10 661800 0000100201 Mah Civ MST 000023 - 02
10 661800 0000100201 Mah Civ MST 000023 - 02
1
 Work Order No.        100201/25
                       WO 25- Method Statement & Risk Assessment for Existing Asphalt Milling
 Document Title
                       Works -Highway 80-RD-12.1 & RD-16.1
 Document No.         10-661800-0000100201-MAH-CIV-MST-000023
Revision 02
10-661800-0000100201-MAH-CIV-MST-000023 Rev.02                                                      1 of 1
        WO 25- Method Statement & Risk Assessment
         forExisting Asphalt Milling Works -Highway
                    80-RD-12.1 & RD-16.1
         10-661800-0000100201-MAH-CIV-MST-000023
                  Date 25/08/2022 - Rev.02
                                             –
10-661800-0000100201-MAH-CIV-MST-000023_02            1 of 15
Document History
10-661800-0000100201-MAH-CIV-MST-000023_02                                              2 of 15
                               MOFARREH AL-HARBI
                                   & PARTNERS
  Document Number:                                                    Revision: 02
                                      DOCUMENT REVISION
                                            HISTORY
 Revision     Issue Date        Prepared By          Issued For     Signature
     01      19 July-2021        IMRAN ARIF            Code
                                                         - B
10-661800-0000100201-MAH-CIV-MST-000023_02                                 3 of 15
Document Number:                                                 Revision: 02
TABLE OF CONTENTS
1. Scope 3
2. Purpose 3
3. Reference Documents 3
4. Definitions / Abbreviations 3
5. Responsibilities 3
7. Methodology 4
8. HSE Requirements 5
13. Appendices 6
  10-661800-0000100201-MAH-CIV-MST-000023_02                        4 of 15
Document Number:                                                                                           Revision: 02
      1.         Scope
                 The scope of the method statement shall be milling of existing asphalt before start jointing the new
                 asphalt, obtained after milling of the Binder & Wearing course as shown on typical sections drawing
                 illustration for asphalt mainroad.
       2.        Purpose
                   The purpose of the method statement is to provide the safe sequence of activities from setting out,
                   layout at location required for removal of the asphalt pavement. Ensure all milled area shall be
                   protected of the barricades by using concrete barriers, warning signs.
3. Reference Documents
Definitions / Abbreviations
Project: Street Lighting & Water Network Batching Plants & Laydown Yard
5. Responsibilities
             5.1      Project Manager is responsible for ensuring on time submission list of deliverables, resources
                      mobilization (manpower and equipment), technical submittals per schedule, and obtained permits
                      (if necessary) from relevant authorities. Ensure the project completion within budget and contract
                      duration without sacrificing the quality and safety of the project.
 10-661800-0000100201-MAH-CIV-MST-000023_02                                                                     5 of 15
Document Number:                                                                                     Revision: 02
        5.2     Construction Manager is responsible for all implementation of construction activities per
                approved method statement inclusive of ensuring that all quality and safety measures are
                implemented and permits are obtained from the relevant authorities connected with the scope of
                works.
        5.3     Quality Manager is responsible for ensuring the quality and correct implementation of works as per
                approved PQP, and the sequence of work as per approved method statements including testing,
                commissioning and inspection such as; acceptance requirements, tests frequency, etc. as per
                approved ITP /checklists in accordance to the NEOM project specifications. Also ensure all
                procured materials are from approved vendors/suppliers, materials delivery inspection are
                conducted with PMC as per approved MIR (if any).
        5.4     Safety Manager is responsible for the enforcement of all internally developed and used, as well as
                external safety procedures and shall ensure that all the works carried out are done in strict
                compliance to minimum standards as set out by NEOM as well as where procedures does not
                exist, best practice.
        5.5     Site Engineer is responsible for the workers and equipment deployment on site for electrical works
                and water network operation as shown on IFC drawings and approved method statement. He is
                reporting to Construction Manager in daily basis regarding work planning, status of work, issue
                and concern that may affect to performance of the work to resolve immediately.
        5.6     Supervisor/ Foreman is responsible for closely supervise the task assigned to them and ensure all
                instructions are follow for electrical, or mechanical work, earthwork backfilling works on site in
                daily basis ensuring daily production rate requirements are meet as per work schedule. Also ensure
                when hauling routes having adequate safety, road signage, and speed limits.
        5.7     Surveyor is responsible for carrying out pre-construction survey to fix the locations and
                corresponding elevations as per the approved Drawings.
        5.8     Others Employees are: Safety Officers, QC Engineers, Skilled & Unskilled such as; Asphalt paving
                workers, Demolition and restoration workers.
  10-661800-0000100201-MAH-CIV-MST-000023_02                                                              6 of 15
Document Number:                                                                                 Revision: 02
7 Methodology
            A. Preparatory Works;
            7.8    Before any execution of work will begin, ensure the mobilization of plant and
                   equipment, operators, drivers, surveyor crew for this activity have been mobilized to
                   the jobsite.
            7.9    Conduct Safety induction to employees newly mobilized for this job, then distribution
                   of Personal Protective Equipment (PPE).
            7.10   Conduct equipment inspection by Safety dept. for newly mobilized equipment to
                   ensure are in good working condition such as; to check that no oil & diesel leakage,
                   good tires, lights, reversing alarm, workable seat belt, foot brake, hand brake, mirrors,
                   available and workable fire extinguisher, as per inspection checklist.
            7.11   Check to ensure have valid driving licensed, Iqama’s, TUV for operator, medical
                   insurance, safety passport to all employees. Consequently, to check and ensure
                   equipment documentations such as; MVPI, vehicle registration, insurance, are all
                   updated.
            7.12   Before to start the activity, Supervisor/Foreman shall lead a toolbox meeting with all
                   employees allocated to that activity in order to identify hazards associated to that
                   activity in that specific location and explain necessary procedure to mitigate risk of
                   accident associated to that task.
            7.13   After meeting employees will sign the attendance sheet and Supervisor will keep the
                   records until the end of the day.
            7.18 Asphalt Paving Requirements for Asphalt Binder & Wearing Course:
            7.19   All Asphalt Paving shell be as per approved Method of Statement 10-661800-0000100201-
                   MAH-CIV-MST-000013.
  10-661800-0000100201-MAH-CIV-MST-000023_02                                                         7 of 15
Document Number:                                                                                     Revision: 02
8. HSE Requirements
                          All personnel involved in the above activities shall follow the DSTI (Daily
                           Safety TaskInstruction) requirements and the Alharbi Project Safety Plan.
                           All safety measures and Internal Company Safety Procedures shall be
                           implemented in alignment with NEOM Standards.
                           Where applicable, barricades, warning signs or safety signs shall be fixed
                           around theconstruction area as per NEOM Standards.
                           If at all necessary, special work permits (as applicable) shall be
                          obtained prior tocommencing any work.
                          Stock piles of fill materials shall be kept well back from perimeter of sand
                          disposal andtops of embankments.
                           All earth moving equipment shall be operated and maintained by
                           Qualified andapproved personnel.
                           All work areas shall be kept clean and tidy during work activities.
                          All requirements of the risk assessment shall be communicated to the
                           appropriate workforce.
                            Emergency Response Plan will be communicated and posted where applicable.
                           Safety Induction will be given to all employees prior to
                           commencement of work activities. As well as to new employees, and
                           where applicable to visitors.
                           All relevant personal Protective Equipment (PPE) shall be provided and
                           worn by allpersonnel when entering the construction site.
                           Frequent HSE Training will be provided to all personnel
                           Toolbox meeting will be conducted daily as well as DSTI Discussions.
                Each employee will be issued with personal protective equipment as set out in the
                Safety plan and internal PPE issuing procedure and enforcement of the wearing of
                the PPE will be done according to procedure. Specifications for personal protective
                equipment shall comply with the relevant minimum construction site standards.
  10-661800-0000100201-MAH-CIV-MST-000023_02                                                             8 of 15
Document Number:                                                                               Revision: 02
            Hard Hat: Employees are responsible for wearing hard hats with chin straps during any work
            activity that is conducted on heights, and where possibility of head injury is present. The hard
            hat must be worn when working within a construction site.
            Safety Vest: High visibility apparel (vest, shirt, or jacket) of orange, strong yellow-green or
            fluorescent versions of these colors must be worn whenever working within any highway right
            of way or on a construction site.
            The following is the minimum personal protective equipment that will be provided to
            employees:
                          Safety glasses (Clear / Dark)
                         Dust masks
                         Gloves
                          Face mask
                          Hearing protection
                          High visibility apparel
                          Hard hat
                          Safety Shoes (Steel toe cap, ankle height)
RA (See attached).
12. Appendices
  10-661800-0000100201-MAH-CIV-MST-000023_02                                                       9 of 15
                                                                           EXISTING ASPHALT MILLING WORK RISK ASSESSMENT
                                                                                                                                                     Revision                                   02
Contract                                                HIGHWAY 80 UPGRADE 100201 WO#25
Task Description                                        Risk Assessment for Existing Asphalt Milling Works -Highway 80-RD-12.1 & RD-16.1
Task Site Location                                      Highway 80-RD-12.1 & RD-16.1
TOOLS &EQUIPMENT IN USE:                                Asphalt milling machine/Asphalt cutter/ Diesel Tanker / Water tanker / Dump Truck
                   Negligible                                            Med           Low           Low             Low        Low              RISK RATING (Likelihood x Severity)
           Minor cuts & bruises or sickness/                  1                                                                            1-4    LOW RISK (No further action required)
       Nuisance release with no adverse impact                            10            4             3               2          1
                                                                                                                                           5-10 MEDIUM RISK (Procedure to be available)
            Likelihood Rating                                              5             4             3               2          1        11-25 HIGH RISK (Full time supervision present)
              10-661800-0000100201-MAH-CIV-MST-000023_02                                                                                                                             10 of 15
                                                              EXISTING ASPHALT MILLING WORK RISK ASSESSMENT
            10-661800-0000100201-MAH-CIV-MST-000023_02                                                                                                                     11 of 15
                                                             EXISTING ASPHALT MILLING WORK RISK ASSESSMENT
           10-661800-0000100201-MAH-CIV-MST-000023_02                                                                                                                12 of 15
                                                                   EXISTING ASPHALT MILLING WORK RISK ASSESSMENT
                                                                Hearing loss or
                                                                damage to                              Ear protection to be used
                                  Noise during milling of
                                                                employees in the       3 4      12     Ear protection to be inspected by              2   2    4
                                  asphalt
                                                                nearby vicinity                        supervisors and use to be enforced.
            10-661800-0000100201-MAH-CIV-MST-000023_02                                                                                                                       13 of 15
                                                           EXISTING ASPHALT MILLING WORK RISK ASSESSMENT
DATE
           10-661800-0000100201-MAH-CIV-MST-000023_02                                                                                                               14 of 15
                                                      EXISTING ASPHALT MILLING WORK RISK ASSESSMENT
10-661800-0000100201-MAH-CIV-MST-000023_02 15 of 15