0% found this document useful (0 votes)
101 views1 page

Pasoš Montažnih Nosača

Uploaded by

qbfnqwrvfm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views1 page

Pasoš Montažnih Nosača

Uploaded by

qbfnqwrvfm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Datum/ Date: Report no.

ZAPISNIK O IZRADI MONTAŽNOG AB ELEMENTA / ID OF RC PRECAST ELEMENT

Projekat:
Objekat:
Vrsta elementa:
Tip elementa:

Beton/Concrete: Pozicija montaže/Assembling position:


Marka betona/ Concrete class: Traka/Lane:
Vodonepropusnost/Water penetration: Polje/Span:
Otpornost na mraz /Frost Resistance: Oznaka Nosača/Beam Mark:

Vrsta Provere / Rezultat Kontrolisao/


Opis Radova / Datum/ Controlled by: Napomena /
Type of ispitivanja /
Description of Works Date Comments
inspection * Test Results Izvođač/Contractor: Nadzor/Supervisior:

Provera pre betoniranja / Inspection Before Concrete Works

Armatura / Reinforcement V

Trasa zaštitnih cevi / Ducts routes V

Oplata / Formwork V

Betoniranje / Concreting V

Provera tokom betoniranja / Inspection During Concreting


Uzimanje uzorka/
R
Test Sampling
Provere nakon betoniranja / Inspection After Concreting

Provera čvrstoće betona pre demontaže oplate/


Checking of Concrete Strength Before Formwork R
Removal

Demontaža oplate /
V
Formwork Removal

Provera čvrstoće betona nakon 28 dana/ Checking


R
of Concrete Strength After 28 Days

Provere pre prednaprezanja kablova / Inspection Before Prestressing

Užad, kotve i druge komponente /


V
Strands, Anchorages and Other Components

Provera čvrstoće betona pre utezanja kablova/


Checking of Concrete Strength Before R
Prestressing
Provere tokom utezanja kablova / Inspection During Prestressing
Faza Ia - utezanje kabla K1/
Phase Ia - Stressing cable K1 R
Utezanje kablova/ Faza Ib - utezanje kabla K1/
Post-Tensioning Phase Ib - Stressing cable K1 R
Faza II - utezanje kabla K2 (i K3)/
Phase II - Stressing cable K2 (K3) R
Faza I - Injektiranje kabla K1/
Phase I - Grouting cable K1 R
Injektiranje/
Grouting Faza II - Injektiranje kabla K2 (i K3)/
Phase II - Grouting cable K2 (i K3) R
Faza I/
Provera čvrstoće injekcione smese Phase I: R
nakon 28 dana/ Checking of Grout
Faza II/
Strength After 28 Days Phase II: R
Transport i montiranje nosača / Transport and Installation of Beams

Transportovanje nosača do mesta ugradnje/


V
Transportation of beams to the installation place

Montaža nosača na ležišnu gredu/


V
Placing of Beam on Bearing Beam
Karakteristike / Characteristics:

TIP 1; TIP 2; TIP 3;


H=1,6m TIP 4;
H=1,6m H=1,8m H=1,6m
L=24,4m L=29,4m L=35,4m L=35,4m

* 1) V = Visual inspection 2) R - Report 3) N/A - Not Applicable

Izvođač radova/Contractor Nadzorni Organ/ Engineer