S-1 Structural Plan Control Building & Connertor Switch - ACPL Comments
S-1 Structural Plan Control Building & Connertor Switch - ACPL Comments
1. Page 1. 1A/S-1, S-1: Revise Typical door opening elevation from 2-10mm dia to 1-16mm dia 31.Page 6. Mechanical Couplers are only required in the event
with 90 degrees bend above the floor line. that concrete and reinforcement ratio is below and above the
limit of 1% to 8% ratio due to congestion of the main column
2. Page 1. 1B/S-1, S-1: Revise typical window opening elevation, vertical 1-16mm each face with reinforcement. Lap splicing is OK if the column ratio is within the
an over lapped of (825mm). Horizontal: 1-16mm each face x 1500mm with an overlapp of said limits. dia 16 x 1500mm long diagonals at
1050mm (which ever is higher) mid depth of wall at each corner.
32. Page 6. Provide column schedule for both switch gear and dia 12 x 1000mm
3. S-1/3 Typical Masonry unit detail: Provide additional detail of masonry on the condition of 1. at control building. Long diagonals at
corner and 2. at intersection. mid - depth of wall
33.Page 6. Structural Stair detail: Reinforcement should not be at each corner. 825mm.
4.Page 1. S-1/8 Typical edge of slab on grade: Provide detail on 1. slab on grade expansion from like this. Refer to the sample attached.
floor to wall. Ensure column stair should be on the center of the footing. If
reinforcement column is suspended at 100mm. Ensure to place 1-dia 16 Each face
5.Page 1. S-1/4 Detail of beam openings: If we are indicating that pipe sleeve shall not be greater a chair bar for the reinforcement starter bar of the stair column. of opening 1-dia 16 Each face
than 150mm dia. (outside diamater). Ensure and double check if beams/girders are more than and IF not, it is also OK that the stair column reinforcement is (typical). (Typical).
700mm. (d/5, where as: 700/5 = 140mm say 150mm max). However if there are beams/girders above the stair footing reinforcement.
that are more than 700mm we can remove the d<=150mm. and retain d<= d/5.
34.Page 6. Please re organize structural detail double check if
6.Page 1. S-1/4 Detail of beam openings: Provide detail of pipe sleeve distance between each its is necessary to have an two way slab detail since all detail of
other on a single beam/girder. (minimum distance of 4d. Where "d" = pipe sleeve diameter which slab are only one way.
ever is higher). Additionally, introduction of pipe sleeve shall be a distance of L/4 from the face of
support where L = span of the beam or girder. 35Page 7. Provide correct and proper construction notes on 1050mm.
Driven piles. (pile drive).
7.Page 1. S-1/4 Detail of beam openings: Add notes:
1. Seek structural engineer approval for the pipe sleeve diamater bigger than the maximum
stipulated.
2. Pipe sleeve shall be located within he tension zones of the beam/girder. S1
3. No pipe shall be allowed at twice the beam depth (2D) from the support. Where D = Depth of S1 7
beam/girder.
1 Provide detail on:
8.Page 1. S-1/9 Provide slab opening detail: either both on one way or two way. Especially the 1. slab on grade
D=FOR BEAM OR
location of trimmer bars. Add note: Omit trimmer bars where opening is framed by beams. Provide masonry details at:
expansion from
30 BAR DIA. 30 BAR DIA. 1. At Corner
floor to wall.
9.Page 1. S-1/6 Typical conc. Beam construction joint. Add note: Main reinforcement to be 2. At Intersection
continuous (top and bottom bars).
(VERIFY)
10.Page 1. Provide constructin notes on foundation. Refer to teragrail report.
E.g. Foundation design based on allowable soil bearing capacity.
Max allowable or minimum allowable settlement (mm). 30 BAR DIA.
23.Page 2. Beam schedule: Once beam schedule is finalize provide an cutting list for beam/girder add notes on:
if reinforcement span is more than 12 meters to become Cont A. and Cont B. Foundation.
For slab provide a cutting list sample for one way for both ground floor and roof deck. 1. Foundation shall rest on natural soil,
unless other wise noted by the
24.Page 2. Assumption of footing tie beam shall be flat and align with the reinforcement schedule. Structural engineer. no part of the
Reinforcement of footing tie beam will pass thru the pile cap connected to the main column and foundation shall rest on fill.
not in the face of the pile cap (see attached PDF).
25.Page 2. In the event that footing tie beam was not layed flat due to site condition. Contractor Provide detail of Pipe sleeve thru wall.
shall provide an STQ for the change soffit (change elevation of the footing tie beam).
26.Page 2. Roof deck framing plan: Please improve drawings of ground floor framing plan and Provide detail of typical stifferner
roof deck framing plan to enlarge. To further see its detail schedule so that once printed it can column and lintel beam on CHB walls.
easily reflect on hard copies.
27.Page 2. Provide notes that in a event that we are required to construction joint. The contractor
S1 S1 Provide wall reinforcing at RC column/
shall notify the structural engineer for its proposal and approval. 5 6 RC wall rebar connection.
PTR NO.:
TIN NO.:
2400
3-Ø10
CP-1 CP-1 CP-1 CP-1
3 3
C-1
FTB-1
C-1
FTB-1
C-1
FTB-1
C-1
SCHEDULE OF FOOTING
Ø16@250 C/C (T)
Ø20@250 C/C (B)
PC-1 PC-1 PC-1 PC-1
150THK PCC
30000
300
EL. -0.80m
450
250
C-1 FTB-1 C-1 FTB-1 FTB-1 C-1
BOP
168
PC-1 PC-1 PC-1
3-Ø10 150
60
6000
P I L E C A P D E T A I L S
FOUNDATION PLAN 1:100MTS SCALE 1:50 MTRS
SCALE
500
piles is free from any debris upon
BEAM SCHEDULE installation of pile cap.
COLUMN SCHEDULE
SCALE 1:20MTS
CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN
PTR NO.:
TIN NO.:
2000
B-1 B-1 B-1 RS-1 RS-2 RS-1
2000
GB-4
GB-5
GB-5
S-2 S-1 S-1
6000
GB-4
RB-1
RB-1
RB-1
RB-1
2000
B-1 B-1 B-1 RS-2 RS-2 RS-2
S-2 S-1
S-1
2000
RS-1 RS-2
GB-2 GB-2 GB-2 RS-1
S-1
S-2 S-1 S-1
2000
RS-1 RS-2 RS-1
B-2 B-2 B-2
GB-4
GB-5
GB-5
2000
GB-4
6000
RB-1
RB-1
RB-1
RB-1
2000
RS-2 RS-2 RS-2
B-2 B-2 B-2
2000
GB-3 GB-3 GB-3 RS-1 RS-2 RS-1
S-1 S-1
S-2
1733
B-2 B-2 B-2 RS-1 RS-2 RS-1
5200
GB-4
GB-5
GB-5
30000
1733
GB-4
RB-1
RB-1
RB-1
RB-1
S-
S-1 S-1
Inquiry: What is the difference between
S-1
5200
30000
1733
RS-2 RS-2
RS - 1 and RS - 2 slab schedule
B-2 B-2 B-2 RS-2
detail?
RB-1 RB-1 RB-1
1733
1733
GB-3 GB-3 GB-3 RS-1 RS-2 RS-1
2266
RS-1 RS-2 RS-1
B-4 B-2 B-2
GB-4
GB-5
2266
S-2 S-2
6800
S-2
RS-2 RS-2 RS-2
2266
RB-1
RB-1
RB-1
RB-1
B-4 B-2 B-2
S-2
S-1 S-1
RS-1 RS-2 RS-1
2266
GB-2 GB-2 GB-2
2000
S-2 RS-2 RS-1
GB-4
GB-5
B-3
S-2
GB-5
GB-4
1700
S-2
6000
RB-1
RB-1
RB-1
RB-1
2000
S-1 RS-2 RS-2 RS-2
B-3 B-2 B-2
RB-1 RB-1 RB-1
S-1 S-1
1700
RS-1
2000
RS-2
Please improve Beam scheduling.
S-2 RS-1
GB-1 GB-1 GB-1 base on the proposed plans. RGB-1 RGB-1 RGB-1
e.g.
GB-1 have:
Discont - Mid span - Cont A
Cont A - Mid span - Cont B
Cont B - Mid span - Discont. ROOF DECK FRAMING PLAN
SCALE 1:100MTS
PTR NO.:
TIN NO.:
FTB-1
FTB-2
FTB-2
FTB-2
FTB-1
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1
PC-1
PC-1 PC-1 PC-1 PC-1 PC-1
6000
FTB-1
FTB-2
FTB-2
FTB-2
FTB-1
P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1 P-1
2400
3-Ø10
and verify if reinforcement will be 3 3
subjected to sag. provide supports.
Ø16@250 C/C (T)
Ø20@250 C/C (B)
SCHEDULE OF FOOTING
150THK PCC
300
Inquiry: the difference between FTB
EL. -0.80m
450
250
here and the other FTB 1 BOP
168
3-Ø10 150
60
150THK PCC 400x400 PILE
500
Ø16@120 C/C (T)
Ø20@150 C/C (B)
500
SECTION 3-3
DETAIL OF PC1
(SCALE 1:50)
P I L E C A P D E T A I L S
COLUMN SCHEDULE Refer on the comments of ties above
SCALE 1:50 MTRS
CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN
PTR NO.:
TIN NO.:
A B C D E A B C D E
24000 24000
6000 6000 6000 6000 6000 6000 6000 6000
CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY
S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 RS-1 RS-1 S-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1
CONC. CANOPY
CONC. CANOPY
CONC. CANOPY
CONC. CANOPY
6000
6000
GB-1
B-1
B-1
GB-2
B-2
B-2
GB-3
B-2
B-2
GB-2
B-1
B-1
GB-1
RGB-1
RB-1
B-1
RGB-2
RB-2
RB-2
RGB-3
RB-2
RB-2
RGB-2
RB-1
RB-1
GB-1
12000
12000
ELEV. =+2.075m ELEV. =+2.075m
S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 S-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1 RS-1
CONC. CANOPY
CONC. CANOPY
6000
6000
GB-1
B-1
B-1
GB-2
B-2
B-2
GB-3
B-2
B-2
GB-2
B-1
B-1
GB-1
RGB-1
B-1
RB-1
RGB-2
RB-2
RB-2
RGB-3
RB-2
RB-2
RGB-2
RB-1
RB-1
GB-1
CONC. CANOPY
CONC. CANOPY
1 GB-4 GB-4 GB-4 GB-4 1 RGB-4 RGB-4 RGB-4 RGB-4
CONC. CANOPY CONC. CANOPY
CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY CONC. CANOPY
BEAM SCHEDULE
SLAB SCHEDULE
CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN
PTR NO.:
TIN NO.:
h
BOTTOM BARS
SECTION A - A
(SECTION OF TIE BEAM)
FOOTING BARS
(X- DIRECTION)
t1 (mm)
t2 (mm)
75
75
100mm THK GRAVEL BASE 100mm THK GRAVEL BASE
FOOTING BARS
(Y-DIRECTION) L1 L2
SECTION
TYPICAL TIE BEAM TO FOOTING DETAILS
LENGHT OF SLAB
L 1/4 L 1/4
TOP BAR @ S L
S1/S2=140mm THICK
BOTTOM BAR @ S L
T Y P I C A L S L A B D E T A I L S
SCALE 1:50 MTRS
16 mm Ø @ 0.15 M
O.C.E.T.B.
TYPICAL CANTILEVER SLAB DETAILS
15CM
L/4
25CM
+/-20CM (VERIFY)
200X350MM
CHB WALL
15CM
NOT TO SCALE
L/4
O.C.E.T.B.
O.C. EACH FACE EVERY 3 LAYER OF CHB
TRAVERSE BARS
SFR (SIDE FACE NGL
1621
10mmØ @ 0.25M REINFORCEMENT)
O.C. EACH FACE EF (EACH FACE)
LONGITUDINAL BARS
400
0.025 CLEAR
550 mm
30 D BOTTOM BARS
1621
16 mm DIA. @ 0.20 M HOR./VERT. BARS BOTTOM BARS @ LAPPED SPLICE Ø10 mm LONGITUDINAL
BOTTOM BARS @
EACH FACE
15CM
SUPPORT MIDSPAN
BOTTOM BARS
BASE BARS W/ Ø10mm BARS
150
800MM
1621
16 mm DIA. @ 0.20 M SUPPORT
BOTHWAYS
200MM
300 mm
STAIR FOOTING (STF-1) WITH 10mm DIA. TIES / STIRRUPS ( SEE SCHEDULE OF BEAMS FOR
SPACING )
ensure column stair should be on 800X800MM
SECTION PLAN
center of the footing. Please re organize structural detail.
TYPICAL BEAM DETAILS double check if it is necessary to have
if reinforcement column is suspended TYP. WALL FOOTING DETAILS
at 100mm. ensure to place a chair bar STRUCTURAL STAIR DETAILS an two way slab detail since all detail
for the reinforcement starter bar of of slab are only one way.
stair column. if not it is also ok that
stair column reinforcement is above
the stair footing reinforcement.
CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN
PTR NO.:
TIN NO.:
Provide
construction notes
(verify actual) on driven piles.
x 96 (verify actual)
CONTRACTOR: ENGINEER: PROJECT TITLE: PROJECT OWNER: SHEET CONTENTS: SHEET NO.
AS SHOWN
PTR NO.:
TIN NO.: