IMIInternal Bracing Guide
IMIInternal Bracing Guide
Preface: Masonry under construction must be temporarily braced until the final lateral support
system is in place. The importance of this bracing is paramount to the safety of both the general
public and those involved with the project under construction. The Standard Practice for
Bracing Masonry Walls Under Construction provides engineering principles and properties for
rationally design bracing systems for masonry walls under construction. Internal bracing, or
using the developing strength of the masonry assembly, can provide significant benefits to a
project team. To support the engineering community in the use of structural masonry, including
effective and efficient temporary bracing, the International Masonry Institute has funded this
guide.
This Guide has been developed by the International Masonry Institute (IMI) for use by engineers
and other qualified persons designing masonry bracing systems. It provides an outline of the
process and illustrates the application of engineering principles for bracing masonry walls using
the wall’s inherent strength rather than external bracing elements. This concept is known as
‘Internal Bracing’ and has been successfully applied in numerous projects with short to very tall
walls.
Bracing masonry walls under construction is a life safety necessity that is mandated by each
state’s legally adopted building code through the referenced masonry standards. The 2011
‘Specification for Masonry Structures’ (TMS 602/ACI 530.1/ASCE 6) was adopted by the 2012
International Building Code for masonry construction and contains requirements for the mason
contractor to ‘Design, provide, and install bracing that will assure stability of masonry during
construction.’ Bracing is also part of federal occupational safety requirements including national
regulations -- OSHA Safety and Health Regulations for Construction (CFR 29) Part 1926.706
and locally adopted regulations -- Michigan’s MiOSHA Construction Standard Part 2, as an
example. Bracing protects project workers as well as the general public who may access the site,
be passing by, or even occupying adjacent facilities or spaces.
Masonry bracing is typically designed by an engineer retained by the project’s mason contractor,
although there is some movement in the industry to incorporate Internal Bracing capacity into the
project’s construction documents prepared by the Engineer of Record. There is an industry
standard for bracing masonry walls: ‘Standard Practice for Bracing Masonry Walls Under
Construction’, 2012, sponsored by IMI and the Mason Contractors Association of America
(MCAA) and published by MCAA. There also are compiled examples and technical literature
available through industry sources as well as proprietary information for external bracing
systems. This Guide applies the content of the Standard and other documents along with
knowledge gained through experience to provide users with one approach to designing internally
braced masonry walls.
The International Masonry Institute offers quality training for craftworkers, professional
education for masonry contractors and free technical assistance to the design and construction
communities. IMI is a strategic alliance between the International Union of Bricklayers and
Allied Craftworkers (BAC) and their signatory contractors to promote quality masonry
construction.
Team IMI consists of architects, engineers, construction managers, skilled craftworkers and
instructors, offering what no other group can: expertise in training, craftsmanship, design,
installation and marketing. That means buildings built by union craftworkers and contractors get
built the right way.
Author
IMI and Walkowicz Consulting Engineers, LLC disclaim all warranties, expressed or implied,
including but not limited to implied fitness for a particular purpose, with respect to this manual.
All designs resulting from the processes defined in this manual should be verified to the user’s
satisfaction. The contents of these written materials may include technical inaccuracies or
typographical errors and may be revised without notice.
This document is intended for the use of industry professionals who are competent to evaluate
the significance and limitations of the information provided herein. This publication should not
be used as the sole guide for masonry Internal Bracing design and construction.
Thanks
IMI and Walkowicz Consulting Engineers, LLC would like to thank Dailey Engineering, Inc.,
Bergmann Associates, Davenport Masonry and Koch Masonry for their willingness to share
ideas based on their work with internally braced masonry walls under construction and for
photographs and figures shared to better illustrate the concepts presented herein. Additional
thanks are extended to Dailey Engineering and Bergmann Associates for their time and effort
spent reviewing this document.
Table of Contents:
Table of Figures: ......................................................................................................................... 1
Section 1: Concepts for Bracing Masonry Walls Under Construction ....................................... 2
1. General.......................................................................................................................... 2
2. External Bracing ........................................................................................................... 2
3. Internal Bracing ............................................................................................................ 2
4. Communication Between the Engineer and the Mason Contractor ............................. 3
5. Modifying Requirements Shown in the Construction Documents ............................... 5
6. The Role of Special Inspection ..................................................................................... 6
Section 2: Short Term Design Approach .................................................................................... 7
1. General.......................................................................................................................... 7
2. Masonry ........................................................................................................................ 9
3. Foundation and Soils .................................................................................................. 10
Section 3: Internal Bracing Design ........................................................................................... 12
1. Analysis ...................................................................................................................... 12
2. Deliverables ................................................................................................................ 13
Section 4: Design Examples ..................................................................................................... 16
1. Component Software (Structural Masonry Design System, V5.0.1) ......................... 17
2. Finite Element (Ram Elements) ................................................................................. 22
Section 5: Concluding Remarks................................................................................................ 26
Table of Figures:
Figure 1: Cantilevered Wall Diagram ............................................................................................ 7
Figure 2: Sample Bracing Plan Graphics, Notes and Legend ...................................................... 15
Figure 3: Design Basis Menu – Codes tab ................................................................................... 17
Figure 4: Design Basis Menu – Concrete Masonry tab ............................................................... 17
Figure 5: Out of Plane Wall Design – Design Data tab ............................................................... 18
Figure 6: Out of Plane Wall Design – Construction Data tab...................................................... 18
Figure 7: Out of Plane Wall Design – Load Data tab .................................................................. 19
Figure 8: Analysis Results – Interaction Diagram Showing Insufficient Capacity ..................... 19
Figure 9: Return to Design Basis – Modify masonry strength .................................................... 20
Figure 10: Analysis Results – Interaction Diagram Showing Sufficient Capacity...................... 21
Figure 11: Data Input Field - Masonry Properties ....................................................................... 22
Figure 12: Data Input Field - Geometry ...................................................................................... 22
Figure 13: Data Input Field - Masonry Criteria ........................................................................... 23
Figure 14: Data Input Field - Loads ............................................................................................. 23
Figure 15: Data Input Field – Design Data .................................................................................. 24
Figure 16: Analysis Report – Good bar size, excessive bar spacing ........................................... 24
Figure 17: Analysis Report – Good bar size and spacing ............................................................ 25
Table of Photographs:
Photograph 1: External pipe braces utilized on a masonry wall under construction. .................... 2
Photograph 2: Masonry walls under construction utilizing Internal Bracing. ............................. 3
2. External Bracing
While not the focus of this Guide, it is
important to note that masonry walls can be
braced using external components. External
bracing has been used effectively for years
and can provide appropriate capacity for
masonry walls under construction and it may
be necessary for certain masonry wall
configurations that cannot be adequately
braced using the wall’s internal capacity.
Advantages of this system include
familiarity, visible components and the
availability of numerous proprietary systems
which are readily available. Disadvantages
of this system may include lack of sufficient
capacity due to improper construction or
installation, inappropriate consideration
given to wall connections and base Photograph 1: External pipe braces utilized on a masonry
wall under construction with anchorage to block pallet 'skids'
anchorage, interference with and exposure to and column foundations. (Credit: Davenport Masonry, Holt,
damage from site traffic and activities (for MI)
example: construction equipment running into braces or their anchorage, trades removing braces
such as steel erectors needing to set roof structure or electricians or plumbers needing to install
trenches for underground utilities and more), mobilization and de-mobilization time and expense,
material acquisition/rental and storage expense as well as the need for anchorage connection to
something with sufficient capacity to resist the loads imparted from the brace. External bracing
is, however, an engineered system with a long track record of successful implementation that
provides good value to the project team and the building owner.
3. Internal Bracing
This Guide presents a newer method for bracing masonry walls under construction: Internal
Bracing. This method provides a highly effective and efficient method to provide stability to
Footing Size The least common shortcoming found in design document engineering,
when considering Internal Bracing, is footing size. When properly
considered for short term loading and life safety only, most existing footings provide sufficient
stability. In fact, footings with a depth of 24 inches or more and a width equal to the wall
thickness plus 4 inches are adequate for the majority of internally braced wall systems. If
footing size is found to be lacking, adjustments can be made and submitted for approval.
Design for the In the Standard, the ‘under construction’ phase definition can be
paraphrased as the entire time between the when the masonry is first laid
Intermediate
and when the wall’s final lateral support is in place. That time period is
Period
broken into two distinct phases: The ‘Initial Period’ and the ‘Intermediate
Period’ and there are different design requirements and restrictions for each. Walls are generally
considered ‘unbraced’ in the Initial Period in that only the wall’s self weight is considered
effective in resisting overturning and flexural stresses. Because of that, walls in the Initial Period
are given prescriptive maximum heights in the Standard and evacuation of the Restricted Zone is
required at lower wind speeds. The primary focus of Internal Bracing and this Guide is bracing
to resist wind load during the Intermediate Period. The Intermediate Period is defined in the
Standard as being ‘The period of time following the Initial Period until the wall is connected to
the elements that provide its final lateral support.’ That can be interpreted as being the period
from when the masonry is more than a day old until the wall is connected to a diaphragm or
other elements that are sufficiently capable of transferring lateral force from the wall through
other elements to the foundation. The intent is that the wall be connected to a continuous lateral
system. Bar joists or beams bearing on or connected to the wall, without connection to a deck or
even when connected to a deck, without an effective shear wall or other bracing may not qualify
as ‘final lateral support’ and each project condition should be evaluated independently to
determine when the Intermediate Period ends.
Remember:
The objective of Internal Bracing design is keeping the wall up during
construction and long enough to provide time for evacuation during
a wind event! Serviceability and protection of property is not the
intended outcome when bracing is designed to the Standard.
Internal bracing can, however, be effective for maintaining
serviceability after a wind event by designing to higher or even
occupancy level wind speeds.
Intermediate Masonry can spend a significant amount of time in the Intermediate Period,
depending on when floor and roof decks are installed and when the final
Period Design
lateral system is fully implemented. It’s a good thing, then, that masonry
begins gaining strength and can often provide its own support for resisting short term loads
during construction. During the Intermediate Period, the Restricted Zone must be evacuated
when the wind speed exceed 35 miles per hour. That evacuation wind speed is coupled with a
design wind speed of 40 miles per hour to, again, provide a time buffer to facilitate evacuation.
Masonry in the Intermediate Period is characterized by being either unreinforced or reinforced.
Unreinforced masonry will resist over-turning and flexure through a combination of self-weight
and flexural stress or strength. Reinforced masonry can provide significant internal bracing
capacity through self-weight and the tension-compression couple developed between the
masonry and reinforcement. See Section 2.2 for a discussion of the design approaches.
Remember:
Reinforced masonry must have the reinforcement and grout installed
AND the grout must have cured either 12 hours or 24 hours,
depending on the length of lap splices employed. If the grout has not
cured sufficiently, analyze the wall as unreinforced as noted above
until the grout has cured.
Chapter 5 of the Standard provides in-depth requirements for Strength and Allowable Stress
designs. Appendix A of the Standard provides tabulated summaries of values for certain block
sizes and mortar types and is a nice place to gather quick design solutions for many bracing
Eliminate the Another point worth discussing is that of eliminating the Restricted Zone.
This can be a great tool when the Restricted Zone extends into roadways or
Restricted
pedestrian walkways that cannot be closed or easily protected. It can also
Zone
prove highly beneficial when the Restricted Zone extends over adjacent
building spaces that must remain occupied during construction. The basic premise for
eliminating the Restricted Zone is to design the Internal Bracing for wind loads based on the full
design level wind speed. Because the wind pressure will increase with the square of the wind
velocity, the pressures will be much greater than those for the standard Intermediate Period wind
speed. For example, the design pressure for a 90 mile per hour wind will be 20.7 pounds per
square foot compared with 4.1 psf for the 40 mile per hour Intermediate Period wind. Note that
bracing designers could implement a risk based approach through documents such as ASCE 37
where comparable exceedance probability could yield wind velocity and/or pressure less than
that. Higher design wind velocities and the resulting higher pressures will more frequently
require modifications to the occupancy design requirements including reinforcement quantity
and possibly foundation size. Evaluate the requirements and the cost effectiveness of
implementing Internal Bracing then submit the changes for approval by the designers of record.
2. Deliverables
Once an Internal Bracing scheme has been evaluated and designed, it is
Communication
important to properly and fully represent that design through verbal and
Tools
graphic documentation. Such documentation provides the mason
Remember:
If you plan to vary from ANY occupancy design provisions included
in the project drawings or specifications – submit those changes in
writing through an RFI or other appropriate device AND receive
approval PRIOR to proceeding with Internal Bracing design.
Remember:
Most Internal Bracing designs will be controlled by compression in
the masonry due flexure plus axial load (once base fixity has been
established).
*1
Structural Masonry Design System, CMS10V5, National Concrete Masonry Association, 2010
*2
Ram Elements V8i, v13.0.2, Bentley Systems, Incorporated, 2012
Remember:
The Standard allows the use of full steel capacity after grout has cured
24 hours with the specified standard lap lengths.
Unfortunately,
Failed Solution
what you’ll see is
that there are a
couple data points outside the interaction
diagram’s capacity curve – this is not a
good solution. Now it’s time to evaluate
options while trying to find an
acceptable Internal Bracing solution.
Possible options include larger bars,
closer bar spacing and increased
masonry strength.
Don’t give up – we have options! See
the next page….
Analysis Now it’s time to check our design. You can click ‘Optimize’ and let the
software determine the best bar spacing or size to fit your input data or
click ‘Check’ to get a pass-fail analysis on the specific size and spacing that were input. Let’s
click ‘Optimize’ for this project and see what happens. We first note the ‘green light’ in the
lower right corner indicating that an appropriate solution was found. We can view the specifics
of that solution in ‘Detailing’at the top menu bar or click ‘Report.’ I prefer to see a full report
including stress ratios and other data, so
let’s click ‘Report.’ The key data is on
the second page of the report and shows
that the wall can be made to work in a
cantilevered condition, but would
require #5’s at 8” on center. While that
could be an alternative design to
consider, it requires bars much closer
than the specified 32” on center and
would need to be submitted for a
change. Based on cost and practicality Figure 16: Analysis Report – Good bar size, excessive bar spacing
Reprinted from Ram Elements V8i with permission of Bentley Systems Incorporated
it’s probably not the best solution!