FEED for Bio Refinery Project
Requisition for Radar & GWR
2A28-FD-INS-RFQ-0013
0 5-Jul-24 Issued for Information FER ENS CHR/MT
Rev Date Issue Purpose Prepared by Checked by Approved by
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
Revision History
Revision Date Section Page Description Note
0 5-Jul-24 All All First Issuance
2A28-FD-INS-RFQ-0013 Rev. 0 Page 2 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
1 TABLE OF CONTENTS
1 DEFINITIONS ............................................................................................................................ 4
2 EQUIPMENT LIST TO BE SUPPLIED BY VENDOR ................................................................. 4
3 DOCUMENTS ATTACHED TO THIS REQUEST FOR QUOTATION ........................................ 5
4 SCOPE OF SUPPLY AND WORK ............................................................................................. 5
4.1 SCOPE OF SUPPLY ......................................................................................................... 6
4.2 SCOPE OF WORK AND RESPONSIBILITY ..................................................................... 6
5 SPARE PART REQUIREMENT ................................................................................................. 7
6 SPECIAL TOOLS ...................................................................................................................... 7
7 SITE SUPERVISION & TRAINING REQUIREMENT ................................................................. 8
8 DATA TO BE SUBMITTED WITH VENDOR QUOTATION ........................................................ 8
8.1 SPECIFICATION AND INFORMATION ............................................................................. 8
9 INSPECTION AND TEST REQUIREMENT ............................................................................... 9
9.1 QUALITY ASSURANCE .................................................................................................... 9
9.2 FACTORY ACCEPTANCE TEST ...................................................................................... 9
10 TECHNICAL COORDINATION MEETING ............................................................................ 9
11 WARRANTY ......................................................................................................................... 9
2A28-FD-INS-RFQ-0013 Rev. 0 Page 3 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
REQUEST FOR: Radar & GWR
Vendor's proposal for equipment and/or materials shall be in strict accordance with condition stated
in this Request for Quotation and any attached documents, exceptions, deviations, and alternatives
will be valid only if approved in writing by purchaser.
1 DEFINITIONS
Definitions Description
PROJECT NAME Bio Refinery Project
CONTRACTOR PT. Tripatra Engineering
2 EQUIPMENT LIST TO BE SUPPLIED BY VENDOR
Radar
No Tag Number Description QTY REMARKS
1. 510-LZT-0036 Non-contact Radar 1
2. 510-LZT-0037 Non-contact Radar 1
3. 520-LZT-0085 Non-contact Radar 1
4. 520-LZT-0086 Non-contact Radar 1
5. 520-LZT-0083 Non-contact Radar 1
6. 530-LZT-0042 Non-contact Radar 1
7. 530-LZT-0043 Non-contact Radar 1
8. 5310-LT-0001A Non-contact Radar 1
9. 5310-LT-0001B Non-contact Radar 1
10. 310-LT-0025 Non-contact Radar 1
11. 520-LZT-0106 Non-contact Radar 1
12. 520-LZT-0114 Non-contact Radar 1
13. 820-LT-0001 Non-contact Radar 1
GWR
No Tag Number Description QTY REMARKS
1. 900-LT-0007 GWR 1
2. 900-LZT-0003 GWR 1
3. 900-LT-0030 GWR 1
4. 900-LZT-0032 GWR 1
5. 900-LT-0038 GWR 1
6. 900-LZT-0036 GWR 1
7. 850-LT-0006 GWR 1
8. 850-LZT-0007 GWR 1
9. 810-LT-0001 GWR 1
2A28-FD-INS-RFQ-0013 Rev. 0 Page 4 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
No Tag Number Description QTY REMARKS
10. 810-LZT-0005 GWR 1
11. 350-LT-0021 GWR 1
12. 350-LT-0001 GWR 1
13. 100-LZT-007A GWR 1
14. 100-LZT-007B GWR 1
15. 100-LZT-007C GWR 1
16. 100-LZT-015A GWR 1 Interface Level
17. 100-LZT-015B GWR 1 Interface Level
18. 100-LZT-015C GWR 1 Interface Level
19. 100-LZT-021A GWR 1 Interface Level
20. 100-LZT-021B GWR 1 Interface Level
21. 100-LZT-021C GWR 1 Interface Level
22. 100-LT-031 GWR 1 Interface Level
23. 100-LT-037 GWR 1 Interface Level
24. 100-LT-045 GWR 1 Interface Level
3 DOCUMENTS ATTACHED TO THIS REQUEST FOR QUOTATION
1. Applicable Documents
2. Inspection and Test Requirement
3. Deviation List Form
4. Vendor Data Requirement List (VDRL)
4 SCOPE OF SUPPLY AND WORK
Basis in defining Scope of Supply and Work:
a. The attached technical specifications and the standards and codes therein as well as all other
applicable bid documents shall be interpreted as a set of the minimum requirements.
b. Any exclusion associated with the Bidder’s Proposal shall be clearly and completely mentioned
in the vendor’s exception list. Vendor shall clearly identify any deviation to this specification and
the reference codes, standards and project specifications and list them with reference to the
document clause, in the quotation. In absence of any specific mentioning of the deviations, it
shall be assumed that Vendor fully complies and agrees with this requisition and related
documents attached and referenced herein. Approval of Vendor drawings and documents shall
not relieve Vendor of the responsibility to provide safe equipment system functionality in
accordance with the specification.
c. All necessary works or supplies other than those mentioned on bidder’s proposal intended to or
required for achieving a proper performance shall be a responsibility of the successful bidder.
d. Sections 4.1 and 4.2 shall have a meaning as a minimum definitive item and by no mean override
the overall requirement as indicated on other applicable document.
2A28-FD-INS-RFQ-0013 Rev. 0 Page 5 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
4.1 SCOPE OF SUPPLY
The Vendor shall supply the Radar & GWR for Bio Refinery Project. The Radar & GWR shall be
as per project specification, datasheet and shall consist of the following components as minimum
requirement:
Radar & GWR shall be supplied complete with all accessories, spare, tools, services, and
other requirement as indicate on datasheet.
Radar & GWR shall have HART Version 7 communication protocol and Modem for
configuration.
SS 316L Nameplate
Commissioning and Start-Up Spare Parts (list of spare parts with unit price to be provided by
VENDOR)
Two years Operation Spare Parts (list of spare parts to be provided by VENDOR)
Special tools for installation & maintenance, including modem for configuration
All items not listed here but required in applicable drawing and specification
Exception list for specification and any code and standard related in the specification
All facilities and equipment required for testing and inspection
Painting / coating materials for primer coat and touch-up (shop and site)
Finish coating
Consumable material
4.2 SCOPE OF WORK AND RESPONSIBILITY
The Vendor scope of work and responsibility shall also include but not limited to the following:
Supply of engineering, design and quality documents and drawings for installation, operations and
maintenance.
All Inspection and Testing
- Equipment and Material Certification
- Performance Guarantee and Material Warranty
- Factory Acceptance Test (FAT)
- Calibration and Test Report
- etc.
Material selection shall be suitable for service conditions and VENDOR shall indicate all
material will be used in his proposal. The VENDOR shall guarantee the material has been
selected.
Responsibility to meet the local codes governing health and safety.
2A28-FD-INS-RFQ-0013 Rev. 0 Page 6 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
Utility consumption guarantee
VENDOR’s submission shall provide sufficient data to allow the equipment to be evaluated
against the total life of field costs to be incurred. In this respect, equipment capital cost, cost
of spares and utility shall be considered as shall the cost of a proposed field life
maintenance program.
Inspection and Testing as per project specification including:
- Performance & acceptance test
- Other test as specified in data sheet
Preparation and Packing for export shipment
Export Custom Clearance
5 SPARE PART REQUIREMENT
Vendor shall provide the recommended spares and spares list for the Construction & Pre-
commissioning, Commissioning and Start-Up, Spare Part Two Years and Consumables for
Purchaser’s review.
Vendor shall follow original equipment manufacturers recommendations in the preparation of
recommended spare list. Vendor shall note long lead items, available shelf replacement spares listing.
a. Installation & Pre-Commissioning Spare-Part
The installation & pre-commissioning spare part shall be included in the Vendor scope.
b. Commissioning and Start-Up Spares
Vendor shall provide in his Proposal/Quotation and shall be included in the Vendor scope.
c. Two Years Operating and Maintenance Spares
Vendor shall submit 2-years operating & maintenance spares and spares list on their
proposal/quotation for Purchaser’s review.
Also, Vendor shall submit proposed schedule for periodic spare parts replacements, service
and maintenance, during 2 (two) years of Operation & Maintenance period.
Spare parts furnished by Supplier shall also be wrapped and packaged to preserve original as-new
condition under normal conditions of storage anticipated at Site. The same parts shall be properly
tagged by stainless steel tags and coded. All items supplied shall be packaged separately and clearly
marked as “Spare Parts” and shipped with the equipment in accordance with the instructions from
Purchaser.
Packing lists shall be furnished complete and in detail so that parts can be handled without un-crating.
6 SPECIAL TOOLS
Vendor shall provide one (1) set of tools required for the installation and / or maintenance of the
equipment including all ancillary equipment.
Vendor shall furnish a detailed list of these special tools with their Proposal.
2A28-FD-INS-RFQ-0013 Rev. 0 Page 7 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
7 SITE SUPERVISION & TRAINING REQUIREMENT
Vendor shall provide technical assistant/technical support during installation, pre-commissioning,
commissioning, start-up and testing at site. Commissioning shall include troubleshooting, checkout,
and training. It shall be performed by qualified representatives.
8 DATA TO BE SUBMITTED WITH VENDOR QUOTATION
All documents and drawings shall be written in English and be submitted in one original and two
copies.
All documents and drawings shall state the name of Client (end user), Project’s work No., Req. No.,
Item No. and the name of the equipment and / or materials.
8.1 SPECIFICATION AND INFORMATION
Vendor shall submit the following document or data as minimum required data to be attached in
Vendor’s proposal.
a. General Arrangement (GA) / Assembly Drawings with major dimension data and complete
with part list, material and equipment description
b. Sizing & Weight of Equipment/Package and Packing Requirement
c. Bill of Material
d. Data Sheets
e. Functional Design Specification
f. Manufacturer’s Standard Factory Acceptance Test (FAT), pre-commissioning,
commissioning and performance test at Site
g. Propose work, fabrication, and delivery schedule.
h. Recommended spare part list for commissioning, start-up & 2 years operation.
i. Detail list of special tools for installation & maintenance.
j. Proposal for training.
k. Inspection & Test Plan (ITP) and ISO Quality Management Plan and Certification for Client’s
review.
l. Deviation, Comment & Exception list to applicable Project Specification, Code & Standard.
m. Warranty
n. Company profile and experience list indicating similar work performed, including such
information as project name, name of client, start and completion date.
o. Vendor’s reference and Brands / manufacturer’s reference.
p. Sizing & Weight of equipment and packing for inland transportation.
q. Vendor data submission schedule.
Vendor shall furnish data for review and approval in accordance with the relevant project
specification
The Vendor shall furnish data as required on the Vendor Data Requirement List with the
number of copies indicated and in the number of days indicated following receipt of
purchase orders.
The drawings and documents shall be considered part of the order. The order shall not
be considered complete for payment until all items are received.
Note: Purchaser has the right to reject sub-Vendor if his capability is judged poor or not
proven.
2A28-FD-INS-RFQ-0013 Rev. 0 Page 8 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
9 INSPECTION AND TEST REQUIREMENT
Vendor shall carry out the inspection and testing as detailed in RFQ and other referenced
specifications, datasheet (Attachment –B). This shall also include all inspection and testing required
by the applicable codes, standards and local regulations.
9.1 QUALITY ASSURANCE
The Vendor shall submit a quality control program including a typical Inspection & Test Plan (ITP)
for Purchaser’s review. The Vendor shall provide facilities for and cooperate with the Purchaser
and its designated authorized inspectors during manufacturing, assembly and testing.
9.2 FACTORY ACCEPTANCE TEST
1. The Vendor shall submit for review and approval by the Purchaser an Inspection and Test
Plan (ITP) covering all relevant components, completed equipment and systems. The vendor
shall include a description of all proposed standard shop tests with its bid.
2. The Vendor shall provide the Purchaser with at least 30 days’ notice to witness tests run in
both his shop and his Sub-Vendor’s shops.
3. The Vendor shall provide the Purchaser with full access to his and his Sub-Vendor’s plant
facilities to verify that equipment is manufactured and tested as specified.
4. The Vendor shall provide certification records for testing instrumentation for review by the
Purchaser prior to each test.
5. The Purchaser reserves the right to request the Supplier to perform positive material
identification of any corrosion resistant alloy material whose certification is not in accordance
with this specification's requirement or is considered suspect.
6. The VENDOR shall submit fabrication design details and non-destructive examination
procedures as part of his contract document submissions.
10 TECHNICAL COORDINATION MEETING
After the order is awarded, Vendor shall, upon receipt of purchaser’s notice, send a sufficient number
of qualified personnel to purchaser’s office at Vendor’s cost to hold the technical coordination meeting
and design clarification meeting.
11 WARRANTY
The warranty will initiate from the first day after the unit has been places in regular use or
demonstrated capability to support such used by CONTRACTOR / COMPANY and continue for a
period of eighteen (18) months from such start-up or twenty-four (24) months after the date of final
shipment of all equipment and materials, whichever occurs first. The warranty period shall be
extending by the number of days of fraction thereof, that the equipment was inoperable because of
warranty defects.
2A28-FD-INS-RFQ-0013 Rev. 0 Page 9 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
ATTACHMENTS
Attachment A : Applicable Documents
Technical Specification & Philosophy
Instrument Datasheet
Mechanical Equipment Datasheet/Drawing
Attachment B : Inspection and Test Requirement
Attachment C : Deviation List
Attachment D : Vendor’s Data Requirement List
2A28-FD-INS-RFQ-0013 Rev. 0 Page 10 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
ATTACHMENT A
APPLICABLE DOCUMENTS
A. Technical Specification and Philosophy
No Document Number Rev Document Name
General Specification for
1. 2A28-FD-INS-SPC-0003 0
Instrumentation
General Specification for Piping
2. 2A28-FD-PIP-SPC-0001 0
Materials
3. 2A28-FD-PIP-SPC-0003 0 Specification For Painting
B. Instrument Datasheet
No Document Number Rev Document Name
Datasheet for Radar & GWR Level
1. 2A28-FD-INS-DTS-0014 0
Transmitter
C. Mechanical Equipment Datasheet/Drawing
No Document Number Rev Document Name
Mechanical Datasheet for Treated Feed
1. 2A28-FD-MEC-DTS-0028 0
Tank 1 2 (510-T-01-1 2)
Mechanical Datasheet for HVO SAF
2. 2A28-FD-MEC-DTS-0029 0
Storage Tank 12 (520-T-01-1 2)
MDS for Off-spec Storage Tank (530-T-
3. 2A28-FD-MEC-DTS-0030 0
01)
Mechanical Datasheet for Bio Naphtha
4. 2A28-FD-MEC-DTS-0031 0
Storage Tank (520-T-02)
Mechanical Datasheet for HP Stripper
5. 2A28-FD-MEC-DTS-0002 0
OH Separator (100-V-102)
Mechanical Datasheet for High
6. 2A28-FD-MEC-DTS-0006 0
Pressure Cold Separator (100-V-103)
Mechanical Datasheet for Hydrocracker
7. 2A28-FD-MEC-DTS-0010 0
Feed Surge Drum (100-V-108)
Mechanical Datasheet for Product
8. 2A28-FD-MEC-DTS-0012 0
Stripper Reflux Drum (100-V-111)
2A28-FD-INS-RFQ-0013 Rev. 0 Page 11 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
No Document Number Rev Document Name
Mechanical Datasheet for Fractionator
9. 2A28-FD-MEC-DTS-0015 0
Reflux Drum (100-V-113)
Mechanical Datasheet for Sour Water
10. 2A28-FD-MEC-DTS-0020 0
Degassing Drum (900-V-01)
Mechanical Datasheet for Sour Gas
11. 2A28-FD-MEC-DTS-0025 0
Reflux Drum (900-V-02)
Mechanical Datasheet for Oily Drain
12. 2A28-FD-MEC-DTS-0027 0
Drum (810-V-01)
Mechanical Datasheet for Sour Water
13. 2A28-FD-MEC-DTS-0038 0
Stripper (900-C-01)
Mechanical Datasheet for HDO Effluent
14. 2A28-FD-MEC-DTS-0069 0
Steam Generator (100-E-102)
Mechanical Datasheet for Sea Water
15. 2A28-FD-MEC-DTS-0095 0 Pre-Treatment Desalination Package
(310-X-01 310-X-02)
Mechanical Datasheet for Cooling
16. 2A28-FD-MEC-DTS-0098 0
Tower Package (350-X-01)
2A28-FD-INS-RFQ-0013 Rev. 0 Page 12 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
ATTACHMENT B
INSPECTION AND TEST
INSPECTION LEVEL REQUIREMENTS
R: Review Documents
W: Witness
D: Prepare Document
I: Information
No Items VENDOR PURCHASER COMPANY
1. Inspection and Testing Plan (ITP) D R R
2. Inspection during fabrication, testing D R R
3. Calibration Test D R R
4. Functional Test D R R
5. Factory Acceptance Test D W W
7. Site Acceptance Test D W W
8. Other: as per applicable project Doc.
Specifications, Codes, Standards & D R R
Data Sheets
2A28-FD-INS-RFQ-0013 Rev. 0 Page 13 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
ATTACHMENT C
DEVIATION LIST
2A28-FD-INS-RFQ-0013 Rev. 0 Page 14 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
ATTACHMENT D
VENDOR’S DATA REQUIREMENT LIST
In addition to the documents required by the Enquiry Package, Supplier/Vendor shall submit technical
data and drawings for Purchaser’s review and / or information as shown on the table below.
All technical data and drawings shall be written in English. All technical data and drawing shall be
submitted in one original and two copies for approval and for final documentation one original and 5
copies. Electronic copies of documentation shall be included as well.
Delivery Date
With Bid
VDB
Item Description Ref ± Number Issued For
of D/W/M
1 Quality Assurance Documents
1.1 Official Certificate of Yes PO + 2 W Approval Yes
Supplier/Vendor & Main
Subcontractors (ISO 9001)
1.2 A Typical Quality Plan for similar PO + 2 W Approval Yes
commodity
2 Health, Safety and Environmental Protection Documents
2.1 Health Safety & Environmental PO + 2 W Review Yes
Plan
2.2 Material Safety Data Sheet (MSDS) PO + 2 W Review Yes
3 Engineering Documents
3.1 Supplier/Vendor Documents Yes PO + 4 W Approval Yes
Register List (VDRL)
3.2 Status of Sub-Orders / List of Sub- PO + 4 W Approval Yes
Contractors
3.3 Bill of Material Yes PO + 4 W Review Yes
3.4 Reference List PO + 2 W Review Yes
3.5 General Arrangement (GA) / Yes PO + 4 W Approval Yes
Assembly Drawing
3.6 Datasheet Yes PO + 2 W Approval Yes
3.7 Catalog Yes PO + 2 W Review Yes
4 Manufacturing and Quality Control Documents
4.1 Inspection & Test Plan Yes PO + 2 W Approval Yes
4.2 Qualification Report PO + 4 W Approval Yes
2A28-FD-INS-RFQ-0013 Rev. 0 Page 15 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
Delivery Date
With Bid
VDB
Item Description Ref ± Number Issued For
of D/W/M
4.3 Progress Report Monthly Review Yes
4.4 Nonconformity Record PO + 4 W Approval Yes
4.5 Factory Acceptance Test (FAT) PO + 6 W Approval Yes
Procedure and Check List.
4.6 FAT Report Review Yes
During
Inspection
4.7 Certification documents: Review Yes
- Certificate of compliance and During
inspection of the equipment Inspection
(IEC Ex certificates, IP
certificates)
- Material certificates
- Calibration certificates
4.8 Recommendations for protection PO + 4 W Review Yes
during transportation
4.9 Packing List (preliminary) PO + 4 W Review Yes
4.10 Packing List (final) DEL - 10 D Review Yes
4.11 Proforma Invoice DEL + 10 D Review Yes
4.12 Certificate of Origin DEL + 10 D Review Yes
5 Assembly & Construction Documents
5.1 Instructions for installation, PO + 6 W Review Yes
handling prior to erection / lifting
and control of installation
5.2 Recommendations for storage prior PO + 6 W Review Yes
and during erection (if any)
5.3 List of spare parts for erection, Yes PO + 4 W Approval Yes
start-up & commissioning
5.4 List of spare parts for 2 years Yes PO + 4 W Review Yes
operation
6 Testing and Commissioning Documents
Site Acceptance Test (SAT)
6.1 PO + 8 W Approval Yes
procedure and check list
2A28-FD-INS-RFQ-0013 Rev. 0 Page 16 of 17
FEED FOR BIO REFINERY PROJECT
REQUISITION FOR RADAR & GWR
Delivery Date
With Bid
VDB
Item Description Ref ± Number Issued For
of D/W/M
Review
6.2 SAT Report During Yes
Inspection
6.3 Operating Manual PO + 10 W Review Yes
6.4 Maintenance Manual PO + 10 W Review Yes
6.5 Special tools for installation and Yes PO + 6 W Review Yes
maintenance
7 Design Dossier
7.1 Manufacturing Record Book DEL + 4 W Review Yes
Note:
DEL : Delivery Date of Purchase Material
FAT : Factory Acceptance Test
PO : Purchase Order Effective Date
SAT : Site Acceptance Test
VDB : VENDOR Data Book
W : Week
D : Calendar Days
M : Months
2A28-FD-INS-RFQ-0013 Rev. 0 Page 17 of 17