HEBS II User Quick Guide
HEBS II User Quick Guide
■ Contents
3. Feature --------------------- p. 5
8. Packaging --------------------- p. 31
-1-
Quick Guide
HEBS-II – Electronic Blasting System
■ General Precautions
-2-
Quick Guide
HEBS-II – Electronic Blasting System
■ HEBS-II components
-3-
Quick Guide
HEBS-II – Electronic Blasting System
3. Blaster (HEBS-B-2A)
4. Logger (HEBS-L-2A)
5. Harness wire
-4-
Quick Guide
HEBS-II – Electronic Blasting System
■ Features
-5-
Quick Guide
HEBS-II – Electronic Blasting System
■ Instructions for Storage
1. Never store detonators with other explosive materials in the same
magazine.
2. Never allow any lighters, matches, open flame or other sources of
ignition or volatile Materials within 50 feet of the magazine.
3. Always lock up explosive materials and keep from children and
unauthorized persons.
4. Always keep the inside of the magazine clean, dry, cool and well
ventilated.
5. Delay detonators should be used in order of manufacturing date as they
deteriorate with age. Use oldest stored product first.
6. Proper storage temperature is from -30℃ to 60℃ (room temperature
storage recommended).
7. The term of use is 5 years from the date of manufacture. For products
that have passed for more than 3 years, the legal stability test shall be
conducted through the Hanwha Corporation.
8. HEBS-II devices (Blaster, Logger, Planner) should be stored at 30% to 50%
battery charge for long-term storage for 1month or longer.
9. Never completely discharge equipment battery.
10. Charge the battery between 0 and 40℃
11. Be aware that when used below 0°C, HEBS-II device’s battery service
time may be significantly reduced.
-6-
Quick Guide
HEBS-II – Electronic Blasting System
■ Instructions for Usage
1. Be careful not to peel off the sheath of leg wire during the explosive
charging.
2. Harness wire must use Hanwha’s own product.
3. When connecting the connector to the harness wires, make sure that
the wires are not twisted, bent.
Twisted Bent
( X ) ( X ) ( O )
-7-
Quick Guide
HEBS-II – Electronic Blasting System
8. In case of defective product, follow the directions of the authorized and
trained personnel.
9. Electronic detonators must be used within 12 months after opening the
package.
10. During the approach and progress of storm, loading shall be suspended
in surface and underground blasting operations and personnel
withdrawn to a safe location.
11. Never use electronic detonators near radio transmitters, thunderstorm,
lightning, snow storm.
12. Never do harm to HEBS-II equipment by any action including dropping,
throwing, striking, frictionizing.
13. Always use exclusive carrying vessel, not to expose to the leg wire of
detonator.
14. Never fight fires involving explosives. Remove yourself and all other
persons to a safe location and guard the area.
15. Never investigate, disassemble and modify the contents of HEBS-II
equipment. There is No responsibility to any modification of the product
such as disassemble and remodel. In this regard, legal responsibility can
be held.
16. Never modify system settings because of malfunction of the product or
application working.
17. Never install an app that is not provided by Hanwha.
18. Never pull leg wires out of any detonator.
19. Always fire electronic detonators with firing currents in the range
recommended.
20. Always keep electronic detonator disconnected from the blaster until
ready to test or fire.
-8-
Quick Guide
HEBS-II – Electronic Blasting System
21. Never mix electronic detonators made by different manufacturers or
different types in the same circuit, unless detonators may misfire
partially.
22. Never handle or use electronic detonators when stray currents or static
electricity are present.
23. Never have electric power wires or cables near electronic detonators or
other explosives except at the time and for the purpose of firing the
blast.
24. Never make final hookup to power source until all personnel are clear
of the blast area.
25. All of the HEBS-II equipment, including Blaster, Logger, Planner and
Harness Wire, must only be used with HiTRONIC-IITM electronic
detonators.
26. HEBS-II equipment must be kept safe from submersion in water and
excessive impact.
27. HEBS-II equipment may be radio-interference during operation.
28. Proper protection measures should be taken when placing the blaster
where there is a possibility of a flyrock.
29. Do not short the output terminals of the blaster.
30. In remote blast mode, you should cautionary note to keep the antenna
from touching the ground or metal, and place it as far as possible from
metal.
31. In remote blast mode, you should blast in line of sight.
-9-
Quick Guide
HEBS-II – Electronic Blasting System
32. The following table is the proper temperature range of HEBS-II
equipment.
Operating Temperature
- 10 -
Quick Guide
HEBS-II – Electronic Blasting System
■ How to Use
※ Follow the normal blasting procedure until the charging and stemming
process. This guide covers the process of wiring, detonator ID collection,
communication, and blasting after charging.
Pairing
Communication
- 11 -
Quick Guide
HEBS-II – Electronic Blasting System
1. Pairing Procedure
① Put logger and planner within 20cm.
② Press power button of logger and planner.
③ Connecting harness wire to logger.
④ Press ‘HiPLANNER’ App on planner.
⑤ Press MENU > LOGGER CONNECTION > LOGGER START.
⑥ If logger and planner connected well, logger displays “REMOTE”
and blue LED and planner displays logger Information (refer to
below picture).
- 12 -
Quick Guide
HEBS-II – Electronic Blasting System
2. Test Procedure
① LINETEST must be performed before the wiring.
② Click the Menu icon and click LINE TEST under the LOGGER
* Planner should not be more than 10 meters away from the
logger.
③ Wiring the electronic detonator’s connector to harness wire.
1) Make sure that the wires are not bent or twisted.
2) Do not step on the connector or submerge it as much as
possible.
④ If the connecter is not properly wired or there is a problem such as
leakage current, an audible alarm and a message will be occurred
during the line test.
- 13 -
Quick Guide
HEBS-II – Electronic Blasting System
3. Planning Procedure
① Press ‘START NEW BLASTING’ at the ‘HiPLANNER’ app.
② Select the blasting mode. (BASIC/OPENPIT/TUNNEL/SOFTWARE)
A. BASIC : Insert the ‘START TIME’ and ‘INTERVAL’.
B. OPENPIT : Insert the information about ‘GROUP’ and ‘TIME’.
C. TUNNEL : Insert the information about
Cut/Stoping/Contour/Floor Group.
D. SOFTWARE : Open the CSV file in the save folder.
- 14 -
Quick Guide
HEBS-II – Electronic Blasting System
4. A. Scanning procedure
① Follow the Pairing and Test Procedure.
② Follow the Planning Procedure.
③ Press menu icon and press ‘SCAN’ under the BASIC MODE.
④ Press second side button at the planner to scan the QR code of
detonator’s connector.
⑤ After each scanning, planner screen displays present hole number,
detonator’s ID, and delay time.
⑥ Press ‘LIST’ tap at the top of planner screen to check and edit all
scanned detonators.
- 15 -
Quick Guide
HEBS-II – Electronic Blasting System
4. B. Logging Procedure
① Follow the Pairing Procedure.
② Follow the Planning Procedure.
③ Press menu icon and press ‘SCAN’ under the BASIC MODE.
④ Connect the electronic detonators to harness wires in order of
detonation.
⑤ After each connecting, planner screen displays present hole number,
detonator’s ID, and delay time.
⑥ Press ‘LIST’ tap at the top of planner screen to check and edit all
connected detonators.
⑦ If you need to eidt the detonator and pattern information, see 5.
Editing detonator.
- 16 -
Quick Guide
HEBS-II – Electronic Blasting System
4. C. Tagging Procedure
* Tagging is used in the open-pit to collect detonator information
before connecting, or as an aid when scanning is difficult due to
damage to the QR code.
① Follow the Pairing Procedure.
② Put the dedicated case in planner, and then combine the planner
with logger.
③ Follow the Planning Procedure.
④ Tag the connector to the tagging terminal of the logger in order of
detonation.
⑤ After each tag, planner screen displays present hole number,
detonator’s ID, and delay time.
⑥ Press ‘LIST’ tap at the top of planner screen to check and edit all
tagged detonators.
⑦ If you need to edit the detonator and pattern information, see 5.
Editing detonator.
- 17 -
Quick Guide
HEBS-II – Electronic Blasting System
5. Edit detonators
① Individual Edit
1) Touch the detonator want to edit.
2) Press and buttons then edit detonator’s Information.
3) Press button then delete the detonator.
② Multiple Edit
1) Press button, set start time and interval with long
press buttons.
2) Touch the all detonators to edit and press button
again.
③ Add Detonator
1) Press button, add new detonator when find a
detonator without scanned in a hole.
- 18 -
Quick Guide
HEBS-II – Electronic Blasting System
6. Communication Procedure
① After entering the detonator’s ID, click Menu icon and
COMMUNICATION under the LOGGER.
② If logger is not connected, repeat pairing procedure.
③ After logger is ready, press ‘COMMUNICATION’.
④ Confirm connection result of detonators as below
GOOD : The number of well-connected detonators.
NG : The number of unconnected but scanned detonators.
GLOBAL : The number of connected but unscanned detonators.
7. Settings
* If you want new blasting, press main menu button, scroll down
- 19 -
Quick Guide
HEBS-II – Electronic Blasting System
8. Blasting Procedure
① Put planner and blaster within 20cm.
② Press power button of blaster and touch start button.
③ Connect the harness wire to blaster.
④ Press ‘Start Blast’ button of the blaster screen.
⑤ Press ‘DATA TRANSFER’ under BLASTER menu of planner.
⑥ Press ‘SEARCH DEVICE’ and press the blaster’s ID. And press
‘TRANSFER DATA’.
⑦ Press SEND TO BLASTER button of planner.
- 20 -
Quick Guide
HEBS-II – Electronic Blasting System
⑧ Confirm the information of planner and blaster screen.
⑨ Download available up to 3,000 detonators and check the number
of planner used in download.
⑩ Tap the green buttons according to manual on the screen of
blaster until select blast mode.
- 21 -
Quick Guide
HEBS-II – Electronic Blasting System
⑪ Stand-alone blast mode
- 22 -
Quick Guide
HEBS-II – Electronic Blasting System
This procedure is real charging detonators for firing.
- 23 -
Quick Guide
HEBS-II – Electronic Blasting System
Wireless blast mode
- 24 -
Quick Guide
HEBS-II – Electronic Blasting System
This procedure is real charging detonators for firing.
- 25 -
Quick Guide
HEBS-II – Electronic Blasting System
■ Technical Data
HiTRONIC IITM
Type Folded Spool
Base Charge PETN, #8 (730mg)
Primary Charge DDNP
Material Copper
Shell
Dimension ø7.5mm × 90mm
Barcode Type QR code
Programmability 1 ms
Maximum Delay Time 50,000 ms
Accuracy 0.02 CV%
15, 20, 25,
6, 9, 12, 15, 18
30, 35, 40,
m
Length of Wire 50 m
(Custom made length
possible)
Small – H: 42mm, D: 90mm
Spool size
Large – H: 42mm, D: 110mm
Normal : 23 kgf,
Tensile strength
Heavy duty : 50 kgf
Wire Color Yellow
Operating Temperature -30 to +70 ℃
- 26 -
Quick Guide
HEBS-II – Electronic Blasting System
Planner
Appearance
- 27 -
Quick Guide
HEBS-II – Electronic Blasting System
Logger
Appearance
- 28 -
Quick Guide
HEBS-II – Electronic Blasting System
Blaster
Appearance
Charge
Temperature 0 to +40 ℃
- 29 -
Quick Guide
HEBS-II – Electronic Blasting System
Harness Wire
Appearance
- 30 -
Quick Guide
HEBS-II – Electronic Blasting System
■Packaging
UN 0030 / 1.1B
Grade
(470 X 295 X 120 mm)
Type
(Folded / Spool) Length (m) Pcs / box Net Weight (kg) Gross Weight (kg)
- 31 -
Quick Guide
HEBS-II – Electronic Blasting System
Please contact the following offices for any emergency or enquiry.
Contact Point
Head Office (Korea)
Hanwha Corporation
Hanwha Building 17th floor
86 Cheonggyecheon-ro, Jung-gu, Seoul, Korea 04541
TEL. +82 2 729 3714
E-mail [email protected]
- 32 -