WRM On 20.03.24
WRM On 20.03.24
ON 20.03.2024
NO. OF WORKS AS PER IRPSM UNDER CONSTRUCTION ORGANISATION
Plan Head 11 14 15 16 30 33 36 42 51 53
No of wroks 7 3 27 12 79 1 1 28 8 2
Works Sanctioned > 10 yr Old 5 3 9 5 11 1 - 2 3 -
Works Sanctioned > 5 to 10 Yrs Old 0 0 9 4 23 - 1 14 5 1
Works Sanctioned < 5 Yrs Old 2 0 9 3 45 - - 12 - 1
INDEX
Sl. No. Plan Head Page No.
1 11 1-3
2 14 4-5
3 15 6-11
4 16 12-14
5 30 15-29
6 33 30
7 36 30
8 42 31-36
9 51 37-38
10 53 39
Figures in Crores of Rupees.
Works under PH-11
Sl. PB No. PH Dy Name of work YOS Allo- Anticipate Exp. till RG 23-24 Exp. in TDC Estimat % age Status
No of 23- CE/C cation d Cost March 23 23-24 e progress
24 (physical)
a) 1 11 GRC MM for New Line 09-10 176 Not fixed as land not S 0% LA required 127 Acres approx. and job required 1800 nos. approx. State Govt. is to
from Champadanga - available. acquire land but not done. CA was appointed.
Tarakeswar (8 km) In fact, Govt. of WB declined to take up LA work vide, memo no.1261-LA III/1E-
59/11 (Pt-I), dt.29.04.2014. Proposal sent to Rly. Board for shelving the project. Rly
Board shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt. 24.09.19.
RoR: Less than zero.
b) 1 11 GRC MM for New Line 09-10 352 Not fixed as land not S 3% LA required 168 Acres approx. and job required 1750 nos. approx. State Govt. is to
from Amta – Bagnan available. acquire land but not done. CA was appointed. In fact, Govt. of WB declined to take
(16 km) up LA work vide, memo no. 1261-LA III/1E-59/11 (Pt-I), dt.29.04.2014. Proposal
sent to Rly. Board for shelving the project. Rly Board shelved the project vide letter
No. 2019/W-1/Genl./Budget/1 dt. 24.09.19. RoR: Less than zero.
c) 1 11 GRC MM for New Line 11-12 270.6 Not fixed as land not S 0% LA required 124 Acres approx. and job required 1700 nos. approx. State Govt. is to
from Janghipara- available. acquire land but not done inspite of perusing from Rly side. Rly Board shelved the
Furfura Sharif (12.3 project vide letter No. 2019/W-1/Genl./Budget/1 dt. 24.09.19. RoR: Less than zero.
km)
1
Figures in Crores of Rupees.
Works under PH-11
Sl. PB No. PH Dy Name of work YOS Allo- Anticipate Exp. till RG 23-24 Exp. in TDC Estimat % age Status
No of 23- CE/C cation d Cost March 23 23-24 e progress
24 (physical)
a) 2 11 GRC MM for New Line 09-10 399.13 Dec'25. S 30% 90% land acquired. 163/194 Acres LA done. Work stopped due to land loser protest
from Deshpran - for jobs. Job required : 2000 Nos. approx. and job given 444 Nos. Rly Board
Nandigram (17 km) shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt. 24.09.19.
Now Vide Board vide letter No. 2023/W-II/SER/NL/03 (e file no. 3425941) dt.
06.04.23 it has been decided re-start the work, accordingly revised estimate of Rs.
399.13 cr. has been sanctioned by Railway Board on 21.09.23. 2 Nos. tender
covering entire section for Earthwork, formation & bridges have been invited and
LOA issued on 01.08.2023 and 13.09.23 respectively. Survey & mobilization in
progress. Load testing arangment of old bridge in progress
b) 2 11 KGP Material Modification 11-12 576.4 Not fixed. Land not S 0% LA required 394 Acres approx. Govt. of WB has to acquire land but not done.
for Kanthi-Egra (26.2 available. Project is not economically viable. Rly Board shelved the project vide letter No.
km) 2019/W-1/Genl./Budget/1 dt. 24.09.19. RoR: ROR – 4.60%.
c) 2 11 KGP Material Modification 12-13 616 Not fixed. Land not S 0% LA required 400 Acres approx. Land is not available. Physical progress is NIL.
for Nandakumar - available. Proposal sent to Rly. Board for shelving the project as it is financially not viable.Rly
Balaipanda (28 Km) Board shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt. 24.09.19.
RoR: Less than zero.
d) 2 11 KGP Material Modification 12-13 154 Not fixed. Land not S 0% LA required 86 Acres approx. Land is not available. Physical progress is NIL.
for Nandigram - available. Proposal sent to Rly. Board for shelving the project as it is financially not viable.
Kandiamari Rly Board shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt.
(Nayachar) (7 Km) 24.09.19. RoR: Less than zero.
3 3 11 ADR Bowaichandi - 10-11 Cap/ 671.15 42.11 0.0001 0.0 Not fixed. S 8% 127/487 Acres (26%) LA done by Rly and thereafter Competent Authority changed
A Arambagh (31 Km) EBR- to State Govt of WB. Job to be given 2500 Nos. approx. Job given 28 Nos. approx.
S/SF Most of the pilling work of 3 Nos Major bridges was completed. LA pending on
State Govt account as Govt. of WB declined to take up LA work vide, memo
no.1261-LA III/1E-59/11 (Pt-I), dt.29.04.2014. Project is not economically viable
(ROR - 4.74%) and proposed for shelving. Hence Rly Board shelved the project
vide letter No. 2019/W-1/Genl./Budget/1 dt. 24.09.19 (ROR - 4.74%).
2
Figures in Crores of Rupees.
Works under PH-11
Sl. PB No. PH Dy Name of work YOS Allo- Anticipate Exp. till RG 23-24 Exp. in TDC Estimat % age Status
No of 23- CE/C cation d Cost March 23 23-24 e progress
24 (physical)
a) 4 11 KGP Material Modification 11-12 682 Not fixed. Land not S 0% LA required 392 Acres approx. State Govt. is to acquire land but not done. Project is
for Digha-Egra (31 available. proposed for shelving as it is financially not viable (ROR : - 5.07%). Rly Board
km) shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt. 24.09.19.
5 5 11 KGP Badutola - Jhargram 11-12 Cap/ 290 0.13 0.0005 0.0 Not fixed. N - Land is not available. Physical progress is NIL. Proposal sent to Rly. Board for
via Lalgarh (54.5 km) EBR- shelving the project as it is financially not viable (ROR – 5.71%). DPR is not
S/SF sanctioned. Rly Board shelved the project vide letter No. 2019/W-1/Genl./Budget/1
dt. 24.09.19.
2 7 11 ADR Kiriburu-Barbil 20-21 Cap/ 1443.7 0.00 0.00 0.0 Dec'25. N 0% DPR submitted on 09.02.2023. Board suggested to merge this project with BBN-
A (24.50 km) EBR-S BXF-NYG Iron Ore project. Merged DPR submitted for A/Cs vetting on 24.04.2023
OR : 14.5 Km & JH : and sent to Board on 03.05.2023. Compliance of observations raised by Railway
10 Km Board in DPR meeting on 23.05.2023, have been sent to Board on 05.06.2023.
Now as per advice of Railway Board the total cost after reducing S&T cost became
Rs.12479.84 Cr, Length-198.73 Km, Updated FIRR-11.05 % and EIRR-26.54 %
and merged DPR hard copy sent to Railway Board on 09.8.2023. EBR Meeting
completed.
3
Figures in Crores of Rupees.
Works under PH-14
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23- Exp. in TDC Estimat % age Status
No of 23- CE/C cation ed Cost March 23 24 23-24 e progress
24 (physical)
2 9 14 RNC Ranchi - Lohardaga with 96-97 Cap/ 678.43 649.58 7.00 4.93 Commissioned. S 100% Ranchi - Lohardaga (67 km) GC : Commissioned on 04.07.2005.
extension to Tori. (111 SF/ Lohardaga – Barkichampi (14.5 km) NL : Commissioned on 12.11.2011.
km) EBR- Barkichampi – Tori (29.5 km) NL : Commissioned on 09.03.17. New Boda station
S/JH commissioned on 09.08.19, ROB-Mckluesganj completed & commissioned on
DEP/E 25.10.2021. Staff Quarters at various stations are in progress. There is funds
BR (IF) constraint. Addl. funds of ` 34.19 cr asked from State Govt. But no funds has been
received from State Govt of Jharkhand. Rly funds are being utilised to complete
balance work.
4
Figures in Crores of Rupees.
Works under PH-14
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23- Exp. in TDC Estimat % age Status
No of 23- CE/C cation ed Cost March 23 24 23-24 e progress
24 (physical)
a) 10 14 ADRA 1st Material Modification 04-05 145 Commissioned. S 100% Rainagar-Mathnasipur (10.5 km) : Line commissioned by Hon'ble MR on
Rainagar to Masagram 17.05.2011.
(20.9 km) Mathnasipur – Masagram (10.40 km) – Line commissioned by Hon'ble MOSR (A)
on 16th April 2013. Line handed over to open line.
b) 10 14 ADRA 2nd Material Modification 04-05 820.0 Not fixed. S 20% 1. 64.42% land acquired. But work can not be done as continuous stretches of land
from Bankura (Chhatna) is not available.
to Mukutmonipur (48.25 2. Rly Board shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt.
km) 24.09.19 as it is not echonomically viable. RoR less than zero.
c) 10 14 ADRA 3rd Material Modification 00-01 366.0 Not fixed. S 20% State Govt acquired 90% land (291/322 Acres). Balance land acquisition proposals
Bowaichandi to Khana are pending with State Govt. ` 14.03 cr deposited to State Govt.
(24.4 kms) Foundation and substructure of Major Bridge No. 17 & 18 across Damodar
completed. Land loosers did not allow work without job. Contracts are foreclosed.
As such Rly Board shelved the project vide letter No. 2019/W-1/Genl./Budget/1 dt.
24.09.19.
d) 10 14 ADRA 4th Material Modification 11-12 587.0 Not fixed. S 0% Govt. of WB has to acquire land but not done. Project is proposed for shelving as it
for Mukutmonipur- is financially not viable (ROR – 5.05%). Rly Board shelved the project vide letter
Uparsol (26.7 km) No. 2019/W-1/Genl./Budget/1 dt. 24.09.19.
e) 10 14 ADRA 5th Material Modification 11-12 1430 Not fixed. S 0% Govt. of WB has to acquire land but not done. Project is proposed for shelving as it
for Bankura (Kalabati)- is financially not viable. Rly Board shelved the project vide letter No.
Purulia via Hura (65 km) 2019/W-1/Genl./Budget/1 dt. 24.09.19.
f) 10 14 ADRA 6th Material Modification 12-13 528 Not fixed. N 0% Material Modification proposal submitted to Board on 28.02.2012. Project appeared
for Mukutmonipur - in the Pink Book 12-13. Rly Board shelved the project vide letter No.
Jhilimili (24 Km) 2019/W-1/Genl./Budget/1 dt. 24.09.19 as it is not economically viable. RoR less
than zero.
5
Figures in Crores of Rupees.
Works under PH-15
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23-24 Exp. in TDC Estima % age Status
No of 23- CE/C cation ed Cost March 23 23-24 te progress
24 (physical)
2 14 15 ADR Sini-Adityapur 3rd line 10-11 Cap/ 218.9 218.89 0.00 0.00 Commissioned S 100% Sini-Ghamharia (16.5 Km) : Commissioned on 19.07.16.
A (23 KM) EBR- Ghamharia–Adityapur (6.5 Km) : Commissioned on 06.06.2017.
S/EBR Line handed over to open line. Final bills are under progress. To be deleted from
(IF) IRPSM after passing of bills.
3 15 15 ROU Champajharan-Bimalgarh 10-11 Cap/ 274.1 250.00 4.07 3.37 Commissioned S 99% i) Bimalgarh-Patasahi (8 Km) : Commissioned on 04.07.2015.
(21 Km) Doubling EBR- ii) Patasahi-Champajharan (13 km) : Commissioned on 24.03.19.
extension S/EBR iii) TSS at Bimalgarh completed and commissioned in Mar'22.
(IF) Misc. work and protection work are in progress. Revised estimate of Rs 274.10 cr.
sanctioned on 31.05.23.
4 17 15 ADR Dangoaposi-Rajkharswan 10-11 Cap/ 629.0 634.88 17.0 14.51 Commissioned. S 100% Rajkharswan-Pandrasali (12 Km) : Commissioned on 19.08.2015.
A 3rd line (75 KM) EBR- Pandrasali-Jhinkpani (25 Km) : commissioned on 03.07.16.
S/EBR Maluka-Dangoaposi (10 km) : Commissioned on 24.01.2018.
(IF) Jhinkpani - Kendposi (18 km) : Commissioned on 13.07.18.
Kendposi -Maluka (10 km) : Commissioned on 14.02.2019.
Jhinkpani - 15 (11+4) days NI done on 11.09.2021 and EI commissioned.
Dangoaposi - 6 (1+5) days NI done on 08.11.2022 and EI commissioned.
5 18 15 KGP Kharagpur-Gokulpur (6 11-12 Cap/ 48.0 46.76 0.00 0.00 Commissioned. S 100% Work commissioned and proposed for deletion from IRPSM.
Km) via Girimaidan EBR-
doubling. S/EBR
(IF)
6 19 15 KGP Kharagpur - Narayangarh 12-13 Cap/ 270.12 253.50 6.25 5.11 Commissioned. S 100% Hijli - Narayangarh (20 Km) : Commissioned on 06.05.2018.
3rd line (23.5 km) EBR- Kharagpur - Hijli (3.5 Km) : Commissioned on 01.06.2022.
(Super critical project) S/EBR
(IF)
7 20 15 ROU Monaharpur - 12-13 Cap/ 365.98 347.54 18.27 14.19 Commissioned. S 99% Monaharpur - Jaraikela (11.2 Km) : Commissioned on 25.08.18.
Bondamunda 3rd line (30 EBR- Jaraikela - Bisra (14.6 Km) : Commissioned on 07.12.19.
km) S/EBR Bisra - Bondamunda (A) (4.2 Km) : Commissioned on 24.08.2021.
(11.2 Km in JH & 18.8 (IF) Misc S&T works at BNDM are in progress.
Km in Odisha)
(Super critical project)
6
Figures in Crores of Rupees.
Works under PH-15
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23-24 Exp. in TDC Estima % age Status
No of 23- CE/C cation ed Cost March 23 23-24 te progress
24 (physical)
9 22 15 GRC Andul - Baltikuri 12-13 Cap/ 94.67 94.65 2.05 1.16 Commissioned. S 100% Line commissioned on 25.01.2020 after NI for Baltikuri (PI), Bankranayabaz (PI) &
doubling(7.25 km) EBR- Mourigram (Modification of EI) station and handed over to open line. Final bill
(Super critical project) S/EBR under process.
(IF)
2 25 15 KGP Chakradharpur-Goilkera 15-16 Cap/ 354.54 318.98 6.83 3.99 Commissioned. S 100% Sonua-Goilkera (12.7 Km) : Commissioned on 03.12.18.
3rd line (34 km) EBR- Chakradharpur-Sonua (21.3 Km) : Commissioned on 06.06.2020.
(Super critical project) S/EBR
(IF)
7
Figures in Crores of Rupees.
Works under PH-15
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23-24 Exp. in TDC Estima % age Status
No of 23- CE/C cation ed Cost March 23 23-24 te progress
24 (physical)
4 27 15 ROU Bondamunda - Ranchi 15-16 Cap/ 3029.0 1594.0 343.40 328.4 Jun'25. S 70% TDC :
& doubling (158.5 Km) EBR- • Hatia - Balsiring (6.0 Km) : Commissioned in May'22.
RNC (128.7 Km in JH & 29.3 S/EBR • Balsiring - Lodhma (9.9 Km) : Commissioned in Dec'21.
Km in the State Odisha) (IF) • Lodhma-Karra (13.1 Km) : Commissioned in Mar’22.
• Karra - Govindpur (12.3 Km) : Commissioned in May'20.
(Coal Project & HUN) • Govindpur- Bakaspur (13.1 Km) : Commissioned in Sep'22.
• Bakaspur - Pakra (13.7 Km) : Commissioned in Mar'23.
• Pakra-Kurkura (8 Km) : Commissioned in Dec'23.
• Kurkura-Bano (16.9 Km) : Dec’23/Mar'24.
• Bano-Kanaroan (7.5 Km) : Dec’23/Mar'24.
• Kanaroan-Tati (12.59 Km) : Dec'23/Feb'25.
• Tati-Parbatania (7.81 Km) : Dec’23/Jun’25.
• Parbatania-Orga (7.94 Km) : Dec'23/Feb'25.
• Orga-Nawagaon (6.8 Km) : Commissioned on 18.08.23.
• Nawagaon - Bangurkela (12.5 Km) : Aug'23/Mar'24.
• Bangurkela - Link ‘B’ (2.25 Km) : Commissioned in Jun'22.
• Link ‘B’- Link ‘C’ (3.23 Km) : Commissioned in May'23.
• Link ‘C’- Dumitra (5.12 Km) : Feb'24/Dec'24
5 28 15 ADR Damodar - Mohishila 16-17 Cap/ 104.04 77.22 7.38 6.92 Commissioned. S 100% Project commissioned and train operations started from 11.03.2023.
A doubling (8.2 km) EBR-
(Coal Project) S/EBR
(IF)
6 29 15 KGP Narayangarh - Bhadrak 16-17 Cap/ 1876.0 955.38 447.6 410.2 Dec'25. S 48% Ranital - Ranital (L) (3 Km) 4th line : Commissioned on 10.01.24.
& 3rd line (155 km) EBR- Ranital - Ranital (L) (3 Km) 3rd line : Commissioned on 07.03.24.
GRC (34 Km in WB & 125 Km S/EBR Ranital (L) -Bhadrak (5.74 Km) : (E.Co. Rly)
in the State Odisha) (IF) Narayangarh - Belda (12.4 Km) : Aug'23/Mar'24.
(Coal Project & HDN) Belda-Dantan (DL) (16.4 Km) : Feb'24/Jun'24.
Dantan-Jaleswar (16.6 Km) : Feb'24/Jun'25.
Soro-Ranital (21 Km) : Dec'23/Mar'25.
Balasore-Soro (33.4 Km) : Feb'24/Dec'25.
Jaleswar-Rupsa (29.5 Km) : Dec'25.
Rupsa-Balasore (17.9 Km) : Dec'25.
8
Figures in Crores of Rupees.
Works under PH-15
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23-24 Exp. in TDC Estima % age Status
No of 23- CE/C cation ed Cost March 23 23-24 te progress
24 (physical)
8 31 15 ROU Dumitra Link C line - 17-18 Cap/ 39.00 16.96 3.80 3.41 Feb'24/ S 40% DPR sanctioned by Railway Board. Earthwork in BZR end - 0.80 Km & Link'C' end
Connection with Bisra EBR- May’25. - 0.600 Km done. Land acquisition of 3.01 Acre (1.760+1.250) Pvt. Land at village
station (2.3 Km) S/EBR Gudgudjore, under Bisra Tahasil. Railway Amendment Act-2008 has been
(HUN) (IF) implementing in lieu of RFCTLAR & R Act-2013.
With approval of GM/SER the project has been declared as “Special Railway
Project” and notified under Gazette of India vide S.O. 388(E.), Dated: 24.01.2023.
Gazette notification for competent authority of land acquisition has been done in
name of LAO /Sundargarh. Land verification at site done by RI/Sundargarh on
12.10.23. 20A notification done on dt. 21.12.2023 & paper publication 15.01.2024.
For further 20D notification, hearing is under progress.
Out of 2.3 km length of project, work completed in 1.5 km. Balance 0.8 km can be
taken up after LA.
9 32 15 ADR Radhanagar Siding Line of 17-18 Cap/ 39.93 0.00 0.00 0.00 NF N 0% DPR (modified) of ` 473.02 Cr. & RoR : 14.71 % was prepared as per revised plan
A Adra Division to Barachak EBR- on the basis of modified alignment and sent to Rly. Board on 13.08.19 for sanction.
& Y-connection Line to S/EBR- Rly. Board advised to propose the alignment so that no LA is required. Accordingly,
Sitarampur (10.3 Km) IF survey as per Rly Board instruction done and advised to Rly Board that project can
not be done without LA. LA involved 10.12 Ha.
9
Figures in Crores of Rupees.
Works under PH-15
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23-24 Exp. in TDC Estima % age Status
No of 23- CE/C cation ed Cost March 23 23-24 te progress
24 (physical)
2 34 15 ADR Chandil-Anara-Burnpur - 18-19 Cap/ 1957.0 0.00 0.00 0.00 NF N 0% Detailed Project Report submitted to Railway Board on 09.02.2023. Board advised
A 3rd line (125 km) with EBR- to resubmit the DPR by incorporating Auto Signal system. Modified DPR submitted
addl loop lines at S/EBR- to Railway Board on 19.04.2023. Board again raised some observations vide MoM
Nimdih, Urma, Tamna, IF on 15.05.2023 which are complied & discussed at Railway Board on 23.05.2023.
Charra & Bagalia. Compliance of observations done & project Report resubmitted to Railway Board by
(108 Km in WB & 13 Km incorporating 4th line provision in conceptual plans on 14.10.23. Total cost Rs.
in JH) 1957.84 Cr ; Length - 121.26 Km, FIRR-(+)14.26% ; EIRR-(+)28.11%. 49 th PEC
Rs.1932.01 Cr ; Length - meeting held on 17.10.2023. Final DPR submitted on 08.11.2023 after complying all
121.26 Km, observations along with final vetting by associate finance and with the approval of
GM/SER. 62nd meeting of NPG held on 07.12.2023. The observations raised are
complied on 21.12.2023. NPG issued some observations on 12.12.2023.
Compliance sent to Rly. Bd. on 21.12.2023. NITI Aayog issued some observations
on 18.12.2023. Compliance sent to Rly. Bd. on 20.12.2023. EBR meeting on
28.12.2023.
3 35 15 RNC Talgoria-Bokaro-N/Cabin 18-19 Cap/ 513.92 380.97 120.00 110.7 Ispatnagar - Bokaro S 95% Talgoria-Chas (13.3 Km) : Commissioned in Mar'23.
- Doubling (32 km) with EBR- (N) (10.77 Km) : Chas - Ispatnagar (7.85 Km) : Commissioned in Jun'23.
two loops at Chas S/EBR Commissioned in Ispatnagar - Bokaro (N) (10.77 Km) : Commissioned in Sep'23.
& Ispatnagar (6 Km) (IF) Sep'23. Project inaugurated by Hon'ble Prime Minister of India on 15.11.2023.
(Coal Project) One LHS 27A (RCC Box 4mx3.6mx28m) at Km 349/TT/12-13 sanctioned as MM at
a cost of 2.17 cr. as per demand of Local villagers near Mahespur village at
trespassing location. Box casting completed, pushing not started.
10
Figures in Crores of Rupees.
Works under PH-15
Sl. PB No. PH Dy Name of work YOS Allo- Anticipat Exp. till RG 23-24 Exp. in TDC Estima % age Status
No of 23- CE/C cation ed Cost March 23 23-24 te progress
24 (physical)
5 37 15 RNC Bhojudih-Talgoria in 20-21 Cap 142.06 0.47 3.00 2.26 Mar’26. S 0% DPR of ` 142.06 with ROR 19.44% has been sanctioned by Rly Board vide letter dt
connection with 29/10/2021 and advised to execute the tender on EPC mode. EPC tender of Rs. 90.42
permanent diversion of cr discharged due to high rates. Rates reassessed and re-tender to be invited. ESP of
fire BJE and SBW has been approved. 03 nos of subway drawing approved. EI bldg and
affected Dhanbad- goomty drawing of SBW station has been approved. Tender Schedule got vetted and
Chandrapura line (12.2 fresh tender document is under finalization.
km)
6 38 15 RNC Muri-Barkakhana (58 km) 20-21 Cap 1018.1 0.00 0.0001 0.00 NF N 0% DPR of Rs. 1018.11 cr with RoR 3.68% submitted to Railway Board on 28.12.2021.
Board vide letter No. 2022/W-II/SER/DL(DPR)/02 dt. 13.07.2022 has shelved the
project for inadequate line capacity utilisation, operationally not justified and
financially unviable. Sanction for new FLS being obtained for fresh DPR. Tender
under process.
7 39 15 ROU Rourkela-Bondamunda A- 20-21 CAP 245.0 0.00 2.13 2.42 Mar'26. S 0% DPR of Rs.244.99 cr has been sanctioned by Railway Board vide letter No. 2021/W-
Cabin 5th line (9.6 km) II/SER/DL/(DPR)/15/(e-office No. 3356159) dt. 26.09.2022. Tender for Execution
of Earthwork in Formation, Construction of Minor Bridges, P. Way Linking works,
Supply of P. Way Fittings, Transportation of P. Way Materials, Supply of Ballast,
Construction of Major Bridges No. 139A (1x30.5m Open Web Girder), Major
Bridge No. 143 (1x18.3m Composite Girder) and Road Over Bridge No. 133
(1x42.0m Bow String Girder-Composite Girder) including Approach Road with
Supply, Fabrication, Assembly and Erection/Launching of Open Web Girders,
Composite Girder and Bow String Girder respectively awarded on 19.12.2023.
8 - 15 RNC Bokaro Steel City - 23-24 CAP 75.5 0.00 0.00 0.00 NF S 0% DPR sanctioned by Railway Board of Rs 75.45 Cr.
Bokaro 'N' cabin - 3rd &
4th line (3.75 km)
9 - 15 RNC Bagdehi - Jharsuguda- 4th 23-24 CAP 321.0 0.00 0.00 0.00 NF S 0% Railway Board sanctioned DPR with Rs 320.95 Cr.
line (21.50 km)
11
Works under PH-16
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
Work Year Cost Upto 23-24 Prog
March (%)
'23
Works sanctioned > 10 years old
1 PB 42 16 CAO C Santragachi - Island 2011- DF(3),RRS 271059 181833 10000 9639 31/03/2024 RE S 20 "1) MOU signed between IRCON & S.E. Rly on
platform between 2012 K 11.10.2012.
1st loop & R3 by 2) Work entrusted to IRCON.
dismantling R1 & R2 3) Revised estimate sanctioned.
with common loop 4) It has been decided to take up the work along with
signalling facility new EI at Santragachi."
(IRCON) 5) Now work is in progress.
2 PB 43 16 CAO C Santragachi - 2011- DF(3),RRS 3797201 3914610 660000 430000 31/03/2024 RE UP 78 "1) MOU signed between IRCON & S.E. Rly on
Development of 2012 K,EBR(S) 11.10.2012.
circulating area, 2) Station building works Prog. (90%),
essential passenger 3) FOB No. 2 completed and commissioned on
amenities & road 19.02.2021,
connectivity with 4) FOB No.1 launching of 12 m wide 56 m portion
Kona expressway done out of 168 on 13.06.22 & 17.07.22.
(IRCON) 5) Now works are in progress."
Revised estimate under sanction of Board.
3 PB 44 16 CAO C Shalimar - 2011- DF(3),RRS 3214379 3283000 1130000 1050000 31/03/2024 RE UP 72 1) MOU signed between IRCON & S.E. Rly on
Development of 2012 K,EBR(S) 11.10.2012.
coaching terminal by 2) Station building structural work completed.
provision of Architectural work in progress.
essential passenger 3) PF-1 refurbishing work Prog. 98%. PF-2 & 3 overall
amenities. progress 83%. Construction of 2 nos. underpass
(IRCON) completed including dispersal & electrical work. Third
underpass in progress (65%).
4) Pit line No. 3 & 4 work 98% completed: 2 Nos
stabling line (line No. 1 & 2) completed, Electrical OHE
works is in progress (85%) and Portal for lighting is in
progress (60%).
5) Overhead water tank 2 out of 3 completed and
commissioned and remaining 1 is in progress.
6) Development of Circulating area is in progress.
Other Electrical and S&T work is in progress."
Revised estimate under sanction of Board.
4 PB 45 16 CAO C Sankrail - Freight 2011- Cap.,EBR(I 1775018 1544600 73100 30273 31/03/2024 S 99 Engg. works completed. Final bill passed. Major
terminal 2012 F) Electrical works completed, some misc. works are in
progress. Revised estimate of Rs. 177.50 cr.
sanctioned on 21.12.2023.
12
Works under PH-16
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
Work Year Cost Upto 23-24 Prog
March (%)
'23
5 PB 46 16 CAO C Sankrail-Santragachi 2011- Cap.,DF(3), 4211830 3015187 361655 230870 31/08/2024 S 85 "1) Formation progress 95%
- Link line (14.5 km) 2012 RRSK,EBR 2) One Rail Fly over (72X18.3 m PSC+2X30.5m OWG
via flyover from (IF),EBR(S) with ballasted deck +1X61 m OWG) : Completed.
down side to up side 3) 3 major Bridges - (4X 12.2 m), (1x45.7m) and
(20x18.3m + 1x12.2m + 1x24.4m) completed.
4) P.way linking in progress. 8.0 Km completed out of
8.6 Km.
5) One cut and connection for link line at Andul done
on 06.11.2022.
6) NI at Sankrail done on 27.02.23.
7) Major remodeling is involved."
"Sankrail – Andul (3.7 Km) : Aug'23/Aug'24.
Andul – Santragachi (4.9 Km) : Aug'24.
6 PB 48 16 CAO C Tikiapara - 2015- Cap.,EBR( 236088 114837 75500 74185 12/10/2023 S 100 "1) It was decided that full Engg & Elect works of SER
Santaragachi - 2016 S) portion will also be done by Eastern Railway.
Direct connectivity 2) All work in SER & ER portion done. NI at TPKR &
for 4th line with HWH done and Tikiapara yard commissioned on
Howrah yard 13.08.2023.
( platform Nos 17- 3) CRS South Eastern Circle has inspected TPKR-
23) HWH 4th line(SER portion) on 12.10.23 and
Authorization for opening of line with 40 KMPH subject
to compliance of observation given by CRS South
Eastern circle. After compliance of CRS observation
passerger service started from 11.11.23."
7 PB 56 16 CAO C Ranital - Extra loops 2017- Cap.,EBR( 262435 214668 40700 34098 31/03/2024 S 99 Work completed. Clearing of financial liabilities are in
in up direction 2018 S) progress.
common loop &
down direction with
reception &
despatch facility
8 LB 46 16 CAO C Construction of Up 2018- Cap.,EBR( 171900 22900 76200 29576 31/03/2024 S 35 Engg. work is in progress (35%). Hard Rock 44,000
loop line at KITA 2019 S) cum out of 55,000 cum has been completed. Agency
terminated.
Final measurement is planned on 18.03.24.
13
Works under PH-16
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
Work Year Cost Upto 23-24 Prog
March (%)
'23
9 LB 52 16 CAO C Construction of 2018- Cap.,EBR( 138200 96900 16200 9888 31/03/2024 S 99 Addl. loop commissioned on 08.02.2023.
additional loop at 2019 S)
JONA Station
10 LB 1 16 CAO C Bhojudih-Yard 2020- Cap.,DF(3), 799889 0 30000 12245 31/12/2024 S 20 "1) Detailed estimate of ` 79.99 cr. has been
remodelling work of 2021 RRSK 31-12-2025 sanctioned.
Bhojudih station to LOA issued on 31.08.202(duration-24 month).
increase the CSL of 2) Engg. & Electrical Tender awarded. S&T tenders
UP and DN yard are to be finalized.
lines. 3) Engg Work in progress.
Goomty no.1(G+1): Earth work was started but
stopped due to S&T cable.
Goomty No.2 (G+1): Top slab casting completed.
Goomty no.3 (G+1): Ground floor slab casting
completed and top floor column casting in progress.`
Goomty no.4 (G+1): Retaining wall in progress.
UG tank: Earth excavation in progress.
Main EI building: Earth work for foundation completed,
PCC in progress.
Earth work :
i)Adra end- (17000/40500 cum) in progress.
ii) BKSC end- (0/65000)
11 LB 53 16 CAO C Extension of 2020- Cap.,DF(3), 246542 1306 5000 5159 31/12/2024 S 5 Detailed estimate of Rs. 24.65 Cr sanctioned on
Coaching & Goods 2021 RRSK 30-06-2025 25.04.22. NIT cancelled due change asked by open
shunting neck at line in span of girder from 30 m to 36 m to
Hatia ( HTE) accommodate additional line. Tender awarded on
towards Ranchi End. 21.04.2023.
1.ROB (36 m,CG): GAD approved, design under
compliance.S&T cable, encroachments, Hoardings,
water pipeline etc need to be shift.
2. Minor bridge: GAD approved & PCE sanction
received.- Hard rock cutting will be start from 18.03.24
3. Formation / hard rock cutting: Jungle cleaning in
progress and breaker will be start on 18.03.24.
4. Drain cum retaining wall- 340 mtr completed.
12 LB 41 16 CAO C Bankra Nayabaz : 2021- Cap.,DF(3) 296904 0 20000 21 30/06/2024 S 0 "Detailed Estimate sanctioned. Tender for Civil Engg
Additional Loop 2022 work awarded on 17.10.23.
lines. S&T and Elect. tenders are to be invited."
14
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
Works > 10 years
1 PB 87 30 CAO C Balichak - Road over 1999- S.Fund, 525300 243719 100 12 30/04/2024 RE S 10 "1) Revised estimate of Rs. 55.4 Cr has been
bridge in lieu of level 2000 RRSK, sanctioned by Railway Board.
crossing No.52 EBR(Dep), 2) ROB is being executed by the State Govt on single
EBR(S) entity basis.
3) Tender of Rs. 43.70 cr awarded and work is in
progress.
4) Railway Portion- 2 spans, ROB proper will be start
after diversion of cable & shifting of lifting barrier.
The Modified ESP has been approved. The diversion
road work has been commissioned on 16.12.2023. All
clearance has been given to start the ROB
proper .Work to be executed by State Govt. authority.
5) State Portion- All the piers along with Deck except
CP-l, RP & CP-2 have been completed."
2 PB 89 30 CAO C Andul-Sankrail - 2011- S.Fund, 1277296 384 5901 3842 31/12/2015 RE S 0 Combined GAD approved on 13.08.2019, Detailed
Road over bridge in 2012 RRSK, estimate sanctioned on 18.03.2020. For land
lieu of level crossing EBR(Dep), acquisition of approach road (Ganga end) length of
No.13 EBR(S) 240m i.e. from Ch: 610.09m to Ch: 850m for 2.9 acre
an amount of Rs. 10.66 Cr. has been kept in detailed
estimate (100% by State Govt.). Land acquisition not
yet completed by State Govt. for approach of
ROB(Ganga end). A revised alignment within the
Railway land (By utilizing abundant delta siding) has
been agreed in principle by CE/Plg/PWD. Revised
Estimate sent to Rly Bd for approval regarding 100%
cost sharing by Railway.
3 PB 90 30 CAO C Bankura-Chhatna - 2011- S.Fund, 497900 142563 66500 67386 31/03/2021 RE S 100 "Rly Portion (3X36 m, open foundation) : Completed in
Road over bridge in 2012 RRSK, Mar'21.
lieu of level crossing EBR(Dep), State portion: Approach portion being executed by
No.KA-94 EBR(S) State Gov is completed except 2 spans. Work was
remaining pending for construction of service road on
Railway land by the state as per award given by Court
against a PIL for provision of Ambulance/Fire vehicles
movement. Permission has been given by Railway on
19.09.2023 to State Govt for use of Railway land for
service road. Works re-started by State Govt."
15
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
4 PB 91 30 CAO C Urma-Barabhum - 2011- S.Fund, 564800 5185 100 1 31/03/2026 S 1 "1) S&T cable clearance and OHE modification work
Road over bridge in 2012 RRSK, completed.
lieu of level crossing EBR(Dep), 2) Railway portion Engg. contract foreclosed as State
No.JC-40 EBR(S) Govt advised LA to be done which will take time. No
information since long time."
5 PB 92 30 CAO C Kharagpur-Gokulpur 2011- S.Fund, 475200 512696 16900 16885 12/01/2023 RE UP 100 "ROB executed by Railway on single entity basis.
- Road over bridge 2012 RRSK, ROB commissioned on 12.01.2023. The final Variation
in lieu of level EBR(Dep), under preparation.
crossing No.KA-1 & EBR(S) Vetted revised estimate sent to State Govt on
KA-2 30.03.2023 for acceptance. State Govt's observations
complied on 10.07.23 & 20.07.2023 have been
complied. 2nd reminder issued on 03.01.2024 for
acceptance of revised estimate."
6 PB 93 30 CAO C Nalpur-Bauria - 2011- S.Fund, 1350858 700 4800 3295 31/12/2015 S 0 Railway will be borne 100% cost Revised Estimate
Road over bridge in 2012 RRSK, sanctioned on 24.02.2024 with cost of Rs
lieu of level crossing EBR(Dep), 135,08,58,368/- .
No.18 EBR(S) Revised Estimate sent to Rly Bd for approval regarding
100% cost sharing by Railway.
7 PB 94 30 CAO C Purulia- 2011- S.Fund, 491484 0 100 0 31/03/2026 S 0 GAD is being finalized by CBE in consultation with
Gourinathdham - 2012 RRSK, State Govt. of WB. Now Railway will bear full cost of
Road over bridge in EBR(Dep), ROB and accordingly detailed estimate of Rs. 49.15
lieu of level crossing EBR(S) Cr. sanctioned on 30.01.24. Rly portion GAD with
No.PK-3 revised RDSO Girder sent to State Govt on 01.09.23
for combined GAD. GAD is finalised. Tender schedule
under preparation.
Detailed Estimate sent to Rly Bd for approval regarding
100% cost sharing by Railway.
16
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
8 PB 95 30 CAO C Chaibasa- 2013- S.Fund, 441633 377466 2000 0 30/07/2021 RE UP 100 "ROB commissioned on 30.07.2021 and LC has been
Singpokharia - Road 2014 RRSK, closed. The commissioning has been inaugurated by
over bridge in lieu of EBR(Dep), Hon’ble Chief Minister of Govt. of Jharkhand, Shri
level crossing EBR(S) Hemant Soren on 31.07.2021.
No.RBK-14 Revised Estimate sent to State Govt. for acceptance.
Accordingly, funds to be deposited by State Govt.
GST impact is not submitted by agency. final bill and
SD is released.
9 PB 96 30 CAO C Tatanagar - Road 2013- S.Fund, 299950 163666 5500 5500 31/05/2020 S 100 "ROB executed on double entity basis by Rly and
over bridge in lieu of 2014 RRSK, State.
level crossing EBR(Dep), ROB completed and commissioned and opened for
No.141 EBR(S) traffic by Hon'ble Chief Minister of Jharkhand on
31.01.2023."
10 PB 97 30 CAO C Noamundi- 2013- S.Fund, 415041 426463 15000 11783 30/09/2021 RE UP 100 "Work executed on Single Entity basis by Rly.
Barajamda - Road 2014 RRSK, ROB commissioned on 04.12.2022 and commissioning
over bridge in lieu of EBR(Dep), inaugurated by local MLAs. ROB handed over to Open
level crossing EBR(S) Line."
No.RBK-49
11 PB 98 30 CAO C Adra Yard - Road 2013- S.Fund, 554751 58373 51000 22147 31/03/2024 S 80 "Railway portion: Substructure completed. Bed block
over bridge at km 2014 RRSK, 30.03.2025 casting of CP1 & CP2 and RP completed. Girder
283/32-34 in west EBR(Dep), fabrication completed for both spans and launching in
end for connecting EBR(S) planned in April 2024
North & South Approach portion: 17 nos foundation out of 19 in
settlement Raghunathpur end and 09 nos foundation out of 12 in
Kashipur end is completed."
17
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
Works > 5 to 10 years
12 PB 99 30 CAO C Ramgarh - 2014- S.Fund, 168982 180300 45000 24439 22/06/2022 RE UP 100 "ROB executed by the Rly on single entity basis on
Rebuilding of road 2015 RRSK, cost sharing.
over bridge at km 88 EBR(Dep), ROB commissioned on 25.06.2022."
(Bijulia) EBR(S) Revised Estimate sent to State Govt. for acceptance.
13 PB 30 CAO C Kukuda gate- Road 2016- S.Fund, 444576 3600 70000 53066 31/03/2025 S 15 "Road Over Bridge of span Railway portion : 1x60m
102 over bridge in lieu of 2017 RRSK, Bow String Girder + 1x24m (Composite Girder ) +
level crossing EBR(Dep), 1x18m(Composite Girder),
No.207 near EBR(S) 1) New agency finalized. Diversion Road & tree Cutting
'A'Cabin completed. 2) S& T cable clearance is in Progress.
Bondamunda 3)Pilling work started, pier no. 16 & 17 total pile 10nos.
& 8nos. respectively completed pile cap of pier no. 16
& 17 completed and Pier works of pier no. 16 & 17
under progress. 4) Fabrication of Girder under
progress.
5) State portion: the tender awarded for appraoch
work and BZR end work under progress and ROU end
land acquisition under progress.
14 PB 30 CAO C Howrah-Kharagpur - 2016- S.Fund, 248800 0 100 0 NF DE UP 0 "The LC situated in heavy built up area where
103 Road over bridge in 2017 RRSK, approaches cannot be built. State was suggested to
lieu of level crossing EBR(Dep), construct ROB within Rly land.
No. 47 at Panskura EBR(S) Now Railway will bear full cost of ROB and accordingly
estimate to be revised. Observation on combined
GAD sent to State Govt on 25.09.23."
15 PB 30 CAO C Panposh-Kalunga- 2016- S.Fund, 305391 45491 20000 27211 31/05/2024 S 70 "State Govt. Vide the letter Dt. 30.07.2021 decided to
104 Road over bridge in 2017 RRSK, execute work of state portion.
lieu of level crossing EBR(Dep), Rly Portion : Foundation, Substructure and Bed blocks
No. 213 (3 lane) EBR(S)) of all 04 piers have been completed. Girder launching
to be done.
State Govt. Portion : Work in progress."
16 PB 30 CAO C Barajamda-Barbil- 2016- S.Fund, 377815 74232 2500 2465 31/03/2022 S 100 "Railway portion completed in May'22.
105 Road over bridge in 2017 RRSK, State portion - Tender cancelled and to be re-floated
lieu of level crossing EBR(Dep), after LA . LA Process to be expedited by State Govt."
No. RBK-61 EBR(S)
18
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
17 PB 30 CAO C Balasore-Nilgiri 2016- S.Fund, 519555 254762 200 0 31/10/2020 S 100 "ROB executed on double entity basis by Rly and
106 Road- Road over 2017 RRSK, State.
bridge in lieu of level EBR(Dep), ROB has been commissioned on 22.12.2022 and LC
crossing No. 79 EBR(S) has been closed."
18 PB 30 CAO C Kalunga Yard - 2016- S.Fund, 561578 41496 20000 15464 31/03/2024 S 50 "Rly Portion: Revised GAD approved. Contract
107 Road over bridge in 2017 RRSK, awarded on 09.05.22. 12 nos/17 nos Piles completed.
lieu of level crossing EBR(Dep), Pile cap of P-14 comlpleted and substructure in
No. 215 (3 lane) EBR(S) progress. Edco Side:- 8 nos pier cap completed out out
of 9.
State Govt. portion Tender Finalized but no work
started so far. Encroachment removal to be done for
the approaches which is not started."
19 PB 30 CAO C Asanboni-Salgajhari- 2016- S.Fund, 689865 901 100 1 31/03/2026 S 0 ROB will be executed on double entity basis. Detailed
108 Road over bridge in 2017 RRSK, estimate sanctioned. Tender for Railway portion will be
lieu of level crossing EBR(Dep), floated after finalization of tender by State Govt. for
No. 138 EBR(S) their portion as approaches in built up area. Land
acquisition by State Govt. at approaches is in
progress.
20 PB 30 CAO C Jaleswar- 2016- S.Fund, 554637 205341 95500 95400 31/03/2022 RE UP 100 "Railway Portion : Completed in Feb'22. Final variation
109 Lakhannath Road- 2017 RRSK, sent for vetting.
Road over bridge in EBR(Dep), State portion : Deck Slab 26 nos completed out of 27
lieu of level crossing EBR(S) Nos. For balance 1 span girder launching completed."
No. 45
21 PB 30 CAO C Barajamda-Barbil- 2016- S.Fund, 356641 88208 5400 4905 31/07/2021 S 100 "Railway portion: Completed in Aug'21.
110 Road over bridge in 2017 RRSK, State portion - Tender cancelled and to be re-floated
lieu of level crossing EBR(Dep), after LA . LA Process to be expedited by State Govt."
No. RBK-60 EBR(S)
22 PB 30 CAO C Jaleswar-Amarda 2016- S.Fund, 973529 947266 56600 38879 31/01/2021 RE S 100 "ROB commissioned on 27.04.23 by Hon'ble MP Mr.
111 Road - Road over 2017 RRSK, Pratap Sarengi and LC closed in Nov'23.
bridge in lieu of level EBR(Dep), Financial liabilities under clearing. Revised estimate of
crossing No. 52 EBR(S) Rs. 97.35 cr. has been sanctioned."
19
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
23 PB 30 CAO C Rajgangpur Yard - 2016- S.Fund, 416840 88573 100 0 31/03/2024 S 80 "ROB is being executed on double entity basis.
112 Road over bridge in 2017 RRSK, Railway Portion (1x18 m +2x36 m +1x18 m) :
lieu of level crossing EBR(Dep), Launching of Girder started with placing of Bowstring
No. 222 EBR(S) Girder.
State Portion : Land acquisition is under process by
state Govt."
24 PB 30 CAO C Rourkela-Panposh - 2017- S.Fund, 404926 25893 4000 310 31/12/2024 S 15 "Rly Portion: Foundation work in progress.
113 2-lane road over 2018 RRSK, State Portion: Tender will be invited after LA. LA under
bridge in lieu of EBR(Dep), process."
manned level EBR(S)
crossing No.209
25 PB 30 CAO C Dhutra-Jharsuguda - 2017- S.Fund, 728200 8 100 0 31/03/2025 DE UP 0 Modified combined GAD is approved by CBE. Details
114 2-lane road over 2018 RRSK, of Structural Drg. for Railway portion is under process.
bridge in lieu of EBR(Dep), Combined Estimate is pending for non submission of
manned level EBR(S) Approaches portion Estimate by State Govt. of Odisha.
crossing No.256
26 PB 30 CAO C Hatia-Balsiring - 2017- S.Fund, 370600 0 200 0 31/03/2024 DE UP 0 "1) ROB will be executed on single entity basis by
115 Road over bridge in 2018 RRSK, State Govt on 50:50 cost sharing.
lieu of manned level EBR(Dep), 2) Revised GAD in new location approved. Detailed
crossing No.HB-1 EBR(S) estimate for Rly portion is ready. Approach estimate
submitted by the State Govt. of Jharkhand. MOU yet to
be finalised by State Govt. regarding executing
authority.
27 PB 30 CAO C Asanbani-Salgajhari 2017- S.Fund, 438596 4110 500 0 31/03/2026 S 0 ROB will be executed on double entity basis. Detailed
116 - Road over bridge 2018 RRSK, estimate sanctioned. Tender for Railway portion will be
in lieu of level EBR(Dep), floated after finalisation of tender by State Govt for
crossing No.137 EBR(S) their portion as approaches in built up area. Land
acquisition process is held up on state part as local
population is resisting the land acquisition falling in
approved alignment.
28 PB 30 CAO C Jharsuguda - 2-lane 2017- S.Fund, 535488 49526 35000 36492 31/05/2024 S 60 "Detailed Estimate sanctioned on 25.10.2021. Railway
117 road over bridge in 2018 RRSK, Portion contract awarded on 09.05.22 and work is in
lieu of manned level EBR(Dep), progress. Pilling completed 28/28, Pier 4/4 completed
crossing No.257 & EBR(S) upto Bed block level. P-12 Pier Cap done. Work in
258 near progress for other pier cap shuttering. Girder launching
Chowkipada planned in Mar'24.
State portion : Agreement drawn & excavation
work just started."
20
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
29 118 30 CAO C Baripada-Bhanjpur - 2017- S.Fund, 923700 4449 1800 1766 31/03/2024 S 20 "1) GAD approved. Detailed estimate sanctioned. Rly
3-lane road over 2018 RRSK, portion : Tender awarded on 24.02.2020. Work
bridge in lieu of level EBR(Dep), stopped due electrical infringement. Payment made to
crossig No.RB-36 EBR(S) TPNODL on 28.3.22 for 11 KV Power line Crossing,
but yet not shifted. The agency already gone for
arbitration proceeding.
2) State portion : Tender for approaches awarded on
04.04.2022 but closed due to LA issue.
3) Local MP requested to Rly not to execute the ROB."
30 PB 30 CAO C Balasore-Nilgiri 2017- S.Fund, 426786 54013 25900 22683 30/06/2024 RE UP 80 "1) GAD finalised on 23.06.17.
119 Road - 3-lane road 2018 RRSK, 2) Detailed estimate sanctioned.
over bridge EBR(Dep), Rly portion (1X48.0m BSG): Substructure completed.
No.268/A in lieu of EBR(S) Tender short closed as land was not available to
level crossing No.80 assemble the BSW Girder. Land recently handed over.
Tender for balance work awarded on 06.01.23. QAP &
WPSS approved. Fabrication of Girder is in progress.
State portion: 150 Piles completed out of 150 nos, 25
pile cap completed out of 25, Abutment Cap 2 Nos
completed. 24 Piers completed out of 25, 24 pier cap
completed out of 25.
RE to be prepared.
31 PB 30 CAO C Panposh-Kalunga - 2017- S.Fund, 699547 64797 38000 21168 31/12/2024 S 30 "1) Railway Portion: substructure completed. Contract
120 2-lane road over 2018 RRSK, terminated. Fresh tender finalised and work resumed.
bridge in lieu of EBR(Dep), 3 piers out of 04 nos. completed.
manned level EBR(S) 2) State portion : Tender will be invited after
crossing No.214 completion of Land acquisition tender to be invited
after completion of Land acquisition process.
Alignments changed and send for approval of State
Authority."
32 PB 30 CAO C Mahalimarup- 2017- S.Fund, 378050 199228 80000 74537 31/03/2023 RE UP 100 ROB opened for public traffic on 01.07.2023 & LC
121 Rajkharswan - Road 2018 RRSK, closed.
over bridge in lieu of EBR(Dep),
level crossing EBR(S)
No.160
21
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
33 PB 30 CAO C Kendposi-Maluka - 2017- S.Fund, 404228 371574 90900 81163 30/05/2023 RE UP 100 ROB opened for public traffic on 01.07.2023 & LC
122 Road over bridge in 2018 RRSK, closed.
lieu of manned level EBR(Dep),
crossing No.RBK-37 EBR(S)
34 PB 30 CAO C Jamadoba-Bhaga - 2017- S.Fund, 262324 38555 600 1560 31/03/2026 S 30 "Railway portion: work was started on 08.03.21 but
123 Road over bridge in 2018 RRSK, stopped due to under ground water pipeline of
lieu of level crossing EBR(Dep), JAMADA (Jharkhand govt.) found. Water pipeline
No.AM-34 EBR(S) shifted by JAMADA. Girder fabrication completed at
workshop. Mean-while the level crossing which was
closed for execution of ROB works, has been opened
for road users as per instruction of DRM/Adra due to
demand of local people. Division should intervene in
the issue.
Approach portion: Agency not yet fixed by State Govt.
of Jharkhand."
22
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
Works < 5 years
35 LB 30 CAO C Kharagpur : 2020- RRSK/EBR 74500 5198 10000 31156 6/30/2024 S 35 "Detailed estimate of ` 7.45 cr sanctioned on 11.06.21.
154 Widening of ROB 21 (S) Tender of ` 6.2 cr awarded on 31.05.22. Work in
(UW) (Bridge No. 125H1 progress. Pile- 16/16. Pile cap-2/2, Abutment-2/2.
(1X10.82M + Work in progress.
2X8.445M) ) at West Approach road- (75+25)x7.5m= 100x 7.5m.
end of Town Thana. Bow string Girder of 30m span -0/1. Girder Raw
material inspected by Railway on 28.11.2023. Draft
print of Launching scheme for ROB Girder submitted
by the agency. "
36 LB 30 CAO C Haur - 2021- S.Fund, 523657 0 100 0 NF N 0 Joint inspection done. Alignment plan awaited from
156 Radhamohanpur : 22 EBR(Dep) State. As per minutes of meeting on dt 22.8.23,
(UW) ROB in lieu of CE/Plg/P.W(Rds)/Dte stated that land schedule,
manned LC No. 50 estimate for RR, estimate for permanent structure an
at km 84/11-13 utility shifting will be carried out by State Highway
(GQ/GD). planning circle. Now Railway will bear full cost of ROB
and accordingly estimate will be prepared.
37 LB 30 CAO C Sardiha - Jhargram : 2021- S.Fund, 480988 0 100 0 NF N 0 During meeting dt. 22.08.23 with State Authority, it was
159 ROB in lieu of 22 EBR(Dep) stated that alternative alignment was to be explored
(UW) manned LC No. 81 considering site constraint by State Govt. Again join
at km152/23-25 inspection conducted on 05.09.2023 for revised
(GQ/GD). alignment which is proposed 750m (KGP end) from
existing LC. Detailled Survey to done by State Govt.
Now Railway will bear full cost of ROB and accordingly
estimate will be prepared.
38 LB 30 CAO C Hijli - Benapur : ROB 2021- S.Fund, 522692 0 500 70 NF N 0 As asked by State Govt, revised GAD of Rly portion
164 in lieu of manned LC 22 EBR(Dep) with carriage width of 7.5m approved by CBE and
(UW) No. 6 at km 125/1-3 submitted to State Govt. for preparation of Combind
of KGP-BLS section. GAD on 01.11.2023. Now Railway will bear full cost of
(GQ/GD). ROB and accordingly estimate will be prepared.
39 LB 30 CAO C Balichak - 2021- S.Fund, 464362 0 100 0 NF N 0 During meeting on dt 22.8.23, CE/Plg/P.W(Rds)/Dte
165 Shyamchak : ROB in 22 EBR(Dep) stated that, alignment plan to be submitted shortly.
(UW) lieu manned of LC Now Railway will bear full cost of ROB and accordingly
No. 54 at km 95/34- estimate to be prepared.
96/2 (GQ/GD).
23
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
40 LB 30 CAO C Benapur - 2021- S.Fund, 484121 0 500 70 NF N 0 As asked by State Govt, revised GAD of Rly portion
166 Narayangarh : ROB 22 EBR(Dep) with carriage width of 7.5m approved by CBE and
(UW) in lieu of manned LC submitted to State Govt. for preparation of Combind
No. 10 at km GAD on 01.11.2023. Now Railway will bear full cost of
131/25-27 of KGP- ROB and accordingly estimate will be prepared.
BLS section
(GQ/GD).
41 LB 30 CAO C Gidhni Yard : ROB 2021- S.Fund, 461084 0 100 0 NF N 0 LC closed by Div on 29.10.21 after commissioning of
167 in lieu of manned LC 22 EBR(Dep) RUB. PCE may review the work.
(UW) No. 92 (GQ/GD).
42 LB 30 CAO C Dantan - 2021- S.Fund, 50.1305 0 100 0 NF N 0 As per minutes of meeting on dt 22.8.23
170 Lakshannath Road : 22 EBR(Dep) CE/Plg/P.W(Rds)/Dte stated that Prima –facie it
(UW) ROB in lieu of appears that the construction of ROB is not feasible,
manned LC No. 41 however PWD and Railway would explore alternative
at km 175/9-11 of alignment. Now Railway will bear full cost of ROB and
KGP-BLS section accordingly estimate will be prepared.
(GQ/GD).
43 LB 30 CAO C Madpur - Jakpur : 2021- S.Fund, 463793 0 100 0 NF N 0 Joint Inspection conducted, Proposed alignment plan
171 ROB in lieu of 22 EBR(Dep) awaited from State Govt. During meeting on dt
(UW) manned LC No. 56 22.8.23, CE/Plg/P.W(Rds)/Dte stated that, alignment
at km 103/3-5 plan will be submitted shortly. Now Railway will bear
(GQ/GD). full cost of ROB and accordingly estimate will be
prepared. Joint inspection was conducted on
24.11.2023 Report to be prepared by State Govt.
44 LB 30 CAO C Hijli - Benapur : ROB 2021- S.Fund, 509314 0 100 0 NF N 0 Joint Inspection conducted . During meeting on dt
173 in lieu of manned LC 22 EBR(Dep) 22.8.23 with State, CE/Plg/P.W(Rds)/Dte stated that,
(UW) No. 4 at km 121/9- alignment plan would be submitted shortly. Now
11 of KGP-BLS Railway will bear full cost of ROB and accordingly
section. (GQ/GD). estimate will be prepared.
45 LB 30 CAO C Belda- Nekurseni : 2021- S.Fund, 533690 0 100 0 NF N 0 Joint Inspection conducted. During meeting on dt
174 ROB in lieu of 22 EBR(Dep) 22.8.23 with State, CE/Plg/P.W(Rds)/Dte stated that,
(UW) manned LC No. 26 alignment plan would be submitted shortly. Now
at km 151/25-27 of Railway will bear full cost of ROB and accordingly
KGP-BLS section estimate will be prepared.
(GQ/GD)
46 LB 30 CAO C Jhargram - Gidhni : 2021- S.Fund, 475076 0 100 0 NF N 0 In the meeting dt. 22.08.23 with State Authority, it is
169 ROB in lieu of 22 EBR(Dep) decided that resurvey to be done to fix alignment.
(UW) manned LC No. 83 Accordingly joint inspection conducted on 05.09.2023
at km 155/1-3 for revised alignment, which is proposed 250m (Tata
(GQ/GD). end) from existing LC. Detailled Survey to done by
State Govt. Now Railway will bear full cost of ROB and
accordingly estimate will be prepared.
24
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
47 LB 30 CAO C Haur - 2022- S.Fund, 449686 0 100 0 NF N 0 Alignment plan finalised and handed over to Rly.
181 Radhamohanpur : 23 EBR(Dep) Railway portion GAD sent to state Govt. on 02.05.22
(UW) ROB in lieu of for preparation of combined GAD. But combined GAD
manned LC No. 49 not yet submitted by state govt . Land schedule,
at km 79/17-19 estimate for RR, estimate for permanent structure and
(GQ/GD). utility shifting will be carried out by State Highway
Planning Circle. Now Railway will bear full cost of ROB
and accordingly estimate will be prepared.
48 LB 30 CAO C Kharagpur - 2022- S.Fund, 519400 0 100 0 NF N 0 The work has been sanctioned on 15.05.2023. Railway
(UW) Nimpura : 23 EBR(Dep) will bear full cost of ROB and accordingly estimate will
Construction of ROB be prepared.
lieu of manned LC
No. 58DN line
(GQ/GD)
49 LB 30 CAO C Kharagpur - Sardiha 2022- S.Fund, 500568 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
867 : Construction of 23 EBR(Dep)
ROB lieu of manned
LC No. 65 (GQ/GD)
50 LB 30 CAO C Hijli - Belda : 2022- S.Fund, 493739 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
868 Construction of ROB 23 EBR(Dep)
lieu of manned LC
No. 16 (GQ/GD)
51 LB 30 CAO C Kharagpur - Sardiha 2022- S.Fund, 497957 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
869 : Construction of 23 EBR(Dep)
ROB lieu of manned
LC No. 62 (GQ/GD)
52 LB 30 CAO C Hijli - Belda : 2022- S.Fund, 495161 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
870 Construction of ROB 23 EBR(Dep)
lieu of manned LC
No. 7 (GQ/GD)
53 LB 30 CAO C Gidhni - Chakulia : 2022- S.Fund, 499991 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
871 Construction of ROB 23 EBR(Dep)
lieu of manned LC
No. 99 (Kanimohuli)
(GQ/GD)
54 LB 30 CAO C Hijli - Belda : 2022- S.Fund, 493757 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
872 Construction of ROB 23 EBR(Dep)
lieu of manned LC
No. 23 (GQ/GD)
25
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
55 LB 30 CAO C Kharagpur - Sardiha 2022- S.Fund, 498739 0 100 0 NF N 0 Work transferred from GSU/KGP on 29.09.23.
873 : Construction of 23 EBR(Dep)
ROB lieu of manned
LC No. 67 (GQ/GD)
56 PB 88 30 CAO C Uluberia - Birshibpur 2010- S.Fund, 377072 192090 1 0 Commissione Y 100% ROB commissioned on 09.12.2019 and LC No. 28 has
ROB in lieu LC No. 11 RRSK d on been closed.
28 at Km 32/29-31. EBR(S) 09.12.19.
57 LB 30 CAO C Kharagpur : ROB & 2020- S.Fund, 215700 180914 22500 22547 133A Y 100% ROB 133B & RoR 133A completed and commissioned
168 ROR at CME Gate 21 RRSK commissione on 25.02.22 & 19.02.22 respectively.
(UW) for replacement of d on Final bill is under preparation.
ROB No. 133B & 19.02.22.
ROR No. 133A. 133B
commissione
d on
25.02.22.
58 LB 30 CAO C ROB in lieu of 2021- RRSK 635088 0 100 0 N.F. N 0 Part Estimate sanctioned. State Govt has expressed
113 manned LC No. 22 EBR(Dep) willingness to do the entire work on Single Entity.
(UW) BG-27 at Km
344/12-13 between
Mohuda- Khanodih.
59 LB 30 CAO C Asanbani - 2022- S.Fund, 526822 0 100 0 31.12.2026 N - Part Estimate sanctioned. GAD is under preparation.
121 Salgajhari ROB at 23
(UW) Km 239/19-21 in lieu
of LC No. 136
(GQ/GD)
60 LB 30 CAO C Lotapahar - Sonua : 2021- S.Fund, 515170 0 100 0 NF N 0 GAD under preparation. Part Estimate sanctioned. To
123 ROB at Km. 22 be executed by NHAI.
(UW) 325/13-15 LC No.
179 (GQ/GD)
61 LB 30 CAO C Lotapahar - Sonua : 2021- S.Fund, 513942 0 100 0 NF N 0 GAD under preparation. Part Estimate sanctioned. To
125 ROB at Km. 22 be executed by NHAI.
(UW) 328/05-07 LC No.
180 (GQ/GD)
62 LB 30 CAO C Galudih - 2021- S.Fund, 438208 0 100 0 NF N 0 GAD preparation in progress. Part Estimate for
184 Rakhamines : ROB 22 Design/Drg sanctioned. Joint Inspection conducted on
(UW) at Km. 224/1-3 in 28.06.2021, Proposed alignment plan not yet
lieu of LC No. 127 in submitted by the State Govt.for which letter issued to
Kharagpur - Tata State Govt. on 29.3.22, 10.05.22 & 01.03.23.
section
26
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
63 LB 30 CAO C Ghatshila - Galudih : 2021- S.Fund, 51.6601 0 1000 438 Mar'24. DE UP 0 Only one approach towards nearby existing ROB at LC
185 ROB in lieu of 22 No 121 will suffice and DM/East Singbhum has
(UW) manned LC No. 122 accorded NOC for such arrangement instead of
at km 214/13-15 of construction of full ROB. Concent of DC jamshedpur
KGP-TATA section obtained for closure of LC by road diversion. GAD is
(GQ/GD) approved by CBE/SER and submitted to State Govt on
04.10.23 for signature. Soil investigation completed
and structural drawing under approval. Detailed
Estimate under sanction.
64 LB 30 CAO C Dalbhumgarh - 2022- S.Fund, 502232 0 500 0 NF N 0 The work has been sanctioned through IRPSM against
(UW) Ghatsila : 23 EBR(Dep) PB No 133 of 23-24. GAD under preparation
Construction of ROB and part estimate is to be prepared for design and
(Road Over Bridge) drawing.
in lieu of manned LC
No. 119 (GQ/GD)
65 LB 30 CAO C Dalbhumgarh - 2022- S.Fund, 503786 0 500 0 NF N 0 The work has been sanctioned through IRPSM against
(UW) Ghatsila : 23 EBR(Dep) PB No 133 of 23-24. GAD under preparation
Construction of ROB and part estimate is to be prepared for design and
(Road Over Bridge) drawing.
in lieu of manned LC
No. 118 (GQ/GD)
66 LB 30 CAO C Rakhamines - Tata : 2022- S.Fund, 498184 0 100 0 NF N 0 The work has been sanctioned on 15.05.2023. GAD
(UW) Construction of ROB 23 EBR(Dep) under preparation and part estimate is to be prepared
(Road Over Bridge) for Design & Drawing.
in lieu of manned LC
No. 132 (GQ/GD)
67 LB 30 CAO C Rakhamines - Tata : 2022- S.Fund, 500938 0 100 0 NF N 0 The work has been sanctioned on 15.05.2023. GAD
(UW) Construction of ROB 23 EBR(Dep) under preparation and part estimate is to be prepared
(Road Over Bridge) for Design & Drawing.
in lieu of manned LC
No. 133 (GQ/GD)
68 LB 30 CAO C Basta - Rupsa : 2021- S.Fund, 646046 0 100 0 NF N 0 Joint Inspection conducted on 19.06.2019, Proposed
157 ROB in lieu of 22 EBR(Dep) alignment plan not yet submitted by the State Govt. for
(UW) manned LC No. 67 which letter issued to State Govt. on 29.3.22, 10.05.22,
at km 212/21-23 of 01.03.23, 22.05.23, 27.06.23 & 21.07.23.
KGP-BLS section
(GQ/GD).
27
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
69 LB 30 CAO C Basta - Rupsa : 2021- S.Fund, 532600 0 100 0 NF N 0 Joint Inspection conducted on 21.06.2019, Proposed
160 ROB in lieu of 22 EBR(Dep) alignment plan not yet submitted by the State Govt. for
(UW) manned LC No. 61 which letter issued to State Govt. on 29.3.22, 10.05.22,
at km 203/29-31 of 1.03.23, 22.05.23 ,21.07.23.
KGP-BLS section
(GQ/GD).
70 LB 30 CAO C Bahanagabazar 2021- S.Fund, 515089 0 500 77 NF N 0 State Govt will execute the work though cost sharing
172 Yd. : ROB in lieu of 22 EBR(Dep) on single entity basis. Part Estimate for Design/Drg
(UW) manned LC No. 94 sanctioned. Rly portion GAD submitted to State Govt
of BLS-BHC section on 21.09.23. Combined GAD under preparation by
(GQ/GD). State Govt. Detailed estimate under vetting.
71 LB 30 CAO C Amarda Rd. - 2021- S.Fund, 566229 0 100 0 NF N 0 JJoint inspection conducted on 01.08.23. Alignment
175 Basta : ROB in lieu 22 EBR(Dep) plan not yet submitted by State Govt.
(UW) of manned LC No.
60 at km 202/11-13
of KGP-BLS section
(GQ/GD).
72 LB 30 CAO C Haldipada - 2021- S.Fund, 604614 0 100 0 NF N 0 Joint inspection conducted on 18.07.23. For early
176 Balasore : ROB in 22 EBR(Dep) submission of alignment plan a letter issued to
(UW) lieu of manned LC CE/WBP/Odisha on 21.07.23.
No. 78 at km 230/3-
5 of KGP-BLS
section (GQ/GD).
73 LB 30 CAO C Soro - Markona : 2021- S.Fund, 495934 0 100 0 NF N 0 GAD under preparation. Joint inspection conducted on
178 ROB in lieu of 22 EBR(Dep) 18.07.23. Alignment plan received from State Govt.
(UW) manned LC No. 106 on 12.10.23. GAD (Railway proper) submitted to Div
at km 265/33-35 of for approval on 30.11.2023.
BLS-BHC section
(GQ/GD).
74 LB 30 CAO C Ranital - Bhadrak : 2021- S.Fund, 484798 0 100 0 NF N 0 GAD preparation in progress. Part Estimate for
180 ROB in lieu of 22 EBR(Dep) Design/Drg sanctioned. Joint Inspection conducted on
(UW) manned LC No. 115 24.08.21. Alignment plan received from State Govt. on
at km 286/13-15 of 12.10.23. GAD (Railway proper) submitted to Div for
BLS-BHC section approval on 30.11.2023.
(GQ/GD).
75 LB 30 CAO C Rourkela - 2021- S.Fund, 555284 0 100 0 31.12.2024 DE UP 0 GAD approved. Detailed estimate submitted to State
129 Jharsuguda : ROB 22 EBR(Dep) Govt. for acceptance. Tender will be called after
(UW) in lieu of LC No. 239 sanction of estimate.
& FOB at LC No.
240 at BMB yard of
TGM-DIH Section.
(GQ/GD)
28
Works under PH-30
SN PB PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No Work Year Cost Upto 23-24 Prog
March (%)
'23
76 LB 30 CAO C Soro - Markona : 2021- S.Fund, 493764 0 100 0 NF N 0 GAD under preparation. Part Estimate sanctioned.
179 ROB in lieu of 22 EBR(Dep) Joint Inspection conducted on 24.08.21. Alignment
(UW) manned LC No. 110 plan received from State Govt. on 12.10.23. GAD
at km 278/21-23 of (Railway proper) submitted to Div for approval on
BLS-BHC section 30.11.2023.
(GQ/GD).
77 LB- 30 CAO C Road Over Bridge in 2023- S.Fund, 633352 0 100 0 NF N 0 Work recently appeared in vide Law Book 2023-24 and
1136 lieu of manned level 2024 RRSK allotted to CAO/C vide PCE's letter dated 04.01.2024.
crossing KA-140 at EBR(Dep)
km 287/15-17
between ADA-JOC
in Adra Divn
78 LB- 30 CAO C ROB (Road Over 2023- S.Fund, 627678 0 100 0 NF N 1 Work recently appeared in vide Law Book 2023-24 and
1137 Bridge) in lieu of LC 2024 RRSK allotted to CAO/C vide PCE's letter dated 04.01.2024.
No. KA-162 at km EBR(Dep)
322/2-3 in between
BURN-ASN Station
in Adra Division
79 LB- 30 CAO C ROB (Road Over 2023- S.Fund, 616914 0 100 0 NF N 2 Work recently appeared in vide Law Book 2023-24 and
1138 Bridge) in lieu of LC 2024 RRSK allotted to CAO/C vide PCE's letter dated 04.01.2024.
No. KA-127 at km EBR(Dep)
269/8-10 in between
JPH and IBL Station
in Adra division.
29
Works under PH-33
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. Upto BG 23-24 Exp in TDC Estimate Phy. Prog REMARKS
Work Year Cost March '23 23-24 (%)
1 PB 33 CSTE C Howrah-Panskura - 2004- DRF, 455773 366876 15300 15500 31/03/2021 RE UP 97 Physical work is completed. Final bill Under
418 Repl. of automatic 2005 RRSK, Preparation.
signalling for EBR(S)
enhancing safety in
train operation
30
Works under PH-42
SN PB PH Agency Short Name of Work Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No. Year Cost Upto 23-24 Prog
March (%)
'23
Works > 10 years
1 PB 42 CAO C Shalimar - Two pit 2011- DF(3), 192703 202725 0 0 30/04/2024 S 99 Work completed. Construction of Pedestal and misc.
494 lines with catwalk & 2012 RRSK, works completed. Final bill under preparation.
light emitting diode EBR(S)
lighting arrangement
2 PB 42 CAO C Padmapukur - 2011- DF(3), 377835 261541 673 2360 30/03/2024 S 98 Work completed.
495 Development of major 2012 RRSK,
coaching maintenence EBR(S)
facilities
3 PB 42 CAO C Bondamunda - 2016- Cap., 113712 91653 2097 2140 31/05/2024 S 98 Engg.-Work completed on 31.3.21. Final Bills passed.
496 Covered shed with CC 2017 EBR(S) Elect- Work completed. Final bill passed.
flooring on existing M&P EOT Crane - Under COFMOW procurement, DP
sick line area - May'24.
4 PB 42 CAO C Haldia - Upgradation 2016- Cap., 326065 232947 11128 5694 24/03/2024 S 90 "1) All engineering work completed. Final bill paid.
497 of sick line 2017 EBR(S) 2) Electrical -Contract awarded. Work in progress.
3) Revised Estimate of Rs. 32.61 cr. has been
sanctioned."
Due:PTC of shearing m/c.
5 PB 42 CAO C Tikiapara & Panskura - 2016- Cap., 119072 41721 6417 6417 31/10/2024 S 20 "1) EMU carshed at Tikiapara: Completed.
498 Dev. of infrastructure 2017 EBR(S) 2) EMU carshed at Panskura: Design & drawings
for maint of 3 Ph. EMU completed. LOA of fresh tender of Panskura work
rakes at EMU carshed issued on 29.11.2023. Mobilization in progress.
at TPKR & extn of Electrical: All OHE infringement cleared."
EMU carshed at PKU
to accomodate 12 car
31
Works under PH-42
SN PB PH Agency Short Name of Work Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No. Year Cost Upto 23-24 Prog
March (%)
'23
6 PB 42 CAO C Kharagpur- Extension 2016- Cap., 213378 157100 2016 516 31/03/2024 S 95 1) Civil Engineering works Completed
499 of MEMU shed 2017 EBR(S) 2) OHE work - Completed.
3) Gen Services work – Completed.
4) One transformer to be installed.
7 PB 42 CAO C Santragachi - 2017- Cap., 299363 107688 34242 47838 31/10/2024 S 55 1) For extension of shed ARM building has to be
502 Renovation of pit lines 2018 DRF, shifted first.
& augmentation of sick EBR(S) 2) Administrative building : completed and part of the
lines building occupied by O/L.
3) IOH Shed & Sick line Shed - IOH shed- piling
22/68/84 , pile cap- 8/28, Steel col.- 0/28, steel truss-
0/14.
4)Sick line Shed- Open foundation- 0/36, Steel col.
0/36 , Steel truss- 0/18. For extension of Sick line
shed, dismantling of existing ARM building started
(10%) and for design of foundation.
8 PB 42 CAO C Kharagpur - Extension 2018- Cap., 107282 90709 16436 25127 31/01/2024 S 100 Work completed. Final bill paid.
504 of heavy lifting shed & 2019 EBR(S)
addl stabling lines at
MEMU car shed
(Phase-1)
9 PB 42 CAO C Santragachi - 2018- Cap. 141486 0 0 0 N 0 Proposed for drop through IRPSM. Currently with Rly.
508 Coaching depot 2019 Bd.
washing line covered
shed
10 PB 42 CAO C Kharagpur - Homing of 2018- Cap., 159609 96400 42425 34746 31/01/2024 S 100 Work completed. Final bill paid.
509 electric locos in diesel 2019 DF(3)
loco shed
11 LB 42 CAO C BONDAMUNDA: 2018- RRSK, 102622 99767 8098 8084 31/03/2024 S 98 Work completed.
592 Extension of ROH 2019 EBR(S)
depot.
12 LB 42 CAO C MSL/BNDM & ADTP:- 2018- RRSK, 145202 110668 27742 27278 30/11/2023 S 100 A) At MSL/ BNDM Scope: Extension of Shed
597 Up-gradation of 2019 EBR(S) 40.0x26.2 m :- Completed and handed over to user
sickline maintenance department & O/L.
facilities. B) ADTP- Completed and handed over to user
department & O/L.
32
Works under PH-42
SN PB PH Agency Short Name of Work Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No. Year Cost Upto 23-24 Prog
March (%)
'23
13 LB 42 CAO C BONDAMUNDA: 2018- RRSK, 488631 45400 48538 41308 31/10/2024 S 16 Work recently transferred from WPO/Patna. Letter
599 Detachment free rake 2019 EBR(S) issued to CME (Plg)/GRC for submission of details
examination facilities. from WPO/Patna. A letter issued to field units for
submission of estimate on 20.12.2023.
Now, as per CME/Plg letter No. M8/201/Closure-WPO
dated 13.03.24 joint measurement of ecxecuted works
for novation of contract agreement is to be done in
view of closure of WPO/Patna. Letter issued to field
units for their action.
14 LB 42 CAO C Nimpura : Freight 2018- RRSK, 128365 116877 3007 20 31/03/2024 S 95 "Engg. work Completed. Final bill paid.
612 examination/ ROH 2019 EBR(S) 1) Electrical works in progress."
extension.
15 LB 42 CAO C Hatia - Extn. of new 2018- RRSK, 153459 86503 5738 5739 31/05/2024 S 97 Engg. Work completed. Handing over processes is in
630 coaching complex at 2019 EBR(S) progress.
coaching depot Pending
CRANE (Intricate) - DP May'24.
16 LB 42 CAO C Kharagpur Workshop:- 2018- RRSK, 353938 13658 64975 73370 31/10/2024 S 40 Work recently transferred from WPO/Patna. Letter
644 Augmentation of POH 2019 EBR(S) issued to CME (Plg)/GRC for submission of details
capacity for LHB from WPO/Patna. A letter issued to field units for
Coaches. submission of estimate on 20.12.2023.
Now, as per CME/Plg letter No. M8/201/Closure-WPO
dated 13.03.24 joint measurement of ecxecuted works
for novation of contract agreement is to be done in
view of closure of WPO/Patna. Letter issued to field
units for their action.
33
Works under PH-42
SN PB PH Agency Short Name of Work Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No. Year Cost Upto 23-24 Prog
March (%)
'23
Works work< 5 years
17 LB 42 CAO C Anara: Development 2019- Cap 620376 4800 70000 45610 12/31/2024 S 13 Work recently transferred from WPO/Patna. Letter
572 of infrastructure for 2020 EBR(S) issued to CME (Plg)/GRC for submission of details
integrated from WPO/Patna. A letter issued to field units for
maintenance of submission of estimate on 20.12.2023.
MEMU, DEMU and Now, as per CME/Plg letter No. M8/201/Closure-WPO
other Coaching Stock dated 13.03.24 joint measurement of ecxecuted works
in SER (Phase 1) for novation of contract agreement is to be done in
view of closure of WPO/Patna. Letter issued to field
units for their action.
18 LB 42 CAO C Bokaro steel 2022- Cap 204562 0 0 0 - S 0 Work sanctioned by Rly Board in 2022-23 under
587 city~~Provision of New 2023 Umbrella works and included in LB 23-24. Work just
Sick lines to cater sick allotted to SER (Con) vide letter No. PL/Budget/2023-
wagons arising out of 24/483 dt. 17.05.2023. Detailed Estimate of Rs. 20.46
Empty Yard and cr. sanctioned. D&D under process. Tender under
Departure Yard/BKSC preparation.
19 LB 42 CAO C Bokaro steel 2022- Cap 278702 0 0 0 - S 0 Work sanctioned by Rly Board in 2022-23 under
583 city~~Extension of 2023 Umbrella works and included in LB 23-24. Work just
Sick line Bokaro to allotted to SER (Con) vide letter No. PL/Budget/2023-
create infrastructure 24/483 dt. 17.05.2023. Detail estimate of Rs. 27.87 cr.
for ROH of has been sanctioned. Tender under preparation.
BOXNHL25T and
other wagons
20 591 42 CAO C ELS/TATA:- 2019- Cap 279936 9486 40000 61695 10/31/2024 S 49 "1) Work sanctioned under Umbrella Work 2019-20. 2)
Increasing holding 2020 EBR(S) Work de-frozen as communicated vide CWE/GRC's
from 150 to 200 locos letter dt. 14.07.2021 and accordingly Detailed Estimate
has been sanctioned.
3) Tender awarded on 22/04/2022 and work is in
progress. Foundation work completed. Column
erection completed.
21 LB 42 CAO C BONDAMUNDA: 2021- Cap 874353 0 100000 10398 - S - Work recently transferred from WPO/Patna. Letter
594 Detachment free rake 2022 issued to CME (Plg)/GRC for submission of details
examination facilities, from WPO/Patna. A letter issued to field units for
Phase-II. submission of estimate on 20.12.2023.
Now, as per CME/Plg letter No. M8/201/Closure-WPO
dated 13.03.24 joint measurement of ecxecuted works
for novation of contract agreement is to be done in
view of closure of WPO/Patna. Letter issued to field
units for their action.
34
Works under PH-42
SN PB PH Agency Short Name of Work Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No. Year Cost Upto 23-24 Prog
March (%)
'23
22 LB 42 CAO C TATA -Extension of 2022- Cap 512911 0 1 0 - S - Work sanctioned by Rly Board in 2022-23 under
607 ROH Shed at MSL & 2023 Umbrella works and included in LB 23-24. Work just
Rake examination allotted to SER (Con) vide letter No. PL/Budget/2023-
facilities at C&W yards 24/483 dt. 17.05.2023. Detailed estimate of Rs. 51.29
and ADTP- cr. sanctioned on 19.01.2024.
Construction of new
sick line facilities.
23 LB 42 CAO C Santragachi : To 2021- Cap 0 0 20000 0 - - - Work transferred to CPM/GSU/KGP. Work returned
607 enhance/ augment 2022 back from GSU/KGP on 29.09.23.
facility at ELS/SRC for Detailed estimate to be prepared.
the homing capacity of
ELS/SRC from 50 to
125 (PH-II).
24 LB 42 CAO C Augmentation of 2021- Cap 0 0 20000 0 - - - New work. Work transferred to CPM/GSU/KGP. Work
610 ELS/SRC from 50 2022 returned back from GSU/KGP on 29.09.23.
to100 locos(Phase-I) Detailed estimate to be prepared.
25 LB 42 CAO C SER: Upgradation of 2022- Cap 2268700 0 10000 0 - S - DE sanctioned by Railway Board on 04-03-24 at a cost
626 maintenance 2023 of Rs. 226.87 Cr.
infrastructure at
Shalimar into Vande
Bharat Chair Car
maintenance cum
workshop depot.
27 LB 42 CAO C Kharagpur Wagon 2019- Cap 93437 33009 20000 38203 3/31/2024 S 70 "1) Detailed Estimate of Rs 9.34 cr. Chargeable to
638 Shop:- New stainless 2020 EBR(S) Capital head sanctioned on 29.04.2021.
steel wagon Paint 2) Tender awarded.
shop and Pit line shop. 3) Track work to be done by workshop. Design of shed
approved.
4) RCC pedestal 50/50, Fabrication and erection of
Steel col 50/50, Erection of truss-25/25, Roof sheeting-
Completed, Boundary wall- completed.
5) Electrical works in progress.
35
Works under PH-42
SN PB PH Agency Short Name of Work Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
No. Year Cost Upto 23-24 Prog
March (%)
'23
28 644 42 CAO C Kharagpur Workshop:- 2019- Cap 391869 5793 80000 50885 10/31/2024 S 30 Work recently transferred from WPO/Patna. Letter
Augmentation of POH 2020 EBR(S) issued to CME (Plg)/GRC for submission of details
capacity for LHB from WPO/Patna. A letter issued to field units for
coaches (Phase - II). submission of estimate on 20.12.2023.
Now, as per CME/Plg letter No. M8/201/Closure-WPO
dated 13.03.24 joint measurement of ecxecuted works
for novation of contract agreement is to be done in
view of closure of WPO/Patna. Letter issued to field
units for their action.
36
Works under PH-51
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. Upto BG 23-24 Exp in TDC Estimate Phy. REMARKS
Work Year Cost March '23 23-24 Prog
(%)
1 PB 51 CAO C Adra Division - 2009- DRF 75173 76176 1618 1618 31/03/2024 S 98 All work completed.
551 Reinforced concrete 2010
cement overhead
tanks for improved
water supply
2 LB 51 CAO C Garden Reach - 12 2009- Cap.,DRF 41621 0 8270 33400 31/03/2024 S 85 4 units completed by open line. Balance 8 unit works
699 units M/S Type II 2010 are in progress. Work to be completed by Mar'24 & to
Qrs.at South colony be deleted from IRPSM.
in replacement of
sub-standard Qrs.
No. 12/A/22 at North
colony
3 LB 51 CAO C Garden Reach - 12 2011- Cap.,DRF 58350 0 5400 53000 31/03/2024 S 85 Work is in progress & nearly completion stage.
690 nos. Type-II 2012 Work to be completed by Mar'24 & to be deleted from
Quarters in Pocket-I. IRPSM.
5 PB 51 CAO C Garden Reach - 2016- Cap.,DRF 254100 117882 52120 37225 31/03/2024 S 17 1) Ty-III 12 units (G+6 storied) Completed and
536 Type-II - 48 & type- 2017 inaugurated by GM/SER on 01.02.2023.
III - 12 units 2) Type -II 68 units, Block-1 -36 units (G+9 storied)
piling work completed, Roof slab - 9/10.
Block 2 -32 units( G+8 storied) Pile- 213/213 done. Pile
cap- 76/76. Roof slab - 3/9.
37
Works under PH-51
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. Upto BG 23-24 Exp in TDC Estimate Phy. REMARKS
Work Year Cost March '23 23-24 Prog
(%)
6 PB 51 CAO C Adra Division - Repl. 2016- Cap.,DRF 209398 80397 47161 29846 31/03/2024 S 61 "i) VAA- All 34 units are completed and handed over to
537 of quarters, type-II - 2017 31.12.24 open line.
106 units ii) MHQ- All 36 unis are completed and handed over to
open line.
iii) BJE- The structural work of 20 units out of 36 units
is completed and others are in progress.
7 PB 51 CAO C Kharagpur - 450mm 2016- DF(2) 81620 25307 8585 8506 31/03/2024 S 31 Progress hampered due to non procurement of pipe by
559 dia DI pipe from 2017 the agency. Now, agency procured pipe and laying in
Gokulpur to D&E progress. 5.4 Km done out of 7.3 Km with 300 mm dia.
Reservoir & Repl. of 0.588 Km done out of 4.5 Km with 450 mm dia.
300mm dia pipe
from GKL-4 well to
JE/W office at
Nimpura.
8 PB 51 CAO C Bondamunda - Repl 2017- Cap.,DRF 105066 39527 50459 42992 31/03/2024 S 30 "Scope : 8 Blocks * 48 unit ( G+2 storied )
538 of quarters, type-I & 2018 1 04nos. block (24 unit) completed and handed over to
type-II quarters by open line.
type-II - 48 units 2 02nos.block (12 unit) unit in final stage under
finishing TDC-31.03.2024
3 02nos. Block (12unit) finishing (tiles, kota, putty &
painting) work under progress
38
Works under PH-53
SN PH Agency Short Name of Sanc. Allocn. Sanc Exp. BG 23-24 Exp in TDC Estimate Phy. REMARKS
Work Year Cost Upto 23-24 Prog
March (%)
'23
Works > 5 to 10 years
1 LB 53 CAO C Shalimar : 2018- Cap., 26855 0 0 0 29/02/2024 N 85 "Placing of RCC box below Road completed and
770 Construction of 2019 EBR(S) structural work of both side approaches completed .
Subway for Jetty Finishing work to be done.
passes connection Presently work stopped as there is no jetty. CTPM may
at Station. review requirement.
Principal Secretary/Govt of West Bengal has been
asked to re-start the jetty vide letter dt. 12.07.2022.
(Work done by IRCON)
2 LB 53 CAO C Ranchi jn.:- Major 2022- Cap 4436600 331100 1000000 10000 30/11/2025 S 15 A) South Side:
793 upgradation of 23 31-12-2025 1.South station Building: Foundation work in
Ranchi Railway progress.TDC: 31.10.2024.
station of S E 2. RPF female barrack: finishing work in progress,
Railway at Ranchi TDC:28.03.24.
on 3. Type-3 quarters (12 unit)- finishing work in progress,
Engineering/Procure TDC 15.05.24
ment and 4. Type-2 quarters (69 unit)-
Construction (EPC TW-1:3rd floor slab casting completed.
Mode) TW-2: 5th floor slab casting completed
5. OH tank (25000 gallan): 3rd lift beam reinforcement
in progress.
6. RPF male barrack: Earth work started.
7. GRP barrack: PCC in foundation in progress.
8. Road work: GSB/WMM in progress.
9.Platform work: in progress.
10. Land scapping: drawing to be submit by agency.
B) Noth side
1. Station building: design in process.
C) Air concourse (112mx72m): Drawing to be submit
by Agency.
D) FOB (6m): HQ observations under compliance.
E):FOB (3m): Drawing to be submit by agency
39