STEEL DESIGN I
Section (1)
Components of Structures
+ General Layout
Steel Structures Division
Structural Engineering Department
Faculty of Engineering, Cairo University
Class Code
Attend on Time
Mutual Respect
Smile
No Cheating is allowed
Introduction
Concrete Beam subjected to
Bending Moment around Major Axis
Mx Compression
Concrete
tensile
strength is AS
neglected
Tension
If Mx increases increase d or As
Introduction
Concrete Beam subjected to
Bending Moment around Major Axis
AS’
Compression
Mx
Compression
d
Concrete
tensile
strength is AS
neglected
Tension
If d is limited & As = Asmax Use Compression reinforcement
Introduction
Concrete Beam subjected to
Bending Moment around Major Axis
AS’
Concrete
strength is
neglected d
AS
I-Beam Section usually used for beams and columns in
steel structures
Introduction
Types of Buildings with respect
to Construction Materials
Timber Building Concrete Building
Introduction
Types of Buildings with respect
to Construction Materials
Combined Steel-Concrete Building Steel Building
Introduction
Typical Steel Structures
Industrial Buildings
Introduction
Typical Steel Structures
Multi-storey Bldgs. Sea Platform
Introduction
Typical Steel Structures
The Chicago Skyscraper Time Warner Center 2003
Skyscrapers
Introduction
Typical Steel Structures
Introduction
Typical Steel Structures
Introduction
Typical Steel Structures
Introduction
We will study Industrial
Buildings this year
Steel Frame Steel Truss
Week # Explanation Grading
1 Components of structures + general layout ----
2 Components of structures+ general layout Q. # 1
3 Dead and live loads Q. # 1
4 Crane + Wind loads Q. # 2
5 Tension members
Q. # 3*
Example 2.1, 2.2, 2.3 & 2.4
Compression members
6 Q. # 4 &
Example 3.1, 3.4 & 3.6 5*
Axially Loaded Columns
7 Q. # 6
Example 3.9 & 3.11
Week # Explanation Grading
8 Midterm Break ----
9 Wind Bracing Systems + Loads Q. # 7*
10 Beams: Purlins + Side Girts Q. # 8
11 Beams: CTG + Monorail Example 5.3 Q. # 9
12 Floor Beams Example 5.4 Q. # 10
Beam-columns (Alignment chart)
13 *
Example 6.1
Beam-columns
14 Q. # 11
Example 6.2
Introduction
Advantages of Steel:
Economy
Durability
Design Flexibility
All Weather Construction
Easy Repair
100% Recyclable
Introduction
Preliminary Grading
100%
Term Work Final Exam
30% 70%
Midterm Exam Sheets Quizes
15% ??% ??%
Introduction
Steel Sections
IPE Sections BFI Sections UPN Sections L Sections
T Sections PIPE Sections BOX Sections
Introduction
Steel Sections
General Layout
1. Types of Main Systems
2. Arrangement of Main Systems
3. Roof Slope
4. Roof Covering Materials
5. Side Cover
6. End Gables
7. Wind Bracing System
Dr. Maha Moddather
1. Types of Main Systems
Columns are
allowed on the
Boundary of the
Area
No columns are
allowed at the
60 m
interior space
Clear Height
= 7m
20 m
20 m
Dr. Maha Moddather
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Dr. Maha Moddather
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Span 7 - 10m
Dr. Maha Moddather
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Span 12 – 25 m
Dr. Maha Moddather
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Span 15 - 25m
Dr. Maha Moddather
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Span 25 - 40m
Dr. Maha Moddather
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Span 7 - 10m Span 12 – 25 m Span 15 - 25m Span 25 - 40m
Dr. Maha Moddather
2. Arrangement of Main System
Main System parallel to the Short Direction
Spacing (S) = 4 7 m
Main System
60 m Rigid Frame
Short Direction
Clear Height
= 7m
20 m
20 m
Dr. Maha Moddather
2. Arrangement of Main System
S=4–7m
S=4–7m
2. Arrangement of Main System
Main System
2. Arrangement of Main System
Rafter / Girder
Main System parallel to the Short Direction
Spacing (S) = 4 7 m
60 m S=6m
Clear Height
Columns
= 7m
20 m
20 m
Dr. Maha Moddather
3. Roof Slope
To accommodate rain water drainage.
Slope 1: 5 1: 15
Slope 1:10 Slope 1:10
1
10
Clear Height Clear Height
= 7m = 7m
20 m 20 m
Dr. Maha Moddather
3. Roof Slope
Slope can reach values equal to: (1:1) in case of bulk material
storage.
Slope 1:1 Slope 1:1
Dr. Maha Moddather
4. Roof Covering Materials
Covering Material
Flexible Cover Rigid Cover
Corrugated Sandwich Precast
R.C. slab
Sheets Panels Units
Dr. Maha Moddather
4. Roof Covering Materials
Covering Material
Flexible Cover Rigid Cover
Corrugated Sandwich Precast
R.C. slab
Sheets Panels Units
Dr. Maha Moddather
4. Roof Covering Materials
Covering Material
Flexible Cover Rigid Cover
Corrugated Sandwich Precast
R.C. slab
Sheets Panels Units
Dr. Maha Moddather
4. Roof Covering Materials
Covering Material
Flexible Cover Rigid Cover
Corrugated Sandwich Precast
R.C. slab
Sheets Panels Units
Dr. Maha Moddather
4. Roof Covering Materials
4. Roof Covering Materials
Spacing bt. secondary beams a
For Flexible Roof: a 2m
For Rigid Roof : a 3m
60 m S=6m
1
10
Clear Height
= 7m
20 m
Very large area for
20 m Use Secondary Beams
the covering material
Dr. Maha Moddather
4. Roof Covering Materials
a=2m
Used Sections for Purlins:
Channel Section
Z Section
60 m S=6m
1
10
Clear Height
Secondary = 7m
Beams
/
Purlins
20 m
20 m
Dr. Maha Moddather
4. Roof Covering Materials
a=2m
Corrugated
Sheets
60 m S=6m
1
10
Clear Height
Secondary = 7m
Beams
/
Purlins
20 m
20 m
Dr. Maha Moddather
4. Roof Covering Materials
Purlin Roof Cover
Rafter
a=2m
Refers to the horizontal
Column
distance
20 m
Dr. Maha Moddather
4. Roof Covering Materials
Purlin Roof Cover
Rafter
a=2m
Refers to the horizontal
Column
distance
Purlin Top Chord Roof Cover
20 m
Purlins should be at Truss Diagonals Verticals
Joints Bottom
Column Chord
Dr. Maha Moddather
4. Roof Covering Materials
Purlin Roof Cover
Rafter
a=2m
Refers to the horizontal
Column
distance
Purlin Roof Cover
20 m
h H
Purlins should be at Truss a B
H=
Joints 12 - 16
Column
h 1 m
Dr. Maha Moddather
4. Roof Covering Materials
Purlins
Dr. Maha Moddather
Dr. Maha Moddather
5. Side Cover
Brick Walls
Corrugated
Sheets
Dr. Maha Moddather
Dr. Maha Moddather
Dr. Maha Moddather
Dr. Maha Moddather
5. Side Cover
Roof Cover
Purlin
Rafter
Side Girt Side Cover
Column
a’ 2
m
Brick
Wall
1.5 – 3.0 m
20 m
Dr. Maha Moddather
5. Side Cover
Side Girts
Dr. Maha Moddather
6. End Gables
Add End Gable Columns with spacing 4 – 6 m
Roof Cover
Purlin
Rafter
Side Girt Side Cover
Column
Brick
Wall
1.5 – 3.0 m
20 m
Dr. Maha Moddather
6. End Gables
Add End Gable Columns with spacing 4 – 6 m
Roof Cover
Purlin Rafter
Side Girt Side Cover
Column Brick
Wall
End Gable
Column
1.5 – 3.0 m
5m 5m 5m 5m
20 m
Dr. Maha Moddather
Dr. Maha Moddather
Dr. Maha Moddather
6. End Gables 5m
End Gable Column
60 m S=6m
20 m
Dr. Maha Moddather
6. End Gables
Use Side Girts at distance 2.0 m
Roof Cover
Purlin Rafter
Side Girt Side Side Cover
a’ 2 m
Girt
Column End Gable Brick
Column Wall
1.5 – 3.0 m
5m 5m 5m 5m
20 m
Dr. Maha Moddather
6. End Gables
For trusses: End Gable Columns at truss Joints
Roof Cover
Purlin Rafter
Side Girt Side Cover
Column Brick
Wall
End Gable
Column
1.5 – 3.0 m
5m 5m 5m 5m
20 m
Dr. Maha Moddather
6. End Gables
Access Doors
Roof Cover
Purlin Rafter
Side Girt Side Side Cover
a’ 2 m
Girt
Column End Gable Brick
Column Wall
Access
Opening
1.5 – 3.0 m
5m 5m 5m 5m
20 m
Dr. Maha Moddather
6. End Gables
Access Doors
Roof Cover
Purlin Rafter
Side Girt Side Side Cover
a’ 2 m
Girt
Column Brick
Wall
Access
Opening
1.5 – 3.0 m
5m 6m 5m
20 m
Dr. Maha Moddather
6. End Gables
Types of Doors Sliding Door (One side)
Roller Shutter Door
Sliding Door (Two side)
Dr. Maha Moddather
7. Bracing System
Bracing system is provided to frames to provide stability under
the lateral loads.
Frame can support loads in
the lateral direction
Short Direction
Dr. Maha Moddather
7. Bracing System
Bracing system is provided to frames to provide stability under
the lateral loads.
Long Direction
Dr. Maha Moddather
7. Bracing System
Bracing System includes:
Horizontal Bracing:
Bracing in a horizontal plane provides a load path to transfer
the horizontal forces (wind pressure on the cladding) to the
planes of vertical bracing.
Horizontal
Vertical Bracing Bracing
Bracing in vertical planes
(between lines of columns)
provides load paths to transfer
horizontal forces to ground
Vertical Bracing
level.
Dr. Maha Moddather
7. Bracing System
Horizontal Bracing
Vertical Bracing
Wind Bracing System
Wind Bracing System
7. Bracing System
Use Bracing at the First and last bays.
Use bracing at intermediate bays, if length > 40 m.
Intermediate
Bay
First Bay
Last Bay
7. Bracing System 5m 7m
Vl. Bracing
Hz. Bracing
Side View
60 m
Plan
7. Bracing System 5m
Vl. Bracing
Hz. Bracing
Side View
Upper Hz. Bracing 60 m
(U.W.B.)
Lower Hz. Bracing
(L.W.B.)
Plan at U.W.B. Level
Example
Vertical Bracing & Side Cover
Vertical Bracing
Assignment
An industrial building, constructed in Alexandria, has a foot print
area of 70m x 84m and comprises 3 halls: a factory hall and two
packaging halls. The 3-bay steel skeleton of the building is shown in
the attached figure. The factory bay has a column-truss frame system
of 30 m span, and is provided with a 20-ton capacity overhead crane.
The packaging bays have a rigid frame system of 20 m span, one of
the bays is served by a 5-ton capacity monorail crane. Spacing
between frames is 6 m. The building is provided with horizontal and
vertical bracing systems. In the plane of the frames, the columns are
fixed at F and hinged at A, D and J. Column DE is a hinged hinged
column capable of only taken axial load.
Assignment
Assignment
84 m
Packaging Factory Hall
Halls
20 m 20 m 30 m
1. Types of Main Systems
Systems
Simple Rigid Simple Column Truss
Beam Frame Truss Frame
Span 7 - 10m Span 12 – 25 m Span 15 - 25m Span 25 - 40m
Dr. Maha Moddather
Assignment
Statical System
Rigid Rigid Column-Truss
Frame Frame Frame
84 m
Packaging Factory Hall
Halls
20 m 20 m 30 m
Assignment
Statical System
Slope 1:10
Slope 1:13.33
Rigid Rigid Column-Truss
Frame Frame Frame
Assignment
An industrial building, constructed in Alexandria, has a foot print
area of 70m x 84m and comprises 3 halls: a factory hall and two
packaging halls. The 3-bay steel skeleton of the building is shown in
the attached figure. The factory bay has a column-truss frame system
of 30 m span, and is provided with a 20-ton capacity overhead crane.
The packaging bays have a rigid frame system of 20 m span, one of
the bays is served by a 5-ton capacity monorail crane. Spacing
between frames is 6 m. The building is provided with horizontal and
vertical bracing systems. In the plane of the frames, the columns are
fixed at F and hinged at A, D and J. Column DE is a hinged hinged
column capable of only taken axial load.
Assignment
Prepare a General Layout Drawing (Using A1 sheet) [1:200]:
Roof Plan:
Arrangement of Main System.
Arrangement of Purlins.
Horizontal Bracing.
End Gable Columns
Main System Elevation.
End Gable Elevation.
Side view for Vertical Bracing/ Side Girts.
Roof Plan
Spacing
(S) = 6 m
14x6000 = 84000
20000 20000 30000
Roof Plan
Arrangement
of Main
System
14x6000 = 84000
20000 20000 30000
Assignment
Distance bt. Roof Purlins
Slope 1:10
Slope 1:13.33
Rigid Rigid Column-Truss
Frame Frame Frame
Distance bt. Purlins = 1875
mm
Assignment
Distance bt. Roof Purlins
Slope 1:10
Slope 1:13.33
Rigid Rigid Column-Truss
Frame Frame Frame
Distance bt. Purlins ≤ 2000 mm
Roof Plan
Add Roof Purlins
14x6000 = 84000
10x2000= 10x2000= 16x1875=30000
20000 20000
Assignment
Prepare a General Layout Drawing (Using A1 sheet):
Roof Plan:
Arrangement of Main System.
Arrangement of Purlins.
Horizontal Bracing.
End Gable Columns
Main System Elevation.
End Gable Elevation.
Side view for Vertical Bracing/ Side Girts.
Main System Elevation
Assignment
An industrial building, constructed in Alexandria, has a foot print
area of 70m x 84m and comprises 3 halls: a factory hall and two
packaging halls. The 3-bay steel skeleton of the building is shown in
the attached figure. The factory bay has a column-truss frame system
of 30 m span, and is provided with a 20-ton capacity overhead crane.
The packaging bays have a rigid frame system of 20 m span, one of
the bays is served by a 5-ton capacity monorail crane. Spacing
between frames is 6 m. The building is provided with horizontal
and vertical bracing systems. In the plane of the frames, the
columns are fixed at F and hinged at A, D and J. Column DE is a
hinged hinged column capable of only taken axial load.
Hz. & Vertical
Bracing Systems
Assignment
Vertical Bracing Levels
Roof Plan
Add Bracing
(Hz. And Vl.)
14x6000 = 84000
Roof Plan
Add Bracing (Hz. And Vl.)
Roof Plan
Add End Gable
Columns
6000 5625
Assignment
Prepare a General Layout Drawing (Using A1 sheet):
Roof Plan:
Arrangement of Main System.
Arrangement of Purlins.
Horizontal Bracing.
End Gable Columns
Main System Elevation.
End Gable Elevation.
Side view for Vertical Bracing/ Side Girts.
End Gable
Formation of Corrugated Sheets
Formation of Corrugated Sheets
Formation of Corrugated Sheets
Roof Plan
Main column
Rafter
Roof purlins
Cladding
End gable col.
14x6000 = 84000
Vertical bracing
Axes
Dimensions
Typical Elevation
Elevation, Pulins, Side girts
Cladding, Rain Gutter, Slope
Axes, Dimensions
Notice that: At truss bay end-gable columns
meets roof purlin and horizontal bracing joint
Elevation End Gable
Elevation, Pulins, Side girts
Cladding, Rain Gutter, Slope
End-gable column, doors,
Axes, Dimensions
Axis D
Side View
Bracing
Struts
Another View
Cladding
Axes
Dimensions
Truss bottom chord level
Truss top chord level
Crane level
Axes
Struts
Bracing
Cladding
Side View
Dimensions
Dimensions
Side cladding
Another View
Missing Items
Adjust col height
Rafter Level
Mid level
Axis A
Rafter Level
Mid level
Axis B
Truss top chord level
Truss bottom chord level
Crane level
Axis C
Truss top chord level
Truss bottom chord level
Crane level
Axis D