Ac1229 Building Consent Booklet
Ac1229 Building Consent Booklet
Building consent
booklet
Defintions:
BCA - Building Consents Authority
LBP - Licenced Building Practitioner
RBW - Restricted Building Work
CCC - Code Compliance Certificate
1. Expiry date:
A building consent lapses and is of no effect if the building work to which it relates does not
commence within:
• 12 months after the date of issue of the building consent; or
• any further period that the building consent authority may allow. Amendments to a building
consent do not extend the time to start or complete the building work; an amendment
is merely a change to the approved design of the original consent’.
Offence
Undertaking or supervising RBW by a non-LBP is considered a serious offence in that critical
building work is being done (without supervision) by practitioners who have not demonstrated
their competence.
The holder of the building consent or their agent could be prosecuted and face a Court fine of up to
$20,000 if they knowingly engaged an unlicensed person to carry out or supervise RBW.
Similarly, the unlicensed person who supervises RBW or carries out RBW without being supervised
by an appropriately licensed trade LBP, could be prosecuted and face a Court fine of up to $20,000.
JULY 2020
Subfloor may be done Pre-line building
in conjunction with can not be approved
framing or as until pre-line plumbing
seperate inspection has been completed
Concrete floor
Membranes must
Slab-building be approved 6a-b.
can not be approved before cladding Mesh
until slab plumbing is completed and plaster 9a.
1a. coats Fire-lining
has been completed
Piling
13.
6c. Code
5a.
If retaining, the tanking Polystyrene compliance
3. Membrane (jointing
may be done in conjunction certificate
Slab- roof/deck and oating
with the blockwork 9b.
or as a separate inspection plumbing systems)
Acoustic
lining
6d.
Brick
veneer
These 3 inspections may occur
at any point up to stage 10
Footing
2a. (isolated Site
Drainage
Tanking pads and meeting
footings)
Typical order of notifiable inspections – residential
Inspection records. Please Note: Reclad inspection regimes may differ to those shown in the standard
plumbing this should occur before the pre-line building it is also possible for some inspections to occur at the
Any of the above inspections may occur more than once, for example there maybe two or more blockwork or slab
inspections. When there is a slab plumbing, this should occur before slab building, similarly when there is a pre-line
1b. 2b. 5a.
Pre- Columns, Membrane
11.
Membranes must Pre-CCC
1a.
be approved before vet
Certificate
for cladding is completed
Public Use
JULY 2020
Typical order of notifiable inspections – commercial and industrial
is a pre-line plumbing this should occur before the pre-line building it is also possible for some inspections
Inspection records. Please note: Reclad inspection regimes may differ to those shown in the standard flowchart.
7
Erosion and sediment control on small sites
Badly managed small construction sites generate sediment run- off. Multiply by this by the number
of construction sites in the Auckland region and it becomes a major problem. Auckland Council
recognises this issue as a major contributing factor in damage to streams and our waterways.
X
To combat this, Auckland Council will be making additional visits to sites to ensure that adequate
erosion control is present from the moment the initial cut is made on your site. Poor erosion control will
result in failed building inspections. We ask that you consider the environment and adequately control
sediment run off during your build. Failure to do so will result in enforcement action consisting of fines
or prosecution
protect drains/catchpits.
The above multilingual Building on Small Site guide is available on Auckland Council’s website
aucklandcouncil.govt.nz/buildingsites
There are five handy “How-to” videos on YouTube that show simple methods for successfully managing
a small site and reducing impact on the environment You can use the following link
http://bit.ly/aklcbuilding
documentation review
tick initials/ approved initials/
NOTE FOR INSPECTORS: This sheet is not required to be updated
(required) date received date received
if all documents are recorded in the tablet inspection checklist.
access (D1)
Electromagnetic hold open device installer PS3 (SS3)
includes interface
Automatic doors installer – PS3 (SS3) include override
or interface
Access control (door) installer PS3 (SS3) include interface
fire
Fire – accredited inspection body certification – alarms
and sprinklers (F7, C Docs)
Fire – alarm system installer PS3 – automatic or manual
emergency warning (SS2)
Fire – automatic systems for fire suppression
e.g. sprinklers (SS1)
Fire – fire protection system (fire alarm system) as‑built plan
emergency lighting
Emergency lighting installation PS3 / test cert
(SS4, F6) and as‑builts (if applicable)
Emergency power systems installer PS3 (SS14)
other
Safety glazing certificate (NZS4233) – shower / barrier /
windows / fire rated / other
Manufacturer joinery certificate
(e.g. NZS4211 cannot be verified)
Installers PS3 certificate for barrier installation
AC1229 (V.11)