CHAPTER 7
ORGANIZATION OF TRAIN OPERATION
Chapter 7 Organization of Train Operation
Train formation
Organization of car flow and fright train
formation plan
2
Train Diagram & Carrying capacity
7.1 Train Formation
Definition, Classification & Number of Train
The train refers to the marshalling train set with locomotive and
prescriptive train signs.
Classification of the train according to the nature of
transportation
1. Passenger train (express, fast and ordinary passenger train)
2. Mail and parcel train (express, fast mail, baggage and parcel
train)
3. Troop train
4. Freight train (five out scheduled, express, heavy-duty,
through, direct, insulated, self-owned vehicle,
district, pickup, overrun and exchange train)
5. Service train
3
Classification according to the place and driving distance of
formation
Through train (through train originated from one loading
point, coal direct, oil direct, through train with empty cars,
technical through train)
Direct train
District train
Pickup and drop train
Exchange train (district exchange train, junction terminal
transfer train)
Short-haul train
4
Marshalling unloading Distract
Marshalling loading
Distract station station station station
station station
Through train
Through train
Exchange train
5
Classification according to features and applications of transportation:
Five out schedule
Express freight train
Overrun train
Heavy haul train
Insulated train
Self-owned train
6
Train number
1. In order to identify the nature and grade of the train, and
to facilitate the train organization and management, each
train is labeled particular number which is called train
number.
2. Trains that are bound for capital and driving from the
branch to the main are up train, labeled double train
number; whereas, the trains are down train, labeled
single train number.
7
The main classification and numbers of freight train
S
train types Nature or purpose numbers
N
Through train The train which In a loading station or several stations after the
1 originated from ones grouping, and through a or above marshalling yard train operations 85001~85998
loading point
without adaptation.
2
Technical through The train which in technical points in the organization, through a or 10001~19998
train above marshalling yard train operations without adaptation.
3
Through freight The train which in technical points in the organization, through a or 20001~29998
train above section of the station operations without adaptation.
The train which in technical points in the organization, reach the
4 District freight train adjacent technology station, do not make Vehicles Abstract hanging 30001~39998
jobs within the section
The train which in technical points in the organization,and make
Pick-up and drop
5
train Vehicles Abstract hanging jobs at intermediate station in adjacent 40001~44998
intervals.
Overweight freight
7
train The train which total traction weightsmore than 5000t 71001~72998
8 “Five fixed” train Fixed, fixed line, fixed trips, timing, pricing cargo direct express trains 80001~81998
Traffic flow and train flow are called transport flow totally
9
• Organizing the goods traffic into traffic flow is the main
problem to resolve;
• managing traffic flow into train flow is the main task of freight
train formulation plan (for short “train formulation plan” or
“formulation plan”);
10
The definition of car flow organization
– Converting the car flow into train flow is called wagon
flow organization;
– Accordingly, the plan of converting the wagon flow
into train flow is called formulation plan. Specifically,
wagon flow organization mainly resolves two
problems:
(1)How to marshal trains in every direction of
road network
(2)Every branch absorbs what kind of wagon
flow
11
Common operations of car flow organization
Freight flow
In a certain period, freight flow is formed by transporting
goods from the place of dispatch to place of delivery。
1. Freight volume
The total sum of goods delivered from every station, is
also the total sum of flow volume from each branch,
N Ni n j (t)
At the formula: Ni —goods tonnage of each station, t;
nj —freight volume of each branch, t
12
2. Density of freight traffic:
The total sum of goods traffic through every district, that is:
D Di (t)
Where Di —Goods traffic through every district, t
3. Freight turnover:
The total sum of a product of the density of freight traffic and
length in every district
T Di Li (t km)
13
4.Average haul of freight traffic
The ratio of freight turnover and freight volume
T
S (km)
N
14
Fright Train Formation Plan
Content of formulation plan
The questions resolved by formulation plan:
(1)which stations to formulate;
(2)planning trains with corresponding stations;
(3)what kind of trains to be marshaled
(4)what direction of car flow can be marshaled
(5)the way to marshal the wagon flow into train
mixed unit train or grouping; group with station;
formulation with order of stations
(6)Arrange different train numbers
15
7.3 Train Diagram and Carrying Capacity of Line
Train diagram is to indicate the range of operating trains and
in railway stations or through the time to send the technical
file, which provides train occupies the interval procedures,
train arrival and departure of each station (or through)
time, the train in the run-time interval, the train stops at the
station and the locomotive routing time, weight and length
of trains, train the whole way the basis of the organization
Function
① railway enter the market, competing products in the market;
② railway transport enterprises to train safe, on-time operation
and cost-effective to organize the work of the train rail
transport production plans;
16
Carrying Capacity of Line
1.Definition
In the conditions of using certain types of rolling stock and
certain train operation organizational methods, the maximum
number of trains can be passed by a variety of fixed equipment in
railway section in unit time (usually one night)
2.Classification:
• Designed carrying capacity
• Existing carrying capacity
• Required passing capacity
17
• The carrying capacity of the block Section can be
calculated according to the following fixed equipment :
Block section
station
Depot equipment and conditioning
equipment
Water supply equipment
Electrified railway power supply equipment
19
7.4 Organization of Station Operation
Receiving-departure operation
Blocking device: To ensure trains run at section (or
blocking section) intervals, only one train in the same
section is allowed to run in a main line at the same
time, preventing that the trains in the same direction
run into each other or that the trains in the opposite
directions make collision .
21
Shunting operation of stations
25
Key indicators of station work
1. Indicators of the Numbers
Number of Loading and unloading cars
Tonnage of cargo sent,
Number of Sending and receiving trains and cars
Number of inbound and outbound car handled
2. Quality indicators
Remain time of a goods vehicle
Average remain time of transit trains
Punctuality rate of freight trains at departure
26
Railway Traffic Production Plan
and Railway Traffic Control
Railway transportation production plan
Railway transportation production plan is divided
into long-term plans, annual plans and monthly plans
according to its preparation period ,and is made up of
month Railway goods transportation plan and Railway
transportation technical plan.
key comprehensive index of Rail transport
1.Railway transport density:
2.Truck turnaround time:
3.Freight locomotives's product per day:
4.Tonne-kilometer cost of conversion: 27
Rail transport Dispatching
Basic tasks:
• Proper organization of transportation and production,
guarantee or exceed transportation and production tasks
and technical indicators.
At the same time, the vehicle distribution and the
composition of traffic must be in the normal range as
technical plan requires.
Mequanent M.
(AAiT)
May, 2013
29