24m00057 Biddocs
24m00057 Biddocs
Procurement of
INFRASTRUCTURE
PROJECTS
Government of the Republic of the Philippines
Sixth Edition
July 2020
Preface
The PBDs are intended as a model for admeasurements (unit prices or unit rates in a
bill of quantities) types of contract, which are the most common in Works contracting.
The Bidding Documents shall clearly and adequately define, among others: (i) the
objectives, scope, and expected outputs and/or results of the proposed contract; (ii) the
eligibility requirements of Bidders; (iii) the expected contract duration; and (iv) the
obligations, duties, and/or functions of the winning Bidder.
Care should be taken to check the relevance of the provisions of the PBDs against the
requirements of the specific Works to be procured. If duplication of a subject is inevitable in
other sections of the document prepared by the Procuring Entity, care must be exercised to
avoid contradictions between clauses dealing with the same matter.
Moreover, each section is prepared with notes intended only as information for the
Procuring Entity or the person drafting the Bidding Documents. They shall not be included in
the final documents. The following general directions should be observed when using the
documents:
a. All the documents listed in the Table of Contents are normally required for the
procurement of Infrastructure Projects. However, they should be adapted as
necessary to the circumstances of the particular Project.
b. Specific details, such as the “name of the Procuring Entity” and “address for
bid submission,” should be furnished in the Instructions to Bidders, Bid Data
Sheet, and Special Conditions of Contract. The final documents should
contain neither blank spaces nor options.
c. This Preface and the footnotes or notes in italics included in the Invitation to
Bid, BDS, General Conditions of Contract, Special Conditions of Contract,
Specifications, Drawings, and Bill of Quantities are not part of the text of the
final document, although they contain instructions that the Procuring Entity
should strictly follow.
1
e. Modifications for specific Procurement Project details should be provided in
the Special Conditions of Contract as amendments to the Conditions of
Contract. For easy completion, whenever reference has to be made to specific
clauses in the Bid Data Sheet or Special Conditions of Contract, these terms
shall be printed in bold typeface on Sections I (Instructions to Bidders) and III
(General Conditions of Contract), respectively.
f. For guidelines on the use of Bidding Forms and the procurement of Foreign-
Assisted Projects, these will be covered by a separate issuance of the
Government Procurement Policy Board.
2
TABLE OF CONTENTS
3
7. Warranty..................................................................................................................22
8. Liability of the Contractor .......................................................................................22
9. Termination for Other Causes .................................................................................22
10. Dayworks ................................................................................................................23
11. Program of Work.....................................................................................................23
12. Instructions, Inspections and Audits .......................................................................23
13. Advance Payment....................................................................................................23
14. Progress Payments ..................................................................................................23
15. Operating and Maintenance Manuals......................................................................23
Section V. Special Conditions of Contract..................................................... 25
Section VI. Specifications ................................................................................ 28
Section VII. Drawings ...................................................................................... 29
Section VIII. Bill of Quantities ....................................................................... 30
Section IX. Checklist of Technical and Financial Documents ..................... 42
4
Glossary of
Terms, Abbreviations, and Acronyms
Bidding Documents – The documents issued by the Procuring Entity as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the Goods,
Infrastructure Projects, and/or Consulting Services required by the Procuring Entity. (2016
revised IRR, Section 5[e])
Consulting Services – Refer to services for Infrastructure Projects and other types of projects
or activities of the GOP requiring adequate external technical and professional expertise that
are beyond the capability and/or capacity of the GOP to undertake such as, but not limited to:
(i) advisory and review services; (ii) pre-investment or feasibility studies; (iii) design; (iv)
construction supervision; (v) management and related services; and (vi) other technical
services or special studies. (2016 revised IRR, Section 5[i])
Contract – Refers to the agreement entered into between the Procuring Entity and the
Supplier or Manufacturer or Distributor or Service Provider for procurement of Goods and
Services; Contractor for Procurement of Infrastructure Projects; or Consultant or Consulting
Firm for Procurement of Consulting Services; as the case may be, as recorded in the Contract
Form signed by the parties, including all attachments and appendices thereto and all
documents incorporated by reference therein.
Contractor – is a natural or juridical entity whose proposal was accepted by the Procuring
Entity and to whom the Contract to execute the Work was awarded. Contractor as used in
these Bidding Documents may likewise refer to a supplier, distributor, manufacturer, or
consultant.
5
DOLE – Department of Labor and Employment.
Goods – Refer to all items, supplies, materials and general support services, except Consulting
Services and Infrastructure Projects, which may be needed in the transaction of public businesses or in
the pursuit of any government undertaking, project or activity, whether in the nature of equipment,
furniture, stationery, materials for construction, or personal property of any kind, including non-
personal or contractual services such as the repair and maintenance of equipment and furniture, as
well as trucking, hauling, janitorial, security, and related or analogous services, as well as
procurement of materials and supplies provided by the Procuring Entity for such services. The term
“related” or “analogous services” shall include, but is not limited to, lease or purchase of office space,
media advertisements, health maintenance services, and other services essential to the operation of the
Procuring Entity. (2016 revised IRR, Section 5[r])
UN – United Nations.
6
Section I. Invitation to Bid
7
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS XII
REGIONAL OFFICE XII
Koronadal City
1. The Department of Public Works and Highways XII, through the Bids and Awards
Committee (BAC) intends to apply the sum One Hundred Forty Four Million Seven
Hundred Fifty Thousand Pesos Only (₱144,750,000.00) being the Approved Budget for the
Contract (ABC) to payments under the contract for 24M00057 - ROAD WIDENING -
COTABATO-LANAO RD, K1858+100 - K1858+558, K1858+263 - K1858+353, K1858+353 -
K1860+558, SULTAN KUDARAT, MAGUINDANAO DEL NORTE. The Contract duration
of 263 Calendar Days. Bids received in excess of the ABC shall be automatically rejected at bid
opening.
The Department of Public Works and Highways XII, through the Funding Source is the
Government of the Philippines (GOP)-(NEP) intends to apply the sum of the above-mentioned
Projects with corresponding Approved Budget for the Contract (ABC). Bids received in excess of
the ABC shall be automatically rejected at bid opening.
2. Bidders should have completed a contract similar to the Project. The description of an eligible
bidder is contained in the Bidding Documents, particularly, in Section II (Instructions to
Bidders).
3. Prospective Bidders should be (1) registered with and classified by the Philippine Contractors
Accreditation Board (PCAB) with PCAB LICENSE Category as indicated above. The
Contractors/applicants who wish to participate in this bidding are encouraged to enroll in the
DPWH Civil Works Application (CWA) at the DPWH Procurement Service (PrS), 5th 9 Floor,
DPWH Bldg., Bonifacio Drive, Port Area, Manila, while those already enrolled shall keep their
records current and updated. The Contractor’s eligibility to bid on the project will be determined
using the DPWH Contractor Profile Eligibility Process (CPEP) and subject to further post-
qualification. Information on registration can be obtained from the PrS during working weekdays
from 7:00 am to 4:00 pm or at the DPWH website www.dpwh.gov.ph.
4. Bidding will be conducted through open competitive bidding procedures using non-discretionary
“pass/fail” criterion as specified in the 2016 revised Implementing Rules and Regulations (IRR)
of Republic Act (RA) No. 9184.
5. Interested bidders may obtain further information from Department of Public Works and
Highways XII and inspect the Bidding Documents at the address given below from 8:00 A.M. to
5:00 P.M.
6. A complete set of Bidding Documents may be acquired by interested bidders on November 09,
2023 to NOVEMBER 29, 2023 from given address and website/s below and upon payment of
the applicable fee for the Bidding Documents, pursuant to the latest Guidelines issued by the
GPPB. The Procuring Entity shall allow the bidder to present its proof of payment for the fees
presented in person.
8
7. The Bidding Documents may also be downloaded free of charge from the website of the
Philippine Government Electronic Procurement System (PhilGEPS), and the website of the
Procuring Entity, provided that bidders shall pay the applicable fee for the Bidding Documents
not later than the submission of their bids.
8. The Department of Public Works and Highways XII will hold a Pre-Bid Conference1 on
November 16, 2023 at 9:00 A.M. at DPWH Regional Office XII Conference Room, Koronadal
City, South Cotabato and/or through videoconferencing/webcasting via Zoom, which shall be
open to prospective bidders.
9. Bids must be duly received by the BAC Secretariat through (i) manual submission at the office
address as indicated below, (ii) online or electronic submission as indicated below, or (iii) both
on or before NOVEMBER 29, 2023 at 10:00 A.M. Late bids shall not be accepted.
10. All bids must be accompanied by a bid security in any of the acceptable forms and in the amount
stated in ITB Clause 16.
11. Bid opening shall be on NOVEMBER 29, 2023 at 2:00 p.m. at the given address below and/or
through videoconferencing via Zoom. Bids will be opened in the presence of the bidders’
representatives who choose to attend the activity.
12. The Department of Public Works and Highways XII reserves the right to reject any and all bids,
declare a failure of bidding, or not award the contract at any time prior to contract award in
accordance with Sections 35.6 and 41 of the 2016 revised Implementing Rules and Regulations
(IRR) of RA No. 9184, without thereby incurring any liability to the affected bidder or bidders.
SHIRLINE G. AVILA
Head, Procurement Unit
Cor. Alunan Ave., Mabini St. Koronadal City, 9506
[email protected]
Tel. No.: (083)228-3908 / 0950-153-7276
facsimile number: (083)228-9577
www.dpwh.gov.ph
9
Section II. Instructions to Bidders
10
1. Scope of Bid
The Procuring Entity, Department of Public Works and Highways XII invites Bids for
the ROAD WIDENING - COTABATO-LANAO RD, K1858+100 - K1858+558,
K1858+263 - K1858+353, K1858+353 - K1860+558, SULTAN KUDARAT,
MAGUINDANAO DEL NORTE with Project Identification Number 24M00057.
2. Funding Information
2.1. The GOP-NEP through the source of funding as indicated below for CY 2024
in the amount of 150,000,000.00
3. Bidding Requirements
The Bidding for the Project shall be governed by all the provisions of RA No. 9184
and its 2016 revised IRR, including its Generic Procurement Manual and associated
policies, rules and regulations as the primary source thereof, while the herein clauses
shall serve as the secondary source thereof.
Any amendments made to the IRR and other GPPB issuances shall be applicable only
to the ongoing posting, advertisement, or invitation to bid by the BAC through the
issuance of a supplemental or bid bulletin.
The Bidder, by the act of submitting its Bid, shall be deemed to have inspected the
site, determined the general characteristics of the contracted Works and the conditions
for this Project, such as the location and the nature of the work; (b) climatic
conditions; (c) transportation facilities; (c) nature and condition of the terrain,
geological conditions at the site communication facilities, requirements, location and
availability of construction aggregates and other materials, labor, water, electric
power and access roads; and (d) other factors that may affect the cost, duration and
execution or implementation of the contract, project, or work and examine all
instructions, forms, terms, and project requirements in the Bidding Documents.
5. Eligible Bidders
5.1. Only Bids of Bidders found to be legally, technically, and financially capable
will be evaluated.
11
5.2. The Bidder must have an experience of having completed a Single Largest
Completed Contract (SLCC) that is similar to this Project, equivalent to at
least fifty percent (50%) of the ABC adjusted, if necessary, by the Bidder to
current prices using the PSA’s CPI, except under conditions provided for in
Section 23.4.2.4 of the 2016 revised IRR of RA No. 9184.
5.3. For Foreign-funded Procurement, the Procuring Entity and the foreign
government/foreign or international financing institution may agree on another
track record requirement, as specified in the Bidding Document prepared for
this purpose.
5.4. The Bidders shall comply with the eligibility criteria under Section 23.4.2 of
the 2016 IRR of RA No. 9184.
7. Subcontracts
7.1. The Bidder may subcontract portions of the Project to the extent allowed by
the Procuring Entity as stated herein, but in no case more than fifty percent
(50%) of the Project.
7.1. [If Procuring Entity has determined that subcontracting is allowed during the
bidding , state:] The Bidder must submit together with its Bid the
documentary requirements of the subcontractor(s) complying with the
eligibility criterial stated in ITB Clause 5 in accordance with Section 23.4 of
the 2016 revised IRR of RA No. 9184 pursuant to Section 23.1 thereof.
7.2. [If subcontracting is allowed during the contract implementation stage, state:]
The Supplier may identify its subcontractor during the contract
implementation stage. Subcontractors identified during the bidding may be
changed during the implementation of this Contract. Subcontractors must
submit the documentary requirements under Section 23.1 of the 2016 revised
12
IRR of RA No. 9184 and comply with the eligibility criteria specified in ITB
Clause 5 to the implementing or end-user unit.
7.3. Subcontracting of any portion of the Project does not relieve the Contractor of
any liability or obligation under the Contract. The Supplier will be responsible
for the acts, defaults, and negligence of any subcontractor, its agents, servants,
or workmen as fully as if these were the Contractor’s own acts, defaults, or
negligence, or those of its agents, servants, or workmen.
8. Pre-Bid Conference
The Procuring Entity will hold a pre-bid conference for this Project on the specified
date and time and either at its physical address {[insert if applicable] and/or through
videoconferencing/webcasting} as indicated in paragraph 6 of the IB.
10.2. If the eligibility requirements or statements, the bids, and all other documents
for submission to the BAC are in foreign language other than English, it must
be accompanied by a translation in English, which shall be authenticated by
the appropriate Philippine foreign service establishment, post, or the
equivalent office having jurisdiction over the foreign bidder’s affairs in the
Philippines. For Contracting Parties to the Apostille Convention, only the
translated documents shall be authenticated through an apostille pursuant to
GPPB Resolution No. 13-2019 dated 23 May 2019. The English translation
shall govern, for purposes of interpretation of the bid.
10.3. A valid PCAB License is required, and in case of joint ventures, a valid
special PCAB License, and registration for the type and cost of the contract for
this Project. Any additional type of Contractor license or permit shall be
indicated in the BDS.
13
10.5. A List of Contractor’s major equipment units, which are owned, leased, and/or
under purchase agreements, supported by proof of ownership, certification of
availability of equipment from the equipment lessor/vendor for the duration of
the project, as the case may be, must meet the minimum requirements for the
contract set in the BDS.
11.2. Any bid exceeding the ABC indicated in paragraph 1 of the IB shall not be
accepted.
a. Philippine Pesos.
14
b. [indicate currency if procurement involves a foreign-denominated bid as
allowed by the Procuring Entity, which shall be tradeable or acceptable
by the BSP.]
15.2. The Bid and bid security shall be valid until [indicate date]. Any bid not
accompanied by an acceptable bid security shall be rejected by the Procuring
Entity as non-responsive.
The Procuring Entity may request additional hard copies and/or electronic copies of
the Bid. However, failure of the Bidders to comply with the said request shall not be a
ground for disqualification.
If the Procuring Entity allows the submission of bids through online submission to the
given website or any other electronic means, the Bidder shall submit an electronic
copy of its Bid, which must be digitally signed. An electronic copy that cannot be
opened or is corrupted shall be considered non-responsive and, thus, automatically
disqualified.
In case the Bids cannot be opened as scheduled due to justifiable reasons, the
rescheduling requirements under Section 29 of the 2016 revised IRR of RA
No. 9184 shall prevail.
15
19. Detailed Evaluation and Comparison of Bids
19.1. The Procuring Entity’s BAC shall immediately conduct a detailed evaluation
of all Bids rated “passed” using non-discretionary pass/fail criteria. The BAC
shall consider the conditions in the evaluation of Bids under Section 32.2 of
2016 revised IRR of RA No. 9184.
19.2. If the Project allows partial bids, all Bids and combinations of Bids as
indicated in the BDS shall be received by the same deadline and opened and
evaluated simultaneously so as to determine the Bid or combination of Bids
offering the lowest calculated cost to the Procuring Entity. Bid Security as
required by ITB Clause 16 shall be submitted for each contract (lot)
separately.
19.3. In all cases, the NFCC computation pursuant to Section 23.4.2.6 of the 2016
revised IRR of RA No. 9184 must be sufficient for the total of the ABCs for
all the lots participated in by the prospective Bidder.
16
Section III. Bid Data Sheet
17
Bid Data Sheet
ITB Clause
5.2 For this purpose, contracts similar to the Project refer to contracts which have
the same major categories of work, which shall be: RCP
10.4 The key personnel must meet the required minimum years of experience set
below:
General Experience Relevant
Key Personnel
(Same Position) Experience
Project Manager
(with copy of TIN ID or TIN) 5 3
Project Engineer
(with copy of TIN ID or TIN) 5 5
Materials Engineer I
(must be a DPWH Accredited
Materials Engineer) 5 5
Const. Safety & Health
Officer (S. O. 3 – with
5 2
mandatory 40hrs basic
OSH Training course)
Foreman 5 3
Others [Specify]
As per DO No. 09 series 2012 “Technical Requirements for Civil Works Project for
Public Bidding”(attached)
10.5 The minimum major equipment requirements are the following:
Number of
No. Equipment Description Capacity
Equipment
1 Bulldozer, DX175 1.5 m3 / 1.95 yd3 1
2 Payloader, LX80-2C 1.5 m3 / 1.95 yd3 1
3 Motorized Road Grader, G710A 1.5 m3 / 1.95 yd3 1
4 Vibratory Roller, SD100DC 10 mt 1
5 Plate Compactor, 400 – 500 Gasoline Engine 1
6 Truck Mounted Crane, All Models 31-35 mt 1
7 Backhoe, Solar 220 LC-3 0.80 m3 / 1.04 yd3 1
8 Backhoe, with Hammer, Solar 220 LC-4 0.80 m3 / 1.04 yd3 1
9 Backhoe, Wheel Mounted, PW60N-1 0.28 m3 / 0.37 yd3 1
10 Concrete Screeder, Wacker Truss Screed 1
11 One Bagger Mixer 4-6 1
12 Transit Mixer, All Models 5 ft3/min 4
13 Dump Truck, All Models 12 yd3 2
14 Cargo/Service Truck, All Models 2-5 mt 1
15 Boom Truck, NXG1160D3ZAL1X 1
16 Cargo/Service Truck, All Models 9-10 mt 1
17 Water Truck/Pump, All Models 16000 L 1
18 Air Compressor, All Models 15-35 cfm 1
18
19 Jackhammer, 2
Chainsaw, HUSQVARNA 2100 CD with CR22, 7ft
20 1
Reach, 9” Std. Blade
15.1 The bid security shall be in the form of a Bid Securing Declaration or any of
the following forms and amounts:
a. The amount of not less than (2%) of ABC, if bid security is in cash,
cashier’s/manager’s check, bank draft/guarantee or irrevocable letter
of credit;
b. The amount of not less (5%) of ABC] if bid security is in Surety Bond.
19.2 Partial bids are allowed, as follows:
[Insert grouping of lots by specifying the items and the quantity for every
identified lot.]
20 [List licenses and permits relevant to the Project and the corresponding law
requiring it, e.g. Environmental Compliance Certificate, Certification that the
project site is not within a geohazard zone, etc.]
3.0 In addition to clause 3 of Bidding Requirements the bidders shall comply with
all the existing rules and regulation related to Infrastructure projects; such as,
but not limited to, DPWH Department Orders issuances, DOLE issuances, &
GPPB issuances.
21 Additional contract documents relevant to the Project that may be required by
existing laws and/or the Procuring Entity, such as construction schedule and S-
curve, manpower schedule, construction methods, equipment utilization
schedule, construction safety and health program approved by the DOLE, and
other acceptable tools of project scheduling.
19
Section IV. General Conditions of Contract
20
1. Scope of Contract
This Contract shall include all such items, although not specifically mentioned, that
can be reasonably inferred as being required for its completion as if such items were
expressly mentioned herein. All the provisions of RA No. 9184 and its 2016 revised
IRR, including the Generic Procurement Manual, and associated issuances, constitute
the primary source for the terms and conditions of the Contract, and thus, applicable
in contract implementation. Herein clauses shall serve as the secondary source for
the terms and conditions of the Contract.
This is without prejudice to Sections 74.1 and 74.2 of the 2016 revised IRR of RA
No. 9184 allowing the GPPB to amend the IRR, which shall be applied to all
procurement activities, the advertisement, posting, or invitation of which were issued
after the effectivity of the said amendment.
3. Possession of Site
4.1. The Procuring Entity shall give possession of all or parts of the Site to the
Contractor based on the schedule of delivery indicated in the SCC, which
corresponds to the execution of the Works. If the Contractor suffers delay or
incurs cost from failure on the part of the Procuring Entity to give possession
in accordance with the terms of this clause, the Procuring Entity’s
Representative shall give the Contractor a Contract Time Extension and certify
such sum as fair to cover the cost incurred, which sum shall be paid by
Procuring Entity.
4.2. If possession of a portion is not given by the above date, the Procuring Entity
will be deemed to have delayed the start of the relevant activities. The
resulting adjustments in contract time to address such delay may be addressed
through contract extension provided under Annex “E” of the 2016 revised IRR
of RA No. 9184.
The Procuring Entity will approve any proposed replacement of key personnel only if
their relevant qualifications and abilities are equal to or better than those of the
personnel listed in the Schedule.
21
5. Performance Security
5.1. Within ten (10) calendar days from receipt of the Notice of Award from the
Procuring Entity but in no case later than the signing of the contract by both
parties, the successful Bidder shall furnish the performance security in any of
the forms prescribed in Section 39 of the 2016 revised IRR.
5.2. The Contractor, by entering into the Contract with the Procuring Entity,
acknowledges the right of the Procuring Entity to institute action pursuant to
RA No. 3688 against any subcontractor be they an individual, firm,
partnership, corporation, or association supplying the Contractor with labor,
materials and/or equipment for the performance of this Contract.
7. Warranty
7.1. In case the Contractor fails to undertake the repair works under Section 62.2.2
of the 2016 revised IRR, the Procuring Entity shall forfeit its performance
security, subject its property(ies) to attachment or garnishment proceedings,
and perpetually disqualify it from participating in any public bidding. All
payables of the GOP in his favor shall be offset to recover the costs.
22
10. Dayworks
Subject to the guidelines on Variation Order in Annex “E” of the 2016 revised IRR of
RA No. 9184, and if applicable as indicated in the SCC, the Dayworks rates in the
Contractor’s Bid shall be used for small additional amounts of work only when the
Procuring Entity’s Representative has given written instructions in advance for
additional work to be paid for in that way.
11.2. The Contractor shall submit to the Procuring Entity’s Representative for
approval an updated Program of Work at intervals no longer than the period
stated in the SCC. If the Contractor does not submit an updated Program of
Work within this period, the Procuring Entity’s Representative may withhold
the amount stated in the SCC from the next payment certificate and continue
to withhold this amount until the next payment after the date on which the
overdue Program of Work has been submitted.
23
15.1. If required, the Contractor will provide “as built” Drawings and/or operating
and maintenance manuals as specified in the SCC.
15.2. If the Contractor does not provide the Drawings and/or manuals by the dates
stated above, or they do not receive the Procuring Entity’s Representative’s
approval, the Procuring Entity’s Representative may withhold the amount
stated in the SCC from payments due to the Contractor.
24
Section V. Special Conditions of Contract
25
Special Conditions of Contract
GCC Clause
2 The Intended Completion Date is November 15, 2024
4.1 [Specify the schedule of delivery of the possession of the site to the
Contractor, whether full or in part.]
6 The site investigation reports are:
7.2 [Select one, delete the other.]
[In case of other structures, such as bailey and wooden bridges, shallow
wells, spring developments, and other similar structures:] Two (2) years.
10 [Select one, delete the other:]
26
and/or operating and maintenance manuals by the date required is
[amount in local currency].
27
Section VI. Specifications
28
Section VII. Drawings
[Insert here a list of Drawings. The actual Drawings, including site plans, should be
attached to this section, or annexed in a separate folder.]
29
Section VIII. Bill of Quantities
30
Department of Public Works and Highways XII (DPWH)
Contract ID : 24M00057
Contract Name/Location : ROAD WIDENING - COTABATO-LANAO RD, K1858+100 -
K1858+558, K1858+263 - K1858+353, K1858+353 - K1860+558,
SULTAN KUDARAT, MAGUINDANAO DEL NORTE
496,052.69
56,562.45
Four Hundred Ninety
Fifty Six Thousand
Six Thousand Fifty
Five Hundred Sixty
Two Pesos and
Provision of 4x4 Pick Up Two Pesos and
69/100 Only
Type Service Vehicle for Vehicle 45/100 Only
A.1.2(2) the Engineer on Bare - 8.77
Rental Basis months
31
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
71,223.40
8,121.26
Seventy One
Eight Thousand One
Thousand Two
Hundred Twenty One
Hundred Twenty
Pesos and 26/100
B.8(1) Traffic Management month 8.77 Three Pesos and
Only
40/100 Only
572,762.40 572,762.40
1,668,267.66 1,668,267.66
32
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
Individual Removal of
100(3) Trees, 301-500 mm dia., each 109.00
a2 Small
Individual Removal of
100(3) Trees, Small, 751 - 900 each 6.00
a4 mm.dia
Removal of Actual
101 Structures/Obstruction, square
PCCP (Unreinforced), 0.20 1,200.00
(3)b2 meter
m thick
33
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
Removal of Existing
101(9) Guardrail Posts each 188.00
34
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
Embankment from
Roadway Excavation, cubic
104(1)a 11,796.00
Common Soil meter
35
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
36
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
37
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
38
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
39
PAY UNIT PRICE(PESOS) TOTAL COST (PESOS)
DESCRIPTION UNIT QUANTITY
ITEM NO. (IN WORDS & IN FIGURES) (IN WORDS & IN FIGURES)
Seedlings/Saplings for
611(3) Other Programs/Initiatives each 11,500.00
Reflectorized
Thermoplastic Pavement square
612(1) 2,458.00
Markings White meter
Reflectorized
Thermoplastic Pavement square
612(2) 737.00
Markings Yellow meter
40
TOTAL BID AMOUNT IN WORDS AND IN FIGURES
_____________________________________________________________________________________
SUBMITTED BY: _________________________________ DATE: ___________
Name of Bidder: _________________________________________
Position:__________________________________________
41
Section IX. Checklist of Technical and Financial
Documents
42
Checklist of Technical and Financial Documents
I. TECHNICAL COMPONENT ENVELOPE
Legal Documents
⬜ (a) Valid PhilGEPS Registration Certificate (Platinum Membership) (all pages);
or
⬜ (b) Registration certificate from Securities and Exchange Commission (SEC),
Department of Trade and Industry (DTI) for sole proprietorship, or
Cooperative Development Authority (CDA) for cooperatives or its
equivalent document;
and
⬜ (c) Mayor’s or Business permit issued by the city or municipality where the
principal place of business of the prospective bidder is located, or the
equivalent document for Exclusive Economic Zones or Areas;
and
⬜ (e) Tax clearance per E.O. No. 398, s. 2005, as finally reviewed and approved by
the Bureau of Internal Revenue (BIR).
Technical Documents
⬜ (f) Statement of the prospective bidder of all its ongoing government and
private contracts, including contracts awarded but not yet started, if any,
whether similar or not similar in nature and complexity to the contract to be
bid; and
⬜ (g) Statement of the bidder’s Single Largest Completed Contract (SLCC) similar
to the contract to be bid, except under conditions provided under the rules;
and
⬜ (h) Philippine Contractors Accreditation Board (PCAB) License;
or
Special PCAB License in case of Joint Ventures;
and registration for the type and cost of the contract to be bid; and
⬜ (i) Original copy of Bid Security. If in the form of a Surety Bond, submit also a
certification issued by the Insurance Commission;
or
Original copy of Notarized Bid Securing Declaration; and
(j) Project Requirements, which shall include the following:
⬜ a. Organizational chart for the contract to be bid;
⬜ b. List of contractor’s key personnel (e.g., Project Manager, Project
Engineers, Materials Engineers, and Foremen), to be assigned to the
contract to be bid, with their complete qualification and experience
data;
⬜ c. List of contractor’s major equipment units, which are owned, leased,
and/or under purchase agreements, supported by proof of ownership
or certification of availability of equipment from the equipment
43
lessor/vendor for the duration of the project, as the case may be; and
⬜ (k) Original duly signed Omnibus Sworn Statement (OSS);
and if applicable, Original Notarized Secretary’s Certificate in case of a
corporation, partnership, or cooperative; or Original Special Power of
Attorney of all members of the joint venture giving full power and authority
to its officer to sign the OSS and do acts to represent the Bidder.
Financial Documents
⬜ (l) The prospective bidder’s audited financial statements, showing, among
others, the prospective bidder’s total and current assets and liabilities,
stamped “received” by the BIR or its duly accredited and authorized
institutions, for the preceding calendar year which should not be earlier than
two (2) years from the date of bid submission; and
⬜ (m) The prospective bidder’s computation of Net Financial Contracting Capacity
(NFCC).
44
PRELIMINARY EXAMINATION OF TECHNICAL PROPOSAL
Date of Submission/Opening of Bids:
Contract ID No. :
Name of Project :
Name of Contractor :
BAC Provisional as
BAC Provisional
End User
BAC Chairman
BAC Regular
BAC Regular
BAC Regular
Tab No.
(1) PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR
(2) a. If the Bidder is not previously enrolled in the CWR: the bidder's Class "A" and Class "B" Documents
not covered by the PhilGEPS Certificate, in accordance with Section 4.8.2 of this DPM Volume II.
These Documents should include, among others, the following information required in IRR Section
25.2b:
i. Valid PCAB License or special PCAB License in case of join ventures, and registration for the type and
cost of the contract to be bid.
ii. Statement of all On-going Government and Private, including contracts awarded but ot yet started, if any,
whether similar or not similar in nature and complexity to the contract to be bid.
ii. Statement identifiying the Bidder's SLCC similar to the contract to be bid
iii. NFCC Computation and Statement of Total Assets and Total Liabilities
iv. JVA, if applicable
b. If the bidder is previously enrolled in the CWR but would like to update any of its Class "A" and
Class "B" Documents in the CWR: the pertinent Documents to be updated.
(3) Bid Security in the prescribe form, amount and validity period (Form DPWH INFR-13).
a. Acceptable Forms Cash, Cashier's Check, Bank Draft/Guarantee, or Surety Bond callable upon Bid Securing
Manager's Check, Irrevocable Letter of Credit demand issued by a surety or Declaration
Issued by a Universal or Issued by a Universal or Insurance Commision as
Commercial Bank (2% Commercial Bank (If issued by authorized to issue such
of ABC) a Foreign Bank it shall be security (5% of ABC)
confirmed or authenticated by a
Universal or Commercial Bank
(2% of ABC)
List of contractor's key personnel-e.g., Project Manager, Project Engineers, Materials Engineers, Construction Safety and
b. Foremen-to be assigned to the contract, with their complete qualification and experience data (Form DPWH-INFR-14).
These personnel must meet the required minimum years of experience set in the BDS.
List of contractor's major construction and laboratory equipment units to be used for the contract-which are owned, leased
and /or under purchase agreements, supported by certification of availability of the equipment from the equipment
c. lessor/vendor for the duration of the project (Form DPWH-INFR-15). These equipment units must meet the minimum
major equipment requirements for the contract set in the BDS and it should be included with a Minimum Testing Materials
Equipment as required in D.O 11, series of 2017 (copy attached in BDS)
Omnibus Sworn Statement by the prospective bidder or its authorized representative in the form
(6)
prescribed by the GPPB
Any missing, incomplete or patently insufficient document in the above-mentioned checklist is a ground for
Note:
outright rejection of the bid.
Overall Rating: ( ) Passed ( ) Failed BAC INITIAL
45
Bidder Form No. 1
Project ID No. :
Name of Contractor :
BAC Provisional
BAC Provisional
as End User
BAC Chairman
BAC Regular
BAC Regular
BAC Regular
Financial Component TAB No.
BAC Vice
Chairman
1. Bid Form indicating the Total Bid Price, using Form DPWH INFR-09.
Bid Prices in the Bill of Quantities (BOQ) (Form s DPWH-INFR-16 and DPWH -INFR-
2.
18)
Detailed Estimates including a Summary sheet indicating the unit prices of construction
3. materials, labor rates and equipment rentals used in coming up w ith the bid;
BAC INITIAL
Financial Proposal
46
Bid Form for the Procurement of Infrastructure
Projects
[shall be submitted with the Bid]
_________________________________________________________________________
BID FORM
Date : _________________
Project Identification No. : _________________
b. We offer to execute the Works for this Contract in accordance with the PBDs;
c. The total price of our Bid in words and figures, excluding any discounts offered
below is: [insert information];
d. The discounts offered and the methodology for their application are: [insert
information];
e. The total bid price includes the cost of all taxes, such as, but not limited to:
[specify the applicable taxes, e.g. (i) value added tax (VAT), (ii) income tax, (iii)
local taxes, and (iv) other fiscal levies and duties], which are itemized herein and
reflected in the detailed estimates,
f. Our Bid shall be valid within the a period stated in the PBDs, and it shall remain
binding upon us at any time before the expiration of that period;
47
the allowable forms of Performance Security, subject to the terms and conditions
of issued GPPB guidelines2 for this purpose;
h. We are not participating, as Bidders, in more than one Bid in this bidding process,
other than alternative offers in accordance with the Bidding Documents;
i. We understand that this Bid, together with your written acceptance thereof
included in your notification of award, shall constitute a binding contract between
us, until a formal Contract is prepared and executed; and
j. We understand that you are not bound to accept the Lowest Calculated Bid or any
other Bid that you may receive.
l. We acknowledge that failure to sign each and every page of this Bid Form,
including the Bill of Quantities, shall be a ground for the rejection of our bid.
Name: ___________________________________________________________________
Legal Capacity: ____________________________________________________________
Signature: ________________________________________________________________
Duly authorized to sign the Bid for and behalf of: __________________________________
Date: ___________________
2
currently based on GPPB Resolution No. 09-2020
48
Bid Securing Declaration Form
[shall be submitted with the Bid if bidder opts to provide this form of bid security]
_________________________________________________________________________
1. I/We understand that, according to your conditions, bids must be supported by a Bid
Security, which may be in the form of a Bid Securing Declaration.
2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any
procurement contract with any procuring entity for a period of two (2) years upon receipt
of your Blacklisting Order; and, (b) I/we will pay the applicable fine provided under
Section 6 of the Guidelines on the Use of Bid Securing Declaration, within fifteen (15)
days from receipt of the written demand by the procuring entity for the commission of
acts resulting to the enforcement of the bid securing declaration under Sections 23.1(b),
34.2, 40.1 and 69.1, except 69.1(f),of the IRR of RA No. 9184; without prejudice to other
legal action the government may undertake.
3. I/We understand that this Bid Securing Declaration shall cease to be valid on the
following circumstances:
a. Upon expiration of the bid validity period, or any extension thereof pursuant
to your request;
b. I am/we are declared ineligible or post-disqualified upon receipt of your
notice to such effect, and (i) I/we failed to timely file a request for reconsideration or
(ii) I/we filed a waiver to avail of said right; and
c. I am/we are declared the bidder with the Lowest Calculated Responsive Bid,
and I/we have furnished the performance security and signed the Contract.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this ____ day of [month]
[year] at [place of execution].
49
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
Omnibus Sworn Statement (Revised)
[shall be submitted with the Bid]
_________________________________________________________________________
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant], after
having been duly sworn in accordance with law, do hereby depose and state that:
[If a sole proprietorship:] I am the sole proprietor or authorized representative of [Name of Bidder]
with office address at [address of Bidder];
[If a partnership, corporation, cooperative, or joint venture:] I am the duly authorized and
designated representative of [Name of Bidder] with office address at [address of Bidder];
[If a sole proprietorship:] As the owner and sole proprietor, or authorized representative of [Name
of Bidder], I have full power and authority to do, execute and perform any and all acts necessary
to participate, submit the bid, and to sign and execute the ensuing contract for [Name of the
Project] of the [Name of the Procuring Entity], as shown in the attached duly notarized Special
Power of Attorney;
[If a partnership, corporation, cooperative, or joint venture:] I am granted full power and authority
to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign
and execute the ensuing contract for [Name of the Project] of the [Name of the Procuring Entity],
as shown in the attached [state title of attached document showing proof of authorization (e.g.,
duly notarized Secretary’s Certificate, Board/Partnership Resolution, or Special Power of
Attorney, whichever is applicable;)];
3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the
Philippines or any of its agencies, offices, corporations, or Local Government Units, foreign
government/foreign or international financing institution whose blacklisting rules have been
recognized by the Government Procurement Policy Board, by itself or by relation,
membership, association, affiliation, or controlling interest with another blacklisted
person or entity as defined and provided for in the Uniform Guidelines on Blacklisting;
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized
representative(s) to verify all the documents submitted;
[If a sole proprietorship:] The owner or sole proprietor is not related to the Head of the
50
Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working
Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit,
and the project consultants by consanguinity or affinity up to the third civil degree;
[If a partnership or cooperative:] None of the officers and members of [Name of Bidder] is related
to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the
Technical Working Group, and the BAC Secretariat, the head of the Project Management Office
or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil
degree;
[If a corporation or joint venture:] None of the officers, directors, and controlling stockholders of
[Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and Awards
Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the
Project Management Office or the end-user unit, and the project consultants by consanguinity or
affinity up to the third civil degree;
7. [Name of Bidder] complies with existing labor laws and standards; and
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or
any form of consideration, pecuniary or otherwise, to any person or official, personnel or
representative of the government in relation to any procurement project or activity.
10. In case advance payment was made or given, failure to perform or deliver any of the
obligations and undertakings in the contract shall be sufficient grounds to constitute
criminal liability for Swindling (Estafa) or the commission of fraud with unfaithfulness or
abuse of confidence through misappropriating or converting any payment received by a
person or entity under an obligation involving the duty to deliver certain goods or
services, to the prejudice of the public and the government of the Philippines pursuant to
Article 315 of Act No. 3815 s. 1930, as amended, or the Revised Penal Code.
IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__ at ____________,
Philippines.
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
51
Performance Securing Declaration (Revised)
[if used as an alternative performance security but it is not required to be submitted with the
Bid, as it shall be submitted within ten (10) days after receiving the Notice of Award]
_________________________________________________________________________
Invitation to Bid: [Insert Reference Number indicated in the Bidding Documents] To: [Insert
name and address of the Procuring Entity]
2. I/We accept that: I/we will be automatically disqualified from bidding for any
procurement contract with any procuring entity for a period of one (1) year for the first
offense, or two (2) years for the second offense, upon receipt of your Blacklisting Order if
I/We have violated my/our obligations under the Contract;
3. I/We understand that this Performance Securing Declaration shall cease to be valid
upon:
a. issuance by the Procuring Entity of the Certificate of Final Acceptance, subject to the
following conditions:
i. Procuring Entity has no claims filed against the contract awardee;
ii. It has no claims for labor and materials filed against the contractor; and
iii. Other terms of the contract; or
replacement by the winning bidder of the submitted PSD with a performance security in
any of the prescribed forms under Section 39.2 of the 2016 revised IRR of RA No. 9184
as required by the end-user.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this ____ day of [month] [year] at
[place of execution].
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
52
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE XII
Koronadal City
Contract ID No. :
Contract Title :
Contract Location :
___________________________________________________________________________
CERTIFICATE AS TO TECHNICAL KEY PERSONNEL
(Department Order No.9 and 58, Series of 2012)
Date
BAC CHAIRMAN
Chairperson – Bids and Awards Committee
DPWH – Regional Office 12
Cor. Alunan Avenue, Mabini Street, Koronadal City
1. That the equipment we have pledged in the project to be bid will be available for
inspection during the post-qualification period in compliance with the D.O. 9, & 58
series of 2012.
2. That the Technical Personnel I have submitted in the bidding documents is an employee
of my firm and working on another project at the time of bidding and I certify that (1)
personnel will be pulled out from on-going project once the contract is awarded to us,
and (2) he/she will be replaced with another person with equal or better qualifications,
as certified by the Head of the Implementing Office Agency upon award of this project,
if won.
3. That I am making this certification in compliance with D.O. No. 9, series of 2012 of the
Implementing Rules and Regulations of the Republic Act. No. 9184 and in accordance
with the requirements of the Department of Public Works and Highways, Regional
Office XII, Koronadal City.
53
1. ORGANIZATIONAL CHART
54
2. LIST OF EQUIPMENT PLEDGED
55
Contract ID No. :
Contract Title :
SWORN STATEMENT
(Conflict of Interest)
1. That the firm has no controlling shareholders in common with another bidder;
2. That the firm never receives or has received any direct or indirect subsidy
from any bidder;
3. That the firm has no the same legal representative as that of another bidder
for a purpose of this bid;
4. That the firm does not submit more than one bid in this bidding, however does
not limit the participation of subcontractors on more than on bid;
5. That the firm does not lends or temporary seconds, its personal to firms or
organization which is engaged in consulting services for the preparation
related to procurement for implementation of the project. If the personnel
would be involved in any capacity in the same project.
6. That we are making this statement in compliance with Section 11A-4 PBD’s
(Conflict of Interest) of the Implementing Rules and Regulations of Republic
Act No. 9184 and accordance with the requirements of the Procuring Entity.
56
In witness whereof, we hereunto set my hand this _____________________,
___________________.
NAME
Proprietor/Manager
CONSTRUCTION FIRM
57
58
59
60
61
62
63