Ref. No.
_______________ Date____________________
TECHNO-COMMERCIAL OFFER
SEWAGE TREATMENT PLANT
CAPACITY 5 KLD
MBBR TECHNOLOGY
FOR
M/S SALUJA STEEL.
JHARKHAND
PREPARED&SUBMITTED BY:
Shivani Enterprises
Sehorpain, Jawalamukhi,
Kangra (HP)- 176031
Ref. No._______________ Date____________________
Ref. No.: SE/Offer/2425/5K/06 Dated: 04th June, 2024
To
Kind Attn:- Mr. Saluja.
Subject: Techno-Commercial offer for Sewage Treatment Plant of 5 KLD capacity
based on MBBR Technology.
Dear Sir,
With reference to the above-mentioned subject and discussion held with your
goodself regarding the installation of 5 KLD Sewage Treatment Plant based on MBBR
Technology. In this regard, please find detailed Techno-Commercial offer for the same.
Scope of Work
The scope of work includes Design, Fabrication & Supply of Electro-Mechanical equipment
supplied for 5 KLD Sewage Treatment Plant based on MBBR Technology excluding civil
work as per the specifications attached herewith.
We feel pleasure to state that our team is dedicated towards their job and our prior moto is the
client satisfaction. Our team is highly qualified and has good experience in the waste water
management and our efficiency has been appreciated by the various reputed concerns.
We hope you will find our offer technically suitable to your requirements. Should you need
any further clarification/specification please feel free to call.
We look forward for your valued order.
Thanking you and assuring you of our best services at all times.
For Shivani Enterprises
SD/-
Er. Puneet Sharma
Authorized Signatory
Encl. As per annexure attached herewith.
Ref. No._______________ Date____________________
ANNEXURE – I
DESIGN DATA
Flow Rate : 250 ltr/ hr
Running Hours : 20 hrs
Nature of Waste Water : Domestic Sewage.
Mode of disposal of Treated water
Recycling in Gardening
Recycling in Flush Tanks
Recycling in Washing floor
Recycling in Car washing
Cooling Towers
Ref. No._______________ Date____________________
2. ANNEXURE-II Process Description
The different streams of effluent coming to the Sewage Treatment Plant comprising of
the Waste Water from different processes shall be taken to existing Equalization Tank.
Then sewage shall be taken into FLUIDIZED MOVING BED BIO-REACTOR (FAB)
for biological oxidation; here air will be diffused from bottom through
Diffuser/Nozzles by the Twin Lobe Air Blower. The organic load will be reduced with
the help of attached growth on synthetic media and dissolved oxygen. The BOD/COD
loads are being reduced in FAB Bio Rector.
From FAB Bio Reactor the effluent shall go into Secondary Tube Settler. In the
Secondary Tube Settler provision of Tube Deck Media is made to make the design
compact. The Effluent shall be feed in the Secondary Tube settler with upward flow.
The sludge settles down and the clear supernatant is collected at the top through
launder. Sludge shall be continuously pushed toward the bottom well and will be
pumped from bottom by Return Sludge Pump into FAB for Sludge Activation
Process. The excess quantity of sludge will be pumped to Sludge Drying Beds for sun
drying before final disposal as manure.
The over flow from Secondary Tube Settler shall discharged into the existing pre-
filtration tank. From this tank effluent will be passed through the Dual Media Filter
with the help of Filter Feed Pump to remove the suspended particles present in the
colloidal form and for polishing of the effluent. The treated effluent will be used for
Horticulture/ Disposal.
Ref. No._______________ Date____________________
FLOW SHEET OF SEWAGE TREATMENT PLANT
COLLECTION TANK
MBBR TANK
Filterate
SLUDGE SECONDARY TUBE AIR BLOWER
SETTLER
FILTER FEED TANK
SLUDGE PRESSURE SAND
DRYING BED FILTER
ACTIVATED
CARBON FILTER
OUTLET
Ref. No._______________ Date____________________
3. ANNEXURE-III Detail of Component for single unit
3.1 Skid Mounted STP
Detail
MBBR Tanks 01 No
Secondary Tube Settler 01 No
MOC MSEP
Thickness 4mm
Make SE
Supporting and Finishing
Angle Suitable
Channel Suitable
3.2 Raw Sewage Transfer Pump
Quantity 01 No.
Capacity 2.0 M3/Hr @ 10 M Head
MOC C.I.
kW/HP 0.375/0.5
Make Lubi/ Kirloskar/CRI
3.3 Ring Type Air Blower
Quantity 02 Nos. (1W+1S).
Capacity 25 m3/Hr
Blower Type Ring Type
Motor
Ref. No._______________ Date____________________
Quantity 01 No.
HP 0.5
3.4 Filter Feed Pump
Quantity 01 No.
Discharge 2.0 M3/H @ 22 M Head
MOC C.I.
kW/HP 0.375/0.5
Make Kirloskar/Lubi/CRI
3.5 Return Sludge Pump
Quantity 01 No.
Discharge 1.0 m3/Hr @ 8-10 M Head
kW/HP 0.37/0.5
MOC CI
Make Kirloskar/Lubi/CRI
3.6 Pressure Sand Filter
Quantity 01 No.
Size 250 mm Dia x 1300 mm Ht
Media Gravels, Sand Media
MOC FRP/M.S.
Make Pentair/SE
3.7 Activated Carbon Filter
Quantity 01 No.
Ref. No._______________ Date____________________
Size 250 mm Dia x 1300 mm Ht
Media Activated Carbon
MOC FRP/M.S.
Make Pentair/SE
3.8 Tube Deck Media
Quantity 01 Lot
Size 120 X 44 X 750 mm
Media Type Hexagonal Chevron Type
MOC PVC
Make EWS/PP
3.9 FAB Media
Quantity 01 Lot
Size 16 X 22 mm
Media Type Trapezoidal Cylindrical Type
MOC PP
Make EWS/PP
3.10 Interconnecting Pipe Line and Valves
Quantity 01 Lot
Size 1”, 1.5”
MOC uPVC
Make Supreme/Astral/Prince/Ashirwad/Equivalent
3.11 Fine Bubble Diffusers
Ref. No._______________ Date____________________
Quantity 01 Lot
Size 66 X 610 mm
MOC EPDM/Silicon
Make EWS/PP
3.13 Electrical Panel
Make BCH/L&T/Schneider
Quantity 01 No.
Ref. No._______________ Date____________________
4. Annexure-4 Schedule of Prices / Payment.
Description Rate Amount
(₹) (₹)
1. Design, Fabrication, Supply of Sewage Treatment 3,30,000/- 3,30,000/-
Plant based on MBBR Technology of capacity 5 KLD
with Electro-Mechanical equipment (As Annexure 3)
excluding civil work.
15,000/- 15,000/-
2. Installation Charges
GRAND TOTAL 3,45,000/-
Rs. Three Lakh Forty Five Thousand Only
(GST @ 18% Extra)
Ref. No._______________ Date____________________
5. Annexure-5 Client’s Scope
1) Any type of Exhaust system at site.
2) To make any weather proofing shelter to protect motor/ starter etc.
3) Any type of flooring at site.
4) Collection Tank for Sewage separately.
5) Any type of civil work.
6) Any drainage system for surplus water.
7) Any other work not specified in the offer.
8) The incoming Effluent shall be available to us in a separate Pipe within the battery
limit.
9) The treated water shall be carried-out by you from the outlet point of the system
10) Power shall be given to us to energize the STP.
11) Leveled site should be provided to us.
12) Suitable Electricity & Water to execute work at night should be provided by you
during work.
13) Main power cable for running of unit will be provided to our Electrical Control Panel
by you.
14) Freight & unloading plant.
15) All local approvals.
16) Tools, tackles, man power, storage facility for the safety of the equipment and other
utilities during erection and testing.
17) Any type of NOC from any Govt Deptt.
18) Operator for Sewage Treatment Plant.
19) Disposal of Sludge.
20) All chemicals required for Effluent Treatment.
21) Dismantling of existing plant (if any).
22) Any cable required for STP.
23) Boarding & Lodging of the technical team shall be provided.
Ref. No._______________ Date____________________
6. Annexure-6 Condition of Contract
PAYMENT TERMS (DD/RTGS favoring Shivani Enterprises)
Our Bank Details
NAME : SHIVANI ENTERPRISES
BANK : CENTRAL BANK OF INDIA
BRANCH : JWALAMUKHI, HP
ACCOUNT NO. : 532850416
IFSC : CBIN0282538
Payment : 60% as advance along with clear Purchase Order
Balance against proforma Invoice before delivery.
Installation Charges : Extra as mentioned in Annexure-4.
Transportation : Extra as per Actual.
G.S.T : Extra @ 18%.
VALIDITY:
Unless stated otherwise, or extended in writing subsequent submission of offer our quotation shall
remain valid for acceptance for a period of 15 days only from the date of this offer.
DELIVERY
Within 4-8 weeks from the date of receipt of technically and commercially correct purchase
order along with advance.
TESTING OF TREATMENT PLANT:-
1. Installation & Testing will be done within 7 days after material transfer at site, Testing will
be done with fresh water if Effluent is not available at site.
2. In case Plant is not tested after supply within a period of 10 days due to non-availability of
Effluent or any other reason whatsoever, the plant shall deemed as successfully tested.
Ref. No._______________ Date____________________
WARRANTY
Bought out components are guaranteed by us only to the extent of guaranteed given to us by
our suppliers.
This warranty is valid subject to:
a) Installation having been complete within 2 months of dispatch of the equipment as per our
installation instruction.
b) The supply/installation having been formally accepted as per the handling over clause.
c) The equipment or part there of not being subject to accede alteration abuse or misuse.
d) The equipment being operated and maintained as per our operation and maintenance manual.
The Warranty does not cover the damage caused by:
a) Improper Electrical supply,
b) Non-qualified personnel loading or unloading, moving or installing the equipment,
c) Fire, Explosion Flood or similar perils.
d) Unauthorized modifications or alterations of the equipment,
e) Improper or inadequate maintenance.
f) Any modification or alteration in the system after installation without authorization render
warranty void.
NOTE:-
1. In order to facilitate the Installation & Testing, we sometimes send extra material while
dispatching the material. Once the Installation / Testing will over, we reserve the option
to take back unused material and customer shall have no lien on such material unless any
extra quantities has been supplied for stand by working / performance of the equipment /
plant.
2. Yours Plant has been designed as per the parameters given by you.
JURISDICTION:
All contracts between purchaser and ourselves are deemed to be entered into at Kangra, and are
therefore, subject to the jurisdiction of court at Kangra.