Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
Schedule Comparison V.S Revised Schedule Comparison
If you use Oracle Primavera 20.1 and later, Claim Digger, see the bottom of this Schedule
Comparison article.
(Schedule Comparison) Claim Digger is one of Primavera's tools:
P6 Schedule Comparison (Claim Digger) is a very useful tool to find the difference between two
versions of schedule or Baseline Schedules V.S Revised Schedules using Primavera P6 without any
additional software required.
First, let me explain what is the benefit of using the Primavera P6 Built-in tool Claim Digger (now
known as Schedule Comparison in the new Primavera P6 versions). Mainly The Claim
Digger compares two schedules and finds out what is the difference between the two of them,
Differences are identified as per the following terms:
1- Total Float
2- Calendar Name
3- Free Float
4- Critical Activities
5- Activity Name
6- WBS Name
7- WBS Code
8- Primary Constraint Type
9- Primary Constraint Date
10- Actual Expense Cost
11- Remaining Expense Cost
12- At Completion Expense Cost
13- Budgeted Expense Cost
14- Planned Finish Date
15- Early Finish Date
16- Early Start Date
17- Actual Start Date
18- Late Finish Date
19- Late Start Date
20- Planned Start Date
21- Actual Finish Date
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 1 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
22- Original Duration
23- Actual Duration
24- Remaining Duration
25- At Completion Duration
26- Actual Cost
27- At Completion Cost
28- Expense Percent Complete
29- Price Per Unit
30- Budgeted Cost
31- Remaining Cost
32- Activity Percent Complete
33- Duration Percent Complete
34- Physical Percent Complete
35- Units Percent Complete
36- Actual Labor Units
37- Budgeted Labor Units
38- At Completion of Labor Units
39- Remaining Labor Units
40- Activities Added/Deleted
40.1- The following Activities have been added to the project
40.2- The following activities have been deleted from the project
41- Activity Code Assignments Added/Deleted
42- Relationship Differences (Predecessor / Successor Relationships added or deleted)
43- At Completion Units
44- Budgeted Units
45- Remaining Units
46- Remaining Units Per Time
47- Actual Units
48- Budgeted Duration
49- Remaining Duration
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 2 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
50- Resource Assignments Added/Deleted
51- Activity Steps
It will spot any variance between the two versions in the schedule.
When you should use Claim Digger, Applications of using This tool :
1- When you receive a new version of the schedule from the contractor, then you should use Claim
Digger to check what has been changed on the schedule.
2- When you Receive an update of the schedule, you should check that nothing has changed from
the baseline original duration, relationships, and constraints.
3- Before submitting your schedule to the client after a new revision or update, just run a fast check
to ensure nothing goes wrong.
How to work with Schedule Comparison Step by Step :
1- open the Schedule Comparison from the Primavera p6 tools menu as per the following photo:
Once you click on Schedule Comparison from tools, it will open the Visualizer.
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 3 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
This is the Window that will show up, now you need to put a name for the Comparison and Click on
Options to go to the next step.
Now you should choose from the first window the Revised Schedule or the updated one with some
differences from the baseline.
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 4 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
Once you click on Add you will see both of the Projects below and will shift you to General
In General, Choose the report format (HTML or CSV)
HTML Report, Compare two projects' schedules HTML Report
Then it will be shifted to Advanced
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 5 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
In Advanced, it will make you choose the Point of Comparison
It is divided into two sections.
1. Project Information
2. Activity Information
The information here is about everything in the Activity.
Like if your consultant asked you to modify the Relations of some activities and their duration
then you will choose the point of Comparison
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 6 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
Here we want to see if there are any deleted or new Activities and we need to check if there are any
changes in Durations, Dates, Relations, and if any relation is added or deleted.
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 7 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
This is the type of HTML Type of Reports
You will see the changes in the Revised Schedule than the Baseline Schedule
This will be the Last format of the HTML File
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 8 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
Oracle mentioned the following cause of this action:
P6 was installed with the packaged SQLite database. In this Standalone configuration (P6 versions
8.4 to 15.2) using SQLite as the database, this is the expected behavior concerning Claim Digger.
Claim Digger is not available in this database option.
P6 Professional Standalone (r8.4-15.2) using an SQLite database supports all of the Project
Management functions of P6 Professional except for the following:
– Update Baseline
– Claim Digger (Schedule compare)
– Job Services – Jobs cannot be scheduled. However, the user can use the Windows scheduler to
invoke the command line interface to import, export, and run batch reports.
– Risk Analysis
– Any existing Java-based integration components developed by the customer using the P6 Remote
Integration API (RMI) are not supported with an SQLite database.
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 9 of 10
Planning Engineer FZE Project Management & Planning Services and Training
بالنينغ إنجينير م م ح خدمات وتدريب إدارة المشروعات والتخطيط
Article Link: https://planningengineer.net/claim-digger-baseline-schedule-v-s-revised-schedule-
comparison-tool/
---------------
Useful links:
Join our email Newsletter, we send useful free content regularly:
https://planningengineer.net/newsletter/
Our Services https://planningengineer.net/our-services/
Our Courses: https://planningengineer.net/lp-courses/
Support Forums: https://planningengineer.net/forums/
Free Arabic Basic Course Playlist:
https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J
---------------
Keep in Touch:
WhatsApp: +201277767728
Email: [email protected]
English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos
Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906
Linked in: https://www.linkedin.com/company/planning-engineer-est/
Facebook Page: https://www.facebook.com/PlanningEngineerDotNet
Facebook Group: https://www.facebook.com/groups/1138400132963230
Twitter: https://twitter.com/PlanningEEst
Instagram: https://www.instagram.com/planningengineerest/
TikTok: https://www.tiktok.com/@planningengineerest
---------------
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
[email protected] https://planningengineer.net/
Page 10 of 10