Chapter 4 – Track Roadbed
Track Substructure - Subgrade
CENG 5271 - Railway Engineering
AAiT
Roadbed sections
→ Roadbed (rail roadway) is the strip of land containing the track,
ditches, and other facilities needed for the operation of the
railroad.
→ Usually, the cross section perpendicular to the center line is called the roadbed
section.
→ Roadway width must be wide enough to accommodate the track side ditches
portion of embankment or cut slopes parallel service roads and other structures
and facilities necessary for the operation of the railway.
Note:
Track centerlines
minimum 13’ apart
Roadbed sloped to
drain
Sometimes wider
shoulders for
maintenance purposes
zewdie
Types of Roadway sections
According to the topography and the shape of the cross section,
about six roadbed sections can be identified.
(1) Embankment
The roadbed forms through filling of soil and roadbed
stone, while the design of which is above
ground
ground.
(2) Roadbed without filling or digging
The design of roadbed is the same as ground, and roadbed
it can directly be laid on the ground. ground
(3) Through cut
The roadbed forms through digging,
while the design of which is under
ground.
ground
roadbed
zewdie
Roadbed sections cont ....
(6) Half through cut
(4) Half-embankment
In the mountain areas, some of
In the mountain areas, some of the
the roadbed is formed through
roadbed is formed through filling.
digging.
roadbed
ground
ground
roadbed
(5) Side-hill cut
The roadbed is formed through filling
and digging.
ground
roadbed
zewdie
Subgrade
Definition :
is the prepared earth on which the railroad ballast section and
track structure are built
A sub grade is an earth structure, which is formed through
excavating or filling and can bear the track structure directly,
including section sub grade and sub grade of station and yard.
Railway sub grade is the foundation of the track, it inherit and
pass on the weight of track and the moving load of train
zewdie
Load vs. Deflection
Characteristics of subgrade Track Modulus vs. Subgrade
→ weakest and most unstable part in railway
line works.
→ instability makes impossible to maintain
track alignment, profile(surface) and cross
level.
For smoothness trackbed, following conditions
shall be satisfied during the design.
→ Control of sub grade deformation
Repeated Load Behavior
→ Evenness of sub grade rigidity
→ Stability under train operation;
→ Stability under natural conditions
The four basic geometric features are:
Width of top of subgrade or bottom of cut
Height of fill or depth of cut
Load pulse
Side slopes of fill or cut
Provision for drainage
zewdie
The main functions of the railroad subgrade are:
To bear the traffic load without becoming damaged
To drain off the water to the side.
Provide smooth platform for construction
zewdie
Form of roadbed
Factors affecting top width of
a) Top surface of roadbed
subgrade:
→ track level (speed, OCS, widening)
→ is where the track (superstructure) laid
→ soil property
on.
→ is refer to the distance from one side of
→ thickness of ballast bed (0.35~0.5m)
the road shoulder to another side. → shape of sleeper
→ The shape (with road camber: and → single line or double lines
without road camber: the roadbed → long-term tack type,
without road camber is higher; → sedimentation and widening of road
→ on curve section, the outside roadbed shoulders,
must be widen; → road maintenance type (mechanical
or manual),
→ setup of cable trench and pit etc.
road shoulder road shoulder
form without road camber top surface
width
side slope side slope
form with road camber zewdie
Width of Top Surface, B
1. Single track:
without camber :
B = 2C + 2x + A
with road camber:
B = 2C + 2m(h1+h2) + A
2. Double line (with camber)
B = 2C + 2x + A + D
Where,
B—width of top surface
C—width of roadbed’s shoulder
x—width of side slope
A—width of ballast bed
D- center to center distance b/n
tracks
zewdie
b) Road shoulder and Side Slope
• Road shoulder: those part without ballast
bed;
side slope
• Side slope: the slope apart from road road
shoulder
shoulder.
Function of road shoulder:
→ Bear the force, strengthen the stability of
roadbed
→ keep ballast bed compacted
→ be convenient for the setting of signs drainage
ditch
→ for the walk of workers
Ancillary facilities
vegetation retaining wall
• Drainage facility
• Safeguards: function to ensure the strength
and stability of roadbed.
zewdie
General Subgrade design procedures:
→ Determine Allowable subgrade stress
→ Determine stress at sub ballast-subgrade
interface due to superstructure load
→ Compare load stress with allowable stress
→ Determine formation/natural ground
bearing capacity
→ Based on formation layer stress determine
the thickness/depth of subgrade
Where:
Pc = subgrade pressure (kPa for JNR and psi for Talbot)
Pm or Pa = applied stress on the ballast (same units as Pc)
h = ballast depth (cm for JNR and in. for Talbot)
zewdie
Chinese Standard
Material type
Typical Thickness of subgrade bed
Designed Surface Layer of Bottom Layer of Sub
Speed Sub grade Bed (m) grade Bed
Designed Speed Surface Bottom Total (km/h) (m)
(km/h) Layer Layer Thickness
Thickness Thickness of V≤160 Group A filling Group A or Group B
(m) (m) Subgrade materials filling materials or
Bed improved soil
(m) V=200 Graded crushed Group A or Group B
V≤160 0.6 1.9 2.5 stone or graded filling materials or
sand gravel improved soil
V=200 0.6 1.9 2.5
200<V ≤250 0.7 2.3 3 200<V Graded crushed Group A or Group B
≤250 stone filling materials or
V≥300 0.4 2.3 2.7
improved soil
V≥300 with
ballast V≥300 Graded crushed Group A or Group B
V≥300 0.7 2.3 3 V≥300 with stone filling materials or
V≥300 without ballast improved soil
ballast V≥300 Graded crushed Group A or Group B
V≥300 stone filling materials or
without improved soil
ballast
zewdie
Generally subgrade design content:
a) Design of subgrade surface (shape,
width, formation level etc.)
Subgrade tests
b) Design of subgrade bed (thickness, - Strength tests
filling materials and compacting CBR, MR
requirements) Shear tests etc.
c) Design of embankment, cutting, cut- - Stability tests
fill adjustment Shaking table tests
d) Design of transitional section - Property test
e) Ground treatment (mainly for the Physical
embankment base and the cutting Classification
foundation base in special cases) Gradation
f) Side slope supporting and retaining
Atterberg tests
and protection (including embankment
Permeability
and cutting)
g) Design of subgrade drainage system Texture etc.
h) Design of land utilization Chemical
zewdie
Subgrade Construction
Impact Roller to
Compact the Ground
Sheep's foot Roller to Compact Clay Soils
Smooth-wheeled Roller zewdie
using geofabrics to strengthen the soil
Soil Nailing
~ steel rods placed into holes
drilled into the walls and grouted
zewdie
Typical or Potential Subgrade Problems
• Stability (strength and stiffness)
→ Massive shear failure, including slope
instability
→ Abrupt and Exceptional conditions
such as excessive rainfall
• Progressive shear failure
(subgrade squeezing)
→ Repeated wheel loads in combination
with water softens clay soils
→ High stress causes soil to move laterally
towards lower stressed soil between ties
and shoulder (“cess” heaves)
→ Leads to ballast and water pockets;
uneven support results
→ Weak underlying soil layers may also
fail in shear
zewdie
Factors Affecting Subgrade Performance
Soil type
Water
Environmental factors (e.g. freeze-thaw, moisture)
Repeated traffic loading (magnitude and reps)
weight of trains
Track superstructure
Heaves
Soft Track Condition
Ballast Pockets
Subgrade degradation
zewdie
Settlement
• Progressive deformation from repeated loads (excessive plastic
deformation including compaction, consolidation and shear deformation)
• Subsidence of fills and deep layer consolidation
• Settlement at bridge approaches
• Shrinkage from moisture loss
Weak ballast restraint
Subgrade excessive swelling and shrinking
Swelling and frost heaving
Poor drainage
Subgrade failure or deformation
Subgrade attrition
Longitudinal variation
Transitions
Unstable embankments
Sinkholes
zewdie
Water pockets
• Voids filled with water. Caused by:
• Poor compaction
• Soil arching
• Decayed vegetation
• Consolidation and progressive shear
• Leads to liquefaction (slurry) of subgrade material and subgrade attrition
(localized subgrade failure)
• Pumping ties may result (discussed further later in this topic)
zewdie
Other component deterioration
Ballast fouling, due to subgrade attrition (localized subgrade failure)
Abrasion of subgrade surface from ballast contact
Hydraulic erosion (pumping) from deflections and water pockets
Fouling
Rail, fasteners, and special track work suffer from impact loads and high
deflections
Overall, subgrade problems are a major source for poor geometry (crosslevel,
profile, warp) which, in turn, are common causes of slow orders (refer back
to Topic 2 for examples of poor geometry).
Track deterioration:
It is well known that deterioration depends on the present quality level:
• Good track behaves well (deteriorates more slowly),
• Poor one deteriorates faster
zewdie
Track quality is deteriorating due to traffic, showing various faults.
This general observation means that a track behaves
according to its quality.
Mathematically it can be expressed as
Where:
Q - the actual track quality
Q0 - the initial quality
b - the deterioration rate
coefficient
t - the time
The development of the track quality
zewdie
Ground treatment
• When sub grade bed of soil cutting can not satisfy material and
strength requirements, replacement measures are usually adopted.
Replacement of bed course
Impact (vibration) rolling
Heavy tamping and heavy tamping replacement
Bagged sand well and plastic drainage board
Crushed rock pile
Sand compaction pile
Lime-soil (cement-soil) compaction pile
Pile trusted-expanded in column-hammer
Cement-soil mixing pile
Rotary jet grouting pile
Reinforced concrete pile net (pile raft) structure
Reinforced concrete pile board structure
zewdie
3. Drainage of roadbed
The subgrade should be designed Principal sources of water to be
with complete & expedite drainage considered:
system Rainfall directly on the track
Effect of water structure
• Surface water: erode the roadbed Surface water flowing toward and
which make the soil soft infiltrating the track structure
• Ground water: increase the humidity Water flowing within the track
of roadbed and lowering the bearing
structure
force.
Ground water
Techniques used to reduce infiltration:
Sloping the upper surface of the sub grade and top formation
Placement of clean ballast
Construction of access drains below the bottom of the top
formation
Shaping embankment shoulders so that water flows away from the
track zewdie
Surface drainage of roadbed
1) Arrangement of drainage ditch
arrange it along the line;
the size should be able to avoid water from overflow;
when two different size ditches are connected, there should be transition
section;
for those special soil area, the ditch should use measures which prevent
leaking and scouring.
2) Facilities
place: two sides of embankment;
function: drain off water around embankment;
drainage
section: the same as side ditch.
Embankment: ditch
used when the place cannot build a drainage ditch.
rectangular tank
zewdie
Safeguards and strengthening of roadbed
Safeguards of roadbed
Appropriate measures shall be selected for protection of side slopes
(cutting slopes and embankments) according to soil property,
lithology, hydrogeological condition, ratio and height of side slope,
requirements for environment protection and soil & water
conservation.
In principle, measures shall be taken for protection of all slopes.
Safeguards of side slope
Plants
grass—for small gradient (1:1.25) and low height side slope;
turf—for big gradient and high height side slope;
trees—for small gradient side slope.
Civil engineering works
Safeguards of eroding
zewdie
Instability, sub grade work cases & Lessons
Instability
Instability results when the shear strength of the soil is not
sufficient to support the loads applied to it
The term landslide is used to define all types of mass
movement of soil or rock, where the mass moves down slope
under the influence of gravity only
Instability that affects the track can be classified according to
the impact that it has on the track.
zewdie
1. A slide that encompasses a track and will
disrupt the track by cutting the 2. A landslide upslope where the toe
alignment. Once the track moves out of crosses the track, burying it in under slide
line, it is no longer serviceable. debris.
4. An event where a landslide threatens
the track, perhaps by encroaching on
3. The track being heaved up in response to the down slope shoulder.
upward movement of he toe of a landslide.
zewdie
5. Base failure in fills on soft foundations 6. How locations over old landslides
can cause the fill to spread and settle. may be reactivated due to a change in
While this may be mistaken as settlement, stresses within the landslide mass. Many
it is actually a shear movement involving of the ancient landslides are extremely
the foundation soils. It is common on large, and the limits of the landslides
organic terrain and other soft foundations. may be difficult to detect.
zewdie
In general, the stability of a Landslides occur either as a
slope is dependent upon: result of reduction in soil
The shear strength of the soils. strength or an increase in the
Pore water pressure within the loading on the slope.
soils that make up the slope
(this can be roughly measured Reductions in soil strength can
by knowing the water table). occur as the result of:
The geometry of the slope, An increase in pore water pressure,
particularly the slope angle Reducing the available shear
and changes of slope. strength of the soil.
In the case of moisture sensitive
Any surcharge loading such as
soils, the amount of water needed
fill or bank widening material to cause this
stored on the slope or train
loads.
zewdie
Sub grade Work Cases and Lessons
2 2
Lessons: Pay great
attention to stability
of works such as
construction roads
adjacent to railways
in soft soil area.
2
1 1
1 Lessons: Pay great attention to stability of
scope outside side slope designed for railway.
3 Lessons: Pay great attention
to spoils above road cutting
1 and drainage smooth.
3
3
zewdie
Lessons: Pay great attention to stability of high fill in
sloping terrain (stratum) sections.
Lessons: Pay great attention to
exploration and rectification of karst
subgrade.
zewdie
Subgrade Problem Solutions and/or Prevention
Drainage, including limiting access to water
Improve engineering properties through compaction and
possible preloading
Selected fill
• New construction
• Undercut and backfill with ballast under existing
conditions
Maintain stable subgrade geometry, through
• Strong material
• Properly shaped during construction
Use of subballast and/or subgrade protection layer
• Properly graded protection layer is a good solution for
ballast fouling from subgrade and for shaping to shed water
zewdie
Special Track sections -(Transition Secions)
• A track transition is a location where the track experiences a
significant change in vertical track stiffness. These areas,
especially bridge approaches, are often sources of significant
maintenance problems
• A recent report (2009)
stated that based on a
survey of several
North American
railroads nearly 50%
of bridges develop low
approaches
• $200M in maintenance
costs
Settlement at a Bridge Approach, Necessitating Track Surfacing
zewdie
• Traditionally, it was thought that the abrupt change in vertical
track stiffness (track modulus) leads to vertical accelerations in
car and corresponding wheel force changes (dynamic loads)
Vertical Path of Wheel Bottom
Dynamic Wheel
Force Distribution
zewdie
• However, research findings are changing the conventional
wisdom
• The change in stiffness, in itself, does not have a practical
effect on settlement or ride quality because dynamic loads of
a significant magnitude are not generated
• Bridge approach settlement often appeared no greater in the
transition zone than in track away from the zone
• Thus, while changes in stiffness may contribute to settlement
in the transition zone, other factors must be involved
So what is causing the problem?
• FRA initiated research is underway to determine this
• Limited cases studies have shed some light on the topic Rough
track geometry due to differential settlement
• Stiffness and damping disparity contribute
• Both combine to induce dynamic (impact) loads of 2 – 3 times the
static load
zewdie
• Substructure affects the settlement, stiffness, and damping at the
transition
• Subgrade settlement and lateral spreading, especially embankment fill, is
affected by the original construction, materials, drainage, and traffic levels
− Ballast settlement due to
inability to properly
compact and tamp
adjacent to the bridge,
plus ballast “memory”
− Ballast at transitions is
typically subject to
increased levels of
deterioration, flow,
fouling, frost, and poor
drainage
zewdie
Attempted solutions
sometimes used in combination, to bridge approach problems
Convert bridge from non-ballasted deck to ballasted deck
Replace standard concrete ties used on the bridge decks with
those with rubber pads, Ballast mats
Wood ties on bridge decks in lieu of concrete ties
Progressively longer ties on approach (generally not found to be
effective)
Progressively shorter tie spacing (makes tamping difficult, thus
not practiced)
HMA, Transition and cantilevered slabs
Geowebs/Geocells, Chemical and/or cement grouting
Deep soil stabilization techniques and Other cost effective
strategies (e.g. minipiles) are currently being researched. Goal is
to reduce induced impact loading.
zewdie