Hard Ground Sheet Pile Installation

Uploaded by

Batu Gajah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

METHOD STATEMENT FOR

HARD GROUND SHEET PILES INSTALLATION


BY CRUSHER PILER MACHINE

The scope of works is mainly installation of sheet piles into the hard ground in which the Standard
Penetration Test N- values more than 30 by boring method thru Giken- Super Crush Piler.

1. Construction Machinery/ Equipment Used

Equipment and working tools required for the execution of works are as follows:

Sno: Description Qty

1 80 Ton Crawler Crane 1

2 Super Crush Piler 1

3 Power pack 1

4 Air Compressor 1

5 Welding Machine 1

6 Torch Cutter 1

7 And Miscellaneous Hand Tools

# The actual types and quantity of the machinery used may vary pending work schedules.

2. Materials
 Use of FSV IV sheet pile (76.1kg/m)
 Use of FSV IIIA sheet pile (58.4kg/m)

3. Setting out & working platform

The licensed surveyor (by others) will be engaged to set out the center line of the sheet piles and
the position of each pile and to establish TBMs on site for determining the cut-off levels of piles.

A reasonable firm and level working platform shall be prepared prior to the installation of sheet piling
works

Rising Engineering Pte Ltd


4. Manpower

Sno: Description Qty

1 Project Manager 1

2 WSHO Coordinator 1

3 Site Supervisor 1

4 Site Engineer 1

5 Safety Supervisor 1

6 Lifting Supervisor 1

7 Rigger, Signalman 2

8 Crush Piler Operator 1

9 Crane Operator 1

10 Welder 1

9 General Worker 1

# The actual manpower used may vary pending work schedules.

5. Hard Ground Press-in Method

To solve the hard ground condition (e.g.: - cobbles and stones) an integral auger is utilized to
enable the Press-in Method to be used in hard ground where water jetting would not be effective.

The press-in procedure with simultaneous with augering can be demonstrate as follow:

Loosen hard soil by augering down to a depth of 50cm below the current pile toe location.
Simultaneous extraction of the auger casing while pressing-in the pile by a stroke. After installing
the pile to the specified depth, the auger with auger casing is fully extracted from the ground.

Rising Engineering Pte Ltd


6. Flow Chart of Hard Ground Press-in Method

M obilization and setting of the equipm ent and m aterials

Setting the R eaction Stand on the piling line at a level


M obilization
Setting the C rush Piler and counter weight on the R eaction Stand

Setting the Pile Auger on the C rush Piler

C om m encing initial pressing-In from the R eaction Stand

Initial P ress-In
Pressing-in four initial piles with integral augering
(Four piles only)

R em oval of the Reaction Stand and counter weight

Step of Preaugering
Fixing of the Preaugering Screw H ead on the Auger Screw

Fixing of the C asing G uide on the bottom of the Auger C asing

C om m encem ent of preaugering along a previously installed pile

Self-m oving of the C rush Piler after the required depth augering

Extraction of the Auger and C asing

R em oval of the Casing G uide from the Auger C asing

R em oval of the Preaugering Screw H ead form the Auger Screw

P ress-in W ork R epeat


Step of Pile P ressing-in w ith Sim ultaneous A ugering
Fixing of the Press-in Screw H ead on the Auger Screw

Pitching of a pile into the C huck of the C rush Piler

C hecking of the verticality and alignm ent of the pile

C om m encem ent of the press-in work with sim ultaneous augering

Installation of the pile fully down to the specified depth

Extraction of the Auger and C asing from ground

R em oval of the Press-in Screw H ead from the Auger Screw

R em oval of the Pile Auger from the C rush Piler

D em obilization D em obilization of the C rush Piler

D em obilization of the equipm ent and m aterials

NOTE:
1. Ensure auger casing must be support by crane before open the chuck clamp and casing lock pin
2. Ensure auger casing must be fully loosen before commencement of press-in work.

Rising Engineering Pte Ltd


7. Machine Placement (Sample Case)

Layout

Cross Section

Rising Engineering Pte Ltd


Side View

Rising Engineering Pte Ltd


8. Super Crush Piler Press-in Procedure
8-1. Initial Piling Work

Rising Engineering Pte Ltd


8-2. Press-in Work with Pre- / Simultaneous Augering

Rising Engineering Pte Ltd


9. Installation of sheet pile at cofferdam

i) Drive the sheet pile both side of cofferdam (when working at cofferdam to be install piler
stage with silent piler).
ii) Mark out level and alignment of tie-rod.
iii) To cut holes of sheet pile for tie rod to inserting using oxy gas.
iv) To use hanging platform attached to sheet pile or a floater to install and secure outer
sheet pile at water area.
v) After tie back the sheet pile back filling the sand between the sheet piles to move the
crane forward.
vi) Repeat Step i) ~ vi).to continue drive the sheet pile

10. Machinery/ equipment catalogues

Please refer to next page