0% found this document useful (0 votes)
54 views7 pages

S-1 Structural Plan Control Building & Connertor Switch - ACPL Comments

S-1 Structural plan Control building & connertor switch_ACPL Comments (1

Uploaded by

markjls02
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views7 pages

S-1 Structural Plan Control Building & Connertor Switch - ACPL Comments

S-1 Structural plan Control building & connertor switch_ACPL Comments (1

Uploaded by

markjls02
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Comment Summary: Comment Summary:

1. Page 1. 1A/S-1, S-1: Revise Typical door opening elevation from 2-10mm dia to 1-16mm dia 31.Page 6. Mechanical Couplers are only required in the event
with 90 degrees bend above the floor line. that concrete and reinforcement ratio is below and above the
limit of 1% to 8% ratio due to congestion of the main column
2. Page 1. 1B/S-1, S-1: Revise typical window opening elevation, vertical 1-16mm each face with reinforcement. Lap splicing is OK if the column ratio is within the
an over lapped of (825mm). Horizontal: 1-16mm each face x 1500mm with an overlapp of said limits. dia 16 x 1500mm long diagonals at
1050mm (which ever is higher) mid depth of wall at each corner.
32. Page 6. Provide column schedule for both switch gear and dia 12 x 1000mm
3. S-1/3 Typical Masonry unit detail: Provide additional detail of masonry on the condition of 1. at control building. Long diagonals at
corner and 2. at intersection. mid - depth of wall
33.Page 6. Structural Stair detail: Reinforcement should not be at each corner. 825mm.
4.Page 1. S-1/8 Typical edge of slab on grade: Provide detail on 1. slab on grade expansion from like this. Refer to the sample attached.
floor to wall. Ensure column stair should be on the center of the footing. If
reinforcement column is suspended at 100mm. Ensure to place 1-dia 16 Each face
5.Page 1. S-1/4 Detail of beam openings: If we are indicating that pipe sleeve shall not be greater a chair bar for the reinforcement starter bar of the stair column. of opening 1-dia 16 Each face
than 150mm dia. (outside diamater). Ensure and double check if beams/girders are more than and IF not, it is also OK that the stair column reinforcement is (typical). (Typical).
700mm. (d/5, where as: 700/5 = 140mm say 150mm max). However if there are beams/girders above the stair footing reinforcement.
that are more than 700mm we can remove the d<=150mm. and retain d<= d/5.
34.Page 6. Please re organize structural detail double check if
6.Page 1. S-1/4 Detail of beam openings: Provide detail of pipe sleeve distance between each its is necessary to have an two way slab detail since all detail of
other on a single beam/girder. (minimum distance of 4d. Where "d" = pipe sleeve diameter which slab are only one way.
ever is higher). Additionally, introduction of pipe sleeve shall be a distance of L/4 from the face of
support where L = span of the beam or girder. 35Page 7. Provide correct and proper construction notes on 1050mm.
Driven piles. (pile drive).
7.Page 1. S-1/4 Detail of beam openings: Add notes:
1. Seek structural engineer approval for the pipe sleeve diamater bigger than the maximum
stipulated.
2. Pipe sleeve shall be located within he tension zones of the beam/girder. S1
3. No pipe shall be allowed at twice the beam depth (2D) from the support. Where D = Depth of S1 7
beam/girder.
1 Provide detail on:
8.Page 1. S-1/9 Provide slab opening detail: either both on one way or two way. Especially the 1. slab on grade

D=FOR BEAM OR
location of trimmer bars. Add note: Omit trimmer bars where opening is framed by beams. Provide masonry details at:
expansion from
30 BAR DIA. 30 BAR DIA. 1. At Corner
floor to wall.
9.Page 1. S-1/6 Typical conc. Beam construction joint. Add note: Main reinforcement to be 2. At Intersection
continuous (top and bottom bars).

(VERIFY)
10.Page 1. Provide constructin notes on foundation. Refer to teragrail report.
E.g. Foundation design based on allowable soil bearing capacity.
Max allowable or minimum allowable settlement (mm). 30 BAR DIA.

Pile cap width design


Allowable bearing capacity in KPA.
S1 S1 S1
11.Page 1. Provide notes on: Foundation shall rest on natural soil, unless otherwise noted by the
structural engineer. No part of the foundation shall rest on fill. 2 3 8
Provide slab
12.Page 1. Provide detail of pipe sleeve thru wall. opening detail:
either both on
13.Page 1. Provide detail of typical stifferner column and lintel beam on CHB walls. one way or two
way. especially
14.Page 1. Provide wall reinforcing at RC column wall rebar connection. the location of
d/2. trimmer bars.
15.Page 2. Pile legend: Provide f'c and fy for driven pile requirements.
Note:
16. Page 2. Please improve FTB-1 beam schedule as there are: omit trimmer bars
Cont A. - Mid span - Cont B. where opening is
Discont - Mid span - Cont A. framed by
Discont - Midspan - Cont B. beams.
Cont B - Midspan - Cont A.
ensure schedule of beams depth shall Provide detail of pipe sleeve distance add notes:
Revise.
17.Page 2. Pile cap detail: Please confirm if this is lean concrete. not be more than 700mm if we are S1
between each other on a single beam/ 1. Seek structural engineer approval S1
indicating d < = 150mm. if beam depth girder. (minimum distance 4d where d for pipe sleeve with diameter bigger
is more than 700mm remove: d < =
4
= pipe sleeve diameter which ever is than the maximum stipulated. 9
18.Page 2. Pile cap detail: add notes: Double check at actual if top bar of dia 16mm @ 120mm
150mm. higher). additionally. introduction of 2. Pipe sleeve shall be located within Main reinforcement to
will not sag (pile cap). If sag occur provide detail of Z bar or Chair bar to support the top
pipe sleeve shall have a distance of tension zones of the beam. be continuous (top and Provide construction notes on:
reinforcement of pile cap.
L/4 from the face of support where L = 3. No pipe sleeve shall be allowed at bottom bars). Foundation. refer to teragrail report
span of the beam/girder. twice the beam depth (2D) from the
19.Page 2. Pile cap detail add note: Ensure that the pile hacked driven piles is free from any
support. where D = depth of beam/ e.g. Foundation design based on the
debris upon installation of pile cap.
girder. allowable soil bearing capacity.
20.Page 2. Column schedule: Ties should be alternating see drawings.
Max allowable or minimum allowable
settlement (mm).
21.Page 2. Slab schedule: Inquiry: what is the difference between RS-1 and RS-2 slab schedule
detail?
D/2. Pile cap width.
22.Page 2. Beam schedule: Please improve beam scheduling base on proposed plans see
allowable bearing capacity in Kpa.
attached PDF.

23.Page 2. Beam schedule: Once beam schedule is finalize provide an cutting list for beam/girder add notes on:
if reinforcement span is more than 12 meters to become Cont A. and Cont B. Foundation.
For slab provide a cutting list sample for one way for both ground floor and roof deck. 1. Foundation shall rest on natural soil,
unless other wise noted by the
24.Page 2. Assumption of footing tie beam shall be flat and align with the reinforcement schedule. Structural engineer. no part of the
Reinforcement of footing tie beam will pass thru the pile cap connected to the main column and foundation shall rest on fill.
not in the face of the pile cap (see attached PDF).

25.Page 2. In the event that footing tie beam was not layed flat due to site condition. Contractor Provide detail of Pipe sleeve thru wall.
shall provide an STQ for the change soffit (change elevation of the footing tie beam).

26.Page 2. Roof deck framing plan: Please improve drawings of ground floor framing plan and Provide detail of typical stifferner
roof deck framing plan to enlarge. To further see its detail schedule so that once printed it can column and lintel beam on CHB walls.
easily reflect on hard copies.

27.Page 2. Provide notes that in a event that we are required to construction joint. The contractor
S1 S1 Provide wall reinforcing at RC column/
shall notify the structural engineer for its proposal and approval. 5 6 RC wall rebar connection.

28.Page 4. Provide cross section detail of pile cap adjacent


CONTRACTOR: to each other to identify further
ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
distance between pile cap.
AS SHOWN
29.Page 5. Inquiry: Double check if this are black outs on beam/girder and to need further
collaboration. Note: that black out on slabs have no restrictions. PROPOSED CONTROL BUILDING CITICORE 1
30.Page 5. Double check if roof deck framing plans also have black outs.
ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7
18000
6000

CP-1 CP-1 CP-1 CP-1

FTB-1 FTB-1 FTB-1


C-1 C-1 C-1 C-1

PC-1 PC-1 PC-1 PC-1

FTB-1 FTB-1 FTB-1 FTB-1

CP-1 CP-1 CP-1 CP-1 Ø16@250 C/C (T)


Ø16@250 C/C (B)
FTB-1 FTB-1 FTB-1 4
C-1 C-1 C-1 C-1 2400

PC-1 PC-1 PC-1 PC-1

FTB-1 FTB-1 FTB-1 FTB-1

2400
3-Ø10
CP-1 CP-1 CP-1 CP-1
3 3
C-1
FTB-1
C-1
FTB-1
C-1
FTB-1
C-1
SCHEDULE OF FOOTING
Ø16@250 C/C (T)
Ø20@250 C/C (B)
PC-1 PC-1 PC-1 PC-1

150THK PCC
30000

FTB-1 FTB-1 FTB-1 FTB-1


4
CP-1 CP-1 CP-1 CP-1
PC-1 2.40 M 2.40 M 0.450 M verify actual 3-10mmØ EF PILE CAP
ALONG L Ø16@250 C/C
Ø16@250 C/C
(T)
(B) PILE CAP PC1 - PLAN
24 SETS
C-1 FTB-1 C-1 FTB-1 C-1 FTB-1 C-1 ALONG W Ø16@250 C/C (T) (SCALE 1:50)
Ø16@250 C/C (B)

PC-1 PC-1 PC-1 PC-1

0.20 0.40 3-16mmØ 3-16mmØ 10mm Ø @ 0.30 O.C.

REF COL DET


LINKS
FTB-1 FTB-1 FTB-1 FTB-1
12-T20 Ø16@250 C/C (T)
Ø16@250 C/C (B)
T10 @ 100 C/C
CP-1 CP-1 CP-1 T10 @ 300 C/C

300
EL. -0.80m

450

250
C-1 FTB-1 C-1 FTB-1 FTB-1 C-1
BOP

168
PC-1 PC-1 PC-1
3-Ø10 150

60
6000

FTB-1 FTB-1 FTB-1 FTB-1 150THK PCC 400x400 PILE


Ø16@120 C/C (T)
Ø20@150 C/C (B)
CP-1 CP-1 CP-1 CP-1
Please confirm if this is lean concrete
C-1
FTB-1
C-1
FTB-1
C-1
FTB-1
C-1
150mm. SECTION 3-3
DETAIL OF PC1
PC-1 PC-1 PC-1 PC-1 (SCALE 1:50)

P I L E C A P D E T A I L S
FOUNDATION PLAN 1:100MTS SCALE 1:50 MTRS
SCALE

Double check at actual if top bar of dia


Column schedule 16mm @ 120mm will not sag (pile
Please improve FTB-1 beam schedule
Ties should be alternating. cap). if sag occur provide detail of z
PILE LEGEND as there are:
bar or chair bar to support top
Cont A. - Mid span - Cont B
PILE SIZE PILE MARK reinforcement of pile cap.
Discont - Mid span - Cont A
400 x 400 CP-1
Discont - Mid span - Cont B 500
Cont B - Mid span - Cont A Add notes.
Provide f'c and fy for driven pile
requirements. Ensure that the pile hacked driven

500
piles is free from any debris upon
BEAM SCHEDULE installation of pile cap.

COLUMN SCHEDULE
SCALE 1:20MTS

CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN

PROPOSED CONTROL BUILDING CITICORE 2


ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7
18000

6000 6000 6000


6000 6000 6000

GB-1 GB-1 GB-1

RGB-1 RGB-1 RGB-1


2000

S-1 S-1 S-1

2000
B-1 B-1 B-1 RS-1 RS-2 RS-1

RB-1 RB-1 RB-1


6000

2000

GB-4

GB-5

GB-5
S-2 S-1 S-1

6000
GB-4

RB-1

RB-1

RB-1

RB-1
2000
B-1 B-1 B-1 RS-2 RS-2 RS-2

RB-1 RB-1 RB-1


2000

S-2 S-1
S-1

2000
RS-1 RS-2
GB-2 GB-2 GB-2 RS-1

SLAB SCHEDULE RGB-1 RGB-1 RGB-1


2000

S-1
S-2 S-1 S-1

2000
RS-1 RS-2 RS-1
B-2 B-2 B-2

RB-1 RB-1 RB-1


6000

GB-4

GB-5

GB-5
2000

S-2 S-1 S-1

GB-4

6000

RB-1

RB-1

RB-1

RB-1
2000
RS-2 RS-2 RS-2
B-2 B-2 B-2

RB-1 RB-1 RB-1


2000

S-2 S-1 S-1

2000
GB-3 GB-3 GB-3 RS-1 RS-2 RS-1

RGB-1 RGB-1 RGB-1


1733

S-1 S-1
S-2

1733
B-2 B-2 B-2 RS-1 RS-2 RS-1
5200

GB-4

GB-5

GB-5
30000

1733

GB-4

RB-1

RB-1

RB-1

RB-1
S-
S-1 S-1
Inquiry: What is the difference between
S-1

5200
30000

1733
RS-2 RS-2
RS - 1 and RS - 2 slab schedule
B-2 B-2 B-2 RS-2

detail?
RB-1 RB-1 RB-1
1733

S-1 S-1 S-1

1733
GB-3 GB-3 GB-3 RS-1 RS-2 RS-1

RGB-1 RGB-1 RGB-1


BEAM SCHEDULE
2268

S-1 S-1 S-1


GB-5

2266
RS-1 RS-2 RS-1
B-4 B-2 B-2
GB-4
GB-5

RB-1 RB-1 RB-1


GB-4
6800

2266

S-2 S-2

6800
S-2
RS-2 RS-2 RS-2

2266

RB-1

RB-1

RB-1

RB-1
B-4 B-2 B-2

RB-1 RB-1 RB-1


2266

S-2
S-1 S-1
RS-1 RS-2 RS-1

2266
GB-2 GB-2 GB-2

RGB-1 RGB-1 RGB-1


2600

S-2 S-1 RS-1

2000
S-2 RS-2 RS-1

B-2 B-2 RB-1 RB-1 RB-1


6000

GB-4

GB-5

B-3
S-2
GB-5

GB-4
1700

S-2

6000

RB-1

RB-1

RB-1

RB-1
2000
S-1 RS-2 RS-2 RS-2
B-3 B-2 B-2
RB-1 RB-1 RB-1
S-1 S-1
1700

RS-1

2000
RS-2
Please improve Beam scheduling.
S-2 RS-1

GB-1 GB-1 GB-1 base on the proposed plans. RGB-1 RGB-1 RGB-1

e.g.
GB-1 have:
Discont - Mid span - Cont A
Cont A - Mid span - Cont B
Cont B - Mid span - Discont. ROOF DECK FRAMING PLAN
SCALE 1:100MTS

Double check if its necessary to


GROUND FLOOR FRAMING PLAN provide 2 Discont. A and B. so that we
SCALE 1:100MTS Please improve drawings of Ground
can align what is left and right for Cont
floor framing plan and roof deck
A and Cont B.
framing plan to enlarge to further see
its detail schedule so that once printed
Once beam schedule is finalize.
Column it can easily reflect on hard copies.
provide an cutting list for Beam/girder
rebar.
if reinforcement span is more than 12
meter to become Cont A. or Cont B.
Pile cap.
For slab provide a cutting list sample
for one way for both Ground floor and
roof deck.

Assumption of Footing tie beam shall


be flat and align with the reinforcement Tie beam.
schedule. reinforcement of footing tie rebar.
Provide a notes that in a event that we
beam will pass thru the pile cap are required to construction joint. the
connected to the main column and not contractor shall notify the Structural
in the face of the pile cap. engineer for its proposal and approval.

In the event that footing tie beam was


CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
not layed flat due to site condition.
contractor shall provide an STQ for the AS SHOWN
change soffit (change elevation) of the

PROPOSED CONTROL BUILDING


footing tie beam.
CITICORE 3
ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7
24000
6000 6000 6000 6000 Same comments on Control building
when it comes to beam scheduling of
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1
footing tie beam.

C-1 FTB-1 C-1 FTB-1 C-1 C-1 C-1


FTB-1 FTB-1
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1

PC-1 PC-1 PC-1 PC-1 PC-1 BEAM SCHEDULE


6000

FTB-1

FTB-2

FTB-2

FTB-2

FTB-1
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1

FTB-2 C-1 FTB-2 C-1 FTB-2 C-1 C-1 C-1


FTB-2 FTB-2
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1

PC-1
PC-1 PC-1 PC-1 PC-1 PC-1
6000

FTB-1

FTB-2

FTB-2

FTB-2

FTB-1
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1

C-1 FTB-1 C-1 FTB-1 C-1 FTB-1 C-1 FTB-1 C-1


P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1

PC-1 PC-1 PC-1 PC-1 PC-1

FOUNDATION PLAN 1:100MTS


SCALE

Ø16@250 C/C (T)


PILE LEGEND Ø16@250 C/C (B)
4
2400
PILE SIZE PILE MARK

400 x 400 P-1 Provide cross section detail of pile cap


adjacent to identify further distance of
pile cap.
Refer comments on reinforcement
sagging on control building to check

2400
3-Ø10
and verify if reinforcement will be 3 3
subjected to sag. provide supports.
Ø16@250 C/C (T)
Ø20@250 C/C (B)
SCHEDULE OF FOOTING
150THK PCC

PILE CAP PC1 - PLAN


(SCALE 1:50)

PC-1 2.40 M 2.40 M 0.450 M verify actual 3-10mmØ EF PILE CAP


ALONG L Ø16@250 C/C
Ø16@250 C/C
(T)
(B) 24 SETS
ALONG W Ø16@250 C/C
Ø16@250 C/C
(T)
(B)

REF COL DET


LINKS
12-T20 Ø16@250 C/C (T)
FTB-1 0.20 0.40 3-16mmØ 3-16mmØ 10mm Ø @ 0.30 O.C. Ø16@250 C/C (B)
T10 @ 100 C/C
T10 @ 300 C/C

300
Inquiry: the difference between FTB
EL. -0.80m

450

250
here and the other FTB 1 BOP

168
3-Ø10 150

60
150THK PCC 400x400 PILE
500
Ø16@120 C/C (T)
Ø20@150 C/C (B)
500

SECTION 3-3
DETAIL OF PC1
(SCALE 1:50)

P I L E C A P D E T A I L S
COLUMN SCHEDULE Refer on the comments of ties above
SCALE 1:50 MTRS

SCALE 1:20MTS on control building.

CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN

COLECTOR SWITCH BUILDING CITICORE 4


ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7
Inquiry: double check if this are black
outs. as black outs on the beam/girder
need further collaboration.
black out on slabs have no restrictions.
double check if roof deck framing has also black outs.

A B C D E A B C D E
24000 24000
6000 6000 6000 6000 6000 6000 6000 6000
CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY

3 GB-4 GB-4 GB-4 GB-4

3 RGB-4 RGB-4 RGB-4 RGB-4

S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 RS-1 RS-1 S-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1

CONC. CANOPY

CONC. CANOPY

CONC. CANOPY

CONC. CANOPY
6000

6000
GB-1

B-1

B-1

GB-2

B-2

B-2

GB-3

B-2

B-2

GB-2

B-1

B-1

GB-1

RGB-1

RB-1

B-1

RGB-2

RB-2

RB-2

RGB-3

RB-2

RB-2

RGB-2

RB-1

RB-1

GB-1
12000

12000
ELEV. =+2.075m ELEV. =+2.075m

2 GB-5 GB-5 GB-5 GB-5


2 RGB-5 RGB-5 RGB-5 RGB-5

S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1

CONC. CANOPY

CONC. CANOPY
6000

6000
GB-1

B-1

B-1

GB-2

B-2

B-2

GB-3

B-2

B-2

GB-2

B-1

B-1

GB-1

RGB-1

B-1

RB-1

RGB-2

RB-2

RB-2

RGB-3

RB-2

RB-2

RGB-2

RB-1

RB-1

GB-1
CONC. CANOPY

CONC. CANOPY
1 GB-4 GB-4 GB-4 GB-4 1 RGB-4 RGB-4 RGB-4 RGB-4
CONC. CANOPY CONC. CANOPY

CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY

GROUND FLOOR FRAMING PLAN


SCALE 1:100MTS
ROOF DECK FLOOR FRAMING PLAN
SCALE 1:100MTS

BEAM SCHEDULE

SLAB SCHEDULE

CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN

COLLECTOR SWITCH BUILDING CITICORE 5


ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7
Mechanical couplers are only required
in the event that concrete and Provide column schedule for both
reinforcement ratio is below and above switch gear and control buildings.
the limit of 1% to 8% (NSCP) due to
the congestion of the main column
reinforcement.
VERTICAL COLUMN BARS
lap splicing is Ok if the column ratio is (SEE SCHEDULE) 10MM Ø LATERAL TIES
10MMØ BAR @ 0.50m BW SPACED @ 1@50, 10@100,
within the said limits. 5@150, REST @ 200MM O.C.
TIE BEAM b

(SEE SCHEDULE) SLAB LEVEL TOP BARS


WEB BARS

h
BOTTOM BARS
SECTION A - A
(SECTION OF TIE BEAM)

FOOTING BARS
(X- DIRECTION)

t1 (mm)

t2 (mm)
75

75
100mm THK GRAVEL BASE 100mm THK GRAVEL BASE
FOOTING BARS
(Y-DIRECTION) L1 L2

SECTION
TYPICAL TIE BEAM TO FOOTING DETAILS

LENGHT OF SLAB

L 1/4 L 1/4
TOP BAR @ S L

TOP BAR @ SUPPORT (Ss)


TOP BARS @ MIDSPAN (Ss)

S1/S2=140mm THICK

BOTTOM BARS @ MIDSPAN (Ss)


B B
BOTTOM BARS (CONTINEOUS)

BOTTOM BAR @ S L

TYPICAL SLAB DETAILS

TYPICAL MOMENT FRAME CONCRETE


COLUMN SPLICE DETAILS

T Y P I C A L S L A B D E T A I L S
SCALE 1:50 MTRS

CANTILEVER SPAN 2.50 M


TOP BAR @ S L

TOP BAR @ SUPPORT (Ss)

reinforcement should not


be like this.
refer to sample below. B B
CHB WALL
6 PCS. -Ø16 MAIN BARS
STIRRUPS Ø10; 1@50;16@100;BAL@150

16 mm Ø @ 0.15 M
O.C.E.T.B.
TYPICAL CANTILEVER SLAB DETAILS
15CM

L/4
25CM
+/-20CM (VERIFY)

200X350MM

TYPICAL ONE-WAY SLAB REINFORCEMENT DETAIL


STAIR BEAM 10mmØ @ 0.25M
O.C. EACH FACE

CHB WALL
15CM
NOT TO SCALE

TYPICAL STAIR LANDING DETAILS


TOP BARS @
TOP BARS @ TOP BARS @
MIDSPAN 150 300
SOPPORT SOPPORT

Ties shall 40 D BOTTOM BARS


LAPPED SPLICE THK. 100 mm CHB WALL
150

be below of Ø 9 mm HOR. BARS SPACED


the beam. 10 mm Ø NOSING BARS AT 600 mm O.C.
10mmØ @ 0.25M
25CM
16 mm Ø @ 0.15 M Ø 10 mm VERT. BARS SPACED
+/-20CM (VERIFY)

L/4
O.C.E.T.B.
O.C. EACH FACE EVERY 3 LAYER OF CHB
TRAVERSE BARS
SFR (SIDE FACE NGL

1621
10mmØ @ 0.25M REINFORCEMENT)
O.C. EACH FACE EF (EACH FACE)
LONGITUDINAL BARS

400
0.025 CLEAR

550 mm
30 D BOTTOM BARS

1621
16 mm DIA. @ 0.20 M HOR./VERT. BARS BOTTOM BARS @ LAPPED SPLICE Ø10 mm LONGITUDINAL
BOTTOM BARS @
EACH FACE
15CM
SUPPORT MIDSPAN
BOTTOM BARS
BASE BARS W/ Ø10mm BARS

150
800MM

@ TIES SPACED AT 300mm O.C.

1621
16 mm DIA. @ 0.20 M SUPPORT
BOTHWAYS
200MM

300 mm

STAIR FOOTING (STF-1) WITH 10mm DIA. TIES / STIRRUPS ( SEE SCHEDULE OF BEAMS FOR
SPACING )
ensure column stair should be on 800X800MM
SECTION PLAN
center of the footing. Please re organize structural detail.
TYPICAL BEAM DETAILS double check if it is necessary to have
if reinforcement column is suspended TYP. WALL FOOTING DETAILS
at 100mm. ensure to place a chair bar STRUCTURAL STAIR DETAILS an two way slab detail since all detail
for the reinforcement starter bar of of slab are only one way.
stair column. if not it is also ok that
stair column reinforcement is above
the stair footing reinforcement.
CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN

PROPOSED CONTROL BUILDING CITICORE 6


ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7
This is bored pile.

Provide
construction notes
(verify actual) on driven piles.

TYPICAL DETAILED SECTION OF PILES


SCALE nts MTRS

yup this is bored


piles.

x 96 (verify actual)

CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN

PROPOSED CONTROL BUILDING CITICORE 7


ENGINEER
S
PRC REG. NO.:

PTR NO.:
TIN NO.:

D/L: LOCATION: BATANGAS


7

You might also like