Administrative Aspects of The Research Project
Administrative Aspects of The Research Project
GENERAL OBJECTIVE:
SPECIFIC OBJECTIVES:
Contrast the types of expenses in a research project (direct costs and indirect
costs).
Detail how the research project budget and the respective financing are
prepared.
1
CHAPTER I
The administrative aspects comprise a part of the research project, equally important
as the others. They refer to resources, schedule of activities and budget, the latter two
consisting of the management of time and financial resources, respectively.
1. WORK SCHEDULE
In 2009, Esteban indicates that "the schedule is the programming of the time in
which the research project must be executed, said programming is made taking
into account the main activities to be developed and the time that each of them will
take" (p . 187)
The schedule allows the execution period to be distributed prudently, so that it can
be used to evaluate the effective progress of its execution.
The total time required to complete a research project depends on the nature of the
work, the conditions in which it was carried out, the qualifications and teamwork of
researchers. However, the minimum reasonable time is one year, in the best of
cases it can last up to more than two years. In general terms, a reasonable time is
between one or two years. This is distributed in bimonthly months or quarters. The
schedule includes the different activities, from the readjustment of the project to the
presentation and presentation of the final report.
To present the schedule, diagrams are generally used, which allow the time of
each activity to be visualized, especially in those cases where there are several
activities at the same time. The most commonly used diagrams, and for projects
whose degree of complexity is not too great, bar charts such as the Gantt Chart
are used; For more complex projects, arrow or network diagrams are used, such
as PERT and CPM.
2
1.1. Chart or Gantt chart
The schedule of activities is also called the Gantt Chart, in honor of its
inventor Henry Laurence Gantt. This graph shows the distribution that the
main activities of the research process will have on the calendar.
In project management, the Gantt chart shows the origin and end of
different minimum work units and groups of tasks or dependencies between
minimum work units. Since their introduction, Gantt charts have become a
basic tool in project management of all types, with the purpose of
representing the different phases, tasks and activities scheduled as part of a
project or to show a timeline in the different activities making the method
more efficient.
Basically, the diagram is made up of a vertical axis where the activities that
constitute the work to be executed are established, and a horizontal axis
that shows the duration of each of them on a calendar.
To better control the development of the work and the investment that it
entails, the activity must be scheduled from the beginning to the end,
sectioned chronologically in time.
3
Stages Tasks Year
Januar February March April May June July August sept. oct. nov. dec.
y
Preliminary
Bibliography and
or Primary information search
Selection
Project presentation
Second Hypothesis
Research and
information
All possible materials that will be used during the research process should be
noted: desk and laboratory materials, teaching materials, supplies, equipment,
etc.
Example:
3. EXPENSE CLASSIFIER
As its name indicates, the costs directly attributable to the project are easily
identifiable, since they are produced in the development of the specific
research activities.
They are: the plant research staff who carry out the project activities;
consumer items; the scientific equipment necessary to carry out these
activities; and a series of miscellaneous expenses for specific services
presented by the institution, or that are contracted with natural or legal
persons other than it, to carry out certain tasks of the project.
10
The calculation of direct items is relatively easy as it is given by objective
and clear parameters, such as commercial quotes, service provision
contracts, collection accounts or invoices (in the case of materials,
equipment and payment of services) or there is a contract labor and an
assignment of functions and salaries formally established by the institution,
as well as some investigative activities proposed in the project.
Indirect costs are basically made up of: legal and extralegal social benefits
that protect investigative personnel; and the costs of administration,
secretariat and general services and operation of the institution.
If the direct costs are relatively easy to calculate, this is not the case with a
series of indirect costs to the project, such as the payment of administrative
services, secretarial services, telephone services, electricity, water,
cleaning, messaging, etc., without which it is not possible for the researcher
to dedicate himself to his task of investigating, in a division of functions. But
how much cost is attributable to the project?
On the other hand, in addition to the salary that the researcher receives for
carrying out his project, he must also be paid a series of legal and extralegal
social benefits, bonuses, severance pay, and make legal payments to
institutions that guarantee social security (ISS, ICBF, SENA). These are also
indirect costs of the project. But how to calculate them and what amounts of
them to charge to the project?
It is very common to find that indirect costs are either not taken into
account, or are calculated in a subjective way, charging an arbitrary
percentage (0.1%, 1%, 10%, 50%) of the total value of the project. A fact
that belies its quality, since formulating a project is synonymous with
objective and careful planning. Furthermore, such a subjective and arbitrary
calculation is not convenient for the institutions that finance projects, as it
does not present valid parameters for evaluating these percentages; neither
11
It is convenient for the institution carrying out the project, which in any case
must receive correct income to cover exactly those expenses.
12
Each year you must pay a legal Christmas bonus, which is equivalent
to one-twelfth (1/12) of the total salaries earned by the worker in the
year, plus salary factors such as food assistance, transportation,
travel expenses. representation, etc.
The formula for its calculation, as defined in the law, would be:
Pn = (wages + salary factors)/12
Given the simplification of the example, let us only take the salaries as
100%, without considering the percentage to which the salary factors
are equivalent in any specific case. Then we would have that the
Christmas bonus is equivalent to a minimum of:
Pn = (100+fs)/12=8.3%
The percentages of the different social benefits are calculated in a
similar way.
4. BUDGET
Valderrama (2015) mentions that the budget “must be estimated. Care must be
taken to ensure that each of the expenses incurred in the development of the
research is detailed in the most realistic way possible. These expenses will be
classified according to the different points” (p.235); for example: equipment,
consumables, transportation costs, acquisition of bibliography, salaries, etc. In
addition, the description and justification of each one must be provided.
13
If the project is justified and the different scientific-technical elements are planned
and the various activities are organized, it is also essential to justify and establish a
strategy to obtain the financial resources that allow the research to be carried out.
This financing strategy includes the detailed calculation of each of the costs that
are grouped by items or titles; as well as the distribution or charge of each of them
to one or several entities, in accordance with the financing policies and criteria.
The procedure for preparing the budget follows the same order: initially, a detailed
calculation of each of the items and expenditure lines is made. Secondly, and once
the previous operation is completed, the costs are distributed by financing sources
or entities to which it is considered appropriate to submit a request.
Example 01:
The total cost of the research work amounts to S/. 3925.00 nuevos soles and will
be self-financed by those responsible for the research, as can be seen in the
following summary:
TOTAL 3925.00
14
Example 02:
TO. STAFF
Support secretarial S/. 400.00
advisory S/. 1000.00
Interviewers S/. 2000.00
Others S/. 600.00
S/. 4000.00
b. ESTATE
Stationery supplies S/. 200.00
Computing materials S/. 200.00
Printing materials S/. 400.00
Others S/. 200.00
S/. 1000.00
c. SERVICES
Mobility S/. 600.00
Travel expenses S/. 900.00
Of computing S/. 200.00
Of impression S/. 700.00
Others S/. 600.00
S/. 3000.00
15
5. FINANCING
According to Esteban (2009), for financing, one must “consider which entities will
finance and in what percentages” (p.189); so that in this way the execution of the
project is carried out.
EXAMPLE:
CONCYTEC: 50%
ONE: 50%
16
CHAPTER II
1. CONCEPT
The consistency matrix is the first instrument that the researcher develops in order
to take into account the internal logic between each of the elements horizontally and
vertically. It is characterized by being the tool for identifying and correcting
inconsistencies.
2. STRUCTURE
17
the research techniques, the statistical treatment that will be used for
hypothesis testing and the plan or scheme to follow.
The consistency matrix is important for research, because it allows the various
steps of a research project to be elaborated sequentially and logically. It is the first
thing to prepare before the project. For example, the general problem must agree
with the general objectives, hypotheses, variables and indicators; That is, between
one and the other there must be a logical foundation.
The importance of the consistency matrix comes from the following points:
It allows you to observe the internal logic of the research proposal and then
validate or correct said matrix.
If there is solidity, cohesion or firmness between the different parts or
constituent elements of the matrix, it shows the consistency that the future
research project will have.
Not only can it be used by the researcher, but also by those who monitor or
evaluate.
18
5. ESSENTIAL ASPECTS THAT SHOULD BE EVALUATED IN A
CONSISTENCY MATRIX
The consistency and agreement of the title with the problem, objective
and general hypothesis
The consistency and agreement between the specific elements of the problem,
the objective and the hypothesis
Congruence between the title of the research project and the type of design
indicated in the matrix.
Coherence between the selected methods and techniques with the research
problem, the population and the study sample.
19
6. EXAMPLE
TITLE: MOTIVATION AND WORK UNEMPLOYMENT OF TEACHERS AT THE UNIVERSIDAD PERUANA MIGUEL ANGEL RODRIGUEZ RIVAS, LIMA –
2013
21
CONCLUSIONS
2. The function of the schedule is to organize the activities for exact and better
fulfillment of them.
3. There are two types of resources that are used in a research project, human and
material, the first have to do with human talent, the number of people involved,
and the second, all the material necessary to use to the investigation.
4. Direct costs differ from indirect costs in that they are those costs produced in the
development of specific research activities.
5. The budget must be prepared in detail where each of the expenses is mentioned,
that is why the budget is an estimate; and for its financing you can resort to your
own resources, or resources from some identities.
6. The importance of the consistency matrix lies in the fact that it helps follow a
logical and organized sequence to develop the investigation.
22
BIBLIOGRAPHIC REFERENCES
4. Godoy, E. (2011). How to write a thesis . Prov. From Buenos Aires, Argentine Republic:
Valleta Edition SRL.
23