The City & Guilds Textbook Plumbing 2nd Edition Book 2 LEVEL 3 APPRENTICESHIP
The City & Guilds Textbook Plumbing 2nd Edition Book 2 LEVEL 3 APPRENTICESHIP
Plumbing
SECOND EDITION
LEVEL 3 APPRENTICESHIP (9189)
LEVEL 3 ADVANCED TECHNICAL DIPLOMA (8202)
LEVEL 3 DIPLOMA (6035)
T LEVEL OCCUPATIONAL SPECIALISMS (8710)
Stephen Lane
Peter Tanner
iii
iv
You will also demonstrate that you are following health ● practical installation test
and safety regulations at all times by drawing upon ● practical application test
your knowledge of legislation and regulations. ● professional discussion.
The exam draws from across the content of the T Level (8710)
qualification, using multiple choice questions to:
This Level 3 course, which runs alongside the
● confirm breadth of knowledge and understanding
apprenticeship programme, offers the opportunity to
● test applied knowledge and understanding – giving
gain essential skills that will enable you to enter full-
the opportunity to demonstrate higher-level
time employment within the plumbing and heating
integrated understanding through application,
sector.
analysis and evaluation.
The course is a two-year programme. All learners
9189 studying a Building Services Engineering for
Level 3 is assessed using multiple choice tests and Construction T Level will complete the core component
practical assignments. These will happen at the end of (350), which introduces the foundational industry
each phase of learning, with there being four phases in principles. This is assessed by two written exams
total. Learners will also be expected to keep a work log and an employer-set project. This core component
for the duration of the programme. is covered in another Hodder Education textbook:
Building Services Engineering for Construction T Level:
The apprenticeship is assessed separately to the Core.
on-programme qualification and is assessed by an
end-point assessment (EPA). In order to progress You will also choose one or two occupational
through the end-test gateway to end-point assessment, specialisms. These include:
you must complete the following: ● 355 Heating engineering
vi
KEY POINT
It is vital that fuels are kept dry and that they
are delivered in good condition for optimum
combustion efficiency to occur.
vii
Acknowledgements
This book draws on several earlier books that were Taylor; Jocelynne Rowan, Steve Owen, Mick Gibbons,
published by City & Guilds, and we acknowledge and Diane Whinney and Dave Driver/Baxi Training Centre;
thank the writers of those books: Paul Morgan/Cotherm; Jamie Purser, Graham Fleming,
● Michael Maskrey John Pierce and Sabir Ahmed/Hackney Community
● Neville Atkinson College; David Simoes/Honeywell; Jonathan Madden,
● Eamon Wilson Andrew Patterson and Carl Spalding/Heatrae Sadia; Rob
● Andrew Hay-Ellis Wellman/National Skills Academy, and models Anup
● Trevor Pickard. Chudasama, Michaela Opara and Sami Simela; Mykal
Trim and Sam, CHS Gas Assessment Centre Norwich.
We would also like to thank everyone who has
contributed to City & Guilds photoshoots. In particular, Contains public sector information licensed under the
thanks to: Jules Selmes and Adam Giles (photographer Open Government Licence v3.0.
and assistant); Martin Biron and the staff at the College
Permission to reproduce extracts from British Standards
of North West London and the following models:
is granted by BSI Standards Limited (BSI). No other
Vivian Chioma, Jennifer Close, Peko Gayle-Reveault,
use of this material is permitted. British Standards can
Adam Giles, Michael Maskrey, Nahom Sirane, Zhaojie
be obtained in PDF or hard copy formats from the BSI
Yu; Michael Maskrey and the staff at Stockport College
online shop: https://shop.bsigroup.com/
and the following models: Michael Maskrey, Jordan
viii
Picture credits
Every effort has been made to trace and acknowledge Fig.2.44 © Upperplumbers Ltd; Fig.2.51 © Fefufoto/
ownership of copyright. The publishers will be glad to stock.adobe.com; Fig.2.60 City & Guilds; Fig.2.61 ©
make suitable arrangements with any copyright holders Ddukang/stock.adobe.com; Fig.2.62 Michael Maskrey;
whom it has not been possible to contact. Fig.3.3 © Danfoss; Fig.3.10 © Bosch Thermotechnology
Ltd; Figs.3.16 & 3.17 © Grundfos Pumps Ltd; Fig.3.20 ©
Fig.1.1 © WRAS; Fig.1.2 © Kiwa; Fig.1.7 Aquatech
Borders Underfloor Heating Ltd; Fig.3.21 © Rigamondis/
Pressmain product image courtesy of Aquatronic
Shutterstock.com; Fig.3.22 © Beggs & Partners; Fig.3.31
Group Management Plc, www.agm-plc.co.uk; Fig.1.9
© M H Mear & Co. Huddersfield, England (www.
© Brimar Plastics Limited; Fig.1.10 © Dewey Waters
mhmear.co.uk); Fig.3.41 © Anton_antonov/stock.
Ltd; Fig.1.17 Image reproduced with permission from
adobe.com; Fig.3.42 © Toolstation; Fig.3.51 © Megger;
Keraflo Ltd; Fig.1.18 © Danfoss; Fig.1.24 © BD|SENSORS
Figs.3.52–3.54 & 3.56 © Fernox; p.286 © Grundfos
GmbH; Fig.1.25 Aquatech Pressmain product images
Pumps Ltd; Fig.4.1 © kurhan/Shutterstock.com; Fig.4.2
courtesy of Aquatronic Group Management Plc, www.
Neville Atkinson; Fig.4.3 © CIPHE - Chartered Institute
agm-plc.co.uk; Fig.1.26 © KSB SE & Co. KGaA; Fig.1.29
of Plumbing and Heating Engineering; Fig.4.4 ©
Image provided courtesy of Dales Water Services
Artazum/Shutterstock.com; Figs.4.17–4.19 & 4.21 ©
Ltd – Water Well Drillers and Private Water Supply
Kingspan Group; Fig.4.22 © Saniflo Ltd; Figs.4.32, 4.33
Engineers; Fig.1.42 © Silverline; Fig.1.47 © KSB SE
& 4.35, 4.36 © Grundfos Pumps Ltd; Fig.4.37 Neville
& Co. KGaA; Fig.1.48 © Whisper Pumps Ltd, www.
Atkinson; Fig.4.38 © Contactum Limited; Fig.4.39 ©
whisperpumps.com; Fig.1.51 © Audrius Merfeldas/
zstock/Shutterstock.com; Fig.4.48 © Astroflame (Fire
stock.adobe.com; Figs.1.52 & 1.53 © Ultra Finishing;
Seals) Ltd; Figs.5.3, 5.4 & 5.10 City & Guilds; Fig.5.11
Fig.1.54 © Methven Limited; Fig.1.55 © hiv360/Adobe
Neville Atkinson; Figs.5.16 & 5.17 © Contactum
Stock; Fig.1.57 Image reproduced with permission
Limited; Fig.5.18 © Toolstation; Fig.5.23 City & Guilds;
from Cistermiser Ltd; Fig.1.59 Monsoon pump image
Fig.5.25 top left © Martindale Electric Co. Ltd, top
courtesy of Stuart Turner Limited © 2019; Fig.1.60 ©
right & bottom City & Guilds; Fig.5.26 City & Guilds;
Toolstation; Fig.1.61 © Ultra Finishing; Fig.1.63 Monsoon
Fig.5.27 © Axminster Tool Centre Ltd; Fig.5.28 City
pump image courtesy of Stuart Turner Limited © 2019;
& Guilds; Fig.5.29 © Axminster Tool Centre Ltd;
Fig.1.64 Image courtesy of Stuart Turner Limited ©
Figs.5.33–5.48 City & Guilds; p.380 City & Guilds;
2019; Fig.1.77 © Paxton Agricultural; Figs.1.80 & 1.88
Fig.5.49 Andrew Hay-Ellis; Figs.5.50–5.54 City & Guilds;
© Arrow Valves; Fig.1.91 © Hans Sasserath GmbH &
p.384 @ City & Guilds; Figs.5.55–5.73 City & Guilds;
Co. KG; Fig.1.94 © Arrow Valves; Fig.1.96 top image
Figs.5.74–5.76 Andrew Hay-Ellis; Figs.5.77–5.95 City &
© & courtesy of Valves Online – valvesonline.co.uk,
Guilds; Fig.5.96 © Health and Safety Executive (HSE);
bottom © Screwfix Direct Ltd; Fig.1.103 © GARDENA
Figs.5.97 & 5.98 Neville Atkinson; Figs.5.101–5.103 ©
Multi-Purpose Spray Gun, www.gardena.com/UK;
Megger; Figs.5.104 & 5.105 City & Guilds; Fig.5.107
Fig.1.107 © HOLLANDGREEN; Fig.1.108 © Thaifairs/
© Megger; Fig.5.108 City & Guilds; Figs.5.109 & 5.110
stock.adobe.com; Fig.1.121 Image kindly provided by
© Megger; Figs.5.113 & 5.114 City & Guilds; p.405
Monument Tools Ltd, Hackbridge, Surrey, UK; Fig.1.124
City & Guilds; Figs.5.122 & 5.123 City & Guilds; p.408
Photograph by kind permission of ROTHENBERGER UK;
City & Guilds; Fig.5.124 City & Guilds; p.410 City &
Fig.1.126 © SUKU - Druck- und Temperaturmesstechnik
Guilds; Figs 5.129–5.131 City & Guilds; Figs.5.132 &
GmbH; Fig.2.10 © Crown Water Heaters Ltd; Fig.2.15
5.133 Neville Atkinson; Fig.5.134 © Megger; Figs.5.135,
© GDC Group Limited; Fig.2.18 © Sebastian Kaulitzki/
5.138, 5.141–5.144, 5.147 & 5.148 City & Guilds;
Shutterstock.com; Fig.2.19 © Horne Engineering Ltd;
Fig.5.149 Neville Atkinson; pp.420–21 City & Guilds;
Fig.2.23 © Grundfos Pumps Ltd; Fig.2.26 © Toolstation;
Figs.5.150–5.151 City & Guilds; Figs.5.152–5.154 ©
Fig.2.32 © RZ/stock.adobe.com; Fig.2.39 © Zilmet UK
Contactum Limited; Figs.5.155–5.159 Neville Atkinson;
Limited; Fig.2.41 Courtesy of Flamco Group, part of
Fig.5.160 City & Guilds; Figs.5.161 & 5.162 Neville
Aalberts; Fig.2.43 © Anton_antonov/stock.adobe.com;
ix
This chapter provides learning in the application of design techniques, installation, maintenance, diagnostics
and rectification of faults and commissioning procedures, along with the backflow protection in plumbing
systems to comply with current legislation and regulations. The chapter also covers systems in multi-storey
dwellings with water supplied from the water undertaker and private water supplies.
By the end of this chapter, you will have knowledge and understanding of the following:
● the legislation relating to the installation and maintenance of cold water systems
● cold water system layouts
● backflow protection in plumbing systems
● design techniques for cold water systems
● diagnosing and rectifying faults in cold water systems and components
● commissioning cold water systems and components
● servicing and maintenance of cold water systems.
Return to Book 1, Chapter 5, Cold water systems, which l the water service pipework to dwellings
covered the following topics: l selecting cold water systems
l the sources and properties of water l backflow protection
l the types of water supply to dwellings l installing cold water systems and components
l the treatment and distribution of water l replacing or repairing defective components
l the sources of information relating to cold water l decommissioning cold water systems.
systems
KEY TERM
Water undertaker: a water authority or company
that supplies clean, cold wholesome water under
Section 67 of the Water Act 1991.
p Figure 1.1 Water Regulations Guide
The Water Act 2003 (Water Industry On 1 July 1999, the Office of the Deputy Prime
Act 1991) Minister issued the first ever water regulations to be
enforced in the UK. They are known as ‘The Water
The Water Act 2003 amalgamates and amends two
Supply (Water Fittings) Regulations 1999’ and they
previous pieces of legislation; the Water Industry Act
offer a common practice throughout the United
1991 and the Water Resources Act 1991. The Water Act
Kingdom. BS 8558 is the lead British Standard on the
2003 introduced changes to the regulation of the water
design, installation, testing and maintenance of services
industry in England and Wales originally made under
supplying water for domestic use within buildings and
the Water Industry Act 1991. They are enforced by the
their curtilages. BS EN 806 contains specifications
Environment Agency and deal with such matters as:
for installations inside buildings conveying water for
● the appointment and regulation of water and
human consumption.
sewerage companies and licensed water suppliers by
the Water Services Regulation Authority (OFWAT) BS EN 806 is a relatively new British Standard that
● water supply and sewage disposal powers and duties came into force in 2011. It is divided into five parts:
of the water companies and suppliers ● general recommendations
Food and Rural Affairs (DEFRA) and the Drinking Both BS 8558 and BS EN 806 replace the old British
Water Inspectorate Standard, BS 6700, Design, installation, testing and
2
maintenance of services supplying water for domestic in rural areas where connection to the water mains is
use within buildings and their curtilages. However, difficult. A private supply may serve one property or
parts of BS 6700 that are not covered in either many properties on a private network. The water may
BS EN 806 or BS 8558 will be retained. be supplied from a borehole, spring, well, river, stream
or pond.
INDUSTRY TIP Under the Water Act 2003, the local authority in
the area where the private water supply is located is
For more information go to the Water Regulations Advisory responsible for the inspection and testing of the water
Scheme (WRAS) website at: www.wras.co.uk
supply to ensure that it is maintained to a quality that
is fit for human consumption. These inspections and
Simply put, the Water Supply (Water Fittings) tests are made in accordance with the Private Water
Regulations were made under Section 74 of the Water Supplies Regulations 2016. Generally speaking, the
Industry Act 1991 and have been put in place to ensure more people that use the supply, the more detailed
that the plumbing systems we install and maintain the tests and the more regular the inspections have to
prevent: be. Supplies for commercial properties and activities
● contamination of water or food production and preparation have to be tested
● wastage of water more frequently and meet more stringent requirements
● misuse of water than domestic supplies.
● undue consumption of water
The Private Water Supplies Regulations 2016 stipulate
● erroneous metering of water.
that a risk assessment must be made of ALL private
An important factor here is that these regulations water supplies including the source, storage tanks, any
ONLY cover installations where the water is supplied treatment systems and the premises using the water
from a water undertaker’s water main and are enforced supply.
by the water undertaker in your area. They are NOT,
however, enforceable where the water is supplied from INDUSTRY TIP
a private water source.
A free copy of the Private Water Supplies Regulations
KEY TERM 2016 can be downloaded from: www.legislation.gov.uk/
uksi/2016/618/contents
Erroneous: wrong or incorrect.
installation would not meet current requirements. any plumbing work complies with the regulations.
However, any alteration or extension completed on an They must ensure that any fittings and materials
existing installation must comply with the regulations are of a sufficient quality and that any installation
in force at the time of the installation date. Regulation is installed in a workmanlike manner to an approved
3 of the Water Supply (Water Fittings) Regulations installation standard requirement. Membership of a
1999 makes this very clear. competent person scheme is advisable.
● Users, owners and occupiers must ensure that
KEY TERM the person employed to undertake the proposed
Retrospective: looking back, in this case, at work is aware of the regulations and that any
previous installations. work completed is done so in accordance with
the regulations. A certificate of compliance MUST
be obtained for the work and retained for future
Regulation 3 states:
reference by the user, owner or occupier. Regulation
1 No person shall: 3 also makes it clear that the user, owner or
a Install a water fitting to convey or receive occupier is responsible for ensuring that waste,
water supplied by a water undertaker, or alter, misuse, undue consumption, contamination or
disconnect or use such a water fitting; or erroneous metering of the water supply does not
b Cause or permit such a water fitting to be occur during usage.
installed, altered, disconnected or used, in ● The Government requires the water undertakers
contravention of the following provisions of enforce the regulations within their area of supply.
this Part. They will undertake inspections of new and existing
2 No water fitting shall be installed, connected, installations to check that the regulations are being
arranged or used in such a manner that it causes complied with. Where breaches of the regulations
or is likely to cause: are found, they must be remedied as soon as
a Waste, misuse, undue consumption or practicable. Where breaches present a significant
contamination of water supplied by a water health risk, the water supply to the premises
undertaker; or may be isolated or, in severe cases, disconnected
immediately to protect the health of occupants
b The erroneous measurement of water
and/or others fed from the same public supply.
supplied by a water undertaker.
The Government has deemed that it is a criminal
3 No water fitting shall be installed, connected, offence to breach the regulations, and offenders,
arranged or used which by reason of being including users, owners and occupiers in cases
damaged, worn or otherwise faulty, causes or is where the original installer cannot be traced, may
likely to cause: face prosecution.
a Waste, misuse, undue consumption or
contamination of water supplied by a water
undertaker; or
Notification requirements
Now we will investigate the requirements of
b The erroneous measurement of water
notification and consent with regard to cold water
supplied by a water undertaker.
installations. We need to consider:
The following points are worth remembering: ● Who needs to notify?
● Plumbers should obtain a copy of the regulations, ● Which types of installations require notification and
any amendments and guidance notes from Her consent?
Majesty’s Stationery Office (HMSO) or a copy ● Why do we need to notify?
of the Water Regulations Guide from the Water ● Who do we notify?
Regulations Advisory Scheme (WRAS) to ensure that
of plumbing installations and anyone installing or using and, if different, of the person to whom the consent
the installation without the water undertaker’s written should be sent
consent could be committing a criminal offence. ● a description of the proposed work and any related
to any job you commence will ensure you are approved plumber is to do the work.
working within the law. Consent cannot be withheld unless there are
reasonable grounds to do so, and may be granted
subject to conditions, which must be followed. If
Notification and consent are also legally required where
written approval is not given within ten working days
water fittings are to be installed on any water or waste
it can be assumed that consent has been granted but
water plants. This requirement applies irrespective
this does not alter the obligation upon the installer and
of whether the plant is owned/operated by the same
the owner or occupier to ensure that the regulations
organisation as the enforcing water undertaker.
have been complied with.
Consent is necessary for the installation of fittings in
new buildings and dwellings, extensions and alterations Notification and consent
of water systems in existing non-domestic premises, requirements: the Building
where there is a material change of use of a building Regulations Approved Document G
and for the installation of certain specified items. These
requirements
include:
● a bidet with an ascending spray or flexible hose
From 6 April 2010 an updated and extended version
● a bath larger than 230 litres (measured to the centre
of Part G was implemented, bringing in a number of
of the overflow) new areas under Building Regulations control. As such,
● a shower unit of a type specified by the regulator
under these new areas of control, the installation of
● a pump or booster drawing more than 12 litres per
the systems mentioned in Regulation 5 of the Water
minute Supply (Water Fittings) Regulations are notifiable
● a reverse osmosis unit
to the local authority building control. In general
● a water treatment unit producing a waste water
terms, notification must take place prior to the work
discharge or requiring water for regeneration or starting and within five working days of the work being
cleaning completed.
● a reduced pressure zone (RPZ) valve or other
mains supply
Incoming supply
● indirect boosting systems, from a break cistern.
NOTE : This drawing does not show
Indirect systems are the most common, as direct any additional backflow prevention
devices that may be required under
boosting systems are often forbidden by the water the Water Supply (Water Fittings)
undertakers because they can often reduce the mains Stop valve Duplicate pump Regulations 1999.
pressure available to other consumers in the locality
p Figure 1.3 Direct boosting system
and can increase the risk of contamination by backflow.
A float switch, or some other no less effective device, A pipeline switch on the header by-pass starts the
situated inside the high-level cistern controls the pumps. pumps when the water level falls to a predetermined
The pumps either switch on or off depending upon the level. The pumps can be time controlled or activated
water level in the cistern. The pumps are activated when to shut down by a pressure switch. When filling the
the water drops to a depth normally equal to about half cisterns, the pumps should shut down when the water
cistern capacity and switch off again when the water levels in the cisterns are approximately 50 mm below
level reaches a depth approximately 50 mm below the the shut off level of the float operated valve.
shut off level of the float operated valve.
Secondary backflow devices may be required at the
If the cistern is to be used for drinking water, then it drinking water outlets on each floor.
must be of the protected type.
Indirect boosting to a storage cistern
Direct boosting to a drinking water This system incorporates a break cistern to store the
header and duplicate storage cisterns water before it is pumped via a boosting pump (known
This system is mainly used for large and multi-storey as a booster set) to a storage cistern at high level.
installations. With this system, the cisterns at high level The pumps should be fitted to the outlet of the break
are for supplying non-drinking water only, a drinking cistern. The capacity of the break cistern needs careful
water header sited on the boosted supply pipe provides consideration and will depend upon the total water
limited storage of 5–7 litres drinking water to sinks in storage requirements and the cistern’s location within
each dwelling when the pump is not running. Excessive the building, but it should not be less than 15 minutes
pressure should be avoided as this can lead to an of the pumps maximum output. However, the cistern
increase in the wastage of water at the sink taps along must not be oversized as this may result in water
with the nuisance of excessive splashing. stagnation within the cistern.
Automatic air inlet valve
Upstand Pump
Pump live stop
Pump shut off
Pump stop Pump
start
Pump start
CWSC
Pump
stop
Pump start
Duplicate pump
Incoming supply
SV NRV p Figure 1.5 Indirect boosting to a storage cistern
Drinking water supplies sinks in flats
NRV taken from the boosted supply pipe
The water level in the storage cistern (or cisterns) is
usually controlled by means of water level switches
Stop valve Duplicate pump which control the pumps. When the water drops to a
predetermined level the pumps start filling the storage
p Figure 1.4 Direct boosting to drinking header
Pressure switches
Gauge
Compressor
Pressure
relief valve
Compressed air
Sight
Water
gauge
Supply from
break cistern
To pressure switches
Pneumatic
pressure
vessel
Drain tap Pressure
relief
Break cistern Filtered air vent valve
Incoming supply
Pump Un-boosted
stop mains supply
Duplicate
Pump pumps
start
NRV
Layout features for large-scale Sectional cisterns are constructed, usually on site,
storage cisterns used in multi-storey from 1 m2 sections, which are bolted together and
can be made to suit literally any capacity and tailored
cold water systems
to fit any space. Sectional cisterns can be internally
The installation of large-scale cisterns differs somewhat or externally flanged and are bolted together with
from the cisterns that were introduced in Chapter 5 stainless steel bolts.
of Book 1. Large cisterns must be installed in
accordance with the Water Supply (Water Fittings) The main materials used for:
Regulations 1999 (and the Scottish Water Byelaws ● One-piece cisterns:
2014). Regulation 5 states that the water undertaker ● glass-reinforced plastic (GRP) BS EN
10
● rubber-lined.
● aluminium – rubber-lined.
11
● The overflow pipe invert must be located at ● Alternatively, the warning pipe may be discarded
least 25 mm above the invert of the warning provided a water level indicator with an audible
pipe (or warning level if an alternative warning or visual alarm is installed that operates when
device is fitted). the water level reaches 25 mm below the invert
● The warning pipe invert must be located at least of the overflow pipe.
25 mm above the water level in the cistern and
must be at least 25 mm diameter.
● Cisterns with an actual capacity greater than
INDUSTRY TIP
5000 litres: References to the ‘actual capacity’ of a cistern simply
● The discharge level of the inlet device must be means the maximum volume which it could hold when
positioned at least twice the diameter of the filled to its overflowing level. ‘Nominal capacity’ is the total
inlet pipe above the top of the overflow pipe. volume it could hold when filled to the top of the cistern.
● The overflow pipe invert must be located at
Shut off
level
Warning alarm
Alarm sounds when the water is
25 mm from the invert of the
overflow pipe
12
Inlet pipe
Float operated valve
25 mm minimum
25 mm minimum
Warning pipe
p Figure 1.13 Relative positions of inlet, warning pipe and overflow for type AG and AF air gaps
For all cisterns greater than 1000 litres, the invert of BS 1212 Parts 1 and 2
the overflow must not be less than 50 mm above the These are the most common types of FOV. The main
working level of the cistern. problem with this type of FOV is that they are very
restrictive to water flow and incur a much greater
Methods of filling large-scale pressure (head) loss than other types of FOVs, making
cisterns cistern filling a long process. Wear on the washer and
Section 7, Schedule 2, Paragraph 16 of the Water orifice can also be problematic when the valve is in
Supply (Water Fittings) Regulations states: constant use. They are, however, satisfactory when
Every pipe supplying water connected to a intermittent use is anticipated. These were looked at in
storage cistern shall be fitted with an effective detail in Book 1.
adjustable valve capable of shutting off the
Equilibrium float operated valves
inflow of water at a suitable level below the
overflowing level of the cistern. The equilibrium FOV offers a greater flow rate and
lower pressure loss than the BS 1212 type and are
In domestic cistern installations up to 1000 litres, this is especially beneficial for large cisterns with a high-
usually a float operated valve to BS 1212. In large-scale pressure inlet cold water supply.
cisterns, however, other means of filling the cistern are
available: KEY TERM
● float operated valves
● solenoid valves.
Equilibrium: in perfect balance. In this case, the
pressure is balanced both sides of the valve.
Float operated valves BS 1212
There are basically four types of float operated valve Unlike other FOVs, the equilibrium type does not rely
(FOV) that can be installed on large-scale cisterns. solely on the float to successfully close the valve.
These are: Instead, the closing operation is aided by the water
● BS 1212 Parts 1 and 2 float operated valves pressure of the incoming mains cold water supply
● equilibrium float operated valves allowing a smaller float to be used.
● pressure operated float valves
As can be seen in Figure 1.14, the piston has a hole
● Keraflo delayed action float valves.
running through its length. This allows water to pass
We will look at the merits of each valve in turn. through to the back of the piston, which has the effect
13
of pushing the piston towards valve shut off whilst How do pressure operated valves work?
the water at the front of piston tends to push it away, At zero pressure, the valve is closed. As water enters
equalising the pressure both sides of the barrel. The float the valve inlet and the pressure increases, the valve
now only has to lift the arm to close the valve greatly opens to allow water to flow to the cistern. When
reducing the effort required to stop the flow of water. the water has reached its shut off level, the pilot
Piston valve, operated by the float and lever, closes. This
Copper float
causes the pressure within the diaphragm chamber to
Water
inlet
increase, thereby closing the water inlet and stopping
the flow of water. As the water level drops, the float
operated pilot valve opens, releasing the pressure of
Water outlet Flange bolts
the diaphragm chamber. Water pressure then re-opens
Float arm
the inlet valve and the cistern fills again to its shut off
level.
p Figure 1.14 An equilibrium float operated valve
Equilibrium valves are an advantage where the water
pressure is high and water hammer may be a concern. Pilot valve
Almost all FOVs above 54 mm are of this type. Linkage Float and lever
is that the variations in water tank levels between fully Inlet Outlet
open and fully closed are greatly reduced. Although the
head loss is greater than with the equilibrium type, the
pressure operated valve is particularly suited to large Water flow direction
cisterns with a high-pressure supply. p Figure 1.15 The pressure operated valve
14
Keraflo delayed action float valve Although very rarely used with modern systems, a
An alternative approach to cistern filling is the Keraflo solenoid valve discharging through an open-ended
delayed action float valve. This type of valve only opens pipe when used in conjunction with a float switch to
when the water falls to a pre-set level in the cistern, activate the solenoid valve is an acceptable alternative
opening fully to achieve a fast cistern fill. The benefits method of filling large-scale cisterns (we will look at
here are that not only does the cistern fill quickly but float switches a little later in the chapter). They are
also that the velocity of the water entering the cistern generally associated with boosted cold water systems.
means that the water will mix with the cistern contents
preventing stratification.
The valve opens at a predetermined water level,
opening and closing fully eliminating water hammer
and unwanted system noise. An adjustable water level
enables the levels to be set based upon water usage or, in
the case of large domestic installations, occupancy levels.
The design of the valve means that boosting pumps are
used less frequently. With a conventional FOV, pumps
activating every few minutes wastes energy and increases
pump wear. A delayed action float valve eliminates this
by allowing the pumps to be activated only once every
few hours when the water level has fallen sufficiently.
KEY TERM
Stratification: describes how the temperature of
the water varies with its depth. The nearer the
water is to the top of the cistern, the warmer it
will be. The deeper the water, the colder it will p Figure 1.17 The Keraflo ‘Aylesbury’ type delayed action float
be. This tends to occur in layers, whereby there is valve
a marked temperature difference from one layer
to the next. The result is that water quality can
vary, the warmer water near the top being more
susceptible to biological growth such as Legionella
pneumophila (Legionnaires’ disease).
Solenoid valves
A solenoid valve is an electromechanical valve that
controls the flow of water into the cistern. The solenoid
is an electromagnet that operates when an electrical
current runs through the coil. When the coil is not
energised, a spring keeps the valve shut.
Most solenoid valves used on large cisterns are of the
servo-type (also called the pilot type solenoid valve).
With this type, the electromagnet operates a plunger,
which opens and closes a pilot orifice. The incoming
water pressure, which is fed through the pilot orifice,
opens the valve seal allowing water to flow through
the valve. As the pilot valve closes, the pressure on the
valve seal decreases and a spring closes the valve. p Figure 1.18 A servo-type solenoid valve
15
Multiple cistern installations the flow of water through each cistern. This can be
Where large quantities of water are required but space achieved by:
● keeping the cistern volumes to a minimum to ensure
is limited, then cisterns can be interlinked, provided the
cisterns are the same size and capacity. Problems can rapid turnover of water to prevent stagnation
● connecting the cisterns in parallel wherever
occur if the cisterns are not linked correctly, especially
where the cisterns are to supply drinking water. possible
● connecting the inlets and the outlets at opposite
Stagnation of the water in some parts of the cistern
may cause the quality of the water to deteriorate. It ends of the cistern
● using delayed action float operated valves to limit
should be remembered that the number of cisterns to
be linked should be kept to a minimum. stratification.
Stagnation can be avoided by following some basic Where it is not possible to connect cisterns in parallel,
rules. Connection must be arranged to encourage cisterns may be connected in series.
Service valve
Independent screened
Cold water supply overflow pipes for each
cistern. Cisterns over 1000
litres require an overflow and a
warning pipe
Service valve
16
Secondary Primary
outlet outlet
In practice, cisterns in series should be interconnected is regular and even across all cisterns. In this situation,
to allow free movement of water from one cistern to it is a good idea to install FOVs on ALL cisterns with
the other. They should be connected at the bottom appropriate service valves as detailed in the Water
AND the middle so that water passes evenly through Regulations:
them. The primary outlet connection should be made Every float operated valve must have a service
on the opposite cistern to the FOV to encourage water valve fitted as close as is reasonably practicable.
movement with the secondary connection made on the
Wherever an FOV is fitted, then an overflow/warning
cistern with the FOV installed. The overflow/warning
pipe must accompany it. These should terminate in a
pipe should be fitted on to the same cistern as the FOV.
conspicuous, visible position outside the building. On
Both cisterns must be of the same size and capacity.
no account should they be coupled together.
KEY TERM There should be service/gate valves positioned to allow
Interconnected: connected together to form one for isolation and maintenance of the cisterns without
cistern. interrupting the supply. In Figure 1.21, you will see that
any two of the four cisterns can be decommissioned,
leaving two in operation. This ensures continuation of
When connecting two or more cisterns together, care supply.
should be taken to ensure that the water movement
Every cylinder has a float operated valve to allow movement of water in every cylinder
Each FOV is fitted with a service valve as detailed in the Water Supply (Water Fittings) Regulations
Gate valves to be positioned so that any Every cylinder to have its own
two cisterns can be decommissioned for independent overflow/warning pipe.
cleaning and maintenance, leaving These should evacuate the building
two in commission for supply separately and NOT be joined together
17
Type AB air gap 2× the inlet pipe diameter Head over weir Not less than 25 mm
Not less than 25 mm
Incoming mains Screened overflow pipe
cold water supply S
Screened warning
pipe
Solenoid valve shown
but this could be a float
operated valve, equilibrium
float valve or delayed action
float valve
Float switch
Weir overflow to be sized in closing the
accordance with the diameter solenoid
of the incoming water supply valve
18
Float lowered
● electronic
● ultrasonic.
Transducers
A transducer is an electronic sensor that converts
a signal from one form to another. In large-scale,
multi-storey water systems it senses system pressure
variations and converts a pre-set low pressure into
voltage to activate either the boosting pumps or the
compressor feeding the pressure vessel to boost the
pressure to normal operating pressure. They may also
be used to sense over-pressurisation. p Figure 1.24 Water pressure transducer with pressure gauge
19
that stored wholesome water should not exceed 20 °C ● vertical multi-stage types.
flow rate
● an accumulator to assist in providing sufficient
p Figure 1.25 Water temperature sensor
system pressure for the installation
● a float switch to prevent the pumps running dry.
KEY TERMS
Potable: pronounced poe-table, from the French
word ‘potable’ meaning drinkable.
Duty of care: in British law, this is a moral and
legal obligation imposed on an organisation or an
individual, which necessitates that a standard of
reasonable care is adhered to. If an action does
not meet the standard of care, the actions are
considered to be negligent and damages may be
claimed for in a court of law.
Water supply in
Single-stage pump
20
Electrical connection
Water for single occupancy
and isolation panel Accumulator dwellings
Pressure transducer Multi-stage A private water supply (PWS) can be described as
centrifugal
Pressure gauge pump motor any water supply that is not provided by a water
Control panel undertaker. The responsibility for the maintenance and
Supply manifold
repair of the supply lies solely with the person that
owns or uses it. Private water supplies are regulated by
the Private Water Supplies Regulations 2016.
Water intake
manifold
INDUSTRY TIP
p Figure 1.27 Components of a vertical multi-stage pump set Access the Private Water Supplies Regulations 2016 at:
www.legislation.gov.uk/uksi/2016/618/contents/made
The accumulator
The accumulator is a pressurised vessel that holds A private water supply can serve a single occupancy
a small amount of water for distribution within the dwelling providing less than 1000 litres (1 m3) per
installation. They are designed to maintain mains day or it may supply many properties or commercial/
operating pressure when the pump is not working and industrial buildings where the extraction rate may be in
to reduce pump usage. Small accumulators can also be excess of 1,000,000 litres (1000 m3) per day.
used to suppress water hammer.
Sources of water vary from boreholes, wells, springs
Small domestic installations use bladder type and streams to rivers and lakes, and each one needs
accumulators. These consist of a synthetic rubber to be assessed for its water quality and suitability.
bladder or bag within a coated steel cylinder or vessel. The monitoring requirements of the Drinking Water
Directive will vary according to the source and the size
Shrader valve under protective cap of the supply. In addition to this, the volume of water
produced and the population it is serving should also be
Compressed air
classified by the nature of the supply and whether the
supply is:
● serving a single occupancy dwelling
the borehole has been sunk. Perched aquifers are the have no confining layers between the water
most unreliable as these may well dry up after long level and ground level
● perched aquifers – these are aquifers that have
periods without rain.
a confining impermeable layer below the water
bearing strata. They sit above the main water
table.
Artesian well
Water
table
Saturated
zone
Aquifer
Largely
impermeable
cover
Largely
impermeable
base
22
Impermeable
strata
23
Water that is collected from surface the water is raw, especially after snow-melt and heavy
water sources rainfall. Installing a small tank or reservoir will help the
settlement process and will do much to reduce the
There are several water sources that can be classified as
variations in water quality. The tank will require regular
surface water sources.
inspections and cleaning because of the solid matter
Rivers within the water.
Rivers offer greater, more reliable yields than boreholes,
Streams
but can be susceptible to pollution and often show a
variable quality of water. Pollution often depends on Small streams often show a variable quality to the
the catchment area and the activities in the general water because of animal and human activity within the
vicinity. Water that is derived from ground where there streams’ catchment area and may show varying colour
is little peat and agricultural activities is usually of changes due to the levels of humic and fulvic acids that
good quality. Peaty ground tends to yield acidic water are used in agriculture as soil supplements.
because of the concentration of CO2, and this can lead Pollution and natural variations in the quality of the
to high concentrations of dissolved metals such as water are the most common problems that can occur
lead. with both stream and river water sources and these
Lowland water is most likely of poor quality and may need to be considered carefully when siting the water
show seasonal variations in terms of quality and supply intake point. Water can be pumped directly
colour at different times of the year, with late autumn from the stream or collected from the ground in the
being the peak of colour changes. Microbiological immediate vicinity of the stream or riverbank. This
contamination may also be high during periods of is desirable in certain situations where the geology
heavy rainfall. allows a natural filtration process, the water therefore
being cleaner than directly from the river itself. The
Coarse filter intake should not be positioned in an area where water
or screen Permeable river bank
River turbulence may be created, especially during periods
of heavy rainfall (for example, on the bend of a river or
at sudden changes in water level). Water intakes must
Inverted tank be protected by a strainer to prevent the ingress of
Graded media
fish, vermin and debris and the inlet pipe must feed a
settlement tank that allows particulate matter within
the water to settle.
p Figure 1.33 River and stream water collection
The outlet of the tank should be situated above the
Because of the potential problems associated floor of the tank and be fitted with a strainer to prevent
with rivers, a surface water source should only be sediment contamination.
considered as a potential drinking water supply where
The tank must be constructed of a material that will
no ground water source exists. The water will require
not contaminate or impair the quality of the water
a minimum of filtration and disinfection treatments.
and must be designed in such a way as to prevent the
This must be designed for a worst-case scenario when
ingress of vermin and debris.
24
Ventilation pipe
Reinforced
concrete slab
Distance between
inlet and level of
overflow
min. 150 mm
25
Springs Fence
Lockable access cover
Where the water table and the surface coincide, then a Cut off ditch
Overflow
spring is formed. The presence of fissures in the Earth’s
surface usually dictates where natural springs occur. The Valve
most reliable of these are from deep aquifers, whereas
To supply
those aquifers nearer the surface are susceptible to
Aquifer
drying up after a short period without rain, especially if
the water is flowing from fissured limestone or granite. Stream
Water table: the point where the earth below p Figure 1.35 Spring water collection
ground becomes saturated with water causing
water to pool.
KEY POINT
Remember that all water sources should be
Spring water is usually of good microbiological and
protected from the ingress of vermin and surface-
chemical quality although, again, shallow aquifers water contamination.
may suffer from variations in water quality due to
surface contamination. The probability of agricultural
contamination must be carefully considered especially
Storing treated water
when the aquifer evacuates the surface. It must also be
Plumbing systems in domestic dwellings that use water
remembered that some shallow ‘springs’ may actually
from private water supplies need to include a method
be land surface drains. Here, the water quality is likely
of storing the treated water to provide a water reserve
to be unacceptable.
in the event of planned or emergency maintenance,
The treatment of spring water is usually much simpler or problems with the water source or the water
than river or stream water because there is much less treatment. Storage will also cater for fluctuations in
suspended solid matter. water demand.
Spring water must be protected from surface Storage may take several forms:
contamination once it reaches ground level. It is ● a small covered reservoir, providing sufficient head
necessary to consider leakage from septic tanks to serve the property
and agricultural activity. A small chamber built ● an externally sited break cistern, the water being
over the spring will protect the source from surface pumped into the property by a booster set
contamination and also serve as a collection source ● a suitably positioned storage tank or cistern in the
and header tank. It should be constructed so the water roof space of a property from which water flows
enters from the base or the side. The chamber top must under gravity to the taps and outlets.
be above ground level and be fitted with a lockable,
The tank, reservoir or cistern should have sufficient
watertight access cover. An overflow must be provided
volume to accommodate the maximum demand and
and sized to accommodate the maximum flow of the
any period where the water supply may be interrupted.
spring. The outlet should be fitted with a strainer and
The storage cistern/tank/reservoir may possibly be
positioned above the floor of the chamber.
contaminated during construction and must, therefore
The chamber must be constructed of a material that be disinfected before use. This is usually achieved by
will not contaminate or impair the quality of the water filling the system with a solution of water/chlorine at
and must be designed in such a way as to prevent the 20 mg/l of chlorine and leaving to stand for several
ingress of vermin and debris. hours, preferably overnight, after which the chlorine
The land in the immediate vicinity of the chamber should be drained and the system thoroughly flushed
must also be fenced off and small ditch dug upslope to using treated water.
intercept and divert surface water run-off.
26
External break cisterns and cisterns in the roof space ● the chemical and microbiological content of the
must be protected against contamination and insulated water must be established and tests performed
against freezing in cold weather and undue warming to determine the effectiveness of any treatment
in warm weather. Cisterns and tanks should also be process and the chemical dosing requirements.
fitted with a lockable, well-fitting but not airtight lid to For small supplies, to a single dwelling, for
prevent the ingress of insects and vermin, and overflows instance, the treatment is often precautionary
and warning pipes must be protected by a mesh screen. and should include disinfection. The disinfection
Storage tanks must be inspected every six months and stage should only be discarded if it can be shown
cleaned, if necessary, to prevent the build-up of silt and without reasonable doubt by risk assessment and
debris. This should be followed by disinfection. frequent testing that the water supply is likely to be
consistently pathogen-free.
Water treatment processes for
private water supplies KEY TERM
Larger water supplies served from a private water Pathogen: a germ or bacteria.
source (for example, those that serve many properties
or commercial/industrial establishments) are often In this section of the chapter we will look at the
treated by ‘point of entry’ treatment methods. These different methods of water treatment that are often
are very similar to those that are used by the local water used with private water supplies. Table 1.1 shows
undertaker, and were discussed in detail in Book 1. It the methods of water treatment available and their
should be remembered that: effectiveness. We will look at the findings of this table
● the design of the treatment process should be based
method by method.
on a full investigation of site conditions
manganese
Pesticides
Aluminium
Taste and
Ammonia
particles
Turbidity
Solvents
Bacteria
Iron and
Arsenic
Viruses
Coarse
Nitrate
Colour
colour
Algae
Coagulation and
+ + + ++ ++ ++ ++ + ++
flocculation1
Sedimentation ++ + + +
Gravel filter/screen + ++ + + +
Rapid sand filtration + + + ++ + + +
Slow sand filtration ++ ++ ++ ++ ++ + +
Chlorination ++ ++ + + ++
Ozonation ++ ++ ++ + ++ ++
Ultraviolet (UV) ++ ++ +
Activated carbon + + + ++
Activated alumina ++
Ceramic filter ++ ++ ++ ++
Ion exchange + + ++
Membranes ++ ++ ++ ++ ++ ++ ++ + ++ ++ ++ ++
+ partly effective
++ preferred technique/effective
1 pre-oxidation may be required for effective removal of aluminium, arsenic, iron and manganese
27
Without exception, all sources of water will need Table 1.2 The Private Water Supplies Regulations 2016 – water
treatment before it is acceptable for human quality parameters
consumption. The health risks presented by poor Parameter Unit of Concentration or
quality water can be due to microbiological or chemical measurement value (maximum
contaminants. Microbiological contamination is the unless otherwise
most important issue as this can lead to infectious stated)
diseases such as Legionnaires’ disease and cholera. Colour mg/1 Pt/Co 20
Chemical contamination often leads to more long-term Turbidity FTU 4
health risks. Substances that affect the appearance, Odour (including Dilution no. 3 at 25 °C
odour or taste often make the water unpalatable to the hydrogen sulphide)
consumers. Particulates in the water may also present Taste Dilution no. 3 at 25 °C
a health risk as these could also be contaminated with Temperature °C 25
microbiological organisms. In these circumstances, Hydrogen ion pH value 9.5 (min. 5.5)
disinfection becomes more difficult. Final disinfection Sulphate mg SO4/1 250
must always be included in any treatment system to Magnesium mg Mg/1 50
effectively kill off any remaining micro-organisms. Sodium mg Na/1 150
Disinfection solutions containing chloride provide
Potassium mg K/1 12
a residual that will act to preserve the quality of
Nitrite mg NO2 /1 0.1
the water during storage and distribution (in larger
Nitrate mg NO3/1 50
systems).
Ammonia mg NH4/1 0.5
Treatment of the water is based upon the physical Silver μg Ag/1 10
removal of contaminants through: Fluoride μg F/1 1500
● filtration
Aluminium μg Al/1 200
● settling, often assisted by the addition of chemicals,
Iron μg Fe/1 200
or
Copper μg Cu/1 3000
● the biological removal of micro-organisms.
Manganese μg Mn/1 50
This usually consists of a number of key stages: Zinc μg Zn/1 500
● initial pre-treatment by settling
Phosphorus μg P/1 2200
● pre-filtration through a coarse medium
Arsenic μg As/1 50
● sand filtration
Cadmium μg Cd/1 5
● disinfection or chlorination.
Cyanide μg CN/1 50
This process is known more commonly as the Chromium μg Cr/1 50
‘multiple barrier principle’ and is designed to provide Mercury μg Hg/1 1
an effective water treatment by not relying on a
Nickel μg Ni/1 50
single, less effective process or the failure of one stage
Lead μg Pb/1 50
in the process. For example, if a system consists of
Pesticides μg/1 0.1
coagulation/flocculation, sedimentation, sand filtration
Conductivity μS/cm 1500 at 20 °C
and finally chlorination, failure of say, the rapid sand
filter does not mean that untreated water will be Chloride mg Cl/1 400
supplied to the property. Other processes will remove Calcium mg Ca/1 250
the majority of the suspended particles and, therefore, Total hardness mg Ca/1 min. 60
many of the microbiological contaminants. Disinfection Alkalinity mg HCO3/1 min. 30
will remove those remaining. Provided the sand filter Total coliforms number/100 ml 0
is repaired quickly, there will be little by the way of Faecal coliforms number/100 ml 0
deterioration in water quality. Faecal streptococci number/100 ml 0
28
sides of the tank and the inlet designed to distribute the ● rapid sand filters
incoming flow as evenly across the tank as possible. The ● pressure filters
across the entire width of the tank. The tank will also ● reverse osmosis.
require covering to prevent external contamination. Note that the difference between slow sand filters and
rapid sand filters is not just a matter of the speed of the
INDUSTRY TIP filtration process, but the underlying principle of the
method. Slow sand filtration is a biological process and
Sedimentation tanks require cleaning when their rapid sand filtration is a physical treatment process.
performance begins to deteriorate, and a 12-month period
between cleaning operations would normally be sufficient. Slow sand filters
Slow sand filters are often preceded by micro-straining
or coarse filtration; these filters are used primarily to
remove micro-organisms, algae and turbidity. It is a
slow but very reliable method of water treatment often
suited to small supplies, provided that there is sufficient
area to properly construct the filtration tanks.
29
Slow sand filters consist of tanks containing sand and water turbidity from raw water. Activated carbon
with a size range of 0.15 to 0.30 mm and to a depth in granular form is used to remove any organic
of around 0.5 to 1.5 m. For single dwellings, circular compounds. Some filters also incorporate an alkaline
modular units, usually used in tandem, are available. medium to increase the pH value of acidic water.
These have a diameter of around 1.25 m. As the
Rapid sand filters are usually constructed from
raw water flows downwards through the sand,
rectangular tanks containing coarse silica sand with a
micro-organisms and turbidity are removed by a
size range of 0.5 to 1 mm, laid to a depth of between
simple filtration process in the top few centimetres
0.6 and 1 m. As the water flows downwards through
of sand. Eventually, a biological layer of sludge
the filter, the solids remain in the upper part of the
develops, which is extremely effective at removing
sand bed where they become concentrated. The
micro-organisms in the water. This layer of sludge
treated water collects at the bottom of the filter and
is known as the schmutzdecke. The treated water
flows through nozzles in the floor. The accumulated
is then collected in underdrains and pipework at the
solids are removed either manually every 24 hours
bottom of the tank. The schmutzdecke will require
or automatically when the headloss reaches a
removing at periods of between two to ten weeks
predetermined level. This is achieved by backwashing.
as the filtration process slows. The use of tandem
filters means that one filter can remain in service A variety of proprietary units are available containing
whilst the other is cleaned and time allowed for the filtering media of different types and sizes. In some
schmutzdecke to re-establish. filters, the water flows upwards, improving the
efficiency.
Slow sand filters should be sized to deliver between 0.1
and 0.3 m3 of water for every 1 m2 of filter per hour.
Inlet
KEY TERM
Schmutzdecke: a layer of mud that is saturated
with friendly, water-cleansing bacteria. Filter media
Backwash
waste
Bellmouth
Float operated valve Filtered
water
Gravel
Wash water
and air supply
Inlet
Fine sand
Pressure filters
Outlet
Pressure filters are sometimes used where it is
important to maintain a head of pressure to remove
Perforated support Gravel
tiles or underdrains the need to pump the water into the supply. The filter
bed is enclosed in a cylindrical pressure vessel. Some
p Figure 1.37 Slow sand filter small pressure filters are capable of delivering as much
as 15 m3/h. The cylinder is typically made of specially
Rapid (gravity) sand filters coated steel, and smaller units can be manufactured
Rapid sand filters are predominantly used to remove from glass-reinforced plastic. They operate in a similar
the floc from coagulated water, but they can be way to the rapid sand filter.
successfully used to remove algae, iron, manganese
30
Inlet
Sand
Air and
Washout wash water
Gravel
inlet
Outlet
Drain
31
32
33
Water out
Pumped supplies
There are two methods of pumped supply from a well
or a borehole:
● pumped supply with pressure control
Jacketed UV
lamp UV light rays ● pumped supply with level control.
35
Water supply in
Single-stage pump
Surface pumps for private water supplies are available ● an accumulator to assist in providing sufficient
either as single components or as packaged units system pressure for the installation
containing all the necessary equipment pre-fitted. ● a float switch to prevent the pumps running dry.
The latter are the easiest to install and only require the
final plumbing and electrical connections. Electrical connection
and isolation panel Accumulator
Submersible pumps may be purchased as separate
Pressure transducer
components or in ‘pack form’ whereby all the Multi-stage
centrifugal
separately matched equipment is supplied ready to Pressure gauge pump motor
assemble. Control panel
Supply manifold
Water intake
manifold
The accumulator
The operation of an accumulator can be broken down
into three stages:
1 When the pump operates it forces water into
the accumulator bladder compressing the air
surrounding it to a pressure greater than the vessel’s
p Figure 1.48 A typical submersible pump kit
pre-charge pressure. This is the source of the stored
A typical pump package would normally consist of the energy.
following components: 2 When the bladder expands due to water being
● the pump forced in by the pump, it deforms in shape and the
● a transducer to sense pressure and flow pressure within the accumulator increases. Bladder
● a control box to monitor pressure differentials and deformation stops when the water and the now-
flow rate compressed air charge become balanced.
36
3 When a tap is opened, the pressure within the we may be asked to install specialist components that
system drops and the compressed air forces the we may only come into contact with on a limited
water out of the accumulator. When all of the water number of occasions. Even so, it is important that we
inside the accumulator is used and the pressure become familiar with these ‘specialist’ components to
falls to a predetermined level, the pump energises ensure that we position and install them correctly and
to recharge the accumulator water storage and according to the manufacturer’s instructions and in line
pressure and the cycle begins again. with any regulations or recommendations.
Probably the most important consideration when In this part of the chapter, we will look at a selection
applying an accumulator is calculating the correct of components that may be unfamiliar to you. We
pre-charge pressure. There are three points to be will investigate how they operate and the best
considered: ways of installing them in accordance with the
● the type of accumulator being used recommendations in place.
● the work to be done, and
37
Cold water
connection
Tap outlet
Thermostatic
blending
Solenoid valve
valve
Alternative sensor
eye position
Hot water
connection
38
Advantages Disadvantages
They are self-closing so water is not wasted due to the tap being The rapid closing of the tap can cause water hammer and
left open. pipework reverberation.
Most models are vandal-proof. They require regular maintenance.
They can help in saving money on water costs if a water meter They should not be used where there is a risk of fouling by
is fitted. grease or dirt.
The tap may block with scale deposits in hard water areas.
Because of the restricted amount of water released when the
tap is used, waste pipes may not reach a self-cleansing velocity
and may block with residue.
in period bathrooms
● deck mixer type – there are many types to suit all
39
Bath/shower mixer taps are designed for use where the same valve body to be used for differing flow rates
pressures of the hot and cold water are equal. They depending on the appliance that it is serving. The flow
should not be fitted where the cold water is direct rate can be changed by using a different cartridge
from the mains supply and the hot water is fed from insert. They can be used on both hot and cold water
a vented, low-pressure hot water storage cylinder. supplies and are ideal for limiting the flow to:
This type of installation creates an imbalance of water ● washbasins
supply and correct mixing of both hot and cold water ● baths and sinks
cannot take place. It can also cause the hot water to be ● bidets
pushed back into the cylinder by the high pressure of ● WCs (when used with a strainer cartridge as
40
41
An alternative connection
direct to the cylinder
using an Essex flange
p Figure 1.58 Pump-assisted shower installation with twin impeller, inlet shower booster pump
42
A connection
direct to the
cylinder using
an Essex
flange
43
Shower in
negative head
water hammer. Therefore, any pressures above those lower, more functional pressure for distribution.
needed to provide sufficient flow to water fittings and ● They maintain a set pressure ensuring that the
appliances becomes damaging, wasteful and reduces pipework and appliances are not subjected to
considerably the life expectancy of the system as a excessive stress and operate at a more moderate,
whole. This adds to the cost of water due to water acceptable pressure.
wastage and increases energy usage.
44
Inlet Outlet 1
0.8
0.4
p Figure 1.66 A pressure reducing valve cut-away
0.2
The diaphragm separates all of the parts in contact
with the water from the control spring and the valve’s 0
0 0.1 0.2 0.3 0.4 0.5
mechanism. The valve body is internally protected from −0.2
Time since closing (seconds)
debris by a stainless steel mesh strainer.
−0.4
● Under no-flow conditions, the downstream pressure
and the spring forces the valve open to allow water p Figure 1.67 The hydraulic shock wave
flow.
Shock arrestors
Shock arrestors/mini Shock arrestors are often manufactured from corrosion
expansion vessels resistant brass, copper or stainless steel. They contain
a piston or a diaphragm, which is cushioned by a
Before we look at shock arrestors (or water hammer
calculated amount of inert gas or air. When the shock
arrestors as they are more commonly known), it may
wave hits the arrestor, the piston (or diaphragm) moves
help to understand why some systems may need to
with the shock wave (or hydraulic impulse) to dampen
include them.
45
its effects by absorbing the kinetic energy. This allows expansion vessel/shock arrestor allows the expansion to
the shock wave to dissipate safely without damaging take place within the vessel, thereby protecting systems
the pipework and fittings. and equipment from internal damage. They are a
requirement of most major shower manufacturers.
Calculated volume
of inert gas Instantaneous hot water heater
Piston absorbs the
Shock wave begins shock wave Mini expansion vessel fitted
with the quick on the cold to the shower to
closure of a valve allow for any expansion
causing water
hammer upstream
Direction of
shock wave Shock wave dissipates
Shower valve
Mains cold Hot
water water
Direction of water flow supply supply
p Figure 1.68 How the shock arrestor works p Figure 1.69 The use of a mini expansion vessel
Using the shock arrestor as a mini Mini expansion vessels can also be fitted on cold
expansion vessel water installations to counteract the problems of
increased system pressure due to water expansion.
Some types of shock arrestors can be used successfully
This occurs when the mains cold water, usually at a
as mini expansion vessels. These are usually required
temperature of around 4°C in the winter and 16 °C
where there is a small amount of water expansion
in the summer, is left to stand in the pipework for a
associated with hot water pipework on mains-fed hot
period of time. The ambient air temperature in the
water supplies (unvented hot water storage systems,
building can be considerably higher, which causes the
combination boilers or multi-point instantaneous hot
water to expand slightly. This expansion can damage
water heaters). The expanded water increases the
backflow protection devices such as single check valves,
internal pressure within the pipework and this can
and terminal fittings such as ceramic disc type taps,
cause damage to terminal fittings such as shower
especially where the run of pipework is extensive.
mixing valves and backflow protection devices. A mini
46
Fluid category 1
INDUSTRY TIP
Fluid category 1 is wholesome water supplied by a
Scotland adheres to its own Scottish Water Bylaws 2004 water undertaker, complying with the Water Quality
which are virtually identical to the UK’s The Water Supply Regulations made under Section 67 of the Water
(Water Fittings) Regulations 1999. Industry Act 1991. It must be wholesome, clean, cold
Before the regulations became law, each local water and potable. All water undertakers have a duty to
undertaker had its own set of water bylaws, which were supply water that conforms to these regulations which
written around the 101 Model Water Bylaws issued in 1986 ensures wholesome water suitable for domestic use
by the UK Government. These gave some commonality to or food production purposes. Whenever practicable,
working practices but failed to address regional variations water for drinking water purposes should be supplied
that often led to confusion regarding what could and could direct from the water undertaker’s mains without any
not be done within a particular area or region. On 1 July intervening storage.
1999, the Office of the Deputy Prime Minister issued the first
ever water regulations to be enforced in the UK, effectively
Fluid category 2
eliminating these variations to provide a common practice.
These were linked to a British Standard, BS 6700, Design, Fluid category 2 is water that would normally be
installation, testing and maintenance of services supplying classified as fluid category 1 but whose aesthetic
water for domestic use within buildings and their curtilages, quality has been impaired because of:
to provide the definitive guide to hot and cold water systems ● a change in temperature
and installations in England and Wales. ● a change in appearance, taste or odour owing to the
BS 6700 has since been superseded by British Standard presence of substances or organisms.
BS EN 806:2012, Specifications for installations inside These changes are aesthetic only and do not constitute
buildings conveying water for human consumption. This
a health risk. Typical situations where this may occur in
extensive document is divided into five parts with each part
domestic properties are:
dealing with a specific subject:
● water heated in a hot water secondary system
● Part 1 General
● mixed fluid categories 1 and 2 water discharged
● Part 2 Design
● Part 3 Pipe sizing – simplified method from combination taps or showers.
● Part 4 Installation
● Part 5 Operation and maintenance. Fluid category 3
This document should be read in conjunction with BS Fluid category 3 is water that constitutes a slight health
8558:2015, Guide to the design, installation, testing and hazard because of the concentration of low toxicity
maintenance of services supplying water for domestic substances. Fluids in this category are not suitable for
use within buildings and their curtilages (complementary drinking or any other domestic purpose or application.
guidance to BS EN 806). This includes:
● ethylene glycol (anti-freeze), copper sulphate or
In this part of the chapter, we will investigate the similar chemical additives such as heating inhibitors,
different fluid categories as defined by the Water cleansers and de-scalers used in domestic properties
Supply (Water Fittings) Regulations 1999 and the ● sodium hypochlorite and other common
potential hazard. The Water Supply (Water Fittings) ● clothes and dishwashing machines
47
● hand-held garden hoses with a flow-controlled ● water treatment plant or softeners that use
spray or shut off valve other methods than salt
● hand-held fertilisers ● pressurised fire-fighting systems.
● in premises other than single occupancy domestic
dwellings: Fluid category 5
● domestic fittings and appliances such as Fluid category 5 represents a serious health risk
washbasins, baths, or showers installed in because of the concentration of pathogenic organisms,
commercial, industrial or other premises may be radioactive material or very toxic substances. These
regarded as fluid category 3. However, if there is include water that contains:
a potential for a higher risk, such as a hospital, ● faecal material or any other human waste
medical centre or other similar establishment, ● butchery or any other animal waste
then a higher fluid category risk should be ● pathogens from any source.
applied in accordance with the regulations
Typical fluid category 5 situations are:
● house garden or commercial irrigation systems
● general:
without insecticides.
● industrial cisterns and tanks
other than a single occupancy dwelling ● commercial clothes washing equipment in care
insecticides, including pop-up sprinkler systems ● butchery and meat trade establishments
● car washing and degreasing plant ● water storage for agricultural applications
48
49
Whole site, zone and point premises or complex, these have their own backflow
protection devices to protect any part of the system
of use protection that is fluid category 1. Zoned protection is also
There are many commercial and industrial processes required where any water supply pipe is supplying more
where the whole or part of a plumbing system can than one separately occupied premises.
present a high risk of backflow to other parts of the
installation or even the water undertaker’s mains
supply despite the fact that the installation is installed Stop Industrial
valve process
to the required standards. In these circumstances whole Gate with a fluid
category
site or zone protection must be installed on those parts valve
4 risk
that are deemed to be high risk.
the application for a water supply and advise on what RPZ valve protection
fluid category of backflow protection device must be on each floor (zone)
Stop
installed to comply with the Water Supply (Water valve
Fittings) Regulations. The backflow protection device
RPZ valve protection
MUST be installed before the system is commissioned. on each floor (zone)
Stop
valve
Industrial
process RPZ valve Cold water supplies to
with a protection individual apartments
fluid on each floor from a common supply
Stop pipe
category valve (zone)
4 risk
RPZ valve protection
on each floor (zone)
Reduced pressure zone (RPZ) Stop valve
valve giving fluid category 4
risk protection to the water Water undertaker’s cold water supply
undertaker's main
p Figure 1.72 Zoned protection for domestic premises
Stop valve
Point of use protection
Water undertaker’s This is the simplest form of backflow protection. Point
cold water mains
supply of use backflow protection devices are used to protect
an individual fitting or outlet against backflow and are
p Figure 1.70 Whole site protection
usually located close to the fitting which they protect,
such as a single check valve on a mixer tap to protect
Zoned protection against fluid category 2 or a double check valve on a
Zoned backflow protection simply means that where domestic hose union bib-tap as protection against fluid
different fluid categories exist within the same building, category 3.
50
51
Table 1.5 Schedule of non-mechanical backflow prevention arrangements and their respective fluid category protection (continued)
Type Description of backflow prevention arrangements and devices Suitable for protection against
fluid category
Back pressure Back siphonage
g AUK3 Air gaps for taps or combination fittings (tap gaps) discharging over any X 5
higher risk domestic sanitary appliances where a fluid category 4 or 5 is
present, such as:
● any domestic or non-domestic sink or other appliance, or
● any appliances in premises where a higher level of protection is
required, such as some appliances in hospitals or other health care
premises shall be not less than 20 mm or twice the diameter of the
inlet pipe to the fitting, whichever is the greater.
h DC Pipe interrupter with permanent atmospheric vent X 5
X indicates that the backflow prevention arrangement or device is not applicable or not acceptable for protection against back pressure for any fluid
category within water installations in the UK.
Arrangements incorporating type DC devices shall have no control valves on the outlet of the device; they shall be fitted not less than 300 mm
above the spillover level of a WC pan, or 150 mm above the sparge pipe outlet of a urinal, and discharge vertically downwards.
Overflows and warning pipes shall discharge through, or terminate with, an air gap, the dimension of which should satisfy a type AA air gap.
Each of the air gaps here will have two fluid categories
KEY TERMS
attached to it, one for back pressure and one for back
siphonage. The difference between the two is simple to Downstream: in water systems, downstream means
explain: travelling away from the point of supply.
● Back pressure – caused when a downstream
Upstream: in water systems, upstream means
travelling toward the point of supply.
pressure is greater than the upstream or supply
pressure in the water undertakers main or the
consumer’s potable water supply. Back pressure can Because the pressure in the main is zero,
gravity forces water in the system back
be caused by: towards the water main
● a sudden loss of upstream pressure, such as a
52
Upstream Downstream
Non-domestic Any size of Minimum diameter of
situation with fluid inlet pipe 20 mm or twice the
categories 4 and 5 diameter of the inlet
Sudden loss of pressure due to (AUK3) pipe, whichever is the
a burst on the undertaker’s main greater of the two
53
Type AB – air gap with weir overflow vermin and dust. A good example of this is feed and
This gives protection against fluid category 5. It is a expansion cisterns in industrial/commercial installations
non-mechanical backflow prevention arrangement of or where high-quality water is required, such as in
water fittings complying with type AA, except that dental surgeries.
the air gap is the vertical distance from the lowest The size of the weir needs to be calculated based upon
point of the discharge orifice which discharges into the the inlet size. This is usually completed using a weir
receptacle, to the critical level of the rectangular weir overflow calculator.
overflow.
The type AB air gap is suitable for high risk fluid IMPROVE YOUR MATHS
category 5 situations and is particularly suited to An example of a weir calculator can be found at:
installations where the contents of the cistern need www.airgapcalculator.co.uk/inletcalc/index.html
to be protected from contaminants such as insects,
54
Type AD – air gap with injector Air gap Critical water level
requirements of BS EN 13076:2003.
Type AG – air gap with minimum
size circular overflow determined by Where storage cisterns are installed, it is likely that
measure or vacuum test the critical water level would differ from installation to
installation because of varying flow rates and pressures
This means a non-mechanical backflow prevention
of the incoming supply and the differing lengths and
arrangement of water fittings with an air gap; together
gradients of the overflow pipe. With this type of
with an overflow, the size of which is determined by
installation, the type AG air gap is not practical because
measure or a vacuum test. This arrangement gives
the critical water level cannot be accurately calculated.
protection against fluid category 3.
It is the critical water level that would determine the
The type B air gap fulfils the requirements of BS EN position on the cistern of the float operated valve and
14623:2005, Devices without moving parts for the the distance between the FOV and the overflow.
prevention of contamination of water by backflow;
Specification for type B air gaps. In a cistern that Type AUK1 – air gap with interposed
is open to the atmosphere, the vertical distance cistern
between the lowest point of discharge and the critical This is a non-mechanical backflow prevention
water level should comply with one of the following arrangement consisting of a cistern incorporating a
requirements: type AG overflow and an air gap. The spillover level of
● It should be sufficient to prevent back siphonage.
the receiving vessel is located not less than 300 mm
● It should not be less than the distances specified in
below the overflow pipe and not less than 15 mm
Table 1.6, depending on cistern type. below the lowest level of the interposed cistern. It is
55
suitable for protection against fluid categories 5 for Type AUK2 – air gaps for taps and
back siphonage and 3 for back pressure. combination fittings (tap gaps)
This arrangement is most commonly found on WC discharging over domestic sanitary
installations with the WC pan being the receiving appliances
vessel containing fluid category 5 water. A conventional This means the height of air gap between the lowest
domestic WC suite consists of a 6 litre/4 litre dual part of the outlet of a tap, combination fitting, shower
flushing cistern, a Part 2, 3 or 4 FOV with an AG air head or other fitting discharging over a domestic
gap and overflow arrangement. This creates an AUK1 sanitary appliance or other receptacle, and the spillover
interposed cistern or, in other words, a cistern that can level of that appliance, where a fluid category 2 or 3 risk
be supplied from a mains supply or another protected is present downstream. An AUK2 air gap is only suitable
cistern without the need for additional backflow for back siphonage up to fluid category 3 and must
protection. comply with the distances stated in Table 1.6.
Type AG air gap Warning pipe
Washbasin cold water pillar tap
connected to fluid category 1
15 mm Washbasin –
Contaminated minimum
water fluid category 3
Interposed cistern
Suitable for protection against or receptacle such Suitable for protection against fluid category:
fluid category: as a WC pan
Back Back
3 Back
pressure 5 Back Outlet X pressure 3 siphonage
siphonage
p Figure 1.83 AUK1 air gap with interposed cistern p Figure 1.85 AUK2 air gap (tap gaps)
56
Spillover level
Normal direction
Type DC pipe interrupter must of flow
Suitable for protection against fluid category: Cold water supply be fitted with the lowest point of
Hot water supply the air aperture not less than
Back Back
X pressure 5 siphonage 150 mm above the free discharge
or spillover level of an appliance Shroud
and have no valve, flow restrictor dust cover
p Figure 1.86 AUK3 air gap (higher risk tap gaps) or tap on its outlet
discharging downwards.
● It must be installed at least 300 mm above the
57
limitations and can be subject to failure. The first check valve is spring loaded to generate a
In this section of the chapter, we will look at some of specific pressure drop across this part of the valve. This
the more common mechanical backflow prevention creates a reduced pressure zone downstream in the
devices and where we can install them (see Table 1.7). middle chamber of the valve and on the downstream
side of the differential relief valve. The incoming mains
Type BA – verifiable backflow supply maintains supply pressure on the upstream
preventer with reduced pressure side of the differential valve and, as long as the mains
pressure is higher, the differential relief valve will
zone (a reduced pressure zone valve)
remain closed.
Better known as an RPZ valve, this is a mechanical,
verifiable, backflow prevention device, offering
protection to water supplies up to and including fluid
Table 1.7 Schedule of mechanical backflow prevention arrangements and fittings and their respective fluid category protection
Type Description of backflow prevention arrangements and devices Suitable for protection against
fluid category
Back pressure Back siphonage
a BA Verifiable backflow preventer with reduced pressure zone 4 4
b CA Non-verifiable disconnector with difference between pressure zones not 3 3
greater than 10%
c DB Pipe interrupter with atmospheric vent and moving element X 3
d EA/EB Verifiable and non-verifiable single check valves 2 2
e EC/ED Verifiable and non-verifiable double check valves 3 3
f HA Hose union backflow preventer. Only permitted for use on existing hose 2 3
union bib tap in house installations
g HUK1 Hose union bib tap incorporating a double check valve arrangement. Only 3 3
permitted as a replacement for existing bib taps in house installations
h HC Diverter with automatic return (normally integral with some domestic X 3
appliance applications only)
X indicates that the backflow prevention device is not acceptable for protection against back pressure for ANY fluid category.
Arrangements incorporating a type DB device shall have no control valves on the outlet of the device. The device shall not be fitted less than
300 mm above the spillover level of an appliance and must discharge vertically downwards.
Relief ports from BA and CA devices should terminate with an air gap, the dimension of which should satisfy a type AA air gap.
58
Differential
Relief port relief valve
Check valve 1 open Check valve
2 open
4
Back
pressure 4
Back
siphonage
p Figure 1.91 A type CA backflow preventer
59
Direction of flow
System boiler
The outer
The vents open to
membrane atmosphere
closes off the when a
outer vent sudden loss of
holes during pressure
normal water occurs. This
flow prevents back
Type CA siphonage
disconnector
Water undertaker’s
Flow Return cold water supply
● Type EB non-verifiable single check valve – does not the water can cause excessive pressure on the check
have a test point but can be used in the same way valve causing it to fail. Other uses include the cold
as the type EA single check valve. water connections to drinks machines.
Spring loaded valve
Direction
of flow
Direction
of flow
61
Rubber membrane
Connection
End on
view to hose
Test point Test point Valve guide
Stainless steel spring
End on
Stainless steel spring Valve guide view
62
63
● Except for types HA and HUK1, backflow G15.10 Bidets of this type may:
prevention devices for protection against fluid ● Be supplied with cold and/or hot water through type
categories 2 and 3, they should not be located AA, AB, or AD backflow prevention arrangements
outside premises; and, serving the bidet only; or,
● They are not buried in the ground; and, ● Be supplied with cold water from an independent
● Vented or verifiable devices, or devices with relief distributing pipe serving the bidet only or a
outlets, are not installed in chambers below ground common distributing pipe serving the bidet and
level or where liable to flooding; and, which may also serve a WC or urinal flushing
● Line strainers are provided immediately upstream cistern only; or,
of all backflow prevention devices required for fluid ● Be supplied with hot water from a water
category 4. Where strainers are provided, servicing heater, which is supplied from an independent
valves are to be fitted upstream of the line strainer distributing pipe, that serves the bidet only, see
and downstream of the backflow prevention device; Figure 1.100; or,
and, ● Where the bidet is at a lower elevation than any
● The lowest point of the relief outlet from any reduced other outlets or appliances, be supplied with water
pressure zone valve assembly or similar device should from a common cold and/or hot water vented
terminate with a type AA air gap located not less distributing pipe providing that:
than 300 mm above the ground or floor level. ● The elevation of the spillover level of the bidet, if
64
Hot
Water undertaker’s Distribution pipes serving other appliances Shower heads or tap inlets to baths,
main supply
washbasins, sinks and bidets
p Figure 1.101 Connections to an over-rim bidet G15.13 Except where suitable additional backflow
protection is provided, all single tap outlets, combination
WCs and urinals tap assembly outlets, or fixed shower heads terminating
G15.12 The water supply to a manually operated over washbasins, baths or bidets in domestic situations
WC or urinal flushing valve may be derived either should discharge above the spillover level of the
from a supply pipe or a distributing pipe. The flushing appliance with a tap gap (type AUK2) as scheduled in
valve should be located above the WC pan or urinal Table 1.5. For a sink in a domestic or non-domestic
and must incorporate, or discharge through, a pipe location, and for any appliances in premises where a
interrupter with a permanent atmospheric vent; see higher level of protection is required, such as some
type DC in Tables 1.5 and 1.7. The lowest part of the appliances in hospitals or other health care premises, a
vent opening of the pipe interrupter should be located tap gap (type AUK3) is required, see Table 1.5.
not less than 300 mm above the spillover level of the
WC pan or not less than 150 mm above the sparge Submerged inlets to baths and
outlet of a urinal. washbasins
G15.14 Submerged inlets to baths or washbasins in any
house or domestic situation are considered to be a fluid
KEY POINT category 3 risk and should be supplied with water from
Flushing valves cannot be used in domestic WCs a supply or distributing pipe through a double check
or urinals.
valve. Submerged inlets to baths or washbasins in other
than a house or domestic situation, and sinks in any
65
location, are considered to be a fluid category 5 risk watered surface is less than 150 mm below the
and appropriate backflow protection will be required. water outlet discharge point), for example irrigation
systems and permeable hoses, are considered to be a
Drinking water fountains fluid category 5 risk and should only be supplied with
G15.15 Drinking water fountains should be designed water through a type AA, AB, AD or AUK1 air gap
so that the outlet of the water delivery jet nozzle is at arrangement.
least 25 mm above the spillover level of the bowl. The
nozzle should be provided with a screen or hood to House garden installations
protect it from contamination. G15.20 Taps to which hoses are, or may be connected
and located in house garden locations are to be
Washing machines, washer-dryers and protected against backflow by means of a double check
dishwashers valve. The double check valve should be located inside a
G15.16 Household washing machines, washer-dryers building and protected from freezing.
and dishwashers are manufactured to satisfy a fluid
category 3 risk. Where they are likely to be used in a Hose union
non-domestic situation, appropriate backflow protection bib tap
Pipe sleeved
through wall
Isolation
valve
fluid category 3 risk. Backflow protection against a fluid Whole-site and zone protection
category 5 risk should be provided where these devices G15.24 A whole-site or zone backflow prevention
are used for the application of insecticides. device should be provided on the supply or distributing
G15.23 Where mini-irrigation systems, such as porous pipe, such as a single check valve or double check valve,
hoses, are installed in house garden situations only, a or other no less effective backflow prevention device,
hose union tap with backflow protection in accordance according to the level of risk as judged by the water
with clauses G15.20 or G15.21 combined with a pipe undertaker where:
interrupter with atmospheric vent and moving element ● A supply or distributing pipe conveys water to two
device (type DB) at the connection of the hose to the or more separately occupied premises (whether or
hose union tap, or not less than 300 mm above the not they are separately chargeable by the water
highest point of the delivery point of the spray outlet supplier for a supply of water); or,
or the perforated surface of the porous hose, whichever ● A supply pipe conveys water to premises, which
67
is considered non-potable, such as recycled water or be completed by the plumbing company who may
harvested rainwater. In extreme circumstances, this employ their own designer/estimator
can result in serious illness and even death. Cross ● existing dwellings – here, the design of systems is
connections occur during correct plumbing design usually completed by an experienced operative who
and installation, such as the hot and cold connections has knowledge of the procedures for completing
to a shower valve or a mixer tap (cross connection simple flow rate and pipe sizing calculations.
between fluid category 1 and fluid category 2) and
The design of a system is the first important step
these, for the most part, are protected by the correct
towards a successful installation as the calculations
use of mechanical backflow prevention devices.
completed must allow the finished installation to
However, some modern plumbing systems require
deliver the specified flow rates and component
much more thought and planning, rather than simply
performances based upon the manufacturer’s literature.
the installation of a check valve. The Water Supply
It is at this stage that the type of materials to be used
(Water Fittings) Regulations 1999 demand that cross
for the installation will be chosen. This will be based
connections from a water undertaker’s mains to
upon the type of building, its uses, the type of system
recycled and rainwater harvesting systems, and even
being installed and cost.
connections to private water supplies are eliminated
completely in order to safeguard the wholesome water
supply. There are several ways in which we can do this: Information sources
● correct design of systems taking into account the The installation of cold water systems needs to comply
requirements of the regulations in place with the Water Supply (Water Fittings) Regulations and
● careful planning and routing of pipework and fittings we must always consider the recommendations of BS
● careful use of mechanical backflow prevention EN 806 and BS 8558. Manufacturer’s instructions have
devices and air gaps to be followed with regard to the appliances installed
● using the correct methods of marking and colour and materials used. Manufacturer’s design flow rates
coding pipework and systems. and operating pressures will need to be considered at
the system design stage for any installation to operate
Of these, identification of pipework is most important,
effectively.
especially when additions to the system are required or
during routine and emergency maintenance operations.
Statutory regulations
Plumbing is one of the most regulated trades within
4 DESIGN TECHNIQUES the building services engineering banner. We are
governed by sets of regulations, which tell us what we
FOR COLD WATER can and what we cannot do and what we must and
what we must not do; failure to comply often results
SYSTEMS in prosecution. Regulations for cold water include:
● Water Act 2003
The design of cold water installations involves the
● Water Supply (Water Fittings) Regulations 1999
calculation of flow rates, capacities of stored water
● Private Water Supplies Regulations 2016
required and pipe sizes. On large contracts it may also
● Building Regulations.
involve the planning of pipe routes based upon the
architect’s drawings. Design processes can be divided Aspects of these regulations were discussed at the
into three distinct groups: beginning of this chapter.
● large industrial/commercial contracts – on large To give us a better understanding of the Water Supply
contracts a building services engineer (BSE) will (Water Fittings) Regulations, the Water Regulations
design the cold water installation Advisory Scheme (WRAS) have written the definitive
● new build domestic installations – with these guide to the water regulations.
types of installations, the cold water design will
68
● e-mails
● faxes
● verbal communication:
Often the regulations and the British Standards will make ● face-to-face
reference to one another, and it may even be the case that the ● via the telephone.
regulations make reference to more than one British Standard.
KEY TERM
Verbal: the spoken word. Any verbal
KEY POINT communication should always be backed up with
However important the regulations and the British written confirmation to verify any agreements and
Standards are, they are not our primary source clarify any details to prevent confusion.
of information when installing equipment and
appliances. It must not be forgotten that the
manufacturer’s literature overrides both of these Written communication
where a conflict arises. ● Letters are an official method of communication
and are usually easier to understand than verbal
Manufacturer’s instructions communication. Good written communication
can help towards the success of any company by
Manufacturer’s installation, servicing/maintenance
portraying and building a professional reputation.
and user instructions are the most important of all
Official company business should always:
documents you will have access to when installing,
● be in written form
servicing and maintaining equipment and appliances.
● be on company headed paper
They tell us in installation (technical) language what we ● have a clear layout (for example, divided into
can and must do for correct and safe operation of their logical paragraphs)
equipment and they must be followed, otherwise:
69
Verbal communication between the company and the ● direct from the architect’s scale drawings
customer is usually: ● by visiting the site and taking measurements in situ.
● during the handover process – explain and show
the customer where all control valves are and how Architect’s scale drawings
to use any appliances and controls that have been Architect’s working drawings are drawn to scale.
installed The scale is necessary because it would be totally
● verbal feedback – most often, discussions with a impractical to draw at full size (1:1) for the entire
customer help us to understand the following points: building. The scale resembles a ruler with one exception;
● details of ways in which the service to the the markings represent proportionally smaller or larger
customer could be improved distances with the millimetre as its base measurement.
● details of any faults that have developed in
Typically, architect’s scale drawings use a variety of
relation to the work completed; discussions scales. The scale can be determined by looking at the
with the customer can help us to diagnose and drawing legend, which is usually situated to the right
identify these faults and, therefore, complete any of the drawing. The legend is the information that the
rectification work quickly and efficiently. drawing contains (such as the architect who drew it,
the scale, the name of the drawing, what the drawing
Taking measurements shows and any notes that should be considered by the
Before design calculations can be made of an person using the drawing).
installation, measurements from the building must first
be taken. This can be done in two ways:
p Figure 1.107 Architect’s drawing showing the legend on the right of the drawing
71
Typical drawing scales are: measurements directly from the building. This can be
● 1:1000 for site plans (10 mm = 10 m) done in several ways:
● 1:500 for site plans (10 mm = 5 m) ● Using an architect’s tape measure, which is an extra-
● 1:100 for plans and elevations (10 mm = 1 m) long tape measure often used by site engineers to
● 1:50 for plans, sections and elevations plot out a building. Requires two people for accurate
(10 mm = 500 mm) measuring of buildings and can be inaccurate if care is
● 1:20 for part plans, sections and internal elevations not taken to prevent the tape bending and distorting.
(10 mm = 200 mm) ● Using a standard tape measure, which requires two
● 1:10 for details and joinery (10 mm = 100 mm) people for accurate measuring of buildings and can
● 1:5 for details (10 mm = 50 mm). be inaccurate if care is not taken to prevent the tape
bending and distorting.
● Using a laser measure, which is by far the most
are easy to make when the drawing is not on a flat ● the number and position of the appliances
2 Identify the scale of the drawing from the legend. ● the number of people living in the dwelling
3 Identify the part of the drawing that you wish to ● frequency of use
measure. This may be a wall, room or a pipe run. ● the available incoming pressure
4 Identify the correct scale on the rule that ● the length and routes of the pipework
corresponds with the scale on the drawing. ● the type of pipework material to be used
5 Place the zero mark of the rule against the start of ● the requirements of any Regulations and British
the line you wish to measure and read the length. Standards
Care must be taken here as it is very easy to ● the requirements of the manufacturer’s installation
misinterpret the length by reading along the wrong and performance data.
scale. Most scale rules have two scales along each Once these areas have been assessed, then the size
edge and it is important that the correct scale is of the components that the system will contain can
used. be calculated. The components that are likely to be
6 Note the length you have measured. required for domestic dwellings are:
● the capacity of any cisterns that may be included in
Taking measurements on site the design
Quite often, especially when dealing with existing ● the pipe size
properties, it may be necessary to visit the site and take
72
73
500 4
water system, then the manufacturer’s data should 400
3
be consulted with regards to flow rate required. 300
➜
74
Because the flow rate is small, no loading unit exists From the chart we can see that the flow rate for 10
for it so once we have worked out the flow rate of loading units is 0.3 l/s. Add to this the 0.15 l/s for
the loading units, the flow rate for the cistern can be the storage cistern gives a total flow rate of 0.45 l/s.
added on. Now compare the total flow rate by using BS EN
The loading unit total is 10. By looking at Figure 1.109 806 Figure B1 which gives a QD flow rate of 0.4 l/s
we can determine the flow rate. for 10 loading units.
INDUSTRY TIP
Flow can be expressed in two ways: moves at it fastest in the centre of the pipe because there
● Laminar flow – this is where a fluid, such as water, is little or no resistance to flow.
travels in regular paths. Often called streamline flow, ● Turbulent flow – this is flow which undergoes irregular
the velocity and pressures at each point remain fairly fluctuations. The fluid continuously changes direction and
constant. Laminar flow over a parallel surface such as velocity. The water swirls and creates eddies while the
the internal bore of a pipe consists of layers that are all bulk of the water generally flows in one direction. In a pipe,
parallel to each other. The fluid that is in contact with turbulent flow can be caused by many factors including
the pipe surface moves only very slowly because of the the internal roughness of the pipe bore or sudden changes
resistance offered by the pipe material and all other layers in direction, such as an elbow or a tee piece.
slide over it with varying degrees of velocity. The pipe
➜
75
column 9 − head
(m) (column 13 −
HEAD AVAILABLE
PIPE REFERENCE
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
RESIDUAL HEAD
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
76
3.5 m
Section Appliance Loading Flow
units LU rate l/s
3 Cistern – 0.15
140 litre cistern 0.15 l/s
5 Basin 1 0.1
Washbasin WC WC 1 0.1
4m 3 0.1 l/s 0.1 l/s Bath 4 0.3
Bath
0.3 l/s 6 0.5
5 0.5 m
2 Appliances – 0.15
from 6 0.5
2m 1m 1m
sections 3
3m 2 Sink 0.15 l/s and 5
W/machine
0.15 l/s 6 0.65
4 0.5 m 4 Sink 2 0.15
1.5 m 2m 1m
Washing 2 0.15
1
m/c
4 0.3
Water main
1 Appliances 4 0.3
6m from 6 0.65
sections 2,
p Figure 1.112 System drawing with flow rates and loading units taken 3, 4 and 5
from BS 6700 (old) 10 0.95
column 9 − head
HEAD AVAILABLE
PIPE REFERENCE
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
(m)
1 10 0.95
2 6 0.65
3 – 0.15
4 4 0.3
5 6 0.5
77
Stage 2 – Assumed pipe diameter the flow rates can be identified. Now add your pipe
Using your experience and skill, you must assume a diameters to column 4. At this stage it is only an
pipe size that will cope with the required demand. The assumption and the rest of the table will prove whether
basis of your assumption is that the larger the diameter the choice is correct.
of pipe, the greater the flow rate. Looking at column 3,
EQUIVALENT PIPE
FLOW RATE (m/s)
column 9 − head
HEAD AVAILABLE
PIPE REFERENCE
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
(m)
1 10 0.95 28
2 6 0.65 22
3 – 0.15 22
4 4 0.3 15
5 6 0.5 15
Stage 3 – Actual and effective pipe lengths Table 1.14 Calculations for column 8
Looking at the sketch made at Stage 1, add up the Section Fitting Number Size Equivalent Total
actual pipe lengths identified and add those lengths (mm) length (m) (m)
to column 7. Using Table 1.13, work out the equivalent 1 Elbow 2 28 1.0 2.0
pipe lengths which identify the impact that fittings Tee 1 28 1.5 1.5
have on the installation, then add those lengths to Stop valve 1 28 10.0 10.0
column 8.
13.5
Table 1.13 Equivalent lengths of pipe for fittings (copper, 2 Tee 1 22 1.0 1.0
stainless steel and plastics only) 1.0
Pipe size Elbow Tee (m) Stop Check 3 Elbow 1 15 0.5 0.5
(mm) (m) valve (m) valve (m) Service 1 15 0 0.0
15 0.5 0.6 4.0 2.5 valve
(fullway)
22 0.8 1.0 7.0 4.3
0.5
28 1.0 1.5 10.0 5.6
4 Elbow 1 15 0.5 0.5
35 1.4 2.0 13.0 6.0
Tee 1 15 0.6 0.6
42 1.7 2.5 16.0 7.9
1.1
54 2.3 3.5 22.0 11.5
5 Elbow 1 22 0.8 0.8
For tees, consider the branch only.
Gate valve resistance is insignificant and will not affect flow rate. Tee 2 22 1.0 2.0
For fittings not shown, consult manufacturer’s literature. 2.8
78
Once you have put the figures into columns 7 and 8, add
them up and put the effective pipe length in column 9.
Table 1.15 The tabular method (stage 3)
EQUIVALENT PIPE
FLOW RATE (m/s)
column 9 − head
HEAD AVAILABLE
PIPE REFERENCE
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
(m)
1 10 0.95 28 7.5 13.5 21.0
2 6 0.65 22 3.0 1.0 4.0
3 – 0.15 22 7.5 0.5 8.0
4 4 0.3 15 3.5 1.1 4.6
5 6 0.5 15 4.5 2.8 7.3
Stage 4 – Head loss and velocity across until you reach the pipe size being used. Then
The graph shown in Figures 1.113 and 1.114 allows you move vertically down to read the head loss figure. Put
to determine the head loss for a given flow rate. Using this into column 5. These figures need to be read as
the flow rates on the left-hand side of the graph, move accurately as possible.
200 200
150 s 150 s
m/ m/
4.0 4.0
100 s 100 s
m/ m/
80 3.0 80 3.0
/ s / s
60 0m 60 0m
2. 2.
s s
m/ m/
40 1.5 40 1.5
s s
30 m/ 8000 30 m/ 8000
1.0 1.0
m /s OD m/s OD
20 .75 mm 5000 20 .75 m m
5000
0
159 0
159
s OD s OD
15 m/ m m 3000 15 m/ m m 3000
0.5 1 33 0.5 1 33
OD OD
10
8 mm 1500
10
8 mm 1500
8 10 8 10
1000 1000
6 800 6 800
OD OD
mm mm
Flow rate l/s
4 76 OD 4 76 OD
mm 400 mm 400
3 67 3 67
OD OD
m m
2 54m 200 2 54m 200
1.5 OD 1.5 OD
mm 100 mm 100
42 42
1.0 OD 1.0 OD
m m 70 m m 70
0.8 35 50 0.8 35 50
OD 40 OD 40
0.6 mm 30 0.6 mm 30
28 28
20 20
0.4 OD 0.4 OD
mm mm
0.3 22 10 0.3 22 10
0.2 5 0.2 5
OD OD
0.15 mm 3 0.15 mm 3
15 15
0.10 1½ 0.10 1½
0.08 0.08
0.06 0.06
0.05 0.05
0.001 0.002 0.005 0.01 0.02 0.03 0.05 0.10 0.20 0.30 0.50 0.001 0.002 0.005 0.01 0.02 0.03 0.05 0.10 0.20 0.30 0.50
Head loss m/m Head loss m/m
p Figure 1.113 Head loss graph p Figure 1.114 Head loss graph with reading
79
Table 1.16 The tabular method (stage 4 after determining head loss)
EQUIVALENT PIPE
FLOW RATE (m/s)
column 9 − head
HEAD AVAILABLE
PIPE REFERENCE
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
(m)
1 10 0.95 28 0.14 7.5 13.5 21.0
2 6 0.65 22 0.26 3.0 1.0 4.0
3 – 0.15 22 0.14 7.5 0.5 8.0
4 4 0.3 15 0.45 3.5 1.1 4.6
5 6 0.5 15 0.16 4.5 2.8 7.3
Using Table D2 from BS 6700 (Figure 1.115), add the Use the assumed pipe diameter column 4 on the table
velocity of flow to column 6. This table is read using to line 5 on Table D2 from BS 6700 (see Figures 1.115
the edge of a ruler. Place the ruler edge on the outside and 1.116).
diameter of the chosen pipe (right-hand line on
Use a ruler edge to line up pipe diameter (line 5) to flow
Figure 1.115). Use that point as a hinge point. Keeping
rate (column 3) to line 4 on Table D2.
the edge of the ruler on the diameter, align the same
edge of the ruler with the flow rate for that section of For example:
the pipe (inside right line on Figure 1.115). Keeping the Section 1 = 28 mm pipe with flow rate of 0.95 l/s
ruler at this point, read off the velocity from the inside
left line. You can now add this figure to column 6. Read off line 1 for velocity.
Now do the same for sections 2, 3, 4 and 5.
Table 1.17 The tabular method (stage 4 after determining head loss and velocity of flow)
column 9 − head
HEAD AVAILABLE
PIPE REFERENCE
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
(m)
80
0.002 0.002
5 5
0.001 6 0.001 6
Key Key
1 Wall friction gradient (head loss) in kPa per metre 4 Flow in litres per second 1 Wall friction gradient (head loss) in kPa per metre 4 Flow in litres per second
2 Velocity in metres per second 5 Outside diameter of copper tube 2 Velocity in metres per second 5 Outside diameter of copper tube
3 Formula applicable between these limits only in millimetres 3 Formula applicable between these limits only in millimetres
Lamont’s smooth pipe formula S3 is: 6 Actual bore of pipe in millimetres Lamont’s smooth pipe formula S3 is: 6 Actual bore of pipe in millimetres
0.6935 0.5645 1.7715 0.6935 0.5645 1.7715
v = 0.5545d i v v = 0.5545d i v
R = 10 R = 10
where 0.6935 where 0.6935
0.5545d 0.5545d
v is the velocity (m/s); v is the velocity (m/s);
d is the diameter (mm); where d is the diameter (mm); where
i is the hydraulic gradient; and R is the wall friction gradient (kPa). i is the hydraulic gradient; and R is the wall friction gradient (kPa).
p Figure 1.115 Determination of velocity of flow – water at 10 °C: p Figure 1.116 Table D2 from BS 6700 with reading
Table D2 from BS 6700
column 9 − head
HEAD AVAILABLE
PIPE REFERENCE
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
EQUIVALENT
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
FLOW RATE
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(m/s)
(mm)
(m)
(m)
81
Stage 6 – Available head pressure the pipework rising vertically. Looking at the sketch,
The head (or pressure) at the outlet can be measured section 1 pipework rises 1.5 m (column 10), so the
vertically in metre head. The table states that there is available head is 30 m − 1.5m = 28.5 m (column 13).
30 m (3 bar) head pressure available. As the water rises Now put all the figures in columns 10 and 13.
through the system, some head pressure is lost due to
EQUIVALENT PIPE
HEAD AVAILABLE
PIPE REFERENCE
column 9 − head
FLOW RATE (m/s)
RESIDUAL HEAD
EFFECTIVE PIPE
LOADING UNITS
VERTICAL RISE
loss of outlets)
(column 13 −
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
(m)
1 10 0.95 28 0.14 1.80 7.5 13.5 21.0 −1.5 2.94 25.56 28.5
2 6 0.65 22 0.26 0.26 3.0 1.0 4.0 −4.5 1.04 24.46 25.5
3 – 0.15 22 0.14 0.14 7.5 0.5 8.0 −8.5 1.12 20.38 21.5
4 4 0.3 15 0.45 0.45 3.5 1.1 4.6 −2.0 2.57 25.43 28.0
5 6 0.5 15 0.16 0.16 4.5 2.8 7.3 −5.0 2.47 22.53 25.0
Stage 7 – Final pipe size If the velocity is below 3.0 m/s and the residual head
To check to see if the assumed pipe diameters are is above 10 m, the pipe choice is good and can be
correct, we need to inspect the table for two figures. installed.
Firstly, the velocity in any of the pipework must not be This tabulated method of pipe sizing is now only
above 3.0 m/s, otherwise there will be system noise used for more complex or commercial pipework
(column 6). installations. Today, BS EN 806 Part 3 allows us to use
the simplified pipe sizing method for basic domestic
Secondly, the available head pressure should be above
installation.
10 m (1 bar) at each section of pipework (column 12).
column 9 − head
(m) (column 13 −
HEAD AVAILABLE
PIPE REFERENCE
EFFECTIVE PIPE
LOADING UNITS
loss of outlets)
VERTICAL RISE
RESIDUAL HEAD
(column 12 ±
ACTUAL PIPE
VELOCITY OF
(column 7 +
(column 5 ×
LENGTH (m)
LENGTH (m)
LENGTH (m)
HEAD LOSS
column 10)
column 11)
(m/m RUN)
SIZE (mm)
column 8)
RATE (l/s)
OR DROP
(mm)
(m)
1 10 0.95 28 0.14 1.80 7.5 13.5 21.0 −1.5 2.94 25.56 28.5 28
2 6 0.65 22 0.26 0.26 3.0 1.0 4.0 −4.5 1.04 24.46 25.5 22
3 – 0.15 22 0.14 0.14 7.5 0.5 8.0 −8.5 1.12 20.38 21.5 22
4 4 0.3 15 0.45 0.45 3.5 1.1 4.6 −2.0 2.57 25.43 28.0 15
5 6 0.5 15 0.16 0.16 4.5 2.8 7.3 −5.0 2.47 22.53 25.0 15
82
The table indicates that 28 mm pipe is suitable for outlets with their loading units and minimum flow
section 1. rates. The loading units (LU) and the flow rates can
be found on BS EN 806 Part 3 Section 5 page 6 in
IMPROVE YOUR MATHS Table 2. For this exercise we use the minimum flow
Do the same exercise to see if 22 mm pipe could be rates (Qmin) in litres per second.
used in that section.
Add up both the loading units and flow rate for each
section of pipe.
Simplified pipe sizing method You will notice from BS EN 806 that the table does not
The simplified pipe sizing method is based on BS EN list a cold water storage cistern.
806 Part 3 Section 5 (pages 6–13). The flow rate is calculated by dividing the capacity by
the required filling time (in seconds), which should not
Stage 1 – Make a simple sketch of the system exceed 1 hour.
Make a sketch of the system installation, numbering
For example:
each section of pipework starting from the incoming
mains and going up through the system. Put any 140 litres ÷ 900 seconds (15 mins) = 0.15 l/s flow
dimensions on the sketch and label the appliance rate
3.5 m
Section
Pipe LoadingAppliance
Litres per Loading Flow
units second units (LU) rate (l/s)
3 1 Sink 0.15 2 0.2
140 litre cistern 0.4 l/s 1.5 Washing
0.10 2 0.2
2 machine
0.05
4m 3 Washbasin WC
0.15 l/s 0.13 l/s 10 Basin0.20 1 0.1
Bath
3.0 l/s 5 13.5 WC 0.35 1 0.1
5 ---- Bath 0.15 4 0.4
1.5 m
2 13.5 Cistern
0.50 1 0.15
2m 1m 1m Actual
11 1.15
3m 2 Sink 2.0 l/s 3 0.10
W/machine 2 Basin 1 0.1
0.20 l/s 3 0.15
4 WC 1 0.1
1.5 m 4 6 0.25
BathActual 4 0.4
1.5 m 2m 1m 13.5 Cistern
0.50 1 0.1
1
1 19.5 0.45 7 0.7
From
Water main 3 Cistern
Figure 1.109 1 1.15
6m
1 4 19.5 Sink 0.6
2 0.2
including
Washing 2 0.2
p Figure 1.117 System drawing cistern
machine
flow rate
4 0.4
5 Basin 1 0.1
WC 1 0.1
6 0.6
83
Table 1.21 Recommended pipe sizes for copper (BS EN 806 Part 3 Table 3.2)
Stage 3 – Pipe size Using these loading units, read the table correctly to
Using the table of loading units completed in stage 1, identify the required pipe size for that section of pipe.
identify the total LU for each section: Taking section 1, which has 11 LU, read the top line of
the table (Max load) until you reach the figure that is
Section 1: 11 LU
either equal to or greater than 11 (≥11). This means you
Section 2: 7 LU must go to 20 loading units on the table.
Section 3: 1 LU
Section 4: 4 LU
Section 5: 6 LU
Table 1.22 Finding recommended pipe sizes using BS EN 806 Part 3 Table 3.2
Now find the recommended pipe size for the other Section 3: LU 1 Pipe size = 15 mm
sections of the installation.
Section 4: LU 4 Pipe size = 15 mm
Section 1: LU 9 Pipe size = 22 mm
Section 5: LU 6 Pipe size = 15 mm
Section 2: LU 7 Pipe size = 22 mm
84
Stage 4 – Design flow rate identified is in section 1, which is supplying the whole
In BS EN 806 Part 3, Table 2 gives the draw off flow house. The LU for section 1 is 11 LU: this is read on the
rate (Qa) and the minimum draw off rate (Qmin), bottom x-axis on the graph.
but there are times where you may be asked about Next, identify the appliance on the system with the
the design flow rate (Qd). If the design flow rate is largest LU, which in this installation is the bath with
required, you need to be able to read the graph in 4 LU. This identifies the line on the graph that you
BS EN 806 Part 3 B1 (shown in Figures 1.118 need to read from. When you look at the graph, you
and 1.119). can see different lines are identified with 2, 3, 4, 5, 8
If we relate this graph to the system we have been and 15. As the bath has an LU of 4, you are going to
using in the above pipe sizing exercise, the highest LU read off the ‘4’ line.
Qd l /s
12.0
10.0
8.0
6.0
• 5.0
3
4.0
Qd l /s
3.0
2.0 2.0
15
1.5 1.5
Design flow rate
1.0 8 1.0
0.8 0.8
0.6 5 0.6
0.5 4 0.5
Qd
0.4 3 0.4
0.3 0.3
2
0.2 0.2
2 3 4 5 6 7 8 910 15 2 3 4 5 6 7 8 9 100 2 3 4 5 6 7 8 91000 2000 3000 5000
Total flow rate
Qt in LU
p Figure 1.118 Design flow rate Qd in l/s for standard installations in relation to LUs
85
Qd l /s
12.0
10.0
8.0
6.0
• 5.0
3
4.0
Qd l /s
3.0
2.0 2.0
15
1.5 1.5
Design flow rate
1.0 8 1.0
0.8 0.8
0.6 5 0.6
0.5 0.5
Qd
4
0.4 3 0.4
0.3 0.3
2
0.2 0.2
2 3 4 5 6 7 8 910 15 2 3 4 5 6 7 8 9 100 2 3 4 5 6 7 8 91000 2000 3000 5000
Total flow rate
Qt in LU
86
Table 1.23 Recommended minimum storage of cold water for domestic installations (BS EN 806 Part 2 Clause 19.1.4 Table 6)
This table can be used in the calculation of cistern IMPROVE YOUR MATHS
capacity.
Cistern sizing
IMPROVE YOUR MATHS A small primary school is to be built accommodating
350 pupils.
Calculation of cistern capacities: example Calculate the cold water storage required and the
Calculating cistern capacity is quite straightforward design flow rate to fill the cistern within a 4-hour fill time.
provided the correct information is to hand.
To determine cistern capacities, the following
calculation should be used:
Calculation of pump power
Calculation of pump power is usually performed to
Litres of storage required (from Table 1.23)
× number of people/guests
ascertain the power of the pump needed to lift a
certain quantity of water at a certain pressure. It is
Consider the following example. based on the physics of ‘work done’ relative to ‘time’.
A hotel has 25 beds and 50 restaurant guests. ‘Work done’ is the applied force through distance
Calculate the amount of cold water storage
moved and the unit of measurement is the joule. It
required.
is thus explained as the work done when a 1-newton
200 × 25 = 5000 litres for hotel guests force acts through a 1-metre distance or:
7 × 50 = 350 litres for restaurant guests 1 joule = 1 N × 1 m
5000 + 350 = 5350 litres total cold water storage ‘Time’ must be expressed as a period of seconds, which
can be combined with work done to become work done
Assuming the cistern will have a 6-hour fill time, the
over a period of time. It is expressed in the following way:
design flow rate required to fill the cistern will be as
follows: Power = work done ÷ time
= (force × distance) ÷ seconds
Design flow rate = litres required ÷ time in seconds
= (newtons × metres) ÷ seconds (J/s)
= 5350 ÷ (6 × 3600) = 0.247 litres/second (l/s)
where: 1 J/s = 1 watt
This shows that it will require a flow rate of 0.25 l/s
Force in newtons = kg mass × acceleration due to
(answer rounded up) to fill a cistern with a capacity
gravity (9.81 m/s2)
of 5350 litres in 6 hours.
Power (watts) = mass × 9.81 × distance ÷ time
87
Length of pipe = 45 m
(actual length + allowance
for fittings, bends and valves)
Break cistern
Centrifugal pump
at 75% efficiency
Pump laws ● Power (W) required will vary with the cube of
A pump is manufactured with an impeller of constant the rotational speed of the impeller (N). This is
diameter. This will have the following characteristics: expressed as:
● Quantity of water delivered (Q) will vary according (W2 ÷ W1) = (N2)3 ÷ (N1)3
to the rotational speed of the impeller (N). This is
Where:
expressed as:
Q2 and Q1 = discharge of water delivered (l/s)
(Q2 ÷ Q1) = (N2 ÷ N1)
● Pressure produced (P) will vary with the square N2 and N1 = rotational speed of the impeller (rpm
of the rotational speed of the impeller (N). This is or rps)
expressed as: P2 and P1 = pressure produced (kPa or kN/m2)
(P2 ÷ P1) = (N2)2 ÷ (N1)2 W2 and W1 = power required (watts)
88
89
90
when and how the fault first manifested itself and associated with them
any characteristics that the fault has shown. Verbal ● methods by which to identify the problem in the
discussion with the customer often results in a form of a flow chart. These usually follow a logical,
successful repair without the need for extensive step-by-step approach, especially if the equipment
diagnostic tests. The customer should be asked: has many parts that could malfunction, such as a
● The immediate history of the fault: cold water boosting set
● When did it first occur? ● the techniques required to replace the
91
correct pressure
● that there are no unusual noises or vibrations
92
93
Backflow prevention devices contamination from back siphonage and back pressure
Most backflow prevention devices contain spring- becomes greater. Therefore, periodic testing is vital to
loaded valves and diaphragms internally and these, maintain the protection offered by these components
occasionally, can fail. When this happens, the risk of and in the case of RPZ valves, it is a mandatory
requirement.
94
95
96
Inadequate commissioning, system flushing and This schedule should be read in conjunction with the
maintenance operations can affect the quality of British Standards.
drinking water, irrespective of the materials that have The British Standards (BS EN 806.4
been used in the system installation. Building debris and
and BS 8558)
swarf (pipe filings) can easily block pipes and these can
The main British Standard for commissioning,
also promote bacteriological growth. In addition, excess
testing, flushing and disinfection of systems is BS EN
flux used during the installation can cause corrosion
806.4:2010 Specifications for installations inside
and may lead to the amount of copper that the water
buildings conveying water for human consumption.
contains exceeding the permitted amount for drinking
Installation (in conjunction with guidance document
water. This could have serious health implications and,
BS 8558:2011 Guide to the design, installation, testing
in severe cases, may cause blue water corrosion.
and maintenance of services supplying water for
It is obvious, then, that correct commissioning procedures domestic use within buildings and their curtilages).
must be adopted if the problems stated are to be avoided.
There are four documents that must be consulted: The Building Regulations
● The Water Supply (Water Fittings) Regulations 1999 The Building Regulations make reference to cold
● British Standard BS 6700 and BS EN 806 (in water services and systems. These are mentioned
conjunction with BS 8558) briefly in Approved Document G1 Cold water supply
● The Building Regulations Approved Document G1 and Approved Document G2 Water efficiency.
and G2 Additional recommendations can be found in Annex
● the manufacturer’s instructions of any equipment 1 Wholesome water and Annex 2 Competent persons
and appliances. self-certification schemes.
97
Visual inspections Only when the stage being filled is leak free should
the next stage be filled.
Before soundness testing a cold water system, visual
● Air locks from cistern-fed supplies are less likely to
inspections of the installation should take place. This
occur as each stage is filled slowly and methodically.
should include:
Any problems can be assessed and rectified as
● walking around the installation. Check that you are
the filling progresses without the need to isolate
happy that the installation is correct and meets
the whole system and initiate a full drain down.
installations standards
Allowing cisterns to fill to capacity and then
● checking that all open ends are capped off and all
opening any gate valves is the best way to avoid
valves are isolated
air locks. This ensures that the full pressure of the
● checking that all capillary joints are soldered and
water is available and the pipes are running at full
that all compression joints are fully tightened
bore. Trickle filling can encourage air locks to form
● checking that enough pipe clips, supports and
causing problems later during the fill stage.
brackets are installed and that all pipework is secure
● It is possible that less manpower will be used by staged
● checking that the equipment (such as boosting
filling procedures. On very large and multi-storey
pumps, float switches, accumulators, etc.) are
systems, the use of two-way radios greatly helps the
installed correctly and that all joints and unions on
operatives during the filling process and isolation of a
and around the equipment are tight
potential problem becomes quicker. Operatives should
● checking that cisterns and tanks are supported
be stationed at the main isolation points to initiate a
correctly and that float operated valves are
rapid turn off should a problem occur.
provisionally set to the correct water level
● checking that all appliances’ isolation valves and When the system has been filled with water, the system
taps are off. These can be turned on and tested should be allowed to stabilise and any float operated
when the system is filled with water valves should be allowed to shut off. The system will
● where underground services have been installed, then be deemed to be at normal operating pressure.
checking that any pipework is at the minimum Once the filling process is complete, another thorough
depth required by the Water Supply (Water Fittings) visual inspection should take place to check for any possible
Regulations. leakage. The system is then ready for pressure testing.
The water undertaker must be given the opportunity
to view and inspect the installation, preferably before Soundness testing
it is tested and commissioned to ensure that the Water Pressure testing can commence when the initial fill to
Supply (Water Fittings) Regulations have been complied test the pipework integrity has been completed. Again,
with. Any remedial work pointed out by the water on large systems, this is best done in stages to avoid
inspector can then be completed without the need to any possible problems.
drain the system.
The requirements of the Water
Filling and venting systems Regulations
– the initial system fill Regulation 12 of the Water Regulations requires that:
The initial system fill is always conducted at the normal The water system shall be capable of
operating pressure of the system. The system must be withstanding an internal water pressure not less
filled with fluid category 1 water direct from the water than 1½ times the maximum pressure to which
undertaker’s mains cold water supply. It is usual to the installation or relevant part is designed to be
conduct the fill in stages so that the filling process can be subjected in operation.
managed comfortably. There are several reasons for this: In practice, this means that a system that has an
● Filling the system in a series of stages allows the
operating pressure of 2 bar:
operatives time to check for leaks stage by stage.
2 bar × 1.5 = 3 bar
98
Regulation 12 also states that the regulation shall be 30 minutes and note the pressure after this time.
deemed satisfied in the case of water systems that do The test must continue with no further testing.
not contain elastomeric (plastic) pipe where the whole Check the pressure after a further 30 minutes. If
system is subjected to the test pressure by pumping, the pressure loss is less than 60 kPa (or 0.6 bar),
after which the test should continue for 1 hour without the system has no visible leakage.
further pumping and without any visible leakage and Visually check for leakage for a further 120 minutes.
any pressure loss. The test is successful if the pressure loss is less
than 20 kPa (0.2 bar). BS EN 806.4 states
Where the system does contain elastomeric (plastic)
Test B can be carried out at 1.1 times MDP over
pipework, there are two acceptable tests that can be
a period of 30 minutes, reducing the pressure in
conducted. These are classified as test type A and test
accordance with Figure 3 in BS EN 806.4.
type B.
1
Cold water systems testing is detailed in BS 6700 and
BS EN 806.4: Y
● Copper tubes and low carbon steel pipes –
2
systems installed in copper tube and low carbon
steel pipes should be tested to 1 1/2 times normal
operating pressure (1.5 times normal operating
pressure or 50 per cent above normal operating
pressure). It should be left for a period of 30 3
minutes to allow for temperature stabilisation
and then left for a period of 1 hour with no visible
X
pressure loss. BS EN 806.4 states a test pressure of
0
1.1 times the maximum design pressure (MDP) for a 0 10 20 30 40 50 60
Planning the test ● Attach the test pump to the pipework and install
extra pressure gauges if necessary.
Before the test is conducted, a risk assessment should
● Check that a suitable hose is available for draining
be carried out.
down purposes.
Personal protective equipment should also be used.
The following factors should be carefully considered: KEY POINT
● Is the test being used appropriate for the service and IMPORTANT! Check that the test pump is working
the building environment? correctly and that the pressure gauge is calibrated
and functioning correctly.
● Will it be necessary to divide the vertical pipework
100
have been undertaken During the disinfection process, the use of household
● where it is suspected that the system has been chemicals, bleaches and toilet cleaners must be avoided
compromised by contamination (such as fouling by as these can react with the disinfectant to produce
drainage, sewage or animals or the physical entry by highly toxic fumes. All personnel and residents within
operatives during maintenance operations or repair) the building, including those that are not normally
● where the system has not been in regular use nor present during working hours, should be informed of
regularly flushed the disinfection operation before it commences.
● where underground pipework has been installed.
101
102
103
104
Before draining the system, the advice of the local remove potential contaminants, such as flux residues,
water undertaker should be sought. Alternatively, a PTFE, excess jointing compounds and swarf.
neutralising chemical (sodium thiosulphate) can be
Simply filling a system and draining down again does
administered to the system to clean the water before
not constitute a thorough flushing. In most cases,
draining takes place. The chemical should be added at
this will only move any debris from one point in the
the rate of:
system to another. In practice, the system should be
System volume × ppm of chlorine × 2 = grams of filled and the water run at every outlet until the water
chemical required runs completely clear and free of any discoloration. It
Once the system has been drained, it should be flushed is extremely important to ensure that all equipment
with clean water until the free residual chlorine content and appliances and every water fitting is flushed
is no more than that in the water undertaker’s mains completely. When flushing boosted cold water supplies,
cold water supply. water from the undertaker’s water main must first be
introduced into the break cistern and then boosted,
using the boosting pumps, to all points on the system.
KEY POINT
● Do take care to warn people before disinfection It is generally accepted that systems should not be
begins. The chemicals are dangerous. left charged with water once the flushing process
● Do handle chemicals with care and always use has been completed, especially if the system is not
PPE. going to be used immediately, as there is a very real
● Do calculate the capacity of the system. risk that the water within the system could become
Using too much chemical disinfectant will not
stagnant. In practice, it is almost impossible to effect
produce better results and may result in the
test having to be completed again. a complete drain down of a system, particularly large
● Do use chlorinated water when topping up systems, where long horizontal pipe runs may hold
cisterns and pipework during the test. This will water. This in itself is very detrimental as corrosion
help keep the correct disinfectant level. can often set in and this can also cause problems with
● Do check the chlorine level at the end of the water contamination. It is recommended, therefore,
test period.
that to minimise the risk of corrosion and water quality
● Do not leave the water in the system for more
than 1 hour and never overnight. problems to leave systems completely full and flush
● Do not discharge the test water direct into a through at regular intervals of no less than twice
water course or drain without first contacting weekly, by opening all terminal fittings until the system
the local water undertaker or the Environment has been taken permanently into operation. If this is the
Agency. case, then provision for frost protection must be made.
● Always complete the disinfection record
paperwork correctly.
Operational checks
Taking flow rate and pressure readings
The flushing procedure When the system has been commissioned and put
into operation, the flow rates and pressures should be
for cold water systems and checked against the specification and the manufacturer’s
components not requiring instructions. This can be completed in several ways:
● Flow rates can be checked using a weir gauge. This
disinfection is sometimes known as a weir cup or a weir jug.
The flushing of cold water systems is a requirement of The method of use is simple. The gauge has a slot
the British Standards. All systems, irrespective of their running vertically down the side of the vessel, which
size, must be thoroughly flushed with clean water direct is marked with various flow rates. When the gauge
from the water undertaker’s main supply before being is held under running water, the water escapes
taken into service. This should be completed as soon out of the slot. The height that the water achieves
as possible after the installation has been completed to before escaping from the slot determines the flow
105
rate. Although the gauge is accurate, excessive flow If the system has been calculated correctly and
rates will cause a false reading because the water the correct equipment has been specified and
will evacuate out of the top of the gauge rather than installed to the manufacturer’s instructions,
the side slot. then problems of this nature should not occur.
● System pressures (static) can be checked using a However, if the pipe sizes are too small in any
Bourdon pressure gauge at each outlet or terminal part of the system, then flow rate and pressure
fitting. Bourdon pressure gauges can also be problems will develop almost immediately
permanently installed either side of a boosting downstream of where the mistake has been made.
pump to indicate both inlet and outlet pressures. In this instance, the drawings should be checked
● Both pressure (static and running) and flow rate can and confirmation with the design engineer that
be checked at outlets and terminal fittings using a the pipe sizes that have been used are correct
combined pressure and flow rate meter. before any action is taken. It may also be the case
that too many fittings or incorrect valves have
been used causing pipework restrictions.
● Another cause of flow rate and pressure
106
The Health and Safety Executive state that equipment is found to be defective, do not attempt
to prevent micro-bacterial growth due to a repair as this may invalidate any manufacturer’s
temperature the cold water must not exceed warranty. The manufacturer should first be
20 °C. To prevent this, the cold water pipework contacted as they may wish to send a representative
should be insulated across the entire system to inspect the component prior to replacement. The
including cisterns and storage vessels. supplier should also be contacted to inform them of
● Leakage – water causes a huge amount of the faulty component. In some instances where it is
damage to a building and can even compromise proven that the component is defective and was not
the building structure. Leakage from pipework a result of poor installation, the manufacturer may
if left undetected causes damp, mould growth reimburse the installation company for the time
and an unhealthy atmosphere. It is, therefore, taken to replace the component.
important that leakage is detected and cured at
a very early stage in the system’s life. Commissioning
● It is almost impossible to ensure that every
care when jointing tubes and fittings, using Fittings) Regulations dictate that the local water
recognised jointing materials and compounds authority must be informed before work starts,
and using manufacturers’ recommended jointing at various stages during its installation and on
techniques. completion. It also states that where backflow
● Microbiological contamination within cold water prevention devices are installed, such as RPZ valves,
systems. Contamination of cold water systems can notification must be given and they must be
occur for a variety of reasons: inspected prior to being commissioned. A list
● the ingress of insects and vermin into stored of notifiable works is provided on page 5.
water Notification should be completed by the installing
● the ingress of debris during installation plumber and involves completing a water
● poor installation practice undertaker’s notification form.
● undue warming of the cold water. ● The local building control office – under
There are many forms of microbiological Building Regulations Approved Document G, cold
contamination, including Legionella pneumophila, water installations and water conservation are
E. coli and Pseudomonas, and most are centred on notifiable to the local authority building control
an increase in water temperature where the bacteria office. Building Regulations approval can be sought
can reproduce. In such instances, the system must from the local authority by submitting a building
be disinfected using the recognised techniques notice. Plans are not required with this process so
discussed previously. In all cases of microbiological it is quicker and less detailed than the full plan’s
contamination, advice should be sought from a application. It is designed to enable small building
recognised company dealing with such outbreaks works to get under way quickly. Once a ‘building
and consultation with the HSE. notice’ has been submitted and the local authority
● Defective components and equipment. Defective has been informed that work is about to start,
components cause frustration and cost valuable the work will be inspected as it progresses. The
installation time. If a component or piece of authority will notify if the work does not comply
with the Building Regulations.
107
components installed
COLD WATER SYSTEMS
● the type of pressure test carried out and its duration Maintenance tasks on cold water services, appliances
● disinfection processes, the disinfection chemicals and valves are essential to ensure the continuing
used and the disinfection readings correct operation of the system. The term used when
● the flow rates and pressures at the outlets isolating a water supply during maintenance operations
● the pressures on both the suction side and the is ‘temporary decommissioning’.
discharge side of any boosting pumps
● the accumulator pressure.
108
Before undertaking the repair or replacement of early stages. Planned preventative maintenance could
components, we must first ascertain what the problem include:
is. The customer will be able to tell you what is ● periodic system inspection – checking for leaks
language, but they will be able to explain the ● re-adjustment of water levels in cisterns
problem well enough for you to understand. ● re-washering of drain valves
● running overflows
Maintenance ● dripping taps
There are basically two types of maintenance: ● loss of low pressure, cistern-fed cold water supply
● planned preventative maintenance due to faulty FOVs
● unplanned/emergency maintenance. ● poor past installation practices, such as incorrectly
109
The risk of Legionella drained from hot water storage cylinders and a check
made for debris and signs of corrosion.
Legionella (or Legionella pneumophila to give it its
correct name), is a water-borne bacterium that develops Water samples should be analysed for Legionella
and multiplies in stagnant water at temperatures between periodically to demonstrate that bacteria counts
20 and 45 °C. The bacteria are dormant at temperatures are acceptable. The frequency of such tests will be
below 20 °C and will not survive temperatures above 60 determined by the level of risk, in accordance with the
°C. It can develop in any hot or cold water system where risk assessment. Water treatments and disinfection by
the water has been left to stand for a long period of time, the use of chlorine dioxide can also be undertaken by
in say, cold water cisterns or hot water storage cylinders. specialist companies.
It can even develop in unused branches (known as dead
legs) of hot and cold water systems. INDUSTRY TIP
Legionnaires’ disease develops from the Legionella The Health and Safety Executive produce a guide called
bacteria and this is potentially fatal if contracted. ‘Legionnaires’ Disease: The control of Legionella bacteria in
Legionnaires’ disease develops by breathing water into water systems’ and a free copy can be downloaded from:
the lungs that is contaminated with Legionella, either in www.hse.gov.uk/pUbns/priced/l8.pdf
aerosol form (mist) or by minute water droplets from air
conditioning coolers and whirlpool/hydro-therapy baths.
Anyone can develop the disease. However, the elderly,
Keeping maintenance records
smokers, people with respiratory and kidney disease A record of all repairs and maintenance tasks
and the young are particularly at risk. completed will need to be recorded on the maintenance
schedule at the time of completion, including their
location, the date when they were carried out and the
HEALTH AND SAFETY
type of tests performed. This will ensure that a record
Any hot or cold water system left to stand for a long
period of time is at risk of containing Legionella of past problems is kept for future reference.
pneumophila. Where appliance servicing is carried out, the
manufacturer’s installation and servicing instructions
should be consulted. Any replacement parts may be
Dealing with Legionella obtained from the manufacturers.
Any system that is installed in healthcare, social care
or public buildings must be tested for the bacteria. A
full risk assessment should be undertaken of the hot SUMMARY
and cold water services and measures put in place to
control the risk. As we have seen as we have worked through this chapter,
there is so much more we need to learn about cold water
When testing for Legionella, temperature readings
systems other than the simple systems we became
must be made at the furthest and the closest outlets to
accustomed to in Book 1. Cold water systems and
the cisterns and hot water cylinders on a monthly basis.
their regulations are often complex in their design and
Hot water storage cylinders should be checked monthly
require great skill in their installation and commissioning.
and cold water cisterns on a six-monthly cycle.
Add to this the difficulties surrounding private water
To reduce the Legionella risk, remove all non-used supplies and it is obvious that the modern plumber must
outlets and corresponding pipework. Rarely used be competent in many different areas of work. This
outlets and shower heads should be flushed and chapter gives an excellent insight into the complexities
cleaned weekly, and clean and de-scale shower heads of modern cold water systems that will build on the
every three months. Cold water cisterns and tanks knowledge from Book 1 and enable you to make a
should be cleaned periodically, and the hot water worthwhile contribution within the work environment.
110
End on
view
Test point Test point Valve guide
Stainless steel spring
111
6 What is the purpose of the item labelled X in 9 Which type of non-mechanical backflow
the image below? prevention is most suitable to protect against
Filtered air vent contamination at a kitchen sink?
Incoming supply a AD
Overflow and filter b AG
c AUK2
d AUK3
Pump stop
10 A HUK1 type mechanical backflow prevention
Pump start
device is suitable for protection up to which
X fluid category?
Duplicate pump a 1
a To start the pump when the water level falls b 2
to within 225 mm of the cistern outlet c 3
b To stop the pump when the water level falls d 4
to within 225 mm of the cistern outlet 11 Which British Standard is used alongside BS
c To automatically isolate the cold water supply EN 806?
if a leak is detected downstream of the pump a BS 12058
d To automatically isolate the cold water supply b BS 8558
if a leak is detected upstream of the pump c BS EN 1212
7 Identify the correct meaning of the term ‘actual d BS 1984
capacity’ when referring to storage cisterns:
12 In a boosted cold water system, what item
a The maximum volume which it could hold activates the pump?
when filled to its overflowing level
a Float switch
b The total volume it could hold when filled to
b Solenoid
the top of the cistern
c Transducer
c The total volume it can hold when shut off
by the float operated valve d Pressure switch
d The total volume it contains including any 13 What must be avoided when cold water cisterns
expansion through heating are joined together in a customer’s loft area?
8 What type of water treatment plant is shown in a Back flow
the image below? b Cross flow
15 What is the purpose of the retaining ring on a 18 Which of the following appliances does NOT
shower hose connected to a combination bath have a risk of category 5 water being present?
tap and shower head? a Bath
a Prevent scalding when in use b WC
b Increase pressure on a low pressure system c Kitchen sink
c Keep the shower head above the bath rim d Bidet
d Restrict flow to the shower head 19 What backflow prevention device MUST be
16 What would this item be used to connect? installed on an outside tap?
a Single check valve
b RPZ valve
c Double check valve
d DC pipe interrupter
20 Which of the following is NOT a statutory
regulation?
a Water Act 2003
b Water Supply (Water Fittings) Regulations
1999
c BS EN 806
d Building Regulations
21 According to BS EN 806, what is the loading
unit for a bath?
a 2
b 3
c 4
d 5
22 A cold water storage cistern in a loft area is
sized to provide cold water to the property over
what period?
a 24 hours
b 12 hours
a Shower hose to bath tap c 8 hours
b Hot feed from cylinder to shower pump d 48 hours
c Rising main to cold water storage cistern 23 What is a fitting marked with DZR resistant to?
d Expansion vessel to cold water mains a Electrolytic corrosion
17 Which of the following does NOT have category b De-zincification
2 water flowing through it?
c Blue water corrosion
a Hot water cylinder
d Contamination
b Rising main
c Mixer shower
d Combination tap and shower
113
24 Which metal is used to prevent electrolytic 30 Which backflow prevention device is notifiable
corrosion taking place in plumbing systems? under the regulations?
a Copper 31 List the Regulative and Guidance
b Zinc documentation that will be required when
designing and installing a new domestic cold
c Magnesium
water system.
d Nickel
32 Plumbers who install systems and fitting have a
25 When disinfecting a system, how many parts per legal responsibility to ensure that the materials
million must the chlorine mixture be diluted to? and fitting comply with the regulations.
a 200 ppm What does the Water Supply (Water Fittings)
b 500 ppm Regulations state in Regulation 3 about waste
c 175 ppm and contamination of water?
d 50 ppm 33 Explain the function of a float switch in a
boosted cold water system.
26 For a single occupancy dwelling, what is the
water extraction rate of a private water supply? 34 List the documentation that the customer will
require at the handover stage after a system has
27 Which system of cold water uses a pneumatic
been tested and commissioned.
pressure vessel?
Answers can be found online at
28 Describe a break cistern.
www.hoddereducation.co.uk/construction.
29 Describe the purpose of a transducer within a
boosted cold water system.
114
This chapter provides learning in application of l different fuels in domestic hot water systems
design techniques, installation and use of specialist l the types of hot water system and their layout
components, maintenance, diagnostics and requirements
rectification of faults and commissioning procedures, l specialist components in hot water systems
along with the backflow protection in plumbing l design techniques for hot water systems
systems to comply with current legislation and l the installation requirements of hot water systems
regulations. The chapter covers open vented and and components
unvented systems in multi-storey dwellings. l testing and commissioning requirements of hot
water systems and components
By the end of this chapter, you will have knowledge
l diagnosing and rectifying faults in hot water
and understanding of the following learning
systems and components
outcomes in this chapter:
l servicing and maintenance of hot water systems.
Return to Book 1 and remind yourself of the topics l system safety and efficiency
covered in Chapter 6, Hot water systems, which l prepare for the installation of systems and
included: components
l sources of information relating to work on hot l install and test systems and components
water systems l decommission systems and components
l hot water systems and components l replace defective components.
1 DIFFERENT FUELS some remote parts of the UK are not connected to the
natural gas network.
IN DOMESTIC HOT Gas (liquid petroleum gas, or LPG) – an alternative
WATER SYSTEMS gas source for properties not connected to the gas
network. It is supplied from a pressurised storage tank
positioned some distance from the building. Supplies
There are several different fuel sources available for
are replenished by tanker delivery. Liquid propane is
heating the supply of hot water in a dwelling. They
preferred to liquid butane, as it boils at a much lower
can be divided into two categories: fossil fuels and
temperature (−45 °C) than butane (−4 °C). LPG tends
renewable energy.
to be very expensive.
115
supplied from a storage tank positioned some distance Hot water system types
from the building. Supplies are replenished by tanker
Hot water systems can be divided into two categories.
delivery. There are many types of heating oil, with the
These are:
most common being C2 grade, 28-second viscosity
l centralised systems where hot water is delivered
oil or kerosene. They are very similar to diesel fuel.
from a central point to all hot water outlets in the
Appliances tend to be big and quite noisy and they
dwelling. The water may be heated by a boiler or an
require regular servicing.
immersion heater
Solid fuel – there are many types of solid fuel used l localised systems, often called single point or point
to produce energy and provide heating and hot of use systems. With these systems, the hot water is
water, although the use of some solid fuels (e.g. coal) delivered by a small water heater at the point where
is restricted or prohibited in some urban areas, due it is needed.
to unsafe levels of toxic emissions. In some areas,
smokeless coal and coke are the only solid fuels used. Centralised systems
Renewable energy Centralised systems are those where the source of
hot water supply is sited centrally in the property for
Solar thermal – solar thermal technology utilises heat
distribution to all of the hot water outlets. They are
from the Sun to generate domestic hot water supply to
usually installed in medium to large domestic dwellings,
offset the water heating demand from other sources,
such as a three-bedroomed house. These can be further
such as electricity or gas.
divided into:
Geothermal – geothermal energy is heat directly from l centralised hot water storage systems
the Earth. It is a clean, renewable resource. Geothermal l centralised instantaneous hot water systems.
heat can be used directly, without involving a power
Centralised hot water storage systems are divided into:
plant or heat pump, for a variety of applications such
l open vented systems – those hot water storage
as space heating and cooling, hot water supply and
systems that are fed from a cistern in the roof
industrial processes. Its uses for bathing can be traced
space and contain a vent pipe that is open to the
back to the ancient Romans.
atmosphere
Biomass – the term ‘biomass’ can be used to describe l unvented systems – those hot water storage
many different types of solid and liquid fuels. It is systems that are fed directly from the cold water
defined as any plant matter used directly as a fuel or main and utilise an expansion vessel or an internal
that has been converted into other fuel types before air bubble to allow for expansion.
combustion. Generally, solid biomass is used as heating
Centralised instantaneous hot water systems can be
fuel, including wood pellets, vegetable waste (such as
divided into:
wood waste and crops used for energy production),
l gas fired instantaneous multi-point hot water
animal materials/wastes and other solid biomass.
heaters – those heaters that heat the water
instantaneously
2 THE TYPES OF l gas or oil fired combination boilers – operate in a
116
Open vented hot water storage l The cistern should be placed as high as possible to
systems ensure good supply pressure. The higher the cistern
then the greater the pressure at the taps. Poor
In an open vented storage hot water system, water is
pressure can be increased by raising the height of
heated, generally by a boiler or an immersion heater,
the cistern.
and stored in a hot water storage vessel sited in a
l All pipes should be laid with a slight fall (except the
central location in the property usually in the airing
hot water draw-off) to prevent air locks within the
cupboard. Open vented systems contain a vent pipe,
system.
which remains open to the atmosphere ensuring that
l The cold feed pipe from the storage cistern must
the hot water cannot exceed 100 °C. The vent pipe
only feed the hot water storage cylinder.
acts as a safety relief should the system become
l A drain off valve should be fitted at the lowest point
overheated. It must be sited over the cold feed cistern
of the cold feed pipe.
in the roof space.
As we discovered in Book 1, there are two types of
The cylinder is fed with water from the cold feed
open vented hot water storage systems. These are:
cistern. The capacity of the cistern will depend upon
l the direct system
the capacity of the hot water storage vessel. The
l the indirect system.
cistern feeding cold water to a hot water storage vessel
must be at least equal to that of the hot water storage Open vented direct hot water storage
vessel. Here are some important points to note about system
open vented hot water systems:
The direct open vented hot water storage system uses
l The open vent pipe must not be smaller than
a direct type hot water storage cylinder. The direct
22 mm pipe and must terminate over the cold
cylinder contains no form of heat exchanger and so
feed cistern.
is not suitable for use with central heating systems.
l The open vent pipe must not be taken directly from
The connections for the cold feed and draw-off are
the top of the hot water storage vessel.
usually male thread connections with the primary flow
l The hot water draw-off pipe should rise slowly from
and return connections are female thread. They are
the top of the cylinder to the open vent pipe and
usually heated by either one or two immersion heaters,
incorporate at least 450 mm of pipe between the
depending on the cylinder type or they may be heated
storage cylinder and its connection point to the
by a gas fired hot water circulator. Existing installations
open vent. This is to prevent parasitic circulation
may also use a back boiler placed behind a solid fuel
(also known as one pipe circulation) from occurring.
fire. Because the water in the boiler comes directly
l The cold feed pipe should be sized correctly. The
from the hot water storage cylinder, the boiler must be
cold feed is the main path for expansion of water
made of a material that does not rust. This is to prevent
to take place within the cylinder when the water is
rusty water being drawn off at the taps. Suitable boiler
heated. The heated water from the cylinder expands
materials are:
up the cold feed pipe raising the water level in the
l copper
cold feed cistern.
l stainless steel
l bronze.
117
A typical direct system using immersion heaters is Open vented indirect (double feed type) hot
shown in Figure 2.1. water storage system
This is probably the most common of all hot water
delivery systems installed in domestic properties. It
uses a double feed indirect hot water storage cylinder,
which contains a heat exchanger, at the heart of the
system. The heat exchanger within the cylinder is
22 mm vent pipe discharging into the usually a copper coil but, in older type cylinders, it
CWSC and sealed with a grommet
can also take the form of a smaller cylinder called
an annular. It is called indirect simply because the
secondary water in the cylinder is heated indirectly by
the primary water via the heat exchanger.
22 mm or 28 mm cold feed to
secondary hot water system
22 mm or 28 mm full way gate valve
In a double feed indirect system two cisterns are used –
or lever type spherical ball valve
a large cistern for the domestic hot water and a smaller
22 mm draw-off to the bath then reduced
to 15 mm to all other appliances
one for the heating. It is now general practice to install
indirect cylinders in preference to direct types, even if
the indirect flow and return are capped off.
The double feed indirect hot water storage cylinder
allows the use of boilers and central heating systems
that contain a variety of metals, such as steel and
Heat source. Top immersion heater for daytime top up.
aluminium because the water in the cylinder is totally
Bottom immersion heater heats up all the water in the
cylinder via a time controller for use with cheap rate separate from the water in the heat exchanger. This
overnight electricity
means that there is no risk of dirty or rusty water being
drawn off at the taps. The system is designed in such a
way that the water in the boiler and primary pipework
is hardly ever changed, the only loss of water being in
the feed and expansion cistern through evaporation.
The secondary water is that which is drawn from the
hot water storage cylinder to supply the hot taps. It is
heated by conduction as the water in the cylinder is in
contact with the heat exchanger.
A feed and expansion cistern feeds the primary
Figure 2.1 Direct open vented hot water storage system
part of the system, and this must be large enough
to accommodate the expansion of the water in the
The indirect system
system when it is heated. The vent pipe from the
An indirect system uses an indirect-type hot water primary system must terminate over the feed and
storage cylinder, which contains some form of heat expansion cistern. An alternative method would be to
exchanger to heat the secondary water. There are two use a sealed heating system, which is fed with water
distinct types: from the cold water main via a filling loop. Expansion of
l the double feed indirect hot water storage cylinder water is accommodated in an expansion vessel.
l the single feed, self-venting indirect hot water
118
15 mm cold feed to
22 mm or 28 mm cold feed to the primary system
secondary hot water system
22 mm or 28 mm full way
gate valve or lever type
spherical ball valve
28 mm primary flow
and return pipes from
Central heating the boiler to the coil in
flow and return the cylinder
Figure 2.2 An old indirect gravity open vented (double feed) hot water storage system
Open vented indirect (single feed, self- feed and expansion cistern. The heat exchanger
venting type) hot water storage system works in such a way that the primary and secondary
This system uses a single feed, self-venting indirect water are separated by a bubble of air that collects
cylinder, often referred to by its trade name – the in the heat exchanger, preventing the waters from
‘primatic’ cylinder. It contains a special heat exchanger, mixing. According to the Domestic Building Services
which uses air entrapment to separate the primary Compliance Guide, these cylinders are no longer
water from the secondary water. allowed for new or replacement cylinders. A ‘double
feed’ type cylinder must be used on all replacement
It is fitted in the same way as a direct system, with
installations.
only one cold feed cistern in the roof space but,
unlike the direct system, it allows a boiler and central A typical open vented indirect (single feed, self-venting
heating to be installed. It does not require a separate type) hot water storage system utilising gravity
circulation is shown in Figure 2.3.
119
Figure 2.3 Indirect open vented single feed self-venting hot and discharge pipework size
water storage system l the type of terminal fittings to be used – this is
120
Most unvented cylinders are manufactured from l Units are delivered with all the components already
high-grade duplex stainless steel for strength and factory fitted and require less installation time.
corrosion resistance. Some older cylinders may be l Packages are delivered with all components
manufactured from copper or steel with a polyethylene separately packaged (except those required for
or cementitious lining. safety, such as temperature relief valves). These
have to be fitted by the installer in line with the
Unvented hot water storage cylinders can be purchased manufacturer’s instructions.
as ‘units’ or ‘packages’:
Isolation valve
In-line strainer
Hot water draw-off Expansion vessel
Temperature Pressure reducing valve
relief valve
Expansion (pressure)
Immersion heaters relief valve
D1 discharge pipework
Tundish
D2 discharge pipework
Cold feed
In-line strainer
D2 discharge pipework
Return
Cold feed
121
The various types of unvented hot water secondary system. This can be done in one of two
system ways:
There are three basic types of unvented hot water l by the use of a gas fired condensing boiler
system. They are defined by how the water is heated. l by the use of an oil fired condensing boiler.
In-line strainer
D2 discharge pipework
Return
Cold feed
Figure 2.6 The indirect type unvented hot water storage cylinder
122
Isolation valve
In-line strainer
Hot water draw-off Expansion vessel
Temperature Pressure reducing valve
relief valve
Expansion (pressure)
Immersion heaters relief valve
D1 discharge pipework
Tundish
D2 discharge pipework
Cold feed
Figure 2.7 The electrically heated direct type unvented hot water storage cylinder
123
Terminal
Isolation valve
In-line strainer
Flue pipe
Pressure
Balanced cold reducing valve Draught diverter
connection
Expansion
vessel
Single
check valve
Temperature
relief valve
Expansion
(pressure)
relief valve Tundish
Discharge
pipe
Figure 2.8 The gas fired direct type unvented hot water storage cylinder
Direct unvented under sink storage heaters surround the installation of larger unvented hot water
Unvented under sink hot water storage heaters are storage units.
connected direct to the mains cold water supply and The expansion of water may be taken up within the
deliver hot water at near mains cold water pressure. pipework, provided the pipework is of sufficient size to
Because they have less than 15 litres of storage, cope with the water expansion. If not, then an external
they are not subject to the stringent regulations that expansion vessel will be required.
Figure 2.9 The unvented type under sink storage water heater pipework layout
124
Table 2.1 Comparisons between vented and unvented storage hot water systems
Advantages Disadvantages
Open vented systems
l Storage is available to meet the demands at peak times l Space needed for both the hot water storage vessel and
l Low noise levels the cold water storage
l Always open to the atmosphere l Risk of freezing
l Water temperature can never exceed 100 °C l Increased risk of contamination
l Reserve of water available if the mains supply is interrupted l Low pressure and often, poor flow rate
l Low maintenance l Outlet fittings can be limited because of the low
l Low installation costs pressure
Unvented systems
l Higher pressure and flow rates at all outlets giving a larger l No back up of water should the water supply be
choice of outlet fittings isolated
l Balanced pressures at both hot and cold taps l If the cold water supply suffers from low pressure or
l Low risk of contamination flow rate, the system will not operate satisfactorily
l The hot water storage vessel can be sited almost anywhere in l There is the need for discharge pipes that will be able
the property making it a suitable choice for houses and flats to accept very hot water and there will be restrictions
alike on their length
l The risk from frost damage is reduced l A high level of maintenance is required
l Less space required because cold water storage is not needed l Higher risk of noise in the system pipework
l Installation is quicker as less pipework is required l Initial cost of the unvented hot water storage vessel is
l Smaller diameter pipework may be used in some high
circumstances
125
Combustion air in
Flue gas outlet
Combustion air in
Pressure
switch
Combustion air in
Automatic
air valve Primary heat exchanger
Spark igniter
Gas burner
Diverter valve
Central heating
flow and return
126
Inside the unit are two heat exchangers which the Gas or oil fired combined primary storage
mains cold water passes through and a small expansion units
chamber. The expansion chamber allows for the These are very similar in design to thermal stores and
small amount of expansion of the secondary water. work in exactly the same way, in that cold water from
The primary water can reach temperatures of up the mains supply is passed through a heat exchanger.
to 82 °C, which can, potentially, be transferred into The difference here is that the unit has its own heat
the secondary water. Because of this, an adjustable source, in the form of a gas burner, to heat the primary
thermostatic mixing valve blends the secondary hot water, eliminating the need for a separate boiler.
water with mains cold water so that the water does not
exceed 60 °C.
Boiler
Heat exchanger
Expansion
chamber
To hot taps
Pump on
primary return To cold taps
Central heating Heat exchanger
pump
Heating flow
Heating return
Adjustable
thermostatic
mixing valve
Central
heating flow Hot water oulet
Central
heating return
Mains cold
water supply
Gas burner
127
128
Insulation
Open vent to allow
for expansion
Heater element
Thermostat
Under sink
water heater
130
Temperatures above this can only be used in and flow rate. The shower control and the water mixer
exceptional circumstances. have digital intelligence built in.
l Showers – these installations usually require a
Digital mixer showers take water from both the hot and
temperature of not more than 43 °C. In residential
cold water supplies and mix them in an electronically
care homes and other medical facilities, a
controlled mixing valve to accurately reach the desired
temperature of not more than 41 °C should be used
temperature. An electronic control panel mounted in
according to NHS guidelines.
the showering area provides separate control of the
l Washbasins – careful consideration must be made
water flow rate and the temperature. A processor box
with washbasin installations because this is probably
sited remotely adjusts the flow and temperature to
the only appliance used in domestic dwellings where
the settings selected by the user on the control panel.
the user puts their hands directly in the running
These are then controlled electronically to provide the
water without waiting for the water to get hot.
desired temperature and flow at the shower.
When the water reaches maximum temperature,
scalding can occur. Therefore, typical temperatures Accurate control is maintained by the adjustment
between 38 °C and 41 °C can be used depending of separate proportioning valves and pumps or by
upon the application. Again, NHS guidelines motorised control of a mixing valve.
recommend a temperature of no more than 41 °C.
l Bidets – a maximum of 38 °C should be used with Group mixing
bidet installations. Installations where a number of appliances of a similar
l Kitchen sinks – this is probably the area where type are fed from a single TMV are allowed in certain
the user is most at risk. The need to ensure that installations. However, installations of this type are not
bacteria and germs are killed and that grease recommended where the occupants are deemed to be
is thoroughly removed dictates that a water high risk, such as nursing homes. If a group installation
temperature of between 46 °C and 48 °C is used. is to be considered, then the following points should be
However, as the kitchen is an area with no published followed:
recommendations on hot water temperature, a safe l The operation of any one appliance should not
notices warning of very hot water are used. outlets, the length of the pipework from the valve to the
outlets should be kept as short as possible so that the
Thermostatic mixing valve mixed water reaches the furthest tap within 30 seconds.
Bath
l With group shower installations, it is not unusual
132
133
Isolation In-line
valve strainer
KEY TERM
Secondary circulation in Dead leg: when a hot tap is opened, a certain
domestic dwellings amount of cold water is usually drawn off and
allowed to run to drain before hot water arrives
Secondary circulation is required where the length of at the tap. This wasted, cold water is known as
any draw-off pipework is excessive. British Standard a dead leg. Under the Water Regulations, dead
BS EN 806 and the Water Supply (Water Fittings) legs must be restricted to the lengths given in
Regulations give the maximum length a hot water Table 2.3. If this is not possible, then secondary
draw-off pipe may travel without a secondary circulation is required.
circulation system being installed. These lengths are
reproduced in Table 2.3 below.
Table 2.3 Maximum recommended lengths of uninsulated hot
INDUSTRY TIP
water pipes
A secondary circulation pump is very similar in design
Outside diameter of pipe (mm) Maximum length (m) to a central heating circulator. The difference is that the
12 20 secondary circulating pump has a body cast from bronze to
Over 12 up to and including 22 12 eliminate discoloured water and subsequent contamination.
Bronze, as we discovered at Level 2, is a non-ferrous metal
Over 22 up to and including 28 8
that does not rust. Central heating circulators have a cast
Over 28 3
iron or steel body that would rust if used on a secondary
It should be remembered that no DHWS dead leg should exceed a circulation system. Under no circumstances should a central
volume of 0.5 litres. The table is designed around this figure with heating circulator be used.
pipe volumes /m giving a maximum length per diameter.
134
In all installations, secondary circulation must use not possible to install a connection of the vessel itself.
forced circulation via a bronze or stainless steel-bodied Where secondary circulation is required, this must
circulating pump to circulate the water to and from the be taken to the cold water feed connection using a
storage cylinder. The position of the pump will depend swept tee just before the cold feed enters the unit. To
upon the type of hot water system installed. safeguard against reverse circulation, a non-return valve
or single check valve must be fitted after the circulating
pump and just before the swept tee branch. The pump
should be fitted on the secondary return, close to the
hot water storage vessel.
Isolation valve
In-line strainer
Single check
valve Pressure
relief valve
Expansion bubble
Temperature
relief valve
Tundish
Single check
valve
Swept
'tee'
Bronze pump
Secondary circulation
135
Some open vented cylinders can be purchased with a cylinder would never reach the disinfecting temperature
secondary return connection already installed on the of 60 °C and so would always be at risk of a Legionella
cylinder. Alternatively, an Essex flange can be used on outbreak, however remote.
cylinders where no connection exists.
By installing a single check valve on the return and
positioning it between the pump and the cylinder,
Open vent pipe
reverse circulation is prevented.
Cold feed pipe
Figure 2.25 Secondary circulation on an open vented hot water Insulating secondary circulation pipework
storage installation If secondary circulation systems are installed, they
should be insulated for the entire length of the system.
This is to prevent excessive heat loss through the
extended pipework due to the water being circulated
by a circulating pump. The insulation should be thick
enough so as to maintain the heat loss below the
values in Table 2.4.
Table 2.4 Insulation thickness for secondary circulation pipework
circulation circuit should have a return temperature of Figure 2.27). This is to circulate the water within
50 °C when it reaches the cylinder at the end of the the cylinder to ensure that the varying temperature
circuit. In this way, the hottest part of the cylinder will (stratification) of the water inside is kept to a
always be the top where the hot water is drawn off. minimum and to ensure an even heat distribution
If reversed circulation were to occur, the water in the throughout, thereby preventing the growth of the
136
Legionella bacteria. Stratification is desirable during Here are some points to remember regarding large
the day so that the draw-off water is maintained at centralised hot water systems:
its hottest for the longest period of time. Because l The pipework should be carefully designed to
of this, the shunt pump should only operate during prevent dead legs as this is a major concern with
periods of low demand (such as at night). regard to Legionella pneumophila.
l The secondary circulation pump (component 5 in l The hot water storage vessel should be capable of
Figure 2.27) is installed on the secondary flow and being heated to 70 °C, again, to kill any Legionella
not the secondary return as with other, smaller that may be present.
systems. l There should be easy access for draining, cleaning,
reverse circulation does not occur. should be insulated on its underside to prevent
l A cylinder thermostat (component 3 in Figure 2.27) excessive heat loss.
is provided to maintain the temperature within the
cylinder at a maximum of 60 °C. The use of trace heating instead of
l A pipe stat (component 2 in Figure 2.27) installed secondary circulation
on the secondary flow maintains the temperature Electric trace heating uses an electric cable that forms
at a minimum of at least 50 °C. a heating element. It is positioned directly in contact
l A motorised valve (component 4 in Figure 2.27) is with the pipe along the whole length of the pipe
installed on the secondary return close to the hot length. The pipe is then covered in thermal insulation.
water storage vessel to prevent water being drawn The heat generated by the element keeps the pipe at a
from the secondary return when the pump is not specific temperature.
operating.
l Lockshield gate valves (components 7 and 8 in The operation of the trace heating element should
Figure 2.27) are provided to balance the system to be timed to a period when the hot water system is in
ensure even circulation throughout the secondary most use (such as early in the morning and evening). If
water system. the pipe is well insulated and installed with a timer, the
l The secondary circulation system, shunt pumps and amount of energy usage will be minimal.
thermostats are controlled through a control box By using trace heating, the additional cost of the extra
(component 1 in Figure 2.27). pipework for the secondary return and its associated
pump and running costs is removed.
2
6
4
5 8
3
INDUSTRY TIP
Figure 2.27 Secondary circulation on a large domestic open Trace heating can also be used as frost protection on cold
vented hot water storage installation
water systems.
137
Pressure
relief
valve Temperature
& pressure
relief
valve
In-line
strainer
Tundish
Pressure
reducing
valve
Isolation valve
Single check valve
138
139
140
Replacement internal cartridges are available and Expansion device (vessel or integral
easily fitted without changing the valve body should a to cylinder)
malfunction occur.
Water expands when heated. Between 4 and 100 °C
Modern PRVs for unvented hot water storage systems are it will expand by approximately 4 per cent. Therefore
supplied with a balanced cold connection already fitted. 100 litres of water at 4 °C becomes 104 litres at
100 °C. It is this expansion of water that must be
accommodated in an unvented hot water storage
system. This can be achieved in one of two ways:
l by the use of an externally fitted expansion vessel
141
Figure 2.38 Workings of a bladder (bag) type expansion vessel Figure 2.39 Bladder (bag)
type expansion vessel
With some bladder expansion vessels, the bladder is Again, like the bladder type expansion vessel, a
replaceable in the event of bladder failure. A flange at Schrader valve is fitted to allow top-up and testing of
the base of the vessel holds the bladder in place. By the air pressure. Figure 2.40 shows the workings of a
releasing the air and removing the bolts, the bladder diaphragm type expansion vessel.
can be withdrawn and replaced.
Internal expansion
The diaphragm type expansion vessel With internal expansion, an air pocket is formed as
Diaphragm expansion vessels are used where the water the hot water storage vessel is filled. A floating baffle
has been de-oxygenated by the use of inhibitors or plate provides a barrier between the air and the water
because the water has been repeatedly heated, such as so that there is minimum contact between the air and
in a sealed central heating system. They must not be the water in the cylinder. When the water is heated,
used with unvented hot water storage systems because the expansion pushes the baffle plate upwards in a
the water is always oxygenated and comes into direct similar manner to an expansion vessel.
contact with the steel of the vessel. Over a period of time, the air within the air bubble
They are made in two parts with a neoprene rubber will dissipate as it is leeched into the water. When this
diaphragm separating the water from the air charge. happens, expansion cannot take place and the pressure
relief valve will start to discharge water. However,
A Diaphragm B C
Figure 2.40 The workings of a diaphragm type expansion vessel Figure 2.41 Diaphragm type
expansion vessel
142
this will only occur as the water heats up. Once the In other words, if the volume is halved, the pressure is
cylinder is at its full temperature, the pressure relief doubled.
valve will close and will only begin to discharge water
Mathematically, Boyle’s law is expressed as:
again when expansion is taking place. Because of
P1V1 = P2V2
this, manufacturers of bubble top units and packages
recommend that the cylinder is drained down Where:
completely and refilled to recharge the air bubble. P1 = initial pressure = 1 bar
V1 = initial volume = 20 litres
INDUSTRY TIP P2 = final pressure = to be found
V2 = final volume = 20 litres – 10 litres of expanded
The cylinder should be drained on an annual basis, or as water
and when required.
So, to find the pressure in the vessel, the formula must
The scientific principles of expansion be transposed:
vessels P1 × V1
P2 =
The principle of an expansion vessel is that a gas is V2
compressible but liquids are not. That principle is based Therefore:
upon Boyle’s law. In this case the gas is air or nitrogen
and the liquid is water. P2 = 1 bar × 20 litres
10 litres
Boyle’s law states: = 2 bar final cold pressure
The volume of a gas is inversely proportional
to its absolute pressure provided that the
temperature remains constant.
Air
143
IMPROVE YOUR MATHS The capacity left in the vessel after the initial fill is
15 litres with a cold fill pressure of 1 bar and that
If, on the initial cold fill of the system, the vessel
10 litres of water are to expand inside the vessel, the
required, say, 5 litres of water to be taken in, the air
final pressure of the system will be:
pressure to apply to the vessel can be calculated. We
can assume a water pressure of 1 bar. P × V1
P2 = 1
P1 = 1 bar V2
Therefore:
V1 = 20 litres
P2 = 1 × 15 = 15 = 3 bar
V2 = 20 litres – 5 litres = 15 litres 15 - 10 5
P2 = pressure to be calculated The initial pressure of the empty 20 litre vessel was
P1 × V1 1.33 bar. On initial cold fill 5 litres of water entered
P2 = the vessel reducing the capacity to 15 litres. As a
V2
result, the air was compressed even more when the
Therefore: expansion of water takes place and instead of 2 bar
final pressure, the pressure when the water is heated
1 bar × 20 litres
P2 = = 1.33 bar will be 3 bar.
15 litres
144
l to provide a visual indication that either the manufacturers now prefer to supply composite valves
pressure relief or temperature relief valves are which incorporate many components into one ‘multi-
discharging water due to a malfunction valve’. A typical composite valve will contain:
l to provide a physical, type A air gap between l a strainer
the discharge pipework and the pressure relief/ l a pressure reducing or pressure limiting valve,
145
is, therefore, very important that it is installed correctly pipe they should be either polybutalene (PB)
with correct size of pipe and that the pipework is made to class S of BS 7291.2:2010 or cross linked
from the correct material, especially since the water polyethylene (PE-X) to Class S of BS 7291.
discharged may be at near boiling point. There are 3:2010
three sections to the discharge pipework: l be marked along the entire length with a
146
600 mm max.
Tundish
300 mm
min.
D2 discharge pipework must Fixed
have continuous fall grating
Trapped
gulley
The pipe size and positioning length of pipe without increasing the pipe size. Where
methods for safety relief (discharge) the discharge pipework exceeds 9 m, the size of the
discharge pipe will require calculating including the
pipework connected to unvented
resistance of any bends and elbows. You can use Table
hot water cylinder safety valves 2.5 to do this.
As we have already seen, the discharge pipework must
not exceed the hydraulic resistance of a 9 m straight
Table 2.5 Sizing discharge pipework
Valve outlet Maximum size Maximum size of Maximum resistance allowed, Resistance
size of discharge to discharge pipe from expressed as a length of straight created by each
tundish (D1) (mm) tundish (D2) (mm) pipe without bends or elbow (m) bend or elbow (m)
22 Up to 9 0.8
G½ 15 28 Up to 18 1.0
35 Up to 27 1.4
28 Up to 9 1.0
G¾ 22 35 Up to 18 1.4
42 Up to 27 1.7
35 Up to 9 1.4
G1 28 42 Up to 18 1.7
54 Up to 27 2.3
147
148
600 mm max.
Tundish
100 mm max.
600 mm max.
Tundish
KEY POINT
The discharge may consist of high temperature
water and steam. Asphalt, roofing felt and other
non-metallic rainwater goods may be damaged by
very high temperature hot water discharges.
149
Cold water systems, planning and design. hot water systems, multiple fuels may be used in
one system, such as utilising gas, oil or solid fuel as
the main fuel source with an electrical alternative
4 DESIGN TECHNIQUES (immersion heater) as back-up or for summer use.
FOR HOT WATER Multipoint heaters do not have this capability and
so fuel type usage is very limited.
SYSTEMS l Installation and maintenance costs – again, a
150
Hot water
supply
Localised or
Centralised system single point system
Immersion Immersion
heater heater
151
l Part 2 is an expanded requirement. It states must be designed and installed to actively reduce the
that any hot water system, including associated amount of CO2 produced. The building fabric must
storage (including any cold water storage cistern) contain insulation to limit heat loss, and heating
or expansion vessel must resist the effects of any appliances, associated controls and equipment and
temperature or pressure that may occur during lighting systems must all reduce the energy wasted.
normal use as a consequence of any reasonably Pipes and storage vessels must also be insulated to
anticipated fault or malfunction. This amendment reduce the waste of energy.
was enforced after the failure of an immersion
heater thermostat that caused the collapse of a This document should be read in conjunction with the
storage cistern containing water almost at boiling Domestic Building Compliance Guide.
point.
l Part 3, again, is an amended requirement. It INDUSTRY TIP
states that any part of a hot water system that
incorporates a hot water storage vessel must Copies of the Building Regulations Approved Documents G3
include precautions to ensure that the temperature 2010 and L 2013 can be downloaded free from these links:
of the stored water does not exceed 100 °C and www.gov.uk/government/publications/sanitation-hot-water-
that any discharge from such safety devices is safety-and-water-efficiency-approved-document-g
safely conveyed to a point where it is visible www.gov.uk/government/publications/conservation-of-fuel-
without constituting a danger to persons in or and-power-approved-document-l
about the building.
l Part 4 states that any hot water supply to a
fixed bath must include provision to limit the The Water Supply (Water Fittings)
temperature of the discharged water from any Regulations 1999
bath tap so that it cannot exceed 48 °C. This In many respects, the Water Regulations mirror
requirement applies to any new-build or property the Building Regulations and these two documents
conversions. It is a new requirement that is should be consulted before undertaking any design or
intended to prevent scalding. installation of hot water systems.
It is interesting to note that Regulation G3 applies to Hot water supply is covered in Section 8 of Schedule
all domestic dwellings, including greenhouses, small 2 of the Water Supply (Water Fittings) Regulations. It
detached buildings, extensions and conservatories, but is reproduced here complete with the guidance notes
only if they are served with hot water supplied from a attached to the regulations (published by Defra –
dwelling. Department for Environment Food & Rural Affairs).
It should be noted that the local building control
officer should be informed before commencing any KEY POINT
installation of a hot water system. Remember! It is an offence to contaminate,
misuse, waste, unduly consume or erroneously
The Building Regulations Approved meter water from a water undertaker’s water main.
Document L1A/B 2010 The Water Supply Regulations are enforceable in a
court of law.
This document promotes the conservation of fuel
and power. The basic outline to this document is that
the building and services contained within a dwelling
152
SECTION 8 Guidance
Schedule 2: Paragraphs 17, 18, 19, 20, 21, 22, 23 and
24: Hot water services
17 (1) Every unvented water heater, not being an Unvented hot water systems
instantaneous water heater with a capacity not greater than G17.1 Every unvented water heater or storage vessel, and
15 litres, and every secondary coil contained in a primary every secondary coil contained in a heater and not being an
system shall: instantaneous water heater or a thermal storage unit of 15
a Be fitted with a temperature control device and either litres or less capacity, should be fitted with:
a temperature relief valve or a combined pressure and a A temperature control device; and either a temperature
temperature relief valve; or relief valve or combined temperature and pressure relief
b Be capable of accommodating expansion within the valve; and
secondary hot water system. b An expansion valve; and
(2) An expansion valve shall be fitted with provision to ensure c Unless the expanded water is returned to the supply pipe
that water is discharged in a correct manner in the event of a in accordance with Regulation 15(2)(a), either;
malfunction of the expansion vessel or system. i An expansion vessel; or
18 Appropriate vent pipes, temperature control devices and ii Contain an integral expansion system, such that the
combined temperature pressure and relief valves shall be expansion water is contained within the secondary
provided to prevent the temperature of the water within a system to prevent waste of water.
secondary hot water system from exceeding 100 °C. G17.2 An expansion valve should be fitted to all unvented hot
water storage systems, with a capacity in excess of 15 litres,
to ensure that expansion water is discharged in a correct
manner in the event of a malfunction of the expansion vessel
or system.
G17.3 Where expansion water is accommodated separately the
expansion vessel should preferably be of an approved ‘flow
through type’ and should comply with the requirements of BS
6144 and BS 6920.
Temperature of hot water within a storage system
G18.1 Irrespective of the type of fuel used for heating, the
temperature of the water at any point within a hot water
storage system should not exceed 100 °C and appropriate
Figure 2.51 Pipe insulation vent pipes, temperature control devices and other safety
19 Discharges from temperature relief valves, combined devices should be provided to prevent this occurring.
temperature pressure and relief valves and expansion valves Hot water distribution temperatures
shall be made in a safe and conspicuous manner. G18.2 Hot water should be stored at a temperature of not
20 (1) No vent pipe from a primary circuit shall terminate over less than 60 °C and distributed at a temperature of not less
a storage cistern containing wholesome water for domestic than 55 °C. This water distribution temperature may not be
supply or for supplying water to a secondary system. achievable where hot water is provided by instantaneous or
(2) No vent pipe from a secondary circuit shall terminate over combination boilers.
any combined feed and expansion cistern connected to a G18.3 The maintenance of acceptable water temperatures
primary circuit. may be achieved by efficient routing of pipes, reducing
21 Every expansion cistern or expansion vessel, and every the lengths of pipes serving individual appliances and the
cold water combined feed and expansion cistern connected application of good insulation practices to minimise freezing
to a primary circuit, shall be such as to accommodate any of cold water pipes and to promote energy conservation
expansion water from that circuit during normal operation. for hot water pipes. For references, see Comments and
22 (1) Every expansion valve, temperature relief valve or Recommendations of Clause 4.3.32.2 of BS 8558.
combined temperature and pressure relief valve connected Temperature of hot water supplies at terminal fittings and on
to any fitting or appliance shall close automatically after a surfaces of hot water pipes
discharge of water. G18.4 Where practicable the hot water distribution system
(2) Every expansion valve shall: should be designed and installed to provide the required flow
a Be fitted on the supply pipe close to the hot water vessel of water at terminal fittings to sanitary and other appliances
and without any intervening valves; and at a water temperature of not less than 50 °C and within
b Only discharge water when subjected to a water pressure 30 seconds after fully opening the tap. This criteria may not
of not less than 0.5 bar (50 kPa) above the pressure to be achievable where hot water is provided by instantaneous
which the hot water vessel is, or is likely to be, subjected or combination boilers.
in normal operation.
➜
153
SECTION 8 Guidance
Schedule 2: Paragraphs 17, 18, 19, 20, 21, 22, 23 and
24: Hot water services
23 (1) A temperature relief valve or combined temperature G18.5 Terminal fittings or communal showers in schools or
and pressure relief valve shall be provided on every unvented public buildings, and in other facilities used by the public,
hot water storage vessel with a capacity greater than 15 litres. should be supplied with water through thermostatic mixing
(2) The valve shall: valves so that the temperature of the water discharged at the
a Be located directly on the vessel in an appropriate outlets does not exceed 43 °C.
location, and have a sufficient discharge capacity, to G18.6 The temperature of water discharged from terminal
ensure that the temperature of the stored water does not fittings and the surface temperature of any fittings in
exceed 100 °C; and health care premises should not exceed the temperatures
b Only discharge water at below its operating temperature recommended in HS(G)104 – Safe hot water and surface
when subjected to a pressure of not less than 0.5 bar temperatures.
(50 kPa) in excess of the greater of the following: Energy conservation
i The maximum working pressure in the vessel in which it
G18.7 All water fittings forming part of a primary or secondary
is fitted, or
hot water circulation system and all pipes carrying hot water
ii The operating pressure of the expansion valve.
to a tap that are longer than the maximum length given in the
(3) In this paragraph “unvented hot water storage vessel” below table should be thermally insulated in accordance with
means a hot water storage vessel that does not have a vent BS 5422.
pipe to the atmosphere.
24 No supply pipe or secondary circuit shall be permanently Maximum recommended lengths of uninsulated hot water pipes
connected to a closed circuit for filling a heating system
unless it incorporates a backflow prevention device in Outside diameter (mm) Maximum length (m)
accordance with a specification approved by the regulator for 12 20
the purposes of this Schedule.
Over 12 and up to 22 12
Over 22 and up to 28 8
Over 28 3
G19.1 Discharge pipes from expansion valves, l have a vertical drop of 300 mm below the tundish
temperature relief valves and combined temperature outlet, and thereafter be laid to a self-draining gradient
and pressure relief valves should be installed in l be at least one size larger than the nominal outlet
accordance with the guidance given in this document size of the valve, unless its total equivalent hydraulic
and should also comply with the requirements of resistance exceeds that of a straight pipe 9 metres
Building Regulation G3. long. Where the total length of the pipe exceeds
9 metres equivalent resistance, the pipe shall be
Discharge pipes from safety devices increased in size by one nominal diameter for
G19.2 Where discharge pipes pass through environments each additional, or part of, equivalent 9 metres
outside the thermal envelope of the building they should resistance length. The flow resistance of bends in
be thermally insulated against the effects of frost. the pipe should be taken into consideration when
determining the equivalent length of pipe
G19.3 The discharge pipe from a temperature relief valve
l terminate in a safe place where there is no risk to
or combined temperature and pressure relief valve should:
persons in the vicinity of the point of discharge. See
l be through a readily visible air gap discharging over
Building Regulation G3.
a tundish located in the same room or internal space
and vertically as near as possible, and in any case
within 600 mm, of the point of outlet of the valve KEY POINT
l be of non-ferrous material, such as copper or stainless
Alternatively, the size of the discharge pipe may
be determined in accordance with Annex D of
steel, capable of withstanding any temperatures
BS EN 806.3 (which refers back to BS 6700:1997
arising from a malfunction of the system Annex C).
154
Discharge pipes from expansion valves l be so arranged that expansion water can pass back
G19.4 The discharge pipe from an expansion valve may through a feed pipe to the cold water storage cistern
discharge into the tundish used for the discharge from a from which the apparatus or cylinder is supplied
temperature relief valve or from a combined temperature with water.
and pressure relief valve as described in G19.1, or: G20.5 Where the cold water storage cistern supplying
l discharge through a readily visible air gap over a water to the hot water storage vessel is also used
tundish located in the same room or internal space to supply wholesome water to sanitary or other
and vertically as near as possible and in any case appliances, any expansion water entering the cistern
within 600 mm of the point of outlet of the valve; through the feed pipe should preferably not raise the
and, temperature of the wholesome water in the cistern to
l be of non-ferrous material, such as copper or more than 20 °C.
stainless steel; and,
l discharge from the tundish through a vertical drop Vented systems requiring dedicated storage
outlet and thereafter be laid to a self-draining cisterns or mechanical safety devices
gradient; and, G20.6 Every vented and directly heated hot water
l not be less than the nominal outlet size of the storage vessel, single feed indirectly heated hot water
expansion valve and discharge external to the storage vessel, or any directly or indirectly heated
building at a safe and visible location. storage vessel where an electrical immersion heater
is installed, should be supplied with water from a
Vent pipes
dedicated storage cistern unless:
G20.1 Vent pipes from primary water systems should l where the energy source is gas, oil or electricity, a
be of adequate size but not less than 19 mm internal non-self-setting thermal energy cut-out device is
diameter. They may terminate over their respective cold provided in addition to the normal temperature-
water feed and expansion cisterns, or elsewhere providing operated automatic-reset cut-out; or,
there is a physical air gap, at least equivalent to the size l where the energy source is solid fuel, a temperature
of the vent pipe, above the top of the warning pipe, or relief valve complying with BS EN 1490:2000, or
overflow if there is one, at the point of termination. a combined temperature and pressure relief valve
G20.2 Vent pipes from hot water secondary storage complying with BS EN 1490:2000, is provided
systems should be of adequate size but not less than complete with a readily visible air-break to drain
19 mm internal diameter and be insulated against freezing. device and discharge pipe as described in G19.3.
G20.3 Where vent pipes, from either a primary or G20.7 Every double feed indirectly heated hot water
secondary system, terminate over their respective cold storage system which is heated by a sealed (unvented)
water feed cisterns, they should rise to a height above primary circuit, or the primary circuit heating medium
the top water level in the cistern sufficient to prevent is steam or high temperature hot water, or where an
any discharge occurring under normal operating electric immersion heater is installed, should:
conditions. l be supplied with water for the secondary circuit
155
G20.9 Vent pipes from primary circuits should not BS EN 1490:2000, should be provided on every
terminate over cold water storage cisterns containing unvented hot water storage vessel. The valve should:
wholesome water for supply to sanitary appliances or l be located directly on the storage vessel, such
secondary hot water systems. that the temperature of the stored water does not
exceed 100 °C; and,
G20.10 Vent pipes from secondary hot water systems
l only discharge water at below its operating
should not terminate over feed and expansion cisterns
temperature when subjected to a pressure not less
supplying water to primary circuits.
than 0.5 bar (50 kPa) greater than the maximum
G20.11 No water in the primary circuit of a single working pressure in the vessel to which it is fitted, or
feed indirect hot water storage vessel, under normal 0.5 bar (50 kPa) greater than the operating pressure
operating conditions, should mix with water in the of the expansion valve, whichever is the greater.
secondary circuit. Single feed indirect hot water storage
vessels should be installed with a permanent vent to Non-mechanical safety devices
the atmosphere. G23.2 If a non-mechanical safety device such as a
fusible plug is fitted to any hot water storage vessel,
Primary feed and expansion cisterns that vessel requires a temperature relief valve or
G21.1 Every expansion cistern, and every cold water combined temperature and pressure relief valve
combined feed and expansion cistern connected to designed to operate at a temperature not less than
a primary or heating circuit should be capable of 5 °C below that at which the non-mechanical device
accommodating any expansion water from the circuit operates or is designed to operate.
and installed so that the water level is not less than
25 mm below the overflowing level of the warning pipe Filling of closed circuits
when the primary or heating circuit is in use. G24.1 No primary or other closed circuit should be
directly and permanently connected to a supply pipe
Expansion and safety devices unless it incorporates an approved backflow prevention
G22.1 Expansion valves, temperature relief valves arrangement.
or combined temperature and pressure relief valves
G24.2 A connection may be made to a supply pipe
connected to any fitting or appliance should close
for filling or replenishing a closed circuit by providing a
automatically after an operational discharge of water
servicing valve and an appropriate backflow prevention
and be watertight when closed.
device, the type of which will depend on the degree
G22.2 Expansion valves should comply with BS EN of risk arising from the category of fluid contained
1490:2000. They should be fitted on the supply pipe within the closed circuit, providing that the connection
close to the hot water vessel and without any intervening between the backflow prevention device and the closed
valves, and only discharge water when subjected to a circuit is made by:
water pressure of not less than 0.5 bar (50 kPa) above the l a temporary connecting pipe which must be
pressure to which the hot water vessel is, or is likely to completely disconnected from the outlet of the
be, subjected to in normal operation. backflow prevention device and the connection to
the primary circuit after completion of the filling or
Temperature and combined temperature replenishing procedure; or
relief valves l a device which in addition to the backflow
G23.1 Except for unvented hot water storage vessels of prevention device incorporates an air gap or break in
a capacity of 15 litres or less, a temperature relief valve the pipeline which cannot be physically closed while
complying with BS EN 1490:2000, or a combined the primary circuit is functioning; or
temperature and pressure relief valve complying with l an approved backflow prevention arrangement.
156
157
158
Table 2.6 Recommended minimum storage of hot water for service depends on the rate of heat input to the stored
domestic installations (BS EN 806 Table 6) water as well as the pattern of use.’
Minimum hot water Table 2.7 shows typical heat inputs.
Type of building storage (litres)
Table 2.7 Typical heat inputs
Hostel 90 per bed space
Hotel 200 per bed space Appliance Heat input (kW)
Office premises with canteen facilities 45 per employee Electric immersion heater 3
Office premises without canteen 40 per employee Gas fired circulator 3
facilities Small boiler with direct cylinder 6
Restaurant 7 per meal Medium boiler and indirect cylinder 10
Nursery/primary day school 15 per pupil Large domestic boiler with indirect cylinder 15
Secondary/technical day school 20 per pupil Directly fired gas hot water storage heater 10
Boarding school 90 per pupil
Children’s home/residential nursery 135 per bed space
KEY POINT
Nurses' accommodation 120 per bed space
Nursing/convalescent home 135 per bed space A brief overview of stratification
Stratification was covered in Book 1, but here is a
The calculation for determining the size of a cistern was reminder.
covered in Chapter 1, Cold water systems, planning and Stratification is where the hot water ‘floats’ on the
design. layer of colder water entering the storage vessel.
The hot water sits in temperature layers with the
Hot water storage vessels hottest water at the top of the storage cylinder,
gradually cooling towards the bottom.
The minimum storage requirements of a hot water
storage vessel are given as:
65 ºC
l 35 litres to 45 litres per occupant, unless the hot
SHC = 4.19
∆t = 61 °C
IMPROVE YOUR MATHS the time M (in minutes) taken to heat a specific
quantity of water through a specific temperature rise.
Calculation of heat input The formula is as follows:
A hot water storage cylinder has a capacity of
M = VT ÷ (14.3P)
140 litres. The cylinder is required to be at 60 °C
in two hours. The temperature of the incoming water
is 4 °C. What is the kW required? Where:
V = volume of water heated (l)
T = temperature of water (°C)
Calculating capacity based on recovery
P = rate of heat input into the water (kW)
time
The capacity of the hot water storage vessel depends The above formula ignores any heat loss from the
upon the rate of heat input to the stored water and the cylinder as this is likely to be negligible over a short
pattern of use. The calculation used for this considers period of time and the formula can be applied to any
160
hot water storage situation whether stratification One bath using 60 litres of hot water @ 60 °C + 40 litres
occurs or not. of cold water + 10 litres of hot water @ 60 °C for kitchen
use followed by a second bath fill 25 minutes later.
So, how does the formula work?
Totals are 70 litres of hot water @ 60 °C followed
The following examples, taken from BS 8558 Annex C,
25 minutes later by 100 litres for a second bath fill,
assume that a small domestic dwelling has one bath
which may be achieved by mixing hot water @ 60 °C
installed, and assumptions on pattern of usage have
with cold water @ 10 °C.
been made. The maximum requirements are as follows.
Heat input Small dwelling with one bath Large dwelling with two baths
to the water With stratification With mixing (indirect With stratification With mixing (indirect
(litres) type) (litres) (litres) type) (litres)
3 109 122 165 250
6 88 88 140 200
10 70 70 130 130
15 70 70 120 130
161
162
1m
20 m
8m
8m 8m 8m
Ma = kW = kg/s
SHC × ∆t (t f - t r) Looking at CIBSE guide C for copper tube (Figure 2.54),
it can be seen that the nearest mass flow rate to the
calculated figure is boxed in red.
163
∆p/l c 10 mm 12 mm 15 mm 22 mm 28 mm 35 mm 42 mm c ∆p/l
qm c qm c qm c qm c qm c qm c qm c
0.1 0.001 0.00 0.00 0.00 0.007 0.01 0.015 0.01 0.1
0.2 0.002 0.01 0.005 0.01 0.014 0.02 0.023 0.02 0.2
0.3 0.003 0.01 0.008 0.02 0.019 0.02 0.026 0.02 0.3
0.4 0.004 0.01 0.011 0.02 0.019 0.02 0.032 0.03 0.4
0.5 0.001 0.01 0.005 0.02 0.014 0.03 0.021 0.03 0.036 0.03 0.5
0.6 0.001 0.01 0.006 0.02 0.015 0.03 0.023 0.03 0.040 0.03 0.6
0.7 0.001 0.01 0.007 0.02 0.015 0.03 0.026 0.03 0.044 0.04 0.7
0.8 0.001 0.01 0.008 0.03 0.015 0.03 0.028 0.03 0.048 0.04 0.8
0.9 0.001 0.01 0.009 0.03 0.016 0.03 0.030 0.04 0.051 0.04 0.9
1.0 0.002 0.01 0.010 0.03 0.017 0.03 0.032 0.04 0.055 0.05 0.05 1.0
1.5 0.001 0.01 0.003 0.02 0.012 0.04 0.022 0.04 0.040 0.05 0.070 0.06 1.5
2.0 0.001 0.01 0.004 0.03 0.012 0.04 0.026 0.05 0.048 0.06 0.083 0.07 2.0
2.5 0.002 0.02 0.005 0.04 0.014 0.04 0.030 0.06 0.055 0.07 0.094 0.08 2.5
3.0 0.001 0.02 0.002 0.02 0.006 0.04 0.016 0.05 0.033 0.06 0.061 0.07 0.105 0.09 3.0
3.5 0.001 0.02 0.003 0.03 0.007 0.05 0.017 0.05 0.036 0.07 0.067 0.08 0.114 0.09 3.5
4.0 0.001 0.02 0.003 0.03 0.008 0.06 0.019 0.06 0.039 0.07 0.072 0.09 0.124 0.10 4.0
4.5 0.001 0.02 0.003 0.03 0.008 0.06 0.020 0.06 0.042 0.08 0.078 0.10 0.132 0.11 4.5
5.0 0.001 0.02 0.004 0.04 0.008 0.06 0.022 0.07 0.045 0.09 0.083 0.10 0.141 0.12 5.0
5.5 0.002 0.03 0.004 0.04 0.008 0.06 0.023 0.07 0.048 0.09 0.087 0.11 0.149 0.12 5.5
6.0 0.002 0.03 0.005 0.06 0.008 0.06 0.024 0.08 0.050 0.09 0.092 0.11 0.156 0.13 6.0
6.5 0.002 0.03 0.005 0.06 0.008 0.06 0.025 0.08 0.053 0.10 0.096 0.12 0.164 0.14 6.5
7.0 0.002 0.03 0.006 0.07 0.008 0.06 0.027 0.09 0.055 0.10 0.100 0.12 0.171 0.14 7.0
7.5 0.002 0.03 0.006 0.07 0.009 0.06 0.028 0.09 0.057 0.11 0.105 0.13 0.178 0.15 0.15 7.5
8.0 0.003 0.05 0.006 0.07 0.009 0.06 0.029 0.09 0.059 0.11 0.108 0.13 0.185 0.15 8.0
8.5 0.003 0.05 0.006 0.07 0.010 0.07 0.030 0.10 0.061 0.12 0.112 0.14 0.191 0.16 8.5
9.0 0.003 0.05 0.006 0.07 0.010 0.07 0.031 0.10 0.064 0.12 0.116 0.14 0.198 0.16 9.0
9.5 0.003 0.05 0.006 0.07 0.010 0.07 0.032 0.10 0.066 0.13 0.120 0.15 0.204 0.17 9.5
10.0 0.05 0.003 0.05 0.006 0.07 0.011 0.08 0.033 0.11 0.068 0.13 0.123 0.15 0.210 0.17 10.0
12.5 0.004 0.07 0.006 0.07 0.012 0.08 0.037 0.12 0.077 0.15 0.140 0.17 0.239 0.20 12.5
15.0 0.005 0.08 0.007 0.08 0.014 0.10 0.042 0.13 0.086 0.16 0.156 0.19 0.265 0.22 15.0
17.5 0.005 0.08 0.008 0.09 0.015 0.11 0.046 0.15 0.094 0.18 0.170 0.21 0.289 0.24 17.5
20.0 0.005 0.08 0.008 0.09 0.016 0.11 0.049 0.16 0.101 0.19 0.184 0.23 0.312 0.26 20.0
22.5 0.005 0.08 0.009 0.10 0.017 0.12 0.053 0.17 0.108 0.21 0.197 0.24 0.334 0.28 22.5
25.0 0.005 0.08 0.010 0.11 0.019 0.13 0.056 0.18 0.115 0.22 0.209 0.26 0.354 0.29 0.30 25.0
27.5 0.005 0.08 0.010 0.11 0.020 0.14 0.060 0.19 0.122 0.23 0.221 0.27 0.374 0.31 27.5
Figure 2.54 CIBSE guide C for copper tube (The Chartered Institution of Building Services Engineers (CIBSE), www.cibse.org)
This shows that a 15 mm copper pipe will deliver alternative. Look at the table again, you will see
0.010 kilograms per second (kg/s) at a velocity of that 12 mm pipe will also deliver 0.010 kg/s but the
0.07 litres per second (l/s) with a pressure loss of pascals per metre is 27.5 with a velocity of 0.11 litres
9.5 pascals per metre (Pa/m). In this case, the mass per second. This means that the pump power will have
flow rate matches perfectly. In most instances, the to be over twice the size than for 15 mm to deliver
nearest figure up would be chosen. However, there the same flow rate, so in this case 15 mm would be
may be instances where there is more than one chosen.
164
IMPROVE YOUR MATHS Pump duty is calculated in kilopascals, the pascal being
Attempt the calculation again, adding 10 m to all
the unit of pressure:
pipe lengths. The temperatures must be: 1 bar pressure = 10 m head = 100 kPa
t f = 60 °C Flow rate is calculated in litres per second. Shower
t r = 50 °C pumps can deliver between 11 and 25 litres per minute
Assume the following fittings: (l/m) or 0.41 litres per second (l/s), depending on the
type and their application.
l 10 elbows
165
H
Pump curve
Duty point
Head
HA.O
System curve
Duty point Q
The actual duty point is always at the point where the IMPROVE YOUR MATHS
pump H–Q and the system H–Q points intersect.
Calculation of pump power
IMPROVE YOUR MATHS Calculation of pump power is usually performed to
ascertain the power of the pump needed to lift a
Calculating pump duty certain quantity of water at a certain pressure. It is
A shower boosting pump is required to deliver based on the physics of work done relative to time.
15 litres per minute at a pressure of 2 bar to a Work done is the applied force through distance
shower head 3 m higher than the pump itself. moved and the unit of measurement is the joule. It is
Frictional losses in the system due to pipework, thus explained as the work done when a 1 newton
valves and fittings can be calculated as static force acts through 1 metre distance or:
head × 0.05. 1 joule = 1 N × 1 m
Static head from the pump to the shower head
The time must be expressed as a period of seconds,
= 3 m or 0.3 bar or 30 kPa
which can be combined with work done to become
Frictional losses = 30 × 0.05 = 1.5 kPa work done over a period of time. It is expressed in
the following way:
Design head = 2 bar or 200 kPa Power = work done ÷ time
Therefore, the pump duty is: = (force × distance) ÷ seconds
30 + 200 + 1.5 = 231.5 kPa
= (newtons × metres) ÷ seconds (J/s)
Now, a pump can be chosen from the manufacturer’s
where: 1 J/s = 1 watt
literature with a duty of 231.5 kPa that will deliver
15 l/m or 0.25 l/s flow rate. Force (newtons) = kg mass × acceleration due
to gravity (9.81m/s2 )
Power (watts) = mass × 9.81 × distance ÷ time
166
167
If the system volume is known, expansion vessels can Table 2.11 Expansion factors
be sized with the following formula:
Expansion factor ‘e’ Temperature (°C)
V = eC 0.0324 85
P
1- 1 0.0359 90
P2
0.0396 95
Where: 0.0434 100
V = the total volume of the expansion vessel
‘e’ can be found from the formula:
C = the total volume of water in the system in litres
d1 - d2
P1 = t he fill pressure in bars absolute (gauge e=
d2
pressure + 1 bar)
Where:
P2 = the setting of the pressure relief valve + 1 bar
d1 = density of water at filling temperature kg/m3
e = t he expansion factor that relates to the
maximum system requirements d2 = density of water at operating temperature kg/m3
Calculate the expansion vessel volume using: Therefore, the expansion vessel volume is:
V= eC V = 0.0170 × 300
P
1- 1 1 - 2.5
P2 7
= 5.1
Step 1: Calculate the expansion factor ‘e’ 1 - 0.357
The temperature of the fill water is 10 °C with a
density of 999.8 kg/m3. The maximum operating = 5.1
temperature is 60 °C with a density of 983 kg/m3. 0.643
Therefore the ‘e’ factor is: = 7.931 litres or 2.64% expansion
e = 999.8 - 983 = 0.0170 So, the expansion vessel volume is: 7.931 litres or
983 2.64% of total system volume.
168
169
Isolation valve
In-line strainer
Shower valve
Temperature
relief valve Washbasin
Expansion Bath
(pressure)
relief valve
Immersion Heating
Wiring centre heater circuit
and cylinder
thermostat
Sink
Filling loop
System boiler
Tundish
Discharge
pipework Immersion
heaters
Figure 2.57 Installation of a directly fired UHWSS with immersion heaters as the primary heat source
170
The floor on which the vessel is to be sited must be critical factors when fitting unvented hot water storage
substantial enough to accommodate the weight of the systems as these rely on a good flow rate and pressure
vessel and its water contents. to provide a satisfactory operation. It should be borne
in mind, however, that boosting pumps that deliver
The pipework must be fitted in accordance with BS
more than 12 litres per minute are not allowed under
EN 806 and BS 8558. Unvented hot water storage
the Water Supply (Water Fittings) Regulations when
systems (UHWSS) require at least a 22 mm cold water
the cold water supply is being taken directly from a
feed supplied by a water undertaker because of the
water undertaker’s mains supply.
high flow rate and pressure that the vessels operate
at. Water can be supplied through a boosting pump
and cold water accumulator if necessary (this will be The issue of poor mains
discussed later in the chapter). A 22 mm hot water supply
draw-off is required in all installations but this may be
Water supply pressures have consistently diminished
reduced for particular appliances such as washbasins,
over the last 30 years. As more and more homes,
sinks and bidets. Isolation valves should be fitted at all
factories, offices and shops are built, the loading on
appliances in line with good practice.
the UK water system has increased with little or no
upgrading of the water mains supply network. The
KEY POINT pipework that serves our towns and cities is now
It doesn’t actually state that isolation valves supplying more properties than ever before and that
are needed at every appliance in the Water
has resulted in a gradual degradation of both pressure
Regulations but it is considered good practice
to install them. The Water Regulations say that and flow rate. In some areas of the UK, the supply
every float operated valve must have a service pressure can be as little as 1 bar, which is unsatisfactory
valve fitted as near to the float operated valve as for an unvented hot water storage system.
possible. Other appliances aren’t mentioned.
Pressure of water takes two forms: static pressure and
dynamic pressure.
The order that the functional and safety components
are installed is of paramount importance if the system KEY TERMS
is to operate safely and efficiently and this can be
Static pressure: this is the water pressure when no
studied from Figure 2.56 for indirectly heated vessels
flow is occurring. This is always greater than the
and Figure 2.57 for directly heated vessels. dynamic pressure.
Unvented hot water storage systems require the Dynamic pressure: also known as ‘running
installation of discharge pipework to safely convey any pressure’, this is the water pressure when outlets
water that may be discharged as the result of a defect are open and water is flowing.
or malfunction. Discharge pipework will be discussed
later in this section. During periods of peak use, both static and dynamic
pressures will decrease. If, during this time, a property
The use of cold water has a static pressure of, say 2 bar, then the dynamic
pressure could drop to below 1 bar. At off-peak times,
accumulators in unvented say during the night, this could rise significantly to 3
hot water systems bar static and 2 bar dynamic simply because less water
The use of cold water accumulators is becoming is being used in the surrounding area. An accumulator
increasingly popular, especially in areas where the would take advantage of the night-time rise in
water pressure is exceptionally low. Accumulators pressures to replenish its storage capacity while the
and boosting pumps, as we saw in Chapter 1, offer a mains pressure is at its highest. With the accumulator
positive solution to the problem of low water pressure fully replenished, a good pressure and flow rate would
and poor low flow rate by storing water at night for be available throughout the day provided that the
use during the day. Both flow rate and pressure are accumulator has been sized correctly.
171
Figure 2.58 shows a typical unvented hot water storage is replenishing. The second PRV reduces the pressure to
system with an accumulator installed to increase both that of the UHWSS manufacturer’s recommendations.
the pressure and the flow rate. An important factor
Accumulators require a minimum incoming supply
here is the use of two pressure reducing valves. The
pressure to replenish successfully, usually around 2
first PRV regulates the pressure entering the property
bar. If the incoming supply cannot deliver this even at
so that any pressure fluctuations can be controlled to a
off peak periods, then a booster pump should also be
predetermined pressure at night when the accumulator
installed as shown in Figure 2.59.
Cold water accumulator
Pressure
reducing
valve
In-line
Pressure strainer
gauge
Isolation
In-line Double valve
strainer check valve
Non-return valve
Water undertaker’s Non-return valve Cold supply to outlets
stop valve
Pressure reducing valve
Pressure
reducing
valve
In-line
Pressure Non-return strainer
gauge valve Isolation
In-line Double valve
strainer check valve
Boosting pump
Non-return valve
172
The installation of hot water thermostat designed to switch off the power to the
unit when the maximum temperature is exceeded.
pipework – general It must be manually reset.
The materials used for hot water installations are l Immersion heaters with a non-resettable double
copper tubes to BS EN 1057 and polybutylene pipes thermostat – one thermostat can be set between
and fittings, as these are the only materials that 50 and 70 °C, the other is a high-limit thermostat
do not cause contamination of the water and can designed to permanently switch off the power to
withstand the temperatures associated with hot water the unit until the immersion heater is replaced and
distribution pipework. The pipework should be capable the fault rectified.
of withstanding at least 1½ times the normal operating l Open vented double feed indirect cylinders with
pressure of the system and sustained temperatures gravity or pumped primary circulation must be
of 95 °C with occasional temperature increases up to fitted with a minimum of a cylinder thermostat and
100 °C to allow for any malfunctions of any hot water a motorised zone valve which closes when the water
heating appliances that may occur. All systems must in the cylinder reaches a pre-set level.
be capable of accommodating thermal expansion and l Open vented cylinders with no high-limit
movement within the pipework. Care should be taken thermostat can be fitted with a temperature relief
when pressure testing open vented cylinders to ensure valve which opens automatically at a specified
that the maximum pressure that the cylinder can temperature to discharge water via a tundish and
withstand is not exceeded. If necessary, the cylinder discharge pipework safely to outside the property.
should be disconnected and the pipework capped
before testing commences. The insulation of hot water
The installation methods for hot water systems are pipework
very similar to those for cold water installations.
When installing new hot water installations in domestic
Care should be taken when installing hot and cold
properties, pipes should be wrapped with thermal
water pipework side-by-side so that any cold water
insulation that complies with the Domestic Heating
installation is not unduly warmed by the hot water
Compliance Guide. There are four main considerations:
pipework.
l Primary circulation pipes for heating and hot water
173
Wash basins Taps for use with wash basins should discharge at least 20 mm above the spillover level of the
appliance (AUK2 air gap). Mixer taps should be protected by the use of single check valves on
Fluid cat. 2 and 3 risk
the hot and cold supplies. Twin-flow mixer taps do not require any backflow protection as the
water mixes on exit of the tap.
Kitchen sinks No backflow protection is required as the height of the outlet is well above the spillover level
of the appliance. This is classified as an AUK3 air gap. If a mixer tap, where both hot and cold
Fluid cat. 5 risk
water mix in the tap body is installed then single check valves must fitted on both hot and cold
supplies. Twin-flow mixer taps do not require any backflow protection as the water mixes on exit
of the tap.
Baths As for wash basins except that the air gap should be 25 mm. Bath/shower mixer taps, where
the water is fed from the mains cold water supply and there is a risk of the shower head being
Fluid cat. 2, 3 and 5 risk
below the water level in the bath, should be protected by double check valves, or a shower hose
retaining ring which maintains an AUK2 air gap above the spillover level of the bath.
Bidets There are two types of bidet that are at risk from backflow. These are:
l The ascending spray type – special consideration must be made when fitting this type of
Fluid cat. 2, 3 and 5 risk
bidet (see Figure 1.100). These cannot be used with mains-fed hot and cold water systems.
Fluid cat 5 risk.
l The over rim with shower hose connection – with this installation, there is fluid cat. 5 risk as
well as a fluid cat. 2 risk.
Shower valves When both hot and cold supplies are fed from a cistern, no backflow protection is required.
However, when both are fed from mains-fed supplies then single check valves are required with a
Fluid cat. 2 and 3 risk
hose retaining ring to prevent the hose entering the water. If no retaining ring is fitted then both
hot and cold supplies should have a double check valve installed.
Electric shower units A double check valve is required where a hose retaining ring is not fitted.
Fluid cat. 2 and 3 risk
174
methods of testing and system commissioning. are happy that the installation is correct and meets
installations standards.
Information sources l Check that all open ends are capped off and all
to be avoided. There are four documents that must be are off. These can be turned on and tested when the
consulted: system is filled with water.
l Water Supply (Water Fittings) Regulations 1999 l Check that the D1 and D2 discharge pipework
l British Standard BS EN 806 (in conjunction with complies with the Building Regulations and that it
BS 8558) terminates in a safe but visible position.
175
open vented systems are less likely to occur as each Flushing procedures for
stage is filled slowly and methodically. Any problems
can be assessed and rectified as the filling progresses
hot water systems and
without the need to isolate the whole system and components
initiate a full drain down. Allowing cisterns to fill to Again, this subject was covered in detail in Chapter 1,
capacity and then opening any gate valves is the best but differs slightly because of the appliances and
way to avoid air locks. This ensures that the full pressure equipment installed on hot water systems.
of the water is available and the pipes are running at
Like cold water installations, the flushing of hot water
full bore. Trickle filling can encourage air locks to form
systems is a requirement of the British Standards. All
causing problems later during the fill stage.
systems, irrespective of their size, must be thoroughly
l Unvented systems – before an unvented hot water
flushed with clean water direct from the water
storage system is filled, the pressure at the expansion
undertaker’s main supply before being taken into
vessel (if fitted) should be checked with a Bourdon
service. This should be completed as soon as possible
pressure gauge to check the pre-charge pressure.
after the installation has been completed to remove
Unvented hot water storage systems should be filled
potential contaminants, such as flux residues, PTFE,
with all hot taps open. This is to ensure that pockets
excess jointing compounds and swarf. Simply filling a
of air at high pressure are not trapped within the
system and draining down again does not constitute a
storage vessel as this can cause the system to splutter
thorough flushing. In most cases, this will only move
water, even after the system has filled. Water should
any debris from one point in the system to another. In
be drawn from every hot water outlet to evacuate
practice, the system should be filled and the water run
any air pockets from the system. The taps can be
at every outlet until the water runs completely clear
closed when the water runs freely without spluttering.
and free of any discoloration. It is extremely important
The temperature and pressure relief valves should be
that any hot water storage vessels and cold water
opened briefly to ensure their correct operation and
storage cisterns should be drained down completely.
to test the discharge pipework arrangement.
l When the system has been filled with water, It is generally accepted that systems should not be
the system should be allowed to stabilise to full left charged with water once the flushing process
operating pressure. Any float operated valves should has been completed, especially if the system is not
be allowed to shut off. The system will then be going to be used immediately, as there is a very real
deemed to be at normal operating pressure. risk that the water within the system could become
stagnant. In practice, it is almost impossible to effect
Once the filling process is complete, another thorough
a complete drain down of a system, particularly large
visual inspection should take place to check for any
systems, where long horizontal pipe runs may hold
possible leakage. The system is then ready for pressure
water. This in itself is very detrimental as corrosion
testing.
can often set in and this can also cause problems with
176
water contamination. It is recommended, therefore, to ensure that any thermostatic mixing valves are
that to minimise the risk of corrosion and water quality operating at the correct temperature and that the
problems to leave systems completely full and flush hot water reaches the outlet within the 30-second
through at regular intervals of no less than twice limit. If a secondary return system is installed, then
weekly, by opening all terminal fittings until the system the circulating pump should be running when the
has been taken permanently into operation. If this is the tests are conducted and the temperature of the
case, then provision for frost protection must be made. return checked just before it re-enters the cylinder
to ensure that the temperature is no less than 10 °C
Taking flow rate and lower than the draw-off, 50 °C minimum.
pressure readings
Once the hot water system has been filled and flushed,
the heat source should be put into operation and the
system run to its operating temperature. Thermostats
and high-limit thermostats should be checked to ensure
that they are operating at their correct temperatures.
When the system has reached full operating
temperature and the thermostats have switched off,
the flow rates, pressures and water temperatures can
then be checked against the specification and the
manufacturer’s instructions. This can be completed in Figure 2.60 Checking hot water flow rates
several ways:
l Flow rates can be checked using a weir gauge.
177
Correct balancing is achieved by opening the valves drawing to the building. Poor installation techniques
on the longest circuits and then successively closing account for:
the lockshield valves a little at a time working towards l Noise – incorrectly clipped pipework can often be a
the cylinder until the flow rate through each circuit is source of frustration within systems running at high
equal. The flow rate should be balanced so that all of pressures because of the noise that it can generate.
the circuits achieve the same temperature at the same Incorrect clipping distances and, often, lack of clips
time. This is especially important with those systems and supports can put strain on the fittings and
that operate through a time clock. cause the pipework to reverberate throughout the
installation, even causing fitting failure and leakage.
Dealing with defects found To prevent these occurrences, the installation should
be checked as it progresses and any deficiencies
during commissioning brought to the attention of the installing engineer.
Commissioning is the part of the installation where the Upon completion, the system should be visually
system is filled and run for the first time. It is now that checked before flushing and commissioning begins.
we see if it works as designed. Occasionally, problems l Leakage – water causes a huge amount of damage
will be discovered when the system is fully up and to a building and can even compromise the building
running, such as systems that do not meet correct structure. Leakage from pipework if left undetected
installation requirements. This can take several forms: causes damp, mould growth and an unhealthy
l Systems that do not meet the design atmosphere. It is, therefore, important that leakage
specification – problems such as incorrect flow is detected and cured at a very early stage in the
rates and pressures are quite difficult to deal with. system’s life.
If the system has been calculated correctly and the It is almost impossible to ensure that every joint on
correct equipment has been specified and installed every system installed is leak free. Manufacturing
to the manufacturer’s instructions, then problems defects on fittings and equipment and damage
of this nature should not occur. However, if the pipe sometimes cause leaks. Leakage due to badly jointed
sizes are too small in any part of the system, then fittings and poor installation practice are much
flow rate and pressure problems will develop almost more common, especially on large systems where
immediately downstream of where the mistake has literally thousands of joints have to be made until
been made. In this instance, the drawings should be the system is complete. These can often be avoided
checked and confirmation with the design engineer by taking care when jointing tubes and fittings,
that the pipe sizes that have been used are correct using recognised jointing materials and compounds
before any action is taken. It may also be the case and using manufacturer’s recommended jointing
that too many fittings or incorrect valves have been techniques.
used causing pipework restrictions.
Another cause of flow rate and pressure deficiency
is the incorrect set-up of equipment such as
boosting pumps and accumulators. In this instance,
the manufacturer’s data should be consulted and
set-up procedures followed in the installation
instructions. It is here that mistakes are often made.
If problems still continue, then the manufacturer’s
technical support should be contacted for advice. In
a very few cases, the equipment specified is at fault
and will not meet the design specification. If this is
the case then the equipment must be replaced.
l Poor installation techniques – installation is the
Figure 2.62 A plumber’s nightmare! A badly designed plumbing
point where the design is transferred from the
system makes fault finding almost impossible
178
179
180
181
The routine checks and l there are no signs of leakage from the pump
l that the pump switches on and off at the
diagnostics performed on hot correct pressure
water system components as l that there are no unusual noises or vibrations
components:
l Thermostats – these can be checked using The methods of repairing
a thermometer in the hot water flow once faults in hot water system
the thermostat has shut off. This will indicate
whether the thermostat is operating at the components
correct temperature. Repairing system components should be undertaken
l Pumps – these should be checked using the using the manufacturer’s servicing and maintenance
manufacturer’s commissioning procedures to instructions, as these will contain the order in
ascertain whether the pump is performing as the which the component should be dismantled and
data dictates. A slight fall in performance is to be re-assembled. As with all components, there will be
expected with age. Check to ensure: occasions when it cannot be repaired and replacement
l there no signs of damage or wear and tear on is the only option. Some of the components that may
the pump be repaired and/or replaced are listed in Table 2.13.
182
Hot water running Usually a sign of thermostat and high Isolate the system from the electrical
constantly limit stat malfunction supply and allow to cool before
attempting a repair. Check and
replace the thermostat and high limit
stat as necessary
Thermostats Hot water too hot System thermostat is not operating at Check the temperature of the hot
the correct temperature water with a thermometer against the
setting on the thermostat. Replace the
thermostat as necessary
No hot water System thermostat not operating Check the thermostat with a GS38
electrical voltage indicator for correct
on/off functions. Replace as necessary
High-limit thermostat No hot water Usually an indication that the system Check the main system thermostat
thermostat has malfunctioned, and reset the high limit thermostat
and the high limit thermostat has
activated to isolate the heat source
Pressure (Bourdon) Sticking pressure Gauge not reading the correct No repair possible. Replace the gauge
gauges indicator needle pressure and does not move when
the pressure is raised or lowered
183
KEY POINT
When replacing or repairing valves and controls,
it is important to ensure that the water supply is
isolated and the section of pipework is completely
drained before beginning to repair or replace the
valve.
184
Table 2.15 Open vented hot water storage system fault finding
Safe isolation of hot water prevent accidental turn on whilst the system is drained
down. Where no such isolation exists, it may be of a
systems or components benefit to use a pipe freezing kit so that total system
during maintenance and isolation is not undertaken. If a component requires
removal and replacing, it is always a good idea to cap
repair off any open ends until the new component is installed.
Repair and maintenance tasks on hot water services,
Where the equipment also uses an electrical supply,
appliances and valves are essential to ensure the
safe isolation of the electricity supply is vital and
continuing correct operation of the system. The term
the safe isolation procedure should be followed and
used when isolating a water supply during maintenance
the fuse/supply locked off for safety (see Chapter 5,
operations is temporary decommissioning. There are
Electrical principles).
basically two types:
l planned preventative maintenance A record of all repairs and maintenance tasks
l unplanned/emergency maintenance. completed will need to be recorded on the maintenance
schedule at the time of completion, including their
When a maintenance task involves isolating the hot
location, the date when they were carried out and the
water supply, a notice will need to be placed at the
type of tests performed. This will ensure that a record
point of isolation stating ‘system off – do not turn on’
of past problems is kept for future reference.
to prevent accidental turn on of the system. Where key
components such as the expansion vessel, pressure relief Where appliance servicing is carried out, the
and temperature relief valves are found to be faulty, manufacturer’s installation and servicing instructions
then the system should be isolated and temporarily should be consulted. Any replacement parts may be
decommissioned until replacement parts are obtained obtained from the manufacturers.
and fitted. In most systems, it will be possible to isolate Do not forget to keep the householder/responsible
specific parts of the installation without the need to person informed of the areas that are going to be
have the whole supply turned off. It may be a good isolated during maintenance tasks and operations.
idea to remove any levers from the isolation valves to
185
thermostats
In this part of the chapter, we will investigate diagnostic
checks that we can perform on shower pumps,
expansion vessels and thermostats.
Table 2.16 Shower pump fault finding
186
Expansion vessels
Expansion vessels are checked at the Schrader valve
with a pressure gauge to ensure that the vessel
contains the correct pressure.
Note: If a faulty expansion vessel is diagnosed, the system should be isolated and temporarily decommissioned until a replacement vessel is
obtained and fitted.
187
p Figure 2.63 Fault-finding chart to assess excessive hot water in an indirectly heated hot water storage system
188
SUMMARY
As we have worked through this chapter, we have seen to determine flow rates, pipe sizes and quantity of hot
that hot water is a very complex subject. It becomes water required. This chapter gives you the knowledge
obvious that careful consideration must be given to the needed to install good, well thought out, well planned
requirements of the customer if the system that we fit hot water storage systems as well as an insight into the
is to meet their specific needs. The subsequent system complexities of good hot water system design.
choice is often the result of the calculations we make
189
Boiler
Heat exchanger
Expansion
chamber
To hot taps
Pump on
primary return To cold taps
Central heating Heat exchanger
pump
Heating flow
Heating return
190
7 Under Building Regulations Part G, what is a new 13 What material is used to make the secondary
or replacement immersion heater required to have? circulation pump that could be fitted to an
a Temperature relief valve unvented system?
b Non-resetting overheat thermostat a Brass
c Restricted thermostat to a maximum b Copper
temperature of 60 °C c Cast iron
d Protective coating to avoid electrolytic d Bronze
corrosion 14 What item could have failed if the pressure
8 What is the maximum distance between the relief valve is letting by in to the tundish?
outlet of a temperature relief valve and the a Expansion vessel
tundish forming part of the D1 pipework?
b Strainer
a 300 mm
c Pressure regulating valve
b 550 mm
d Cylinder stat
c 600 mm
15 Between what temperatures does Legionella
d 650 mm multiply?
9 Water at the outlet of a shower installed within a 15–25 °C
a school should be fitted with a TMV so that the
b 20–30 °C
water does not exceed what temperature?
c 20–45 °C
a 43 °C
d 30–45 °C
b 48 °C
16 The Water Regulations state that hot water
c 50 °C
should be distributed at a temperature of not
d 60 °C less than 55 °C and should reach the outlets at
10 Which Building Regulation Approved Document 50 °C within what time period?
relates to unvented hot water storage systems? a 30 seconds
a L1A b 15 seconds
b L2B c 45 seconds
c G3 d 60 seconds
d G2 17 At what temperature will the temperature and
11 At what temperature should a TMV that is pressure relief valve discharge water?
supplying a domestic bath be set? a 65 °C
a 44 °C b 85 °C
b 38 °C c 75 °C
c 48 °C d 95 °C
d 31 °C 18 What is a typical kW rating of an immersion
12 When installing a balanced cold supply with an heater in a hot water cylinder?
unvented hot water system, what is positioned a 1 kW
immediately after the pressure reducing valve? b 2 kW
a Single check valve c 3 kW
b Isolator d 4 kW
c Cold supply
d Strainer
191
19 The minimum storage requirement of a hot 25 If a hot water cylinder contains 150 litres of
water storage vessel allows how many litres of cold water before being heated, what is the
water per person? approximate volume of the expansion?
a 15–25 litres per person a 1.5 litres
b 25–35 litres per person b 15 litres
c 35–45 litres per person c 6 litres
d 45–55 litres per person d 8 litres
20 In what units is specific heat capacity 26 What is the requirement for the installation of a
measured? TMV if installing a wash hand basin in an infant
school?
a °C/litre
27 Describe what happens to Legionella bacteria
b kJ/kg/°C
when water is held at a temperature of 60 °C.
c kJ/litre
28 Name the functional controls of an unvented
d litre/kJ/kg hot water storage system.
21 At what temperature is water most dense? 29 Using the formula below, calculate the kW input
a 0 °C required to raise the temperature of a 300-litre
b 4 °C cylinder from 4 to 65 °C in 2 hours:
c 60 °C SHC × litres of water × temperature difference ( ∆t)
d 100 °C × boiler efficiency (93)
= kW
22 By how much, approximately, does water Time in seconds ×100
expand when heated in a hot water system? When:
a 10% SHC = 4.19
b 7.5% litres of water = 300 litres
c 4% ∆t = 61 °C
d 2% time in seconds = 7,200 seconds (2hrs)
23 If the coefficient of linear expansion of copper 30 A discharge pipe from a ¾" temperature relief
pipe is 0.000016 mm/m/°C, by how much valve is to be installed. The route from the
would a 5.0 m length of copper pipe expand by tundish will include 7.5 m of pipework and two
if heated from 10 °C to 60 °C? elbows. What size D1 and D2 pipework will be
a 4 mm required and why?
b 0.048 mm 31 Describe a centralised hot water system.
32 Outline the three tiers of safety and their
c 0.48 mm
temperatures that are required for an unvented
d 48 mm hot water cylinder.
24 If a customer had a problem with low pressure 33 When designing a hot water system, state what
at a shower, which of the following would NOT the Water Supply (Water Fittings) Regulations
improve the installation? state about the temperature of the hot water at
a Install an unvented hot water system with the outlet point.
balanced cold feed 34 A customer states that there is a continual drip
b Install a twin impellor pump through the tundish when the hot water system
c Install a larger open vented indirect cylinder gets up to temperature. Explain what the most
d Install an electric shower likely cause of this is.
Answers can be found online at
www.hoddereducation.co.uk/construction.
192
Central heating is a vast and complex subject. There in-depth learning of system types, components,
are now more options with regard to sources of heat, controls, and servicing requirements in systems up
pipe materials and heat emitters than ever before. to large domestic dwellings and/or systems of equal
Environmentally friendly technology and the re- size in commercial and industrial premises. We will
emergence of underfloor heating has meant that the investigate new and exciting technology that has the
customer can now afford to be selective about the potential to dramatically cut the cost of heating our
system they have installed into their property. The homes whilst, at the same time, reducing our carbon
advent of heat pumps and solar systems, with the emissions. We will also look at new controls and
savings on fuel and running costs, has dramatically components that can transform an existing wasteful
lowered the carbon footprint of domestic properties. installation into an energy efficient system.
No longer does the customer have to rely appliances
By the end of this chapter, you will have knowledge
that burn carbon rich fuels such as gas and oil. Zero
of the following six areas:
carbon and carbon neutral fuels have revolutionised
l types of central heating system and their layout
domestic heating whilst advances in technology have
requirements
lowered the cost of the energy saving appliances that
l design techniques for central heating systems
were once only available to a select few.
l positioning central heating system components
In this chapter, we will build on the knowledge of l installation, connection and testing requirements
central heating systems you learned in Book 1. of electrically operated central heating
components
This chapter provides learning in installation,
l commissioning central heating systems and
maintenance, application of design techniques
components
to include heat and ventilation loss through the
l diagnosing and rectifying faults in central heating
building fabric, diagnostics and rectification of
systems and components.
faults and commissioning procedures. It provides
193
The current Building Regulations came into force zone must be controlled by its own time clock/
in 2013 (with 2016 amendments) for England and programmer
Wales. Part L is currently being updated and should be ● living and sleeping areas (zones) must be controlled
re-issued in the coming months. This update should at different temperatures by means of a thermostat
include any amendments along with elements from ● every radiator should be fitted with a thermostatic
Boiler plus, CHeSS, Domestic Heating Compliance radiator valve, unless the radiator is being used as
Guide and The Building Services Compliance Guide. The the reference radiator for a thermostat situated
document is divided into four specific sections: elsewhere in the room.
● Part L1A Installations in new domestic dwellings
These requirements apply every time a home is built.
● Part L1B Installations in existing domestic dwellings
for Parts L1A and L1B (see Table 3.1 on page 195) Simple boiler servicing is exempt from this, but the
● the Non-Domestic Building Services Compliance
recommendation is made that radiator thermostats
Guide for Parts L2A and L2B. should be fitted when the system is drained down.
194
Table 3.1 Recommended minimum controls for new gas-fired wet central heating systems (BEAMA Domestic Building Services
Compliance Guide 2021, Table 3)
Table 3.2 Recommended minimum standards when replacing components of gas-fired wet central heating systems (BEAMA Domestic
Building Services Compliance Guide 2021, Table 4)
195
Table 3.2 Recommended minimum standards when replacing components of gas-fired wet central heating systems (BEAMA Domestic
Building Services Compliance Guide 2021, Table 4) (continued)
2. Boiler Emergency/ All boiler types except heating boilers that are combined with Upgrade gravity-fed systems
planned range cookers to fully pumped.
The ErP[2] seasonal efficiency of the boiler should be a Fit individual radiator
minimum of 92% and not significantly less than the efficiency controls such as thermostatic
of the appliance being replaced. radiator valves (TRVs) on all
In the exceptional circumstances defined in the Guide to the radiators except those in the
condensing boiler installation assessment procedure for dwellings reference room.
(ODPM, 2005), the boiler SEDBUK 2009 efficiency should not
be less than 78% if natural gas-fired, or not less than 80% if
LPG-fired. In these circumstances the additional requirements
for combination boilers would not apply.
Install a boiler interlock as defined for new systems.
Time and temperature control should be installed for the
heating system.
Combination boilers
In addition to the above, at least one of the following energy
efficiency measures should be installed. The measure(s) chosen
should be appropriate to the system in which it is installed:
● Flue gas heat recovery
● Weather compensation
● Load compensation
● Smart thermostat with automation and optimisation.
3. Radiator Emergency Fit a TRV to the replacement
radiator if in a room without
a room thermostat.
Planned Fit TRVs to all radiators
in rooms without a room
thermostat.
4. New Planned The new boiler and its controls should meet the standards in In dwellings with a total floor
heating section 2 of this table. area > 150 m2, install at
system – Fit individual radiator controls such as TRVs on all radiators least two heating circuits,
existing except those in the reference room. each with independent time
pipework and temperature control,
retained together with individual
radiator controls such as
TRVs on all radiators except
those in the reference rooms.
Always also follow manufacturers’ instructions.
[1] Best practice would be as for a new system.
[2] Refers to the efficiency methodology set out in Directive 2009/125/EC for energy performance related products.
196
which is designed to relieve the excess pressure by this means that slightly smaller heat emitters may
releasing the system water and discharging safely to a be used in some cases.
drain point outside of the dwelling. This is vital as the ● Greater range of heat emitters – the slightly higher
water may be in excess of 80 °C. A pressure gauge is operating temperature offers a greater range in
also included so that the pressure can be set when the heat emitters, including fan convectors and skirting
system is filled and periodically checked for rises and heating.
falls in the pressure as these could indicate a potential ● Quicker installation time – sealed systems are
component malfunction. The system is usually often easier to install and this results in quicker
pressurised to around 1 bar. There are several types: installation time.
● sealed systems with an external pressure vessel ● Quicker filling – sealed systems fill much more
● system boilers that contain all necessary safety quickly than vented systems because the filling water
controls is coming straight from the mains cold water supply.
● combination boilers. ● Fewer airlocks – filling the system from the mains
cold water supply eliminates the problems of airlocks.
All fully pumped systems, such as those with two or
● Sealed system components inside the boiler –
three 2-port zone valves (known as the S-plan and the
system boilers are supplied with all necessary
S-plan plus) or a 3-port mid-position valve (known as
sealed system components already installed as part
the Y-plan) or a 3-port diverter valve (known as the
of the boiler within the boiler casing. This simplifies
W-plan), can be installed as sealed systems or they can
the system installation.
be purpose designed ‘heating only’ systems using a
● Fewer components – if a system boiler is used,
combination boiler with instantaneous hot water supply.
the problems of siting and installing the expansion
It is important to remember that the safety controls vessel and its associated components are eliminated.
are installed to prevent explosions caused by high
pressure and also products of steam. Fully pumped systems with two or
three 2-port zone valves (known as
The advantages of sealed central heating
systems the S-plan and the S-plan plus)
There are several advantages to sealed heating systems. The S-plan has two 2-port motorised zone valves to
● Less pipework – because the need for a feed and
control the primary and heating circuits separately by the
expansion cistern is removed, less pipework is cylinder and room thermostats respectively. This system is
often used. recommended for dwellings with a floor area greater than
● Smaller pipework – sealed heating systems operate
150 m2 because it allows the installation of an additional
at a slightly higher temperature than vented 2-port zone valve to zone the upstairs heating circuit from
systems, which means that the heat delivery the downstairs circuit (the S-plan plus). A separate room
for the size of pipe is increased. This means that thermostat and, possibly, a second time clock/programmer
smaller pipework can often be used. would also be required for upstairs zoning.
● Higher heat emitter temperatures – because sealed A system bypass is required for overheat protection of
systems operate at a slightly higher temperature, the boiler.
KEY TERM
Overheat protection: when water cannot circulate required. A pump-overrun circuit, which is fitted
or the thermostats have been satisfied and the to most modern boilers, will ensure that the pump
motorised valves have closed, the boiler will continue continues to run when the boiler has shut down to
to heat up for a short period even though the dissipate any latent heat. If the motorised valves are
burner has shut down. This is because of the latent closed, the automatic bypass valve opens from the
heat (see Book 1) in the boiler casing. If the boiler pump pressure to allow water circulation, allowing
overheats, the high-limit thermostat will activate, the excess heat to dissipate, keeping the boiler
and the boiler will fail to operate when it is next temperature below high-limit shut-down.
197
Two-port
zone valve for
downstairs
circuit
Wiring centre
Programmer
Pressure gauge
Filling loop
Pressure relief valve
and discharge pipework
Thermostat
Pressure gauge
198
Fully pumped systems with 3-port The system contains a system bypass fitted with an
mid-position valve (known as the automatic bypass valve which simply connects the
flow pipe to the return pipe. The bypass is required
Y-plan) or a 3-port diverter valve
when all circuits are closed either by the motorised
(known as the W-plan) valve or the thermostatic radiator valves as the
The 3-port valve mid-position (Y-plan) or diverter valve rooms reach their desired temperature. The bypass
(W-plan) controls the flow of water to the primary valve opens automatically as the circuits close to
(cylinder) circuit and the heating circuit. The valve protect the boiler from overheating by allowing water
reacts to the demands of the cylinder thermostat or to circulate through the boiler keeping the boiler
the room thermostat. below its maximum high temperature. This prevents
the boiler from ‘locking out’ on the overheat energy
cut-out.
System boilers
A system boiler is an appliance where all necessary
safety and operational controls are included and fitted
directly to the boiler. There is no need for a separate
expansion vessel, pressure relief valve or filling loop
and this makes the installation much simpler.
The system boiler has all the components for a sealed system contained within the boiler unit. It is filled directly from the mains cold
water via a filling loop which is often fitted by the boiler manufacturer.
Expansion vessel
Pressure
gauge
199
Room thermostat
Time clock
Combination boiler
Expansion vessel
Filling
loop
Heating
flow
Heating
Hot return
water
supply
200
Zone
controller
Zone
controller
Outdoor
sensor
Zone
valves
Shunt
pumps
Primary circuit Secondary circuit
Expansion
vessel
Boiler Boiler Boiler
Pressurising unit
Water velocity is just part of the problem. Water that may collect in the header. Both of these features
temperature is also important. There are two potential are usually fitted as standard on most low loss headers.
problems here:
● If the difference in temperature between the flow How it works – the low loss header
and return is too great, it puts a huge strain on the Low loss headers act as an intermediary between the
boiler heat exchangers because of the expansion boiler and the heating and hot water circuits. They are
and contraction. This is known as thermal shock. designed to provide a hydraulic separation between the
● For a condensing boiler to go into condensing mode, boiler and the heating circuits. This helps to regulate
the return water temperature must be in the region the flow rate through the boiler at optimum velocity
of 55 °C. In some instances, temperature sensors are for the best efficiency of the appliance(s), ensuring
fitted to the low loss header to allow temperature greater performance of the heating system.
control over the primary circuit.
Controls for heating systems
KEY TERM No matter how good the central heating design or how
Thermal shock: the rapid cooling or heating of a accurate the calculations, the system requires proper
substance that can lead to failure of the material. control to be effective, efficient and economical to run.
The types of controls that are added to a system can
The low loss header is ideal for use with systems greatly improve its performance. Even older systems can
that have a variety of different heat emitters. It is benefit from the addition of modern and effective controls.
the perfect place for installing an automatic air valve In this part of the chapter, we will look at the various
for removing unwanted air from the system. Drain controls for central heating systems, their function and
points can also be fitted for removing any sediment how they ‘fit’ into modern systems.
201
Zone control of multiple spaces within a dwelling is Valves of 22 mm can be used on boilers up to around
achieved by the use of motorised valves activated 20 kW. 28 mm or larger should be used where the
and controlled by a time clock/programmer/room system is greater than 20 kW.
thermostat arrangement or a programmable room
thermostat that will do the same function. Advanced controls – weather
The most common types of motorised valves are 2-port compensation, optimum start and
zone valves and 3-port mid-position and diverter valves. delayed start
The method of use of these valves will depend on the Domestic central heating systems can benefit from more
pipework layout and installer/end user preference. advanced controls, which are often digital, especially
● 3-port valves provide separate hot water and when a condensing boiler is fitted. Condensing boilers
heating circuits. Zoning of the living spaces can be respond to lower flow and return temperatures better
achieved by the inclusion of additional 2-port valves than non-condensing appliances. Advanced controls
on the individual space circuits (such as upstairs and enhance system efficiency.
downstairs circuits). 3-port valves include a mid- ● Weather compensation – compensates for
position which allows shared flow. the external temperature. This control uses an
● 2-port motorised zone valves are probably the externally fitted temperature sensor fitted on a
most common of all zone arrangements used. They north or north-east facing wall so as not to be in
provide zoning of individual circuits and are used the direct path of solar radiation. As the external
where more than one zone is needed. A separate temperature rises, the weather compensator
zone valve is used for each zone. reduces the circulation temperature of the flow
from the boiler to compensate for the warmer
outside temperature. Similarly, the reverse occurs if
the weather gets colder.
● Delayed start – here, the end user sets the time to
202
External
temperature (°C) 5 6 7 8 9 10
20 Time (hours)
Typical settings
Warmer
16 Maximum heat up period, e.g. 6 a.m. to 8 a.m.
Normal occupancy period, e.g. 8 a.m. to 10 a.m.
203
204
b HC8: Best practice for systems using The application of system controls
a combination boiler or combined – time and temperature – to space
primary storage unit:
heating zones
i programmable room thermostat
The number of homes that require both time and
ii boiler interlock. temperature zone control has increased in recent
iii TRVs on all radiators, except in years. In 2006, a survey showed that the average floor
rooms with a room thermostat area of a domestic property with four bedrooms was
iv automatic bypass valve (see note 2) around 157 m2 and over 200 m2 for a five-bedroom
v more advanced controls, such as domestic property. With properties of this size, zoning
weather compensation, may be becomes a necessity and in 2006, Document L1A/B of
considered. the Building Regulations requested that zoning of the
Note 1 (from CHeSS): Boiler interlock is heating system must be installed in all properties of
not a physical device but an arrangement 150 m2 or more. This was updated in 2010 to include
of the system controls (room thermostats, any property.
programmable room thermostats, cylinder In most instances zoning requires the separating of
thermostats, programmers and time switches) the upstairs circuit from the downstairs or, in the
so as to ensure that the boiler does not fire case of single-storey dwellings, separating the living
when there is no demand for heat. In a system space from the rest of the property. Separate time
with a combi boiler this can be achieved by and temperature control of the individual circuits is a
fitting a room thermostat. In a system with a necessity.
regular boiler this can be achieved by correct
wiring interconnection of the room thermostat, Zoning with separate temperature
cylinder thermostat, and motorised valve(s). control
It may also be achieved by more advanced Separate temperature-controlled zones provide a
controls, such as a boiler energy manager. TRVs much better living environment because different
alone are not sufficient for boiler interlock. parts of the dwelling can be maintained at different
Note 2 (from CHeSS): An automatic bypass temperatures without relying on a single room to
valve controls water flow in accordance with dictate the temperature across the whole system.
the water pressure across it, and is used to Lower temperatures can be maintained in those
maintain a minimum flow rate through rooms within the dwelling that are not occupied,
the boiler and to limit circulation pressure allowing the dwelling to take full advantage of
when alternative water paths are closed. A any solar gains, especially in rooms that face
bypass circuit must be installed if the boiler south, south-east or south-west. This can be quite
manufacturer requires one, or specifies that a pronounced, even in the winter Sun. Significant
minimum flow rate has to be maintained while savings on both energy usage and fuel costs can be
the boiler is firing. The installed bypass circuit made by simply taking advantage of the free heat
must then include an automatic bypass valve that the Sun can provide. Outside sensors linked
(not a fixed position valve). to weather compensators and delayed start and
Care must be taken to set up the automatic optimum start controls further help to reduce energy
bypass valve correctly, in order to achieve the usage and cost.
minimum flow rate required (but not more)
when alternative water paths are closed. Zoning with separate time control
Source: Energy Saving Trust (2008) Central heating system Zoning with separate time control offers another
specifications (CHeSS) dimension to the concept of zoning by allowing the
heating to be controlled at different times of the day
205
in different zones. The heat can be focussed in those Zoning can help make significant energy savings. It
rooms that are occupied throughout the day with the allows the optimisation of the heating system whilst
heating to other parts of the dwelling timed to come maintaining the dwelling at a comfortable temperature
on in the early morning and evening. Separate zones and saving money at the same time.
reduce energy usage and costs whilst maintaining
improved comfort levels throughout the property. Underfloor heating systems
Zoning in practice Underfloor heating has been around for many years –
the Romans used a warm air system 1500 years ago
The choice of controls for the zones should be decided
to good effect. It is only fairly recently that its benefits
by the predicted activity in those zones. There
have been rediscovered. It is very suitable for use with
are many options that can be used individually or
the lower flow temperatures from new environmental
collectively to achieve a good system control:
technologies such as air and ground source heat
● Using individual temperature and timing controls in
pumps and solar heating, and so it has become not
every zone.
only a viable option for the domestic dwelling but
● Multi-channel programmers allow the timing of
one that will also save money, energy, reduce CO2
individual rooms or multiple zones to be set from a
emissions and, as a consequence, significantly reduce
single point. This is often more desirable than many
environmental impact.
individual programmers at different locations within
the dwelling. The design principles of underfloor
● Thermostatic radiator valves (TRVs) vary the
talking to the customer and finding out their ● 50–60 °C for timber floor constructions.
206
Underfloor heating
Such is the nature of underfloor heating that many
fuel types can be used, some utilising environmentally
friendly technology. Gas and oil fired boilers are
20 ºC common, but biomass fuels, solar panels and heat
pumps are also used.
Underfloor pipework
at 35–40 ºC VALUES AND BEHAVIOURS
More information regarding green energy heating
18–29 ºC
solutions can be found at: www.gov.uk/green-
deal-energy-saving-measures
207
Quite often, underfloor heating is used in conjunction valve to maintain a steady temperature required
with traditional wet radiators, especially on properties for the underfloor system. Zoning the upstairs and
such as barn conversions. The higher temperatures downstairs circuits with 2-port motorised zone valves
required for radiators do not present a problem because and independent time control for the heat emitters also
the flow water for the underfloor system is blended helps in this regard.
with the return water via a thermostatic blending
Theoretical Underfloor Radiator heating Warm air
ideal heating heating on inside wall heating
2.7 m
Eye level
1.7 m
16º 20º 24º 16º 20º 24º 16º 20º 24º 16º 20º 24º
4
5
3
2 6
1 7
Top view
Boiler
Underfloor heating circuits
Figure 3.14 Typical underfloor heating system combined with wet radiators
208
Advantages Disadvantages
● The pipework is hidden underfloor. This allows better ● Not very suitable for existing properties unless a full
positioning of furniture and interior design. renovation means the removal of floor surfaces.
● The heat is uniform giving a much better heat distribution than ● Can be expensive to install when compared to more
traditional systems. traditional systems.
● These systems are very energy efficient with low running costs. ● Heat up time is longer as the floor will need to get to
● Environmentally friendly fuels can be used. full temperature before releasing heat.
● Underfloor heating is almost silent with low noise levels when ● Slower cool-down temperatures mean the floors may
compared to other systems. still be warm when heat is not required.
● Cleaner operating with little dust carried on convector currents. ● Greater installation time.
This can help those people who suffer allergies, asthma and ● More electrical installation of controls is required,
other breathing problems. as each room will need its own room thermostat and
● System maintenance is low and decorating becomes easier as associated wiring.
there are no radiators to drain and remove.
● Individual and accurate room temperatures as every room has
its own room thermostat that senses air temperature.
● Lower possibility of leaks.
● Greater safety, as there are no hot surfaces that can burn the
elderly, infirm or the very young.
● Better zone control as each room is in effect a separate zone.
Hot water
cylinder
Ground source Two-way
heat pump manifold
Pump Pump
1
4
5
7
6
Figure 3.15 Typical underfloor heating system using a ground source heat pump
209
The working principles of underfloor Most manifolds contain a circulating pump and a
central heating system pipework and thermostatic mixing valve, often called a blending
valve. These will be discussed below.
components
As we have already seen, underfloor heating works by The thermostatic mixing (blending) valve
distributing heat in a series of pipes laid under the floor The thermostatic mixing or blending valve is designed
of a room. To do this, certain components are required to mix the flow and return water from the heat source
to distribute the flow of heat to ensure that the system to the required temperature for the underfloor heating
warms the room. However, the components must be circuits. They are available in many different formats,
controlled in such a way so as to maintain a steady flow the most common being as part of the circulating
of heat whilst ensuring that the floor does not become pump module as shown in Figure 3.17. The temperature
too hot to walk on. This is achieved by the use of: of the water is variable by the use of an adjustable
● manifolds
thermostatic cartridge inside the valve.
● a thermostatic blending valve
● a circulating pump
its coverings
● the application of system controls – time and
210
Manifolds
The longer the circuit, the more energy is needed
to push the water around it. Water will always take
the least line of resistance and shorter circuits will
always be served first. In many instances, balancing
the system will help even out the circulation times
so that all circuits receive the heat at the same time
but the system will only be as good as the slowest
circuit. If the longest circuit is slow, once the system is
balanced, then ALL circuits will be slow. In this regard,
the positioning of the manifold is of great importance.
By positioning the manifold centrally within the
dwelling, the length of each circuit is balanced so that
long circuits become shorter. Even if the short circuits
become longer, the time for the heating system to
reach full temperature will be shortened and balancing
the system will become much easier.
Figure 3.18 The series pattern
211
A potential problem that may occur where the manifold Pipework installation techniques
is located is that the area may become a potential Solid floor
‘hot spot’ on the system because of the pipework
There are many types of underfloor heating installation
congestion around the manifold. This can be prevented
techniques for a solid floor. The drawing above shows one
by insulating the pipework around the manifold until
of the more common types using a plastic grid where the
the pipework enters the room it is serving.
underfloor heating pipe is simply walked into the pre-
Pipework arrangements (cabling) made castellated grooves for a precise centre-to-centre
guide for the pipework using a minimum radius bend.
There are many variations to these two basic layouts.
The pattern should be set out in accordance with
the orientation and the shape of the room. Window
areas may be colder and may require the bulk of the
heat in that area. Other considerations include the
type of floor construction and the floor coverings.
The pipework should be laid in one continuous length
without joints. In some instances, the pipe is delivered
on a continuous drum of up to 100 m to enable large
areas to be covered without the need for joints. Large
rooms may require more than one zone and the
manufacturer’s instructions should be checked for
maximum floor coverage per zone.
Figure 3.21 The snail pattern laid out Conduit pipe 2 m/circuit
212
Wall
Floor panel
Insulation
Suspended timber floor Table 3.5 Key design and installation information for suspended
floor
This system is designed for use under timber suspended
floors. It uses aluminium double heat spreader plates to Maximum heat output Approx. 70 W/m2
transmit heat evenly across the finished floor surface. Recommended design 60 °C
flow temperature
This system is suitable for any timber suspended
Maximum circuit length 80 m (15 mm pipe)
floor with joist widths up to 450 mm. The heat plates
are simply fixed to the joists using small flat headed Maximum coverage per 17 m2 @ 225 mm centres
circuit using a double
nails or staples. A layer of insulation must be placed
spreader plate
below the plates to prevent the heat penetrating
Material requirements
downwards.
Pipe 4.5 m/m2 @ 100 mm centres
Where the pipework must cross the joists, the joists 2 plate/m2
Heat spreader plates
must be drilled in accordance with the Building
Regulations.
213
Wall
Insulation
Timber joists
Underfloor heating pipes
Wall
214
215
16 and 22 °C, dependent upon the type of activity designing any central heating system is that the
being carried out, age of occupants and the level customer requirements are satisfied. However,
and quality of clothing. Air temperature at feet legislation will also need to be taken into account as
level, not greater than 3 °C below that at head the system must comply with the requirements of
level. Room surface temperatures not above the air the regulations in force.
temperatures. Consultation with the customer is most important
● Air velocity – this is the speed at which the air
and the design needs to be approved with them
travels within the building. If it travels too fast then before work can begin.
● Building layout and features – the positions of key
a draught will be felt by the occupants; if there
is no movement, then the air changes will not be components and appliances are often dependent on
satisfied. Airflow past the body is horizontal and at the layout and the features of the property. Many
a velocity of between 0.2 and 0.25 m per second. A designers will look at the plans of the property
variable air velocity is preferable to a constant one. and assess the best methods of heating the space.
● Activity within the building – applies to the
Consultation with the building owner is important
type of work that is being carried out within the as they may have their own ideas of what they want
building. The more activity that is carried out by within a particular space or room.
216
● Energy efficiency – in many cases, the controls ● availability of the chosen fuel
whether a system is energy efficient or not. New ● legislation and regulation of the local area.
controls such as night setback, delayed start and ● Cost – the bigger and more complex the system,
weather compensation will assist in making the the more it will cost. To a large degree, regulations
most of good system design and this will help in dictate the type of system that is installed with
creating an energy efficient and economical system. regard to zoning and control, but other factors such
Again, zoning will help in this regard by limiting as heat emitter type, boiler type, size and location
the heat in areas which are not occupied whilst and system design, all play a significant role in the
maintaining a comfortable environment within the cost of materials and labour usage costs.
dwelling.
● Environmental impact – new technology KEY POINT
developed in recent years means that systems no Where a conflict exists between the customer
longer have to rely on carbon-rich fuels to maintain requests and the legislation, it must be explained
a warm living environment. Both carbon neutral to the customer that their wishes cannot be
fuels, such as biomass systems, and low and zero fulfilled as the system would not meet the
requirements of the regulations.
carbon options, such as air and ground source heat
pumps means that the opportunity to lower the
carbon fuel usage is available. Biomass is particularly
good when a communal heating system serving a
IMPROVE YOUR ENGLISH
A successful consultation process means you obtain
number of dwellings is being considered.
all the necessary information in order to design
● Occupancy and purpose of the building – heating a system that fulfils the individual’s needs. Clear
design must always consider what the building is to and structured communication is vital if the system
be used for, the number of occupants in the building is to perform to the necessary requirements of
and how often the building will be occupied. You the occupants. Remember to ask questions about
must consider: the structure of the building such as cavity wall
insulation. Assumptions made on the designer’s
● how many occupants there will be and whether
part could mean that the system does not live up
they will be sedentary or physically active – to expectations. Also, offer choices in boiler make
activity leads to heat gain and model, radiator design etc. Find out where you
● what heat gains can be expected from processes, can install pipework and where the customer does
machinery and electrical equipment within the not want pipework. These are all points that make a
building good design into a superb installation.
217
for significant savings, not only to the customer, other than dwellings.
but to the environment as a whole. You would consult these documents if you were designing
heating installations in commercial or industrial properties.
218
from the building using a tape measure or a laser Heat loss through the fabric of the
rule building
● taking the information from working drawings and The thermal transmittance of heat from a building to
plans using a scale rule. the outside is known as U-values. U-values express,
for the purposes of calculation, the rate of heat transfer
The type of data needed to successfully design heating
through the building structure (its walls, floors, ceilings,
systems:
roofs and windows) and because the construction of
● the length, width and height of the room
buildings varies so much due to different materials
● the number of external walls and their construction
and construction methods, the U-values vary too. This
● the number of internal walls and their construction
means that on occasion the U-value for a particular
● the construction of the floor
building will need to be calculated from scratch.
219
Heat flow
1
0.130 + 0.0125 + 0.050 + 0.100 + 0.050 + 0.102 + 0.040
0.25 0.038 0.11 0.18 0.77
= W/m2K
221
will gain more heat due to the length of exposure to Heat gain also occurs because of the warmth of the
the Sun’s solar radiation. In simple terms, the Sun rises air. This is known as sol-air temperature and occurs
in the east, swings out to the south during the day because the Sun has warmed the air surrounding
whilst gaining height until it reaches a peak height at the dwelling. The same principle occurs inside the
noon, before slowly setting in the west. This height to dwelling when heat is transferred from one room to
angle ratio is called an ‘azimuth’ and is crucial when another when the two rooms have different internal
calculating solar gain for air conditioning and cooling temperatures. If one room is at 21 °C and an adjoining
purposes. The solar effect even exists in the winter room is at 18 °C then heat will be gained by one and
when the angle of the Sun is much lower. On average, lost by the other. The rate at which this heat transfer
a south-facing wall in London will gain about 900 takes place and the amount of heat lost or gained will
watts of heat per square metre (m2) every hour during depend on the U-value of the wall.
the summer and around 300 watts in the winter. This
Dwellings also gain heat from other sources, such as
reduces for east and west-facing walls as they are not
electrical equipment and lighting, as these give off heat
exposed to the Sun for as long a period. A north-facing
when they are on. A 150 watt bulb, for instance will
wall gains very little solar radiation because it never
give off just that: 150 watts of heat. Human beings
feels the heat of the Sun.
also contribute to heat gains in a building. A human will
emit around 115 watts of sensible heat and around 50
INDUSTRY TIP watts of latent heat when at rest. This increases with
physical exercise.
The intensity of the Sun during the summer explains why
solar hot water heating works so well in the summer. Solar INDUSTRY TIP
hot water panels can give as much as 60 per cent of a
household’s yearly hot water needs, free of charge, just from Sensible and latent heat were discussed in Book 1, Chapter 3,
the heat of the Sun! Scientific principles.
222
The heating requirements of rooms to select a design room temperature that needs to be
in dwellings when designing a achieved when the central heating system is operating.
There are three aspects that must be considered to
central heating system
achieve a comfortable condition in a room:
Now that the U-values have been determined for the ● temperature
heat loss calculations, the information needed can be ● humidity
collated to allow the calculations to be performed. The ● ventilation rate.
information that is required is listed below:
● room size The temperature of the heated space during the
● temperature required – indoor to outdoor winter at which humans feel comfortable falls within
● air change rate. a temperature range of 19 and 23 °C when wearing
normal clothing. Some people may disagree when
The room size subjected to temperatures in the higher or lower
The size of the room may seem like an obvious piece of end of the acceptable range. The exact comfort
information but if the room is measured inaccurately temperature often results from the physical condition
then the calculations will also be inaccurate. It follows of the individual. Because of these varying temperature
that the bigger the room, the greater the heat loss. The ranges, exact room temperatures need to be discussed
heat emitter positioning also becomes troublesome as and agreed with the customer before any design work
the room size increases. In most cases it is better to commences.
consider the use of two or more strategically positioned Too much heat in a room can be controlled by
heat emitters in larger rooms rather than using just one thermostatic means but a shortfall in temperature
large one. This subject will be discussed later in this is rather more difficult to assess and may result in a
chapter. costly re-design of the heat losses. Design temperatures
Key information is required about each room before become even more critical if the customer is to be the
heat loss calculations can be performed, such as: permanent resident within the dwelling, as is the case
● the length, width and height of the room with domestic dwellings. If the customer is an architect
● the number of external and internal walls and their or a developer, temperatures may have been specified
construction as part of the design brief or specification.
● the number and type of internal walls and party Special considerations may be needed where the
walls customer is elderly or infirm. The table below illustrates
● the type of floor and ceiling the risk that the elderly and infirm face during the
● the type and size of the windows and doors. winter months.
The information required may be noted during a site Table 3.8 The effects of low temperatures on the elderly and
visit or it may be taken from working drawings and infirm
plans. Temperature (°C) Effects
24 Top end of the comfort condition
The room temperature and the outside
21 Recommended living condition
temperature
<20 Below 20 °C, the risk of death begins
Internal design temperatures
18 Recommended bedroom temperature
The design temperatures within dwellings are based Resistance to respiratory diseases is
upon the type and usage of the room. Internal design 16
weakened
temperatures should be chosen to ensure satisfactory More than two hours at this
comfort conditions. In order to achieve a comfortable 12 temperature, the risk from raised blood
living condition within the room and to enable the pressure, heart attack and strokes
heat loss calculations to be completed, it is necessary 5 Significant risk of hypothermia
223
Kitchen/breakfast room
Lounge/sitting room
Bedroom/en-suite
Bedroom/study
Dressing room
Games room
Dining room
Utility room
Living room
Cloak room
Storeroom
Bathroom
Bedroom
Landing
Kitchen
Study
Toilet
Hall
Design
21 21 21 18 21 21 18 18 18 18 21 21 18 18 21 21 18 22 21 16
temperature (°C)
The temperatures listed in the table represent normal during the coldest months. Research shows that the
living conditions and working conditions. For properties temperatures vary greatly in the UK with the south-
that are designed for the elderly or the infirm, these eastern corner being the mildest throughout the year
temperatures should be increased by one or two and the north of Scotland being the coldest.
degrees for each given application and usage. It will
also be seen that the temperatures vary depending on INDUSTRY TIP
the intended use of the room. This is simply because
the body temperature of an individual and their For further information on climatic conditions in the UK,
subsequent comfort levels will vary depending on their reference should be made to CIBSE guides A and J, and
activity (such as resting, sleeping, bathing, etc.). Hence local meteorological data.
the wide range of temperatures quoted.
Some building services engineers design heating The UK often sees temperatures between −2 and −6 °C
systems for residential buildings with a constant during the winter and, on occasions, it has been known
temperature throughout, irrespective of the room type to drop as low as −15 °C or lower. However, it would
or usage. This single temperature approach reduces be uneconomical to design a central heating system
the amount of calculations required, as it uses the using −15 °C as it occurs so infrequently. The resultant
‘whole house’ assessment method but this can lead to over-sizing would encourage the boiler to ‘hunt’ on its
over-sizing of the heating system and an unnecessary thermostat and increase the risk of boiler breakdown.
increase in overall energy usage. Therefore, a more logical external design temperature
should be used based upon the lowest average
External design temperatures temperature for the location. Another possibility for
The successful design of any central heating system determining the external design temperature is to use
is based on the fact that the dwelling is maintained the lowest two-day mean temperature, which has been
at a certain specified temperature based upon the registered ten times over a twenty-year period.
prevailing (at the time) external temperature. It follows Table 3.10 shows the recommended base temperatures
that calculations must be based on a realistic external for the UK but local knowledge can also be applied, as
temperature that can be expected for the region severe exposure conditions are not always obvious.
224
Air change rates Air enters the building because of the poor seal in the
It is necessary to prevent the air in the room from building structure, usually through airbricks, ventilators,
becoming stale and to prevent the onset of moisture flues and chimneys. Flues and chimneys often cause
problems and mould growth. As the air change occurs, excessive air change because warm air escapes through
the heat in the room is lost by warm air leaving the the flue, due to the fact it is less dense. As cold air
room and cold air entering. enters, it forces out more warm air. This effect is known
as the stack effect.
Stack
effect
Wind pressure
NEGATIVE POSITIVE
(−) PRESSURE ZONE (+) PRESSURE ZONE
225
Lounge/sitting room
Kitchen/breakfast
Bedroom/en-suite
Bedroom/study
Dressing room
Games room
Dining room
Utility room
Living room
Cloak room
Storeroom
Bathroom
Bedroom
Landing
Kitchen
Study
Toilet
room
Hall
Air change
1.5 1.5 1.5 2.0 2.0 2.0 2.0 2.0 2.0 1.5 1.5 1.5 1.0 2.0 1.5 1.5 2.0 2.0 1.5 1.0
rate
The air change rates listed below are for modern Each room needs to be dealt with separately. We
buildings. When calculating heat losses for older will look at a simple example which should help in
dwellings, there is a case for increasing the rates to understanding how the heat losses are put together.
allow for ill-fitting doors and windows because these
The simple room shown in Figure 3.28 has four outside
will affect the heat loss from the building.
walls and heat loss through both the floor and roof.
The exact amount of air infiltration is difficult to assess Intermediate rooms in a large building may not have
and because of this, exact design temperatures are often these losses unless there is a temperature difference
difficult to predict. The air changes listed in Table 3.11 between the rooms.
are arrived at by methods that are verifiable or by
Window 2.0 m × 1.5 m
demonstrable means and can be considered accurate for
new and well-maintained buildings.
226
is quite straightforward. So, the calculations revolve 3 Calculate the glazing heat losses.
around the following elements: 4 Calculate the floor and roof heat loss.
1 Calculate the air change heat loss. 5 Calculate any adjustments due to exposure and
2 Calculate the external wall heat loss. intermittent heating loads.
This can be a little involved. If we laid all of the external Floor: 15 × 24 × 0.25 = 90 watts
walls flat, we would end up with the following: Ceiling/roof: 15 × 24 × 0.25 = 90 watts
5 + 5 + 3 + 3 = 16 m So, the total heat loss for the room is the sum of all of
This figure must now be multiplied by the height of the the calculated elements:
wall: 594 + 294 + 208.8 + 139.2 + 90 + 90 = 1416 watts
16 × 2.5 = 40 m2 Point 5, the last stage, is the calculation of any
But this figure is not much use to us as it is. There are adjustments.
windows and doors that have a greater heat loss than Point 5 – calculating adjustments
the wall so these MUST be deducted BEFORE we
calculate the external wall heat loss. The window and We are assuming that the room is in an exposed location.
door heat loss will be dealt with separately. So first This would mean an increase in the total of 10 per cent
calculate the area of the windows and doors: in case of severe weather. Furthermore, we are also
assuming that the heating will be on intermittently. In
Window: 2 m × 1.5 m = 3
other words, it will only be on at certain times of the
Door: 2 m × 1 m = 2 day or when external controls call for heat such as a
= 5 m2 frost stat. This will result in an extra 15 per cent increase
in the total to cope with the intermittent heating patterns:
This figure can now be deducted from the external
wall total: Exposed location @ 10% = 1416 × 0.10 = 141.6 watts
40 – 5 = 35 m2 Intermittent heating load @ 15% = 1416 × 0.15
So, the heat loss from the external walls is: = 212.4 watts
35 × 24 × 0.35 = 294 watts = 1416 + 141.6 + 212.4 = 1770 watts
Progress to Point 3. Therefore, the heat loss from the room when all
adjustments have been made is 1770 watts.
Point 3 – glazing heat loss The calculation is probably more understandable when
This part of the calculation is made easy by the fact viewed in a table format. Take a look at Table 3.12. It
that we have already calculated the areas of the must be realised, however, that because all of the walls
glazing, so it’s a straightforward calculation. Also, were external and the structure was a single-storey,
the same U-value is used for both window and door there is no data for internal wall structures or where
because they are made from the same material. This there is another room above. This will be dealt with next.
➜
227
228
Room 1 Room 2
Now using the formula previously shown, we can
enter the details on the table and calculate the
4.0 m
external wall heat loss (see Table 3.14). We can also
4.0 m
calculate the heat loss for the glazing.
Look at the internal wall dimensions. The wall is 3.5 m
in length including the door opening and 3 m high.
Window 1.75 m × 1.5 m Some designers will work out the heat loss for the
door, but for this chapter it will be treated as part of
Figure 3.29 Plan of Rooms 1 and 2 the wall for simplification. The most important factor
Table 3.13 Room data for Rooms 1 and 2 here is that the room temperatures are different. The
adjoining room requires a warmer temperature at
Element Room 1 Room 2 21 °C. This means that Room 1, at 18 °C, will GAIN
Temperature 18 °C 21 °C heat from the Room 2 next door and so any heat gain
must be DEDUCTED from our calculation and NOT
Outside temperature −3 °C −3 °C
added. The temperature difference between Room 1
Temperature difference 21 °C 24 °C and Room 2 is 3 °C. Take a look at Table 3.14.
Number of exterior walls 4 3 When the calculation for the internal walls is
Number of interior walls 1 1 conducted, it will be seen that there is a gain of
U-value of exterior walls 0.35 0.35 54.18 watts. This is highlighted in red to remind us to
deduct it and not add it. If the temperatures were the
U-value of interior walls 1.72 1.72
same, then the internal wall would be ignored purely
U-value of the glazing 2.9 2.9 because there is neither a heat loss nor a heat gain.
U-value of the floor 0.25 0.25 The rest of the table can now be completed.
U-value of the roof/ceiling 0.16 0.16 Now look at Room 2. The heat gain that was seen in
Number of air changes 1 2 Room 1 now becomes a heat loss in Room 2 because
Room 1 is a cooler 18 °C and so this must be allowed
The rooms are of normal exposure. for in the heat loss calculations. All other factors
The heating is intermittent. remain the same and so the heat loss for the room
We will deal with Room 1 first. The first thing to note can be calculated in the normal way.
is that the data states that there are four outside walls
229
230
➜
18/04/22 10:39 PM
9781398361621.indb 231
Table 3.15 Heat loss calculation table for Figure 3.29, Room 2
➜
231
18/04/22 10:39 PM
The City & Guilds Textbook: Plumbing Book 2
From the table, it can be seen that the heat gain from These two examples show only heat loss. They do not
Room 1 is exactly the same as the heat loss in Room 2. tell us the size of heat emitter each room requires. The
The total heat loss for the room is greater simply totals here require further work to convert them into
because the air change rate was doubled in Room 2 heat emitter emissions and these will be discussed
and the temperature difference between the internal later in the chapter.
temperature and external temperature was higher.
1.3 m
7.8 m
Lounge
21 ºC
Bedroom 1 Bedroom 3
18 ºC 18 ºC 3.5 m
Doors
h 2.3 m
Window Window Window
2.2 m × 1.2 m 2.0 m × 1.2 m 1.5 m × 1.2 m
232
The methods of sizing the central The different models available allow the calculation
heating pipework and central of single dwelling heat losses, conservatory heat
losses and the heat loss from industrial heating
heating circulating pumps
systems.
There are three very different methods for sizing the
pipework and circulators for central heating systems
KEY POINT
and each one has its advantages and disadvantages:
The index circuit of a central heating system is
● Longhand calculations – this is by far the most
the circuit which has the biggest resistance to
accurate of all heating design methods, as U-values flow and NOT the circuit with the biggest heat
can be calculated to suit the building structure load. The index circuit is always taken as the
where the installation is to take place. This ensures circuit with the longest run of pipework because
that an economical and environmentally friendly the circulating pump will have to overcome the
design of the building heating system can be resistance due to length of pipe.
guaranteed. Longhand calculations involve the use
of external data such as the tables for flow rate
and resistance published by the Chartered Institute
of Building Services Engineers (CIBSE) in the CIBSE
design guide C.
Circulating pump size is fairly simple to calculate
as most of the work is done during the pipe sizing
calculation. It should be remembered that the size
of the circulator will be based around the resistance
in the index circuit. This will be discussed later in
this chapter.
● Computer aided central heating design
234
The selection criteria for central if the pipe is insulated and the water is at 75 °C.
heating boilers An uninsulated pipe distributes the heat loss into
its surrounding and, as such, will help to warm
The selection of central heating boilers is often based
the dwelling. However, the heat loss contributes
on experience, efficiency and cost. Many installers will
to the water losing heat, so by the time it reaches
install what they are familiar with simply because of
the heat emitter, it has already cooled from when
the cost and the ease of installation. However, boiler
it had left the boiler. In most cases, the heat loss
selection should be based upon the suitability of the
from the pipes is acceptable as insulating all of the
boiler in relation to the system on which it is installed.
heating pipes could lead to the boiler overheating
The points that should be considered are:
and the undesirable operation of the high limit
● Space heating load – will the boiler satisfy the
thermostat on the boiler due to an insufficient
space heating load? Or, put more simply, will it
temperature difference between the flow and
warm the dwelling to the design temperatures? It is
return heating pipes as they leave and return from
uneconomical to oversize a boiler. It may well heat
and to the boiler. As a rough guide, a 5 to 10 per
the system but the water content may be higher,
cent allowance can be made on the boiler size for
which will require more heat, therefore more fuel
uninsulated pipes.
and in consequence will cost more to run and give
● Factors for intermittent heating – central heating
off more CO2 emissions than would otherwise be
systems for domestic dwellings are normally
necessary. Similarly, if the boiler is undersized, then
operated on time clocks and programmers that
the boiler will struggle to meet the demands of the
allow for the system to run at specific times of the
system. This will mean that the boiler is working
day. When the heating system is off, the rooms will
far too hard and could fail to reach the desired
lose heat very quickly creating a noticeable drop in
temperature as quickly as it should. Boiler cycling
temperature. Because of this, an increase of around
would increase and fuel usage would be high.
15 per cent on the total heating load is advisable
● Hot water heating load – will the boiler satisfy
to counter the effects of intermittent heating. This
the hot water demand? Combination boilers are
would amount to a slight increase in heat emitter
not always the best choice, especially where hot
size across all rooms ensuring a quick heat up of
water demand is considered. They may well satisfy
the room to bring the rooms back to the desired
the heating requirements but will they deliver
temperature in cold weather.
the amount of hot water required at the desired
flow rate and temperature? The ‘one boiler fits all’
approach is the wrong approach to take, especially VALUES AND BEHAVIOURS
where multiple hot water outlets are to be supplied
All too often, the customer is not told of the
or long distances exist between the appliance and
disadvantages with combination boilers. It’s good
the hot water outlets.
practice for you to ensure they are well informed
When storage of hot water is considered, then the
on the positive and negatives of all systems
kW required to heat it must firstly be calculated
available to them.
properly and then added to the total space heating
load, otherwise the boiler will fail to meet the total
heat demand, especially where a hot water priority
system is installed, such as the Honeywell W-plan Sizing expansion vessels for sealed
system. heating systems and feed and
● Heat loss from pipework – uninsulated heating expansion cisterns for open vented
pipes will lose heat. The amount of heat loss will systems
depend on the material that the pipe is made from Water, when it is heated, expands. The amount of
and the temperature of the water. On average, expansion will depend on the temperature of the
a copper 15 mm pipe will lose around 40 watts water. At atmospheric pressure, water is at its greatest
per metre (W/m) when uninsulated and 8 watts density at 4 °C. At this temperature, 1 m3 of water has
235
a mass of 1000 kg. From this point forwards as the in an open vented system, the feed and expansion
water temperature increases, 1 m3 will lose density. cistern accommodates the expansion of water. Both of
At 100 °C, 1 m3 of water has a mass of 958 kg or an these vital parts of the installation will need to sized
expansion rate of 4 per cent. The densities of water correctly.
at various temperatures and pressures are shown in
Table 3.17. Sizing an expansion vessel
Table 3.17 The densities of water at various temperatures and There are several methods for sizing expansion vessels.
pressures All methods must take into account the volume of cold
water in the system and the amount by which it will
Temperature (°C) Density (kg/m3) Specific volume
10 −3 (m3 /kg) expand in order to reach its design temperature. The
CIBSE method is shown below.
0 (ice) 916.8
0.01 999.8 1.00 If the system volume is known, expansion vessels can
4 (maximum density) 1000.0 be sized with the following formula:
5 999.9 1.00 eC
V=
10 999.8 1.00
P
1- 1
15 999.2 1.00 P2
20 998.3 1.00 V = the total volume of the expansion vessel
25 997.1 1.00
C = the total volume of water in the system in litres
30 995.7 1.00
35 994.1 1.01 P1 = t he fill pressure in bars absolute
(gauge pressure + 1 bar)
40 992.3 1.01
45 990.2 1.01 P2 = the setting of the pressure relief valve + 1 bar
50 988 1.01
e = t he expansion factor that relates to the
55 986 1.01 maximum system requirements
60 983 1.02
65 980 1.02 Expansion factor ‘e’ Temperature (°C)
70 978 1.02 0.0324 85
75 975 1.03 0.0359 90
80 972 1.03 0.0396 95
85 968 1.03 0.0434 100
90 965 1.04
95 962 1.04 ‘e’ can be found from the formula:
d1 – d2
100 958 1.04 e=
d2
The expansion of the water in a central heating system, Where:
if not accommodated, will lead to an increase in system d1 = density of water at filling temperature (kg/m3)
pressure and possibly component or appliance failure
d2 = density of water at operating temperature
as a result. In a sealed heating system, the expansion
(kg/m3)
of water is accommodated in an expansion vessel;
236
Calculate the expansion vessel volume using: Therefore, the expansion vessel volume is:
V = eC V = 0.0286 × 600
P
1- 1 1 - 2.5
P2 7
= 17.16
Step 1: calculate the expansion factor ‘e’ 1 - 0.357
237
Bottom, bottom, opposite end Top, bottom, opposite end Top, bottom, same end
(BBOE) (TBOE) (TBSE)
238
Lounge: L 6 m × W 5 m Bathroom: L 4 m × W 3 m
Kitchen 21 ºC 22 ºC
2 air changes 2 air changes
Window: H 1.5 m × W 2 m Window: H 1.5 m × W 1.7 m
Bedroom 1 Bathroom Heat loss: 2400 watts Heat loss: 1300 watts
Bed 2: L 6 m × W 4 m Cloaks: L 2 m × W 2 m
18 ºC 18 ºC
1 air change 1 air change
Window: H 1.5 m × W 2 m Heat loss: 460 watts
Heat loss: 1700 watts
Lounge Bedroom 2
Kitchen: L 3 m × W 3 m
18 ºC
2 air changes
Door: H 2.2 m × W 1.2 m
Heat loss: 860 watts
Cloaks
The heat losses from the dwelling are as follows: Therefore, a radiator with an output of 2727 watts is
● Lounge: 2400 watts required and NOT 2400. If a radiator of 2400 watts
was chosen, with a ∆t of 50 °C, the radiator would
● Bedroom 1: 1400 watts
only give out the following:
● Bedroom 2: 1700 watts
2400 × 0.798 × 0.98 = 2112 watts
● Kitchen: 860 watts
● Bathroom: 1300 watts What this means is that even though the
● Cloaks: 460 watts manufacturer’s data states that the output of the
radiator is 2400 watts, this is with water with a ∆t of
● Hall: 960 watts.
75 °C and NOT 50 °C as is required so the radiator
The lounge at 21 °C has a heat loss of 2400 watts, would be only 88 per cent of the required size.
so, if the factors are applied:
The final heat emitter sizes can now be calculated.
2400 ÷ 0.898 ÷ 0.98 = 2727 watts
Table 3.19 Heat emitter final sizes
Where:
IMPROVE YOUR MATHS
SHC = specific heat capacity of water. This is taken
You should have, by now, calculated the heat loss
as being 4.19 kJ/kg/°C
for the single-storey building previously shown.
Calculate the heat emitter/radiator sizes for the Litres of water = the storage of water in the hot
building from the heat losses previously calculated. water storage vessel
240
Calculating total boiler size This can be rounded up to 21 kW. A suitable boiler can
In previous sections, the totals for both heat emitter now be sourced from the various manufacturers’ literature.
output and hot water input were calculated. Now,
these must be added together to find out what the
Calculating central heating pipe sizes
boiler size will be: Pipe sizing central heating systems is not calculated on
● Radiator output: 10828 watts or 10.828 kW the amount of heat required by any one room in kW. It is
● Hot water input: 7.14 kW calculated on the amount of water containing heat that
will flow down a pipe in kilograms per second or kg/s.
When these are added together a total of 17.968 kW
is obtained. However, this does not consider the fact As the heated water moves along the pipe, it will
that there will be heat loss from the pipework. If all of encounter frictional resistance. In other words, the
the pipework is to be surface mounted in the rooms movement of water will be slowed by the size of the
on walls and skirting boards, then no allowance need pipe, the smoothness of the internal surface of the pipe,
be made because the heat loss will contribute directly the number of changes of direction and restrictions,
to the heating of the room but, typically, much of the such as radiator valves and other fittings. To counteract
pipework will be under floors and in roof spaces. In the resistance to flow, a central heating circulating
this instance it is usual to allow around 10 per cent to pump is used to force the water around the system. In
15 per cent extra to take into account heat loss from any system, the resistance will always be greater at the
pipework and further extensions to the system. The beginning of the circuit than at the end because the
extra percentage of heat allowance will also ensure a resistance, measured in pascals, diminishes with length.
quick water heat up but caution must be exercised if The greatest resistance to flow will be in the longest
boiler oversizing is to be avoided. circuit. If the pump used will overcome the resistance
in the longest circuit, it will always circulate around any
So, taking the 17.968 kW and adding 15 per cent will
other circuit, simply because the resistance is less. For
give:
this reason, pump sizing is always calculated from the
17.968 × 0.15 = 2.7 longest circuit. This is known as the index circuit. This
17.968 + 2.7 = 20.668 will be discussed in the next section.
241
Other circuits
B A
Cyl. A to Cyl. 1.5 m 3m
B to C 1.5 m 3m
Hall 10.0 m C to C1 7m 14 m
H1 C to D 1.5 m 3m
E F D to D1 5m 10 m
D to D2 8m 16 m
Lounge 2 H2
E to F 2m 4m
Bedroom F2 F to F1 6m 12 m
F to F2 7m 14 m
2
G
H G to H 1.5 m 3m
H to H1 5m 10 m
H to H2 7m 14 m
Lounge 1 Boiler
F1
G1
Cloaks
8.0 m
➜
242
● Column 7: the actual length of pipe from the If you look at Table 3.22, you will see that these
drawing. figures have been added.
● Column 8: this is the allowance made for fittings As was discussed earlier, the heat required is converted
and changes of direction, usually around 33 per from kilowatts to kg/s. The method is as follows:
cent of the actual pipe length.
Flow rate = kW = kg/s
● Column 9: the presumed length of pipe once the
SHC × ∆t
resistance from column 8 has been added. This
will be used to calculate the total resistance to flow Where:
so that the pump can be sized correctly. kW = total heat carried by the pipe
● Column 10: the velocity of the water through the
pipe. This should not be greater than 1.5 metres SHC = specific heat capacity of water taken as 4.19
per second (m/s) or the system may be noisy. A kJ/kg °C
typical velocity of between 0.5 and 1 m/s should
∆t = flow and return temperature difference
be adequate.
● Column 11: this is the resistance per metre of the The boiler is to be a condensing boiler with a 20 °C
size of pipe chosen and will be used to calculate temperature difference across the flow and return.
the pump size. Therefore, the calculation looks like this:
● Column 12: the total of the pascals per section is 19.765 = 0.235 kg/s
Flow rate =
calculated by multiplying columns 9 and 11. This is 4.19 × 20
used for pump sizing.
Now, we must look at the CIBSE copper pipe sizing
The pipe sizing procedure tables for water at 75 °C.
Because the pump size is calculated from the index As you can see, the CIBSE tables are divided into
circuit, this is what we will be concentrating on. The columns. To the far left and the far right are columns
index circuit is the longest circuit and follows the with the heading ∆p/l. This is the resistance and is
sections of pipework shown in Table 3.21. measured in pascals, the unit of pressure. This is a vital
piece of data as we cannot calculate the pump size
Table 3.21 The index circuit (see Figure 3.34) without it and so must be entered on our Table 3.22
Section Heat required (kW) in column 11. Across the top of the tables are the
various pipe sizes. Below each pipe size are two
Boiler to A 17.968
columns. The left column is marked qm and is the
A to B 10.828 flow rate that we have calculated. The flow rates
B to E 6.436 calculated and the flow rate on the table may not be
E to G 3.868 identical. In this instance, the nearest flow rate ABOVE
the calculated flow rate should be used and NEVER
G to G1 1.364
below or the pipe will not deliver enough heat. To the
A provisional pipe size can be estimated by looking right is a column marked c. This is the water velocity
at how much heat a pipe will carry: and should not exceed 1 m/s for small-bore systems
and 1.5 m/s for micro-bore systems. The maximum
28mm = 22 kW velocity is 1.5 m/s across all systems. The velocity
22mm = 12 kW must be entered on to Table 3.22 in column 10. The
15mm = 6 kW zig-zag line also relates to velocity. To read it, follow
10mm = 3 kW the line upwards until you find the velocity in m/s.
Remember! The flow rate we require is 0.235 kg/s.
Stage 1
Now look at the chart and find the flow rate, which
Look at section Boiler to A in Table 3.21. The total either matches or is slightly above. Also keep an eye
boiler load is 17.968 kW (without the 15 per cent) on the left/right columns as the pascals should not
and so the pipe size from Boiler to A will need to exceed 300 pa/m for any one section or the pump,
carry all of that heat. A 10 per cent margin for heat when its size is calculated, will be need a large head
loss from the pipe is being added and the length of of pressure and this could possibly create noise in the
the pipe run is 12 m. system. Figure 3.35 is a snapshot of CIBSE table 1.
The nearest flow rate is boxed for identification.
17.968 × 1.10 (10%) = 19.765 kW
➜
243
∆p/l c 10 mm 12 mm 15 mm 22 mm 28 mm 35 mm 42 mm c ∆p/l
qm c qm c qm c qm c qm c qm c qm c
35.0 0.006 0.10 0.012 0.13 0.023 0.16 0.069 0.22 0.140 0.27 0.253 0.31 0.429 0.36 35.0
37.5 0.007 0.12 0.012 0.13 0.024 0.17 0.071 0.23 0.145 0.28 0.263 0.32 0.446 0.37 37.5
40.0 0.007 0.12 0.013 0.15 0.025 0.18 0.074 0.24 0.151 0.29 0.273 0.33 0.462 0.38 40.0
42.5 0.007 0.12 0.013 0.15 0.026 0.18 0.077 0.25 0.156 0.30 0.283 0.35 0.478 0.40 42.5
45.0 0.008 0.13 0.014 0.16 0.026 0.18 0.079 0.25 0.161 0.31 0.292 0.36 0.494 0.41 45.0
47.5 0.008 0.13 0.014 0.16 0.027 0.19 0.082 0.26 0.166 0.32 0.301 0.37 0.509 0.42 47.5
50.0 0.008 0.13 0.015 0.17 0.028 0.20 0.084 0.27 0.171 0.32 0.310 0.38 0.524 0.44 50.0
52.5 0.15 0.008 0.13 0.015 0.17 0.029 0.20 0.087 0.28 0.176 0.33 0.319 0.39 0.539 0.45 52.5
55.0 0.009 0.15 0.016 0.18 0.030 0.21 0.089 0.28 0.181 0.34 0.327 0.40 0.553 0.46 55.0
57.5 0.009 0.15 0.016 0.18 0.031 0.22 0.091 0.29 0.186 0.35 0.336 0.41 0.567 0.47 57.5
60.0 0.009 0.15 0.016 0.18 0.031 0.22 0.094 0.30 0.190 0.36 0.344 0.42 0.581 0.48 60.0
62.5 0.009 0.15 0.017 0.19 0.032 0.23 0.096 0.31 0.195 0.37 0.352 0.43 0.594 0.49 0.50 62.5
65.0 0.010 0.17 0.017 0.19 0.033 0.23 0.098 0.31 0.199 0.38 0.360 0.44 0.608 0.51 65.0
67.5 0.010 0.17 0.018 0.20 0.034 0.24 0.100 0.32 0.203 0.39 0.368 0.45 0.621 0.52 67.5
70.0 0.010 0.17 0.018 0.20 0.034 0.24 0.102 0.33 0.208 0.40 0.375 0.46 0.634 0.53 70.0
72.5 0.010 0.17 0.018 0.20 0.035 0.25 0.104 0.33 0.212 0.40 0.383 0.47 0.646 0.54 72.5
75.0 0.010 0.17 0.019 0.21 0.036 0.25 0.107 0.34 0.216 0.41 0.390 0.48 0.659 0.55 75.0
77.5 0.011 0.19 0.019 0.21 0.036 0.25 0.109 0.35 0.220 0.42 0.398 0.49 0.671 0.56 77.5
80.0 0.011 0.19 0.019 0.21 0.037 0.26 0.111 0.35 0.224 0.43 0.405 0.50 0.683 0.57 80.0
82.5 0.011 0.19 0.020 0.22 0.038 0.27 0.113 0.36 0.228 0.43 0.412 0.51 0.695 0.58 82.5
85.0 0.011 0.19 0.020 0.22 0.038 0.27 0.114 0.36 0.232 0.44 0.419 0.51 0.707 0.59 85.0
87.5 0.011 0.19 0.021 0.24 0.039 0.28 0.116 0.37 0.236 0.45 0.426 0.52 0.718 0.60 87.5
90.0 0.012 0.20 0.021 0.24 0.040 0.28 0.118 0.38 0.240 0.46 0.432 0.53 0.730 0.61 90.0
Figure 3.35 Snapshot of CIBSE copper pipe sizing table 1 (The Chartered Institution of Building Services Engineers (CIBSE),
www.cibse.org)
Pipe sizing tables 2
qm = mass flow rate kg/s
c = velocity m/s Copper tubes BSEN1057 R250
∆p/l = pressure loss per unit length pa/m
Water at 75 °C
∆p/l c 10 mm 12 mm 15 mm 22 mm 28 mm 35 mm 42 mm c ∆p/l
qm c qm c qm c qm c qm c qm c qm c
92.5 0.012 0.20 0.021 0.24 0.040 0.28 0.120 0.38 0.243 0.46 0.439 0.54 0.741 0.62 92.5
95.0 0.012 0.20 0.022 0.25 0.041 0.29 0.122 0.39 0.247 0.47 0.446 0.55 0.752 0.63 95.0
97.5 0.012 0.20 0.022 0.25 0.042 0.30 0.124 0.40 0.251 0.48 0.452 0.55 0.763 0.63 97.5
100 0.012 0.20 0.022 0.25 0.042 0.30 0.126 0.40 0.254 0.48 0.459 0.56 0.774 0.64 100
120 0.014 0.24 0.025 0.28 0.047 0.33 0.139 0.44 0.282 0.54 0.508 0.62 0.857 0.71 120
140 0.015 0.25 0.027 0.30 0.051 0.36 0.152 0.49 0.308 0.59 0.554 0.68 0.934 0.78 140
160 0.017 0.29 0.029 0.32 0.056 0.40 0.164 0.52 0.332 0.63 0.598 0.73 1.000 0.83 160
180 0.30 0.018 0.30 0.032 0.36 0.060 0.42 0.176 0.56 0.354 0.67 0.638 0.78 1.070 0.89 180
200 0.019 0.32 0.034 0.38 0.063 0.44 0.186 0.59 0.376 0.71 0.677 0.83 1.130 0.94 200
220 0.020 0.34 0.035 0.39 0.067 0.47 0.197 0.63 0.397 0.75 0.714 0.88 1.200 1.00 1.00 220
240 0.021 0.35 0.037 0.41 0.070 0.49 0.207 0.66 0.417 0.79 0.750 0.92 1.260 1.05 240
260 0.022 0.37 0.039 0.44 0.074 0.52 0.216 0.69 0.436 0.83 0.784 0.96 1.310 1.09 260
280 0.023 0.39 0.041 0.46 0.077 0.54 0.226 0.72 0.454 0.86 0.817 1.00 1.370 1.14 280
300 0.024 0.40 0.042 0.47 0.080 0.56 0.235 0.75 0.472 0.90 0.849 1.04 1.420 1.18 300
320 0.025 0.42 0.044 0.49 0.083 0.59 0.243 0.78 0.490 0.93 0.880 1.08 1.470 1.22 320
Figure 3.36 Snapshot of CIBSE copper pipe sizing table 2 (The Chartered Institution of Building Services Engineers (CIBSE),
www.cibse.org)
➜
244
This shows that the nearest flow rate is slightly above take a look at the pascals per metre. At 300 Pa/m it
0.235 at 0.236 with a pipe size of 28 mm. The is at the limit of the 300 Pa/m maximum. There are
velocity 0.45 m/s and the pascals are 87.5 pa/m several advantages to using 22 mm. It is cheaper to
pressure drop. On the face of it this looks good BUT buy, which keeps the cost of the installation down
are there any alternative pipe sizes? Look at sheet 2, and it is easier to work with and install. However, the
in Figure 3.36. pascals may present a problem later, but this will not
There is an alternative pipe size because a 22 mm be known until the rest of the index circuit is calculated.
pipe will also deliver the required flow rate with a For the purpose of this example, 22 mm pipe will be
velocity of 0.75 m/s (nearer to the ideal 1 m/s) but chosen. The data can be entered into Table 3.22.
1 2 3 4 5 6 7 8 9 10 11 12
Section Heat Mains Total Flow Pipe Length Fittings Effective Velocity Pressure Total
required loss heat rate size of pipe resistance length (m/s) loss pascals
(kW) (%) required (kg/s) (mm) run (m) (33%) of pipework (Pa/m) by section
(kW) (m)
Boiler 17.968 10 19.765 0.235 22 12 1.33 15.96 0.75 300 4788
to A
A to B 10.828 5 11.37 0.135 22 6 1.33 7.98 0.44 120 957.6
B to E 6.436 5 6.75 0.080 22 4 1.33 5.32 0.26 47.5 252.7
E to G 3.868 5 4.10 0.049 15 4 1.33 5.32 0.36 140 744.8
G to G1 1.364 10 1.50 0.017 10 20 1.33 26.6 0.29 160 4256
Total pascals for pump sizing from the index circuit 10999.1
A to Cyl 7.140 5 3 1.33
B to C 4.392 5 3 1.33
C to C1 1.665 7 14 1.33
C to D 2.727 5 3 1.33
D to D1 1.022 5 10 1.33
D to D2 1.705 7 16 1.33
E to F 2.568 5 4 1.33
F to F1 0.547 6 12 1.33
F to F2 2.021 7 14 1.33
G to H 2.505 5 3 1.33
H to H1 1.141 5 10 1.33
H to H2 1.364 7 14 1.33
Stage 2 Therefore:
At the beginning of the process we allowed a Length of run × 78 watts (see Table 3.22)
percentage of the total kW for the section for heat 12 × 78 = 936 watts
loss from the pipe. This can now be checked to see if
it is adequate. Percentage emission = Total watts of run × 100
To check to see if the 5 per cent we added to the heat Total heat emission in watts
required is sufficient, we perform another calculation. 93,600
Percentage emission = = 5.2%
If the room is to be maintained at 21 °C and the flow 17,968
pipe is at 80 °C, this gives a temperature difference
of 59 °C. For the purposes of the calculation, we can So, the estimation of 5 per cent heat loss from the
round this up to 60. pipework was correct therefore the pipe size is also
correct.
➜
245
B to E
INDUSTRY TIP
B to E = 6.436 + 5% = 6.75 kW
There are four sheets for pipe sizing copper tubes. These Flow rate =
6.75
= 0.080 kg/s
documents are taken from the CIBSE concise guide. CIBSE 4.19 × 20
also produce pipe sizing tables for low-carbon steel pipe Pipe size = 22 mm
and plastic pressure pipe. Velocity = 0.44 m/s
Pascals = 120
Stages 1 and 2 can now be performed for the entire
index circuit. Percentage check
Length of run × 78
The index circuit
4 × 78 = 312 watts
A to B Total watts of run × 100
Percentage emission =
A to B = 10.828 + 5% = 11.37 kW Total heat emission in watts
∆p/l c 10 mm 12 mm 15 mm 22 mm 28 mm 35 mm 42 mm c ∆p/l
qm c qm c qm c qm c qm c qm c qm c
0.1 0.001 0.00 0.00 0.00 0.007 0.01 0.015 0.01 0.1
0.2 0.002 0.01 0.005 0.01 0.014 0.02 0.023 0.02 0.2
0.3 0.003 0.01 0.008 0.02 0.019 0.02 0.026 0.02 0.3
0.4 0.004 0.01 0.011 0.02 0.019 0.02 0.032 0.03 0.4
0.5 0.001 0.01 0.005 0.02 0.014 0.03 0.021 0.03 0.036 0.03 0.5
0.6 0.001 0.01 0.006 0.02 0.015 0.03 0.023 0.03 0.040 0.03 0.6
0.7 0.001 0.01 0.007 0.02 0.015 0.03 0.026 0.03 0.044 0.04 0.7
0.8 0.001 0.01 0.008 0.03 0.015 0.03 0.028 0.03 0.048 0.04 0.8
0.9 0.001 0.01 0.009 0.03 0.016 0.03 0.030 0.04 0.051 0.04 0.9
1.0 0.002 0.01 0.010 0.03 0.017 0.03 0.032 0.04 0.055 0.05 0.05 1.0
1.5 0.001 0.01 0.003 0.02 0.012 0.04 0.022 0.04 0.040 0.05 0.070 0.06 1.5
2.0 0.001 0.01 0.004 0.03 0.012 0.04 0.026 0.05 0.048 0.06 0.083 0.07 2.0
2.5 0.002 0.02 0.005 0.04 0.014 0.04 0.030 0.06 0.055 0.07 0.094 0.08 2.5
3.0 0.001 0.02 0.002 0.02 0.006 0.04 0.016 0.05 0.033 0.06 0.061 0.07 0.105 0.09 3.0
3.5 0.001 0.02 0.003 0.03 0.007 0.05 0.017 0.05 0.036 0.07 0.067 0.08 0.114 0.09 3.5
4.0 0.001 0.02 0.003 0.03 0.008 0.06 0.019 0.06 0.039 0.07 0.072 0.09 0.124 0.10 4.0
4.5 0.001 0.02 0.003 0.03 0.008 0.06 0.020 0.06 0.042 0.08 0.078 0.10 0.132 0.11 4.5
5.0 0.001 0.02 0.004 0.04 0.008 0.06 0.022 0.07 0.045 0.09 0.083 0.10 0.141 0.12 5.0
5.5 0.002 0.03 0.004 0.04 0.008 0.06 0.023 0.07 0.048 0.09 0.087 0.11 0.149 0.12 5.5
6.0 0.002 0.03 0.005 0.06 0.008 0.06 0.024 0.08 0.050 0.09 0.092 0.11 0.156 0.13 6.0
6.5 0.002 0.03 0.005 0.06 0.008 0.06 0.025 0.08 0.053 0.10 0.096 0.12 0.164 0.14 6.5
7.0 0.002 0.03 0.006 0.07 0.008 0.06 0.027 0.09 0.055 0.10 0.100 0.12 0.171 0.14 7.0
7.5 0.002 0.03 0.006 0.07 0.009 0.06 0.028 0.09 0.057 0.11 0.105 0.13 0.178 0.15 0.15 7.5
8.0 0.003 0.05 0.006 0.07 0.009 0.06 0.029 0.09 0.059 0.11 0.108 0.13 0.185 0.15 8.0
8.5 0.003 0.05 0.006 0.07 0.010 0.07 0.030 0.10 0.061 0.12 0.112 0.14 0.191 0.16 8.5
9.0 0.003 0.05 0.006 0.07 0.010 0.07 0.031 0.10 0.064 0.12 0.116 0.14 0.198 0.16 9.0
9.5 0.003 0.05 0.006 0.07 0.010 0.07 0.032 0.10 0.066 0.13 0.120 0.15 0.204 0.17 9.5
10.0 0.05 0.003 0.05 0.006 0.07 0.011 0.08 0.033 0.11 0.068 0.13 0.123 0.15 0.210 0.17 10.0
12.5 0.004 0.07 0.006 0.07 0.012 0.08 0.037 0.12 0.077 0.15 0.140 0.17 0.239 0.20 12.5
15.0 0.005 0.08 0.007 0.08 0.014 0.10 0.042 0.13 0.086 0.16 0.156 0.19 0.265 0.22 15.0
17.5 0.005 0.08 0.008 0.09 0.015 0.11 0.046 0.15 0.094 0.18 0.170 0.21 0.289 0.24 17.5
20.0 0.005 0.08 0.008 0.09 0.016 0.11 0.049 0.16 0.101 0.19 0.184 0.23 0.312 0.26 20.0
22.5 0.005 0.08 0.009 0.10 0.017 0.12 0.053 0.17 0.108 0.21 0.197 0.24 0.334 0.28 22.5
25.0 0.005 0.08 0.010 0.11 0.019 0.13 0.056 0.18 0.115 0.22 0.209 0.26 0.354 0.29 0.30 25.0
27.5 0.005 0.08 0.010 0.11 0.020 0.14 0.060 0.19 0.122 0.23 0.221 0.27 0.374 0.31 27.5
30.0 0.006 0.10 0.011 0.12 0.021 0.15 0.063 0.20 0.128 0.24 0.232 0.28 0.393 0.33 30.0
32.5 0.006 0.10 0.011 0.12 0.022 0.16 0.066 0.21 0.134 0.25 0.243 0.30 0.411 0.34 32.5
35.0 0.006 0.10 0.012 0.13 0.023 0.16 0.069 0.22 0.140 0.27 0.253 0.31 0.429 0.36 35.0
37.5 0.007 0.12 0.012 0.13 0.024 0.17 0.071 0.23 0.145 0.28 0.263 0.32 0.446 0.37 37.5
40.0 0.007 0.12 0.013 0.15 0.025 0.18 0.074 0.24 0.151 0.29 0.273 0.33 0.462 0.38 40.0
42.5 0.007 0.12 0.013 0.15 0.026 0.18 0.077 0.25 0.156 0.30 0.283 0.35 0.478 0.40 42.5
45.0 0.008 0.13 0.014 0.16 0.026 0.18 0.079 0.25 0.161 0.31 0.292 0.36 0.494 0.41 45.0
47.5 0.008 0.13 0.014 0.16 0.027 0.19 0.082 0.26 0.166 0.32 0.301 0.37 0.509 0.42 47.5
50.0 0.008 0.13 0.015 0.17 0.028 0.20 0.084 0.27 0.171 0.32 0.310 0.38 0.524 0.44 50.0
52.5 0.15 0.008 0.13 0.015 0.17 0.029 0.20 0.087 0.28 0.176 0.33 0.319 0.39 0.539 0.45 52.5
55.0 0.009 0.15 0.016 0.18 0.030 0.21 0.089 0.28 0.181 0.34 0.327 0.40 0.553 0.46 55.0
57.5 0.009 0.15 0.016 0.18 0.031 0.22 0.091 0.29 0.186 0.35 0.336 0.41 0.567 0.47 57.5
60.0 0.009 0.15 0.016 0.18 0.031 0.22 0.094 0.30 0.190 0.36 0.344 0.42 0.581 0.48 60.0
62.5 0.009 0.15 0.017 0.19 0.032 0.23 0.096 0.31 0.195 0.37 0.352 0.43 0.594 0.49 0.50 62.5
65.0 0.010 0.17 0.017 0.19 0.033 0.23 0.098 0.31 0.199 0.38 0.360 0.44 0.608 0.51 65.0
67.5 0.010 0.17 0.018 0.20 0.034 0.24 0.100 0.32 0.203 0.39 0.368 0.45 0.621 0.52 67.5
70.0 0.010 0.17 0.018 0.20 0.034 0.24 0.102 0.33 0.208 0.40 0.375 0.46 0.634 0.53 70.0
72.5 0.010 0.17 0.018 0.20 0.035 0.25 0.104 0.33 0.212 0.40 0.383 0.47 0.646 0.54 72.5
75.0 0.010 0.17 0.019 0.21 0.036 0.25 0.107 0.34 0.216 0.41 0.390 0.48 0.659 0.55 75.0
77.5 0.011 0.19 0.019 0.21 0.036 0.25 0.109 0.35 0.220 0.42 0.398 0.49 0.671 0.56 77.5
80.0 0.011 0.19 0.019 0.21 0.037 0.26 0.111 0.35 0.224 0.43 0.405 0.50 0.683 0.57 80.0
82.5 0.011 0.19 0.020 0.22 0.038 0.27 0.113 0.36 0.228 0.43 0.412 0.51 0.695 0.58 82.5
85.0 0.011 0.19 0.020 0.22 0.038 0.27 0.114 0.36 0.232 0.44 0.419 0.51 0.707 0.59 85.0
87.5 0.011 0.19 0.021 0.24 0.039 0.28 0.116 0.37 0.236 0.45 0.426 0.52 0.718 0.60 87.5
90.0 0.012 0.20 0.021 0.24 0.040 0.28 0.118 0.38 0.240 0.46 0.432 0.53 0.730 0.61 90.0
Figure 3.37 CIBSE sheet 1 (The Chartered Institution of Building Services Engineers (CIBSE), www.cibse.org)
247
∆p/l 10 mm 12 mm 15 mm 22 mm 28 mm 35 mm 42 mm ∆p/l
c c
qm c qm c qm c qm c qm c qm c qm c
92.5 0.012 0.20 0.021 0.24 0.040 0.28 0.120 0.38 0.243 0.46 0.439 0.54 0.741 0.62 92.5
95.0 0.012 0.20 0.022 0.25 0.041 0.29 0.122 0.39 0.247 0.47 0.446 0.55 0.752 0.63 95.0
97.5 0.012 0.20 0.022 0.25 0.042 0.30 0.124 0.40 0.251 0.48 0.452 0.55 0.763 0.63 97.5
100 0.012 0.20 0.022 0.25 0.042 0.30 0.126 0.40 0.254 0.48 0.459 0.56 0.774 0.64 100
120 0.014 0.24 0.025 0.28 0.047 0.33 0.139 0.44 0.282 0.54 0.508 0.62 0.857 0.71 120
140 0.015 0.25 0.027 0.30 0.051 0.36 0.152 0.49 0.308 0.59 0.554 0.68 0.934 0.78 140
160 0.017 0.29 0.029 0.32 0.056 0.40 0.164 0.52 0.332 0.63 0.598 0.73 1.000 0.83 160
180 0.30 0.018 0.30 0.032 0.36 0.060 0.42 0.176 0.56 0.354 0.67 0.638 0.78 1.070 0.89 180
200 0.019 0.32 0.034 0.38 0.063 0.44 0.186 0.59 0.376 0.71 0.677 0.83 1.130 0.94 200
220 0.020 0.34 0.035 0.39 0.067 0.47 0.197 0.63 0.397 0.75 0.714 0.88 1.200 1.00 1.00 220
240 0.021 0.35 0.037 0.41 0.070 0.49 0.207 0.66 0.417 0.79 0.750 0.92 1.260 1.05 240
260 0.022 0.37 0.039 0.44 0.074 0.52 0.216 0.69 0.436 0.83 0.784 0.96 1.310 1.09 260
280 0.023 0.39 0.041 0.46 0.077 0.54 0.226 0.72 0.454 0.86 0.817 1.00 1.370 1.14 280
300 0.024 0.40 0.042 0.47 0.080 0.56 0.235 0.75 0.472 0.90 0.849 1.04 1.420 1.18 300
320 0.025 0.42 0.044 0.49 0.083 0.59 0.243 0.78 0.490 0.93 0.880 1.08 1.470 1.22 320
340 0.026 0.44 0.046 0.52 0.086 0.61 0.252 0.81 0.506 0.96 0.910 1.12 1.530 1.27 340
360 0.027 0.46 0.047 0.53 0.089 0.63 0.260 0.83 0.523 0.99 0.940 1.15 1.570 1.31 360
380 0.028 0.47 0.049 0.55 0.092 0.65 0.268 0.86 0.539 1.02 0.968 1.19 1.620 1.35 380
400 0.028 0.47 0.050 0.56 0.094 0.66 0.276 0.88 0.555 1.05 0.996 1.22 1.670 1.39 400
420 0.029 0.49 0.052 0.58 0.097 0.68 0.283 0.90 0.570 1.08 1.020 1.25 1.720 1.43 420
440 0.50 0.030 0.51 0.053 0.59 0.099 0.70 0.291 0.93 0.585 1.11 1.050 1.29 1.760 1.46 440
460 0.031 0.52 0.054 0.60 0.102 0.72 0.298 0.95 0.600 1.14 1.070 1.31 1.800 1.50 1.50 460
480 0.032 0.54 0.056 0.63 0.105 0.74 0.306 0.98 0.614 1.17 1.100 1.35 1.850 1.54 480
500 0.032 0.54 0.057 0.64 0.107 0.76 0.313 1.00 0.628 1.19 1.120 1.37 1.890 1.57 500
520 0.033 0.56 0.058 0.65 0.109 0.77 0.320 1.02 0.642 1.22 1.150 1.41 1.930 1.61 520
540 0.034 0.57 0.060 0.67 0.112 0.79 0.326 1.04 0.656 1.25 1.170 1.44 1.970 1.64 540
560 0.035 0.59 0.061 0.68 0.114 0.81 0.333 1.06 0.669 1.27 1.200 1.47 2.010 1.67 560
580 0.035 0.59 0.062 0.69 0.116 0.82 0.340 1.09 0.682 1.30 1.220 1.50 2.050 1.70 580
600 0.036 0.61 0.063 0.71 0.119 0.84 0.346 1.11 0.695 1.32 1.240 1.52 2.090 1.74 600
620 0.037 0.62 0.065 0.73 0.121 0.85 0.353 1.13 0.708 1.35 1.270 1.56 2.130 1.77 620
640 0.037 0.62 0.066 0.74 0.123 0.87 0.359 1.15 0.721 1.37 1.290 1.58 2.160 1.80 640
660 0.038 0.64 0.067 0.75 0.125 0.88 0.365 1.17 0.733 1.39 1.310 1.61 2.200 1.83 660
680 0.039 0.66 0.068 0.76 0.127 0.90 0.371 1.19 0.745 1.42 1.330 1.63 2.240 1.86 680
700 0.039 0.66 0.069 0.77 0.130 0.92 0.378 1.21 0.757 1.44 1.350 1.66 2.270 1.89 700
720 0.040 0.67 0.070 0.78 0.132 0.93 0.383 1.22 0.769 1.46 1.380 1.69 2.310 1.92 720
740 0.041 0.69 0.071 0.80 0.134 0.95 0.389 1.24 0.781 1.48 1.400 1.72 2.350 1.95 740
760 0.041 0.69 0.073 0.82 0.136 0.96 0.395 1.26 0.793 1.51 1.420 1.74 2.380 1.98 2.00 760
780 0.042 0.71 0.074 0.83 0.138 0.97 0.401 1.28 0.804 1.53 1.440 1.77 2.410 2.00 780
800 0.043 0.73 0.075 0.84 0.140 0.99 0.407 1.30 0.816 1.55 1.460 1.79 2.450 2.04 800
820 0.043 0.73 0.076 0.85 0.142 1.00 0.412 1.32 0.827 1.57 1.480 1.82 2.480 2.06 820
840 0.044 0.74 0.077 0.86 0.144 1.02 0.418 1.34 0.838 1.59 1.500 1.84 2.510 2.09 840
860 0.044 0.74 0.078 0.87 0.146 1.03 0.423 1.35 0.849 1.61 1.520 1.86 2.550 2.12 860
880 0.045 0.76 0.079 0.88 0.147 1.04 0.429 1.37 0.860 1.63 1.540 1.89 2.580 2.15 880
900 0.046 0.78 0.080 0.90 0.149 1.05 0.434 1.39 0.871 1.65 1.560 1.91 2.610 2.17 900
920 0.046 0.78 0.081 0.91 0.151 1.07 0.440 1.41 0.881 1.67 1.570 1.93 2.640 2.20 920
940 0.047 0.79 0.082 0.92 0.153 1.08 0.445 1.42 0.892 1.69 1.590 1.95 2.680 2.23 940
960 0.047 0.79 0.083 0.93 0.155 1.09 0.450 1.44 0.902 1.71 1.610 1.97 2.710 2.25 960
980 0.048 0.81 0.084 0.94 0.157 1.11 0.455 1.45 0.913 1.73 1.630 2.00 2.740 2.28 980
1000 0.048 0.81 0.085 0.95 0.158 1.12 0.461 1.47 0.923 1.75 1.650 2.02 2.770 2.30 1000
1100 0.051 0.86 0.090 1.01 0.167 1.18 0.486 1.55 0.973 1.85 1.740 2.13 2.920 2.43 1100
1200 0.054 0.91 0.094 1.05 0.176 1.24 0.510 1.63 1.020 1.94 1.820 2.23 3.060 2.54 1200
1300 0.056 0.94 0.098 1.10 0.184 1.30 0.533 1.70 1.060 2.01 1.910 2.34 3.200 2.66 1300
1400 1.00 0.059 1.00 0.103 1.15 0.191 1.35 0.555 1.77 1.110 2.11 1.980 2.43 3.330 2.77 1400
1500 0.061 1.03 0.107 1.20 0.199 1.41 0.577 1.84 1.150 2.18 2.060 2.53 3.460 2.88 1500
1600 0.063 1.06 0.111 1.24 0.206 1.45 0.598 1.91 1.190 2.26 2.140 2.63 3.580 2.98 3.00 1600
1700 0.066 1.11 0.115 1.29 0.214 1.51 0.618 1.97 1.230 2.34 2.210 2.71 3.700 3.08 1700
1800 0.068 1.15 0.118 1.32 0.220 1.55 0.638 2.04 1.270 2.41 2.280 2.80 3.820 3.18 1800
1900 0.070 1.18 0.122 1.37 0.227 1.60 0.658 2.10 1.310 2.49 2.350 2.88 3.930 3.27 1900
2000 0.072 1.21 0.126 1.41 0.234 1.65 0.677 2.16 1.350 2.56 2.410 2.96 4.040 3.36 2000
Figure 3.38 CIBSE sheet 2 (The Chartered Institution of Building Services Engineers (CIBSE), www.cibse.org)
248
Flow rate =
1.50
= 0.017 kg/s Percentage emission = 100000 = 5.5%
4.19 × 12 17968
Pipe size = 10 mm
Velocity = 0.29 m/s IMPROVE YOUR MATHS
Pascals = 160 Using the techniques discussed in this section,
complete the pipe sizing table for the single-storey
Percentage check dwelling.
Length of run × 50
20 × 50 = 1000 watts
1 2 3 4 5 6 7 8 9 10 11 12
Section Heat Mains Total heat Flow Pipe Length Fittings Effective Velocity Pressure Total
required loss required rate size of pipe resistance length of (m/s) loss pascals by
(kW) (%) (kW) (kg/s) (mm) run (m) (33%) pipework (m) (Pa/m) section
Boiler 17.968 10 19.765 0.235 22 12 1.33 15.96 0.75 300 4788
to A
A to B 10.828 5 11.37 0.135 22 6 1.33 7.98 0.44 120 957.6
B to E 6.436 5 6.75 0.080 22 4 1.33 5.32 0.26 47.5 252.7
E to G 3.868 5 4.10 0.049 15 4 1.33 5.32 0.36 140 744.8
G to G1 1.364 10 1.50 0.017 10 20 1.33 26.6 0.29 160 4256
Total pascals for pump sizing from the index circuit 10,999.1
The total needs to be converted to metres head. If one Assuming there is a pressure drop at the boiler of 2 m
pascal is equal to 0.0001019977334 metres head then: head, then the total for the system will be:
10,999.1 × 0.0001019977334 = 1.122 metres head 2 + 1.122 = 3.122 metres head pressure drop
You can see that the index circuit has a pressure loss This must be converted to kilopascals (kPa). To convert
of 1.122 metres head. metres head to kPa simply multiply the metres head by
The next step is to find out if the boiler creates a 9.81:
significant pressure drop. Some low water content 3.122 × 9.81 = 30.63 kPa
boilers generate a high resistance to flow through the
heat exchanger and this results in a drop in pressure. You must now consult the pump manufacturer’s literature
This, too, is measured in metres head. Consulting the to select a pump and pump speed based on your
boiler manufacturer’s instructions will indicate if this is the calculation. From Figure 3.39, it will be seen that a
case. Any pressure drop at the boiler will also need to Grundfos UPS-15/50 pump will give 30.63 kPa on
be added to the pressure drop across the index circuit. either speed 2 @ 0.28 l/s or speed 3 @ 0.38 l/s.
➜
249
P H
(kPa) (m)
4.5
40
4.0
3.5
30 3.0
2.5
20 2.0
1.5
10 1.0
Speed 3
0.5 Speed 2
Speed 1
0 0.0
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8 3.0 Q (m3/h)
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 Q(I/s)
30.31 kPa
Presenting the calculations to the and can be saved as either a hard copy in portable
customer document format (PDF) or as Word or Excel documents.
The methods that can be used to present the design of Many proprietary heating design packages also produce
a central heating system and the results of calculations a printable report of the heat losses, heat emitters
performed were covered previously, but it is worth and pipework sizes. These too can be supplied to the
revisiting the basic principle of design and calculation customer at the estimation stage.
presentation.
250
System under negative System under positive System under positive pressure.
pressure. pressure. Correct arrangement showing
Pushing into the cistern Pumping over the vent pipe the position of the vent and feed
behind the pump. This is known
as the neutral zone
251
Sealed system components On cooling, the water contracts, the air in the expansion
As we have already seen, sealed systems do not contain vessel forces the water back into the system and the
a feed and expansion cistern nor open vent pipe. Instead, pressure reduces to its original pressure of 1 bar.
these systems incorporate the following components: Periodically, the pressure in the vessel may require
● an external expansion vessel fitted to the system return topping up. This can be done by removing the cap on the
● a pressure relief valve Schrader valve and pumping the vessel up to its original
● the system is filled via a temporary filling loop or a pressure with a foot pump. The operation of expansion
CA disconnection device vessels was discussed in more detail in Chapter 2.
● a pressure gauge.
252
The pressure relief valve constitutes a cross connection between the cold
The pressure relief valve (also known as the expansion main (fluid category 1) and the heating system (fluid
valve) is installed on to the system to protect against category 3), which is not allowed under the Water
over-pressurisation of the water. Pressure relief valves Supply (Water Fittings) Regulations. The filling loop
are usually set to 3 bar pressure. If the water pressure must protect the cold water main from backflow and
rises above the maximum pressure that the valve is set this is done in two ways:
● A filling loop has a type EC verifiable double check
to, the valve opens and discharges the excess water
pressure safely to the outside of the property through valve included in the filling loop arrangement.
● The filling loop must be disconnected after filling
the discharge pipework.
creating a type AUK3 air gap for protection against
Pressure relief valves are most likely to open because backflow.
of lack of room in the system for expansion due to a
malfunction with the expansion vessel. This can be
caused if:
● the diaphragm in the expansion vessel has ruptured
253
normal operation, the valve should not discharge water. The pressure gauge
However, the valve may discharge a small amount of This is to allow the correct water pressure to be
water if the supply pressure falls below 0.5 bar or set within the system. It also acts as a warning of
11 per cent of the downstream pressure. component failure or an undetected leak should the
pressure begin to inexplicably rise or fall.
Pressure gauge
60
40
80
20
100
Type CA
device
254
Zone 1
Zone valve
M
~ M
~
Preheat
CH ON
Programmer
255
C-PLAN
Gravity hot water pumped central heating
Link terminals 5-9 in the 10-way junction box
A
5
B
A
** 1 **4 CM901
1
5 3 5
B CM907 1
4 2 2 2
DT90E T6360B Wireless 3
Room Room thermostats Brown
thermostat OR thermostat OR 8 4
available
Blue 2 5
Grey 1 6 L
1 Orange I
C 10 7 N
L 1 6 Green/ 3 8 K
N 2 Not used yellow
2 9
E 3 8 White 9
10
230 volt L641A Hot water
mains Cylinder valve 10-way junction
input thermostat box Honeywell
part No.
42002116-001
230 V G/YELLOW
50 Hz
3 A rated
L N E 28 mm
GREY
BLUE
Cylinder Zone
Room stat. stat. valve
BROWN
2 1 3
1 C ORANGE
LINK WHITE
1 2 3 4 5 6 7 8 9 10
BOILER
HTG
HW
L E N
PUMP L
L N E
N
Fully pumped incorporating 3-port sit in the mid-position. The diverter valve (W-plan),
valves – mid-position (Y-plan) and however, will either allow flow to the hot water or
central heating circuits. The W-plan system is known
diverter valves (W-plan)
as a hot water priority system. In other words, the
The two diagrams here look very similar but are two hot water storage cylinder must be satisfied before
very different systems. The mid-position valve (Y-plan) the central heating circuit will operate. The W-plan is
allows water to be circulated to both heating and hot identifiable because there are only three wires (L/N/E)
water circuits simultaneously because the valve will from the diverter valve.
256
230 V MID-POSITION
50 Hz ZONE VALVE
WHITE
ORANGE
3 A rated
G/YELLOW
L N E Cylinder LINK 8 to10
BLUE
stat.
GREY
Room stat. 1 PUMP
OVERRUN
2 1 3
8 9 10
C 2
BOILER
SL
1 2 3 4 5 6 7 8 9 10 N E L
PL
PUMP
L
E
N
BOILER
HW OFF
HW ON
N E L
HTG
L
PUMP
E
N L N
DIVERTER VALVE
230 V
BROWN
50 Hz
G/YELLOW
3 A rated Cylinder
BLUE
BOILER
SL
1 2 3 4 5 6 7 8 9 10 N E L
PL
PUMP
L
E
N
BOILER
H.W.
HTG
N E L
L
PUMP
N L E
N
Figure 3.46 Fully pumped incorporating 3-port valves – mid-position and diverter
Fully pumped incorporating include a system boiler will not require an external
2 × 2-port valves (S-plan) pump as shown in the diagram and this can be
omitted.
This system is immediately identifiable because of the
2 × 2-port motorised zone valves. Some systems that
257
S-PLAN
If using a 6 wire 28mm or 1" BSP V4043H on either circuit, the white wire is not needed and must be
made electrically safe.
A Brown 5
Fully pumped system only
5 Blue 2
B
** **4
A 1 Grey 1
1 Orange
CM901 10
5 3 5 Green/
B CM907 3 1
4 2 2 yellow
2
DT90E T6360B Wireless V4043H 3
Room Room thermostats Hot water
thermostat OR thermostat OR valve 4
available
5
6
Brown 8 7
Blue 2 8
C 1 Grey 1 9
6 L 1
Orange 10 10
Not used N 2
2 Green/ 3
8 yellow E 3
10-way junction
L641A V4043H 230 volt box Honeywell
Cylinder Hot water mains part No.
thermostat valve input 42002116-001
When circuit is wired as above: Complete wiring will be as line drawing below
NOTE:
It is recommended that either the 10-way junction box or sundial Wiring Centre should be used to
ensure first time, fault free wiring.
Motor Motor
G/YELLOW
BROWN
BROWN
GREY
BLUE
BLUE
ORANGE
BOILER
SL
N E L
PL
PUMP
1 2 3 4 5 6 7 8 9 10 L
E
N
BOILER
HTG
HW
N E L
PUMP L
N L E
N
258
S-PLAN PLUS
If using a 6 wire 28 mm or 1" BSP V4043H on either circuit, the white wire is not needed and must be made electrically safe.
Fully pumped system only
Brown 5 1
Blue 2 2
** **4
A Grey 1 3
1 Orange 10 4
5 3 5 Green/
B 3 10-way junction 5
4 2 2 yellow box Honeywell
part No. 6
DT90E T6360B V4043H 42002116-001 7
Room Room Hot water
thermostat OR thermostat OR valve 1 8
9
A Brown 7 10
Brown 8
Blue 7 Blue 2
2
B 1 Grey 1
C 1 Grey 1
6 Orange L 1
Orange 10 CM901 10
Not used CM907 Green/ 3 N 2
2 Green/ 3
yellow yellow E 3
8
L641A V4043H Wireless V4043H 230 volt
Cylinder Hot water thermostats Hot water mains
thermostat valve available valve 2 input
When circuit is wired as above: Complete wiring will be as line drawing below
NOTE:
It is recommended that a 10-way junction box should be used to ensure first time, fault free wiring.
G/YELLOW
BROWN
BROWN
GREY
BLUE
BLUE
BLUE
ORANGE
ORANGE
stat. Programmable
BROWN
Room stat.
stat.
2 1 3 A B
1 C
PUMP
1 2 3 4 5 6 7 8 9 10 OVERRUN
8 9 10
BOILER
SL
BOILER
HTG
N E L
HW
N E L PL
PUMP L PUMP
L
N L E
E
N
N
Figure 3.48 Fully pumped incorporating hot water and multiple space heating zones (S-plan plus)
259
Fully pumped incorporating weather and the zone valves have closed. Water is then
compensation, optimum start or circulated through the automatic bypass valve to keep
the boiler below the high limit temperature.
delayed start controllers
The diagram in Figure 3.49 shows a fully pumped The diagrams previously shown indicate the wiring
S-plan system including weather compensation. The arrangement of a pump overrun facility.
red dashed line shows the alteration that must be
made to a standard S-plan wiring arrangement to Frost thermostats
accommodate the weather compensator. Frost thermostats should always be fitted in
conjunction with a pipe thermostat. The frost
Application of frost thermostats and thermostat will sense the temperature of the air whilst
boilers with pump overrun the pipe thermostat will sense the temperature of the
Pump overrun is a feature that some boilers require to water. Both thermostats have to be closed before the
dissipate the heat after the burner has finished firing. boiler will fire. When the water temperature reaches
Pump overrun allows the hot water to be circulated near freezing point, then the boiler will fire preventing
away from the boiler preventing the operation of the the system from freezing. Frost thermostats will
energy cut-out. It often occurs when both the hot override all other controls to ensure the safety of the
water and heating circuits have reached temperature system.
CH HW
2-port 2-port
zone valve zone valve
Fused spur
L N E
C/S
R/S
NOTE: Changes to cylinder stat
connections and addition of
HW OFF from timer
LINK
Boiler
CH R/S HW HW L N E sL
L N E C/S 9 10
ON ON ON OFF
Weather compensation
sL N
L N CH ON Outside sensor
HW ON
Time clock
HW OFF 'HW OFF' wiring centre
Figure 3.49 Fully pumped incorporating weather compensation, optimum start or delayed start controllers
260
261
Testing for earth continuity 2 Connect the live conductor to the earth conductor
by using one of the spare earth connections on the
When we test for earth continuity, we are ensuring that
earth bar of the consumer unit. By doing this, a
the current will have a safe path to earth in the event
circuit will be created which is half live conductor
of a fault or short circuit occurring.
and half earth conductor.
3 Select the correct test function on the test
Insulation and continuity testers equipment. This should usually be the low reading
The use of an insulation and continuity tester covers ohm meter function.
all aspects of domestic, commercial and industrial 4 The test equipment must be zeroed before the
electrical contracting, building maintenance, testing, test is performed. This can usually be completed by
inspection and servicing. Combining both insulation connecting the two test leads together and pressing
testing and continuity testing, each instrument the test button on the tester until the reading on
caters for all aspects of fixed wiring installations. The the test equipment reads 0 ohms.
instruments are useful for checking circuits that trip 5 Unscrew the switched fused spur from the back box
their protective devices. to expose the electrical connections behind.
6 On the switch fuse spur, touch the earth connection
with the green test lead and the live connection
with the brown test lead. The test reading must be
less than 1 ohm.
7 At the consumer unit, place the live conductor back
into the correct circuit connection.
5 COMMISSIONING
CENTRAL HEATING
Figure 3.51 Insulation and continuity testers
SYSTEMS AND
COMPONENTS
KEY POINT
The earth continuity test is performed WHILE Testing and commissioning of central heating systems
THE CIRCUIT IS DEAD. Always perform the safe is probably the most important aspect of any heating
isolation procedure before working on electrical installation as it is here that we see if the system
circuits. we have installed is leak-free and performs to the
requirements of the design.
The earth continuity test sequence Correct commissioning procedures are laid down by
industry standards and manufacturer’s instructions, but
1 Select the circuit to be tested on the distribution
experience will also play a vital part in the testing and
board (consumer unit) and remove the live
commissioning process.
conductor from the residual current device (RCD) or
circuit breaker (MCB). In this section, we will assess the correct
commissioning and testing processes that are designed
to set up the system to work as the design intended.
262
work on domestic central This document should be read in conjunction with the
British Standards.
heating systems
Inadequate commissioning, system flushing and The British Standards – BS EN
maintenance operations can inflict damage to even 12828, BS EN 12831, BS EN 14336
the best designed and installed central heating system. and BS 7593
Building debris and swarf (pipe filings) can easily block The main British Standards for the design, installation,
pipes and these can also promote bacteriological commissioning and testing of central heating systems
growth. In addition, excess flux used during the are:
installation can cause corrosion and may lead to ● BS EN 12828:2003 Heating systems in buildings.
system leakage and component failure. Design for water-based heating systems
It is obvious, then, that correct commissioning ● BS EN 12831:2003 Heating systems in buildings.
procedures must be adopted if the problems stated Method for calculation of the design heat load
are to be avoided. There are documents that must be ● BS EN 14336:2004 Heating systems in buildings.
Remember, Scotland has its own but almost identical ● 5.6 System filling and venting
Scottish Water Bylaws 2004. ● 5.7 Frost precautions
● 9.3 Instructions on operation and use the commissioning of central heating systems. In
● 9.4 Hand over documentation Section 2 of the guide, its states that:
● Annex A: Guide to good practice for water tightness a On completion of the installation of a boiler
test or hot water storage system, together with
● Annex B: Guide to good practice for pressure testing associated equipment such as pipework,
● Annex C: Guide to good practice for system flushing pumps and controls, the equipment should
and cleaning be commissioned in accordance with
● Annex D: Guide to good practice for operational the manufacturer’s instructions. These
tests instructions will be specific to the particular
● Annex E: Guide to good practice for static completion boiler or hot water storage system.
● Annex F: Guide to good practice for setting to work b The installer should give a full explanation
● Annex G: Guide to good practice for balancing water of the system and its operation to the user,
flow rates including the manufacturer’s User Manual
● Annex H: Guide to good practice for setting of where provided.
control systems.
These will be looked at a little later in the chapter. Manufacturer’s instructions
Where appliances and equipment are installed
The Building Regulations on a system, the manufacturer’s instructions are
The Building Regulations make reference to a key document when undertaking testing and
commissioning of central heating systems. These are commissioning procedures and it is important that
mentioned briefly in Approved Document L1A/B. Here these are used correctly at both installation and
it states that: commissioning operations. Only the manufacturers
(3) Where this regulation applies the person will know the correct procedures that should be used
carrying out the work shall, for the purpose to safely put the equipment into operation so that it
of ensuring compliance with paragraph performs to its maximum specification. Remember:
● Always read the instructions before operations begin.
F1(2) or L1(b) of Schedule 1, give to the local
● Always follow the procedures in the correct order.
authority a notice confirming that the fixed
● Always hand the instructions over to the customer
building services have been commissioned in
accordance with a procedure approved by the upon completion.
● Failure to follow the instructions may invalidate the
Secretary of State.
manufacturer warranty.
(4) The notice shall be given to the local
authority–
a Not later than the date on which the notice Visual inspections of central
required by regulation 16(4) is required to be heating systems
given; or Before soundness testing a central heating system,
b Where that regulation does not apply, not more visual inspections of the installation should take place.
than 30 days after completion of the work. British Standard BS EN 14336 states:
● that all plant items are in accordance with the
The Domestic Building Services design, drawings, specifications and, where
Compliance Guide applicable, the manufacturers’ instructions
The Domestic Building Services Compliance Guide 2013 ● that correct installation procedures are being followed
(amended 2018) gives specific instructions regarding ● that the standards of installation are being met
264
This should include the following actions: Only when the stage being filled is leak free should
● Walk around the installation. Check that you are the next stage be filled.
happy that the installation is correct and meets ● Air locks from cistern-fed, open vented systems are
installations standards. less likely to occur as each stage is filled slowly and
● Check that the power supply and fuel supply i.e. gas, methodically. Any problems can be assessed and
oil, etc. is off and cannot be inadvertently switched rectified as the filling progresses without the need
on. If necessary, place warning notices at key to isolate the whole system and initiate a full drain
isolation points. down.
● Check that all radiator valves and air release valves ● Where a sealed system has been installed, the
are closed. system should be filled until the pressure gauge
● Check that the drain-off valves for the system are reaches the normal fill pressure, usually 1 bar.
closed.
Once the system pressure has stabilised and the cistern
● Check that all motorised valves have been manually
(if an open vent system) is full, the furthest radiator on
opened.
the index circuit can be opened and the radiator bled
● Check that the pump has been removed and a
of air. Where sealed systems are concerned, this will
temporary section of pipe installed. This is to
cause the pressure to drop. The system should then be
prevent the pump being damaged by any debris that
recharged with water to normal operating pressure.
has found its way into the system.
● Ensure that all room and cylinder thermostats are in
KEY POINT
the off position.
Do not be tempted to overfill the system just for
● Check that all capillary joints are soldered and that
the sake of filling the system with water, as this
all compression joints are fully tightened. can often cause the pressure relief valve to open
● Check that enough pipe clips, supports and brackets and discharge water.
are installed and that all pipework is secure.
● Check that the equipment (boiler, pump, motorised
Working back towards the boiler, open and fill the
valves, expansion vessels, etc.) are installed correctly
downstairs radiators first. This will ensure that airlocks
and that all joints and unions on and around the
do not occur on any pipework work drops to the lower
equipment are tight.
radiators. Once the downstairs circuit is full, then the
● Check that cisterns and tanks are supported
upstairs circuit can be filled working from the furthest
correctly and that float operated valves are
radiator back towards the boiler.
provisionally set to the correct water level.
If the system has been connected to the heat
The initial system fill exchanger coil of a hot water storage vessel, open and
vent the air from any automatic air valves.
The initial system fill is always conducted at the normal
operating pressure of the system. Again, the British When the system has been filled with water, the
Standard BS EN 14336 is very clear: system should be allowed to stabilise and any float
The heating system shall be water tight and operated valves should be allowed to shut off and a
tested for leakage. … This test may be an check made to see where the water line is to ensure
independent test or a combined test for water there is room for the expansion of water. Where a
tightness and pressure verification. sealed system is installed, the water pressure should
be topped up and the system allowed to stabilise. The
The system must be filled with fluid category 1 water system will then be deemed to be at normal operating
direct from the water undertaker’s mains cold water pressure.
supply. It is usual to conduct the fill in stages so that
the filling process can be managed comfortably. There Once the filling process is complete, another thorough
are several reasons for this: visual inspection should take place to check for any
● Filling the system in a series of stages allows the
possible leakage. The system is then ready for pressure
operatives time to check for leaks stage by stage. testing.
265
Pressure testing procedures 1 When filling the system with water or other liquid,
‘walk’ the system continuously checking for leaks by
Pressure testing can commence when the initial fill to
the noise of escaping air or signs of liquid leakage.
test the pipework integrity has been completed. Again,
2 Release air from high points systematically up
on large systems, this is best done in stages to avoid
through the system.
any possible problems.
3 When the system is full of water, raise the pressure
to test pressure and seal.
The requirements of the British 4 Should the pressure fall, check that stop valves
Standards are not letting and then ‘walk’ the system again
BS EN 14336:2004, Heating systems in buildings. checking for leaks.
Installation and commissioning of water-based heating 5 When satisfied that the system is sound, have the
systems, is very specific regarding the testing of central test witnessed by, for example, the clerk of works, the
heating systems. It states: client’s representative, and obtain relevant signatures.
The heating system shall be pressure tested to
a pressure at least 30 per cent greater than the The requirements of the Water
working pressure for an adequate period, as Regulations
a minimum of 2 hours duration. A suggested In most domestic situations, pressure testing of central
method is given in Annex B. heating systems follows closely the requirements
of Water Supply (Water Fittings) Regulations.
Annex B of BS EN 14336
The procedure for this is given in British Standard
B.2.2 Hydraulic pressure testing BS EN 806. These documents suggest that the method
B.2.2.1 Preparations of testing should relate to the pipework materials
installed and give specific tests for both systems with
When preparing a hydraulic pressure testing, the metallic pipes and those with elastomeric (plastic)
following procedure should be applied: pipes. This subject was covered in detail in Chapter 1.
1 Blank, plug or seal off all open ends.
2 Remove and/or blank off vulnerable items, fittings Planning the test
and plant pressure switches and expansion bellows.
Before the test is conducted, a risk assessment should
3 Close all valves at the limits of the test section of
be carried out. Pressure testing involves stored energy,
the pipework. Plug the valves if they are not tight, or
the possibility of blast and the potential hazards of
could be subjected to vibration or tampering.
high velocity missile formation due to pipe fracture and
4 Open all valves in the enclosed test section.
fitting failure. A safe system of work should be adopted
5 Check that all high points have vents, and that these
and a permit to work sought where necessary. Personal
vents are closed.
protective equipment should also be used.
6 Check that the testing pressure gauge or manometer
is functioning, has the correct range and has been The following factors should be carefully considered:
recently calibrated. ● Is the test being used appropriate for the service and
7 Check that there are adequate drain cocks, a hose is the building environment?
available and that it will reach from the cocks to the ● Will it be necessary to divide the vertical pipework
266
● Are there enough operatives available to conduct 7 Refit any vulnerable pieces of equipment,
the test safely? components and appliances.
● Can different services be inter-connected as a
temporary measure to enable simultaneous testing? The flushing requirements
How long will it take to fill the system using the
of central heating systems
●
267
correct size fuse of 3 amps has been used in the radiator valves. Mineral oils can also lead to eventual
switched fused spur. pump failure. Flux residues lead to corrosion of the pipe
● Ensure that the fuel supply to the boiler has been and fittings, especially in those systems using copper
tested in line with the regulations in force and that tubes. The risk of failures is eliminated by the use of a
it has been turned on. chemical cleanser which is administered in accordance
● Ensure that all radiator valves are open to allow with the recommendations in BS 7593:2006. The
water circulation to take place. cleanser should then be circulated around the system for
● Ensure that all thermostats are calling for heat. a period of one hour with the boiler on, after which the
system should be drained down and the system flushed
When the system has reached temperature, it should
to remove the cleanser until the water runs clear.
be switched off and completely isolated from the
electricity and gas/oil supplies to prevent accidental
operation of the system and drained down whilst the
water is still hot.
268
can cause major problems with loss of boiler efficiency, water containing an acid is harmful to the environment
boiler noise and component failure. and causes major problems for water undertakers
when discharged down a drain or sewer. A neutraliser,
System corrosion and scaling is prevented by adding a
administered through either the F and E cistern,
central heating inhibitor to the system water via the
injected through a radiator or via a power flushing unit,
feed and expansion cistern in open vented systems or
will pacify the effects of the cleanser on the inside
via a radiator in sealed systems. Approved Document
of the system, neutralising its effects. The system
L of the Building Regulations stipulates that where the
should be thoroughly flushed and the water tested
water undertaker’s cold water main exceeds 200 ppm of
to ensure that the system is free of both acid cleaner
calcium carbonate, the feed water must be chemically
and neutraliser. An inhibitor can then be put into the
treated to reduce the rate of limescale accumulation.
system once the system has been flushed through.
To be completely effective, the inhibitor must be
administered at the correct dosage. If not enough
inhibitor enters the system, then its protection will be
diminished. A 1-litre bottle of inhibitor is enough for a
ten radiator system with a water content of 100 litres.
One radiator = 10 litres. Double panel radiators count
as two radiators.
Power flushing
When replacing boilers, or dealing with blocked
pipework or radiators, a power flush may be required
to remove any sludge within the system. In most cases,
where a new boiler is being installed, a power flush is
Figure 3.53 System inhibitor required as part of the warranty.
269
270
The table shows the record for just one room. Each 14 Repeat 11, 12 and 13 until all radiators are fully hot
room would require the same table. and the temperature differences are as near to 10 °C
as possible.
The balancing process 15 Adjust the boiler temperature to give a flow
1 Record the initial TRV and lockshield valve settings temperature of 80 °C. Then, adjust the pump speed
of all radiators. Also record the room thermostat to give a temperature difference of 10 °C across the
temperature, the boiler temperature setting and the radiator flow and returns. Caution must be exercised
pump speed. here as altering the pump speed may mean that
2 Open all zone valves. points 12 and 13 may need to be repeated to give
3 Open all TRVs fully. the correct temperature difference.
4 Open all lockshield valves fully. It is important that 16 Adjust all TRVs to give the desired temperatures
you record how many turns it takes to open the in all rooms. This is best done over several days as
lockshield valves from fully closed to fully open. rooms often take time to warm up and cool down.
5 Set the room thermostats to maximum. 17 Now, set the room thermostats to the desired
6 While the system is off and cold, bleed all radiators temperatures.
to remove any air. 18 Turn the boiler down to the lowest setting needed
7 Check and reset, if necessary, the system pressure. to maintain the temperatures required. It can always
8 Turn on the boiler. be increased later if needed.
9 As the system begins to warm up, visit each radiator 19 Measure and record the flow and return
in turn and check which is the flow and return of temperatures at the boiler. This information should
each radiator. Make a note of which radiators get be kept with all other system records to assist in any
hot first. fault-finding procedures in the future.
10 While the system is warming, turn down the
lockshield valves of the radiators that are heating Dealing with defects with
up the quickest half way so that the cooler radiators
catch up. This gives an approximate balance.
central heating systems
11 Now let the system stabilise for about an hour. that are discovered during
12 Using an infrared thermometer, record the first
set of temperatures on the chart. Don’t forget to
commissioning
Commissioning is the part of the installation where the
calculate the temperature difference. This should
system is filled and run for the first time. It is now that
be about 10 °C but, as this is only the first set of
we see if it works as designed. Occasionally problems
figures it is unlikely to be so.
will be discovered when the system is fully up and
13 On the radiators with the smallest temperature
running, such as:
difference, close the lockshield valves a little,
● Systems that do not meet correct installation
recording how many turns were made. The radiators
requirements. This can take two forms:
with the highest temperature difference should be
● Systems that do not meet the design specification
left fully open.
– problems such as incorrect flow rates and
271
temperatures are quite difficult to deal with. If free. Manufacturing defects on fittings and
the system has been calculated correctly and equipment and damage sometimes cause
the correct equipment has been specified and leaks. Leakage due to badly jointed fittings
installed to the manufacturer’s instructions, and poor installation practice are much more
then problems of this nature should not occur. common, especially on large systems where
However, if the pipe sizes are too small in any part literally thousands of joints have to be made
of the system, then flow rate and temperature until the system is complete. These can often
problems will develop almost immediately be avoided by taking care when jointing tubes
downstream of where the mistake has been made. and fittings, using recognised jointing materials
In this instance, the drawings should be checked and compounds and using manufacturers’
and confirmation with the design engineer that recommended jointing techniques.
the pipe sizes that have been used are correct ● Poor balancing techniques – as we have seen, the
before any action is taken. It may also be the case correct balancing of a system is vital if the system
that too many fittings or incorrect valves have is to achieve the correct room temperatures in the
been used causing pipework restrictions. dwelling. Incorrect balancing often means that a
Another cause of flow rate and temperature well designed and installed system is incapable
deficiency is the incorrect set-up of equipment of achieving its true efficiency potential. A poorly
and balancing processes. In this instance, the balanced system will often lead to:
manufacturer’s data should be consulted and ● insufficient room temperatures
the point where the design is transferred from ● Defective components and equipment – defective
the drawing to the building. Poor installation components cause frustration and cost valuable
techniques can cause: installation time. If a component or piece of
● Noise – incorrectly clipped pipework can equipment is found to be defective, do not attempt
often be a source of nuisance within systems a repair as this may invalidate any manufacturer’s
running at high pressures because of the warranty. The manufacturer should first be
noise that it can generate. Incorrect clipping contacted as they may wish to send a representative
distances and, often, lack of clips and supports to inspect the component prior to replacement. The
can put strain on the fittings and cause the supplier should also be contacted to inform them of
pipework to reverberate throughout the the faulty component. In some instances where it is
installation, even causing fitting failure and proven that the component is defective and was not
leakage. To prevent these occurrences, the a result of poor installation, the manufacturer may
installation should be checked as it progresses reimburse the installation company for the time
and any deficiencies brought to the attention taken to replace the component.
of the installing engineer. Upon completion,
the system should be visually checked before Commissioning records for
flushing and commissioning begins.
● Leakage – water causes a huge amount of
central heating systems
damage to a building and can even compromise Commissioning records for large central heating
the building structure. Leakage from pipework systems should be kept for reference during
if left undetected causes damp, mould growth maintenance and repair and to ensure that the system
and an unhealthy atmosphere. It is, therefore, meets the design specification. Typical information that
important that leakage is detected and cured should be included on the record is as follows:
at a very early stage in the system’s life. ● the date, time and the name(s) of the commissioning
272
● the types and manufacturer of equipment and authority will notify if the work does not comply with
components installed the Building Regulations.
● the type of pressure test carried out and its duration
the type and quantities of any inhibitors and
●
INDUSTRY TIP
de-scalers administered
● the temperatures of the flow and return from the Notice should be given to building control not later than
boiler five days after work completion and until this is received no
● the balancing procedure and resulting temperature completion certificates can be issued.
differences of the heat emitters/radiators
● the expansion vessel pressure. Building Regulations Compliance
certificates
IMPROVE YOUR ENGLISH From 1 April 2005, the Building Regulations demanded
Clear and thorough completion of written records
that all installations must be issued with a Building
during initial installation will ensure the best course
of action can be followed later in the event of any Regulations Compliance certificate, issued by the local
repair work. Ask yourself – will this information be authority. This is to ensure that all Building Regulations
clear and legible for future engineers? relevant to the installation have been followed and
complied with.
At all stages of the installation from design to servicing manuals for the boilers, heat emitters and
commissioning, notification of the installation will need any other external controls, such as motorised zone
to be given so that the relevant authorities can check valves, pumps and temperature/timing controls
that the installation complies with the regulations and fitted to the installation
to ensure that the installation does not constitute a ● the commissioning records and certificates
273
The Energy Related Products Directive (ErP) sets new The position of these components is shown on the
efficiency levels for many energy related products. Its cutaway diagram of a combination boiler (Figure 3.57).
aim is to reduce carbon emissions from products that
consume energy. It came into effect on 26 September
Gas valve (hidden from
2015. The customer has no responsibility under ErP. Air pressure view under burner)
switch
ErP has two parts: Heat
● Ecodesign – this implemented new regulations for exchanger
274
The cooler return water typically enters at the bottom ● a gas regulator – this regulates the gas to the
of the heat exchanger and the heated flow water exits correct pressure for the burner
from the top. ● a solenoid valve – this opens when the appliance
calls for heat
Water-to-water heat exchanger ● a gas inlet pressure test point
Often called plate heat exchangers, these are ● a gas burner pressure test point
constructed from a number of corrugated plates – the ● a pilot flame adjustment screw (if applicable).
more plates that are sandwiched together, the better There are many designs of multi-functional control, and
the heat transfer. The plates provide two separated most are based on two specific methods of operation:
circuits for water to flow through. One circuit is ● controls fitted to boilers that have a permanent
connected to the primary system and is heated by the pilot flame and incorporate a thermoelectric flame
water in the primary heat exchanger. The other circuit failure device (thermocouple)
is connected to the mains cold water supply. ● controls that utilise some form of electronic ignition
As the cold water flows through the heat exchanger, and flame-ionisation flame failure system.
it is warmed instantly by the heated plates from the
primary circuit, thereby providing instant hot water to
Condense trap
the taps. A condense trap, or condensate trap, is fitted to
condensing boilers to collect the condensate that
Diverter valve forms as a part of the boiler’s operation, and to allow
In a combination boiler, the diverter valve is an a path for the condensate to evacuate from the boiler
electrically operated valve that provides a means of to the outside of the building via a drain or soakaway.
changing the direction of the flow of heated water Condense traps are usually made from moulded plastic,
produced by the primary heat exchanger. and often incorporate a siphon to maintain some
water in the trap at all times. The body of the trap has
When the boiler is in heating mode, the diverter valve an inlet from the boiler heat exchanger/combustion
allows water to flow to the heating circuit. When a chamber and an outlet to the drain.
hot tap is opened, a flow switch activates the diverter
valve to alter the flow of water through the plate heat Air pressure switch
exchanger to warm the flowing water to the hot tap. The air pressure switch uses pressure differential
caused by the running of the flue fan to activate a
Gas valve (multi-functional control) small micro-switch. Inside the air pressure switch is a
The gas valve, or to give its correct name, the multi- small diaphragm that moves due to the movement of
functional control, is a valve that incorporates many air caused when the fan starts. When the diaphragm
components in one unit: moves, it operates the small micro-switch that
● a filter activates the ignition sequence on the boiler. The air
● a thermoelectric safety shut off valve – this shuts pressure switch is usually connected to the fan and the
down the boiler in the event of pilot failure (if flue by rubber tubing.
applicable)
275
or poor servicing techniques. A simple omission, such and maximum settings to ensure that the boiler
as not administering inhibitor to the system at the shuts down satisfactorily.
commissioning stage, will, over time develop into a 5 Every radiator must be checked to ensure that it
major problem with black oxide sludge that could, achieves the correct temperature and that the
in severe cases, mean the system has to be de- temperature difference across the flow and return
commissioned, removed and re-installed. is within 10 °C ± 1 °C. Over time, as deposits
within the system form, openings of valves
In this part of the chapter, we will look at fault-finding
become narrower and this affects the balancing
procedures for central heating systems, the causes of
of the system. The system may need a complete
faults and, of course, their remedies.
re-balancing procedure depending on its age and
condition.
The periodic servicing 6 Linked to point 4, if the system balancing is out,
requirements of central check the condition of the water. Initiate a test
to ensure that the system has inhibitor in it by
heating systems using a test kit like the example below. If too much
Central heating systems, like other plumbing systems sediment is detected, the system may need a
in the home, require a certain amount of periodic complete power flush.
maintenance to ensure a continued and efficient 7 Check the operation of the room thermostat and
operation. Most servicing techniques centre around cylinder thermostat. Take a water temperature
the appliance and its correct operation. In reality, reading and, if possible an air temperature reading.
though, this is only part of the story. For a central 8 Check the system for signs of leakage. Repair any
heating system to be properly serviced, there are leaks that may be present on the system.
many points and NOT just the boiler that need to be 9 The customer should receive a boiler servicing
looked at: report on the checks carried out and their findings.
1 Talk to the customer and ask if there have been any The benchmark service log book should also be
problems with the system. completed by a suitably qualified gas safe registered
2 The boiler is the centre of the system. Without engineer.
it, none of the heat emitters will work. The boiler
must be thoroughly serviced in accordance with the
IMPROVE YOUR ENGLISH
manufacturer’s instructions by a gas safe registered
Communicate with your customer in the first instance
engineer. The flue gases must be analysed for the – they will be your first source of information on any
correct CO2 content and the appliance case checked developing or persistent problems.
to ensure a correct seal.
3 The system must be run and the temperatures of
the flow and return at the boiler checked to ensure Obtaining details of system faults
that the temperatures and subsequent temperature from end users
difference across the flow and return are within
When identifying faults that have occurred on central
manufacturer’s data. This is crucial for condensing
heating systems, the customer can prove an invaluable
appliances as the boiler will not go into condensing
source of information as they can often describe
mode without the correct temperature difference.
when and how the fault first manifested itself and any
4 Linked with point 2, check the correct operation
characteristics that the fault has shown.
of the boiler thermostat to ensure it operates with
acceptable limits. It should be checked at minimum
276
A replacement parts list will also be present for those dismantling and reassembly).
components that can be replaced. When ordering parts,
277
● Checking for correct operation of system often display an incorrect pressure. They should
components: be replaced as necessary.
● Thermostats – can be checked using a ● Checking for correct operation of system safety
thermometer in the hot water flow once the valves:
thermostat has shut off and against the surface ● Pressure relief valves – can be checked by
of the radiator. This will indicate whether twisting the top and holding the valve open for
the thermostat is operating at the correct 30 seconds. Always ensure that the valve closes
temperature. completely and that the water stops without any
● Thermostatic radiator valves – should be drips.
checked to ensure that they have not stuck in ● Checking for blockages in heat emitters – if a
the closed position. TRVs that stick could indicate radiator only gets hot at the top and down each
either potential TRV failure or system debris side, it is probably blocked with black oxide sludge.
holding the valve closed. Black oxide sludge collects in low spots on the
● Motorised valves – should be activated to system, especially radiators and circulating pumps.
ensure that they are operating in line with the Being metallic in nature, the sludge is also attracted
system thermostats. to any electrical component that emits a magnetic
● Pumps – these should be checked using the field. Radiators can be removed and flushed out but
manufacturer’s commissioning procedures to this will only be a temporary solution. The problem
ascertain whether the pump is performing as the is system deep and requires further investigation.
data dictates. A slight fall in performance is to be It could even be the system design that is causing
expected with age. Check to ensure: the fault. One solution is to initiate a full system
● there no signs of damage or wear and tear on power flush using a sludge remover and then treat
the pump the system with inhibitor but the root cause of the
● there are no signs of leakage from the pump problem must be investigated if a total cure to the
● that there are no unusual noises or vibrations problem is to be found.
when the pump is operating.
● Timing devices – time clocks can be checked HEALTH AND SAFETY
to see if they activate at the correct time and Caution should be exercised when checking for
that any advance timings such as 1-hour boost system air, especially when bleeding the radiator as
buttons, work correctly. The time display should hydrogen is highly flammable!
be checked against the correct time of the check
and any alterations to the time made. Should any components require replacing, they should
● Expansion vessels – should be checked for
be replaced with like-for-like components or, if this is
the correct pressure using a portable Bourdon not possible, check with the manufacturers that the
pressure gauge. The type used to check tyre part is approved for use with the system.
pressures is ideal for this. Any signs of water
leakage should be investigated. Always refer to Methods of repairing faults in central
the manufacturer’s instructions for the correct heating system components
charge and pre-charge pressures.
Repairing system components should be undertaken
● Feed and expansion cisterns – check that the
using the manufacturer’s servicing and maintenance
float operated valve has not stuck in the off
instructions, as these will contain the order in
position and that the vent pipe terminates above
which the component should be dismantled and
the water line. Check that the feed pipe is clear
re-assembled. As with all components, there will be
of any debris.
occasions when it cannot be repaired and replacement
● Gauges and controls – gauges are notorious for
is the only option. Some of the components that may
requiring replacement or re-calibration as they
be repaired and/or replaced are listed in Table 3.26.
278
280
281
If a faulty expansion vessel is diagnosed, the system should be isolated and temporarily decommissioned until a replacement vessel is obtained
and fitted.
282
Table 3.28 Filling loop fault finding (this assumes that the filling loop has been left connected)
Pressure gauge a terminal 1 does not become live when calling for
If a fault with the pressure gauge is suspected, simply hot water, or
tap the front of the gauge to see if the needle moves. If b terminal 2 does not become live when satisfied
the gauge continues to give a false reading, replace the (terminal C must be live in both cases).
pressure gauge.
Room thermostat
Control components 1 Make sure the terminals have been wired correctly:
a Disconnect terminal 3 while the checks are
Control components include motorised valves,
taking place. This will prevent false readings due
thermostats and time clocks. These are best diagnosed
to backfeed.
through the system type. In other words, the type of
b Remove wire from terminal 3.
system may dictate the diagnostics that are performed.
c Make sure terminal 1 is live.
d Turn the room thermostat to call for heat, if
KEY POINT
live is not detected on terminal 3 then the
Remember the fault-finding rule with controls – first,
thermostat is faulty.
check that you have wired the system correctly!
Only start suspecting component faults when you Mid-position valve – Y-plan system
are sure that the system is correctly wired.
The valve is faulty if the valve does not operate as
described in the following checks. The checks should be
Cylinder thermostat
made in the correct order, from 1 to 6.
1 Make sure that the terminals have been wired
correctly: Valve is open for heating only:
a Terminal C (common) is the left-hand terminal. 1 a Switch off the electricity supply.
b Terminal 1 is the middle terminal. b Disconnect grey and white wires from
c Terminal 2 is the right-hand terminal. appropriate junction box terminals.
2 Disconnect terminals 1 and 2 while the checks are c Reconnect both grey and white wires to
taking place; this will prevent false readings due to permanent live terminal in junction box.
backfeed. The cylinder thermostat is faulty if: 2 a Switch on the electricity supply. The valve should
move to the fully open heating position at port A.
283
b The motor should stop automatically when 2-port motorised zone valve – S-plan and
port A is open. The valve should remain in this S-plan plus
position as long as electricity is applied to white Zone valves on S-plan systems are faulty:
and grey wires. ● if the motor fails to operate when live is applied
c With port A fully open, the orange wire to the brown wire and neutral to the blue wire
becomes live to start pump and boiler. This can (motor can be viewed with valve cover removed)
be checked by feeling port A heating outlet is – the motor should stop automatically when the
getting progressively hotter. valve is fully open and will stay in this condition as
Valve is open for domestic hot water only: long as live is applied to the brown wire; the valve
3 a Switch off the electricity supply. automatically closes under the spring return when
b The valve should now automatically return to live is removed from the brown wire
open the domestic hot water port B. ● the orange wire only becomes live after the valve
c Heating port A should close. has fully opened (make sure the grey wire is live)
4 a Isolate grey and white wires and tape over them ● if the boiler continues to run when the cylinder
pump should start. This can be checked by feeling ● Disconnect the brown wire to the valve and
port A heating outlet and B hot water outlet to terminate safely by taping it over.
see if they are getting progressively hotter. ● Disconnect the white wire and reconnect it to the
6 a Switch off the electricity supply. permanent live terminal at the wiring centre.
b Reconnect white and grey wires to their junction ● Disconnect pump live connection at the wiring
is elsewhere in the circuit. remain in the closed position. The orange wire
should become live and the boiler should fire.
284
285
286
CH HW
2-port 2-port
zone valve zone valve
Fused spur
L N E
C/S
R/S
NOTE: Changes to cylinder stat
connections and addition of
HW OFF from timer
LINK
Boiler
CH R/S HW HW L N E sL
L N E C/S 9 10
ON ON ON OFF
Weather compensation
sL N
L N CH ON Outside sensor
HW ON
Time clock
HW OFF 'HW OFF' wiring centre
a Snail c Linear
b Bifilar d Series
287
9 What is the most efficient method of connecting 15 What standard outlines the commissioning
radiators to pipework? procedure for a central heating system?
a BOE a BS EN 806
b TBOE b BS EN 14336
c BBOE c BS EN 12828
d TBSE d BS EN 442
10 Where is the best place for an automatic bypass 16 Which of the following is NOT an advantage of
valve to be installed? underfloor heating?
a On the flow pipe immediately above the a Pipework is hidden
boiler b The system is efficient
b On the primary return after the circulator c Low maintenance
c Between the flow and return pipes near to d Suitable for existing properties
the hot water cylinder
17 Which of the following is NOT an advanced
d Between the flow and return pipes of the control installed with a central heating system?
index radiator
a Weather compensation
11 Where does the water system water flow to on
b Automatic by-pass
the ‘B’ connection of a three-port mid-position
c Delayed start
valve?
d Optimum start
a The boiler
18 How does a three-port divertor valve work?
b The hot water cylinder
a Central heating priority
c The radiators
b Timed priority
d Both the heating and hot water circuits
c Hot water priority
12 Which central heating system incorporates two
two-port valves to control the system water? d Equal system pressure
a S-plan system 19 What is the principal way in which a radiator
heats up a home?
b Y-plan system
a Convection
c C-plan system
b Radiation
d W-plan system
c Infrared
13 On a central heating system with a conventional
boiler, what is the recommended temperature d Conduction
difference between the flow and return 20 You are called to a customer’s property, where
pipework? a radiator fitted with a TRV is not getting hot.
a 25 °C What could be the problem?
b 20 °C a The circulator has failed
c 15 °C b The boiler has not fired
d 10 °C c The regulating pin in the head is stuck
14 What type of central heating system is filled d There is blockage in the return pipe
using a filling loop?
a Y-plan plus system
b W-plan system
c Sealed system
d Open vented system
288
21 What would be the primary symptom if a 26 Using the formula below, calculate the size
circulator were positioned immediately prior to of an expansion vessel required for a large
the open vent pipe? domestic central heating system containing
a Pumping over 200 litres of water.
b Over heating V= eC
c Restricted heating 1 - P1
P2
d Positive pressure
Where:
22 What is required to be installed either side of a
circulator? V = the total volume of the expansion vessel
a Air release valve C = 200 l
b Isolators P1 = 1.5 + 1
c Zone valves
P2 = 6 + 1
d Lockshield valves
e = 0.0324
23 When replacing a synchron motor, what should
be your first course of action? 27 Calculate the air change heat loss of a dining
room measuring 4 m × 4 m × 3 m, when the
a Release the motor housing and pull the tab
outside temperature is −5 °C and the internal
connectors off
temperature is 20 °C.
b Isolate the electrics and check the supply is
28 What function does a weather compensator
dead
provide?
c Disconnect the wires, noting the connections
29 Where would a low loss header typically be
d Isolate the water for the boiler used?
24 To install an oil fired boiler, the competent 30 What is the basic difference between an S-plan
person is required to be registered with which system and an S-plan plus system?
organisation?
31 Describe the function of a low loss header in a
a OFTEC central heating system.
b NICEIC 32 List the advantages of an underfloor heating
c HETAS system compared to a conventional central
d Gas Safe heating system.
25 Which statement best describes a programmer? 33 Describe why air changes are a factor when
a A switched timer that controls the boiler selecting and designing a heating system.
b A controller that is designed to directly 34 Complete the following table for the faults and
activate the pump and boiler repairs that may occur on a central heating
circulating pump.
c A switched timer that independently controls
the hot water and heating systems Fault Symptom Repair
d A timer that activates the zone valves Broken impellor
Burnt out motor
Cracked case
Faulty capacitor
289
Plumbers all over the country will be working on By the end of this chapter, you will have knowledge
sanitation and rainwater systems which need to be and understanding of the following areas of
installed correctly, work efficiently and remove waste advanced sanitation and rainwater systems:
hygienically. This means a good understanding is l the legislation relating to the installation
required about the fundamental design and workings and maintenance of sanitation and rainwater
of these systems so that an informed discussion systems
can take place with the customer over the choice of l system layouts of sanitation systems
materials, components and layouts. It will also mean l design techniques for sanitation and rainwater
that the customer’s and installer’s health and safety systems
will be paramount whilst working on the system at l commissioning sanitation systems and
height or underground; whilst using some heavy components
materials and due to the nature of the foul water. l servicing and maintenance of sanitation and
rainwater systems
A well-designed, installed and maintained system
l diagnosing and rectifying faults in sanitary
will result in a satisfied customer who will be much
systems and components.
more likely to offer repeat trade.
You can revisit Book 1 to remind yourself of the In Book 1, Chapter 9, we covered:
basics of sanitation and rainwater systems. In Book 1, l sanitary pipework and appliances used in
Chapter 8, we covered: dwellings
l understanding layouts of gravity rainwater systems l installing sanitary appliances and connecting
l installing gravity rainwater systems pipework systems
l understanding maintenance and service l service and maintenance requirements for
requirements of gravity rainwater systems sanitary appliances and connecting pipework
l decommissioning rainwater and gutter systems systems
and components l the principles of grey water recycling.
l performing a soundness test and commission
rainwater, gutter systems and components.
290
KEY TERM
Equilibrium: when referring to drainage systems p Figure 4.1 Plumber talking with customer
this relates to keeping the air pressure even within
the system, so that any negative pressure or
pressure fluctuation does not cause any trap seal
loss and therefore the ingress of foul air in to the
property.
291
INDUSTRY TIP
You can access the data of approved Building Regulations
at: www.gov.uk/government/collections/approved-documents
requirements
KEY POINT
l Part 2 Sanitary pipework including layout calculations
You should have read Book 1, Chapter 9, which
l Part 3 Roof drainage and layout calculations
covers all the basic information for drainage.
l Part 4 Waste water lifting plant
l H3 Rainwater drainage
292
filled branch discharge pipes which are designed with a l lengths of waste run
filling degree of 0.5 (50 per cent) and are connected to l occupancy.
293
Shower
50 mm parallel
junction to avoid
cross flow
40 mm dia 40 mm dia
32 mm dia
Sink
WB WC
Rodding eye
To sewer
294
Rodding eye
To sewer
295
WB
Dimensions and WC
distances of Bath
appliances and Bidet
waste pipework
from the soil stack.
Shower
32 mm
waste 1.7 m
40 mm
waste 3.0 m
50 mm
waste 4.0 m
100 mm Sink
waste 6.0 m
WB WC
Waste pipes
50 mm parallel 3m
40 mm
waste 3.0 m junction to avoid
cross flow
50 mm
waste 4.0 m
40 mm dia 40 mm dia
32 mm dia
100 mm Sink
waste 6.0 m
WB WC
Waste pipes 3m
1.7 m
All of the measurements above will be 3m
drastically reduced if bends are introduced 6m
to change direction or the gradient on the Washing m/c 75 –100 mm dia
branch discharge pipework is too steep. Large radius
or dishwasher 450 mm min.
bend
p Figure 4.10 The maximum branch pipework diameters, lengths, gradients and trap seals on a ventilated stack system
296
Branch connections 60
Pipe size Maximum Approximate
(mm) length (m) gradient (mm/m) 40
32 1.7 22
32 1.1 44 20
32 0.7 87
40 3.0 Between 18 and 80
0.5 0.75 1.0 1.25 1.5 1.75
50 4.0 Between 18 and 80 Length of branch (m)
100 6.0 Minimum 18
p Figure 4.11 Gradient graph for a 32 mm wash basin waste pipe
Whenever the pipe lengths shown in Table 4.1 are
exceeded, the waste pipe diameter should be increased KEY POINT
to the next size up. The graph clearly shows that if the gradient of
fall is increased, then the length of waste pipe is
By using the graph in Figure 4.11, showing 32 mm reduced accordingly.
waste pipe, it can be seen that if the gradient changes
297
1E xcluding the ‘connection bend’ fitted directly or close to the trap Operating principle of an AAV
outlet.
2 If no longer than 3 m, this may result in noisy discharge, and there The valve incorporates a sealing diaphragm which
will be an increased risk of blockage. lifts and allows air to be drawn into the system when
3 Should ideally be as short as possible to limit deposition problems.
4 Sweep bends should be used: not ‘knuckle’ bends.
subject to negative pressure. Once the negative
5 For up to 7 people: longer slabs should have more than one outlet. pressure has ceased – equilibrium – the pressure on
6 Includes small potato-peeling machines. the diaphragm returns to the closed position thereby
7 Wash basins must not be fitted with outlet plugs. preventing any escape of foul air into the building.
Some AAVs have a spring to return the diaphragm to
ACTIVITY the closed position. The AAV is designed to open and
When you are next on site, identify the design of soil
close spontaneously when required allowing a supply
stack used for various styles of buildings including
larger and non-residential properties; or as a learner of air to adequately ventilate the system to ensure a
group walk past nearby buildings and carry out a smooth discharge.
similar survey. Photograph them and discuss their
An AAV enables ventilating pipes to be terminated
installation on return.
inside a building, which eliminates the need for a vent
These drainage systems will connect in to differing pipe to penetrate a roof and so offers flexibility in the
underground systems according to the location and age design of new systems. Bear in mind that an AAV is
of the property. The design of the underground system NOT a substitute for a ventilation stack; wherever an
can be identified by a site survey or by contacting the AAV is installed the system at some point must have
local authority. The three main types of underground an open vent to outside air – a ventilating pipe should
drainage systems are fully outlined in Book 1, Chapter 9: be provided at or near the head of each main drain.
l An AAV should not be used if the soil stack provides
l separate system
298
KEY POINT
Rubber
connection
An air admittance valve provides a means of
ventilation to a drainage system under conditions
of reduced pressure when ventilating pipes are
terminated inside a building in accordance with
BS EN 12056.2:2000.
p Figure 4.13 Cut away AAV
l Where a drain serves more than four properties l if there are between 11 and 20 properties
with AAVs, like a housing estate, then: then ventilation is required at the head, foot
l if there are between 5 and 10 properties and mid-point of the drain run.
ventilation is required at the head and foot
of the drain run
6 2 6 6
4 4 4
3 3 3 3
4 4 4
4 4 1 4
5
5 Inspection covers 5
are at ground level
Primary ventilated system configuration
1. Floor gully 2. Air admittance 3. Stack 4. Branch discharge 5. Drain lid 6. Stack vent
valve pipe (mid and ground level)
6 6 6
2 2
4 7 8 7 8
3 3 3 3
4 4 8 8
4 8 4 2 4
1
5 5
5
Inspection covers
are at ground level
p Figure 4.14 Illustrations from BS EN 12056 to demonstrate the installation variations for AAVs
300
5.0 m maximum
correct installation.
Inlet
Asphalt or cement
Different types of AAVs mortar
There are many different applications and pipe sizes
for AAVs which give the plumber a variety of options
when specifying and installing.
Puddled clay
The working principle and
layout features for foul tanks
in sanitary systems p Figure 4.15 Cesspool
Building Regulations H2 should be sourced and It is important that customers are informed that
referenced for the design and installation requirements. cesspools require emptying on a regular basis to
prevent the unit from overflowing. This process must
Cesspools be carried out by a drainage contractor who will use
In rural areas many homes and buildings are self- the principle of mechanical suction to draw the waste
contained; the combined waste ends up in a local into the vehicle. Older cesspools were designed with an
cesspool, septic tank or treatment plant. These have NO overflow, but these now no longer conform to current
connection to the public sewer system and are known requirements.
as off-main. A cesspool is also known as a cesspit. Leakage is another problem which is more common with
A cesspool is an underground tank that stores the brick-built units, due to the fabric and structure breaking
sewage until the time of disposal. The design of a down, which would lead to the ingress of groundwater
cesspool will incorporate an inlet pipe but no outlet and the leakage of foul water. This will result in foul
pipe, as the cesspool only collects the waste until it is smells and pollution of the surrounding area. The use of
disposed. Older cesspools were made from brickwork, cesspools is no longer an option in most instances.
but modern ones are made from glass-reinforced
plastic (GRP) – fibre glass. Septic tanks
A septic tank is a multi-chamber storage tank allowing
Cesspools must be constructed so they are watertight
liquid and solid waste to separate. The liquid is allowed
to prevent any leakage of foul water or the ingress of
to flow out of the tank and be disposed of separately.
surrounding groundwater.
The sewage enters the settlement chamber, allowing
KEY POINT the solid waste (sludge) to sink to the bottom and the
Ingress in this context describes the action of, liquid to rise to the surface. The surface liquid is in
or fact that, foul water from the cesspool has contact with oxygen and the organic material starts
entered the groundwater and contaminated it. to break down biologically. This liquid still contains
some sewage but only in small enough particles to be
carried away through the discharge outlet and into the
ground (soakaway).
301
(Approved Document H)
p Figure 4.17 A section showing the inside of a basic septic tank
l the installation will not contaminate any ditch,
Scum
1.5 m
Inlet manhole
Concrete base
Sludge
Dip pipes
Inlet manhole
302
It is very important to consult with the building control 3 Refill with water and observe the time taken to
officer from the local authority prior to any installation. drain from 75 per cent full to 25 per cent full
A proper survey of the area and ground type will also (which is 150 mm of water).
need to take place; this will include a soil porosity test. 4 Divide the time by 150 (150 mm).
The following procedure will need to be adopted: 5 The answer will give the average time in seconds
1 Excavate a hole 300 mm × 300 mm × 300 mm (Vp) required for the water to drop 1 mm.
below the proposed invert level of the land drain. 6 Repeat the exercise two more times in at least
2 Fill the hole with water and allow it to drain away two trial holes.
overnight.
Table 4.3 A chart used to help installers work out the suitability of land drainage
p Figure 4.18 A section of land prepared to receive discharge from a septic tank
303
The average time for drain away can be calculated by A sewage treatment plant is ideal for a location where
referencing the table to work out the length of drain there will be a discharge or sub-surface irrigation or to
run required for various capacity tanks. Drainage field a suitable watercourse (which has been approved by
disposal should only be used on test values between 15 the regulator) and where a septic tank will not meet
and 100. Where the Vp value is outside these figures, the required standard.
technical advice should be sort from the supplier.
Reed bed
A reed bed is only required when local water authorities
request a better quality of effluent than that being
discharged from a standard unit.
KEY POINT
A reed bed is a natural filtration process which is
more aesthetically pleasing. Oxygen from effluent
is transferred from leaves down through the reed
stem and out via its root system in the gravel bed.
friendly
l they significantly improve the discharge from a
treatment plant.
800
Outlet
from
treatment
2500
plant
800
304
KEY POINT
If a macerator is installed, Building Regulation
Part G requires that a gravity WC MUST be
Pipe carrying effluent located in the same building.
305
Vertical before
horizontal within
300 mm of unit
Normal
gravity
fall
306
22 mm copper pipe
l The ground above is not subject to heavy Installation options need to be considered at the design
wheel loads. stage and are often outlined in the manufacturer’s
l The pipe is insulated to protect against frost. instructions. The instructions may offer two or three
l If the pipe is laid within 450 mm of the ground installation options that could be considered.
level, either concrete casing or paving slabs should
protect the pipe.
Electrical connections
Installation options Full details of how to connect the macerator to the
electrical supply will be outlined in the manufacturer’s
It is normal practice to position the macerator unit
instructions. The macerators require an unswitched
directly behind and connected to the WC. However, it
fused spur connected with a 5 amp fuse. The
is possible to position the unit a short distance away
connection can be to a spur which is connected to
from the WC (for example, the other side of a wall). The
the ring main circuit.
extension should be no longer than 150–200 mm
long – extensions longer than this tend to cause
blockages. Always check for leaks at every joint and HEALTH AND SAFETY
never install the unit underneath the floor. Safe isolation is essential if you are working on any
electrical appliance. The full safe isolation procedure
Macerators are often installed behind a panel for is outlined in Book 1, Chapter 1.
aesthetic reasons. If this is the case, make sure the unit
307
Principle of operation
The WC discharges into the macerator drum. A float
or diaphragm switch rises and starts the motor. The
motor has stainless steel blades attached to the
FUSE
Connect with unswitched rotating spindle which breaks up any solids entering the
fused spur with 5 amp fuse macerator drum area and suspends the solid in liquid.
This transformed mass is then positively pumped to the
outlet at a higher part of the unit and into a vertical
pipe through a non-return valve into the discharge
pipe. The discharge pipe then runs horizontally with a
minimum of 1:200 fall to the soil stack. Figures 4.27
p Figure 4.26 Fused spur
to 4.29 show the mechanical sequence of operation.
Discharge pipe
Air valve with charcoal filter
(closed when macerator is
not operating to prevent
escape of odour) Outlet from
WC enters here
Shredder
blades
Backflow
valve
Electric
pressure
switch Motor
(inside base
of unit)
Bath/basin Bath/basin
inlet pipe Inlet control Switch Discharge pump Inlet control inlet pipe
valve operating impeller valve
diaphragm
308
Air valve
(remains closed) Outlet from WC
begins entering
Rising
water
level
Waste
discharging
Rising
water
level
(falls back
to lowest
level on
completion
of discharge)
309
310
but much smaller volume. This option offers versatility The installation of a waste water lifter can be below
when specifying and installing therefore impacting on or on the same finished floor level of a property.
the overall cost of a project. These units can reliably The discharge pipe enters the soil stack and forms a
discharge domestic waste water with a pH4–pH10 backflow loop, as shown in Figure 4.34. The vent pipe
value containing fibres, textiles and faeces. must discharge in accordance with BS EN 12056.1
for faecal lifting plants to above roof level to avoid the
BS EN 12056 Part 4 gives guidance on the types of
ingress of foul smells in to the property.
waste water lifting plant and discharge pipework.
Table 4.4 Minimum size of discharge pipe in accordance with KEY TERM
BS EN 12056.4 Backflow loop: prevents backflow. See Figure 4.34,
where the backflow loop rises above the mains
Type of wastewater lifting plant Minimum size of
sewer and drops into the top of the pipe.
discharge pipework
Non-macerating faecal lifting plant DN 80
to prEN 12050-1 Lifting units
Macerating faecal lifting plant to DN32
prEN 12050-1
AAVs cannot be installed on the discharge pipework.
These lifting units are designed to lift waste water
Faecal-free lifting plant to prEN DN32
12050-2 from below the sewer level in a property and then
Non-macerating faecal lifting plant DN25 discharge into the sewer system. They combine pumps,
for limited applications to prEN tanks and controls in one self-contained unit to ease
12050-3 installation and maintain reliable operation. They
Macerating faecal lifting plant DN20 include cabling, sensors and hoses. These units have
for limited applications to prEN a sloping tank bottom design to ensure that dirt and
12050-3
solids are guided towards the pump at all times. The
If the building is located far away from the main sewer, aim is to minimise sedimentation and reduce the need
for example in a rear housing situation or when the for tank cleaning.
use of gravity is impossible, a pumping station could
provide an ideal solution against having to excavate
the land, which would be costly.
311
KEY POINT
The permanent level control is a device which
triggers an alarm in the event of high water levels.
312
p Figure 4.37 A waste disposal unit fitted to the base of a sink unit
ACTIVITY
The process turns anything in the unit into a paste
Use manufacturer’s instructions and the internet
solution and water flushes it into a drain via a 40 mm to compare the advantages and disadvantages
waste outlet. The electric motor that turns the rotor between waste water lifters and macerators in a
where the blades are attached is located at the base of domestic and then a commercial installation.
the unit. The motor on the unit should be connected
to an electrical supply via the correctly sized fuse
spur, typically 10 amp, but will be specified in the HEALTH AND SAFETY
manufacturer’s instructions. Manufacturers often Care should be taken when servicing these
require the circuit to be protected by a 30 mA RCD. appliances; it is important to ensure you are fully
trained and aware of the manufacturer’s servicing
procedures. The units will be supplied with a special
release tool for the blades, should they become
trapped. The device must have some form of
accessible thermal trip cut-off device that will turn
off the unit in the event of blades jamming or no
water flow.
KEY POINT
The device MUST have some form of accessible
thermal trip cut-off device that will turn off the
unit in the event of blades jamming or no water
flow.
p Figure 4.38 Fused spur
313
Wet rooms
A wet room is a waterproofed (tanked) area which is
usually equipped with a walk-in shower, and therefore
the room itself becomes the enclosure. A wet room
can be fitted out with standard or specialist equipment
to suit the customer’s requirements, so it is very
important to discuss with the customer prior to
designing a wet room to get a complete understanding
of what is required. The drain point is inset into the
floor area which has a gently sloping floor draining the
water towards the drain point (this is instead of the
shower tray).
314
illustrations give some indication, but in all cases the grate which will accommodate the flow of waste
the manufacturer’s instructions MUST be read and water. The trap is connected under the grate and then
followed at all times. flows to the soil stack. Figures 4.41 and 4.42 show one
style of installation method and design for wooden floors
The built-in fall is designed to drain the water towards
which is adapted to suit solid floors as well.
the outlet. There are two main options for the location of
Reinforcement
on back of wall Tiles/tiled bricks
Tile mortar
Wall membrane
Reinforcement
Fastening Floor membrane
Wall flange Grate Tile mortar
Frame Tiles/tiled bricks
Grate removed
Strainer
Reinforcement
Drain unit
Water trap
Outlet unit
Batons Joists
315
UniSlope®
Joists
Classic Square
Column Stripe
316
317
overlaps also apply to a cloakroom and downstairs WC. p Figure 4.47 Overlap – provision in a downstairs WC
ACTIVITY
600 mm When looking at bathroom designs you will now
700 mm
be able to determine if the spacing requirements
800 mm 700 mm
are sufficient, especially in smaller areas. Use your
1000 mm
1100 mm knowledge and reference BS 6465 to design a
Hand rinse
wash basin
Domestic wash basin Bath bathroom layout and WC to a dimension given by
your tutor.
400 mm
Fire stop arrangements
600 mm 600 mm
700 mm
900 mm
Whenever a soil or vent pipe penetrates a wall or a
800 mm 800 mm
900 mm ceiling an intumescent collar is fitted around the soil
Bidet WC Enclosed shower tray Unenclosed shower tray
pipe to prevent the risk of smoke and fire spreading
p Figure 4.45 Provision of space for sanitary installations between areas.
318
KEY TERM
PVCu (unplasticised poly vinyl chloride): a common
material used in rainwater guttering and pipework
systems.
Discharge pipe
Non-combustable Mineral wool with
sleeve wire binding Fire resisting floor
319
The Building Regulations Approved Document B3 gives l the provision, or lack of a ventilating pipe
an example, showing a range of different applications l surcharging of the drain
of fire stopping. l provision, or lack of an interceptor trap.
If a material, such as a timber suspended floor, is Therefore, when sizing drainage systems we must
penetrated by an incorrectly installed heating appliance refer to BS EN 12056 and the following pipework
flue pipework which did not have the required air gap, dimensions (Table 4.6) in relation to appliances in
then the adjacent material could become pryolised the UK.
and its ignition temperature could be significantly Table 4.6 Pipework dimensions showing waste pipe diameter
reduced, and as a result create a weak point where and appliances
fire could spread.
Waste pipe Appliance
size (mm)
KEY TERM
32 Wash basin, bidet, drinking fountain
Pryolised: when a material begins to decompose 40 Sink, bath, shower, urinal, sanitary towel
due to elevated temperatures. macerator
50 Food waste disposal unit, multiple appliances
320
Appliance System I (DU, l/s) System II (DU, l/s) System III (DU, l/s) System IV (DU, l/s)
Wash basin, bidet 0.5 0.3 0.3 0.3
Shower without plug 0.6 0.4 0.4 0.4
Shower with plug 0.8 0.5 1.3 0.5
Single urinal with cistern 0.8 0.8 0.4 0.5
Urinal with flushing valve 0.5 0.3 – 0.3
Slab urinal 0.2* 0.2* 0.2* 0.2*
Bath 0.8 0.6 1.3 0.5
Kitchen sink 0.8 0.6 1.3 0.5
Dishwasher (household) 0.8 0.6 0.2 0.5
Washing machine up to 6 kg 0.8 0.6 0.6 0.5
Washing machine up to 12 kg 1.5 1.2 1.2 1.0
WC with 4.0 I cistern ** 1.8 ** **
WC with 6.0 I cistern 2.0 1.8 1.2–1.7*** 2.0
WC with 7.5 I cistern 2.0 1.8 1.4–1.8*** 2.0
WC with 9.0 I cistern 2.5 2.0 1.6–2.0*** 2.5
Floor gully DN50 0.8 0.9 – 0.6
Floor gully DN70 1.5 0.9 – 1.0
Floor gully DN100 2.0 1.2 – 1.3
* Per person Use Table 4.9 to select the frequency factor for the use
** Not permitted
*** Depending on type (valid for WCs with siphon flush cisterns only)
of the appliances.
*** Not used or no data
Step 3
Use Table 4.8 (discharge units) to select the total
number of appliances running in to the stack. Qww is the expected flow rate of waste water in a part
System III is based on the British above ground or in the whole drainage system where only domestic
sanitation system as stated earlier. The next stage sanitary appliances are connected to the system.
is to add up the discharge units (DU) for these Where:
appliances.
Qww = K√ΣDU
Step 2 Qww = waste water flow rate (l/s)
Table 4.9 Typical frequency factors (K) K = frequency factor
Usage of appliances K ΣDU = sum of discharge units
Intermittent use, e.g. in dwelling, guesthouse, 0.5
office Use the formula to work out the waste water flow rate.
Frequent use, e.g. in hospital, school, restaurant, 0.7
hotel
Congested use, e.g. in toilets and/or showers open 1.0
to the public
Special use, e.g. laboratory 1.2
321
Step 4 Table 4.11 Hydraulic capacity (Qmax) and nominal diameter (DN)
for secondary vent systems
Table 4.10 Hydraulic capacity (Qmax) and nominal diameter (DN)
Stack and Secondary System I, II, III, IV Qmax (I/s)
Stack and stack vent System I, II, III, IV Qmax (I/s) stack vent vent
DN Square entries Swept entries DN DN Square Swept
60 0.5 0.7 entries entries
70 1.5 2.0 60 50 0.7 0.9
80* 2.0 2.6 70 50 2.0 2.6
90 2.7 3.5 80* 50 2.6 3.4
100** 4.0 5.2 90 50 3.5 4.6
125 5.8 7.6 100** 50 5.6 7.3
150 9.5 12.4 125 70 7.6 10.0
200 16.0 21.0 150 80 12.4 18.3
200 100 21.0 27.3
* Minimum size where WCs are connected in system II.
** Minimum size where WCs are connected in system I, III, IV. * Minimum size where WCs are connected in system II.
** Minimum size where WCs are connected in system I, III, IV.
Use the Qww (litres per second) to size the pipe from
Table 4.10. We tend to use swept entry fittings in the If the soil and waste system includes secondary
UK, but as you can see there is also a column for sizing ventilation, then Table 4.11 should be used.
square entry.
KEY POINT
The frequency factor is a variable that should be rate based on the frequency of use of the sanitary
used when determining the pipework system flow appliances for different building functions.
322
323
When carrying out the survey of the property, it The angle of the roof is a vital consideration when
would be wise to establish the type of drainage for designing a gutter system. The steeper the roof angle
the premises for the property and plan your system the faster the rain will flow off the roof, the shallower
around whether it is a combined, separate or partially the roof incline the slower the rain will flow off the
separate system and whether the local authority has roof.
any preference for connections. If a partially separate
BS EN 12056.3 gives the following formula to work
system is installed, check for any soakaways on existing
out the effective roof area.
remote downpipes.
Sometimes a new build extension will require a KEY TERM
rainwater system. This could be connected to an
Effective roof area: different to the actual size of the roof
existing system already installed on the premises. In
area. In effect it is the plan view area of the roof.
this situation a recalculation for the gutter size and
design may be required, to accommodate gutter
size and number of outlets for the additional flow of
L
rainwater.
W
Legislation relating to
design and installation of H
Rainwater drainage
l BS EN 12056.3:2000 Rainwater system design,
Calculating the size of a gutter To calculate effective maximum roof area (allowance
for wind), use the following formula:
To assess the suitability of a gutter system to drain the
roof on a building efficiently, the following factors need H
W + × L
to be taken in to account: 2
l the effective roof area to be drained Where:
l the local rainfall intensity
W = horizontal span of the roof slope
l the flow characteristics of the gutter system
324
Table 4.13 Multiplication factor for all roof pitches If the roof pitch is 45° then the roof area should be
multiplied by a factor of 1.5.
Type of surface Design in (m2) 102 m2 × 1.5 = 153 m2
Flat roof Plan area of relevant portion
Pitched roof at 30° Plan area of portion × 1.29
The manufacturer’s chart can now be used to select an
Pitched roof at 45° Plan area of portion × 1.50
appropriate gutter size and style for the installation.
Pitched roof at 60° Plan area of portion × 1.87
Pitched roof over 70° or any Elevation area × 0.5 The area of a flat roof should be considered as the total
wall plan area. When a roof is more complex with a range of
spans and pitches, then each individual area should be
The next stage is to include the factor for the correct calculated and added together.
roof pitch which can be selected from Table 4.14.
325
REA W
NA L
PLA p Figure 4.52 Elevation of a roof with a 75° pitch
326
(25 mm for every 15 m). This fall greatly increases the Rainwater
flow capacity. outlet
Another reason for the fall of 1:600 is so that the gutter Rainwater
outlet
will not fall too low at the end of the run. Brackets
should be installed at a maximum of 1.0 m intervals so
that it does not sway when filled with water, but holds Inspection
Surface water sewer
the fall. in the road chamber
327
1. 8m
KEY TERM
3m
Ratio: 1:600 means 1 mm fall for every 600 mm
length of gutter.
A
2. 4m 4m
By comparing the
IMPROVE YOUR MATHS
3m location of outlet
positions shown in
Work out the maximum fall for a gutter length of 3.2 m.
1, 2 and 3 it can
be seen how the
efficiency of the
guttering system
A C
Alternative position C: Here the single
outlet is equal to two outlets either
B can be affected.
4 COMMISSIONING
SANITATION SYSTEMS
end because of the outlet design
Example 3 shows that 3. 2m 2m 2m 2m
the outlets would only
AND COMPONENTS
have 1/4 of the flow to
manage and as a result 3m
the risk of flooding is
reduced.
KEY POINT
A B
Commissioning of rainwater systems was covered
p Figure 4.55 Outlet positions on a roof in Book 1, Chapter 8, so refer back to remind
yourself of information such as rainwater testing
By dividing the expected flow rate from the roof by the and maintenance.
flow rate of the outlet, you can work out how many
outlets should be installed. When doing this, always Like all newly installed systems sanitation systems will
refer to the manufacturer’s literature for their particular need to be commissioned. In other words, make sure it
flow rate. works and performs as expected. Some manufacturers
will outline a recommended commissioning procedure,
ACTIVITY but all will follow this basic outline.
Looking at Figure 4.54, discuss the important design
The correct procedures must be followed and there are
criteria and possible repositioning of the outlets.
several documents that must be consulted:
l BS EN 12056.2:2000
Changes in direction l Building Regulations Approved Document H
follows the roof profile, but they will affect the flow l Building Regulations Approved Document G
greater than 10°. A single 90° angle will affect the flow
rate by around 15 per cent, so the more there are in a Visual inspection
single run, the less efficient the flow rate will be.
It is important to check that all the connections are
When designing a gutter system, ensure you: properly fitted, such as push fit fittings are completely
l try to install straight gutter runs which offer the engaged and that solvent welded components are
maximum flow rate secure. It is essential that none of these components
l do not locate outlets near to a change in direction leak. The discharge pipework fall needs to be inspected
l apply the maximum fall ratio (1:600) where there and tested to confirm correct discharge.
are lots of bends
Clips are often overlooked, but must be inspected to
l install larger gutters where there are lots of changes
make sure the pipework is supported sufficiently, and
in direction.
the clips are anchored securely.
328
329
Water sucked
out of trap
330
331
4 Inspect the switching and setting controls in the and mould will start to show and the possibility of
collection tank. a foul smell may occur. The system will need to be
5 Inspect for water tightness. inspected and a soundness test may need to take
6 Carry out a functional test on the non-return valve. place to find the leak. Replacement of the seal or
7 Inspect the pipework support and clipping. part will need to take place.
8 Test the motor protection switch. l Blockages – this will be evident by a slow discharge
9 Check oil levels if required. from an appliance or a back-up of fluid in the
10 Ensure correct warning light function. appliance. Care will need to be taken with the
11 Check correct voltage. rectification of blockages. Look for any local access
12 Inspect hand pump if fitted. caps that could be removed to allow drain rods
access. The use of correct chemicals is an option,
Sink waste disposal unit maintenance but this will need to be carried out with care, after
These units are installed on specific sinks with fully reading the manufacturer’s instructions. It
89–90 mm waste holes. Care should be taken when could be as simple as just removing a trap and
servicing and maintaining these units. It is important clearing it, or as complicated as replacing a section
to be trained and fully aware of the manufacturer’s of the system.
procedures. The units are supplied with a specific tool l Inadequate support – this will be evident with the
to free the grinding blades should they become blocked. sagging of discharge pipes or easy movement of
The device will have a thermal cut-off device that will pipework. Broken supports or additional supports
trip in the event of the blades jamming. It is important can be installed.
to inspect the earth bonding, RCD and fuse sizes of l Broken pipework – this will be very evident with
these units. major leaks and smells. A section of the system will
need to be replaced and tested.
l Incomplete systems – this will only be found on
6 DIAGNOSING AND new builds where contractors have been changed.
A visual inspection of the property will need to take
RECTIFYING FAULTS place and discussion with your supervisor and the
IN SANITARY SYSTEMS l
site manager will need to take place.
Incorrect fall – the required fall of 2½–5° will give
AND COMPONENTS the correct self-cleaning discharge. If the fall is too
shallow, debris can remain in the discharge pipe,
Fault diagnosis and repairs to sanitation systems tend creating build-ups and then blockages. If the fall is
to be quite simple and can normally be rectified quite too steep, this can create siphonage and pull the
easily. Any fault on a system will generally be described trap seal out. A visual inspection of the system will
by a customer outlining the symptoms. This can be need to be made and an assessment made. This
followed up by a visual inspection which may need to could mean changing the design and fall of the
backed up with manufacturer’s instructions. Listen to the system or installing an anti-vac trap.
customer describe the symptom which will help in the
diagnosis. The customer will need to be informed of your Addressing faults in
findings, costs, time scale and any disruption that may
occur. With all work like this a risk assessment will need rainwater systems
to be made and the correct PPE will need to be worn. l Leaks – these may not be obvious to start with until
it rains, but over time there may be black/green
Addressing faults in moss growing on the side of the building. Leaks are
caused either by a seal being damaged or a crack in
sanitation systems the system. This can be rectified by replacing the
l Leaks – these will become obvious as the system seal or a section of the system.
is used and appliances discharged. Over time, moss
332
333
13 According to BS EN 12056, what gradient should 19 Which item is the correct electrical connection
the discharge branches of a solid stack be for a macerator unit?
normally kept between? a Switch fused spur with 10 amp fuse
a 0–2.5° b Switch and luminated fused spur with 10
b 2.5–5° amp fuse
c 3–6° c Unswitched fused spur with 13 amp fuse
d 5–10° d Unswitched fused spur with 5 amp fuse
14 What is the recommended discharge branch 20 When would a waste water lifter be used?
size for a kitchen sink? a When draining by gravity is not an option
a 20 mm b When the discharge into the system is high
b 32 mm c When the maximum flow capacity of the
c 40 mm system reaches 75%
d 50 mm d When a system includes a surface water
15 Which appliance does not have an overflow? discharge
a Shower 21 What safety cut-out device is incorporated into
a sink waste disposal unit?
b Bath
a Over load cut-out
c Sink
b Flow switch
d Basin
c Thermal cut-out
16 What is the maximum number of WCs that can
be attached to a 100 mm discharge branch? d Non-return valve
a 2 22 Which standard outlines the minimum space
requirements for each sanitary appliance?
b 5
a Building Regulations part M
c 8
b BS EN 6465
d 12
c BS EN 806
17 Which phrase best describes a septic tank?
d BS 8000
a An underground tank that stores the sewage
until the time of disposal 23 According to BS EN 12056, what should be fitted
when a pipe goes through a ceiling or floor to
b An underground tank that allows the sewage
another property?
to settle
a Non-return valve
c A multi chamber tank allowing the liquid and
solid waste to separate b Air admittance valve
d A multi chamber tank storing the sewage c Water trap
until the time of disposal d Intumescent collar
18 Which one of the installation factors is NOT 24 What size of waste pipe is required as a
associated with a WC macerator? discharge if multiple hand wash basins are
a Always use smooth bends connected together?
b Remember to re-burr any cut edges a 32 mm
c Gravity fall fills the macerator unit b 40 mm
d Only copper pipe is used for the discharge c 50 mm
d 100 mm
335
25 What is the formula for working out the effective 30 List and describe the four types of sanitation
roof area when designing a rainwater system? systems outlined in BS EN 12056.
H 31 List the regulative and guidance documentation
a �W + � × L
2 that would need to be referenced when
W designing and installing a soil stack at a
b �L + � × H
2 domestic property.
L
c �H + � × W 32 State the advantages of a reed bed if connected
2
to a septic tank.
W
d (H + L) × + 33 Describe why a macerator might be installed
2
behind a WC in a bathroom.
26 Which Building Regulation Approved Document
outlines foul water drainage? 34 Describe the use and function of an
intumescent collar.
27 Which pipe on a primary ventilated stack
system acts as the vent? Answers can be found online at
www.hoddereducation.co.uk/construction.
28 Describe the function of a permanent level
control in a lifting unit.
29 When designing a primary ventilated stack for a
domestic property, the installation must always
be designed to operate at what pressure?
336
Plumbing is a very diverse craft which often awareness of some of the electrical equipment and
encompasses electrical applications. For example, circuits you will be working on. It will show you how
a plumber’s work could include the installation to connect electrical equipment to circuits and check
of an immersion heater for a hot water cylinder, the connections are safe.
a central heating control system, fitting electric
By the end of this chapter, you will have a knowledge
showers or checking bonding to gas or water
and understanding of:
systems. Many components or equipment used for
l the principles of electricity
plumbing installations require an electrical supply
l the legislation relating to electrical work and the
or control circuit.
control of plumbing and domestic heating systems
In addition, working in the building services industry l the types of electrical system and layouts
requires the use of electrical plant and machinery, l performing pre-installation activity prior to
which can also involve risk. Whether you are undertaking electrical work on plumbing and
installing electrical equipment or not, you will be domestic heating
working on or around electricity and the purpose l safe isolation procedures
of this chapter is to give you an understanding of l safe installation and testing of electrical equipment
the risks involved as well as an understanding and l diagnosing faults and safe repair of electrical work.
Remember, some of the basic electrical safety ● components used in electrical installations and
and principles were covered in Book 1, Chapter basic electrical tasks
11, Electrical principles and processes for building ● electrical tests and procedures for safely isolating
services engineering. This covered: supplies
● electrical supplies used in domestic plumbing ● identifying critical safety faults on electrical
systems components.
KEY POINT
It is important to note that the knowledge gained
1 THE PRINCIPLES OF
from this chapter does not make you a qualified
electrician, but opportunities do exist for you to
ELECTRICITY
take further training in your career to enable you Electricity is a flow of electrons that cannot be seen or
to install and commission a defined scope of
smelt. It flows around a circuit where its energy makes
electrical systems and circuits.
things work. When electricity is simply quantified, we
use a number of terms, represented by certain symbols
(see Table 5.1).
337
light R
points
Supply
Ceiling rose then:
230 = 1.92 A
120
E
Alternatively, Ohm’s law could be used to work out
voltage loss due to cable conductor resistance.
One-way
switch
339
then:
V = 2× 3 = 6 V
Electric shock
So, if the supply was 230 V and 6 V was lost due Very small current values can cause electric shock,
to the conductor resistance, only 224 V would be and values around 0.05 A (50 mA) can cause death.
present on the load line terminal.
The human body responds to different current values
as the body uses electrical signals to make muscles
Power move. Coming into contact with external currents can
override the body signals causing involuntary operation
The power of a load is measured in watts. This value
of muscles. If the current is an alternating current (AC),
dictates the amount of current drawn by the load
this could cause parts of the body, such as the heart
depending on the circuit or supply voltage as:
muscle, to operate at speeds equal to the electrical
Power (P) = voltage (V) × current (I) supply frequency.
or: KEY TERM
I= P
V
Electric shock: where a current flows through the
human body and causes an accident or injury as
IMPROVE YOUR MATHS a result.
Worked example: calculating power
So, if an immersion heater element has a power The electrical supply frequency for AC in the UK is
rating of 3 kW and is connected to a 230 V supply, 50 hertz, meaning the current alternates direction
how much current is drawn by the element? 50 times in one second. An alternating current is
As a kilowatt is 1000 watts then 3 kW is 3000 W so: effectively switching on and off twice in one alternation
or cycle so this has the effect of turning the current on
I = P so 3000 = 13.04 A and off twice in one cycle or 100 times a second.
V 230
180° 360°
0°
So, the immersion heater circuit conductors would + V
I
KEY POINT
It is always a good exercise to know how much
current certain loads draw as this has an impact
on the switches or devices selected to control
them. For example, if the immersion heater above
needed to be controlled by a time clock switch,
the switch must be capable of switching at least
13.04 A. If the time clock switch selected was
only capable of switching 10 A, the switch would –
burn out very quickly. 1 cycle or period
If an AC current exceeding 0.05 A was able to flow There are two ways a person can receive an electric
through the heart, this could cause the heart to shock:
pump 100 times a second and it will not take long for l directly, by touching a part which is meant to be
the heart to stop functioning in a short time period live such as a live conductor
causing arrest. l indirectly, by touching a metallic part which isn’t
The EAWR cover the principles of electrical safety l Regulation 16 – persons to be competent to prevent
that apply to work activities and systems, including danger and injury.
342
343
344
345
346
kWh
25 mm2 tails
6243Y
16 mm2 earthing
conductor
32 A cooker 6 mm2 6242Y
10 mm2 main
protective
bonding
R Y B
Circuit diagrams
Circuit diagrams contain information on how circuits MCCB
and systems operate. They can be provided as detailed Thermal over load relay
layouts, although some information such as length of
run may be omitted for clarity. In most instances, these Delta Star
contactor contactor
diagrams are used for diagnostic purposes so that KM2 KM1
designers, installers and maintainers understand how
1 3 5 1 3 5 1 3 5
their actions may influence a particular component or
arrangement. 2 4 6 2 4 6 2 4 6
U1 V1 W1 W2 V2 U2
3-phase
motor
347
manufacturer’s instructions when fitting electrical (many of these components will also be covered
appliances. By reading them in advance it will help in other chapters).
greatly with the selection of the product to ascertain
whether or not it is suitable for a specific application. Consumers’ control unit (CCU)
Generally, the first unit in an installation, where the
Manufacturer’s literature will also give fault-finding
supply is split into circuits, is called the consumers’
flow charts and a spare parts list for anyone trying to
control unit (CCU). This may sometimes be referred to
diagnose a fault with an existing appliance.
as a distribution board, or DB, and sometimes simply
While products must comply with the relevant as a consumer unit (CU). The CCU will have protective
standards of safety and performance, sometimes there devices inside. They control and protect the circuits and
are extraordinary applications or special functions could include:
which are covered solely by a manufacturer, provided l circuit breakers (CB)
the product is installed in accordance with their l residual current breakers with overload (RCBO)
directions, hence the importance of a compliance l fuses.
certificate and benchmark log book.
The CCU will also have a main switch which can be
User information is limited to the daily operation used to isolate the entire installation. In a domestic
of an appliance and the installer during the handover dwelling, the main switch must be double-pole
should give demonstrations and explanations to the meaning it isolates both line and neutral.
customer when commissioning is complete.
INDUSTRY TIP
3 THE TYPES OF You may hear a CCU called many different things such as
ELECTRICAL SYSTEM fuse boards, DBs or distribution boards. Distribution boards
(DB) are often the name given to further units on the end of
AND LAYOUTS a distribution circuit. A distribution circuit is a circuit that
supplies a distribution board whereas a final circuit is one
It is important to understand how electrical systems that supplies current using equipment such as lights and
are arranged in order to safely work on parts of them. heaters or socket outlets.
348
● care homes
residential buildings.
Figure 5.8 Six-way DB with eight modules
AFDDs are recommended for other types of premises.
AFDDs monitor the supply to the circuit being Some CCUs/DBs are known as split-way boards. This
protected and can detect both series and parallel means that some of the modules can be protected by
arcing. Series arcing is generally caused by a loose or one residual current device (RCD) or switch and the
failing connection creating an arc where the electricity others by another RCD or switch. Split-way boards
jumps the gap between the connections. Parallel arcing should always have one main switch that can isolate all
is where insulation breaks down or has been damaged, circuits. The advantage of split-way boards is that any
meaning arcing takes place between conductors in a fault on one circuit will only trip part of the installation
circuit. protected by one of the RCDs.
N1 2 3 4 5 6
Parallel arc 1
2
3
Figure 5.7 Types of arc
4
5 6A 6 A 16 A 32 A 32 A 45 A
L N
6
E
6 5 4 3 2 1
349
Fuses
Fuses have been a tried and tested method of circuit
protection for many years. A fuse is a very basic
protection device where a high enough fault current
causes the fuse element to heat up to the point where
the element is destroyed and cuts the current from the
circuit. Once the fuse has ‘blown’ (when the element of
the fuse has melted or ruptured), the fuse needs to be
replaced.
l BS 3036 semi-enclosed rewireable fuses – in
350
current. Overload currents, which are smaller than fault l Power circuits, which are provided for socket-outlet
currents, are detected by a thermal trip, such as a bi- circuits or other appliances such as immersion water
metallic strip, which causes the device to trip. heaters or showers. They require larger protective
devices due to the demand for current and, in
The difference between a circuit breaker and RCBO
most instances, require RCD protection due to the
is that an RCBO also incorporates a residual current
additional risk presented by the portable equipment
device (RCD) which will cause disconnection if a fault
connected to the socket outlets.
to earth is detected as small as 30 mA, in the case
of an RCBO having a residual trip setting of 30 mA,
Lighting circuits
which is the most common setting for domestic type
Lighting circuits are generally rated at 6 A but can, in
installations.
some installations, be rated at 10 A or 16 A. As the
The physical difference between a CB and RCBO is an name suggests, lighting circuits are intended to supply
RCBO has a test button incorporated on it. It is very lighting points, but in some cases they may also supply
important that this test button is pushed at least once some very small power equipment such as bathroom
every six months as this keeps the tripping mechanism fans or shaver supply units.
free from sticking and that means the device will trip
quickly should very small fault currents occur to earth. Power circuits
With only one or two rare exceptions, all circuits in Power circuits generally supply socket outlets, but may
domestic type electrical installations must have RCD also supply individual appliances. Power circuits may be
protection and this is either provided with individual wired in two ways: ring-final and radial.
RSBOs protecting each circuit or the use of split-way
CCUs where RCDs protect several circuits. Ring-final circuits
N1 2 3 4 5 6 Ring-final circuits are the traditional means of wiring
socket-outlet circuits within the UK and are rated at
32 A. The reason for their use was to provide a high
1
2 number of conveniently placed outlets adjacent to the
3 loads. The circuit load is shared by two sets of cables
4
5 6A 6 A 16 A 32 A 32 A 45 A
L N run in a ring formation. This also assists in improving
6
E
voltage drop as the conductors being in parallel reduce
the overall resistance.
6 5 4 3 2 1
351
L E N L E N L E N L E N
L E N L E N
L E N
Supply
L E N
Fused spur
L E N L E N L E N
L E N
Spur
L E N L E N L E N L E N
L E N
Supply
Branch
L E N
Figure 5.13 Ring-final circuit showing spurs and radial circuit showing branch
352
protective conductors such as earthing and, where Table 5.4 Current causing effective disconnection of type B
necessary, bonding. These conductors must provide a circuit breakers
low resistance path to earth so should any metal part Device rating Current needed to cause automatic
become live due to a fault, Ohm’s law dictates that (A) disconnection to occur in 0.4 seconds (A)
the low resistance path provided by the protective 6 30
conductors will ensure there is a high fault current. The 10 50
high fault current will disconnect the device protecting 16 80
the circuit very quickly; hopefully before anyone
20 100
touches the part and gets an electric shock.
32 160
Regulations for electrical circuits, known as BS 7671
(which will be covered later in this chapter), state that
KEY TERM
most low power circuits, such as those in domestic
installations, must disconnect within 0.4 seconds. Type B circuit breakers: the most sensitive type
of CB and should be the types used to protect
As currents as low as 0.05 A can cause electric shock circuits in domestic type installations. Other types
(as discussed earlier in this chapter) fault currents may are type C intended for motors and transformers
as well be hundreds of amperes as they are likely to kill and type D for very specialised machines such as
anyway. What saves a person’s life is the disconnection welding equipment or medical equipment.
of the circuit’s supply in a very quick time and this will
only happen with high fault currents. As the current needed to cause disconnection of a
To give an illustration of this, Table 5.4 shows the amount protective device is high, the resistance of the whole
of current needed under fault conditions to disconnect fault circuit needs to be low. This resistance is known as
the various ratings of type B circuit breakers in the the total earth fault loop impedance (Zs). The diagram
specified disconnection time of 0.4 seconds. in Figure 5.14 shows the total earth fault current path
Fault current
TN-C-S (Ze=0.35 Ω)
N
Earth neutral
Pen conductor MET
TN-S (Ze=0.8 Ω) Link
cpc
Metallic return path E
Cable sheath The earthing conductor
Mass of earth
TT (Ze-21Ω)
Return path
The values of ohms shown are maximum values the electrical distribution network operator tries to
achieve for the supply impedance.
353
for the three common earthing arrangements, which reduced in csa. In these situations the length of the
starts at the sub-station transformer, through the supply circuit should be restricted as the smaller csa cpc may
network line conductor, into the electrical installation end up having a resistance too high. The Institute of
and through the circuit line conductor. The current then Engineering Technology (IET) produce a publication
flows through the fault onto earthed parts and back called the IET On-Site Guide, and Table 7.1 in the guide
through the cpc (circuit protective conductor) to the main gives maximum circuit lengths based on the type and
earthing terminal (MET). From this point, it flows through rating of protective device, how the cable is installed
the installation earthing conductor which then connects and csa of the circuit line and cpc.
to the supply network earth back to the transformer.
ACTIVITY
KEY TERM Have a look at Table 7.1 in the IET On-Site Guide and
Sub-station transformer: a piece of equipment see the vast range of cable sizes used depending on
which is owned by the electricity distribution the circuit rating and protective device.
network operator (DNO) and is used to step down Using the table, determine the smallest cable
large distribution voltages of 11000 V to 230 V for combination (line/cpc) permitted for circuits
supplies into houses. Sub-stations are sometimes protected by:
located behind panel fences and can serve up a 20 A circuit breakers
to 100 houses or more depending on its size. b 32 A RCBO
Sometimes they are located on poles where they
serve one or two houses in more rural locations. In c 6 A BS 3036 fuses.
cities and large towns, they are normally located in
brick or concrete structures.
Bonding
Main protective bonding conductors (MPB), sized in
IMPROVE YOUR MATHS accordance with Section 4 of the IET On-Site Guide
Use Ohm’s law and values from Table 5.4 to work must be installed connecting the MET and:
out what the earth fault impedance needs to be to l metallic installation service pipes such as gas,
cause the following circuit breakers to disconnect water, oil
when the voltage is 230 V: l metallic exposed structural steelwork of a building
l 10 A rising from the ground
l 20 A l other extraneous conductive parts.
l 32 A.
KEY TERM
Extraneous conductive parts: metallic parts of
Earthing a building structure or services that have a low
The green and yellow earthing conductors in each resistance path to the general mass of earth but
circuit are called circuit protective conductors (cpc) and do not form part of the electrical system.
must be present in all parts of a circuit. Every exposed
metallic part in an electrical circuit must be connected
to the cpc to ensure the metal part is connected to INDUSTRY TIP
the earth path should a fault occur. This will ensure the
Although various sizes of MBP conductor are required
low resistance earth path creates a high fault current
depending on the type of supply and installation, most
causing quick disconnection.
domestic dwellings will be protected using 10 mm2
As a general rule, the cpc should ideally be the same conductors.
cross-sectional area (csa) as the circuit line conductor.
This however isn’t always the case, and cables such
Where the MPB conductor is connected to the
as the flat PVC twin and cpc cables commonly used
incoming service pipework, the connection must be
in domestic electrical circuits in the UK have a cpc
made within 600 mm of any stop valve or meter or
354
point of entry to the building but before any branch In some situations, supplementary bonding may need
pipe is installed. to be installed, but this is not normally needed where
circuits have RCD or RCBO protection.
Connection is made to the pipework using a specific
bonding clamp which complies with BS 951, Electrical The purpose of MPB is to ensure equal potential.
earthing. Clamps for earthing and bonding. Different Should a fault occur in an electrical installation, the
clamps have colour coding on them for installing in cpc for the circuit will become live to 230 V, as will
different conditions. They may be: the MET and any services or parts connected by MPB.
l red for dry conditions If equal potential is present between the electrical
l blue for damp locations. installation and extraneous parts, current cannot flow
between, especially through a person, meaning the
HEALTH AND SAFETY risk of electrocution is reduced.
Each bonding clamp must have a label fitted which
states the words ‘Safety electrical connection – do KEY TERMS
not remove’.
Supplementary bonding: where a bonding
conductor is installed either between pipes or from
a socket outlet or other accessory to a pipe. Unlike
INDUSTRY TIP MPB, supplementary bonding doesn’t come from
the MET. The minimum csa of cable permitted for
BS 7671 does state that services entering a building supplementary bonding is 4 mm2 where the cable
having an insulated section do not require the is in free air. Supplementary bonding is sometimes
connection of a main protective bonding conductor, so also called cross-bonding.
always seek the advice of an electrician as connecting a Equal potential: where the voltage between any two
bond to a part that is not extraneous may create a danger parts is within safe touch voltage levels, usually
that wasn’t there. 50 V AC but dependent on the location.
Circuit protective
conductors
Electrical accessories
There are several types of electrical accessories or
Main protective
bonding conductors junctions that are commonly used to connect electrical
equipment used in the plumbing industry. These can be:
Gas l socket outlets
Other installation l fused connection units
extraneous pipe
conductive part l double pole switches
l junction boxes
Water l wiring centres.
installation
pipe
Socket outlets
Although socket outlets are common place in all
Earthing
conductor buildings, they are normally provided for portable
appliances. It is not good practice to use a socket
outlet to connect permanently fixed equipment
such as boiler systems, immersion heaters or other
equipment but that doesn’t mean you will not see it
Means of earthing
sometimes.
Figure 5.15 Protective conductor arrangement for earthing and
bonding
355
Wiring centre
Wiring centres are normally manufacturers specific
boxes having terminals inside that are specifically
labelled for certain equipment such as boiler circulating
pumps, boilers or programmers.
356
Instantaneous showers
As these appliances heat up the cold water to produce
hot water, they usually require a large electrical supply
direct from the consumer unit.
Most electric showers are rated between 7 and 10 kW.
This means that a 10.5 kW shower requires a 45 A
electrical circuit to supply it which in turn will likely
need a large 10 mm2 cable to supply it, depending on
the cable installation conditions. These circuits should
be installed by an electrician. To allow mechanical
works to be carried out on the shower, the circuit
should contain a local switch such as a pull cord switch
located in the bathroom.
l instantaneous showers
Macerators
l jacuzzi bath or hot tubs A macerator is a device that compacts and pumps waste
l macerators water or black water (toilet waste) where no natural
l boiler control devices waste fall exists such as in basement toilets where the
l optimisers building’s waste pipes are higher than the toilet.
l home automation (Wi-Fi enabled equipment).
These devices are usually quite low in power ratings
and are typically around 5 A. They normally come
Shower pumps
fitted with a flexible cable requiring a permanent
These are normally installed under a bath or in a connection to a local fused spur connection unit.
void. They usually come fitted with a flexible cable
357
Boiler/heating controls
GREY permanent live
Micro-switch
There are a large number of devices used to control
heating and hot water systems which require an WHITE room stat on C Plan
electrical connection, these include:
l Programmers – these are dual zone time clocks ORANGE switched live to boiler
and pump (boiler only on C Plan
that turn on the central heating or hot water at BROWN motor from thermostat
varying times of the day. These are normally wired BLUE neutral
GREEN/YELLOW earth
to a wiring centre to control the room thermostat
Motor
or cylinder thermostat.
l Room thermostats – these are used to monitor Valve closed
the room temperature and control the zone Figure 5.19 A 2-port zone valve showing the cable connection
valve for the heating system should the room colours
temperature fall below that set by the thermostat.
Older thermostats used bimetal strips, but Optimisers
modern ones use electronic sensors to monitor the These are more sophisticated forms of time-clock
temperature. switches or programmers. They are used to control
l Cylinder thermostats – on a cylinder thermostat heating or hot water systems but may incorporate
there is a calibrated bimetallic strip positioned at the thermostats within them. Other forms use radio
back of the thermostat, which is firmly positioned connections for remote thermostats or temperature
against the bare surface of a cylinder with the aid monitors which can monitor internal and external
of a tensioned wire. Once the thermostat senses temperatures ensuring the heating system maintains a
the pre-set temperature it turns off the electrical desired temperature efficiently.
supply to a zone valve. A cylinder thermostat should
be installed approximately one third the distance Home automation and Wi-Fi devices
from the base of the cylinder and be set to operate With huge advances in the internet of things (IoT),
between 60 and 65 °C. home automation devices advance just as quickly. It is
l Zone valves – these are electrically controlled
now very common to control all central heating and
valves which are supplied using a 5-core flexible hot water systems using a smartphone connection
cable which connects to a wiring centre. The valve anywhere in the world. As long as the system is able
has a small motor in it which opens and closes the to connect to the internet using a Wi-Fi or Bluetooth
valve as well as a small micro-switch which is used connection, it can ‘talk’ to other devices removing the
to control the boiler and pump when the valve need for any control wiring. In some situations, where
opens and closes. the devices are battery powered, the need for any
wiring is completely removed.
358
either by direct contact with a live part or indirectly by particularly if at high voltage
contact with an exposed conductive part (for example, l exposure to high-frequency radiation (e.g. from
a metal equipment case) that has become live as a radio transmission antennas).
result of a fault condition.
HEALTH AND SAFETY
Faults can arise from a variety of sources:
Accidents do happen even when you put measures
l broken equipment case exposing internal bare live
in place to remove all risks. Electricity cannot
connections be seen, and working on a busy site could lead
l cracked equipment case causing ‘tracking’ from to exposure to electricity if others do not work
internal live parts to the external surface safely such as an electrician not placing covers
l damaged supply cord insulation, exposing bare live over potentially live parts. Always be familiar with
conductors the emergency procedures and accident reporting
covered in Book 1, Chapter 1.
l broken plug, exposing bare live connections.
359
or off)
l for use in an emergency (switching in the event of
an accident)
l so that equipment can be switched off to prevent its
use and allow maintenance work to be done safely Figure 5.20 This symbol may appear on Class I items
on the mechanical parts
l to isolate a circuit, installation or piece of
Class II
equipment to prevent the risk of shock where
Class II equipment has either no external conductive
exposure to electrical parts and connections is likely
parts apart from fixing screws (insulation-encased
for maintenance purposes.
equipment) or there is adequate insulation between
The preparation of electrical equipment for maintenance any external conductive parts and the internal live
purposes requires effective disconnection from all live parts to prevent the former becoming live as a result of
supplies and the means for securing that disconnection an internal fault (metal-encased equipment). Periodic
(by locking off). inspection or testing needs to focus on the integrity of
the insulation. Class II equipment is identified by the
symbol shown in Figure 5.21.
360
Another way of reducing the risk of electric shock is lift rooms or other areas where portable electrical
by using a reduced low voltage system. This is not a equipment is in frequent use)
Class III system but is a safer arrangement than using l through small portable transformers designed to
mains-operated (230 V) equipment because of the lower supply individual portable tools known as 110 V
potential shock voltage. Supply is provided via a mains- Centre Tapped Earth (CTE) transformers.
powered (230 V) step-down transformer with the centre
point of the secondary winding connected to earth.
III
Figure 5.22 This symbol may appear on Class III items Figure 5.23 Portable CTE transformer and drill
361
Mains 230 V
supply
110 V output
HEALTH AND SAFETY
NEVER rely on a standard local switch for isolation
55 V where you will be working on electrical terminals
unless it can be secured in the open/off position. If
the device cannot be secured as open/off, isolate the
N entire circuit.
You should also isolate the whole circuit when you
E E
are making a connection into a fused connection
Figure 5.24 Circuit diagram for a 110/55 V CTE transformer unit (or similar) and the incoming supply terminals
are live.
Alternatively, cordless or battery-powered tools offer
a convenient way of providing a powered hand tool
without the inconvenience of using a mains supply and
without the hazard of trailing power leads.
INDUSTRY TIP
Access Regulation 12 and 13 of the Electricity at
KEY POINT Work Regulations 1989 at: www.legislation.gov.uk/
PAT testing was covered in detail in Book 1, uksi/1989/635/made
Chapter 1.
362
How to undertake a basic l a lock and/or multi-lock system (there are many
types of lock available)
practical procedure for l warning notices which identify the work being
isolation carried out
l relevant personal protective equipment (PPE) that
Being able to perform safe isolation is a key skill every
adheres to all site PPE rules – this may include
person working with electricity needs. It is always a
gloves to assist grip, hard hats due to the location
good idea to practise this procedure, so be sure to do
and eye protection due to the risk of arcing.
this under supervision by a skilled person such as your
tutor.
INDUSTRY TIP
Gather together all of the equipment Return to Book 1, Chapter 1, to remind yourself of the
required for this task relevant PPE.
You will need the following equipment:
l a voltage indicator which has been manufactured The equipment shown in Figure 5.25 can be used to
and maintained in accordance with Health and isolate various main switches and isolators. To isolate
Safety Executive (HSE) Guidance Note GS38 individual circuit breakers with suitable locks and
l a proving unit compatible with the voltage indicator locking aids, you should consult the manufacturer’s
guidance.
363
364
365
Things that can cause risk to you include: Risks to buildings and systems within
l inadequate information to enable safe or effective buildings
installation, such as no diagrams, legends or charts Risks to buildings and systems within buildings might
l poor knowledge of the system you are working on involve applying excessive voltages to sensitive
(and so not meeting the competence requirements electronic equipment, for example:
of Regulation 16 of EAWR) l computers and associated IT equipment
l insufficient risk assessment l residual current devices (RCDs) and residual current
l inadequate test instruments (not manufactured or operated circuit breakers with integral overcurrent
maintained to the standards of GS38). protection (RCBOs)
Even tasks that seem low risk, such as removing a l heating controls
bonding clamp from a water pipe, can be high risk if l surge protection devices.
isolation has not been undertaken. If dangerous potentials There might also be risk of loss of data and
exist between the electrical system and the water pipe, communications systems.
you will become the bridge between these potentials
as soon as you remove the clamp. NEVER REMOVE ACTIVITY
BONDING UNLESS THE WHOLE SYSTEM IS ISOLATED.
Write down a list of the risks associated with
isolation and the effects isolation can have on
Risks to other tradespersons, customers people, livestock, systems and buildings. You could
and clients think about:
Risks to other tradespersons, customers and clients 1 Who is at risk if isolation is not carried out
might include: correctly?
l switching off electrical circuits – for example, 2 What might happen if you need to switch off
switching off a heating system might cause a socket-outlet circuit? For example, in a care
hypothermia (resulting from being too cold); if lifts home?
stop, people may be trapped 3 What must you do if you encounter a computer
server that requires a permanent supply and you
l applying potentially dangerous test voltages and
need to switch off the main supply to enable safe
currents working?
l access to open distribution boards and consumer
units
l loss of service or equipment, for example:
l loss of essential supplies
366
Electrical tools
There are a wide range of tools you will use when
working on electromechanical systems. This section
will look at the ones specifically used when working on
electrical systems.
Wire strippers
Wire strippers provide a safe and reliable method of
removing the insulation from a wire or cable without
damaging the conductor. Wire strippers come in Figure 5.27 Side cutters
various designs, but the common principle is that the
Depending on the size of the cutters, cable sizes up
cutting jaws only cut into the insulating material and
to 16 mm2 can be cut easily. However, larger cables
not into the conductor.
require larger types of cutters. These range from cable
Wire strippers can be either manually set (by a screw or loppers, up to hydraulic, manual pump cutters for
dial) or automatically set. Side cutters can also be used cables up to 300 mm2.
but these often damage the conductor.
Screwdrivers
An electrician will use a selection of different sized
screwdrivers. They will all have one thing in common
in that they will all be of approved standards. The most
common screwdrivers used include:
l terminal (3–3.5 mm)
l pozidriv (PZ2)
Cable cutters
There are a variety of different tools that can be used
to cut cables, the most common being side cutters.
Side cutters are probably one of the most important
tools that electricians have in their tool kit. These are
used for cutting cables to length, cutting sleeving and
cutting nylon tie-wraps, for example. They work on a
compression-force basis and are shaped so that the
cutting point is along one side.
367
length. It should always be used pointing away from a cable and could include systems such as cable
the body. tray, basket or simply clips or cleats.
l Cable management system or cable containment
368
Use of wire strippers is recommended for single-core Stripping flat-profile thermoplastic cable
conductors. Automatic wire strippers tend to rip the
Flat-profile cable is stripped in the same way as single-
insulation from the conductor and can damage the
core cables, once the sheath has been removed. There
insulation. Manual wire strippers are preferred and
are several ways to do this, but some methods can
these come in various forms, but all work on a similar
damage the cables.
principle.
369
370
371
372
526.5
526.3
All terminations and joints in live conductors must
Poor and loose terminations cause many fires of be enclosed within a suitable enclosure or accessory.
electrical origin. Regulation 526.3 requires every There are no exceptions. This requirement applies to
connection or joint to be accessible for inspection, both low-voltage and extra-low voltage connections,
testing and maintenance, with the exception of: but sadly it is not uncommon to see poor examples
l joints designed to buried in the ground
of connections, especially where down-lighters are
l a compound-filled joint
fitted.
l an encapsulated joint
INDUSTRY TIP
From this regulation it is clear that the practice of using
screw terminal junction boxes and placing these in
inaccessible places, such as ceiling or floor voids, is not in
compliance with BS 7671.
526.6
This requires that there is ‘no appreciable mechanical
strain in the connections of conductors.’ Mechanical
strain may come about due to:
p Figure 5.35 Types of connection not required to be accessible
l the conductor bending too tightly before entering
373
under constant stress. Cables must be installed in protection against relevant external influences. The
accordance with the minimum bend radii, as given minimum requirements for an enclosure to meet the
in the IET On-Site Guide or IET Guidance Note 1 requirements for basic protection are that:
(GN1). l the bottom sides and face meet at least IP2X or IPXXB
l cables having no form of strain relief fitted. This can l for the top surface, the enclosure must meet IP4X or
374
IP 4 3 D
Code letters
International protection
IP Requirement Example
0 No protection
1 Full penetration of 50.0 mm diameter sphere not allowed and shall have Back of the hand
adequate clearance from hazardous parts. Contact with hazardous parts
not permitted.
2 Full penetration of 12.5 mm diameter sphere not allowed. The jointed test A finger
finger shall have adequate clearance from hazardous parts.
3 The access probe of 2.5 mm diameter shall not penetrate. A tool such as a screwdriver
4 The access probe of 1.0 mm diameter shall not penetrate. A wire
5 Limited ingress of dust permitted. No harmful deposit. Close fitting
6 Totally protected against ingress of dust. Dust-tight
INDUSTRY TIP
Do not use your own finger to test equipment. Use a proper
test finger.
IP Requirement Example
0 No protection
1 Protected against vertically falling Drips from
drops of water condensation or
similar
p Figure 5.39 The first digit of the IP code shown relates to the 2 Protected against vertically falling
ingress of solid objects and the second digit relates to the drops of water with enclosure
ingress of liquids tilted 15° from the vertical
➜
375
ACTIVITY ACTIVITY
When removing knockouts from a plastic box the
What is meant by the code IP44?
slot should be as tight to the cable as possible. What
tool should be used to cut the slot?
q Additional letter A–D: Enhanced protection of persons
IP Requirement Example
INDUSTRY TIP
A Penetration of 50.0 mm diameter The back of
sphere up to guard face must not the hand
contact hazardous parts When cables enter the top of an enclosure, IP4X must be
maintained, meaning there should be no gap larger than 1 mm.
B Test finger penetration to a maximum A finger
of 80.0 mm must not contact
hazardous parts
526.8
C Wire of 2.5 mm diameter × 100.0 mm A screwdriver
long must not contact hazardous parts Where the sheath of a cable has been removed the
D Wire of 1.0 mm diameter × 100.0 A wire cores of the cable must be enclosed within an enclosure
mm long must not contact hazardous as detailed in 526.5. This also applies to non-sheathed
parts may be protected by an internal cables, contained within trunking or conduit.
barrier
The IP codes that you are most likely to come across 526.9
are: The group of regulations designated 526.9 relates to
1 For protection against the ingress of solid the connection of multi-wire, fine-wire and very-fine
objects and protection to persons. The codes are wire conductors.
IP2X and IP4X used in relation to barriers and
enclosures. 526.9.1
2 For protection against the ingress of water the codes To stop the ends of multi-wire, fine-wire and very-fine
are IPX4, IPX5, IPX6, IPX7 and IPX8. wire conductors from spreading or separating, this
3 For enhanced personal protection IPXXB and regulation requires that suitable terminals, such as plate
IPXXD again used in relation to barriers and terminals, or suitable treating of the ends be undertaken.
enclosures. One suitable method is to fit ferrules on the ends of
the conductor. Manufacturers will almost always fit
some form of ferrule to the ends of flexes so that the
conductor can be terminated in a screw terminal.
376
526.9.3
The connection of soldered and non-soldered ends on
multi-wire, fine-wire and very-fine wire conductors
is not permitted where there is relative movement
p Figure 5.43 Square terminal showing possible problems if
between the two conductors. conductor is not doubled over
377
Circular terminal
Circular terminals can be seen in accessories such as
light switches and ceiling roses, where single cables or
small cables are terminated. They are also commonly
found in consumer units and distribution boards on
both the neutral and earth bars.
Circular bottom terminals are designed to ensure
that the conductor is positioned directly beneath the
terminal screw, so there is no need to bend the end of
p Figure 5.46 Two types of moving-plate terminal
the conductor over.
If there is no option other than to mix flexible cable and
solid or stranded conductors in the same terminal, the
flexible conductor must be fitted with a ferrule. This is
a small, metal tube that is crimped onto the end of a
flexible conductor to hold the strands together.
Terminating copper and aluminium conductors within
the same terminal should also be avoided due to
the electrolytic reaction between the two different
metals.
Whatever types of terminal and conductor are being
p Figure 5.45 Circular base terminal used, always make sure that the screw tightens on the
conductor and not the insulation. To ensure this, the
Moving-plate terminal insulation should stop at the opening of the terminal.
Moving plate terminals are often used on protective Take care not to stop the insulation too early, leaving
devices, such as circuit breakers and fuse holders that the conductor exposed, with the possibility of faults
are mounted in consumer units and distribution boards. occurring.
The option of bending over the end of the conductor
INDUSTRY TIP
depends not only on the size of the conductor, but also
on the size and type of the terminal. If the terminal is Common faults with terminations are exposed conductors or
the type where the bottom moves up towards the top screwing down onto the insulation.
when the screw is tightened, it is not necessary to bend
over the conductor, as the terminal tightens evenly. If,
however, the terminal has a plate that moves towards
378
Advantages and disadvantages of screw The jaws of the crimping tool are shaped to apply a
terminals different crimp style and pressure to the conductor and
The advantages of screw terminals are: insulation sides of the connection. The crimping tool
l they are cheap to produce applies the correct amount of pressure through a ratchet
l they are reliable that cannot be defeated unless the correct amount of
l they are easily terminated, with basic tools pressure is used, or the release button is pressed.
l the terminals are reusable. Once a crimp has been installed, it must be checked to
The disadvantage of screw terminals are that: ensure that the conductor of the wire protrudes from
l over-tightening could result in damage to the the crimped part of the lug and that the insulation has
terminal or the conductor been trapped on the other end, so that no exposed
l under-tightening of the terminals can result in conductor is showing. Bearing in mind that crimps are
overheating and arcing used in applications where vibration occurs, they should
l terminals can become loose, due to movement of never be used on solid conductors.
the conductor in use or due to mechanical vibration
l terminations need to be accessible for inspection. ACTIVITY
It is not unknown for pliers to be used for fitting
Crimps crimps, instead of the correct crimping tool. List two
possible faults that could occur.
Crimps and crimp lugs come in two basic forms,
insulated and uninsulated.
Uninsulated crimps
Insulated crimps Uninsulated crimps are used on conductors with cross-
When using a cable crimp lug, the wire’s insulation must sectional areas from 6 mm2 upwards. It is important
be stripped back about 5 mm. This enables the crimp that the crimp is sized in accordance with the cross-
to be installed with the correct amount of conductor sectional area of the conductors and is compatible with
within the crimp and with the insulating section being the conductor material being terminated.
sealed down onto the insulation of the wire.
Whilst a hand crimper may be suitable for smaller-sized
conductors, on larger conductors a hydraulic crimper
will be required. Battery-operated crimp tools are
available that take all of the hard work out of crimping
a lug onto a conductor.
379
STEP 4 The cable lug is then crimped to the cable, using a proprietary
cable crimper that suits the size of the lug.
STEP 1 Select the correct size cable lug for the conductor. Cable lugs with
different-sized holes are available, so be sure to always choose one that
has the correct-sized hole for the connection bolt or screw.
STEP 2 Strip enough insulation from the cable so that the copper
Advantages and disadvantages of
conductor meets the end of the cable lug, while the sheath of the cable crimped connections
fits tight to the base of the lug. The advantages of crimped connections are that they:
l are quick and convenient to install
INDUSTRY TIP
Crimped connections are far quicker and cleaner to make
than soldered joints. They also avoid the risk of the heat
source damaging the insulation or setting fire to the
building.
STEP 3 Ensure that the cable reaches right to the end of the lug tube.
380
381
382
q First letter
Code Definition
A1 For unarmoured cable with an elastomeric or plastic
outer sheath, with sealing function between the
cable sheath and the sealing ring of the cable gland.
A2 As type A1, but with seal protection degree IP66 –
means 30 bar pressure
B No seal
C Single outer seal
E Double (inner & outer) seal
q Second letter
383
STEP 3 Push the shroud onto the cable. The top of the shroud should
now be a snug fit to the outer sheath of the cable. Remember, when
assembling the gland and shroud combination, the shroud goes on before
the gland.
p Figure 5.54 A badly fitted shroud could trap moisture
384
INDUSTRY TIP
While a plumber wouldn’t generally need to install shrouding, you
should be aware of it as some less common installations require
it, e.g. jacuzzis. If in any doubt, refer to a qualified electrician.
ACTIVITY
Use the internet to find a cable coupler suitable for
outside use.
INDUSTRY TIP
Grommets are available as open or blind. An open grommet has
a hole in the middle. A blind grommet has a thin membrane,
through which the cable is pushed, and provides a better seal.
Grommet strip is also available for irregular-shaped holes.
enter
l front, sides and bottom, a 12.5 mm diameter
385
Terminating flexes The ringing tool is removed, the cable is bent to finish
Tools required the cut and the sheath is then pulled off.
l Ringing tool (Method 1)
l Stripping knife (Method 2)
Method 1
The outer sheath can be removed with the use of a
ringing tool. These come in various shapes and forms,
the most basic of which is shown in the diagram. This
tool slides over the end of the cable to the required
stripping position, and is then rotated around the cable,
cutting it slightly.
p Figure 5.59 Flexible cable sheath stripping tool for use on flex
386
Terminating single-core cables Manual wire strippers have two blades that cross one
Tools required another, like scissors. Each blade has a notch so that
together they cut around the conductor in the middle.
l Cable strippers.
In addition, wire strippers also have some means of
adjustment so that different sizes of conductor can be
stripped.
Before wire strippers can be used, they must be set
to the correct size. This can be done using a scrap or
off-cut of wire of the correct size. With the jaws of the
wire strippers together, turn the adjustment screw until
the hole in the jaws is just bigger than the conductor to
be stripped. Test the setting on the off-cut of wire, by
placing the wire strippers over the wire and squeezing
the handles to close the jaws. Then slightly release the
jaws and try to slide the insulation off, using the wire
p Figure 5.62 Different types of cable strippers are available strippers.
Safety considerations
There is a risk of injury from slipping with cutters
or pliers. The use of gloves and eye protection is
recommended.
p Figure 5.63 Cable stripper jaws If the wire strippers are correctly set, the insulation
will come off easily and there will be no damage to
Method the copper conductor. If the aperture is set too small,
the insulation will slide off easily but the conductor
As single-core cables do not have outer sheaths to
may be damaged. If it is set too large, the insulation
remove because they are intended to be installed
will not come off easily. A simple adjustment of the
within trunking or conduit, the termination method
adjusting screw will correct these problems. Now,
is straightforward and requires the minimum of tools.
with the correct setting, the wires can be stripped
This termination method will therefore also apply to
safely.
the final connection of other cable types.
Other types of wire stripper will have pre-set stripping
Use of wire strippers is recommended for single-core
holes so that selecting the correct hole will ensure that
conductors. Automatic wire strippers tend to rip the
the depth of cut is correct every time.
insulation from the conductor and can damage it.
Manual wire strippers are preferred and these come in Once the conductors are stripped they are ready to be
various forms, but all work on a similar principle. connected to the electrical equipment.
387
l side cutters
l pliers.
Method 1
Having decided on the length of sheath required, and
with the cable in place, score the sheath at the point to
which it is to be removed. This can be performed with
an electrician’s knife. Care should be taken not to cut
into the cable.
Safety considerations
l Cuts to hands from use of knife
l Injury from slipping with cutters or pliers
The use of gloves and eye protection is recommended.
p Figure 5.67 Scoring the outer sheath
Method
From the end of the cable, snip down the centre of the
Before the conductors can be connected, the outer
cable, using a pair of side cutters. Split the line to one
sheath of the cable must be removed.
side and the neutral to the other.
First, identify how much of the sheath should be
removed from the cable. The purpose of the sheath
is to provide some mechanical protection for the
insulation on the conductors. Too much sheath,
however, takes up space within the accessory and
will put excess strain on the conductors. The sheath
should, therefore, be stripped back almost to where the
cable enters the accessory, leaving only 10–15 mm, a
thumb’s width, of sheath within the accessory.
There is more than one way to remove the outer
sheath. Each has its advantages and disadvantages
but, whichever method is used, care must be taken to
avoid damage occurring to either the conductors or the
insulation around the conductors. p Figure 5.68 Snipping the end of the cable
388
p Figure 5.69 Tearing down to the score mark (left) and removing the outer sheath (right)
Method 2
Snip down the end of the cable with the side cutters,
then use a sharp electrician’s knife to slice down the
cable. To do this, run the blade along the protective
conductor. Note that this can damage the protective
conductor or, even worse, the insulation of one of the
live conductors if it is not done carefully.
389
Once you have reached the desired strip position in the protective bonding conductor. An understanding of the
outer sheath, use side cutters to cut away the outer term ‘extraneous conductive part’ helps when deciding
sheath. whether an item requires bonding or not.
KEY TERMS
Bonding: a term used to describe the connection
of extraneous conductive parts to the earthing
system.
Earth: earth with a capital E represents the
potential of the ground we stand on.
potential, and
p Figure 5.72 Using side cutters to cut away the outer sheath
l not forming part of the electrical installation.
cpc. The sleeving must cover all of the bare cpc, apart l The potential is usually taken as the mass of Earth,
from a small amount at the end, enough to go into the hence the capital E in ‘Earth potential’.
terminal. Extraneous conductive parts would include such items
as:
l metallic water installation pipes
390
earthing arrangement and length of the cable run. In service into the building
the majority of domestic type installations, a 10 mm2 l where practicable, within 600 mm of the service
conductor would normally be suitable. meter or at the point of entry if the service meter is
external
391
p Figure 5.76 Bonding to gas supply Some extraneous parts, such as steelwork, are of an
irregular shape but still require bonding. Various clamps
Choice of bonding clamps are available from suppliers and these must be:
l electrically durable
Bonding clamps must:
l of adequate mechanical strength
l meet the requirements of BS 951
l suitable for the environment where they are to be
l be suitable for the environment in which they are to
installed
be installed
l labelled in accordance with Regulation 514.13.1 of
l be labelled in accordance with Regulation 514.13.1
BS 7671.
of BS 7671 The IET Wiring Regulations.
BS 951 clamps are designed only to fit circular pipes Labels for bonding clamps
or rods. They are not designed to fit objects of irregular BS 7671 requires that the point of connection of every
shape, to be attached to steel wire armoured cable bonding conductor to an extraneous conductive part
or lead-sheathed cable. They are available in different has a permanent and durable label fixed in a visible
lengths and different materials to suit different pipe position stating ‘safety electrical connection – do not
sizes and different installation environments. remove’ (Figure 5.78).
392
INDUSTRY TIP
Even if the pipe looks clean there may be an oxide on the
surface. Make sure you clean the pipe before fixing the
p Figure 5.79 A bonding clamp as supplied
clamp to it.
The six parts of the bonding clamp are:
1 strap
2 label
3 bonding clamp body
4 cable termination point and screw p Figure 5.81 Preparing the pipe for installation of the bonding
5 locking nut clamp (Step 2)
6 tightening screw.
Step 3 – installation of bonding clamp to
Step-by-step instructions for fitting a pipe
BS 951 clamp
Step 1 – preparing the bonding clamp for
installation
l Remove the label from the strap.
l Remove the tightening screw and locking nut from
the body of the clamp.
l Pass the tightening screw through the hole in the
label and fit the locking nut.
l Refit the assembly to the clamp body, but leave the
screw so that it is not protruding into the slot of the p Figure 5.82 Place the body of the clamp against the cleaned
body. section of pipework
l The clamp is now ready for installation.
393
p Figure 5.83 Pass the strap around the pipe and through the slot
in the body of the bonding clamp
p Figure 5.86 The bonding clamp is now installed ready for
Pull the strap tight with one hand and, with the other connection of the protective bonding
hand, tighten the screw with a screwdriver.
Make sure that the locking nut is far enough up the Termination of bonding
tightening screw to prevent it locking against the body
of the clamp.
conductors
Regulation 526.1 of BS 7671 The IET Wiring
Regulations requires that all electrical connections are:
l electrically durable
p Figure 5.84 The bonding clamp should now be tight against the
pipe
394
INDUSTRY TIP
Be careful not to over-tighten the screws and strip the
thread. This can be very time wasting as you remove the
damaged clamp and search for a new one.
395
7 DIAGNOSING FAULTS
AND SAFE REPAIR OF
ELECTRICAL WORK
p Figure 5.92 Bonding clamp for use without cable lug
Communication and
Termination of more than one cable regulations
to a bonding clamp
There are many faults that can occur in electrical
Where two services are in close proximity to one circuits that include component failure as well as errors
another, it is acceptable to run one bonding cable to in design and poor workmanship in the installation of
serve both services. If the bonding cable loops from electrical systems.
one bonding clamp to another, the bonding conductor
should be unbroken. Before any work begins on investigating an electrical
problem it is essential that a conversation with the
INDUSTRY TIP client is carried out as this will help in identifying
the problem and enable effective faulting finding to
There is a risk that if another trade removes a bonding be applied in conjunction with the manufacturer’s
conductor they may not bother to replace it. By using an instructions. Reference to the IET On-Site Guide may
unjointed bonding conductor for two services at least the often be required and the systems and processes of
end service is still bonded. testing electrical circuits can be found in Section 9. In
Section 10 of the IET On-Site Guide, it states that:
As shown in Figure 5.93, strip off enough insulation It is the test operative’s duty to ensure their own
from the bonding cable to enable the cable to make safety and the safety of others whilst working
metal-to-metal contact with the bonding clamp. A through the test procedures.
stripping knife would be the ideal tool to accomplish
this task. The guide goes on to emphasise the importance of
having a good working knowledge and experience
of the correct electrical application and use of the
test instruments that includes the leads, probes and
accessories. It goes on to say check to ensure any
test equipment is safe and suitable. It is important to
p Figure 5.93 Preparing cable to loop from one bonding clamp to check the accuracy and calibration of such devices
another and to make sure they are in good working order.
Testing equipment
Before any testing begins the plumber must ensure
p Figure 5.94 Parting the strands of the cable so that the that all leads, probes and instruments are in good
connection screw of the bonding clamp can be fitted condition, undamaged and that they function properly.
HSE Guidance Note GS38 for electrical test equipment
396
KEY POINT
p Figure 5.96 HSE GS38 Guidance Note
HSE Document GS38 advises that the test probe of
It is important that test equipment is calibrated in any instrument should not exceed 4 mm, and where
accordance with the manufacturer’s instructions. practicable be reduced to 2 mm. The leads should
also be insulated and each be a different colour.
Test lamp
Test lamp detectors rely on an illuminated bulb to
indicate the voltage. The robust leads are well insulated
and the probe has a HBC fuse not exceeding 500 mA.
They are fitted with glass bulbs which should not cause
any danger if the bulb is broken and the bulb can be
protected by a guard.
Lamp
HSE Document GS38 also advises that the leads on test Minimum of exposed metal
397
Barrier to
prevent
HBC fuse
Robust, flexible
Voltage tester
and/or current
access to limitation well insulated leads A voltage tester enables AC and DC voltage indication
live terminals
and measurement on the model shown in Figure 5.101 is
between 6–1,000 volts. They often have other features
incorporated into their design, such as an acoustic
sounder and a visual continuity function. They can also
test the function of 30 mA RCD, RCBO and MCBs.
KEY TERMS
Alternating current: flows in both directions
Minimum of Shrouded or firmly
Direct current: an electrical current in which
exposed metal attached connectors electrons flow in a single direction.
Digital clampmeter
A digital clampmeter will give readings not only of
current and voltage but of power quantities too.
They are ideal for use in the installation, maintenance,
monitoring or for the checking of AC or DC electrical
systems and equipment. It is also useful for testing
applications, as they are typically on electrical systems
and equipment where there is a need to measure
current, volts, resistance and frequency.
The digital clampmeter is therefore intended for use
while installing, maintaining, fault finding or monitoring
those systems. One of their features includes being able
to detect the load currents from equipment and identify
a range of load currents and start-up currents to motors
on pumps for heating systems. Information from tests
p Figure 5.102 Digital multimeter
can be transferred to a PC which can be convenient
when storing and producing maintenance reports.
398
KEY POINT
If a customer reported a problem with nuisance
tripping of a CB when the heating was on, a
clampmeter could confirm a measurement of
the current drawn from the pump motor to help
the engineer ascertain if that component was p Figure 5.105 Reading with Power on shows 0.24 A being drawn,
the cause of the problem. The advantage of this which equates to circa 60 W which is normal for a pump of this size
method means that testing can occur without
disconnection of the supply.
LOAD
Path of current
flow
The current is
being measured in
series with the
load.
Socket testers
Socket testers are very useful additions to a working
plumber’s tool kit as they can be used for initial
identification of faults following socket replacement or
re-wire work of any kind. Simple miss-wires or missing
connections can be quickly identified prior to full
BS 7671 electrical test and inspection, which saves
time during the testing and certification process. They
p Figure 5.104 Clampmeter with no reading as power is off may also be used during installation or commissioning
399
of electrical equipment connected to 13 mA sockets. isolation. When the probe tips are applied to the proving
By simply plugging the device into a socket outlet, the unit, it automatically begins in auto-test mode. The
polarity of the connections can be identified as any output voltage from the device will increase from 50 V up
faults are signalled by three bright LEDs on the front of to around 690 V and then gradually return back to 50 V
the unit and a simple diagnosis chart for typical errors is and then OFF. The voltage output is clearly indicated on
included on the label next to the LED display, as shown the five LED indicators on the front of the unit.
on the Megger. A typical use of a socket tester would
be when a boiler or other electrical appliance requires
servicing or replacing as the plumber will be aware of
the existing wiring at the point where the tester is fitted.
KEY TERMS
Dead testing: testing is carried out on electrical
components or parts of an installation when the
electrical supply is disconnected.
Live testing: a test is carried out when components
p Figure 5.108 A common socket tester used in situation are live.
400
securely fitted and located in the correct terminals, also testing is the only practical way to carry out this type
referred to as checking for correct polarity. of work then the person must be competent and fully
trained to work in such a high risk environment. In
Incorrect polarity would be easily identified during a
addition they must only use approved testing equipment
simple visual inspection where wiring problems such
not neon screwdrivers or homemade test lamps. Finally,
as neutral and earth conductors were in the wrong
they must let others in the vicinity know what they are
connections. The correct way to put this problem right
doing and protect the area with barriers and notices.
would be to safely isolate the electrical supply, verify
the supply was the correct polarity and then refit the q Table 5.6 Sequence of live testing on an electrical installation
conductors into the proper terminals as indicated on Live test sequence Instrument
the connection terminal.
Polarity GS38 approved test leads
If any damage, installation errors or defects are discovered Earth electrode resistance Earth loop impedance tester
during a visual inspection they must be made good before Earth fault loop impedance Earth loop impedance tester
any electrical installation certificate can be issued. Prospective fault current Prospective fault current tester
Quite often during a visual inspection a plumber can Functional testing RCD tester
come across burnt or scorched connections. If a conductor
Once it is confirmed that it is safe to work on an
and its insulation have been scorched, this must be
installation, a live test can be carried out.
remedied before any certification is produced. The cause
of the problem must be identified and often both the All types of electrical testing come with an element of
conductor and component will need to be replaced. risk to the person carrying it out. They must be aware
that they are responsible for their own safety and for the
Loose wiring or reduction of conductor csa could cause
safety of others who could be affected by their actions.
high resistance at this point. However, if the inspection
and testing of an installation prove to be satisfactory On heating circuits, the control system should have only
then a signed installation certificate, together with a one means of isolation but quite often it is assumed
schedule of inspections and a schedule of test results, that a circuit is dead because isolation has been carried
should be given to the person ordering the electrical work out from the fused switched spur connection unit.
(IET On-Site Guide). This person is often the customer After the safe isolation of gas supply for example, an
but could be an agent, landlord or site representative. engineer could open the case of a boiler and expect all
Any visual inspection must always come before tests of the terminals to be dead. At this stage it is essential to
of electrical installations using instruments. A dead test carry out a dead test to establish that there is no current
should always be carried out before a live test therefore present using a commonly used instrument known as a
all tests should be carried out in their correct sequence. voltage indicating device. Sometimes there are surprise
readings showing that there is a current present because
q Table 5.5 Sequence of dead testing on an electrical installation
there has been a rogue supply installed, such as a remote
Sequence of dead testing Test instrument frost thermostat with its supply taken from a different
Continuity of earth conductors Low reading ohmmeter circuit from that serving the heating system.
Continuity of final ring Low reading ohmmeter This stresses the importance of a visual inspection of
conductors
wiring arrangements and of dead testing. To remedy
Insulation resistance Insulation resistance tester
this situation the frost thermostat would have to be
Polarity Low reading ohmmeter
re-installed as part of a fully controlled system with
According to the Regulation 4(3) of the Electricity at a single point of isolation in accordance with the
Works Regulations 1989, it is preferable that electrical manufacturer’s instructions.
supplies should be made dead before any work begins. It is worth noting that the control systems within a
The regulations do also mention that some work such boiler vary and the manufacturer’s instructions and
as fault finding and testing may require the electrical the boiler labels will indicate if the AC supply has been
equipment to be energised. It is essential that if live transformed to DC.
401
Does the
Yes main burner
ignite?
No
No Is there a faulty or
Replace as necessary Yes blown fuse?
Has there has
been a short No
Replace if Yes circuit on the
necessary external controls Is the main injector
or wiring? Clean the injector Yes blocked?
No No
402
HW HW CH CH
OFF ON OFF ON
Fused to 3 amp
HW switch CH switch
Clock
403
p Figure 5.115
Zone valve
A typical problem with a heating system is the failure CLOSED OPEN
of a zone valve to operate. This will result in either no
heating or no hot water. The first test is visual. If a zone
valve does not open the lever mechanism will not move
p Figure 5.116 Zone valve
and the two most likely reasons are either the control
404
STEP 1 A synchronous motor is removed from a STEP 2 Motor showing a resistance reading. STEP 3 Motor showing an infinity reading.
zone valve and tested with a multimeter set to Ω.
Because the motor is a resistive component there An example of the sequence of switching which can be
should be a reading when probes are connected to the found in a Honeywell S-plan is shown in Figure 5.118
leads attached to the motor. and works in the following way.
If there is an infinity (OL) reading it means that the V4043H V4043H
ZONE VALVE ZONE VALVE
motor is no longer operational and should be replaced. HTG HW
The manufacturer’s instructions provide expected Ωs GREY
BLUE
BLUE GREY
readings for a working component. MOTOR MOTOR
230 V BROWN
KEY TERM 50 Hz
3 A RATED
G/YELLOW
Resistance testing: the Ω scale is used for
G/YELLOW
LNE
ORANGE
ORANGE
example to find out the level resistance of a coil in L641A
CYLINDER
BROWN
a motor, to ascertain whether it works or not, e.g. STAT.
testing a motor on a zone valve.
1 C
1 2 3 4 5 6 7 8 9 10
LOAD
N L
NEL
Resistance is measured HWHTG PUMP
L
across the load. E
ST9420 N
PROGRAMMER
Note: the load must be
BOILER
isolated and disconnected
from the supply.
p Figure 5.118 Honeywell S-plan system
405
406
Flame sensing
probes
Gas valve
Pump
p Figure 5.121 A standard gas fired fanned flued boiler with key p Figure 5.122 External boiler control section with operating
components identified temperature and fault displays to be used in conjunction with
the manufacturer’s fault-finding flow charts
Switches and resistors This is the first step to assess the operation of the
The sequence of operations here represents a series appliance as it is always good practice to operate an
of switches and resistors. A switch controls the flow appliance within an installed system to evaluate if
of a current through a circuit or to a resistor and will all the components are working properly before any
be in either an open or closed position. A resistor work begins. Any problems should be reported and
converts electrical current into a form of energy. documented then discussed with your supervisor or if
The energy could be heat, movement, magnetism or you have been authorised to do so, directly with the
even light. A circulating pump is in fact a resistor as customer. Listening for excessive noise from components
current is used to induce movement into a circulating during operation such as humming, chattering or
impeller. With this information the fault-finding grinding will give some indication of the condition of the
sequence can be identified as switches and resistors. moving parts. Sometimes poor electrical connections
For example the boiler thermostat is a switch while will produce scorch marks and if the problem is not
the fan motor is a resistor and the gas valve solenoid visible the fault can be identified by the smell of burning.
also a resistor. By referring to the manufacturer’s instruction each
LED light on the panel of a modern boiler will reveal
KEY TERMS its functional stage during operation. Often there is a
Switch: component that breaks an electrical circuit digital display on the front of the boiler showing any
by interrupting or diverting current. fault or operational codes. If any faults are evident then
Resistor: a passive thru-terminal electrical direct reference to the manufacturer’s fault-finding flow
component that resists electrical current. chart is required.
407
Boiler thermostat
A boiler thermostat typically consists of a liquid filled
phial which is inserted into a socket on the boiler. This
liquid in this phial expands and contracts in relation to
the ambient heat. The capillary wire is connected onto
liquid bellows which will open or close a switch when
the liquid expands or contracts. The liquid is usually
ethanol based but it used to be mercury on older
appliances.
A dead test can be used to check if a boiler thermostat
switch is functioning. Ensure safe isolation and
disconnect the boiler thermostat from the circuit. By
using the Ω scale, a test can be carried out to check
operation of the thermostat switch.
p Figure 5.123 An engineer referring to manufacturer’s flow charts
STEP 1 The switch is in the closed position as STEP 2 The switch is now in the open position STEP 3 The testing of an overheat thermostat
there is an Ω reading. Sometimes an audible as the meter is displaying the infinity (OL) sign. can be carried out to check if the switch is
buzzer is provided on meters to confirm the operating correctly. Because there is an infinity
By moving the thermostat dial and testing
continuity of a circuit. reading (OL) it means that the switch is open
as shown above, the operation of the boiler
and will require resetting to complete any circuit.
thermostat switch can be verified.
408
Once the signal from the zone valve is received and the
boiler thermostat calls for heat, the electrical signal is
then relayed in conjunction with the control panel, to
operate the fan.
The fan
As an advanced plumber you will invariably be involved
in dealing with problems associated with appliance fans,
and when qualified to do so you will need to be able to
competently fault-find and repair them. In the illustration
shown, the customer has reported that the boiler did
not operate when they turned on the programmer. After
carrying out safe electrical and fuel isolation, a basic
p Figure 5.124 visual inspection and referencing the manufacturer’s flow
A similar test can be carried out on an unvented chart, you could be led to the possible conclusion that
cylinder temperature control which incorporates two the problem is a fan operational failure.
phials, one for the standard operating thermostat and A continuity test while the appliance is safely isolated,
the other for the overheat thermostat. known as a dead test, would confirm whether a wire
The process of dead testing of a switch is shown in or cable had integrity throughout is length. By using
Figure 5.125. an ohmmeter or a multimeter, used on the ohms
setting, the continuity of the wire can be tested. Often
SWITCH
instruments have audible tone when used on the ohms
Switch open circuit, setting and this is very useful when testing.
then infinity (OL) will
show on display. The fan is an essential part of the process of removal of
products of combustion. If it does not operate because of
Note: the load must be
isolated and disconnected poor electrical connections or motor failure, its operation
from the supply. will not be detected on the PCB and the ignition cycle
OPEN will break down. When the fan operates the new
movement of air is sensed by pulse tubes which are
connected to a pressure operated switch. It is important
that those hoses are properly connected and not kinked.
A continuity reading (closed circuit 0Ω) means that
there is a short circuit and if the fan was connected it
SWITCH would blow a fuse.
Switch closed circuit, When checking the performance of the fan motor,
then continuity (c0.00Ω) which is a resistive component, the meter should be set
will show on display.
to the Ω scale. The test leads should then be connected
Note: the load must be across the live and neutral connections.
isolated and disconnected
from the supply. If there is a resistance recorded it would indicate that
CLOSED the component was operating satisfactorily.
When there is an open line (OL) infinity reading it
means that the fan motor resistance winding is broken
and therefore it will not turn the fan.
After confirming safe isolation, the switching function
p Figure 5.125 Dead testing of an air pressure switch can be verified.
409
STEP 1 With appliance safely isolated STEP 2 Resistance displayed on meter STEP 3
remove the connection from the boiler indicates that the fan motor is satisfactory.
circuit.
STEP 4 STEP 5
Air pressure switch The connections of the pulse tubes must be properly
An air pressure switch serves a range of functions as fitted and the electrical connections from the pressure
its ON/OFF action sends signals to the PCB to indicate operated switch should be checked for their condition
whether the fan is running or not. The action of the and continuity.
pressure switch can also prevent the boiler from firing There are two types of pressure switching methods,
if the heat exchanger primary flue way is blocked or one which includes three wires and the other
obstructed. Therefore, it is essential it is tested as part two. The process begins when the PCB checks the
of a boiler safety check. operation status of the switch to see if it is in the
This component consists of a diaphragm which normally closed (NC) position which means that the
responds to the pressure applied to its surface by the fan is not running. A signal is then sent from the PCB
positive and negative movement of air generated by to operate the fan and then it checks that the switch
the fan via the pulse tubes. There the switch is fitted has moved to the normally open (NO) position and
within the component which becomes activated the boiler ignition process begins. The purpose of the
when the diaphragm moves. This then sends a signal sequence is to prevent the boiler from firing when the
to the control panel to begin the ignition process. fan is not running.
410
NC
Voltage is measured
from the supply into
C the switch across to a
suitable neutral
connection.
411
Printed circuit boards (PCB) lead to an electrode situated on the burner. Providing
The control panel of a boiler is linked to the printed there is a gap of about 3–5 mm between the nearest
circuit board and is often a very expensive component. metal components which is usually the gas pilot
Therefore, great care should be taken when inspecting shroud, a spark will travel from the electrode to the
them. There are many components fitted to the shroud, then back to earth. Often the spark rate can be
PCB such as relays, rectifiers and transformers. Safe as high as eight sparks per second.
isolation is imperative and a visual inspection should
precede any physical testing to check for obvious
signs of distress such as scorching or burn marks. The
receiving and sending of signals for components to
operate a boiler mainly come from the PCB. Typical
faults include loose connections and corrosion on the
board. Sometimes the control panel can malfunction
because of component failure on the board itself. This
usually means that the whole unit must be replaced
as modifications are not permitted. However PCBs
are sometimes changed in error because the logical
fault-finding sequence found in the manufacturer’s
instructions has not been followed and individual
components remotely attached to the board have not
been properly tested. Testing of the PCB is often limited
p Figure 5.130 A continuity test on a high tension lead from an
to a continuity test on leads or removable fuses on the electrode to the boiler PCB
circuit board. Manufacturer’s flow charts will help with
diagnosing common problems on printed circuit boards
KEY TERM
and offer a parts list, with specific product reference
numbers to enable accurate replacement. Continuity test: a test to ensure that a conductor
has integrity along its whole length. For example it
could be used to test a high tension lead to ensure
its connection from the spark generator to the
probe on the boiler burner bar is sound.
412
ACTIVITY
Inspect your test equipment to ensure that it is
calibrated then carry out a simple continuity test while
at work. Set your meter to Ω and see if your instrument
has a continuity buzzer. Select a scrap piece of cable
and apply the tips of your tester at each end. First of p Figure 5.132 A solenoid on p Figure 5.133 A side view of a
all take a Ω reading then try with the buzzer function. a gas valve Honeywell multifunctional valve
Once a system has been made electrically safe try
the same test on either side of a fitted pump. If there A multimeter for example could be used to carry out a
are any brass push fitting connectors installed on the dead test on a solenoid with the meter set to read Ω.
copper pipework, carry out the same test again and
make a note of the readings.
p Figure 5.131 Spark ignition in action; the spark can be seen p Figure 5.134 A multimeter
travelling from the tip of the electrode probe to the gas burner
A multifunctional gas valve will incorporate a solenoid
valve, a flame supervision device and a pressure
Gas solenoid regulator. Once the solenoid is activated it will open
Often there are two solenoids fitted on a and gas will flow to the burner. A solenoid can be
multifunctional gas valve and during the ignition tested when in the dead mode by checking the
process which is generated from the control panel, a resistance on the coil to ensure it is operating properly.
simultaneous signal is sent to open the pilot solenoid.
When the pilot flame is ignited the conductance
of the flame enables an electrical signal from the
rectification device to travel back to the control panel,
which in turn allows the main solenoid to open and
the full flow of gas to travel to the burner and ignite.
There are several variations on the ignition process
and the one mentioned incorporates the intermittent
pilot method.
413
AC current DC current
Pilot/burner
Earth
Fan control NO
High
limit
Ignition
control Fan motor
module Pilot and
Pilot line electrode
sensor
414
Hot junction
Copper-nickel Copper-iron
alloy alloy
Cold junction
Insulated
copper
wire Copper sheath
Cold junction
Multivolt
meter
415
416
Power to appliance
(230 V live to neutral)
Yes
Yes
Go to next stage
p Figure 5.145 A sample of a generic chart to show a logical sequence of typical faults on a combi boiler
417
Detection electrodes
Heating flow switch
Ignition electrodes
Power supply/fuse
External controls
Expansion vessel
System pressure
Regulation PCB
Internal wiring
Diverter valve
Internal fuses
Fan venture
Thermistors
Filling loop
Gas valve
Modureg
Polarity
Pump
Fan
No power light
Boiler does not start when tap turned on
Boiler does not start when heating turned on
Pump does not run
Poor hot water
Poor central heating
Noisy ignition
No ignition
No spark
No modulation
Ignition lockout
Fan not detected
DHW overheats
CH overheats
Burner cycles on/off
Flame lifts from burner
Boiler makes groaning sound when tap turned off
Noisy boiler when flame on maximum gas rate
Pump not detected
Boiler runs continually
Rads warm up when running hot water
DHW only available when CH is on
Pressure loss overnight
Pilot out overnight
Ignition lockout first thing in morning
Water leaks from boiler
Low water pressure light on
Safety discharge runs continually
Pressure drops to zero when hot tap turned on
Blowing fuses
When the chart in Figure 5.146 is used in conjunction part of a normal service by a suitably qualified plumber.
with the manufacturer’s flow chart then accurate fault- In addition, it requires a connection to a special feed-in
finding can take place and the correct component can tariff (FiT) meter or smart meter to supply the energy
be replaced or repaired. generated from the stirling engine back into the
electrical grid, which only a fully qualified electrician
The flow chart logic sequence is used for a combination
should undertake (PART P level A).
boiler and will help an engineer identify any faults. This
type of chart is commonly used on many appliances; These appliances provide heating and hot water for a
logical sequences will be added or removed depending domestic dwelling and are controlled in the same way as
on the type of appliance. a standard boiler but with the bonus of the production of
about 3 kW of electrical energy. It is now quite common
New and alternative heat sources for new energy efficient appliances to incorporate more
The appliance in Figure 5.147 is a micro-combined heat advanced electrical controlled systems, hence the need
and power unit and requires an electrical supply to for the modern plumber to improve their knowledge and
energise the controls and pump which can be tested as understanding of electrical installation, testing and fault
finding.
418
Other appliances such as biomass boilers are emerging with fuel they are electrically controlled in much the
on the market and even though some are manually fed same way as an oil or gas boiler.
419
STEP 1 After safely isolating the supply to the STEP 2 Carefully remove the phase (line) STEP 3 Connect one test lead from an insulation
immersion, remove the protective cover on and neutral conductors from the immersion resistance tester to a suitable earth point on the
the cylinder and proceed while referring to the connection using an appropriate tool such as appliance.
manufacturer’s instructions. insulated long nose pliers. Always safely isolate
before beginning any electrical testing.
➜
420
STEP 4 Connect the next test lead to one of the STEP 5 Turn on the tester and set to 500 V. STEP 6 Push the test button and hold for
element connections on the immersion. approximately three seconds.
ACTIVITY
When involved in carrying out a functional test on
a hot water cylinder immersion installation, check
the fuse size in the spur and calculate if it is correct
by using the power triangle equation. Inspect the
consumer unit to ensure that it can be isolated by an
individual MCB which provides a dedicated radial
circuit supply to the fused spur serving the immersion
heater. If a visual test reveals that it is connected to a
ring circuit inform your supervisor.
STEP 7 There will be no fault if the reading shows OL (above 0.5 MΩ is also
acceptable). Any reading below 0.5 MΩ should be investigated further.
Relays – switching and connections
When the test is finished turn off the tester and remove the leads.
Electrical relays are often found in heating components
such as boilers and they are used for the remote control
An immersion removed from a cylinder was tested of switches and frequently for switching on a mains
and the reading was below 0.5 MΩ. voltage circuit by means of a low voltage control.
Both are comprised from an electromagnet and an
armature which moves and in turn operates a switch.
The armature is held away from the magnet by a
spring when the current is off but when energised the
armature is drawn onto the coil and the switch is then
moved to the other position.
Many modern boilers use a solid state relay (SSR) or
semiconductor switches, which have no moving parts
p Figure 5.150 The reading on p Figure 5.151 After a close
and reduce the risk of sparks being created.
this immersion is 0.002 MΩ visual inspection the fault When a relay on a boiler receives a signal from a zone
shown above was found valve micro-switch the ignition sequence will then
begin.
421
INDUSTRY TIP
Where a pull cord switch fitted to a shower shows signs of
burning insulation or terminals, it is likely that the wrong
p Figure 5.152 Lockable socket p Figure 5.153 100 A device has been installed and the pull cord is not correctly
outlet main switch rated to switch the load correctly. Switches capable of
switching the full load current must be installed, not
isolators which are not switch rated.
Lockable socket outlets are often found in situations
where tampering with the supply could cause nuisance
and unauthorised access is thereby prevented. Methods of correcting deficiencies
Pull cord switches
in electrical components
Pull cord switches located on the ceiling are suitable for Defective cables and broken connections
use within a bathroom zone. Their typical applications
For example a plumber working on a gas appliance
include electric showers and gas boiler installation with-
may find that the fan is not operating and as a result
in compartments that are located in restricted zones.
the ignition sequence is halted. The fan may not be
Common problems associated with pull cord switches operating because it is not receiving a signal from the
are failing switching mechanisms and cord breakage. boiler control box and this could be because there is a
It is essential when installing one of these switches fault in that component but it could be because there
that sufficient slack is allowed in the length of the is a broken conductor at the connection, which receives
conductors for the components as any remedial or the signal to power the fan. The fan could be exposed
inspection work would prove difficult at a later date to heat as well as movement and vibration when
owing to the restriction of not being able to open the operating. Broken conductors could occur because of
fitting fully. This is especially important when working work hardening and even thermal movements or if
on fittings located at a high level. there is a very tight radius on the cable or flex where it
makes its connection.
422
423
Fuse carrier
Fuse element
Screw securing
fuse element
Fuse element
Screw securing
fuse element
Re-wireable fuse
If electrical connections are properly fitted with the Loose connections where conductors are fitted cause
appropriate conductors in place, for example a power high resistance and localised heat can occur. Extreme
supply to an electric shower, and during the course scorching or even fire can result when a high current
of its operation one of those conductors is broken, it circuit produces unwanted resistance at a loose
would follow that if this occurred to either the line or connection resulting in a dissipation of hundreds of
the neutral conductor the circuit would stop. If this watts at that weak point. Components, cable and
happened to an earth conductor then a higher risk flex damage can also occur, which could result in the
could be presented as the operation of the system operation of the conductive protective device owing to
protective devices such as MCBs could be compromised the failure of the insulation, creating a short circuit. Fire
which could expose someone to a serious shock hazard. is the worst outcome.
Another effect of loose connections can result in
Loose connections
performance drop in different parts of the circuit with
High resistance faults often occur where conductors
the outcome of appliance damage and even protective
are connected in junction boxes or switches and
devices failing to operate.
connection itself is not tight. The reason for this
could include poor workmanship, dirt or debris in the Loose wiring caused this extreme effect on an unvented
connection itself or the thermal movement of the hot water cylinder immersion. There were also exposed
conductor during its working cycle has resulted in it conductors at the connector on the immersion heater.
working loose. Vibration could also cause the loosening Note: Once the thermostat was removed, the location
of conductors in a cold water booster pump installation of the fault is clear, with the damage originating from
during its working cycle or even acoustic transmissions either a bad wiring connection to the thermostat and/
from percussive water outlets creating water hammer. or incorrect alignment of the thermostat to immersion
Good clipping and effective cable support will help element fasten connection. Both would cause a high
reduce or eliminate these problems. resistance connection.
The effect of high resistance on a loose connection
can lead to localised heating around a connection.
424
425
426
12 One conductor has a voltage of 100 V and 17 What is the maximum fuse rating that can be
another has a voltage of 400 V. used in a fused connection unit?
What reading would a voltmeter give if a 1A
the meter probes were connected to each b 3A
conductor?
c 5A
a 100 V
d 13 A
b 200 V
18 What is the purpose of a proving unit when
c 300 V undertaking the safe isolation procedure?
d 400 V a To check the lock is fixed and secure
13 What is the frequency of the electrical supply in b To ensure the supply to the circuit is dead
the UK?
c To enable the use of multiple padlocks
a 20 Hz
d To verify the function of the voltage indicator
b 50 Hz
19 Describe the safe isolation process.
c 60 Hz
20 Describe the three parts of a cable.
d 100 Hz
21 Explain what is meant by IP54 when
14 What is the value of IP protection that is considering the ingress protection of electrical
regarded as finger protection? equipment.
a IP2X 22 Describe a non-electrical method of testing if a
b IPX2 zone valve operates correctly.
c IP4X 23 Explain what is meant by ‘flame rectification’.
d IPX4 24 Explain the purpose of a split-way consumer
15 What type of drawing shows the location of unit.
electrical accessories in a building? 25 Describe situations where it would not be
a Plan drawing appropriate to bond a metal water pipe using a
main protective bonding conductor.
b Wiring diagram
26 Describe the general requirements of HSE
c Circuit diagram
document GS38.
d Schematic drawing
27 Describe what a motorised zone valve does in a
16 What rating of circuit breaker should be used to central heating control system.
protect a 230 V, 9 kW shower circuit?
Answers can be found online at
a 20 A www.hoddereducation.co.uk/construction.
b 32 A
c 40 A
d 50 A
427
ADVANCED ENVIRONMENTAL
TECHNOLOGY SYSTEMS
Wherever you seem to look these days there are l the operating principles of micro-renewable
environmental technologies being installed and energy and water conservation technology
used commercially and in domestic properties. l the installation requirements of micro-renewable
Governments and house builders are under pressure energy and water conservation technologies
to include a variety of systems to help cut back carbon l the benefits and limitations of micro-renewable
emissions that are contributing to the greenhouse energy and water conservation technologies.
effect, and therefore climate change. As plumbers we
All of these learning outcomes will be addressed for
are looking to install systems that offer practical and
each environmental technology system in turn as
sustainable alternatives to fossil fuels, systems that
follows:
potentially offer heat and power to the property.
l solar thermal (hot water)
This is a growing market area that is here to l ground source heat pumps
stay. Plumbers need to have a good working l air source heat pumps
understanding along with specialist training in l biomass systems
these areas to offer the customer suitable ‘green l combined heat and power (CHP)
technology’ solutions within a domestic property. l rainwater harvesting
l grey water reuse
By the end of this chapter, you will have knowledge
l solar photovoltaic
and understanding of the following:
l micro-wind
l the legislation relating to micro-renewable
l micro-hydro.
energy
428
429
Status Source
Primary legislation Building (Scotland) Act 1984
Secondary legislation Building (Scotland) Regulations
2004 (amended 2009)
Guidance Technical guide books
To hot
Differential
Table 6.4 Building Regulations in Northern Ireland taps
temperature
controller
Hot water
Status Source storage cylinder
takes place. also cheaper. The heat transfer fluid circulates around
the collectors and is directly heated by the Sun. The
Solar thermal (hot water) collectors need to be well insulated to avoid heat loss.
l Evacuated tube collector – an evacuated tube is
systems more efficient, but also more expensive. It consists of
Solar thermal hot water systems use solar radiation a specially coated, pressure-resistant, double-walled
to heat water, either directly or indirectly. Key glass tube. The air is evacuated from the tube to aid
components of these systems include the following: the transfer of heat from the Sun to the pipe housed
inside the tube. The pipe contains a heat-sensitive
430
liquid which vaporises. The warmed gas rises Differential temperature controller
in the tube and the heat is focused on a small The differential temperature controller (DTC) has
heat exchanger, which is plugged into the header sensors connected to the solar collector (high level)
tube. The header tube contains the heat transfer and the hot water cylinder (low level). It monitors
liquid which absorbs the heat from the evacuated the temperature at both points of the system. The
tube. As the gas cools so the heat sensitive liquid DTC switches the circulating pump on when there is
condenses and runs down to the bottom of the enough solar energy available and there is a demand
evacuated tube, ready for the process to start again. for water to be heated. Once the hot water cylinder
The collectors must be mounted at a suitable angle reaches the required temperature the DTC switches
to allow the vapour to rise and condense. the circulating pump off.
Outlet connection
Flow tubes
Insulation: to the bottom and sides of Absorber plate: usually black chrome absorbing
the collector to reduce the loss of heat coating to maximise heat-collecting efficiency
Heat transfer
m
tto
o p bo
Solar energy o t to
absorbed by s t rns
r ise retu
evacuated tube ur d
po ui
Va d liq
e
ns
n de Copper header
C o
Heat absorbed He
by heat pipe at
tr
an
sf
er
431
Circulating pump
This is controlled by the DTC and circulates the
system’s heat transfer liquid around the solar hot water Solar
circuit. The circuit is a closed loop system between collector
the solar collector and the hot water cylinder coil. The
heat transfer fluid is normally water based and would
normally contain glycol so that at night or during Boiler
KEY TERM
Figure 6.4 Twin coil cylinder
Glycol: a liquid anti-freeze which is odourless and
colourless in its raw state.
Solar
INDUSTRY TIP collector
Boiler
432
Location of solar thermal systems The space or area needed to mount the collectors
and building requirements will be dependent on the demand for hot water. The
number of outlets and people living in the property
When deciding to install a solar thermal hot water
determines the demand.
system and whether a particular property is suitable it
l Compatibility with the existing hot water
is important to consider several factors:
system – solar thermal systems provide stored hot
l Orientation of the solar collectors – the best
water and do not provide instant hot water:
direction for a solar collector to face is due south.
l Properties using an under the sink or over the
However, as the Sun rises in the east and sets in the
sink water heater and electric showers will not
west, any location that has a roof facing east, south
be suitable for a solar thermal system.
or west is suitable for mounting these collector
l Properties using a combination boiler to provide
panels on, although the efficiency of the system is
hot water will not be suitable for a solar thermal
reduced for any system not facing due south.
system, unless substantial alterations are made
l Tilt angle of the solar collectors – at different
to the existing system.
times of the year, the elevation or height of the
Sun relative to the horizon does vary – summer
time being the highest and winter time being the VALUES AND BEHAVIOURS
lowest. Ideally, solar collectors should always be
Always read the manufacturer’s instructions
perpendicular to the path of the Sun’s rays.
concerning the installation factors for their system
It is generally not practical to change the tilt angle
and discuss these with the customer to ensure they
of the solar collector. A compromise angle has to be
are clear on the proper operation of their system.
used. In the UK the angle is 35°. However, collectors
will work, but less efficiently, from a vertical to
horizontal position.
KEY TERM
l Shading of the solar collectors – when positioning
collectors, you must be aware of any structure, tree, Perpendicular: at an angle of 90° to a certain
chimney, aerial or other objects that could stand plane. In other words, the Sun’s rays need to be at
90° to the collector where possible for maximum
between the collector and the Sun’s rays. This could efficiency.
mean a visit to the property at different times of
the day to note any potential shadows. The Sun
Table 6.5 The effect of shading on collectors
shines for a limited time each day, so any reduction
in the amount of heat energy reaching the collector Shading % of sky Reduction in
will reduce its ability to provide hot water to meet blocked by output
the demand. obstacles
l The suitability of the structure for mounting Heavy Up to 80% 50%
the solar panel – the structure, quite often the Significant 60–80% 35%
roof area, will need to be surveyed for the chosen Modest 20–60% 20%
mounting system for the collectors. Consideration Little Up to 20% No real reduction
will need to be given to the strength and condition
of the structure and its suitability to the fixing type.
The effect of wind and location must also be taken IMPROVE YOUR ENGLISH
into consideration. The force exerted by the wind A customer lives in a semi-detached property where
on the collectors can be quite noticeable which will the front of the house is north-east facing. It is very
close to the coast line and has a roof angle of 45°. It
affect the collectors and the fixings. is an older style property with slate tiles on the roof.
If the installation is on a property which is jointly Outline the discussion points that need to be raised
owned, such as flats, maisonettes and semi-detached, with the customer.
the ownership of the structure will need to be
carefully considered and discussed with the customer.
433
Planning permission required for In every other case planning permission will be required.
solar thermal systems
Permitted development applies where a solar thermal INDUSTRY TIP
system is installed:
It is always worth asking the local authority about the
l on a property or block of flats
restrictions for these installations in your area.
l on a building within the grounds of a property or
block of flats
l as a standalone system in the grounds of a property
grounds
l it must not exceed 4.0 m in height
Other regulatory requirements
l it must not be installed within 5.0 m of the applicable for solar thermal systems
property boundary l BS 7671 The IET Wiring Regulations – this will
l it must not be more than 9.0 m2 in area cover the installation and maintenance of controls
l no dimension can exceed 3.0 m in length. and circulators.
l For both standalone and building mounted systems: l Approved Document Part G3 Unvented hot water
l the system cannot be installed in the grounds of systems – this will cover the installation of the hot
or be installed on a listed building or monument water cylinder and the temperature at which hot
l if the system is to be installed within a water must be stored.
conservation area or world heritage site then the l Water Supply (Water Fittings) Regulations 1999 – this
system cannot be installed closer to a highway will mainly cover the prevention of contamination
than the property is located. where wholesome water is concerned.
Table 6.6 Building Regulations applicable for solar thermal heating systems
434
435
Expansion valve
Compressor
Heat
Gas output
input 0.95 kW
Evaporator 1 kW (95%
efficiency)
Outside air
436
l heat pump
The higher the CoP value, the greater the efficiency.
l heating system.
The higher CoP values are generally achieved in the The collection of heat from the ground is accomplished
milder weather, because in the colder weather the by means of a pipe run containing a mixture of water
compressor has to work harder to extract the heat. and antifreeze, which is buried in the ground. This type
of system is known as a ‘closed loop system’ There are
Storing excess heat produced three methods of burying the pipe used to collect the
heat, each having advantages and disadvantages:
Heat pumps are not able to provide instant heat, so
l horizontal loops
therefore work better when run continuously. Start-
l vertical loops
stop operations will shorten the lifespan of the heat
l slinkies.
pump. A buffer tank is incorporated into the system so
that when heat is not required in the system, the heat
Horizontal loops
pump can ‘dump’ the heat into the vessel and thus
keep running. When heat is needed, it can be drawn Piping is installed in horizontal trenches that are
from the buffer tank. These buffer tanks can be used about 1.5–2.0 m deep. Horizontal loops require more
with both ground source and air source heat pumps. piping than vertical loops (around 200 m of pipe for
an average house), although a proper calculation will
be required for every installation. This installation will
Buffer tank require a large area to sink the pipework in.
(accumulator)
Heat pump
To
heating
system Ground source to water
heat pump with horizontal
closed-loop collector
437
Vertical loops
Most commercial installations use vertical loops. Holes
are bored to a depth of 15–60 m deep, depending
on soil conditions. Pipes are then inserted into the
boreholes. This style of system needs far less land area,
but the deeper the hole the greater the pump force
required to circulate the system fluid. Access will need
to be available for the drilling rigs.
Heat
pump
Building foundations
omitted for clarity
Borehole
438
Heating cycle
Planning permission
The installation of a ground source heat pump is
Evaporator Condenser
5.5 bar 17 bar Circulating pump usually considered to be a permitted development
and therefore will not require a planning application
to be made. It is always worth checking with the local
authority to find out if they have any criteria that need
Heat source to be adhered to.
Earth
439
Benefits and limitations of GSHPs An ASHP works in a similar way to a refrigerator, but
As with solar thermal systems, there are both benefits the cooled area becomes the outside of the property
and drawbacks to using GSHPs. Advantages include: and the heat is released inside the property.
l The pipework of the pump contains refrigerant that
l high efficiency
heating.
The final heat output from an ASHP is lower than that
of a standard gas boiler. Ideally, an ASHP should be
used in conjunction with an underfloor heating system
or low temperature radiators.
Figure 6.17 Air source heat pump wall to mount the unit.
l There will need to be space around the unit to allow
Key components include: good air flow.
l heat pump containing a heat exchanger, compressor l The ideal system to link an ASHP up to is an
and expansion valve underfloor heating system.
l heating system.
440
Compressor
l The payback period for an ASHP is shorter if it l The ASHP cannot be installed within 1.0 m of the
replaces an electric, coal or oil system, rather than a property boundary.
gas boiler. l The ASHP cannot be installed on a pitched roof.
l If the unit is installed on a flat roof, it must not be
INDUSTRY TIP within 1.0 m of the edge of the flat roof.
l If the unit faces a highway, it cannot be mounted
ASHPs are ideal for new builds where the insulative value of above ground level.
the property is greater and the likelihood of an underfloor l The unit cannot be installed on a designated
heating system being installed is greater. monument.
l The unit cannot be installed on or in the grounds of
a listed building.
Planning permission required for l An ASHP cannot be installed within a conservation
ASHPs area or a world heritage site.
A permitted development applies to an ASHP when:
l it is installed on a house or block of flats ACTIVITY
l it is installed on a building within the grounds of a Use the internet to look up and detail the
house or block of flats Microgeneration Certification Scheme (MCS)
l it is installed within the grounds of a house or block planning standards and what they outline by visiting:
of flats. www.microgenerationcertification.org
441
442
443
quality, so in 1956 the Clean Air Act was formed. It Other regulations applicable for
was subsequently replaced by the Clean Air Act 1993, biomass systems
which made it illegal to sell or burn unauthorised fuel
l The Water Supply (Water Fittings) Regulations 1999
in a smoke-controlled area, unless it was burnt in an
apply. The main area of concern is the avoidance
‘exempt appliance’.
of cross contamination between system water
and wholesome water; this is known as backflow
INDUSTRY TIP prevention.
Exempt appliances are able to burn smoky fuel without l BS 7671 will apply to the installation’s electrical
emitting smoke into the atmosphere. supplies and controls.
be installed, it will normally be classed as permitted l When burnt the waste gases are low in nitrous
development as long as the flue is to the rear or side oxide, with no sulphur dioxide.
elevation and is not higher than 1.0 m above the roof
ridge. INDUSTRY TIP
If the property is a listed building, checks will need to
Nitrous oxide and sulphur dioxide are both greenhouse
be made with the local authority for both internal and gases which are linked to global warming.
external work.
If the property is within a conservation area or in a The disadvantages of installing a biomass system include:
world heritage site, checks will need to be made with l Transportation of the biomass fuel is expensive.
the local authority for internal work, external work and l Storage space is required for the fuel. (Pellets and
any additional construction for storage. chips are bulk delivered.)
l Control of heat is not instant (as it would be for a
Compliance with Building gas boiler). The fuel cannot be instantly removed to
Regulations stop combustion.
The Building Regulations that apply to a biomass l It requires a suitable flue system.
444
produce between 1 kW and 1.5 kW of electricity. Figure 6.21 Component parts of the micro-CHP boiler
These units are known as a carbon-reducing
Key components of the mCHP boiler:
technology rather than a carbon-free technology.
l the engine burner
Heat
Heat Heat
80%
65% 95%
15%
Electricity
Old boiler Condensing boiler Micro-CHP
445
The burner preheats the heating system return water l The Water Supply (Water Fittings) Regulations will
before it passes on to the main heat exchanger. Hot need to be referenced to avoid any contamination
flue gases from the engine burner are passed across the of wholesome water.
heat exchanger to heat the heating system water even l BS 7671 The IET Wiring Regulations will apply to
more. If there is more demand than supply, then the the electrical supply and controls.
supplementary burner operates. l G83 requirements will have to be followed when
connecting the generator to the system.
The Stirling engine within the unit uses the expansion
l Microgeneration Certification Scheme will need to
and contraction of internal gases to operate the piston.
be referred to when electricity is generated.
The gases do not leave the engine and no explosive
combustion takes place. Helium is often used as the Benefits and limitations of mCHP
internal gas. When the engine burner fires, the helium The advantages of installing an mCHP system include:
expands, forcing the piston downwards. The return water l It has the ability to produce electricity and not be
from the heating system passes across the engine causing dependent on building direction or weather conditions.
the gas to contract. A spring mechanism in the engine l The system generates electricity while there is
returns the piston to the stop and the process starts again. demand for heat.
l A feed in tariff is available (but there are limitations).
heat/well insulated).
Location and building requirements l It has limited capacity for electrical generation.
446
The Code for Sustainable Homes sets a target for Looking at how water is used, you can see that on
reducing average drinking water consumption from average the amount of water used for drinking or
150 litres per person per day to an optimum of 80 litres. food preparation (potable) is estimated to be around
3.4 per cent of the total consumption. This outlines
ACTIVITY that there are obvious opportunities for water savings.
Access ‘The Code for Sustainable Homes’ and list
Table 6.10 Types of water
the areas being highlighted for new builds.
www.theccc.org.uk/wp-content/uploads/2019/02/ Terminology Meaning
UK-housing-Fit-for-the-future-CCC-2019.pdf Wholesome, potable water Water that is suitable for
human consumption. The
water supplied from the local
At present the adopted target is 103 litres; Part G water authority to properties
sets the level at 125 l. Whichever target is used, the in the UK is known as
conclusion is that a reduction in consumption from WHOLESOME or POTABLE
150 litres is vital. Rainwater Water captured from the roof
line of a property when it
rains, flowing into the gutter
VALUES AND BEHAVIOURS Grey water
and downpipe to be collected
Waste water from wash
Given the demands for water and the problems basins, showers, baths and
water extraction from rivers and lakes causes, washing machines
it is essential that better use is made of the Blackwater Sewage
available water. More houses are being built and
the people living in those houses are putting
a demand on the water supply. This increased Rainwater harvesting
demand affects water levels in rivers and Rainwater harvesting refers to the process of capturing
reservoirs and therefore puts pressure on the and storing rainwater from the surface it falls on, rather
natural environment around them. Customers than letting it run off into the drains. The harvesting
are becoming well informed about water of rainwater can result in sizeable reductions in
conservation, so it is important to be able to wholesome water usage. Instead of refilling the WC
discuss these technologies with them. with wholesome water, the WC could be refilled with
rainwater. Every time a WC is fully flushed it uses 6
litres of water. Water authorities claim 1 litre of tap
Clothes washing 13%
water costs around 1p. Over a period of time this adds
Washing up and
up. This offers financial savings for the customer and
cleaning 8.6%
Toilet
carbon reductions in the environment.
flushing
28.1% If harvested water is correctly filtered, stored and used
regularly, it will not remain in the storage tank for
Other 6.1%
excessive periods of time. It can be used for:
l flushing toilets
Garden l car washing
watering 6.6%
l garden watering
l washing dishes
Figure 6.22 How water is used
l food preparation
447
Collection
Reuse
Filtration
Storage
448
The size of the tank will be determined by the rainwater Rainwater inlet
available and the demand for the harvested water. Air gap for Water
Regulations compliance
Different manufacturers offer various calculators to size Rainwater level control
the tank effectively. Wholesome water level control
A submersible pump is used to transport the water Overflow
the loft. This in turn feeds the outlets under low warming and sunlight
pressure within the property. l if below ground, tanks need excavation work.
449
450
l garden watering
Figure 6.26 Rainwater harvesting l washing clothes (after additional treatment).
451
Overflow to sewer
Toilet and kitchen to sewer
l distribution system (moving the stored water to the This type of system would normally be fitted in a new
point of use) build as it is more difficult to retrofit. This system is
l some form of treatment.
452
best suited for a self-contained bathroom and toilet, thrive in water logged conditions, transfer oxygen
collecting and serving the water within the same room. to their roots. The grey water is allowed to infiltrate
through the reed bed. The added oxygen from the
Physical and chemical system roots of the reeds and the naturally occurring bacteria
This system uses a filter to remove the physical debris remove the organic matter contained in the grey water.
from the collected water. After the water has been The disadvantage of reed beds is the land area required
filtered, chemical disinfectants such as chlorine or and the expertise required.
bromine are added to prevent any bacterial growth
There are companies that make and offer smaller-
whilst the water is stored.
scale systems, such as the green roof recycling system
(GROW).
Biomechanical system
This type of system is the most advanced of the
ACTIVITY
grey water reuse systems. It uses both biological and
Research reed bed filtration systems to assess the
physical methods to treat the collected grey water.
range of systems available in the UK.
These systems vary in size, but on average are a similar
size to a large refrigerator.
Grey water enters the system through the filter, where Location and building requirements
particles like hair and textiles are filtered out. The When considering the installation of a grey water reuse
filter is monitored electronically and is flushed out system, the following should be taken into account:
periodically. The water then enters the main recycling l a suitable supply of grey water to meet the demand
chamber where organic matter is decomposed using l suitability of location and availability of space to
bio-cultures. The grey water remains in this chamber store the grey water
for three hours before being pumped into the second l storage tanks need to be located away from heat
chamber for further bio-culture treatment. Biological and direct sunlight to avoid algae growth
sediment settles at the bottom of both these l location or storage needs to be protected from
into the final storage tank where it is ready for use. l access for excavation equipment may be required
453
Grey water
water reuse systems
l The Water Supply (Water Fittings) Regulations 1999
apply. The main area of concern is the avoidance
of cross contamination between grey water and
wholesome water; this is known as backflow
prevention. Grey water is classified as category 5,
which is a high health risk. The usual method is by
use of an air gap.
l Any pipework used to supply outlets and any outlet
using grey water needs to be labelled to avoid any
mistakes.
l The local authority must be informed prior to
installing a grey water system.
BS 7671 will apply to the installation’s electrical
Not Suitable
l
Table 6.12 Building Regulations applicable for grey water reuse systems
454
l only certain appliances can be supplied by grey The major advantages of these technologies are that
water reuse they do not use any of the planet’s dwindling fossil fuel
l potential cross contamination risk resources. They also do not produce any carbon dioxide
l water meter will need to be fitted on the property (CO2) when running.
supply
With each of the electricity-producing micro-renewable
l the need for filtering and pumping contributes to
energy technologies, two types of connection exist:
the property carbon footprint.
l on-grid or grid-tied – where the system is
Demand 2 kW
455
INDUSTRY TIP There are many arrangements for PV systems but they
can be divided into two categories:
Photovoltaic is probably the most common system being l off-grid systems, where the PV modules are used to
installed. It is fairly simple to install and requires minimum charge batteries
disruption when connecting the system to the meter l on-grid systems, where the PV modules are
position.
connected to the grid supply via an inverter.
The key components of an off-grid PV system are:
Working principles l PV modules
The basic element of photovoltaic energy production l a PV module mounting system
that sits between that of an insulator and a conductor. l a deep-discharge battery bank
the making of PV cells, the most common material is Other components, such as isolators, will also be
silicon. Adding a small quantity of a different element required.
456
PV Charge a.c.
Batteries Inverter
module controller equipment
15 to 20 per cent.
l Polycrystalline modules range in efficiency, from
457
ACTIVITY
What is the purpose of an inverter?
Metering
A generation meter is installed on the system to record
the number of units generated, so that the feed-in tariff
can be claimed. Figure 6.35 Ideal orientation is south
458
W
Figure 6.37 Shading of PV system
Tilt
30º to 40º Location within the UK
N
The location within the UK will determine how much
sunshine will fall, annually, on the PV array and, in turn,
this will determine the amount of electricity that can
PV array facing south at fixed tilt be generated. For example, a location in Brighton will
generate more electricity than one in Newcastle, purely
because Brighton receives more sunshine.
Azimuth
S
E The suitability of the structure for
Figure 6.36 Ideal tilt is 30–40° mounting the solar collector
The structure has to be assessed for its suitability for
Shading of the PV array fixing the chosen mounting system. Consideration
needs to be given to the strength of the structure, the
Any structure, tree, chimney, aerial or other object
suitability of fixings and the condition of the structure.
that stands between the PV array (collector) and
Consideration also needs to be given to the effect
the Sun will prevent some of the Sun’s energy from
known as ‘wind uplift’, an upward force exerted by
reaching the collector. The Sun shines for a limited
the wind on the module and mounting system. The
time and any reduction in the amount of sunlight
strength of the PV array fixings and the fixings holding
landing on the collector will reduces its ability to
the roof members to the building structure must be
produce electricity.
great enough to allow for wind uplift.
In the case of roof-mounted systems on flats and other
shared properties, consideration must also be given to
the ownership of the structure on which the proposed
system is to be installed.
459
Connection to the grid Table 6.13 Building Regulations applicable for solar
photovoltaic systems
A spare way within the consumer unit will need to be
available for connection of the PV system. If one is Building Title Relevance
not available then the consumer unit may need to be Regulation
changed. A Structure The PV modules will impose
both downward force and
Planning permission wind uplift stresses on the
roof structure
Permitted development applies where a PV system is
B Fire safety The passage of cables through
installed: the building fabric could
l on a dwelling house or block of flats reduce the fire-resisting
l on a building within the grounds of a dwelling house integrity of the structure
or block of flats C Resistance to The fixing brackets for on-roof
contaminants systems and the passage of
l as a stand-alone system in the grounds of a dwelling
and moisture cables through the building
house or block of flats. fabric could reduce the moisture-
resisting integrity of the structure
However, there are criteria to be met in each case.
E Resistance to The passage of cables through
For building-mounted systems: the passage of the building fabric could
l the PV system must not protrude more than sound reduce the sound-resisting
properties of the structure
200mm from the wall or the roof slope
L Conservation of The efficiency of the system
l the PV system must not protrude past the highest
fuel and power and the building overall
point of the roof (the ridgeline), excluding the
P Electrical The installation of the
chimney. safety components and wiring system
For stand-alone systems the following criteria must be
met. Compliance with Building
l Only one stand-alone system is allowed in the
Regulations
grounds.
l The array must not exceed 4 m in height.
The regulations outlined in Table 6.13 will apply.
l The array must not be installed within 5 m of the
Other regulatory requirements
boundary of the grounds.
l The array must not exceed 9 m2 in area.
applicable for solar photovoltaic systems
l No dimension of the array may exceed 3 m in
l BS 7671 The IET Wiring Regulations will apply to
length. the PV installation.
l G83 requirements will apply to on-grid systems
For both stand-alone and building-mounted systems up to 3.68 kW per phase; above this size the
the following criteria must be met. requirements of G59 will need to be complied
l The system must not be installed in the grounds or
with. (G83 and G59 are both specific Engineering
on a building within the grounds of a listed building Recommendations that cover part of the installation
or a scheduled monument. and commissioning of PV systems.)
l If the dwelling is in a conservation area or a World
l Microgeneration Certification Scheme requirements
Heritage Site, then the array must not be closer to a will apply.
highway than the house or block of flats.
l In every other case, planning permission will be
INDUSTRY TIP
required.
All systems will require some penetration of the building
ACTIVITY fabric, be it the roof or walls, depending on the building
What documentation should be completed by the type and construction. You should be able to describe the
electrical installer after testing the new PV installation? methods of making good for all building fabrics.
460
Benefits and limitations of solar A HAWT has a tailfin to turn the turbine so that it is
photovoltaic systems facing in the correct direction to make the most of the
available wind. The gearbox and generator will also be
Advantages of solar photovoltaic systems include the
mounted in the horizontal plane.
following:
l They can be fitted to most buildings. Vertical-axis wind turbines, of which there are many
l There is a feed-in tariff available for electricity different designs, will work with wind blowing from any
generated, regardless of whether it is used on site or direction and therefore do not require a tailfin. A VAWT
exported to the grid. also has a gearbox and generator.
l Excess electricity can be sold back to the
roof area.
l It requires a relatively large array to offset
installation costs.
l It gives variable output that is dependent on the
Figure 6.38 Horizontal-axis wind turbine
amount of sunshine available. Lowest output is at
times of greatest requirement, such as at night and Rotor
in the winter. Savings need to be considered over diameter
the whole year.
l There is an aesthetic impact (on the appearance of
the building).
Micro-wind
Wind turbines harness energy from the wind and turn
it into electricity. The UK is an ideal location for the
installation of wind turbines, as about 40 per cent of
Europe’s wind energy passes over the UK. A micro-wind
turbine installed on a suitable site could easily generate Rotor
blade
more power than would be consumed on site.
Working principles
Generator
The wind passing the rotor blades of a turbine causes Gearbox
it to turn. The hub is connected by a low-speed shaft
to a gearbox. The gearbox output is connected to a
high-speed shaft that drives a generator which, in turn, Vertical axis
produces electricity. Turbines are available as either Figure 6.39 Vertical-axis wind turbine
horizontal-axis wind turbines (HAWT) or vertical-axis
wind turbines (VAWT).
461
The two types of micro-wind turbines suitable for the output varies in both voltage and frequency. The
domestic installation are: output is connected to a system controller, which
l pole-mounted, free-standing wind turbines rectifies the output to d.c.
l building-mounted wind turbines, which are generally
In the case of an on-grid system the d.c. output from
smaller than pole-mounted turbines.
the system controller is connected to an inverter which
Micro-wind generation systems fall into two basic converts d.c. to a.c. at 230 V 50 Hz, for connection
categories: to the grid supply via a generation meter and the
l on-grid (grid-tied), which is connected in parallel consumer unit.
with the grid supply via an inverter
With off-grid systems the output from the controller is
l off-grid, which charge batteries to store electricity
used to charge batteries so that the output is stored for
for later use.
when it is needed. The output from the batteries then
The output from a micro-wind turbine is wild feeds an inverter so that 230 V a.c. equipment can be
alternating current (a.c.). ‘Wild’ refers to the fact that connected.
Grid
Controller Inverter
connection
462
l turbine noise, vibration, flicker. Figure 6.42 A suitable site for a micro-wind turbine
Prevailing wind
10 h+
463
The distance of the shadow-flicker zone from the the building or within the grounds of the building.
turbine will be at its greatest when the Sun is at its l The highest part of the wind turbine (normally the
lowest in the sky. blades) must not protrude more than 3 m above the
ridge line of the building or be more than 15 m in
height.
l The lowest part of the blades of the wind turbine
monument
l a listed building
464
l The wind turbine cannot be installed on the roof Benefits and limitations of
or wall of a building that fronts a highway, if that micro-wind turbines
building is within a conservation area.
Advantages of micro-wind turbines include the
The following conditions also apply. following:
l The blades must be made of non-reflective material. l They can be very effective on a suitable site as the
l The wind turbine should be sited so as to minimise UK has 40 per cent of Europe’s wind resources.
its effect on the external appearance of the building. l There are no carbon dioxide emissions.
The regulations outlined in Table 6.14 will apply. l This can be a very effective technology where mains
465
exiting the turbines and returns it to the main This is used in calculations of potential power
stream of the river. generation and takes into account losses due to friction,
as the water passes through the penstock.
See Figure 6.46.
Flow
This is the amount of water flowing through the water
course and is measured in cubic metres per second (m3/s).
Intake
Canal
Forebay
Penstock
Head
Powerhouse
Tailrace
INDUSTRY TIP
The idea of water turbines sounds great but of course
few people live near a water course that is suitable for
this application. PV and solar thermal systems are more
adaptable for different locations.
466
Turbines
There are many different types of turbine but they fall
into two primary design groups, each of which is better
suited to a particular type of water supply.
Impulse turbine
In an impulse turbine, the turbine wheel or runner
operates in air, with water jets driving the runner. The
water from the penstock is focused on the blades
by means of a nozzle. The velocity of the water is
increased but the water pressure remains the same
so there is no requirement to enclose the runner in a
pressure casing. Impulse turbines are used with high- Figure 6.49 Pelton turbine
head water sources.
Turgo
This is similar to the Pelton but the water jet is
designed to hit the runner at an angle and from one
side of the turbine. The water enters at one side of
the runner and exits at the other, allowing the Turgo
turbine to be smaller than the Pelton for the same
power output. This type of turbine is used with water
sources with medium or high heads of water.
Pelton
This consists of a wheel with bucket-type vanes set
around the rim. The water jet hits the vane and turns
the runner. The water gives up most of its energy and Figure 6.50 Turgo turbine
falls into a discharge channel below. A multi-jet Pelton
turbine is also available. This type of turbine is used Cross-flow or Banki
with water sources with medium or high heads of With this type of turbine the runner consists of two
water. end-plates with slats, set at an angle, joining the two
discs, much like a water wheel. Water passes through
the slats, turning the runner and then exiting from
below. This type of turbine is used with water sources
with low or medium heads of water.
467
Kaplan (propeller)
This works like a boat propeller in reverse. Water
passing the angled blades turns the runner. This type
of turbine is used with water sources with low heads of
water.
Reaction turbine
In the reaction turbine, the runners are fully immersed
in water and are enclosed in a pressure casing. Water Figure 6.53 Kaplan or propeller turbine
passes through the turbine, causing the runner blades
to turn or react. Reverse Archimedes’ screw
The Archimedes’ screw consists of a helical screw
thread, which was originally designed so that turning
the screw – usually by hand – would draw water up
the thread to a higher level. In the case of hydro-
electric turbines, water flows down the screw, hence
reverse, turning the screw, which is connected to the
generator. This type of turbine is particularly suited
to low-head operations but its major feature is that,
due to its design, it is ‘fish-friendly’ and fish are able
to pass through it, so it may be the only option if a
hydro-electric generator is to be fitted on a river that is
environmentally sensitive.
Francis wheel
Water enters the turbine housing and passes through
the runner, causing it to turn. This type of turbine is
used with water sources with low heads of water.
Figure 6.54 Reverse Archimedes’ screw
468
469
There are three types of licence that may apply to a l A feed-in tariff is available.
hydro-electric system. l There is a reasonable payback period.
l An abstraction licence will be required if water l It is an excellent system where no mains electricity
is diverted away from the main water course. exists.
The major concern will be the impact that the l It is not dependent on weather conditions or
project has on fish migration, as the majority of building orientation.
turbines are not fish-friendly. This requirement may Disadvantages include the following:
affect the choice of turbine. It may mean that fish l It requires a high head or fast flow of water on the
screens are required over water inlets or, where the property.
turbine is in the main channel of water, a fish pass l It requires planning permission, which can be
around the turbine may need to be constructed. onerous.
l An impoundment licence – an impoundment is any
l Environment Agency permission is required for
construction that changes the flow of water, so if water extraction.
changes or additions are made to sluices, weirs, etc l It may require strengthening of the grid for grid-tied
that control the flow within the main stream of systems.
water, an impoundment licence will be required. l Initial costs are high.
l A land drainage licence will be required for any
470
471
13 Which of the following would be a crucial 18 Which item is a central component of a micro-
component in a solar thermal installation? CHP boiler?
a Condenser a Stirling engine
b Ground loop b Compressor
c Water filter c Evaporator
d Evacuated tube d Flat plate collector
14 Which Building Regulation must be complied 19 Approximately what percentage of used water
with when installing a solar PV system? within a domestic property is used to flush
a K toilets and could be saved if a rainwater
harvesting system were installed?
b D
a 12%
c L
b 17%
d M
c 28%
15 Which phrase is correct in relation to a heat
source (air or ground) installation? d 33%
a The smaller the temperature difference 20 Which of the following fuels is carbon neutral?
between the refrigerant and the heat source, a Natural gas
the greater the efficiency b Peat
b The larger the temperature difference c Oil seed rape
between the refrigerant and the heat source,
d Coal
the greater the efficiency
21 Why is it important to have a high coefficient of
c The smaller the temperature difference
performance?
between the refrigerant and the heat source,
22 List and outline the Building Regulations that a
the lower the efficiency
grey water system comes under.
d The larger the temperature difference
between the refrigerant and the heat source, Regulation Title Relevance
the lower the efficiency
16 When installing an air source heat pump, what
item can store additional heat until required by
the system?
a Hot water cylinder
b Expansion vessel
c Accumulator
d Condenser
23 Describe why a twin coil cylinder should be
17 Why is the net result of a biomass system used on a solar thermal system.
‘carbon neutral’?
24 Describe the working principle of a solar
a It does not release any carbon dioxide when thermal collector.
burnt
25 Outline why Building Regulations Part E is
b The carbon dioxide that is produced is important to consider when installing an ASHP.
retained within the system
c The biomass material absorbs carbon dioxide
when it grows
d The carbon (ash) left over is put back into
the ground
472
Regulation for
England and Wales Content
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Outside air
27 Describe why ‘shading’ is a consideration when
29 State four benefits and four limitations for a
designing a solar system.
grey water reuse system.
28 Complete the following diagram for the
Answers can be found online at
refrigeration process, identifying the following
www.hoddereducation.co.uk/construction.
parts:
● Expansion valve
● Compressor
● Condenser
● Evaporator
473
For hundreds of years humans relied on solid fuel in reserves set to last only 50 years and much of the
the form of wood and coal to heat their homes. Then, coal left below the Earth’s surface unreachable, we
in the 1850s, gas in the form of coal gas was used have to look for alternative forms of energy for our
to heat and light dwellings and factories. This was heat and light.
followed soon after by oil.
This chapter will investigate the types of fuels used
These fuels, coal, gas and oil, are known as in the appliances we install and identify the reasons
hydrocarbons and, because of the way they were that certain fuels are chosen. We will also take a look
formed millions of years ago, they are very carbon at how these fuels are supplied and stored, and the
rich. When they are combusted, they produce physics of the combustion of fuels. Finally, we will
copious amounts of CO2 which has systematically study the construction of flues and chimneys and how
altered the Earth’s climate and this has led to the we test them to ensure the safety of the customer.
phenomenon known as global warming.
The learning outcomes for this chapter are:
Now, less than 300 years later, hydrocarbon fuels are l factors affecting fuel selection
all but depleted and the damage to the climate they l combustion processes of fuel supply systems
have caused practically irreparable. With gas and oil l principles of chimney/flue systems.
474
Natural gas is composed primarily of five combustible l butane – four atoms of carbon and 10 atoms of
gases, two inert gases and water vapour. hydrogen (C4H10)
l iso-butane is butane that has the same elements,
The distinctive ‘rotten eggs’ smell that natural gas has but these are connected in a slightly different way.
is added to the gas when it is cleaned of the impurities
q Table 7.2 The composition of LPG fuels
and naphtha it contains at the refinery. The smell is
a chemical called mercaptan and is added to aid the LPG attribute Propane Butane
detection of gas leaks. Chemical formula C3H8 C4H10
Natural gas is lighter than air, having a specific gravity Energy content: MJ/m3 95.8 111.4
of 0.6–0.8. Energy content: MJ/kg 49.58 47.39
Boiling temp: Cº −42 −4
Natural gas is available in most cities, towns and
Pressure @ 21ºC: kPa 858.7 215.1
villages through a national grid of underground pipes,
with only the most isolated of places not connected to Flame temp: Cº 1967 1970
KEY TERMS
Both of these compounds are heavier than air in
Naphtha: a waxy oil deposit that is present in
their gaseous form, with propane having a specific
natural gas in its unrefined state. It is removed
and later reused in other products such as gravity of 1.5 and butane having a specific gravity
cosmetics. of 2.0. In liquid form both are thinner than water,
Calorific value: the amount of energy stored in butane having a relative density of 0.58 and
the gas in its uncombusted state. It is the amount propane, 0.51.
of energy released when the gas is combusted.
It is measured in megajoules per cubic metre When LPG gas is subjected to high pressure, it turns
or MJ/m3. into a liquid, but it also takes up less space than
the gas. One litre of LPG in its liquid state makes
274 litres of LPG gas. This means that one cylinder
Liquid petroleum gas (LPG) of LPG liquid is equivalent to 274 cylinders of
Liquid petroleum gas, like natural gas, is a fossil LPG gas.
hydrocarbon fuel that is closely linked to oil. About
two thirds of all LPG used is extracted directly from oil
wells; the rest is extracted during the manufacture of
petroleum from crude oil. 274 litres
LPG gas
There are many types of LPG but, generally, only two
types of LPG are used commercially. These are propane
and butane. These gases share common elements but
in different quantities and these are reflected in their 1 litre
LPG liquid
chemical symbols:
p Figure 7.1 Liquid to gas ratio
l propane – three atoms of carbon and eight atoms of
hydrogen (C3H8)
475
Compound Uses
Butane Used for portable supplies, such as camping
(C4H10) equipment, boats and barbecues. Not much
use for plumbing or heating installation as it
boils (turns from a liquid to a gas) at −4 °C.
Propane Has a very low boiling point at −42 °C.
(C3H8) Can be used in domestic situations as an
alternative to natural gas where the mains
gas supply is not available. Many appliances
are available for use with propane, including
boilers, cookers, fires and water heaters.
Iso-butane Used as a refrigerant in domestic p Figure 7.2 A domestic kerosene oil tank for oil fired heating
(C4H10) refrigerators and fridge/freezers.
Environmentally, LPG is relatively clean when compared Solid fuel (coal, coke and peat)
to other fuels such as coal or oil, creating far less air
There are three main types of solid fuel. These are:
pollution in the form of soot and carbon particulates,
l coal
sulphur and carbon dioxide and, therefore, adds less to
l coke
global warming than might be realised.
l peat.
Cost, however, is an issue, since LPG is much more
expensive than conventional natural gas. Coal
This is a fossil fuel created from the remains of plants
Fuel oil (kerosene grade C2, 28 that lived and died between 100 and 400 million years
second viscosity oil to BS 2869:2017) ago when large areas of the Earth were covered with
A simple definition for fuel oil is a liquid by-product of huge swamps and forest bogs.
crude oil, which is produced during petroleum refining.
The energy that we get from coal comes from the
There are two main categories under which it is classified.
energy that the plants absorbed from the Sun millions
One is distillate oils, such as diesel fuel, and the others
of years ago. The process is called photosynthesis.
are residual oils, which includes heating kerosene. It is
When plants die, this stored energy is usually released
distillate fuel oil that is generally used for home heating.
during the decaying process, but when coal is formed
Around 95 per cent of domestic boilers burning fuel the process is interrupted preventing the release of the
oil in domestic properties use kerosene, which is also trapped solar energy.
known generically as C2 grade 28 second viscosity oil.
As the Earth’s climate evolved and the vegetation died,
This is the preferred oil fuel grade for domestic heating,
a thick layer of rotting vegetation built up that was
due to its clean combustion. Modern oil central heating
covered with water, silt and mud, stopping the decaying
boilers only require a single annual service, if being used
process. The weight of the water and the top layer
with an atomising pressure jet burner. It is the only oil
of mud compressed the partially decayed vegetation
grade that can be used with balanced or low-level flues.
under heat and pressure, squeezing out the remaining
Kerosene has very good cold weather characteristics oxygen leaving rich hydrocarbon deposits. What once
and remains fluid beyond minus 40 °C although it does had been plants gradually fossilised into a combustible
tend to thicken slightly during extremely cold weather. carbon-rich rock we call coal.
Kerosene is a high carbon fuel and is clear or very pale
Types of coal
yellow in colour. Newer boilers have a label inside
the casing with information on nozzle size and pump Coal is classified into four main types, depending on
pressure that show that the boiler has been set up to the amount of carbon, oxygen, and hydrogen present.
use kerosene. It may also reference the British Standard The higher the carbon content, the more energy the
for kerosene BS 2869 grade C2. coal contains.
476
Coal is still used for central heating boilers both domestic absence of oxygen, in boggy waterlogged ground. This
and industrial and for steam and electricity generation. encourages the growth of moss which forms the basis
of the peat. As the plants die, they do not decompose.
Instead, the organic material slowly accumulates as peat
because of the lack of oxygen in the bog. Peat is a poor-
quality fossil fuel which is easily cut and dried.
Peat has a high carbon content, but much less than coal,
with large amounts of ash produced during combustion.
It is used in many domestic fires, room heaters and
peat-burning stoves.
methane gas and coal tar, both of which can be cleaned to describe many different types of solid and liquid
and reused. Coke burns cleanly and without a flame fuels. It is defined as any plant or animal matter used
and gives out a lot of heat but it has to be mixed with directly as a fuel or that has been converted into
coal as it will not burn by itself. other fuel types before combustion. When used as
a heating fuel, it is generally solid biomass including
Coke is a smokeless fuel that is valued in industry
wood pellets, vegetal waste (including wood waste
because it has a calorific (heat) value higher than any
and crops used for energy production), animal
form of natural coal. It is widely used in steel making
materials/wastes and other solid biomass.
and in certain chemical processes but can also be used
l Heat pumps – a heat pump is an electrical device
in many domestic boilers and room heaters.
with reversible heating and cooling capability.
Peat It extracts heat from one medium at a low
temperature (the source of heat) and transfers it to
Peat is an organic material that forms over hundreds of
another at a high temperature (called the heat sink),
thousands of years from the decay of plant material in the
cooling the first and warming the second. They
477
work in the same way as a refrigerator, moving heat l Combined cooling, heat and power (CCHP) – very
from one place to another. Heat pumps can provide similar to CHP (see above), combined cooling, heat and
space heating, cooling, water heating and air heat power uses the excess heat from electricity generation
recovery. There are several different types: to achieve additional building heating or cooling.
l ground source heat pumps l District heating – this uses the principle of CHP
l air source heat pumps to supply low-carbon, high-efficiency heat to high-
l water source heat pumps density properties, businesses and public buildings. This
l geo-thermal heat pumps. system is used extensively in mainland Europe to good
l Combined heat and power (CHP) – combined heat effect. In the UK, there are more than 17,000 district
and power is a plant where electricity is generated heating systems installed, mainly in city areas. District
and the excess heat generated is used for heating. heating relies on high efficiency and areas with a large
It is used primarily for district heating systems, but and dense population. There is one highly efficient
micro-CHP has also been developed for domestic heat source: heat from this source is transferred
properties. through plate heat exchangers into the primary pipe
Hot water
storage
cylinder
Secondary heat
exchanger Hot water outlet
Expansion
Pressure vessel Expansion
Boiler relief vessel Pressure
relief Solar collector
Control system
478
Services Domestic
distribution properties Flow Return
Stack
Electrical distribution station
Heat exchanger
Power supply
Control
panel
Thermal
store
Gas
turbine
Transformer
Generator
Natural gas supply
Factors that affect the l Appliance type – the type of fuel available will
dictate the type of appliance used and vice-versa.
selection of fuels Some appliances may be duel-fuel types, where two
There are many reasons why the fuels used in domestic types of fuel may be used in the same appliance. It
appliances are chosen: must be remembered that gas appliances must be
l Availability – the availability of fuels plays a big purchased in line with gas type available. A natural
part when choosing the right fuel for an installation. gas appliance CANNOT be used on an LPG supply.
For example, for most of the UK, natural gas is Similarly, a coal fired boiler will have solid fuels
available piped to the home with no interruption recommended by the manufacturer and must not
of supply. However, in many rural areas, piped gas be used with other types of solid fuel.
supply is many miles away. In this instance, like l Fuel storage requirements – with exception of
other fuels such as coal and oil, gas is delivered natural gas, all fuels require storage space within
by suppliers and the customer is dependent on a the boundary of the property. With solid fuels and
regular fuel delivery. Whilst in most cases this does biomass, these can take up considerable space.
not pose a problem, in times of inclement weather, Biomass also needs to be kept reasonably dry.
deliveries may be interrupted or cancelled, leaving Where oil and LPG are concerned, space may not
the customer with no means of heat or cooking. be the issue. However, safe distances from the
479
assist in the compliance of the regulations. Many voluntary, but being a member is considered good
guidance notes are produced by the Health and practice. OFTEC registration means that installers
Safety Executive. They should be read in conjunction are able to self-certify installations without the
with the regulations and manufacturer’s instructions. need for local authority intervention and inspection.
OFTEC also administer recognised and authorised
KEY POINT training courses for installers.
There is a comprehensive list of British Standards l HETAS – this is the official body that is recognised
in Approved Document J of the Building by the UK Government for approving solid fuel
Regulations – Combustion appliances and fuel and biomass domestic heating systems, fuels and
storage systems. appliances. HETAS also manage a register of approved,
competent installers and servicing businesses and
oversee HETAS registered training courses.
Regulatory bodies that
govern the installation of INDUSTRY TIP
fuel systems More information can be found at:
Before we investigate the regulatory bodies concerned www.gassaferegister.co.uk
with the installation of fuel systems and appliances, we www.oftec.co.uk/technicians/industry-news-and-training/
must first understand what a regulatory body is. training-for-heating-technicians
A regulatory body is an organisation set up by the www.hetas.co.uk/professionals/training-courses
Government to monitor, control and guide various
sectors within industry. Its aims are to protect
consumers and to educate and guide installers in
the ways of good practice. Occasionally, it may be
necessary for a regulatory body to prosecute, in the
interests of public safety, those installers who refuse to
comply with regulations. In the plumbing and heating
industry, it is compulsory to belong to the regulatory
bodies if you engage in the installation of either gas,
oil or solid fuel appliance and fuel supply systems.
KEY TERM
Regulatory body: an organisation set up by the p Figure 7.8 OFTEC logo
Government to monitor, control and guide various
sectors within industry.
481
shovelling of the fuel. Oil tanks should be inspected annually as part of the
l If the fuel is stored in a coal bunker, a slight slope
heating system regular servicing. Oil tanks have a
on the base of a coal bunker prevents water from useful working life of around 20 years and using a tank
collecting inside the bunker. Keeping the fuel dry beyond this time carries the risk of failure.
makes it easier to combust.
Protection of the environment
l The area around the coal bunker should be well lit to
ensure safe bagging and shovelling. Some tank installations require a secondary
l Good ventilation of the bunker helps to prevent a
containment system, known as a bund, to counteract
build of moisture, allowing the fuel to stay dry. the risk of pollution from oil spillage. This may be
achieved by using an integrally bunded oil tank with
secondary oil containment built in or building an
INDUSTRY TIP oil impermeable containment wall around the tank
installation. These are generally required where the
Unlike other fuel sources, there are no special rules,
regulations or restrictions when it comes to storing fuel, other tank is close to a river or water source. The bund must
than storing it away from the heating appliance or boiler. be capable of holding 110 per cent of the oil tank
Over-fill preventation
Contents dial Anti-siphon valve
device
Vent
Non-return valve
Fill point
Drain/sludge
Secondary
point
containment (bund)
rendered with oil-
resistant sealant
482
Bund or secondary
containment
Access for oil tanker
Internal tank
Storage of liquid petroleum gas
p Figure 7.11 Secondary containment tank
It should be remembered that LPG is heavier than air
and will ‘search’ for the lowest position if a leak occurs
The location of fuel oil tanks and, although LPG has a distinctive smell, this will not
The siting of oil tanks must comply with fire separation be apparent until a person is at the same level as the
distances to protect the fuel oil from a fire or heat low-lying gas.
source that may occur within the building itself. It is
very unlikely that any fire would occur within the tank KEY POINT
itself. The regulations state that fuel oil tanks should Above all else, LPG is extremely flammable and
be sited: explosive, and the siting of any LPG storage tanks
l 1.8 m from non-fire rated eaves of a building must comply with certain recommendations and
l 1.8 m from a non-fire rated building or structure any gas installation is subject to the Gas Safety
such as a garden shed (Installation and Use) Regulations 1998.
l 1.8 m from openings such as doors or windows in a
483
q Table 7.5 The distances from buildings and structures for LPG storage tanks
Maximum LPG capacity Minimum separation distances
Of any single vessel in a group Of all vessels in a group
LPG capacity Typical water capacity LPG capacity From buildings, boundary, property line Between
(tonnes) (litres) (tonnes) or fixed source of ignition vessels (m)
Without fire wall (m) With a fire wall (m)
0.05 to 0.25 150 to 500 0.8 2.5 0.3 1
> 0.25 to 1.1 > 500 to 2500 3.5 3 1.5 1
> 1.1 to 4 > 2500 to 9000 12.5 7.5 4 1
484
l safety
40º Pressure relief angle
l weather conditions
l distribution
l proximity to dwelling.
485
Delivery requirements
The transportation and delivery requirements for
domestic fuels differ according to the fuel, as described
below.
l Heating oil – most oil tankers carrying domestic
486
of combustible dust, which is available from its to the fuel bed of the boiler. Wood chip biomass can
website at: www.hse.gov.uk begin to de-compost if it gets too damp and this,
l Carbon monoxide build-up – for any confined paradoxically, can cause the fuel to heat internally
space close to the place of combustion of a and spontaneously combust.
fossil fuel, combustion problems may lead to
a build-up of carbon monoxide (CO), which is KEY POINT
highly toxic. An audible CO alarm installation is It is vital that fuels are kept dry and that they
recommended in fuel storage facilities. are delivered in good condition for optimum
l Slips, trips and falls – fuel stores of all kinds are combustion efficiency to occur.
dangerous places. Build-up or spillages of fuel
create slip, trip and fall hazards. Some hazards
may be limited by fuel store design. However, Distribution
where solid fuel and biomass are concerned, the The distribution of fuels becomes a vital consideration,
fuel storage space height may be high and so especially the further outside a major town or city
safety nets and harnesses should be considered. you live. Natural gas coverage in the UK through the
l Fuel delivery – fuels are delivered to properties by national grid stands at around 7000 km of pipelines, but
either tanker (heating oil, LPG, biomass) or flat-bed there are still many rural areas that are too far away
truck (solid fuels – coal, coke, etc.). Care should be from the grid for a supply to be economically viable. In
exercised while fuel deliveries are taking place. Follow these cases, other fuel supplies have to be considered.
the recommendations of the fuel delivery driver.
By far the most viable fuel in rural areas is domestic
l Personal hygiene – there should be no reason for
heating oil, otherwise known as C2 grade, 28 second
the fuel itself to be handled. However, in the event
viscosity kerosene. Distribution of this still vital fuel is
that contact with the fuel must be made, always
nationwide. However, kerosene poses an environmental
wear appropriate PPE, such as overalls, gloves, hard
risk if leakage occurs, especially where the installation
hat, goggles and respirator (especially in dusty
lies close to a watercourse, river or stream or where the
environments).
water table is high.
Weather conditions LPG distribution is also very comprehensive, with most
The prevailing weather can have a severe effect on areas in the UK reachable by tanker. However, there
the storage of fuels. Bad weather, such as wind, rain, are certain restrictions with LPG that do not exist with
hail and snow, is often a cause for late deliveries and heating oil, such as that the delivery driver must have
even cancellations of fuel deliveries, especially in line of sight to the LPG storage tank at all times during
rural areas. In almost all cases, fuel is delivered by delivery of the liquid gas. LPG is also very expensive as
large tanker or flat-bed vehicles that find it next to a domestic heating fuel.
impossible to negotiate small, narrow roads when Coal and coke solid fuels continue to be readily
the weather conditions are poor. While the weather available all over the UK, although many areas
can be unpredictable in the UK, good planning of fuel now forbid the use of these fuels because of the
deliveries can reduce the impacts of bad weather. environmental pollution they release. If solid fuel is to
Ordering more when severe weather is forecast can be used, then local authority advice should be sought.
often mean the difference between running out of fuel
The use of biomass in rural and suburban areas is
and keeping the heating on.
permitted under the permitted development legislation,
Similarly, bad weather can render some fuels, such as which came into force in 2008. However, some areas,
wood chip and wood pellet biomass, almost unusable. especially suburban districts, may put restrictions on its
Coal and coke too suffer from the negative effect use if they lie within a smoke control zone. Outside of
of excessive rain, whereby the fuel can become too these zones, there are no major restrictions other than
wet to burn effectively. Wood pellets swell from the a requirement not to emit ‘dark smoke’. In most cases,
effects of the rain and these then clog fuel delivery domestic biomass does not fall into this category.
487
INDUSTRY TIP
Access the permitted development legislation 2008 at
www.legislation.gov.uk/uksi/2015/596/contents
N
INDUSTRY TIP
HE
E
YG
AT
Biomass fuel sources are available the length and breadth
of the UK with many companies supplying a wide variety of
OX
biomass pellets and chips, as well as liquid biofuels, such
as biodiesel. A list of local biomass suppliers is available at:
www.hetas.co.uk
FUEL
Proximity to dwelling
Figure 7.17 The fire triangle
The installation of fuel storage and its requirements
with regard to the proximity of the dwelling are
covered elsewhere in this chapter. The main constituents of complete
and incomplete combustion
2 COMBUSTION Combustion can take two forms:
l Complete combustion – complete combustion
488
Flame pictures
When gas and oxygen are burned in a mixture, a
chemical reaction takes place and a flame is produced.
This happens when a mixture of gas and air is heated Primary air port
Primary air
to its ignition temperature.
Gas
There are two main types of flame relevant to the
combustion process and they are pre-aerated and Pre-aerated flame
post-aerated. Figure 7.18 Four major components make up a pre-aerated
burner. They are the primary air port, injector, mixing tube and
KEY TERMS the burner incorporating the flame ports
Pre: means ‘before’.
Pre-aerated flame: air is entrained in the mixing
tube before ignition.
Post: means ‘after’.
Post-aerated flame: air is drawn for combustion Combustion air
from the surrounding air once the flame is lit, (Secondary air)
often resulting in a loose yellow, floppy flame.
489
490
l death.
491
depends on the type of fuel. For natural gas (CH4), l control internal humidity
the oxygen to fuel ratio for complete combustion l replenish necessary oxygen
carbon dioxide
Since the atmosphere of Earth is not 100 per cent
l create air movement – this improves thermal
oxygen, the actual amount of air needed for complete
comfort.
combustion of natural gas is much more than the
2:1 ratio. The atmosphere of Earth consists of: There are two methods of supplying ventilation:
l nitrogen: 78.08 per cent l natural
l oxygen: 20.95 per cent l mechanical.
492
not be required. In this instance, the air is provided by Mechanical ventilation for
‘adventitious air’ where the air that naturally infiltrates combustion air
the room through draughts, under doors and through
Combustion air can be provided mechanically through
cracks is sufficient to allow replacement of the air used
the use of fans, provided a positive pressure zone is
for combustion.
maintained in the room where the boiler is installed.
Locating air vents and grilles It is the operation of the fan blowing combustion air
into the room that creates a positive pressure which is
These should be placed where the occupants are not
necessary to ensure that the products of combustion
tempted to cover them due to noise or draughts.
do not back spill into the room. Negative pressure zones
Draught discomfort can be avoided by placing the air
must be avoided. Generally, mechanical ventilation
vents close to the appliance, such as floor vents or by
methods require the use of an interlock, which is an
drawing supplementary air from intermediate spaces
electrical switch that shuts down the gas appliance
such as halls, or by ensuring a good mix of incoming
should the ventilation fan fail. These systems are not
air. Air vents MUST NOT be placed within a fireplace
usually specified for domestic properties and are more
opening.
likely to be installed in commercial boiler rooms.
When installing air vents, it must be remembered that
the cavity in the wall must be sealed to the air vent Installation practices for
opening and any fly/insect screens must be removed
from the grille. It must also be remembered that air ventilation
vents need to be properly sized in accordance with the Ventilation is required to provide combustion air where
input rating of the appliance and the type of fuel being open flued and flueless appliances, such as open fires,
combusted to give the correct amount of air required. gas fires, gas boilers and gas cookers are installed. It
should be remembered that ventilation needs to be:
l Adequately sized – ventilation should be sized to
Supply of air for combustion to gas fired
provide sufficient replacement air to supplement the
appliances
air used during the combustion process.
An air supply for gas fired appliances should be l Continuous size – it should be of continuous size
provided in accordance with the following British throughout the thickness of the wall.
Standards: l Sleeved – it must be sleeved through the wall
l BS 5871.3:2005 Specification for the installation
so that any cavities in the wall construction are
and maintenance of gas fires, convector heaters, sealed off from the ventilation opening. This is to
fire/back boilers and decorative fuel effect gas prevent gas entering the cavity in the event of a
appliances. Decorative fuel effect gas appliances of gas escape.
heat input not exceeding 20 kW (second and third l Permanently open – ventilation openings must be
family gases) permanently open to the outside and must not be
l BS 5871.2:2005 Specification for the installation
open/closed type vents.
and maintenance of gas fires, convector heaters, l Fly screen removed – fly screens must be removed
fire/back boilers and decorative fuel effect gas to prevent them from becoming blocked with dust,
appliances. Inset live fuel effect gas fires of heat spiders’ webs, etc.
input not exceeding 15 kW, and fire/back boilers l Correctly positioned – ventilation must be
(second and third family gases) correctly positioned in accordance with the
l BS 5440.2:2009 Flueing and ventilation for gas
appliance manufacturer’s instructions, Building
appliances of rated input not exceeding 70 kW net Regulations Approved Document F – Ventilation
(first, second and third family gases). Specification 2010 with 2013 amendments and British Standard
for the installation and maintenance of ventilation BS 5440 Part 2 Specification for the installation
provision for gas appliances. and maintenance of ventilation provision for gas
appliances.
493
KEY POINT
A vent designed to provide air for combustion
should be marked with the amount of free air it
provides.
A
B
In a room
Figure 7.20 Ventilation options for open-flued appliances in a room or internal space
494
In a compartment
In a compartment
495
ROOM 1 ROOM 2
496
A
ROOM 1 ROOM 2 ROOM 3
Figure 7.24 Venting through two internal walls and into a compartment
Located in a room
1
No vent is required
Compartment
2 If the appliance is ventilated direct to
outside air then 5 cm2 kW of free air
ventilation is required both at high
and low level
497
Compartment
Figure 7.27 Compartment ventilation for room-sealed appliances via room/internal space
Many manufacturers now state that ventilation is An engineer should always verify the free air admitted
not required for compartment installations because through a vent and this should preferably be marked
of the low surface temperature of their room-sealed on the vent. While inspecting a vent it can sometimes
boilers. The correct operating temperature of an be seen that the space between two vents has become
appliance relates directly to its performance and the blocked either by debris or even intentionally by an
following information is essential to maintain optimum owner to prevent unwanted draughts. Therefore the
performance. removal of the outer cover of the vent may be required.
It is important for the purposes of cooling not to As a practical solution to the problem of customers
exceed air temperatures of: blocking vents, an innovative device which incorporates
l 25 °C up to 100 mm from finished floor level (FFL) baffles to reduce the effect of draughts has been
l 32 °C at 1.5 m above FFL developed. However, tests have shown that the vent
l 40 °C at 100 mm below and up to ceiling level. may not always produce the required amount of air for
combustion. Therefore a spillage test should always be
Vents and grilles carried out when one of these devices is installed.
l Ventilation must allow free air to pass and vents The brown plastic terracotta part will be located on
should not be closable. the external wall to blend with brickwork; the free air
l The air cannot be taken from bath or shower rooms. volume of the device is then protected with ducting
l Vents should not incorporate any gauzes or screens. which incorporates a baffle system and the device
l Air vent openings should be not be larger than eventually terminates with a white plastic vent inside
10 mm and no smaller than 5 mm. the building.
l Air vents located externally should be located so
that they will not become blocked.
l Air vents located on internal walls should not be
fitted any higher than 450 mm.
l An air vent should never penetrate a protected shaft
or stairway.
l Vents can be made from a range of materials such
as terracotta, plastic, brass and aluminium.
Plastic vents are installed through a wall using a core
drill. The free area for combustion is printed on the
vent.
Sometimes a more aesthetically pleasing style of Figure 7.28 A circular option incorporating a baffle system to fit
vent may be required to complement a design within a cored hole through a wall
a dwelling, but in any event the free air rating of the High- and low-level vents should be located at the
fitting will still be shown on its surface. greatest vertical distance apart.
498
499
Type of appliance Maximum rated Room volume (m3) Permanent vent size (cm3) Openable window or
input limit (net) equivalent also required
Domestic oven, None <5 100 Yes
hotplate, grill or any 5 to 10 50
combination thereof
> 10 Nil
Instantaneous 11 kW <5 Installation not permitted Yes
hot water heater 5 to 10 100
> 10 to 20 50
> 20 Nil
If the room or internal space containing these appliances has a door which opens directly to the outside, then no permanant opening is
required.
The full guide to the minimum permanent opening free KEY TERM
area for flueless appliances can be found on Table 6 of
Intumescent air vents: an intumescent vent
BS 5440 Part 2:2009. contains a substance which swells when exposed
to heat and blocks the free air opening which will
Flueless ventilation calculation help prevent the spread of smoke in a fire.
If, for example, a flueless water heater of 10 kW net
were located in a room measuring 2 m × 2 m × 2.4 m, Multi-appliance installations
the total volume of the room would be 9.6 m3. By
referring to the flueless ventilation guidance it can be Where a room or an internal space contains more
seen that if the room was between 5 and 10 m3, then than one gas appliance then the air vent free airs
100 cm² ventilation would be required, as well as an should be calculated from the greatest of the following:
openable window or equivalent such as a hinged panel. l the aggregate maximum rated heat input of all
If a domestic cooker were located in the same room it flueless space heating appliances
would require a permanent vent and 50 cm² with an l the aggregate maximum rated heat input of all
openable window or equivalent. Details, guidance and open-flue space heating appliances*
ventilation requirements for other flueless appliances l the greatest maximum rated heat input of any other
are given in Table 6 in BS 5440 Part 2:2009. type of appliance in the same area, for example, this
could be an oil boiler.
Intumescent air vents * There is an exception to the second point when there
is a situation where the interconnecting wall between
Intumescent air vents are special types of air vents
two rooms has been removed and, as result, the room
that are designed to close in the event of a fire to stop
contains only two similar chimneys each fitted with a
the spread of smoke and fumes. It is important to check
similar gas fire of an individual rating less than 7 kW. In
the vents to ensure the correct free air space. BS 5440
this situation an air vent may not be required.
Part 2:2009 describes them as an assembly specified
for preventing the spread of fire, consisting of a metal
louvre or grille with an intumescent block secured
KEY TERM
behind it which incorporates a latticework of holes to Internal space: an indoor space not classified as
provide continuous ventilation but which will expand a room because it is either a hall, passageway,
stairway or landing.
and close in the event of extreme heat build-up such as
in a fire. When fitted to doors the assembly usually has
a louvre or grille on both sides.
500
501
Flue Category Flue of chimney design Natural draught Fan downstream Fan upstream of
type letter with identified by the of heat exchanger heat exchanger
first digit second digit identified by the identified by the
second digit second digit
Flueless A Not applicable A1 A2 A3
Open- B1 With draught diverter B11 B12 B13
flued B2 With draught diverter B21 B22 B23
➜
502
Flue Category Flue of chimney design Natural draught Fan downstream Fan upstream of
type letter with identified by the of heat exchanger heat exchanger
first digit second digit identified by the identified by the
second digit second digit
Room- C1 Horizontal balanced flued inlet with C11 C12 C13
sealed air ducts to outside air
C2 Inlet and outlet ducts connect to a C21 C22 C23
common duct system in SE-duct for
multi-appliance connections
C3 Vertical – balanced flue and inlet C31 C32 C33
ducts to outside
C4 Inlet and outlet connections to U-duct C41 C42 C43
system for multi-appliance system
C5 Unbalanced flue or inlet air ducted C51 C52 C53
system
C6 Appliance purchased with a flue or air C61 C62 C63
inlet ducts
C7 Vertical flue to an outlet which takes C71 C72 C73
its air from a loft space
C8 Flue connected to a common duct C81 C82 C83
system which takes an air supply
from outside making it an unbalanced
system
Open flues With a boiler having this type of flue, air for
The open flue is the simplest of all flues. Because heat combustion is taken from the room in which the boiler
rises, it relies on the heat of the flue gases to create an is located. The products of combustion are removed
updraught. There are two different types: by natural draught vertically to atmosphere, through
l natural draught
a suitable terminal. The room must have a route, for
l forced draught.
combustion air, direct from outside. This is usually
supplied through an air brick on an outside wall. All
Products of combustion Terminal natural, draught, open flue appliances work in this way.
escape through the terminal
The material from which the flue is made, however,
will differ depending on the type of fuel used.
Occasionally, an open flue may be forced draught. This
Secondary flue
is where a purpose designed fan is positioned either
before the combustion chamber or close to the primary
flue. The fan helps to create a positive updraught by
Deflector plate blowing the products of combustion up the flue. Forced
Draught diverter draught open flues are not suitable for all open flue
Air drawn in through the types and it will depend upon the boiler manufacturer
draught diverter Primary flue
and the boiler/flue design.
Flow The flue type for an open-flued system can be one of
Return the following:
Combustion chamber
l rigid single-walled
Combustion air l rigid double-walled (twin-walled) with or without
Burner
insulation
Figure 7.30 The operation of an open flue l flexible single- or double-walled (twin-walled).
503
Single-walled flues primary flues and secondary flues can be made up with
proprietary components such as heat-resistant rope
Single-walled flues are usually connected by a socket and fire cement, for example, and these should always
and a spigot with the socket facing uppermost. They be checked for integrity when testing and inspecting
can be made from stainless steel or vitreous enamel, the operation of an appliance. Creative ideas can lead
and older flues were made from cement and even to leaks and fires on gas installations.
asbestos. Single-walled flues are not suitable for
external installations or even in uninsulated loft spaces Flexible flue liners
as cold temperatures affect the flue performance.
A flexible flue liner is fitted to the primary flue outlet
KEY POINT of a fire/back boiler unit (BBU) and from there it travels
Any open flue under 10” requires a flue terminal. within an existing chimney to a terminal. At the point
where it enters the base of the chimney a register plate
must be installed to prevent secondary flue pull. In the
Double-walled flues same way, it must be sealed at the top of the chimney
A double-walled or (twin-walled) metal chimney should with a sealing plate where it connects with the
be installed with the internal socket facing uppermost. terminal. A typical way of sealing the annular space
Whenever bayonet joints are utilised then the full twist between the chimney and the flexible flue liner is with
movement process should be applied to ensure that the use of mineral wool.
the joint is complete and secure. They provide thermal
protection during the conveyance of flue gases. This is KEY TERM
achieved by the air gap between the inner and outer Annular space: the required 25 mm gap between
walls. Some flues have insulation in this space. any hot surface of a flue and any combustible
materials when travelling through a floor in a
Whenever a double-walled metal chimney is connected dwelling.
to an appliance or chimney fittings and components,
then an appropriate adaptor should be used. Similarly,
BS 5440 Part 1 states that under normal
when the connection of different makes of metal
operating conditions, a correctly installed metallic
chimneys are carried out, it is recommended that the
liner conforming to BS EN 1856.1:2003, BS EN
chimney manufacturer’s recommended adaptor is used.
1856.2:2004 and BS 715:2005 should operate safely
With all applications of flue connection, it is essential
for at least the operational lifespan of an appliance,
that the appliance manufacturer’s instructions be
which is normally 10 to 15 years.
followed. Double-walled metal chimneys are mainly
made from stainless steel or zalutite outer shells and Half-round terminals are not fit for use as flue
stainless steel or aluminum inner shells. To avoid terminals because they are there purely to ventilate
condensation no external run of twin-walled flue pipe a decommissioned stack in order to prevent
insulated with an air gap should exceed 3 m. condensation. When carrying out a flue flow test, an
engineer should always check to ensure that the flue
When installing flues, fittings and components, unless
terminal is not restricted or impeded by any adjacent
the manufacturer specifically gives permission and
obstruction such as a TV aerial.
details, then metal chimney components or fittings
should not be cut. Each individual section must be
examined before assembly is completed and any KEY POINT
sections that have damaged joints or other internal Aerials can affect the performance of a flue in
damage should not be used. the same way as a tree that is located too close
to a terminal or even a wind turbine that operates
Never improvise a connection or adapt a flue. Always nearby.
consult the manufacturer’s instructions. Connections to
504
Terminal
Flue support clamp and
sealing plate
Mortar flaunching
Vermiculite or
rock wool
Sealing plate
Sealing plate
Figure 7.31 A sectional view of a typical back boiler installation in a builder’s opening
505
KEY POINT
Any installation which has previously used a solid
fuel appliance must have the chimney swept
and tested if an open flued space heater is to be
installed. Any obstructions such as flue dampers
Builder’s opening
should be either removed or fixed in the fully open
position.
Lintel
Chairback
Hearth
(minimum of 12 mm
non-combustible material)
506
At the base of the builder’s opening is the area where Chimney type/ Void volume Spigot height
circumstance (litres) (mm)
the appliance is located known as the ‘void volume’.
Unlined brick 12 250
The dimensions of the area behind the appliance
are critical when determining the suitability of an Lined brick – new/unused/ 2 75
used with gas
installation and Table 7.9 gives guidance on different
Lined brick – previously 12 250
types of application determined on individual type and solid fuel/oil
previous usage of a chimney.
Flue block – new/unused/ 2 75
The void volume is determined by the length × width used with gas
of the opening × the distance below the appliance Flue block – previously 12 250
spigot. The spigot of the appliance must not be less solid fuel/oil
Closure plate
Terminal guards 50 mm space between the guard and any hot surface of
the flue terminal. The purpose of this guard is to protect
Flue terminal guards should be installed on balanced anyone from coming in contact with the hot surface.
flue appliances if the underside flue is less than 2 m
from the ground. There should be a minimum of a
507
BS 5440 Part 1:2008 gives precise information Both of the terminal guards have versions that are
about the location of flues in respect to openings to suitable for gas and are designed to BS 5871:2005
a building. While this installation might have been requirements.
acceptable when it was installed, it may not comply
with the new standard. An engineer must test and
assess the performance of a flue to ensure that it
operates without causing a risk to anyone. If the
appliance operates without POCs entering a building
then it could be considered ‘not to current standard’
(NCS). Engineering judgement is essential and in some
instances this installation could be classified as ‘at risk’
(AR). If POCs did enter the building then the appliance
would be ‘immediately dangerous’ (ID).
KEY TERM
Engineering judgement: this is a technical decision
which is based on the competence of a person
who has an appropriate combination of technical
education, training and practical experience in
the specific field of work. Competence in specific
areas of gas work is verified by assessments of
an engineer’s theoretical and practical knowledge
at an independent nationally approved ACS
gas centre, and then registration with the HSE
Figure 7.36 Brewer Birdguard
approved Gas Safe register.
508
Staggered blocks
Starter blocks
located at base of flue
509
Ridge terminals
300 mm 1.5 m
minimum minimum
510
simple – both the combustion air (fresh air in) and the l The process is aided by a fan, which ensures the
products of combustion (flue gases out) are situated in positive and safe evacuation of all combustion
the same position outside the building. The products products and any unburnt gas which may escape.
of combustion are evacuated from the boiler through l The flue terminal is circular, much smaller and
a duct that runs through the combustion air duct, one can be positioned in many more places than its
inside the other. predecessors.
Fresh Fresh
air inlet air inlet
Fan
Flue
gases
outlet
Fresh
air inlet
Flue
gases
outlet
Burner
Burner
Room-sealed
boiler casing
Room-sealed
boiler casing
Figure 7.41 The operation of a natural draught room sealed Figure 7.42 The operation of a fan-assisted room sealed boiler
boiler
There are two very different versions of the fan-
assisted room sealed boiler. These are:
INDUSTRY TIP l The fan positioned on the combustion products
511
The part of the flue that carries the products of combustion towards the outside. This can either be
installed outside or inside the property, depending on the position of the appliance within the property.
Secondary flues should:
Secondary flue l be as straight as possible and take the shortest possible route
l must not contain any 90° bends
l changes of direction should be kept to a minimum angle of 45°
l be constructed of twin-wall insulated to reduce heat loss and to prevent condensation within the flue.
The part where the flue gases evacuate the property to the outside. Flues up to 170 mm require a
terminal. The terminal’s job is to:
Terminal
l help the flue gases discharge to atmosphere
l prevent wind, rain, leaves, birds, etc. from penetrating the flue.
The effects of layout on its length. Bends in flues should be avoided as these
have the effect of creating frictional resistance, which
chimney/flue systems slows down the velocity of the flue gases, but where
The way a flue is designed and installed greatly affects this is not possible should be kept to a minimum
its ability to perform the function of dispersing the angle of 45°.
products of combustion safely away from the building
to the outside environment. There are several factors Effective height
that need careful consideration. The effective height of a flue is different than the
physical, measured height of the flue. The effective
Flue route and bends in flues height takes into consideration the frictional resistances
As mentioned earlier, the route a flue takes should be encountered as the products of combustion flow
as straight as possible, travelling vertically throughout upwards through the flue towards the terminal.
512
1 2 3 4 5 6 7 8 9 10 11
Ki Ko 1+2 Ke Ha 4×5 3−6 ∑K 7+8 3÷9 5 × 10
l In column 1, enter the internal resistance of the l In column 6, enter the sum of column 4 × column 5.
appliance (Ki) from Table 7.11. l In column 7, enter the sum of column 3 − column 6.
l In column 2, enter the external resistance of the l In column 8, enter the total of all resistance factors
flue (Ko) from Table 7.11. (∑K) due to flue pipe and fittings. These are taken
l In column 3, enter the total of column 1 + from Table 7.12.
column 2. l In column 9, enter the sum of column 7 + column 8.
l In column 4, enter the resistance factor per m run l In column 10, enter the sum of column 3 ÷ column 9.
of flue pipe (Ke) from Table 7.12.
l In column 11, enter the equivalent height. This is
l In column 5, enter the total measured height calculated by entering the sum of column
vertically in metres, above the draught diverter. 5 × column 10.
513
So, how does the calculation work? 1 The internal resistance of the appliance from
Look at Figure 7.43. It shows the installation of a Table 7.11 = 1.0 (Ki)
25 kW input open flued gas appliance installed on 2 The external resistance of the flue from Table 7.11
a 125 mm twin wall flue pipe system. Extract the = 1.0 (Ko)
information for the calculation table from the drawing. 3 Column 1 + column 2 = 2
4 The resistance factor of the flue pipe 125 mm dia.
from Table 7.12 = 0.25 (Ke)
5 The height of the flue vertically = 2.5 m (Ha)
1.5 m 6 Column 4 × column 5 = 0.625
7 Column 3 − column 6 = 1.375
8 The total sum of the resistance of pipe and fittings
Ha = vertical height 2.5
0.4 m (∑K) is as follows:
0.6 m
Ki = inlet resistance from
45° 1.0 2 × 45° bends @ 0.25 = 0.5
appliance
0.6 m bends
Ko = outlet resistance from 1 × terminal @ 0.25 = 0.25
Draught diverter 1.0
flue
25 kW Ke = resistance factor per 2.5 m flue pipe @ 0.25/m = 0.625
gas boiler 0.25
m run of selected flue
Total = 0.5 + 0.25 + 0.625 = 1.375. This is entered
p Figure 7.43 Installation of a 25 kW input open flued gas in column 8.
appliance installed on a 125 mm twin wall flue pipe system 9 Column 7 + column 8 = 2.75
10 Column 3 ÷ column 9 = 0.727
11 Column 5 × column 10 = 1.817
1 2 3 4 5 6 7 8 9 10 11
Ki Ko 1+2 Ke Ha 4×5 3−6 ∑K 7+8 3÷9 5 × 10
1.0 1.0 2 0.25 2.5 0.625 1.375 1.375 2.75 0.727 1.817
The equivalent height in this instance is 1.817 m. minimum height of the flue must be at least 1 m.
To check whether this height is sufficient, it must be Therefore, the calculated flue equivalent height
compared to the figure in Table 7.13. suggests that the flue design equivalent height at
The appliance calculated was an open flue gas 1.817 m is adequate.
boiler of 25 kW input. The table tells us that the
514
515
There are two points to remember when positioning There are differences between these types, but
terminals: both share the same basic functions – to remove
l A terminal should not be located where it is likely the products of combustion safely to atmosphere.
to cause a nuisance.
When designing chimneys, the geographical location
l It should be positioned outside of any potential
must be considered. Much of the United Kingdom has
pressure zone that could affect the flue
weather which is classified as severe or very severe
performance.
exposure to wind and driving rain, and the construction
Table 7.14 shows the minimum flue heights required. of the chimney should be such that ensures long-
lasting, trouble-free life, in adverse conditions.
q Table 7.14 Minimum flue heights required for termination
Brick chimneys constructed before 1966 were built
At ridge, or 600 mm
to accept coal fires and were generally 225 mm
above or at least
Pitched × 225 mm (9 in × 9 in) in dimension. Since 1966,
1.5 m measured
roof horizontally to the chimneys were built with a 175 mm diameter or
roof line 200 mm × 200 mm square clay, pumice or concrete
With parapet 600 mm above the flue linings to BS EN 1857:2010. There is a specific
<70 kW or external roof line*
reason for this. Brick chimneys without linings are
net input flue
generally considered too large for gas fires. The size
Flat roof Without 250 mm above the
of the flue means that combustion gases cool rapidly
parapet and roof line*
providing as they reach the top of the chimney, which causes the
internal velocity to slow down to the point where the water
routed flue
vapour in the gas products of combustion condenses
>70 kW 1000 mm above the on to the inside of the chimney. This causes the
Pitched or flat roof line**
net input
chimney to deteriorate at the mortar joints. By the
*If within 1.5 m of a nearby structure the flue must be raised to inclusion of a clay, pumice or concrete flue lining,
600 mm above that point.
chimneys can be used for both solid fuel fires and gas
**If within 2.5 m of a nearby structure the flue must be raised to
1000 mm above that point. fires without deterioration of the chimney structure.
Masonry chimneys should be constructed of frost-
The layout and features resistant bricks above the roof line with sulphur
resistant mortar used in the joints. Below the roof,
of chimney and flue the stack may be constructed of normal bricks and
construction mortar. Several points should be remembered:
Chimney and flue construction depend on the materials l Where chimneys penetrate the roof, weatherings
that they are constructed from. All flues and chimneys will be required to stop the rain from penetrating
are designed to evacuate the products of combustion, the building below.
whether that is coal smoke or gas fumes, to the l Because chimneys are in exposed positions, a
atmosphere. There are many different types. damp-proof course (DPC) may be required to
be built into the brickwork to stop downwards
Brick and masonry chimney saturation of rain.
construction (class 1 flue) l A coping stone made of precast concrete must be
516
Raincap
Chimney pot
Top Ring
Capping for Capping for rendered
brick chimney stack chimney stack
Casing rendered
above roof
Lead flashing
Corbel for
brick stack
Flue blocks
installed with socket 2 × casing
uppermost ties at maximum
intervals of
Staggered joints 1.5 metres
between casing
and flue
block
Support block
and adaptor
for connection
to stove pipe
Pre-cast flue blocks (class 2 flue) an external wall. In the roof space, the flue converts
gas flue blocks certified to BS EN to a normal 125 mm twin wall flue pipe. It is usually
distinguishable by either a metal terminal on the roof
1858:2008
or a terminal at the ridge of the roof (known as a ridge
Pre-cast flue blocks are manufactured from pre-cast terminal). The main problem with a pre-cast concrete
concrete and are designed to be built and bonded flue is that the ‘pull’ on the flue can be quite poor
into the house wall construction. This can be either because the flue blocks are very shallow and do not
a party wall between dwellings or the inner leaf of give a good flue combustion products extraction rate.
517
Pre-cast flue blocks are designed with a socket and Taper terminal
spigot system, which provides a concrete to concrete
joint that is sealed with a special heat resisting sealant. Storm collar
518
Flexible metallic liners (types and rated input not exceeding 70 kW net (1st,
suitability) BS EN 1856.2 2nd and 3rd family gases). Specification for
installation and maintenance of flues
Flexible flue liners are made from stainless steel. They
l BS 5871.3:2005 Specification for installation of
are used specifically to line existing chimneys. There are
gas fires, convector heaters, fire/back boilers and
two specific types:
decorative fuel effect gas appliances. decorative
l Single skin liners – specifically used for gas
fuel effect gas appliances of heat input not
appliances such as gas fires and gas boilers. They
exceeding 20 kW (2nd and 3rd family gases)
must never be directly connected to the appliance
l BS EN 15287.1:2007+A1:2010 Chimneys.
when the appliance and the flue liner are exposed.
Design, installation and commissioning of
They MUST be connected to a flue pipe. Single skin
chimneys. Chimneys for non-room sealed
flue liners must not be used for solid fuel appliances.
heating appliances
l Double skin liners – manufactured from two layers
l Manufacturer’s instructions – these should
of stainless steel, and specifically manufactured
be consulted when designing and installing
for use on wood and multifuel stoves. Again, these
flues, chimneys and appliances. In some cases,
must not be connected directly to the appliance
manufacturer’s instructions may contradict the
when the appliance and liner are exposed.
regulations or British Standards. In these instances,
Flexible liners are threaded down existing chimneys but the manufacturer’s instructions must take
only after the chimney has been swept to remove any precedence over all other documents.
existing soot and debris. The chimney must be sealed
around the flue liner at the top and bottom effectively Inspection and testing
creating a twin walled flue. This helps prevent excessive
condensation. procedures for chimney/flue
systems
Installation requirements Inspection and testing of flues and chimneys
for chimney/flue systems ensures that they continue to work correctly and
safely. There are several different tests that must be
from relevant documents employed both to the flue/chimney system and the
The construction and installation of flues and chimneys appliance itself.
is covered by several documents:
l Approved Document J of the Building Visual inspection (BS 5440 Part 1)
Regulations – this document covers the application All chimneys and flues should be visually inspected
and construction of chimneys and flues and should before an appliance is installed and during the
be used in conjunction with the relevant British appliance annual service. There are several points to
Standards. Together these documents dictate the remember:
mandatory requirements to work to for a chimney/ l The flue/chimney should have no obstructions and
flue to function safely. only serve one room or appliance.
l British Standards – the following British Standards
l If a gas appliance is fitted, then a terminal should
contain information regarding the design, be fitted that conforms to BS 5440 Part 1. If the
installation and termination methods of chimneys chimney serves a coal/solid fuel fire, a terminal
and flues: is not recommended but an appropriate chimney
l BS EN 13502:2002 Specification for clay flue
pot is.
linings and flue terminals l Dampers and restrictor plates must be removed or
l BS EN 1443:2019 Chimneys. General
fastened in the permanently open position.
Requirements l The catchment space should be of sufficient size
l BS 5440.1:2008 Installation and maintenance
for the appliance installed and be free of debris and
of flues and ventilation for gas appliances of sealed from the surrounding structure.
519
520
injectors
l incorrectly set gas rate or pressure.
521
522
13 Which of the following is the regulatory body for 19 When an open flued gas appliance has been
oil fired boiler installation and maintenance? installed, how much ventilation is required
a Gas Safe for each 1 kW rating above the adventitious
ventilation?
b HETAS
a 5 cm3
c OFTEC
b 10 cm3
d NICEIC
c 15 cm3
14 Which of the following fuel types does NOT
require any storage provision? d 20 cm3
a Oil 20 Which test would you use a smoke match on?
b Natural gas a Flue flow test
c LPG b Visual inspection
d Biomass c Spillage test
15 There are three elements to the fire triangle d Flue gas analysis test
to form combustion. If there is fuel and heat 21 What does air consist of? State the percentages
available, what is the third element that is of each part.
required? 22 When mechanical means are used to supply
a Oxygen air for combustion or remove products of
b Nitrogen combustion within a gas fired appliance, what
must be provided should the ventilation fail?
c Hydrogen
23 Describe the purpose of the draught diverter.
d Methane
24 Determine the minimum height of a flue
16 In a natural gas appliance, what colour flame
terminating above a flat roof with a parapet if
proves complete combustion?
the appliance is rated at 28 kW and not within
a Yellow
1.5 m of another structure.
b Red
25 Explain the purpose of a spillage test.
c Orange
26 What are the five categories of domestic fuels?
d Blue
27 Describe how a heat pump works.
17 With a natural gas appliance, what is the oxygen
28 What are the regulatory bodies for the following
to fuel ratio required for complete combustion?
fuel types?
a 4:1 ● Solid fuels
b 3:1 ● Oil
c 2:1 ● Gas
523
ADDITIONAL TOPICS
In this chapter we will look at the effectiveness of relationships between the plumber and the client, the
plumber and their suppliers and the plumbing team with other on-site trades, to enable systems to be installed
quickly, efficiently and with minimal problems.
We will also look at how you can plan your career development, setting goals to help realise your plans.
524
Time
Task Duration Week Week Week Week Week Week Week Week Week Week Week Week Week
(Days) 1 2 3 4 5 6 7 8 9 10 11 12 13
03 Aug
10 Aug
17 Aug
25 Aug
06 July
13 July
20 July
27 July
01 Jun
08 Jun
15 Jun
22 Jun
29 Jun
Clear 1
oversite
Excavate 3
foundations
Concrete 1
foundations
Footings 4
to DPC
Drainage/ 4
services
Backfill 2
Ground floor 2
Walls to 14
first floor
First floor 3
carcass
First floor 2
deck
Walls to wall 15
plate
Roof structure 5
Roof covering 10
Rainwater gear 2
Windows 4
External doors 1
526
Explain the sequence of pipework runs can be installed and a decision made
about the system type and the materials that will be
work in a domestic dwelling used. Many installers now favour polybutylene pipe
plumbing system installation over copper tubes and fittings because of the benefits
it offers in installation time.
A well-functioning plumbing system that meets or
exceeds the customer’s requirements is the result of Once the design is completed, an estimated cost of the
a number of important aspects: installation can be prepared.
l good design
l removing all scrap and unused materials from site. Materials that arrive on site must be stored in a secure
and safe lock-up to prevent theft and to ensure that a
Planning a plumbing installation is often completed check can be made of the materials in stock at any one
using a Gantt chart, as described in the previous section. time. Fragile materials such as sanitary ware should be
kept separate and stored so as to prevent breakages.
Designing a plumbing installation
Designing a plumbing installation will involve taking Installation planning
measurements from site drawings or visiting the site Once the system has been designed in accordance with
in person and taking measurements from the building the customer’s wishes, the installation planning can
so that pipework sizes, heat losses and heat emitter take place. Installation can be divided into five separate
outputs, flow rates, hot water temperatures etc. can and distinct phases:
be calculated. The layout of a building is instrumental l First fix – Usually the first fix phase is where the
in how we design the systems for it. In many cases, installer will get their first look at the property.
the position of appliances, such as bathroom suites, They will walk the job and plan the pipework routes,
has already been dictated by the architect’s drawings marking any floorboards that require lifting. On new
and our job is to design a functioning system based build installations, the plumber will arrive before
upon these predetermined positions. Where central any ceilings are fixed and often before the upper
heating is concerned, positioning components, such as floors are down. Marking and notching/drilling of
radiators, may be a little more flexible and consultation the joists will take place in accordance with the
with the customer is needed to ensure that the position Building Regulations and the pipework for the hot
of radiators, the boiler and so on is satisfactory. It is and cold water, the central heating, any gas pipework
here that the designer/installer will get a feel for where and sanitary pipework, waste pipes and so on will
527
be installed. At this stage, because there are no emergency contact details for use in the event of
appliances or components installed, the plumber will a problem. The customer should be instructed in
position the pipework tails to where the appliances the use of all system controls and shown where
will eventually be fitted, using the working drawings isolation points for the water, gas and electricity
of the building to position the pipework correctly. are. Any system servicing requirements, such as
Any pipework that is to be positioned behind annual boiler servicing, should also be pointed out.
plasterboard walls, such as droppers for central
heating behind the dot and dab plasterboards, Describe difficulties that
will be installed. This phase of pipework is often
called ‘carcassing’. Once the carcassing has been may arise when supervising
completed, it must be fully pressure tested according system installations
to BS EN 806, which is 1.1 times the maximum
design pressure. Conflicts in the workplace
l Second fix – The second fix takes place after all of When people work together in groups, there will be
the internal work, such as fitting plastering, skirting occasions when individuals disagree and conflicts occur.
boards and internal doors, has been done. Where Whether these disagreements become full-blown feuds
bathroom suites are installed, the bath is fitted or instead fuel creative problem-solving is, in large
first so that the tiler can tile around the bath and part, up to the person in charge. Conflicts can occur
any areas where the wash basin and WCs are to for many reasons, such as:
be fitted. These can then be completed once the l unfair working conditions
tiler has finished. Boilers, radiators and any central l unfair pay structures
heating electrical controls can be installed and l clash of personalities
any hot water storage vessels, cold water cisterns l language differences
fitted and connected. Once the second fix has been l attitudes towards ethnic differences.
completed, commissioning can begin.
l Commissioning and testing – Commissioning It is important to deal with workplace conflicts quickly
and testing procedures depend upon the system and effectively, as if left unchecked they can affect
being commissioned. It is at this point that the morale, motivation and productivity, and potentially
system is filled up with water to full operating cause stress and even serious accidents. Conflicts may
pressures and the systems are run for the first occur between:
l employer and employee – may need union
time. Any leaks must be cured and flow rates and
pressures checked to ensure that the installation involvement or some form of mediation
l two or more employees – will need employer
meets the design specification. Central heating
systems can be balanced and the temperatures intervention
l customer and employer – may need intervention
checked against the design specification.
Benchmarking the system can take place during by a professional body
l customer and employee – will need employer
this stage of the installation.
l Snagging – Snagging is the term used to describe intervention.
the curing of minor problems that have emerged
Dealing with workplace conflicts
during the commissioning and testing process.
l Signing off – Commonly called ‘handover’, this There are several ways that your employer may deal
is where we present the customer with all of the with disagreements. They should:
l Identify the problem. Make sure everyone involved
system documentation, including benchmarking
certificates, Building Regulation compliance knows exactly what the issue is, and why they
certificates, manufacturers’ instructions and are arguing. Talking through the problem helps
commissioning documentation. This is often everyone to understand that there is a problem,
presented in a system folder together with any and what the issues are.
528
l Allow every person involved to clarify their l Employees don’t keep their manager informed
perspectives and opinions about the problem. and avoid talking to management.
They should make sure that everyone has an l Employees do their best to hide their deficiencies
opportunity to express their opinion. They may even or performance problems.
establish a time limit for each person to state their l Employees refuse to take responsibility.
case. All participants should feel safe and supported.
Poor communication in the workplace can disrupt the
l Identify and clarify the ideal end result from each
organisation and cause strained employee relations
person’s point of view.
and lower productivity which can often result in the
l Work out what can reasonably be done to achieve
following issues:
each person’s objectives.
l Time may be lost as instructions may be
l Find an area of compromise to see if there is some
misunderstood and jobs may have to be repeated.
part of the issue on which everyone agrees. If not,
l Frustration may develop, as people are not sure of
they may try to identify long-term goals that mean
what to do or how to carry out a task.
something to all parties.
l Materials may be wasted.
Informal counselling is one method that helps l People may feel left out if communication is not
The effects of poor communication contributing factor when jobs and contracts are not
at work completed on time. When delivery dates are missed,
it has a knock-on effect:
The effects of poor communications can be extremely
l Operatives are left standing idle.
harmful to both businesses and personnel. If poor
l Jobs get behind on time.
communication exists then goals will not be achieved
l Completion dates are missed.
and this could develop into problems within the
l Customers become annoyed at the lack of
company. It can lead to demotivation of the workforce
progress.
and the business will not function as a cohesive unit.
l Poor quality components – Many of the
The effects are obviously negative:
components, fittings and appliances used in
l Employees become mistrustful of management and,
the plumbing industry are mass-produced.
often, of each other.
Occasionally, fittings and appliances are delivered
l Employees argue and reject their manager’s opinions
to site that have not undergone quality checks
and input.
and arrive not fit for purpose. This can cost time
l Employees file more grievances related to
and money in seeking replacements. Common
performance issues.
problems include the following:
529
l Appliances such as boilers arrive with faulty The customer must be shown around the system and
components that are only discovered when the shown the operating principles of any controls, time
appliance is commissioned. clocks and thermostats. Emergency isolation points on
l Delays occur because bathroom suites often the system should be pointed out and a demonstration
arrive with damage that has occurred during of the correct isolation procedure in the event of an
transit or poor quality components or parts emergency. Explain to the customer how the systems
missing. work and ask if they have any questions. Finally, point
l Fittings occasionally arrive either of the wrong out the need for regular servicing of the appliances and
type or the wrong size. leave emergency contact numbers.
There are a number of dos and don’ts to observe when
parts, appliances, components and equipment are
delivered to site:
2 PLAN FOR CAREERS
l DO check all materials that are delivered whilst the
When the system has been tested and commissioned, admire and could ask for advice on how they’ve
it can then be handed over to the customer. The got to where they are
l networking – through attending industry events
customer will require all documentation regarding
the installation and this should be presented to the or asking to be introduced to people who might be
customer in a file, which should contain: able to help you through advice or contacts within
l all manufacturers’ installation, operation and
companies that are recruiting
l job centres and recruitment agencies.
servicing manuals for the boilers, heat emitters and
any other external controls such as motorised zone The internet is a logical and easy place to look for sources
valves, pumps and temperature/timing controls of information to support career planning. However,
fitted to the installation resources found on the internet should always be read
l the commissioning records and certificates carefully in the light of the original purpose of the website
l the Building Regulations Compliance certificate or blog and the actual benefit you can glean from them.
l an ‘as fitted’ drawing showing the position of all For example, many websites relate just to overseas
isolation valves, drain-off valves, strainers, etc. employment or specific sectors. Before relying on such
and all electrical controls. information, make sure it is relevant to your needs.
530
531
You should also know the difference between a specific Personal statement
goal and a vague goal. For example, there is a big A personal statement is a short summary of your key
difference between saying, ‘I would like a job’ and ‘I skills and experience that you should put at the top
would like to be an apprentice plumber’. You may also of your CV. It is vital to spend time getting this right,
like to set a goal of contacting a certain number of as many employers will often use this statement to
companies a week. This is then measurable. decide whether or not to read the rest of your CV. The
So, if you want to attain anything of significance, you best advice is to keep it short: your personal statement
must sit down and define what you really want, put it in should be just a few lines or bullet points, around
writing, develop a real plan, and lay out the guidelines 50–100 words.
for completion. There’s no better way to accomplish a
really strong desire than a well-written plan. Covering letter
A covering letter accompanies a CV (and/or completed
Set out your goals application form). It is an opportunity to highlight
Break your goals into short term, medium term and what is in your CV and to provide any real examples
long term. The short- and medium-term goals can be to support your ability to do the job.
thought of as stepping stones to the long-term goal.
For example: SMART targets
SMART targeting is an acronym for the five steps of
In one year’s time I want to have …
Specific, Measurable, Attainable, Relevant and Time-
In five years’ time I want to be … based targets and is one of the most effective tools
In ten years’ time I want to be able to … used to achieve a desired goal.
q Table 8.1 SMART targets can be a useful tool to help you in your
career path
ACTIVITY
Define your own short-, medium- and long-term goals. S Specific What is the task to be done?
What evidence could be used to show if
M Measurable
and how well the task has been done?
Curriculum vitae (CV) A Attainable Is the task possible?
How you write your CV and covering letter is up to you, R Relevant Why is this target important?
but there are some basic rules to follow if you want to Are review dates built in to check
create the best impression. T Time-based
progress?
You should include a summary of your educational
and academic background, and skills you have SWOT analysis
demonstrated. You should also include any interests, When planning your career, the first thing to look
hobbies and work experience. at is what you can already do. Ask yourself, ‘What
am I already good at or do I have an aptitude for?’ It
KEY POINT may be that you already have a number of skills and
A curriculum vitae (CV) can be literally translated qualifications that are transferrable to a new career.
as ‘course of life’. This provides an overview of a A useful self-analysis tool is SWOT analysis.
person’s experience and other qualifications. A CV
is typically the first item that a potential employer SWOT is an acronym for Strengths, Weaknesses,
encounters regarding a job seeker. CVs are often Opportunities, Threats. It is a planning tool used to
used to screen applicants in order to shortlist understand the strengths, weaknesses, opportunities
them for an interview. and threats involved in a project or in a business.
It involves identifying the internal and external
Most employers would expect to receive a CV along factors that are either supportive or unfavourable
with a covering letter outlining your suitability for the to achieving that objective.
position that you are applying for.
532
533
Consultancy Subcontractor
Once a lot of experience and qualifications have been A subcontractor is a person or company that is hired
attained, there are opportunities for consulting work. by a main contractor to perform a specific task as
A consultant is a professional who provides expert part of an overall project and is normally paid for the
advice in a particular area, for example, in: services by the main contractor. A building company
l hot water that doesn’t have its own plumber may subcontract
l cold water the plumbing work out.
l central heating
l cold water
As you progress, you may need to become a l oil
‘competent’ person. This means you have been trained, l solid fuel
tested and passed in a certain area of work. A certificate l environmental technologies
is given that states you are competent to carry out l health and safety.
work in that area.
Gas
Competent persons The Gas Safe Register is the official gas registration
Competent Person Schemes were introduced by the body for the United Kingdom, the Isle of Man and
Government to enable companies to self-certify Guernsey, appointed by the relevant health and safety
plumbing and heating works that fall under the scope authority for each area. By law, all gas engineers who
of Building Regulations. Self-certification provides a are actively working on gas installations must be on
much more cost-effective route compared with the the Gas Safe Register. Registration must be renewed
alternative of notifying work through local building every five years.
control bodies.
534
SUMMARY
In this chapter we have investigated the aspects of We have also looked at ways in which you can take the
good system installation that you will need to have at next step towards getting a job in the building services
least a basic knowledge of, as well as discussing good sector.
communication techniques.
535
536
1.0 kW
1465
1.4 kW
1915
1.2 kW Hot water
3715
3715
cylinder
2100
2850
0.8 kW
1635
1.2 kW
4380
4380
1.2 kW
3150
1.0 kW
2580
1.2 kW
537
Situation Temperature
Legionella growth
According to Building Regulations Part G, hot water must never
exceed
Unvented hot water cylinder thermostat
Unvented hot water cylinder high-limit thermostat
Unvented hot water cylinder temperature/pressure release valve
Maximum temperature for domestic water at the outlet of a TMV
to a batch, according to Part G
Domestic bath hot water temperature at the outlet of a TMV
Maximum temperature for communal or public showers, according
to Part G
Commercial basin, according to the code of practice for safe water
temperatures
Commercial bidet, according to the code of practice for safe water
temperatures
Temperature the hot water should reach at an outlet within 30
seconds, according to Part G
Maximum temperature of a cold water storage cistern, according
to the Water Regulations
Maximum temperature of a cold water storage cistern, according
to the BS EN 806
538
539
Dynamic pressure: also known as but do not form part of the electrical Integral filling loop: a filling loop that
‘running pressure’, this is the water system. is designed and installed as part of the
pressure when outlets are open and From every source of electrical boiler by the manufacturer.
water is flowing. energy: many accidents occur due Interconnected: connected together
Earth: earth with a capital E to a failure to isolate all sources to form one cistern.
represents the potential of the ground of supply to or within equipment Internal space: an indoor space not
we stand on. (for example, control and auxiliary classified as a room because it is
Economical: good value for money. supplies, uninterruptable power supply either a hall, passageway, stairway or
(UPS) systems or parallel circuit landing.
Effective roof area: different to the
arrangements giving rise to back
actual size of the roof area. In effect it Intumescent air vents: an
feeds).
is the plan view area of the roof. intumescent vent contains a substance
Functional testing: a process carried which swells when exposed to heat
Electric shock: where a current flows
out to check that components within and blocks the free air opening which
through the human body and causes
an installation operate correctly. For will help prevent the spread of smoke
an accident or injury as a result.
example, an immersion heater should in a fire.
Electrolytic corrosion: a process of be tested to ensure safe operation of
IP2X: meaning that there is no hole in
accelerated corrosion between two or heating element and thermostat.
the barrier or enclosure greater than
more differing metals when placed in
Glycol: a liquid anti-freeze which is 12.5 mm in diameter, which provides
an electrolytic environment.
odourless and colourless in its raw ‘finger protection’, meaning no person
Engineering judgement: this is a state. can insert their finger and touch live
technical decision which is based parts.
Guidance Note GS38: electrical test
on the competence of a person who
equipment for use by electricians IP4X: meaning that there is no hole in
has an appropriate combination of
(published by the Health and Safety the barrier or enclosure greater than
technical education, training and
Executive, HSE) was written as a 1 mm in diameter stopping parts from
practical experience in the specific field
guideline to good practice when using falling into the enclosure.
of work. Competence in specific areas
test equipment on circuits operating
of gas work is verified by assessments Isolation: this means the
at voltages >50 V AC or >120 V DC
of an engineer’s theoretical and disconnection and separation of the
or where tests use these voltages. It
practical knowledge at an independent electrical equipment from every
is intended to be followed, in order to
nationally approved ACS gas centre, source of electrical energy in such
reduce the risk of danger and injury
and then registration with the HSE a way that this disconnection and
when performing electrical tests.
approved Gas Safe register. separation is secure.
Haemoglobin: the part of the red
Equal potential: where the voltage Legible: readable.
blood cell that carries vital oxygen
between any two parts is within safe Line: the conductor, having brown
to the brain. When CO enters the
touch voltage levels, usually 50 V AC coloured insulation, which is normally
bloodstream, the haemoglobin
but dependent on the location. connected to terminals marked L.
becomes carboxyhaemoglobin, which
Equilibrium: in perfect balance (e.g., effectively blocks the red blood cells Live conductor: a conductor intended
the pressure is balanced both sides of from carrying the oxygen to the brain to be energised in normal service, and
the valve). When referring to drainage and this causes the body’s cells and therefore includes a neutral conductor.
systems this relates to keeping the air tissue to fail and die. Live testing: a test is carried out when
pressure even within the system, so components are live.
Head: the pressure exerted by a
that any negative pressure or pressure
column of water under gravity. Loading unit: a number or a factor,
fluctuation does not cause any trap
Insulation: the material that covers which is allocated to an appliance. It
seal loss and therefore the ingress of
the conductor, and should have a relates to the flow rate at the terminal
foul air into the property.
high resistance stopping current flow. fitting, the length of time in use and
Extraneous conductive parts: the frequency of use.
Insulation is intended to stop current
metallic parts of a building structure
from leaking from one conductor into Mandatory: required by law or
or services that have a low resistance
another conductor or person which regulation.
path to the general mass of earth
could in turn cause an electric shock.
540
Mass flow rate: the mass of a connected to the same soil stack, the identified by the fact they look like
substance (e.g. kilograms) which trap depths remaining should be at circuit breakers but have a test button
passes in a unit of time. least 25 mm deep. located on them.
Multi-storey building: a building Perpendicular: at an angle of 90° to Resistance testing: the Ω scale is
having more than three floors. a certain plane. In other words, the used, for example, to find out the
Naphtha: a waxy oil deposit that is Sun’s rays need to be at 90° to the level resistance of a coil in a motor, to
present in natural gas in its unrefined collector where possible for maximum ascertain whether it works or not (e.g.
state. It is removed and later reused in efficiency. testing a motor on a zone valve).
other products such as cosmetics. Planning permission: official Resistor: a passive thru-terminal
National standard: based on permission from the local authority electrical component that resists
International Standards produced by allowing a new build, alteration or electrical current.
the International Electrotechnical addition to an existing building to be Reverse osmosis: method of purifying
Commission (IEC), member nations made. water.
create their own versions specific to Post: means ‘after’. Rodding point: a place where the
their needs. Other CENELEC countries Post-aerated flame: air is drawn for drain or section of drain can be
use the term ‘rules’ rather than combustion from the surrounding air accessed to clear any blockages.
‘regulations’. For example, the national once the flame is lit, often resulting in Schmutzdecke: a layer of mud that
wiring standard in the Republic of a loose yellow, floppy flame. is saturated with friendly, water
Ireland is the National Rules for
Potable: pronounced poe-table, from cleansing bacteria.
Electrical Installations (ET101).
the French word ‘potable’ meaning Secure: security can best be achieved
Neutral: the conductor, having blue drinkable. by locking off with a safety lock (such
coloured insulation, which is normally
Pre: means ‘before’. as a lock with a unique key). The
connected to terminals marked N.
Pre-aerated flame: air is entrained in posting of a warning notice also serves
Overheat protection: when water to alert others to the isolation.
the mixing tube before ignition.
cannot circulate or the thermostats
Pryolised: when a material begins Solar radiation: radiant energy
have been satisfied and the motorised
to decompose due to elevated emitted by the Sun.
valves have closed, the boiler will
continue to heat up for a short period temperatures. Standard English: use of English
even though the burner has shut PVCu (unplasticised poly vinyl chloride): following correct spelling and grammar.
down. This is because of the latent a common material used in rainwater Static pressure: this is the water
heat in the boiler casing. If the boiler guttering and pipework systems. pressure when no flow is occurring.
overheats, the high-limit thermostat Ratio: 1:600 means 1 mm fall for This is always greater than the
will activate, and the boiler will fail every 600 mm length of gutter. dynamic pressure.
to operate when it is next required. A Refrigerant: a substance or mixture, Statutory: the law, and therefore
pump-overrun circuit, which is fitted usually a fluid, used in a heat pump there are serious consequences if they
to most modern boilers, will ensure and refrigeration cycle. In most cycles are not followed.
that the pump continues to run when it undergoes phase transitions from a Stratification: describes how the
the boiler has shut down to dissipate liquid to a gas and back again. temperature of the water varies with
any latent heat. If the motorised its depth. The nearer the water is to
Regulatory body: an organisation set
valves are closed, the automatic the top of the cistern, the warmer
up by the Government to monitor,
bypass valve opens from the pump it will be. The deeper the water, the
control and guide various sectors
pressure to allow water circulation, colder it will be. This tends to occur
within industry.
allowing the excess heat to dissipate, in layers, whereby there is a marked
keeping the boiler temperature below Residual current device (RCD): a
temperature difference from one layer
high-limit shut-down. sensitive device which trips, cutting
to the next. The result is that water
current from a circuit, should a
Pathogen: a germ or bacteria. quality can vary, the warmer water
very small fault occur between any
Performance test: carried out on a near the top being more susceptible to
live conductor and earth. They are
sanitary system to ensure that after biological growth such as Legionella
intended to give maximum protection
simultaneous operation of appliances pneumophila (Legionnaires’ disease).
against electric shock and can be
541
Sub-station transformer: a piece of causes expansion and contraction Other types are type C intended for
equipment which is owned by the and, eventually, the loosening of motors and transformers and type D
electricity distribution network operator terminals. for very specialised machines such
(DNO) and is used to step down large Tanking: a process used to ensure as welding equipment or medical
distribution voltages of 11000 V to that a wet room area installation is equipment.
230 V for supplies into houses. Sub- completely leak free. Upstream: in water systems, upstream
stations are sometimes located behind means travelling toward the point of
Thermal shock: the rapid cooling or
panel fences and can serve up to 100 supply.
heating of a substance that can lead to
houses or more depending on its size.
failure of the material. Verbal: the spoken word. Any verbal
Sometimes they are located on poles
Tone of voice: a way of sounding communication should always be
where they serve one or two houses in
to express meaning or emotion. backed up with written confirmation
more rural locations. In cities and large
For example, your tone of voice to verify any agreements and clarify
towns, they are normally located in
can communicate confidence and any details to prevent confusion.
brick or concrete structures.
conviction, assuring customers that Verifiable: able to be checked.
Supplementary bonding: where a
you are knowledgeable and capable. Vertigo: the feeling that the sufferer
bonding conductor is installed either
between pipes or from a socket outlet Transpose: to rearrange the or objects around them are moving
or other accessory to a pipe. Unlike information to determine a different when they are not; feels like a spinning
MPB, supplementary bonding doesn’t part of the formula. or swaying movement.
come from the MET. The minimum csa Turbidity: refers to how clear or cloudy Vitiated air: the word ‘vitiated’
of cable permitted for supplementary the water is due to the amount of simply means ‘to be made impure’, so
bonding is 4 mm2 where the cable is total suspended solids it contains. The ‘vitiated air’ is air that has been made
in free air. Supplementary bonding is greater the amount of total suspended impure.
sometimes also called cross-bonding. solids (TSS) in the water, the cloudier it Water table: the point where the earth
Switch: component that breaks an will appear. Cloudy water can therefore below ground becomes saturated with
electrical circuit by interrupting or be said to be turbid. water causing water to pool.
diverting current. Type B circuit breakers: the most Water undertaker: a water authority
Thermal cycling: heating and sensitive type of CB and should be or company that supplies clean, cold
cooling of metal (in this case) which the types used to protect circuits wholesome water under Section 67 of
in domestic type installations. the Water Act 1991.
542
543
544
545
fused connection units (FCUs) 356 single-storey dwelling 239–40 insulation and continuity testers 262
fuses 350, 423–4 tabulation method 226–33 insulation, electrical
G heat pumps 435–7, 477–8 insulated crimps 379
Gantt chart 526 air source (ASHP) 440–2 of live conductor 338, 341, 369
garden watering systems 66–7 ground source (GSHP) 437–40 regulations 372, 373
gas detectors 491 HETAS 481, 535 insulation of pipework 136, 173
gas fuels 474–6, 483–4, 492 home automation devices 358 to conserve heat 154, 235
gas safety issues 157, 481, 534 hose union bib taps (outside tap) integral filling loop 200
gas solenoid 413 62–3, 66–7 interconnected cisterns 17
gas valve 275 hot water heating load 235 internal space 500
geothermal energy/heat 116 calculation 240–1 intumescent air vents 500
glycol 432 hot water storage vessels 159–62 intumescent collars 318–19
goal setting (careers) 531–2 hot water systems 115 inverters 458
grates, wet room 314–16 design techniques 150–69 IP (International Protection) Code
grey water reuse systems 451–2 fault diagnosis and repair 181–8 374–7
benefits and limitations 455 fuel sources for 115–16 IP2X and IP4X 341
regulations 453–4 installation requirements 169–74 isolation 362
types of 452–3 killing bacteria vs scalding central heating system 281
grilles 498–9 129–30 of electricity supply 261, 281,
ground source heat pumps 437–40 servicing/maintenance 188–9 363–6
underfloor heating system 209 solar thermal 430–5 hot water systems 185
Guidance Note GS38 364, 396–7 specialist components 138–50 valves 138, 140, 251
gutter system, designing 324–8 testing and commissioning J
H 175–80 jacuzzis/hot tubs 357
haemoglobin 491 types and layouts 116–37 junction boxes 356
handover/’signing off’ 528, 530 hydraulic pressure testing 98–100, K
central heating systems 273–4 266–7 kerosene 476
cold water systems 70, 108 hydraulic shock wave 45 L
sanitation systems 331 hydro-electric generation 465–6 large-scale cisterns 8–18
head (available water pressure) 75 I layouts
health and safety 535 IET Wiring Regulations 157, 343, central heating systems 193–
carbon monoxide 491 344, 370–1, 390, 394 215
cold water systems 32, 95, 100, immersion heaters 117–18, 122, cold water systems 7–46
101 123, 155, 170 electrical systems 348–58
electricity 339, 359, 362, 366, functional testing 420–1 hot water systems 116–37
372, 391, 392 temperature control 173 sanitation systems 293–316
hot water and Legionella 110, index circuit, pipe sizing 246–50 leaks
130, 179 industry standards 157 central heating systems 272
sanitary systems 293, 318–20 information sources cold water systems 99, 107
sink waste disposal unit 312–14 for career planning 530–1 hot water systems 178
heat emitter sizing 238–40 central heating 218–19, 263–4 rainwater systems 332
heat exchangers 274–5 cold water systems 68–71 sanitation systems 301, 329,
heat gain 221–2, 229 fuel supply installation 480–1 332
heat loss 219–21 hot water systems 151–2 shower pump 187
from pipework 136, 235 infrared operated outlets 37–8 legible 273
heat loss calculations 220–1, 222 inhibitors, central heating 268–9 Legionella
from pipework 245–6 initial system fill 98, 176, 215, 265 dealing with 110
546
and hot water temperature design mass flow rate 162 non-mechanical backflow prevention
129–30 calculation of 163 51–7
and mixed water systems 131, materials non-screw compression connectors
132 delivery problems 529–30 381
risk from 110, 179 ordering and storing 527 notification of works carried out 5,
legislation and regulations mCHP (micro-combined heat and 107–8, 179–80, 273
cold water systems 1–6, 46–9, power) unit 445–6 O
68 Mears calculator 234 Ohm’s law 339–40
and electrical safety 342–3, measurements, taking 71–2, 158, oil 115–16, 476
358–9 219 combi boilers 126
environmental technology mechanical backflow prevention OFTEC 481, 535
systems 428–30 58–63 storage of 482–3
rainwater systems 324–8 micro-hydro-electric systems 465 water heaters 123
smoke control 444, 480 benefits and limitations 470 open vented hot water storage
line 338 regulation and requirements system 117–20
liquid petroleum gas (LPG) 475–6 469–70 comparison with unvented
storage of 483–4 turbines 467–8 125–7
live conductor 373 working principles 465–6 expansion vessel sizing 167–8,
live testing 400 micro-renewable energy technologies 235–8
loading unit 73 electricity-producing 455–70 fault finding 185
local authority building control heat-producing 430–46 fill points 251
office, notifying of works legislation relating to 428–30 initial system fill 176
carried out 5, 107–8, mini expansion vessels 46 maintenance requirements 189
179–80, 273 mixer taps 38–40 secondary circulation installations
localised water heaters 128–9 backflow risks 174 135–6
lockshield (gate) valves 137, 271 motor control equipment 356–7 optimisers 358
loose wiring connections 382, 424 motorised valves 251 over sink heaters 128, 129
low loss headers 201 moving plate terminals 378 overflows, large-scale cisterns
lugs 371, 379–81, 394–6 multi-functional control valve 275 11–13
M multi-storey buildings 7 overheat protection 197
macerators 305–10, 357 base design temperatures 225 oxygen and combustion 488, 492
maintenance of 331 cold water system layout 7–21 ozonation 33
magnetic toggle float switch 18–29 N P
mains water supply, problems of naphtha 475 pathogens 27
poor 171–2 national standard 344 peat 477
maintenance natural gas 474–5 performance test 329
cold water systems 109–10 natural ventilation 492–3 perpendicular 433
hot water systems 188–9 negative head shower pumps 43–4 photovoltaic energy production
sanitation systems 331–2 neutral (conductor) 338 456–61
mandatory 95 neutralisers 269 pipe sizing
manifolds 210, 211–12 noise issues central heating systems 241–9
manufacturer’s instructions 69, 91, central heating systems 272 cold water systems 73–90
97, 109 cold water systems 106 discharge stacks 320–3
central heating 219, 264, 277 hot water systems 178 regulations for sanitary 320–3
electrical installations 348 turbines 464 simplified method 83–6
fuel systems 480, 519 non-concussive taps 38–9 tabulated method 76–83
hot water systems 158, 181 waste pipes 296–8, 320
547
548
549
thermostatic mixing valves (TMVs) fault finding 184 Water Supply (Water Fittings)
130–2, 210 G3 requirements 535 Regulations (1999) 2–3, 97
guide for selecting 133 initial system fill 176 backflow protection 46–7, 63–7
thermostatic radiator valves (TRVs) installation of 169–71 central heating systems 263,
206, 278 maintenance requirements 189 266
thermostats 183, 280, 404 secondary circulation installations fluid categories 47–9
boiler 408–9 135 hot water systems 134, 140,
checking faulty 182, 187–8, use of cold water accumulators 150, 152–6
278 171–2 notification requirements 5, 6
cylinder 280, 283, 358 upstream 52 water table 26
frost 260–1 urinals 40–1, 65 water treatment 27–34
as heating controls 173, 283, V water softener issues 93
358 ventilation water turbines 465–70
room 280, 283, 358, 405–6 domestic fuel systems 492–501 water types 447
safety controls in hot water sanitary systems 293–301 water undertaker 2, 107
systems 139 verbal communication 69, 70–1, WCs 65
time clocks 136, 182, 278, 358 277, 526 backflow prevention 55–6
tone of voice 70 verifiable 58 flow limiting valves 40
trace heating 137 vertical loops, ground heat 438 macerators 305–10, 331, 357
transducers 19, 92 vertigo 491 spacing requirements 318
transformers 361 visual inspections ventilation design 293–301
transpose 89 central heating systems 264–5 weather compensators 202, 203
tundish 138, 144–5 chimney/fuel systems 519–20 weather conditions, fuel storage
turbidity 29 cold water systems 98 487
turbines prior to electric tests 400–1 weir gauges, flow rate checks
micro-hydro-electric 465–70 sanitation systems 328–9 105–6, 177
micro-wind 461–5 vitiated air 490 wells, water pumped from 22–3
turbulent flow 75, 76 voltage 338 wet rooms 314–16
type B circuit breakers 353 voltage testers 398 wind speed, turbines 463
U W wind turbines 461–5
U-values 219–21 waste disposal unit, sinks 312–14 wire strippers 367, 369, 387
ultraviolet irradiation 33–4 waste pipes, sizing 296–8, 320 wiring
under sink heaters 124–5, 128–9 waste products from fuel use, alternative methods 285
underfloor heating systems 206–15 problems of 480 centres 356, 403
unvented hot water storage systems waste water lifters 310–12 diagrams 254–61, 347
(UHWSS) 120–5 maintenance of 331–2 IET regulations 344–5
balanced and unbalanced supply Water Act (2003) 2, 3 systems, installing 368–70
pressures 132, 134 water conservation technologies working relationships 524–6
comparison with open vented 446–55 workplace conflicts 528–9
125–7 water demand and use 73, 447 written communication 69–70, 525
controls, function and position of water hammer 45 Z
138–45 water quality parameters 28 zone valves 202, 284, 358, 404–6
discharge pipework 146–50 water softeners 92, 93 zoning 194–6, 205–6
550
Boost eBooks are interactive, accessible and flexible. They use the latest
research and technology to provide the very best experience for students
and teachers.
● Personalise. Easily navigate the eBook with search, zoom and an image
gallery. Make it your own with notes, bookmarks and highlights.
● Revise. Select key facts and definitions in the text and save them as flash
cards for revision.
● Listen. Use text-to-speech to make the content more accessible to students
and to improve comprehension and pronunciation.
● Switch. Seamlessly move between the printed view for front-of-class
teaching and the interactive view for independent study.
● Download. Access the eBook offline on any device – in college, at home or
on the move – with the Boost eBooks app (available on Android and iOS).