION PROCESS $ATA REPORTING MUST BE NO LATER THAN THREE MONTHS AFTER
requirements for displaying THE END OF THE PERIOD OVER WHICH THE OPERATIONAL RATING IS CALCULATED
energy consumption for a
building that has undergone a
change of occupier. /PERATIONAL RATINGS WILL REQUIRE YEAR ON YEAR REPORTING WITH A CERTIFICATE
SHOWING CURRENT AND ENERGY CONSUMPTION FOR A ROLLING THREE YEAR PERIOD
/CCUPIERS OF NEW BUILDINGS FOR WHICH HISTORICAL DATA IS NOT AVAILABLE WILL BE
PERMITTED TO DISPLAY AN OPERATIONAL RATING AFTER THE FIRST YEAR RISING TO THREE
YEARS
© BSRIA BG 1/2007
Part 4
/PERATIONAL RATINGS WILL REQUIRE ACCURATE ENERGY USE INFORMATION TO BE AVAILABLE The British Property Federation
$ATA COLLECTION WOULD BE MUCH EASIER IF ANNUAL ENERGY USE INFORMATION WAS has developed a voluntary energy
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
"OUNDARIES NEED TO BE CLEARLY DEFINED AND TO INCLUDE ALL INSIDE AND OUTSIDE
AREAS ASSOCIATED WITH THE BUILDING AND ITS ENERGY USE AND PRODUCTION SUCH AS
OUTBUILDINGS EXTERNAL LIGHTING FOUNTAINS AND EXTERNAL PLANT SUCH AS A CHILLER
'ENERATION DEVICES OF INTEGRATED RENEWABLE ENERGY SYSTEMS SHOULD BE
CONSIDERED TO BE OUTSIDE THE BOUNDARY SO THEIR INPUTS CAN BE ACCOUNTED FOR
SEE 3TEP .
● 4HE CONDITIONED NET INTERNAL AREA OF THE BUILDING IN TERMS OF ITS HEATED AND
COOLED SPACES EXCLUDING NON HABITABLE CELLARS SI 2007/991 MENTIONS hUSEFUL
AREAv AND IN Part L THIS IS INTERPRETED TO BE GROSS INTERNAL AREA (OWEVER
DIFFERENT DEFINITIONS MAY BE PERMITTED IN DIFFERENT SECTORS SUCH AS NET INTERNAL
AREA FOR RENTED OFFICES
● 4HE NET ANNUAL CONSUMPTION OF ALL OTHER ENERGY SUPPLIES FOR EACH SUPPLY
SEPARATELY
© BSRIA BG 1/2007
4HE ENERGY SOURCES WILL NEED TO BE WEIGHTED FOR THEIR #/ EMISSIONS FOR
EXAMPLE KG#/K7H FOR ELECTRICITY AND KG#/K7H FOR NATURAL
GAS BASED ON THE HISTORICAL WEIGHTING FACTORS APPLYING AT THE TIME OF THE
MEASURED ENERGY USE4HIS WILL BE CONSISTENT WITH VALUES DERIVED FROM THE
RETURNS OF 5+ ELECTRICITY GENERATORS IN THE %5 EMISSIONS TRADING SCHEME
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
)N THE PAST BENCHMARKS FOR WHAT AMOUNTS TO OPERATIONAL RATINGS HAVE BEEN
DERIVED FROM MEASURED ANNUAL ENERGY STATISTICS FOR EACH SECTOR GENERALLY USING A
TYPICAL GRADING TO REPRESENT THE MEDIAN AND A GOOD PRACTICE GRADING OFTEN TO
SIGNIFY THE LOWEST ENERGY USE QUARTILE &OR A FEW SECTORS SUCH AS OFFICES AND
SPORTS CENTRES THESE BUILDING ENERGY BENCHMARKS ARE BROKEN DOWN BY ACTIVITY
ANDOR ENERGY END USE AND EVEN INTO THEIR SEPARATE COMPONENTS CREATING SUB
BENCHMARKS FOR PARAMETERS SUCH AS INSTALLED LIGHTING IN 7ATTS PER SQUARE METRE
PER LUX VENTILATION IN 7ATTS PER LITRE PER SECOND AND SMALL POWER IN 7ATTS
PER WORKSTATION OR 7ATTS PER SQUARE METRE4HESE COMPONENT BENCHMARKS CAN
GIVE DETAILED INSIGHT INTO WHERE TO LOOK FOR ENERGY EFFICIENCY IMPROVEMENTS
● %STABLISHES NATIONAL BENCHMARKS FOR THE REGIONAL AVERAGE CLIMATE FOR THE
BUILDING USING DEGREE DAYS
● )F YEAR ON YEAR COMPARISONS ARE MADE THE OPERATIONAL RATING CORRECTS THE
BUILDINGS ENERGY USE FOR HEATING FOR THE REGIONAL AVERAGE CLIMATE
● ,EVEL #ORRECTING FOR READILY VERIFIABLE EXCEPTIONS WHERE A BUILDING AND ITS
BENCHMARK ARE NOT WELL MATCHED FOR EXAMPLE AN OFFICE WHICH HAS A
SWIMMING POOL 7HERE NECESSARY THE EXCEPTIONAL ITEMS SHOULD BE REVIEWED
© BSRIA BG 1/2007
Part 4
NOT JUST FOR THEIR ENERGY USE BUT ALSO THEIR ENERGY EFFICIENCY AND THE SCOPE FOR
SAVINGS
/PERATIONAL RATINGS WILL USE THE FAMILAR RAINBOW GRAPHIC TO GRADE BUILDING See Appendix E for a draft Go to page 112
ENERGY PERFORMANCE4HE ! ' SCALE PROVIDES IMPORTANT MARKET TRANSFORMATION example of a display energy
certificate.
INCENTIVES 0EOPLE CAN ASK FOR AN ! RATED FRIDGE OR CAR AND SHOULD BE ABLE TO
DO THE SAME FOR THE DESIGN OR USE OF A BUILDING
4HE POSITIONS OF THE SCALE BOUNDARIES ARE IMPORTANT /N THE ONE HAND PLACING
TODAYS TOP PERFORMERS IN BANDS ! OR " WEAKENS THEIR INCENTIVES TO IMPROVE
/N THE OTHER HAND PLACING MOST BUILDINGS IN "ANDS & ' AND ( APPEARS TO
PLACE A GOOD RATING OUT OF REACH4HE RAINBOW SCALE WILL BE CALIBRATED TO COVER
THE WIDE RANGE OF SERVICES EQUIPMENT USED IN BUILDINGS AND WILL REFLECT THE
CATEGORY OF BUILDING BEING ASSESSED SUCH AS NATURALLY VENTILATED OR AIR
CONDITIONED )F EXPERIENCE WITH DOMESTIC APPLIANCES IS ANYTHING TO GO BY
PEOPLE SOON FIND INNOVATIVE WAYS OF IMPROVING PERFORMANCE RADICALLY TO HIGHER
LEVELS THAT WERE ARGUED TO BE ECONOMICALLY IMPOSSIBLE ONLY A FEW YEARS EARLIER
● 3TANDARD LISTS AS ABOVE BUT WITH ADDED COMMENTS ON THE APPLICABILITY OF EACH
MEASURE ITS LIKELY COST EFFECTIVENESS AND ANY OTHER RELEVANT DETAILS4HIS WOULD
SUIT A RAPID ASSESSMENT BUT WOULD NEED TO BE DONE BY AN ACCREDITED EXPERT
© BSRIA BG 1/2007
Step 6: Preparing the operational rating certificate
!N ENERGY CERTIFICATE WILL NEED TO GIVE THE INFORMATION REQUIRED BY SI 2007/
991 IN LINE WITH THE REQUIREMENTS OF THE Energy Performance of Buildings Directive
EPBD 4HE CERTIFICATE MUST CONTAIN OR BE ACCOMPANIED BY
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● !DMINISTRATIVE DATA: THE PROCEDURE USED AND ITS DATE NAME OF PERSON
RESPONSIBLE ADDRESS OF BUILDING CERTIFIED DATE OF ISSUE AND LIMIT OF VALIDITY
● 4ECHNICAL DATA ONE OVERALL INDICATOR AND ITS TYPE REFERENCE VALUES
INFORMATION ON THE ENERGY PERFORMANCE OF THE MAIN BUILDING AND SYSTEM
COMPONENTS RECOMMENDATIONS FOR COST EFFECTIVE IMPROVEMENTS AND
OPTIONALLY THE ENERGY PERFORMANCE CLASS ! ' AND OTHER INDICATORS
Go to page 112 See Appendix E for an example ● 0AGE (EADLINE INFORMATION SUITABLE FOR PUBLIC DISPLAY IN PARTICULAR THE
of the rainbow graphic and the SUMMARY GRAPHIC THE ! ' RAINBOW SCALE THE BENCHMARKS AND THE HISTOGRAM
associated histogram
SHOWING PERFORMANCE OVER A CONSECUTIVE THREE YEAR PERIOD 4HE ASSET RATING
WILL BE REQUIRED WHERE OPERATIONAL INFORMATION IS NOT AVAILABLE SUCH AS FOR A
NEW BUILDING AND ANY SUPPORTING INFORMATION
● 4HE REPORT WITH INFORMATION SUPPORTING THE OPERATIONAL RATING INCLUDING THE
APPROPRIATE BENCHMARKS AND OTHER INFORMATION REQUIRED BY SI 2007/991 AND
THE CERTIFICATION PACKAGE RECOMMENDATIONS
© BSRIA BG 1/2007
Part 4
#ONDITION SURVEYS HELP TO PLAN FOR THE NECESSARY HUMAN AND FINANCIAL RESOURCES
BEFORE FAILURE OF THE PLAN AND INSTALLATIONS #ONDITION SURVEYS CAN ALSO HELP TO
● $EVELOP A PROPERTY CONDITION DATABASE THAT CAN BE USED FOR OTHER PURPOSES
SUCH AS ASSET VALUATIONS
#ONDITION SURVEYS ARE ALSO CARRIED OUT FOR OTHER REASONS4HESE ARE
7HAT FOLLOWS IS A SUGGESTED FORMAT AND STRUCTURE FOR CONDITION SURVEY REPORTS
Executive summary
4HIS SHOULD PROVIDE A SUMMARY OVERVIEW OF THE CONDITION SURVEY AND THE
OVERALL CONCLUSIONS DRAWN FROM IT
Introduction
4HIS SHOULD CONTAIN
● 4HE DATE AND TIME OF THE SURVEY AND THE PERSONS INVOLVED
● $ETAILS OF THE PROPERTY AND INSTALLATIONS COVERED INCLUDING THEIR AGE FUNCTIONS
AND IMPORTANCE AND CRITICALITY
● 4HE SURVEY METHODOLOGY INCLUDING HOW THE SURVEY IS TO BE CARRIED OUT AND
THE TECHNIQUES TO BE USED
© BSRIA BG 1/2007
● /THER SOURCES OF INFORMATION
Main report
4HIS SHOULD DESCRIBE THE FOLLOWING IN DETAIL
● 4HE EVALUATION AND ANALYSIS PROCESS SUCH AS THE DETAILED COMPARISON WITH THE
REQUIRED MAINTENANCE STANDARDS DEFECTS ANY NON COMPLIANCE NOTED AND RISK
ASSESSMENTS
● !SSET REFERENCE
● !SSET TITLE
● !SSET LOCATION
● #OST
Enclosures
4HIS SECTION SHOULD CONTAIN ANY INFORMATION SUPPLEMENTARY TO THE DETAILS GIVEN
IN THE MAIN REPORT SUCH AS DRAWINGS SPECIFICATIONS AND PHOTOGRAPHS
4HE FORMAT AND STRUCTURE OF THE FORWARD MAINTENANCE REGISTER &-2 DEPENDS
ON THE NEEDS OF THE PARTICULAR ORGANISATION )T MAY BE KEPT IN HARD COPY OR
© BSRIA BG 1/2007
Part 4
● 0LANASSET REFERENCE
● 0RIORITY
© BSRIA BG 1/2007
E
nergy Management/Sustainability
Effective energy management can reduce company overheads and improve cash flow,
particularly in this age of rising energy prices.
Haleys have moved progressively into becoming a leading force in reducing energy
consumption across its client portfolio and can offer a highly qualified and experienced team
of consultants to advise on energy conservation within your building.
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Clients can typically expect between 10-30% savings potential in energy costs and usage with
minimal investment and attractive payback periods.
In addition to existing building reviews, Haleys are able to offer new low carbon designs with
full compliance or even exceeding compliance with Part L of the Building Regulations.
Services offered
Rapid results energy surveys Energy awareness campaigns
Detailed energy surveys and audits Staff energy training and education programmes
Utility purchasing reviews and fuel Energy efficient design
supply tariff analysis On-going management of maintenance
On-going utility monitoring and contracts to ensure energy efficient operation
target setting Alternative energy schemes
Administration of good Combined heat and power studies
housekeeping programmes Investment appraisals
Established in 1989, the practice has developed and grown from strength to strength in line
with clients’ needs and prides itself on the ability to offer a tailored service in a cost effective
fashion.
Our ethos of providing a quality professional solution is consistent throughout each of our
offices and across all disciplines of our offering. We bring to bear an extensive collection of
experience in a variety of sectors for our clients’ benefit.
Other Services
4HE 5+ BUILDING INDUSTRY IS NOT KNOWN FOR LEARNING LESSONS FROM COMPLETED
PROJECTS AND USING THE INFORMATION TO REFINE ITS DESIGN AND CONSTRUCTION
PRACTICES -OST CONTRACTS DO NOT INCLUDE A PROVISION FOR POST COMPLETION
PERFORMANCE ASSESSMENTS NOR FOR THE MONITORING OF SYSTEMS FOR THEIR ENERGY
EFFICIENCY OR USABILITY
-OST POST OCCUPANCY SURVEYS CARRIED OUT BY RESEARCHERS SINCE THE MID S The PROBE articles and a list of
MOST NOTABLY THE 02/"% PROJECT 0OST OCCUPANCY 2EVIEW /F "UILDINGS AND project feedback tools is held on
www.usablebuildings.co.uk/fp/
THEIR %NGINEERING REVEALED THAT BUILDINGS REGULARLY FAIL TO PERFORM TO index.html.
EXPECTATION #ASE STUDIES REVEAL THAT UNDER PERFORMANCE CAN SHOW UP IN MANY
WAYS SUCH AS
● #ONTROLS SYSTEMS THAT FAIL TO RESPOND TO NEEDS CONFLICT WITH ONE ANOTHER Controls for End Users – a Guide for
Good Design and Implementation is
TYPICAL OF A MIX OF AUTOMATIC AND MANUAL CONTROLS ANDOR THAT POSSESS POOR available as a free PDF download
USER INTERFACES to BSRIA Members from
www.bsria.co.uk/bookshop
● #ONTROL SYSTEMS THAT RESTRICT TRADE OFFS SUCH AS THE INABILITY FOR OCCUPIERS TO
OPEN A WINDOW FOR VENTILATION DESPITE BEING PREPARED TO ACCEPT THE PENALTY OF
INCREASED TRAFFIC NOISE
● ,ACK OF USER INFLUENCE OVER ADVERSE EFFECTS SUCH AS DRAUGHTS FROM GRILLES OR
WINDOWS GLARE VIA GLASS PARTITIONS OCCUPANCY SENSED LIGHTS THAT SWITCH ON AND
OFF UNDESIRABLY BANGING DOORS AND PROXIMITY TO NOISY CIRCULATION ROUTES
● 5SE STRATEGIC BRIEFING TO FIND OUT EACTLY WHAT IS NEEDED AND EXPRESS THE
OUTCOMES FOR THE CLIENT AND END USERS CLEARLY
© BSRIA BG 1/2007
● +EEP DESIGN SIMPLE AND DO IT WELL AND ONLY OPT FOR COMPLICATED SOLUTIONS
WHERE THEY ARE ABSOLUTELY NECESSARY
● #HECK THAT IT ALL WORKS #LOSE THE LEARNING LOOP BY MODIFYING AND FINE
TUNING SYSTEMS BASED ON FEEDBACK AND DIALOGUE WITH THE END USERS
● &INISH EVERYTHING OFF PROPERLY -AKE IT WORK BETTER AND SPOT AND DEAL WITH
UNINTENDED CONSEQUENCES AND REVENGE EFFECTS SUCH AS DRAUGHTS OVERHEATING
GLARE POOR WINTER AIR QUALITY NOISE AND PRIVACY PROBLEMS
● ,EARN FROM IT ALL AND SHARE EXPERIENCES WITH COLLEAGUES THE CLIENT AND THE
BUILDINGS END USERS
0OST HANDOVER SUPPORT AND FINE TUNING IS ESSENTIAL TO ENSURE THAT THE
PERFORMANCE OF NEW BUILDINGS MEETS CLIENT AND DESIGNER EXPECTATIONS )T IS ALSO
VITAL THAT DESIGNERS IDENTIFY EMERGING PROBLEMS BEFORE THEY EITHER TURN INTO BIG
PROBLEMS OR BECOME CHRONIC SHORTCOMINGS IN THE BUILDING SERVICES THAT ARE
NEVER SOLVED
! NEW BUILDING THAT FAILS TO MEET ITS EXPECTED ENVIRONMENTAL PERFORMANCE WILL
PROBABLY UNDER PERFORM DURING ITS ENTIRE LIFE4HE ODDS ARE STACKED AGAINST
REMEDIAL ACTION NOT ONLY WILL THE DESIGN AND CONSTRUCTION TEAM HAVE
DISBANDED AFTER PROJECT HANDOVER THERE WILL BE VERY LITTLE TO BIND THE TEAM TO
THE PROJECT BEYOND THE DEFECTS PERIOD
Go to page 76 Sections 4.2 and 4.3 in Part 4 )N THE %5S Energy Performance of Building Directive EPBD INTRODUCED THE
cover energy auditing and energy CONCEPT OF ASSET RATINGS AND OPERATIONAL RATINGS FOR BUILDINGS4HE Directive WAS
assessment techniques
ENACTED THROUGH !pproved Document L2 OF THE Building Regulations )T ALSO LED TO
SI 2007/991 WHICH DESCRIBES THE REQUIREMENTS FOR MANDATORY ENERGY
LABELLING OF BUILDINGS
© BSRIA BG 1/2007
Part 5
● "UILDING USERS WILL FEEL THAT THEIR OPINIONS HAVE BEEN HEARD AND WILL MATTER
AND THAT THEY ARE PART OF THE DECISION MAKING CHAIN IN THE PROCUREMENT OF A
NEW BUILDING4HEY ARE ALSO MORE LIKELY TO BE TOLERANT OF ANY SUBSEQUENT
SHORTCOMINGS IN THE BUILDING AND ITS SERVICES
● $ESIGNERS WILL BE BETTER INFORMED ON THE ISSUES THAT MATTER MOST TO BUILDING
OCCUPANTS SUCH AS LOCAL CONTROL OVER THEIR ENVIRONMENT USABILITY STORAGE VIEWS
OUT AND THE ABILITY TO TRADE OFF CONFLICTS BETWEEN VENTILATION AND NOISE AND
NATURAL LIGHT AND ELECTRIC LIGHT
● 4HE OCCUPANT SATISFACTION DATA GAINED AT THE DESIGN STAGE CAN BE CHECKED AND
VALIDATED BY A SECOND SURVEY AFTER BUILDING COMPLETION !NY DISCREPANCIES IN
USABILITY AND THE EFFECTIVENESS OF COMFORT SYSTEMS CAN BE ADDRESSED AND SOLVED
4YPICAL SURVEY QUESTIONS CAN INCLUDE AIR QUALITY IN SUMMER AND WINTER DEGREE
OF CONTROL OVER HEATING COOLING AND LIGHTING SYSTEMS JOURNEY TO WORK TIMES
BEST AND WORST AND HOURS PER DAY SPENT AT THE DESK
! SURVEY CAN POSE MORE SEARCHING QUESTIONS DEPENDING ON THE BUILDING AND
THE NEED OF THE CLIENT TO KNOW MORE &OR EXAMPLE A SURVEY CAN ELICIT
OCCUPANTS VIEWS ON THE DEGREE TO WHICH THEY PERCEIVE THEIR HEALTH AND
PRODUCTIVITY AS BEING IMPROVED OR COMPROMISED BY BEING IN A BUILDING .OTE
THAT PERCEIVED PRODUCTIVITY SHOULD BE A MEASURE OF HOW PEOPLE FEEL THAT A
BUILDING CONTRIBUTES POSITIVELY OR NEGATIVELY TO THEIR PRODUCTIVITY )T IS RISKY
EXPENSIVE AND TIME CONSUMING TO TRY AND MEASURE ACTUAL PRODUCTIVITY
© BSRIA BG 1/2007
&IGURE BASED ON THE SURVEY METHOD DEVELOPED BY "UILDING 5SE 3TUDIES
SHOWS HOW THE MAIN INDICES OF HUMAN SATISFACTION WITH BUILDINGS n OVERALL
COMFORT LIGHTING NOISE AND SO ON n CAN BE MEASURED BY USE OF AN OCCUPANT
SURVEY 2ESULTS SHOULD ALWAYS BE PRESENTED FOR EASE OF COMPREHENSION
PARTICULARLY FOR THE COLOUR BLIND
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
)N THE CASE OF THE EXAMPLE GRAPH FROM "UILDING 5SE 3TUDIES GREEN TRIANGLES
REPRESENT MEAN VALUES SIGNIFICANTLY BETTER OR HIGHER THAN BOTH THE BENCHMARK
AND SCALE MIDPOINT )N OTHER WORDS A GOOD SCORE !MBER CIRCLES ARE MEAN
VALUES NO DIFFERENT FROM BENCHMARK A TYPICAL SCORE WHILE RED DIAMONDS ARE
MEAN VALUES WORSE OR LOWER THAN BENCHMARK AND SCALE MIDPOINT A POOR SCORE
Figure 3: An example of easily- #OMPREHENSION AND NEEDS OF USERS DIFFER AND MANY ARE FEARFUL OF STATISTICS4HE
understandable occupancy RED AMBER AND GREEN SYSTEM IS GOOD ENOUGH FOR MOST BUT SPECIALISTS WILL ALSO
survey data. Benchmarks are
represented by the line through WANT TO KNOW ABOUT FOR EXAMPLE SIGNIFICANCE TESTS AND SAMPLING SO A DETAILED
each variable. It is preferable to EXPLANATION SHOULD BE AVAILABLE ABOUT THE METHOD APPROACH AND ASSUMPTIONS
use survey methods that rely
on public-domain benchmarks.
(Example summary charts for a
3OME OF THESE TECHNICAL CRITERIA ARE IMPORTANT &OR EXAMPLE ALTHOUGH SOME
school are available on ORGANISATIONS LIKE "UILDING 5SE 3TUDIES CAN CARRY OUT INTERNET BASED SURVEYS
www.usablebuildings.co.uk/ WHEN ASKED THEY PREFER TO USE TRADITIONAL HAND OUT AND COLLECT METHODS
6944SummaryChart/ BECAUSE RESPONSE RATES ARE MUCH HIGHER AND THE CHANCE OF BIAS IN THE RESULTS IS
SummaryChartAll.html)
LESSENED4HE RESEARCHER ALSO GETS TO SEE THE BUILDING PROPERLY AND MEETS THE
USERS
4HE QUALITY AND AMOUNT OF BENCHMARK DATA WILL VARY ACCORDING TO THE
QUESTION AND THE TYPE OF BUILDING7HATEVER SURVEY METHOD IS USED THE RESULTS
OF EACH QUESTION SHOULD BE MEASURABLE AGAINST BENCHMARK UPPER AND LOWER
LIMITS
© BSRIA BG 1/2007
Part 5
)DEALLY THE SURVEY PROVIDER SHOULD BE ABLE TO SHOW EVIDENCE OF BENCHMARK See Appendix F: Principles of Go to page 113
DATASETS PREFERABLY IN THE PUBLIC DOMAIN "EWARE BENCHMARK DATA THAT IS percentiles
CONFIDENTIAL TO THE SURVEY PROVIDER AND WHICH HAS NOT BEEN SUBJECT TO PEER See Appendix G: Components of Go to page 114
REVIEW OR PUBLIC SCRUTINY benchmarking
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
4HE OPEN LOOP BETWEEN CLIENT EXPECTATION DESIGN ASPIRATION AND PERFORMANCE
IN USE WILL CAN BE CLOSED BY USING FEEDBACK TOOLS ! VARIETY OF TECHNIQUES ARE For details of the latest public
AVAILABLE TO CLIENTS AND DESIGNERS TO ENABLE FEEDBACK TO HAPPEN AT BOTH THE domain feedback tools, go to
www.usablebuildings.co.uk.
DESIGN AND POST COMPLETION STAGES OF A PROJECT
4HE FEEDBACK TOOLS DESCRIBED BELOW HAVE BEEN ASSEMBLED BY THE 5SABLE
"UILDINGS 4RUST 5"4 4HE LIST IS NOT EXHAUSTIVE BUT DOES COVER THE MAIN
METHODS AVAILABLE AT THE TIME OF PUBLICATION !S THEY ARE BEING CONSTANTLY
DEVELOPED AND ADDED TO THE READERS SHOULD CHECK THE LATEST PORTFOLIO OF
TECHNIQUES ON THE 5"4 WEBSITE
4HE METHOD SUPPORTS CLIENTS AND BUILDING USERS WHO WISH TO IMPROVE THE
EFFECTIVENESS AND EFFICIENCY OF AN EXISTING SPACE OR TO IMPROVE A FUTURE PROJECT
)T CAN BE USED TO HELP CREATE A BRIEF AND PLAN FOR CHANGE TEST HOW FAR
OBJECTIVES HAVE BEEN MET AND IDENTIFY ANY IMMEDIATE MINOR OR FUTURE MAJOR
CHANGES THAT COULD ENHANCE USER BENEFITS
● ! SPACETIME UTILISATION SURVEY GENERALLY OVER A WEEK OF ALL SPACES FOR WORK
MEETINGS SOCIAL AMENITY AND SUPPORT &OUR MAIN ACTIVITIES CAN BE CHARTED WITH
SUBDIVISIONS FOR DESK BASED ACTIVITIES
4HE QUESTIONNAIRE TOOL HAS SOME SIMILARITIES TO THE "UILDING 5SE 3TUDIES Go to 97
/CCUPANT 3URVEY AND THE /VERALL ,IKING 3CORE SEE BELOW BUT IS NOT DIRECTLY
COMPATIBLE WITH EITHER METHOD AT THE TIME OF WRITING
4HE !-! 7ORKWARE 4OOLKIT WAS DEVELOPED BY !-! !LEXI -ARMOT !SSOCIATES
AND HAS BEEN IN REGULAR USE SINCE
© BSRIA BG 1/2007
Whole Building Functionality and Serviceability
4HE !MERICAN 3OCIETY FOR 4ESTING AND -ATERIALS 3TANDARDS !34-3 HAS
DEVELOPED A METHOD OF DEFINING THE FUNCTIONAL REQUIREMENTS OF AN OCCUPANT
GROUP RATING THE CAPABILITY OF A BUILDING OR FACILITY AND CHECKING THE MATCHES
OR MISMATCHES4HE PERFORMANCE BASED APPROACH HAS BEEN DEVELOPED IN
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
4HE TOOL COMES WITH "EST&IT SOFTWARE TO FIND THE BEST MATCH BETWEEN PEOPLE
AND BUILDINGS )T IS APPLICABLE FOR ALL BUILDING SECTORS BUT MAY BE MOST USEFUL
ON COMPLEX PROJECTS WITH RIGOROUS REQUIREMENTS
● 2ELATIVE IMPORTANCE
● !UDITING
BREEAM
4HE "UILDING 2ESEARCH %STABLISHMENT %NVIRONMENTAL !SSESSMENT -ETHOD
"2%%!- IS A BUILDING RATING METHODOLOGY WITH AN EMPHASIS ON ASSESSING THE
ENVIRONMENT EFFECTS OF DESIGN DECISIONS4HE SCHEME WAS ORIGINALLY DEVELOPED
FOR OFFICES BUT HAS BEEN EXTENDED TO APPLY TO MANY DIFFERENT TYPES OF NEW AND
REFURBISHED BUILDINGS INCLUDING SCHOOLS SHOPS AND PRISONS4HE .(3
%NVIRONMENTAL !SSESSMENT 4OOL .%!4 TOOL FOR THE HEALTH SECTOR IS BASED ON
Go to page 100 "2%%!-
"2%%!- IS USED MOSTLY DURING THE DESIGN STAGE AND FOR POST COMPETITION
CHECKS )T CAN ALSO BE USED TO REVIEW MANAGEMENT AND OPERATION PROCEDURES
BUT THERE IS LITTLE USE OF THE METHOD FOR QUANTIFYING ACHIEVED PERFORMANCE
! SYSTEM OF CHECKLISTS AND SCORECARDS ENABLES TRAINED ASSESSORS TO RATE BUILDINGS
ON THE BASIS OF ENVIRONMENTAL WEIGHTINGS AND CERTIFICATES ARE AWARDED TO THE
BUILDINGS
BREEAM Schools
"2%%!- 3CHOOLS IS A VERSION OF "2%%!- TAILORED FOR SCHOOLS INTRODUCED IN
"2%%!- 3CHOOLS ADDRESSES A RANGE OF ENVIRONMENTAL CONSIDERATIONS IN A
SIMPLE EASY TO UNDERSTAND AND FLEXIBLE WAY )T ALSO HELPS DESIGN TEAMS IDENTIFY
© BSRIA BG 1/2007
Part 5
AND ADDRESS ENVIRONMENTAL ISSUES DURING THE DESIGN AND CONSTRUCTION PHASES
4HE METHODOLOGY IDENTIFIES DESIGN DECISIONS THAT MAY HARM OR ENHANCE THE
ENVIRONMENT UNDER EIGHT BROAD HEADINGS MANAGEMENT ENERGY USE WATER
HEALTH AND WELL BEING POLLUTION TRANSPORT LAND USE AND ECOLOGY AND MATERIALS
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
AND WASTE
"Y ADOPTING MEASURES IN RESPONSE TO THE ABOVE ISSUES DESIGNS ARE AWARDED More details about BREEAM
CREDITS4HE NUMBER OF CREDITS ACHIEVED IS USED TO CALCULATE AN OVERALL SCORE FOR Schools are at www.breeam.org/
schools.html.
THE BUILDING WHICH IS TRANSLATED INTO A "2%%!- 3CHOOLS RATING OF 0ASS 'OOD
6ERY 'OOD AND %XCELLENT
4HE "53 WILL CARRY OUT A SURVEY ON A CONSULTANCY BASIS OR WILL MAKE IT
AVAILABLE TO DESIGNERS ARCHITECTS AND UNIVERSITY RESEARCH TEAMS UNDER LICENCE
4HE SURVEY METHOD CAN BE USED AS THE BASIS FOR OCCUPANT SURVEYS EITHER ALONE
OR IN CONJUNCTION WITH OTHER TECHNIQUES AS PART OF POST OCCUPANCY EVALUATION
OR DIAGNOSTIC PERFORMANCE STUDIES
4HE $1) METHOD IS USEFUL AT THE DESIGN STAGE TO HELP EXTRACT THE REACTIONS OF
THE CLIENT DESIGNERS AND ANYBODY ELSE TO A DEVELOPING DESIGN "EING DEVELOPED
AND CHAMPIONED BY THE #ONSTRUCTION )NDUSTRY #OUNCIL #)# MEANS THAT THE
METHOD HAS SUBSTANTIAL POLITICAL AND INSTITUTIONAL SUPPORT
4HE $1) TOOL WAS DEVELOPED BY THE 5NIVERSITY OF 3USSEX WITH GUIDANCE BY
THE #ONSTRUCTION )NDUSTRY #OUNCIL AND STEERING COMMITTEE MEMBERS!SPECTS
OF THE TOOL HAVE THEIR ROOTS IN TECHNIQUES USED BY .(3 %STATES $1)S WERE
© BSRIA BG 1/2007
FIRST TESTED IN WITH FULL SCALE TESTS CARRIED OUT BY WITH ORGANISATIONS IN
A TRAILBLAZING SCHEME BETWEEN *ULY AND *UNE
For further information e-mail 4HE $1) TOOL COMPRISES A SELF COMPLETION QUESTIONNAIRE )NITIAL QUESTIONS ON
dqi.cic.org.uk. THE TYPE AND PURPOSE OF THE BUILDING ARE FOLLOWED BY ABOUT MAIN QUESTIONS
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
● )MPACT INCLUDING FORM AND MATERIALS THE INTERNAL ENVIRONMENT URBAN AND
SOCIAL INTEGRATION CHARACTER AND INSPIRATION
!T THE END OF THE DOCUMENT RESPONDENTS ARE ASKED TO PRIORITISE THE THREE
COMPONENTS AGAIN BY ALLOCATING POINTS4HEY ARE ALSO ASKED TO NAME THE THREE
PRINCIPAL INDICATORS THEY MIGHT WISH TO USE TO IDENTIFY WHETHER THE PROJECT HAD
ACHIEVED ITS AIMS4HE PROJECT TEAM IS ALSO ASKED ABOUT THE CONSTRAINTS AND
ENABLERS OF THE PROJECT SPECIFICALLY TIME COST AND RESOURCES
)N THE INITIAL STAGE THE $1) FOR 3CHOOLS CAN BE USED TO HELP A GROUP OF
STAKEHOLDERS FORM A CONSENSUS ABOUT PRIORITIES AND AMBITIONS FOR THE DESIGN
BRIEF4HE TOOL CAN THEN BE USED BY THE GROUP DURING THE DESIGN PHASE TO ASSESS
WHETHER THE BUILDING WORK MEETS THE OBJECTIVES
/NCE THE BUILDING WORK IS COMPLETED AND THE SCHOOL IS IN USE THE $1) FOR
3CHOOL TOOL CAN BE USED TO ASSESS HOW WELL IT FUNCTIONS IN RELATION TO THE INITIAL
OR REVISED AMBITIONS OF THE STAKEHOLDER GROUP
4HE $1) FOR 3CHOOLS CONTAINS QUESTIONS ON THE TYPE AND PURPOSE OF THE
BUILDING GROUPED INTO THREE SECTIONS
For further information see 4HE $1) FOR 3CHOOLS TOOL ALSO PROVIDES FEEDBACK FOR BENCHMARKING AND FOR
www.dqi.org.uk/schools THE BRIEFING OF FUTURE PROJECTS
© BSRIA BG 1/2007
Part 5
4HE %NERGY !SSESSMENT AND 2EPORTING -ETHOD USES A THREE STAGE METHOD FOR
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
COLLECTING AND REPORTING ANNUAL ENERGY CONSUMPTION COST AND CARBON DIOXIDE
EMISSIONS DATA
● 3IMPLE FOSSIL FUEL AND ELECTRICITY CONSUMPTION INDICES PER SQUARE METRE OF
FLOOR AREA
4HE %NERGY !SSESSMENT AND 2EPORTING -ETHOD IS USEFUL AT ANY TIME IN THE
INCEPTION DESIGN DEVELOPMENT AND RUNNING OF A BUILDING4HE TECHNIQUE CAN
BE USED TO SUMMARISE DESIGN INFORMATION AND PREDICTIONS AND AS A CRADLE TO
GRAVE BENCHMARKING TOOL
4HE TIME NEEDED FOR A FULL TM22 STUDY DEPENDS ON THE AVAILABILITY OF
INFORMATION PARTICULARLY ON BUILDING FLOOR AREA AND ENERGY CONSUMPTION4HE
METHOD IS PROGRESSIVE AND ITERATIVE SO USERS GET USEFUL RESULTS IN RELATION TO THE
EFFORT PUT IN )F GOOD BACKGROUND DATA IS AVAILABLE USERS WILL BEGIN TO GET USEFUL
RESULTS WITHIN AN HOUR OR SO $ETAILED ANALYSIS AND REPORTING CAN TAKE LONGER
4HE METHOD IS POWERFUL AND RELATIVELY QUICK AND EASY TO USE ONCE IT IS FAMILIAR
(OWEVER EXPERIENCE SUGGESTS THAT PEOPLE ARE NOT GOOD AT LEARNING IT FOR
THEMSELVES THEY NEED TRAINING BY AN EXPERIENCED USER BUT IDEALLY A NEW
USER SHOULD WORK WITH AN EXPERIENCED USER ON TWO OR THREE SURVEYS TO BUILD
UP CONFIDENCE
4HE SYSTEM WAS DEVELOPED FOR THE %UROPEAN (EALTH 0ROPERTY .ETWORK !
SECOND PHASE OF DEVELOPMENT WAS BEGUN IN 4HUS FAR THE METHOD HAS
BEEN USED ON BUILDINGS IN &INLAND 4HE .ETHERLANDS .ORWAY .ORTHERN
)RELAND AND )RELAND
4HE ASSESSMENT INVOLVES AN ON SITE CASE STUDY WITH WALK THROUGH STRUCTURED
INTERVIEWS QUESTIONNAIRES AND AN OVERNIGHT STAY IN THE BUILDING
© BSRIA BG 1/2007
BY THE 2)"! $ESIGN 1UALITY &ORUM WITH DE -ONTFORT 5NIVERSITY
For more details, download reports 4HE (%$1& MEETS THE REQUIREMENT OF THE (IGHER %DUCATION &UNDING
on the methodology from #OUNCIL FOR %NGLAND (%&#% FOR POST PROJECT REVIEWS !T THE TIME OF
www.usablebuildings.co.uk/fp/
index.html WRITING THE TOOL IS NOT WIDELY USED BUT HAS THE POTENTIAL TO BE THE DEFAULT
TECHNIQUE THAT MEETS (%&#% REQUIREMENTS
4HE -!25 RUNS -3C COURSES IN 0LANNING "UILDINGS FOR (EALTH #ONSTRUCTION
0ROJECT -ANAGEMENT
© BSRIA BG 1/2007
Part 5
4HE METHOD IS APPLICABLE TO ANY OCCUPIED BUILDING BUT MOSTLY FOR PEOPLE
UNDERTAKING DESK BASED WORK4HE METHOD PROVIDES SCORES TO ENABLE DESIGNERS
AND OCCUPIERS TO PRIORITISE REMEDIAL ACTIONS4HE SCHEME CAN ALSO BE USED IN
CONJUNCTION WITH THE CONTINUOUS COMMISSIONING SERVICE OFFERED BY !"3
#ONSULTING
4HE SURVEY METHOD INVOLVES A SURVEY OF AROUND QUESTIONS BUT MORE ARE
OFTEN ADDED %ACH QUESTION IS ON A SEVEN POINT RATING SCALE PLUS A SEVEN POINT
IMPORTANCE SCALE4HE SCORE FOR EACH QUESTION IS THE PRODUCT OF RATING AND
IMPORTANCE NORMALISED TO A RANGE OF PLUS AND MINUS PERCENT
4HE METHODOLOGY CONTAINS IDEAS WHICH A CLIENT MAY WANT TO INCORPORATE IN ITS
PRE QUALIFICATION REQUIREMENTS WHEN SELECTING A DESIGN AND CONSTRUCTION TEAM
AND IN THEIR CONDITIONS OF APPOINTMENT4HE APPROACH IS RELEVANT FOR
ESTABLISHING A DIALOGUE BETWEEN THE CLIENT THE SUPPLY SIDE AND WHERE
APPROPRIATE THE USER CLIENT ON THE SERVICES THAT ARE REQUIRED AND HOW THEY WILL
BE UNDERTAKEN AND RESOURCED
! CHECKLIST ENABLES CLIENTS AND THE DESIGN AND BUILDING TEAM TO DECIDE WHICH
ACTIVITIES THEY WISH TO UNDERTAKE AND IN WHAT MANNER AND TO PREPARE FOR THEM
AS A PROJECT IS BEING BUILT ! FURTHER CHECKLIST ALLOWS THE PROJECT MANAGER TO
PROGRESS THE AGREED ACTIVITIES
4HE CHECKLISTS ARE DESIGNED FOR SELF COMPLETION 3OME PEOPLE WILL REQUIRE
ADVICE ON AT LEAST SOME OF THE TECHNIQUES THEY MAY CHOOSE AND ASSISTANCE IN
IMPLEMENTING THEM
4HE SYSTEM WAS FIRST USED IN AND FURTHER DEVELOPMENT IS UNDERWAY )T
COMPRISES A QUESTIONNAIRE AND INTERVIEW METHOD4HE QUESTIONNAIRE REQUIRES A
LICENCE WHICH MUST BE SIGNED IN ADVANCE
© BSRIA BG 1/2007
The PROBE system
02/"% 0OST OCCUPANCY 2EVIEW /F "UILDINGS AND THEIR %NGINEERING IS A
COLLECTIVE TERM FOR THE ASSESSMENT METHODS USED IN THE POST OCCUPANCY
EVALUATION OF NOTABLE 5+ BUILDINGS CARRIED OUT AND PUBLISHED IN Building
Services Journal BETWEEN
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
www.usablebuildings.co.uk has 4HE 02/"% PROJECT DEVELOPED AND USED A SUITE OF ASSESSMENT PROCEDURES
most of the PROBE surveys
available for free download
INCLUDING
● 4HE "UILDING 5SE 3TUDIES OCCUPANT SURVEY INCLUDING A JOURNEY TO WORK MODULE
4HE PACKAGE OF SURVEY TECHNIQUES CAN BE USED ON ANY BUILDING BUT PRINCIPALLY
PUBLIC COMMERCIAL AND EDUCATIONAL BUILDINGS
!LL THE METHODS CAN BE USED INDEPENDENTLY BUT USED TOGETHER THEY CAN DEAL
SIMULTANEOUSLY WITH PEOPLE RELATED ISSUES AND TECHNICAL AND ENVIRONMENTAL
PERFORMANCE ISSUES IN AN EFFECTIVE AND PRAGMATIC MANNER
Soft Landings
3OFT ,ANDINGS IS AN INNOVATIVE ARRANGEMENT BETWEEN A CLIENT AND A DESIGN AND
BUILDING TEAM TO SMOOTH THE OFTEN FRAUGHT TRANSITION LEADING UP TO THE
HANDOVER OF A BUILDING 3OFT ,ANDING METHODS INCLUDE CONTRACT CLAUSES TO
SMOOTH THE TRANSITION OF A BUILDING THROUGH COMPLETION TO OCCUPANCY
● 0ROVIDES A MORE RIGOROUS SIGN OFF OF BRIEFS DESIGNS WORK ON SITE AND
COMMISSIONING TRIALS
● %NABLES CLOSER WORKING BETWEEN THE DESIGN AND BUILDING TEAM AND OCCUPIERS
AND MANAGERS
© BSRIA BG 1/2007
Part 5
4HE 3OFT ,ANDINGS PROCESS SHOULD EXTEND OVER THE WHOLE LIFE OF A PROJECT AND
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
THEN FOR ABOUT THREE YEARS BEYOND PRACTICAL COMPLETION (OWEVER MOST OF THE
EXTRA ACTIVITY WILL BE IN IMPROVING COMMUNICATION AND UNDERSTANDING AND
ATTENDING TO ANY TEETHING PROBLEMS IN THE FIRST THREE MONTHS OR SO OF
OCCUPANCY
© BSRIA BG 1/2007
Business-Focused Maintenance Toolkit
- the essential systems analysis tool for facilities managers
...It gives you Hindsight an understanding of how your plant has been run,
the likelihood of plant failures, and the risk to the business if something were
to fail
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
...It gives you Insight a greater understanding of how well your plant is
working now, and a way of measuring the performance of your maintenance
activities
It gives you Foresight you can plan cost-effective maintenance to fit your
business, allowing you to focus maintenance resources on critical plant items
,ARGE COMPLEX SITES WITH ESSENTIAL ENGINEERING SERVICES ARE MORE LIKELY TO JUSTIFY
DIRECT LABOUR ALTHOUGH THE MODERN MAINTENANCE CONTRACTOR CAN OFFER H
PERMANENT COVER
%XAMPLES OF THE SPECIFIC OPTIONS AVAILABLE WITHIN THE BROAD CHOICES OUTLINED
ABOVE INCLUDE
● %MPLOYMENT OF DIRECT LABOUR FOR DAY TO DAY SPECIALIST WORK SUCH AS ON LIFTS
HIGH VOLTAGE EQUIPMENT REFRIGERATION PLANT AND PEAK LOAD TASKS UNDERTAKEN BY
SPECIALIST CONTRACTORS
● 5SE OF DIRECT LABOUR TO PROVIDE MINIMUM COVER ONLY4HIS OFFERS A FIRST AID
RESPONSE TO FAILURES AND ENSURES THAT SIMPLE ROUTINE TASKS ARE CARRIED OUT WITH
ALL OTHER MAINTENANCE UNDERTAKEN BY SPECIALIST CONTRACTORS
● 3PECIALIST LABOUR PLUS EMERGENCY CALL OUTS CONSUMABLE SPARES AND SPECIFIED
REPLACEMENT PARTS ANDOR EQUIPMENT
● ,ABOUR PLUS SPECIALIST SUPPORT CONSUMABLE SPARES AND EMERGENCY CALL OUT
© BSRIA BG 1/2007
● ,ABOUR PLUS SPECIALIST SUPPORT CONSUMABLE SPARES EMERGENCY CALL OUTS AND
SPECIFIED REPLACEMENT PARTS ANDOR EQUIPMENT
© BSRIA BG 1/2007
Appendix B
Go to page 1
!UTOMATIC DOORS
#ATERING
##46
#ENTRAL CONTROL
#ENTRAL REFRIGERATION
#LOCKS
#OLD WATER
#OMMUNICATIONS
#OMPUTER SERVICES
#OOLING DISTRIBUTION
$RYWET RISERS
%ARTHING AND BONDING
%MERGENCY LIGHTING
&IRE DETECTION AND ALARM
&IRE HOSE REELS
&UEL SUPPLY
'ENERAL LIGHTING
'ENERAL SUPPLY AND EXTRACT
(OT WATER
(OT WATER HEATING
,IFTS AND VERTICAL TRANSPORT
,IGHTNING PROTECTION
,6 DISTRIBUTION
-ECHANICAL HANDLING
0RESSURISED WATER
0RIMARY HEAT DISTRIBUTION
3ECURITY
3PRINKLERS
3TEAM GENERATORS
4HERMAL INSULATION
4OILET EXTRACT
4RANSPORT
503
7ARM AIR HEATING
7ASTE DISPOSAL
4HE ABOVE SYSTEM CATAGORIES HAVE BEEN DERIVED FROM THE .ATIONAL %NGINEERING
3PECIFICATION
© BSRIA BG 1/2007
C Appendix
5.2.1 Documentation
(a) the location, including level if buried, of all public service connections (e.g. fuel, gas and
cold water supplies) together with the points of origin and termination, size and materials
of pipes, line pressure and other relevant information.
(b) The layout, location and extent of all piped services showing pipe sizes, together with
all valves for regulation, isolation and other purposes as well as the results of all balancing,
testing and commissioning data;
(c) The location, identity, size and details of all apparatus and control equipment served by,
or associated with, each of the various services together with copies of any test certificates for
such apparatus where appropriate.The information with respect to size and details may be
presented in schedule form;
(d) The layout, location and extent of all air ducts showing dampers and other equipment,
acoustic silencers, grilles, diffusers or other terminal components. Each duct and each
terminal component should be marked with its size, the air quantity flowing and other
relevant balancing data;
(e) The location and identity of each room or space housing plant, machinery or apparatus.
5.2.2 Drawings
(a) detailed general arrangements of boiler houses, machinery spaces, air-handling plants,
tank rooms and other plant or apparatus, including the location, identity, size and rating of
each apparatus.The information with respect to the size and rating can be presented in
schedule form;
(b) isometric or diagrammatic views of boiler houses, plant rooms, tank rooms and similar
machinery, including valve identification charts. It is useful to frame and mount a copy of
such drawings on the wall of the appropriate room;
(c) comprehensive diagrams that show power wiring and control wiring and/or pneumatic
or other control piping including size, type of conductor or piping used and identifying the
terminal points of each.
Subject to the recommendations given in 5.1, documentation should record the following,
including locations, as installed:
(a) main and submain cables, showing origin, route, termination, size and type of each
cable; cables providing supplies to specialist equipment, e.g. computers, should be identified
separately;
© BSRIA BG 1/2007
Appendix C
(b) lighting conduits and final subcircuit cables, showing origin, route, termination and size
of each, together with the number and size of cables within each conduit.The drawings
should indicate, for each conduit or cable, whether it is run on the surface or concealed, e.g.
in a wall chase, in a floor screed, cast in situ, above a false ceiling etc.These drawings
should also indicate the locations of lighting fittings, distribution boards, switches, draw-in-
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
(c) location and purpose of each emergency lighting fitting including an indication of the
circuit to which it is connected;
(d) single and three-phase power conduits and final subcircuit cables showing locations of
power distribution boards, motors, isolators, starters, remote control units, socket outlets and
other associated equipment;
(f) lightning conductor air terminals, conductors, earth electrodes and test clamps;
(g) location of earth tapes, earth electrodes and test points other than those in f); cables
providing earth circuits for specialist equipment, e.g. computers, should be identified
separately;
(h) distribution diagrams or schedules to show size, type and length (to within 1 m) of each
main and submain cable, together with the measured earth continuity resistance of each;
(i) schedule of lighting fittings installed stating location, manufacturer, type or catalogue
number together with the manufacturer’s reference, voltage and wattage of the lamp
installed;
(j) Schedule of escape and emergency lighting fittings installed stating location,
manufacturer, type or catalogue number together with the manufacturer’s reference, voltage
and wattage of the lamp installed. For battery systems the position of the battery, its ampere
hour rating and battery system rated endurance in hours should be stated;
(k) Records of smoke detectors, sprinklers, fire precautions generally, as well as security
precautions (see BS 8220 : Part 1).
(l) Incoming supply details; the type of system, voltage, phases, frequency, rated current and
short circuit level, with the details of supply protection and time of operation as appropriate;
(m) Main switchgear details; for purpose made equipment this should include a set of
manufacturer’s drawings and site layout;
(n) Transformer, capacitor and power plant details; the leading details should be given, e.g.
for transformers the VA rating, voltages and type of cooling;
5.4.1 Application
© BSRIA BG 1/2007
C Appendix
5.4.2 Drawings
Drawings should be in accordance with the provisions of 5.2 as appropriate, and should
shown the following as installed:
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
(a)Telephone extension wiring, exchange lines and private circuits, direct exchange lines and
coin box lines and similar communications cabling for direct speech intercommunication
systems, and for digital data communications the following;
1) Details of cable routes, sizes and types of conduits and ducts; number of cable pairs fitted
for immediate use, and also spare ways; joint boxes, sub-distribution frames and extension
instruments or other terminal apparatus (private circuit reference numbers should be shown);
2) In the case of digital communication cabling, detail of the type of cable in use ( e.g. twisted
pair, fibre optic etc), and the type of wall mounting outlet (i.e. simple type or loop – around);
3) Floor plans of telephone equipment rooms and operators’ rooms, showing location and type
of equipment; main distribution frame; batteries and charging equipment; operators’ consoles
and all associated cabling, trunking and ducts (any special provision such as anti-static or
computer flooring should be noted and floor plans should also include details of any switching
or processing equipment associated with direct speech telecommunication or digital data
communication systems);
4) Radio paging and loop systems, including routes and details and the location and details of
equipment.
(d) equivalent information as in (a) to (c) above for direct speech intercommunication and
digital data communications systems;
(f) master telephone extension directory, including the facilities available to each extension;
A schedule should be maintained for radio paging systems, to include details of:
© BSRIA BG 1/2007
Appendix D
82 In accordance with Requirement L1(c), the owner of the building should be provided
with sufficient information about the building, the fixed building services and their
maintenance requirements so that the building can be operated in such a manner as to use
no more fuel and power than is reasonable in the circumstances.
Building log-book
84 The data used to calculate the TER and the BER should be included in the log-book.
It would also be sensible to retain an electronic copy of the input file for the energy
calculation to facilitate any future analysis that may be required by the owner when altering
or improving the building.
© BSRIA BG 1/2007
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
112
D
E Appendix
RA
F
© BSRIA BG 1/2007
T
C
O
PY
Appendix F
Principles of percentiles
For this scale, best values are at
the top (7 = satisfactory)
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Mean score 7
for the study
variable. In this
example (not from
the current study), 6
the variable is
Design and the
score is 4.31
5
4
Scale mid-point
1
0 10 20 30 40 50 60 70 80 90 100
© BSRIA BG 1/2007
G Appendix
Components of benchmarking
Variable name
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Test limits
Scale midpoint lower limit
Benchmark lower limit
Scale midpoint
Benchmark mean Summaries of percent values
Benchmark midpoint upper limit (percent satisfied, neutral, dissatisfied)
Benchmark upper limit
© BSRIA BG 1/2007
Available now from
BSRIA
A facilities management specification
Licensed copy from CIS: southbank, Southbank University, 20/02/2018, Uncontrolled Copy.
Testing Troubleshooting
Modelling Information
Research Training
Consultancy Publications
Whatever your
building services
requirement contact Instrument hire, sales Market research and
BSRIA: and calibration intelligence
T: +44 (0)1344 465600
F: +44 (0)1344 465626
E: [email protected] Membership is the foundation of BSRIA’s
W: www.bsria.co.uk expertise and independence