Aayush Neupane - Design Report
Aayush Neupane - Design Report
Dhulikhel, Kavre
Department of Electrical and Electronics
Power and Control
Where,
L = length of transmission line = 240 Km
P = Power to be transmitted = 390 MW
Cos 𝜙 = Power factor = 0.95
Nc = Number of circuits
By using the formula presented above, we can calculate the most economical voltage (Veco).
Thus,
For Nc = 1 (Single Circuit),
Standard Voltage levels are:
240 390∗1000
Veco = 5.5 * √( 1.6 + 0.95∗1∗150)
66 KV
132 KV
= 295.511 KV
220 KV
(The nearest Standard Voltage will be 400 KV) 400 KV
500 KV
For Nc = 1 (Single Circuit), 700 KV
750 KV
240 390∗1000
Veco = 5.5 * √( 1.6 + 0.95∗2∗150)
= 214.318 KV
(The nearest Standard Voltage will be 220 KV)
The Multiplying factor (MF) limit for the 240 km is 1.75 from the standard table.
Circuit Criteria
Surge Impedance Loading:
For Single Circuit line:
Zc = 400 Ω
Veco = 400 KV
SIL = V2eco/Zc
= 400 MW
Multiplying factor:
𝑃
MF = 𝑆𝐼𝐿
= 1.611
Where,
Equivalent dry 1 min voltage is taken from standard table = 435 KV
Equivalent Voltage Level = 435 * 1.15 * 1.1 *1.2= 660.33 kV
From Standard Table, number of discs required to withstand above equivalent voltage
level = 12
b) Voltage level for wet condition = Equivalent wet 1 min voltage * FOWR * NACF * FS
Where,
Equivalent wet 1 min voltage is taken from standard table = 395 KV
Equivalent Voltage Level = 395 * 1.15 * 1.1 *1.2= 599.61 kV
From the Standard Table number of discs required to withstand above equivalent
voltage level = 16
II) Number of Insulator discs required for temporary O/V:
Temporary O/V = Earth Factor (EF) * Maximum system voltage
= 0.88 * (220 * 1.1)
= 212.96 kV
Equivalent voltage (Veq) = Temporary O/V * √2 * FOWR * NACF * FS
Equivalent Voltage (Veq) = 212.96 * √2 * 1.15 * 1.1 * 1.2
= 457.17 kV
Since, in this case we have to see the worst-case scenario i.e. in the wet condition.
Thus, from standard table number of insulator discs required to withstand above
equivalent voltage = 12
III) Number of Insulator discs required for switching over voltage:
Voltage level = switching o/v * switching to impulse ratio * FOWR * NACF * FS
Where,
Switching to impulse ratio (SIR) = 1.15
SSR = Switching Surge Ratio = 2.8 (For 220 kV)
√2
Switching O/V = ( ) * 220 * 1.1 * SSR
√3
After calculating the value of ‘a’ we can find the other Air Clearance parameters as follows:
• Maximum swing angle = 𝜙max = 45°
• Shield angle = 𝜙sh = 45°
• Shield Length (l) = asec𝜙
• Tower width (b) = 1.5a
• Cross Arm Length (CL) = a(1+tan𝜙)
𝑏
• Distance of the earth wire from the conductor (d) = √3(CL + )
2
(𝑙+𝑎)
• Vertical distance between two adjacent conductor (y) = 𝑥 𝑙+𝑎
√1−( )^2( )^2
𝑦 2𝑎
Where 0.25<x/y<0.33
Continuous Selection
Continuous Current Carrying Capability:
P = 390 MW, Nc = 2, VL = 220 kV, cos𝜙 = 0.95
Line current is calculated as
𝑃 390∗103
Line current (IL) = = = 538.676
√3∗𝑉∗𝐶𝑂𝑆∅∗𝑁𝑐 √3∗220∗0.95∗2
Comparing the Value of the Current with the Current capacity form the given standard ACSR
conductor table, the Conductor “KUNDAH” with current capacity 566 Amperes is selected.
I) Transmission efficiency Criteria:
For KUNDAH Conductor:
Resistance at 20℃(R20) = 0.07311 Ω/Km
Coefficient of Resistivity (α20) =0.004 /0C (For Aluminum)
This efficiency is <94%. So, this conductor cannot be used. To get the higher efficiency we
proceed in the same way and calculate efficiency for other Conductors.
Conductors Resistance (20℃) Resistance (65℃) Efficiency (%)
Sheep 0.07730 0.091214 94.023
Zebra 0.06868 0.081042 94.063
Moose 0.05595 0.066021 95.163
Deer 0.06786 0.080075 94.134
Elk 0.06110 0.072098 94.710
From the above conductors let us select conductor ‘SHEEP’ for the further criteria.
II) Voltage Regulation Criteria:
The SHEEP conductor has 37 strands (30 Aluminum strands and 7 steel strands).
Diameter of conductor (D) = 27.93mm
Radius of the conductor(R) =13.965mm
GMR for inductance (r’) =0.768R =0.778 * 13.965 =10.72mm = 1.086 cm
GMR for capacitance (r) = R = 13.965 mm. = 1.3965 cm
𝐷𝑎𝑐
Dab = √( + 12.542 ) = 12.86 m
2
Now,
2𝜋𝜀
Capacitance per unit length(C) = 𝐺𝑀𝐷 F/m
ln( )
𝐺𝑀𝑅𝑐
D = A = 0.9672 + j0.006613
Voltage regulation <11% so this conductor can be used. Voltage regulation Criteria has also
been fulfilled.
Since Vci> Maximum system voltage (242.2 kV), there is no corona effect on SHEEP
conductor. So, Corona Inception Voltage criterion is satisfied and all the technical criteria is
met by the Conductor.
Hence the five best bundled conductors which satisfy all the criteria are:
1. Sheep
2. Deer
3. Zebra
4. Elk
5. Moose
ϵ= Modulus of Elasticity
α= Coefficient of linear expansion
A = Cross-section area of conductor
θ2 = Temperature at normal condition = 270C
θ1 = Temperature at toughest condition = 00C
w1 = per unit length conductor weight @ toughest condition
w2 = per unit length conductor weight @ stringing condition
Four Different conductors below conductor Sheep in ASCR conductor table is chosen. Hence
Tension calculation will be done for conductor “Sheep, Deer, Zebra, Elk, and Moose” with
Span length 250 m, 275 m, 300 m, 325 m, and 350 m. Tensions for Toughest, Stringing and
Easiest condition are calculated and tabulated below:
Sample Calculation
For Conductor Sheep (250 m span)
Area of conductor (A) = 462.60 mm2
Coefficient of linear expansion (α) = 17.73*10-6 / 0C
Modulus of Elasticity (ε) = 0.789*10^6 kg/cm2
Ultimate Tensile Strength (UTS) = 15910 kg
Wt. of conductor per unit length (wc) = 1726 kg/km
Wind Pressure (wp) = 100 kg/m2
Conductor diameter (d) = 27.93 mm
Thickness of ice (t) = 10 mm = 0.01 m ؞
Wt due to wind (Ww) per km = (wp*1000)*(d*2/3) kg/km
= 100*1000*27.93*10-3*2/3
= 1862kg/km
Wt due to ice loading (Wi) = π t (d+t) ρice *1000 kg/km
= π * 0.01 (0.02793+0.01) * 950 *1000
= 1132.02 kg/km
2
؞Wt. @ toughest condition (w1) = √(Wc + Wice) + Ww 2 )
= 3411.063 kg/km ؞
Wt. @ Stringing Condition (w2) = Wc = 1726 kg/km ؞
Wt. @ Easiest Condition (w3) = Wc = 1726 kg/ km
Temperature @ Toughest condition (ɵ1) = 0℃
Temperature @ Normal Condition (ɵ2) = 27℃
Temperature @ Easiest Condition (ɵ3) = 65℃
Calculation of T1
T1 = 𝑈𝑇𝑆/ 𝐹𝑆 = 15910/2 = 7595kg
Calculation of T2
(𝑊12 𝐿2 )
𝐾1 = −𝑇1 +∝ (𝜃2 − 𝜃1 )𝐴 ∈ + 24𝑇12
= -3939.80
(𝑊22 𝐿2 )
k2 = 𝐴∈
24
= 28244293719.56
𝑻𝟐 = 5048.133 Kg
Calculation of 𝑇3
(𝑊12 𝐿2 )
𝐾1 ′ = −𝑇2 +∝ (𝜃3 − 𝜃2 )𝐴 ∈ + 24𝑇22
= 1733.52
(𝑊22 𝐿2 )
k2’ = 𝐴∈
24
= 28244293719.56
T3 is given by stringing equation
𝑇32 (𝑇3 + 𝐾1 ′) − 𝐾2 ′ = 0
𝑻𝟑 = 2563.71 Kg
Table 1 Calculation of Weight @ Toughest Condition
S.NO Conductor Wc Ww W1 W2 T1(Kg)
1 Sheep 1726 1862 3411.06 1726 7595
2 Deer 1977 1992.66 3742.18 1977 9115
3 Zebra 1623 19.08 3368.16 1623 6658
4 Elk 2196 2100 4025.70 2196 10120
5 Moose 1998 2118 3874 1998 7175
Table 2 Calculation of T3
S.n Conducto Span K1 K2=K2_ T2 K1_ T3
o r
1 Sheep 0.25 -3939.80 2.824*e10 5048.13 1733.53 2563.17
0
0.27 -3538.20 3.417*e10 4939.12 2985.34 2496.79
5
0.30 -3098.35 4.067*e10 4836.83 4406.02 2437.79
0
0.32 -2620.26 4.773*e10 4742.52 5999.24 2385.90
5
0.35 -2103.92 5.535*e10 4656.74 7766.71 2340.35
0
Sample calculation:
For sheep, W = 1726 kg/km.
L = 0.25 Km.
T3 =2563.17 Kg.
Using the above equation, Dmax = 5.260m.
Let the minimum ground clearance (hg) = 10.08m.
Height of lower conductor (H1) = hg+ Dmax =15.34m.
Height of middle conductor (H2) = H1+y/2 = 18.22m.
Height of top most conductor (H3) = H1+y = 21.11m.
Total height of tower (Ht) = H3+y+d = 31.96m.
Similarly, the maximum sag, H1, H2, H3 and the total height of the tower are calculated and
presented in the table below:
Sample Calculation
For Conductor Sheep
BM due to Power Conductor
= 50897.77 Kg/m
Where,
Ne = No. of earth wire = 1
= 8378.84 Kg/m
Note: All the Value of the Data has been written from the above Table 2 and 4.
Similarly, we can calculate the total bending moment and tower weight for different conductors
at different span length:
Deer 0.250 14.53 17.42 20.30 31.15 8166.49 12770.10 52058.41 78120.31 151115.32 10.805
0.275 15.71 18.60 21.49 32.34 9326.317 13257.94 61154.94 83428.01 167167.21 11.799
0.300 16.94 19.83 22.71 33.56 10557.97 13758.09 71114.28 88930.07 184360.43 12.857
0.325 18.30 21.19 24.07 34.92 11901.31 14315.63 82325.03 95030.18 203572.16 14.059
0.350 19.80 22.68 25.57 36.42 13367.35 14930.56 94920.67 101743.29 224961.89 15.414
Zebra 0.250 16.44 19.33 22.21 33.06 8667.23 13553.16 55312.92 63043.64 140576.91 11.061
0.275 17.99 20.88 23.77 34.62 9983.81 14192.64 65734.41 68110.62 158021.52 12.280
0.300 19.73 22.61 25.50 36.35 11530.09 15024.85 77663.23 73764.76 177982.94 13.797
0.325 21.65 24.54 27.43 38.28 13046.46 15693.08 91303.52 80049.55 200092.62 15.280
0.350 23.76 26.65 29.53 40.38 14820.80 16553.98 106767.86 86921.51 225064.17 17.094
Elk 0.250 14.44 17.33 20.21 31.06 8142.89 12733.20 54579.00 85908.49 161363.60 11.133
0.275 15.47 18.36 21.25 32.10 9257.10 13159.55 63617.40 91031.93 177066.00 12.053
0.300 16.63 19.52 22.40 33.25 10460.45 13631.00 73773.00 96766.88 194631.34 13.090
0.325 17.91 20.80 23.68 34.53 11768.39 14155.75 85148.70 103096.80 214169.65 14.260
0.350 19.32 22.20 25.09 35.94 13191.17 14733.78 97916.70 110087.82 235929.48 15.578
Moose 0.250 15.89 18.77 21.66 32.51 8523.03 13327.64 59642.88 65993.91 147487.47 11.141
0.275 17.26 20.14 23.03 33.88 9770.42 13889.27 70394.90 70809.87 164864.49 12.275
0.300 18.79 21.68 24.56 35.41 11139.98 14516.51 82640.12 76200.00 184496.62 13.572
0.325 20.48 23.37 26.25 37.10 12644.29 15209.33 96506.67 82140.86 206501.16 15.044
0.350 22.33 25.22 28.10 38.95 14295.94 15967.75 112158.69 88644.17 231066.56 16.706
Sample Calculation
For Conductor Sheep,
Length of span = 250m, Wt. of tower = 10.467 Tonnes
Cost per tower = cost per tonnes* weight of tower
= Rs.150000*10.467
= Rs. 1570050.00
Cost of tower per unit length = (962295*641)/160
= Rs.6290012.81
Similarly the cost of tower per unit length of different conductor and different span are shown
in table below:
Table 5 Tower Cost Calculation
Total annual cost per km = Annual energy loss cost + Annual capital cost
Sample Calculation
For Conductor Sheep,
Total cost of power conductor per km = No. of conductors*cost of power conductor per
km/conductor
= 6* (20105*1036+150000*690)*10-3
= Rs. 743252.40
Annual Cost of energy loss per km = PL * LLF * time * cost per unit energy
= 41.81 * 0.3*(365*24)*7.50
= Rs. 82137.72
Total annual cost per km = Annual cost of energy loss per km + Annual capital cost
= Rs. 1598308.99
Similarly, we can calculate the Total annual cost per km for each conductor with their respective
economic span length. The tabulated form of the calculation is shown below:
Conductor Span(Km) Tower Cost of Capital Annual Power Energy Total Annual
cost/L (Rs.) cond/L cost/L (Rs.) Capital loss/L Loss Cost (Rs.)
(Rs.) cost/L cost/L
(Kw)
(Rs.) (Rs.)
Sheep 0.250 6290012.81 746252.40 7036265.21 444667.26 41.76 823137.72 1598308.99
Deer 0.300 6440553.43 853729.20 7294282.63 803596.52 36.66 722614.82 1526211.35
Zebra 0.250 6646969.68 538003.80 7184973.48 791554.15 37.10 731346.68 1522900.84
Elk 0.30 6557271.87 947988.00 7505259.87 826839.46 33.01 650630.20 1477469.67
Moose 0.250 6695044.68 658376.70 7353421.38 810111.72 30.22 595789.85 1405901.58
Hence, From above table, it can be seen that MOOSE is the most economical conductor with
span length of 250m.
A. Electrical Characteristics
The MOOSE conductor has 61 strands with 7 Steel strands and 54 Aluminum strands.
A, B, C, D parameters calculation
𝑍𝑌
A=1+ = 0.96719 + j2.574
2
B=Z = 7.922+j100.9455
𝑍𝑌
C = 𝑌(1 + ) = -0.000000836 + j0.000639
4
B. Mechanical characteristics:
Length of span =250 m
Tension at toughest condition = T1 = 7175 kg
Tension at stringing condition = T2= 5283.56 kg
Tension at easiest condition =T3= 2687.16 kg
Tower Heights:
H1 = 15.89 m
H2 = 18.77 m
H3 = 21.66 m
Ht = 32.51 m
Maximum sag (Dmax) = 5.80 m
Bending Moment on Earth wire due to Wind Force (BMeW) = 8523.03 kg/m
Bending Moment on Earth wire due to Turning (BMet) = 13327.64 kg/m
Bending Moment on Power Conductor due to wind force (BMpW) = 59642.88kg/m
Bending Moment on Power Conductor due to turning (BMpt) = 65993.91 kg/m
Total Bending Moment (TBM) = 147487.47 kg/m
Tower Weight = 11.141 tonnes
Tower Cost per unit Length = Rs 6695044.68
No. of Towers (Nt) = 960
Capital Cost per km = Rs. 7353521.38
Total Annual cost per km = Rs. 1405901.58