1.25 MW Wind Energy Project, Sangli District, Maharashtra, India
1.25 MW Wind Energy Project, Sangli District, Maharashtra, India
CONTENTS
D. Environmental impacts
E. Stakeholders’ comments
Annexes
Annex 1: Contact information on participants in the proposed small scale project activity
1
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
2
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Version : 01
Date : 01/08/2007
The electricity generation from the WEG will contribute annually to GHG reductions estimated at 2,299
tCO2eq. (tonnes of carbon dioxide equivalent). Although the project life is envisaged as 20 years, it is
proposed that the project activity needs to mitigate the risks involved in renewable energy technology for
the first 10 years. The project activity will evacuate approximately 2.8 GWh of renewable power annually
to the power deficit western region grid.
Apart from generation of renewable electricity, the project has also been conceived for the following:
¾ To enhance the propagation of commercialisation of wind turbines in the region
¾ To contribute to the sustainable development of the region
¾ To reduce the prevalent regulatory risks for this wind park through revenues from the CDM
View of the project participants on the contribution of the project activity to sustainable development
Ministry of Environment and Forests, Govt. of India has stipulated the following indicators for
sustainable development in the interim approval guidelines for CDM projects:
3
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The project activity leads to an investment of about Rs. 64.73 millions to a developing region which
would not have happened in the absence of the project activity. The generated electricity is fed into the
western regional grid through the local grid, thereby improving grid frequency. The project activity also
leads to diversification of the national energy supply, which is dominated by conventional fuel based
generating units.
4
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
>>
District : Sangli
Taluk : Kawthe Mahakal
Village : Jarandi
Figure A.1: Location of Maharashtra in India Figure A.2: District Map of Maharashtra
5
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Technology
In wind energy generation, kinetic energy of wind is converted into mechanical energy and subsequently
into electrical energy. Wind blowing at high speeds, has considerable amount of kinetic energy. When
this kinetic energy passes through the blades of the wind turbines, it is converted into mechanical energy
and rotates the wind blades. When the wind blades rotate, the connected generator also rotates, thereby
producing electricity. The technology is a clean technology since there are no GHG emissions associated
with the electricity generation. The project installs 1 WEG of Suzlon make, having capacity of 1.25 MW
6
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Operating Data:
1. Rotor Diameter : 69.1 m
2. Hub Height : 74 m
3. Cut in Speed : 3 m/s
4. Rated Speed : 12 m/s
5. Cut out Speed : 20 m/s
6. Survival Speed : 67 m/s
Rotor:
1. Blade : 3 Blade Horizontal Axis
2. Swept Area : 3750 m2
3. Rotational Speed : 13.2 to 19.8 rpm
4. Regulation : Pitch Regulated
Generator:
1. Type : Asynchronous 4 / 6 Poles
2. Rated Output : 250 / 1250 kW
3. Rotational Speed : 1010 / 1515 rpm
4. Frequency : 50 Hz
Gear Box:
1. Type : Integrated (1 Planetary & 2 Helical)
2. Ratio : 77.848:1
Yaw System:
1. Drive : 4 electrically driven planetary gearbox
2. Bearings : Polyamide slide bearing
Braking System:
1. Aerodynamic Brake : 3 times independent pitch regulation.
2. Mechanical Brake : Spring power disc brake, hydraulically released, fail safe
3. Control unit : Microprocessor controlled, indicating actual operating
conditions, UPS back-up system
7
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Tower: Tubular
Technology transfer:
No technology transfer from other countries is involved in this project activity.
A.4.3 Estimated amount of emission reductions over the chosen crediting period:
>>
Table A.3: Estimated amount of emission reduction
Annual Emission
S. No. Year / Period
Reduction (tCO2eq.)
1 01/11/2007 - 31/10/2008 2,299
2 01/11/2008 - 31/10/2009 2,299
3 01/11/2009 - 31/10/2010 2,299
4 01/11/2010 - 31/10/2011 2,299
5 01/11/2011 - 31/10/2012 2,299
6 01/11/2012 - 31/10/2013 2,299
7 01/11/2013 - 31/10/2014 2,299
8 01/11/2014 - 31/10/2015 2,299
9 01/11/2015 - 31/10/2016 2,299
10 01/11/2016 - 31/10/2017 2,299
Total emission reductions (tCO2eq.) 22,990
Total number of crediting years 10
Annual average over the crediting period
2,299
of estimated reductions (tCO2eq.)
A.4.5. Confirmation that the small-scale project activity is not a debundled component of a
large scale project activity:
>>
According to paragraph 2 of Appendix C to the Simplified Modalities and Procedures for Small-Scale
CDM project activities (FCCC/CP/2002/7/Add.3), a small-scale project is considered a debundled
component of a large project activity if there is a registered small-scale activity or an application to
register another small-scale activity:
¾ With the same project participants
¾ In the same project category and technology
¾ Registered within the previous two years; and
¾ Whose project boundary is within 1 km of the project boundary of the proposed small scale
activity
The project promoters hereby confirm that there is no registered small scale project activity, registered
within the previous two years with them in the same project category and technology whose project
boundary is within 1 km of the project boundary of the proposed small scale activity. Thus the project is
not a debundled component of any other large-scale project activity.
8
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
small-scale project activity:
>>
Project Type : I - Renewable energy project
Project Category : D - Grid connected renewable electricity generation
Version : 12
Date : 27th July 2007
Reference : http://cdm.unfccc.int/methodologies/SSCmethodologies/approved.html
The project activity meets the eligibility criteria to use simplified modalities and procedure for small-scale
CDM project activities as set out in paragraph 6 (c) of decision 17/CP.7.
The project boundary is thus composed of the wind energy generators, the metering equipment for each
generator and substation, and the grid which is used to transmit the generated electricity. The project is
supplying the generated electricity to the western region grid, thus the western grid, which includes all the
power plants connected physically to this system, has been chosen as the grid system for the baseline
calculation.
9
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
There are five regional grids: Northern, Western, Southern, Eastern and North-Eastern. Different states
are connected to one of the five regional grids as shown in the table below-
Table B.1: States connected to different regional grids
Regional
Northern Western Southern Eastern North Eastern
grid
States Haryana, Himachal Gujarat, Andhra Bihar, Arunachal
Pradesh, Jammu & Madhya Pradesh, Orissa, Pradesh, Assam,
Kashmir, Punjab, Pradesh, Karnataka, West Manipur,
Rajasthan, Uttar Maharashtra, Kerala, Bengal, Meghalaya,
Pradesh, Uttaranchal, Goa, Tamil Nadu, Jharkhand, Mizoram,
Delhi, Chandigarh Chattisgarh Puducherry Sikkim Nagaland, Tripura
The management of generation and supply of power within the state and regional grid is undertaken by
the state load dispatch centres (SLDC) and regional load dispatch centres (RLDC). Different states within
the regional grids meet the demand from their own generation facilities plus generation by power plants
owned by the central sector i.e. NTPC and NHPC etc. Specific quota is allocated to different states from
the Central sector power plants. Depending on the demand and generation there are exports and imports
of power within different states in the regional grid. Thus there is an exchange of power among states in
the regional grid. Similarly there exists imports and export of power between regional grids.
The Western Region grid managed by Western Region Electricity Board (WREB) constitutes five states
(viz. Maharashtra, Madhya Pradesh, Chhattisgarh, Gujarat and Goa) and two Union territories (Daman &
Diu and Dadar & Nagar Haveli). These states under the regional grid have their own power generating
stations as well as centrally shared power-generating stations. While the power generated by own
generating stations is fully owned and consumed through the respective state’s grid systems, the power
generated by central generating stations is shared by more than one state depending on their allocated
share. WREB facilitates the share of power generated by the central generating stations. Presently the
share from central generating stations is a small portion of their own generation.
10
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
member states and the union territory through the Western Region Load Dispatch Centre (WRLDC), the
entire western grid is considered as a single entity for estimation of baseline.
a) A combined margin (CM), consisting of the combination of Operating Margin (OM) and Build
Margin (BM) according to the procedures prescribed in the approved methodology ACM0002.
Any of the four procedures to calculate the operating margin can be chosen, but the restrictions to
use the Simple OM and the Average OM calculations must be considered.
or
b) The weighted average emissions (in kgCO2eq./kWh) of the current generation mix. The data of
the year in which project generation occurs must be used.
Calculations must be based on data from an official source (where available) and made publicly available.
The project developers have calculated the emission factor for both the cases that is as the combined
margin consisting of weighted average of the operating margin and build margin. The weightage for the
operating margin and the build margin1 is 75% and 25% respectively. The emission factor is also
calculated for the weighted average emission rate for the current generation mix. Among these two values
the conservative value is considered.
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered small-scale CDM project activity:
>>
Referring to Attachment A to Appendix B document of “Indicative simplified baseline and monitoring
methodologies for selected small scale CDM project activity categories”, project participants are required
to provide a qualitative explanation to show that the project activity would not have occurred anyway, at
least one of the listed elements should be identified in concrete terms to show that the activity is either
beyond the regulatory and policy requirement or improves compliance to the requirement by removing
barrier(s); The guidance provided herein has been used to establish project additionality. The barriers that
were considered are listed below:
a) Investment barrier
b) Technological barrier
c) Barrier due to prevailing practice
d) Other barriers
Project proponents had to face various barriers to innovate and implement the project activity that would
prevent the installation of the technology. The following section addresses barriers faced by project
proponents to implement the project activity.
1
As per the ACM0002 version 06, 19th May 2006
11
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
unpredictable of all the other common sources of generating energy i.e. coal, diesel etc. Further wind
turbines generation plant has the lowest load factor of all other sources. In the concerned cases it is in
between 18% to 21%.
The total installed electricity generating capacity2 in Maharashtra, Western Region and India, as on 31st
December 2005 is given in the table below:
Table B.2: Total Installed capacity of electricity generation.
As on 31.12.2005 (in MW)
Hydro Thermal Nuclear Wind Other RE Total
Maharashtra 3,170.67 11,643.33 582.06 456.30 248.8 16,101.16
Western Region 6,476.33 26,006.70 1,300.00 738.68 346.03 34,867.74
India 32,135.05 82,064.44 3,310.00 3,594.75 6,158.32 123,667.81
From the above table it can be seen that the total installed electricity generating capacity in Maharashtra,
as on 31.12.2005 was 16,101.16 MW. This includes 72.31 % thermal (11,643.33 MW), 19.69 % hydro
(3,170.67 MW), 3.62 % nuclear (582.06 MW), 2.83 % wind based generation (456.30 MW) and 1.55 %
other renewable energy (248.8 MW). Coal based thermal power generation has been the mainstay of
electricity generation in the state. It clearly shows that the share of electricity generation from wind is
very low in the region and the current practice being followed in the state is preferential generation of
electricity from fossil fuel based power plants.
2
Annual Report 2005-06, Ministry of Power.
12
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The gross wind potential3 of the state of Maharashtra, which is in the western part of the country, is 3,650
MW whereas technical wind power potential is approximately 3,040 MW. The current practice followed
by investors (investing in WTGs) is to execute wind electricity projects in southern states of India because
of higher generation potential (these states observe two monsoon seasons, leading to a higher PLF).
Owing to this fact, the total capacity exploited in the state of Maharashtra (as on 31st December 2005) was
just about 15 % of the technical potential, which is far behind the potential harnessed in southern states.
Hence, a wind power project in Maharashtra needs to be encouraged.
The western regional grid, which is the baseline for the present project consists of a major industrial belt
of the country. Being the hub of most of the commercial operations, the demand for power in this region
is indeed very high. According to the western regional profile, published by the Ministry of Power,
Maharashtra for the period April 2006 to March 2007, recorded a second highest shortage of 26.63 %
while Gujarat scored the highest shortage at 29 %. In the view of the above, the power sector is planning
to invest greatly in power generating stations in the western region. Owing to the relatively low cost of
electricity and higher PLF, the power sector is looking at fossil fuel generated power plants to meet this
shortage. In the future also, the Government of Maharashtra plans to meet this shortage through investing
largely into fossil fuel based power plants. The speech of the Honourable Chief Minister4 Mr. Vilasrao
Deshmukh at the Conference of Chief Minister on Power sector, May 28, 2007 clearly etches out the
government’s plans to invest into fossil fuel power plants.
Apart from this, the central government has envisaged capacity addition of 100,000 MW5 by 2012 to
meet its mission of power for which five Ultra Mega Power Projects (UMPP) of capacity 4,000 MW each
are being brought up. The projects were awarded on International competitive bidding (ICB) basis. Out of
them, two have been awarded to private parties. Owing to the principle of large scale economies, these
projects have managed to quote very low prices (lowest bid for Rs. 1.19) as compared to other sources of
energy. Incidentally, four of these five UMPP’s would be located in the western region and Maharashtra
would be drawing heavily from these generating stations. Below is the table from the same report, which
states the demand stated and the tentative allocation of power from these projects to the respective states.
Table B.4: Quantum of demand as projected by various states from UMPP
S. State Sasan Mundra Akaltara Ratnagiri Coastal Site
No (Madhya (Gujarat) (Chhattisgarh) (Maharashtra) (Karnataka)
Pradesh)
1 Delhi 600 750 - - -
2 Uttar Pradesh 1000 500 1000 - -
3 Uttaranchal 200 - - - -
4 Punjab 1000 1000 - - -
5 Rajasthan 500 750 750 500 300
6 Haryana 850 700 700 - -
3
Indian Wind Turbine Manufacturers Association.
http://www.indianwindpower.com/potential.html
4
http://www.maharashtra.gov.in/english/chiefminister/POWERSPEECH-%20New%20Delhi-
%2028%20May%202007.pdf
5
Ministry of Power, India
http://powermin.nic.in/whats_new/pdf/development_of_project.pdf
13
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Madhya
7 Pradesh 1500 - 1000 500 -
8 Chhattisgarh 500 - 1500 500 -
9 Gujarat 1600 - - - -
10 Maharashtra 1500 1000 2000 1000 -
11 Karnataka - - 500 1500 -
12 Tamilnadu - 500 - 1000 -
13 Kerala - - - - 200
14 A.P - - - - -
Total 6150 6050 6300 4000 4000
Table B.5: Tentative power allocation from the proposed five UMPP
S. State Sasan Mundra Akaltara Ratnagiri Coastal Site
No (Madhya (Gujarat) (Chhatisgarh) (Maharashtra) (Karnataka)
Pradesh)
1 Delhi 500 - - - -
2 Uttar Pradesh 500 300 - - -
3 Uttaranchal 100 - - - -
4 Punjab 600 500 - - -
5 Rajasthan 400 400 - 500 300
6 Haryana 450 400 - - -
Madhya
7 Pradesh 1200 - - 500 -
8 Chhattisgarh 250 - - 500 -
9 Gujarat 1600 - - -
10 Maharashtra 800 - 2000 1000 -
11 Karnataka - - 500 1500 -
12 Tamilnadu - - - 1000 -
13 Kerala - - - - 200
Andhra
14 Pradesh - - - - -
Total 4000 4000 - 4000 4000
With market forces favouring fossil fuel based conventional power plants in the future and government’s
full fledged support to these projects (Refer: Paragraph 3 of Development of Ultra Mega Power Projects,
Ministry of Power) the western region in the coming years is soon going to become highly carbon
intensive. Thus, clearly, the prevailing practice in the state and the region is that of investing into
conventional fossil fuel based power plants.
Regulatory Risk:
A healthy regulatory environment is a pre-requisite for the development of wind power in the country,
due to the inbuilt disadvantages of this source. Following are few of the issues which question the
feasibility of wind power projects in the existing scenario.
14
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
“MERC shall be approached to review the tariff structure (contained in the Agreement) once the
project becomes eligible for CDM benefit or similar credits and any mechanism for sharing of
CDM or similar credit between the seller (in this case PPL) and MSEDCL. The decision of the
MERC will be binding on both parties.”
Though an Agreement has been signed, the rate at which electricity will be sold to MSEDCL may change
if the project is benefited under CDM or they may have to share the benefit with MSEDCL. The extent of
sharing of the CDM benefit has not been specified by MERC. Benefit sharing of this sort decreases the
net expected revenues to the project and thus affects the returns. Moreover, no fixed proportion of the
CDM sharing has been mentioned, thus causing huge uncertainty in the returns to the project. In such a
case, a healthy benefit from CDM will ensure that any legible proportion of benefit sharing stated by the
MERC does not affect the returns to the project greatly. Hence, this is a big risk undertaken by the project
promoter as his revenue, either from the sale of electricity or from the CDM benefit may be affected
depending upon the decision of MERC.
The following is an excerpt from the MERC order in the matter of application filed by the (i) Maharashtra
State Electricity Board [MSEB], (ii) Shri Pratap G Hogade, (iii) Renewable Energy Developers
Association of Maharashtra [REDAM], and (iv) Indian Wind Energy Association [INWEA] for
procurement of wind energy & wheeling for third party-sale and/ or self-use, 2002, which discusses the
regulatory commission’s policy to introduce the concept of CDM benefit sharing.
“The Commission understands that several renewable energy projects may be eligible for the
benefits available through the “Clean Development Mechanism” under Kyoto Protocol. While
these benefits are not available to a large number of projects which are on the verge of
commercial viability, they can be availed of in future. Since the consumer is supporting the
renewable energy projects by way of higher tariffs, it is essential that any such credits secured by
a project should be shared on an equitable basis by the developer with the utility and its
consumers. The Commission shall review the tariff structure for RE Projects that become eligible
for CDM or similar credits, and devise a system, which will enable sharing of benefits between
the consumers and the project developers at that stage.”
The extract also mentions that once the project has been registered as a CDM project the tariff for the
project would be reviewed. Thus, uncertainty also lies in the tariff which would be applicable to the entire
project.
Though the investors are eligible for the entire CDM benefits for investing into clean technology yet they
would be entitled to only a small portion of it because of the policy of sharing with the utility. Moreover,
the financial returns to the project initially conceived would also change if and when the commission
revises the tariff applicable. Thus a great deal of uncertainty exists even after the investors become
entitled to CDM benefits. The importance of the CDM benefits to the project is reflected from the fact
that the investors still want to go for apply for CDM benefits.
15
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The power purchase agreement signed between project participants and the utility will last only for 13
years from the date of commercial operation. Beyond this period, the tariff rate applicable is highly likely
to change. Keeping in mind the following issues, decrease in the tariff rates would not be surprising:
− Unhealthy financial status of the utilities
− Introduction of Availability Based Tariff
− Competitive Bidding
Thus, for the rest of the seven years of operation of the project, great deal of uncertainty will exist among
the present investors. Moreover, past record related to group 2 projects (projects commissioned between
27th December 1999 and 1st April 2003) do not portray a very encouraging picture. The group 2 projects
which had a PPA of ten years are facing great trouble as their agreement has neither been renewed nor
extended. Thus, the project proponents are incurring huge losses for the same. In a situation like this,
wind power projects are definitely not the most preferable investment strategy. However, the proponents
of this project have still gone ahead to invest in a green energy to contribute to the process of sustainable
development.
Other barriers
i) Grid related problems
Wind generated electricity do not form part of the base load to the grid. The infrequent nature of wind
power is the main reason behind it. In case of low demand or the requirement of maintaining the grid
stability, wind power is often disconnected from the grid. This leads to loss of the generated electricity
and thus loss to the revenue earned by the investors. There are various other grid related problems which
face wind power for example poor grid availability, grid outages etc. For instance, on the 25th February,
2007, a major grid disturbance occurred where in the 400 kV and 220 kV lines in western Maharashtra
tripped. Below is an extract from the press release of the incident (Source: http://www.wrldc.com/):
“Preliminary reports indicate that a fault occurred around Phadge, Nagothane, Bableshwar area
of Maharashtra causing multiple line trippings. These trippings led to islanding of Gujarat,
Western Maharashtra and Mumbai system and loss of generation of around 4000 MW in Western
grid including Tarapur nuclear station.”
Such incidences cause loss of the generated electricity. Although the loss is applicable to all sources, it is
more crucial for a renewable energy sources as these are not as competitive and efficient on other grounds
like technology, cost of electricity etc.
The project proponent being in the Bidi manufacturing did not have any expertise in the renewable energy
business. The technology was new to them. They did not have the infrastructure or organizational
capacity to manage, operate and maintain the wind mills. They also did not have skilled manpower to
operate the machines. The available manpower was trained to work in Bidi industry and did not have the
capacity to absorb the new technology of wind mill operation and linking up with grid supply. Under this
situation the alternative was to invest the money in the own business and not replace the grid power
16
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
which came mainly from fossil fuel based plants. Instead, the project proponent has taken up this risk and
tried to overcome the barrier by incurring a recurring expenditure by appointing the supplier itself to
operate and maintain the project activity.
The project activity therefore is subject to a very high degree of uncertainty on account of the
unpredictable and varying wind pattern in Maharashtra and the ensuing low capacity utilization factors.
The associated risk is further compounded because of the fact that the project activity uses higher
capacity (1.25 MW) S70 class machines whose capital cost is significantly higher than other wind turbine
types. Therefore achieving a high CUF is critical to the project’s viability. The risk associated with the
project activity is substantially higher than conventional power generation activities and also other wind
power projects. These risks have actually materialized in case of the project activity as evident from the
fact that the actual CUF achieved by the project activity since inception is less than 19%.
The barriers outlined above have the potential to render the present project unviable. In a scenario like
this, risk mitigating mechanisms like CDM revenues can help the project to a great deal.
Baseline Scenario
For the project activities that do not modify or retrofit an existing electricity facility, the baseline scenario
is the following:
Electricity delivered to the grid by the project would have otherwise been generated by the operation of
grid connected power plants and by addition of new generation sources. The baseline emission factor
(EFy) is calculated in transparent and conservative manner as combined margin (CM), consisting of the
combination of Operating Margin (OM) and Build Margin (BM) and the weighted average emission rate.
Calculation of this emission factor is based on data from an official source and is made publicly available.
17
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Version : 2.0
Dated : 21st June 2007
This database is prepared as per ACM0002, Version 6.
(Reference: http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm )
b) EFOM,y
Data / Parameter: EFOM,y
Data unit: tCO2/GWh
Description: CO2 Operating margin emission factor of the grid.
Source of data used: CEA: ‘The CO2 Baseline Database for the Indian Power Sector’
Version 2.0, 21st June 2007
Value applied: 998.5460
Justification of the − This is used in calculation of emission factor EFy.
choice of data or − The emission factor is calculated ex-ante at the time of PDD
description of submission.
measurement methods
and procedures actually
applied :
Any comment: Calculated as indicated in ACM0002.
c) EFBM,y
Data / Parameter: EFBM,y
Data unit: tCO2/GWh
Description: CO2 Build margin emission factor of the grid.
Source of data used: CEA: ‘The CO2 Baseline Database for the Indian Power Sector’
Version 2.0, 21st June 2007
Value applied: 630.00
18
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The operating margin emission factor has been calculated using a 3 year data vintage:
The EFOM,Y is estimated to be:
For the year 2003-2004 the EFOM,Y is 990.3 tCO2/GWh
For the year 2004-2005 the EFOM,Y is 1012.0 tCO2/GWh
19
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
The EFBM,Y is estimated as 630.0 tCO2/GWh (with sample group m constituting most recent capacity
additions to the grid comprising 20% of the system generation).
6
As stated in the ACM0002 version 6.
20
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
From the above table the weightage average emission rate for the current generation mix is given as the
882.9 tCO2/GWh.
Total project activity emissions, including leakage are zero for the project activity.
Therefore, net anthropogenic emission reductions due to the proposed project are equal to the baseline
emissions on a yearly basis. The annual emissions reductions are equal to 2,299 tCO2.
21
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
b) EFy
Data / Parameter: EFy
Data unit: tCO2/GWh
Description: Emission factor of the existing generation mix
Source of data to be CEA: ‘The CO2 Baseline Database for the Indian Power Sector’
used: Version 2.0, 21st June 2007
Value of data The baseline emission factor would be furnished every year and data of the
year in which project generation occurs will be used.
22
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Description of The data will be taken from the CEA database and this data is made publicly
measurement methods available.
and procedures to be
applied:
QA/QC procedures to The CO2 Baseline Database is taken from Central Electricity Authority (CEA),
be applied: Ministry of Power, Govt. of India hence it is authenticated and reliable.
Any comment: Used to calculate emission reductions every year
a) Tower Torquing
b) Blade Cleaning
c) Nacelle Torquing and Cleaning
d) Transformer Oil Filtration
e) Control Panel & LT Panel Maintenance
f) Site and Transformer Yard Maintenance
2 Security Services
This service includes watch & ward and security of the wind farm and the equipment.
3 Management Services
a) Data logging in for power generation, grid availability, machine availability.
b) Preparation and submission of monthly performance report in agreed format.
c) Taking monthly meter reading jointly with SEB, of power generated at each wind farm and
supplied to SEB grid from the meter/s maintained by SEB for the purpose and co-ordinate to
obtain necessary power credit report/ certificate.
4 Technical Services
a) Visual inspection of the WTG and all parts thereof.
b) Technical assistance including checking of various technical, safety and operational
parameters of the Equipment, trouble shooting and relevant technical services.
Leakage
The project activity essentially involves generation of electricity from wind, the employed WEGs convert
wind energy into electrical energy and do not use any other input fuel for electricity generation. Thus no
special ways and means are required to monitor leakage from the project activity.
23
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Metering Equipment
The project activity essentially involves generation of electricity from wind, the employed WEG can only
convert wind energy into electrical energy and cannot use any other input fuel for electricity generation.
Thus no special ways and means are required to monitor leakage from the project activity.
1. The proposed CDM project activity requires evacuation facilities for sale to grid and the
evacuation facility is essentially maintained by the state utility MDEDCL, which also requires
electricity generation measurements.
2. The project activity has therefore envisaged two independent measurements of generated
electricity from the wind turbines.
3. The primary recording of the electricity fed to the state utility grid will be carried out jointly at
the incoming feeder of the state power utility, MSEDCL. The metering is carried out at the sub
station via a common meter for a group of windmills that is inclusive of the WEGs not a part of
this proposed CDM project activity. However, metering of the sole WEG is observed at two
distinct levels:
3.a.: At the first level, the generation from the sole WEG is recorded by an energy meter
installed near the machine. This is a combination of a main and a check meter. This meter
provides monthly generation data and the records are maintained on paper and
electronically for reference. The meters installed at the feeder of the state power utility
are calibrated periodically. The joint measurement will be carried out once in a month.
3.b.: The secondary monitoring, which will provide a backup (fail-safe measure) in case
the primary monitoring is not carried out, would be done at the WEG. WEG is equipped
with an integrated electronic meter. This meter is connected to the Central Monitoring
Station (CMS) of the wind farm maintained by Suzlon Energy Limited. The generation
data of individual machine can be monitored as a real-time entity at CMS. The snapshot
of generation on the last day of every calendar month will be kept as a record both in
electronic as well as printed (paper) form.
4. JMRs are taken at the feeder level by the local electricity utility. The JMR readings can be further
broken in to the individual turbine generation with the help of generation data from the central
monitoring station of the WTGs. Therefore, for monitoring of the project activity, data shall be
gathered from both the sources and the most conservative values shall be taken for calculating
emission reductions arising from each WTG.
5. The investors have entered into Operation & Maintenance Agreement with the EPC contractors
M/s. Suzlon Infrastructure Services Limited (SISL), (then, Suzlon Wind Farm Services Limited)
for carrying out the necessary maintenance of the installations during the designed life of the
project. SISL will be responsible for collecting the necessary data in order to monitor emission
reductions generated by the project activity.
6. SISL will do the operation and maintenance of the installations and measurement of generated
electricity is done by state electricity utility. The EPC contractors are ISO certified organizations
and follow designated procedures for the assigned tasks.
B.8 Date of completion of the application of the baseline and monitoring methodology and the
name of the responsible person(s)/entity(ies)
>>
24
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Contact Organisation:
Senergy Global Private Limited
9th Floor, Eros Corporate Tower, Nehru Place,
New Delhi – 110 019
India.
Tel. : +91- 11- 4180 5501
Fax : +91- 11- 4180 5504
E.mail : [email protected]
Url : www.senergyglobal.com
C.2.2.2. Length:
25
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
>>
10 years 0 month.
D.1. If required by the host Party, documentation on the analysis of the environmental impacts
of the project activity:
>>
According to Indian regulation, the implementation of the wind park does not require an Environmental
Impact Assessment (EIA) study. As per the prevailing regulations of the Host Party i.e. India represented
by the Ministry of Environment and Forests (MoEF), Govt. of India and also the line ministry for
environmental issues in India, Environmental Impact Assessment (EIA) studies need not to be conducted
for the projects which comes under the list whose investment is less than Rs. 1000 millions7, 8 Since the
Wind parks are not included in this list and also the total cost of the project is only Rs 64.73 millions, the
project activity doesn’t call for EIA study.
Also, in the redefined EIA notification i.e. S.O. 15339, dated 14th September 2006, Ministry of
Environment & Forests (MoEF), Govt. of India, the wind projects are not included in the list of projects
that has to get Prior Environmental Clearance (EC) either from State or Central Govt. authorities and
hence no EIA study was conducted.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
>>
Since the project is a electricity generation through a clean and renewable source of energy i.e. wind, the
project doesn’t creates negative impact on the environment. Hence, no EIA conducted and thereby no
reports or documents available.
E.1. Brief description how comments by local stakeholders have been invited and compiled:
>>
The local stakeholders identified for the project activity were as follow;
− Maharashtra State Electricity Distribution Company limited, MSEDCL
− Maharashtra Energy Development Agency (MEDA)
− The local people of village Jarandi.
The land used for implementation of the Wind farm belongs to the villagers and has been procured by the
EPC contractor “Suzlon Energy Limited” for development of WEG wind farm purposes, thus local
7
S.O. 60 (E), Environment Impact Assessment Notification, Ministry of Environment and Forests, Govt. of India
dated 27th January 1994.
8
Amendments made on 13th June 2002 vide S.O. 632 (E), Ministry of Environment and Forests, Govt. of India.
9
Page No: 10, S. O. 1533, Ministry of Environment & Forests (MoEF), Govt. of India,
http://envfor.nic.in/legis/eia/so1533.pdf
26
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
stakeholders was approached right at the inception of the project. The concerned land has been sold to
Chhotabhai Jethabhai Patel & Co.
The villagers were apprised about the proposed use of land and their consent was taken for the same. The
villagers entered into commercial agreement with the EPC contractor for selling out their land for the
wind farm activity, and proper documentary evidence (sale agreements) for transfer of land to the EPC
contractors are available for validation.
E.3. Report on how due account was taken of any comments received:
>>
The submissions from the villagers were considered by the concerned management and
− The right of way was given to the villagers even after selling land to the EPC contractors.
− Employment of O & M staff, up to the level of technicians and machine supervisors has been
done from the local villages only.
27
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 1
28
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 2
There is no public funding involved in the project activity and the project participants hereby confirm that
there is no diversion of overseas development assistance.
29
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 3
BASELINE INFORMATION
VERSION 2.0
DATE 21 June 2007
BASELINE METHODOLOGY ACM0002 / Ver 06
EMISSION FACTORS
Weighted Average Emission Rate (tCO2/MWh) (excl. Imports) Weighted Average Emission Rate (tCO2/MWh) (incl. Imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
North 0.7237 0.7265 0.7379 0.7095 0.7134 0.7137 North 0.7237 0.7265 0.7401 0.7098 0.7203 0.7240
East 1.0876 1.0573 1.1128 1.1035 1.0768 1.0756 East 1.0876 1.0320 1.0852 1.0758 1.0534 1.0473
South 0.7347 0.7451 0.8231 0.8417 0.7837 0.7353 South 0.7446 0.7478 0.8235 0.8417 0.7843 0.7355
West 0.8988 0.9247 0.9034 0.9020 0.9242 0.8746 West 0.8984 0.9242 0.9026 0.9009 0.9234 0.8829
North-East 0.4239 0.4140 0.4020 0.4281 0.3180 0.3309 North-East 0.4239 0.4140 0.4020 0.4281 0.4799 0.3309
India 0.8216 0.8309 0.8546 0.8507 0.8423 0.8170 India 0.8191 0.8284 0.8520 0.8479 0.8397 0.8145
Simple Operating Margin (tCO2/MWh) (excl. Imports) Simple Operating Margin (tCO2/MWh) (incl. Imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
North 0.9768 0.9778 0.9988 0.9870 0.9745 0.9933 North 0.9768 0.9778 0.9996 0.9871 0.9758 0.9946
East 1.2198 1.2210 1.2025 1.2303 1.2037 1.1585 East 1.2198 1.1874 1.1703 1.1959 1.1745 1.1255
South 1.0219 1.0001 1.0071 1.0041 0.9997 1.0073 South 1.0292 1.0001 1.0065 1.0041 0.9999 1.0073
West 0.9791 1.0102 0.9845 0.9922 1.0132 0.9936 West 0.9784 1.0094 0.9830 0.9903 1.0120 0.9934
North-East 0.7335 0.7101 0.7418 0.7366 0.7143 0.6994 North-East 0.7335 0.7101 0.7418 0.7366 0.8402 0.6994
India 1.0169 1.0239 1.0207 1.0259 1.0274 1.0228 India 1.0132 1.0202 1.0170 1.0217 1.0234 1.0189
Build Margin (tCO2/MWh) (excl. Imports) Build Margin (tCO2/MWh) (not adjusted for imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
30
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Combined Margin (tCO2/MWh) (excl. Imports) Combined Margin in tCO2/MWh (incl. Imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
North 0.7552 0.7557 0.7662 0.7603 0.7540 0.7969 North 0.7552 0.7557 0.7666 0.7603 0.7547 0.7976
East 1.0620 1.0626 1.0534 1.0673 1.0540 1.0628 East 1.0620 1.0458 1.0373 1.0501 1.0394 1.0463
South 0.8654 0.8545 0.8580 0.8565 0.8543 0.8593 South 0.8690 0.8545 0.8577 0.8565 0.8544 0.8593
West 0.8746 0.8901 0.8773 0.8811 0.8916 0.8118 West 0.8742 0.8897 0.8765 0.8802 0.8910 0.8117
North-East 0.4395 0.4278 0.4437 0.4411 0.4299 0.4242 North-East 0.4395 0.4278 0.4437 0.4411 0.4929 0.4242
India 0.8561 0.8596 0.8580 0.8606 0.8614 0.8534 India 0.8543 0.8578 0.8562 0.8585 0.8594 0.8515
31
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
South 121,158 123,630 127,789 128,373 134,676 138,329 South 89,019,263 92,112,060 105,187,726 108,049,156 105,539,862 101,712,149
West 150,412 153,125 164,448 159,780 170,726 176,003 West 135,192,153 141,597,621 148,557,341 144,127,175 157,781,065 153,933,199
North-East 5,195 5,213 5,671 5,752 7,762 7,655 North-East 2,202,108 2,158,348 2,280,049 2,462,796 2,468,463 2,532,819
India 465,345 481,479 502,492 517,376 548,423 576,206 India 382,306,576 400,038,640 429,426,898 440,147,681 461,958,846 470,751,761
20% of Net Generation (GWh) Net Imports (GWh) - Net exporting grids are set to zero
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
North 27,046 28,283 28,949 31,009 31,458 33,641 North 0 0 0 0 3,616 5,748
East 10,670 11,619 11,968 13,686 15,594 17,203 East 489 555 357 1,689 0 0
South 24,232 24,726 25,558 25,675 26,935 27,666 South 1,162 1,357 518 0 0 0
West 30,082 30,625 32,890 31,956 34,145 35,201 West 321 0 797 962 285 11,982
North-East 1,039 1,043 1,134 1,150 1,552 1,531 North-East 0 0 0 0 2,099 0
India 93,069 96,296 100,498 103,475 109,685 115,241
Net Generation in Build Margin (GWh) Share of Net Imports (% of Net Generation)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
32
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
North 32,064 34,340 North 0.0% 0.0% 0.0% 0.0% 2.3% 3.4%
East 15,818 17,567 East 0.9% 1.0% 0.6% 2.5% 0.0% 0.0%
South 27,987 28,158 South 1.0% 1.1% 0.4% 0.0% 0.0% 0.0%
West 35,257 35,425 West 0.2% 0.0% 0.5% 0.6% 0.2% 6.8%
North-East 2,055 1,793 North-East 0.0% 0.0% 0.0% 0.0% 27.0% 0%
India 113,181 117,283
33
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
Annex 4
MONITORING INFORMATION
The investors have entered into Operation & Maintenance Agreement with the EPC contractor M/s.
Suzlon Energy Limited for carrying out the necessary maintenance of the installations during the
designed life of the project. The O & M is furnished in the flow chart below. The agency will be
responsible for the operation and maintenance activities that will be implemented in order to monitor
emission reductions generated by the project activity and are described as under:
The organization structure for the Operation and Maintenance of the windmills is depicted below:-
Manager (Windmills)
(at Wind Farm site)
Site In-charge
(at Wind Farm site)
Supervisor
(at Wind Farm site)
g) Tower Torquing
h) Blade Cleaning
i) Nacelle Torquing and Cleaning
j) Transformer Oil Filtration
k) Control Panel & LT Panel Maintenance
l) Site and Transformer Yard Maintenance
2 Security Services
34
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
This service includes watch and ward and Security of the Wind Farm and the Equipment.
3 Management Services
d) Data logging in for power generation, grid availability, machine availability.
e) Preparation and submission of monthly performance report in agreed format.
f) Taking monthly meter reading jointly with SEB, of power generated at each Wind Farm and
supplied to SEB Grid from the meter/s maintained by SEB for the purpose and co-ordinate to
obtain necessary power credit report/ certificate.
4 Technical Services
c) Visual inspection of the WTG and all parts thereof.
d) Technical Assistance including checking of various technical, safety and operational
parameters of the Equipment, trouble shooting and relevant technical services.
Leakage
The project activity essentially involves generation of electricity from wind, the employed WEGs convert
wind energy into electrical energy and do not use any other input fuel for electricity generation. Thus no
special ways and means are required to monitor leakage from the project activity.
Metering Equipment
The details about the metering equipment and procedures are mentioned in section B.7.2 of the PDD.
-----
35