Form, Punchlist Form
Form, Punchlist Form
I GROUND FLOOR
Ceiling
Walls
Windows
Doors & Jambs
Floor
Kitchen Counter
Cabinets
III TOILET & BATH
Ceiling
Walls
SCW
Doors & Jambs
Floor Tiles
Fixtures (Plumbing)
Fixtures (Electrical)
IV BEDROOMS
Ceiling
Walls/Partitions
Windows
Doors & Jambs
Flooring (vinyl tiles)
Cabinets/Closet
Electrical Fixtures
V EXTERIOR
Ceiling
Main Roof / Canopy
Perimeter Walls
Pre-cast décor
Catch Basin
Septic Tank and Cover
Serv. Entrance Post
Perimeter Area
VI OTHERS
We expect you to mobilize this ___________________,_____, and complete the repair works on / before _________________,______
Should you fail, the company has the option to take over remaining works / project or exercise necessar measures to complete the
works and all incurred cost will be charge to your account.
Punchlisted by: Conforme: Re-inspected & Approved: