FAIRMAN MIXED-USE BUILDING
MAURO ST., SAMPALOC, MANILA
LHK Square, 288 N. Domingo Street, San Juan City, Philippines
Tels.: (632) 724-9214; (632)725-0385 Telef ax:(632)705-7175 FAIRMAN MARKETING, INC.
E-mail:
[email protected] Website:www.jslaarchitects.com
Unit 305 Toyama Group Center, 22 Timog Avenue, Quezon City, Philippines
Tel. Nos. (632)412-1792/96/(632)374-8629 (632)374-8779 Mobile No. (63917)324-1573
Project : Fairman Mixed-used Building
Location : Mauro St.,Brgy 581, Sampaloc Manila
Owner : Fairman Marketing Inc.
Architect : Jose Siao Ling and Associates
Date : As of May 5, 2023
Subject : Cost Comparison for 2nd Floor Partition
AS PER SITE ESTIMATE AS PER JJB CONSTRUCTION SERV. AS PER CALUPITAN ENGR'NG SERV. AS PER ROOFTECH SERVICES
Items Particular/Description (per_original_Design) U/Cost U/Cost U/Cost U/Cost
Qty unit Total Cost Qty unit Total Cost Qty unit Total Cost Qty unit Total Cost
Material Material Material Material
DRY WALL PARTITION
SUPPLY AND INSTALLATION OF DRYWALL PARTITION 36.45 sq.m 2,400.00 87,480.00 37.85 sq.m 2,370.00 89,704.50 36.45 sq.m 1,950.00 71,077.50 36.45 sq.m 2,175.00 79,278.75
GYPSUM BOARD 12mm 4ft x 8ft - - - -
METAL STUD 100mm X 50mm X 0.60mm - - - -
METAL TRACKS 100mm X 50mm X 0.60mm - - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
SUB TOTAL 87,480.00 89,704.50 71,077.50 79,278.75
AMOUNT ₱ 87,480.00 ₱ 89,704.50 ₱ 71,077.50 ₱ 79,278.75
GENERAL REQUIREMENT 15% ₱ 13,455.68
DISCOUNT ₱ -
GRAND TOTAL ₱ 87,480.00 ₱ 103,160.18 ₱ 71,077.50 ₱ 79,278.75
VARIANCE -₱ 15,680.18 ₱ 16,402.50 ₱ 8,201.25
Prepared by:
Roedhel Araos Engr. Denis Cezar Engr. Michael Mangulabnan
Project Engineer Project - in - charge Senior Supervisor
TO: FAIRMAN MARKETING INC.
OWNER
THRU: ARCH. MARCELO EDISON ROGUEL
JSLA SENIOR ARCHITECT
ENGR. DENVER NARIO
ELS Consultancy & Management Inc.
Project Manager
PROJECT FAIRMAN MIXED-USE BUILDING
LOCATION Mauro St. Sampaloc, Manila
OWNER Fairman Marketing Inc.
SUBJECT VO #2 - Additional Architectural Finish at 2nd Floor
AS PER BOQ
ITEM SCOPE OF WORK QTY UNIT MATERIAL COST LABOR COST AMOUNT
I. ADDITIVE WORKS
A MASONRY WORKS
CHB 4.62 m2 792.00 178.00 4,481.40
STIFFINER COLUMN 2.31 lm 463.00 178.00 1,480.71
LINTEL BEAM 0.54 lm 463.00 178.00 346.14
LINEAR PLASTERING 9.24 m2 36.00 178.00 1,977.36
REBAR FOR CHB 32.90 kgs 51.75 1,702.58
REBAR FOR SC/LB 10.65 kgs 51.75 - 551.14
GI WIRE 0.25 rolls 2,902.00 725.50
B. DRY WALL
SUPPLY AND INSTALLATION OF DRY WALL PARTITION 36.45 sq.m 2,400.00 87,480.00
GYPSUM BOARD 12mm 4FT X 8FT
METAL STUDS 100mm X 50mm X 0.60mm
METAL TRACKS 100mm X 50mm X 0.60mm
C. STEEL DOOR
MFD - 9 1.00 set 26,000.00 1,380.00 27,380.00
GA. #18 GALVALUME 2HRS FIRE RATED METAL FLUSH DOOR
W/ VISION PANEL ON A GA # 16 DOUBLE RABBET METAL DOOR JAMB
W/ EXTENDED GROOVE IN AUTOMOTIVE LACQUER SPRAY PAINT
-
-
D. HARDWARES - -
4" X 4" S/S FLAG HINGES WITH BALL BEARING 4.00 pcs 851.00 115.00 3,864.00
FOOTBOLT ON ONE DOOR SIDE W/ DUMMY DOOR LEVER TRIM 1.00 set 575.00 230.00 805.00
PANIC DEVICE W/ LEVER TRIM @ OPPOSITE SIDE 1.00 set 8,038.00 575.00 8,613.00
SURFACE MOUNTED DOOR CLOSER DOORMAKABA TS90 1.00 set 2,074.00 576.00 2,650.00
-
E. WINDOW -
SLW - 1 1.00 set 148,680.00 148,680.00
ALUMINUM LOUVER WINDOW ON 50mm X 100mm ALUMINUM
TUBULAR FRAME IN POWDER COATED FINISH -
-
-
F. PAINTING WORKS -
Dry Wall Partition 93.78 sq.m 280.00 26,258.40
Misc 5% 1,312.92 - 1,312.92
- -
-
Sub-total ADDITIVE WORKS 318,308.14
-
-
TOTAL DEDUCTIVE -
ADDITIVE COSTS 318,308.14
(plus 12% overhead and supervision) 38,196.98
TOTAL ADDITIVE COST 356,505.12
AMOUNT IN WORDS:
Subnitted by: Approved by:
ENGR. RODERICK S. WEE ARCH. MARCELO EDISON ROGUEL
Baseline Construction Corp. JSLA SENIOR ARCHITECT
President
Evaluated by: Conformed by:
ENGR. DENVER NARIO FAIRMAN MARKETING INC.
ELS Consultancy & Management Inc. Owner
Project Manager
JJB CONSTRUCTION SERVICES
BLOCK 1, LOT 2, GREENMARK 2,MALAGASANG II-B , CITY OF IMUS
CONTACT NO. 09297877103
April 13, 2023
TO: Baseline Construction Corporation
ATTENTION: Engr. Roedhel Araos
SUBJECT: Quotation for the Installation and Materials for Drywall Partition
Dear Sir,
We are pleased to submit herewith our price proposal for the Installation and Materials for Drywall
Partition along 2nd to 4th Floor area.
Our Offer:
DESCRIPTION AREA QUANTITY UNIT MATERIAL LABOR AMOUNT
COST COST
SUPPLY AND INSTALLATION OF 2F 37.85 SQM 1470 900 89,704.5
DRYWALL PARTITION 12mm
3F 177.879 SQM 1470 900 421,573.23
Gypsum Board and 2x3 Metal
Stud 4F 100.13 SQM 1470 900 237,308.1
SUB-TOTAL Php 748,585.83
GENERAL REQUIREMENT FOR PRELIMS X 15%
TOTAL Php 860,873.70
NOTE: Any additional materials or labor scope the client wish to add which is not included on the above
list will be quoted and charge separately.
REMINDERS:
Payment Terms- 50% downpayment, balance weekly progress billing
We thank you for giving us the opportunity to quote on your requirement and shall be looking forward
to be of further service to you soon.
Prepared by: Conforme:
Engr. Arnulfo Ferrer
Contractor Signature over printed name
Attention Baseline Construction Corporation April 12,2023
Thru Engr. Roedhel Araos
Project Fairman Mixed used Building
Location 2063 Mauro st. Sampaloc Manila
Subject Quotation ( Drywall Partittion )
Location Particular Description Quantity Unit Unit Price Amount
2nd floor Supply and installation of Gypsum Board 12mm x 4' x 8' 36.45 sq.m 1,950.00 71,077.50
Drywall Partition Track .6mm x 50mm x 100mm
Double face Studs .6mm x 50mm x 100mm
3rd floor Supply and installation of Gypsum Board 12mm x 4' x 8' 177.88 sq.m 1,950.00 346,866.00
Drywall Partition Track .6mm x 50mm x 100mm
Double face Studs .6mm x 50mm x 100mm
4th floor Supply and installation of Gypsum Board 12mm x 4' x 8' 100.13 sq.m 1,950.00 195,253.50
Drywall Partition Track .6mm x 50mm x 100mm
Double face Studs .6mm x 50mm x 100mm
Contract Amount 613,197.00
Terms of Payment
50% Downpayment, Balance Weekly Progress Billing
Note
area subject for actual measurements
Not included
Skimcoating, sanding and painting
Temporary Facilities
Water and Power Supply
Permits
Covid 19 test & Disinfectants
Prepared by Conforme
Calupitan Engineering Services Print and sign name
Robbie. M. Calupitan Date
ROOFTECH SERVICES
No. 27 Napindan St., Sta Ana, Taguig City
Date: April 21, 2022
Thru: Engr. Roedhel Araos
Project: Fairman Mixed Use Bldg.
Location: Mauro St., Sampaloc, Manila
Subject: Dry Wall Partition
LOCATION DESCRIPTION DESCRIPTION AREA UNIT UNIT AMOUNT
PRICE
2F Supply and Gypsum Board 36.45 sq.m 2175 79,278.75
Installation 12mm 8’x 4’
Dry Wall Partition Metal Studs 100mm
x 50mm x 0.60mm
CONTRACT 79,200.00
AMOUNT
NOTE:
Any additional labor or supplies requested by the client that are not on the list above will be
quoted and charged individually.
Payment terms:
50% Downpayment Weekly Progress Billing
We appreciate the chance to provide a quote for your needs and look forward to continuing to serve you
in the near future.
Prepared By: Conforme:
________________ ___________________
Engr. Jose Juadinez
Q U O T A T IO N
B A S E L IN E C O N S T . C O R P . D a te : A p r il 2 8 , 2 0 2 3
U n it # 3 0 5 T o y a m a G r o u p C e n te r P R O JE C T: F a ir m a n M ix e d - U s e B ld g .
T im o g A v e , Q u e z o n C ity L O C A T IO N : M a u r a s t., S a m p a lo c , M a n ila
E m a il A d d : b c c .r e c e p tio n 2 0 2 0 @ g m a il.c o m OW NER: F a ir m a n M a r k e tin g In c .
M o b ile N o .: 0 9 1 7 - 7 1 4 0 7 6 5 A R C H IT E C T J S L A A r c h ite c ts
A tte n tio n : E n g r . D e n is C e z a r
In c o m p lia n c e w ith y o u r r e q u e s t, w e a r e p le a s e d to q u o te o u r b e s t p r ic e fo r th e fo llo w in g , s u b je c t to th e te r m s a n d c o n d itio n s
o n th e fa c e a n d b a c k h e r e o f.
IT E M Q TY. U N IT # of U N IT TO TAL
CODE PNL D E S C R IP T IO N O F A R T IC L E S / M E A S U R E M E N T COST COST
A D D I T I O N A L O R D E R
4 4 m m T h k . G A L V A N IZ E D S T E E L F L U S H D O O R , w ith H o n e y c o m b In s u la tio n
G a # 1 8 D o o r P a n e l, o n G a # 1 6 S td . D o u b le R a b b e t J a m b w ith G r o o v e , S u S F la g H in g e s
P r o v i s i o n o f H o l e f o r c l i e n t 's L o c k s e t E p o x y P r i m e r P a i n t e d O n l y .
M F D -9 01 set 0 2 p n ls 2 .1 0 0 m H x 1 .8 0 0 m W - w / N a r r o w lite O p e n in g 2 6 ,0 0 0 .0 0 2 6 ,0 0 0 .0 0
M F D -10 01 set 01 pnl 2 .1 0 0 m H x 0 .9 0 0 m W - P la in T y p e 1 2 ,7 5 0 .0 0 1 2 ,7 5 0 .0 0
3 8 ,7 5 0 .0 0
L e s s : D is c o u n t 7 5 0 .0 0
N E T A m o u n t ( in P e s o s ) 3 8 ,0 0 0 .0 0
T E R M S O F P A Y M E N T : 5 0 % U p o n A c c e p ta n c e ; 5 0 % U p o n D e liv e r y ( N o t S u b je c t to R e te n tio n )
V A L ID IT Y : F ifte e n ( 1 5 ) d a y s . P r ic e is s u b je c t to c h a n g e w ith o u t p r io r n o tic e .
IN C L U S IO N S : D e liv e r y to a b o v e in d ic a te d s ite , g r o u n d flo o r le v e l o n ly .
E X C L U S IO N S : 1 . S u p p ly o f la b o r fo r h a u lin g a n d in s ta lla tio n .
2 . S u p p ly o f h a r d w a r e s s u c h a s p a n ic d e v ic e w ith le v e r tr im , lo c k s e ts , d o o r c lo s e r , s /s p u s h p la
p u ll h a n d le , c le a r / w ir e d / te m p e r e d g la s s , e tc . ( b y o th e r s )
: 3 . A l l l o c a l g o v 't . f e e s , V a l u e A d d e d T a x ; a n d p e r m i t s .
C O N D I T I O N S : F a b r i c a t i o n o f o r d e r s t a r t s o n l y a f t e r r e c e i p t o f C l i e n t 's a p p r o v e d s h o p d r a w i n g a n d
c o r r e s p o n d in g p a y m e n t s h a ll h a v e b e e n m a d e .
***** n o th in g fo llo w s *****
It is u n d e r s to o d th a t, u p o n y o u r a c c e p ta n c e , th is Q u o ta tio n s h a ll c o n s titu te a n O r d e r / C o n tr a c t s u b je c t to a ll th e T e r m s a n d
C o n d itio n s c o n ta in e d h e r e in . T h a n k y o u fo r th e o p p o r tu n ity to q u o te a n d w e h o p e th e a b o v e w ill m e e t y o u r a p p r o v a l.
R O B I N T E C H L E A D E R S I N T 'L . , I N C . CO NFO RM E:
R u b e n T . L im ____________________________
A u th o r iz e d S ig n a tu r e S ig n a tu r e O v e r P r in te d N a m e /D a t