CS Energy Site Conditions

Uploaded by

rumplestilkins
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

CS-SCP-609

AMENDED - 12/14
REVIEW DUE - 12/16

CS ENERGY PROCEDURE FOR

SITE CONDITIONS
CS-SCP-609

Responsible Officer: Group Manager Procurement and Contract Management


Responsible Executive: Executive General Manager Strategy and Commercial

DOCUMENT HISTORY

Key Changes Prepared By Checked By Approved By Date


Initial Release G Oduko July 2011
Updated format and references J Langton-Smith G Hamilton G Hamilton 07/09/2012
S Collard
Correct refer to clause error J Langton-Smith G Hamilton G Hamilton 17/10/2012
Updated J Langton-Smith G Hamilton G Hamilton 24/04/2013
Updated for outdated references H Lonsdale C Clark J Mahoney 12/12/2014

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 1


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

CONTENTS

DOCUMENT HISTORY ............................................................................................................................ 1


1 INTRODUCTION ........................................................................................................................... 5
2 PURPOSE ..................................................................................................................................... 5
3 SCOPE..........................................................................................................................................5
4 PRECEDENCE ............................................................................................................................. 5
5 CONTRACTOR PRE-START GENERAL RESPONSIBILITY ....................................................... 5
6 SITE WORKS, SITE ACCESS AND INDUCTION ......................................................................... 6
6.1 Access to Site ................................................................................................................... 6
6.2 Site Induction .................................................................................................................... 6
6.3 Electronic Swipe Cards .................................................................................................... 7
6.3.1 Vehicle Access ..................................................................................................................................... 7
6.4 Security ............................................................................................................................. 8
6.4.1 Prohibited Items ................................................................................................................................... 8
6.5 Permits and Inspections .................................................................................................. 9
6.6 Smoking ............................................................................................................................ 9
7 RISK MANAGEMENT, WORKPLACE HEALTH, SAFETY AND ENVIRONMENT ....................... 9
7.1 Compliance ....................................................................................................................... 9
7.2 Occupational Health and Safety (OHS) Plan ................................................................... 9
7.3 Job Safety and Environmental Analysis (JSEA) .......................................................... 10
7.4 Permit to Work System .................................................................................................. 10
7.4.1 Permit to Work (PTW) - Authorisation ................................................................................................ 10
7.4.2 Permit to Work (PTW) – Supporting Documents ............................................................................... 11
7.5 Safety Performance ........................................................................................................ 13
7.6 Incident Reporting .......................................................................................................... 13
7.7 Contract Safety Resources ............................................................................................ 14
7.8 Life Savers and Minimum Standards for Critical Risks ............................................... 14
7.8.1 Life Savers ......................................................................................................................................... 14
7.8.2 Minimum Standards for Critical Risks ................................................................................................ 15
7.9 Personal Protective Equipment (PPE)........................................................................... 15
7.10 Equipment ....................................................................................................................... 15
7.11 Miscellaneous Safety Provisions .................................................................................. 16
7.12 Supervision and Personal Conduct .............................................................................. 16
7.13 Fit for Duty ...................................................................................................................... 16
7.13.1 Minimum Standards for Critical Risks ................................................................................................ 17
7.13.2 Fatigue Management ......................................................................................................................... 17

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 2


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

7.14 First Aid and Emergency Recovery ............................................................................... 17


7.15 Vaccinations ................................................................................................................... 18
7.16 Hazardous Substances and Dangerous Goods ........................................................... 18
7.17 Audit ................................................................................................................................ 18
7.17.1 Non-Conformance .............................................................................................................................. 19
7.18 Electric and Magnetic Fields.......................................................................................... 19
7.19 Radioactive Substances ................................................................................................ 19
7.19.1 Approvals, Licenses and Permits ....................................................................................................... 19
7.19.2 Identification ....................................................................................................................................... 19
7.19.3 Transport ............................................................................................................................................ 19
7.19.4 Radiography ....................................................................................................................................... 20
7.19.5 Radiation Gauges .............................................................................................................................. 20
7.20 Lasers .............................................................................................................................. 20
7.21 Environmental Management Plan (EM Plan)................................................................. 20
7.22 Environmental Performance .......................................................................................... 20
7.23 Environmental Non-Conformance, Incidents and Complaints .................................... 21
7.24 Cleaning of Equipment ................................................................................................... 22
8 FACILITIES ................................................................................................................................. 22
8.1 General ............................................................................................................................ 22
8.2 Other Site Facilities ........................................................................................................ 23
8.3 Portable Office / Crib and Ablution Buildings .............................................................. 23
8.4 Workshop and Storage Area .......................................................................................... 23
8.5 Site Cleaning ................................................................................................................... 24
8.6 Power Supplies ............................................................................................................... 24
8.7 Lighting ........................................................................................................................... 25
8.8 Water ............................................................................................................................... 25
8.9 Telephone ....................................................................................................................... 26
8.10 Compressed Air .............................................................................................................. 26
8.11 Removal of Contractor Facilities ................................................................................... 26
8.12 Photography or Video Footage...................................................................................... 26
8.13 Site Relationships .......................................................................................................... 26
9 CONTRACTOR’S TOOLS AND EQUIPMENT ............................................................................ 26
9.1 Tools and Equipment ..................................................................................................... 26
9.2 Responsibility for Equipment ........................................................................................ 27
9.3 Electrical ......................................................................................................................... 27
9.3.1 Electrical Cord Extension Sets ........................................................................................................... 28

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 3


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

9.3.2 Inspection, Measurement and Test Equipment ................................................................................. 28


9.4 Statutory Authority Certificates ..................................................................................... 28
9.5 Lifting, Rigging and Scaffolding Equipment................................................................. 28
9.6 Machinery – Cranes and Mobile Plant ........................................................................... 29
9.6.1 Transformer Oil Regeneration Plants ................................................................................................ 29
9.6.2 Certification of Machinery................................................................................................................... 29
9.6.3 Permits and Inspections ..................................................................................................................... 30
10 COMPETENCY / WORKMANSHIP ............................................................................................. 30
10.1 Qualifications and Experience ....................................................................................... 30
10.2 Pressure Welders ........................................................................................................... 30
10.3 Trades Assistants / General Hands / Apprentices........................................................ 30
11 ACCOMMODATION AND TRANSPORT .................................................................................... 31
12 EMPLOYEE AND INDUSTRIAL RELATIONS ............................................................................ 31
12.1 Equal Employment Opportunity (E.E.O.) ...................................................................... 31
12.2 Bullying, Harassment and Victimisation ....................................................................... 31
12.3 Contractor’s Representative (Contractor’s Rep.) ......................................................... 31
12.4 Access to Site for purposes other than Contracted Works ......................................... 32
13 INTERFERENCE......................................................................................................................... 32
14 AUDIT REQUIREMENTS ............................................................................................................ 32
15 BUSINESS SYSTEMS ................................................................................................................ 32
16 MAKING GOOD .......................................................................................................................... 32
17 CONTRACTOR’S REPORTING OBLIGATIONS ........................................................................ 32
17.1 Contractor Staff staying longer than the allowed time ................................................ 32
17.2 OHS Incidents Statistics ................................................................................................ 33
17.3 Non-Conformance .......................................................................................................... 33
17.4 Environmental Incidents and Complaints..................................................................... 33
17.5 Insurance Certificate ...................................................................................................... 33
17.6 Advice of Emissions made on CS Energy Sites for NGERS Reporting ...................... 33
18 ASSOCIATED DOCUMENTS ..................................................................................................... 33
19 DEFINITIONS.............................................................................................................................. 34
20 REFERENCES ............................................................................................................................ 35
21 RECORDS MANAGEMENT ........................................................................................................ 35

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 4


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

1 INTRODUCTION

CS Energy owns and maintains Callide A, B and C, Kogan Creek, and Wivenhoe Power Stations.
Callide C Station is owned and operated in partnership with Intergen. The locations of these Power
Stations may be seen on the CS Energy website:
http://www.csenergy.com.au/content-(17)-power-stations.htm

2 PURPOSE

This document outlines the conditions to which all CS Energy staff, Contractor or Supplier or visitors
must comply with whilst accessing and / or working on any CS Energy site. Additional conditions may
be found in the contract document itself.

3 SCOPE

These Site Conditions (as amended from time to time) apply to all persons visiting or working in CS
Energy sites. These Site Conditions do not apply to Mines that operate as defined by the Queensland
Coal Mining Safety & Health Act 1999.
The expectation of compliance depends on the work or services that are to be performed by the
Contractor or Suppliers; or the area(s) that are to be visited in case of non-services providing visitors.
Some aspects of the Site Conditions can be varied from time to time for specific circumstances based on
rigorous risk assessments approved before the event by the Site Manager. The request to vary the Site
Conditions must be prepared and submitted by the CS Energy staff responsible for the events three (3)
working days before the event to the Site Manager for approval.
These site conditions apply unless otherwise specified in the contract between the CS Energy and the
Contractor.

4 PRECEDENCE

Where there is an inconsistency between the contract terms and the applicable Site Conditions, the Site
Conditions will prevail, unless the parties expressly agree otherwise.

5 CONTRACTOR PRE-START GENERAL RESPONSIBILITY

Prior to the Contractor’s personnel accessing the site, the Contractor must ensure that the information
and documents as requested in the Site Conditions Checklist (Form S2024 - "B/D/10/33442") are
provided to the Principal’s Representative.
CS Energy reserves the right to refuse entry, or withdraw permission, for any person from the site if they
do not comply with these site conditions, or do not have the necessary competencies.
Where the Contractor has personnel that have not undergone the registration process, prior notice must
be provided to the Principal’s Representative. The Principal’s Representative can then decide to grant
access or not.
The Contractor is also responsible for:
• ensuring that its personnel comply at all times with these site conditions.
• ensuring that all personnel are available at site at the designated times, and ready for the
performance of the services.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 5


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

• If any of the personnel are not available at the designated time and ready for the performance of the
services, unless provided for in the contract, the contractor shall supply a replacement within three
(3) hours of such an event or as agreed with the Principal’s Representative, and,
• all aspects of security within the Contractor’s own work areas.

6 SITE WORKS, SITE ACCESS AND INDUCTION

CS Energy sites are manned 24hrs per day, but standard working hours are between 0700hrs and
16:30hrs Monday to Friday, excluding closure days and gazetted public holidays. However, staff may
work outside of this period. Some Sites may have other standard working hours that are different to the
hours stated. Working hours for contractors will be as agreed in each contract or as designated by the
Principal’s Representative.
Work on weekends, or overtime during normal work periods will require review by the Principal’s
Representative. However, rosters for employees and contractors must work within the CS Energy
Fatigue Management Policy (refer clause 7.13.2 for further detail).
Unless otherwise provided for in the contract, the Contractor will be responsible for the supply and
delivery on the site of all plant and materials required for the purposes of the contract, including
consumables and personal protective equipment (PPE).
Access to the work area at all times will be accorded to CS Energy’s Representative and other
authorised employees of CS Energy. Lay down areas, and facilities for site fabrication and assembly
prior to installation, will be carried out in areas allocated by CS Energy’s Representative. The standing
of vehicles and equipment on access roads, and within site buildings, is prohibited unless expressly
approved by the Principal’s Representative.

6.1 Access to Site

Each operational site has a site access/permission process to control the entry and exit of people onto
site. The site access procedures are in place to maintain a secure and safe site.
Your CS Energy contact will provide you with the necessary paperwork to arrange access to site.

6.2 Site Induction

CS Energy has moved to an online induction process for employees, contractors and visitors to its power
station sites

How to find the online induction:


Staff and contractors can access the online induction at https://csenergy.clui.com/. Contractors can also
follow the links from CS Energy's website.
To save time, complete your online site induction prior to arrival at site. A limited number of computers
will be available in the security office to complete the online induction at site.

Induction types
• Once you've logged into the online site induction, select the relevant induction type for you:

Induction Type Access Online Module/s


Visitor Not accessing plant, accompanied on-site Site-specific module (15 minutes)
All employees. Contractors conducting work on Site specific module and core safety
Worker
plant, signing onto PTW board. module (45 minutes)

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 6


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

No personnel shall perform work on site prior to completing the CS Energy site induction and, in some
instances, PTW or Officer in Charge (OIC) training. Specific inductions are required for certain areas of
plant and types of work including, but not limited to:
• confined space entry
• electrical access
• cooling tower entry
Depending on the site and induction type, CS Energy requires that inductions are refreshed after set
periods.
On completion of site induction, Contractor personnel will be issued with an electronic swipe card and a
blue personal lock for use under the PTW system. OIC’s will be issued a yellow lock.
Contractor’s personnel are not permitted access to any area outside the immediate location where the
services are being performed. Specifically, Contractor’s personnel are not permitted to enter the Control
Room or any of the administration buildings, laboratory, workshops or stores, or drive on ash dam roads
unless permitted by the Principal’s representative.
If any of the conditions in the Site Conditions are breached, the Principal reserves the right to refuse or
withdraw permission for any person to access the site. In such circumstances, the Contractor shall
ensure that replacement personnel be acceptable to the Principal and be available to commence work
on the site within three (3) hours or as agreed with the Principal’s Representative or as stipulated in the
contract, at no additional charge.

6.3 Electronic Swipe Cards

Electronic swipe cards will be issued to individuals only after they have completed the site induction. It is
the card holder’s responsibility to ensure that they log on whenever they enter site, and log off whenever
they leave. It is the responsibility of the card holder to carry their electronic swipe card on their person at
all times whilst onsite. On completion of the contract works or on termination of contract, the card holder
must return their swipe card to site security. Failure to do so shall result in a $75 payment per
outstanding card which shall be deducted from the Contractor’s final invoice.
A restricted short term access swipe card may be issued where the work does not exceed one (1) day.
Conditions apply.
If any of the Contractor’s personnel are not required to be onsite for any more than three (3) consecutive
business days, they must return their electronic swipe cards issued to them to the Principal’s
Representative at the completion of each site visit.

6.3.1 Vehicle Access

Only Contractor's vehicles carrying equipment necessary for the performance of the services shall be
allowed on site, and entry to site by each vehicle will be subject to approval by the Principal. Private
vehicles belonging to contractor’s personnel are not permitted to enter site. Application for vehicle
access must be requested via the site contact.
All vehicles required to access the site shall be registered and comply with Queensland Road Transport
legislative requirements. They must also abide by the following specific conditions:
• Vehicles shall be site registered with site security and provided with a Vehicle Access Pass prior to
being granted access to site. Applications for Vehicle Access Pass must be submitted to the
Principal’s Representative at least three (3) days prior to bringing vehicles onsite.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 7


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

• All personnel driving vehicles on site shall have current driving licences endorsed for the type of
vehicle being driven – drivers licenses shall be copied and provided to the Principal’s Representative
at least three (3) days prior to bringing vehicles onsite, and vehicle operators are to carry their
license on their person at all times. Persons are required to notify of the loss of their licences.
• All vehicles should be clearly marked with the name of the Contractor.
• Flashing lights or hazard lights are required to be on when entering site buildings (e.g., turbine halls)
or when in close proximity to heavy vehicles and equipment (e.g., loaders & cranes).
• Vehicles shall give way to pedestrians and heavy vehicles at all times.
• Vehicles shall at all times obey road line markings and signs on site.
• Posted speed limits onsite will be adhered to at all times.
• Vehicle speed limit whilst inside site buildings is 5kph.
• Parking in site buildings, and any other ‘no parking’ areas onsite is not permitted.
• Seatbelts must be worn on site at all times whilst driving vehicles.
• Vehicles will be operated onsite, and whilst travelling to site, in accordance with Queensland Road
Rules at all times.
• Keys shall be left in vehicles at all times when the vehicle is unattended outside of designated
parking areas on site.
• No smoking will be allowed in any vehicle, including contractor vehicles, while on site at any time, in
accordance with the Queensland Tobacco and Other Smoking Products legislation.
• Vehicle drivers will not use mobile phones or other communications devices unless equipped with
“hands-free” capability.
• Parking brakes will be set in all parked vehicles.
All vehicles entering or leaving site can be subjected to inspection and search of both the vehicle and its
contents. All containers including personal bags and cases being brought onto or taken from the site will
be subject to inspection.

6.4 Security

The Contractor’s personnel shall comply with the Principal’s security procedures and policies with
respect to entry to and exit from site, vehicle parking and traffic control. All personnel shall comply with
any direction(s) given by the Principal’s Representative, including security staff.
Any mobile plant, containers, personal bags, cases, toolboxes and the like being brought onto or taken
from the site can be subject to inspection. All personnel on site will be deemed to have consented to
such inspection.
The Contractor shall immediately report any theft to the Principal’s Representative. Theft of any kind will
result in disciplinary action and will be reported directly to the police.

6.4.1 Prohibited Items

At no time shall pyrotechnics, illicit drugs or alcohol be brought on to the site. Written permission is
required from the Principal, for any firearms, ammunition, explosives or animals (excluding guide dogs)
to be brought on to any CS Energy site.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 8


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

6.5 Permits and Inspections

The Contractor will obtain all necessary permits and pay the fees required for completion of the works as
stated in the contract. The Contractor will make such tests as are called for by regulations.

6.6 Smoking

CS Energy Power Stations operate smoke free work areas. Smoking will only be permitted in smoking
areas designated by the Principal.

7 RISK MANAGEMENT, WORKPLACE HEALTH, SAFETY AND ENVIRONMENT

7.1 Compliance

The Contractor will, before commencing work on site, become familiar with CS Energy’s procedures and
legislative requirements for health, safety and environmental management whilst working onsite.
The Contractor will be responsible for the safety of all persons employed on the work under the contract.
The Contractor will ensure that all employees receive adequate instruction in the safety and emergency
procedures applicable to their duty and place of employment.
The Contractor shall comply with all of the Principal’s policies and procedures as well as relevant
Workplace Health and Safety Legislation and Standards. These may include, but are not limited to:
• Workplace Health and Safety Legislation
• Work Cover Legislation
• Environmental Legislation
Further guidance on legislative and procedural requirements can be reviewed at the supplier portal:
http://www.csenergy.com.au/content-(103)-Supplier_downloads.htm
www.legislation.qld.gov.au

7.2 Occupational Health and Safety (OHS) Plan

At least seven (7) business days prior to commencing work on site, the Contractor will submit an
Occupational Health and Safety Plan to the Principal’s Representative for approval. The plan will cover
off on at least the following key elements:
• a general policy statement which nominates the Contractor’s senior executive responsible for the
implementation of safety policy throughout the organisation
• details of the safety management infrastructure showing lines of communication and command within
the Contractor’s workforce and with the Project Safety Officer
• details of expertise available for the preparation of applicable safety procedures; and
• details of the safety orientated training programmes and facilities, both in house and external, used
by the Contractor for staff training
The Plan shall also detail the main activities and tasks to be involved while performing the Services on
Site. The OHS Plan shall show the assessment and control of risks for the potential hazards associated
with the performance of the Services.
The Contractor’s OHS Plan shall also detail the requirements and methods to be used to ensure that all
personnel are physically fit and capable of performing the work and that work practices are
environmentally sound and able to be carried out in a safe manner.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 9


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

7.3 Job Safety and Environmental Analysis (JSEA)

The Contractor and its employees will prepare a health and safety risk assessment for the work under
the contract. This will be documented using a Job Safety & Environmental Analysis (JSEA) or safe work
method statement form.
Note that the Contractor is not obliged to use the CS Energy template for JSEA. However, if the
Contractor elects to use its own risk assessment document, it must meet the requirements outlined in
CS Energy’s procedure for JSEA (see CS-OHS-11). All JSEA’s or safe work methods statements
prepared by the Contractor must be provided to the Principal’s Representative at least seven (7)
business days prior to the work commencing for review.
The development of JSEA’s shall involve the workers for the contract, and requires that workers sign
onto the document. Signing onto a JSEA acknowledges that the workers have read and understood the
document. Appropriate Permit to Work (PTW) requirements will be determined from the requirements of
the JSEA, and specialised training may need to be given to the Contractor by CS Energy to fulfil these
duties.
7.4 Permit to Work System

CS Energy operates a Permit to Work (PTW) system that is used to control all work on site. All
personnel shall comply with the PTW system requirements. The PTW system ensures that all potential
energies on plant and equipment are properly isolated prior to the performance of any work.
Refer to the PTW Manual (see CS-PTW-01) and associated procedures on the supplier portal.
Non-adherence to this guideline and unauthorised interference with danger tags, isolation locks and / or
PTW boards constitutes a serious breach of the site conditions.
Blue personal locks and yellow OIC locks are to be returned to security at the completion of the services
on site. Failure to return locks to Principal’s Representative will result in a charge of $75 for each lock.
This amount will be deducted from the Contractor’s final invoice.

7.4.1 Permit to Work (PTW) - Authorisation


Persons required completing the following work or performing the following roles onsite must be
authorised by the site PTW Administrator:
• Person in Charge of Work (PICW)
• Officer in Charge (OIC)
• Manage Confined Space Entry
• Safety Observer (General & Electrical)
• Electrical Work
• Isolating Officer
• Switching Officer
• Switching Assistant
• Instructed Person in Switchyard
• Working near LV and HV Equipment (e.g., switch rooms, battery rooms)
• Work at Heights
• Asbestos Removal
• Work in / on Cooling Towers

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 10


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

The Contractor must complete form S1949 and provide any supporting evidence to the Principal’s
Representative, and receive approval in accordance with the CS Energy Training and Authorisation of
Roles in the PTW System procedure, prior to commencing works. See CS-PTW-SOP-02 on the CS
Energy supplier portal for further information on the process.

7.4.2 Permit to Work (PTW) – Supporting Documents

In addition to managing plant isolations, the PTW System is also used to manage other high risks
activities Work permit requirements are based on the scope of works being performed, and include the
following:

7.4.2.1 Confined Space

Work in confined spaces is managed under the Confined Space Entry (CSE) Permit and requires the
use of the following forms:
a) Risk assessment
b) Air monitoring
c) Re / response plan, and,
d) Sign on / sign off forms
The Contractor shall review the CS Energy safety and PTW procedures relating to confined space entry,
and ensure that all personnel comply. This will include, amongst other things, the requirement to sign on
/ sign off the PTW and confined space entry log sheet.
The Contractor shall ensure that personnel supplied are competent and capable of working within a
confined space. CS Energy shall provide mandatory confined space awareness training for all
personnel needing to perform work in a confined space. In the event that the Contractor is to appoint
one of their staff members as an OIC, the Contractor must ensure that person has undertaken the
Nationally Accredited Confined Space Entry training and CS Energy Site specific confined space
training.

7.4.2.2 Hot Work

Hot work is managed under the Hot Work Permit and requires the use of a hot work / control checklist.
The Contractor shall review the CS Energy safety and PTW procedures relating to hot works, and
ensure that all personnel comply. This will include, amongst other things, the requirement to sign on /
sign off the PTW and hot work permit sheet, the implementation of fire prevention measures and the use
of fire spotters.
The Contractor shall ensure that personnel supplied are competent and capable of performing hot works
safely. In the event that the Contractor is to appoint one of their staff members as an OIC, the
Contractor must ensure that person is made available to undergo the OIC training modules related to hot
works.
More information on the Hot Work Permit can be found in the PTW Manual (see CS-PTW-HAZ-01)
which is available on the CS Energy supplier portal.

7.4.2.3 Digging and Excavation

Excavation work is managed under the Digging and Excavation Work Permit. A permit is required if
digging is greater than 100mm in depth.
The Contractor shall review the CS Energy safety and PTW procedures relating to excavation, and
ensure that all personnel comply. This will include, amongst other things, the requirement to sign on /

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 11


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

sign off the PTW and digging and excavation permit sheet, the conduct of services searches, and other
measures that will ensure the work is carried out in compliance with the Queensland Workplace Health &
Safety Regulations.
The Contractor shall ensure that personnel supplied are competent and capable of performing digging
and excavation works safely. In the event the Contractor appoints any of their staff members as an OIC,
the Contractor must ensure these persons are made available to undergo the OIC training modules
related to excavation.
More information on the Digging and Excavation Permit can be found in the PTW Manual (see CS-PTW-
HAZ-02) which is available on the CS Energy supplier portal.

7.4.2.4 Working at Height

A permit is required if the fall risk is greater than two (2) metres, or when creating a fall risk removing
handrails, flooring, guide mesh, gates or physical barriers and the fall is 0.5metre or more.
All personnel must ensure they comply with the Principal’s policies, procedures and permitting systems
regarding working at heights and must implement fall protection control measures when working at
heights greater than 2m, or creating a fall risk of greater than 0.5m. Creating a fall risk of greater than
0.5m may be done through removing flooring, gridmesh, gatic covers, or other physical barriers, and
may only be performed once the appropriate permit has been obtained. Fall protection must be
implemented by any of the following means, either alone or in combination with other control measures:
• Edge protection – permanent handrails
• Scaffold – handrails and mid-rails with kickboards
• Fall arrest or fall restraint systems utilising approved anchorage points in conjunction with an
approved recovery plan
• The use of a cherry picker, JLG or other similar elevating work platform
All personnel must be trained in height safety to a level satisfactory to the Principal’s representative
before work at height is to commence onsite.

7.4.2.5 Risk Assessment for Lower Heights

A risk assessment is required to determine if fall protection is needed at lower heights. (e.g. working one
metre above rotating parts or sharp impaling objects)

7.4.2.6 Live Work

Live electrical work is managed using the Live Electrical Work Checklist in the PTW system.
The Contractor shall review the CS Energy PTW procedures relating to live electrical work, and ensure
that all personnel comply. This will include, amongst other things, the requirement to complete form
S1885 and obtain the appropriate approvals as outlined in the PTW system. Live electrical work
includes, amongst other things, fault finding, testing of electrical equipment, testing to prove de-
energised for isolations and any other work where the worker may be exposed to a live electrical
conductor.
Live work is also covered in the CS Energy Electrical Safety procedure (see CS-OHS-31) and the CS
Energy Selection, Maintenance and Use of Electrical Safety Equipment and PPE (see CS-OHS-34).
Further detail on electrical safety is covered in S10.3 of these site conditions.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 12


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

7.5 Safety Performance

The Contractor will ensure that all employees and Subcontractors’ employees observe the safety
requirements of the Power Station safety procedures at all times. The Contractor shall complete JSEA
for all work to be conducted, and submit them to the Principal’s Representative for approval at least
seven (7) business days prior to commencing that work.
The Contractor must ensure that hazards are controlled to as low as reasonably practicable. If the risk
estimate remains at moderate level or above, the Contractor must liaise with the Principal’s
Representative.

7.6 Incident Reporting

All incidents, accidents, injuries, near misses, dangerous occurrences, and all incidents involving
breakage, distortion or damage to any part of the plant or works on CS Energy sites must be reported to
the Principal’s Representative in accordance with the CS Energy procedure for Incident Management
(see CS-IM-01). Refer to the supplier portal for detail on this procedure.
For any incidents or near misses that may have occurred while carrying out the contract the Contractor
shall provide the Principal’s Representative with details in the approved CS Energy form as per CS-IM-
01.
Table 1 shows the different categories that will be used depending on the nature of the incidents. The
ultimate classification of an incident will be at the discretion of the Principal’s Representative.
Table 1 - Health & Safety and Environmental Incident Categories
Category 1 Category 1 incidents are of a minor localised nature and are controlled immediately by the Site
Category 2 Category 2 incidents may require specialist assistance and are controlled and managed by the
Site.
Category 3 Category 3 incidents require notification to the Corporate Stakeholders as relevant. These
incidents may be reportable to the Regulatory Authorities, require specialist assistance or impact
off-site
Category 4 Category 4 incidents impact adversely on people, plant, environment, production and / or the off-
site community and would normally initiate the crisis response management plan

The details of the incidents shall be advised to the Principal immediately, or as soon as practicable,
following the event. An incident investigation process shall follow on from the initial notification in
accordance with CS-IM-01. The Contractor is required to cooperate completely with the Principal’s
Representative in ensuring that all incidents are investigated and corrective actions are closed out in a
timely fashion. In some circumstances this will require the Contractor to undertake their own incident
investigation reporting back on a form that provides detail consistent with the CS Energy Incident
Management process.
The Contractor will, within five (5) days of the end of each calendar month, submit to the Principal’s
Representative a report detailing the number and type of accidents, incidents and dangerous events. In
the event of no occurrences it remains a requirement that a NIL REPORT be submitted.
The Contractor is required to comply with the statutory requirements for incident notification. Documents
relating to the reports, notification and investigation are to be provided to the Principal within two (2)
hours. It is the Contractor’s responsibility to correctly complete the appropriate sections of the approved
forms, and cooperate with the Statutory Authority under all circumstances.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 13


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

7.7 Contract Safety Resources

Where a Contractor employs more than 30 personnel on site, the Contractor shall appoint and maintain
an onsite accredited Workplace Health and Safety Officer (WHSO) and a Rehabilitation Officer at all
times while works are being delivered onsite. The accreditation of the WHSO must be suitable to the
scope of works being carried out under contract.
If the Contractor engages less than 30 personnel they are still required to provide adequate resources to
provide functional safety and rehabilitation coordination for those personnel whilst they are on CS
Energy worksites. The provision of safety and rehabilitation support services to the works shall be to the
satisfaction of the Principal’s Representative.
The Contractor shall provide the Principal’s Representative with details of the names, contact numbers
and qualifications of the persons appointed to the WHSO, Rehabilitation Officer and other Safety
Support Services roles at least three (3) days prior commencing works onsite.
Regardless of the nomination of safety support resources for works under contract, the Contractor shall
allow the election, by the workforce, of a Safety Representative to cover the works onsite. In some
instances the Safety Representative may be required to participate in the activities of the broader Safety
Committee at CS Energy Sites, or a specific Safety Committee may be required under a contract. This
will be negotiated with the Principal’s Representative prior to works commencing.

7.8 Life Savers and Minimum Standards for Critical Risks

CS Energy maintains two safety standards processes to emphasise the importance of compliance to the
CS Energy Safety Management System. These procedures are used in conjunction with the CS Energy
‘Fair and Just Culture’ procedure to determine accountability and culpability of persons responsible for
breaching critical safety standards.
These systems apply to all people on CS Energy site including all CS Energy personnel and
Contractors. Contractors are required to review and communicate these procedures to their employees
and subcontractors prior to commencing onsite.

7.8.1 Life Savers

Health and Safety Life Savers are rules that, if not followed, are considered to be serious safety
breaches and will result in predefined disciplinary action applying the procedure for ‘Fair and Just
Culture’ (see CS-OHS-47). Any such breach is considered a serious matter by CS Energy as it has the
potential to cause serious injury or fatality of employees, contractors and / or members of the general
public.
The Health and Safety Life Savers are specific rules that are pivotal to upholding the integrity of the CS
Energy safety management system. These are detailed as follows:
• No person shall direct anyone to break a life savers rule
• Only operate equipment for which you are trained, competent and authorised
• Only commence work after all appropriate permits to work (PTW) are in place
• All necessary isolations must be in place and verified as effective in accordance with your role,
before work can commence
• Do not remove, bypass or modify a safety protection device without appropriate authorisation
• Do not work at heights without appropriate fall protection systems in place for people and objects
These life savers shall be communicated to, and understood by all contract personnel and are displayed
in prominent locations around each site.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 14


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

All personnel must work to ensure compliance with the health and safety life savers. Where a person
has acted and in breach of the life savers, disciplinary action will be taken.
The CS Energy Life Savers procedure is available for review on the supplier portal.

7.8.2 Minimum Standards for Critical Risks

The minimum health and safety standards for critical risks apply to key areas of the CS Energy health
and safety management system. These areas are summarised below:
• Permit to Work
• Risk Assessments
• Isolation, Electrical Access & Switching
• Excavation Work
• Confined Space Entry
• Working at Heights and Falling Objects
• Incident Reporting
• Hazardous Substances and Dangerous Goods
• Training and Authorisation
• Personal Protective Equipment
• Manual Handling
• Fit for Duty
The Contractor shall review the CS Energy Minimum Standards for Critical Risks procedure (see CS-
OHS-48) and communicate the specific minimum performance standards to be followed to their
workforce prior to commencing work onsite.
The CS Energy Minimum Standards for Critical Risks procedure is available for review on the supplier
portal.

7.9 Personal Protective Equipment (PPE)

The Contractor shall ensure that all contractor personnel wear protective clothing and are provided with,
and use safety equipment in accordance with the contract and in accordance with CS Energy procedure
for Personal Protective Equipment (PPE) CS-OHS-50.
Contractors are to ensure their personnel are trained in the use of the PPE they are required to use.
The Principal will not provide protective clothing or wet weather gear to the Contractor’s personnel.

7.10 Equipment

No equipment will be used which may be unsuitable, unsafe or liable to cause damage or personal
injury. Without lessening the absolute responsibility of the Contractor in regard to such equipment, CS
Energy’s Representative will have the right to inspect such equipment and exclude it from the works if it
is determined to be unsuitable. In this event the Contractor will provide replacement equipment, at no
additional cost to CS Energy.
The Contractor shall develop and maintain a testing and tagging program for equipment to capture that
all tools and equipment that require periodic inspection and testing. Such equipment will include,
amongst other things, electrical tools, lifting / rigging equipment and height safety equipment. The

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 15


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

program shall be provided to the Principal’s Representative at least seven (7) business days prior to the
Contractor bringing such equipment onto site.

7.11 Miscellaneous Safety Provisions

Within the Contractor’s work area, the Contractor will, to the satisfaction of the Principal’s
Representative:
• provide and maintain adequate lighting and access to all working areas
• provide and maintain adequate edge protection around each temporary floor and wall opening to
prevent the falling of persons or objects
• take all precautions against the occurrence of fire onsite. The Contractor will provide fire
extinguishers, and other fire fighting media as appropriate, in each of their site buildings and
vehicles, and acquaint themselves with the CS Energy safety procedures in force for fire prevention
and control (e.g., hot work procedures, not bringing prohibited items onsite, etc). The Contractor
shall ensure compliance to all fire prevention and control processes required under the contract by its
employees and Subcontractors
• ensure adequate controls are put in place for traffic management, and the protection of Contractor
personnel working alongside roadways and other public thoroughfares in consultation with the
Principal
• ensure that each employee is the holder of the necessary statutory permits and certificate of
competency, these requirements are to be identified during the pre-contractual phase and all permits
and certificates are to be provided to the Principal’s Representative at least three (3) days prior to
commencing onsite

7.12 Supervision and Personal Conduct

The Contractor will co-operate fully with Principal’s Representative’s supervising staff on all matters
affecting safety.
The Principal’s Representative has the right to require the Contractor, at no additional cost to CS
Energy, to immediately on receipt of notice in writing, to remove any employee or Subcontractor from the
site who fails to comply with the Power Station Safety Procedures.

7.13 Fit for Duty

All personnel must comply with CS Energy’s policies and procedures regarding fitness for duty. The
policies and procedures are listed below:
• Fit for Duty Policy
• Alcohol and Other Drugs Policy
• Fatigue Management Policy and Procedure
• Managing Alcohol & Other Drugs Procedure
All personnel are to be fit for the duties they undertake and work in a manner that protects both
themselves and other personnel from potential harm. The Principal will exclude from any of the
Principal’s Sites, any personnel whose test result does not meet the requirements set out in the
procedure, or any person who refuses to participate in the testing program.
Contractor personnel must notify the Principal’s Representative if they are on prescribed medication that
will impair their ability to work safely on site.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 16


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

7.13.1 Minimum Standards for Critical Risks

The Contractor acknowledges that while at the Principal’s workplace and / or conducting business on
behalf of the Principal they are obliged to participate in testing programs as a condition of access to the
workplace. Specific to the management of alcohol and other drugs procedure, the Contractors personnel
may be asked to provide a sample, either breath (for alcohol testing) or saliva (for drug testing).
Refer to the CS Energy Managing Alcohol & Other Drugs procedure (see CS-OHS-42) on the supplier
portal for further detail.

7.13.2 Fatigue Management

Risks due to the effects of fatigue shall be managed by the Contractor with appropriate control measures
implemented. The most effective means to manage fatigue is to develop and implement managed work
rosters with rest periods, and ensure their personnel have had adequate restorative sleep.
The Contractor shall comply with the CS Energy Fatigue Management procedure (see CS-OHS-12)
which is available for review on the supplier portal. Key requirements of this procedure include:
• Maximum nominal rostered shift times of no more than 12hrs.
• Fatigue risk assessments prepared and approved by the Principal’s Representative for personnel
working in excess of 12hrs.
• Maximum weekly working hours of no more than 72hrs.
• Maximum weekly rosters of no more than six (6) consecutive shifts without a 24hr break.
• CS Energy may approve a maximum of 14 hours on site supported by a risk management process.
Travel is to be arranged to transport workers after 14 hours on site.
Where a Contractor, or their personnel, have not complied with CS Energy fatigue management
conditions they may be requested to leave site or refused entry to the site.

7.14 First Aid and Emergency Recovery

CS Energy will provide first aid qualified personnel to cover the Contractor’s personnel during normal
working hours. However, the Contractor is required to provide additional or specialist coverage during
normal working hours if it is warranted by the risk presented by the scope of works under contract.
The Contractor is required to provide first aid coverage outside of normal working hours.
Where the Contractor performs high risk activities (work at heights, confirmed space, hot works,
excavation, work with hazardous substances, explosives etc) the provision of first aid, emergency
response, recovery and evacuation is to be reviewed by the Principal’s Representative with input from
the Site OH&S, ERT, Environment and Chemical staff as necessary. Personnel are to notify of any injury
by using the emergency phone system dialling ‘555’.
The Contractor shall ensure that all injuries to its personnel are reported to the Principal as soon as soon
as reasonably practicable in accordance with the CS Energy Incident Management procedure (see CS-
IM-01). An injury report must be completed by the Contractor and handed to the Principal within twenty-
four (24) hours of the injury occurring in the approved form (S1814 – Injury illness report form).
Some injuries will be classified as ‘notifiable incidents’ and require notification to the Statutory Authority.
Refer to clause 7.6 for further detail. All injuries must be reported to the Principal before leaving site.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 17


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

7.15 Vaccinations

Where the Contractor is performing work that requires vaccinations such as Hepatitis A & B, tetanus,
etc, the Contractor is responsible for ensuring its personnel are appropriately vaccinated, and that these
vaccinations are up to date at all times.
Vaccination requirements will be identified during the pre-contractual phase based on the risk presented
by the work. This will be undertaken in consultation with the, and to the satisfaction of, Principal’s
Representative.

7.16 Hazardous Substances and Dangerous Goods

No hazardous substance or dangerous goods (including gasses and chemicals), are to be bought onto
CS Energy sites without undergoing risk assessment and approval first. Details of some hazardous
substances and dangerous goods which have already been approved for use onsite, are stored on the
ChemAlert database. The Contractor is to consult with the Principal’s Representative during the pre-
contractual phase to determine which hazardous substances and dangerous goods require approval
before being bought onto site.
The site Emergency Response Team (ERT) are to be notified on hazardous chemicals response
requirements prior to the chemicals being brought on site.
In the case of all non-approved hazardous substances and dangerous goods, the Contractor is to
complete a copy of the Chemical Approval Request Form (see form S0004) and submit it to the
Principal’s Representative for approval prior to bringing any such substances onto site.
The Contractor is to prepare a register of all hazardous substances and dangerous goods to be bought
onto site as part of the scope of works. This register is to contain compliant Material Safety Data Sheets
for all hazardous substances and dangerous goods to be bought onto site. The hazardous substance
and dangerous goods register is to be provided to the Principal’s Representative for review and approval
at least seven (7) business days prior to the materials being bought onto site.
A Material Safety Data Sheet (MSDS) is to be maintained on file for all hazardous substances and
dangerous goods used on CS Energy sites. A copy of all MSDS’ shall be kept in the Contractor’s
register of hazardous substances and dangerous goods. The MSDS is to be compliant with statutory
requirements and is to be kept at the work area and reviewed each time the hazardous substance or
dangerous good is used.
Hazardous substances and dangerous goods will be managed in accordance to the CS Energy
Hazardous Substances and Regulated Waste procedure (see CS-OHS-08). This procedure is available
on CS Energy supplier portal. The Contractor shall remove from site unused portions of chemical.
The Contractor will ensure that the use of hazardous substances or dangerous goods is incorporated
into the JSEA for works being undertaken. This will include the requirement to ensure that the
Contractor’s personnel are trained and competent in the safe use of hazardous substances and
dangerous goods. The Contractor will provide any specialist PPE required for the safe use of hazardous
substances and dangerous goods.

7.17 Audit

The Contractor’s OHS Plan will be subject to CS Energy review and monitoring. The number of audits
will vary according to the length of the contract, time spent on site and the risk level of the work. CS
Energy audits are generally conducted in three stages:
a) Pre-Mobilisation: Prior to commencement of work on site the OHS Plan will be reviewed by the
Principal’s Representative against the CS Energy safety system standards to ensure
compatibility. This review will require at least five (5) business days lead-time to undertake.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 18


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

b) Execution Phase: CS Energy may choose to conduct an audit of the Contractor’s safety
management system as they relate to the works onsite. This is to ensure compliance with the
OHS Plan and CS Energy Safety System.
c) Works Completion: Overall compliance of contractor performance to the OHS Plan and CS
Energy Safety Management System shall be assessed as part of the contractor review and
evaluation process.
CS Energy reserves the right to audit contractors against the HSE system.

7.17.1 Non-Conformance

Non-conformances to the OHS Plan and CS Energy Safety Management System identified whilst
Contractors are onsite shall be reported in writing to the Principal’s Representative. These written
notifications shall describe the non-conformance in detail and state actions required to correct the non-
conformance. The Contractor shall be provided with details in writing of the non-conformance along with
corrective action that is required for rectification.
Matters of non-conformance with the OHS Plan and CS Energy Safety Management System shall be
recorded on the CS Energy Contractor Safety Database and may be used for Contractor evaluation
purposes in future. Extensive or repeated non-conformance and acts of incompetence or reckless
negligence will be considered a breach of contract.
The Principal will not tolerate any breaches of the site safety conditions and will require immediate action
to remedy any breach. Repeat non-compliance can result in the contract being terminated without any
compensation to the Contractor.

7.18 Electric and Magnetic Fields

Some areas of the site and plant have access restrictions due to the presence of high voltage generation
or transmission sources. The Contractor must advise the Principal’s Representative if any of their
personnel have pacemakers, metallic medical implants or hearing devices. The Contractor is to ensure
persons are not exposed to electric and magnetic fields in excess of the statutory requirements.

7.19 Radioactive Substances

The Contractor shall submit a Radiation Safety Plan to the Principal’s Representative at least seven (7)
business days prior to bringing a radiation source onto site. The Contractor is obliged to comply with the
Radiation Safety Act whilst engaging in radiation work on CS Energy sites. In addition to this, the
following applies:

7.19.1 Approvals, Licenses and Permits

The Contractor will obtain all approvals, licenses and permits for the transportation, possession, storage
and use any radioactive substance.

7.19.2 Identification

All equipment producing or capable of producing ionising radiation will be identified in accordance with
Appendix B of AS1345.

7.19.3 Transport

Transport of radioactive substances will be carried out in accordance with the current ‘Commonwealth of
Australia - Environmental Protection (Nuclear Codes) Act, current ‘Code of Practice for the safe transport
of Radioactive Substances’ Contractor’s Radiation Safety Nominee.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 19


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

The Principal’s Representative will nominate an on-site Radiation Safety Officer (RSO) or the Principal’s
Representative can request the Contractor to nominate an on-site RSO. The nominated RSO shall
possess the qualifications, official approval and experience commensurate with their duty. A copy of
RSO certifications are to be provided to the Principal’s Representative at least three (3) days prior to
their arrival onsite. Where necessary, the nominee may be required to attend an approved Radiation
Safety Course.

7.19.4 Radiography

Approval for radiography on site will be obtained from the Principal’s Representative who will be advised
of the arrival and departure of radioactive sources at the site. The Contractor will ensure that any
radiography work at CS Energy Power Station complies with all requirements of the Radiation Safety
Act, and any CS Energy procedures for the control of radiography.

7.19.5 Radiation Gauges

When the Contractor notifies the relevant Statutory Authority of their intention to bring sources of ionising
radiation into Queensland, the Contractor will supply to Principal’s Representative sufficient details to
enable an application for the necessary licenses. The Contractor will notify Principal’s Representative
immediately when the sources for radiation gauges arrive at the site.

7.20 Lasers

The Contractor will comply with recommended practices and certification of operators in accordance with
Australian Standards; AS 2211 ‘Laser Safety’ and AS 2397’ Guide to the Use of Lasers in the
Construction Industry’. All laser equipment brought onto the site will be notified to CS Energy’s
Representative. Laser equipment other than Australian Classifications 1, 2 and 3A will not be allowed
on the site.

7.21 Environmental Management Plan (EM Plan)

At least seven (7) business days prior to commencing work on site, the Contractor will submit an
Environmental Management Plan (EM Plan) to the Principal’s Representative as detailed in the contract
for approval. CS Energy Procedure CS-ENV-08 is to be used as guidance for the preparation and
evaluation of an EM Plan consistent with the CS Energy ISO14001 accredited Environmental
Management System. The Plan shall detail the main activities and tasks to be involved while performing
the Services on Site. The EM Plan shall show the assessment and control of environmental risks
associated with the performance of the Services. The EM Plan may be subject to auditing by the
Principal throughout the duration of the scheduled works to ensure Contractor compliance to
environmental obligations.

7.22 Environmental Performance

The Contractor shall comply with approved EM Plan and any relevant requirements of the Environmental
Protection Act 1994 and the Sustainable Planning Act 2009 or any current legislation and the
requirements of the Principal relating to environmental management and protection.
Some of these provisions include:
a) The Contractor must ensure that all reasonable and practicable measures have been taken to
prevent and/or minimise harm to the environment from any activity that will or is likely to cause
environmental harm.
b) The Contractor must prevent the occurrence of nuisance from dust, water, noise and vibration or
other sources through or in connection with the execution of the Services.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 20


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

c) The Contractor must comply with any reasonable direction given by the Principal where the
Principal forms the view that the Contractor’s work practices or those work practices of the
Contractor’s Personnel may cause nuisance from dust, water, noise and vibration or harm,
damage or pollute the environment through or in connection with the Services.
d) If the Contractor becomes aware that the Contractor or any other individual or group has caused
any environmental incidents, the Contractor shall notify the Principal immediately.
e) The Contractor must immediately notify and supply details to the Principal of any complaint made
to the Contractor by any person about the Services undertaken by the Contractor on the Site.
f) All oils, fuels and chemicals brought on to Site or decanted on Site by the Contractor must be
adequately labelled, contained and bunded at all times to prevent spillage onto the ground or
stormwater systems. They must be accompanied by a Material Safety Data Sheet, (“MSDS”) and
registered in accordance with clause 7.16 of this document.
g) Compliance to the Site’s Environmental Authority issued under the Environmental Protection Act
1994 to undertake certain Environmentally Relevant Activities (ERAs).
h) Conform to the principles stated within the CS Energy Environment Policy.
Any spillage of wastes, contaminants or other materials shall be contained and then cleaned up as
quickly as practicable and in the manner specified in the Site induction and relevant Site procedures.
Spillages are not to be cleaned by hosing, sweeping or otherwise releasing such wastes, contaminants
or materials into any stormwater drainage system, roadside gutters or watercourses. Collection of spills
and waste should be done in proper Contaminated Waste Bags.
Any oil or chemical spill shall be contained and then cleaned up immediately with an approved dry type
oil absorbent material. Vehicles or equipment with oil leaks will not be used on the site. Any oil spill will
be cleaned up immediately with an approved dry type oil absorbent material. No oil will be discharged
into the station drainage system. In case the Contractor has equipment on Site that could potentially leak
or spill oil the Contractor shall hold on Site a stock of an approved oil absorbent material. The material
may also be obtained from one of the many Oil Spill Kits located around the Site. Used oil absorbent
material shall be placed in the designated disposal bins. No oil or absorbent material shall be permitted
to discharge into stormwater drainage system, roadside gutters or watercourses.
Regulated Waste shall be supported by a Waste Tracking certificate in order to ensure that wastes are
disposed off in accordance with regulation.

7.23 Environmental Non-Conformance, Incidents and Complaints

The Contractor must report any non-conformances to the Environmental obligations referred to in clause
7.22, incidents and complaints in the following manner for:
a) Incidents and non-compliance with any legal environmental obligations, including Site
Environmental Authorities, and the EM Plan.
i. Written advice of the following information must be provided as soon as possible but no later
than 24 hours following an occurrence, incident or event (for the purposes of this clause all
referred to as “event”):
A. The location of the event;
B. The time of the event;
C. The time the holder of the Environmental Authority became aware of the event;
D. The suspected cause of the event;
E. A description of the resulting effects of the event;

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 21


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

F. Actions taken to mitigate any environmental harm and/or environmental nuisance caused
by the event; and
G. Proposed actions to prevent a recurrence of the event.
b) Complaints
i. Time, date and nature of complaint;
ii. Type of communication (telephone, letter, personal etc);
iii. Name, contact address and contact telephone number of the complainant (Note: if the
complainant does not wish to be identified then “Not Identified” is to be recorded);
iv. Response and investigation undertaken as a result of the complaint (Note: if the complaint is
considered frivolous or vexatious, the reasons for considering the complaint frivolous or
vexatious must be recorded.);
v. Name of person responsible for investigating the complaint;
vi. Action taken as a result of the complaint investigation and signature of responsible person;
and
vii. Advise if the complaint is about dust and provide on-site meteorological data relevant to the
time from a representative site including wind speed and direction, temperature, barometric
pressure, daily rainfall and relative humidity.

7.24 Cleaning of Equipment

All vehicles and implements passing through declared weed infested areas should be cleaned down to
ensure the load is free of reproductive material (seeds) prior to leaving the weed infested site. The cost
of the wash down will be borne by the vehicle owner. The drivers of such vehicles are to present a
completed Weed Hygiene Declaration Form prior to entry to Site in order to meet the legislative
requirements of a 'written notice' under the Land Protection (Pest and Stock Route Management) Act
2002. Both the Contractor and Site need to keep a copy of the form for five years. A written notice is
required before supplying anything that is, or could be, contaminated with the following Class 2 declared
plants:
• parthenium (Parthenium hysterophorus)
• prickly acacia (Acacia nilotica)
• giant rat´s tail grass (Sporobolus pyramidalis and S. natalensis)
• American rat´s tail grass (Sporobolus jacquemontii)
• giant Parramatta grass (Sporobolus fertilis)
• Parramatta grass (Sporobolus africanus)
Refer to the Queensland Department of Primary Industries and Fisheries (DPI&F) website for further
information regarding weed identification and vehicle washdown facility locations
http://www.dpi.qld.gov.au/documents/Biosecurity_EnvironmentalPests/IPA-Cleandown-Procedures.pdf

8 FACILITIES

8.1 General

The Contractor may be allocated a lay down and storage area or building or part thereof on site by the
Principal. Power, water, sanitation and drainage may be available for the Contractor's use.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 22


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

The Contractor’s use of any laydown area, facility, building or part thereof, is pursuant to a non-exclusive
licence only. CS Energy may at any time withdraw or amend the permission for such use. The
Principal’s permission for any use by the Contractor does not create or imply any form of tenure in any
area, lay down, building or part thereof. When requested, the Contractor will submit a plan for approval
to the Principal’s Representative showing the layout of any proposed site facilities necessary for the
contract. The use of such areas will be at the Contractor’s risk.
All maintenance or improvements to any area shall be approved by the Principal prior to any work being
done. The cost of maintenance and improvement of any property of the Contractor shall be met by the
Contractor. When finished, the Contractor shall ensure that any lay down, storage area, or building that
is used by the Contractor for such purposes is returned to CS Energy control in the way it was left, if not
better.
Any area occupied by the Contractor, but outside the area allocated to the Contractor shall, at the
request of the Principal, be cleared at the Contractor's expense. The Principal has the right to change
and / or allocate new areas to the Contractor.

8.2 Other Site Facilities

CS Energy’s dressing rooms, sanitary conveniences and washing facilities may be available for use by
the Contractor’s employees while on site with prior approval from the Principal’s Representative.
Lockers will not be provided.
A site canteen is available to Contractor’s employees on some CS Energy sites. Where available, the
site canteens typically operate between Monday and Friday.

8.3 Portable Office / Crib and Ablution Buildings

With Principal’s written consent, the Contractor may supply and install the Contractor’s own portable site
buildings including offices, lunchrooms, toilets, locker rooms, washing facilities and containers, all of
which must be installed and maintained to the satisfaction of the Principal. All buildings / containers
shall be designed and erected in accordance with all applicable legislative requirements, relevant
Australian Standards and Building Code of Australia requirements, and otherwise be of a standard
satisfactory to the Principal.
Demountable buildings / containers shall only be placed in laydown areas approved by the Principal
Representative.
Without lessening the responsibility of the Contractor to comply with the statutory obligations, all
buildings or containers may be inspected by the Principal’s Representative prior to the equipment being
permitted onsite. Any building or container that does not, in the opinion of the Principal, comply with any
requirement of the Principal will not be permitted on site.
All buildings / containers shall be clearly marked with the Contractor’s name. All shipping containers
being used for work on site shall have an emergency hatch / exit fitted.
Upon any request by the Principal, Contractor’s buildings and containers onsite shall be available for
inspection by the Principal.

8.4 Workshop and Storage Area

Equipment and material will not be stored outdoors without prior approval. The Contractor will be
responsible for the adequacy and integrity of all weather protection. The Contractor will provide all
material for storage purposes. No items will rest on the floor or ground.
The Contractor shall be responsible for the adequacy of protection against loss, corrosion damage or
mechanical damage of the Principal’s materials and / or equipment in their possession. If necessary, the

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 23


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

Contractor shall arrange covered storage at the Contractor’s expense. Any damage that may occur to
material and / or equipment shall be repaired, refurbished or replaced to a condition reasonably required
by the Principal before that item is installed.
As soon as any part of the Contractor’s site facilities is no longer required, the Contractor will remove
such facility and restore the vacated area to a clean and tidy condition fit for immediate use.
The Contractor’s portable site buildings will be in good condition, will provide adequate unobstructed
means of access and escape, and comply with the appropriate Australian Standard specifications for
portable site buildings.

8.5 Site Cleaning

Each Contractor is responsible for work area cleanliness and to maintain any necessary services with
local authorities in accordance with that authority’s regulations. The Contractor will be responsible for
the regular removal of all rubbish, spoil and the like from site.
The Contractor shall not allow combustible rubbish or materials to accumulate to a point where it
presents an unacceptable fire hazard at any time whilst onsite.
The Contractor may use the Principal’s waste removal facilities where it is documented in the contract or
with the approval of the Principal’s Site Representative
Failure to maintain the work area in a clean and tidy condition will be an adequate reason for CS Energy
to have the Contractor removed from site
No dumping is permitted on any adjacent land without prior written approval from the owners and the
Principal’s Representative.
When working on the site the Contractor at all times, will make adequate provision to prevent damage
and defacement of adjacent plant, building and floors and to ensure the health and safety of the
workforce.
Upon completion of the contract the Contractor will, subject to the provision of the contract, remove all
buildings, workshops and temporary works, all equipment and surplus materials and will restore the site.
The whole of the works and surroundings are to be left in a clean and tidy condition fit for immediate use
and / or occupation – that is, they are to be returned to CS Energy control in the same state that they
were left, if not better.
Should the Contractor fail in any of the above, CS Energy reserves the right to perform such work and to
recover from the Contractor any associated expenses.

8.6 Power Supplies

A limited supply of electricity at 240V and 415V 3-phase, 4-wire 50Hz will be provided free of charge at
fixed points throughout CS Energy Power Stations to the Contractor. All electrical work performed by the
Contractor must be performed in accordance with these site conditions, and any applicable legislative
and Australian Standard requirements.
The Contractor shall supply approved power distribution boards and electrical appliances, tested and
tagged as per clause10.3, to connect to CS Energy power supply outlets for all the Contractor’s power
requirements. The power distribution boards provided by the Contractor shall be designed and installed
in accordance with AS3000 and any other relevant legislative and Australian Standard requirements. All
temporary construction wiring shall comply with AS3012.
Residual Current Device (RCD) protection is required for all power distribution boards used to supply
infield electrical equipment. RCD protection is to be provided by the Contractor. The Contractor will
supply any other equipment necessary to connect to these fixed points at no cost to CS Energy. It is the
responsibility of the Contractor to ensure that this requirement is met. If a supply is not permanently

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 24


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

protected with a RCD then the Contractor is to supply a portable RCD for their use so as to comply. The
Contractor’s inspection, measuring and testing regime shall comply with the requirements of CS Energy
Maintenance and Testing of Portable Electrical Equipment, RCD’s and Tools safety procedure (see CS-
OHS-33) which is available for review on the supplier portal.
Additional supply points may be arranged by discussion with CS Energy’s Representative but such
additional supply points will be installed at the Contractor’s expense. The Contractor is to notify the
Principal’s Representative of electricity supply requirements at least seven (7) business days prior to the
commencement of work onsite. Continuity of supply of electricity is not guaranteed.
The Contractor will provide and maintain the whole of the installation on the load side of such points of
supply. All 240V and 415V general purpose outlets (GPO) will be RCD protected. The Contractor is
responsible for the supply and maintenance of all RCD protection for GPO’s in accordance with AS3000
and any other relevant legislative and Australian Standard requirements. CS Energy’s Representative
will require the disconnection or alteration of any electrical distribution equipment or electrical appliances
which may be considered dangerous. CS Energy will carry out all connections and disconnections at the
above mentioned supply points.
In the case of supply circuits to motors, driving plant of a portable nature, the use of bare or insulated
cables carried on wooden pole construction will not be permitted and the final connections to the control
equipment and motors will be made by the use of approved mining type trailing cables.
Where directed by CS Energy’s Representative, cable shall be run in conduit construction. All electric
circuits shall be kept off the ground.
Underground cables will not be installed unless approved by the Principal’s Representative. No
underground supply will be energised unless the Principal’s Representative’s staff have inspected the
cabling and approve. The Contractor will maintain an accurate record of the location of each
underground cable required for the works, and provide drawings illustrating the location of these cables
prior to being energised. All connections and disconnections at the above mentioned supply points shall
be carried out by the Contractor and approved by the Principal prior to use. Buried cables shall be
removed once no longer required.

8.7 Lighting

The Contractor shall provide all temporary lighting required for the performance of the services.
All lighting must comply with AS3000 and any other relevant legislative and Australian Standard
requirements. All temporary construction wiring shall comply with AS3012. The Contractor shall not
tamper with or remove any lighting that has been installed by the Principal.
The Contractor shall be responsible for the maintenance and supply of parts for all the Contractor’s own
lighting.

8.8 Water

A limited supply of potable and / or non-potable water will be provided to the Contractor and at various
locations on the site free of cost, subject to the Contractor exercising strict control over its usage. Any
Contractor who is considered by the Principal’s Representative to be wasteful in the use of water will be
directed to change their work practices.
Any pipe-work required by the Contractor for reticulation beyond the Principal’s points of supply shall be
provided by the Contractor at no cost to the Principal. Each connection will commence with an approved
type of isolating valve capable of being locked in either the open or closed position. The lock will be
provided by CS Energy, and the keys for the lock held by the Principal’s Representative.
The Contractor shall install and maintain such pipe-work with the approval of and to the reasonable
satisfaction of the Principal.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 25


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

The Contractor shall advise the Principal’s Representative of their proposed water requirements at least
seven (7) business days prior to commencing onsite.

8.9 Telephone

CS Energy will not provide IT telephone or facsimile access unless provided for in the contract. The
Contractor has an obligation to provide sufficient and reliable communication methods or services to
contact the Emergency Response Team in the event of an emergency.

8.10 Compressed Air

A limited supply of compressed air from station compressors may be made available for the operation of
the Contractor’s pneumatic tools, but only for the performance of the works under contract. The
Principal’s Representative may, at its absolute discretion, supply the Contractor’s proposed quantity of
compressed air.
If CS Energy does not supply the Contractor with compressed air, the Contractor must provide their own
compressors. If the compressors are to be used inside buildings they must be electrically driven
compressors. All compressors must be fitted with approved silencers and located in an area nominated
by the Principal’s Representative.
The Contractor shall advise the Principal’s Representative of their proposed compressed air
requirements at least seven (7) business days prior to commencing onsite.

8.11 Removal of Contractor Facilities

As soon as any part of the Contractor’s installation is no longer required under the contract, the
Contractor will disconnect and remove their equipment to the satisfaction of CS Energy’s
Representative.

8.12 Photography or Video Footage

Photographs and / or videotaping are not to be taken on site without the written permission of the
Principal.

8.13 Site Relationships

The Contractor is required to co-operate with CS Energy, its Representatives and with all other
Contractor’s onsite. CS Energy will not be responsible or liable for any damage caused by any other
Contractor to the Contractor’s equipment or plant. It is the Contractor’s responsibility to recover costs
directly from any other Contractor(s) who may be involved in any such loss.

9 CONTRACTOR’S TOOLS AND EQUIPMENT

9.1 Tools and Equipment

The Contractor shall ensure that all tools and equipment supplied to perform the services are fit for
purpose and are maintained in a clean and safe condition. Where applicable, such tools and equipment
shall comply with legislative and CS Energy safety procedural requirements (e.g., electrical equipment
being tested and tagged, lifting slings to be certified, etc.).
All electric welding equipment must be fitted with a Voltage Reduction Device (VRD) to AS3195.
Unless authorised by the Principal’s Representative, the Contractor will not bring any internal
combustion engine inside a building. If so authorised, then the Contractor will ensure that there is

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 26


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

adequate ventilation of fumes from any such engine, and silencers are used to keep noise to an
acceptable level within the internal environment.

9.2 Responsibility for Equipment

The Principal will not accept responsibility for loss of or damage to the Contractor’s vehicles, tools,
clothing or equipment. The Contractor shall arrange to insure its tools, equipment and other properties
and also for any security deemed to be necessary within the contractor’s own work area at no cost to the
Principal.
Each item of equipment belonging to the Contractor shall be clearly marked with identification specifying
ownership and contact details of the Contractor.

9.3 Electrical

All electrical work on site shall be conducted in accordance with the CS Energy Electrical Safety
Management Procedure (see CS-OHS-31) as well as the relevant Australian Standards, Codes of
Practice and Statutory requirements. Refer to the CS Energy supplier portal for this procedure.
The Contractor shall submit to the Principal, no later than seven (7) business days prior to the
commencement of work on site, a plan showing where the power distribution boards and proposed
buried electrical cables are to be located and an inventory of all electrical equipment to be utilised on
site. The electrical equipment inventory is to include a test and tag program.
Without lessening the responsibility of the Contractor in regard to safety of equipment and Statutory
obligations, all electrical equipment, shall have clear and permanent identification and have current
certification as “tested and tagged”. All equipment may be subject to inspection by the Principal prior to
being permitted on site, and at any time during the Contractor’s tenure onsite. Any equipment that does
not comply with all Statutory and / or CS Energy safety procedural requirements will not be permitted on
site.
Any equipment or tooling found to be defective by the Contractor or the Principal is to be immediately
removed from service by the Contractor and clearly marked ‘Out Of Service’. All electrical faults that
occur during the conduct of the services must be reported to the Principal. The Contractor shall ensure
that all of the Contractor’s electrical equipment is suitably maintained, calibrated, certified and repaired
at no cost to the Principal.
The Principal has in place restrictions relating to the performance of live electrical work and work in
proximity of exposed energised conductors. Under normal circumstances, Contractors should not be
expected to perform live electrical work unless it is absolutely necessary or they are testing to prove de-
energised. Personnel must not encroach on safe approach distances and exclusion zones as specified
in the CS Energy Electrical safety procedure (see CS-OHS-31), the CS Energy Selection, Maintenance
and Use of Electrical Safety Equipment and PPE safety procedure (see CS-OHS-34), and the Electrical
Safety Act and Regulations. If live work is to be performed, the Contractor must complete the Live
Electrical Work Checklist (see form S1885) which is available on the CS Energy supplier portal.
Personnel must be authorised through the PTW System to work in any explosive atmospheres or
hazardous areas, undertake live electrical work, test to prove de-energised, and work in an "authorised
zone".
All personnel are to treat any exposed electrical part as energised until it is isolated and proven de-
energised. The Principal requires all electrical personnel to implement a test for dead before
commencing work on electrical equipment and installations.
Where electrical work has been conducted on electrical equipment, a certificate of testing and safety is
to be provided to the Principal by a licensed electrical contractor.
Where electrical installation work has been performed on a high voltage electrical installation, or on an

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 27


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

electrical installation located in a hazardous area, the work is to be inspected by an accredited high
voltage electrical auditor and an inspection and test certificate is to be provided to the Principal.

9.3.1 Electrical Cord Extension Sets

All electrical cord extensions sets on site shall comply with AS3120 – Approval and test specification –
Cord Extension Sockets. All socket ends of electrical leads used on site must be fitted with a socket with
a “shroud” or protection of the socket face.
All power leads used to conduct the services shall be run in a neat and safe manner, ensuring that
access for personnel and vehicles is not endangered or impeded. Electric cables shall not be draped
across, or tied to, metallic structures. Where cables cross walkways, then suitable protective covers shall
be supplied and installed by the Contractor.

9.3.2 Inspection, Measurement and Test Equipment

The Contractor’s inspection, measuring and test equipment shall comply with the Principal’s calibration
requirements. Records shall be provided to the Principal prior to the equipment’s use on any plant or
equipment on Site.

9.4 Statutory Authority Certificates

Before any item of plant that is subject to Statutory Authority Certification is put to use on site the
Contractor shall provide copies of the relevant Statutory Authority Certificates to the Principal. No
modification shall be made to any plant or equipment that is the subject of a certificate unless the
modification is approved by the Authority that issued the certificate. The Contractor shall provide the
Principal with a copy of the authorisation of the modification.

9.5 Lifting, Rigging and Scaffolding Equipment

All lifting, rigging and scaffolding equipment to be used on site must comply with the statutory
requirements and CS Energy safety procedural requirements. The Contractor is required to have a
procedure that prescribes the methods of registration and inspection of all lifting and rigging equipment.
Scaffolds erected on site must be tagged if they are greater than 2m high. Scaffold design, erection,
inspection and maintenance must be in line with the Queensland Workplace Health & Safety Regulation,
the Queensland Code of Practice for Scaffolding and any applicable Australian Standards. CS Energy
uses the ‘Scafftag’ system to manage periodic inspection and maintenance of scaffold onsite, the
Contractor is required to provide a system that achieves an equivalent or better standard of inspection
and maintenance. Under some circumstances the Contractor may apply to have their scaffold included
under the CS Energy site-specific scaffold inspection and maintenance regime if negotiated with the
Principal’s Representative.
The Contractor is to provide the Principal’s Representative with a scaffold register and scaffold
inspection / maintenance plan at seven (7) business days prior to commencing onsite.
Without lessening the responsibility of the Contractor in regard to safety of equipment and statutory
obligations, all lifting, rigging or scaffolding equipment and associated certificates and records may be
inspected by the Principal prior to the equipment being allowed onsite, or at any time whilst in use onsite.
Contractors shall ensure that containers carrying lifting, rigging and scaffolding equipment are accessible
so that the Principal may conduct an inspection prior to equipment entering site. Any equipment that
does not comply with all Statutory and / or site requirements shall not be allowed on site.
All equipment found by the Principal to be defective or inappropriate for use shall be immediately
removed from service and costs incurred in repairing or replacing the equipment be met by the
Contractor.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 28


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

The Contractor is to provide the Principal’s Representative with a rigging / lifting register at seven (7)
business days prior to commencing onsite.

9.6 Machinery – Cranes and Mobile Plant

Where necessary the Contractor will provide mobile plant or unloading equipment required at the site.
Such equipment will only be brought on site during normal CS Energy’s working hours. The Contractor
shall provide a crane lifts plan to the Principal’s Representative before the commencement of work with
the crane. A current compliance and history certificate will accompany all mobile plant and unloading
equipment and be presented to the Principal’s Representative for verification before that plant or
equipment is permitted to enter site and commence work.
The Contractor will ensure that all workers employed by the Contractor or Subcontractors to operate
cranes and mobile plant, comply with the requirements and rules of the various Statutory Authorities. All
workers must hold the licences applicable to the roles they perform.
The Contractor will ensure that all cranes and other high risk plant are fitted with a daily pre-start
inspection sheet, logbook, etc., that is used by Contractors to assess condition before use each day.
The Contractor shall provide the Principal’s Representative with a plant register outlining all high risk
plant (e.g. cranes, excavators, forklifts, civil plant, etc) at least seven (7) business days prior to
commencing onsite. This will include all registration and compliance certificates.

9.6.1 Transformer Oil Regeneration Plants

Transformer Oil Regeneration Plants are to have either a:


a) fire suppression system fitted; or
b) fire monitoring, prevention and control plan that is approved by the Principal’s Representative.
The Contractor must take all precautions against the occurrence of fire onsite and acquaint themselves
with the CS Energy safety procedures in force for fire prevention and control. The Contractor shall
ensure compliance to all fire prevention and control processes required under the contract by its
employees and Subcontractors
The Contractor shall not allow combustible rubbish or materials to accumulate to a point where it
presents an unacceptable fire hazard at any time whilst onsite.
The Contractor shall provide the Principal’s Representative with its fire monitoring, prevention and
control plan at least seven (7) business days prior to commencing onsite. This will include all
registration and compliance certificates.

9.6.2 Certification of Machinery

The Contractor will ensure that all machinery for use on site have, a unique identification number, all
current registrations and inspection certificates, approvals or other compliances as required for their
operation in accordance with Queensland Legislation or Codes of Practice affecting that equipment.
Such certificates, approvals and registration evidence will be presented to the Principal’s Representative
by the contractor or a nominated Subcontractor on the day the machinery arrives at the Power Station.
In the event of the documentation not being available or not current, entry to the Power Station will be
refused. Such a refusal of entry to the Power Station or delays in the inspection of such certificates and
registration will not be grounds for extension of time or claims for additional costs. This requirement is in
addition to the requirement to provide the high risk plant register discussed in the previous section seven
(7) business days prior to commencing onsite.
All operators and other persons operating the machinery brought on site will be properly licensed and

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 29


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

trained in their use. The appropriate licences and certificate of competency must be presented to the
Principal’s Representative at least three (3) days prior to starting work on site and be carried on the
operator’s person whilst working onsite. Security will require the operator to show photo ID that matches
the documentation supplied to the Principal’s Representative when Site access form was completed
before the site access card is issued

9.6.3 Permits and Inspections

The Contractor will obtain all necessary permits and pay the fees required, as stated in the contract, and
will make such tests as are called for by the regulations of all Authorities having jurisdiction over the
installation.

10 COMPETENCY / WORKMANSHIP

10.1 Qualifications and Experience

Only competent, experienced, skilled, licensed and certified personnel will be utilised to provide the
services. All contractors’ personnel shall:
a) Possess experience commensurate with the tasks they are employed to do, for example, in
heavy industry maintenance or construction, be experienced in working at heights, confined
space entry, and be able to communicate and cooperate with other employees
b) Ensure that all workers employed by the Contractor or Subcontractors, comply with the
requirements and rules of the various Statutory Authorities with regards to prescribed
occupations. All workers must hold the relevant high risk work or high risk plant operation
licences appropriate for the work they are required to perform
c) Possess the appropriate trade certificates / statutory tickets relevant to the services being
performed or specified in the contract. The Contractor shall provide evidence of such skills,
experience competencies and certification / licenses to the satisfaction of the Principal before at
least three (3) days before the work commences. These must also be attached to the Power
Station swipe card application to be completed prior to access to site, and held on the
Contractor’s person at all times whilst participating in high risk work or operating high risk plant
onsite.
All personnel will be expected to work alongside the Principal’s multi-disciplined, multi skilled workforce,
and other Contractors on Site.

10.2 Pressure Welders

If the services include coded welding then, the Contractor shall ensure that its Weld Supervisor is
qualified in accordance with AS1796-2001 to Certificate No.10, and that pressure welders maintain
current qualifications for codes required to perform the services. Testing shall be the responsibility of the
Contractor and shall be undertaken within 6-months prior to commencement of work on site. The
Contractor is to maintain records of such qualifications and provide them to the Principal at least three
(3) days prior to the commencement of works onsite.

10.3 Trades Assistants / General Hands / Apprentices

All trades assistants shall have experience working with tradespersons on large industrial sites. Where
the Contractor chooses to employ people with little or no experience of this type of work, or where the
person is younger than seventeen (17) years of age they shall only be employed in areas and on work
approved by the Principal.
Supervision for these persons must be appropriate to the risk associated with the works.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 30


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

11 ACCOMMODATION AND TRANSPORT

Unless otherwise specified in the contract, the Principal will not provide accommodation and transport for
personnel, or meet the cost of any accommodation and transport that the Contractor provides for the
Contractor’s personnel. The Contractor shall be deemed to have made all appropriate allowances in the
contract price.

12 EMPLOYEE AND INDUSTRIAL RELATIONS

The Contractor is responsible for industrial relations within their own workforce and within the
workforce(s) of each Subcontractor(s).
The Contractor shall keep the Principal fully informed of any disputes or other matters likely to affect
industrial relations on the Site.
Upon request, the Contractor must provide copies of all industrial instruments and agreements
applicable to the Contractors workforce to the Principal.
The Contractor must ensure that it deals with all industrial matters relevant to its Personnel at the Site
such that the services are executed without interruption, avoiding industrial disputes and ensuring all
Personnel are paid and receive all amounts, benefits, allowances and conditions to which they are
entitled to.
The Contractor will notify immediately the Principal’s Representative of an industrial dispute or a
potential dispute with a statement of the problems and the number of personnel involved. A written
report to CS Energy’s Representative must be received within one hour of the settlement of the dispute
or problem.

12.1 Equal Employment Opportunity (E.E.O.)

The Contractor shall provide employment conditions that ensure equal employment opportunities and
that are free from unlawful discriminatory practices and are in accordance with statutory requirements.
The Contractor will also ensure that all persons engaged by the Contractor and engaged in the
performance of the contract works have received training in the relevant aspects of E.E.O. legislation
and requirements to a standard that complies with CS Energy’s expectations of acceptable behaviour of
persons working within a CS Energy workplace.

12.2 Bullying, Harassment and Victimisation

The Contractor must take all necessary measures to prevent the occurrence of bullying, harassment and
victimisation by the Contractor’s Personnel. If the Contractor becomes aware of any instance of bullying,
harassment or victimisation then the Contractor must notify the Principal immediately and take steps to
address the issue.

12.3 Contractor’s Representative (Contractor’s Rep.)

The Contractor shall appoint and make available at no additional expense to the Principal, its
Contractor’s Representative who may assist the Contractor in the performance of the contract and also
to act as liaison officer between the Principal and the Contractor.
The Contractor shall notify the Principal in writing of the name and contact numbers of the Contractor’s
representative and of any subsequent changes.
Any direction given by the Principal to the Contractor’s representative in relation to the Services under
the Contract shall be deemed to have been given to the Contractor.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 31


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

Matters within the knowledge of the Contractor’s representative shall be deemed to be within the
knowledge of the Contractor.

12.4 Access to Site for purposes other than Contracted Works

Not linked to Fatigue Management


The principal, at its discretion may grant or extend access to defined areas of the site for purposes other
than the contracted works.
Any such extension must be agreed in advance of the event by the Principal’s Representative. The
Principal’s Representative can decide whether to allow such extension or not.

13 INTERFERENCE

As an electricity generating authority, the operation and maintenance of the Station is at all times of
primary importance to the Principal. The Contractor shall not do anything that could interfere in any way
with the continuity of electricity supply without approval of the Principal whose decision shall be final and
despite any other provision of the Contract may be in the interest of the Principal alone.

14 AUDIT REQUIREMENTS

Upon reasonable notice, if required by the Principal, the Contractor shall make available for inspection,
time sheets, wages books and any other documentation that substantiates a claim for payment or
evidences compliance with any requirement of these Site Conditions.

15 BUSINESS SYSTEMS

If required, the Contractor shall utilise the Principal’s business management systems, SAP, the
document management system – TRIM; and the Risk Management System (to provide work close out
information) as required by the Principal.

16 MAKING GOOD

The Contractor will make good to the satisfaction of the Principal’s Representative all damage or
defacement to the buildings, paintwork, plant etc. caused by the Contractor during the course of the
Contract. All holes cut through walls, floors etc will be made good to the satisfaction of CS Energy’s
Representative.
All trenches made by the Contractor will be filled in by the Contractor, compacted and graded with
approved filling to the satisfaction of the Principal’s Representative. Excavated materials shall be
dumped at sites approved by the Principal’s Representative.

17 CONTRACTOR’S REPORTING OBLIGATIONS

The Contractor shall be required to provide the following reports to the Principal’s Representative at
intervals as stipulated hereunder or as stated in writing by the Principal’s Representative to the
Contractor or the Contractor’s Representative. Other reports as stated in the contract document must
also be supplied by the Contractor in accordance with the contract terms.

17.1 Contractor Staff staying longer than the allowed time

The Contractor shall submit to the Principal’s Representative a list of its staff that are staying longer than
the allowed time in accordance with clause12.4. The number should be submitted before each event.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 32


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

17.2 OHS Incidents Statistics

The Contractor shall submit the OHS Incidents reports in accordance with clause 7.6 of this Site
Conditions.

17.3 Non-Conformance

The Contractor shall detail any non-conformances to the Occupational Health and Safety Plan and
Environmental Management Plan, CS Energy Safety and Occupational Health, and Environmental
Management System etc in accordance with clauses 7.17.1 and 7.23 of these Site Conditions.

17.4 Environmental Incidents and Complaints

The Contractor shall submit the OHS and Environment reports on any incidents or complaints in
accordance with clause 7.23 of these Site Conditions.

17.5 Insurance Certificate

The Contractor shall submit the appropriate Insurance Certificates in accordance with the contract
between the Principal and the Contractor before work commences or where the insurance expires during
the contractual period. The Contractor must always have a current insurance during the period of the
performance of the contract.

17.6 Advice of Emissions made on CS Energy Sites for NGERS Reporting

The National Greenhouse and Energy Reporting (NGERS) Act of November 2007 established
mandatory reporting of all emissions made and energy used at each of CS Energy’s facilities (sites)
during the respective reporting periods. To comply with the principles of accuracy, completeness,
comparability and traceability the reporting of the emissions made by Contractors while working at CS
Energy’s sites has to be included in annual submissions.
Please note the different scopes of emissions below, however, only scope 1 emissions fuels data are to
be supplied.
• Scope 1 is emissions from fuel or energy consumed on the site/facility.
• Scope 2 is emissions from fuel or energy purchased from another facility/site.
• Scope 3 is emissions from fuel or energy consumed on behalf of the facility/site away from the site
for example travel fuel (vehicles, air etc.)
Also, fuels and energy supplied by the CS Energy sites to the Contractor are not to be included.
As CS Energy is required to report on a facility (site) basis, the data shall be collected on a per site
basis. For reporting the data, please fill out the form S2051 for each facility (site).
The form is also available on CS Energy website –
http://www.csenergy.com.au/content-(103)-Supplier_downloads.htm

18 ASSOCIATED DOCUMENTS

Copies of required documents are either available in the Principal’s website -


http://www.csenergy.com.au/content-(103)-Supplier_downloads.htm or can be obtained from the
Principal’s Representative.
All up-do-date drawings relating to electrical, civil and mechanical components of existing infrastructure
are to be obtained and available to relevant personnel prior to the commencement of the works.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 33


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

19 DEFINITIONS

Term Definition
The official working day of the week, that is, days between and including Monday to Friday
Business Day
but excluding public holidays that fall within the period
The agreement between CS Energy and a Supplier or Contractor to purchase goods and/or
Contract services. The contract may be in the form of a purchase order, service order, contract, or
other agreement.
Contractor’s (Contractor’s Rep.) Any person nominated from time to time by the Contractor to represent
Representative the Contractor in the performance of the contract
Contractor’s Site The site based person representing the Contractor for the overall management of the
Representative technical / commercial aspects of the Contract on behalf of the Contractor.
The entity contracted to perform and complete the services and / or any party, which makes
Contractor /
a supply to the Principal under the Contract, however named in that Contract. The words
Supplier
‘Contractor’ and ‘Supplier’ can be used interchangeably.
Legislative The requirements of all statutes, rules, regulations, proclamations, ordinances, awards, and
Requirements by-laws, present and future.
a) in relation to the Principal, its employees, agents, consultants and contractors (other
than the Contractor), and
Personnel b) in relation to the Contractor, its Workers, the Contractor’s employees, agents,
consultants, subcontractors and their employees, agents, consultants and
contractors.
The defined areas within a Site where plant (e.g. Boiler, Turbine, etc), are installed or
Plant Area
located.
Principal CS Energy Limited (ABN: 54 078 848 745) and its subsidiaries.
The CS Energy’s Representative, Contract Manager, Overhaul Manager or the Outage
Principal’s Manager or any person nominated from time to time by the Principal and may include any
Representative or all of any of the Power Station employees or its agents so designated to provide direction
to the Contractor.
Principal’s Site The site based person representing the Principal for the overall management of the
Representative technical / commercial aspects of the Contract on behalf of the Principal.
Permit to Work An authorisation on the prescribed form giving approval for a specific scope of works on
(PTW) specified equipment or in a specified area.
The whole and any part of the work which the contractor is required to perform and
Services (or complete under the contract and includes variations, remedial work and all other work
Works) reasonably necessary for the performance of the Contract. Services may include the supply
of materials and equipment.
The place where the services are to be performed and includes any area that is located
Site within the boundaries of the Power Station, any buffer land that the station manages and
any other locations that CS Energy may have works or services.
Station Any CS Energy Power Station.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 34


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT
CS-SCP-609
AMENDED - 12/14
REVIEW DUE - 12/16

20 REFERENCES

Reference No Reference Title Author


External Links
Portal Link CS Energy Website  Supplier Information  Supplier Downloads CS Energy

Internal Links
Procedure - CS-OHS-08 - Management of Hazardous Substances and
"B/D/11/30976" CS Energy
Regulated Waste
"B/D/11/30939" Procedure - CS-OHS-11 - Job Safety and Environmental Analysis (JSEA) CS Energy
"B/D/11/30940" Procedure - CS-OHS-12 - Fatigue Management CS Energy
"B/D/11/30957" Procedure - CS-OHS-31 - Electrical Safety Management CS Energy
Procedure - CS-OHS-34 - Selection, Maintenance and Use of Electrical Safety
"B/D/11/30960" CS Energy
Equipment and PPE
"B/D/11/30965" Procedure - CS-OHS-42 - Managing Alcohol and Other Drugs CS Energy
"B/D/11/30969" Procedure - CS-OHS-47 - Fair and Just Culture CS Energy
Procedure - CS-OHS-48 - Minimum Health and Safety Standards for Critical
"B/D/11/30970" CS Energy
Risks
"B/D/12/1363" Procedure - CS-OHS-50 - Personal Protective Equipment (PPE) CS Energy
"B/D/11/19582" Procedure - CS-PTW-01 - Permit to Work (PTW) Manual CS Energy
"B/D/11/19583" Procedure - CS-PTW-SOP-02 - Training for Roles in the PTW System CS Energy
"B/D/11/19573" Procedure - CS-PTW-HAZ-01 - Hot Work CS Energy
"B/D/11/19581" Procedure - CS-PTW-HAZ-02 - Working at Heights CS Energy
"B/D/11/45318" Procedure - CS-IM-01 - Incident Management Plan CS Energy
"B/D/11/31096" Procedure - CS-ENV-08 - Guidelines for Health Safety and Environment Plans CS Energy
"B/D/12/66139" Form - S0004 - Chemical Approval Request CS Energy
"B/D/11/36208" Form - S1814 - Injury / Illness Report CS Energy
"B/D/10/21585" Form - S1878 - JSEA - Job Safety and Environmental Analysis Template CS Energy
"B/D/11/36153" Form - S1885 - Live Electrical Work Checklist CS Energy
"B/D/10/33442" Form - S2024 - Site Conditions Checklist CS Energy
"B/D/12/71202" Form - S2051 - National Greenhouse and Energy (NGERS) Reporting CS Energy
"B/D/13/25987" Form - S2136 - Safe Work Method Statement Declaration CS Energy

21 RECORDS MANAGEMENT

In order to maintain continual improvement, suitability, safety and effectiveness of the organisation,
registered documents will be reviewed on a two yearly basis, or where it has been identified that there
are changes in technology, legislation, standards, regulations or where experience identifies the need for
alteration to the content. Registered documents should also be reviewed following an incident, change
management process, modification or where directed as part of a risk assessment process.
CS Energy must ensure that records are retained according to accountability, legal, administrative,
financial, commercial and operational requirements and expectations. In compliance with records
retention and disposal, all documentation created in relation to CS Energy business must be retained in
line with minimum retention periods as detailed in legal retention and disposal schedules.

B/D/11/28673 – CS-SCP-609 – SITE CONDITIONS Page 35


THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT