Broiler Hatchery Project SMV Poultry Farm EIS Fina
Broiler Hatchery Project SMV Poultry Farm EIS Fina
Figure 1. Direct Impact Area and Indirect Impact Areas of the Project ................................................. ix
Figure 2. Regional Map showing the Project Site..........................................................................................1
Figure 3. Municipal Map showing the Project Site ........................................................................................2
Figure 4. Vicinity Map showing Project Site ...................................................................................................3
Figure 5. Project Plant Site with Geographical Coordinates ......................................................................4
Figure 6. Site Development Plan of Broiler (1 Million Egg-Capacity) Hatchery Project............................5
Figure 7. Process Flow Diagram of the Proposed Broiler (1 Million Egg-Capacity) Hatchery Project ...10
Figure 8. Existing Land Use Plan of Sta. Barbara (2014) ...............................................................................17
Figure 9. Proposed Land Use Plan of Sta. Barbara (2011-2021) ................................................................18
Figure 10. Soil Map of the Municipality of Sta. Barbara .............................................................................23
Figure 11. Climatological Map of the Philippines ........................................................................................29
Figure 12. Maps Showing the Projected Seasonal Temperature Increase (in°C) ....................................30
Figure 13. Maps Showing the Projected Rainfall Change (increase/decrease) in % .............................31
Figure 14. Age and Sex Distribution of Population, 2007 .............................................................................42
Figure 15. The Environmental Risk System of Proposed Broiler (1 Million Egg-Capacity) Hatchery
Project ...............................................................................................................................................................48
Figure 16. The Broiler Hatchery Project’s Environmental Unit Organizational Chart ...............................68
List of Tables
EXECUTIVE SUMMARY
Project Fact Sheet
Project Category and Type Livestock Animal Industries – Broiler Hatchery Project
                                                                                                     iv
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
 Project Components
            Facilities                 No. of Units      Area/Capacity        Specifications/Description/Remarks
 Hatchery Building                          1            1,524.03 sq.m.      with a capacity of 1 Million Eggs per
                                                                             harvest
   ➢ Egg Room                                3
   ➢ Setter Room with twelve                 1                               with twelve (12) units Setter Machine
     (12) units Setter Machines
   ➢ Hatchery Rooms with
     twelve 12 units Hatchery                                                with twelve (12) units Hatchery
     Machines                                2                               Machines
   ➢ Clean Room
   ➢ Chicken Pull-out and Wash               1
     Room
   ➢ Chicken     Holding    and              1
     Processing room
                                             1
 Staff House/Shower                          1
 House/Mess Hall/Common Area
 Guardhouse/Waiting                          1           150 sq. meters
 Area/Receiving Trucker’s
 Lounge
 Office Building                             1           180 sq. meters
 Generator set/Transpad Area                 1           200 sq. meters
   ➢ Diesel Generator Sets                   2           175 kVA each
Process Documentation
    ➢ Review and gathering of relevant data for the four modules (Land, Air, Water and People) to be
      incorporated in the EIS Study.
                                                                                                                 v
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    ➢ Establishment of baseline environmental conditions and preparation of the EIS Report based on the
      Revised Procedural Manual for DENR Administrative Order No. 30, Series of 2003 and EMB Memorandum
      Circular No. 005, Series of 2014
EIA Team
The proponent has hired the services of an Environmental Consultant, Engr. Darrell A. Palabrica, an environmental
engineer who has gained his experience in environmental impact assessment, solid waste management, water
pollution management and toxic and hazardous waste management at the Environmental Management Bureau –
DENR Region VI. He has been with this National agency for more than 18 years. He was previously designated as
the OIC- Chief of the Environmental Impact Assessment Division. There were also the representatives of the
proponent, Mr. Romeo Felicano D. Licup who in one way or another have greatly provided the data and
information about the proposed project that were needed for the inclusion to the EIS Report.
Upon agreement with the proponent for the preparation of the said report, the environmental consultant has
initially requested/gathered the pertinent documents such as site development plan of the whole project, list of
equipment and its support facilities, survey plan, transfer certificates of title, lease agreement, zoning certificate
from deputized zoning administrator, vicinity map and other related documents for the project. It is within this
stage that the preparer could have a macro point of view on the project and relate the possible impacts that the
project might generate. Hereunder is the EIS Schedule for the proposed Broiler (1-Million Egg Capacity) Hatchery
Project of SMV Agro Industrial Corporation.
Activities Timeframe
                                                                                                                    vi
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Activities Timeframe
A new mandate was made by EMB Central Office wherein the old processing of the EIS-based was reverted back,
so all EIS-based projects will now undergo the third-party review process and will follow the previous processes
wherein there are the IEC activities and the scoping process before the series of reviews will be undertaken. This
has lengthened the number of days in processing the request for an ECC. As part of the IEC program of the
proponent it was able to conduct posting of project information to the areas (bulletin boards) of the identified
stakeholders. Officially these were received by the stakeholders and received copies have served proof that an
IEC activity was undertaken before the request for a Technical and Public Scoping. The same IEC materials were
furnished to EMB R6 as requirements for the scheduling of the scoping process. Annex A presents the IEC
Materials that were submitted to EMB R6.
Due to the enhanced community quarantine which was implemented nation-wide to address the spread of COVID-
19, the conduct of the public scoping and public hearing was based on EMB Memorandum Circular No. 2020-30
“Interim Guidelines on Public Participation in the Implementation of the Philippine Environmental Impact
Statement System (Pd 1586) During the State of National Public Health Emergency”. The proponent opted for the
conduct of these activities through Consultation through online channels such as video conferencing, webinar,
etc.
The EIS Report must include in its discussion the direct and indirect impact areas of the project and its proposed
operation and processes.     The delineation of the impact areas will be based on both social and technical
considerations. The Direct Impact Area (DIA) will be project site and the Indirect Impact Area (IIA) on the other
hand will be temporarily designated to be the area 1-km radius from the center of the identified DIA. Figure 1
presents the Direct Impact Areas and the Indirect Impact Areas
                                                                                                               vii
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The possible impacts of the whole project are not only contained to this primary and secondary impact areas but
is also included in the regional impact zone (RIZ), this is where the zone that the impacts of the project could still
be felt.
EIA Methodology
Upon agreement by the environmental consultant and the proponent to process for the ECC, the initial step was
to gather information about the proposed project.
The Revised Procedural Manual for DENR Administrative Order 30, Series of 2003 was used as the basis in coming
up with the required documents. Based on this guideline, the consultant utilized the checklist (Annex 2-1a) to
determine the extent of coverage of the project to the Philippine EIS System. This was made as a self-screening
tool and it contains the list of all requirements to effect an application to the Philippine EIS System. It will further
fall under the category of Group II Livestock Industries – Broiler Hatchery Project. This kind of project is considered
as a Non-Critical Project located in an Environmental Critical Area. An Environmental Impact Statement (EIS) must
be prepared as a requirement for the issuance of the ECC.
                                                                                                                    viii
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                                                                                 Indirect Impact
                                                                                                                      Area
Figure 1. Direct Impact Area and Indirect Impact Areas of the Project
                                                                                                                                     ix
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
An initial assessment has already been made basing on the submitted documents. The possible impacts made
by construction and operation of the hatchery project have been identified and these impacts will be further
reassessed upon the conduct of the field reconnaissance. One of the major concerns of the consultant is on
the washwater during the maintenance of the egg trays and other hatchery equipment. There is also the
volume of sewage water from the workers/personnel during construction and operational phases. Solid
wastes generated such as broken egg shells will be the majority of wastes that will be generated during the
operational phase of the project.
A field reconnaissance at the project site was conducted to gather the secondary data. This activity is also
undertaken to determine whether the proponent has started the proposed project and to relate the possible
identified impacts to the existing environmental scenario. Other existing information surrounding the project
were noted and observed as well. The gathering of such information will serve as supplemental reference to
some of the results that were being gathered as baseline/sampling data.
The preparation of the EIS Report has taken approximately 10 weeks incorporating all the data and
information that were gathered, the identification of possible impacts both positive and negative, the
mitigating measures that will be recommended for the proponent to undertake so that it can minimize the
adverse impacts of the project, and the updated environmental management and monitoring plans that will
be conducted after the issuance of the ECC.
Based on the Revised Procedural Manual for DAO 03-30, the proponent submits one copy of the EIS to EMB-
R6 for procedural screening within a timeframe of 3 days the document should be validated for the screening
process and completeness of the EIS Report to ensure the information is sufficient to make a decision on the
application. Five (5) hard copies of the EIS Report and a CD copy will be submitted to EMB R6. The EIS
Document will undergo the review process with the third-party EIA Review Committee.
Summary of the EIA Findings on the Key Significant Impacts of the Project and Corresponding EMP Highlights
The Revised Procedural Manual for DENR Administrative Order No. 30 Series of 2003 which serves as the
guideline has provided information that the study must cover the total operation of the project with specific
discussions on the construction and operational phases. Based on the information which includes the
secondary data that were gathered there are four aspects of the environment that will be affected by the
project, namely: Land, Air, Water and People. The impacts that are identified vary from each aspect of the
environment and these will be discussed thoroughly in Chapter 3 of this study. The key significant impacts of
the project will focus on the pre-construction, construction, operational and abandonment phases of the
project.
On the land environment, there will be the generation of solid wastes (egg shells, dead chicks, cartons and
crates) and other undesirable wastes generated by the project. For the water environment there will be
generation of wastewater and if improperly managed and disposed could create detrimental impacts to the
environment. It will also create a competition between different users of the said underground aquifer where
                                                                                                           x
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
the source of water will be taken. The project will have an impact on the air environment through the fossil
fuels (diesel) that are being combusted by the generator set during operational phase and airborne dust
emission from the areas that are being developed/constructed. These impacts could particularly affect
directly the personnel/staff and workers of the project and adjacent areas
On the socio-economic environment, there will be more of positive impacts such as provision of job
opportunities to host barangay and contribution to the increase in taxes through local revenues. The aspect
on the health and safety of the personnel and workers that will be directly affected during the construction
and operational phases are also considered. There is also the identification that one of the possible impacts
that will be generated by the project will be increase in traffic at the area due to the numerous hauling trucks
that will ply in the area.
Summary of the Environmental Management and Monitoring Plans on the most significant impacts and key
measures
In Chapter 4 there is the detailed presentation of the Impacts Mitigation Plan which is the result of the
gathered information of the project and the identification of the key significant impacts of the project. The
identification of the key significant impacts in Chapter 3 will provide the proponent a guide to come up for an
effective impact mitigation plan. The updating of the Environmental Monitoring Plan will further help the
proponent and other concerned stakeholders to have a guide on what parameters and monitoring activities/
schemes should be undertaken in certain key significant impacts. The activities in the monitoring plan will
help provide information later on if the proponent has indeed complied with the requirements as set forth in
the issued ECC.
                                                                                                              xi
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental Aspects           Potential Impacts           Mitigating Measures to be Implemented                   Responsible Party
        per Project Phase
 Construction Phase
            Land                Generation of Domestic and     •    Proper collection and disposal of solid wastes       Proponent/Contractor
                                Construction Wastes            •    Provision of garbage bins especially at the
                                                                    resting/eating areas of the personnel/staff and
                                                                    workers adopting the concept of segregation at
                                                                    source
                                                               •    Good housekeeping must be implemented at all
                                                                    times
                                                               •    Excavated soils from the construction of the
                                                                    structure’s foundation should be properly
                                                                    stockpiled and disposed of properly
            Water               Domestic Effluents generated   •    Provision of portable toilet facilities and timely   Proponent/Contractor
                                by Personnel/Staff and              disposal of the generated wastes
                                Workers                        •    Include in the conditions that contractor should
                                                                    provide portable toilets for its workers
              Air               Air Pollution (Generation of   •    Provision of masks or improvised masks to            Proponent/ Contractor
                                Particulate Matter )                workers to minimize inhalation of dust emission
                                                                    during the activities.
                                                               •    Regular spraying of water at dusty areas where
                                                                    airborne dust emission usually occurs
                                                               •    Limit clearing to the areas that need to be
                                                                    developed.
                                                                                                                                                 xii
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental Aspects           Potential Impacts            Mitigating Measures to be Implemented                 Responsible Party
        per Project Phase
                                                                •    Trucks hauling the construction materials
                                                                     should be properly covered with tarpaulin
                                                                     especially those bringing materials that could
                                                                     generate airborne dust emission
                                                                •    Speed limit at the plant’s site should be 15-20
                                                                     kph.
                                                                •    Regularly clean roads utilized in the delivery of
                                                                     construction materials to avoid fallen earth
                                                                     spoils
                                                                •    Implement the proper Traffic Management
                                Generation of Noise Pollution
                                                                     Scheme at the area.
  Socio-Economic (People)       Job Opportunities               •    Prioritize the hiring of people depending on        Proponent/Contractor
                                                                     their skills at the host barangay
                                                                                                                                                xiii
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental Aspects              Potential Impacts       Mitigating Measures to be Implemented                Responsible Party
        per Project Phase
                                                              •    Provision of adequate signage or warning signs
                                                                   to those areas where there are on-going
                                                                   construction activities
                                                              •    Provision of Personal Protective Equipment
                                                                   (PPEs) to all personnel and workers
 Operational Phase
           Land                 Generation of Solid Wastes    •     Proper collection and disposal of solid wastes        Proponent
                                                              •    Provision of garbage bins especially at the
                                                                   resting/eating areas of the personnel/staff and
                                                                   workers adopting the concept of segregation at
                                                                   source
                                                              •    Good housekeeping must be implemented at all
                                                                   times
                                                              •    Hazardous wastes such as busted fluorescent
                                                                   lamps, lead compounds (e.g. lead acid
                                                                   batteries), empty paint containers, and other
                                                                   miscellaneous wastes shall be properly stored
                                                                                                                                           xiv
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental Aspects           Potential Impacts          Mitigating Measures to be Implemented               Responsible Party
        per Project Phase
                                                                   on-site and transported by accredited
                                                                   transporter/treater of said wastes.
            Water               Sewage Effluents from the     •    Provision of toilet facilities with septic tanks      Proponent
                                Personnel/Staff and Workers        and proper and timely disposal of the
                                                                   generated wastes.
                                                              •    Provision of a comprehensive drainage plan for
                                                                   sewage and surface runoffs
Proponent
                                                                                                                                          xv
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental Aspects              Potential Impacts           Mitigating Measures to be Implemented                Responsible Party
        per Project Phase
              Air               Air Pollution                 •        Proper and regular maintenance of the air              Proponent
                                                                       pollution source and control equipment (i.e.
                                                                       generator set and smokestacks)
                                                              •        Provision of adequate smokestack and air
                                                                       pollution control devices.
  Socio-Economic (People)       Job Opportunities                 •     Prioritize the hiring of people depending on          Proponent
                                                                        their skills/expertise at the host barangay
   Key Environmental Aspects           Potential Impacts         Mitigating Measures to be Implemented             Responsible Party
        per Project Phase
 Abandonment Phase
         Land                   Generation of Solid Wastes   •    Proper collection and disposal of solid wastes      Proponent
                                                             •    Reuse materials that can be utilized for other
                                                                  purposes
                                                             •    Good housekeeping must be implemented at
                                                                  all times
                                                                                                                                       xvii
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental            Potential             Parameter to                   Sampling and Measurement Plan               Lead Person          Estimated
          Aspects               Impacts Per            be Monitored      Method              Frequency            Location                                Cost
     per Project Phase          Envt’l Sector
 I. Construction Phase
           Land          •   Generation of            Proper area for   Inspection         Quarterly (until      Project Area       EU/PCO           Included in the
                             Domestic and             disposal of                        construction phase                                         Construction Cost
                             Construction Waste       construction                           is finished)
                                                      wastes
         Water           •   Release of Domestic      Check provision   Inspection         Quarterly (until      Project Area    EU/Contractor       Included in the
                             Sewage                   of portable                        construction phase                                         Construction Cost
                                                      toilets                                is finished)
          Air            •   Airborne Particulate           TSP         Ambient Air      Semi-annual (until      Project Area       EU/PCO           Incorporated in
                             Emissions from the                          Sampling        construction phase                                         the Construction
                             clearing of the areas                                         is finished or as                                              Cost
                             and paved roads                                             mandated by EMB
                             utilized by hauling of
                             construction materials
         People          •   Job Opportunities        No. of local      Checking of         Semi annual          Project Area   EU/Administrative    Included in the
                                                      people hired        records                                                    Office         Construction Cost
                         •    Health and Safety of    Health and        Checking of          Quarterly           Project Area       Safety           Included in the
                              Workers                 Safety program      records                                                 Department        Construction Cost
                                                      Accidents/Near
                                                      misses
                                                      experienced
                                                                                                                                                                   xviii
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental            Potential              Parameter to                      Sampling and Measurement Plan                    Lead Person      Estimated
         Aspects               Impacts Per             be Monitored        Method               Frequency              Location                               Cost
    per Project Phase          Envt’l Sector
         Water          •   Release of Domestic       Check provision     Inspection           Semi annual           Project Area           EU/PCO       Included in the
                            Sewage                    of toilet                                                                                         Operational Cost
                                                      facilities with
                                                      septic tanks
                        •   Contamination of          TSS, fluoride,    Grab Sampling        Semi annual or as   All                        EU/PCO       Included in the
                            nearby water bodies       pH, iron and      on the                agreed by EMB      identified/established                 Operational Cost
                                                      chloride          established                              stations that are
                                                                        stations of RIS                          being monitored by
                                                                        Sta. Barbara                             the Proponent
                                                                        leading to River
                                                                        and regular
                                                                        effluent
                                                                        sampling.
                        •   Effluent sampling         BOD, TSS, Total   Grab sampling       Semi annual or as    After the Wastewater
                                                      Coliform,                             mandated by EMB      Treatment Facility
                                                      Ammonia and
                                                      Phosphate
          Air           •   Emissions from the         TSP and PM10       Ambient Air        Semi-Annual or as    Generator Set Area        EU/PCO       Included in the
                            burning of fuel for the                        Sampling          mandated by EMB                                            Operational Cost
                            operation of the plant
        People          •   Job Opportunities         No. of local        Checking of          Semi annual           Project Area           EU/PCO       Included in the
                                                      people hired          records                                                                     Operational Cost
                                                                                                                                                                       xix
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
   Key Environmental           Potential            Parameter to                   Sampling and Measurement Plan             Lead Person      Estimated
         Aspects              Impacts Per           be Monitored      Method              Frequency            Location                          Cost
    per Project Phase         Envt’l Sector
                                                   Health and        Checking of          Quarterly           Project Area     EU/PCO       Included in the
                        •   Health and Safety of   Safety program      records                                                             Operational Cost
                            Personnel/Staff
                                                   Accidents/Near
                                                   misses                                                                      Safety
                                                   experienced                                                               Department
 IV. Abandonment
 Phase
         Land           •   Generation of Solid    All wastes must   Inspection             Once              Project Area     EU/PCO      Abandonment
                            Waste                  be disposed                                                                             Cost
                                                   properly
                                                                                                                                                          xx
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
SMV Agro Industrial Corporation (SAIC) will construct and operate a broiler hatchery (1 million egg -capacity)
project to address the demand of broiler poultry growers for quality chicks. The project will be located at Lot 3951
-A (portion of Lot 3951) (TCT No. T-180,017), Brgy. Lanag, Sta. Barbara, Iloilo. It will have a total project area of
11,892 square meters. The project site is being leased by the proponent from Heirs of Feliciana Licup for a period
of ten years starting from June 2020.
Annex B presents the Transfer Certificate of Title and Contract of Lease (Landowner and SMV Agro Industrial
Corporation). Figures 2, 3, 4 and 5 present the Regional and Municipal Maps and Vicinity Map showing the
Project Site and Site Development of Proposed Broiler (1 Million Egg-Capacity) Hatchery Project, respectively.
Figure 5 and Table 1 present the corner point coordinates of the project area.
According to the Philippine Statistics Authority (PSA), the chicken industry accounted for 14.72% of the total value
of agriculture output, equivalent to P25.941 billion, in the third quarter. In the third quarter of 2017 and 2018,
the industry accounted for 13.27% and 13.96%, respectively.
Volume of production grew 8.48% to 465,150 metric tons (MT) during the third quarter of 2019. The PSA noted
that increased production was brought by increased demand as consumers shift from pork to chicken due to the
African Swine Fever (ASF) outbreak.
In 2019, the total number of chickens in poultry farming in the Philippines was around 186.4 million heads. The
entire inventory of chickens in the Philippines has increased over the last ten years.
Based on the performance of Philippine Agriculture (for January to March 2019), poultry output which contributed
16.74 percent to the total agricultural production registered a 5.41 percent increment in the first quarter of 2019.
                                                                                                        1|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The aggregate chicken demand is projected to increase from about 1.4 million MT in 2017 to 1.6 million MT in
2020 to about 1.8 million MT by 2023.
The demand for chicken meat has increased in the previous years which opted businesses to focus in broiler
poultry projects. However, due to the regular demand of poultry in the market, the broiler poultry growers are
facing some shortages in the supply of one-day old quality chicks in the market which prompted others to focus
in the hatchery production of broiler chicks. It is within this premise that the proponent plans to construct and
operate a broiler hatchery project to compensate the demands for quality one-day old chicks.
                                                                                                     2|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Project Site
                                                                                                     1|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Project Site
                                                                                                     2|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Project Site
                                                                                                    3|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                                                                          4|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                                                                                       5|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Preliminary planning for the location of the proposed project site was considered by the proponent. The following
criteria in the selection of the project site was based on the following:
        •     The proposed area should be strategically located near the existing poultry breeder’s farms which
              could be of make a great impact in terms of hauling of the eggs to the hatchery project;
        •     The project area is accessible from the business stand point of the proponent;
        •     The project area should have sufficient space for the components of the hatchery project with its
              support facilities; and
        •     The project area is zonified as agricultural and project is allowed to be operated at this area.
The property of the Licup Family (Heirs of Feliciana Licup) located at Brgy. Lanag, Sta. Barbara would fit the above-
mentioned criteria. Furthermore, the project site has been an idle lot which was not utilized by the family. It would
be an additional cost if the project will be located in another place so the proponent opted to utilize this area as
the project site for the proposed hatchery project.
Technology Alternatives
In terms of technology alternatives, the proponent will still be utilizing the concept of hatching the chicks using the
artificial process of incubation (utilizing the machine incubators to hatch the fertile eggs). Due to the desired
output of a large volume of one-day old chicks to be produced, the proponent opted to operate the state of the
art equipment in incubation. These involve the acquisition of egg setters and incubators/hatchery machines.
Proper acquisition of the equipment and management process will also produce a high efficiency of one-day old
chicks.
The proposed Broiler (1 Million Egg-Capacity) Hatchery Project will have the following major components and
support facilities:
                                                                                                          6|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
 Staff House/Shower                 1                200 sq. meters         This building is intended for the staff
 House/Mess                                                                 that are on break where they could
 Hall/Common Area                                                           rest and eat.
 Guardhouse/Waiting                 1                150 sq. meters         This building will house the security
 Area/Receiving Trucker’s                                                   guards on duty and will serve as a
 Lounge                                                                     lounge for the drivers hauling the
                                                                            eggs to be processed and the one-
                                                                            day old chicks
 Office Building                    1                180 sq. meters         This building will be intended for the
                                                                            offices of the accounting and
                                                                            marketing section. All transactions
                                                                            will be undertaken in this building.
 Houses                                              445 sq. meters         These will accommodate the staff
                                                                            and workers living at the project
                                                                            site.
 Generator set and                  1                200 sq. meters         This area will house the Two (2)
 Transpad Area                                                              units Diesel Generator Set (175 KVA
                                                                            each).
 Wastewater Treatment               1                                       This will treat all the domestic and
 Facility                                                                   other wastewater (washings from
                                                                            cleaning of egg trays) prior to
                                                                            discharge to the nearby irrigation
                                                                            canal leading to the Tigum River.
The sources of eggs intended for hatching will come from two sources, namely: the Luzon Breeder Farms and the
Vismin Breeder Farms. The eggs will be transported to the hatchery plant through shipping by sea or through land
transport.
                                                                                                      7|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
From the sources of breeder egg farms, the eggs will be prepared upon arrival at the hatchery plant with the
following activities:
                   ➢ Egg Receiving
                   ➢ Egg Preparation
                   ➢ Incubation
                         ▪ Setting Activity
                         ▪ Transfer Activity
                   ➢ Chick Pull-out
                   ➢ Chick Processing
                   ➢ Chick Dispatching and Delivery
Egg Receiving
Prior to unloading of the eggs from the van, the receiving party (proponent) must ensure that temperature of the
van is monitored to its desired setting and proper documentation will be done. After checking the van’s
temperature, it would unload the eggs at the egg rooms for initial inspection.
In this activity there will also be the verification of actual volume delivered versus records. There will be recording
of any discrepancies and/or observations being encountered during the receiving of the eggs.
Egg Preparation
At the egg rooms there will be the preparation of the eggs. It will undergo the grading and re-traying, grouping
(as to its sizes), tagging (this is to ensure the receiving day and the day it will start its incubation period). During
the grouping of the eggs, all undersize (eggs falling under the small sizes and below) and oversize eggs (jumbo sizes
and up) will be collected by the contractor. There is also the setting or the report preparation providing for the
details of the eggs to be incubated. Lastly, there will be disinfection process in order to eliminate or kill
microorganisms on the surface of the eggshell.
Incubation
Setting Activity
It is in this phase that the eggs after proper preparation will be placed in a setter machine for the setting activity.
There will be tray assignment and setting for the eggs that are ready for the setter machines. It would take 18 days
(day 1 to day 18) for the eggs to be transferred to the hatcher machines.
There is also the monitoring of the setter temperature to ensure that it is within the prescribed settings. The
optimum temperature for chicken egg in the setter (for first 18 days) ranges from 99.50 to 99.75° F and in the
hatcher (last 3 days) is 98.5 ° F. Other activities during the setting activity period are candle lighting (to check if
the eggs are fertile), cleaning and disinfection. Unfertilized eggs identified during the candling activities are
collected by the contractor and removed immediately from the hatchery plant
The eggs from the setter machines are pulled out for transfer. It will be in this activity that there will be the
designation of eggs to its hatcher machine assignment. After the 18-day period at the setter machines the eggs
are transferred to the hatcher machines for the final phase of the incubation. It would take about three days
                                                                                                           8|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
before the eggs are hatched at the hatcher machines. Unhatched eggs, egg shells and dead chicks are immediately
collected by the contractor and removed from the hatchery plant.
Other activities that would be undertaken during this phase are the segregation and recording of gas eggs, cleaning
and disinfection and monitoring of hatcher machine’s temperature.
Chicks Pull-out
In this activitiy, there is now the pulling out and checking of the chicks from the hatcher machines. The newly
hatched chicks will be placed in the chicken pull-out and wash room for initial inspection. The hatcher machines
after being utilized will be cleaned and disinfected.
In every harvest there is always the mortality of some of the chicks, these dead chicks are properly collected and
disposed to third party buyers (serves as feeds for the catfish production).
The egg shells are properly collected as well and disposed by an accredited third-party waste collector.
The pulled-out chicks will be transferred to the Chicken Holding and Processing Room.
In the event that there are circumstances that would be experienced during the dispatching and delivery of the
one -day old chicks (such as typhoons), the washroom and clean room section of the hatchery plant will be utilized
to accommodate the chicks (for about one week).
Chick Processing
The activities to be undertaken in this phase are the following: grading, counting and packing; vaccination, tagging
and grouping; and the preparation of the preparation of the chick output record.
The grading of the chicks will involve the selection of the chicks that will be sold directly to the commercial
consumers and grower/breeder farms and those that are grade-out chicks to the sales shed.
Hatchery Level
At the hatchery plant there will be the preparation of the delivery documents, checking of the chick van condition,
loading of day-old chicks, and guard’s inspection and sealing of van. The one-day old chicks will be placed in a
plastic container with a capacity of 100 heads. These plastic containers have a product lifespan of five years and
will be reused for the operation. Prior to the loading of the chicks these plastic containers and vans are cleaned
and disinfected.
Farm Level
Once the chicks are delivered to the farm the following activities must be first undertaken to ensure the proper
turn over of the chicks:
Figure 7 presents the Process Flow Diagram of the Proposed Broiler (1 Million Egg-Capacity) Hatchery Project.
                                                                                                       9|Page
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Figure 7. Process Flow Diagram of the Proposed Broiler (1 Million Egg-Capacity) Hatchery Project
                                                                                                                               10 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The whole project will get its needed power requirements from Iloilo Electric Cooperative 1 (ILECO 1). The
projected power consumption of the project averages monthly to about __________kwh.
To further ensure that there will be sufficient power supply, proponent will provide two (2) units of 175 kva
Diesel Generator Set each. These generator sets would augment the power needed by the project in the
event that there will be occurrences of power failures.
The water consumption of the proposed project is estimated to be 15 cubic meters per month, this water
requirement will cover the domestic needs of the staff/workers and the washing/cleaning of trays for the
setter and hatcher machines. The source of the water that will be needed for the project will be a deep well
located within the project site.
The plant will have only two (2) units air pollution source and control equipment:
The hatchery plant will be provided with a three-chambered septic tank with a dimension of 2.4 m x 3.05 m x
6.35 m (with a capacity of 46.482 cu. meters). All domestic and other wastewater discharges (washing from
the trays for the setter and hatcher machines) will undergo treatment to this facility before it will be
discharged to the irrigation canal.
An area will be provided at the project site for the generated hazardous wastes such as Used lead acid
batteries from Gen Set and Vehicles, Busted bulbs (mercury based), Used oil from generator set and vehicles,
and Waste Electrical & Electronic Equipment. This area is separated from the materials recovery facility and
proper care and storage of these hazardous wastes will be implemented by the management. Proper labeling
is also done on each hazardous waste and unauthorized personnel are not allowed to enter that area.
                                                                                               11 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
For the purpose of discussion, the pre-construction, construction, operational and abandonment phases are
discussed thoroughly in this section.
1.7.1 Pre-construction
This is the first phase of the project which involves the preparation of the feasibility study, water treatment
design, booster and reservoir design, transmission main design, survey plan, site development plans and
vicinity map. It is also in this phase that the necessary clearances from different government agencies (local
and national) are usually secured before the commencement to the next phase
1.7.2 Construction
The construction of the Proposed Broiler (1 Million Egg-Capacity) Hatchery Project would take about 266 days
or 11 months after which the commissioning phase will follow for a month.
1.7.2.1 Post-Construction
This is the period wherein the construction phase has just finished and the period for which it is entering the
operational phase of the project. During this phase the proponent will facilitate the disposal and possible
reuse of construction materials that were utilized. There is also the removal of heavy equipment and
rehabilitation/landscaping of the project area.
1.7.3 Operation
Discussion on the operational phase could be found in Section 1.5 Process Technology Options of this report.
It is during the operational phase that there will be job opportunities that will be provided due to the project’s
manpower requirement. These people will be provided with the mandatory benefits as provided by law. The
project will eventually generate some environmental impacts such as the increase in volume of solid waste
and wastewater generation.
1.7.4 Abandonment
The proposed project is not expected to be abandoned in the nearest foreseeable future, instead it will be
maintained and operated as long as necessary. Life of the project is around 15 years with another 5 years
with the proper maintenance of its equipment.
In case of abandonment due to decommissioning, removal of equipment and rehabilitation of the project site,
the Proponent will allocate sufficient time and resources for proper decommissioning of its project and its
support components. Decommissioning activity shall be done by phases to ensure orderly and proper
removal of the structures, facilities, equipment and residual wastes.
The Abandonment Plan, in case there is, shall be submitted by the Proponent to proper authorities such as
the EMB-DENR for approval six (6) months before the planned abandonment/decommissioning.
1.8 Manpower
Manpower Requirements
The construction and operation of the proposed project is estimated to utilize at a maximum manpower
requirements per phase is presented below:
                                                                                                    13 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Annex C presents the manpower requirement (construction and operational phases) of the Broiler (1 Million
Egg-Capacity) Hatchery Project
The total project cost of the proposed project is estimated to be PhP 8,625,098.71.                  Annex D
presents the breakdown of the project investment cost,
                                                                                                 14 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
It is 15.7 kilometers north or a twenty-minute drive from the City of Iloilo, through a well-maintained
asphalt/concrete national highway. It is accessible by any land transportation with the presence of a national
highway, provincial, municipal and barangay road networks cutting and criss-crossing its environs.
Data from the Municipal Government of Sta. Barbara showed that for the existing and proposed land use plan
of the municipality for the period 2011-2021 the majority of the land areas are still zonified under the
agricultural lands having an area of 10,508.760 hectares for the existing and proposed land use for agricultural
purposes has downed to 9,737.930 hectares. This is followed by residential with 1,694.994 hectares for the
existing and the proposed residential land use is 1,903.260 hectares. There are additional categories that
                                                                                                  15 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
were included in the proposed land use plan of the municipality such as mixed used development complex,
new town development, recreational adventure tourism, eco-adventure park, economic zone and socialize
housing project.
Table below presents the 2011-2021 Existing and Proposed Land Use Plan of the Municipality of Sta. Barbara.
Table 2. Existing and Proposed Land Use Plan of the Municipality of Sta. Barbara (2011-2021)
                                                    EXISTING                      PROPOSED
       Land Use Classification        Area (HAS.)       % Total Land     Area (HAS.)     % Total Land
                                                        Area                             Area
                                                                                                    16 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                        EXISTING                      PROPOSED
          Utilities                                 20.018           0.152          21.968       0.167
          Bodies of Water                          153.349           1.162        153.349        1.162
          Total                                   13,196.00            100       13,196.00        100
     Source: Ecological Profile of Sta. Barbara
There is no inconsistency in the land use of the project site. A locational clearance was granted per Local
Zoning Board Adjustment and Appeals (LZBAA) Resolution No. 03-2020 for the project which was issued by
the Zoning Administrator Designate of the Municipal Zoning Administrator of Santa Barbara.
Figures 8 and 9 present the Existing Land Use Plan (2014) and Proposed Land Use Plan (2011-2021)
                                                                                                   17 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                                                                18 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
 2    Areas set aside as Aesthetic potential tourist spots           No   The project area is not a
      aesthetic potential declared and reserved by the                    declared as a potential
      tourist spots;      Department of Tourism (DOT)                     tourist spot declared by
                          or other appropriate authorities                DOT.
                          for tourism development.
 3    Areas          which     This refers to areas considered       No   The project area could not
      constitute         the   as wilderness areas and areas              be considered as an area
      habitat for any          identified by the Protected and            for the habitat of any
      endangered          or   Wildlife Bureau (PAWB) to be               endangered or threatened
      threatened species       natural habitats of endangered             species of Indigenous
      of        indigenous     or      threatened, rare and               Philippine Wildlife.
      Philippine Wildlife      indeterminate species of flora
      (flora and fauna);       and fauna.
 4    Areas of unique          Areas which are more than 100         No   There are no areas of
      historic,                years old and declared by the              unique             historic,
      archaeological, or       National      Institute, National          archaeological or scientific
      scientific interests;    Museum           or      National          interests that could be
                               Commission for Culture and                 found at the project site.
                               Arts, through national or local
                               laws or ordinances as areas of
                               cultural, historical and scientific
                               significance to the nation.
 5    Areas which are          All ancestral lands of Natural        No   The project area is not
      traditionally            Communities identified in P.D.             occupied   by      cultural
      occupied by cultural     410 and settlements designed,              communities or tribes
      communities       or     implemented and maintained
      tribes                   by the PANAMIN for national
                               minorities (non-Muslim tribes
                               referred to in P.D. 719) as may
                               be amended by Republic Act no
                               8371 The Indigenous People
                               Rights Act of 1997 and its IRR.
                                                                                             19 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                                                         20 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                      Volcanology        and
                                      Seismology (PHIVOLCS)
                                      as Permanent Dange
                                      Zone as well as areas
                                      delineated to be prone
                                      to pyroclastic flow
                                      hazard,    lava   flow
                                      hazard, lahar hazard
                                      and other volcanic
                                      hazards.
 7    Areas with critical This refers to all lands with           No    Project area is flat and do
      slopes              slopes of 50% or more classified              not have slopes of 50% or
                          determined from the latest                    more
                          official topographic map from
                          NAMRIA.
 8    Areas classified as Refer to lands that can be used         No    Project area is not
      prime agricultural for     various     or     specific            considered as a prime
      lands;              agricultural activities and can               agricultural land
                          provide optimum sustainable
                          yield wit minimum inputs and
                          development         costs      as
                          determined by the Department
                          of Agriculture, NIA or concerned
                          LGU through their zoning
                          ordinances.
 9    Recharged areas of Recharged areas of aquifers              No    Project Area does have any
      aquifers           shall refer to sources of water                recharged aquifers
                         replenishment where rainwater
                         or seepage enters the aquifers.
 10 Water bodies              All natural water bodies (e.g.      Yes   Project is adjacent to the
                              river, lake, bay) that have been          Tigum River.
                              classified or not
                                                                                          21 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The project falls within an Environmentally Critical Area as defined in the DENR Administrative Order No, 30,
Series of 2003 (Implementing Rules and Regulations of Presidential Decree 1586, Establishing the Philippine
Environmental Impact Statement System, thus it is covered by such law. The securement of the ECC will form
part of the compatibility and requirements with the classification as an ECA.
The project area is not located in areas under CARP or with CADC/CADT.
2.1.2 Geology
The Cabatuan Formation was designated by Corby and others (1951) for the nearly flat-lying rocks in the
central part of the Iloilo Basin. These rocks are largely exposed between Cabatuan and Sta. Barbara, Iloilo
along the Tigum River. They divided the formation into three members – Balic Clay (renamed here as Balic
Mudstone Member), Maraget Sandstone and Sta. Barbara Silt. The formation was dated Plio-Pleistocene by
Santos (1968) but BED (1986b) considers its age as Pleistocene.
There is no change in the surface landform, topography and terrain of the project site since the area is already
flat and there will be minimum changes in the surface landform (this will be due to the construction of the
building’s foundation.
There will be no change in the sub-surface/underground geomorphology of the project area with the
construction of the proposed hatchery project.
2.1.3 Pedology
Based on genetic and morphological characteristic, there are three (3) different types of soil in the
municipality. Generally, Sta. Barbara’s soil is thick, fertile and suitable for raising all kinds of agricultural
products. Predominantly, it is of loam classification which makes it readily conducive to rice farming.
        a. Sta. Rita Clay Loam- covers 75% or 9,897 has. found among the plains of Sta. Barbara.
        b. Umingan Fine Sandy Loam- covers 15% or 1,979.40 has. found in upland areas.
        C. Alimodian Clay Loam - covers 10% or 1,319.60 has. found in the hills of the municipality.
The project area has the Sta. Rita Clay Loam for its type of soil.
There will be the occurrence of soil erosion and loss of top soil particularly to the areas where the building
structures will be constructed.
To address such possible impacts contractor must be provided with mitigating measures such as provision of
proper drainage and silt traps at the construction area to avoid loose soils from being carried to the nearest
water body, proper stockpiling of excavated materials and proper disposal of excess overburden outside of
the project area.
The project site is presently an idle land previously which was not utilized by the Licup Family. The area where
the project will be situated is relatively flat with only grasses thriving and secondary shrubs. It is an open area
with some few vegetation and it is adjacent to an irrigation canal. Surrounding the project area are some
residential houses and agricultural lands.
The removal of such vegetation to pave way for the project will temporarily disrupt the habitat of certain
wildlife species living in that area. However, due to the vastness of the adjacent areas as agricultural lands
they could easily locate for their new habitat within that area.
                                                                                                     23 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
No endangered plants or animal species can be found in the proposed site. The area of the proposed project
will be constructed inside the proponent’s property and the whole area is considered an industrial zone.
Hence, conduct of study pertains the whole area is irrelevance/immaterial.
With the construction of the hatchery project in the area, the habitat for any wildlife species thriving in the
area could be disturbed and affected. The tendency of these species is to stay away from the disturbed area
and would locate to nearby areas with the same habitat characteristics.
2.2.1 Hydrology/Hydrogeology
The nearest water body in the project site is the Tigum River which is located at the west and southwest
portions of the project site (approximately 150 meters from the project site). There is also an existing
irrigation canal which connects to the Tigum River and this will serve as the discharge point of the treated
wastewater generated by the hatchery plant.
Tigum River originates from Mt. Inaman located at the Iloilo Antique border and traverses the Municipalities
of Maasin, Cabatuan and Sta. Barbara. Its downstream area from Pavia to its mouth in Brgy. Hinactacan, Lapaz,
Iloilo City.
Primarily, Tigum River is the main source of water supply of Iloilo City for its domestic, commercial and
industrial needs. The Dam at Brgy. Daja, Maasin, Iloilo and the pumping station at Brgy Ungka, Pavia Iloilo
being maintained by Metro Iloilo Water District (MIWD) are primarily part of this river system.
This drainage basin is serving several agricultural farms’ irrigation requirements, not to mention the volume
of water daily that go into the water system of MIWD. The Tigum River’s water supply and its natural flow
have been fragmented by the dam and by some man-made diversions for irrigation purposes
This specific adverse impact is not applicable as the drainage in the whole area is generally parallel to sub-
parallel. Construction activities will not alter the drainage characteristics of the host barangay.
                                                                                                 24 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
There are no available information with regards to the flood peaks, volumes, frequency rating curves and
storm water flow estimates and related matters for the waterbody within the area. Flooding is an indirect
formation due to the ever-present changes due to Global Warming. Last recorded flooding that occurred in
the area was when Typhoon Frank (internationally known as Typhoon Fengshen) hit Panay Island in June 18,
2008. After Iloilo Flood Control Project was built the area did not experience any flooding.
Iloilo Flood Control Project (Phase I and II) is a Loan Project by DPWH from JICA implemented from 1999-2000
and 2002-2011. The Project included the construction of the Jaro Floodway and other structural and non-
structural measures that include: river improvement works, diversion channels, dams, flood retarding basins,
sabo dams, and watershed management. The Project is considered by CTII as a major project in the Philippines
that cemented its place in the engineering consulting industry as the leading firm in designing and managing
construction of flood infrastructure facilities in the Philippines and in other parts of the world
Proper drainage systems will be constructed for the project to avoid inducement to flooding.
There is no available information or reports with regards to the change in stream water depth as a result of
the proposed project of SMV Agro Industrial Corporation. The possible discharges from the treated effluent
will not change the stream depth of the river considering that it would pass through the manmade irrigation
canal before it reaches the Tigum River.
There will be no water resource use and competition when you relate the proposed project to the nearby
Tigum River. Source of water for the proposed plant will be the groundwater source (deep well) and the
hatchery plant is not an intensive water usage operator, considering that average monthly water consumption
for its operation (domestic and other washings) is about 15 cu. meters.
Proper documentation and permits shall be secured from the National Water Resources Board (NWRB) before
given the authority to extract and processed the surface water. The NWRB is the government agency which
manages and regulates all water resources and services in the Philippines. It integrates and coordinates all
water related activities that have social, environmental and economic impacts in the country.
2.2.2 Oceanography
The nearest saltwater body is Guimaras Strait (middle portion) is approximately 13.10 kilometers based on
the ground length distance from the project area. The impacts of the project such as change in bathymetry
and circulation patterns could be considered negligible due to the distance from the said strait.
                                                                                               25 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The utilization of the groundwater resources for the plant’s operation will not degrade the ground water
quality in the area.
A permit will be secured from the National Water Resources Board (NWRB) for the usage of the groundwater
source. This would regulate the withdrawal/extraction rate from the said source thus managing the possibility
of resource depletion and competition.
Domestic discharge and other wastewater discharges will be provided with the wastewater treatment
facilities that would ensure that effluent being discharged will be within the DENR Effluent Standards and will
not affect any groundwater or surface water bodies.
Jaro-Tigum-Aganan River
Tigum is part of the Jaro-Tigum-Agana River and this river system was already officially classified by the
Environmental Management Bureau R6.
Tigum River originates from Mt. Inaman located at the Iloilo Antique border and traverses the Municipalities
of Maasin, Cabatuan and Sta. Barbara. Its downstream area from Pavia to its mouth in Brgy. Hinactacan, Lapaz,
Iloilo City. While Aganan River as part of this drainage channel traverses the Municipalities of Alimodian, San
Miguel and also part of Sta. Barbara and finally joined Jaro River in Brgy. Ungka, Pavia, Iloilo. Jaro-Tigum River
is the principal river channel while Aganan River is its major tributary. Jaro-Tigum has an approximate length
of about 35-kilometers from its source down to its mouth at Brgy. Hinactacan, Lapaz, Iloilo City, while Aganan
River has an approximate length of about 20 kilometers from its source down to its confluence with Jaro-
Tigum River in Pavia Bridge, Pavia, Iloilo.
Primarily, Tigum River is the main source of water supply of Iloilo City for its domestic, commercial and
industrial needs. The Dam at Brgy. Daja, Maasin, Iloilo and the pumping station at Brgy Ungka, Pavia Iloilo
being maintained by Metro Iloilo Water District (MIWD) are primarily part of this river system.
This drainage basin is serving several agricultural farms’ irrigation requirements, not to mention the volume
of water daily that go into the water system of MIWD. The Tigum River’s water supply and its natural flow
have been fragmented by the dam and by some man-made diversions for irrigation purposes.
The uppermost stream being the source of drinking water has been officially classified as Class ‘A’ (Maasin
Dam) and the rest of the midstream down to its mouth have been officially classified as Class “C”. Both rivers
                                                                                                    26 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
are recipient of discharges from piggery, poultry dressing plant, paper mill, domestic waste from urban centers
where it traverses, and agricultural un-off from nearby agricultural field. It is also a source of irrigation water
to about 2,500 hectares of rice fields where irrigation system is being managed by the National Irrigation
administration (NIA).
Jaro-Tigum-Aganan River is the first pilot project for Water Quality Management Area in the Region 6. Eight
(8) sampling stations were established for water quality monitoring 3 of which were added last year for
additional monitoring data needed for its Water Quality Management Area. Table below disclosed the location
of the sampling stations where water samples were collected and analyzed in EMB Laboratory. Among these
stations, two (2) are located in Aganan River and the rest are located in Jaro-Tigum River.
One of the requirements during the Technical Scoping was to conduct the baseline water quality data.
Considering that the proposed project will not directly discharge its treated effluent to the Tigum River but
will be in the manmade irrigation canal, it was decided that sampling stations will be established at the
upstream and downstream portion of the irrigation canal.
Baseline samplings were conducted last September 13, 2021 and laboratory analysis was conducted by the
Negros Prawn Producers Cooperative Analytical and Diagnostic Laboratory. The following were the
established sampling stations along the stretch of the manmade irrigation canal leading to Tigum River:
                                                                                                     27 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Summary of the Parameters that were analyzed during the water quality sampling of the Manmade Irrigation
Canal which is connected to Tigum River is showed at the table below. Annex _ presents the copies of the
Official Results of the Laboratory Analysis of Manmade Irrigation Canal.
 Table 5. Results of Laboratory Analysis for Irrigation Canal which serves as the Discharge Point of SMV’s
                   Wastewater from the Hatchery Plant, Brgy. Lanag, Sta. Barbara, Iloilo
It could be noted that there were exceedances in the BOD5 value of the downstream and upstream sampling
stations. Likewise the parameters for Total Suspended Solids at the downstream and upstream sampling
stations have exceeded the DENR Water Quality Standards.
There were also exceedances of Fecal Coliform parameters for the downstream and upstream sampling
stations based on the results of the laboratory analysis. Information gathered that possible other contributors
are the residential houses which discharges its sewage to the manmade irrigation canal.
The proposed project could not contribute to the degradation of the water quality of any coastal or marine
water body since it is approximately 13.10 kilometers from the nearest marine waterbody.
                                                                                                 28 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
2.3 Air
2.3.1 Meteorology/Climatology
Climate
Based on Corona’s modified Classification, Sta. Barbara, Iloilo has a climatic condition that falls under the Type
III which seasons are not very pronounced: relatively dry from November to April and wet during the rest of
the year. Figure 11 presents the Climatological Map of the Philippines.
Project Site
Rainfall
The nearest weather station of the Department of Science and Technology –Philippine Atmospherc ,
Geophysical, and Astronomical Services Administration (DOST-PAGASA) is located in Jaro, Iloilo City
approximately 9 km east of the diversion point. Historical climate data from the Iloilo Station show a mean
annual rainfall of 2,955 mm with a minimum of 61 mm in February and a maximum of 472 mm in September
. Meanwhile, the mean annual temperature is 27.9 °C with a minimum of 26.7°C in January and a maximum
29.6 °C in April.
                                                                                                    29 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Climate Projection
Seasonal Temperature Change
Source: PAGASA-DOST
Figure 12 shows the projected seasonal temperature increase in the Philippines in 2020 to 2050. Mean temperatures
in all areas in the Philippines are expected to rise by 0.9°C to 1.1 °C in 2020 and by 1.8°C to 2.2°C in 2050.
Likewise, all seasonal mean temperatures will also have an increase in these time slices; and this increase during the four
seasons are quite consistent in all parts of the country. Largest temperature increase is projected during the summer
(March-April-May) season.
                                                                                                                 30 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Source: PAGASA-DOST
Figure 12. Maps Showing the Projected Seasonal Temperature Increase (in°C)
Generally, there is reduction in rainfall in most parts of the country during the summer (March-April-May)
season. As seen in the maps in
                                                                                             31 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
There are varied trends in the magnitude and direction of the rainfall changes, both in 2020 and 2050. What
the projections clearly indicate are the likely increase in the performance of the southwest and the northeast
monsoons in the provinces exposed to these climate controls when they prevail over the country. Moreover,
the usually wet seasons become wetter with the usually dry seasons becoming also drier; and these could
lead to more occurrences of floods and dry spells/droughts, respectively.
                                                                                                32 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
In 2009, the Government of the Philippines initiated the implementation of the Millennium Development
Goals Fund (MDGF) Joint Programme entitled “Strengthening the Philippines’ Institutional Capacity to Adapt
to Climate Change”. It is a three-year program funded by the Government of Spain through the United Nations
Development Program (UNDP) Philippines and the various UN agencies (UNEP, FAO, WHO, UN Habitat, and
others). The three outcomes of this Joint Programme are:
    •   climate risk reduction mainstreamed into key national and selected local development plans and
        processes;
    •   enhanced national and local capacity to develop, manage and administer projects addressing climate
        change risks; and
    •   coping mechanisms improved through pilot adaptation projects.
                                                                                              33 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Central to achieving the three outcomes is developing the capacity of local government units in the Philippines
to mainstream climate change adaptation in their development plans, programs and activities. Planning for
and implementing climate change adaptation will require detailed information on plausible future climates,
such as changes in temperatures, rainfall and frequency of extreme weather events. These climate
information, called climate change scenarios, are generated from climate simulations. Climate change
scenarios provide characteristics of plausible future climates and are constructed using climate models. These
are either global or regional climate models and are mathematical representations of the climate system
which simulate the physical and dynamical processes that determine global/regional climate. There is no
certainty as to how emission pathways in the future would go, inasmuch as development pathways in both
the developed and developing countries all over the globe are defined by factors such as population and
demographic characteristics, access to technology, economic development, energy use and policies pursued,
including outcomes of negotiations on greenhouse gas emission reductions.
In order to generate projections of temperature increase and rainfall change in the Philippines in the future,
the Philippine Atmospheric, Geophysical and Astronomical Services Administration (PAGASA) used the PRECIS
(Providing Regional Climates for Impact Studies) model in two time frames; 2020 and 2050. This model was
developed by the UK Met Hadley Centre (in the United Kingdom) to facilitate impact, vulnerability and
adaptation assessments in developing countries where capacities to do climate modeling are still not fully
developed or do not exist. Three of the emission scenarios developed by the Intergovernmental Panel on
Climate Change in its Special Report on Emission Scenarios (IPCC SRES) were chosen to run the models;
namely, A2 (high-range), A1B (mid-range), and B2 (low-range). The A2 scenario is at the so-called higher end
of the emission scenarios (although not the highest), and is preferred by most countries because from an
impacts and adaptation point of view, if man can adapt to a larger climate change, then the smaller climate
changes of the lower end scenarios can also be adapted. On the other hand, the A1B scenario is considered
because the future climates in the next 30-40 years will be greatly influenced by past emissions, principally
due to the long lifetimes of carbon
Main outputs presented in this Report are the projected temperature increase in °C, magnitude and direction
of rainfall change in %, and frequency of extreme weather events (e.g., extreme temperature expressed in
number of days with maximum temperature greater than 35 °C, dry days indicated by the number of days
with less than 2.5mm of rain, and extreme rainfall or number of days with greater than 300mm of rain) in the
country.
Highlighted in this Report are the present (baseline) climates, key findings of future climates in 2020 and 2050
in the Philippines under the three emission scenarios, and how would these future climates impact on the
different key sectors and systems, including how adaptation could be pursued. The present (baseline) climate
gives the current changes in the Philippine climate in terms of temperature, rainfall and extreme events,
including tropical cyclone occurrence. The key findings on future climates (e.g., in 2020 and 2050) in each of
the provinces are presented in terms of temperature increase and rainfall change by seasons (e.g., DJF or
northeast monsoon season, MAM or summer season, JJA or southwest monsoon season, and SON or
                                                                                                  34 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
transition from southwest to northeast monsoon season) and changes in frequency of daily extreme events
in graphs and/or tables1.
The computation will based on the tables that are given and will provide results on the extreme temperature
expressed in number of days with maximum temperature greater than 35 °C, dry days indicated by the number
of days with less than 2.5mm of rain, and extreme rainfall or number of days with greater than 300mm of rain.
For Iloilo Province, the values that will be utilized in determining the frequency of extreme events under
medium-range emission scenario will be of Iloilo City.
For Iloilo province, the projected values in 2020 using the DJF (northeast monsoon season) and JJA
(southwest monsoon season) are:
1Climate Change in the Philippines, Executive Summary, MDG Achievement Fund & PAAGASA, February
2011
                                                                                               35 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
For Iloilo province, the projected values in 2050 using the DJF (northeast monsoon season) and JJA
(southwest monsoon season) are:
The climate projections of 2020 and 2050 would help also the proponent identify the possible scenario during
prolonged drought “El Niño Phenomenon” or occurrence of “La Niña Phenomenon” in that way it could always
prepare the possible needed source of water for their operation of the project in the event that there will be
the depletion of groundwater sources of the project.
The project will also provide rainwater harvesting through the provision of the drums that would collect water
from the project’s down spouts and can be utilized in watering the plants and other landscaping activities of
the project.
                                                                                                 36 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
One of the concerns of the EIA Review Committee is the adequacy and effectiveness of the drainage canal
system of the project in the event of heavy downpour. The hatchery plant was elevated 1.5 meters from the
original ground level before the construction of its foundation. Proper drainage system was provided as to
contain immediately the rainwater and discharge it to the nearby irrigation canal without contributing to the
flooding of adjacent areas.
The implementation of the project especially during the construction phase could temporarily change the air
quality of the area which could be categorized as moderate or unhealthy to sensitive groups. It is important
that mitigating measures should be implemented by the proponent.
The introduction of noise generating activities could also alter the present situation of the area especially
during the construction phase.
Noise is technically measure in terms of sound and pressure levels expressed as decibels (dB) which is the
ratios of two (2) amount of electronic or acoustic signal power equal to ten (10) times the common logarithm
of this ratio. The dB readings may be measured either on the A, B, or C network depending on the frequency
of sound, e.g. fast, slow, etc. The major source of noise pollution in the project areas comes from the passing
of motor vehicles and operation of heavy equipment.
The maximum allowable noise level for a certain area is dependent on two (2) factors, namely: a) Category of
the area e.g. residential, commercial, institutional, industrial, etc. and b) Division of twenty-four (24) hour
period, e.g. morning, daytime, evening, etc.
One of the requirements during the Technical Scoping with the EMB R6 and EIA Review Committee was to
conduct a baseline on the noise level and the ambient air quality taking into consideration the parameters for
PM10 and TSP. There were two sampling stations that were established, namely:
                        Location                                    Remarks
                        Upwind                               Parameters Monitored are
               (10.82931N and 122.54269E)                         PM10 and TSP
                       Downwind                              Parameters Monitored are
               (10.83162N and 122.54002E)                         PM10 and TSP
The baseline sampling for the above-mentioned parameters were conducted last August 13, 2021. Summary
of the results of the ambient air quality monitoring for the PM10 and TSP parameters in both stations are
within the standards for the National Ambient air Quality Guidelines. Table below presents the summary of
the Ambient Air Quality Monitoring.
                                                                                                 37 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The same established stations were utilized in measuring the noise levels near the project site which are the
upwind and downwind. There were five number of trials for each 5-minute segment for each station.
Summary of the Noise Level Measurements could be found in the table below.
Annex E presents the Official Ambient Air Quality Monitoring Results and Result of Noise Level Measurements.
Considering that the project involves the generation of emission of air pollutants due to the burning of fossil
fuel (diesel) from the operation of its generator sets the air quality condition can be considered as moderate
or unhealthy for sensitive groups for which some members of sensitive groups may experience health effects
                                                                                                 38 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
although the general public will not be likely affected. The plant will have two (2) units air pollution source
equipment:
All reciprocating Internal Combustion (IC) engines operate by the same basic process. A combustible mixture
is first compressed in a small volume between the head of a piston and its surrounding cylinder. The mixture
is then ignited, and the resulting high-pressure products of combustion push the piston through the cylinder.
This movement is converted from linear to rotary motion by a crankshaft. The piston returns, pushing out
exhaust gases, and the cycle is repeated.
There are 2 methods used for stationary reciprocating IC engines: compression ignition (CI) and spark ignition
(SI). This section deals with both types of reciprocating IC engines. All diesel fuelled engines are compression
ignited, and all gasoline-fuelled engines are spark ignited. In CI engines, combustion air is first compression
heated in the cylinder, and diesel fuel oil is then injected into the hot air. Ignition is spontaneous because the
air temperature is above the auto ignition temperature of the fuel.
Emissions
Most of the pollutants from IC engines are emitted through the exhaust. However, some total organic
compounds (TOC) escape from the crankcase as a result of blowby (gases that are vented from the oil pan
after they have escaped from the cylinder past the piston rings) and from the fuel tank and carburetor
because of evaporation. Nearly all of the TOCs from diesel CI engines enter the atmosphere from the exhaust.
Evaporative losses are insignificant in diesel engines due to the low volatility of diesel fuels.
The primary pollutants from internal combustion engines are oxides of nitrogen (NOx), total organic
compounds (TOC), carbon monoxide (CO), and particulates, which include both visible (smoke) and nonvisible
emissions. Nitrogen oxide formation is directly related to high pressures and temperatures during the
combustion process and to the nitrogen content, if any, of the fuel. The other pollutants, HC, CO, and smoke,
are primarily the result of incomplete combustion. Ash and metallic additives in the fuel also contribute to the
particulate content of the exhaust. Sulfur oxides (SOx) also appear in the exhaust of the Internal Combustion
Engines.
Nitrogen Oxides
Nitrogen oxide formation occurs by two fundamentally different mechanisms. The predominant mechanism
with internal combustion engines is thermal NOx which arises from the thermal dissociation and subsequent
reaction of nitrogen (N2) and oxygen (O2) molecules in the combustion air. Most thermal NOx is formed in
the high-temperature region of the flame from dissociated molecular nitrogen in the combustion air. Some
NOx, called prompt NOx, is formed in the early part of the flame from reaction of nitrogen intermediary
species, and HC radicals in the flame. The second mechanism, fuel NOx, stems from the evolution and
reaction of fuel-bound nitrogen compounds with oxygen. Gasoline, and most distillate oils have no chemically-
bound fuel N2 and essentially all NOx formed is thermal NOx.
                                                                                                    39 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The pollutants commonly classified as hydrocarbons are composed of a wide variety of organic compounds
and are discharged into the atmosphere when some of the fuel remains unburned or is only partially burned
during the combustion process. Most unburned hydrocarbon emissions result from fuel droplets that were
transported or injected into the quench layer during combustion. This is the region immediately adjacent to
the combustion chamber surfaces, where heat transfer outward through the cylinder walls causes the mixture
temperatures to be too low to support combustion.
Partially burned hydrocarbons can occur because of poor air and fuel homogeneity due to incomplete mixing,
before or during combustion; incorrect air/fuel ratios in the cylinder during combustion due to maladjustment
of the engine fuel system; excessively large fuel droplets (diesel engines); and low cylinder temperature due
to excessive cooling (quenching) through the walls or early cooling of the gases by expansion of the
combustion volume caused by piston motion before combustion is completed.
Carbon Monoxide
Carbon monoxide is a colorless, odorless, relatively inert gas formed as an intermediate combustion product
that appears in the exhaust when the reaction of CO to CO2 cannot proceed to completion. This situation
occurs if there is a lack of available oxygen near the hydrocarbon (fuel) molecule during combustion, if the gas
temperature is too low, or if the residence time in the cylinder is too short. The oxidation rate of CO is limited
by reaction kinetics and, as a consequence, can be accelerated only to a certain extent by improvements in
air and fuel mixing during the combustion process.
White, blue, and black smoke may be emitted from IC engines. Liquid particulates appear as white smoke in
the exhaust during an engine cold start, idling, or low load operation. These are formed in the quench layer
adjacent to the cylinder walls, where the temperature is not high enough to ignite the fuel. Blue smoke is
emitted when lubricating oil leaks, often past worn piston rings, into the combustion chamber and is partially
burned. Proper maintenance is the most effective method of preventing blue smoke emissions from all types
of IC engines. The primary constituent of black smoke is agglomerated carbon particles (soot) formed in
regions of the combustion mixtures that are oxygen deficient.
Sulfur Oxides
Sulfur oxides emissions are a function of only the sulfur content in the fuel rather than any combustion
variables. In fact, during the combustion process, essentially all the sulfur in the fuel is oxidized to SO2. The
oxidation of SO2 gives sulfur trioxide (SO3), which reacts with water to give sulfuric acid (H2 SO4), a
contributor to acid precipitation. Sulfuric acid reacts with basic substances to give sulfates, which are fine
particulates that contribute to PM-10 and visibility reduction. Sulfur oxide emissions also contribute to
corrosion of the engine parts.
Computation for the Emissions of Each Pollutant (Stand-by Power Generating set , capacity-750 kVA)
Emission factors are from EPA AP 42, 3.3 Gasoline and Diesel Industrial Engines & 3.4 Large Stationary Diesel
and All Stationary Dual-Fuel Engines 10/96.
                                                                                                     40 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Assumption :
Since the generator set is only a standby unit, the usage of this equipment will be during power failures only
so it is estimated that 1% of the total number of hours that the project operates will have some power
disruptions/failures
Number of hours (in operation) per year = 8,064 hrs/yr x 1% = 80.64 hours
Emission (tons/yr) = Emission Factor (lb/hp-hr) x hp rating (hp) x (No. of hours/yr) x 1 ton/2000 lb
It is important that the air pollution source equipment to have their air pollution control devices maintained
and working effectively and efficiently. In doing so would minimize the impacts on air pollution in the project
site and its surrounding areas.
Furthermore, proponent must comply with the requirements of Republic Act No, 8749 of the Philippine Clean
Air Act of 1999. Emission standards shall be based on mass rate of emission for all stationary source of air
pollution based on implementing Rules and Regulations of R.A. 8749. The standards shall be the limit on the
                                                                                                 41 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
acceptable level of pollutants emitted from a stationary source for the protection of the public’s health and
welfare.
Permit to Operate must be secured from the Environmental Management Bureau for the above- mentioned
air pollution source and control equipment.
2.4.1 Identify settlers that will be displaced from among the existing settlers
The project site was previously an idle land and presently there are no affected families or settlers particularly
to the proposed areas for the construction of hatchery plant.
 With the implementation of the proposed project the increase of possible migrants in the project area could
 be considered significant due to the job opportunities that the project has offered. Once the positions have
 been filled up, only the indirect labor related to the project will be considered in the possible in-migration
 patterns. There is also the understanding of the proponent and the Local Government Unit on prioritizing
 local residents when hiring to minimize if not eliminate in-migration in the area caused by the proposed
 project.
 There are no indigenous people (IPs) in the project area. The migration of different kinds of people from
 other areas (if there is any) could change the culture/lifestyle in some other way but such alteration will be
 considered very negligible. The impact of this proposed project as far as lifestyle is concern is indirect,
 through tax revenues. More revenues for the municipality mean more access to government services, e.g.
 health, sports and livelihood. More revenues also means, the municipality’s economic growth are strong and
 would result in opening of new opportunities for investors.
2.4.4 Discuss the project implementation's threat to public health vis-a-vis the baseline health conditions
in the area
During the operational phase, the health conditions in the area will primarily be dependent to the health,
environment and safety programs of the proponent. For the expansion project activities of the project, prior
to the commencement of the construction phase the workers/personnel involved will be briefed on the health
and safety aspects of the activities. The people involved will adhere to the policies in health and safety to
avoid any untoward accidents.
                                                                                                    42 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The expected local benefits from the implementation of the proposed project will be opportunities for
temporary work during the construction phase, additional job opportunities during the operational phase
due to the operation of the Broiler Hatchery Project and payment of local taxes which will have a domino
effect on the delivery of basic services.
2.4.6   Discuss how the project would affect the delivery of basic services and resource competition in the
area
Considering that the project falls within the industrial zone, it could spur for the competition of other project
related businesses. It could also help the host barangay with its social development programs. The timely
payment of local taxes will help improve the provision of the basic services that the local government of Sta.
Barbara is giving.
2.4.7 Discuss how the project would affect traffic situation in the area
The project could affect traffic situation in the area during the construction and operational phases if the
proponent will not implement the proper traffic management plan. It is vital that there should be the
scheduling of the hauling of raw materials and finished products and proper designation of parking areas
inside and outside the project area.
The proponent will be responsible for the environmental management of the area. It will establish an
Environmental Unit that is responsible in all the issues and concerns pertaining to the compliance of the
proponent’s activities to the existing environmental laws. The unit will be composed of a Pollution Control
Officer (PCO) and its members. In-house monitoring will be conducted by this unit from the construction
phase up to the abandonment phase.
2.4.9 Discuss how the project would affect existing properties in the area in terms of relocation and
devaluation
The project area and the adjacent areas/properties will have an increased land value since the areas mostly
fall within the industrial zone of the Municipality and due to the economic activities of the project. There will
no devaluation of the project area and adjacent areas.
Sex Distribution
In the 2007 National Statistics Office survey, females outnumbered males by 300, that is 23,188 females over
22,888 males, a ratio of 99 males for every 100 females. The same trend may hold true by year 2005 to 2015
where in females outnumber males.
Age Distribution
                                                                                                   43 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Figure 14 and Table 7 shows that in 2007 ages 5-9 have the most number of population having 4,917 (both
sexes) while ages 80 and over have the least with only 597. Moreover, classifying the present age distribution
of population to child and youth population would reveal that a large portion of the population belongs to
child and youth with a population of 33,635 or approximately 73% of the total population.
Consequently, with a large percentage of the population belonging to the child and youth, we can foresee
that a large potential labor force will be joining the labor market of the municipality ten years later. The more
workers will be joining the labor force the better it will be for the municipality to be economically productive.
                                                                                                   44 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Table 8. Age and Sex Distribution of the Population of the Municipality of Sta. Barbara (2000-2021)
                                                                                                                                45 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The wastes of the municipality consist of solid wastes classified as biodegradable, non-biodegradable, residual
wastes and special and hazardous wastes. With the enactment of RA 9003 otherwise known as the Ecological
Waste Management Act the municipality was challenged to undertake the program. With the implementation
of the said program in 2002, the Local Government Unit of Sta. Barbara had been a recipient of several national
awards.
The Ecological Solid Waste Management Program of the municipality adopted the “ No Segregation, No
Collection Policy “. With this, solid waste coming from the residential and commercial establishments are
segregated from the source and are stored in containers like plastic bags, polyethylene garbage bags, broken
pails or cans. The Sanitary Technician under the Municipal Environmental and Natural Resources Office
(MENRO) schedules the collections of garbage. Wastes collected everyday are brought to the Material
Recovery Facility 1 (MRF 1) located at the Eco-Park in Barangay Daga. Final sorting is conducted at MRF 1 for
sale, reusing and recycling. The biodegradable materials are shredded and made into compost.
Wastes coming from the public market are segregated at MRF 2 within the site. The non-biodegradable wastes
are transported to the MRF 1 at Eco Park for final sorting. Biodegradable materials are shredded and
processed into compost both at the MRF 1 and MRF 2. There are two methods used in composting. One is
done with the use of vermin called African Night Crawlers. Product of this process is called vermicast which is
harvested every 2 weeks. Another method of composting is with the use compost fungus activator (CFA) called
trichogramma. This process is being done with the incorporation of animal waste to the shredded
biodegradable materials. Composts produced from these two methods are used in the Eco Park and
Gulayanng Bayan while some are for sale.
The proportion of households with access to sanitary manner of garbage disposal provides statistics on the
environmental living conditions essential for the formulation of plans and programs to improve general health
conditions.
The solid waste management of the project will be handled by the proponent in coordination with the
contracted party for the proper disposal of wastes (egg shells and general garbage). Dead chicks after hatching
will be sold to interested third parties engaged usually in catfish production.
The top most priority of the present administration in the municipality is health and sanitation. This requires
the participation of both government and nongovernment organization/ institution which are directly
involved in the delivery of basic health services.
The Municipality of Santa Barbara is strategically located in the centermost of the province. It is a twenty-
minute drive from the city of Iloilo. It is accessible via any land transportation and air through the Iloilo Airport
                                                                                                      46 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
of International Standard. It has 60 barangays with a total population of 51, 075 as of 2007. The health
situation of the municipality for the last 3 years shows that in every year, there is slight increase in the crude
birth rate from 18.7% of 2008 to 20% of 2010 and with a fertility rate of 91 per 1000 as of 2010.
Health is cared for by 29 health personnel headed by the municipal health officer. There are 8 Barangay Health
Stations, 1 main health center and 5 satellite substations. The municipal health staff consists of 1 municipal
health officer, a medical officer V, 2 public health nurses, 3 sanitation inspectors, a dentist and a dental aide,
a medical technologist, laboratory assistant, 18 midwives and 4 health aides. Regular trainings and seminars
are provided for to enhance knowledge and skills of health personnel.
The municipal health center is open 24 hours a day 7 days a week. Medicines were provided but on a limited
basis only. It is Philhealth accredited for OPD package and TB DOTS package. It is Phil CAT/DOTS certified
facility and it is also accredited as Sentrong Sigla level I phase II. It has 2 ambulances manned by 5 ambulance
drivers. There are 310 Barangay Health Workers (BHW) who are assisting the midwives in their work. They are
volunteer workers.
There are 60 Barangay Nutrition Scholars who help in the nutrition program implementation. The Nutrition
program is handled by the Municipal Nutrition Committee headed by the municipal Mayor. The members are
from the different departments as well as the NGO’s. They meet monthly to discuss the nutrition programs of
the LGU.
In 2002 and 2003, Sta. Barbara was adjudged as the most outstanding municipality in the implementation of
the nutrition program in the whole province.
                                                                                                    47 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Morbidity
Data taken from the Comprehensive Landuse Plan 2011-2021 of the Municipality of Sta. Barbara revealed that
for the past three years (2008, 2009 and 2010- these are the latest information given by the Municipality) the
ten (10) leading causes of morbidity are: Upper Respiratory Tract Infection (URTI), Pneumonia, Hypertension,
Skin infections, Animal bites, Gastroenteritis, Bronchitis, Asthma, PTB and UTI. Table below presents the
Morbidity Data for 2008, 2009 and 2010
Mortality
Data taken from the Comprehensive Landuse Plan 2011-2021 of the Municipality of Sta. Barbara revealed that
for the past three years (2008, 2009 and 2010- these are the latest information given by the Municipality) the
ten (10) leading causes of mortality are: Pneumonia, Cardiovascular diseases, Malignancy, Myocardial
infarction, PTB, Diabetes mellitus, Renal Failure, Bronchial Asthma, Hemorrhage, Congenital Heart disease,
and Pancreatitis.
                                                                                                48 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Table 10. Mortality (2008, 2009, 2010) of the Municipality of Sta. Barbara
It is important that first we have to make a common understanding on what environmental risk assessment
is all about. One of the definitions of environmental risk assessment is the method used to understand
whether contaminants or hazardous substances may be harming the human health or the environment. It is
within this premise that we will be able to discuss thoroughly if the project will have an environmental risk to
human beings or to the environment. Based on this definition the project does generate environmental risks
with the containment of flammable and toxic substances (diesel).
Based on the guidelines of DAO 30, Series of 2003 (Implementing Rules and Regulations of Presidential Decree
No. 1586, Establishing the Philippine Environmental Impact Statement System) particularly Annex 7e
(Procedural Guidelines for Scoping of Environmental Risk Assessment (ERA)), the project is assessed for any
contaminants or hazardous substances that may be stored at the project site that might harm the human
health of the environment. Table below presents the substance stored on-site with its capacity.
                                                                                                  49 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The phrase environmental risk is taken to mean a specific substance, such as asbestos or PCBs or CFCs or lead
and in this case the above-mentioned substances that are stored on-site and would be the sources of the risk.
In reality, the issue is far more complex and until the full complexity is understood, the impact of an
environmental risk cannot be evaluated from either a management or a property value impact point of view.
Environmental risks are not simply the presence or absence of a single substance. They are in fact the source
of the risks and the conditions which surround the risk source; how it is controlled, how a target may become
endangered, and the extent of danger. This section treats the risk source and the surrounding context of the
existence of the risk source as a whole (the risk system), discusses how this approach defines and determines
the identification and management of the risk system, and how the management and control of the risk
system any impact the value of the stakeholder’s interests.
An environmental risk must be viewed not as a substance, but as a system of components that govern the
risk. Figure 15 sets out the four major components of the environmental risk system and their relationship to
each other.
Figure 15. The Environmental Risk System of Proposed Broiler (1 Million Egg-Capacity) Hatchery Project
The risk source is what we most commonly refer to when we think about environmental risks for this kind of
project the risk source is diesel that will be stored at the plant site. This source of the risk and without it
there simply would be no environmental risk. Some risk sources can conceivably be eliminated, while others
cannot. Both risk sources have both positive and negative aspects.
The primary control mechanism is the means by which a risk source is controlled to render it both useful and
relatively benign. Useful with respect to the function it performs and benign with respect to damage to human
                                                                                                   50 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
health and/or the environment. The basic problem of environmental risk management is not whether or not
the risk source exists, but whether or not it is under control. The cost to establish and maintain control, or to
remove the risk source if adequate control cannot be established and maintained, determine the value impact
of the presence of a risk source.
The primary control mechanism almost always consists of two major components a physical component in
the form of some device that directly maintains the risk source in a benign state, and a human component
that interacts to ensure that the physical component functions as intended. Both components must function
for the risk source to be both useful and benign.
If the primary control mechanism(s) fail, the question will become one of whether or not a transport
mechanism is available to move the risk source into the immediate presence of a target, and how efficiently
that transport mechanism is likely to function. The USEPA has identified in its Hazard Ranking System, five
transport modes: surface water, ground water, air movement, direct contact, and fire/explosion.
Inextricably associated with the transport mechanism are a number of possible secondary control mechanisms
that may be either natural or artificial in origin. Like the primary control mechanisms, the secondary control
mechanisms must be evaluated in order to determine efficiency of the transport mechanism in moving the
risk source to the target in sufficient concentration to result damage. In many cases, the analysis of secondary
control mechanisms can lead to the development of significant risk reduction strategies that improve the
risk/benefit relationship.
The Target
Targets are basically of two forms: human and sensitive environments, of the two, the human target is of the
greatest concern and considerable resources must be allocated to the analysis of the relationship between
the components of the risk system to determine the likely impacts on targets.
The overall analysis of a target is governed by the negative default principle. This implies that the number of
possible targets, the probable impacts on targets, and the failure of primary control mechanisms must be in a
“worst case” scenario. The mitigating factors are the efficiency and availability of the transport/secondary
control mechanisms, the probability of use of the transport mechanism, and the probability of failure of the
primary control mechanisms.
                                                                                                   51 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The Broiler Hatchery Project will have only one risk source. Table below presents the Environmental Risk
System of the project.
                                                      Human Component:
                                                      As part of the duties and responsibilities of some
                                                      personnel they are mandated to regularly
                                                      monitor the storage tank for any leakages in the
                                                      tank and immediately call the attention of the
                                                      Supervisor-in-charge or the Plant Manager.
                                                                                                     52 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
          Secondary Control Mechanisms                The storage tank will be provided with gauges to
                                                      determine leakage and bund walls to ensure that
                                                      it will address the 1st and second transport
                                                      mechanisms.
Annex G presents the Emergency Response Plan and COVI-19 Health Measures.
                                                                                                  53 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
There are no impacts identified in this phase since this is more on the planning stage of the project.
Construction Phase
The potential impact on the water environment that is identified during this phase is the sewage effluents
generated by the personnel/staff and workers.
        •   Provision of portable toilet facilities and timely disposal of the generated wastes
        •   Include in the conditions that contractor should provide portable toilets for its workers
                                                                                                  54 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Possible airborne dust emissions during this phase are from dusty areas (cleared and excavated area for the
foundation of the structures).
            •     Provision of masks or improvised masks to workers to minimize inhalation of dust emission during
                  the activities.
            •     Regular spraying of water at dusty areas where airborne dust emission usually occurs
            •     Limit clearing to the areas that need to be developed.
            •     Trucks hauling the construction materials should be properly covered with tarpaulin especially
                  those bringing materials that could generate airborne dust emission
            •     Speed limit at the plant’s site should be 15-20 kph.
            •     Regularly clean roads utilized in the delivery of construction materials to avoid fallen earth spoils
            •     Implement the proper Traffic Management Scheme at the area.
            •     Provide ear plugs/ear muffs for those workers/laborers that are working in noise generating areas
            •     Limitation of vehicle speeds and provision of good mufflers.
4.1.4 Potential Impacts on the Socio-Economic (People) and its Mitigation (Enhancement) (Construction
Phase)
The identified potential impacts on people during the operational phase are the job opportunities, health and
safety of personnel, staff and workers, traffic and increase in revenues through local taxes.
• Prioritize the hiring of people depending on their skills at the host barangay
        •       All staff, personnel and workers must undertake safety and health briefing before they are put to
                their work assignments
        •       Provision of first-aid training to some personnel to address untoward accidents in the workplace
        •       Provision of first-aid kits at the workplace
        •       Provision of adequate signage or warning signs to those areas where there are on-going construction
                activities
        •       Provision of Personal Protective Equipment (PPEs) to all personnel and workers
                                                                                                         55 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
4.1.4.3 Traffic
Operational Phase
The impacts that will be generated during the operational phase will be the generation of solid wastes.
The potential impact on the water environment that is identified during this phase is the sewage effluents
generated by the personnel/staff and workers, wastewater generated from project’s operation, and
contamination of nearby water bodies due to generated wastewater.
        •     Provision of toilet facilities with septic tanks and proper and timely disposal of the generated
              wastes.
        •     Provision of a comprehensive drainage plan for sewage and surface runoffs
        •     Provision of an effective and efficient wastewater treatment facilities (sludge treatment facility)
        •     No effluent shall be directly discharged to any bodies of water without undergoing the treatment
              process. Treated wastewater must pass the DENR Effluent Standards.
        •     Regular monitoring and maintenance shall be conducted on the components of the wastewater
              treatment facilities to ensure its efficient operation.
Air pollution emissions during this phase are from the combustion of fossil fuels for its generator set.
            •     Proper and regular maintenance of the air pollution source and control equipment (i.e. generators
                  and mufflers)
            •     Provision of adequate smokestack and air pollution control devices.
4.1.8 Potential Impacts on the Socio-Economic (People) and its Mitigation (Enhancement)- Operational
Phase
The identified potential impacts on people during the operational phase are the job opportunities, health and
safety of personnel and staff, traffic and increase in local taxes.
• Prioritize the hiring of people depending on their skills/expertise at the host barangay
        •       All staff and personnel must undertake safety and health briefing before they are put to their work
                assignments
        •       Provision of first-aid training to some personnel to address untoward accidents in the workplace
        •       Provision of first-aid kits to the workplace
        •       Provision of Personal Protective Equipment (PPEs) to all personnel and workers
4.1.8.3 Traffic
    •     Implement properly the traffic management (route) plan in the project’s operation (Please refer to
          Annex F)
        • Designate properly parking areas for the workers/personnel and other haulers
Abandonment Phase
The abandonment and decommissioning plan for the plant can be formulated six months before actual
abandonment and decommissioning. The proponent commits to submit said plan should the project reach its’
economic or service life.
                                                                                                       57 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
The plan would include the discussion on the activities, the manpower needed and the estimated cost it will
incur during the implementation of this phase.
Demobilization will be undertaken after all the construction works have been completed. Dismantling of
temporary facilities and proper disposal of solid wastes generated during demobilization activities will be
carried out, before commissioning or actual operation commences.
                                                                                              58 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental Aspects            Potential Impacts            Mitigating Measures to be Implemented                  Responsible Party
         per Project Phase
 Construction Phase (Expansion)
            Land              Generation of Domestic and          •   Proper collection and disposal of solid wastes       Proponent/Contractor
                              Construction Wastes                 •   Provision of garbage bins especially at the
                                                                      resting/eating areas of the personnel/staff and
                                                                      workers adopting the concept of segregation at
                                                                      source
                                                                  •   Good housekeeping must be implemented at all
                                                                      times
                                                                  •   Excavated soils from the construction of the
                                                                      structure’s foundation should be properly
                                                                      stockpiled and disposed of properly
             Water               Domestic Effluents generated     •   Provision of portable toilet facilities and timely   Proponent/Contractor
                                 by Personnel/Staff and Workers       disposal of the generated wastes
                                                                  •   Include in the conditions that contractor should
                                                                      provide portable toilets for its workers
              Air                Air Pollution (Generation of     •   Provision of masks or improvised masks to            Proponent/ Contractor
                                 Particulate Matter )                 workers to minimize inhalation of dust emission
                                                                      during the activities.
                                                                  •   Regular spraying of water at dusty areas where
                                                                      airborne dust emission usually occurs
                                                                  •   Limit clearing to the areas that need to be
                                                                      developed.
                                                                                                                                         59 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental Aspects            Potential Impacts           Mitigating Measures to be Implemented                   Responsible Party
         per Project Phase
                                                                 •   Trucks hauling the construction materials should
                                                                     be properly covered with tarpaulin especially
                                                                     those bringing materials that could generate
                                                                     airborne dust emission
                                                                 •   Speed limit at the plant’s site should be 15-20 kph.
                                                                 •   Regularly clean roads utilized in the delivery of
                                                                     construction materials to avoid fallen earth spoils
                                                                 •   Implement the proper Traffic Management
                                                                     Scheme at the area.
   Socio-Economic (People)       Job Opportunities               •   Prioritize the hiring of people depending on their     Proponent/Contractor
                                                                     skills at the host barangay
                                                                                                                                         60 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental Aspects              Potential Impacts       Mitigating Measures to be Implemented               Responsible Party
         per Project Phase
                                                               •   Provision of adequate signage or warning signs to
                                                                   those areas where there are on-going
                                                                   construction activities
                                                               •   Provision of Personal Protective Equipment (PPEs)
                                                                   to all personnel and workers
 Operational Phase
            Land                 Generation of Solid Wastes    •    Proper collection and disposal of solid wastes        Proponent
                                                               •   Provision of garbage bins especially at the
                                                                   resting/eating areas of the personnel/staff and
                                                                   workers adopting the concept of segregation at
                                                                   source
                                                               •   Good housekeeping must be implemented at all
                                                                   times
                                                               •   Hazardous wastes such as busted fluorescent
                                                                   lamps, lead compounds (e.g. lead acid batteries),
                                                                   empty paint containers, and other miscellaneous
                                                                   wastes shall be properly stored on-site and
                                                                                                                                   61 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental Aspects            Potential Impacts         Mitigating Measures to be Implemented                  Responsible Party
         per Project Phase
                                                                   transported by accredited transporter/treater of
                                                                   said wastes.
             Water               Sewage Effluents from the     •   Provision of toilet facilities with septic tanks and      Proponent
                                 Personnel/Staff and Workers       proper and timely disposal of the generated
                                                                   wastes.
                                                               •   Provision of a comprehensive drainage plan for
                                                                   sewage and surface runoffs
              Air                Air Pollution                 •   Proper and regular maintenance of the air                 Proponent
                                                                   pollution source and control equipment (i.e.
                                                                   generator set and smokestacks)
                                                               •   Provision of adequate smokestack and air
                                                                   pollution control devices.
                                                                                                                                      62 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental Aspects              Potential Impacts           Mitigating Measures to be Implemented                 Responsible Party
         per Project Phase
   Socio-Economic (People)       Job Opportunities                 •    Prioritize the hiring of people depending on their      Proponent
                                                                        skills/expertise at the host barangay
 Abandonment Phase
          Land                   Generation of Solid Wastes    •       Proper collection and disposal of solid wastes           Proponent
                                                               •       Reuse materials that can be utilized for other
                                                                       purposes
                                                                                                                                         63 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental Aspects            Potential Impacts       Mitigating Measures to be Implemented          Responsible Party
         per Project Phase
                                                             •   Good housekeeping must be implemented at all
                                                                 times
                                                                                                                            64 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
In the previous chapters there was the presentation of the key potential impacts of the project and the mitigating measures that will be undertaken by the
proponent to minimize the adverse impacts. It is imperative that a compliance monitoring shall be conducted to check whether the mitigating measures that are
implemented have been effective to address the potential impacts that the project might generate. An Environmental Monitoring Plan is being presented showing
the key environmental aspects per project phase, parameters to be monitored, the sampling and measurement plan, lead person and the annual estimated cost.
Considering that the report is an Environmental Impact Statement (EIS), the discussion on the monitoring plan will focus on the construction and operational
phases only. The monitoring of the abandonment phase will be based once the proponent has provided the details of the abandonment plan to EMB.
     Key Environmental             Potential               Parameter to                   Sampling and Measurement Plan                Lead Person           Estimated
           Aspects                Impacts Per              be Monitored      Method               Frequency               Location                              Cost
      per Project Phase           Envt’l Sector
 I. Construction Phase
            Land          •   Generation of Domestic      Proper area for   Inspection         Quarterly (until       Project Area       EU/PCO           Included in the
                              and Construction Waste      disposal of                        construction phase is                                       Construction Cost
                                                          construction                             finished)
                                                          wastes
          Water           •   Release of Domestic         Check provision   Inspection         Quarterly (until       Project Area    EU/Contractor       Included in the
                              Sewage                      of portable                        construction phase is                                       Construction Cost
                                                          toilets                                  finished)
            Air           •   Airborne Particulate              TSP         Ambient Air       Semi-annual (until      Project Area       EU/PCO          Incorporated in the
                              Emissions from the                             Sampling        construction phase is                                        Construction Cost
                              clearing of the areas and                                         finished or as
                              paved roads utilized by                                         mandated by EMB
                              hauling of construction
                              materials
          People          •   Job Opportunities           No. of local      Checking of          Semi annual          Project Area   EU/Administrative    Included in the
                                                          people hired        records                                                     Office         Construction Cost
                                                                                                                                                              65 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental              Potential             Parameter to                     Sampling and Measurement Plan                         Lead Person      Estimated
          Aspects                 Impacts Per            be Monitored         Method               Frequency                 Location                               Cost
     per Project Phase            Envt’l Sector
                          •    Health and Safety of     Health and          Checking of             Quarterly              Project Area           Safety       Included in the
                               Workers                  Safety program        records                                                           Department    Construction Cost
                                                        Accidents/Near
                                                        misses
                                                        experienced
          Water          •    Release of Domestic       Check provision      Inspection            Semi annual             Project Area           EU/PCO       Included in the
                              Sewage                    of toilet                                                                                             Operational Cost
                                                        facilities with
                                                        septic tanks
                          •   Contamination of          TSS, fluoride,    Grab Sampling       Quarterly or as agreed   All                        EU/PCO       Included in the
                              nearby water bodies       pH, iron and      on the                    by EMB             identified/established                 Operational Cost
                              (Tigum River)             chloride          established                                  stations that are
                                                                          stations at the                              being monitored by
                                                                          irrigation canal                             the Proponent
                                                                          leading to Tigum
                                                                          River and regular
                                                                          effluent
                                                                          sampling.
           Air            •   Emissions from the         TSP and PM10         Ambient Air      Semi-Annual or as        Generator Set Area        EU/PCO       Included in the
                              burning of fuel for the                          Sampling        mandated by EMB                                                Operational Cost
                              operation of the plant
                                                                                                                                                                  66 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
    Key Environmental             Potential           Parameter to                       Sampling and Measurement Plan                 Lead Person       Estimated
          Aspects                Impacts Per          be Monitored        Method                Frequency                Location                           Cost
     per Project Phase           Envt’l Sector
                                                                                                                  Generator Set Area
                                                       Particulate     Source Sampling       Semi-Annual or as                           EU/PCO        Included in the
                                                         Matter             Test             mandated by EMB                                          Operational Cost
         People           •   Job Opportunities      No. of local        Checking of            Semi annual          Project Area        EU/PCO        Included in the
                                                     people hired          records                                                                    Operational Cost
                          •   Health and Safety of   Health and          Checking of             Quarterly           Project Area        EU/PCO        Included in the
                              Personnel/Staff        Safety program        records                                                                    Operational Cost
                                                     Accidents/Near
                                                     misses                                                                              Safety
                                                     experienced                                                                       Department
                                                                                                                                                         67 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
SMV Agro Industrial Corporation will be complying with the environmental laws that are being
mandated by the Environmental Management Bureau Region VI, particularly with Republic Act 8749
(Philippine Clear Air Act of 1999), Republic Act 9275 (Philippine Clean Water Act of 2004), Presidential
Decree 1586 (Philippine Environmental Impact Statement System) and Republic Act 6969 (Toxic
Substances and Hazardous and Nuclear Wastes Control Act of 1990). The Environmental Unit that
will be established will be complying with the EMB requirements specifically the Self-Monitoring
Reports (SMRs), Permit to Operate (Air Pollution Source and Control Installations) and Discharge
Permit (Wastewater).
The Social Development Program of the company will vary each year but the following activities will
be adopted by the management on a yearly basis:
In every activity of the proponent on its social development program, there is always the information,
education and communication component that is being undertaken so that those who are involved in
the said activities would be aware of the social responsibilities of the proponent and the reason why
they are doing these activities.
The plan would include the discussion on the activities, the manpower needed and the estimated
cost it will incur during the implementation of this phase.
                                                                                          68 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
It is very important that the proponent will create the Environmental Unit (EU) at the very earliest
stage of the project. The Environmental Unit will be responsible in carrying the environmental
monitoring and other related programs of the proponent. The EU will be responsible and tasked in
coordinating with the concerned National Agencies (NAs), Local Government Units (LGUs) in the
implementation of the environmental programs of the project so as to minimize the impacts
generated to the environment.
                                Position                                  Number
               Hatchery Plant Manager (Managing Head)                       1
                       Pollution Control Officer                            1
                               Assistants                                   2
The Pollution Control Officer will be under the supervision of the Hatchery Plant Manager. The
Hatchery Plant Manager will supervise those operational activities related to the compliance of the
company to environmental regulations and in the environmental related activities/commitments of
the company. The Pollution Control Officer will be the point person of the company with regards to
the compliance of the project with the requirements of the environmental laws being implemented.
There will be two members that will assist the PCO to its designated tasks in order to fulfil the
functions of the EU. Figure 16 shows the proposed the broiler hatchery project’s Environmental Unit
Organizational Chart.
                                                                                      69 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Figure 16. The Broiler Hatchery Project’s Environmental Unit Organizational Chart
Telephone No. :
                                                                                     70 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
I. PROJECT CONSIDERATIONS
1.1.2 Type
1.2.1 Enumerate Waste Type and Specify Quantity of Wastes generated in your facility.
                                                         Type                        Quantity
     Category                 Waste
                                             Hazardous      Non-Hazardous             Tons/yr.
                      PM10                                        x                 0.01664707
                      SOx                                         x                 0.01551205
        Air           NOx                                         x                 0.23457248
                      VOCs                                        x                 0.01902307
                      CO                                          x                 0.05054659
Category Remarks
                                                                                           71 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                                       Regularly collected by
                                                                       third party garbage
              Solid                              Recycling             collector; recycled waste
                                                                       is purchased by a
                                                                       contractor
II. PATHWAYS
2.1 Prevailing wind towards barrio or city?(mark the corresponding point) Yes X_ No _
2.3 Terrain (select one and mark) Flat __x__ Steep ____
2.4 Is the facility located in a flood-prone area? (select one and mark) Yes_x_ No _
                                                                                             72 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
3 to 10 ________________
0.5 to 1 km _____________
AA _________________
A _________________
B _________________
C ________X_______
D _________________
                 3.2.3.3 Economic value of water use                (may select more than one of the
                                                                    criteria below)
Drinking _______x_________
Domestic _______x_________
                                                                                             73 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Recreational ________________
Fishery _________________
Industrial _______x_________
Agricultural ________x_________
SA _________________
SB _________________
SC _________________
SD _________________
3.2.4.2 Economic value of water use (may select more than one of the criteria below)
Fishery ________________
Recreational _________________
Industrial _________________
0.5 to 1 km _______x_________
0.5 to 1 km _________________
3.3.3 Groundwater use within the nearest well (may select one and mark)
Drinking _____x___________
Industrial ______________
                                                                                            74 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Agricultural ______X___________
3.4 Land
3.4.1 Indicate current/actual land uses within 0.5 km radius: (may select one and mark)
Residential _____x_________
Commercial/Institutional ______x________
Industrial _______________
Agricultural/Recreational ______x___________
3.4.2 Potential/proposed land uses within 0.5 km (may select one and mark)
Residential _______x_________
Commercial/Institutional _______x_______
Industrial _______x_________
Agricultural/Recreational _______x__________
0.5 to 1 km _______________
3.5 Compliance (pls. take note that this will be double-checked with PCD files)
                                                                                                     75 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
……………………………………………………………………………………………………….....
RECOMMENDATION/S:
________________________________________________________________________________
________________________________________________________________________________
___________________________________________________________
                                                                                                76 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
This is to certify that all information in the submitted Project Environmental Monitoring and Audit
Prioritization Scheme (PEMAPS) Questionnaire of Proposed Broiler (1 Million Egg-Capacity) Hatchery
Project of SMV Agro Industrial Corporation located at          Brgy. Lanag, Sta. Barbara, Iloilo are true,
accurate and complete. Should I learn of any information, which makes this inaccurate, I shall bring
said information to the appropriate Environmental Management Bureau Regional Office.
In witness whereof, I hereby set out my hands this ___ day of ________ 20 at ______________.
____________________
Notary Public
                                                                                            77 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
10.0 BIBLIOGRAPHY
    1. Department of Environment and Natural Resources (DENR), Revised Procedural Manual for
       DENR Administrative Order 30, Series of 2003 (Implementing Rules and Regulations of
       Presidential Decree No. 1586,Establishing the Philippine Environmental Impact Statement
       System, 2003
    2. Department of Environment and Natural Resources (DENR), Memorandum Circular No. 2010-
       14 (Standardization of Requirements and Enhancement of Public Participation in the
       Streamlined Implementation of the Philippine EIS System, 2010
    3. Department of Environment and Natural Resources. DENR Administrative Order No. 34.
       Revised Water Usage and Classification Water Quality Criteria Amending Section Nos. 68
       and 69, Chapter III of 1978 NPCC Rules and Regulations. Quezon City. 1990.
    6. Municipal Government of Sta. Barbara. Municipal Planning and Development Office. Socio-
       Economic Profile of Sta. Barbara, Iloilo.
                                                                                    78 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
This is to certify that all the information and commitments in this Environmental Impact Statement
(EIS) Report for the Proposed Broiler (1 Million Egg-Capacity) Hatchery Project of SMV Agro Industrial
Corporation located at Brgy. Lanag, Sta. Barbara, Iloilo are accurate and complete to the best of our
knowledge, and that an objective and thorough assessment of the Project was undertaken in
accordance with the dictates of professional and reasonable judgment. Should I/we learn of any
information, which would make this EIS inaccurate, I shall immediately bring the said information to
the attention of DENR-EMB.
I hereby certify that no DENR-EMB personnel was directly involved in the preparation of this EIS Report
other than to provide procedural and technical advice consistent with the guidelines in the DAO 03-
30 Revised Procedural Manual.
I hereby bind myself to answer any penalty that may be imposed arising from any misrepresentation
or failure to state material information in this EIS Report.
In witness whereof, I hereby set my hand this ____ day of __________ at ______________________.
SUBSCRIBED AND SWORN TO before me this _____ day of ____________ 2018, affiant exhibiting
his/her Community Tax Certificate No. ___________________ issued at ______________________
on __________________________.
                                                                                         79 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
This is to certify that all the information and commitments in this Environmental Impact Statement
(EIS) Report for the Proposed Broiler (1 Million Egg-Capacity) Hatchery Project of SMV Agro Industrial
Corporation located at Brgy. Lanag, Sta. Barbara, Iloilo are accurate and complete to the best of our
knowledge, and that an objective and thorough assessment of the Project was undertaken in
accordance with the dictates of professional and reasonable judgment. Should I/we learn of any
information, which would make this EIS inaccurate, I shall immediately bring the said information to
the attention of DENR-EMB.
I hereby certify that no DENR-EMB personnel was directly involved in the preparation of this EIS Report
other than to provide procedural and technical advice consistent with the guidelines in the DAO 03-
30 Revised Procedural Manual.
I hereby bind myself to answer any penalty that may be imposed arising from any misrepresentation
or failure to state material information in this EIS Report.
In witness whereof, I hereby set my hand this ____ day of __________ at ______________________.
                                                               DARRELL A. PALABRICA
                                                             _______________________
                                                               NAME OF PREPARER
SUBSCRIBED AND SWORN TO before me this _____ day of ____________ 2021, affiant exhibiting
his/her Community Tax Certificate No. ___________________ issued at ______________________
on __________________________.
                                                                                         80 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
ANNEXES
                                                             81 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                         Annex A
                                         IEC Materials
                                                             82 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                             83 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Contents:
    1. Received copy of the Letter from Proponent requesting the Municipal Government of
       Sta. Barbara to allow the posting of information of the proposed Broiler (1 Million Egg-
       Capacity) Hatchery Project at their area of jurisdiction;
    2. Received copy of the Letter from Proponent requesting the Local government Unit of
       Brgy. Lanag to allow the posting of information of the proposed Broiler (1 Million Egg-
       Capacity) Hatchery Project at their area of jurisdiction;
    3. Received copy of the Letter from Proponent requesting the Lanag Elementary School
       to allow the posting of information of the proposed Broiler (1 Million Egg-Capacity)
       Hatchery Project at their area of jurisdiction;
    4. Received copy of the Letter from Proponent requesting the MENRO Sta. Barbara to
       allow the posting of information of the proposed Broiler (1 Million Egg-Capacity)
       Hatchery Project at their area of jurisdiction;
    5. Received copy of the Letter from Proponent requesting the Municipal Planning and
       Development Office of Sta. Barbara to allow the posting of information of the
       proposed Broiler (1 Million Egg-Capacity) Hatchery Project at their area of jurisdiction;
    6. Contents of the Basic Project Information of the proposed Broiler (1 Million Egg-
       Capacity) Hatchery Project for posting on the bulletin boards of the Municipal
       Government of Sta. Barbara and Barangay Lanag;
                                                                                   84 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                             85 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                             86 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                             87 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                             88 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
                                                             89 | P a g e
      Environmental Impact Statement (EIS)
      PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
      Barangay Lanag, Sta. Barbara, Iloilo
      PROPONENT: SMV Agro Industrial Corporation
                                      PROJECT INFORMATION
1.0   BASIC PROJECT INFORMATION
Goals/Objectives
            •        Aim at producing quality chicks for poultry broiler projects and satisfy customers’ needs
                     by providing a strong and up to date technical support, making use of the latest
                     technologies in egg hatchery while continually striving to provide safe working conditions
                     and striving to reduce our impact to the environment.
      Consistent with the principles of sustainable development, it is the policy of the DENR to
      implement a systems-oriented and integrated approach to the EIS system to ensure a rational
      balance between socio-economic development and environmental protection for the benefit
      of present and future generations. The following are the key operating principles in the
      implementation of the Philippine EIS System:
      The EIS System is concerned primarily with assessing the direct and indirect impacts of a
      project on the biophysical and human environment and ensuring that these impacts are
      addressed by appropriate environmental protection and enhancement measures.
                                                                                                   90 | P a g e
      Environmental Impact Statement (EIS)
      PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
      Barangay Lanag, Sta. Barbara, Iloilo
      PROPONENT: SMV Agro Industrial Corporation
      SMV Agro Industrial Corporation (SAIC) will construct and operate a broiler hatchery (1 million egg -
      capacity) project to address the demand of broiler poultry growers for quality chicks. The project will
      be located at Lot 3951 -A (portion of Lot 3951) (TCT No. T-180,017), Brgy. Lanag, Sta. Barbara, Iloilo.
      It will have a total project area of 11,892 square meters.
      The project site is being leased by the proponent from Heirs of Feliciana Licup for a period of ten years
      starting from June 2020.
The following is the proposed structures and support facilities of the project:
          •   One (1) unit Hatchery Building (with a capacity of 1 Million Eggs per harvest) – 1,524.03 sq.m.
                  ➢ Three (3) units Egg Room
                  ➢ One (1) unit Setter Room with twelve (12) units Setter Machines
                  ➢ Two (2) units Hatchery Rooms
                  ➢ One (1) unit Clean Room
                  ➢ One (1) unit Chicken Pull-out and Wash Room
                  ➢ One (1) unit Chicken Holding and Processing room
          •   Staff House/Shower House/Mess Hall/Common Area –
          •   Guardhouse/Waiting Area/Receiving Trucker’s Lounge – 150 sq.m.
          •   Office Building – 180 sq. m.
          •   Houses – 445.00 sq.m.
          •   Generator set/Transpad Area – 200 sq.m.
                  ➢ Two (2) units Diesel Generator Set (175 KVA each)
          •   Wastewater Treatment Facility – One (1) unit three-chambered septic tank
      Resource Utilization:
      Electrical Power Source          : Ileco 1
      Water Source                     : Deep Well
                                                                                                 91 | P a g e
Environmental Impact Statement (EIS)
PROPOSED BROILER (1 MILLION EGG-CAPACITY) HATCHERY PROJECT
Barangay Lanag, Sta. Barbara, Iloilo
PROPONENT: SMV Agro Industrial Corporation
Project Rationale
According to the Philippine Statistics Authority (PSA), the chicken industry accounted for 14.72% of
the total value of agriculture output, equivalent to P25.941 billion, in the third quarter. In the third
quarter of 2017 and 2018, the industry accounted for 13.27% and 13.96%, respectively.
Volume of production grew 8.48% to 465,150 metric tons (MT) during the third quarter of 2019. The
PSA noted that increased production was brought by increased demand as consumers shift from pork
to chicken due to the African Swine Fever (ASF) outbreak.
In 2019, the total number of chickens in poultry farming in the Philippines was around 186.4 million
heads. The entire inventory of chickens in the Philippines has increased over the last ten years.
Based on the performance of Philippine Agriculture (for January to March 2019), poultry output which
contributed 16.74 percent to the total agricultural production registered a 5.41 percent increment in
the first quarter of 2019.
The aggregate chicken demand is projected to increase from about 1.4 million MT in 2017 to 1.6
million MT in 2020 to about 1.8 million MT by 2023.
The demand for chicken meat has increased in the previous years which opted businesses to focus in
broiler poultry projects. However, due to the regular demand of poultry in the market, the broiler
poultry growers are facing some shortages in the supply of one-day old quality chicks in the market
which prompted others to focus in the hatchery production of broiler chicks. It is within this premise
that the proponent plans to construct and operate a broiler hatchery project to compensate the
demands for quality one-day old chicks.
Project Cost:
                                                                                          92 | P a g e
93 | P a g e
94 | P a g e
95 | P a g e
                                                        VISMIN BREEDER FARMS
       LUZON BREEDER FARMS
HATCHERY
                                    HATCHING EGG
                                    PREPARATION
                                    HATCHING EGG
                                     INCUBATION
                                        CHICK
                                     PROCESSING
                                                         GRADE-OUT EGGS
                   UNHATCHED EGGS
      CONTRACT BUYER                CHICK DELIVERY
                                                         GRADE-OUT CHICKS
COMMERCIAL CUSTOMER
                                                                               SALES SHED
CONTRACT GROWERS
                                                                                    96 | P a g e
                Annex B
Transfer Certificate of Title (TCT No. 180017)
              Contract of Lease
                                                 97 | P a g e
98 | P a g e
99 | P a g e
100 | P a g e
101 | P a g e
            Annex C
Manpower Requirements of the Project
(Construction and Operational Phases)
                                        102 | P a g e
PROPOSED MANPOWER REQUIREMENT
     Construction Phase
           (1) Project Manager
           (4) Project/Site Engineers (Electrical and Instrumentation, Mechanical, Civil and
               Chemical)
           (1) Safety Officer acting also Pollution Control Officer
           (5) Equipment Mechanic and Welder
           (20) Laborers ( prioritize hiring those within the surrounding barangays from the
                              project area wherever they are qualified)
           (1) Field Office Personnel
           (2) Heavy Equipment Operators
     Operation Phase
           (1) Plant Manager
           (1) Supervisor
           (1) Office Staff
           (7) Technician/Maintenance
           (8) Classifieds
                                                                                    103 | P a g e
            Annex D
Breakdown of Project Investment Costs
                                        104 | P a g e
105 | P a g e
106 | P a g e
                   Annex E
Official Ambient Air Quality Monitoring Results and
         Result of Noise Level Measurements
                                                 107 | P a g e
108 | P a g e
109 | P a g e
110 | P a g e
         Annex F
 Project Site Development Plan
Traffic Management Plan/Route
                                 111 | P a g e
112 | P a g e
        Annex G
  Emergency Response Plan
and COVID 19 Health Measures
                               113 | P a g e
This Emergency Response Plan is applicable to the project and will be implemented when there is the
occurrence of fire, flood and other natural calamities.
ACCIDENT – FIRE
The only possible source of fire is the generators and hatcher machines and power system of the project.
Several fire extinguishers will be provided in strategic places of the project area and there would be trainings
of the personnel on how to use these devices in the event of fire.
    1. Do not panic. Evaluate the extent of fire. The Emergency Response Team shall execute based on
       the roles of every members.
    2.    Some of the personnel will be trained in firefighting and first aid. Two of the personnel will be
         responsible of putting off the fire. The Safety Officer will coordinate with local government unit
         especially the Bureau of Fire Protection in the event that such fire could not be extinguished by the
         team.
    3. The Safety Officer will be responsible in communicating with the Plant Manager if he is not around
       during the occurrence of the fire.
    4. The Plant Manager will be responsible in informing the proponent about the fire and the extent of
       damage so that any decision making with regards to the operation of the plant will be provided
       immediately. He will be responsible in the safety of his personnel/workers in the event that they
       could not put off the fire.
    5. All personnel and workers will utilize the emergency exit at the back of the project so as not to
       hamper the entrance of any emergency vehicle (firetruck or ambulance).
                                                                                                 114 | P a g e
               CALAMITY – FLOOD and OTHER CALAMITIES (EARTHQUAKE)
   1. Plant Manager through its Safety Officer shall notify the personnel and workers in the event of a
        severe weather/earthquake alert. Constant communication with the LGU concerned about the status
        of the weather and rise of the river water or the occurrence of earthquake;
   2. Prepare communication equipment that should be properly operational and first aid kits and survival
        packs such as food ration, flashlights, water, matches, extra clothes, radio and other communication
        facilities shall be ready in the event of flooding.
   3.   Briefing of the personnel on the evacuation plan in the event municipal disaster committee will
        inform that there is a need to vacate the area;
   4. In the event of a flood or earthquake, chairman should still monitor the rise of level of river water or
        the extent of earthquake (immediate evacuation of personnel and workers) and when there is
        certainty that It could reach/flood the building/structures, personnel should put off all the power
        generating equipment and the source of power.
   5. Initiating an evacuation of an area by orders of the Plant Manager and notifying additional resources
        to request assistance from the proponent.
   6. Plant Manager should ensure that all personnel have been gathered and brought to a safer place
        and it should inform the proponent on the status of the project.
                                                                                               115 | P a g e
PROTECTION OF WORKERS FROM COVID-19
The protocol for protecting the workers from COVID 19 are the following:
                                                                                           116 | P a g e
               Annex H
Photographs of the Project Site (Geotagging)
                                               117 | P a g e
View of Hatchery Plant
                         118 | P a g e
Irrigation Canal (leading to Tigum River) adjacent to the Project Area which will be utilized as the
                               discharge point of treated wastewater
                                                                                           119 | P a g e
Another view of the Irrigation Canal
                                       120 | P a g e
Generator Area near the entrance of the Hatchery Plant
                                                         121 | P a g e
Guest House
              122 | P a g e
Another entrance/exit located at the northern portion of the project site
                                                                            123 | P a g e
Wastewater Treatment Facility
                                124 | P a g e
Back portion of the Project Area being surrounded by Trees to serve as buffer
                                                                                125 | P a g e
Vacant Spaces at the southern portion of the project area with uncut trees
                                                                             126 | P a g e
Another view of the southern portion with trees that serve as buffer
                                                                       127 | P a g e
Office
         128 | P a g e
Northern portion of the Project Site provided with proper drainage
                                                                     129 | P a g e
          Annex I
Hatchery Plant Designs and Layout
                                    130 | P a g e
131 | P a g e
132 | P a g e
133 | P a g e
134 | P a g e
135 | P a g e
    Annex J
Locational Clearance
                       136 | P a g e
137 | P a g e
             Annex K
PERT/CPM of the Broiler Hatchery Project
                                           138 | P a g e
139 | P a g e
                      Annex L
Official Laboratory Results of Water Quality Samplings of
  Manmade Irrigation Canal connected to Tigum River
                                                    140 | P a g e
141 | P a g e
142 | P a g e
143 | P a g e
144 | P a g e