Sow - Transducer & FT Switch - Pts-24-Mdptd-10
Sow - Transducer & FT Switch - Pts-24-Mdptd-10
AND
SCOPE OF WORK
MDNOD, SEC-EOA
Page 1 of 25
SECTION
I INTRODUCTION
1.01 GENERAL
1.02 PROJECT DESCRIPTION
1.03 WORK SCHEDULE
1.04 PROJECT SUMMARY
3.01 GENERAL
3.02 WORK TO BE DONE BY THE CONTRACTOR
3.03 AC/DC SUPPLY
3.04 DESIGN DOCUMENTS, CALCULATIONS & DRAWINGS
3.05 STANDARDS, CODES & SPECIFICATIONS
IV COMMISSIONING TESTS
Page 2 of 25
SECTION I – INTRODUCTION
1.01 GENERAL
The purpose of this SOW is to call for qualified vendors to supply new
TRANSDUCERS with FT switch, associated spare materials/hardware, and replace the
existing installed at the substations in Dammam area. Hence, The Saudi Electricity
Company-EOA proposes procurement of Transducer and installation associated
equipment necessary for urgent replacement in order to maintain efficiency and
reliability of 69 kV network in Dammam area.
The CONTRACTOR shall perform on LSTK basis, the design, engineering, material
Procurement, quality management, factory inspection/testing, transport and delivery to
site, construction, site inspection, testing and commissioning, and all associated work
and services until final handing over of the proposed work in a satisfactorily working
and operating condition to the COMPANY as specified in this Scope of Work and
Technical Specifications.
Page 3 of 25
SECTION II - BASIC REQUIREMENTS AND GUIDELINES
A. All components and accessories required for the completion and successful operation
of the WORK covered under the scope of this PROJECT, either specified in detail or
not, shall be supplied and installed by the CONTRACTOR as necessary.
B. The engineering design and specifications of equipment and materials supplied under
this PROJECT shall be in accordance with this Scope of WORK and Technical
Specifications and COMPANY Standards. If the equipment either does not conform to
the specifications or is not acceptable to COMPANY based on past operating
experience/any other reason; the CONTRACTOR shall propose alternative equipment
for review and acceptance by COMPANY. However, in case of a conflict in the
requirements, the CONTRACTOR shall bring this to the attention of the COMPANY and
shall obtain such applicable requirements in writing from the COMPANY. The
CONTRACTOR shall have no right to decide the requirements on his own. In case of
such a conflict, and in case of such an eventuality, he will be doing so at his own risk
and cost as the COMPANY reserves the right to reject any or the complete part of such
WORK arising out of the CONTRACTOR'S own decision.
The base design shall be finalized through base design review meeting based on the
guideline drawings issued hereof, manufacturer's drawings, calculations and data
sheets and detailed design shall be finalized based on the base design review and other
information.
F. COMPANY acceptance of the CONTRACTOR’s design does not relieve him of any part
of his obligations to meet all the requirements of the CONTRACT.
G. All WORK including services, demonstrations, test and inspection required by the
COMPANY for familiarization of operation and maintenance of new switchgear
equipment to COPMANY personnel, shall be provided by the CONTRACTOR
Page 4 of 25
H. All materials/scrap items shall be removed/returned to COMPANY designated
warehouses, at no cost to COMPANY.
I. CONTRACTOR shall protect from damage all existing structures, improvements or
utilities at or near the WORK SITE, and shall repair and restore at CONTRACTOR's
expense any damage thereto resulting from CONTRACTOR's failure to exercise
reasonable care in protecting the same during CONTRACTOR's performance of the
WORK. If CONTRACTOR fails to undertake these repairs or restoration, COMPANY
shall have such repairs or restoration performed by others at CONTRACTOR's
expense.
The CONTRACTOR shall submit eight (4) sets of the complete base design documents
at most twelve (12) weeks after the contract award plus soft copy on a flash memory .
The Base Design shall at minimum comprise but not limited to the following:
The base design submittal shall be submitted fully complete, containing all discipline drawings and
calculations as stated. Partial submittals or packages are unacceptable and will be rejected.
After completing the Base Design, the CONTRACTOR shall present the Base Design
Package for technical review along with the Drawing Control Sheet. CONTRACTOR's
Project Manager, Project Engineer and the Design/Construction Engineer in each field
of specification shall attend the presentation meeting. During this meeting, the
COMPANY's comments on the base design package will be reviewed and discussed in
detail to finalize the base design for the PROJECT. Minutes of the meeting shall be
prepared by the contractor and concurred by the COMPANY REPRESENTATTVE.
The COMPANY reserves the rights to reject any equipment proposed by the
CONTRACTOR if the equipment does not conform to the specifications, based on
unsatisfactory past operating experience or any other reason. In such cases, the
CONTRACTOR shall propose alternative equipment for review and acceptance by the
COMPANY.
Page 5 of 25
2.04 DRAWINGS
A. General
1. The CONTRACTOR shall provide all drawings required in accordance with the
requirements of the COMPANY Drawing Procedure EDSD/DR-8 (Rev.5). The
drawings shall be assigned with drawing numbers and indexed as outlined in the
above procedure. A block of drawing numbers shall be provided by the
COMPANY for all drawings.
2. Drawings shall be of uniform size in each discipline as much as possible and ISO
scales shall be 1:10, 1:50, 1:100 and 1:1200, etc.
3. The submission of drawings shall be progressive and phased out to give sufficient
review time to the COMPANY, but in no case shall be less than two (2) weeks
prior to commencement of any manufacturing activity.
4. The COMPANY’s acceptance of the CONTRACTOR’S design does not relieve him
of any part of his obligations to meet all the requirements of the specification nor
the responsibility for the correctness of the design and drawings.
5. The existing system drawings of the related substations are generally available with
the COMPANY in digital format (TIFF-GROUP-4 "*.tif' or "*.DGN" Which can be
opened through Windows Microstation *.DGN). In cases where existing system
drawings are not available in digital format or quality of digital format drawings are
not good and corresponding drawing prints of good quality are available with' the
COMPANY, then CONTRACTOR shall develop the PROJECT drawings from
these prints by scanning the drawing prints to create images files or by re-drafting.
Copies of existing available drawings shall be provided on CONTRACTOR's
written request. However, if any related information is not available, the
CONTRACTOR shall be responsible to develop all the required drawings in SEC
standard format to satisfy the PROJECT requirements.
B. Bid Drawings
The CONTRACTOR shall submit to the COMPANY with his technical proposal, as a
minimum, the drawings and data sheets requested by the COMPANY in Tender
Documents. The CONTRACTOR shall submit to the COMPANY with his Technical
Proposal a complete list of drawings that the CONTRACTOR proposes to prepare under
this project.
1. All existing drawings affected by this PROJECT shall be revised and submitted for
COMPANY reviewing as part of CONTRACTOR's design submittals. The drawings
in general shall be computer drafted (Microstation -*.DGN) CAD system.
Page 6 of 25
2. For modification WORKS of existing substation, the existing drawings only shall be
revised as far as possible. If revising the existing drawings are not feasible or not
practical and new drawings needs to be developed, then preferably the same
drawing number with additional/different sheet number shall be allotted. New
drawings having new drawing numbers shall be created only if drawings of existing
system are not available. New drawings having new drawing numbers if created
shall be included in the existing drawing control sheet only and a new drawing
control sheet for an existing station shall not be created unless specifically
instructed.
4, The existing drawings are listed in the drawing control sheet(s) for the substation and
may be covered in more than one (1) drawing control sheets for each of the
affected existing substations, The CONTRACTOR shall review/study these various
drawing control sheets and drawings, identify the superseded/latest drawings and
carry out field verification to ascertain the correctness of the existing drawings,
Only the appropriate / correct drawings shall be used for developing the drawings
for modification WORKS,
C. Vendor Drawings
All vendor drawings shall be subjected to review and approval by the COMPANY before
being issued and filed.
The CONTRACTOR shall submit to the COMPANY with his base design package, four
(4) sets of all drawings, data sheets, specifications and studies requested in Subsection
2.02.
Page 7 of 25
E. Final Detail Design/Construction Drawings
No WORK shall be started at site unless all interconnected drawings for a particular
WORK has been fully reviewed and agreed upon by the COMPANY.
F. As-Built Drawings
2. All revisions shall reflect field modifications to engineering flow diagrams, electrical
one-line diagrams, electrical schematic connection and interconnection wiring
diagrams; instrument hook-ups, wiring diagrams, terminal connections,
dimensioned equipment layouts.
4. Five (5) copies of the as-built documents shall be submitted to the COMPANY for
review as to adequacy, completeness, legibility and conforming to drafting
standards. If returned, the CONTRACTOR shall make corrections, provide
additional data and improve the quality as instructed prior to resubmittal and
COMPANY acceptance. The revised “As-Built” drawings shall be resubmitted
within four (4) weeks after commissioning. Five (5) sets of final “As-Built”
drawings, one (1) set of good quality “As-Built” Mylars and one (1) set of “As-Built”
digital Microstation *.DGN format drawings (if applicable) in flash memory shall be
submitted to the COMPANY for record purposes.
3. Construction / Installation.
Page 8 of 25
B. The following information shall be included in the Progress Reports:
A. Bi-Weekly Progress Meeting shall be conducted between the COMPANY and the
CONTRACTOR during the entire CONTRACT duration.
A. Quality Management
1. Procurement Control
CONTRACTOR’S QA/QC engineers shall review all products and services prior
to procurement to ensure conformance to specified requirements. Procurement
control shall include source evaluation and selection, source inspection and
evaluation of objective evidence of quality furnished by a supplier against the
Technical Specification.
2. Manufacturers/Suppliers
a. The CONTRACTOR shall procure all major material items for the
WORK from COMPANY qualified and approved sources.
b. The CONTRACTOR shall ensure that purchase orders to
manufacturers/suppliers contain all the applicable industry and
COMPANY developed standards and specifications.
c. The CONTRACTOR shall ensure that Purchase Order(s) to approved
manufacturers/suppliers are not re-assigned or sub-contracted to
other manufacturers/suppliers without the Company’s written
consent.
Page 9 of 25
Test Plan shall be submitted to the COMPANY together with the Quality
Plan/Quality Program for review and approval.
2. The essential features of the required Quality Control Plan/Inspection and Test
Plan are as follows:
3. The Quality Control Plan/Inspection and Test Plan shall indicate the scheduled
dates of testing and inspection at the designated location.
Page 10 of 25
E. Receipt Inspection
The Contractor shall establish and document all procedures and Work instructions to
ensure that the construction and installation processes are performed in a controlled
manner. The necessary qualification of personnel and procedure for activities such as
welding, non-destructive examinations, etc shall be defined. Work instructions and
procedures shall be adhered to by the Contractor’s personnel.
The Contractor shall conduct inspection and testing activities at all phases and quality
audit at appropriate stages of the Work. The Contractor’s QA/QC engineers/inspectors
shall develop and use field inspection checklists to facilitate checking of a process,
activity, material or equipment. The field inspection checklist shall state the
characteristics to be verified, inspection method, acceptance criteria and clause
reference of the applicable standards or specification. The checklist shall have provision
for writing the result of inspection, date of inspection and name and signature of the
QA/QC engineer/inspector. Such activities where inspection checklists are required
Page 11 of 25
shall include but not necessarily be limited to all pre-commissioning and commissioning
checks and tests, material/equipment receiving inspection. All inspection and testing
results shall be reviewed, safely stored and maintained by the Contractor. A typical
checklist shall be provided to the Company for review and comment.
The Contractor shall develop and implement the use of inspection logbook for use by
the Contractor’s QA/QC engineers/inspectors in according their comments and
observations as a result of their inspection. The Contractor’s personnel responsible for
rectifying any observed deficiency or non-conformance should also write their reply in
the logbook stating the action taken to correct the deficiency. The Contractor’s QA/QC
engineers/inspector’s shall ensure that all unsatisfactory observations on an item are
cleared before any activity proceeds to the succeeding stage of that item.
2. Four (4) complete sets of fully revised manuals (original and no photo copies)
incorporating the COMPANY's comments to the full satisfaction of the COMPANY
before mechanical completion.
C. Soft Copies along with hard copies for commissioning, operation and maintenance
manuals as detailed in items A & B above, shall be as given.
Page 12 of 25
2.08 TEST RECORD BOOK
A. The CONTRACTOR shall provide a "Test Record Book" which shall include the
following:
B. Each test form where applicable shall include a column quoting the acceptable
maximum and minimum limits of the test in terms of voltage, current, frequency, time,
etc. and include “As Found” and “As Left” values.
Three (3) copies of the "Test Record Book" are to be submitted within thirty (30) days
after completion of the PROJECT.
A. The CONTRACTOR shall affix Plant Tag to each and every individual equipment
including independent components to be installed under this CONTRACT, which have a
material value of Five Thousand Saudi Riyals (SR 5,000), or more. The
CONTRACTOR shall install Plant Tags adjacent to the Manufacturer's Data Plate or at
any other place approved by the COMPANY REPRESENTATIVE. The CONTRACTOR
shall affix Plant Tags by bolts and nuts, or rivets or welds, or adhesives, as instructed in
writing by the COMPANY REPRESENTATIVE, depending on the type of equipment to
be tagged. The CONTRACTOR shall complete Plant Tagging before Technical
Acceptance.
B. At least sixty (60) days before completion of the installation of all equipment covered
under this CONTRACT, CONTRACTOR shall submit to COMPANY a list of all
equipment and independent components to be tagged, using the format of COMPANY
Form No. 16511 (2/10) Exhibit I to the Job Specifications. Based on this list,
COMPANY shall assign Plant Tag Number to each item and CONTRACTOR shall
install the Plant Tags in accordance with this list. COMPANY will, within one (1) month
from the date of receipt of the list, issue to CONTRACTOR the Plant Tags together with
the list showing assigned Plant Tag Numbers.
Page 13 of 25
C. The CONTRACTOR shall, if required, assist the COMPANY REPRESENTATIVE in
locating all equipment identified by Plant Tag Numbers in accordance with the list
provided by the CONTRACTOR.
The CONTRACTOR shall strictly comply with the following Loss Prevention
requirements:
A. General Requirements
3. The CONTRACTOR shall submit his Loss Prevention Program (LPP) to the
COMPANY sufficiently in advance to obtain COMPANY approval prior to
commencement of WORK at site (MDNOD shall get soft or hard copy of LPP) of
contractor. The Loss Prevention Programs shall contain the following:
- CONTRACTOR’s Name
- Title of Submittal
- PROJECT Title and Location
- CONTRACT Number
- COMPANY’s Name
b. Table of Contents
d. Specific program items (suitable for the SOW) that the CONTRACTOR
proposes to implement during the CONTRACT execution.
Page 14 of 25
- Construction Schedule
- CONTRACTOR’s standard forms for safety related reports.
5. The CONTRACTOR shall provide and use adequate and suitable safety/warning
signs, cordon tapes, portable barricades, warning lights and personnel protective
equipment at the JOB SITE to protect the safety of COMPANY and CONTRACTOR
personnel and the public, and to prevent damage to property.
6. The CONTRACTOR shall provide first aid facilities and must have a certified
employee to administer first aid and Cardio-Pulmonary Resuscitation (CPR).
9. The CONTRACTOR shall obtain from the COMPANY, ID cards for his employees
and stickers for his vehicles/equipment prior to mobilization to site.
It is a SEC requirement that all contractor personnel shall ware Arc Flash Resistant clothes in
restricted area substations all the time.
Page 15 of 25
Description of Hazard Risk Category FRC clothes / PPE and their applications are mention in
the below table:
Page 16 of 25
CONTRACTOR's proposed Supervisors/Engineers assigned as a
Work Permit Receiver shall undergone on examination for
“DISTRIBUTION SAFETY RULES AND SAFE ISOLATION”
in order to be qualified as PTW Receiver. CONTRACTOR shall pay
the all corresponding training fees for these qualification courses thru
SADAD System.
CONTRACTOR shall at all times comply with COMPANY’s 5-Star
4 Occupational Safety and Health Management System with Regard To OHS-PR-02-21
Safe Design, Construction and Commissioning
CONTRACTOR shall at all times comply with Safety Violation OHS-PR-02-01A
5 Procedures implemented by COMPANY’s 5-Star Occupational OHS-PR-02-22
Safety and Health Management System.
C. Elevated WORKS
1. The CONTRACTOR shall submit his heavy equipment (i.e. cranes and bucket
trucks) to the COMPANY for safety inspection and certification and
correspondingly stick with green safety sticker.
2. The CONTRACTOR shall provide the welding gas cylinders with suitable rack that
is equipped with security chain(s).
Observe working clearances when working near or about energized line or equipment
as per COMPANY’s ISD Safety Manual – 2nd revision 2011
Submit material safety data sheets (MSDS) of chemicals required or which are to be
used in the execution of the WORK.
2.11 SHUTDOWN/OUTAGE COORDINATION
CONTRACTOR shall plan for minimum outages of existing equipment, which are
required for CONTRACTOR’s installation of new equipment, or movement/relocation of
existing equipment during execution of the PROJECT.
Page 17 of 25
Where outages of existing equipment cannot be avoided, CONTRACTOR shall
coordinate all details of planned outages through the COMPANY REPRESENTATIVE
with initial coordination at the base design stage.
CONTRACTOR’s plan and detailed schedule for outages shall be subject to COMPANY
review and approval. All outages shall be scheduled at least four (4) weeks in advance.
3.01 GENERAL
A Under the subject project, the VENDOR/MANUFACTURER shall design, supply
and replace the TRANSDUCER for various stations in Dammam area on a
Lump Sum Turnkey (LSTK) basis consisting of the major equipment/systems
indicated in this section. All components and accessories required for the
satisfactory operation of the new facilities of the PROJECT, whether specifically
mentioned / specified in details or not shall be supplied and installed as
necessary at the following substations:
1. MIDRA JANUBI
2. ANAK
3. SHWOAIBA
4. BOHAIRA
5. DAMMAM BSP
6. SHATE
7. DOHA
8. ANOOD
9. NAKHEEL
B The Bidder/CONTRACTOR shall visit the sites and make himself aware of the
details of the existing system/facilities. The modifications WORK at the
associated substations shall be compatible with the existing system.
Page 18 of 25
C In case the annunciator system is to be installed on a separate free standing
panel assembly, the panel shall meet or exceed all the relay panel requirements
specified in applicable clauses of 31-TMSS-01.
D Terminal blocks for field points shall have knife action isolation.
Table 3.01
Detail &
Base
Title Bid Construction As-Built
Design
stage
Equipment/Materials
LV Power, Control and Instrumentation Cables X
Protective Relays, Relays Manuals & Catalogue’s X X
Relay Application/Installation/Commissioning Manuals X X X
Design Calculations Test & Procedure
CT Calculations to confirm CT adequate to proposed relay X X X
Relay Application and Relay Setting Calculations X X X
Design Drawings
Abbreviations, Symbols and Legend X X X
Composite Relaying and Metering One-Line Diagram X X X
Composite DC Schematic Diagrams X X X
Composite AC Schematic Diagrams X X X
DC Composite Schematic for Protection X X X
Panel Wiring Diagrams for Relay X X
Page 19 of 25
Revision of Existing System Drawing X X X
Inspection/Test Plan X
Site Commissioning Tests X X
Page 20 of 25
iii. Final approval of design drawings, after incorporating all comments of
COMPANY, shall be obtained.
iv. Vendor drawings.
b. Construction Drawings:
i. Final construction drawings shall be provided for each indicated item in the table.
ii. Revised final construction drawings shall be provided, if required.
4. As-Built Stage:
a. As-Built drawings shall be provided for each indicated item in the table.
b. Along with the final detail design package, CONTRACTOR shall submit the following
in Adobe Portable Document Format (PDF) files:
1. Design Drawings
2. Design calculations
3. Material data schedules
4. Equipment catalogues
Each discipline documents shall be arranged in a separate folder designated by
discipline’s name, CONTRACTOR shall furnish the same in a flash memory.
The revision numbers and notes reflecting the changes made throughout the design
shall be retained in the submitted final design drawings. Also, the input and output
files for design calculations carried out by computer programs shall be furnished.
All PDF files shall have the following document security level: (1) without open
password, (2) allowing for printing and (3) allowing for text and graphics selection.
Page 21 of 25
40-TMSS-02 rev 0, Meters.
31-TMSS-01 rev 0 Relay and Control Panels
Page 22 of 25
Required
Expected date of With or without FT
Sr.No. Station Name quantity Equipment’s number Comments
decommission switch
2-Lines
• T501 ( 4000297610 )
• T502 ( 4000297619 )
2-Lines
• T501 ( 4000297802 )
• T502 ( 4000297811 )
3-Lines
• T501 ( 4000309707 )
• T502 ( 4000309713 )
• T503 ( 4000309719 )
1-Transformers
4 ANAK Q2 2026 1 Need FT
• T503 ( 4000042095 )
3-Lines
• T501 ( 4000302667 )
• T502 ( 4000302675 )
• T503 ( 4000302683 )
2-Lines
Page 23 of 25
2-Transformers
• T501 ( 4000302667 )
• T502 ( 4000302675 )
3-Transformers
2-Lines
• T501 ( 4000310387 )
• T502 ( 4000310389 )
• T503 ( 4000310391 )
2-Lines
• T501 ( 4000309461 )
• T502 ( 4000309465 )
• T503 ( 4000309469 )
2-Lines
• T501 ( 4000311305 )
• T502 ( 4000311307 )
3-Lines
• T501 ( 4000310527 )
• T502 ( 4000310529 )
• T503 ( 4000310531 )
Page 24 of 25
Page 25 of 25