3-24-7 Vibracast Refractory Lining - V-Anchors-13767-7
3-24-7 Vibracast Refractory Lining - V-Anchors-13767-7
Indication
UOP Engineering Department
STANDARD SPECIFICATION
3-24-7 Page 1 of 38
DATE STATUS SPNSR APVD
VIBRACAST REFRACTORY LINING
V-ANCHORS 28MAY19 Revised MJK MAS
1. TABLE OF CONTENTS
1. TABLE OF CONTENTS ............................................................................................................... 1
2. GENERAL ..................................................................................................................................... 2
2.1 Scope ...................................................................................................................................... 2
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
2. GENERAL
2.1 Scope
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
a. This specification describes the refractory and anchorage materials to be used, and the
methods of application, for internally insulating vessels, equipment, piping, and duct
work with a 3” (75mm) to 6” (150mm) thick, vibracast monolithic refractory lining.
Refractory lining in fired process heaters is not included.
b. The refractory and all required hydrating water are blended in the mixer. The resulting
mixture is transported to the installation site and placed where required. Forms are
used to define the exposed surface of the lining. Consolidation and removal of air
pockets is accomplished by vibration of the in place refractory.
c. This specification is not applicable to materials that are conveyed or pumped to the
installation site, nor is it applicable to self-leveling, pumpcast, or similar materials.
d. Exceptions or variations shown in the UOP Project Specifications take precedence over
requirements shown herein.
e. When the Manufacturer’s requirements for storage, mixing, placement, curing and heat
drying, etc. are more stringent than those herein, the Manufacturer’s requirements shall
govern.
2.2 References
The edition in effect on the date of the contract award for the equipment shall be used,
except as otherwise noted. When a referenced document incorporates another document,
use the edition of that document required by the referenced document.
(1) A479 “Standard Specification for Stainless Steel Bars and Shapes for Use in
Boilers and Other Pressure Vessels”
(2) A516 “Standard Specification for Pressure Vessel Plates, Carbon Steel, for
Moderate - and Lower-Temperature Service”
(4) C20 “Standard Test Methods for Apparent Porosity, Water Absorption,
Apparent Specific Gravity, and Bulk Density of Burned Refractory
Brick and Shapes by Boiling Water”
(6) C113 “Standard Test Method for Reheat Change of Refractory Brick”
(7) C133 “Standard Test Methods for Cold Crushing Strength and Modulus of
Rupture of Refractories”
(8) C134 “Standard Test Methods for Size, Dimensional Measurements, and
Bulk Density of Refractory Brick and Insulating Firebrick”
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(15) D4285 “Standard Test Method for Indicating Oil or Water in Compressed
Air”
f. The Society for Protective Coatings (SSPC), Specification SP-7, “Brush-Off Blast
Cleaning”.
a. Refractory lining materials, testing, installation, and inspection shall comply with
the requirements of API Standard 936, except where modified by either the UOP
Standard Specifications or UOP Project Specifications and Drawings.
2.4 Definitions
Terms related to refractory materials, installation, testing, inspection, etc. are defined in
API Standard 936 and ASTM C71.
a. Areas in which refractory lining is to be installed and the type, thickness, and extent of
the lining in each area, are identified in the UOP Project Specifications and UOP
Project Drawings.
b. Refractory lining is not required in non-flowing (e.g., dead end) nozzles 6 inch NPS
and smaller.
c. Ceramic fiber shall be installed into nozzles, onto the shell, or in other locations only
where specified in the UOP Project Specifications or UOP Project Drawings. Fiber
packing in the annular space of nozzles shall extend to a point flush with the inside
surface of the shell and then shall be covered with a metallic disc (see the UOP Project
Specifications and Drawings) and the shell refractory.
3.1 Materials
a. Anchors shall be 5/16 inch (8 mm) diameter, ASTM A479 Type 304, austenitic
stainless steel rods, bent into the configuration illustrated on Figure 1. The anchors
shall be solution annealed after forming.
b. Provide rubber or plastic caps 1/2 inch (13 mm) long and 30-50 mil (0.75 to 1.25mm)
thick on the tip of each anchor leg. The caps shall be of a contrasting color for easy
visual identification. The caps shall be shipped loose. Install the caps after anchor
welding and postweld heat treatment, and immediately prior to the refractory
installation.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
c. Collars and edging bars shall be 1/4 inch (6 mm) thick, fabricated from the same
material as the shell to which they are welded. Collars and edging bars shall be a
minimum of ASTM A516 Grade 55.
d. Welding electrodes for anchor attachment to carbon, low alloy, or ferritic stainless
steel shall be AWS A-5.4 / ASME SFA-5.4/SFA-5.4M, Class E-309-15, 16 or E-310-
15, 16 or AWS A-5.9 / ASME SFA-5.9/SFA-5.9M Class ER 309 or ER 310. The
welding electrode may also be AWS A-5.11 / ASME SFA-5.11/SFA-5.11M, Class
ENiCrFe-2 or Class ENiCrFe-3.
a. Immediately prior to anchor installation, prepare the interior plate surface by grit blast
cleaning to remove rust, loose mill scale, oil, dirt, or other foreign materials. The grit
shall be compatible with the base metal (e.g. steel grit shall not be used on stainless
steel base metal) and shall not damage or leave residue on the base metal. The grit and
the blasting air supply shall be dry and clean. Testing of the air stream discharged
from the hose shall be in accordance with ASTM D4285. Cleaning shall be brush-off
blast clean in accordance with SSPC-SP-7.
b. After grit blast cleaning, the surfaces to be lined shall be vacuum cleaned to remove all
debris. Do NOT wash with water. Inspect the surfaces for cleanliness and repeat the
above blast cleaning as necessary.
c. Wax crayons, grease markers or other substances that will interfere with the quality of
the attachment weld shall not be used to locate anchor, bar, and collar positions.
d. Anchors, bars, and collars shall be welded to the shell as illustrated in Figures 1
through 5, 7, and 8. Welding shall be done after any radiographing or other
nondestructive examination requirements are completed, but before postweld heat
treatment. Do not weld to shell weld seams. When a row of anchors is to be placed at
a shell weld seam, the anchors shall straddle the seam (i.e., anchors are placed on
alternating sides of the seam). Grind all weld and weld slag that will interfere with
placement of anchors, bars, and collars.
f. Installed anchors, bars, and collars shall be inspected by the Owner or Owner’s
authorized representative. Each anchor shall be hammer tested by striking from
several directions with an 8 to 16 ounce (225-455 gram) hammer. Loose or broken
anchors or cracked welds shall be removed and replaced. Hammer test the replaced
anchors.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
g. After installation of the anchors, after all post weld heat treatments, and just before
refractory installation, place the anchor caps onto the end of each anchor leg.
4. LINING MATERIALS
4.1 Refractory
e. The as supplied refractory materials shall NOT include metal reinforcing fibers.
Organic fibers, as recommended by the refractory manufacturer, are acceptable.
h. Each bag and/or pallet of material shall include, as a minimum, the following
information: manufacturers name; plant of manufacture; product brand name; batch
identification; date of manufacture; an accurate bag weight (+ 2 weight percent);
mixing instructions (included hydrating water requirements); special cautions and/or
requirements. If organic fibers are included, their presence shall be clearly indicated
on each bag.
i. Refractory material shall be kept at a temperature between 50F (10C) and 80°F
(27°C) for 24 hours prior to use. At all times the material shall be stored on an
elevated ventilated platform, protected by a weatherproof covering above and on all
sides, and so arranged that no water can come into contact with any of the material or
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
bags. The platform shall be supported by a concrete slab or dry, durable surface,
sloped to drain moisture away from the storage area. Care shall also be taken to avoid
high humidity under the covering.
j. Previously opened bags of refractory, materials that are older than the lesser of nine
months or the manufacturer’s shelf life from their date of manufacture, materials
exhibiting agglomeration or lumps that are not easily broken by hand, and material that
has gotten wet or is otherwise damaged shall not be used.
k. The properties listed in Paragraphs 4.1l.(3), 4.1m.(3) and 4.1n.(3) are the range of
values from the product catalog data sheets for the recommended products. These
values are often averages, rather than minimums. Guaranteed (or compliance) values
shall be agreed upon with the chosen refractory vendor. The guaranteed values shall
be the reference(s) used for all testing and material evaluations (see Section 8.1).
Testing shall be in accordance with the listed specification(s).
(1) These materials are used when excellent insulating ability is required but abrasion
resistance and low iron content are not necessary.
(3) Following is the range of product catalog data sheet values for the recommended
materials. The properties are based upon samples prepared by vibracasting and
without metal reinforcing fibers. The listed ranges are for informational purposes
and are not to be used for quality control or decision making regarding individual
products.
(c) Density after heating to 1500°F (815°C) and cooling to ambient temperature
is between 70 lb/ft3 (1120 kg/m3) and 90 lb/ft3 (1440 kg/m3) per ASTM
C134.
(d) Cold crushing strength after heating to 1500°F (815°C) and cooling to
ambient temperature is at least 600 psi (42 kg/cm2) per ASTM C133.
(e) Modulus of rupture after heating to 1500°F (815°C) and cooling to ambient
temperature is at least 200 psi (14 kg/cm2) per ASTM C133.
(f) Permanent linear change after heating to 1500°F (815°C) and cooling to
ambient temperature is between 0.00 and -0.30% per ASTM C113.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(g) Apparent porosity after heating to 1500°F (815°C) and cooling to ambient
temperature is between 30 and 50 percent per ASTM C20.
(1) These materials are used when a material with good insulating and good abrasion
resistant properties is required but low iron content is not a primary concern.
(3) Following is the range of product catalog data sheet values for the recommended
materials. The properties are based upon samples prepared by vibracasting and
without metal reinforcing fibers. The listed ranges are for informational purposes
and are not to be used for quality control or decision making regarding individual
products.
(c) Density after heating to 1500°F (815°C) and cooling to ambient temperature
is between 100 lb/ft3 (1600 kg/m3) and 145 lb/ft3 (2320 kg/m3) per ASTM
C134.
(d) Cold crushing strength after heating to 1500°F (815°C) and cooling to
ambient temperature is at least 6000 psi (420 kg/cm2) per ASTM C133.
(e) Modulus of rupture after heating to 1500°F (815°C) and cooling to ambient
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(f) Permanent linear change after heating to 1500°F (815°C) and cooling to
ambient temperature is between 0.00 and -0.30% per ASTM C113.
(g) Apparent porosity after heating to 1500°F (815°C) and cooling to ambient
temperature is between 20 and 40 percent per ASTM C20.
(1) These materials are used when an insulating material with a low iron content
(below 1.0 weight percent) is required and abrasion resistance is not necessary.
(3) Following is the range of product catalog data sheet values for the recommended
materials. The properties are based upon samples prepared by vibracasting and
without metal reinforcing fibers. The listed ranges are for informational purposes
and are not to be used for quality control or decision making regarding individual
products.
(c) Density after heating to 1500°F (815°C) and cooling to ambient temperature
is between 65 lb/ft3 (1040 kg/m3) and 100 lb/ft3 (1600 kg/m3) per ASTM
C134.
(d) Cold crushing strength after heating to 1500°F (815°C) and cooling to
ambient temperature is at least 500 psi (35 kg/cm2) per ASTM C133.
(e) Modulus of rupture after heating to 1500°F (815°C) and cooling to ambient
temperature is at least 200 psi (14 kg/cm2) per ASTM C133.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(f) Permanent linear change after heating to 1500°F (815°C) and cooling to
ambient temperature is between 0.00 and -0.30% per ASTM C113.
(g) Apparent porosity after heating to 1500°F (815°C) and cooling to ambient
temperature is between 30 and 50 percent per ASTM C20.
4.2 Water
Mixing water shall be potable (suitable for drinking) with a pH between 6 and 8. Water
from the firefighting system shall not be used. Water shall contain less than 50 ppm
chlorides, and be free from deleterious impurities. Equipment used for storing and handling
of the water shall be clean, so that no contaminating material is introduced. Water
temperature shall be between 40F (5C) and 80°F (27°C) {see paragraphs 5.4a.(2), 5.4a.(3)
and 5.4b.(8)}.
Reinforcing fibers shall comply with ASTM A820. Fibers shall be 20 mil (0.5mm) Type
304 austenitic stainless steel, with a length of 1 inch (25 mm). The material tensile strength
shall comply with the requirements of the specified metallurgy. Fibers shall be of a uniform
size and shape and shall not clump together. Fibers that become magnetic shall not be used.
Fibers manufactured by the melt extract process (ASTM A820 Type III) are preferred,
alternatively, corrugated fibers may be manufactured from slit sheets (ASTM A820 Type
II). Corrugated fibers shall be twisted about their longitudinal axis. The corrugations shall
be a smooth and gentle curvature, without any sharp bends. The corrugation range shall not
exceed 1/16 inch (1.5 mm).
5. REFRACTORY INSTALLATION
a. Equipment and tools used for refractory mixing, handling, and installation shall be
clean and in good operating condition.
b. Backup or spare equipment and tools shall be provided at the jobsite for all items that
would halt refractory placement in the event of their failure.
c. The capacity and number of pieces of equipment and tools in use during refractory
installation shall be sufficient to ensure that application will proceed uninterrupted.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
5.2 Preparation
a. Refractory installation shall not begin until after completion of welding, postweld heat
treatment, and pressure testing. If the refractory installation must take place prior to
pressure testing, all pressure retaining weld seams shall be left unlined, i.e., exposed to
the testing medium, and the testing medium shall not damage or degrade the refractory.
b. The mixing area and the installation site shall be kept clean, dry, and isolated from the
surrounding area by use of heavy plastic or other means. The protective means shall
prevent the entry of dust, rain or other deleterious material and shall protect against
excessive wind, heat, and exposure to the sun (i.e., shaded).
c. The area to be lined shall be well lit and ventilated to provide good visibility and a
cool breathable atmosphere during refractory installation.
d. Provide a reliable means of communication between the mixing and installation sites
that is effective while both sites are in operation. Test the system under actual
conditions and locations.
e. The surface to which the refractory lining is to be installed shall be dry and clean. Grit
blast cleaning immediately prior to installation of the refractory is required if:
(2) Rust, weld slag or spatter, oil or grease, dirt, loose scale, debris, or other foreign
materials are present on the surface to be lined
(3) The surface does not comply with the requirements of SSPC SP-7.
(4) Hydrotest was performed after the grit blast cleaning for anchor installation.
f. When grit blast cleaning is required, remove the anchor caps prior to grit blast
cleaning. Per paragraph 5.2l, the removed caps shall be discarded; new caps will be
reinstalled. The grit shall be compatible with the base metal (e.g. steel grit shall not be
used on stainless steel base metal) and shall not damage or leave residue on the base
metal. The grit blasting air supply shall be clean and dry. Testing for contamination
of the air stream discharged from the hose shall be in accordance with ASTM D4285.
Grit blast cleaning shall be brush-off blast clean in accordance with SSPC-SP-7.
g. After grit blast cleaning, the surfaces to be lined shall be vacuum cleaned to remove all
debris. Do NOT wash with water. Inspect the surfaces for cleanliness and repeat the
above grit blast cleaning as necessary.
h. Structural members, nozzle extensions, and other items within the limits of the lining
shall be wrapped with 1/8 inch (3 mm) thickness of non-absorbent paper (not
cardboard) or coated with bitumen to prevent moisture absorption from or bonding to
the refractory lining. Paper shall be taped into place. Additional paper or bitumen
may be required for large nozzles, elevated temperatures, or other conditions in order
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
i. Openings shall be closed by means of sealed wood or metal jacketed plugs, slightly
tapered (smaller towards the shell), and of such dimensions that they fit snugly into the
openings. The surfaces of the plug(s) shall be lightly coated with a release agent
approved by the refractory manufacturer to prevent binding. The plugs shall not be
removed from the openings or disturbed until the refractory lining has developed its
final set.
j. Obstructions that will interfere with the satisfactory and continuous application of the
refractory lining (e.g., ladders, scaffolding, etc.) shall be avoided.
k. Nozzle necks and other areas that cannot be vibracast with the shell shall be cast or
hand packed prior to beginning installation of the shell lining. Cast or hand packed
nozzle lining shall extend to one inch (25 millimeters) from the inside shell surface.
The full thickness nozzle lining shall be trimmed perpendicular to the nozzle inside
diameter. The remaining refractory is installed with the shell lining.
l. Immediately prior to refractory placement, place anchor caps onto the ends of any
anchor legs not already covered by a cap. Caps that are loose or are removed for any
reason shall be replaced with new caps prior to refractory placement.”
m. When welded joints or seams in the backing material will be completed after the
refractory has been installed, the refractory shall be installed as shown in Figure 7.
After welding, examination, and heat treatment have been completed, the remaining
lining shall be installed. This interruption of application shall follow the procedures
described in Paragraph 5.4e. When the seam is located in an inaccessible location of a
small (less than or equal to 24 inch ID of lining) item, and neither heat treatment or
radiography is performed, the detail shown in Figure 8 may be used.
5.3 Forms
a. The free surface of the refractory shall be defined by watertight, carbon steel, forms.
b. The formwork shall be solid and stable with bracing as required. It shall not deform,
shift, or deflect under the load (weight), buoyancy, and head of fluid refractory at any
time during the refractory installation process. The formwork shall withstand an
unbalanced refractory head of at least three feet (one meter). The forms shall be
designed to withstand vibration of the refractory including the possible attachment of
vibrators to the formwork.
c. The formwork shall be designed for easy, rapid disassembly after the refractory has
hydrated and cured. Disassembly shall not damage the refractory, e.g., cutting with
heat (arc gouging) or water jets is not acceptable. Bolted forms are preferred.
d. Form components shall fit tightly together and shall align with one another to avoid
creation of steps or ledges in the lining. Joints in the forms shall be sealed to prevent
leakage of refractory and water.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
e. Forms shall be coated with a parting agent approved by the refractory vendor to
prevent adherence between the refractory and the form.
f. When the forms are in place the area into which refractory will be cast shall be clear
and unobstructed.
g. The forms shall be provided with casting (pouring) ports or openings as described in
paragraph 5.4c.(10). Provide a means of closing and sealing the opening when the
refractory level approaches the opening. The closure means shall be adequate for any
applied loads and head of refractory.
h. All forms shall be in place prior to the start of casting to eliminate unnecessary
interruptions in the placement of refractory. Interruptions contribute to the formation
of cold joints.
i. The forms shall be installed concentrically within the lined item or as otherwise
specified by the project documents to result in the required lining thickness and
configuration.
j. The formwork shall result in an inner lining surface within ± 1/4 inch (6 mm) of the
specified dimensions. The lining thickness shall be within ± 1/2 inch (13 mm) of the
specified value.
k. Joints between adjacent forms shall not be located at nozzles or critical areas.
5.4 Application
a. Precautions
(1) When mixing and handling refractory, personnel shall wear appropriate personnel
protective equipment (PPE), shall comply with all appropriate safety measures as
defined by the refractory manufacturer’s Material Safety Data Sheet (MSDS) for
the subject material, and shall comply with other measures required at the site and
by the applicable licensing and governing bodies.
(2) During cold weather, the refractory lining and the surface to which it is applied
shall be continuously kept at a temperature above 50°F (10°C) during application,
curing, and before heat drying. If required, suitable means for heating and/or
exterior insulation shall be provided; however, live steam shall not be used for
this purpose.
(3) During hot weather, the refractory lining and the surface to which it is applied
shall not exceed a temperature of 95°F (35°C) during application. If required, the
exterior surface of the vessel shall be cooled by shading, spraying with cold
water, air conditioning, or other means before and while the refractory lining is
being applied. Installation at night, when it’s cooler and there is no radiant heat
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
from the sun, may be considered. After refractory application, cooling of shell is
no longer required.
(4) The interior shell temperature shall be registered by temperature recorders with a
minimum of 3 thermocouples around the shell for each recorder. The
thermocouples shall be calibrated in accordance with ASTM E 220. The number
of recorders and thermocouples and their location shall be approved by the Owner
or the Owner’s authorized representative. The shell temperature where refractory
is being applied shall be monitored. Certified copies of the shell temperature
control log shall be provided to the Owner or the Owner’s authorized
representative.
(1) Mixing shall be performed in a horizontal, paddle type mixer. Concrete mixers
shall not be used.
(2) The mixer shall be stabilized, grounded and fixed into place on level ground or a
solid platform near the installation site. Provide large, clear, access areas at the
mixer. Cover the mixer with a coarse metal grid, or other system, to prevent entry
of bags, tools, or other foreign objects.
(3) Mix only as much refractory as will be placed within 20 minutes or the working
time of the refractory, whichever is less.
(4) The full contents of each bag of premixed refractory material shall be used. Do
not use bags that have been wet or that have been previously opened.
(5) No cement, lime, or other admixtures of any kind shall be added to the premixed
refractory materials as received from the manufacturer. The only permitted
addition is metal reinforcing fibers.
(6) Refractory lining materials from one manufacturer shall not be mixed with those
from other manufacturers.
(7) Metal reinforcing fibers shall be screened into the dry refractory lining material in
the mixer at the job site. Fibers shall be added at a rate of 3% by weight (i.e.,
weight of fibers divided by weight of refractory) for each batch of refractory
material.
(8) The mix temperature shall be maintained between 60˚F (15˚C) and 80˚F (27˚C).
(9) Prior to mixing the first batch of the day, or after a lengthy pause, moisten all
interior surfaces of the mixer, including the blades.
(10) Weigh 10 bags randomly selected from throughout the pallet of refractory (e.g.,
not all from the top). If each bag is within ± 2 percent of the weight marked on
the bag, the water to be added to the mixer for bags from that pallet may be based
upon the average weight of the sampled bags. If any bags are outside of ± 2
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
percent of the weight marked, each bag from that pallet must be weighed before it
is discharged into the mixer. The mixer water addition is then based upon the
actual weight of the refractory in the mixer. Each pallet of material shall be
evaluated separately.
(11) The refractory material shall be thoroughly dry mixed with the reinforcing fibers.
The refractory shall be introduced into the mixer first and dry mixing begun. The
reinforcing fibers shall be introduced into the refractory materials in the operating
mixer as a rain of individual fibers through a shaken or vibrating screen to
prevent clumping of the fibers.
(12) The amount of water required for proper hydration, the mixing procedure and
time, and the mix consistency shall be in accordance with manufacturer's
recommendation and the results of the prequalification testing (see Section 8.4).
(a) Ninety to ninety-five percent of this water is initially added to the mixer
and blended. If necessary, additional water is then added and blended until
a mix of the proper consistency is obtained.
(b) Do not add excess water. The mix should have a slightly moist sheen and
should be stiff, i.e., retaining its shape when placed on a flat surface.
ASTM C860, the “ball in hand” method is one way to evaluate the mix
consistency.
(c) The final water addition shall be within the water range provided by the
refractory manufacturer.
(d) The water shall be added to the refractory/fiber mixture as a rain while the
refractory dry mixes.
(13) The mixer shall be discharged into a clean dry metal, plastic, or sealed/lined
wooden container. Material that misses the container, is discharged onto the
ground, etc. shall not be used. Discharged refractory shall not be placed back into
the mixer or remixed.
(14) The refractory shall be transported to the installation site in clean, dry, metal or
plastic buckets, trays, or other similar impervious container. The means of
transportation shall prevent the separation of the refractory components or the
entry of foreign material.
(15) All equipment (mixer, discharge and transport containers, etc.) shall be
thoroughly washed and dried before use, at the end of each workday, and at the
end of the refractory installation. The mixer and paddles shall be thoroughly
cleaned after each batch (i.e., mixer charge) to prevent build-up of refractory
lining materials. The discharge and transport containers and all tools used in
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
mixing and applying the refractory lining shall be cleaned after each batch and
kept free of all deleterious materials.
(16) The supply of refractory to the installation site shall be continuous, uninterrupted,
and provided to the site at approximately the rate of refractory placement
throughout the refractory installation.
(17) For each batch of refractory mix, the total weight of water, refractory, and
reinforcing fibers added to the mixer, and the resulting weight percent of water,
shall be reported and recorded. The refractory manufacturer and product name,
type of reinforcing fibers, installation location, atmospheric conditions, mixing
temperatures, installation procedures, and job site conditions shall also be
recorded. Provide the Owner or the Owner’s authorized representative with
certified copies of the quality control log.
c. Placement
(1) Application shall be made by vibracasting. The size and style of the equipment,
and the installation procedure, shall be as required for the specific refractory
lining application.
(2) Refractory shall be placed at its final location. Movement of the refractory within
the forms shall be minimized.
(3) Application by hand packing of the refractory is permitted only in limited areas
where contouring is required or where space limitations do not permit formwork
and vibracasting. Approval by the Owner is required before hand packing is
used. The refractory shall be suitable for hand-packing and shall be installed in
accordance with the manufacturer’s instructions. The refractory shall be placed in
a manner that ensures complete filling of the area to be lined, e.g., “knifing” or
puddling. Prior to installation, a mock-up shall be prepared to demonstrate that
the hand packed material is properly consolidated and flaw free. Samples shall be
taken for property testing in accordance with Paragraphs 8.3b. and 8.3c.
Troweling of the surface is not permitted.
(4) Only qualified personnel thoroughly familiar and experienced with vibracast
installation of refractory lining shall be employed for this work.
(5) The shell, form, and anchors shall be inspected to confirm that they are clean and
that all anchor caps are in place before the lining is installed. Refractory that
adhered to the shell, form, or anchors during earlier refractory installation shall be
removed before refractory is installed. Replace any missing caps. The lining
installation procedure shall not dislodge any of the anchor caps.
(6) Do not use refractory that has begun to setup or that is more than 20 minutes or
the manufacturers’ recommended working time old (whichever is less).
(7) The lining installation procedure, including vibration, shall not dislodge any
anchor tip caps. If any caps come loose, they shall be removed from the
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(9) During refractory installation the item to be lined shall be placed in a position that
provides good access for refractory placement, permits downhand refractory
installation, eliminates all enclosed or unvented areas, and permits the escape of
air during refractory vibration. If necessary, venting or installation (casting)
nozzles in the forms or shell may be considered to allow complete filling and a
high quality refractory installation. Venting or installation (casting) nozzles in
the shell shall be filled with refractory and blanked-off. Venting or installation
(casting) nozzles in the forms shall be filled with refractory to a point beyond the
lining surface. After removal of the forms, the excess refractory shall be trimmed
flush with the lining surface.
(10) The refractory shall not fall more than 6 feet (1800 mm) between the shell and the
form. When a drop of more than 6 feet (1800 mm) is required, installation shall
utilize a chute and observation/casting ports in accordance with Figure 9.
a. At least two casting ports shall be provided at each elevation. The casting
ports shall be no more than 180˚ or 6 feet (1800 mm) apart in
circumference nor separated by more than 6 feet in elevation. Casting ports
at each elevation shall be located midway between the ports at the previous
elevation.
d. The installation chute or hose length shall be vertical and as short and
straight as possible. Bends shall not interfere with the smooth, continuous
flow of refractory. The hose or chute shall completely discharge under the
influence of gravity.
(11) Refractory installation shall be continuous and uninterrupted to avoid the creation
of joints within the refractory. Refractory shall be installed around the
circumference or perimeter in a manner to raise the refractory level behind the
forms at an approximately even rate; i.e., the refractory head shall not be
significantly greater on any portion of the formwork than on any other portion.
(12) Lined items shall remain in the same position throughout lining installation and
curing unless this results in an area of inferior refractory placement. In that case
the refractory may be installed in two (or more) placements with the lined item
orientation optimized for each placement. The joint(s) between placements shall
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
be located in sheltered areas and shall comply with the requirements of Section
5.4.e. Reorientation shall not detrimentally affect the previously placed
refractory.
(13) The full refractory thickness shall be placed at each location in a single
application. The direction of placement shall be perpendicular to the thickness,
i.e., parallel to the surface being lined.
(15) Refractory shall not be placed in longitudinal strips, or in any manner that results
in continuous joints in the direction of process fluid flow.
d. Vibration
(2) The means and duration of vibration shall be based upon the methods and
procedures demonstrated during the crew prequalification (see paragraph 8.4c).
This is particularly critical for lightweight refractories, which are especially
susceptible to separation or other damage if incorrectly vibrated.
(3) Vibration shall not be used to move the refractory. Refractory shall be deposited
at its intended, final position.
(5) Vibrators shall be attached to the lined item by circumferential straps, chains or a
similar means. The straps shall be tightened to transmit the vibration around the
circumference. Do not attach the vibrator to welded lugs or attachments.
(6) The vibrators shall input a force greater than the weight being vibrated, including
the refractory, form, and shell. Vibrators shall be located so that all portions of
the refractory receive sufficient vibration energy for effective consolidation.
Each vibrator shall be independently controlled.
(8) Vibration shall begin before placement of refractory and, at each point, continue
until the refractory has been placed, has fully consolidated, and air bubbles are no
longer being released. The surface may begin to develop a slight sheen due to
water. Do not over vibrate. Lightweight refractories are especially susceptible to
over-vibration.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
e. Interruption of Application
(1) When application is interrupted before completion of the lining, sections of the
forms that are not completely filled shall be removed and the refractory lining
shall immediately be cut back to the shell between anchors with a steel trowel.
The cutback shall be made at a right angle to the shell and at a location where the
full refractory thickness has already been applied. Material beyond the cut and
material left in the chute, hose, and mixer over 20 minutes shall be discarded.
(2) Anchors and plate surfaces shall be completely cleaned of all refractory lining
materials. Replace any dislodged anchor caps.
(3) During the period of interruption in application, curing of the refractory lining
already applied shall be in accordance with Section 6.1.
(4) Immediately prior to resuming refractory application, the exposed surface of the
refractory lining to which a bond must be made shall be cleaned of all loose
refractory material and debris, roughened, and thoroughly wetted with lining
mixing water.
(5) The lining shall not be permitted to stand before heat drying when the ambient
temperature is expected to fall below 50°F (10°C), unless provisions are taken to
keep the lining above 50°F (10°C).
(6) When installation is halted for the day, all exposed surfaces of the refractory shall
be covered, and/or sealed. All openings in the item being lined shall be covered,
closed, and/or sealed.
6.1 Curing
a. The curing period shall begin immediately after installation of each section of lining
and shall last until a minimum of 24 hours after curing of the last segment of the lining
has begun. Refractory shall be cured for at least 24 hours.
(1) The lined item shall not be moved until at least 24 hours after the completion of
the refractory lining installation.
(2) During the curing period, the temperature of the vessel shell and refractory lining
shall be kept above 50°F (10°C).
b. During the curing period, exposed refractory lining shall be protected from moisture
loss by a spray applied owner and refractory manufacturer approved membrane curing
compound. Refractory surfaces covered by forms do not require additional measures
(e.g., curing compound) to prevent moisture loss. The curing compound shall be a non-
flammable, non-reactive, non-toxic, membrane forming solution of resin and
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
c. Spray application of the membrane curing compound shall begin immediately after
application of the lining, as soon as the surface is dry to the touch. A one coat
application of membrane curing compound of sufficient thickness to completely cover
the exposed surfaces of the lining shall be used. The membrane curing compound
shall be allowed to dry tack free before lining is installed in an adjoining area.
Adequate ventilation shall be provided during the membrane curing compound
application and curing period.
d. After curing and removal of the forms, the refractory lining shall be tested by striking
with the ball of a 16 ounce (455 gram) ball peen hammer at about one foot (300 mm)
intervals over the entire surface. Any voids or dry filled spaces will emit a dull sound;
the full lining depth in these areas shall be removed and replaced.
e. Refractory shall not be exposed to steam until heat drying has been completed.
a. All refractory lining shall be heat dried after removal of the forms and prior to being
placed into service. If the lining is to be subjected to hydrostatic testing, it shall be
cured and fully heat dried before and fully heat dried again after testing.
b. Heat drying shall be performed by personnel experienced in, and with the equipment
required for, heat drying of refractory lined equipment.
c. The heat drying contractor shall prepare a detailed plan for review and approval prior
to the start of heat drying (see paragraph 2.3b.). The plan shall include the heating and
cooling rates, hold points and durations, heat source(s) and location(s), the means of
monitoring refractory and shell temperatures, and the means of ensuring all of the
refractory is exposed to the dryout medium and adequately dried.
d. Heat drying of the refractory shall begin as soon after completion of the refractory
installation, the 24 hour curing period, and the removal of forms as is practical. Items
that were lined in the shop shall be heat dried in the shop. Between the end of curing
and the performance of heat drying, the refractory shall be kept above 50°F (10°C) and
shall not be exposed to moisture (e.g., rain, snow, steam, etc.) or contaminants. If heat
drying does not occur within 30 days of completion of the refractory curing period, the
equipment shall be sealed and kept above 50F (10C) until heat drying is performed.
e. Lining shall be completely heat dried and inspected prior to (and independent of)
startup of the equipment, vessels, piping, and duct work.
f. Sections that do not have the full required thickness of insulating refractory lining or
are otherwise not adequate for the maximum heat drying temperature (e.g., inadequate
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
g. Provide the heat necessary for dryout by use of gas fired heaters only. The gas supply
shall be clean, reliable, and adequate to reach and maintain the required temperatures.
h. Heat shall be applied to the exposed surface of the refractory lining only. Heaters shall
not be located inside of equipment being dried nor shall the lining be exposed to
radiant heat or flame impingement. Heat drying shall not be performed in a furnace or
as a part of postweld heat treatment. Do not insulate the outer metal surface.
i. Multiple heaters may be used to maintain the required temperatures over the entire
lining surface. If multiple heaters are used, their operation shall be coordinated so that
all hold periods and temperature changes occur at the same time and rate.
j. The flow of heated air shall be controlled so that the entire surface of the refractory is
subjected to the movement of air and the full heat drying cycle. Dead or low flow
areas are not permitted. Back pressure, throttling of the air flow, or other means may
be necessary. During heat drying the lined equipment shall be oriented to allow even
heating of the refractory (i.e., a more uniform temperature profile) and permit the
escape of moisture (steam)(i.e., eliminate trapped or enclosed areas). Vertical
positioning of the item to be dried is generally preferred. During the drying period,
adequate ventilation shall be provided for the escape of moisture. Special
consideration shall be given to areas that are difficult to dry or vent, such as refractory
lined nozzles with an interior metallic liner.
k. Interior temperatures during heat drying shall be monitored and controlled with
thermocouples placed a maximum of 1/2 inch (13mm) from the lining surface.
(1) The thermocouples shall be arranged to measure the air, not the refractory,
temperature.
(4) Thermocouples shall also be placed near the hot air inlets, the exhaust air vents,
and in the rear of any enclosed areas.
(7) The final arrangement of thermocouples and recorders shall be approved by the
Owner or their authorized representative before the start of heat drying.
n. Provide exterior skin thermocouples to monitor the exterior metal temperature during
dryout. Frequent infrared scans may be substituted for external skin thermocouples.
At a minimum, monitor the temperature in areas expected to see the greatest metal
temperature (e.g., at the hot air inlet or where the exterior of the metal is in an enclosed
or heated area). Monitor and record these temperatures in the same manner as used for
the interior temperatures.
o. Heat drying shall proceed as follows (except where the refractory manufacturer’s
recommended heat drying procedure is more stringent):
(1) Raise the temperature of the air in contact with the refractory lining at a
continuous rate not to exceed 50°F (28°C)/hour to approximately 300°F (150°C).
(2) Hold for a minimum of 1.5 hours per inch (25 mm) of lining thickness. All
thermocouples shall reach and maintain a steady temperature for a minimum of
30 minutes prior to completing the hold and proceeding with the dryout.
(3) Raise the internal temperature of the air in contact with the refractory at a
continuous rate not to exceed 50°F (28°C)/hour to approximately 700°F (370°C).
(4) Hold for a minimum of 1.5 hours per inch (25 mm) of lining thickness. All
thermocouples shall reach and maintain a steady temperature for a minimum of
30 minutes prior to completing the hold and proceeding with the dryout.
(5) Raise the internal temperature of the air in contact with the refractory at a
continuous rate not to exceed 50°F (28°C)/hour to the internal process operating
temperature.
(6) The shell temperature shall reach at least 220°F (105°C) during the final hold.
(7) Hold for a minimum of 1.5 hours per inch (25 mm) of lining thickness. All
thermocouples shall reach and maintain a steady temperature for a minimum of
30 minutes prior to completing the hold and proceeding with the dryout.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(8) After the final hold period, cool down shall be at a continuous rate not to exceed
100°F (56°C) /hour with no holds to approximately 300°F (150°C). After
reaching approximately 300°F (150°C) the remaining cool down may be without
heating.
(9) If steaming is observed during any hold period, the hold period shall be
maintained until steaming ceases.
(10) Length of the hold periods, and the overall duration of the heat dry, shall be
determined by the thickest portion of lining being dried.
(12) The shell temperature shall not exceed the design temperature of the shell.
(13) The air temperature differential between any two thermocouples within the item
being heat dried shall not exceed 100F (56C).
(14) If heat is lost, resume the dryout procedure using the heating rate specified at the
temperature at which the ability to heat is regained.
q. When heat drying is completed the lining shall be inspected and any area with full
depth cracks 1/16 inch (1.6 mm) wide and larger, non-full depth cracks 1/8 inch (3.2
mm) wide and larger, depressions exceeding 1/4 inch (6 mm) in depth or two inches
(50 mm) in any other direction, and spalling or unbonded material shall be removed
and replaced in accordance with Section 9.
r. When lining that has been in hydrocarbon operation is exposed to the heat drying of
new lining, precautions shall be taken to prevent ignition of the coke.
s. Field seams and repairs shall receive the same curing and heat drying as the remainder
of the lining.
t. Provide the Owner or the Owner’s authorized representative with certified copies of
the heat drying procedure, internal heater, recorder, and thermocouple locations, and
temperature control log.
7. INSPECTION
The Owner or the Owner’s authorized representative reserves the right to inspect the refractory
lining during all phases of preparation, application, repair, curing, heat dry, and clean-up. The
following operations shall be included in those witnessed:
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
a. Pre-installation meeting with the refractory installer to discuss the installation procedure
and any deviations from this Standard Specification or the UOP Project Specifications and
Drawings.
b. Preparation of the vessel by grit blast cleaning; welding of anchors, bars, and collars;
wrapping of paper; placing of insulation; and covering of openings.
d. Pre-installation testing of the refractory materials (if required) and pre-qualification of the
installation crew.
e. Mixing of refractory materials with reinforcing fibers and water to ensure that correct
materials and procedures are used, that containers and water are clean, and that the entire
contents of each bag is poured into the mixing machine.
f. Application of vibration to ensure that vibration is present for the proper time period,
proper vibration methods are used, the vibration is effective, the refractory is neither over or
under-vibrated, and separation or other undesirable effects do not occur.
h. Curing and heat drying of the refractory lining to ensure that the proper curing technique
and heat drying temperatures, ramps, and holds are used.
i. Removal of the forms after curing and inspection of the lining for voids or other damage.
j. Inspection of lining after curing and after heat drying to ensure no unacceptable voids,
cracks, spalling, or unbonded material is present.
k. Removal and replacement of unacceptable refractory lining to ensure that the rework is
compatible with the original lining application.
l. Copies of all logs, record of areas of refractory repair, and test reports.
m. Removal from plant site of refractory lining applicator’s equipment, materials, and debris.
Job site to be left broom clean.
The approval or acceptance of the above operations by the Owner or the Owner’s authorized
representative does not relieve the refractory manufacturer and/or refractory lining applicator of any
responsibility, warranty, or guarantee.
8. TESTING
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
a. The Owner, refractory manufacturer, and contractor (as applicable) shall agree upon
vibration cast installation based guaranteed or compliance values for all physical
properties to be tested. If guaranteed or compliance values are not specified, then the
manufacturer’s data sheet values shall be used. The results of physical property testing
shall be compared against the guaranteed or compliance values.
a. The manufacturer of the refractory materials shall provide material data sheets and test
certificates of vibration cast samples of the supplied refractory (i.e., the material to be
shipped). Sample preparation shall be in accordance with ASTM C862. Tests may be
performed by the manufacturer or a mutually agreed upon independent laboratory.
Specimen requirements (e.g., preparation, number, and shape) and testing shall be in
accordance with the ASTM Standards and modifications listed below. Except for mid-
weight insulating and erosion resistant materials, each lot or batch and every third
pallet (beginning with the first pallet) or fraction thereof of materials within each batch
or lot shall be tested. For mid-weight insulating and abrasion resistant materials, each
lot or batch and each pallet within each lot or batch shall be tested. Samples shall be
prepared from a bag of refractory randomly selected from the pallet. The entire bag
shall be used to prepare the refractory from which the samples are prepared. Testing
shall be without metal reinforcing fibers. The test certificates shall include the
following information:
(6) Bulk density (minimum of 3 specimens per sample, tested per ASTM C134 as
modified per API Standard 936), undried (green) and fired.
(7) Cold crushing strength (minimum of 3 specimens per sample, tested per ASTM
C133 as modified per API Standard 936) using 2 inch cubes.
(8) Permanent linear change (minimum of 2 specimens per sample, tested per ASTM
C113 as modified per API Standard 936)
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(9) Apparent porosity (per ASTM C 20 using one-half of the permanent linear
change specimen.)
(10) Abrasion Resistance (minimum of 2 specimens per sample, tested per ASTM
C704 as modified per API Standard 936) – Mid-weight insulating and abrasion
resistant refractory materials only
b. Tests shall be performed on samples that have been heated to 1500F (815C) and
cooled to ambient temperature. Heating shall be in accordance with ASTM C865.
d. No specimen result shall be more than 5 percent of the limiting value beyond the
minimum or maximum limiting value. All of the specimen results shall be within ± 20
percent of the average value of the sample. No more than one specimen of the sample
shall be beyond the limiting value(s).
a. Material that is more than three months old, shows evidence of minor damage or minor
moisture exposure (including any pallet from which a wet bag has been discarded, and
any other pallets stored with it.), or has been exposed to temperatures beyond the
storage limits of this specification, shall be retested approximately two weeks before
the start of the refractory installation. Material that is nine or more months old or
beyond its shelf life, if it is less than nine months, shall not be used. With the
exception of mid-weight insulating and abrasion resistant materials, prepare vibration
cast samples for testing from each lot or batch and every third pallet (beginning with
the first pallet) or fraction thereof, of refractory material within each batch. For mid-
weight insulating and abrasion resistant materials, each lot or batch and each pallet
within each lot or batch shall be tested. The samples shall be prepared from a bag of
refractory randomly selected from the pallet and shall be in accordance with ASTM
C862. The entire bag shall be used to prepare the refractory from which the samples
are made. Samples shall not include metal reinforcing fibers.
b. The samples shall be tested for bulk density (per ASTM C134), cold crushing strength
(per ASTM C133) and permanent linear change (per ASTM C113) after heating to
1500F (815C) in accordance with ASTM C865, and cooling to ambient temperature.
Mid-weight insulating and abrasion resistant refractories shall also be tested for
abrasion resistance (per ASTM C704). All tests shall be modified as noted in
Paragraph 8.2a.
the manufacturer (see Section 8.2) by more than 20 percent. If the tests do not meet
these criteria, the refractory material shall not be used.
d. Provide the Owner or the Owner’s Authorized Representative with certified copies of
the test results.
a. Each refractory installer and other members of the installation crew shall be pre-
qualified with each vibration cast refractory material before refractory installation to
ensure that proper procedures are used. Pre-qualification shall be performed at the job
site using the same equipment, materials, utilities, crew members, and installation
procedures (including vibration method (vibrator type, force, arrangement, and
attachment) and time) that will be used for the refractory lining application. A
minimum of one mock-up (see paragraph 8.4b.) shall be cast for each material to be
installed by vibration casting. Certification from a previous job or site is not
acceptable.
b. Installer prequalification shall consist of casting and inspecting a mock-up for each
material to be vibracast.
(1) The mock-up shall simulate the most difficult area to be vibracast, e.g., complex
geometry (elbows, nozzles, protrusions through the lining, tees, etc.) or poor
access (remote and confined areas, beneath horizontal forms, etc.). At a
minimum the mock-up assembly shall be a cylinder 24 inches (600 mm) OD and
36 inches (900 mm) long.
(2) The refractory thickness shall equal the lining thickness to be installed and shall
utilize the same tolerances.
(3) The mock-up shell and the forms shall be steel. Both shall be designed for
removal without damaging the contained refractory and shall be coated with a
refractory vendor approved parting agent to prevent adherence to the refractory.
The form system shall simulate the forms and form system to be used for the
lining installation.
(4) The mock-up assembly and the forms shall withstand the fluid head of freshly
placed refractory and the applied vibration without deformation or displacement.
(5) Provide anchors of the same style and spacing as will be used for the refractory
lining. Anchors shall be bolted to the mock-up assembly in a manner that permits
removal of the mock-up plates.
(6) The refractory shall be vibracast (with steel fibers if steel fibers will be used for
the installed lining) using the same installation and vibration procedures to be
used for the installed lining.
d. After curing for 24 hours (see Section 6.1), remove the forms and the mock-up backing
plates to observe the installation. Weigh the mock-up and determine the undried
(green) density. The undried (green) density shall be within ± 5 percent of the
manufacturer’s value for vibration cast samples. The intact mock-up shall be
inspected, then broken and re-inspected. Voids, spalling, laminations,
honeycombing, over compaction, uneven fiber distribution, shadowing at anchors, or
other indications of poor installation are not acceptable. Samples of the refractory
shall be tested as indicated in Section 8.3b. and 8.3c. Only if inspection of the pre-
qualification mock-up and the results of any testing are acceptable will the crew be
allowed to install the refractory lining.
a. The refractory lining installer shall prepare as-installed refractory samples on the job
site as a part of the installation process. Samples shall be prepared once per crew per
shift, for each lined item, for each continuously cast portion of the lining, for each
refractory material, and for each mixing station. The number of test boxes required on
the job site shall be agreed upon with the Owner or the Owner’s authorized
representative.
b. The samples (with reinforcing fibers) shall be representative of the installed refractory,
including casting procedures, vibration, and curing in the same manner (but not heat
drying). Use a suitably marked 4 ½” by 9” (115 x 225 mm) box of a depth equal to the
lining thickness. A standard “shoebox” {(4 ½” x 4 ½” x 12” (115 x 115 x 300 mm)} is
also acceptable. Test specimens shall be cut from the refractory block. Cast enough
boxes to provide all of the required test specimens. Alternatively, the test specimens
may be directly formed and cast per ASTM C862.
c. Boxes shall be coated with a refractory manufacturer approved parting agent to prevent
adherence of the refractory. The sample shall be cured in accordance with Section 6.1
for 24 hours. The box may be placed on the scaffolding after vibracasting but
otherwise shall remain undisturbed and protected at the installation site until curing has
been completed.
d. Marking of the refractory samples shall make it possible to identify each sample by
number; date, time, and method of application; product name and batch number of the
refractory material; location of application (e.g., sample map); steel fiber percentage;
weight percent of water added; weather; shell surface, water, material, and mix
temperatures; and name of the installer. Markings shall also indicate the front, back,
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
e. The lining installer shall keep the cured samples on site available to the Owner or the
Owner’s authorized representative, who will indicate the extent of testing to be
performed in accordance with ASTM Standards. Testing shall be in accordance with
the procedures and requirements of Section 8.3.
f. In case of disagreement on the test results, or failure to comply with the acceptance
criteria, the refractory lining applicator may remove additional samples from the
installed lining. Testing (at his own expense) shall be in accordance with the specified
ASTM Standards by a mutually agreed upon qualified independent laboratory. Any
remedial measures required as the result of testing shall be agreed upon with the
Owner or the Owner’s authorized representative.
9.1 Preparation
a. Unacceptable refractory lining shall be saw cut at a right angle to the shell the full
depth of the lining, laterally to acceptable lining, and removed. The shell shall not be
damaged. Unacceptable lining includes thin areas, severely spalled, fractured, poor
quality (e.g., soft, porous), eroded and missing lining, refractory at hot spots, and
refractory not performing its intended function. With the exception of core samples,
the minimum area removed shall be sufficient to expose at least three noncontinuous
anchors as indicated on Figure 6. Cuts shall be made midway between anchors.
Corners shall be rounded to a smooth, generous contour throughout the depth of the
refractory.
b. Small (e.g., hairline), random, cracks are not a concern nor a cause for repair. These
cracks are frequently a positive feature, indicating the lining is held tightly to the shell.
They also act as expansion joints and close as the refractory heats and expands.
Cracks larger than the limits given in paragraph 6.2q., or cracks exhibiting signs of
coking, catalyst entry or other indications they are open and allowing flow during
operation require repair.
c. Core samples shall be round, taken at a right angle to the shell, and shall extend to the
shell. The shell shall not be damaged. The shell shall be cleaned and a new anchor
installed. Caps shall be placed on the anchor tips.
d. The anchors and shell shall be cleaned of refractory, debris, loose material, or
contaminants and new caps installed on the anchor tips. If the anchors or their
attachment weld are damaged, the anchor shall be replaced.
(1) Cut the legs from the old anchor but leave the weld undisturbed.
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.
(2) If the base metal was not postweld heat treated (PWHT), weld the new anchor to
the base metal.
(3) If the base metal was PWHT and PWHT will be required if the new anchor is
welded to the base metal, consider welding the new anchor to the remnants of the
old anchor.
a. Immediately before placement of the new refractory, the joining surface of the sound
lining adjacent to the seam or repair area shall be cleaned of debris, roughened, and
completely wetted with lining mixing water prior to application of the replacement
lining.
b. Refractory lining at seams and repairs shall be performed in the same manner as the
original lining application, including curing and heat drying. The seam or repaired
area shall be fully vented to permit complete filling by the refractory and venting of
the steam produced during heat drying. If necessary, venting or installation (casting)
nozzles in the forms or shell are permissible (see paragraph 5.4c.(9)). Proposed
methods of repair shall be approved by the Owner or the Owner’s authorized
representative before repairs are started.
10. SHIPPING
10.1 Preparation
Shop installed refractory lining shall be prepared for shipment in a manner that ensures
delivery to the destination in the original cast, cured, and heat dried condition.
Distortion or deflection of the lined item may damage the refractory lining. Prevent
distortion or deflection by means of braces, truing rings, support location, proper lifting and
rigging techniques, and /or other means.
10.3 Sealing
Seal the equipment from atmospheric conditions (e.g., apply a curing compound to the
refractory surface, close and seal all openings) during shipment and storage.
Figure 1 Anchors
CONFIDENTIAL – The information in this document is confidential and must not be used for any purpose, duplicated, or disclosed to others without UOP's written permission.